Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD 
24 November 2022 
NOTICE OF MEETING 
A meeting of the ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE will
be held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND
BY MICROSOFT TEAMS on THURSDAY, 1 DECEMBER 2022 at 10:30 AM, which you are
requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST (IF ANY) 
3. MINUTES (Pages 3 - 6)  
Environment, Development and Infrastructure Committee held on 1 September 2022 
4. LOCAL FLOOD RISK MANAGEMENT PLANS – CYCLE 2 2022-28 (Pages 7 - 30)  
Report by Executive Director with responsibility for Roads and Infrastructure 
5. CEMETERY ASSET UPDATE (Pages 31 - 44)  
Report by Executive Director with responsibility for Roads and Infrastructure 
6. ELECTRIC VEHICLE CHARGING STRATEGY UPDATE (Pages 45 - 92)  
Report by Executive Director with responsibility for Roads and Infrastructure 
7. PLAY PARK FUNDING (Pages 93 - 100)  
Report by Executive Director with responsibility for Roads and Infrastructure 
8. BIN AND SIGNAGE REPLACEMENT PROGRAMMES (Pages 101 - 106)  
Report by Executive Director with responsibility for Roads and Infrastructure 
9. LATEST UPDATE ON STAYCATION PROPOSALS (Pages 107 - 122)  
Report by Executive Director with responsibility for Development and Economic
Growth
Public Document Pack

Page 2

REPORTS FOR NOTING 
10. CLEANING AND DRAINAGE IMPROVEMENTS IN RESPONSE TO CLIMATE
CHANGE (Pages 123 - 126)  
Report by Executive Director with responsibility for Roads and Infrastructure 
11. ARGYLL AIR SERVICES - PUBLIC SERVICE OBLIGATION CONSULTATION
(Pages 127 - 134)  
Report by Executive Director with responsibility for Development and Economic
Growth 
12. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORKPLAN (Pages 135 - 136) 
EXEMPT REPORT FOR DECISION
E1 13. WASTE PPP OPTIONS APPRAISAL (Pages 137 - 180)  
Report by Executive Director with responsibility for Roads and Infrastructure 
The Committee will be asked to pass a resolution in terms of Section 50(A)(4) of the Local
Government (Scotland) Act 1973 to exclude the public for items of business with an “E” on the
grounds that it is likely to involve the disclosure of exempt information as defined in the
appropriate paragraph of Part I of Schedule 7a to the Local Government (Scotland) Act 1973. 
The appropriate paragraph is:- 
E1 Paragraph 8  The amount of any expenditure proposed to be incurred by the authority
under any particular contract for the acquisition of property or the supply of goods or
services.
Paragraph 9  Any terms proposed or to be proposed by or to the authority in the course of
negotiations for a contract for the acquisition or disposal of property or the supply of goods
or services. 
Environment, Development and Infrastructure Committee 
Councillor John Armour Councillor Jan Brown
Councillor Garret Corner Councillor Robin Currie (Chair)
Councillor Mark Irvine Councillor Andrew Kain (Vice-Chair)
Councillor Donald Kelly Councillor Jim Lynch
Councillor Tommy MacPherson Councillor Ian MacQuire
Councillor Luna Martin Councillor Ross Moreland
Councillor Gary Mulvaney Councillor William Sinclair
Councillor Andrew Vennard Councillor Peter Wallace   
Contact: Hazel MacInnes  Tel: 01546 604269

Page 3

MINUTES of MEETING of ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
COMMITTEE held ON A HYBRID BASIS BY MICROSOFT TEAMS AND IN THE COUNCIL
CHAMBER, KILMORY, LOCHGILPHEAD 
on THURSDAY, 1 SEPTEMBER 2022 
Present: Councillor Robin Currie (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Garret Corner
Councillor Andrew Kain
Councillor Donald Kelly
Councillor Jim Lynch 
Councillor Ian MacQuire
Councillor Luna Martin
Councillor Ross Moreland
Councillor William Sinclair
Councillor Andrew Vennard
Councillor Peter Wallace 
Attending:  Kirsty Flanagan, Executive Director
Jim Smith, Head of Roads and Infrastructure Services
Fergus Murray, Head of Development and Economic Growth
Stuart McLean, Committee Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Mark Irvine and Tommy
MacPherson. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. MINUTES 
The Minutes of the meeting of the Environment, Development and Infrastructure
Committee held on 2 June 2022 were approved as a correct record. 
4. SERVICE ANNUAL PERFORMANCE REVIEWS 2021/22: DEVELOPMENT AND
ECONOMIC GROWTH SERVICES & ROADS AND INFRASTRUCTURE
SERVICES 
The Committee gave consideration to a report presenting the Service Annual Performance
Reviews and Scorecard 2021/22 for the Development and Economic Growth, and Roads
and Infrastructure Services. 
Decision 
The Environment, Development and Infrastructure Committee approved the Service
Annual Performance Reviews (Service APRs) and Scorecards 2021/22 as presented prior
to publishing on the Council Website. 
(Reference:  Report by Executive Director with responsibility for Customer Support
Services dated 13 July 2022, submitted) 
Page 3 Agenda Item 3

Page 4

5. WINTER SERVICE POLICY 2022-23 
The Committee gave consideration to a report presenting the Council’s Winter Service
Policy for approval.  The policy for 2022/23 remained similar to that of the policy for
2021/22. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. approved the 2022/23 Winter Maintenance Policy Document at Appendix 1 to the
submitted report;  
2. approved the Salt Use Reduction and Preservation of Stock Protocol at Appendix 2 to
the submitted report; 
3. noted the Advisory signing, routes unsuitable in severe conditions at Appendix 3 to the
submitted report; 
4. noted the Frontline Treatment Vehicle Fleet at Appendix 4 to the submitted report; 
5. noted the Salt Stocks monitoring and resilience record at Appendix 5 to the submitted
report; and  
6. noted the weather summary from 2021/22 at Appendix 6 to the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated August 2022, submitted)   
6. FOOTWAYS RECONSTRUCTION PROGRAMME 2022-23 
The Committee gave consideration to a report providing a programme of Footway
Reconstruction Schemes for 2022/23.  The Council had awarded £500k at its Budget
Meeting in February 2022 and the budget had been allocated by proportion of the footway
inventory values in each geographical area, and was set out in each appendix to the
report. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. endorsed the programme of capital works for 2022/23; and 
2. agreed that details of each Area Committee programme would be forwarded on to the
respective Ward Members.   
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated August 2022, submitted) 
Page 4

Page 5

7. STREET LIGHTING CAPITAL IMPROVEMENTS/LED PROJECT AND
REPLACEMENT COLUMNS PROGRAMME 2022-23 
The Committee gave consideration to a report providing details of the proposed Street
Lighting Reconstruction Programme for 2022/23. The programme was based on an
allocation of £740,000, comprising of £440,000 of Capital allocation from this year and the
previous financial year, and an additional £300,000, awarded through the budget process,
to deal with defective columns and cabling. 
Decision 
The Environment, Development and Infrastructure Committee endorsed – 
1. the Street Lighting Capital Improvements Programme for 2022/23; and 
2. the LED and Replacement Column Programme for 2022/23. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated August 2022, submitted)   
8. TRANSFORMATIONAL PROJECTS & REGENERATION TEAM - LARGE SCALE
PROJECT UPDATE REPORT 
The Committee gave consideration to a report providing an update on the progress of the
large scale, externally funded, project work of the Transformational Projects and
Regeneration Team, highlighting key issues that could impact on the successful delivery
of the projects. 
Decision 
The Environment, Development and Infrastructure Committee noted the current progress
contained within the submitted report. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated 31 July 2022, submitted) 
9. COMMUNITY EMPOWERMENT (SCOTLAND) ACT 2015 - ALLOTMENTS
WAITING LIST REGISTER 
A report providing an update on the ongoing actions that were being undertaken in
response to duties placed on the Council under Part 9 of the Community Empowerment
(Scotland) Act 2015 was before the Committee for noting. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
submitted report. 
(Reference:  Report by Executive Director with responsibility for Legal and Regulatory
Support dated May 2022, submitted) 
Page 5

Page 6

10. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORKPLAN 
The Environment, Development and Infrastructure Committee Workplan was before the
Committee for noting. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
Workplan. 
(Reference:  Environment, Development and Infrastructure Committee Workplan dated
September 2022, submitted) 
The Committee resolved in terms of Section 50(A)(4) of the Local Government (Scotland)
Act 1973 to exclude the press and public for the following item of business on the grounds
that it was likely to involve the disclosure of exempt information as defined in Paragraph 6
of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. 
11. WASTE STRATEGY UPDATE 
The Committee gave consideration to a report providing an update on the work relating to
the Waste PPP contract and on the options appraisal work streams being taken forward. 
Decision 
The Environment, Development and Infrastructure Committee noted – 
1. the report and the approach being taken to determine the most appropriate option for
the Council regarding waste disposal; 
2. the good progress being made in relation to the options appraisal; and 
3. that a further report detailing the full appraisal and proposed next steps will come
forward to the December EDI committee, providing information on the preferred option
and outlining any capital and revenue cost implications. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated August 2022, submitted) 
Page 6

Page 7

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT
AND INFRASTRUCTURE
COMMITTEE 
ROADS AND INFRASTRUCTURE SERVICES        1 DECEMBER 2022   
LOCAL FLOOD RISK MANAGEMENT PLANS – CYCLE 2 2022-28 
1.0  EXECUTIVE SUMMARY 
1.1  The Flood Risk Management (Scotland) Act (2009) (The Act) sets out a process for
delivering a plan-led, risk-based approach to flood risk management in Scotland. 
The legislation requires all ‘responsible authorities’, as defined by the Act and
Scottish Ministers, to work collaboratively to assess and agree a plan of measures or
actions to reduce the risk of flooding in the most vulnerable areas in their Local Plan
District (LPD). 
1.2  Scottish Environment Protective Agency (SEPA) are responsible for developing
Flood Risk Management Plans which provides the basis from which Lead Local
Authorities (LLA) develop Local Flood Risk Management Plans (the LFRMP)
identifying detail on what actions entail, who will undertake them and when they will
be done.  Although the SEPA Plan and the Local Plans are separate reports, much
of the background information in each is the same. 
1.3  The SEPA Plans for Cycle 2 (2022-2028) were approved by Scottish Ministers and
published in December 2021. Local flood Risk Management Plans are due to be
published by 31 December 2022.   
1.4  Argyll and Bute Council is part of two Local Flood Risk Management Plan Districts 
 Highland and Argyll 
 Clyde and Loch Lomond (CaLL) 
1.5  Members are asked to agree the content of the draft Highland and Argyll Local Flood
Risk Management Plan Cycle 2 (See Appendix 3) to be published by Highland
Council and recognise that Highland Council as Lead Local Authority has the
statutory duty to publish before 31 December 2022.   
1.6  Members are asked to note that Argyll and Bute Council Flooding Policy Lead will be
invited to attend the Clyde and Loch Lomond LPD Joint Committee meeting to
approve the CaLL LFRMP.  The date of the committee is yet to be confirmed by the
Lead Local Authority, Glasgow City Council. 
1.7 Acceptance and publication of the LFRMP will commit Argyll and Bute Council to
Page 7 Agenda Item 4

Page 8

delivery of the LFRMP.  The Council cannot knowingly change priorities or reduce
funding of flood risk management activities which would prevent the delivery of the
actions in the Local Plan.  Flood Protection Studies and Schemes are the most
significant commitment within the Local Plan both financially and in terms of resource
and the timescales for delivering these must be met. 
1.8 Proposed schemes were submitted to SEPA in December 2019 as part of a national
Flood Protection Schemes (FPS) prioritisation process. The outcome of this process
is still to be published by SEPA. As part of the process additional grant funding has
been sought from Scottish Government for the delivery of Flood Protection Schemes.
Historically this has covered 80% of all eligible scheme costs, however at the current
time it is unclear what the funding provisions will be.  There is a high likelihood due to
tender price increases in the Cycle 1 programme that schemes that have been put
forward to the Scottish Government will not receive funding in Cycle 2.  Progression
with schemes is subject to success in the grant funding application process. The
summary of schemes and studies which form the basis of the Local Flood Risk
Management Plans are listed in this report in Appendix 2.  These are subject to
appropriate funding being in place from the Scottish Government and the Council. 
RECOMMENDATIONS 
 It is recommended that the Committee approves the content of the Highland and
Argyll Local Flood Risk Management Plan allowing publication by the Lead Local
Authorities (LLA) (The Highland Council) to take place by 31 December 2022. 
 The Committee notes that the approval of the Clyde and Loch Lomond Local Flood
Risk Management Plans (LFRMP) will be agreed at the Clyde and Loch Lomond
Local Plan District (LPD) Joint Committee. 
 The Committee notes progression of the schemes and studies are subject to
appropriate funding being in place from the Scottish Government and the Council.   
Page 8

Page 9

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT
AND INFRASTRUCTURE
COMMITTEE 
ROADS AND INFRASTRUCTURE SERVICES        1 DECEMBER 2022   
LOCAL FLOOD RISK MANAGEMENT PLANS – CYCLE 2 2022-28 
2.0  INTRODUCTION 
2.1  The purpose of this report is to update the Committee on Cycle 2 of the Highland
and Argyll Local Flood Risk Management Plan and to seek their endorsement of the
summary of actions identified to be taken forward by the Council, noting the status of
the funding arrangements. 
2.2  The Act requires the LFRMP to be published by each Lead Local Authority (LLA) by
31 December 2022. 
2.3  Acceptance and publication of the Local Plan will commit Argyll and Bute Council to
delivery of the Local Plan.  The Council cannot knowingly change priorities or reduce
funding of flood risk management activities which would prevent the delivery of the
actions in the Local Plan.  Flood Protection Studies and Schemes are the most
significant commitment within the Local Plan both financially and in terms of resource
and the timescales for delivering these must be met. 
2.4  Additional grant funding has been sought from Scottish Government for the delivery
of Flood Protection Schemes actioned in both LFRMP’s.   
3.0  RECOMMENDATIONS 
 It is recommended that the Committee approves the content of the Highland and
Argyll Local Flood Risk Management Plan allowing publication by the Lead Local
Authorities (LLA) (The Highland Council) to take place by 31 December 2022. 
 The Committee notes that the approval of the Clyde and Loch Lomond Local Flood
Risk Management Plans (LFRMP) will be agreed at the Clyde and Loch Lomond
Local Plan District (LPD) Joint Committee. 
 The Committee notes progression of the schemes and studies are subject to
appropriate funding being in place from the Scottish Government and the Council.   
Page 9

Page 10

4.0  DETAIL 
4.1  The Flood Risk Management (Scotland) Act 2009 placed duties on Scottish
Environment Protection Agency (SEPA), Scottish Water, the National Park
Authorities, Scottish Forestry and Local Authorities as “Responsible Authorities” to
work together to reduce flood risk across the country.   
4.2  SEPA are responsible for developing Flood Risk Management Plans (the ‘SEPA
Plans’, formerly known as Strategies), which involved carrying out a National Flood
Risk Assessment. The National Flood Risk Assessment (2018) developed by SEPA,
defined a total of 235 Potentially Vulnerable Areas (PVAs) across Scotland.  These
PVAs provide a focus for all responsible authorities to fully understand the risk from
all sources of flooding and agree planned measures to reduce that risk 
4.3  SEPA Plans provide the basis from which Lead Local Authorities (LLA) develop the
Local Flood Risk Management Plans (LFRMP’s) for each LPD. This is done by
identifying the Objectives and Actions identified in the SEPA plans and who
undertakes the Actions, and when they will be progressed is identified in the SEPA
plan and confirmed in the LFRMP.  
4.4 Argyll and Bute Council are partially responsible for producing two LFRMPs:- 
 Highland and Argyll LFRMP led by The Highland Council
 Clyde and Loch Lomond LFRMP led by Glasgow City Council 
4.5  Although the SEPA Plan and the LFRMP’s are separate reports, much of the
background information in each is the same and significant partnership working
among the responsible authorities has been carried out. 
4.6  Both SEPA Plans and LFRMP’s operate in 6 year cycles. In December 2021 SEPA
published the SEPA Plans which have now been approved by Scottish Ministers.
The first cycle of ABC’s LFRMP’s started in June 2016 after approval by the EDI
Committee in April 2016.  Cycle 2 was due to be published in June 2022, however
delays due to the Covid pandemic have resulted in a deferred publishing date of 31
December 2022.  The Act requires the LFRMP’s to be published by each Lead Local
Authority (LLA) by 31 December 2022. 
4.7  Flood Protection Schemes identified in Cycle 1 of the LFRMPs for inclusion in Cycle
2 are as follows: 
Highland and Argyll
Clachan Flood Protection Scheme
Tarbert Flood Protection Scheme
Lochgilphead Property Flood Resilience Scheme
Oban Flood Protection Scheme 
Clyde and Loch Lomond
Helensburgh Property Flood Resilience Scheme
Kilcreggan Surface Water Drainage Scheme
Sandhaven Flood Protection Scheme
Page 10

Page 11

Black Park, Dunoon Flood Protection Scheme 
See Appendix 2 for further details. 
4.8  Proposed schemes were submitted to SEPA in December 2019 as part of a
national FPS prioritisation process. The outcome of this process is still to be
published by SEPA. As part of the process additional grant funding has been
sought from Scottish Government for the delivery of Flood Protection Schemes. 
Historically this has covered 80% of all eligible scheme costs, however at the
current time it is unclear what the funding provisions will be.  There is a high
likelihood due to tender price increases in the Cycle 1 programme that schemes
that have been put forward to the Scottish Government will not receive funding in
Cycle 2.  Progression with schemes is subject to success in the grant funding
application process. 
4.9  Also identified in Cycle 2 are flood risk studies and shoreline management plans that
are scheduled to be delivered within this cycle. These are expected to be completed
using consultants, with Argyll and Bute Council’s Infrastructure Design Team
managing these contracts and financed as detailed in Appendix 2. 
5.0  IMPLICATIONS 
5.1  Policy – Argyll and Bute Council Flood Risk Management Policy.   
5.2  Financial – Projects identified will need to have appropriate capital funding made
available. 
5.3  Legal – Acceptance by Environment, Development and Infrastructure Committee
and all responsible authorities within the LPD to the Local Plan satisfies paragraph
34 of the Act.  Completion of the Local Plan is achieved when the above is satisfied
and the SEPA Plan is approved by Scottish Ministers.   
5.4  HR – None.   
5.5  Fairer Scotland Duty 
5.5.1  Equalities – Protected characteristics – None.
5.5.2  Socio Economic Duty – None.  
5.5.3  Islands – None.   
5.6  Climate Change – The actions set out within the Local Plan take account of the
impact of climate change.  The Plans are designed to enable communities to adapt
and be prepared for the risk of flooding through the predicted increase in storm
events and rising sea levels.  Sustainable development is promoted and managed
through the Planning system. 
5.7  Risk – There is a statutory deadline of 31 December 2022 that the LLA (The
Highland Council) has to report progress with the Local Plan to Scottish Ministers.  It
is important therefore that Members appreciate that approval of the plan (as modified
or agreed by Environment, Development and Infrastructure Committee) is required to
Page 11

Page 12

achieve the reporting programme set out in the legislation. 
5.8  Customer Service – The actions set out within the Local Plan are designed to protect
communities and make them more resilient to the risk of flooding. 
Executive Director with responsibility for Roads and Infrastructure 
Services, Kirsty Flanagan 
Head of Roads and Infrastructure Services, Jim Smith 
Policy Lead for Climate Change and Environment Services – Councillor Ross
Moreland 
December 2022 
For further information contact: 
Jim Smith Head of Roads and Infrastructure Services 
Jim.Smith@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – Links to SEPA Flood Risk Management Plans for Highland and Argyll, noting
that Clyde and Loch Lomond can also be accessed from this link 
Appendix 2 – Table of LFRMP Actions and estimated costs (2022-2028) 
Appendix 3 - Highland and Argyll Local Flood Risk Management Plan (2022 – 2028) 
Page 12

Page 13

APPENDIX 1 - LINKS TO SEPA FLOOD RISK MANAGEMENT PLANS FOR
HIGHLAND AND ARGYLL 
Flood Risk Management Plan – Highland and Argyll Local Plan District Highland and
Argyll Flood Risk Management Plan – 2021 Flood risk management plans 2021
(sepa.org.uk) 
Flood Risk Management Plan – Clyde and Loch Lomond Plan District – 2021 Flood risk
management plans 2021 (sepa.org.uk) 
Page 13

Page 14

APPENDIX 2 – TABLE OF LFRMP ACTIONS AND ESTIMATED COSTS (2022-2028) 
Target
Area ID
SEPA
Plan
Local
Plan
District
Target
area
name
Action
ID
Action
type
SEPA Plan general
description (called
'Action' in final target
area datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
LFRMP
Funding
source
Estimated
Cost
£ k
(2019
Prices)
26 Clyde
and Loch
Lomond
Helens
burgh
2601 Property
flood
resilience
scheme
The proposed scheme to
provide resilience
measures against
flooding for individual
buildings is to be taken
forward to help prevent
water entering the
property and to minimise
flood damage. 
As part of the Helensburgh
Flood Protection Scheme
property flood resilience and
resistance measures will be
implemented. 
To be
confirmed -
progression
dependent
upon budget 
Capital plus
any available
external
funding
1,438
26 Clyde
and Loch
Lomond
Helens
burgh
2602 Shoreline
managem
ent plan
(coastal
adaptive
plan)
An assessment of
coastal flood and erosion
risk is to be carried out.
The plan should include
assessment of climate
change and develop
adaptive approaches to
allow for the impacts of
climate change to be
monitored, understood
and managed. 
Progress the development of
the shoreline management
plan for the Argyll and Bute
coastline. 
Estimated
delivery
2023/24
Capital plus
any available
external
funding
10 Page 14

Page 15

26 Clyde
and Loch
Lomond
Helens
burgh
2605 Surface
water
managem
ent plan 
Areas at risk of heavy or
prolonged rainfall
causing flooding due to
water ponding on man-
made surfaces or
overwhelming the
drainage system are to
be identified. These
priority areas will provide
a baseline for the
identification of next
steps in managing water
ponding or over-
whelmed drainage
systems. This should
guide adaptive planning
to allow for the impacts
of climate change to be
monitored, understood
and managed. 
Develop and implement a
surface water management
plan to reduce the risk of
flooding from surface water
and small watercourses in
Helensburgh. The impacts of
climate change on flood risk
should be assessed. The
results of the sewer flood risk
assessment should be
considered. Opportunities to
disconnect surface water from
the sewerage system should
be identified. The surface
water management plan
should be reviewed and
updated regularly.
To be
confirmed -
progression
dependent
upon budget 
Capital/
Revenue
plus any
available
external
funding
40
67 Clyde
and Loch
Lomond
Kilcreg
gan
6701 Flood
scheme or
works
implement
ation
The flood scheme/works
is to be built following
agreement of the design,
costs and timescales.
Progress the flood works
based on the detailed design.
The works involve
refurbishment of an existing
surface water channel and a
new pipe network which
discharges to a watercourse. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
Ongoing Capital/
Revenue
plus any
available
external
funding
425
67 Clyde
and Loch
Lomond
Kilcreg
gan
6702 Surface
water
managem
ent plan 
Areas at risk of heavy or
prolonged rainfall
causing flooding due to
water ponding on man-
Implement the surface water
management plan. The plan
should be reviewed and
updated regularly.
Ongoing Capital/
Revenue
plus any
available
10
Page 15

Page 16

made surfaces or
overwhelming the
drainage system have
been identified. Next
steps in managing such
water ponding or over-
whelmed drainage
systems have been
identified and should be
implemented. The plan is
to be reviewed and
updated as needed.   
external
funding
Target
Area ID
SEPA
Plan
Local
Plan
District
Target
area
name
Action
ID
Action
type
SEPA Plan general
description (called
'Action' in final target
area datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
LFRMP
Funding
source
Estimated
Cost
£ k
(2019
Prices)
88 Clyde
and Loch
Lomond
Rothes
ay and
Port
Bannat
yne
8801 Flood
study
An understanding of
flood risk and associated
issues in the area is to
be developed, which
may include surveys and
modelling and should
consider the impacts of
climate change on flood
risk. In areas where flood
risk is confirmed, a range
of possible options to
manage flood risk are to
be identified, including
natural flood
management actions
where suitable, and a
preferred approach is to
be chosen. This should
include adaptive
planning to allow for the
impacts of climate
change to be monitored,
A flood study should be carried
out to address coastal and
surface water flood risk in
Rothesay and Port Bannatyne.
Using the best understanding
of current coastal processes
and anticipated changes due
to climate change, flood
modelling should be
undertaken to review the
standard of protection offered
by the coastal defences.
Surface water flood modelling
should also be progressed and
include the Lade area. The
impacts of climate change on
flood risk should be evaluated.
The interactivity between
coastal flooding and surface
water flooding should be
assessed. If flood risk is
Ongoing Capital/
Revenue 
70 Page 16

