Democracy Spraffa

Cleaning and Drainage Improvements in Response to Climate Change

Argyll and Bute Council · 1 December 2022
Back to Environment, Development and Infrastructure Committee — 1 December 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL                     ENVIRONMENT, DEVELOPMENT AND     
INFRASTRUCTURE COMMITTEE 
ROADS AND 
INFRASTRUCTURE SERVICES                          1 DECEMBER 2022 
CLEANING AND DRAINAGE IMPROVEMENTS IN RESPONSE TO CLIMATE
CHANGE 
1.0 EXECUTIVE SUMMARY 
1.1. The report provides the Environment, Development and Infrastructure Committee
with an update on the additional funding allocated from the 2020/21 budget
process to mitigate the impacts of weather related damage and climate change
with specific emphasis on gully cleaning and drainage improvements.   
1.2 At the February 2022 Council budget meeting, £0.500m of funding was allocated
for two new multi-purpose vehicles, which would be used for road side gully
cleansing as well as for winter maintenance. Due to a number of external factors,
the procurement of these vehicles have been delayed. 
1.3 Members of the Environment, Development and Infrastructure Committee were
provided with an update on 10th September 2020, which outlined the delay in
progress, as a result of the Covid pandemic.  This report confirms that the
vehicles are currently being built and are expected to be delivered to the council
at the turn of the year.   
RECOMMENDATIONS 
It is recommended that Members note the update provided in this report

Page 2

ARGYLL AND BUTE COUNCIL                     ENVIRONMENT, DEVELOPMENT AND     
INFRASTRUCTURE COMMITTEE 
ROADS AND 
INFRASTRUCTURE SERVICES                          1 DECEMBER 2022 
CLEANING AND DRAINAGE IMPROVEMENTS IN RESPONSE TO CLIMATE
CHANGE 
2.0  INTRODUCTION 
2.1  At the Council’s budget meeting in February 2020, additional funding of £0.500m
was agreed for the procurement of two multi-purpose vehicles to help mitigate the
impacts of weather related damage and climate change.  This report provides
members of the Environment, Development and Infrastructure with an update on
the procurement of the vehicles.   
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members note the update provided in this report 
4.0 DETAIL 
4.1 As part of the 2020/21 budget process additional funds were allocated to be
spent across 20/21 and 21/22 to mitigate the impacts of weather related
damage and climate change with specific emphasis on gully cleaning and
drainage improvements. The additional funding was £0.500m and is planned to
be used for a new gully machine, operative(s) and investment in an inventory
enhancement /programme. The delivery of this project has slipped due to the
Covid pandemic and the delay in procuring vehicles and the funding remains in
the earmarked reserves.    
4.2 Within the council’s existing vehicle fleet there are currently two chassis units with
interchangeable gully and winter maintenance units. These machines are used
across the whole of the council area for gully cleansing and provide additional
back up for winter maintenance covering for breakdowns and/or heavy localised
winter weather events. Utilising multi-body vehicles provides value for money
enabling one chassis unit to be used for multiple purposes. 
4.3 In line with the February 2020 budget decision, officers are progressing the
procurement of two additional multi-purpose vehicles which will be similar to the
existing gully/winter machines mentioned above. This will enable one unit to be

Page 3

based in each of the four area committee locations. In addition to the vehicles,
two additional drivers/operators will be recruited on time limited contracts of up to
two years to focus on gully cleansing and drainage work. The delivery of these
vehicles was originally anticipated much earlier. 
4.4 During lockdown the majority of vehicle suppliers had effectively closed and
furloughed staff which meant progressing new and replacement vehicles was not
always possible. This was the case for the gully/multi-body vehicles and due to
back orders, availability etc, build was significantly delayed with delivery
anticipated towards the end of this year/beginning of next. The two vehicles due
to be added in to the fleet are quick change body units with Plough Conversions
to enable a gritter body with a 6 cubic metre capacity spread. The gritter body
being demountable can be added or removed as required to support the winter
programme and to offer resilience to the current Fleet. Currently the two ECON
chassis’ and gritter bodies are complete with the gully cleansing bodies currently
being built. 
4.5 Due to the Covid pandemic and delays detailed above, the delivery of this project
has slipped and budget will be drawn down from earmarked reserves when
required. 
5.0 CONCLUSION 
5.1 The additional resource outlined in this report, in terms of both vehicles and
drivers/operators, will help to mitigate the impacts of weather related damage and
climate change with specific emphasis on gully cleansing and drainage
improvements. Due to the Covid pandemic the procurement and progress of this
particular project has slipped with budget rolled forward into 2022/23. 
6.0 IMPLICATIONS
6.1 Policy – in line with budget decision from February 2020.
6.2 Financial – budget agreed in February 2020 and currently in earmarked
reserves for drawdown.  
6.3  Legal – none known. 
6.4  HR – none known.
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – none known.
6.5.2   Socio-economic Duty – none known.
6.5.3 Islands – none known.
6.6. Risk – this additional resource will reduce the risk of flooding and blocked
drains.  
6.7  Climate Change - mitigate the impacts of weather related damage and climate
change with specific emphasis on gully cleaning and drainage improvements. 
6.8  Customer Service – none known.   
Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan

Page 4

Policy Lead for Roads and Transport, Councillor Andrew Kain                                                  
For further information contact:   
Jim Smith, Head of Roads and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk