Transformational Projects & Regeneration Team - Large Scale Project Update Report

Argyll and Bute Council · 1 September 2022
Back to Environment, Development and Infrastructure Committee — 1 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
1 SEPTEMBER 2022
TRANSFORMATIONAL PROJECTS & REGENERATION TEAM – LARGE SCALE
PROJECT UPDATE REPORT 
1. EXECUTIVE SUMMARY
1.1 The purpose of this report is to update the Environment, Development and
Infrastructure Committee on progress of the large-scale, externally funded
project work of the Transformational Projects and Regeneration Team, and to
highlight key issues that may impact on the successful delivery of projects. 
1.2 The last update report was considered by the Environment, Development and
Infrastructure Committee in March 2022. 
1.3 The Team is currently responsible for the delivery and or management of
projects and or associated grants with a cumulative value of £35.5m. Projects
are listed in Appendix A.   
RECOMMENDATIONS 
It is recommended that the Environment, Development and Infrastructure
Committee consider, and note the current progress contained within the report.

Page 2

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
1 SEPTEMBER 2022
TRANSFORMATIONAL PROJECTS & REGENERATION TEAM  –  LARGE SCALE
PROJECT UPDATE REPORT 
2. INTRODUCTION
2.1 This report sets out the current position of the large-scale projects, which are
currently being delivered by the Transformational Projects and Regeneration
Team. 
2.2 Transformational Projects and Regeneration sits within the Council’s
Development and Economic Growth Service and works region-wide. The Team
has a particular focus on ‘place’, heritage regeneration, the creative industries,
renewables and Islands and works closely with communities, third sector
organisations, town centre heritage building owners and businesses to realise
positive change. 
2.3 The Team’s work broadly includes the following areas:-   
 Drafting/submitting bids to secure external funding of various scale, such
as the new Heritage and Place Programme previously referred to as the
Conservation Area Regeneration Scheme (CARS) programmes;
 Development/delivery of regeneration projects with a particular emphasis
or theme, such as the suite of measures to encourage shopping locally;
 Development/delivery of a number of place-based engagement projects,
working in partnership with the community and key partners, leading to
action plans, such as charrettes, and working with communities to
realise these community ambitions; 
 Development of the economic opportunities for Argyll and Bute across
Film, Creative Industry and Renewable sectors, with the objective of
securing income to the area and delivering local economic benefit,
including support to community organisations working across these
sectors; 
 Support to third sector organisations involved in the delivery of their own
individual economic regeneration projects, as well as support to third
sector organisations delivering regeneration focused projects where
council funding is involved and/or where projects align with council
outcomes, such as Regeneration Capital Grant Funded (RCGF) projects
funding;
 Development and Administration of the Council’s, Strategic Events and
Festivals Grant, 16 SEF grants awarded under SEF Round 4; and;

Page 3

 Overseeing the delivery programme and financial administration of
projects supported through funding from Scottish Government, such as
the Town Centre Fund (TCF) and more recently Place Based Investment
Fund (PBI) and Islands Programme as well as Crown Estate funding. 
2.4 This paper also seeks to report on key issues that may impact on the current
status of each project, such as any amendments to project scope or timeframe. 
2.5 The 18 large-scale projects currently in delivery, either directly by the Team or by
a third party and where the team is responsible for managing the associated
grant, are included within the table in Appendix 1, and have a cumulative total
value of £35.5m. 
3. RECOMMENDATIONS
3.1  It is recommended that the Environment, Development and Infrastructure
Committee consider, and note the current progress contained within the report. 
4. DETAILS
4.1 The following sections summarise the progress associated with each of the large-
scale projects that are currently in delivery and are either directly delivered by the
team or the grant is managed by the Transformational Projects and Regeneration
Team. The projects are listed in Appendix 1. 
Conservation Area Regeneration Scheme (CARS) Projects 
4.2 The council currently is responsible for the delivery of four heritage-led
regeneration schemes in progress. The total value of the four CARS schemes
successfully secured by the council via a competitive process, represents in
excess of £10m of investment into the built heritage of key towns, and is largely
comprised of funding from Historic Environment Scotland (HES) and National
Lottery Heritage Fund (NLHF), with match funding from the council and private
owners. 
4.3 The CAR schemes operate as grant administration programmes that offer grant
to property owners to help them repair and safeguard historic buildings. A
significant number of building owners have, and continue to benefit from the
funding, which has delivered a significant level of investment over the last ten
years. 
4.4 Due to the cost of repairing traditional buildings, many of these owners would
have been unable to undertake the level of repairs required without grant
assistance and their properties would have continued to deteriorate. Had
deterioration continued, the council may well have had to step in to undertake
emergency work to these buildings. CARS grants have also helped to safeguard
existing businesses, and new businesses have opened as a consequence of the

