ANNUAL STATUS AND
OPTIONS REPORT   
MARCH 2023
Appendix 1

Page 2

2 
Document Control 
Document History 
Version  Status  Date  Author  Changes from Previous Version 
1.0  First Draft  Oct
2022 
Update 2021 ASOR report with current
available data for management team review
1.8 Working Draft Nov
2022 
All updates completed with current available
data for management team review
1.10  Managers
Final Draft
Dec
2022 
Data now confirmed and updated to final
draft     
Document Control
Version  Status  Date  Comments

Page 3

3 
Contents 
 
Report Content ............................................................................................................................................... 5 
Management of Road Infrastructure Assets ................................................................................................... 8 
1.0 Carriageways ............................................................................................................................................ 9 
1.1 Road Length .......................................................................................................................................... 9 
1.2 Condition ............................................................................................................................................... 9 
1.3 Asset Valuation ................................................................................................................................... 10 
1.4 Investment  .......................................................................................................................................... 10 
1.5 Capital ................................................................................................................................................. 10 
1.6 Strategic Timber Transport Fund ........................................................................................................ 11 
1.7 Maintenance Backlog .......................................................................................................................... 13 
1.8 Capital Road reconstruction ................................................................................................................ 13 
1.9 Winter Maintenance ............................................................................................................................ 15 
1.10 CAPITAL RESURFACING INVESTMENT OPTIONS ....................................................................... 17 
OPTION 1— £3M .................................................................................................................................. 17 
OPTION 2— £5M .................................................................................................................................. 17 
OPTION 3 — £8M ................................................................................................................................. 17 
OPTION 4 — £11M ............................................................................................................................... 17 
1.11 Revenue Funded Preventative Maintenance Investment Options .................................................... 18 
2.0 Footways ................................................................................................................................................ 19 
2.1 Length ................................................................................................................................................. 19 
2.2 Condition ............................................................................................................................................. 19 
2.3 Asset Valuation ................................................................................................................................... 19 
2.4 Maintenance backlog .......................................................................................................................... 19 
2.5 Investment ........................................................................................................................................... 19 
2.6 Public Liability Claims ......................................................................................................................... 20 
2.7 Investment Options ............................................................................................................................. 21 
3.0 Street lighting .......................................................................................................................................... 22 
3.1 Inventory ............................................................................................................................................. 22 
3.2 Condition ............................................................................................................................................. 22 
3.3 Valuation ............................................................................................................................................. 22 
3.4 Investment ........................................................................................................................................... 23 
3.4 Investment (Cont). ............................................................................................................................... 24 
3.5 Energy Consumption ........................................................................................................................... 24 
3.6 Investment Options ............................................................................................................................. 26 
4.0 Structures ...................................................................................................................................... 27 
4.1 Assets ................................................................................................................................................. 27 
4.2 Condition ............................................................................................................................................. 27 
4.3 Asset Valuation ................................................................................................................................... 28

Page 4

4 
4.4 Investment ........................................................................................................................................... 28 
4.5 Maintenance backlog .......................................................................................................................... 29 
4.6 Flood Prevention ................................................................................................................................. 29 
4.7 Match Funding Opportunities .............................................................................................................. 30 
4.8 Flood Prevention Maintenance Backlog .............................................................................................. 31 
4.9 Investment Options ............................................................................................................................. 32 
5.0 Traffic Signals ......................................................................................................................................... 33 
5.1 Assets ................................................................................................................................................. 33 
5.2 Condition ............................................................................................................................................. 33 
5.3 Valuation ............................................................................................................................................. 34 
5.4 Investment ........................................................................................................................................... 34 
5.5 Maintenance Backlog .......................................................................................................................... 34 
5.6 Investment Options ............................................................................................................................. 35 
6.0 Street Furniture ....................................................................................................................................... 36 
6.1 Assets ................................................................................................................................................. 36 
6.2. Condition ............................................................................................................................................ 36 
6.3 Valuation ............................................................................................................................................. 37 
6.4 Investment ........................................................................................................................................... 37 
6.5 Maintenance Backlog .......................................................................................................................... 38 
6.6 Asset Data and Knowledge ................................................................................................................. 38 
6.7 Electric Vehicle Charging .................................................................................................................... 39 
6.8 Weather Stations ................................................................................................................................. 40 
6.9 Vehicle Restraint Systems .................................................................................................................. 40 
6.10 Investment Options ........................................................................................................................... 42 
7.0 Climate Change and a Resilient Network ............................................................................................... 43 
7.1 Investment ........................................................................................................................................... 44 
7.2 Condition ............................................................................................................................................. 45 
7.3 Maintenance Backlog .......................................................................................................................... 45 
7.5 Investment Options ............................................................................................................................. 45

Page 5

5 
Report Content 
This report has been compiled based on current available data which may be subject to change as
more information becomes available. Where little or no data exists then various assumptions and
estimates have been made to provide illustrations or add context to the subject matter. The report
provides a snapshot of road infrastructure assets within Argyll and Bute Council based on 2021-22
data for asset condition, previous investment, asset valuation and other relevant information. It
provides indicative future investment options for consideration within each asset group based on
available information and resource levels to develop same.

Page 6

6 
This is a headline summary on the condition of Argyll and
Bute Council Road infrastructure assets. It provides key
information on inventory, condition and the continued
need for greater investment in essential maintenance. 
Our roads support thousands of journeys every day and
are a vital component of a thriving economy for our
remote communities. Road transport infrastructure
benefits everyone by providing access socially,
commercially, educationally and enabling service access
for energy supply, communications and the digital
network (ie service ducts, maintenance).  
The covid-19 pandemic interrupted the annual road
condition assessment programme which meant island
roads were unable to be surveyed. However the latest
survey results show a marked improvement in overall
condition since the last normal survey from 54.4% to
49.8% as detailed in carriageway section 1.0. This
indicates that sustained investment targeted through the
road reconstruction programme has delivered
improvements contributing towards the council vision
“Our infrastructure supports sustainable growth”. The
results also show, this is the first time since SRMCS
surveys began that more than half our fragile road
network is within the green or good condition band which
demonstrates the efforts road maintenance teams have
achieved across the authority.
However, our road infrastructure assets are suffering
from long term under-investment creating an aged and
deteriorating asset base. The current maintenance
backlog for road Infrastructure assets (Roads, Footways,
Street lighting, Structures, Traffic Signals & Street
Furniture) is circa £140million. The annual investment
needed calculated as annual depreciation is £24.9million
(201/22 asset valuation) with current funding at
£18.3million / Year (2021/22 Asset valuation). 
Essential safety maintenance works on assets are being prioritised on a risk based, worst first basis due to funding
constraints leading to more expensive whole life costs. Because we carry out less preventative maintenance, service
life cannot be extended, therefore assets in good condition deteriorate further until defects are identified or reported.
This cycle happens over time and does not represent good long term value. Policies and maintenance strategies,
combined with longer term financial planning are needed to break this cycle of under-investment and accelerated
deterioration. This will support corporate objectives and demonstrate better value through well managed assets. 
Argyll and Bute Council is driving to improve services for communities within the constraints of resources and funding.
The covid pandemic has brought change to many aspects of service delivery with road asset maintenance facing
even greater challenge to deliver essential services due to the impact of higher materials costs and energy for street
lighting. The service also needs to consider and implement appropriate carbon reduction measures to support the
Decarbonisation Plan (2022-25) objectives and its ambition of achieving a 75% reduction in carbon emissions by
2030.

Page 7

7 
A decade of capital investment has provided almost steady state RCI condition
through a planned and prioritised programme of works. The maintenance
backlog for carriageways is £112m (2019 SCOTS report). Revenue funding has
reduced to the point where almost all activities are undertaken on a reactive
basis, effectively when assets stop functioning. Road maintenance services are
stretched to breaking point with resources being swallowed up by intensive
reactive maintenance demands. This is a vicious maintenance cycle (ASOR
Oct 2015) which requires more focus on delivering a planned programme of
preventative maintenance works to break the cycle and deliver appropriate level
of service standards. 
The recent £1m investment (2017-20) in footways has dealt with the worst
identified areas of concern and brought welcome improvement to localised
areas. Third party insurance claims have remained low with only one settled
claim in 2020/21. Greater emphasis and planning is required to deliver a
sustained long term funding and maintenance regime. Current fluctuation of
investment does not provide the best value for the long term sustainability of the
asset so that it can continue to meet user demands and expectations. Current
investment is £500k for 2022/23. 
Structures are inspected in accordance with the Management of Highway
Structures Code of Practice. This provides data to assess asset condition and
prioritise necessary maintenance. Since 2012/13 overall stock condition has
declined with 53 structures now subject to special monitoring precautions an
increase from 29 last year. Currently 15 bridges are subject to acceptable weight
restrictions and 28 bridges have failed the European Standard Assessment
which is the same as last year. Asset valuation is £290m with annual
depreciation at £1.3m/yr. Infrastructure Design Service secured £5.45m
investment from Scottish Government’s Local Bridge Maintenance Fund to help
address critical structures. 
Rising energy costs highlight the benefits of previous investment through the
LED replacement programme which has almost halved energy consumption
since the project began.  This project highlighted further necessary works to
replace aged columns and update the obsolete 5th core electricity supply which
is a source of many reported dark lamps and outages. A business case shall be
developed from collated data obtained via LED project to explore future long
term asset needs. Meanwhile continued investment totalling £440k for
completion of the LED replacement project and a further £300k for column and
cabling renewal will help towards asset improvement and supporting council
climate change objectives. Longer term maintenance strategy and investment
options are needed going forward to realise further savings  
The traffic signal asset condition has recently been surveyed highlighting a
substantial number of issues to update and modernise assets to comply with
current regulations. This requires the use of specialist contractors through a
tendering process to undertake the works. The costs are expected to outweigh
the current available budget and will require a prioritised list of works to be
compiled in line with available funding.            
The extent and condition of our street furniture asset isn`t fully recorded within
the asset database. Vehicle safety barriers were assessed in 2015. This showed
significant investment is needed to replace existing obsolete, damaged or
noncompliant safety fencing. The estimated cost £2.1m far outweighs current
budget allocation of £100k. This requires specialist external services to assess
needs and undertake necessary works. Additionally, council data on street assets
will now be subject to mandatory reporting to The Street Works Commissioner in 2023. 
Argyll and Bute Council have reduced carbon emissions by 27% in the last five years. The LED project has
contributed to this achievement through much reduced energy use. The Decarbonisation Plan (2022-25) sets out
actions for Argyll and Bute to become more climate friendly with aims to be carbon neutral by 2045. More
frequent severe weather events increase the likelihood of flooding and damage to road infrastructure assets or
property and requires more investment in regular preventative maintenance activities to mitigate the risk. Major
projects like the £15.215m Campbeltown Flood Prevention Scheme will provide a range of improvements to
reduce the risk of flooding in the town.

