APPENDIX 5 – HITRANS FASTER PROJECT
As previously reported to the December 2021 EDI meeting, the FASTER Project is a
joint proposal across Scotland, Ireland and Northern Ireland to support the
overarching ambition to transition to low carbon transport systems. It is a project
supported by the European Union’s INTERREG VA Programme, managed by the
Special EU Programmes Body. 
HITRANS are directly managing the install of up to eight public charge points in
Argyll and Bute. Once installed these will become Council assets, and be managed
and maintained as part of our existing network. 
The initial procurement exercise brought the overall project in above budget and
resulted in a non- award.  The project have been granted an extension until Oct 23
and is back out to tender after HITRANS re-evaluated and re-prioritised sites.  Some
sites are now on a reserved list as an explicit back-up option for the tender.  For
those sites with an end of life replacement instead of an additional EVC being added
we have agreed to incur the removal costs as funders would not cover this element. 
This is expected to be able to be absorbed within the existing EV budget which, as
reported above, is developing a small surplus through the cost recovery model. It
could be the case that older models being removed could be recycled within the
Council estate at least in the short term [for the likes of depots].
HiTRANS, with input from Council Officers, have selected the following sites for the
re tender; it does not differ significantly from the original selection. The table provides
the new and updated locations and comments on the alignment with, or departure
from, the Council’s strategy and draft site list. The HiTRANS scheme should be
viewed as something complementary to the Council’s own plans. 
Site Comments
Going ahead with amendments
Rothesay Pier Two chargers. 
Site in ABC expansion plan for one
RAPID charger – this scheme delivers
ABC priority and provides welcome
additional provision at a busy ferry port.
Corran Halls Two chargers. 
This has been identified as a site for the
destination charging theme for a FAST
charger. The option of an additional
RAPID charger here is nevertheless a

Page 2

welcome additional provision, and
provides for a useful charging option at
that end of the town with direct access to
the trunk road.
Tarbert Ferry Terminal One charger. 
Although a site not in Council ownership
or responsibility, this would provide for a
charging option for users of the Tarbert to
Portavadie ferry. The site is owned by
Tarbert Harbour Authority, who have
consented in principle to the scheme on
the basis that the Council adopt the
charger. Given that this will provide
further transport connectivity at no capital
outlay or ongoing revenue cost for the
Council, this seems reasonable.  
Removed
Port Askaig Remains a Council priority but cost
prohibitive for HiTRANS scheme. Could
be picked up in addition to LUF proposed
marshalling area works.
New
Craignure Two chargers. 
Supplement existing provision at
Craignure. Although the Council’s
immediate policy focus is on filling gaps,
the EVC use and demand data from this
site suggests that an additional RAPID
would be well used, and would begin to
create a charging ‘hub’.
Reserve list
Dunoon Pier  Two RAPID to replace an end of life EVC. 
This provides an additional RAPID
charger at an existing site. Although the
Council’s immediate policy focus is on
filling gaps, the EVC use and demand

Page 3

data from this site suggests that an
additional RAPID would be well used, and
would begin to create a charging ‘hub’.
Lorne Street, Lochgilphead Replacement of one end of life EVC.
New Quay, Campbeltown As above
Ledaig, Tobermory As above 
This has been a highly resource intensive project to support, with calls on the project
team’s time as well as a significant draw on resources from colleagues in legal
[commercial and conveyancing]. While the project will eventually lead to installs of
new EVCs, and while some useful professional contacts have been made and
knowledge gained through the process, it is regrettable that we are a year on from
reporting to this Committee on the project and no installs have yet taken place. This
is a departure from the normal EVC delivery model where funding goes directly to
local authorities – because of the nature of this rollover European fund it is managed
cross-regionally. 
As we move ahead in the delivery of our EVC strategy it is likely that we will focus on
funding options which are structured in the more traditional way as this has proven to
be the most effective and efficient model – the Council has directly administered
approaching £1million of funding in the past seven years and successfully installed a
competent public and business network of 40 chargers in that time.