Page 4

regeneration, helping to create jobs within the community. 
4.5 Such investment has, and continues to change the physical appearance of our
key town centres for the better, making them more attractive places in which to
live, learn, work and do business. 
Rothesay Townscape Heritage Phase 2 (2017 – Mar 2023) Project Status -
GREEN 
Rothesay TH is a £2.75m project in year four of a five year programme.
The partnership project is funded by NLHF (£1,888,500), HES (£500k), Argyll
and Bute Council (£200k), HIE (£70,249), LEADER (£65,800) and Sustrans
(£21,500). Project staff are fully funded for the project duration. 
Of the 5 priority building repair projects, 3 are complete, 1 due to complete in
November 2022, and the final priority project is awaiting a start date with
completion due in March 2023. 4 shopfront restorations have been completed,
with another within planning stages. A series of window repair grants have also
been provided for the restoration of traditional timber sash and case windows. 
The project seeks to facilitate traditional skills development and host events
that celebrate the island’s heritage. To date a maintenance awareness raising
event, community engagement event and 14 workshops have been held. In
addition, a substantial amount of audience development analysis has been
undertaken, resulting in recommendations to support the visitor market and
enhance the end-to-end visitor experience. The potential for a WASPS style
studio has been analysed, Rothesay Castle has been lit up in animation, and
the pilot pop-up shop in the former Clydesdale Bank has successfully continued
beyond the scope of the TH funding. 
Dunoon CARS (2017 – March 2023) Project Status - GREEN 
Dunoon CARS is a £1.95m project in its final year of delivery. A fully funded
project officer is employed to deliver the project for its duration. 
The envelope restoration of 3 priority buildings and 22 shopfronts has been
completed to date, with a further 1 priority project going out to tender at the end
of July 2022. 
A complementary scheme of skills development, in partnership with Dunoon
Community Development Trust, CHARTS, Dunoon Grammar School and Tacit
Tacit is also being undertaken this summer. Local boat builder Ben Neville is
running workshops on traditional timber skills in order to build elements of a
beach hut to be displayed in an exhibition along West Bay. 
Helensburgh CARS – (2021 – Mar 2026) Project Status - GREEN 
Helensburgh CARS is a £1.8m project in the first of a five-year delivery period.
The partnership project is funded by Argyll and Bute Council (£500k) and HES
(£1.24m). A fully funded project officer is employed to deliver the project for its

Page 5

duration. 
CARS priority building status has been removed from the property at 5-7 East
Clyde Street due to owner complexities. A new priority building has been
identified within the Conservation Area 65-67 Sinclair Street Helensburgh and
owners details are being collated. 
Two expressions of interest are being progressed for the smaller repair grant pot.
Expressions of Interest received from the owners of 6 shopfronts are also being
progressed. The CARS Officer will work with the property owners with the aim of
developing these expressions of interest into formal applications. 
A complementary scheme of skills development, in partnership with HES and
Build Your Future (BYF), took place on 13th May at Hermitage Academy which
was very well received by teachers and pupils. Further events are also being
planned to engage and maximise community benefits.   
Lochgilphead CARS (2020 – Mar 2026) Project Status – GREEN 
Lochgilphead CARS is £1.6m partnership project with HES (£969,700) in its
third year of delivery. An additional £200,000 has been secured from the latest
allocation of Place Based Investment funding. The additional funds will help to
deliver two more priority building projects, enhancing project outcomes. 
Following some delays, the first priority building project is due to commence in
August 2022.  Development work is underway for the second priority building. 
Good progress is being made with the remaining two priority buildings. 
The first Small Repair Grant has been awarded.  Discussions continue with a
number of other building owners. 
From the 10-13th May 2022 we delivered the Argyll and Bute Traditional
Building Skills roadshow to high schools across four towns, starting in
Lochgilphead.  Almost 200 pupils were given the opportunity to try their hand at 
skills ranging from roof slating to building surveying and thermal imagining. 
Other training activities have involved us helping  Argyll College students to
manufacture play equipment for a local nursery and a Keeping Warm in Older
Homes event for the public.  Further activates are currently being developed. 
Hermitage Park, Parks for People (2016 –Dec 22) Project Status GREEN 
The £3.7m Parks for People project is in its final year. The main project funders
are NLHF (£2.3m) and Argyll and Bute Council (£380k), with the remainder
coming from a range of other grant/in-kind funding. Capital delivery is now
complete. 
The focus continues to be on delivering the activity plan and finalising some
smaller landscaping and planting projects. Green Flag Status was reconfirmed
in July 2022 for the third consecutive year. The park will continue to be