Page 8

8 
Management of Road Infrastructure Assets  
Argyll and Bute Council currently manages road infrastructure assets in line with available resources.
Resources are very limited, particularly in terms of asset data to support more informed decision making
which would reduce reliance on officer knowledge and experience. Robust and reliable asset data is a key
driver in realising predictable outcomes through the use of well-established asset management processes.
It provides decision makers with confidence whilst delivering better value and demonstrating a well-
managed asset portfolio in line with the SCOTS Asset Management Framework.  
Argyll and Bute Council participates in the SCOTS Road Asset Management (RAM) project with all other
Scottish Local Authorities. The project facilitates collaboration and development of a consistent asset
management approach across Scotland. The project recently commissioned consultants ATKINS to audit
authorities’ progress with developing the SCOTS asset management framework practices. The audit when
complete, provides individual authority reports and a national summary report for submission to the SCOTS
Executive. 
The Argyll and Bute audit draft report was completed in August 2020. The report highlighted a key factor
limiting asset management progress was resource constraints. It provided three recommendations that are
anticipated to provide significant benefits:  
Develop a Data Management Plan. 
Focus data collection on business needs, requirements and priorities. 
Identifies, risks and supports mitigation    
Documents data management processes      
▪ Enables review and auditing of data, systems and processes      
▪ Supports consistency of data collection and management.      
Provides data ownerships and promotes continuous improvements
Development of local monitors and KPI’s that:  
Align with the corporate plan and assist in linking performance across the service to its influence on             
achieving the corporate objectives / priorities / outcomes.  
Link monitors to key risks identified in the Road Asset Management Plan.  
Develop an Asset Management Communication plan  
Provides key asset management stakeholders  
Identifies key stakeholder’s asset management knowledge and competency  
Stakeholder AM knowledge and competency gap analysis
Stakeholder AM knowledge and competency improvement plan
Officers are organising Members Seminars in early 2023 to inform members and in particular new
members, of the engineering and back office asset management processes used to deliver our Capital and
Revenue Scheme selections. This will include information around resourcing and prioritising how officers
deliver the annual roads maintenance schemes across Argyll and Bute as well as our Asset Management
methods.

Page 9

9 
1.0 Carriageways 
1.1 Road Length 
A Class Roads   505.3km 
B Class Roads            613.5km 
C Class Roads            434.3km 
Unclassified Roads     733km 
Total Network Length    2286km 
The chart opposite shows that nearly one third of our
network is made up of unclassified roads (U Class). Most
of the carriageway is rural with over 80% of the network
in rural areas.  It should be noted that 38% of the network
is located on an island. This incurs additional cost to
maintenance operations through associated
transportation and remote working costs. Careful
planning is required to make the most of available
resources when undertaking island road maintenance
works.  
1.2 Condition 
Road condition is measured by the Scottish Road
Maintenance Condition Survey (SRMCS) which
assesses parameters such as surface texture and
cracking, smoothness and rutting. This provides an
indication of the residual life of the road structure.    
The latest road condition survey results show a marked
improvement in condition from the last normal survey
54.4% to current 49.8%. This highlights the sustained
investment from members recognising the significance of
our road network, which has allowed over 50% of our
Network to be in the ‘Green’ condition for the first time
over the last 8 years of reporting. The impact of covid
travel restrictions with much reduced vehicle movements
could potentially have reduced road surface
deterioration. Road condition results are based on a two
year rolling average which overlaps the covid pandemic.
Capital investment targeted towards the strategic A-
Class network has delivered much improvement with
condition now very good at 37.4% RCI compared to B, C & U road classifications. The urban network is also
considered to be in very good condition with and RCI value of 31.6%.

Page 10

10 
1.3 Asset Valuation 
The asset valuation for carriageways is detailed within
the table 3.7 opposite. It shows the Gross Replacement
Cost as £2.35billion. This is the cost of a new
replacement asset. The Depreciated Replacement Cost
is £2.09billion which is the present value of asset based
on condition data. The Annualised Depreciation Cost is
£20.81million which is the calculated level of annual
investment needed to sustain current asset condition. 
1.4 Investment   
The capital reconstruction programme
delivered £7.5m of investment on a range of
surfacing projects aimed at improving
network condition across Argyll.  The table
details the surfacing quantities and value
within each activity. The percentage split
across activities shows the bulk of
investment (77%) is attributed to Surface
Dressing (SD) and thin surfacing works to
maximise network coverage. The aim being
to seal and extend surface life with a SD
treatment and tackle as much deteriorated
surface as possible with thin surfacing works
so as to help reduce demand for reactive
treatment works.  
The adjacent table provides an indicative
guide on asset sustainability by comparing
annual works delivery via capital
reconstruction programme against expected
service life and asset inventory. This
provides an indicative treatment cycle in
years. 
1.5 Capital  
The tables and charts below illustrate the relationship between investment and the annual RCI results. By comparing
the capital spend average against the RCI average, this shows a steady state road condition budget allocation of
£7.688m/year for combined capital and revenue carriageway surfacing treatments would keep the carriageway from
further deterioration.  This value differs from the SCOTS Steady state figure £11.5m which can be attributed to the
SCOTS methodology using a more robust treatment matrix in the context of nationwide networks as opposed to
treatments specifically aimed at Argyll and Bute Council’s variable network. Surfacing treatments in Argyll are based
on several factors often unique such as island works that are not necessarily truly reflected in a national modelling tool
unless specifically formulated for that purpose. 
Surface Treatment  Length (m)  Cost (£)  Percentage 
Surface Dressing  82389  £2,263,946   30% 
Thin/Micro Surfacing (up to 25mm)  1191  £108,125   1% 
Thin Overlay (>25mm to 60mm)  39010  £2,244,509   30% 
Moderate Overlay (>60mm to
100mm) 
866  £94,181   1% 
Structural Overlay (>100mm)  1130  £146,570   2% 
Thin Inlay (>25mm to 60mm)  9079  £1,250,779   17% 
Moderate Inlay (>60mm to 100mm)  3658  £565,766   8% 
Structural Inlay (>100mm)  1019  £227,842   3% 
Planned Patching  0  £24,366   0% 
Reconstruction (250mm+)  3707  £599,584   8% 
Total   £7,525,669  
Treatment  Expected
Service Life    
(Years)
Quantity 
Works 
(Km)
Inventory  Treatment  Cycle
(Years) 
Surface Dressing 12-15  82.4  2286  28 
Resurfacing
Works 
20-30  55.9  2286  41

Page 11

11 
1.6 Strategic Timber Transport Fund 
Argyll and Bute Council has consistently secured significant funding support from the
Strategic Timber Transport Fund (STTF). The past decade has seen over £9M additional
investment from STTS to support the road reconstruction programme, this has enabled the
council to deliver noticeable upgrading on the strategic and other timber transport routes
which has improved safety, road user experience and reduced reactive maintenance
demands on already stretched budgets.
Agreed standard bidding process across all local authorities, final decision being made by
STTF. The STTF funding is earmarked for projects which minimise the impact of timber
lorries on our rural road network. It means that for every £1 Argyll and Bute Council spend
the STTF funding support, on average more than doubles this investment.  
The works being undertaken will make it easier for local residents and businesses to share
the roads. Getting timber off our own road network and improving journey times when
shifting timber from forests to processing facilities is another major benefit of improving the
network. 
Roads which have seen improvements from the joint funding between the council and
STTF are: 
A816 Lochgilphead – Oban strategic route; 
Lochawe haulage routes- B840, C30 and C29; 
Kintyre B842; and 
B8000 Strathlachlan, Cowal.  
Forestry is a key industry sector in Argyll and Bute, growing our economy and providing employment in management
and harvesting operations. Forestry also enables community access to forest trails to enjoy outdoor activities and
encourage healthier lifestyles.
The Strategic Timber Transport Fund (STTS) has enabled Argyll and Bute Council through a competitive bidding
process to secure significant 50:50 funding support for a number of identified road reconstruction projects across the
authority. These projects are delivered via the capital road reconstruction programme to improve sections of road
Year Capital &
Revenue
Survey year RCI
2013-14  £9,826,466  2013-15  55.6 
2014-15  £8,896,996  2014-16  54.4 
2015-16  £6,799,499  2015-17  55.3 
2016-17  £5,821,104  2016-18  55.5 
2017-18  £5,233,219  2017-19  54.4 
2018-19  £11,502,343 2018-20  54.17 
2019-20 £9,472,398 2019-21 N/A (covid)
2020-21 £8,426,346 2020-22 49.8
Average
Spend 
£8,247,296 Average  54.2

Page 12

12 
utilised for timber transport. This investment have provided welcome improvements to our strategic road network that
benefits all road users. 
Argyll and Bute Council continue to explore the possibility of further external funding with the Northern Roads
Collaboration and SCOTS to approach the Scottish Government regarding funding from Spirit Based Transport from
Distillery's (similar to the STTS Funding) which would provide additional roads funding.

