ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE 
ROADS AND INFRASTRUCTURE         01 DECEMBER 2022 
ELECTRIC VEHICLE CHARGING STRATEGY UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council has an existing network of 28 public EVCs, which are
now charged for. As EVC becomes increasingly popular, and as the ban on new
internal combustion engine vehicles approaches, there is a clear need for a
comprehensive EVC strategy which includes both options to sustainably
manage and maintain the existing network as well as developing it at pace as
and when funding arises.  
1.2 This report provides an update under various headings: 
 EVC expansion plans and public consultation
 Possible costs and future external funding options
 Maintenance of the current network
 Future procurement and installation 
 Update on installation work over the past 12 months 
1.3 Background information including previous committee reports and the EV strategy
Part One; Cost Recovery Model is available on the Council website here. 
RECOMMENDATIONS 
The Committee is asked to: 
Agree the development and prioritisation methodology at Appendix 1 and the 55
site EV expansion list at Appendix 2, noting that the expansion plan was
supported by three-quarters of respondents to the EVC public consultation. 
Note that Officers continue to engage with Transport Scotland on future funding
options through the new Electric Vehicle Infrastructure Fund and that a specific
Member Seminar will be arranged on EVC when there is clarity on how that fund
will operate

Page 2

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE 
ROADS AND INFRASTRUCTURE          01 DECEMBER 2022 
ELECTRIC VEHICLE CHARGING STRATEGY UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on the work over the past year to continue the
development of the Council’s EVC strategy, including public consultation, and
developing future options for maintenance, funding and procurement.   
3.0 RECOMMENDATIONS 
The Committee is asked to:
3.1 Agree the development and prioritisation methodology at Appendix 1 and the 55
site EV expansion list at Appendix 2, noting that the expansion plan was
supported by three-quarters of respondents to the EVC public consultation. 
3.2 Note that Officers continue to engage with Transport Scotland on future funding
options through the new Electric Vehicle Infrastructure Fund and that a specific
Member Seminar will be arranged on EVC when there is clarity on how that fund
will operate

Page 3

4.0 DETAIL 
4.1 EVC expansion plans and public consultation [EVC strategy Part Two]
4.1.1 A detailed methodology was presented to the June 2021 meeting of this
committee, then discussed at a Member Seminar in September 2021 which led
to changes to the original proposed methodology. The original draft had sites to
be prioritised large towns to small, whereas feedback from the Seminar meant
that we changed the prioritisation to focus on small villages/towns first on the basis
that larger towns already have at least one charger. We had also originally
proposed to cut off at settlements smaller than 1,000 population but following
feedback we included villages with a smaller resident population than that but
acknowledging that tourist traffic is significant. An updated draft list and
methodology was then presented to the December 2021 meeting. Appended to
this report at Appendix 1 is the development methodology and the draft long list
is at Appendix 2. 
4.1.2 The agreed draft development methodology and site list went out to public
consultation to ensure that communities had the opportunity to be involved in the
process of deciding where future public EVCs installations should be across the
Council area, and how that network should be developed and prioritised. 
4.1.3 The consultation was promoted in a variety of ways, from social media and
website links and via the national EVC back office support provider Charge Place
Scotland.  People were informed that the consultation was taking place and a link
to the online survey was provided on each of the platforms. We received 254 
responses from across Argyll and Bute; and as well as giving views on specific
questions, respondents also provided more than 500 comments. 
4.1.4 The full consultation findings report is appended to this report at Appendix 3 and
an overview of themes from the consultation is at Appendix 4. 
4.1.5 On the basis that three-quarters of those responding to the consultation supported
the proposed expansion plan and development methodology, these are therefore
recommended to the committee for approval to be adopted as the Council’s EVC
expansion policy. This will effectively complete the second part of the five part
EVC strategy.
4.1.6   The list is entirely theoretical, and it is anticipated that as the list is worked through
there could be infrastructure limitations or technical considerations which may
prevent development at a specific site. Although the development methodology
provides for different priority bands, until such time as there is clarity on the
possible future funding options it is not possible to develop a method to determine
how that funding should be allocated to sites within the priority bands e.g. how
sites are prioritised within the priority bands against available funding. As and
when there is clarity on external funding a further report will come forward for
Members to agree funding allocations.