Page 17

understood and
managed. 
confirmed, scoping of the next
steps should be completed.
88 Clyde
and Loch
Lomond
Rothes
ay and
Port
Bannat
yne
8802 Flood
defence
maintenan
ce
The existing flood
defences are to be
maintained by the asset
owner to ensure they are
in good condition.  
Maintenance to the Rothesay
Flood Protection Scheme
should continue and updates
to the maintenance regime be
made based on the findings of
the flood study.
Ongoing Capital/
Revenue
plus any
available
external
funding
250
100 Clyde
and Loch
Lomond
Sandba
nk
10001 Flood
scheme or
works desi
gn
The selected preferred
approach for managing
flood risk is to be
designed following the
completion of the flood
study, including
consideration of the long-
term impacts of climate
change. These can
include small scale
works or works to
improve catchment
management. This
should guide adaptive
planning to allow for the
impacts of climate
change to be monitored,
Further development of the
preferred option may be
required prior to commencing
with the detailed design. Argyll
and Bute Council to develop
the detailed design of the flood
protection works in
Sandhaven, Sandbank based
on the preferred option from
the surface water management
plan. The preferred option
identified to mitigate surface
water flooding is a small
embankment with discharge to
open channel. 
The responsible authority
proposes this action as the
To be
confirmed -
progression
dependent
upon budget 
Capital/
Revenue
plus any
available
external
funding
20
Page 17

Page 18

understood and
managed. 
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available. 
100 Clyde
and Loch
Lomond
Sandba
nk
10002 Flood
scheme or
works
implement
ation
The flood scheme/works
is to be built following
agreement of the design,
costs and timescales.
Progress the flood works
based on the detailed design. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
108
Target
Area ID
SEPA
Plan
Local
Plan
District
Target
area
name
Action
_ID
Action
type
SEPA Plan general
description (called
'Action' in final target
area datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
LFRMP
Funding
source
Estimated
Cost
£ k
(2019
Prices)
Page 18

Page 19

105 Clyde
and Loch
Lomond
Cardro
ss
10501 Flood
study
An understanding of
flood risk and associated
issues in the area is to
be developed, which
may include surveys and
modelling and should
consider the impacts of
climate change on flood
risk. In areas where flood
risk is confirmed, a range
of possible options to
manage flood risk are to
be identified, including
natural flood
management actions
where suitable, and a
preferred approach is to
be chosen. This should
include adaptive
planning to allow for the
impacts of climate
change to be monitored,
understood and
managed. 
A flood study should be carried
out to improve understanding
of coastal, river and surface
water flood risk in Cardross.
The interactivity between
sources of flooding should be
assessed. The impacts of
climate change on flood risk
should be evaluated. If flood
risk is confirmed, scoping of
the next steps should be
completed. Data collection
may also be included. Argyll
and Bute Council to consider
installing rain and river
monitors on Kilmahew Burn. 
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
90
105 Clyde
and Loch
Lomond
Cardro
ss
10502 Shoreline
managem
ent plan
(coastal
adaptive
plan)
An assessment of
coastal flood and erosion
risk is to be carried out.
The plan should include
assessment of climate
change and develop
adaptive approaches to
allow for the impacts of
climate change to be
monitored, understood
and managed. 
Progress the development of
the shoreline management
plan for the Argyll and Bute
coastline. 
Ongoing Capital/Reve
nue plus any
available
external
funding
10
Page 19

Page 20

107 Clyde
and Loch
Lomond
Dunoon 10701 Flood
scheme or
works desi
gn
The selected preferred
approach for managing
flood risk is to be
designed following the
completion of the flood
study, including
consideration of the long-
term impacts of climate
change. These can
include small scale
works or works to
improve catchment
management. This
should guide adaptive
planning to allow for the
impacts of climate
change to be monitored,
understood and
managed. 
Further development of the
preferred option may be
required prior to commencing
with the detailed design. Argyll
and Bute Council to develop
the detailed design of the flood
protection works in Black Park
(Ash Park), Dunoon based on
the preferred option from the
surface water management
plan. The preferred option
identified to mitigate flooding is
a filtration trench discharging
to the combined sewer. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
35
107 Clyde
and Loch
Lomond
Dunoon 10702 Flood
scheme or
works
implement
ation
The flood scheme/works
is to be built following
agreement of the design,
costs and timescales.
Argyll and Bute Council to
progress the flood works
based on the detailed design. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
500
Target
Area ID
SEPA
Plan
Local
Plan
District
Target
area
name
Action
_ID
Action
type
SEPA Plan general
description (called
'Action' in final target
area datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
LFRMP
Funding
source
Estimated
Cost
£ k
(2019
Prices)
Page 20

Page 21

107 Clyde
and Loch
Lomond
Dunoon 10705 Flood
defence
maintenan
ce
The existing flood
defences are to be
maintained by the asset
owner to ensure they are
in good condition.  
Continue to maintain the Milton
Burn Flood Protection Scheme
(2012), Kilbride Road, Dunoon
Flood Prevention Scheme
(2007) and other existing flood
defences in Dunoon.
Ongoing Revenue 3
107 Clyde
and Loch
Lomond
Dunoon 10707 Surface
water
managem
ent plan 
Areas at risk of heavy or
prolonged rainfall
causing flooding due to
water ponding on man-
made surfaces or
overwhelming the
drainage system have
been identified. Next
steps in managing such
water ponding or over-
whelmed drainage
systems have been
identified and should be
implemented. The plan is
to be reviewed and
updated as needed.   
Argyll and Bute Council to
implement the surface water
management plan. The plan
should be reviewed and
updated regularly.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
20
111 Clyde
and Loch
Lomond
Gareloc
hhead
11101 Flood
study
An understanding of
flood risk and associated
issues in the area is to
be developed, which
may include surveys and
modelling and should
consider the impacts of
climate change on flood
risk. In areas where flood
risk is confirmed, a range
of possible options to
manage flood risk are to
be identified, including
natural flood
management actions
where suitable, and a
preferred approach is to
A flood study should be carried
out to improve understanding
of coastal flood risk in
Garelochhead. The
interactivity between coastal
and other sources of flooding
should be assessed. The
impacts of climate change on
flood risk should be evaluated.
If flood risk is confirmed,
scoping of the next steps
should be completed. Data
collection may also be
included.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
40
Page 21

Page 22

be chosen. This should
include adaptive
planning to allow for the
impacts of climate
change to be monitored,
understood and
managed.
111 Clyde
and Loch
Lomond
Gareloc
hhead
11102 Shoreline
managem
ent plan
(coastal
adaptive
plan)
An assessment of
coastal flood and erosion
risk is to be carried out.
The plan should include
assessment of climate
change and develop
adaptive approaches to
allow for the impacts of
climate change to be
monitored, understood
and managed. 
Progress the development of
the shoreline management
plan for the Argyll and Bute
coastline. 
Ongoing Capital/Reve
nue plus any
available
external
funding
5
Page 22

Page 23

Target
Area ID
Local
Plan
District
Target
area
name
Action
ID
Action
type
SEPA Plan general
description (called
'Action' in final target area
datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
Funding
source
Estimated
Cost
£ ,000
(2019
Prices)
346 Highlan
d and
Argyll
Campb
eltown
34602 Surface
water
manage
ment
plan 
Areas at risk of heavy or
prolonged rainfall causing
flooding due to water
ponding on man-made
surfaces or overwhelming
the drainage system have
been identified. Next steps
in managing such water
ponding or over-whelmed
drainage systems have
been identified and should
be implemented. The plan
is to be reviewed and
updated as needed.   
Implement the Campbeltown
Surface Water Management
Plan which will help to manage
residual surface water and
sewer flood risk. In the
Meadows and Burnside
Square areas road gullies will
be disconnected from the
combined sewer network with
drainage held in above ground
and below ground storage
basins, for a controlled release
back into the combined
system. Additional properties
are targeted for property level
flood resilience. 
Ongoing Capital  plus
any available
external
funding
Included
in contract
awarded
for £12.7
Million
346 Highlan
d and
Argyll
Campb
eltown
34603 Shorelin
e
manage
ment
plan
(coastal
adaptive
plan)
An assessment of coastal
flood and erosion risk is to
be carried out. The plan
should include assessment
of climate change and
develop adaptive
approaches to allow for the
impacts of climate change
to be monitored, understood
and managed. 
Progress the shoreline
management plan. This should
consider the impacts of sea
level rise on future flood risk.
The need for an adaptation
plan should be assessed. 
Ongoing Capital  plus
any available
external
funding
10
346 Highlan
d and
Argyll
Campb
eltown
34604 Flood
scheme
or works
impleme
ntation
The flood scheme/works is
to be built following
agreement of the design,
costs and timescales.
Progress the Campbeltown
Flood Protection Scheme. As
built drawings should be made
available to SEPA, for
consideration in the Scottish
Flood Defence Asset
Database, flood map
Ongoing Capital  plus
any available
external
funding
CONTRA
CT
AWARD
£12.7
Million
Page 23

Page 24

improvements and flood
warning scheme updates.
353 Highlan
d and
Argyll
Clacha
n
35301 Flood
scheme
or
works de
sign
The selected preferred
approach for managing
flood risk is to be designed
following the completion of
the flood study, including
consideration of the long-
term impacts of climate
change. These can include
small scale works or works
to improve catchment
management. This should
guide adaptive planning to
allow for the impacts of
climate change to be
monitored, understood and
managed. 
Develop the detailed design of
the flood protection works in
Clachan based on the
preferred option from the flood
study. The preferred option
includes removal of a weir
structure from the Clachan
Burn and property flood
resilience. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital  plus
any available
external
funding
25
353 Highlan
d and
Argyll
Clacha
n
35302 Flood
scheme
or works
impleme
ntation
The flood scheme/works is
to be built following
agreement of the design,
costs and timescales.
Progress the flood protection
works in Clachan based on the
detailed design. As built
drawings should be made
available to SEPA, for
consideration in the Scottish
Flood Defence Asset
Database, flood map updates
and flood warning scheme
updates. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
To be
confirmed -
progression
budget
dependent
Capital  plus
any available
external
funding
263
Page 24

Page 25

action is subject to capital
funding being made available.
Target
Area ID
SEPA
Plan
Local
Plan
District
Target
area
name
Action
_ID
Action
type
SEPA Plan general
description (called
'Action' in final target area
datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
LFRMP
Funding
source
Estimated
Cost
£ k
(2019
Prices)
353 Highlan
d and
Argyll
Clacha
n
35305 Commun
ity flood
alert
A community river level
alerting system is to be
installed to provide
information on the potential
for localised flooding.
A river level alerting system is
being installed with the help of
the Scottish Flood Forum. 
Ongoing Revenue 1.5
361 Highlan
d and
Argyll
Tarbert 36101 Flood
scheme
or
works de
sign
The selected preferred
approach for managing
flood risk is to be designed
following the completion of
the flood study, including
consideration of the long-
term impacts of climate
change. These can include
small scale works or works
to improve catchment
management. This should
guide adaptive planning to
allow for the impacts of
climate change to be
monitored, understood and
managed. 
Further development of the
preferred option may be
required prior to commencing
with the detailed design.
Develop the detailed design of
the Tarbert Flood Protection
Scheme based on the
preferred option from the flood
study. The preferred option
consists of flood defence walls
and demountable defences.
Property flood resilience is to
be provided outwith the
scheme extent. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
428
Page 25

Page 26

361 Highlan
d and
Argyll
Tarbert 36102 Flood
scheme
or works
impleme
ntation
The flood scheme/works is
to be built following
agreement of the design,
costs and timescales.
Progress the Tarbert Flood
Protection Scheme based on
the detailed design. As built
drawings should be made
available to SEPA, for
consideration in the Scottish
Flood Defence Asset
Database, flood map updates
and flood warning scheme
updates. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital/Reve
nue plus any
available
external
funding
4,285
361 Highlan
d and
Argyll
Tarbert 36105 Surface
water
manage
ment
plan 
Areas at risk of heavy or
prolonged rainfall causing
flooding due to water
ponding on man-made
surfaces or overwhelming
the drainage system are to
be identified. These priority
areas will provide a
baseline for the
identification of next steps
in managing water ponding
or over-whelmed drainage
systems. This should guide
adaptive planning to allow
for the impacts of climate
change to be monitored,
understood and managed. 
Develop and implement a
surface water management
plan. This should be reviewed
and updated regularly. The
impacts of climate change on
flood risk should be assessed.
The results of the sewer flood
risk assessment should be
considered. Opportunities to
disconnect surface water from
the sewerage system should
be identified. The plan should
be reviewed and updated
regularly.
To be
confirmed -
progression
dependent
upon budget 
Capital  plus
any available
external
funding
45 Page 26

Page 27

Target
Area ID
SEPA
Plan
Local
Plan
District
Target
area
name
Action
_ID
Action
type
SEPA Plan general
description (called
'Action' in final target area
datasheets)
LFRMP description of Action
to be carried out by Argyll
and Bute Council
Indicative
Delivery
LFRMP
Funding
source
Estimated
Cost
£ k
(2019
Prices)
366 Highlan
d and
Argyll
Oban 36601 Flood
scheme
or
works de
sign
The selected preferred
approach for managing
flood risk is to be designed
following the completion of
the flood study, including
consideration of the long-
term impacts of climate
change. These can include
small scale works or works
to improve catchment
management. This should
guide adaptive planning to
allow for the impacts of
climate change to be
monitored, understood and
managed. 
Develop the detailed design of
the Oban Flood Protection
Scheme based on the
preferred option from the flood
study. The preferred option
consists of a combined flood
storage and direct defence
solution to protect against
flooding from the Black Lynn
and property flood resilience to
protect against coastal
flooding. Some more work is
required on the surface water
element. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available. 
In accordance with the flood
risk management plan, as part
of the scheme or works, the
responsible authority should
aim to ensure the action will
not have an adverse effect on
the integrity of the Inner
Hebrides and the Minches
Special Area of Conservation.
To be
confirmed -
progression
dependent
upon budget 
Capital/
Revenue
plus any
available
external
funding
760
Page 27

Page 28

366 Highlan
d and
Argyll
Oban 36602 Flood
scheme
or works
impleme
ntation
The flood scheme/works is
to be built following
agreement of the design,
costs and timescales.
Progress the Oban Flood
Protection Scheme based on
the detailed design. As built
drawings should be made
available to SEPA, for
consideration in the Scottish
Flood Defence Asset
Database, flood map updates
and flood warning scheme
updates. 
The responsible authority
proposes this action as the
best viable option for
managing flood risk in this
community. The delivery of this
action is subject to capital
funding being made available.
To be
confirmed -
progression
dependent
upon budget 
Capital/
Revenue
plus any
available
external
funding
7,600
366 Highlan
d and
Argyll
Oban 36604 Surface
water
manage
ment
plan 
Areas at risk of heavy or
prolonged rainfall causing
flooding due to water
ponding on man-made
surfaces or overwhelming
the drainage system have
been identified. Next steps
in managing such water
ponding or over-whelmed
drainage systems have
been identified and should
be implemented. The plan
is to be reviewed and
updated as needed.   
Implement the surface water
management plan. The plan
should be reviewed and
updated regularly.
To be
confirmed -
progression
dependent
upon budget 
10  Page 28

Page 29

APPENDIX 3 - DRAFT HIGHLAND AND ARGYLL LOCAL FLOOD RISK MANAGEMENT PLAN CYCLE 2   
Highland and Argyll Local Flood Risk Management Plan (2022-2028) Highland and Argyll Local Flood Risk Management Plan (2022-2028)   
Page 29

Page 30

This page is intentionally left blank

Page 31

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                    1 DECEMBER 2022
SERVICES                     
CEMETERY ASSET REPORT 
1.0  EXECUTIVE SUMMARY 
1.1 This report provides an update on the current Argyll and Bute cemetery provision
and, highlighting interventions within the asset group since this was last reported to
Committee in 2019 and providing a revised list of at risk assets based on current
figures and a revised projection model. Overall the number of high risk assets has
reduced since 2019 
2.0 RECOMMENDATIONS 
The Environment, Development and Infrastructure Committee are asked to: 
2.1 Endorse the works done to date to reduce the number of high risk cemetery assets; 
2.2 Endorse and approve the temporary local arrangement to restrict the pre-sale of
lairs to protect the cemetery capacity; 
2.3 Consider the future capital investment required in this asset group; and 
2.4 Note that a further report on cemetery assets will be brought forward to the March
Environment, Development and Infrastructure Committee meeting, which will
present options for reviewing the current policy as well as management of cemetery
assets in the context of current needs and future demands. 
3.0 DETAIL 
3.1 In December 2019 the Committee gave consideration to a report that presented
a summary of the Council’s cemetery assets.  The report provided information
on the condition of the cemeteries including available lair space.  At that time 14
sites were identified as high risk e.g. breaching capacity within 5 years. This list
showed two entries against different sections of Pennyfuir – on reflection it is
better to consider that as a single site, which brings the high risk sites down to
13.   
3.2 Since then a number of interventions have been made or are identified at various
sites including agreed capital extension works and reclaiming lair
space/maximising where possible the existing footprint of sites which has
improved the position. 
Page 31 Agenda Item 5

Page 32

3.3 As well as physical works, Officers have revised the expectancy projections.
Previously expectancy was calculated based on a five year average of lair sales.
The new projections are based on last year’s lair sale figures only because it
better reflects the current climate. The Burial Service and the provision of Lair
Spaces in Cemeteries are linked but are two distinct and separate parts of the
Bereavement Service provided by the Council as the Burial Authority. The selling
of Lair Certificates at point of request, uses up land in burial grounds in advance
of the requirement for the Burial team to open a lair for an interment. There are
however differing rates of uptake of lairs at each location and hence a variation
in the remaining time before all space is sold. This is separate from the number
of interments, as lairs can be used multiple times. The timescales vary from 1
year to over 100 years within the portfolio of active cemeteries. 
3.4 Officers are aware that in particular new cemetery development in Kintyre has
been challenging, despite efforts over the past three years we have been unable
to progress a suitable site. As such and to protect the capacity of the cemetery
for local residents, officers have taken the decision to prevent the pre-sale of lairs
unless there has been a death. Although this has not been a policy decision,
along with the new counting mechanism introduced, it now means Kilkerran
Cemetery has a predicted expectancy which was less than 4 years in 2019 to 10
years. This now allows officers more time to develop plans for a new site. 
3.5  As a result of this works the number of high risk sites has reduced from 13 to 4.
The 2019 ‘at risk’ asset list has been updated to reflect the above and is
appended to this report at Appendix 1. A summary of the main highlights of that
work, where sites which were previously high risk now have a future capacity of
10+ years is summarised in the table below: 
Site Intervention/change Outcome
Appin Extension  90 additional lairs
created; 38 years of
expectancy. 
Lismore Reclaimed space within
existing site
9 additional lairs
created; 16 years of
expectancy 
Kilmorlich No new lairs sold since
2019
13 years of expectancy
Carrick Reclaimed space 70 additional lairs
created; 72 years of
expectancy 
Pennyfuir Developed space with
further options within
current landholding
230 lairs created;
further areas to secure
40-50 years of
expectancy
Achnaba A further extension was
available for use
Expectancy now 49
years
Kilchattan Only 1 lair sold in last 3
years
Expectancy now 28
years
Page 32

Page 33

Tobermory Contract let for extension Will create 190 lairs;
expectancy 95 years
Kilkerran A local arrangement was
put in place to restrict pre-
sale, which has slowed
the rate of purchase.
10 years expectancy
now based on current
sales figures 
3.6 At Appendix 2 there is a revised development programme based on the new
projection model and taking account of the interventions since 2019. This shows
5 high risk sites, with 1 new site shown based on the up to date sales figures. 
3.7 Capital funds will be required in order to either purchase adjacent land and
extend current cemeteries, or to provide new cemeteries. There are currently no
capital funds allocated to a future cemetery expansion programme. Based on
current high level estimates the costs of extending or creating new cemeteries to
address the high risk assets is £310,000. To secure the future of all sites on the
identified programme at Appendix Two would likely cost £910,000 based on initial
high level estimates. Members will note that some sites identified as at risk in the
revised programme do not have obvious solutions in terms of new land. It is
recommended that Members consider future capital investment required in this
asset group as part of the 23/24 budget process. 
3.8 The Policy and Resources Committee recently agreed to allocate £300,000 from
possible future Crown Estate for improvements to cemeteries within their existing
footprint e.g levelling sunken lairs, repairs to access tracks, pathway restorations
etc. This possible future funding will be split evenly across the four administrative
areas. As and when funding is confirmed Officers will bring forward a set of
proposals.   
4.0 CONCLUSION 
4.1 This report provides an update on the current Argyll and Bute cemetery provision. 
5.0 IMPLICATIONS 
5.1 Policy – Potential policy issue re stopping pre-sale of lairs 
5.2 Financial – Capital funding will be required for the ongoing provision of additional
lair capacity 
5.3 Legal – None known. 
5.4 HR – None known. 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – None known. 
Page 33

Page 34

5.5.2   Socio-economic Duty – None known. 
5.5.3 Islands – None known. 
5.6. Climate Change – None known. 
5.7  Risk – None known. 
5.8  Customer Service – None known. 
Executive Director with responsibility for Roads and Infrastructure Services: 
Kirsty Flanagan 
Policy Lead for Climate Change and Environment Services: Councillor Ross
Moreland 
November 2022                                                  
For further information contact:  
Hugh O’Neill, Network and Standards Manager 
Appendices:
Appendix 1 – At Risk Asset List 2019 Updated 
Appendix 2 – Cemetery Development Programme 
Page 34

Page 35

APPENDIX 1 – 2019 AT RISK CEMETERY ASSETS UPDATED:
Status key:
<5 years 
5-10 years 
10-15 years 
>15 years 
Cemetery Lairs
available
2019
Expectancy
in 2019
based on
avg. 5yr
model
Interventions Current
lairs
available 
Expectancy
based on
previous
year
figures
Further
possible 
interventions
within
budgets
Revised
status 
Comments 
Appin new
extension
0 0 Land
purchased
and Extension
constructed
21/22 value
£45k
providing 90
additional
lairs 
87 – As
three were
issued as
part of the
land
purchase
agreement
to the land
owner.
38 years n/a – No
further
extension
practicable on
this site 
38 years
of
estimated
burial
space
based on
new
calculation
method –
sale of lair
space only 
Community
Council
purchased
land at a cost
of £20k and
passed it to
ABC to
develop.
Total Cost
for 90 lairs
was £65k. 
Lismore 0 0 Reclaimed
space within
existing site 
Additional 9
lairs created
8 16 Officers are
engaging with
Church of
Scotland to
establish a
further
cemetery
16 years
of
estimated
burial
space
based on
new
Officers
reviewed the
area and
increased lair
space by
moving a
shed.  Cost to
Page 35

Page 36

area on
adjacent land.
calculation
method –
sale of lair
space only
the council
was minimal
and part of
operations
work. 
Kilmorlich 2 1 Exploring the
possibility of
an extension
on new land
in the vicinity
2 13 – No
new lairs
sold since
2019.
Average of
lair sales
was
therefore
estimated.
Exploring the
possibility of
an extension
on new land
in the vicinity 
Previous
figures for
2019 were
based on
interments
and therefore
skewed.
Pennyfuir
Section Q
1 1 New sections
(R&S) are
being
developed at
present –
please refer
to below
updates.
FULL -
See
Pennyfuir
update
below
FULL - See
Pennyfuir
update
below
FULL - See
Pennyfuir
update below
FULL -
See
Pennyfuir
update
below
Section Q is
now Full,
Sections R&S
are now
selling lair
space 2019
onwards. 
This line
should be
discounted –
rather than
looking at
Pennyfuir in
sections the
site should be
considered
as one. 
Page 36

Page 37

Kilmun 31 1 33 additional
lairs
developed by
reducing
roadway to
footpath width
in 2021.
64 – Pre
sale of
lairs has
reduced
this to 28.
2 No more land
available at
this site. –
Cowal
Cemetery
Extension 5
miles away
being done.
2 years
providing
no pre-
sale of
lairs
Officers
consider
stopping the
pre-sale of
lairs to
preserve
remaining
space at this
site.  
Carrick 19 1 – based
on 2019
calculation
of 16
interments
per year
NOT lairs
sold.
70 Additional
lair spaces
released due
to re-design
of current site. 
72 72 years
based on
last year’s
sale of only
1 lair
Potential
extension
access road
repositioned
within current
footprint.
72  Land
purchase is
required to
allow
alternative
access road
and lair
space to
preserve
service at this
site. 
Pennyfuir  101 1 Sections R&S
being
developed
ahead of lair
space
requirement. 
230 6 years There is
sufficient land
to allow
further
extensions.
Possibility
of a
further 40-
50 years
within
current
land
ownership
when this
is
prepared. 
Section R
has been
completed
and section S
is being
prepared at
present.
Page 37

Page 38

Tobermory
(New)
Beadoun
12 2 New
contractor
appointed for
works
beginning 28
November
2022 – 
2 (will be in
excess of
190 after
completion
of work in
June 2023)
1 Construction
of extension
allowing extra
190 lairs by
June 2023 
95 years £800,000
scheme
agreed,
contractor
appointed –
this will
create 190
additional
lairs
Strachur 14 2 Reclaimed
space by
moving
footpaths etc. 
12 lairs
created
6 2 Site for a new
cemetery
currently
being
assessed at
Succoth
Road
Glenbranter 
New site will
need to be
purchased
from 3rd party
and needs a
hydrological
assessment
to ascertain
site
suitability.
Cowal High
Road
123 2 Council
owned Land
on adjacent
site
transferred to
RIS and now
being
prepared for
an extension.
50 2 Tree root
clearance
and ground
preparation
within
revenue
programme 
Extensive
works
required to
make the
ground
suitable for a
cemetery
extension.
Achnaba Ex
1&2 
3 3 Extension 3
was available
for further use
148 49 Achnaba
extensions
1&2 now
FULL.
49 Lair sales
restricted to
parish
Page 38

Page 39

and is now
being utilised.
Residents
only. 
Kilkerran
Extension
187 4 A local
arrangement
was put in
place to
restrict pre-
sale, which
has slowed
the rate of
purchase. 
147 10 – based
on the
reduced
rate of
annual lair
sale 
Additional
space may be
achievable by
reconfiguring
space within
the current
footprint 
No
adjacent
land
suitable
for
extension
1st
alternative
site
rejected –
landowner
not willing
to deal
with
Council
NEW
Campbeltown
cemetery  - 4
sites west of
town on
A83/B842
being
explored for
suitability
Calgary 5 5 Adjacent land
fenced off and
work in kind
delivered in
lieu of land
purchase.
2 – No
lairs sold in
last years
2 Shared
Access track
and fencing
upgraded,
land ready for
use. 
Planning
application
and transfer
of ownership
- 2023
Kilchattan 15 5 Revised
assessment
Only 1 lair
sold in last
3 years
28 years Now outwith
20year
priority list 
Review in 10-
15 years
Pennygowan 36 6 None 30 8 Adjacent land
in Council
ownership 
Assess
options for
extension
2024>
between
Page 39

Page 40

cemetery and
Roads yard.
Achnabreac
Section K
70 6 Additional 328
lairs
developed  in
owned land
Sept 2021
348 lairs
available in
total 
45 years at
current rate
of sale 
Main M-A
cemetery –
review in 5-
10 years
Kingarth
extension
50 7 None 36 9 Option to
extend
behind or
adjacent to
existing
extension. 
Land owner
details to be
confirmed –
towards land
purchase
options
Kilmodan 9 9 None 6 6 Limited scope
for adjacent
extension 
Review
options for
new site in
vicinity - 2024
onwards.
Clachan
(New)
46 9 None 40 – only 2
lairs sold in
last year 
20 Revised
assessment 
Consider
extension 5-
10 years time
Putechan  38 10 4 lairs sold in
last year
33 lairs in
remaining
extension
8 Scope to
extend in
adjacent field 
Land
purchase
required –
landowner
contacts
2024 >
Lochgoilhead 20 10 None 16 8 Limited scope
to extend
without major
works 
Options for
adjacent of
nearby sites
to be
Page 40

Page 41

considered
2024 >
Kilbrandon
Old
40 11 Figure
actually relate
to NEW
cemetery 1
lair sold in last
year
33
remaining
9 Scope for
further
extension in
adjacent field 
Land
purchase
required –
landowner
contacts
2024 > 
Page 41

Page 42

This page is intentionally left blank

Page 43

ARGYLL AND BUTE COUNCIL - CEMETERIES DEVELOPMENT REVUE - 2021-22  APPENDIX 2 - Cemetery Development Programme
CEMETERIES DEVELOPMENT PROGRAMME - in order of Priority  ( Red, Amber, Yellow only)
HIERARCHY OF NEED -  by age -    Area Data -  as at OCT 22. -  BASED ON SALE OF LAIRS TO NEW APPLICANTS  ( uptake of remaining land)
Key RED =  0-5Years remaining at current Lair Sale Rate  = CURRENT DEVELOPEMNT PROGRAMME  2022-23 >
AMBER = 5-10 Years For consideration in future programmes = early options to be considerd
YELLOW - 10-20years Future Years - NO PLANS AT PRESENT - but uptake to be monitored.
Cemeteries ACTIVE Expectancy - YEARS REMAINING CAPACITY  - RE-EVALUATION OF PREVIOUS SITES  - OCTOBER 2022      
AREA  /   DISTRICT CEMETERY
LAIRS SOLD
SEPTEMBER
2021 TO              
SEPTEMBER
2022
NUMBER OF
NEW LAIRS
REMAINING
FOR SALE 
OCT22
ESTIMATED
REMAINING
OPERATIONAL 
YEARS
UPDATED COMMENTS - NOVEMBER 2022  - INCLUDING ASSESSMENT OF
CONSTRUCTION POTENTIAL AND EXTIMATED COST
ESTIMATED VALUE OF
DEVELOPMENT 
INCLUDING ANY  LAND
PURCHASE
or Average  5yr 
Cowal
Strachur 3 6 2.00
12 New spaces FOUND 2022 in existing area      On prog 2022-23  NEW
SITE - Succoth Road tbc - land enquiries and Planning applications 2023. £  150,000.00 Sandbank 10miles
Isle of MULL
Calgary 1 2 2.00
Development of extension 2021-22  ( ~160 single depth lairs )
Works completed in Lieu of land sale - to prepare area for use  / access -                                  
Planning application for change of use  -  early 2023  £  20,000.00
Beadoun
(Tobermory) 15miles
Cowal
Cowal High Road 24 50 2.08
On development programme 2022 (# NEW ADJACENT SITE SANDBANK #)
Major development of main cemetery for Dunoon and South Cowal - land
enquiries and Planning applications  2023 for development in stages £  100,000.00 n/a
Cowal
Kilmun 12 28 2.33
33 ADDITIONAL LAIRS IN EXTENEDED AREA 2022 however 12 already
sold  -                28 Lairs remain available 2023 - NO PRESALE TO
PRESERVE SPACE. None - No land Sandbank 5miles
Isle of ISLAY
Keills, Islay 3 15 5.00
***NEW*** Potential for extension of existing to be considered , brought
into programme due to increased sales   -  CONSIDER NO PRE-SALE TO
PRESERVE SPACE £  40,000.00 Bowmore 8miles
Cowal Kilmodan 1 6 6.00
Limited scope for extension on adjacent ground consider alternatives by
2024 None - No land Strachur 8miiles
Kintyre
Skipness 2 12 6.00
Sufficient capacity for foreseeable future - reconsider in 3 years  (2025)                           
CONSIDER NO PRESALE TO PRESERVE SPACE  £  40,000.00 Carrick   M-A 11miles
Isle of MULL
Pennygowan 4 30 7.50
Limited scope for extension on adjacent ground - consider alternatives site
- enquiries on suitable locations within next 2-3 years. (  by 2025) £  50,000.00
Beadoun
(Tobermory) 12miles
Cowal Lochgoilhead 2 16 8.00
Limited scope for extension on adjacent ground-consider alternatives by
2024 £  30,000.00 Strachur 10miles
Kintyre Patchen 4 33 8.25
Potential for extension of existing to be considered within 3-4 years by
2025 £  15,000.00 C/Town new 11miles
Isle of ISLAY Bowmore 7 59 8.43 Potential for extension of existing review 3-4 years - adjacent land  by 2025 £  15,000.00 n/a
Isle of BUTE
Kingarth extension 4 36 9.00
Explore potential for Ph3 extension option in adjacent field - ownership
enquiry and planning application  Feb  2022 >     re-asses Jan 2023  > £  20,000.00 Barone Rd 7miles
Isle of BUTE
N. Bute Cnoc-an-raer extension 2 16 156 9.75
updated Sept 21 - Sufficient capacity - reconsider in 5 years    CONSIDER
NO PRESALE TO PRESERVE REMAINING SPACE  - scope for adjacent
extension £  30,000.00 Barone Rd 5miles
Helensburgh and Lomond Barbour 3 31 10.33 Limited scope for extension  - reconsider alternatives in 5 years (2027) no suitable ground Rosneath 6miles
Kintyre
Kilkerran Existing  Extension  ## 14 147 10.50
No scope to extend  - 4 sites West of Campbeltown to be considered 2022
for development of new main cemetery for Campbeltown and South
Kintyre Currently - NO PRESALE OF LAIRS TO PRESERVE
SPACE  - sale rate reduced . £      150,000.00
Campbeltown
(New  site  - tbc) ~3miles
DISTANCE TO NEXT
NEAREST  OR "MAIN"
DISTRICT CEMETERY  .
Name              Miles
Page 43

Page 44

Isle of IONA Iona 2 26 13.00
Special residents requirements necessary for Lair Sales- review 5yrs (
2027) £        30,000.00 Suidhe(Bunessan) 5miles
Cowal
Kilmorich 0.15 2 13.33
On development programme 2021   NEW ADJACENT SITE    land enquiries
and design pending , towards planning application 2022 .  No new lair sale
since 2019 £        30,000.00 Strachur 5miles
Lorn Kilninver 2 27 13.50 Sufficient capacity for foreseeable future - reconsider in 5 years (2027) £        30,000.00 Pennyfuir 10miles
Isle of LISMORE
Lismore 0.5 8 16.00
Additional 9 Lairs Sept 21  -   On Development programme 2021-22 >  in
discussion with community council on suitable sites at chuch or
elsewhere - IMPORTED SOIL REQUIRED - INSUFFICIENT DEPTH AT
PRESENT £        70,000.00 Appin 10miles
Isle of BUTE
Barone Road section A & B 10 190 19.00
updated Sept 21 - Sufficient capacity - reconsider in 5 years    CONSIDER
FOOTPATH EXTENSION AS PART OF WORK   - scope for adjacent
extension £        60,000.00 n/a
Kintyre Clachan (New) 2 40 20.00 Potential for extension of existing to be considered within 10 years by 2032 £        30,000.00 Carrick   M-A 9miles
Isle of GIGHA Keil 1 24 24.00 Sufficient capacity for foreseeable future - 5 yrs - Scope for adjacent extension Patchen-Kintyre 12miles
Kintyre Killean 2 58 29.00 Sufficient capacity for foreseeable future - reconsider in 5 years  (2027) Patchen-Kintyre 6miles
Lorn Kilbrandon (Balvicar) 1 33 33.00 Sufficient capacity for foreseeable future - reconsider within 2-3 years (by 2025) Pennyfuir 15miles
Lorn Achnaba Ext 3 3 148 49.33 Special residents requirements for Lair Sales (limited scope to further extend) Pennyfuir 8miles
Isle of ISLAY Kilchoman 3 184 61.33 Sufficient capacity for foreseeable future - reconsider in 5 years  (2027) Bowmore 11miles
Mid-Argyll
Carrick Old and New 1 72 72.00
Additional 70 Lairs released Sept 21.   New Extension to lairs to north and
carpark & access road to east  - Plan started 2020 -21 , progress in next 5 yrs Achnabreac 16miles
Kintyre Brackley 2 215 107.50 Sufficient capacity for foreseeable future C/Town new 16miles
Cowal Cladhamhulin/Millhouse 2 273 136.50 Sufficient capacity for foreseeable future Strachur 22miles
5 year programme Budget 310,000.00£         
6 - 15 year programme Budget 600,000.00£         
TOTAL 910,000.00£         
Page 44

Page 45

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE 
ROADS AND INFRASTRUCTURE         01 DECEMBER 2022 
ELECTRIC VEHICLE CHARGING STRATEGY UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council has an existing network of 28 public EVCs, which are
now charged for. As EVC becomes increasingly popular, and as the ban on new
internal combustion engine vehicles approaches, there is a clear need for a
comprehensive EVC strategy which includes both options to sustainably
manage and maintain the existing network as well as developing it at pace as
and when funding arises.  
1.2 This report provides an update under various headings: 
 EVC expansion plans and public consultation
 Possible costs and future external funding options
 Maintenance of the current network
 Future procurement and installation 
 Update on installation work over the past 12 months 
1.3 Background information including previous committee reports and the EV strategy
Part One; Cost Recovery Model is available on the Council website here. 
RECOMMENDATIONS 
The Committee is asked to: 
Agree the development and prioritisation methodology at Appendix 1 and the 55
site EV expansion list at Appendix 2, noting that the expansion plan was
supported by three-quarters of respondents to the EVC public consultation. 
Note that Officers continue to engage with Transport Scotland on future funding
options through the new Electric Vehicle Infrastructure Fund and that a specific
Member Seminar will be arranged on EVC when there is clarity on how that fund
will operate 
Page 45 Agenda Item 6

Page 46

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE 
ROADS AND INFRASTRUCTURE          01 DECEMBER 2022 
ELECTRIC VEHICLE CHARGING STRATEGY UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on the work over the past year to continue the
development of the Council’s EVC strategy, including public consultation, and
developing future options for maintenance, funding and procurement.   
3.0 RECOMMENDATIONS 
The Committee is asked to:
3.1 Agree the development and prioritisation methodology at Appendix 1 and the 55
site EV expansion list at Appendix 2, noting that the expansion plan was
supported by three-quarters of respondents to the EVC public consultation. 
3.2 Note that Officers continue to engage with Transport Scotland on future funding
options through the new Electric Vehicle Infrastructure Fund and that a specific
Member Seminar will be arranged on EVC when there is clarity on how that fund
will operate 
Page 46

Page 47

4.0 DETAIL 
4.1 EVC expansion plans and public consultation [EVC strategy Part Two]
4.1.1 A detailed methodology was presented to the June 2021 meeting of this
committee, then discussed at a Member Seminar in September 2021 which led
to changes to the original proposed methodology. The original draft had sites to
be prioritised large towns to small, whereas feedback from the Seminar meant
that we changed the prioritisation to focus on small villages/towns first on the basis
that larger towns already have at least one charger. We had also originally
proposed to cut off at settlements smaller than 1,000 population but following
feedback we included villages with a smaller resident population than that but
acknowledging that tourist traffic is significant. An updated draft list and
methodology was then presented to the December 2021 meeting. Appended to
this report at Appendix 1 is the development methodology and the draft long list
is at Appendix 2. 
4.1.2 The agreed draft development methodology and site list went out to public
consultation to ensure that communities had the opportunity to be involved in the
process of deciding where future public EVCs installations should be across the
Council area, and how that network should be developed and prioritised. 
4.1.3 The consultation was promoted in a variety of ways, from social media and
website links and via the national EVC back office support provider Charge Place
Scotland.  People were informed that the consultation was taking place and a link
to the online survey was provided on each of the platforms. We received 254 
responses from across Argyll and Bute; and as well as giving views on specific
questions, respondents also provided more than 500 comments. 
4.1.4 The full consultation findings report is appended to this report at Appendix 3 and
an overview of themes from the consultation is at Appendix 4. 
4.1.5 On the basis that three-quarters of those responding to the consultation supported
the proposed expansion plan and development methodology, these are therefore
recommended to the committee for approval to be adopted as the Council’s EVC
expansion policy. This will effectively complete the second part of the five part
EVC strategy.
4.1.6   The list is entirely theoretical, and it is anticipated that as the list is worked through
there could be infrastructure limitations or technical considerations which may
prevent development at a specific site. Although the development methodology
provides for different priority bands, until such time as there is clarity on the
possible future funding options it is not possible to develop a method to determine
how that funding should be allocated to sites within the priority bands e.g. how
sites are prioritised within the priority bands against available funding. As and
when there is clarity on external funding a further report will come forward for
Members to agree funding allocations. 
Page 47

Page 48

4.2 POSSIBLE COSTS AND FUTURE FUNDING OPTIONS
4.2.1 It was previously reported to this committee that the third part of the strategy would
give consideration to future funding requirements and options – mapping,
application, management – to deliver on the outline programme developed
through Part Two.
4.2.2 Since then the Scottish Government has set out its vision for electric charging
infrastructure in Scotland. To briefly summarise, the vision expects that £60million
of investment will be made in EVC, with that investment to be 50% publicly funded
by SG, with the other 50% coming from private finance.  
4.2.3 It is not clear at this stage how the private element would work, but what is clear
is that the Scottish Government will provide £30million of public funding across
Scotland’s 32 local authorities through an Electric Vehicle Infrastructure Fund
[EVIF]. This funding will be allocated through a competitive bidding process, the
details of which are not yet available. 
4.2.4 Based on historic costs, we are estimating an average EVC purchase and
installation cost of £25,000. With the rise in inflation a contingency element has
been built in to our estimates which gives an average cost for estimating purposes
of £30,000 per site. This gives an estimated total of £1,650,000 to deliver our 55
site plan. 
4.2.5 The Scottish Futures Trust has been tasked with supporting the Scottish
Government in developing various delivery models for local authorities to
consider, and they have outlined three possible delivery models, two of which
indicate how private finance could potentially be levered in:
(i)  Leasing sites 
Local authorities consider land holdings that may be suitable for commercial
charge point delivery and offer sites they own to a private partner via a long lease
which affords the opportunity to install and operate charge points. The private
partner retains financing, installation, and service delivery risk.  It sets tariffs and
retains all the revenue it generates from EV users (subject to the terms of the
lease).  A lease might include conditions regarding the private partner’s actions,
but typically allows freedom and flexibility for the private partner.  Sites could be
offered to the partner in bundles with a mixture of high and low income sites, but
this option is more suitable for more sites with higher utilisation that require little
or no public subsidy. 
Land and all below ground assets could remain in local authority ownership.  The
local authority could offer a “prepared site” and use its grant funding to secure
network upgrades as well as any associated civils works.  The local authority may
wish to charge rent and/or take a share of future revenues.   
(ii)  Concession contracts 
The risk associated with installation, maintenance, and service delivery across
multiple sites, including asset utilisation, is transferred to a private partner who
Page 48

Page 49

finances the capital and replacement costs of new charger points after taking any
grant funding into account.  The private partner sets tariffs and retains the revenue
it generates from EV users (subject to the terms of the concession agreement). 
The contract term would reflect the period required by the private partner to
recoup and make a return on invested capital.  At the end of the contract term the
assets are expected to revert to the local authority. 
Land and all below ground assets could remain in local authority ownership (which
could command a rent and/or share of future revenue) or the private partner could
be expected to source land from other parties.  The local authority could offer
some “prepared sites” and use its grant funding to secure network upgrades as
well as any associated civils works.   
The local authority may also decide to transfer the operation, maintenance and
replacement risk of its existing charge point assets to the private partner for the
duration of the contract and in turn, allow the private partner to generate income
from these exiting sites. 
Unlike the leasing option, where the local authorities would not be involved in
service delivery, the private partner’s performance in a concession contract would
be monitored via a KPI Framework. 
This model is expected to be deployed where private sector investment on its own
is unlikely to be viable.
(iii)  Local Authority Owner Operator 
Local authorities set the specification, procure the capital works, and retain
responsibility for the operation and maintenance of the charging network.  They
procure a Charge Point Management System and a customer support provider,
or a full turnkey Charge Point Operator to provide the interface with the EV users,
collect data, monitor performance, manage costs, process payments, and
facilitate fault resolution.   
Whilst capital costs are likely to be procured via a fixed price contract, and
maintenance costs covered by warranties, all risk relating to capital, operation,
and maintenance costs as well as charge point utilisation, income generation and
customer relationship management are retained by the local authority. The local
authority funds the capital costs, operation, maintenance, and repairs are funded
from the tariff and income generated.
4.2.6 SFT have recognised that variations to each of these models to meet local
circumstances may be required to reflect each local authority’s preferred long-
term role in the delivery of public charging services.  It may be the case that in
some circumstances local authorities wish to consider the merits of establishing
a joint venture with a private sector organisation.
4.2.7 At this stage Officers continue to engage with SFT and Transport Scotland
through various forums to monitor and contribute to the development of the
national vision and to ensure Argyll and Bute Council is well placed to bid for
funding when the EVIF fund officially opens up. This is expected to be early 2023. 
Page 49

Page 50

4.3 MAINTENANCE OF THE NETWORK/FAULT ISSUES 
4.3.1 The fourth part of the strategy focusses on maintenance. Fault reporting is simple
for the EVC user; it can be done via the CPS phone number which is on all units
or their online form.  Once received it is assigned a ticket number and various
back office troubleshooting is undertaken to try and bring the unit back into use
remotely. If this communication fails an engineer is scheduled with a Service Level
Agreement of 48hrs, unfortunately the SLA is rarely met due to a combination of
manpower over commitments and our geography.  This is not uncommon across
all local authorities. If the fault can be fixed within the warranty agreement this is
carried out and if not a quote for the work is provided by SWARCO directly to the
Council for approval and authorisation.  Once the fault is rectified the back office
system is updated.    
4.3.2 We have been proactive with fault and maintenance issues.  We are monitoring
faults and adding service disruptions to the Council’s website, liaising closely with
SWARCO to stay up to date on faults that run longer than the SLA and have
recently gone out to tender for new maintenance and warranty contracts.
4.3.3 We are currently running a tender process to replace and simplify the numerous
maintenance and warranty contracts that currently exist as a result of contracts
being extended over the years.  This new single contract will see units being
added to it as their existing contract ends making it easier to manage and monitor
moving forward.  The new contract has been done using the Scottish
Governments new Scotland Excel procurement framework and we have
progressed this with our Procurement colleagues. At the time of writing this report
that procurement exercise has not concluded but it may conclude prior to the
Committee meeting. Once that new contract is in place and we have a detailed
maintenance plan that will effectively complete this part of the EVC strategy. 
4.4 PROCUREMENT AND INSTALLATION STRATEGY
4.4.1 Part Five of the strategy considers future procurement and installation. Previously
EVC installs were procured through open tender which was time consuming. As
a result of engagement with and work by Scotland Excel there are now national
framework contracts which are in place which should allow for much faster call
offs as and when funding arises. Once we have funding clarity it is our intention
to develop a detailed programme year by year subject to a further decision by
Members on funding allocations, and to look to appoint large contracts on allotted
basis with optional follow on lots – this should find the balance between pace of
delivery and ensuring quality. 
4.5 UPDATE ON ASSET MANAGEMENT AND EXPANSION 
4.5.1 A summary of the work to deliver installations, relocate charger and explore
new EVC opportunities is summarised in the table below: 
Page 50

Page 51

Item Funding Comments
HITRANS
FASTER project
c. £372,000 This is a fund administered by
HITRANS directly. This is a detailed
piece of work which is covered fully at
Appendix 5 of this report. 
Dunoon Grammar
pilot
The Power Networks
Demonstration Centre
[PNDC] at Strathclyde
University were
managing a project which
aimed to gain data in
order to improve the
maintenance and repair
of EVC. The academic
and Industrial research
and development scheme
funded from the
Infrastructure Solutions
for Zero Emission Vehicle
fund, provided by the
Office for Zero Emission
Vehicles (OZEV).   
It was planned that Argyll and Bute
would receive 4 fully funded EV charge
points, including the costs of hardware,
installation and operation (excluding
metered energy costs). Unfortunately
the opportunity was lost due to the
project funding tight timescales and the
additional layer of complexity to the
sites due to them being managed by
third parties. 
It is important to note this was not
wasted exercise, a lot of learning was
gained and that knowledge and future
planning will now be applied to future
installs like the one noted below at
Oban High School.
Relocation of
Helensburgh Pier
EVCs
Helensburgh Waterfront
Development
This has been a highly resource
intensive project to support, with calls
on the project team’s time along with
colleagues from Infrastructure Design
to assist in relocating the Helensburgh
EVC from their previous position near
the old leisure centre to the new leisure
facility car park.  There has been 6+
months of intense modification work
required to ensure the EVCs are
reinstated to full working capacity and
in line with Transport Scotland
specification. Unfortunately at the time
of writing there remain some snagging
issues with the relocated chargers
which are being picked up directly with
the contractor.
Council business
chargers
£130,000 from Switched
on Fleets
Successful installs at Jackson’s Quarry
depot, Oban, and an additional unit at
Helensburgh Civic Centre 
Working on a scheme to install a
charger at Oban High School if a
suitable agreement can be reached
with ABC Schools who manage the
school on behalf of the Council.
Tarbert  £47,000 from SSEN This would provide a charger in Tarbert
[an identified site within the Expansion
Page 51