Page 13

13 
1.7 Maintenance Backlog 
The SCOTS Headline Maintenance Backlog figure is calculated every two years using road condition data collected
via the Scottish Road Maintenance Condition Survey (SRMCS). The calculation uses surveyed condition data with a
surfacing treatment matrix and unit rates to determine the extent of maintenance required to bring whole network
surfacing to an ‘A1’ condition.  
For the steady state calculations the model was run and values were output so that each authorities red RCI
percentage was held at the current level by treating any amber RCI values which would otherwise deteriorate into red
values in the subsequent year.  This has been evidenced as best value. 
1.8 Capital Road reconstruction 
The capital reconstruction programme plays a key role in targeting available funding. The past decade has seen over
£86M investment in road resconstruction on sections of road that can provided greatest benefits and value to road
users. The table below illustrates the the capital reconstruction budgets over past ten years. 
ROAD RE‐CONSTRUCTION AND RE‐SURFACING BUDGETS 2011‐2023  
Fin.Year    
 
  Capital Invest.   STTS  Other   Comment 
2011‐12  £5,147,793  £4,295,000  £852,793       
2012‐13  £8,706,321  £8,137,000  £569,321       
2013‐14  £8,012,160  £6,165,640  £599,909  £1,246,611  add cap 
2014‐15  £6,922,089  £6,822,000  £100,089       
2015‐16  £4,440,987  £4,367,487  £73,500       
2016‐17  £4,693,612  £4,616,612  £77,000       
2017‐18  £3,616,443  £3,000,000  £616,443       
2018‐19  £9,747,042  £8,382,000  £1,365,042       
2019‐20  £7,867,469  £6,243,388  £1,624,081       
2020‐21  £6,918,222  £4,828,509  £1,255,568  £834,145  add cap ‐ Covid Deferred 
2021‐22  £10,809,462  £6,900,000  £1,299,462  £2,610,000  add cap ‐ Incl. Covid c/o 
2022‐23  £9,258,445  £8,000,000  £958,445  £300,000  Coastal Communities. 
TOTAL  £86,140,045  £71,757,636  £9,391,653  £4,990,756    
The photos below show some of the road reconstruction and resurfacing works being undertaken as part of the 2019-
20 capital investment programme. The photo opposite is part of the Islay retread process which involves churning up
existing deteriorated surfacing, adding some bitumen and regrading and compacting the surface to restore surface
condition. The process reduces the quantity of new materials required and contributes to lower carbon emissions for
the project as well as delivering best value on the Island road network. 
SCOTS Headline Maintenance Backlog   2019 SCOTS Report  Average Annual Investment 
Headline Backlog Figure  Steady State Figure  Capital Road Reconstruction
(2011-2022) 
£112,251,000  £11,507,000  £7,178,337

Page 14

14 
The photos below show  resurfacing works on B842 High Askimol and carriageway widening on A816 Blaran. Photos
below illustrate some of the recent capital reconstruction road resurfacing works.

Page 15

15 
1.9 Winter Maintenance 
Keeping our roads ‘open for business’ is vital for our economy and the health
and well-being of our communities. This includes carrying out winter
maintenance services aimed at keeping our roads safe during periods of
snow and ice through the winter months. This requires substantial resources
to monitor weather conditions, predict treatments, procure and store de-icing
salt, gritters, loaders and drivers to deliver same across Argyll and the Isles
every day of the winter period.  
Climate change is affecting how we deliver the service with winter weather
becoming more marginal and less predictable requiring more responsive
treatments and actions all within the confines of complying with driver hours
legislation. The table below provides some details of the scale of winter operations over the last ten years undertaken
on 31 planned treatment routes using a fleet of 33 gritting vehicles.

Page 16

16 
The cost of providing this vital service is a significant portion of annual road maintenance spend at almost 40% of
existing total revenue budget. This impacts other essential preventative maintenance activities with less works being
afforded. Consideration may be needed on alternative funding mechanisms for winter services so that the full extent of
revenue budget allocation can be utilised to achieve more extensive planned preventative maintenance to extend
service life of assets. Delivering these tasks to appropriate service standards can better support council corporate
goals whilst demonstrating well managed assets.   
Spend Roads Winter Total Winter %
2015-16 £4,173,702 £1,832,248 £6,005,950 30.51%
2016-17 £4,243,332 £1,885,851 £6,129,183 30.77%
2017-18 £3,926,258 £2,669,341 £6,595,599 40.47%
2018-19 £3,765,604 £1,791,150 £5,556,754 32.23%
2019-20 £3,485,315 £2,165,845 £5,651,160 38.33%
2020-21 £ 3,360,100 £ 2,251,432 £ 5,611,532 40.12%
2021-22 £3,516,984 £2,355,154 £5,872,138 33.03% 
Winter Treatment Information  Ten Year Average 
Total number of planned treatment runs  ( equiv Full Fleet)  65  Runs 
Total aggregate annual treatment mileage travelled by all gritting vehicles on all
planned routes  105024 Miles 
Total tonnage of salt used on carriageways  11030 Tonnes 
Total Winter actual spend carriageways  £2,258,229  Spend 
Budgets Roads Winter Total Winter %
2015-16 £3,957,298 £1,644,490 £5,601,788 29.36%
2016-17 £3,972,055 £1,836,286 £5,808,341 31.61%
2017-18 £3,832,056 £1,636,828 £5,468,884 29.93%
2018-19 £3,832,056 £1,621,674 £5,453,730 29.74%
2019-20 £3,411,055 £2,122,154 £5,533,209 38.35%
2020-21 £3,506,058 £2,122,618 £5,628,676 37.71%
2021-22 £ 3,422,540 £ 2,119,974 £5,542,514 38.25%

Page 17

17 
1.10 CAPITAL RESURFACING INVESTMENT OPTIONS   
OPTION 1— £3M    
 
 
 
 
 
An annual investment of £3m would lead to a substantial
deterioration on overall RCI with 69% of our roads requiring
attention after 20 years including 38% of roads considered
in the red category, this would significantly increase risk to
road users safety.  The volume of reactive temporary
repairs would steadily rise, year on year as would public
liability claims. Customer satisfaction levels can be
expected to steadily decrease. 
OPTION 2— £5M  
 
An annual investment of £5m would lead to a slower
deterioration on overall RCI with 59% of our roads requiring
attention after 20 years including 30% of roads considered
as red category. This is almost double the latest result
(16.34%) for red category roads. The volume of reactive
temporary repairs would steadily rise, year on year as would
public liability claims. Customer satisfaction levels can be
expected to steadily decrease.  
 
 
OPTION 3 — £8M 
An annual investment of £8m would lead to steady state in
overall RCI with 41% of our roads requiring attention after
20 years including 18% of roads considered as red category
which is on par with current red condition (16.34%). The
volume of reactive temporary repairs would likely remain
similar to current levels over initial period and would be
expected to remain similar over time as road condition
remains constant. Public liability claims would also be
expected to remain similar. Customer satisfaction levels
would also remain in steady state.   
OPTION 4 — £11M   
An annual investment of £11m for the next 20 years should
lead to a substantial improvement in overall RCI with only
27% of roads requiring attention including only 8% of roads
in red category, half the current red condition (16.34%). This
differs slightly from the projected value from the SCOTS
Backlog and Steady State model, due to a different method
of predicting future carriageway condition. This would
potentially make Argyll and Bute council the leading Scottish
authority in terms of RCI. A substantial reduction in reactive
repairs and public liability claims can be expected. Demands
on limited resources would be lessened and customer
satisfaction levels will also be greatly improved through this
investment.

Page 18

18 
1.11 Revenue Funded Preventative Maintenance Investment Options 
The value of undertaking adequate preventative maintenance works cannot be over stated. It is the most vital and
fundamental function required to extend infrastructure service life, strengthen network resilience and minimise
demand for capital investment. 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.   
Benefits Drawbacks Considerations
Less maintenance works afforded Doesn`t support corporate objectives
Increased asset deterioration Difficult to demonstrate value
Greater demand for expensive reactive works Future demand for capital investment far greater than 
initial savings realised
May compromise current internal service delivery
Benefits Drawbacks Considerations
Maintains existing budget No council budget saving Supports some corporate goals
Retains internal service delivery Requires change in approach Training to focus efforts on prioitised  business needs
Need more focus on planned works Needs commitment to deliver Some investment in better mobile technology
Need better data capture and analysis Development of appropriate service standards
Better value works can be afforded Additional resources needed to implement any changes
Benefits Drawbacks Considerations
Better control of costs No Council budget savings Supports council objectives
Delivers better value maintenance 
services
Potential increased budget required Implementing  SCOTS Asset Management recommended 
practices
Requires significant cahnges Investment in better mobile technology
More informed decision making Needs commitment to deliver Staff training & Additional resources to implement
Benefits Drawbacks Considerations
Vital maintenance activities delivered Compliance with capital investment rules Supports council objectives
Ability to demostrate value May impact capital investment on other assets  Implementing  SCOTS Asset Management recommended 
practices
Improved asset management Investment in better mobile technology
Staff training & Additional resources to implement
OPTION 1 Increased pressure on council budgets and the need to realise savings may reduce current investment levels for preventative maintenance  
activities. This needs careful consideration and will impact the quantity of works afforded necessary to provide adequate protection to vital road 
assets. It will increase demand for more expensive reactive works which is the vicious cycle essential maintenance activities are currently experiencing. 
It will increase future demand for capital investment far greater than initial savings realised.
Delivers short term budget savings
OPTION 2 Maintain existing investment levels  and consider prioritising  activity funding using a risk based approach. Prioritised activities  should be 
delivered through a planned programme of works to maximise value for money through appropriate service standards.  Combined with improved 
recording of maintenance works asset information can be enhanced to assist driving an improved asset management approach that can break the 
current vicious  cycle of reactive maintenance demands. 
OPTION 3 Maintain or increase investment levels through a zero based budget approach. This would essentially allocate a percentage budget for 
reactive maintenance with the balance of funding allocated through planned schedules and programmes of works to effectively justify and approve 
funding allocation against a measured works quantity to meet appropriate service standards. This would refocus effort on delivering measured work 
packages  whilst improving capture of asset information to assist delivery of  the benefits from implementing recognised asset management practices.
OPTION 4 Consider funding some maintenance activities using a capital funding allocation. Preventative maintenance is a critical activity some of which 
can be easily quantified (Ditching, Gully cleaning, Patching etc.). Delivering planned measurable works would greatly enhance ability to demonstarte 
value and prudent stewardship of assets.