Page 6

assessed annually in order to retain this status of excellence, and also as a
condition of funding. 
As part of the agreed activity plan, work on creating a new volunteer bothy in
the Demonstration Garden is now complete, and the Demonstration Garden
itself is progressing. The University of the Highlands and Islands have used the
park as the venue for practical elements of their NC Horticulture course. The
Green Gym project continued in 2022 with a specifically targeted group from
Alzheimers Scotland. The Community Room in the new Pavilion has been
available for hire and has attracted art workshops, craft fairs, bridge clubs and
some use for fitness classes. It has also been the venue for horticulture
workshops offered for free as part of the NLHF Activity Plan and for a second
Lime Mortar Training course. Volunteer numbers are picking up with some
specific help for lime mortar pointing and helping in the Demonstration Garden.
In July 2022, the Park hosted an event as part of the Dandelion Scotland
programme which was well attended.  An area suitable for outdoor fitness has
been identified and marketed, one bid being received and accepted. The
successful bidder is currently taking their proposals through planning. 
Tarbert / Lochgilphead Regeneration Fund Project Status – AMBER 
In its 2016/17 budget, Council allocated £3m from reserves to support
regeneration and economic development in the settlements of Tarbert,
Lochgilphead and Ardrishaig. 
4.6 Following recommendations from, and discussions with, a number of local
organisations, 6 projects were identified to proceed to Full Business Case (as
ratified by Policy and Resources Committee on 19th October 2017). 
4.7 To date, the following 4 projects are complete: 
 Gleaner (Phase 1 only) - completed summer 2019.
 Tarbert Harbour – shore side facilities completed in May 2019, car park
completed in March 2021.
 Barmore/Garvel Road junction improvements - completed February
2020.
 Colchester Square/Argyll Street, Lochgilphead – completed May 2021. 
4.8 Current projects are as follows: 
Lochgilphead Front Green 
Works commenced on the Front Green on 31st May 2021 and are expected to
complete in August 2022. 
As reported previously, we were able to use Town Centre Funding and unused
contingency to extend the works. Issues with delivery on site together with
these additional works account for the delays in completing the project.

Page 7

Ardrishaig North Public Realm 
Following a second procurement exercise, contractors P1 Solutions Limited
have been appointed to undertake the works. Pre-construction works are
underway and at the time of writing work is expected to start on site in late
August/early September. Work should be complete early in 2023. 
During the period of construction areas of the site will need to be closed off, we
will work with the contractor to minimise disruption as much as possible.
Regular updates will be issued to stakeholders and other interested parties and
on the Council website. 
Gleaner Phase 2 
We continue to work with Scottish Canals with regards to this wider site, but do
not yet have any further information to share. 
Regeneration Capital Grant Funding (RCGF) Project Status – GREEN 
Over the past seven years, a total of £8.96m RCGF funding has been secured
from Scottish Government to support 15 projects across the area. A further 3
projects secured funding during 2022-23, as follows: Obair Ùr Thirodh – Tiree
Community Business Hub (£565k), Kerrera Old School - Community Hub Final
Phase  (£285k), and Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha
(£603k) taking the total to circa £10million. 
Although RCGF supports community projects, the Fund is only open to local
authorities, and as all 32 local authorities are eligible to apply, this makes for a
highly competitive process. The team has responsibility for applying to RCGF
each year and also managing the respective grant awards. The team is working
to get grant agreements in place with the most recent grant beneficiaries as
soon as possible. 
A further 4 stage 1 bids were submitted to the most recent call for funding:
(Round 10 2023/24) from RCGF. The four bids were as follows: 
 Aros Waterfront Development, Tobermory, Mull  – outdoor activity
hub,  RCGF grant request £370,000 (total project cost £370,600)
 Nonhebel Light Industrial Park Expansion – RCGF grant request £600,000
(total project cost £900,000)
 Tarbert Sea Sports Centre– RCGF grant request £503,000 (total project cost
£773,500 )
 Re-development of East Pier Tarbert– RCGF grant request £1.5million (total
project cost £1.7million) 
If any of the above stage 1 bids are successful stage 2 bids will need to be
developed and submitted later this year with a decision early next year, start of
spend would be 1 April 2023.

