ARGYLL AND BUTE COUNCIL                 ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE                                                              
ROADS AND 
INFRASTRUCTURE SERVICES                                                  2 JUNE 2022 
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2022/23 UPDATE 
1.0 EXECUTIVE SUMMARY
1.1 Each year the Council through its annual budget setting process allocates
budget for various capital projects. During this year’s budget setting process,
the Council allocated £8m for roads reconstruction works. A programme of work
was endorsed by the Environment, Development and Infrastructure (EDI)
Committee in March 2022, following which information on projects for each
administrative area was sent to Members.  The March Environment,
Development and Infrastructure Committee report and appendix can be found
at item 6 in the link appended below, for ease of reference.   
Environment, Development and Infrastructure Committee - 3 March 2022 
1.2 Since the programme was set, there have been significant international
occurrences which have affected the prices of both fuel and bitumen. At the
time of writing this report (early May) there has been a price increase of
approximately 20% for coated roadstone. Whilst each of the planned schemes
will be delivered, there will be less surfacing delivered than originally planned
as a direct consequence of the price increase. 
1.3 It is recommended that the Environment, Development and Infrastructure
Committee: 
i. Endorses the approach taken to deliver the programme within budget
given the price increases; and 
ii. Note that the 2022/23 footway programme will be reported to the
September Environment, Development and Infrastructure Committee.

Page 2

ARGYLL AND BUTE COUNCIL                 ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE                                                              
ROADS AND 
INFRASTRUCTURE SERVICES                                                  2 JUNE 2022 
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2022/23 UPDATE 
2.0 INTRODUCTION
2.1 This report provides details of the roads reconstruction programme for
2022/23. The programme was initially based on an allocation of £5.378m
which was increased to £8.0m at the Council’s Budget Meeting on 24
February 2022. 
3.0 RECOMMENDATIONS
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:
i. Endorses the approach taken to deliver the programme within budget
given the price increases; and 
ii. Note that the 2022/23 footway programme will be reported to the
September Environment, Development and Infrastructure Committee. 
4.0 DETAIL
4.1 A programme of work was endorsed by the Environment, Development and
Infrastructure Committee in March 2022 following which information on projects
for each administrative area was sent to Members.  Since the programme was
set there have been significant international occurrences which have affected the
prices of both fuel and bitumen. At the time of writing (early May) there has been
a price increase of approximately 20% for coated roadstone.  Consideration was
given to pausing the roads reconstruction programme however this was
discounted on the basis that bitumen prices are not expected to reduce any time
soon and more importantly pausing the programme would lead to an acceleration
in deterioration which would ultimately cost more to correct. 
4.2 In order to manage the programme within the budget, the following
methodology has been applied, this has resulted in individual schemes being
reduced in length:

Page 3

o Surface dressing schemes to remain as is, no reduction in length/area
– this is to ensure that the road network receives protection from
surface dressing and that maximum benefits are achieved, thereby
reducing the need for reactive revenue maintenance.
o Urban schemes where full streets are to be treated to remain as is (i.e.
don’t leave 20m untreated on a 100m long street if it is all to a similar
standard and requiring treatment).
o Linier schemes (inlays/overlays etc) as part of a longer section of road
to be reduced in length to ensure that the overall programme is
managed within budget.
o Scheme specification (material type, depth etc) to remain as is i.e. do
not reduce thickness, keep with the original design to ensure good
value is achieved and there is no compromise to whole life costs etc
which shall be maintained by using the original design. 
4.3 Whilst there will be a need to adjust some scheme costs based on the above,
the four area allocations shall remain as approved - no redistribution of funds
across areas. The 2023/24 programme will be developed based on the overall
network requirements at that time – this may or may not include sections of
network programmed for this year not treated due to increasing prices,
depending on deterioration etc (continue with the asset management
approach of programming sections of road where the treatment will deliver the
best return in terms of value for money/whole life costs).  The list of schemes
taken through and endorsed by the March 2022 EDI Committee shall continue
to be the list of schemes/road numbers delivered. 
Future Price Increase 
4.4 There continues to be uncertainty regarding the future price of coated
roadstone. Currently there is an expectation that there will be further price
increases of around 20% over the coming weeks. If this is the case, then it is
likely that we would be unable to carry out all projects in the current scheme
unless further budget is allocated.  The Council set aside a contingency for
capital contract increases when it set the budget on 24 February 2022 and it
may be that a request will come forward to access some of that funding.  
4.5 Officers have submitted a grant application to the Strategic Timber Transport
Scheme (STTS). This funding, should the grant be successful, will be used to
match fund existing schemes on the council network where timber extraction
was programmed to be carried out. 
Footway Programme
4.6  As part of the February budget setting process Members allocated £500k for
footway works. Officers are developing an area based programme of works
which will be reported to the September ED&I Committee. It is proposed that
these works are delivered in the latter part of this financial year, as in previous

Page 4

years, allowing the carriageway works to be delivered during the more favorable
weather window.   
5.0 CONCLUSION
5.1 This report provides and update on the roads reconstruction programme for
2022/23, details the price increase and advises that a report will be brought to
the EDI Committee in September in respect of the footway programme.   
6.0 IMPLICATIONS
6.1 Policy - works assessed and carried out under the current Roads Asset     
Management Plan.
6.2 Financial - programme will be based on capital allocation for year 2022/23. The
increase in prices means that less work on the ground will be delivered than in
previous years.
6.3  Legal – None known 
6.4  HR - reconstruction works delivered by a combination of in-house roads
operations team and sub-contractors.
6.5  Fairer Scotland Duty: None known 
6.5.1   Equalities - protected characteristics – None known
6.5.2   Socio-economic Duty – None known
6.5.3 Islands – None known
6.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  
6.7 Risk - completed works will reduce requirement to repair roads and will arrest
the carriageway/footway deterioration.
6.8 Customer Service - overall improvement in road surfaces and the quality of
driven journeys. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan
Policy Lead for Roads and Transport: Councillor Andrew Kain
20 May 2022

Page 5

For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service 
APPENDIXES 
Appendix 1 – Scheme List