Page 19

19 
2.0 Footways 
2.1 Length 
The footway asset is approx. 520km in length as detailed in
tables 2.1a & 2.1b opposite. The extent of the asset is not fully
known and is updated as new data becomes available. 
2.2 Condition 
Asset condition surveys are not currently undertaken due to
limited resources and cost implications.  
Generally footways are considered safe
and fit for purpose with maintenance
works undertaken in response to
identified defects or public complaints
as investment and resources permit. 
2.3 Asset Valuation 
Details of the asset valuation are shown in table 2.3 below;  
Table 2.3 Footway Valuation by Hierarchy       
Footway Hierarchy Gross Replacement
Cost 
Depreciated
Replacement Cost
Annualised
Depreciation Cost 
Higher Amenity Footways £10,431,218 £8,855,040 £67,272
Other Footways £89,430,884 £69,430,323 £882,053
Total £99,862,102 £78,285,363 £949,325
2.4 Maintenance backlog 
The maintenance backlog for footways is based on officers estimation of condition calculated as three percent of
gross replacement cost of the asset.   
Gross Replacement Cost (GRC)  Backlog Estimate 3% GRC 
Investment Need based on   
Annualised Depreciation Cost
£99,862,102 £78,285,363 £949,325  
2.5 Investment 
Footways investment of £1m over previous 3 years has tackled
some of the worst identified sections of the network aimed at
reducing reactive maintenance demands. The planned capital
investment for 2021/22 was £900k and a further £500k for
2022/23 
Table 2.5a details the extent of capital works undertaken 2019-
20.  
Table 2.5b provides indicative information on the current
footways treatment cycle.    
2.5b Footway Treatment Cycle     
Treatment  Expected Service Life (Yrs)Quantity (Km)  Inventory (Km) Treatment  Cycle (Years) 
Surface Treatment  15-20  0.802  529  660 
Resurfacing Works  30-40  1.913  529  277 
Reconstruction  50-60  0.471  529  1123   
All Works     3.186  529  166 
Table 2.1a Footways
Quantities by Hierarchy 
Footway
Hierarchy 
Length (m)  Area (sqm) 
Higher Amenity
Footways  41,977  117,536 
Other Footways  470,174  1,001,471 
Total  512,151  1,119,006 
Table 2.1b   All Footpath Quantities  
Quantity  Length (m)  Area (sqm) 
All Footpaths  9,349  11,219 
Total  9,349  11,219 
2.5a Footways   
Treatment  Length (m)  Cost (£) 
Surface Treatment  802  £20,641.74 
Resurfaced  1,913  £139,205.57 
Reconstruction    471  £74,045.90 
Totals  3,186  £233,893.21

Page 20

20 
2.6 Public Liability Claims 
The number of public liability claims and resultant costs are illustrated in the charts below. The last few years have
shown a decreasing trend in the number of carriageway settled claims. The capital reconstruction programme
improvements have likely contributed to this although the restrictions in travel during covid pandemic may also be
influencing data. Continued investment particularly that targeted towards preventative maintenance measures will
extend service life and preserve the functionality of road assets to help mitigate any risk to road users.   
5
1
0 0 0 0
14
0
2
4
6
8
10
12
14
16
2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21
Number of Public Liability Claims Settled

Page 21

21 
2.7 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources. Investment options should be inked to the long
term maintenance strategy for the asset. . 
Benefits Drawbacks Considerations
Continues service delivery for defects Continued long tern asset deterioration Adopting risk based approach to managing the asset
Growing demands for capital investment  Resource condition survey of asset to gain information on 
asset needs
Rising number of public liability claims  Development of long term maintenance strategy for asset 
group
Reactive maintenance is expensive and poor 
value
Resource development of a prioritised list of planned 
works
Benefits Drawbacks Considerations
Investment tackles asset deterioration limited asset information and condition data Implementing SCOTS asset management recommended 
practices
Planned works deliver better value  resources required to identify, quantify and 
works
Resource development of a prioritised list of planned 
works
Reduced demand for reactive works Level of works limited within available revenue 
budget allocation
Development of long term maintenance strategy for asset 
group
Less complaints
Benefits Drawbacks Considerations
Investment tackles deterioration and 
gradually improves whole asset
limited asset information and condition data Development of long term maintenance strategy for asset 
group
Demonstrates prudent stewardship of 
assets
resources required to identify scope of works Investment in mobile technology to capture asset data
Supports corporate objectives Requires increased levels  investment Implementing SCOTS asset management recommended 
practices
Benefits Drawbacks Considerations
All asset approach to maintenance requires substantial capital investment  Use of SCOTS asset management tools
Investment in mobile technology
Deveolpment of appropriate maintenace strategy
Option 1   Undertake maintenance only on a reactive basis to repair defects within existing revenue budget allocation
Option 2 Increased investment in revenue planned maintenance activities
Option 3 Develop business case for investment through capital budget for resurfacing/reconstruction of sub standard footways and footpaths. Extend 
the capital programme of improvements undertaken 2017‐20 via a rolling 3 ‐ 5 year programme of works that can be prioritised in line with available 
resources.
Option 4 Capital investment for improvement in kerbing in conjunction with carriageway surfacing and street lighting projects. Requires a holistic 
planned approach across all road asset groups to collaborate works programmes to support overall council goals and objectives. A streetscene 
approach to delivering improvements.

Page 22

22 
3.0 Street lighting 
3.1 Inventory 
The extent of street lighting asset is detailed in Tables 3.1a,b,c, d & e below; 
There is no available data on the extent of cabling associated with street lighting assets. The quantities within table
3.1d have been estimated based on 30 Lin.m per column. The estimated quantities have also been sub-divided into
likely cable tracking location as 10% carriageway, 50% footway and 40% in verge. 
3.2 Condition 
The condition of street lighting assets is normally determined based on the age of assets. Unfortunately there is no
available historic data on the installation dates for the majority of street lighting assets. However following the recent
investment in replacement of luminaires with new low energy LED Lanterns data has been collected on the condition
of columns and apparatus across the network. Work is ongoing to collate the data so that it can be fully assessed to
determine the extent of asset deterioration. Initial LED replacement works highlighted a substantial number of
columns in very poor condition and unsuitable for installing new LED lanterns.  
Currently identifying the best options to manage street lighting maintenance for future years including replacement
columns, 5th core cabling, finalising LED works  
3.3 Valuation 
The asset valuation has been undertaken in accordance with the CIPFA Transport Asset Code recommendations
using the 
SCOTS asset management framework tools and guidance. The valuation is detailed in Tables 3.3a,b & c below; 
Other Street Lighting Assets Quantity
Wall Bracket 1,191
Wooden Pole 110
High Mast Column 0
Control Cabinet 751
Total 2,052
Table 6.2e Other Street Lighting Assets
Cable Assets Quantity (m)
Cable under Carriageway 43,050
Cable under Footway 215,250
Cable under Verge 172,200
Total 430,500
Table 6.2c Street Lighting Cable Quantities
Illuminated Signs Quantity
Signs 433
Bollards 46
Total 479
Table 6.2d Illuminated Sign Assets

Page 23

23 
3.4 Investment 
The street lighting asset has seen investment directed towards new LED lanterns as part of spend to save
initiative aimed at lowering energy usage to reduce annual energy costs. Reduced energy usage supports
council objective to meet its climate change targets by reducing carbon footprint. The LED project is almost
completed and has clearly demonstrated the positive impact investment can make towards achieving
council objectives.  
However the project has highlighted a number of issues with the asset as many columns were unable to
accept new LED lanterns due to their deteriorated state.  An exercise is ongoing to collate data from the
project to ascertain the extent of columns needing replaced so that a suitable business case can be
progressed. It is known that a large but undetermined quantity of the inventory of street lights is still
powered from the “5th core” electrical supply system, which is pre-2nd world war in origin. This dated
infrastructure is a source of regular failure requiring the electricity supply company to attend and repair
outages. Table 3.4 below details the cost of reconnections in previous year. There are currently 19 power
supply defects requiring attention with repair costs to date in Bute and Cowal at almost £20k representing
almost 30% of the annual maintenance budget for the area.