Page 8

4.9 An update on the current RCGF projects is provided below, and is followed by a
table of all awards to date (Table 1). 
 Kilmartin Museum – Work on the construction phase started in the spring
2021 is due for completion later this year, the project has drawing down
the initial grant award of £200,000 plus the council funding award. An
uplift of £50k has been approved by RCGF, and at the request of
Kilmartin Museum, a request for a cash flow loan has been approved by
the Council.
 Mid Argyll Community Pool - Construction work concluded and funding
has now been fully drawn down and the project is complete.
 Storas Ulbha Heritage project, Ulva – Unfortunately the organisation was
unable to secure a contractor within the budget and the decision was
taken not to progress at this time. £49,591 remained unclaimed.
 Port Ellen Community Hub, Islay – The organisation is working to secure
a main contractor. They have been awarded a further £300k from RCGF
to address a funding shortfall.
 Scalasaig business units, Colonsay - A contractor is in place and
construction is underway.  Project end date is September 2022.  
 Kilmory Business Park, Lochgilphead – This will help deliver a joint
project with M&K MacLeod on the proposed Kilmory Business Park. 
 Obair Ùr Thirodh – Tiree Community Business Hub – Procurement is
underway.
 Kerrera Old School - Community Hub Final Phase - Procurement is
underway.
 Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha – Procurement
strategy being developed. 
Table 1 
RCGF Project  Grant
Awarded
Year
Awarded
Balance
Remaining / 
Yet to Drawdown
Kilmartin Museum  £275,000 2019/20 £50,000
MACPool  £400,000 2020/21 £0
Storas Ulbha £194,090 2020/21 £113,796
Port Ellen Community hub, Islay  £1,046,223 2021/22 £964,005
Scalasaig business units, Colonsay  £335,000 2021/22 £335,000
Kilmory Business Park in
Lochgilphead 
£829,000 2021/22 £829,000
Obair Ùr Thirodh – Tiree Community
Business Hub
£565,000 2022/23 £565,000
Kerrera Old School - Community
Hub Final Phase  
£285,000 2022/23 £285,000
Ulva Ferry Shore Facilities Building -
Doras Caolas Ulbha
£602,590 2022/23 £602,590

Page 9

4.10 Scottish Government Place Based Investment 2021 – 2026 
Town Centre Funding has been superceded by Place Based Investment (PBI)
funding, which the Scottish Government has committed to allocating on an
annual basis over a five year period. Argyll and Bute’s allocation for 2021/22
was £821k. 
At their respective meetings of 24th June 2021, 12th August 2021, and 2nd
September 2021, Argyll and Bute Council, Policy and Resources Committee
and Environment, Development and Infrastructure Committee agreed to use
PBI towards 8 projects that support a living well locally concept, have climate
friendly ambitions, and which have stemmed from the community through
design-led consultation activity or through needs identified by key partner
organisations. 
The Scottish Government expect that any uncommitted funds by 1st April 2022
will be returned to Scottish Government. Funding has been committed to 8
projects, as follows: 
 £80k towards a region-wide (excluding CARS/BID towns) shopfront
improvement scheme; 
 £100k towards a Rothesay TH priority building; 
 £80k towards public realm enhancements in Bowmore town centre; 
 £70k towards improvements to the area surrounding Castle House
Gate Lodge, Dunoon; 
 £50k as third party grant to Dunoon Burgh Hall Trust towards
landscaping works to support a café garden and support the
sustainability of the facility; 
 £163k towards enhancing the surface of Helensburgh masonry pier; 
 £250k towards public realm improvements in Gibraltar Street, Oban;
and, 
 £28k towards the Helensburgh Hermitage Park, Greening The Bothy
project. 
All the above are either completed or progressed to the point that the funding
is secured. 
The Councils PBI allocation for financial year 2022/23 from Scottish
Government is £712,000. At the meeting of the Policy and Resources
Committee on 16 May members agree to allocate £389,514 of the PBI funding
to some initial projects.  These are listed below: 
 Lochgilphead CARS Priority Buildings – additional £200,000 from PBI 
 Helensburgh Pier, enhanced hard landscaping and lighting of the
masonry pier section – additional £89,514 from PBI to cover increased
costs