Page 52

Plan] funded through SSEN at no cost
to the Council. This is a community
benefit from the power installation
projects in the area. Funding has now
been secured. 
Tighnabruaich £63,000 from Transport
Scotland
This is a legacy scheme from the
previous Local Authority Install
Programme
Arrochar Any costs absorbed in
EVC budget
We are relocating the EVC that
currently sits within Luss Estates
carpark, Arrochar.  The Council did
lease this carpark but when that
agreement ended in 2021 the EVC
was effectively nested in a third party
site which had different access
arrangements from our other EVCs. 
There is an outline proposal for an
improvement project at the Glen Loin 2
car park and we had been hoping to
synchronise the proposed works there
with the move of the EVC, but it now
appears that that project won’t proceed
in earnest for some time depending on
other funding applications. With that in
mind we are making arrangement to
move the EVC now, so that it is
publically available in the adjacent car
park in advance of future works to that
site. 
5.0 CONCLUSION
5.1  If Members adopt the long list of public sites and the delivery methodology, which
were supported by three-quarters of those responding to the public consultation,
this will become Council policy and will be the list of sites to be worked through
as and when external funding arises. 
5.2  A significant amount of work has gone into the development of the EVC strategy
and the Council is now well placed to deliver on further EVCs and to have robust
systems in place to manage the network. How the strategy develops from this
point will largely depend on clarity on future funding. 
6.0 IMPLICATIONS 
6.1 Policy – EVC strategy would be formally adopted as Policy and will guide
development of EVC as and when future funding arises.
6.2 Financial – cost recovery model is covering electricity costs; capital costs
currently 100% externally funded.
Page 52

Page 53

6.3  Legal – none 
6.4  HR – none
6.5  Fairer Scotland Duty:
6.5.1 Equalities - protected characteristics
6.5.2 Socio-economic Duty - none   
6.5.3 Islands – gaps in the network are prioritised through the public programme. 
6.6 Climate Change – implications for climate change through EVC strategy are
very positive. Expanding our public network will encourage people to transition
to electric vehicles, reducing CO2 emissions and moving towards a greener
transport system. 
6.7 Risk – in terms of future options, there may be risks associated to a commercial
model.
6.8  Customer Service – Working to ensure a better maintenance and warranty
contract which will increase network reliability and provide a better service for
our customers. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure 
Jim Smith, Head of Roads and Infrastructure 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
October 2022 
For further information contact: 
Mark Calder, Project Manager 
Mark.Calder@argyll-bute.gov.uk 
Victoria Weir, Project Officer 
Victoria.Weir@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – EVC Infrastructure Development Methodology
Appendix 2 – Proposed EVC Expansion List
Appendix 3 – Consultation Responses
Appendix 4 – EVC Consultation Headlines and Key Themes 
Appendix 5 – HITRANS FASTER Project 
Page 53

Page 54

This page is intentionally left blank

Page 55

APPENDIX 1: EVC INFRASTRUCTURE DEVELOPMENT METHODOLOGY –
(UPDATED 9.11.21) 
Aim: to inform Part Two of the EVC strategy, with a view to arriving at a consolidated
long list of future EVC sites across various asset groups. Focus on network coverage
[addressing any gaps in the existing network], with network expansion [expansion of
existing provision on existing sites] to follow. Focus on equity. 
Infrastructure should be split into three distinct themes, with a default charger
type/composition per theme:
Theme 1 – charging on the move [rapid [50kw] – 90mins to 2 hours to fully
charge]
This theme should provide rapid chargers at/on/near the public road network [and as
that relates to car ferry routes]. 
The assumption is that users will utilise these chargers while ‘on the move’ for a ‘top
up’, therefore these should be in the fastest charging category. 
Theme 2 – destination charging [fast [22kw] – charge in 4 hours; slow [7kw] –
charge in 7 hours]
This theme should provide fast chargers at locations where users are likely to leave
their cars for an extended period of time such as long stay off-street car parks, with
the default charger in these locations being fast. 
Slow chargers may be considered for transport hubs/park and ride facilities where
users are likely to leave their vehicles overnight. 
Theme 3 – residential charging [slow [7kw] – charge in 7 hours]
This theme should provide overnight charging capability for residential housing which
lacks on street parking, either retrospectively [likely responsibility of RSLs] or through
planning gain. 
Theme 1 – charging on the move
Addressing any gaps in the existing network to provide for one rapid charger every
25 – 35 mins [HiTRANS/Strathclyde University methodology for the FASTER project
recommend the figure of 30mins to ensure driver confidence], as an aspiration, while
acknowledging that this may not be appropriate for every setting:
 Sites should be at/on/near existing settlements with local amenities, with a
view that the network development should bring consequential economic
development gains e.g. EV users utilise local shops, cafes etc. while their car
charges. 
 Sites should be in Council ownership/control
 Consideration of grid capacity and associated cost barriers. 
 Sites should have the potential for future expansion. 
Page 55

Page 56

 Delivery prioritised in tranches according to the existing road and pier
hierarchy
 Sites not in Council ownership can be considered if necessary to fill a network
gap. Bringing these into Council ownership would be preferable. 
Therefore the strategic priorities for site identification and delivery should be as
below: 
Gaps every 25-35 minutes
Hierarchy Priority rating
A roads 
Principal car ferry ports [mainland side]
1
B roads 
Principal car ferry ports [island side] 
Car ferry ports [mainland side]
2
C roads 
Car ferry ports [island side]
3
U roads 4 
Note: this is a theoretical methodology at this point – it is unlikely that significant
gaps will exist further down the priority rating/hierarchy. 
Theme 2 – destination charging 
This theme should provide for charging infrastructure where users are likely to leave
their cars for an extended period of time. 
 Sites should be in Council ownership as part of existing medium-long stay
parking provision
 Sites not in Council ownership can be considered if necessary to fill a network
gap. Locating chargers at site within Council ownership would be preferable. 
At least one fast charger
Hierarchy Coverage Priority rating
Towns 1,000 – 2,000 
Principal ferry ports
[mainland side] 
Rail park and rides 
Airport [mainland]
One car park 
All 
All 
All
1
Page 56

Page 57

Towns 2,000 to 5,000 
Principal ferry ports
[island side] 
Ferry ports [mainland
side]
25% of off-street car
parks [largest to smallest
or as appropriate for local
needs] 
All 
All
2
Towns 5,000 to 10,000 
Ferry ports [island side]
50% of off-street car
parks [largest to smallest
or as appropriate for local
needs] 
All
3
Towns of greater than
10,000 
Island airports
All off-street car parks 
All
4
Theme 3 – residential charging
This theme will need to be explored further to see if there are any residential areas
with a lack of on-street parking which are within Council ownership. 
At present it is anticipated that the Council will have little if any involvement in
providing residential charging infrastructure as the requirement for this is likely to be
on RSL owned sites. 
Future planning policy should reflect the need for residential EV provision. 
Note for all themes: in developing the consolidated long lists consideration will
need to be given to suitable delegated infrastructure cost barriers relative to the
particular location and likely future usage. These barriers or cost ranges are likely to
become clear once sites are selected and cost estimates can be prepared. 
Page 57

Page 58

This page is intentionally left blank

Page 59

AREA TOWN/VILLAGE EXISTING LOCATION COUNCIL OWNED PROPOSED THEME PRIORITY COMMENTS
STRACHUR MEMORIAL HALL Y 1 x RAPID 1 1 This would provide for a network gap between Dunoon and
Inveraray/Arrochar
GUILDFORD SQUARE Y 1 x RAPID 1 1 Currently therE is no rapid charging provision on the island
GUILDFORD SQUARE Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks
1 x SLOW GUILDFORD SQUARE Y
CHAPELHILL ROAD CAR PARK Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks
ROTHESAY HARBOUR Y 1 x RAPID 1 2 Principal fery port [island side]. Rapid charger to be provided for
cars in the ferry queue as opposed to parked up.
ROTHESAY HARBOUR Y 1 x FAST or SLOW
[TBC] 2 2 Second charger at this site to provide for those ferry passengers
who wouldleave their car.
TIGHNABRUAICH ROCKBANK Y 1 x RAPID 1 2 Previousy committed to via 2019/20 TS LAIP funding
INNELLAN SANDY BEACH Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
PORT BANNATYNE ON-STREET PARKING BAY [EXACT
DETAILS TBC] Y 1 x FAST 2 1 On the basis that there is no off-street car park proposed on street
to meet network gap
1 x FAST AND 1 x
RAPID COAL PIER ALEXANDRA PARADE Y
HANOVER STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
KIRK STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
ARGYLL STRET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
GLENMORAG CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
JANE VILLA CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
MOIR STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
SANDBANK TSC CAR PARK Y 1 x FAST 2 1
Population 1,000 to 2,000 - one car park. It should be notedhere
that there is another car park owned by a local community group
which may provide for a better location [Ardnadam]
LOCHGOILHEAD SHORE ROAD CAR PARK Y 1 x FAST 2 1 Population fewer  than 1,000 but known tourist hotspot
CARDROSS MAIN STREET CAR PARK Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks [or at least
one]
ARROCHAR 1 x RAPID LOCH LONG CAR PARK N
Currently engaged in discussions with Luss Estates as the Council's
lease on this car park has now ended.  agreed terms for one section
(Clydebank Developments) which Legal are nearing completion on
and the other section which is owned by Crown Estates is under
discussion but seems likely that we will agree terms soon to
purchase that as well
KILCREGGAN SHORE ROAD CAR PARK Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
GARELOCHHEAD COMMUNITY CENTRE Y 1 x FAST 2 2
Population of 2,000 to 5,000 - 25% off-street car parks [or at least
one]. Divergence from the 'higher to lower' original criteria of car
parks on the basis of local geography.
FERRY ROAD CAR PARK Y 1 x RAPID 1 2 Filling a network gap c. 30min drive from Helensburgh
FERRY ROAD CAR PARK Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
2 x FAST AND 3 x
RAPID WEST CLYDE STREET Y These are being moved within the site to accommodate the new
Swimming Pool
SINCLAIR STREET CAR PARK Y 1 x FAST 2 4 Population greater than 10,000 - all off street car parks
MAITLAND STREET CAR PARK Y 1 x FAST 2 4 Population greater than 10,000 - all off street car parks
KIDSTON PARK CAR PARK Y 1 x FAST 2 4 Population greater than 10,000 - all off street car parks
GRANT STREET PARK AND RIDE Y 1 x FAST or SLOW
[TBC] 2 1 Rail park and ride
LUSS OLD TOLL HOUSE CAR PARK Y 1x FAST 2 1 Population less than 1,000 but known tourist hotspot
BUTE & COWAL
HELENSBURGH &
LOMOND
DUNOON
ROTHESAY
ROSNEATH
HELENSBURGH
Page 59

Page 60

PIER, FERRY ROAD Y 1 x RAPID 1 1 To address a rapid charging network gap between Campbeltown
and Lochgilphead [on the public road network for drivers]
TAYINLOAN FERRY FERMINAL Y 1 x RAPID 1 1 Rapid charger to be provided for cars in the ferry queue as opposed
to parked up.
TAYINLOAN FERRY FERMINAL Y 1 x FAST or SLOW
[TBC] 2 1 Second charger at this site to provide for those ferry passengers
who wouldleave their car.
FERRY TERMINAL Y 1 x RAPID 1 2 Rapid charger to be provided for cars in the ferry queue as opposed
to parked up.
FERRY TERMINAL Y 1 x FAST 2 2 Second charger at this site to provide for those ferry passengers
who wouldleave their car.
CARRADALE SHORE ROAD CAR PARK Y 1 x RAPID 1 2 To address  a network gap in East Kintyre
CAMPBELTOWN ROAD CAR PARK Y 1 x RAPID 1 1 To address an existing rapid charging network gap between
Campbeltown and Lochgilphead
1 x FAST CAMPBELTOWN ROAD CAR PARK Y
NEW QUAY CAR PARK y 1 x FAST 2 2
Population of 2,000 to 5,000 - 25% off-street car parks. Divergence
from the 'higher to lower' original criteria of car parks on the basis
of local geography.
1 x RAPID NEW QUAY CAR PARK y
ARDRISHAIG CHALMERS ST No. 2 CAR PARK 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
2 x FAST AND 1 x
RAPID LORNE ST No. 1 CAR PARK Y
2 x FAST MANSE BRAE CAR PARK Y
INVERARAY 1 x FAST AND 1 x
RAPID THE AVENUE Y
COLONSAY COLONSAY AIRPORT Y 1 x FAST or SLOW
[TBC] 2 4 Island airport
BOWMORE 1 x RAPID AND 1 x
FAST SCHOOL STREET CAR PARK Y
FERRY TERMINAL Y 1 x RAPID 1 2 Rapid charger to be provided for cars in the ferry queue as opposed
to parked up.
FERRY TERMINAL Y 1 x FAST or SLOW
[TBC] 2 2 Second charger at this site to provide for those ferry passengers
who wouldleave their car.
CRAIGHOUSE COUNCIL CAR PARK 1 x FAST 2 3
Proposed instead of Feoilin ferry terminal with a view to providig
for the main service centre, also noting that the ferry crossiNG s
relatively short and there is provision on the Islay side
OBAN LOCHAVULLIN CAR PARK
Y
1 x FAST
2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
Consideration will need to be given to known flooding at this site
OBAN
1 x FAST AND 1 x
RAPID TWEEDDALE STREET CAR PARK Y
OBAN LONGSDALE ROAD CAR PARK Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
OBAN CORRAN HALLS 1 Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
OBAN NORTH PIER Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
OBAN GANAVAN SANDS Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
TIREE 1 x RAPID FERRY TERMINAL SCARANISH N
COLL 1 x RAPID COMMUNITY CENTRE, ARINAGOUR N
FIONNPHORT 1 x RAPID COLUMBA CENTRE CAR PARK Y
CRAIGNURE
1 x RAPID AND 1 x
FAST CRAIGNURE CAR PARK Y
TOBERMORY 1 x RAPID LEDAIG CAR PARK Y
PORT APPIN FERRY TERMINAL/SLIPWAY Y 1 x RAPID 1 2 Mainland-side ferry
MID-ARGYLL,
KINTYRE AND THE
ISLANDS
PORT ASKAIG
TAYINLOAN
GIGHA
TARBERT
CAMPBELTOWN
LOCHGILPHEAD
Page 60

Page 61

PORT APPIN FERRY TERMINAL/SLIPWAY Y 1 x FAST or SLOW
[TBC] 2 2 Mainland-side ferry
SEIL
[ELLENABEAICH] FERRY TERMINAL/SLIPWAY Y 1 x RAPID 1 2 Mainland-side ferry
SEIL
[ELLENABEAICH] FERRY TERMINAL/SLIPWAY Y 1 x FAST or SLOW
[TBC] 2 2 Mainland-side ferry
CUAN FERRY
[SEIL]
FERRY TERMINAL/SLIPWAY
Y
1 x RAPID 1 2 Mainland-side ferry
CUAN FERRY
[SEIL]
FERRY TERMINAL/SLIPWAY
Y 1 x FAST or SLOW
[TBC] 2 2 Mainland-side ferry
CULLIPOOL FERRY TERMINAL/SLIPWAY Y 1 x RAPID 1 3 Island-side ferry
CULLIPOOL FERRY TERMINAL/SLIPWAY Y 1 x FAST or SLOW
[TBC] 2 3 island-side ferry
COLL AIRPORT Y 1 x FAST or SLOW
[TBC] 2 4 Island airport
OBAN AIRPORT Y 1 x FAST or SLOW
[TBC] 2 1 Mainland airport
28 54
OBAN LORN AND
THE ISLES
Page 61

Page 62

This page is intentionally left blank

Page 63

ELECTRIC VEHICLE CHARGER (EVC) Consultation
The EVC Consultation was run from 23rd May until 30th June 2022.  254 responses were submitted.
The consultation was as follows: 
Page 63

Page 64

Page 64

Page 65

Q.6 In response to Q.4  - Argyll and Bute Council intends to expand on its existing network of 28
public EVCs. Can you explain why you disagree with this approach:
PLEASE SEE APPENDIX 1 FOR THEMED RESPONSES
Q.7 In response to Q.5 
There are different types of chargers for different types of use: Rapid, Fast and Slow chargers.  We
intend to install a mixture based on the following criteria: [Themes 1-3]
If you answered NO to the question above, can you explain why you disagree with this approach?
PLEASE SEE APPENDIX 2 FOR THEMED RESPONSES
Q.8 Do you have any comments about the proposal?
PLEASE SEE APPENDIX 3 FOR THEMED RESPONSES 
Page 65

Page 66

APPENDIX 1
Argyll and Bute Council intends to expand on its existing network of 28 public EVCs.
If / when funding is available, we have proposed sites which will fill gaps in the
existing network, rather than increasing the number of chargers at our existing
sites.   This is on the basis that we want a good spread of chargers across different
communities along our road network, as well as at different sites within our larger
towns.
Can you explain why you Disagree with this Approach? 
COMMENT THEMES
MANAGING EVC PROJECT
Be more ambitious and lead the way.  Pair up with companies that can deliver a car park size of
chargers and uses solar panels or wind.
As you can tell from my postcode, I live in Garelochhead, according to your plans you intend to fit
one charging station for a population of 3,700.  I fully understand that you are limited by the
available funding (if any funding arrives), however I can not see how the addition of a single
charging point will have any effect on a population of this size (other than to cause arguments
about who gets access to it).  The issue of charging points really does need to be addressed on a
significantly larger scale if our goal is to move from fossil fuel to EVs then I would suggest that one
action that may be within our council remit would be to refuse planning permission for new
houses unless they include at least one off-road parking space per household with EV charging
capability and, additionally, provide some plan for retrofitting old housing stock with EV charging
capability. I understand that this issue is not of your making and that you are trying to help,
however, I believe that any additional funding our council can get to address this problem would
be better used by fighting for a more realistic approach to the EV charging problem, you need to
convince central government that the only way people will accept EVs is if they can charge them
up at home.
hubs with multiple chargers (or different speeds) offer the best user experience for both residents
and visitors
The parking spaces do not work for all vehicles, plug in points at different positions on cars means
the cables don't reach or are plugged in at angle and therefore the connection is void and unable
to charge
existing network is appalling and not well maintained
Should be up to the private sector to provide chargers.  It should not be for a council to provide
assistance to the wealthier people in society i.e. those that can afford electric cars.
NOT ENOUGH EVCS
Oban & Lochgilphead underserved with no rapid chargers. Also none from Oban over to Rest and
be Thankful via either Crianlarich or Inveraray.
Not enough !!! There should be a minimum of 4 charge points in each named location in A&B ie
Rhu Shanndon finart cove Rosneath etc etc
Fails to provide anywhere near sufficient chargers for residential use
Nowhere near enough. I live in Connel, and would like to see at least 2 charge points here.
Similarly, every village in rural Argyll should have provision made, if you are serious about a
commitment to electric vehicles.
The existing infrastructure is inadequate in peak season - most sites have only 2-4 chargers wth
very few fast chargers. If these are occupied it can mean a wait of several hours. The number of
Page 66

Page 67

chargers needs to be increased at existing sites, as well as new sites being introduced, but in my
view as an EV owner, expansion at existing sites is most important. 
NOT ENOUGH EVCS contd.
If electric vehicle uptake is to be encouraged and the sale of petrol/diesel vehicles are to be
discontinued in the near future then the odd charger or two in a few towns and public car parks
isn’t going to encourage people to switch over. There should be charging point s located in
public/private parking areas to support the move the electric vehicles.
Loch Lomondside is being neglected
Not enough chargers in our area. What about rapid charger in Strathlachlan - either at
Strathlachlan church or Strathlachlan community centre
We need more in rural areas e.g from lochgilphead to Inveraray is 24 miles, what happens if there
are a few people waiting to charge and I have an appointment in Glasgow? 
We  need FAR MORE chargers / charging stations if we ever want the majority of drivers to
consider replacing their cars with electric ones
Our village would all have to travel to Lochgilphead, with nothing in between. There's nothing in
Inveraray, or at Crarae Gardens, and there are quite a few villages in the area where people still
commute and live. There needs to be something near here, if not in Minard directly. I am disabled
and considering an electric vehicle, but it's becoming a struggle to figure out where to charge it in
such a remote location.
People could be marooned at southend. Not enough propsed for kintye generally, especially east
side
Only one fast charger is proposed at the community centre (Gibson Hall) at Garelochhead.  At this
time the nearest chargers to Garelochhead are at Arrochar (10 miles away) and Helensburgh (8
Miles away).  Garelochhead should have a minimum of two chargers with one being located in the
large layby opposite the Post Office.  The Head of Service has confirmed that there are now no
parking restrictions in this layby.  All overnight accommodation is in the centre of the village so
the first priority should be a charger opposite the Post Office.  Garelochhead should be upgraded
to a Priority 1.  The large number of people booking accommodation overnight will not park their
cars at a charger at the Gibson Hall when their accommodation is in the centre of the village. 
Another charger in Ardnadam Pier car park owned by Sandbank Community Development Trust
who would like to accommodate one or more.  
There are no charging facilities set out for Southend.  There are also no funding requirements
available for home charging units.
More fast eV chargers are needed particularly in areas with high number of visitors plus finding to
ensure existing chargers are maintained. 
The chargers that are currently in place are not adequate as it is. Most times a car is already
plugged meaning no charging can be done when required. I love my car but the world is not ready
for them.
Too few rapid chargers to encourage visitors and travellers
Need to have more chargers at existing sites as well as filling the gaps in the existing network.
Not enough chargers in existing locations. You need to do both. 
Not enough
More chargers needed on Kintyre 
NOT ENOUGH EVCS ON ISLANDS
The council are not proposing to expand the number of charging points by nearly enough of
what’s actually needed to get residents especially, to adopt EV usage. On the Isle of Mull, for
example, there’s only one additional charging point proposed at Ulva Ferry. Whilst welcome this is
not nearly enough, we need much more capacity at centres where there are larger populations as
well as tourist traffic, eg at Craignure, Tobermory, Dervaig, Bunessan for example.
Page 67

Page 68

NOT ENOUGH EVCS ON ISLANDS contd
Need to put some in rural areas nit just in towns like Tobermory it’s like Difiberators why is it
Turin get all the resources and money why nit put one at Dervaig or Calgary or Salen Mull 
On the Isle of Mull you need more charge points than just the one at Ulva Ferry.  There needs to
be a number in Salen, Dervaig and Calgary as well as points at/near the Ferry Terminal at Fishnish. 
Also, you need to stop overnight parking in the small car park at Craignure where commercial
vehciale reglularly parki in the parking places for the charge points making it impossible to put
your car on charge when travelling on the first ferry to Oban.
Islay needs electric chargers at both ferry ports. 
EVC SITES IN THE WRONG PLACE
I agree in principle, but leaving Tighnabruaich with the huge number of visitors it has as a priority
2? Does this mean it’s down the pecking order? And by Rockbank, precisely where would this be? 
Big hole in network right around Loch Awe when that area has most infrastructure (hydro &
windfarms) so should benefit not only have downside 
In Rothesay Guildford Square already has 2 and parking spaces are required for shopping
purposes. Better to install more than 1 at Chapelhill Car Park. 
Having chargers dispersed makes it more likely that when you arrive it is either in use or broken.
Much better to have larger charging hubs in Oban, Lochgilphead, Campbell town etc.
This approach is wrong.  Rapids in areas where there is hardly any traffic.  Look at the strategy of
the likes of instavolt, they have a nice spread at equi distance on the main roads for rapids, we
need more on the main trunk roads in and out of Argyll, having raids on the likes of gigha is
ridiculous especially if there is one across the water.  Please review this and expand the current
rapid stations, with more added to Oban and Cowal.
A glance at proposed sites for Oban and Lorn, appears to favour tourist areas, as opposed to
actual communities. By not attempting to provide these charging points, you are ensuring electric
vehicles remain an impractical option. That is simply not good enough.
EV placement seems for tourists and visitors, not locals - on Islay having Port Ellen and Bowmore
as big populations makes sense, having one at Port Askaig is purely for tourists.  Try prioritising
those who live here - why not Port Charlotte/Portnahaven/Bruichladdicb?
I agree but blank spots in taynuilt, dalmally, bridge of orchy, between oban and Lochgilphead 
Still nothing in Dalmally as one of the main areas reached after a long journey to Argyll?
I can only talk about Dunoon, since I live there. Almost every site proposed in Dunoon is within 1
mile of the town centre when in fact the big challenge  for charging and EV ownership is to give
people with no off road parking access to chargers. I therefore feel that a number of chargers
should be earmarked for the housing estates where the majority of Dunoon's population live,
many like myself with no feasible way to fit a charge point to our house. I feel a better approach
would be to use grants available for lamp post chargers spread through areas of high urbanisation
or fit them in school car parks which tend to be in densely populated areas. This may also
encourage teachers to take up EV ownership.
All of the charging points are situated to the north and centre of the town. There are none in the
south of the town where there is a huge population. What about one or two near the college or
OHS [Lochgilphead? Helensburgh?]
I think the B840 needs a public electric charge point and Portsonachan Hall which has a large
parking area by the B840 would seem to be a natural choice for a Theme 1 (rapid) charger for
local and tourist use 
Ellanabeich main car park would benefit from a charger for visitors. 
Page 68