Page 4

4.2 POSSIBLE COSTS AND FUTURE FUNDING OPTIONS
4.2.1 It was previously reported to this committee that the third part of the strategy would
give consideration to future funding requirements and options – mapping,
application, management – to deliver on the outline programme developed
through Part Two.
4.2.2 Since then the Scottish Government has set out its vision for electric charging
infrastructure in Scotland. To briefly summarise, the vision expects that £60million
of investment will be made in EVC, with that investment to be 50% publicly funded
by SG, with the other 50% coming from private finance.  
4.2.3 It is not clear at this stage how the private element would work, but what is clear
is that the Scottish Government will provide £30million of public funding across
Scotland’s 32 local authorities through an Electric Vehicle Infrastructure Fund
[EVIF]. This funding will be allocated through a competitive bidding process, the
details of which are not yet available. 
4.2.4 Based on historic costs, we are estimating an average EVC purchase and
installation cost of £25,000. With the rise in inflation a contingency element has
been built in to our estimates which gives an average cost for estimating purposes
of £30,000 per site. This gives an estimated total of £1,650,000 to deliver our 55
site plan. 
4.2.5 The Scottish Futures Trust has been tasked with supporting the Scottish
Government in developing various delivery models for local authorities to
consider, and they have outlined three possible delivery models, two of which
indicate how private finance could potentially be levered in:
(i)  Leasing sites 
Local authorities consider land holdings that may be suitable for commercial
charge point delivery and offer sites they own to a private partner via a long lease
which affords the opportunity to install and operate charge points. The private
partner retains financing, installation, and service delivery risk.  It sets tariffs and
retains all the revenue it generates from EV users (subject to the terms of the
lease).  A lease might include conditions regarding the private partner’s actions,
but typically allows freedom and flexibility for the private partner.  Sites could be
offered to the partner in bundles with a mixture of high and low income sites, but
this option is more suitable for more sites with higher utilisation that require little
or no public subsidy. 
Land and all below ground assets could remain in local authority ownership.  The
local authority could offer a “prepared site” and use its grant funding to secure
network upgrades as well as any associated civils works.  The local authority may
wish to charge rent and/or take a share of future revenues.   
(ii)  Concession contracts 
The risk associated with installation, maintenance, and service delivery across
multiple sites, including asset utilisation, is transferred to a private partner who

Page 5

finances the capital and replacement costs of new charger points after taking any
grant funding into account.  The private partner sets tariffs and retains the revenue
it generates from EV users (subject to the terms of the concession agreement). 
The contract term would reflect the period required by the private partner to
recoup and make a return on invested capital.  At the end of the contract term the
assets are expected to revert to the local authority. 
Land and all below ground assets could remain in local authority ownership (which
could command a rent and/or share of future revenue) or the private partner could
be expected to source land from other parties.  The local authority could offer
some “prepared sites” and use its grant funding to secure network upgrades as
well as any associated civils works.   
The local authority may also decide to transfer the operation, maintenance and
replacement risk of its existing charge point assets to the private partner for the
duration of the contract and in turn, allow the private partner to generate income
from these exiting sites. 
Unlike the leasing option, where the local authorities would not be involved in
service delivery, the private partner’s performance in a concession contract would
be monitored via a KPI Framework. 
This model is expected to be deployed where private sector investment on its own
is unlikely to be viable.
(iii)  Local Authority Owner Operator 
Local authorities set the specification, procure the capital works, and retain
responsibility for the operation and maintenance of the charging network.  They
procure a Charge Point Management System and a customer support provider,
or a full turnkey Charge Point Operator to provide the interface with the EV users,
collect data, monitor performance, manage costs, process payments, and
facilitate fault resolution.   
Whilst capital costs are likely to be procured via a fixed price contract, and
maintenance costs covered by warranties, all risk relating to capital, operation,
and maintenance costs as well as charge point utilisation, income generation and
customer relationship management are retained by the local authority. The local
authority funds the capital costs, operation, maintenance, and repairs are funded
from the tariff and income generated.
4.2.6 SFT have recognised that variations to each of these models to meet local
circumstances may be required to reflect each local authority’s preferred long-
term role in the delivery of public charging services.  It may be the case that in
some circumstances local authorities wish to consider the merits of establishing
a joint venture with a private sector organisation.
4.2.7 At this stage Officers continue to engage with SFT and Transport Scotland
through various forums to monitor and contribute to the development of the
national vision and to ensure Argyll and Bute Council is well placed to bid for
funding when the EVIF fund officially opens up. This is expected to be early 2023.