Page 24

24 
The costs for repairing power outages is unpredictable  due
to the unknown element of works involved until repairs have
commenced to expose the full extent of the fault. This
requires further design work and cost benefit analysis to
enable the most appropriate solution within confines of
available resource. However the continued allocation of
individual power connection fault costs to the revenue
maintenance budget as part of dark lamp or section fault
repairs is unsustainable both in the short to medium term and within the longer term need for asset improvement. 
3.4 Investment (Cont). 
The replacement of deteriorated assets that have reached the end or beyond their expected service life is currently
not part of a longer term maintenance strategy or plan. For many years the need to deliver investment savings has
over ridden the need for asset renewals. This reduced funding has delayed asset renewal projects creating an even
older and more fragile asset base leading to a growing backlog of outages and reactive maintenance demands on
very limited resources.  
Between 2010—2017 lighting column replacement schemes dwindled due to funding constraints with annual renewal
of columns  averaging approx. 20—50 units per year. The adoption of new roads generally in urban areas added circa
40 additional column assets annually to inventory database. Since 2017 the LED replacement programme has taken
precedent over column and cable renewal and has delivered substantial savings in energy consumption and carbon
emissions. Over this period no planned column and cable replacement works were undertaken other than as part of
reactive works to restore outages. The LED project highlighted the condition of assets and the growing need for
urgent action to develop a longer term maintenance strategy for investment in asset renewals. Table 3.4 provides and
indicative treatment cycle based on current average expected asset renewal and clearly illustrates the present
investment strategy is unsustainable. 
Table 3.4 Street lighting Column and Cable Treatment Cycle    
Treatment  Expected Service Life
(Yrs) 
Annual
Quantity
(Ave)  
Inventory (No.)  Treatment  Cycle
(Years) 
Column Replacement 30  25 No.  13047  522 
Cable replacement  60  750 Lin m.  430,500 (Lin.m)  574 
Luminaire (LED)       20  N/A  14640  All new assets 
3.5 Energy Consumption 
Annual energy consumption for street lighting has been significantly reduced since 2017/18 following the investment
in new LED lanterns. Table below clearly illustrates the benefits delivered from this investment package. Data
supplied from hHums from Power Data Associates.   
Table  3.5 Annual Energy Consumption 
Year  Total   Unit 
2014/15  4361341.9  kWh 
2015/16  6325655.3  kWh 
2016/17  6119183.7  kWh 
2017/18  4288415.2  kWh 
2018/19  3267835.1  kWh 
2019/20  3232557.7  kWh 
2020/21 3228999 kWh 
Table 3.4 Power Supply Outages 
Year  Description  No   Cost  Average   
2019-20  Reconnection  20  £65,678  £3,284

Page 25

25 
Section 35 of the Roads (Scotland) Act 1984 refers to the provision of lighting by roads authorities in
Scotland and states: 
(1)  A local roads authority shall provide and maintain lighting for roads, or proposed roads, which are,
or will be, maintainable by them and which in their opinion ought to be lit. 
At present our current LED replacements allow up to 30% reduced power during the hours of darkness and
provide the previously listed savings. 
Some local authorities in England have taken the decision to switch off street lighting between certain hours
(ie from midnight to 0500hrs) to provide further cost savings. This would need to be balanced with road
safety and the possibility of an increase in crime. 
A further option would be to remove sections of street lighting altogether. As a Local Roads Authority we
are only required to provide and maintain lighting for roads where in our opinion roads ought to be lit. Again
this must be heavily caveated by the possible road safety and criminal activity which could be a direct result
of our towns and villages losing street lighting sections.  
Year  Carbon Total  Units 
2014/15  2325  tonnes CO2 
2015/16  3140  tonnes CO2 
2016/17  2733  tonnes CO2 
2017/18  1636  tonnes CO2 
2018/19  996  tonnes CO2 
2019/20  889  tonnes CO2 
2020/21 810 tonnes Co2

Page 26

26 
3.6 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require
further investigation, research and development to progress more detailed information on which option is
best suited to support council objectives within the confines of available resources.  Investment options
should be linked to development of a long term maintenance strategy for the asset. 
Benefits Drawbacks Considerations
Continues service delivery for defects Continued long tern asset deterioration Adopting risk based approach to managing the asset
Growing demands for capital investment  Resource condition survey of asset to gain information on 
asset inventory, condition Etc.
Rising number of public liability claims  Development of long term maintenance strategy for the  
asset group
Reactive maintenance is expensive and poor 
value
Resource development of a prioritised list of planned 
works
Benefits Drawbacks Considerations
Investment tackles worst asset 
deterioration
limited asset information and condition data Implementing SCOTS asset management recommended 
practices
Planned works deliver better value  resources required to identify and quantify  
works
Current use, Is it needed? Can it be removed?
Reduced demand for reactive works Level of works limited within available revenue 
budget allocation
Resource development of a prioritised list of planned 
works
Less complaints Development of long term maintenance strategy for asset 
group
Benefits Drawbacks Considerations
Investment tackles deterioration and 
gradually improves whole asset
limited asset information and condition data Development of long term maintenance strategy for asset 
group
Demonstrates prudent stewardship of 
assets
resources required to identify scope of works Investment in mobile technology to capture asset data
Supports corporate objectives Requires increased levels  investment Implementing SCOTS asset management recommended 
practices
Benefits Drawbacks Considerations
Whole asset approach to maintenance requires substantial capital investment Use of SCOTS asset management tools
Requires significant improvement in asset data Investment in mobile technology
Deveolpment of appropriate maintenace strategy
Option 1  Undertake maintenance on a reactive basis to repair defects within existing revenue budget allocation.
Option 2      Increased investment in planned revenue maintenance activities
Option 3    Develop a business case for investment through capital budget for replacement of obsolete, damaged and deteriorated assets particularly 
vehicle safety barriers. Align the business case to a suitable long term maintenance strategy for the asset group.
Option 4   Business case development for capital investment in conjunction with other asset groups that aligns with the Road Asset management Plan 
(RAMP) and council priorities.

Page 27

27 
4.0 Structures 
4.1 Assets 
Table 4.1 : Structures Inventory 
Quantity 
Road Bridges  889 
Footbridges  11 
Unusual Structures  2 
Retaining Walls  1,404 
Height, Sign and Signal Gantry 0 
Culverts   294 
Subways  0 
Total  2,600  
4.2 Condition 
Our bridges and structures are inspected and assessed to comply with the Management of Highway Structures Code
of Practice. Data gathered from bridge inspections is used to calculate a Bridge Stock Condition Indicator value which
can enable analysis and trending of condition information. The condition results since 2012/13 are illustrated in the
chart below which shows a steady decline in overall bridge stock condition from a reduction in capital investment with
revenue investment being prioritised towards reactive repairs. The long term trendline in blue shows a continued
deterioration of assets with condition of less critical structures expected to decline further without increased levels of
investment.  
There are currently 53 structures subject to special monitoring precautions and 28 bridges that have failed the
European standard assessment (prior to restrictions). 15 bridges are currently subject to acceptable weight
restrictions.
Bridges are subject to regular inspections with principal inspections every 6 years and general inspections every 2
years. 
88.00
88.50
89.00
89.50
90.00
90.50
91.00
2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22
BSCIav 90.72 90.00 89.88 89.88 89.28 89.18 89.18 89.31 89.06 89.01
Bridge Stock Condition Indicator BSCIav

Page 28

28 
4.3 Asset Valuation 
Table 5.5 Structures Valuation Summary
Structure Type
Gross Replacement
Cost 
Depreciated
Replacement Cost 
Annualised
Depreciation Cost 
Road Bridges £115,251,542 £108,769,286 £1,268,947
Footbridges £2,934,648 £2,924,575 £2,117
Unusual Structures £2,286,856 £1,876,450 £18,390
Retaining Walls £166,492,505 £166,442,331 £20,470
Height, Sign and Signal Gantries £0 £0 £0
Culverts   £3,533,754 £3,528,339 £294
Subways £0 £0 £0
TOTALS £290,499,306 £283,540,981 £1,310,218 
4.4 Investment 
Funding for the refurbishment or renewal of bridges has dwindled over time to meet with required budget
savings needs. Current funding levels are:
 Capital Bridge Strengthening and Replacement Programme 
o £350k per annum for next 3 years
o £999k slippage from previous years carried forwards
o Strengthening & Replacement of Bridges & Retaining Walls
o Current Programme also incorporates Local Bridge Maintenance Fund 
 Revenue Structural Maintenance
o £231k per annum confirmed annually
o Bridge & Retaining Wall Inspections
o Bridge & Retaining Wall Maintenance Repairs 
o Management of Abnormal Load Notifications
o Technical Approval 
o Asset Management 
 Revenue Structural Assessment
o £64k per annum confirmed annually
o Assessment of Bridges and Retaining Walls 
 Capital Coastal Protection 
o £20k 22-23 / £80k 23-24 / £100k 24-25 
o Coastal Protection Strengthening Repairs 
 Revenue Coastal Protection
o £180k per annum confirmed annually
o Coastal Protection Inspections
o Coastal Protection Maintenance Repairs 
o Asset Management 
 Capital Ardbeg Seawall
o £750k 22-23
o Temporary repair & Permanent reconstruction of seawall damaged by storm in December
2021 
 Capital Coastal Change Adaptation
o £159k 22-23
o Coastal Change Adaptation Repairs

Page 29

29 
Additional funding of £5.45m has been secured by Infrastructure Design Service from Scottish
Government’s Local Bridge Maintenance Fund.  This was secured for replacing 4 bridges and replacing 5
(9 total) critical infrastructure bridges in Argyll and is expected to be delivered over the following 4 years. 
A number of structures have been repaired following severe storm damage on a reactive basis to maintain
vital transport or community links. 
When structures are replaced, they are generally larger, very few are the same size, construction or span
due to flooding requirements which considers climate change.  It has been assumed an average of
between one and four structures are refurbished or replaced annually.  The table below provides an
indicative illustration of the bridge renewal cycle. 
4.5 Maintenance backlog 
The maintenance backlog for structures is detailed in table below. It has been calculated using the SCOTS
asset management framework guidance to provide an estimated value for maintenance needed to bring the
asset to very good condition in one year.  
Headline Backlog Figure   Steady State
Figure 
Source 
£24.4m   N/A  Argyll and Bute Council Asset
Management Reporting 
4.6 Flood Prevention 
Argyll and Bute Council has a statutory duty under the Flood Risk Management Act (Scotland) 2009 to reduce the
overall flood risk. This includes flood risk assessment, maps, plans and management of the risk. These works are
undertaken in conjunction with the Scottish Environment Protection Agency (SEPA) using local historical data to
assess the risk and impact of flooding events. The current budget allocation for flood risk management are:  
 Revenue Flood Management 
o £222k per annum confirmed annually
o Flood Management
o Flood Incident Investigation
o Section 17 Mapping
o Section 18 Waterbody Assessments 
o Section 59 Clearance and Repair Works
o Provision Of Flood Consultancy (General Flood Advice)
o Flood Monitoring Network
o Flood Risk Assessments
o Shoreline Management Plan 
Item
Expected Service
Life of Assets
Annual Replacement
Quantity (Estimated) Current Inventory
Indicative Asset    
Renewal cycle
Bridge 120-150 years 3 902 301 years
Table 4.6 Flood Risk Management Budget  
Year   Capital  Revenue  Project 
2020-21  £387k  £323k  General Flood Risk Management Plans 
2021-22  £955k  £323k  Campbeltown Flood Prevention 
2022-23          
2023-24