Page 69

EVC SITES IN THE WRONG PLACE contd
There are obvious gaps at destinations such as Crinan and kilmartin
In these relatively early stages the chargers should be grouped in small/medium numbers which
makes these area essentially hubs - this will make installation costs lower and highlight to the
community where these chargers are. Also greater incentives for installing home charge points. 
The approach is fine but the map shows the new point predominantly closer to the age of the
Argyll rather then along the main roads across Argyll.      
With the size of population in Campbeltown and surrounding and given the distance one has to
travel to get to a charging point outside of South Kintyre, there should be more charging points
allocated to Campbeltown/South Kintyre/surrounding villages.  I can appreciate that this initiative
will have budgetary constraints but to see the number of units in Lochgilphead for example
compared to Campbeltown this does not add up.  
EVC SPEED OF CHARGING
Need super fast everywhere, unless you are inserting multiple points at each site. Parking is an
issue across Kintyre. 
With the existing (old) chargers, if one fast DC outlet is in use (CCS or CHAdeMO) then the other
cannot be used. There should be at least two chargers per location.
I feel there should be charging points on the Sandbank Community Area next to the A815 the
main road from Western Ferries into Cowal. It used to be called Ardnadam Car Park and was used
by the US Navy. It is now owned by Sandbank Community Development Trust. It should be rapid
chargers.
Rapid chargers should be left to commercial enterprises on main arterial routes. Public charging
should be focused on residential fast or slow charging for overnight charging near where people
live.  
NEED MONEY SPENT ON OTHER THINGS
Hardly ever a car in Guildford square but I have to drive via a unmarked pot holed road to get to
car park - think you need to address the state if the roads for us to drive safely before you add to
this scheme 
We need parking, not charging
A total waste of rate payers money.  Nobody subsidises my diesel.
Wasting money better spent on healthy housing stock for all, not stuff for the privileged 
Waste of money, fix the potholes first 
Page 69

Page 70

APPENDIX 2
Q.7 Responses 
There are different types of chargers for different types of use: Rapid, Fast and Slow chargers.  We
intend to install a mixture based on the following criteria: [Themes 1-3]
If you answered NO to the question above, can you explain why you disagree with this approach?
COMMENT THEMES
THEMES
Theme 1 charging is most useful for all types of user. In tourist destinations, the concern would
be that Theme 2 charging could be over-utilised by tourists overnight. To counter this, could
there not be a Theme 1 charging station at sports centre car parks, which are mostly used by
residents?
I agree with theme 1 and 2 but not with 3. If you are expecting places to be carbon neutral and
encourage people to buy electric vehicles as they are able to there needs to be better
infrastructure for on street charging.
I cannot see much if any demand in your theme 3.
I agree with themes one and two but it sounds as if in theme three that the council is washing
its hands of those of us who live in houses/flats unsuitable for charge points.
Generally, because there is a lack of funding, the piecemeal approach to building this
infrastructure has to be "themed" but Theme 1 ignores the ever increasing use of Ultra-rapid
chargers which would allow a faster turnaroound on the machine -reducing waiting times in
the busy summer periods. These machines will be most used by visitors on route to a
destination.
Theme 2 needs to be looked at. Most evs can’t pull 22kw on AC charger so end up reverting to
between 7-11kw. You need to know more about what the current EVs are capable of. One
option for the rapid chargers (Theme 1) is to top out at 80% which pod point fo to stop the
rapids being clogged up on time consuming the last 20% which slows considerably. 
You need to have some theme one chargers for people who r on a journey and just need to
top up so they can continue with their journey.Having so few at each venue means only one or
two vehicles will be able to charge if the intention is for them to charge overnight
Several proposed EVCs, even when they are in locations passed through by road users, are
designated Theme 2 (Fast).  Over and above that, utilising faster technology seems more
sensible.  One Rapid charger could charge at least two cars in the time it takes a Fast charger
to do one.  Fewer, but quicker, new chargers would be an alternative strategy worth
considering.  4 hours may be too long for passing visitors to wait.
Agree to theme 1 and 2.
Concentrate on Theme 1. If possible install even faster chargers. The problem is range, What is
needed is the facility to charge up quickly whilst travelling.
EVC SITES
If we as a society intend to move completely to EV’s. Then in locations that there are currently
petrol stations, then there should be EV chargers. These chargers should be of the differing
types but in LARGE numbers.
Why only council ownership locations? Surely all residential parking areas should be planned -
even if some funding comes from either residents or private bodies. 
Page 70

Page 71

LACK OF SPACES TO CHARGE 
In places like Port Bannatyne there are lots of privately owned flats witj no parking where only
the council could provide residential charging 
Super fast charging here at Kilcreggan Pier. There are limited number of spaces here anyone.
Slow  chargers will encourage locals to leave their cars for a long time and they will take much
needed spaces. 
Majority of charging needs to be catered for overnight charging. This requires sufficient on
street chargers to enable vehicles to be charged at residential on street chargers within short
distance of residences
You must ensure you expand your areas for locating charge points. 
We visit my parents in Islay and there is very limited charging there and the majority of people
do not have driveways
Expecting social landlord sites to be responsible is ridiculous. London have brought in on
street charging through their lampposts. I understand there are cost implications in this but
should at least be looked at rather than saying the council will have no involvement.
If you assume it will be down to social landlords [to provide EVC] then they will presumably
only allow their tenants access to the chargers, leaving everyone in owned or privately rented
homes unable to access convenient charge points. Another point is that it is the council that is
responsible for road infrastructure and light fittings and this is where these slow chargers
should be fitted. this is the reason the government has grants available for fitting lamp post
points and charge points for residential areas. It is utterly irrelevant if the council owns the said
properties. This is about building a network that is convenient and affordable to be used by
the largest amount of people possible.
residents without off street parking need to be catered for. Rapid charger hubs can also
provide a residential solution as they can operate more like traditional filling stations. 
You should be providing more residential charging infrastructure where there are no
opportunities for off street parking
Council should at least be driving residential charging points in social housing areas even if not
financially responsible. 
in residential areas where there overnight parking by residents, the use of street lighting poles
should be actively pursued.
NOT ENOUGH CHARGERS
Not enough 
You can only do theme 2 and 3 if you have significantly more chargers as it ends up with
people waiting next to cars waiting to use.  Already happens with fast chargers at service stops
off the motorway 
Still nothing in Dalmally as one of the main areas reached after a long journey to Argyll?
NUISANCE FACTOR WITH PARKING & CHARGING
If people are going to be charging their cars overnight these chargers will surely be located in
a central location and not next to homes. 
SPEED / POWER OF EVCHARGING
Why no super fast ones? On the move has to be under 45 minutes 
Suggest rapid chargers at all locations. Turnaround time would be quicker allowing more
vehicles to access the facility. 
Why only fit 50kw rapids - these need upped to 150kw to facilitate the new EV cars,
infrastructure in the electrical network will take this - future proof while you have the chance.
On the move charging needs to be faster than 50kW - 150 would be a sensor baseline.
Otherwise agreed. 
Page 71

Page 72

SPEED / POWER OF EVCHARGING contd
Need more rapid chargers - bias should be towards installing them.  Domestic chargers should
be individual responsibility 
Should be more Rapid chargers to encourage tourist traffic.
Need fast chargers 
Slow chargers would be ok in residential areas, but are generally fast chargers are needed
when on the move e.g. long drive fur work or holiday. Good maintenance service required for
chargers. Can you add a time limit to avoid drivers using them for too long e.g. a cost after 1.5
hours? They need to be freed up regularly
think about the charging times..on many charge points only one vehicle can charge at a time.
Imagine having to sait several hours to get petrol/diesel! It is simply not enough.  plus too
often charge points are not functioning. There is not enough facility now for existing users.. no
good playing catch up for next 10 years, visitors will be frightened off.
There needs to be more rapid chargers. More and more people are getting EV's and having
medium- to slow chargers will cause delays in charging. Rapid chargers are the way to go as
people can charge quickly. Also a lot of passing traffic therefore rapid would be preferred.
Local businesses can also benefot from medium and fast chargers as will encourage trade
when people are waiting for charge. 
Rapid charging (for on the go use) should now be 100kw or more. There are already 350kw
chargers out there.
There are only two types of charger, fast as possible or at home, slow, overnight.  The main
population served by these charging points are the working population, when working they
need to be flexible and have their cars charged to maximum capacity in minimum time, when
at home and not working they can afford to take time overnight charging their cars. All
'community' charging points should provide the fastest possible charging capability, home
charging points should provide a default 'overnight' charging capability with options for
upgrade.
We need far more rapid chargers. Slow chargers at stations can be helpful but you’ll need lots
and lots of them as one car takes out the charger for the whole day. 
All should be rapid to cope with increasing demand and to save people hanging around for
hours in rural areas
We need fast chargers everywhere
Rapid are much offered when you’re  out and about
All chargers should be rapid at this stage to facilitate greater number of vehicles able to charge
per day. Biggest problem for EV s is time required to charge.
We need faster chargers 
All charging points should be rapid
All chargers should be rapid charge to ensure maximum usage form owners and prompt
charging.
Put fast ones in then more cars can use one 
As far as possible with the available supply, almost all chargers should be "Rapid" but with a
time limit of (say) two hours so that they are not clogged up all day and effectively prevent any
visitors from using them.  
What is a point to have slow charger if even on a rapid one 2 hours is not enough to fully
charge a car? To address the need created by flood of visitors a wider net of rapid chargers are
much more valuable.   
Page 72

Page 73

GETTING AROUND
We tend not to take our electric car [to Islay] due to the poor infrastructure. They are trying to
be carbon neutral by 2030 as well as other islands. As well as many other measures needed this
is going to be very difficult if there is no street charging infrastructure.
The technology is simply not feasible in a rural area such as A&B. The charging times are
orders of magnitude too long (it takes minutes to fill a car with diesel or petrol) and the ranges
are inadequate.
Rapid charging is still too slow to make it viable
COST OF ELECTRIC VEHICLES / EVCs
Realistically, in the socio-economic profiles most commonly associated with RSL's how many
folk will be able to afford an electric vehicle in the short to medium term?
Funding should be made available for home charging units
NEED MONEY SPENT ON OTHER THINGS
You should be spending money or what we need and not what we’d like!
We need parking, not charging 
Electric vehicles will lead to much more ecological problems than hydrocarbons will ever do.
Need decent housing stock for all, not toys for the privileged few
Dont really see why the Council should be  lead on this
why should council tax payers subsidise the richer members of society?  I.e. those with electric
cars. 
Page 73

Page 74

APPENDIX 3
Do you have any comments about the proposal?
COMMENTS THEMES
MANAGEMENT & SPEED OF PROJECT
Will you survey the local residents for feedback before going ahead with this or just do it without
consultation? It is absolutely necessary to have the facility but feel it should be thought out
carefully. 
Not ambitious enough
The current infrastructure will not cope with everyone charging cars at their house and loads of
people won’t be able to park at their house to charge.  What is the bigger long term plan, this
does not scale.
It is extremely limited, and serves only a small section of the council area. Extremely
disappointing. It appears to be lacking in any insight, and very clearly shows no commitment to
actually supporting residents to reduce carbon emissions. Very poor (non existent ) planning. 
We pick up our EV next week, given price advantage over petrol diesel there should be rapid
expansion of the network
Not ambitious enough
priority should be given to 'theme 1' , which allow multiple users and faster turnover, thanks 
Good that Council proposes more chargers but they bmneed to be seen to be getting on with it. 
Demand is building fast 
As a tourist centric economy, I would like the Council to explore more, the possibilities of working
closely with those organisations with car parking, where people can stop off and spend their
money in the local economy whilst charging their cars. Less of a necessity more an enjoyment too.
i.e. don't just look at Council owned land. By all means increase what is available in town car
parks, but alongside the main road networks where could the Council partner up with local
business?  e.g. 1. In Tarbert, rather than more EVC points in the car park, why not install one at
"The Gather" - signing people there if the 2x car parking ones are in use?   e.g.2.  local
caravan/mobile home parks to encourage those who have made the switch - who have the money
- to holiday here?  I don't know how funding for this works, but if there were a way for the local
tourism sector land owner to get a grant, and work with the Council to install, the budget may go
further as installation costs could be shared, thereby increasing the number provided from the
Council budget.  Just an idea for a slightly different - dare I say joined up - approach moving
forward.
help for people to put charging points into their homes (which I believe there was, but now isn't).
The proposed extension to the EV charge network is a start but is by no means enough. With the
increase in electric and plug in hybrid vehicles forecast the number of charge points will require to
be increased massively to cope.
More chargers the better. Would encourage others to go electric. Would be good to see Argyll
and Bute become an leading example of the way forward
Many councils still don't charge for ev charging but a&b do. I wonder if there could be an annual
or monthly scheme? It's also very challenging as many points have an overstay charge which is
quite limiting of working somewhere for the day
Not thought through at all.
Great idea
The more the better!  Go for it!
If anything double the budget for this, too small an investment in the green transition. 
Slow chargers just wont be suitable for the future of EVs
Just do it - soon! Please. Just too few chargers around at present. 
Seems to be on the right track; just need to hurry! 
Page 74

Page 75

MANAGEMENT & SPEED OF PROJECT contd
Many more EVC's are needed immediately.  Lack of charging infrastructure is holding back the
switch from fossil fuels. 
SWARCO are currently in charge of ChargePlaceScotland. Nothing seems to be moving with regard
to Government/Private investment in at least twice the present number of chargers. This initiative
(by yourselves) appears not to add much to the situation.
we are facing a climate crisis and the transition needs to happen quickly!! This is the survival of
the human race we are gambling with here and we have the solutions it just needs visionary and
competant leadership from governments and councils! Please please be that!
I understand that your approach is trying to make the best of a bad situation and appreciate that
you have noticed the problem and are at least doing something, however, I do believe that
resolving this issue is beyond the capability of any local council and you may wish to consider
creating some form of 'community of local councils' who could then speak to central government
with a single voice and possibly help to resolve this really significant issue.
Yes please! We need lots and lots more chargers!  
I   believe   that  all proposed sites  are  under Council  control and  generally  town/village based. 
As  more  people change  to EV, the   demand  will  be  increase. ( It  is already  frustrating  when 
EV users have  already  hooked  up  to  chargers when  you  arrive  to  charge  your  car and  you
need to wait your  turn,  adding  to  the  time of  charging).   It will  be  of  the  utmost  importance  
to consider opening up  other  sites  on Argyll  and  Bute's   road network,  using private 
landowners  property,  especially  on the out  of  town  routes,  where  people  will  be  able  to 
enjoy  the  outdoors  while  they  wait  for  their  car  to  charge.  This  would  be highly  beneficial
to  residents/visitors and  businesses  alike.
The proposed chargers do not have enough options either in the type or the situations 
It's a good start but it does need action quickly.
Hopeful of being able to commit to an EV at some point in the future so see this as a positive step
Build build build. Unless you want tourism to bomb over the next few years, and Argyll to hold the
UK back in hitting low carbon targets.
Excellent to see more of these coming to Argyll and Bute
Am I correct in assuming that private sector providers will also install chargers where profitable
without necessarily discussing or referring to the council strategy?
I hope it’s going to be done in a short time span.
Not enough being done.  Token gesture so you can say you are improving matters, however so
behind most othe councils. 
We just need a lot more
I think there is further opportunity for the Council to join with the private sector and co fund
installations.  This could be a win win once a suitable format is agreed.
leave to private sector
Fair usage practices need to be taken into account. For example, in a location with only one
charger it would be unfair for someone to be able to leave their car connected all day or night.
Other people should be able to use the charger after a full charge has been reached
Sounds like positive progress to me.
Fully supportive of more chargers in new locations - we need a better spread of infrastructure
across the region 
GETTING AROUND
Future proof the network - EV cars are flooding onto the roads and its an opportunity in A&B to
use this to increase tourist numbers.  Increase the current stations to multi chargers, these have a
good spread on the trunk roads.  This is what EV drivers want/need when it comes to stress free
motoring.
I hear that when driving to Glasgow from Islay, charging points along the way quite often are not
working.  This puts me off buying an EV.  Charging points need to be reliable and accessible.  
Page 75

Page 76

GETTING AROUND contd
The new machines are great however, many of your current chargers are not working. Before
expanding these should be properly maintained. The situation on Islay at present is dreadful.
Another consideration is the difficulty in accessing chargers at ports. Often these are blocked by
ferry staff, are not able to be used by those waiting for the ferry due to check in procedures with
the ferry operators. A way of being by able to check in and charge while waiting for the ferry
would be very helpful. 
Don’t think electric cars will be a good thing in remote areas.  If another car is charging the only
point in a village and it takes 2 hours, how on Earth will that work??
Yesterday I did a very stressful journey to Glasgow hospital, having to charge at Loch Fyne Hotel
Inveraray on route, then got the rapid chargers at Newton Street Car Park Glasgow 50kw charged
from 12% to 100% in an hour and 40 minutes. Then stoping at the hotel again on the way home.
Other chargers that I can connect to on route were occupied. Very stressful. Please site chargers
where there are toilets, and cafe/restaurant facilities near by. Disabled passengers can’t walk far.
Argyll is not compact and tourists that come to Argyll explore in their cars, hence to maintain a
vibrant tourism sector charge points must be made available in out the way places too.
Travel in A&B involves long rural journeys with limited diversion options. For example I have twice
when travelling from Inverary to Helensburgh had to divert via Dalmally and Crianlarich because
the head of Loch Fyne was closed because of an accident. A diversion of this length could deplete
the battery and under your proposals there is no where to charge up on this route. I think
Dalmally is essential as a charge point. Also a prolonged delay in winter due to road jams could
again deplete batteries if heating is required (especially for young and old) so charge points on
route are necessary eg. The rest and be thankful.
There is certainly a shortage of chargers which will only get worse as more EVs go on the road. I
would like to see many more at points along the main roads eg Oban to Edinburgh and Glasgow.
There is a benefit in having a time limit on these, particularly when there are not that many. Also
strong penalties for non-EVs parking in them, which I have heard has happened.
My experience with EV travel in Argyll is that rapid chargers are the problem. You can eaily travel
100 miles one way and without a reliable charger en route you fear running out. before getting
home. Chargers should ideally be near other facilities so you can go for a coffee or do some
shopping whilst waiting for the batteries to charge. 100% EVs in  few years is very ambitious and
we seem to have hardly started putting the infrastructure in place. Massive Government
investment needed rather than relying on small, disjointed and often private, initiatives.
I think there needs to be more charging points as Argyll & Bute is a holiday destination for many
people. If we want to attract visitors and be part of Green Tourism, we need to provide the
facilities.
maintenance, you need to make sure these things keep working, all the rapid chargers from
lochgilphead to fortwilliam were brocken last week which really is a disgrace,
EVC SITES
Agree with expanding the number of locations, unless that is going to mean that all the chargers
are often likely to be occupied at the initial locations
Put in the fastest across the region because it will future proof it a little. 
Still nothing in Dalmally as one of the main areas reached after a long journey to Argyll?
I think you need to think where are the charge points going to be needed when everyone has EV's.
ie areas of low off street parking availability. 12 or 14 chargers all within a mile of each other in
Dunoon town centre is not in my opinion a good use of obviously limited funds.
A few dotted here and there will not be sufficient to meet deman - big sky thinking required. 
we need to think much bigger and faster. eg 7kw new points at Tesco..if you shop very slowly you
might het a few .iles' worth!!
I would prefer to see a charging point in Carradale as priority 1.  It's a 30 mile round trip from
Campbeltown to Carradale and people will not visit if they cannot charge a vehicle in the village.
Page 76

Page 77

EVC SITES contd
Being at the end of the Kintyre peninsula, it is critical to have effective charging points. I believe all
transport links should be included, Campbeltown Airport car park would be a ideal location for
slow charging. There should be a more and better spread of chargers in Campbeltown with
Burnside Square, Aqualibrium and Bolgalm street car parks being ideal locations that are council
owned. 
Rapid charging needed in Strachur as many tourists visit.
I think Oban Airport is particularly important
Chargers in rural locations or near need-based sites such as supermarkets where you could use
fast chargers whilst doing your shopping
I would like to see one installed in Furnace
There appear to be obvious gaps in provision e.g. Taynuilt, Dalmally, and locations with relatively
generous provision e.g. Seil Island. 
With the increase in vacationers in Ardentinny, I recommend a couple of chargers at the Church
Car park, which is closest to the holiday homes and near to the village for residents. if required.
Again, while we may not be Lochgilphead or Oban, there are still people here, and we require
some options: and investment is needed.
Plan to move from kintyre due to this issue, as living here no longer sustainable for long term
Charging point at Kilmory HQ car park would also be useful.  Not just for staff but this car park is
well used by people going on forest walks.  
Sites should be accessible, near public toilet facilities if in tourist locations and also be at transport
'hub' interchanges.  
I would like to request that a charger is installed at Ardnadam car park, in Sandbank. 
Charging facilities to be available at Ardnadam
The Sandbank Community Development Trust land at Ardnadam would be good site for
consideration.
Sandbank Ardnadam Community Park should be considered for Rapid charge points.
Yes the charging point for Sandbank is in the totally wrong place and not good for any female on
her own and literally nothing to do the charger should be places in the Ardnadam community car
park. It’s open and on the main road from the ferry.
As a female the proposal for the charging point in Sandbank is hidden and I would not feel safe.
The most logical place is the community space at Ardnadam it’s open and great for tourists
coming off the ferry 
I wish to recommend that an EV charging point is installed at the Ardnadam Community Park
(adjacent to Ardnadam Pier).
I agree with the proposal for Strachur and please also install an EV charging point at Ardnadam
Community Park i.e. adjacent to the old Ardnadam Pier.
Pleased to see charging point is proposed for Strachur. Would also suggest one required at
Sandbank village
Sandbank Trust has a large car park on the main road heading north from Western Ferries which
would be an ideal place 
Ardrishaig currently has zero charging points 
As long as you distribute the different types of charger sensibly!
Priority should be given to essential car users such as social work, home care, district nurse etc as
unfortunately siting chargers at ferry terminals could lead to the main users being tourists.
Please don’t just stick them at ferry terminals - but near to facility for cup of tea etc in villages 
Page 77

Page 78

EVC SITES contd
I welcome the addition of public chargers at various places in Helensburgh. At present, the "all
eggs in one basket" situation with the cluster of chargers in the pier car park and tendency for
Helensburgh to be gridlocked (due to roadworks or an accident on the A82, for example) means
actually getting to the chargers at the pier can be a challenge. Additional units at the Sinclair
Street car park and Kidston would certainly spread the load. I find it curious that the chargers at
the Civic Centre are marked as for use by staff only, as they are often unused or have ICE cars
parked in the bays. Allowing the public to top up there would ease the burden.
Should install them in a school car parks for staff to use and at any council buildings. Focus should
be on remote areas where fuel costs are even higher than the mainland. 
Dalmally could do with a fast charger.Possibly near to market 
Obviously, the more chargers, the better. With no refuelling options at all in Lochgoilhead (the
nearest fuel station is in Arrochar), the community, local businesses and even emergency services
face additional costs when refuelling. Visitors have begun to avoid holidaying here as there are no
charging facilities in the village, and even National Park employees have become stuck here
without power, requiring residents to lead cables from their home to charge their stranded
vehicles. The approach suggested is practical, given funding constraints, but I would encourage
the Council to consider Lochgoilhead as a priority if possible.
Argyll and Bute is falling behind other parts of Scotland with access to chargers. There needs to be
more fast chargers in tourist hotspots and 7 or 22 kw ones in every town and village. 
There appear to be obvious gaps in provision e.g. Taynuilt, Dalmally, and locations with relatively
generous provision e.g. Seil Island.
To give confidence and encourage people to buy electric vehicles in the Cowal area and to help
tourists there should be at least two or three rapid charge units at a site in Tighnabruaich. There
should also be a Rapid charger at Portavadie. In addition a Rapid charge point at Colintraive would
also be sensible as this is an important route into Bute.
Residential areas and home charging units should be a priority, especially in remote areas.
ISLAND CHARGING SITES
Need charging points on the islands and more rural areas to be able to promote these areas as
easy places to travel to with eco travel, go for it, delighted to see this survey
The use of Rapid charges on Gigha seems pointless as all residents can use home charging and the
island is only a few miles long so not required for visitors. The location of chargers on the mailand
around the queuing ferry traffic is fraught with difficulties as they will get used by people
travelling north-south on the mainland as well as queuing for the ferry Ultra-rapid chargers here
would seem best suited not rapid.
A charging point on the Isle of Gigha would be very beneficial 
I feel rapid chargers would benefit Rothesay/Isle of Bute. Day visitors need to be able to access a
quick charge before heading home on the ferry. 50kW-150kw would be what’s needed. 
Charging points on Gigha would be great.
On Bute there is a fair amount of on-street parking, some of which could be set aside for this,
including in Port Bannatyne, and other less central areas. 
Villages like Salen, Bunessan and Dervaig require fast chargers to cater for visitors staying in the
area.
I thought you were asking for suggested locations?!  Port Wemyss bus stop, the nearest public
charger is 17 miles away, this would serve two villages .
SPACE TO CHARGE
Appears to lack any knowledge of how people will charge their vehicles without off street parking.
No where near ambitious enough. You need to target residential parking areas, not just council
car parks.
I personally rely on public charge points as I rent in a flat therefore have no access to at home
charging.
Page 78