Page 6

4.3 MAINTENANCE OF THE NETWORK/FAULT ISSUES 
4.3.1 The fourth part of the strategy focusses on maintenance. Fault reporting is simple
for the EVC user; it can be done via the CPS phone number which is on all units
or their online form.  Once received it is assigned a ticket number and various
back office troubleshooting is undertaken to try and bring the unit back into use
remotely. If this communication fails an engineer is scheduled with a Service Level
Agreement of 48hrs, unfortunately the SLA is rarely met due to a combination of
manpower over commitments and our geography.  This is not uncommon across
all local authorities. If the fault can be fixed within the warranty agreement this is
carried out and if not a quote for the work is provided by SWARCO directly to the
Council for approval and authorisation.  Once the fault is rectified the back office
system is updated.    
4.3.2 We have been proactive with fault and maintenance issues.  We are monitoring
faults and adding service disruptions to the Council’s website, liaising closely with
SWARCO to stay up to date on faults that run longer than the SLA and have
recently gone out to tender for new maintenance and warranty contracts.
4.3.3 We are currently running a tender process to replace and simplify the numerous
maintenance and warranty contracts that currently exist as a result of contracts
being extended over the years.  This new single contract will see units being
added to it as their existing contract ends making it easier to manage and monitor
moving forward.  The new contract has been done using the Scottish
Governments new Scotland Excel procurement framework and we have
progressed this with our Procurement colleagues. At the time of writing this report
that procurement exercise has not concluded but it may conclude prior to the
Committee meeting. Once that new contract is in place and we have a detailed
maintenance plan that will effectively complete this part of the EVC strategy. 
4.4 PROCUREMENT AND INSTALLATION STRATEGY
4.4.1 Part Five of the strategy considers future procurement and installation. Previously
EVC installs were procured through open tender which was time consuming. As
a result of engagement with and work by Scotland Excel there are now national
framework contracts which are in place which should allow for much faster call
offs as and when funding arises. Once we have funding clarity it is our intention
to develop a detailed programme year by year subject to a further decision by
Members on funding allocations, and to look to appoint large contracts on allotted
basis with optional follow on lots – this should find the balance between pace of
delivery and ensuring quality. 
4.5 UPDATE ON ASSET MANAGEMENT AND EXPANSION 
4.5.1 A summary of the work to deliver installations, relocate charger and explore
new EVC opportunities is summarised in the table below:

