Democracy Spraffa

Street Lighting Capital Improvements/Led Project and Replacement Columns Programme 2022-23

Argyll and Bute Council · 1 September 2022
Back to Environment, Development and Infrastructure Committee — 1 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
1 SEPTEMBER  2022
STREET LIGHTING CAPITAL IMPROVEMENTS PROGRAMME 2022/23
LED PROJECT AND REPLACEMENT COLUMNS PROGRAMME 2022/23 
1.0 EXECUTIVE SUMMARY
1.1 Argyll and Bute Council are responsible for the maintenance of over 14,500
street lights and associated lighting columns, control pillars and lit road signs.
A large quantity of the inventory of streetlights is still powered from the “5th core”
electrical supply system, dating from 1930s. This is a hidden problem which
manifests itself in frequent power failures which are costly to rectify. 
1.2 There is also a parallel issue, where the age of street lighting columns is
unknown. The newest columns are now approaching 25 years, since the
previous upgrading programme in 1990’s, with many others estimated as
between 50 – 80 years. This is well outside the Industry recognised life
expectancy of 25 years for columns and wiring. 
1.3 As a direct result of this, over recent years additional costs have been incurred
through the Street Lighting Revenue budget, to replace failed power supplies
and deal with actual or potential column failures due to corrosion. 
1.4 The £3.9M LED Replacement Luminaires project commenced in Helensburgh
and Lomond in 2015. Sections of work were completed in the period to 2018
bringing approximately 12,580 new LED Luminaires onto the system. 
1.5 The disruption due to Coronavirus has delayed the continuation of the project until
now. At the time of writing, the final assessment and award of a tender is
underway with an expected start onsite in the remaining area of Oban, Lorn and
the Isles in August 2022. Thereafter a “mop-up” process will replace any columns
classed unsuitable for continued use and catch any luminaires missed in the
original works. 
1.6  The remaining works packages for LED fit out and column replacement works are
estimated at £485,000 and is fully funded within the existing LED Project budget. 
RECOMMENDATIONS: 
It is recommended that the Environment, Development and Infrastructure Committee:-
i. Endorses the Street Lighting Capital Improvements programme
2022/23; and 
ii. Endorses the LED and Replacement Column programme 2022/23.

Page 2

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
1 SEPTEMBER  2022
STREET LIGHTING CAPITAL IMPROVEMENTS PROGRAMME 2022/23
LED PROJECT AND REPLACEMENT COLUMNS PROGRAMME 2022/23
2.0 INTRODUCTION
2.1 This report provides details of the proposed Street Lighting reconstruction
programme for 2022/23. The programme is based on an allocation of
£740,000, comprising of £440,000 of Capital allocation from this and the
previous financial year and an additional £300,000, awarded through the
budget process, to deal with defective columns and cabling. 
2.2 This report also provides details of the proposed LED Replacement luminaires
project, to completion in OLI and follow-on process of replacement of defective
columns and “catch-up” luminaire fittings in all areas. This is valued at £485,000
and funded through the £3.9M LED project budget.   
3.0 RECOMMENDATIONS
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Endorses the Street Lighting Capital Improvements programme for
2022/23; and 
ii. Endorses the LED and Replacement Column programme for 2022/23. 
4.0 DETAIL        
4.1 Street Lighting Capital Improvements programme 22022/23
4.1.1 The Street Lighting inventory of 14,500 lighting columns is located generally,
one third in Helensburgh and Lomond, a third in Bute and Cowal and the
remaining third distributed throughout Kintyre, Mid-Argyll, Lorn and the outer
islands centers of population.
4.1.2 Faulty cables and corroded columns are an issue throughout the network but a
large number of recurring faults remain outstanding in the eastern districts
where the bulk of the inventory is situated. Schemes have been identified and
prioritised in these areas, where lights remain in fault condition or the risk of
recurring failures is likely. This is the first batch of schemes identified to rectify
the previous backlog in inventory improvements.
4.1.3 The plan is to design new lighting systems as part of each scheme, fully
compliant with current regulations and include independently controlled cabling
systems through new control pillars, known as Highway Distribution Units

Page 3

(HDUs). This will provide one new power supply to each HDU and give full
control of the cable network to each lighting column, through ducting which will
allow future cable replacement without the requirement to re-excavate tracks
between columns. This will eliminate the current “5th core” issues and also
“wired armoured” cables, which were previously buried directly in the ground
without ducts and require full re-excavation to replace any defective sections.
4.1.4 The programme for delivery will be through the mixed economy model, partly
for smaller schemes, delivered through the in-house Street Lighting Team,
which consists of three electricians and one apprentice, working with local
contractors from the framework contract, to provide the tracking, cabling and
column placement element of the works. Larger schemes will be let to
experienced Street Lighting Contractors through a tendering process.   
4.1.5 Appendix 1 details the specific schemes and estimated values for the Street
Lighting Capital Replacement Schemes programme 2022/23.  At the time of
writing, works are scheduled to commence in August 2022 and continue
through to March 2023.  
4.1.6 An element of parallel working to improve footways affected by lighting tracking
works has been allowed for in the programme. This will generate minor savings
in the lighting works estimates, where final full width footway re-surfacing is
funded through the parallel Footways Capital Improvements programme. This
will allow two improvements in one, in certain locations and provide additional
benefit to communities.
4.2 LED Luminaires and Replacement Columns programme 2022/23 
4.2.1 Capital funding in recent years, pre-Covid, focused on the LED luminaire
replacement project. This reduced the overall power consumption of the system
by approximately 45%.  In some cases columns deemed unsuitable for new
luminaires were by-passed in the project and are part of further “column
upgrade catch–up” works, in parallel with this programme of full system
upgrades. 
4.2.2 The design element of the LED project will be delivered by WSP Ltd, in parallel
with the Street Lighting Capital replacement schemes design work. The new
lighting for each street requires a design assessment. This will comply with current
lighting standards and be based on the existing location and height of the lighting
columns, to determine the specification of LED luminaire required. This will
provide a new fully compliant LED lighting system in each location. 
4.2.3 The tender assessment and award process is underway. A start to the fitting out
of the LED programme in Oban and Lorn is anticipated in August. 
4.2.4 The follow-on works packages for column replacement and “catch-up” LED fitting
will follow-on from the completion of the OLI original LED programme. This will be
delivered by a combination of in-house Street Lighting / Framework contractors
toward completion of the LED project by 31st March 2023.