Page 79

SPACE TO CHARGE contd
I think there should be charging points in new house builds.  
Installing them in housing estates would be a good idea too 
You should not charge parking for people who are charging their cars.  They are already paying to
charge.  Also need to ensure repairs to charging points are undertaken timeously. 
Car parks should have at least 50% of their spaces available for EV charging.
Can you install them in lamp posts. 
When the Council is considering planning applications, the default position should be that the
developer should be required to install a minimum of one charging point within the development
which will help to ease the demand on public charging points.  
Use street lights for on street charging
On residential charging you only seem to be considering rented property. In Helensburgh over the
last few years a number of residential developments have taken place for owner occupiers and I
specially notice old properties converted to flats - I think it is necessary to insist as part of planning
permission that charging facilities be provided on the premises, this would also encourage take up
of electric vehicles.
if the chargers are in a pay and display car park, do we need a parking ticket?
Chargers at ferry ports require that people can charge up while not losing their place in the queue
- especially standby queues.
Could lamppost chargers or other public chargers for flats or tenements be looked into? I live in a
flat and would love to purchase an electric car. 
ACCESS TO ENERGY 
The current infrastructure will not cope with everyone charging cars at their house and loads of
people won’t be able to park at their house to charge.  What is the bigger long term plan, this
does not scale.
On an island energy access overnight will be limited to those residents who can afford to install at
home charging. Care must be taken to ensure fair access to community charging facilities no
matter what the season.
Islands that have no vehicular access will find it impossible to use their own power. I would be
interested to know how we can all move to electric vehicles and be sure of being able to charge
your vehicle.
POWER / SPEED OF EVC
Pleasing to see more sites but slow/fast chargers are already outdated.
Need more fast chargers
Many vehicles can only charge at 7kW from a 22kW charger and so overstay charges for these
posts are unfair. 
If Electric vehicles are to be commonplace, many more chargers of all categories will be needed. 
Should we not be going for ultra fast chargers that can charge in say 30mins this would future
proof to a degree. Why are Argyle and Bute funding this? Would it not be better to partner with
industry suppliers and developers? Thereby reducing the council tax burden
Its too limited in terms of numbers and rapid chargers
Charging better than 50kw is needed to reduce time as more electric vehicles take to the road. 
Please install fast chsrgers
90 minutes is not a rapid charge when I can fill my car up in 5 minutes with Diesel
Whatever you do the chargers need to be reliable!
Would have thought plenty of instances where cars are left for less than four hours when owners
are just doing weekly shopping so perhaps more rapid charging facilities could be offered with this
in mind? ie for drivers going to larger towns such as Oban.
The higher rate chargers of today become the standard chargers of tomorrow. These days are not
far apart
Page 79

Page 80

POWER / SPEED OF EVC contd
The more fast chargers the better
I don't know the cost of the various chargers but if the differences aren't huge, rapid chargers are
likely to be better utilised and have a longer life as slow chargers have to become obsolete fairly
quickly if EVs are to be a viable alternative to the combustion engine.
7kw will.not get used, they are a waste of time. 7 hours is optimistic charge time! Is 300kw out of
the question? 
More fast chargers please.
Charging points in Sandbank should be of the rapid type for transiting vehicles.
A mixture is best, sometimes you need the fastest charger available, but if there were a lot of slow
chargers then you could have regular top ups and wouldn't always need rapid chargers.
Fast ones make more sense on tourist areas
Majority of charging will be for day to day usage NOT while on the move. I currently spend 3 x 30
minutes each week charging at nearest 50kw rapid chargers which are between 3 and 8 miles
from home. It would be hugely advantageous to have several slow chargers within the parking
areas at home (no off street parking but 30 parking bays). At present, 3 EVs in the street all having
to use public chargers. 4 or 5 7Kw chargers in parking areas would encourage more take up of EVs.
EVC MAINTENANCE
"Whatever is installed, please make sure that 1) it has a good connection so that it doesn’t drop
out and stop chargers like the one at Oban Ferry Terminal does.
2) that the chargers are well maintained and in service as close to 100% of the time as possible.
Finding none of the 4 chargers in Tyndrum on my way back from a hospital visit was beyond
stressful. (This was after the Balloch and Crianlarich ones not working either!!!) 
PRICE OF CHARGING
There should be clear signage of the price as with petrol stations.
On the top of that there is a fee if one charges over 2 hours at councils parking. 
EVC COMPATABILITY
Our Mazda car dose not connect to the old tethered existing chargers on your system. I have been
informed by Charging Places Scotland that a lot of new EV will not connect to these old systems.
Please if possible update these old chargers as well, as they are basically useless. 
SPEND MONEY ON OTHER THINGS
Ensure your roads are fully safe with no homes and correct marketing before wasting our money 
Weak
Stop!
All of them and realise that you are, like the rest of the "green" sheep, heading in the completely
wrong direction 
no
build cycle paths. 
Rediculous waste of money when the price of electricity has skyrocketed, how about using the
money to insulate, and improve mouldy housing stock. 
A waste of money based on a false premise and driven by the "green" religion.
Improve your quangos housing stock, not create chargers for the rich and wealthy
Waste of money - improve services already in place 
Page 80

Page 81

APPENDIX 4 EVC CONSULTATION HEADLINES AND KEY THEMES 
Page 81

Page 82

Page 82

Page 83

In terms of the specific comments, these can be split into key themes, which are shown in the table below with some commentary
against them:- 
Theme  General Feedback Response
Managing / speed of
project
Good the Council are proposing more
chargers, but should develop charging hubs. 
Help to install chargers at home. 
Whatever you do, do it quickly. 
Focus on network coverage [addressing any
gaps in the existing network], with network
expansion [expansion of existing provision on
existing sites] to follow. Focus on equity. Sites
should have the potential for future expansion. 
While we do not offer funding the Council does
offer advice and signpost to organisations that
do. 
Should funding become available we will
progress as quickly as possible. An aspect of this
is having call-off contracts in place for EV
suppliers which we are picking up as part of our
EV strategy.
Not enough EVCs  Not enough being proposed. 
What about rural areas?
We have an agreed methodology in place which
will address network gaps. We can monitor the
use of EVC and will set up a system where
people can text us to let us know I they’ve gone
to use one and it is busy. That way we can build
up an evidence base of where more are needed. 
We have prioritised smaller areas first in our
delivery programme for destination charging and
we have plans to ensure there is a rapid charger
every 30mins or so along the main road network.
Page 83

Page 84

EVCs in the wrong
location 
Better to have hubs rather than dispersed. 
Tourist areas rather than residents/ locals
have been favored.  Residential areas should
be the focus.
The focus is to address gaps in the existing
network.  Sites should have the potential for
future expansion. 
The council is developing a publically accessible
network for all users, including residents, tourists
and those passing through. The main bulk of EV
charging is done at home and our network is
more of a ‘top up’ one. We are exploring options
for on-street residential charging. 
Need money spent
on other things
Parking and pot holes need to be priority. 
Waste of tax payers money, what about
housing stock.
Separately to the EV strategy we have parking
review ongoing at the moment; and this year
we’ve spent over £8million on improving our road
network. A lot of the external funding we get
comes with conditions/is ring fenced – if we get
funding for EV it must be spent on EV; if we get
funding for schools it must be spent on schools
etc. 
The Council no longer has housing stock, this
transferred to ACHA in 2006. We work with our
RSL partners through our Strategic Housing
Investment Programme [SHIP] to develop
affordable housing across the area.
Installations themes Can’t see a need for theme 3.  Residential charging is important as not everyone
has access to private driveways, while we may not
have housing stock we do have a role in working
in partnership with HOMEArgyll, particularly where
there is a crossover with the public road network. 
Page 84

Page 85

Not all EVs can draw the maximum kW,
chargers that charge 2 cars at the same time
are needed.  
Charging times will vary depending on the vehicles
on board convertor capability, capacity of the
charger used, the size of a vehicle’s battery and
the amount of charge your battery has upon arrival
at the charging point. 
EVC Sites Petrol stations should be turned into charging
stations. 
Why only council owned locations.
We are aware that some private providers are
installing EV at traditional fuel stations although
this seems to be initially at motorway service
stations. 
Sites not in Council ownership can be considered
if necessary to fill a network gap. Locating
chargers at sites within Council ownership would
be preferable as this is more efficient in terms of
consents and future management.
Lack of space to
charge
There is a lack of parking spaces this will
reduce that even more. 
Council has to think about people social
housing that has no driveways / more
residential charging needed. 
What about lamp post chargers.
We are working towards SG targets, eventually
all new cars will be electric and as this transition
happens more parking bays will be allocated for
that. We are conscious of finding a balance
between EV charging and parking spaces. 
We will work with HOME Argyll partners and
explore options for people who don’t have
driveways. 
We are exploring the option of  piloting a targeted
lamp post scheme to investigate how popular
these would be.
Nuisance factor with
parking and charging
Surely chargers will be centrally located and
not next to homes.
Current focus is to install within Council owned
car parks.
Page 85

Page 86

Speed/power of EVC Ultra, rapid or faster chargers should only be
installed. 
Slow only in residential areas.
Different chargers required for different uses i.e.
on the move, destination and residential. 
7kW EVC are suitable for overnight, residential
charging. 
Getting around Charging times are too long. 
Chargers should be near other facilities. 
Hubs are needed.
Charging times will vary depending on the vehicles
on board convertor capability, capacity of the
charger used, the size of a vehicle’s battery and
the amount of charge your battery has upon arrival
at the charging point. 
Sites should be at/on/near existing settlements
with local amenities, with a view that the network
development should bring consequential
economic development gains e.g. EV users
utilise local shops, cafes etc. while their car
charges. 
Focus on network coverage [addressing any
gaps in the existing network], with network
expansion [expansion of existing provision on
existing sites] to follow. Focus on equity. Sites
should have the potential for future expansion.
Cost of electric
vehicles
How many can afford an electric car. 
Funding should be available for home
chargers.
The cost of electric cars is not something the
Council can comment on/control. 
While we do not offer funding the Council does
offer advice and signpost to organisation that do.
EVC sites Put in the fastest chargers available.  Different chargers required for different uses i.e.
on the move, destination and residential. 
Page 86

Page 87

Hubs rather than isolated EVCs. 
School car parks should be used.
Focus on network coverage [addressing any
gaps in the existing network], with network
expansion [expansion of existing provision on
existing sites] to follow. Focus on equity. Sites
should have the potential for future expansion. 
This is being explored.
Island charging sites On street charging should be available. 
Rural areas of island need chargers not just
towns.
We are piloting a targeted lamp post scheme to
investigate how popular these would be. There
are broader considerations about road safety and
parking turnover with on street chargers. 
We have prioritised smaller areas first in our
delivery programme for destination charging and
we have plans to ensure there is a rapid charger
every 30mins or so along the main road network.
Access to energy How will the energy network cope.  This isn’t something the Council can control –
what we do is apply to connect to the mains and
the DNO advises what the infrastructure
requirements and costs are.
EVC maintenance Chargers need to be reliable.  New maintenance and warranty contracts are
being negotiated.
Price of charging Pricing should be made clear. 
EVC users shouldn’t pay for parking.
Tariff labels are on all EVCs and traffic wardens
carry out regular inspections and replace any that
are missing. 
No parking fees apply while using Council EVC.
EVC compatibility  Newer electric vehicles are not compatible
with Councils EVC.
Advances in technology will make this inevitable
– the life cycle of an EV charger is estimated at
10 years and we will look to replace/upgrade our
existing stock as it reaches the end of its life. 
Page 87

Page 88

This page is intentionally left blank

Page 89

APPENDIX 5 – HITRANS FASTER PROJECT
As previously reported to the December 2021 EDI meeting, the FASTER Project is a
joint proposal across Scotland, Ireland and Northern Ireland to support the
overarching ambition to transition to low carbon transport systems. It is a project
supported by the European Union’s INTERREG VA Programme, managed by the
Special EU Programmes Body. 
HITRANS are directly managing the install of up to eight public charge points in
Argyll and Bute. Once installed these will become Council assets, and be managed
and maintained as part of our existing network. 
The initial procurement exercise brought the overall project in above budget and
resulted in a non- award.  The project have been granted an extension until Oct 23
and is back out to tender after HITRANS re-evaluated and re-prioritised sites.  Some
sites are now on a reserved list as an explicit back-up option for the tender.  For
those sites with an end of life replacement instead of an additional EVC being added
we have agreed to incur the removal costs as funders would not cover this element. 
This is expected to be able to be absorbed within the existing EV budget which, as
reported above, is developing a small surplus through the cost recovery model. It
could be the case that older models being removed could be recycled within the
Council estate at least in the short term [for the likes of depots].
HiTRANS, with input from Council Officers, have selected the following sites for the
re tender; it does not differ significantly from the original selection. The table provides
the new and updated locations and comments on the alignment with, or departure
from, the Council’s strategy and draft site list. The HiTRANS scheme should be
viewed as something complementary to the Council’s own plans. 
Site Comments
Going ahead with amendments
Rothesay Pier Two chargers. 
Site in ABC expansion plan for one
RAPID charger – this scheme delivers
ABC priority and provides welcome
additional provision at a busy ferry port.
Corran Halls Two chargers. 
This has been identified as a site for the
destination charging theme for a FAST
charger. The option of an additional
RAPID charger here is nevertheless a
Page 89

Page 90

welcome additional provision, and
provides for a useful charging option at
that end of the town with direct access to
the trunk road.
Tarbert Ferry Terminal One charger. 
Although a site not in Council ownership
or responsibility, this would provide for a
charging option for users of the Tarbert to
Portavadie ferry. The site is owned by
Tarbert Harbour Authority, who have
consented in principle to the scheme on
the basis that the Council adopt the
charger. Given that this will provide
further transport connectivity at no capital
outlay or ongoing revenue cost for the
Council, this seems reasonable.  
Removed
Port Askaig Remains a Council priority but cost
prohibitive for HiTRANS scheme. Could
be picked up in addition to LUF proposed
marshalling area works.
New
Craignure Two chargers. 
Supplement existing provision at
Craignure. Although the Council’s
immediate policy focus is on filling gaps,
the EVC use and demand data from this
site suggests that an additional RAPID
would be well used, and would begin to
create a charging ‘hub’.
Reserve list
Dunoon Pier  Two RAPID to replace an end of life EVC. 
This provides an additional RAPID
charger at an existing site. Although the
Council’s immediate policy focus is on
filling gaps, the EVC use and demand
Page 90

Page 91

data from this site suggests that an
additional RAPID would be well used, and
would begin to create a charging ‘hub’.
Lorne Street, Lochgilphead Replacement of one end of life EVC.
New Quay, Campbeltown As above
Ledaig, Tobermory As above 
This has been a highly resource intensive project to support, with calls on the project
team’s time as well as a significant draw on resources from colleagues in legal
[commercial and conveyancing]. While the project will eventually lead to installs of
new EVCs, and while some useful professional contacts have been made and
knowledge gained through the process, it is regrettable that we are a year on from
reporting to this Committee on the project and no installs have yet taken place. This
is a departure from the normal EVC delivery model where funding goes directly to
local authorities – because of the nature of this rollover European fund it is managed
cross-regionally. 
As we move ahead in the delivery of our EVC strategy it is likely that we will focus on
funding options which are structured in the more traditional way as this has proven to
be the most effective and efficient model – the Council has directly administered
approaching £1million of funding in the past seven years and successfully installed a
competent public and business network of 40 chargers in that time. 
Page 91

Page 92

This page is intentionally left blank

Page 93

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                    1 DECEMBER 2022
SERVICES                     
PLAY PARK FUNDING 
1.0 EXECUTIVE SUMMARY 
1.1 In 2021 the Scottish Government allocated £76k to Argyll and Bute Council for
investment in play park equipment, with a further £79k being allocated for 2022. 
In August 2022, the Scottish Government confirmed further funding through to
2025.  Argyll and Bute will receive a total of £938k for Play Park funding as
detailed below. All Scottish Councils have received funding through the Capital
Allocation for Renewal of Play Parks Fund for investment in play park equipment.
The distribution was based on population 0-14 years with an element for rurality. 
In 2021/22 the rurality share was 5%, for all other years’ rurality increased to 7%
in recognition that renewal of equipment costs are higher in rural areas. 
1.2 The Scottish Government commitment was to ensure that all children have
access to quality play in their own community and the budget was specific in
that the funding was for renewing play parks. A definition/scope of investment
was also issued as part of the grant offer and is as below:- 
 The agreed definition of an eligible play park is one which is local
authority owned, managed or maintained sites, designated for play,
which are free to access and open to all. Play parks in private ownership,
those that require an entry fee or those only available to specific groups
/ with conditions for entry would be outwith scope. We would expect that
play parks with equipment (swings, slides etc) aimed at children aged 0-
14 would be included as would other facilities used by the same age
group (e.g. pump tracks), but MUGAs (Multi Use Game Areas) or
dedicated sports fields would be outwith scope. 
1.3 The Scottish Government also required councils to carry out engagement with
local youth groups to help to shape the type and style of equipment being
installed. 
1.4 Due to the low level funding in the first two years, officers looked at an equal split
across the 4 geographical areas, with a view to re-evaluating this when the final
funding was announced. As Scottish Government has now confirmed funding
over the 5 years as £938k officers recommend that this is now looked at across
the whole play park network and split according to the number of play parks
Page 93 Agenda Item 7

Page 94

needing refurbished in each area for the last three years of funding. Table 1 below
lists the area and number of play parks, allocation totals and the recommended
budget splits, with a short narrative thereafter listing closed or newly built play
parks. 
Table 1: 
AREA  No of
Playparks
Adjustments TOTAL
MAKI  13   Lochgilphead Front Green is newly built
and the Mull of Kintyre Play park has
been closed. Therefore suggested split
for 11 play parks not 13.
£368.5k
OLI  2  OLI – Atlantis Leisure is a relatively new
park and does not require refurbishment.
Therefore suggested split is based on 1
play park not 2
£33.5k
H&L  11 N/A £368.5k
B&C  5 N/A £167.5k
TOTAL (31) 31 28 £938k 
1.5  In 2021/22 discussion took place with local youth forums together with a review
of all play parks. These processes identified which play parks were most in need
of refurbishment balanced against the youth forum feedback. This identified a
prioritised hierarchy of play parks for year 1 which was then continued into year 2
for each area as per Appendix 1 attached. This was subsequently reported to the
Environment, Development and Infrastructure Committee in June 2022. 
RECOMMENDATIONS 
It is recommended that Members: 
 Note the available funding for play park equipment as detailed in the report
and agree the budget split for each of the 4 administration areas as
outlined in table 1; and 
 Note and consider the proposed further engagement with youth and that a
report outlining process and timelines will be brought to the March 2023
Environment, Development and Infrastructure Committee.    
Page 94

Page 95

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                    1 DECEMBER 2022
SERVICES                     
PLAY PARK FUNDING 
2.0 INTRODUCTION 
2.1  This report provides an update on the 5 year budget allocated to Argyll and Bute
Council by the Scottish Government from 2021/22. The Scottish Government
commitment was to ensure that all children have access to quality play in their
own community and the budget was specific in that the funding was for
renewing play parks. 
2.2  The report further outlines what engagement officers have had locally through
Youth Forums and proposes a further consultation approach via schools. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members: 
 Note the available funding for play park equipment as detailed in the report
and agree the budget split for each of the 4 administration areas as
outlined in table 1; and 
 Note and consider the proposed further proposed further engagement with
youth and that a report outlining process and timelines will be brought to
the March 2023 Environment, Development and Infrastructure Committee.   
4.0  DETAIL 
4.1 The Council is responsible for delivering the Play Park facilities across all of Argyll
and Bute’s 30 play parks. The council utilised the Framework Tender Scotland
Excel to procure bids for the £76k in year 2021/22, unfortunately no tenders came
forward. The year one funding was carried into year two and tenders were sought
for the £155k. Again no bidders came forward. As part of the procurement process
officers contacted potential bidders to identify the reasons for this. Timescales, as
well as full order books, were stated as the reasons why suppliers did not return
a tender. This is also being experienced in some other Local Authorities and is
very likely due to the fact that all Scottish Local Authorities are carrying out similar
work, consequently there is a shortage of organisations able to do this. The
geography of Argyll and Bute may also make our area unattractive to bidders. 
Page 95

Page 96

4.2 Officers now believe that this project should be delivered through a mixed
economy model of external procurement of equipment which is installed, where
possible, in-house and supported by specialist external local businesses. This will
help to ensure the programme of play park equipment is delivered. 
4.3 The Scottish Government had stipulated that key to this will be the engagement
of children and young people as part of the process of agreeing local priorities.
Initially Officers carried out engagement with local Youth Forums, however it has
been recognised by members that this engagement may well not have fully
covered our whole area. As such officers propose to engage with our Education
Colleagues to agree a programme of contact and engagement with pre-school
and primary schools to better understand the refurbishment/replacement wishes
of local play park users. This can be extended into early secondary school years
too. 
4.4 Officers are also considering the best way to engage locally with disability forums
to gauge the needs of children with disabilities to see if there is anything we can
do to assist making play parks more accessible for them. 
4.5 Should the budget split be agreed by members, Officers will engage with
Educational Colleagues and disability forums in early 2023 and propose to
provide a short update report outlining the engagement process and timelines for
the March 2023 EDI Committee. 
5.0 CONCLUSION 
5.1 The Scottish Government has allocated a total of £938k for Play Park funding to
Argyll and Bute Council for investment in play park equipment through to 2025
from the Capital Allocation for Renewal of Play Parks Fund. This report
recommends that funding is allocated on the basis that the fund is split across the
four areas according to the number of play parks within each administrative area
as per table 1 above. 
5.2 Area Officers from Roads and Infrastructure Services have previously engaged
with our Youth Forums locally with some success however it has been suggested
that this could be improved. It is now the intention to consult more widely through
Educational Colleagues as well as disability forums to better understand the
needs of local areas and groups. 
6.0 IMPLICATIONS 
6.1 Policy – In line with Scottish Government policy intent. 
6.2 Financial – funded from grant funding from Scottish Government.
.
6.3  Legal – None known. 
6.4  HR – None known.
Page 96

Page 97

6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – none known. 
6.5.2   Socio-economic Duty – None known. 
6.5.3 Islands – None known. 
6.6. Climate Change – None known.
6.7  Risk – None known. 
6.8  Customer Service – None Known. 
Executive Director with responsibility for Roads and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Roads and Transport Councillor, Andrew Kain 
November 2022                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager 
Hugh.ONeill@argyll-bute.gov.uk 
APPENDICES: 
Appendix 1 – Play Park Hierarchy List for year 1 and 2 
Page 97

Page 98

APPENDIX 1: PLAY PARK HIERARCHY LIST FOR YEAR 1 AND 2 
Inspections and feedback from Youth Forum from 2021/22
AREA PLAY PARK PRIORITY RATING
Helensburgh and Lomond  Hermitage Low
Kirkmichael Low
Red Guantlet Low
Arrichar High 
Bendarroch High
Howie Low
Kidston Low
Kilcreggan/Cove Low
Rhu Medium
Tarbet Low
Cardross Low
Bute and Cowal  Meadows Medium
Port Bannatyne Low
Sandbank High
Glen Morag Medium
Page 98

Page 99

Dunoon Skate Park Low
Mid Argyll, Kintyre and the Islands  Lochgiphead Front Green N/A New
Ardrishaig KGV High
Bayview Low
Tarbert High
Kinloch Low
Lochend Medium
Hillside Low
Meadows  Low
Stewarton Low
Jock’s Boat Low
Bengullion Road Skate Park Low
Ramsay Hill Low
Oban, Lorn and the Isles  Atlantis N/A New
Tobermory High 
Page 99