Page 30

30 
 Revenue Flooding – Direct Costs 
o £100k per annum confirmed annually
o Works carried out by Argyll and Bute Council’s DLOs 
 Capital Flood Prevention 
o £474k 22-23 / £305k 23-24 / £305k 24-25
o Current Projects
 Tigh Dearg Road
 Rothesay FPS Performance 
 Capital Helensburgh Flood Mitigation 
o £432k 22-23 
 Capital Campbeltown Flood Protection Scheme 
o £6.870m 22-23 / £7.133m 23-24 / £0.05m 24-25 / £0.38m 25-26 
4.7 Match Funding Opportunities 
The Scottish Government currently offers 80% funding opportunity for local authorities towards development of
necessary flood prevention schemes. A key factor in securing this funding is participation in the Scottish Governments
defined process for assessing flood risk and prioritising investment across Scotland. Efforts should be made to ensure
participation in the Scottish Governments defined process to enable capture of any potential funding for Argyll. 
The Campbeltown Flood Protection Scheme is 80% funded through this.
The timescales for the next stage of funding have not yet been confirmed.
A paper was presented to Committee in December 2022 which updated on Cycle 2 of the Local Flood Risk
Management Plan. This identified the studies and schemes which the Council is obligated to progress under the Flood
Risk Management (Scotland) Act 2009. 
Campbeltown Flood Protection Scheme, 
This is a £15million major engineering scheme which will put measures in place to reduce the impact of
flooding on residents and businesses in Campbeltown, the town has suffered flooding at various times in
recent decades.
This investment will take forward a
number of different pieces of work to
address the various causes of flooding in
the town.
The picture opposite uses detailed
hydraulic modelling to show the scale of
potential flood risk for a 1 in 200 year
event. 
The photos below show the impact of
previous flooding events within
Campbeltown.

Page 31

31 
4.8 Flood Prevention Maintenance Backlog 
The current maintenance backlog for flood prevention assets is estimated at Circa £250k. This is partly due to
designated Flood prevention assets being relatively new. However historically across Argyll there are many un-
designed assets which are currently not recognised as part of the flood prevention asset portfolio or owned by the
council but nonetheless serve a purpose Eg. The Banks of the Black Lynn Burn in Oban. The backlog of repairs
needed for these assets is not quantified but is expected to be tens of millions of pounds to bring assets up to good
condition.  
The photo opposite shows the extent of flooding at Lochavullin Road Oban October 2014 which caused extensive
damage to vehicles and property. The photo below shows a similar flooding event at Lochavullin car park in October
2018.   
Following these incidents some temporary flood prevention works have been undertaken to help protect property from
flooding damage.  
There is a need for much more extensive projects to help alleviate the issues causing these events which are beyond
the scope of existing budget allocation.

Page 32

32 
Investigations and studies are currently being undertaken for Rothesay Flood Protection Scheme’s efficacy and on
Lochavullin Car Park resilience measures.  
4.9 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require
further investigation, research and development to progress more detailed information on which option is
best suited to support council objectives within the confines of available resources.  Investment options
should be linked to development of a long term maintenance strategy for the asset. 
Benefits Drawbacks Considerations
Continues service delivery for defects Continued Asset deterioration Development of a long term maintenance strategy 
Increased risk of more  weight restrictions or 
road closures
Strengthen the business case for investment
Impacts Economy and vital transport links Explore funding opportunities Etc. (Flood prevention Etc)
Reactive maintenance is expensive and poor 
value
Benefits Drawbacks Considerations
Continues service delivery for defects  Asset deterioration remains  greater than 
investment
Development of a long term maintenance strategy 
Tackles some preventative maintenance 
backlog
Impacts Economy and vital transport links Strengthen the business case for investment
Contributes to lowering  risk of more  
weight restrictions or road closures
Reactive maintenance is expensive and poor 
value
Explore funding opportunities Etc. (Flood prevention Etc)
Benefits Drawbacks Considerations
Contributes to development of more 
sustainable asset management regime
Requires investment Development of a long term maintenance strategy 
Planned preventative maintenance 
programme of works
Requires resource to develop business case Strengthen the business case for investment
More sustainable asset condition Explore funding opportunities Etc. (Flood prevention Etc)
Supports corporate objectives Resources to undertake increased workload
Benefits Drawbacks Considerations
Sustaniable asset management regime Requires substantial level of investment Development of a long term maintenance strategy 
Improves asset condition Requires resource to develop successful business 
case
Resources to undertake/ manage increased workload and 
projet design and development.
Reduced weight restrictions May require additional data capture to support 
business case development
Explore funding opportunities Etc. (Flood prevention Etc)
Supports corporate objectives
Option 1   Undertake maintenance only on a reactive basis to repair defects within existing revenue budget allocation
Option 2       Increased investment in revenue planned maintenance activities
Option 3 Develop business case for investment through capital budget for strengthening and refurbishment of structures. Development and 
implementation of an appropriate long term maintenance strategy for the asset group. Continued improvement in asset management.
Option 4 Development of a successful business case for investment to tackle deterioration and improve overall asset condition as part of a developed 
asset management process.

Page 33

33 
5.0 Traffic Signals 
5.1 Assets 
The extent of traffic system management assets is detailed in table 5.1a & b below; 
Table 5.1a  Traffic Management System Quantities
Traffic Signal Types Quantity 
Traffic Signal (Junction) Subtypes  
Minor Junction  0
Medium Junction  11
Major Junction  0
Complex Junction 0
Traffic Signal (Pedestrian
Crossing) Subtypes  
Single Carriageway 14
Double Carriageway 0
Total 25 
5.2 Condition 
The traffic management system asset is subject to condition survey which is being undertaken by specialist
consultants. Survey data is being collated and should provide a comprehensive insight on the current status of assets.
Initial survey results show significant evidence of asset deterioration particularly control cabinets and poles. There are
a number of issues where existing assets do not meet current standards requiring a number of updates to tactile
paving, road markings, traffic lights and detector loops Etc. The full results of the survey will need to be assessed and
a prioritised list of repairs compiled. A business case may be needed to support the case for investment to address
the issues highlighted within the survey report. 
Table 5.1b  Other Traffic Management System
Quantities
Other Traffic Management
System Types Quantity 
Information Systems 2
Safety Cameras 0
Variable Message Signs 2
Vehicle Activated Signs 18
Real Time Passenger
Information 0
Total 22

Page 34

34 
5.3 Valuation 
Traffic Signal Types Quantity 
Gross
Replacement
Cost 
Depreciated
Replacement
Cost
Annualised
Depreciation
Cost
Junctions 11 £539,550.00 £333,131.25 £22,481.25
Pedestrian Crossings 14 £305,200.00 £145,923.75 £13,352.50
Total 25 £844,750.00 £479,055.00 £35,833.75 
5.4 Investment 
Traffic management systems require specialist contractors to undertake regular inspection and necessary
maintenance. Increasing reactive maintenance costs are being incurred as some assets are functioning beyond their
expected service lives and when problems arise replacement of obsolete parts is difficult to procure. 
Many traffic management assets have had essential works postponed over time due to budget restrictions. Although it
is the smallest asset group delays in asset renewal particularly electronic hardware can lead to parts becoming
obsolete as advances in technology become available. A recent survey has highlighted the need for some urgent
repairs to bring systems up to date. Historically junctions and pedestrian crossing have been replaced ad hoc in
response to system failures or inability to obtain replacement components. Generally this equates to approx. one
junction or crossing per year.  The table below provides an indicative illustration of the asset renewal cycle. 
Item 
Expected
Service
Life 
Annual     
Replacement
Quantity 
Current
Inventory Indicative Renewal cycle 
Traffic Control Unit  20 Years  1  24  24 Years 
5.5 Maintenance Backlog 
The maintenance backlog is calculated at £225k based on initial condition survey data and local officer estimate of
upgrading assets to meet current standards. It provides an indicative measure of the level of investment needed to
sustain the asset in good condition.

Page 35

35 
5.6 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options should be linked to
development of a long term maintenance strategy for the asset. 
Benefits Drawbacks Considerations
Maintains existing service Specialised works undertaken by external 
contractors Revised tender for routine inspection and maintenance
Deteriorated asset base drives increasing reactive 
maintenance costs
Requires additional resource to develop appropriate 
business case.
Requires occaissional capital investment to 
replace obsolete /defective equipment.
Benefits Drawbacks Considerations
Improved asset relaiability Requires investment Resource and staff training to improve asset knowledge
Reduced maintenance costs Requires resource to develop suitable business 
case for investment using capital budget
Development of a suitable maintenance strategy for asset
Requires rescoure to procure tenders and 
administer/supervise potential contract works
Benefits Drawbacks Considerations
Modernises asset to meet current 
standards
Requires investment
Resource to manage and supervise works
Improves reliability Requires resource to develop suitable business 
case for investment using capital budget
resource required to procure tender documentation and 
administration of same
reduces reactive maintenance costs Use SCOTS Asset management tools 
Improves user experience
Benefits Drawbacks Considerations
Modernises asset to meet current 
standards
Requires investment
Resource to manage and supervise works
Improves reliability Requires resource to develop suitable business 
case for investment using capital budget
Resource required to procure tender documentation and 
administration of same
reduces reactive maintenance costs Use SCOTS Asset management tools 
Improves user experience
Assess need for individual assets. Can they be removed? 
Are alternative control measures available?
Option 1    Continue to fund Traffic Signals within existing annual allocation of £45k revenue budget
Option 2           Utilise latest condition survey data to develop an appropriate business case for investment in renewal of apparatus
 
 
 
Option 3    Produce a business case based on latest survey data to upgrade all apparatus to meet  compliance with current standards over a three to 
five year period
Option 4      Utilise latest condition survey data to identify asset needs. Address any priority repairs and progress a maintenance strategy as part of the 
RAMP to develop a long term investment plan over next three ‐ five years to bring asset condition to meet compliance with current standards.