Page 4

5.0 CONCLUSION
5.1 This report provides details of the proposed Street Lighting Improvement
programme for 2022/23.
5.2   This report provides details of the parallel LED Luminaires and Replacement
Column programme 2022/23. 
6.0 IMPLICATIONS
6.1 Policy - works assessed and carried out under the current Roads and Lighting
Asset Management Plan.
6.2 Financial – Programme based on capital allocation for year 2022/23. The
increase in LED luminaires will further reduce the overall power consumption
requirement for the street lighting asset.
6.3  Legal – None.
6.4  HR - Works delivered by a combination of in-house operations teams with sub-   
contractors and external contractors.
6.5  Fairer Scotland Duty 
6.5.1   Equalities - protected characteristics – None Known. 
6.5.2   Socio-economic Duty – None Known. 
6.5.3  Islands – None Known.
6.6 Climate Change – All Luminaires–low energy LED, plus recyclable equipment.
6.7. Risk - Completed works will reduce requirement for reactive repair of lighting
faults and improve the overall condition of the Street Lighting asset.
6.8  Customer Service - overall improvement in Street Lighting service. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure
Jim Smith, Head of Roads and Infrastructure 
Policy Lead for Roads and Transport, Councillor Andrew Kain
AUGUST 2022                                                  
For further information contact: 
Hugh O’Neill, Network and Standards Manager
Jim Smith, Head of Roads and Infrastructure Service

Page 5

APPENDICES 
Appendix 1 – Street Lighting - Capital Reconstruction Programme 2022/23 
Appendix 2 –  LED project - Programme to completion 2022/23

Page 6

APPENDIX 1 - STREET LIGHTING - CAPITAL RECONSTRUCTION
PROGRAMME 2022/23 
APPENDIX 2 – LED PROJECT - PROGRAMME TO COMPLETION 2022/23 
Street Lighting Capital Program 2022/23 v2 - 11/05/2022
v3 06/07/2022 (Est red)
Funding through Capital and other allocation
Note £440,000
HDU = Highway Distribution Unit £300,000
Power connection and control box £740,000 CAPITAL BUDGET 2022-23
DUCTING , CABLE AND COLUMN UPGRADE AND REPLACEMENT PROGRAMME
Area Scheme Name Estimated Value Proposed Scheme Details Contractor Delivery
Model
Works programmed after Design process completed - to appointed Small Works Framework Contractor
BC Dunoon  - Argyll Street Car
Park / Pier Esplanade £1,500
12No. 8M Column Brackets Single Head,
12No. 8m Column Brackets Double
Head, Install 2No. 4m Columns and
56No. New LED Luminaires
In House
HL Rosedale Gardens £26,500 Column (7No.) and HDU Replacement /
cabling and ducting
In House / Small Works
Framework
HL Eastwood Lane From the
A814 £32,200 Column (9No.) and Cable Replacement /
Cabling and ducting
In House / Small Works
Framework
HL Kathleen Park (From Rhu
Road Higher) £43,200 Column (12No.) and HDU / Cabling
Replacement
In House / Small Works
Framework
BC Ladside Road and Ladeside
Place Rothesay £66,000 Column (18No.) and HDU / Cabling
Replacement
In House / Small Works
Framework
BC St Brides Road / Blain
Terrace Ballochgoy Rothesay £42,000 Column (12No.) and Cable Replacement In House / Small Works
Framework
Works let after Design ,Tendering  and Procurement process completed - to appointed Contractor
HL Kilmahew Drive & Kilmahew
Grove Cardross £72,000 Column (20No.) and Cable Replacement Contractor
HL St Modens Way £54,200 Column (15No.) and HDU Replacement Contractor
BC A815 Innellan Shore Road £204,600 Column (60No.) and HDU (6No.) /
Cabling Replacement Contractor
Lorn
OBAN - Nant Drive and Spur
roads ( Phase 1 of £238K 
project estimate) ( £114K c/o)
£124,700 Column (71No) 8 HDU and cable
replacement  ( PH 1 2022 ) Contractor
Mull Tobermory  - Back Brae £73,200 Column (20no.) 2 x HDU and Cabling
Replacement Contractor
£740,100 Estimated Value of Works
Additional allocation for Defective Columns and Cables.
Capital Allocation ( inc £190,000 carred over from 2021-22)
Funded through remaining  LED Replacement Project Budget
OTHER  INSTALLATION WORKS  -   LED PROJECT
Works programmed after Design process completed - to appointed Small Works Framework Contractor
Kin Sound of Kintyre £55,000 95 nr LED REPLACEMENT In house
Var Cat 4 Columns - LED mop up £180,000 200 nr Column replacement & LED In house / framework
Works let after Design ,Tendering  and Procurement process completed - to appointed Contractor
Lorn Oban and Lorn upgrade £150,000 1100nr  LED REPLACEMENT Contractor
Var Sweep Through  - LED Catch £100,000 600nr  tbc  LED REPLACEMENT  Contractor
£485,000 Estimated Value of Works