Page 100

This page is intentionally left blank

Page 101

ARGYLL AND BUTE COUNCIL         ENVIRONMENT, DEVELOPMENT AND   
INFRASTRUCTURE
ROADS AND INFRASTRUCTURE                                     1 DECEMBER 2022 
BIN AND SIGNAGE REPLACEMENT PROGRAMMES 
1.0 EXECUTIVE SUMMARY 
1.1 At the budget meeting on 24 February 2022, the Council allocated £100k for a
litter bin replacement programme and infrastructure, providing new/better bins
across the area where required due to condition/need and with a focus on town
centres and prominent locations, to support cleaner communities.
1.2   An update on this scheme was provided as part of a wider update report on
Council-funded projects being delivered by the Roads and Infrastructure Service
at the June Environment, Development and Infrastructure (EDI) Committee
meeting. That update provided background to the scheme:- 
The bin programme will focus on bin replacements and where possible
combining multiple bins to improve the street scape, with a view to supporting
and managing staycation/increased visitor numbers. Where possible the
replacement bins will be 240L wheel bins contained in a ‘street cabinet’ similar
to those installed in Oban town centre. These are better bins which increase
capacity for some of the older bins and ease loading where wheeled bin can be
contained within the street cabinets (which look more attractive and are not
susceptible to blowing around in a storm unlike empty wheeled bins). Funding
spilt evenly across the four administrative areas. At market prices available in
February this had been assumed to provide 49 bins per area (196 across Argyll
and Bute). Recently we have seen prices increases across a whole range of
sectors – the current estimate is that the £100k budget will now provide a total of
156 bins in total. This is a reduction on the numbers estimated in February when
the budget was allocated.   
RECOMMENDATIONS  
Members of the Environment, Development and Infrastructure Committee are
asked to note and consider this report.  
Page 101 Agenda Item 8

Page 102

ARGYLL AND BUTE COUNCIL         ENVIRONMENT, DEVELOPMENT AND   
INFRASTRUCTURE
ROADS AND INFRASTRUCTURE                                     1 DECEMBER 2022 
BIN AND SIGNAGE REPLACEMENT PROGRAMMES 
2.0 INTRODUCTION 
2.1  This report provides a short update on the bin and signage replacement 
programmes, following the allocation of £100K at the Council’s budget meeting
on 24 February 2022.   
3.0 RECOMMENDATIONS 
3.1  Members of the Environment, Development and Infrastructure Committee are
asked to note and consider this report.   
4.0 DETAIL 
4.1 BIN REPLACEMENT PROGRAMME
4.1.1 At the budget meeting on 24 February 2022, the Council allocated £100k for a
litter bin replacement programme and infrastructure, providing new/better bins
across the area where required due to condition/need and with a focus on town
centres and prominent locations, to support cleaner communities.
4.1.2 An update on this scheme was provided as part of a wider update report on
Council-funded projects being delivered by the Roads and Infrastructure Service
at the June Environment, Development and Infrastructure (EDI) Committee
meeting. That update provided background to the scheme:- 
The bin programme will focus on bin replacements and where possible
combining multiple bins to improve the street scape, with a view to supporting
and managing staycation/increased visitor numbers. Where possible the
replacement bins will be 240L wheel bins contained in a ‘street cabinet’ similar
to those installed in Oban town centre. These are better bins which increase
Page 102

Page 103

capacity for some of the older bins and ease loading where wheeled bin can
be contained within the street cabinets (which look more attractive and are not
susceptible to blowing around in a storm unlike empty wheeled bins). Funding
spilt evenly across the four administrative areas. At market prices available in
February this had been assumed to provide 49 bins per area (196 across
Argyll and Bute). Recently we have seen prices increases across a whole
range of sectors – the current estimate is that the £100k budget will now
provide a total of 156 bins in total. This is a reduction on the numbers
estimated in February when the budget was allocated. 
4.1.3 The tender was awarded for production and delivery of replacement bins in
September with a delivery timeframe of circa six weeks provided. At the time of
writing this report we are expecting the new bins to start arriving in our depots in
the next fortnight, so by the time of the committee meeting the installation of the
new bins should be underway. 
4.1.4 The original assumed prices and number of possible bins was based on a single
specification of 240ltr metal bin cabinets with additional coating to protect from a
marine/coastal environment. Officers revisited the proposed programme and
where possible altered the specification of bins to model a mixture of cabinets
based on the specific needs of particular settings; this exercise provided for a
mixture of coated metal, metal, fibreglass and plastic bin cabinets, and in some
cases smaller capacity bins as appropriate. This combined with tender returns
being at a lower rate than expected based on previous orders [an economy of
scale realised by buying in bulk which shows the benefit of this type of significant
capital investment] means the successful bidder is able to provide 286 bins in
total. The tender ran through a mini-competition on the Scotland Excel Recycle
and Refuse containers framework which contains ten suppliers, two of whom
submitted bids which were reviewed on a 70/30 price/quality scoring. 
4.2 SIGNAGE REPLACEMENT PROGRAMME 
4.2.1 The Council previously allocated £200,000 to replace street litter bins and key
road signage. This was intended to help reduce future budget pressures for
replacements of bins and signs and would also help to enhance the streetscape
and general appearance of the area by refreshing the street furniture.
4.2.2 At the June meeting of this Committee, in the same Council funded project update
report mentioned above, the following information was provided: 
This funding has focused on replacing signage assets based on condition and
road hierarchy, with a focus on directional and speed signage (and where required
the posts supporting signs). We have been able to replace signs which were faded
and rusted, work which we would not otherwise have been able to do through
existing budgets. Costs vary according to the size of signs and what other
infrastructure is required. The available funding has provided for a package of
nearly 500 new signs across the Council area. The programme of installations is
progressing will in the western areas (OLI and MAKI), and signs are on order for
Page 103

Page 104

the eastern areas (BC and HL). Note that in line with Council policy and directional
or place name signs will be bi-lingual with English and Gaelic.
4.2.3 We have successfully completed approximately 50% of sign replacements in the
West (OLI and MAKI) with the remaining 50% of signs all ordered. In the East (BC
& HL) signs are ordered and in stock with installation commencing at the time of
writing this report, now that the majority of the roads reconstruction programme is
complete.  Appendix 1 of this reports shows some of the replacement signs which
have been installed to date.     
5.0 CONCLUSION
5.1 This report provides a short update on the bin and signage replacement
programmes. The bin programme will be more extensive than originally
envisaged thanks to prudent alterations to the programme specification and a
successful procurement exercise. The signage programme will be completed
over the winter months – its delivery slowed during the summer months due to
the need to focus resources on roads capital schemes.   
6.0 IMPLICATIONS
6.1 Policy – Signage being designed and erected in line with national
requirements/regulation.
6.2 Financial – Funded through budgets allocated as detailed above.
6.3  Legal – none known.
6.4  HR – none known.
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics 
6.5.2   Socio-economic Duty – none known 
6.5.3  Islands – none known
6.6 Climate Change – none known. 
6.7 Risk – none known.
6.8  Customer Service – none known. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure Services 
Jim Smith, Head of Roads and Infrastructure Services 
Policy Lead for Roads and Transport Councillor, Andrew Kain 
Page 104

Page 105

November 2022         
For further information contact: 
Tom Murphy, Operations Manager  
Tom.Murphy@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – Example of signs replaced 
Page 105

Page 106

APPENDIX 1 – EXAMPLE OF SIGNS REPLACED 
Page 106

Page 107

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
1 DECEMBER 2022
LATEST UPDATE ON STAYCATION PROPOSALS 
1.0 EXECUTIVE SUMMARY 
1.1 The council has allocated two funding pots to support staycations in Argyll
and Bute. £500,000 was allocated from the 2021/2022 budget and
supplemented by a further £100,000 from the 2022/2023 budget to support
the delivery of a range of facilities across Argyll and Bute necessary to
support camping and motorhome staycations. 
1.2 The majority of the staycation facilities approved at a previous Environment,
Development and Infrastructure (EDI) Committee for 2022 have been set up
and running. For instance, the Staycation Graduate Project Officer was
employed in April 2022, until the end of March 2023, to help administer the
council’s investment. Council wardens were appointed for the period April to
October 2022 to raise awareness in respect of visiting responsibly. In addition
to this, £20,000 has been set aside from the Staycation budget to support four
community groups/trusts to employ temporary wardens. 
1.3 There is an ongoing process of developing new waste disposal points and
supporting local business/community groups in upgrading and developing
existing and new campsites. 
1.4  Officers have developed a new approach and are working in partnership with
private organisations/communities to create Motorcaravan Overnight Parking
sites throughout Argyll and Bute to support Motorcaravan management and
road safety issues. 
RECOMMENDATIONS 
Members of the Environment, Development and Infrastructure Committee are
asked to:- 
 Consider and approve Officer recommendations that
 Funding for Gateway and passing place signage is approved.
 Funds are set aside for Portaloos in hot spots for 2023 as with 2021
and 2022.
 The Staycation Officer contract is extended by 6 months (to end of
September 2023) to allow for the development and completion of
projects
Page 107 Agenda Item 9

Page 108

 Review of Public Toilet upgrades with VisitScotland funding.
 Completion of the Motorcaravan Overnight Parking Project with an
additional £30,000 allocated from the staycation budget.
 Completion of the Glenmorag project.  
Page 108

Page 109

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
1 DECEMBER 2022
LATEST UPDATE ON STAYCATION PROPOSALS 
2.0 INTRODUCTION 
2.1 The council has allocated two funding pots to support staycations in Argyll
and Bute. £500,000 was allocated from the 2021/2022 budget and
supplemented by a further £100,000 from the 2022/2023 budget to support
the delivery of a range of facilities across Argyll and Bute necessary to
support camping and motorhome staycations. 
2.2 The majority of the staycation facilities approved via the Environment,
Development and Infrastructure (EDI) Committee for 2022 have been set up
and running. For instance, the Staycation Graduate Project Officer was
employed in April 2022, until the end of March 2023, to help administer the
council’s investment. Council wardens were appointed for the period April to
October 2022 to raise awareness in respect of visiting responsibly. In addition
to this, £20,000 has been set aside from the Staycation budget to support four
community groups/trusts to employ temporary wardens. 
2.3 There is an ongoing process of developing new waste disposal points and
supporting local business/community groups in upgrading and developing
existing and new campsites. 
2.4  Officers have developed a new approach and are working in partnership with
private organisations/communities to create Motorcaravan Overnight Parking
sites throughout Argyll and Bute to support Motorcaravan management and
road safety issues. 
3.0 RECOMMENDATIONS 
Members of the Environment, Development and Infrastructure Committee are
asked to:- 
 Consider and approve Officer recommendations that
 Funding for Gateway and passing place signage is approved.
 Funds are set aside for Portaloos in hot spots for 2023 as with 2021
and 2022.
 The Staycation Officer contract is extended by 6 months (to end of
September 2023) to allow for the development and completion of
projects
Page 109

Page 110

 Review of Public Toilet upgrades with VisitScotland funding.
 Completion of the Motorcaravan Overnight Parking Project with an
additional £30,000 allocated from the staycation budget.
 Completion of the Glenmorag project. 
4.0 DETAIL 
4.1 Council officers are continuing to work closely with a number of agencies,
including the National Park, Police Scotland, Transport Scotland and Argyll
and the Isles Tourism Cooperative (AITC) to name a few, to help mitigate
against the surge in domestic visitor numbers. Officers continue to work with
these agencies to build on the successes of interventions set up in 2021 and
to develop and set up new initiatives in 2022/2023 and beyond. 
4.2 It is worth pointing out that whilst there were 16,608 new motorhomes
registered between July 2020 and June 2021, an 8.25% increase on the
previous pre-COVID record of 15,342 (National Caravan Council, 2021). The
vast majority of these were responsible and respectful to our environment and
communities. This was likely a result of the extensive communication and
physical interventions put in place in 2021 and the fact that the vast majority
of tourist facilities are now fully operational albeit still hampered by staff
shortages. It was therefore imperative that we revisited these interventions for
2022/23. 
4.3 It has been noted that overall staycation pressures were fewer in 2022 as
other tourism markets opened up. That said, the tourism infrastructure has not
fully recovered from the impact of COVID-19 with a number of facilities still
closed or operating with fewer staff and services for visitors. With international
visitors still not back to pre-COVID-19 levels the overall visitor number are
down 33.6% when compared to pre COVID-19. This figure is under further
downward pressure by the cost of living crisis and the current economic
climate. 
Staycation Interventions 
4.4 The current Staycation Project officer was recruited and started on 4th April
2022 until the end of March 2023. The officer is managing a variety of
projects, engaging with communities, public sector partners and businesses
on littering, signage, provision of toilets, parking for motorhomes, and waste
disposal development funding applications. 
4.5 The Economic Growth team, working closely with Environmental Health,
Planning and Roads and Infrastructure colleagues, delivered a number of new
activities mitigating negative effects on our countryside and tourism sector.
Appendix 1 gives an overview of the interventions/actions in 2022/23. 
4.6 Waste disposal facilities for camping/campervans. Officers are continuing
to engage with campsite providers across Argyll and Bute in an attempt to
encourage better usage of existing waste disposal facilities by non-resident
Page 110

Page 111

campervans and motorhomes.  Officers continue to engage with local
businesses through providing an expression of Interest form and regular
communication. 
4.7 Temporary Toilets. Through funding from the staycation budget, twelve  
temporary toilets have been deployed by a contractor at five locations
(Westport, Bridge of Orchy, Glen Orchy, Kilchurn Castle and Victoria Bridge).
This included maintenance checks on a weekly basis. The toilet units were
removed on 14/10/2022 after discussion with site owners. 
Throughout the season officers received constant feedback from the
temporary toilet provider. The feedback showed a high level of usage on all
sites with some units needing to be maintained more frequently than others.
With the feedback from the supplier, we added an extra unit at Bridge of
Orchy which helped cope with the demand. Please see examples of the
feedback below; 
“They are still being used well, all toilet rolls are empty and sanitiser is going
down fast too. They’re definitely still being required from the public which is
good news. I believe that the Westport ones are still the busiest”
(Honeywagon) 09/09/2022 
“There is no doubt that without your toilets we would have to consider
closing the car park as the area was becoming a health hazard” (Kilchurn
Castle) 20/09/2022 
4.8 General Waste. To promote responsible behaviour about 200 bin stickers
have been put up on council bins at some hot spots by wardens and due to
their durability they will remain throughout 2022. Analysis of data collected by
Roads & Amenity Services, during 2022 in the Cowal and Helensburgh area
there were a total of 901 inspections where wardens allocated their time
dealing with litter, fly tipping, leaflet distribution along with dealing with other
staycation issues. 
4.9 Additional Warden Posts Four warden posts were advertised to cover each
administrative area. There were initial recruitment issues in certain areas,
resulting in only two wardens remaining in post for the term of contract. 
4.10 Community Wardens £20,000 of the Staycation budget was set aside to
support four community wardens in 2022/23. Two lots of £5,000 of funding
were granted to support community wardens on Bute and Appin. Throughout
the season we have approached other community groups to offer funding and
support for community wardens. 
Appendix 3 shows feedback provided by Appin Community Development
Trust (ACDT). 
4.11 Web pages and Social media posts. An information web page was
developed in 2021 with an interactive map of locations of PC and caravan
touring sites with information about waste disposal facilities available across
Page 111

Page 112

Argyll and Bute - Touring sites and filling stations (argyll-bute.gov.uk). These
pages are reviewed by the Communications team and Staycation Officer on a
regular basis. 
Staycation leaflet (Staycation leaflet (argyll-bute.gov.uk) was updated in
partnership with the Communications team and uploaded to the staycation
webpage (Have a great time. Be a great visitor. (argyll-bute.gov.uk) as a
downloadable PDF. The leaflets have been distributed throughout Argyll and
Bute Staycation Project Officer and Staycation Wardens. 
5.0 New initiatives for 2023 
5.1 Motorcaravan Overnight Parking
Council Officers have developed a new Motorcaravan Overnight Parking
scheme and are working in partnership with private organisations/communities
to create sites throughout Argyll and Bute. This scheme is funded with an initial
£20,000 from the Staycation Budget and a possible additional £30,000 increase
to bring the total to £50,000 dependent on approval by Committee and the
uptake of the grant. It will provide management support for new businesses,
through Business Gateway, and Roads and Infrastructure services for road
safety issues. Council Officers have worked with the Council’s Website Team
to create a Motorcaravan Overnight Parking web page (to be released shortly)
for all relevant information including an information brochure(Motorcaravan
overnight parking (Aires) guidance Sept 22 (argyll-bute.gov.uk) created by the
Economic Growth Team with design support from the Communications team.
Through the Economic Growth Team, the Council has also partnered with the
Argyll and the Isles Tourism Co-operative Ltd to conduct marketing for this new
scheme for up to 10 registered sites on a first come first served basis according
to budget. 
5.2  Glenmorag Car Park 
The Staycation Officer will work with Roads and Infrastructure on developing
options for the potential upgrading of the Glenmorag car park and public toilets.
£100,000 of funding has been agreed from Place Based Investment towards a
Aires style Motorcaravan site. This site has the potential to include upgraded
toilets, electric hook up points, potable water, and waste water disposal points
as a pilot project for the area. 
5.3 Potential Rural Tourism Infrastructure Fund (RTIF) Strategic Tourism
Infrastructure Grant (STID)
As the majority of our Public Toilets are now open it gives an opportunity to
improve services to the general public and staycationers by reviewing which
Public Toilets are used more frequently and which require a considerable
upgrade. This funding application will be in addition to the funding of public toilet
charging infrastructure allocated from the Crown Estate funding. If the STID
project is approved by Committee consultants could be engaged to do this with
a view to “thinking out of the box”. This could include, but not be limited to,
working towards Net Zero (this is one of the fund objectives), enhancing the
design and making them fit for the future and perhaps installing waste disposal
Page 112

Page 113

points for Motorcaravans and other infrastructure to make it a multipurpose
intervention. 
If STID funding is obtained and the consultants make proposals, the Council is
not obliged to carry any or all of the proposals out. A small list of our most high
profile and high use toilets could then be considered as part of a next stage
application for RTIF funding which could provide a significant amount of match
funding for any project. If the Council is granted this next step RTIF funding then
it would need to provide match funding which will depend on the amount sought
from VisitScotland.   
5.4 The staycation officer has been crucial in moving forward the staycation
interventions and it is proposed that the contract is extended by 6 months
(approximately £20,000) to the end of September 2023 to allow  for successful
completion of the Motorcaravan Overnight Parking scheme and to lead on the
application for STID funding and to lead the project if funding is obtained. 
5.5 Welcome to Argyll and Bute signage and signs with information on passing
pace etiquette to be designed and installed as appropriate with an approximate
cost of £20,000. 
5.6 Reintroduction of portaloos at the same locations of 2022 with an approximate
cost of £42,500. 
6.0  FINANCE 
6.1 The total for actual and committed spend to date is £496,649. If the additional
spend of £92,500 is approved, this leaves a balance of £10,852 of remaining
budget that can be used for other interventions as and when identified.
Appendix 2 provides further information on the expenditure. 
7.0 CONCLUSION
7.1 The staycation fund has been welcomed by local communities and has greatly
helped in addressing a surge in staycationers due to the reopening of the
visitor economy. Officers have received positive feedback from Appin
community from a programme of interventions from communities, businesses
and individuals and this is being collated and analysed by the Staycation
Officer (Appendix 3). 
7.2  It is recommended that the Motorcaravan Overnight Parking and Glenmorag
projects are to be developed to their full potential it would be advantageous to
extend the Staycation Officer contract by 6 months (end of September 2023). 
7.3  Council Officers continue to hold staycation meetings to address current
enquires with a wide range of partners some of whom have taken forward
their own initiatives. Officers will continue to work with partners to respond to
the challenges and opportunities that have arisen.
Page 113

Page 114

8.0 IMPLICATIONS 
8.1  Policy – The Council supports a strong economy with tourism identified as a
priority sector.
8.2  Financial – The council has an approved budget for staycation activities to be
spent over a number of financial years.
8.3  Legal – All appropriate legal implications will be taken into consideration.
8.4  HR – The council has approved the temporary employment of four additional
wardens and one staycation officer.
8.5  Fairer Scotland Duty – The Fairer Scotland Duty, Part 1 of the Equality Act
2010, came into force in April 2018. The duty places a legal responsibility on
particular public bodies in Scotland, such as Argyll and Bute Council, to pay
due regard to (actively consider) how they can reduce inequalities of outcome,
caused by socio-economic disadvantage, when making strategic decisions
and how this has been implemented. 
8.5.1  Socio-economic Duty – Council services focus on removing socio-economic
disadvantage for vulnerable residents across Argyll and Bute.
8.5.2  Equalities – All activities will comply with all Equal Opportunities/Fairer
Scotland Duty policies and obligations.
8.5.3  Islands - Staycation interventions are being delivered across the whole of
Argyll and Bute, including the island communities.  
8.6  Climate Change – All activities will comply with the Decarbonisation Plan with
the intention to minimise litter, pollution and support the vitality of our town
centres.
8.7  Risk – Littering and Health and Safety issues arising from informal toilet waste
disposal. Any staycation activity has potential to impact our ability to meet
Climate Change target obligations.
8.8  Customer Services – Information is being communicated in different formats
to our customers.   
Executive Director with responsibility for Development and Economic Growth:
Kirsty Flanagan 
Policy Lead for Economy and Rural Growth: Councillor Robin Currie 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 
Nathan Gallogley, Staycation Officer
Nathan.Gallogley@argyll-bute.gov.uk 
Page 114

Page 115

APPENDICES 
Appendix 1 – List of actions being taken forward 
Appendix 2 – Staycation Expenditure 2021/22 
Appendix 3 - Appin Community Development Trust (ACDT) Report 
Page 115

Page 116

Action Point Date of Implementation and
activity
Responsible
Officer
Action to date – 4th April 2022 Action to date – 3rd
November 2022
Web pages; social media
posts and
communication plan
Content is continually reviewed
and is now available 
Jane Jarvie Ongoing  Updated literature for 2022
focused on making the
material accessible.
Identification of private
waste water disposal
sites 
Sites identified in Appin; Tarbet;
Holy Loch Marina;
Lochgilphead Caravan Site;
Portavadie
Fergus Murray All potential sites contacted with a
mixed response– some facilities
are on-site and but
communication continues with
others around possibilities.
Once sites have been made
aware to officers they contact
the relevant source.
Identification of Portaloos
site (confirmed not
needing planning
consent).
Sites already identified Duck
Bay; Arrochar car park; Bridge
of Orchy, Victoria Bridge, West
Port, Kilchurn Castle 
Jim
Smith/Fergus
Murray
On site from 14th April until mid-
October 
The toilet units were removed
on 14/10/2022 after
discussion with site owners.
Community Hotspots
identified via community
councils/individuals and
members
Continued contact Jim Paterson Action so far – portaloos in place,
review of activities
Please see section 4.0
Recruitment of wardens Underway and advertised
hoping to get in post asap.
Operational plans being pulled
together to ensure supervision
and support is in place for out
of hours and weekends. In
addition we will look to carry out
joint patrols with Police
Scotland and council wardens
where it is considered
necessary and police have
available resource to commit to
this.
Jim
Smith/Tom
Murphy
As of 14th April 2022 two wardens
are now in place - Bute and Cowal
and Helensburgh and Loch
Lomond.
There were initial recruitment
issues in certain areas,
resulting in only two wardens
remaining in post for the term
of contract.         
APPENDIX 1: 2022/2023 INTERVENTIONS/ACTIONS 
Page 116

Page 117

LGE 9 post to assist
Economic Growth
Tourism Officer 
Staycation project Officer is in
post since 4th April 22
Jim Paterson No further update  Staycation Officer
continues to work on
staycation interventions.
Community Wardens  4 grants of £5,000 allocated
for  Community Wardens 
Jim Paterson  Funding granted to the Mount
Stuart Trust; grant to Appin
Community Development Trust 
They are currently two
remaining Community
Warden grants available.
There are a number of
larger scale interventions
planned at Tobermory,
Arrochar Car Park; Duck
Bay etc.
Completed for 2023 Jim Paterson,
Hugh O’Neill
Completed for 2023 The Glen Loin car park is
part of an RTIF design
grant from VisitScotland.
RTIF offer of funding for
Tobermory has been
withdrawn and the project
will not go ahead.
Motorcaravan Overnight
Parking
Working in partnership with
private
organisations/communities to
create sites throughout Argyll
and Bute
Nathan
Gallogley
N/A Working in partnership
with AITC to help develop
sites. 
Officers have been In
contact with multiple
proposed sites and have
provided funding for an
initial site on Islay. 
Glenmorag car park and
toilet development
2022/23
To develop a Motorcaravan
Overnight Parking  site and
upgrade Public Toilets
Nathan
Gallogley
N/A – new project Working in partnership
with RIS to help develop
the site. 
Road signage advising of
no parking in passing
places
To reduce congestion  RIS/Nathan
Gallogley
N/A – new project Working in partnership
with RIS to help develop
the site. 
Argyll and Bute welcome
signs
Entrance signs to Argyll and
Bute 
RIS/Nathan
Gallogley
N/A – new project Working in partnership
with RIS to help develop
options. 
Potential Strategic
Tourism Infrastructure
Grant (STID) 
To develop options for
upgrades to Public toilets
RIS/Nathan
Gallogley
N/A – new project Working in partnership
with RIS to help develop
options. 
Page 117