Page 10

 Tobermory Harbour Wall and Railings, Phase 2 - £100,000 from PBI
(£100,000 from CE and a request of £250,000 from Islands
Programme) 
Members are considering a report at the August Policy and Resources
Committee in regard to the allocation of the remainder of the £322,486
unallocated PBI funding for 2022/23. 
4.11  Scottish Government Islands Programme 2021/22 & 22/23
The Scottish Government wrote to Councils on 17 December 2021 advising of
the distribution of the 2021-22 Islands Infrastructure Fund (IIF). Argyll and Bute
Council’s share of the funding was £740,000. The fund was for capital works
and required to be committed via a grant contract or contract award by 31
March 2022. At the Policy and Resources Committee meeting on 17 Feb 2022
members agreed to allocate the IIF to 11 projects, 9 of which were third party
projects. The allocation was as follows: 
Organisation Project Details Grant Awarded
Jura Community Business Petrol Station Upgrade £50,000.00
Gigha Heritage Trust Improvements to Achamore
Gardens
£30,000.00 
Tiree Community
Development Trust Renewable heating solutions
£45,000.00
Isle of Kerrera
Development Trust
Redevelopment of the Old
School
£55,000.00
Tobermory Harbour
Association Pier and quay restoration
£50,000.00
South West Mull and Iona
Development Seaweed infrastructure
£67,000.00
South Islay Development Port Ellen Playing Fields £50,000.00
Colonsay Community
Development Company
Ltd Creation of campsite
£40,000.00
Isle of Jura Development
Trust Mooring repair and upgrade
£40,000.00
Argyll and Bute Council Upgrade to Colonsay road
network
£100,000.00
Argyll and Bute Council Improvements to Rothesay
Pontoons
£213,000.00 
TOTAL £740,000.00 
Grant contracts have been issued to all third parties and the team are currently
in the process of working with the individual organisations to ensure the draw
down and compliance as per the grant offer and conditions of Scottish
Government. 
In regard to the island programme for 2022/23 the Scottish Government has
introduced a competitive bidding process for all 6 island authorities as opposed

Page 11

to a direct allocation. A total of 4 bids were submitted to SG in early summer. A
decision is pending. The submissions were as follows: 
1. Island Airports Resilience and Sustainability project – Coll and Colonsay -
£300,000 IP grant request. 
2. Island Community Halls Digital Hubs – Islay , Iona, Tiree and Coll - £100,000
IP grant request. 
3. Tobermory Seawall and Railings  project - £250,000 IP grant request. Total
project costs is £450,000, remaining £200,000 secured from PBI and CE
2022/23 allocation
4. Kerrera Road project - £357,577.32 IP grant request. Total project cost
£557,577.32, £200,000 match from previous CE award. 
4.12  Scotland Loves Local Projects 
Scotland Loves Local funding (£46k) secured from Scotland Town’s
Partnership (STP) has been used to develop a suite of measures to support the
resilience and recovery of town centres, to encourage shopping locally and
promote the idea of the ‘20 minute neighbourhood’. 
As well as having awarded over 120 shopfront improvement grants to business
owners, work to date includes the following: 
Bespoke Argyll and Bute Shop Local Messaging (argyll-bute.gov.uk) 
Digital Training - Webinars and one-to-one sessions were held with business
owners on making the most of Google My Business, to increase the chances of
ranking in local search results and presenting a better offer digitally. Feedback
from businesses was overwhelmingly positive, with 93% of all attendees stating
that the webinar would help their business. 
Digital Photography - 125 local businesses were professionally photographed to
support business owners update and enhance their online presence. The
photographer updated streetview images to ensure that the Argyll and Bute offer
as viewed online reflects the most current position and presents the area in the
most positive light. 
Argyll and Bute Gift Card - The gift card for Argyll and Bute formally launched in
October 2021. The initiative is a year-long pilot, funded by Scottish Government
and administered through STP, designed to boost local spending and support
local businesses. To date, over 115 Argyll and Bute businesses have registered
to accept the card as a means of payment for goods and services. As of 22nd
July 2022, a total of 262 cards have been purchased to the value of £13,010.00. 
At the full Council meeting of 28th April 2022, members agreed to commit a share
of the Local Authority COVID Economic Recovery (LACER) Fund to the Gift
Card. The approved options were:-
 Issue Scotland Loves Local Gift Card to households in receipt of
Council Tax Reduction Scheme - £797,720;