Page 36

36 
6.0 Street Furniture 
6.1 Assets 
The street furniture asset covers a wide range of items. The full extent of these items is often unknown with little
information currently held on asset database systems. Table 6.1 provides details of the current information held for
each of the identified item which is subject to change as more information becomes available. 
Table 6.1 Street Furniture Quantities
Street Furniture Assets Quantity of Assets Unit
Traffic Signs (non-illuminated) 5,012 Number
Safety Fences 61,628 Length (m)
Road Blockers 0 Number
Hostile Vehicle Barriers 0 Length (m)
Pedestrian Barriers 198 Length (m)
Street Name Plates 0 Number
Bins 0 Number
Bollards 276 Number
Bus Shelters 124 Number
Grit Bins 583 Number
Cattle Grids 162 Number
Gates 0 Number
Trees  0 Number
Seating 0 Number
Verge Marker Posts 2,322 Number
On-Street Parking Meter 92 Number
Electric Car Charging Points 28 Number
Milestones 0 Number
Information Boards 0 Number
Bike Parking Lockers 0 Number
Bike Parking Stands 0 Number
Automatic Trash Screens 0 Number
Watercourse Telemetry 0 Number
Weather Stations 0 Number
Total 70,425   
6.2. Condition 
There is currently no condition data available other than for some individual items such as vehicle safety barriers. The
nature of street furniture assets is such that individual assets are generally not subject to condition survey rather they
are replaced when items are no longer fit for purpose or cannot function as intended. Items where possible are
generally replaced in response to identified need or public complaints within the confines of available revenue budget
allocation. 
The condition of vehicle safety barriers has been reported previously and requires substantial investment to address.
Initial local officer estimates indicate £2.1m investment need which requires resource to develop an appropriate
business case. It should be noted that vehicle barriers are a specialist work requiring appropriate national certification
and staff training to enable progress. There is currently no staff resource with required certification so design works
will need external consultants to survey and quantify full extent of works.

Page 37

37 
6.3 Valuation 
The asset valuation is detailed in Table 6.3 below. The valuation is based on current available data within the street
furniture asset group which has numerous different asset types.  
Table 6.3  Street Furniture Valuation
Street Furniture Assets Gross Replacement
Cost
Depreciated
Replacement Cost 
Annualised
Depreciation Cost 
Traffic Signs (non-illuminated) £149,257.36 £74,631.66 £7,462.87
Safety Fences £4,403,936.88 £2,201,997.02 £220,196.84
Road Blockers £0.00 £0.00 £0.00
Hostile Vehicle Barriers £0.00 £0.00 £0.00
Pedestrian Barriers £14,149.08 £6,961.63 £565.96
Street Name Plates £0.00 £0.00 £0.00
Bins £0.00 £0.00 £0.00
Bollards £16,438.56 £8,072.76 £657.54
Bus Shelters £1,433,912.44 £719,268.98 £71,695.62
Grit Bins £69,437.81 £35,894.07 £4,629.19
Cattle Grids £771,815.29 £378,665.92 £30,872.61
Gates £0.00 £0.00 £0.00
Trees  £0.00 £0.00 £0.00
Seating £0.00 £0.00 £0.00
Verge Marker Posts £55,301.91 £28,575.04 £3,686.79
On-Street Parking Meter £361,008.00 £180,896.40 £18,050.40
Electric Car Charging Points £588,608.72 £332,143.49 £58,860.87
Milestones £0.00 £0.00 £0.00
Information Boards £0.00 £0.00 £0.00
Bike Parking Lockers £0.00 £0.00 £0.00
Bike Parking Stands £0.00 £0.00 £0.00
Automatic Trash Screens £0.00 £0.00 £0.00
Watercourse Telemetry £0.00 £0.00 £0.00
Weather Stations £0.00 £0.00 £0.00
Total £7,863,866.05 £3,967,106.97 £416,678.70 
6.4 Investment 
The street furniture asset consists of many different individual assets all of which deteriorate at different rates.
Generally assets deteriorate to the point where they stop performing their intended function and are replaced with new
items in line with available funding. Table 6.4 below provides an indication of the renewal cycle for some street
furniture assets based on previous year budget allocation and estimated asset renewal rates to calculate an indicative
renewal cycle based on current funding allocation. 
Table 6.4 Indicative Treatment Cycle for Asset Renewals 
Item 
Budget Allocation 
2019-20 
Current
Inventory Data 
Annual
Replacement
Quantity 
Indicative
Renewal cycle 
Cattle Grid  £24,000  162  1.6  101 
Traffic Signs  £52,000  5010  173  29 
Vehicle Safety
Fence 
£98,000  616289  653  94

Page 38

38 
6.5 Maintenance Backlog 
There is currently no condition data available for all street furniture assets to assess and calculate an accurate
backlog value. However a backlog estimate can be gauged from some of the major items and officer estimates.
Vehicle barriers condition previously reported in ASOR estimated investment need at circa £2.1m. This combined with
officer estimate for smaller assets at £0.9m provides an indicative value circa £3million maintenance backlog figure for
street furniture assets. 
6.6 Asset Data and Knowledge 
There is limited data available on the extent and condition of the street furniture asset. Many items were installed by
the previous Argyll County Council or district council. Over time and several restructuring processes for the authority
some data has not been retained or local staff knowledge lost due to retirements or redundancies. Consideration is
needed on developing a suitable maintenance strategy for this asset group particularly in terms of updating asset
data, inspecting and obtaining condition data and associated maintenance records. This will require resource and
appropriate investment however there may be scope to combine this with other asset groups needs to achieve better
value.  Acquiring and maintaining a reliable and robust database will enable future investments needs to be more
accurately calculated and the outcomes from same better able to support corporate objectives. This will ultimately
allow demonstration of a well-managed asset portfolio with investment tailored to asset needs and council aims. 
The SCOTS asset management project provides a range of tools and guidance to assist authorities implement better
asset management practices. The photos below illustrate the diverse nature of this asset group which can have many
bespoke items.

Page 39

39 
6.7 Electric Vehicle Charging   
Argyll and Bute Council currently has 28 public electric vehicle charging points which users
now need to pay for using. There is a growing demand for installation of more charging
points as electric vehicle numbers on our road network rise. This drives greater demand for
availability of charging points in line with customer expectations. The existing and proposed
new network installations will also require adequate maintenance aligned with regular
inspection regime to ensure charging points are functioning properly to meet growing
demand. This will require resource and budget moving forward and likely staff training due
to the specialist technical nature of the apparatus. 
Asset Inventory 
Type No.
Rapid  11 
Fast  10 
Unknown 7
Electric Vehicle 
Charging points 
Year Units
2017  4 
2018  3 
2019  8 
2020  1 
Planned Future Installation 
Year Type of  Unit 
Fast  Rapid 
2019-20  2  2 
2020-21 1  1 
2021-22  1  1

Page 40

40 
6.8 Weather Stations 
Argyll and Bute council operate and maintain a number of
weather stations situated in key locations to capture
weather data. The data includes road surface and air
temperature, rainfall, and other key climate monitoring
information. Some stations also have cameras that can
provide a visual history of conditions at these locations.
These stations provide vital information to officers
managing the winter maintenance operations across the
authority. The enable pre planned winter treatments to be
organised in advance of forthcoming sub-zero weather
conditions to ensure our roads are safe for road users
within the practicalities and resource limitations of service
delivery.   
6.9 Vehicle Restraint Systems
Barrier replacement and maintenance is underfunded and major investment is required across the whole network. It is
vital that the Council maintains and upgrades its safety/crash barrier and bridge parapet stock to ensure the safety of
road users.  
Policy, Assessment and Inspection processes need to be revised and at the moment we are currently reliant on
specialist contractors and consultants to maintain our barrier stock. 
Vehicle barriers – A general appraisal / condition survey of our
safety barrier inventory was carried out August / September
2015 (See Table below for Results) 
The survey identified almost 14km (18.5%) of barrier
considered to be in poor condition and requiring to be replaced
at an estimated cost of circa £2M. The barriers in poorest
condition and those that are Non -Compliant because of their
construction have been prioritised for replacement/repair
within the confines of existing revenue funding at circa
£100k/year since 2016/17. The replacement of our barrier
stock through utilising the current funding allocation will take
up to 20 years dependant on the locus.  
A follow up detailed survey to identify the condition of all
remaining safety barriers is being considered, to fully assess
and prioritise future necessary barrier maintenance and inform
the budget process. This is likely to require the assistance of a specialist consultant or contractor to deliver this initial
data gathering project.

Page 41

41 
The table below shows historical investment for each area.
District 2015-16 2016-17  2017-18  2018-19  2019-20  2020-21 2021-22
01 Mid Argyll £1,440 £27,322 £6,370 £18,011 £6,590 0 0
02 Kintyre 0 0 £43,959 £5,556 0 0 0
03 Islands 0 0 0 0 0 £22,467 0
04 Lorn £24,368 £15,112 £5,338 £25,136 £16,134 £57,290 £20,095
05 Mull £232 £8,006 £23,132 0 0 0 £18,375
06 Bute £475 £668 0 £110 0 0 0
07 Cowal £183 £11,209 £26,567 £23,257 £8,525 £5,298 0
08 Lomond £18,917 £31,214 0 £25,204 0 0 £20,397
Grand Total £45,615 £93,531 £105,366 £97,274 £31,249 £85,055 £58,867  
The photo below shows a new section of barrier erected at Kilmaha. 
The table below shows the results of the 2015 condition survey.