Page 7

Item Funding Comments
HITRANS
FASTER project
c. £372,000 This is a fund administered by
HITRANS directly. This is a detailed
piece of work which is covered fully at
Appendix 5 of this report. 
Dunoon Grammar
pilot
The Power Networks
Demonstration Centre
[PNDC] at Strathclyde
University were
managing a project which
aimed to gain data in
order to improve the
maintenance and repair
of EVC. The academic
and Industrial research
and development scheme
funded from the
Infrastructure Solutions
for Zero Emission Vehicle
fund, provided by the
Office for Zero Emission
Vehicles (OZEV).   
It was planned that Argyll and Bute
would receive 4 fully funded EV charge
points, including the costs of hardware,
installation and operation (excluding
metered energy costs). Unfortunately
the opportunity was lost due to the
project funding tight timescales and the
additional layer of complexity to the
sites due to them being managed by
third parties. 
It is important to note this was not
wasted exercise, a lot of learning was
gained and that knowledge and future
planning will now be applied to future
installs like the one noted below at
Oban High School.
Relocation of
Helensburgh Pier
EVCs
Helensburgh Waterfront
Development
This has been a highly resource
intensive project to support, with calls
on the project team’s time along with
colleagues from Infrastructure Design
to assist in relocating the Helensburgh
EVC from their previous position near
the old leisure centre to the new leisure
facility car park.  There has been 6+
months of intense modification work
required to ensure the EVCs are
reinstated to full working capacity and
in line with Transport Scotland
specification. Unfortunately at the time
of writing there remain some snagging
issues with the relocated chargers
which are being picked up directly with
the contractor.
Council business
chargers
£130,000 from Switched
on Fleets
Successful installs at Jackson’s Quarry
depot, Oban, and an additional unit at
Helensburgh Civic Centre 
Working on a scheme to install a
charger at Oban High School if a
suitable agreement can be reached
with ABC Schools who manage the
school on behalf of the Council.
Tarbert  £47,000 from SSEN This would provide a charger in Tarbert
[an identified site within the Expansion

Page 8

Plan] funded through SSEN at no cost
to the Council. This is a community
benefit from the power installation
projects in the area. Funding has now
been secured. 
Tighnabruaich £63,000 from Transport
Scotland
This is a legacy scheme from the
previous Local Authority Install
Programme
Arrochar Any costs absorbed in
EVC budget
We are relocating the EVC that
currently sits within Luss Estates
carpark, Arrochar.  The Council did
lease this carpark but when that
agreement ended in 2021 the EVC
was effectively nested in a third party
site which had different access
arrangements from our other EVCs. 
There is an outline proposal for an
improvement project at the Glen Loin 2
car park and we had been hoping to
synchronise the proposed works there
with the move of the EVC, but it now
appears that that project won’t proceed
in earnest for some time depending on
other funding applications. With that in
mind we are making arrangement to
move the EVC now, so that it is
publically available in the adjacent car
park in advance of future works to that
site. 
5.0 CONCLUSION
5.1  If Members adopt the long list of public sites and the delivery methodology, which
were supported by three-quarters of those responding to the public consultation,
this will become Council policy and will be the list of sites to be worked through
as and when external funding arises. 
5.2  A significant amount of work has gone into the development of the EVC strategy
and the Council is now well placed to deliver on further EVCs and to have robust
systems in place to manage the network. How the strategy develops from this
point will largely depend on clarity on future funding. 
6.0 IMPLICATIONS 
6.1 Policy – EVC strategy would be formally adopted as Policy and will guide
development of EVC as and when future funding arises.
6.2 Financial – cost recovery model is covering electricity costs; capital costs
currently 100% externally funded.

Page 9

6.3  Legal – none 
6.4  HR – none
6.5  Fairer Scotland Duty:
6.5.1 Equalities - protected characteristics
6.5.2 Socio-economic Duty - none   
6.5.3 Islands – gaps in the network are prioritised through the public programme. 
6.6 Climate Change – implications for climate change through EVC strategy are
very positive. Expanding our public network will encourage people to transition
to electric vehicles, reducing CO2 emissions and moving towards a greener
transport system. 
6.7 Risk – in terms of future options, there may be risks associated to a commercial
model.
6.8  Customer Service – Working to ensure a better maintenance and warranty
contract which will increase network reliability and provide a better service for
our customers. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure 
Jim Smith, Head of Roads and Infrastructure 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
October 2022 
For further information contact: 
Mark Calder, Project Manager 
Mark.Calder@argyll-bute.gov.uk 
Victoria Weir, Project Officer 
Victoria.Weir@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – EVC Infrastructure Development Methodology
Appendix 2 – Proposed EVC Expansion List
Appendix 3 – Consultation Responses
Appendix 4 – EVC Consultation Headlines and Key Themes 
Appendix 5 – HITRANS FASTER Project