Page 12

 Fully fund Gift Card for 2022/2023 into 2023/2024 - £30,000;
 Marketing budget to promote the Gift Card. 
The marketing allocation from the LACER funds will be used to encourage
additional business registration across Argyll and Bute to maximise offer of the
card for consumers. Officers are currently considering options for spend and
anticipate marketing activity will be rolled out towards the end of the year.  
The Argyll and Bute Gift Card can be purchased as follows: Argyll & Bute Gift
Card | Scotland Loves Local Gift Cards (scotlandgiftslocal.com) 
4.13  Budget: The above project updates are predominantly in relation to the
externally funded projects for which the team are responsible for firstly
securing and then delivering as per grant requirements or overseeing the
specific budget claiming and monitoring process where these relate to a third
party project. A number of these include a proportion of council funding as well
as TCF, PBI or CE funding. There is a set budget for each project and each is
subject to specific outcomes and timelines, as agreed with respective funders.
The externally funded elements of the project costs can only be claimed once
proof of all necessary information has been provided to the respective funder.
Each funder has a different criteria against which delivery is measured, and the
council has entered into formal grant contracts with all funders involved. 
5 CONCLUSION
5.1 Place based investments are taking place across much of Argyll and Bute
making significant improvements to the quality of life of local people and our
communities. Much of the work is externally funded adding to the capital
funding committed by the council to enable this investment to happen. The
successful delivery of the projects require careful monitoring and close
working with colleagues, partners and community stakeholders. The impact
from the Covid-19 pandemic and the UK having left the EU sets a background
that creates a challenging environment in which to work. Prices are currently
exceptionally high, due mainly to supply chain issues, but also shortages in
labour. The Team therefore adopts a pragmatic approach to delivering
projects, ensuring that these are as meaningful as possible using the budget
available however the environment in respect of project delivery is a very
challenging one. 
5.2 The projects contained within this report will result in assisting the economic
recovery of Argyll and Bute, helping to sustain numerous small businesses,
making the place more investor ready, improving our towns and villages as
places to live and visit together with adding to the significant regeneration works
that are being taken forward for Argyll and Bute, and seek to make an improved
and lasting difference to the area.