Page 118

Headline Detail Spent or
Committed
Agreed Spend 2021/22/23 Further spend for
approval
Comments
Staycation Officer
2021/22
Temporary post for 1 year
to progress Staycation
proposals. recruited 
Spent  £14,741   Only part year
Staycation Officer
2022/23
Temporary post for 1 year
to progress Staycation
proposals. recruited 
Committed 
To be decided 
£38,382  
£20,000
If post is to be extended a
further £20k will be required
from the Staycation budget
Additional
Staycation
Wardens 2021
Four additional Wardens for
a period of 5/6 months to
October 
Spent  £41,386  
Additional
Staycation
Wardens 2022
Four additional Wardens for
a period of 5/6 months to
October 
Spent
£56,000  Ledger run August 22 is for
£50,748.24 but £18,895.01 of
this is for car parking which is
not accounted for in the 22/23
budget therefore only
£31,853.23 has been spent
as per budget outline.
Additional street
sweeping/uplifts
etc 2021
Extra street sweeping and
uplifts, includes car park
maintenance 
Spent  £19,816  
Grab Trust 2021 Anti-littering campaign
staffing Spent  £18,830  
Grab Trust 2022 Anti-littering campaign
staffing Spent
£17,000           
APPENDIX 2 – STAYCATION EXPENDITURE 2021/22 AND OPTIONS FOR 2023/24 
Page 118

Page 119

Additional Police
2021
To provide additional Police
Services to assist in
promoting responsible
camping – across Argyll and
Bute, for a 12 week
Period. 
Spent 
£23,040 
Additional Police
2022
To provide additional Police
Services to assist in
promoting responsible
camping – across Argyll and
Bute, for a 12 week
Period. 
Spent
£3,492  £23,040 committed but
£19,548 of these funds have
not been spent by Police
Scotland  and have been
reclaimed
Waste Water
disposal points
Grants 2021
Holy Loch Marina,
Bunessan, Lochabie,
Kilbride Farm, Pucks Glen,
Gigha, South Islay
Development, Portavadie,
South Kintyre Development
Trust 
Spent  £57,393  
Waste Water
disposal points
Grants 2022
Secret Glen, Dunoon 
Sunny Tiree campsite  Spent  £15,438.50  
Portaloos 2021
Installing 11 portable toilet
facilities in places
including Westport, Bridge
of Orchy, Glen Orchy and
Victoria Bridge plus
support to Friends of Loch
Lomond (£3,500)
Spent  £5,833  
Actual is low as this was part
funded by NatureScot
Portaloos 2022
Installing 11 portable toilet
facilities in places
including Westport, Bridge
Spent   
Page 119

Page 120

of Orchy, Glen Orchy,
Kilchurn castle and
Victoria Bridge plus
support to Friends of Loch
Lomond (£12,500)
£42,500
Portaloos 2023
Installing 11 portable toilet
facilities in places
including Westport, Bridge
of Orchy, Glen Orchy,
Kilchurn castle and
Victoria Bridge plus
support to Friends of Loch
Lomond (£12,500)
To be decided 
£42,500 
Temporary
Campsite 2021
Colonsay - contribution to
overall project costs  Committed  £4,778  
Publicity 2021 Information - leaflets etc Spent  £13,131  
Publicity 2022 Information - leaflets etc Spent  £578  
Staycation car
park
improvements (17
locations) 2021
Lining and information Spent  £24,310 
This was paid out of the
Staycation account in 2022
Community
Staycation
Wardens 2022
To support local
communities and inform
visitors 
Spent  £10,000  
Motorcaravan
Overnight parking
scheme 2022/23
To support local
communities to develop new
business opportunities 
Committed 
To be decided
£20,000  
£30,000
£30,000 subject to approval
by Committee
Page 120

Page 121

Glenmorag car
park and toilet
development
2022/23
To develop a Motorcaravan
Overnight Parking  site and
upgrade Public Toilets
Committed   This has a separate budget of
£100,000
South Islay
Development
To help set up Motorhome
development
Committed  £20,000  RTIF Project
Road signage
advising of no
parking in passing
places
To reduce congestion  To be decided £20,000  
Argyll and Bute
welcome signs
Entrance signs to Argyll and
Bute 
To be decided £30,000  Possible support from the
Gaelic budget 
Total   £496,649 £92,500 
Overall total    £589,148 
Budget    £600,000 
Remaining    £10,852 
Page 121

Page 122

APPENDIX 3 - APPIN COMMUNITY DEVELOPMENT TRUST (ACDT) REPORT 
Introduction in Spring 2022 Appin Community Development Trust (ACDT) was
awarded grants by Argyll & Bute Council (£5,000) and NatureScot (£8,163) to
support implementation of the Appin community ranger initiative. A further £1,000
was committed by ACDT to provide a budget contingency. 
The grants enabled ACDT to appoint a part time Community Ranger for 21 hours
a week over the period June to October 2021 and covered the cost of associated
expenses such as travel costs, publicity materials and waste supplies. 
Due to our Ranger relocating at the end of September the 2022 project was
drawn to an early close. Given the limited time remaining and the downturn in
levels of visitor activity it was both impractical and inappropriate to seek a
replacement ranger for the remainder of the season. 
Outcomes 
The key objective has been to manage and deliver a community-led initiative that
helps sustain a clean and attractive outdoor environment across the Appin area
over the summer months when visitor numbers are particularly high. Beneficiaries
include both visitors and the local community. 
Ranger Role 
The role of the Community Ranger is to: 
 make daily checks of agreed routes to identify where wild camping and
off-site campervan parking is taking place overnight;
 welcome visitors to the area and explain their responsibilities in terms of
complying with the Scottish Outdoor Access Code (SOAC);
 distribution of information leaflet;
 provide information and guidance on accessing waste disposal facilities;
and
 clean up and dispose of any litter left in camping places, recording and
photographing significant problems for reference. 
Page 122

Page 123

ARGYLL AND BUTE COUNCIL                     ENVIRONMENT, DEVELOPMENT AND     
INFRASTRUCTURE COMMITTEE 
ROADS AND 
INFRASTRUCTURE SERVICES                          1 DECEMBER 2022 
CLEANING AND DRAINAGE IMPROVEMENTS IN RESPONSE TO CLIMATE
CHANGE 
1.0 EXECUTIVE SUMMARY 
1.1. The report provides the Environment, Development and Infrastructure Committee
with an update on the additional funding allocated from the 2020/21 budget
process to mitigate the impacts of weather related damage and climate change
with specific emphasis on gully cleaning and drainage improvements.   
1.2 At the February 2022 Council budget meeting, £0.500m of funding was allocated
for two new multi-purpose vehicles, which would be used for road side gully
cleansing as well as for winter maintenance. Due to a number of external factors,
the procurement of these vehicles have been delayed. 
1.3 Members of the Environment, Development and Infrastructure Committee were
provided with an update on 10th September 2020, which outlined the delay in
progress, as a result of the Covid pandemic.  This report confirms that the
vehicles are currently being built and are expected to be delivered to the council
at the turn of the year.   
RECOMMENDATIONS 
It is recommended that Members note the update provided in this report  
Page 123 Agenda Item 10

Page 124

ARGYLL AND BUTE COUNCIL                     ENVIRONMENT, DEVELOPMENT AND     
INFRASTRUCTURE COMMITTEE 
ROADS AND 
INFRASTRUCTURE SERVICES                          1 DECEMBER 2022 
CLEANING AND DRAINAGE IMPROVEMENTS IN RESPONSE TO CLIMATE
CHANGE 
2.0  INTRODUCTION 
2.1  At the Council’s budget meeting in February 2020, additional funding of £0.500m
was agreed for the procurement of two multi-purpose vehicles to help mitigate the
impacts of weather related damage and climate change.  This report provides
members of the Environment, Development and Infrastructure with an update on
the procurement of the vehicles.   
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members note the update provided in this report 
4.0 DETAIL 
4.1 As part of the 2020/21 budget process additional funds were allocated to be
spent across 20/21 and 21/22 to mitigate the impacts of weather related
damage and climate change with specific emphasis on gully cleaning and
drainage improvements. The additional funding was £0.500m and is planned to
be used for a new gully machine, operative(s) and investment in an inventory
enhancement /programme. The delivery of this project has slipped due to the
Covid pandemic and the delay in procuring vehicles and the funding remains in
the earmarked reserves.    
4.2 Within the council’s existing vehicle fleet there are currently two chassis units with
interchangeable gully and winter maintenance units. These machines are used
across the whole of the council area for gully cleansing and provide additional
back up for winter maintenance covering for breakdowns and/or heavy localised
winter weather events. Utilising multi-body vehicles provides value for money
enabling one chassis unit to be used for multiple purposes. 
4.3 In line with the February 2020 budget decision, officers are progressing the
procurement of two additional multi-purpose vehicles which will be similar to the
existing gully/winter machines mentioned above. This will enable one unit to be
Page 124

Page 125

based in each of the four area committee locations. In addition to the vehicles,
two additional drivers/operators will be recruited on time limited contracts of up to
two years to focus on gully cleansing and drainage work. The delivery of these
vehicles was originally anticipated much earlier. 
4.4 During lockdown the majority of vehicle suppliers had effectively closed and
furloughed staff which meant progressing new and replacement vehicles was not
always possible. This was the case for the gully/multi-body vehicles and due to
back orders, availability etc, build was significantly delayed with delivery
anticipated towards the end of this year/beginning of next. The two vehicles due
to be added in to the fleet are quick change body units with Plough Conversions
to enable a gritter body with a 6 cubic metre capacity spread. The gritter body
being demountable can be added or removed as required to support the winter
programme and to offer resilience to the current Fleet. Currently the two ECON
chassis’ and gritter bodies are complete with the gully cleansing bodies currently
being built. 
4.5 Due to the Covid pandemic and delays detailed above, the delivery of this project
has slipped and budget will be drawn down from earmarked reserves when
required. 
5.0 CONCLUSION 
5.1 The additional resource outlined in this report, in terms of both vehicles and
drivers/operators, will help to mitigate the impacts of weather related damage and
climate change with specific emphasis on gully cleansing and drainage
improvements. Due to the Covid pandemic the procurement and progress of this
particular project has slipped with budget rolled forward into 2022/23. 
6.0 IMPLICATIONS
6.1 Policy – in line with budget decision from February 2020.
6.2 Financial – budget agreed in February 2020 and currently in earmarked
reserves for drawdown.  
6.3  Legal – none known. 
6.4  HR – none known.
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – none known.
6.5.2   Socio-economic Duty – none known.
6.5.3 Islands – none known.
6.6. Risk – this additional resource will reduce the risk of flooding and blocked
drains.  
6.7  Climate Change - mitigate the impacts of weather related damage and climate
change with specific emphasis on gully cleaning and drainage improvements. 
6.8  Customer Service – none known.   
Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan
Page 125

Page 126

Policy Lead for Roads and Transport, Councillor Andrew Kain                                                  
For further information contact:   
Jim Smith, Head of Roads and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Page 126

Page 127

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND 
ECONOMIC GROWTH  
1 DECEMBER 2022 
ARGYLL AIR SERVICES - PUBLIC SERVICE OBLIGATION CONSULTATION   
1.0 EXECUTIVE SUMMARY  
1.1 The Argyll Air Services Public Service Obligation (PSO) contract is up for
renewal. Similar to previous contract renewals Strategic Transportation
undertook a public consultation to determine the key priorities of the
communities using the air service.  Potential bidders have been given access to
the consultation's findings in order to assist them with their bid submissions. The
consultation ran from 8th April 2022 until 1st May 2022. The consultation was
advertised extensively across a range of platforms and each Community
Council was directly contacted for response. Respondents had access to the
consultation online using Survey Monkey, which was made up of 63 questions
on the Air Service. 
1.2 There were a total of 135 responses to the consultation and made up of 90%
individuals; 5% community organisations; and 5% businesses. 
1.3 The consultation revealed that the main uses of the air service is to access
health facilities, access shops/leisure facilities, for tourism, and for business
purposes. The most significant use was for access to health facilities which is
particularly significant given that 56% or 26,000 referrals made in Argyll and
Bute are for referral to hospitals within the central belt. 
1.4 Nearly all respondents felt that the Argyll Air Service was vital to the community
and that same day return was very important. 
1.5 The recommendations to improve the service from the respondents included:
access to the central belt; better advertisement; larger aircraft for greater
number of passengers; higher fares for tourists; and flight times better aligned
with other transport. 
1.6 A majority of respondents also expressed optimism about the proposed UAV
hub at Oban Airport which is currently subject to a ‘Levelling Up’ bid to the UK
Government and the benefits that drones could bring to island communities,
meaning there is a general consensus of the benefits this new technology could
bring. 
Page 127 Agenda Item 11

Page 128

RECOMMENDATIONS
We request members of the Environment, Development and Infrastructure 
Committee to note the content of the report, which is a summary of a recent online
Argyll Air Services PSO consultation.  
Page 128

Page 129

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND 
ECONOMIC GROWTH  
1ST DECEMBER 2022 
ARGYLL AIR SERVICES - PUBLIC SERVICE OBLIGATION CONSULTATION   
2.0 INTRODUCTION 
2.1 Aviation forms a crucial, often lifeline, element of the transport network in many
parts of the Argyll and Bute area. The airports in Oban, Coll and Colonsay are
owned and operated by Argyll and Bute Council. These air services along with a
service to Tiree provide lifeline connections to the mainland for island residents
to access healthcare and education and are currently subsidised by Argyll and
Bute Council, however Tiree Airport is operated by Highlands and Islands
Airport Ltd (HIAL). There is no High School on Coll and Colonsay and the pupils
from the islands use the air services to access education from the mainland
Oban High School. 
2.2 The input of the public through a consultation is crucial to ensure that the service
is meeting the needs of the community. The consultation ran from 8th April 2022
until 1st May 2022. It was accessible through a link to the website, where
Survey Monkey is located. Each Community Council was contacted individually,
and the consultation was widely publicised on a variety of media. The
consultation consisted of 63 questions designed to gather data regarding Argyll
Air Service. 
2.3 There were a total of 135 responses, 90% of which were individuals; 5% were
community organisations; and 5% were businesses. 
2.4 58% of respondents were above the age of 55, 33% of respondents were
between the ages of 35 and 54, and 9% of respondents were under the age of
34, making up the respondents' age demographic. 
2.5 30% of respondents live on the Isle of Coll, 30% live on the mainland, 25% live
on the Isle of Colonsay, 11% live on the Isle of Tiree, 7% live on the Isle of Islay,
and 3% responded "other." 
2.6 According to the consultation, the primary uses of the air service are for access
to medical facilities, to access to retail and leisure facilities, for travel, for
business use, for employment, and for school/further education. 
Page 129

Page 130

2.7 The responses showed that the Argyll Air Service were deemed to be more
important compared with Loganair Air Service where both services were
available. 
2.8 Twice or more each year was the most common frequency of travel, followed by
once per month. The Argyll Air Service was deemed essential for the community
by 93% of respondents, and the same number of respondents either strongly
agreed or agreed that it is crucial to be able to make a return trip on the same
day. 
2.9 From the consultation, the predominant recommendations for better practice
were access to the central belt; better advertisement; larger aircraft for greater
numbers of passengers; higher fares for tourists; a greater number of flights;
and flight times better aligned with other transportation. 
3.0 RECOMMENDATIONS 
3.1 We request members of the Environment, Development and Infrastructure 
Committee to note the content of the report, which is a summary of a recent
online Argyll Air Services PSO consultation. 
4.0 DETAIL 
4.1 The consultation identified the main applications of the air service. According to
63% of respondents, the service was mostly utilised to access medical services.
Other common uses included access to stores and recreational facilities,
tourism, business use, and employment. This shows how the community uses
the service in a variety of ways and how important it is to the residents of the
communities it serves. 
4.2 The main use of the air service was for “access to health facilities” with 63% of
respondents noting this as their use of the service. Meaning that the NHS are
making significant use of the service to give patients access to medical facilities
and healthcare. Despite this use, Argyll Air Service is not linked directly to the
central belt which is particularly salient given that 56% or 26,000 of annual
referrals in Argyll and Bute are to hospitals within the central belt. 
4.3 The consultation also demonstrated other uses of the service. These include for
“site visits”, for “veterinary services”, for “training” and for “consulting visits to the
islands”. These responses represent the variety of both personal and business
use of the service. 
4.4 A significant point from the consultation was that the Argyll Air Service is the
preferred airport option compared with Loganair Air Service with a higher
proportion of individuals choosing Argyll Air Service as their preferred transport
compared to Loganair Air Service.   
Page 130

Page 131

4.5 The reason that Argyll Air Service was chosen include that it is “Much faster. It
allows you to go out and back in the same day” and “It is an essential service to
these isolated islands which can be cut off by ferry cancellations”. 
4.6 The overall preferred mode of transport was the CALMAC ferry service due to
“ferry important obviously because of ability to get car to and from the island”
and “cost – cheap for foot passenger”. 
4.7 There were, however, criticisms about the lack of reliability of the ferry, the
length of time it takes, irregularity of the service and lack of transport links when
on the mainland. 
4.8 Comments also indicated ways to improve the Argyll Air Service and make it
more favourable and these included “a definite schedule link between Hebrides
airways (Coll/Tiree) and Loganair therefore offering a link to Glasgow/London
and beyond so promoting businesses commerce and other lifeline services”. 
4.9 The most common frequency of travel was twice or more annually or monthly.
The most common mode of transport was the CALMAC ferry service, followed
by Argyll Air Service, Loganair Air Service and finally other non-CALMAC Ferry
service. 
4.10 CALMAC Ferry Service, followed by Argyll Air Service, with a difference of about
5%, is the most popular form of transportation for those who go twice or more
annually. In contrast, people who travel on a regular basis were substantially
more likely to use the CALMAC Ferry service, which was then followed by the
Argyll Air Service, with a difference of almost 17%. 
4.11 The consultation revealed that 93% of respondents either strongly agreed or
agreed that Argyll Air Service was vital for the community. 
4.12 Argyll Air Service allows residents to complete a return journey within the same
day of travel, 93% of the respondents either strongly agreed or agreed that it is
important to be able to complete a return journey in a single day. 
4.13 There were a number of barriers to travelling using Argyll Air Service. The most
prominent was due to timetabling followed by availability of seats, cost of tickets,
integration with bus/train and reliability of service. A small proportion of
respondents had issues booking a ticket. 16% of respondents felt they had no
barriers to travel. 
4.14 Some of the other barriers discussed are mostly related to timetabling and the
lack of a direct link to Glasgow commenting “The service stopping in Oban.
There has to be a through to Glasgow.” 
4.15 The largest benefit to the community was seen to be enabling pupils to get
to/from school. This is followed by the links to hospital/healthcare, then
supporting businesses, tourism, visits from friends/family and then finally helping
residents go on holiday. 
Page 131

Page 132

4.16 The consultation revealed the most prominent recommendations to improve the
service, these include: Access to the central belt; better advertisement; larger
aircraft for greater numbers; higher fares for tourists; a greater number of flights;
and, flight times better aligned with other transportation. 
4.17 There were further recommendations which includes suggesting greater funding
commenting “Approach the Scottish Government, Transport Scotland and HIAL
to seek out capital or operational funding. It is their National Transport strategy
that seeks equitable access to services for the islands. It seems the other Island
Councils are more equitable than A&B islands!” 
4.18 In order to enhance the community benefits, the suggestions recommend
extending the timetable during the summer months, a more regular service in
general and better advertisement of the service with information on the flight
times and fare cost. 
4.19 Argyll and Bute Council is working in partnership with Skyports, to develop a
West Coast Advanced Air Mobility Logistics Innovation Hub and Training centre.
The new infrastructure at Oban Airport will support the operation of electrically
powered UAVs including cargo drone deliveries, and other advanced air mobility
(AAM) use cases. Royal Mail are also interested in UAVs as part of their service
delivery and have undertaken trials with Skyports from Oban out to the island of
Mull. 
4.20 In the consultation, when asked if they believed the UAV hub would be ideal
environment in Argyll and Bute and that it can provide real benefit, 74% of
respondents either strongly agreed or agreed with this statement showing a
positive response to the UAV Hub. Further to this, 78% strongly agreed or
agreed that the UAV Hub would benefit islands in the future. 
4.21 The reason that people were optimistic about the UAV hub included that it would
add resilience, it is quicker than the ferry, better for the environment, and it is
vital to embrace new technologies. 
4.22 However, there were other people who were hesitant of the new technology and
believed that it would not be appropriate in the area due to the frequently
inclement weather and that they were unsure of the new technology.
Furthermore, some people were concerned about the noise of the drones, the
reliability and were concerned it would replace existing services and not
interested in deliveries using drones. 
4.23 The Scottish Government conducted a public consultation on an Aviation
Strategy for Scotland and encouraged response from all. The consultation
asked the respondents there awareness of the Scottish Aviation Strategy. 30%
of the respondents were aware that the Scottish Government are developing an
aviation strategy. In addition, just 12% of respondents to this consultation
submitted a response, which means that 88% of the respondents did not. 
Page 132

Page 133

5.0 CONCLUSION
5.1 The public consultation for the Argyll Air Services revealed the perspective of
the public on the Air Service and the priorities for the communities utilising the
service. 
5.2 The main takeaway from the consultation shows that the Air Service is used
most often for access to health facilities, this is particularly salient given that
56% of annual referrals in Argyll and Bute are to hospitals in the central belt and
the Air Service does not link directly to the central belt. 
5.3 The other prominent uses of the air service include access to shops/leisure
facilities, tourism, for business use and employment showing that the service
supports the key businesses and sectors such as tourism. 
5.4 A key part of the service is the ability to complete same-day return, one of the
main attractions for use of the service by customers. 
5.5 The consultation revealed clear recommendations for improvements to the
service including access to the central belt, better advertisement, increased
flights and better timetabling as well as better links with other transportation. 
6.0 IMPLICATIONS
6.1 Policy - Argyll and Bute Council provide PSO air services to some of our fragile
Island communities. 
6.2 Financial - Argyll and Bute Council has a budget of £512,207 available per
annum (2019-2022) for the provision of air services. This contract is coming up
for renewal for the period 16th September 2023 – 15th September 2027 and is
currently going through procurement.   
6.3  Legal - Tenders for PSO air services must be compliant with Scottish
Government regulations.
6.4  HR - None
6.5  Fairer Scotland Duty:
6.5.1  Equalities - Air services provide connections to rural island
communities primarily for scholars but are also used by public and
private sector services e.g. NHS, ABC, and Housing Associations. 
6.5.2  Socio-economic Duty – The air service supports an equitable standard
of living for island residents. 
6.5.3  Islands - The air service supports vulnerable island populations and is a
lifeline service. There is a chance that if this service isn't provided,
people won't want to live or work there as much, which could affect the
SOA's goal of population growth.
Page 133

Page 134

6.6 Climate Change - Multiple passengers on a one-hour flight may have less of an
environmental impact than those travelling by vehicle and ferry for six hour.
6.7 Risk - Risk of break in air services as a result of requirement to retender.
6.8  Customer Service – None.   
Kirsty Flanagan, Executive Director responsible for Development and
Economic Growth
Policy Lead for Roads and Transport: Councillor Andrew Kain
November 2022 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 
Moya Ingram, Strategic Transportation and Infrastructure Manager
Moya.Ingram@argyll-bute.gov.uk 
Page 134

Page 135

Environment, Development and Infrastructure Committee Work Plan 2022/23 
This is an outline plan to facilitate forward planning of reports to the Environment, Development and Infrastructure Committee. 
Date  Title Service/Officer Date Due Comments
1 December 2022 
Local Flood Risk
Management Plans – Cycle
2 2022-28
Roads and Infrastructure
Services
8 November 2023 
Cemetery Asset Update Roads and Infrastructure
Services   
Electric Vehicle Charging
Strategy
Roads and Infrastructure
Services   
Play Park Funding Roads and Infrastructure
Services   
Bin and Signage
Replacement project
Roads and Infrastructure
Services   
Staycation update Development and
Economic Growth   
Cleaning and Drainage
Improvements in Response
To Climate Change
Roads and Infrastructure
Services   
Argyll Air Services – Public
Service Obligation
Consultation
Development and
Economic Growth   
Waste PPP Options
Appraisal
Roads and Infrastructure
Services  
2 March 2023 
Annual Status and Options
Report (ASOR) Road
Condition Index Annual
Report
Roads and Infrastructure
Services
7 February 2023 
Shared Prosperity Fund Development and
Economic Growth  
Page 135
Agenda Item
12

Page 136

Environment, Development and Infrastructure Committee Work Plan 2022/23
Future
Items     
TBC   
Page 136

Page 137

Document is Restricted
Page 137 Agenda Item 13NOT FOR PUBLICATION by virtue of paragraph(s) 8, 9
of Schedule 7A of the Local Government(Scotland) Act 1973

Page 138

This page is intentionally left blank

Page 139

Document is Restricted
Page 149
NOT FOR PUBLICATION by virtue of paragraph(s) 8, 9
of Schedule 7A of the Local Government(Scotland) Act 1973

Page 140

This page is intentionally left blank