Page 13

6. IMPLICATIONS 
6.1  Policy - The delivery of these projects fits with the Council’s Corporate Plan,
Argyll and Bute Local Outcome Improvement Plan and the Economic
Development Action Plan. The economic outcomes from this project will
contribute to the Government’s Economic Strategy. 
6.2  Financial - All funding has been approved for the projects detailed in the
report. The funding comes from the council and from external funding
sources.  We will continue to review costs and assess budgets. 
6.3  Legal  Each project will have differing legal and procurement requirements
depending on the grant funder and the associated grant contract conditions
and we are working closely with colleagues to identify the support required
and to allow this to be factored into future work plans. 
6.4  HR - The resources required to deliver the projects will be continually
monitored. The management of these externally funded projects as well as
the management of the Council, PBI, CE and IP and RCGF grants requires a
significant amount of resources from the team to ensure that all the necessary
due diligence and financial management is undertaken and the risk is
minimised to the council. 
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics - None
6.5.2   Socio-economic Duty - None
6.5.3 Islands - None 
6.6  Climate Change - It is an ambition of our project work to work towards net zero
by adopting a carbon conscious approach throughout.   
6.7  Risk - Construction projects by their very nature are challenging given issues
that can arise relating to site conditions, managing contractors/the design
team and associated budgets and meeting funder’s requirements. The effects
of Covid-19 has added even more challenges both in regard to the
development/delivery phases of projects. We continually seek to minimise the
risk through strong project management processes, however until the projects
are fully delivered on site there remains a risk. Other areas of risk relate to the
potential for limited uptake in regard to CARS/TH grants and also over-run on
costs for third party projects. In regard to the latter this is a high risk
particularly as the council is not the responsible body for the projects or their
delivery on the ground. The setting up of regular benefits realisation group
meetings and building good working relationships with the third parties assists
in identifying where issues may arise and where additional support may be
required. Covid-19 and the resulting impact on the construction industry and
costs is an additional risk to the delivery of these projects and we are
reviewing all costs and working with funders to minimise the impact and
manage the risk as much as we can

Page 14

6.8  Customer Service – None 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Policy Lead for Economy and Rural Growth: Councillor Robin Currie 
31st July  2022 
For further information - please contact 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Audrey Martin, Transformation Projects and Regeneration Manager
Audrey.Martin@argyll-bute.gov.uk 
Appendices: 
Appendix A – List of Council and Third Party projects that the Team is either
responsible for delivering directly or for managing the grants given by the council to a
third party organisation.

Page 15

APPENDIX A - LIST OF COUNCIL AND THIRD PARTY PROJECTS 
Council & Third Party Regeneration Projects  Project
Value 
Council
Funding
Contribution
External
Funding -
Including TCF
Delivery
Start
Delivery End -
(Excludes
Defect Period)
Dunoon CARS  £1,949,965 £500,000 £1,002,348 2017 2022 
Rothesay TH2 £3,244,856 £200,000 £2,508,781 2017 2022 
Tarbert Lochgilphead Regeneration Fund (Includes TCF Grant) £6,374,952 £3,000,000 £3,374,952 2018 On going
Hermitage Park (Includes TCF and PBI Grant) £3,754,625 £455,000 £3,299,625 2016 2021
Kilmartin Museum RCGF & Council Grant plus cash flow loan  £7,171,932 £400,000 £225,000 2019 2023
MACPool RCGF Grant £1,464,045 £0 £400,000 2020 2022/23
Port Ellen Community hub, Islay  RCGF grant  £1,365,223 £0 £1,046,223 2021/22 2022/23
Scalasaig business units, Colonsay RCGF grant  £467,398 £0 £335,000 2021/22 2021/22
Kilmory Business Park in Lochgilphead RCGF grant  £1,980,000 TBC £979,000 2021/22 2022/23
Lochgilphead CARS (Includes 22/23 PBI Grant) £1,806,096 £386,220 £1,169,731 2020 2026
Helensburgh CARS £1,740,000 £500,000 £1,240,000 2021 2026
Events and Festivals grants (including annual Mod)16 SEF4 grants awarded £170,614 £170,614 - 2022 2023
Place Based Investment 21/22* £821,000 £0 £621,000  2021/22  2022/23
Place Based Investment 22/23** £512,000
£0
£712,000
2022/23  2022/23
Obair Ùr Thirodh – Tiree Community Business Hub - RCGF Grant £860,000 £0 £565,000 2022 2023
Kerrera Old School - Community Hub Final Phase - RCGF Grant £427,290 £0 £285,000 2022 2023
Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha - RCGF Grant £652,590 £0 £602,590 2022 2024
Islands Infrastructure Fund 21/22 £740,000 
£0
£740,000
2021/22 2022/23
Scotland Loves Local £46,000 £0 £46,000 2022/23 2022/23
LACER Fund £40,000 £0 £40,000 2022/23 2023/24
Total £35,588,586 £5,611,834 £18,571,250     
* See separate 12th August 2021 Policy and Resources committee report for proposed breakdown of projects and values.
** Full award for 22/23 was £712,000.  This figure has had the £200,000 awarded to Lochgilphead CARS deducted.  See separate 16th June 2022 Policy and
Resources committee report for proposed breakdown of projects and values.