Page 42

42 
6.10 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options should be linked to
development of a long term maintenance strategy for the asset. 
Benefits Drawbacks Considerations
Continues service delivery for defects Continued long tern asset deterioration Adopting risk based approach to managing the asset
Growing demands for capital investment  Resource condition survey of asset to gain information on 
asset inventory, condition Etc.
Rising number of public liability claims  Development of long term maintenance strategy for the  
asset group
Reactive maintenance is expensive and poor 
value
Resource development of a prioritised list of planned 
works
Benefits Drawbacks Considerations
Investment tackles worst asset 
deterioration
limited asset information and condition data Implementing SCOTS asset management recommended 
practices
Planned works deliver better value  resources required to identify and quantify  
works
Current use, Is it needed? Can it be removed?
Reduced demand for reactive works Level of works limited within available revenue 
budget allocation
Resource development of a prioritised list of planned 
works
Less complaints Development of long term maintenance strategy for asset 
group
Benefits Drawbacks Considerations
Investment tackles deterioration and 
gradually improves whole asset
limited asset information and condition data Development of long term maintenance strategy for asset 
group
Demonstrates prudent stewardship of 
assets
resources required to identify scope of works Investment in mobile technology to capture asset data
Supports corporate objectives Requires increased levels  investment Implementing SCOTS asset management recommended 
practices
Benefits Drawbacks Considerations
Whole asset approach to maintenance requires substantial capital investment Use of SCOTS asset management tools
Requires significant improvement in asset data Investment in mobile technology
Deveolpment of appropriate maintenace strategy
Option 1  Undertake maintenance on a reactive basis to repair defects within existing revenue budget allocation.
Option 2      Increased investment in planned revenue maintenance activities
Option 3    Develop a business case for investment through capital budget for replacement of obsolete, damaged and deteriorated assets particularly 
vehicle safety barriers. Align the business case to a suitable long term maintenance strategy for the asset group.
Option 4   Business case development for capital investment in conjunction with other asset groups that aligns with the Road Asset management Plan 
(RAMP) and council priorities.

Page 43

43 
7.0 Climate Change and a Resilient Network 
Climate change is global but can be evidenced locally through more frequent severe weather events and greater
annual rainfall. This requires action to ensure drainage assets are functioning properly and have the capacity to deal
with these more regular events. Water is road infrastructures greatest enemy and is capable of destroying structures
and transportation links very quickly. Good drainage management is vital to protect valuable assets from the effects of
water. The illustrations below shows the affect standing water has on a newly resurfaced road over a relatively short
time as vehicles effectively pump the water into the surface accelerating the deterioration process. Lack of investment
in drainage assets impacts the outcome and benefits realised from the original resurfacing works undermining the
substantial investment made and incurring further avoidable expense in repair of the defect. 
Carbon Reduction
Sustainability through carbon reduction has never been more important in highway asset management, surface
treatments and the preparations works required on many roads can be delivered with significant savings in carbon
generation over traditional maintenance methods.
The Road Industry are now looking at how laboratory testing prior to road trials is enabling further investment into
surface treatments, how some companies are on their way to achieving net zero, the CO2 reduction benefits of road
maintenance will have positive effects on how road networks are effectively managed.
Argyll and Bute Council will monitor these treatments and intend to report back on what can be achieved in reducing
Carbon Emissions for our Road Network in future Annual Status and Options reports. 
Infrastructure projects and climate change strategies – Impact on local roads.
Major projects to improve the resilience of the electricity supply in Argyll and Bute, which has been partly driven by the
planned increase in renewable energy generation, risks damage and deterioration of our local road network. 
There are three distinct areas which are affected for differing reasons. However the outcome – rapid deterioration of
the fragile rural network - is liable to be similar.
1/ Power Line upgrades in Kintyre, Mid-Argyll, Lorn and sea connections to Islands. 
2/ Development of Cruachan PH2 and potential 1.5GW scheme south of Loch Awe.
3/ Developments on Islay, new Distilleries and parallel expansion of Bio-mass units.   
Powerline Upgrades

Page 44

44 
Works have previously been carried out between Carradale and Crossaig in Kintyre including a new sea connector to
Hunterston in Ayrshire and Inveraray to Port Ann Mid-Argyll to upgrade the major National Grid power line network
and associated electricity sub-stations.  Under the Electricity Act 1989, projects to improve the national grid are
considered to have “presumed consent” and the planning authority has little control over granting of works, to install
new pylon and cabling networks. Associated infrastructure such as upgraded electricity sub-stations are covered
under the local planning process, which gives the authority some leverage on the impact of these developments.
A programme of work is currently under way throughout 2022 to upgrade the Port Ann to Crossaig overhead lines and
also sections from Inveraray to Cruachan and Sloy power stations. Also delivered in 2022 were new sea connectors
at, Carradale to Arran and Mull to Coll. In all cases careful negotiation by officers was necessary to mitigate the risk of
damage to our fragile road networks and whenever practicable obtain financial contributions to the upkeep of the
network from the developer.
Development of Cruachan Power Station – Phase 2   600MW extension.
The original Cruachan Power Station is rated at 440MW with the proposed 600MW extension resulting in a combined
maximum power rating in excess of 1 GW. There is an anticipated volume of approximately 1 million cubic meters of
rock to be excavated for from the new generating hall cavern and associated tunnel network. Whilst a small proportion
of this rock will be used to form the new tunnel access working platform and re-alignment of the A85 Trunk Road past
the site, at the new power station entrance, the bulk of this material will be classed as “waste”. 
This volume of rock material could be used on several future coastal development improvements throughout North
Argyll and beyond. However a safe method of transport, which does not impact on the local road network would be
essential. There is also scope for local quarries to be utilised in the manufacture of products for the development,
however all of the local sites are on fragile roads and already subject to restrictions on volumes, through current
planning approval.
Isle of Islay - Expansion of Distilleries and associated Bio-Mass plants.
There are several recent or proposed new distilleries planned for sites on Islay, each of which will impact on the fragile
public road network. A recent development at an existing distillery at Bunnahabhain, has seen the installation of a Bio-
Mass boiler unit. At present (Nov 22) there is no direct local supply of timber or chip, with round timber being imported
by ferry and chipped onsite. This is causing considerable strain on the single track access road from the A847 and
A846. 
Should this short term supply issue be resolved and the true benefit of the Bio-Mass unit be realised, there is a
potential for more Bio-Mass units to be set up at other distilleries, either retrospectively or as part of new
developments. There is a risk that both at the harvesting end of the journey and the delivery to bio-mass unit end,
considerable damage may occur on single track roads, much of which are supported over peat bases and subject to
deflection and cracking of the bituminous surface. 
7.1 Investment

Page 45

45 
7.2 Condition 
The 2015 ASOR provided details of a sample drainage survey with results based on the SCOTS condition index. This
survey identified 53.9% of ditches on B, C & U Class roads required attention . 
7.3 Maintenance Backlog  
The ASOR 2015 provided a maintenance backlog figure for carriageway ditching based on results of the sample
survey. This clearly illustrated need for investment in road drainage management. Efforts are required to maximise the
effectiveness of available investment for cleaning or servicing assets and capturing data on maintenance records to
demonstrate prudent stewardship of assets. Reliable and robust data will properly inform the most efficient and
effective future management of drainage assets. This can enable a more data driven approach to be developed and
the optimum value maintenance programme delivered that aligns with asset needs and customer expectations. 
The estimated ditching maintenance backlog requires substantial funding to bring existing ditching assets to a good
condition standard. At current average spending this equates to a 15 year maintenance backlog timeline generally
exceeding the expected normal cleaning cycle. Sustained investment coupled with robust data collection and
coordinated maintenance activities is required to prioritise ditch cleaning to ensure roads are protected from damage
due to water ingress and flooding. 
7.5 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options should be linked to
development of a long term maintenance strategy for the asset.

Page 46

46 
-
Benefits Drawbacks Considerations
Provides budget savings Increase risk  to assets from storm events Improved data capture to inform decision making
Reduction in expected service life of road asset Review of existing drainage maintenance 
Does not support Flood Prevention Act Scotland 
(2009)
Explore options for implementing a more data driven 
approach
Increased reactive flooding costs  and complaints 
Benefits Drawbacks Considerations
Protects drainage budget allocation Does not provide adequate protection for assets Improved data capture to inform decision making
Continues to offer same level of asset 
protection
Lack of data to make informed choices Review of existing drainage maintenance regime
mitigates some risk from weather events Existing maintenance is generally driven by 
reactive needs rather pre‐planned programmes 
Explore options for implementing a more data driven 
approach
Contributes to Flood prevention Act Unable to clearly demonstrate prudent 
stewardship
Focus on improved record keeping to provide 
demonstrable service standards and identify areas for 
improvement
Benefits Drawbacks Considerations
Provides welcome investment Resources to develop work programmes and 
measurable outputs from captured data.
Investment in mobile data capture devices
reduces risk from weather events Potential technical difficulties for data capture Development of 3 ‐ 5 year work programmes
supports the Flood Prevention Act Requires leadership focus on achieving goals Review of existing drainage maintenance regime
commences a data driven approach Breaking vicious reactive maintenance cycle Development of a data management plan
Benefits Drawbacks Considerations
Enables improved service delivery Requires leadership commitment to deliver Exploring mobile technology options
Enables informed decision making Procurement of mobile technology devices Review options for a progressive staged implementation
Mitigates risks and delivers objectives in 
Flood Prevention Act
Initial resource to focus on revised delivery   
model and achieving change.  Development of data management plan
Enables a fully optimised drainage 
maintenance regime to achieve best value  Requires additional finance and resource Development of target service standards
Drainage improvements would contribute 
substantially to improving network 
resilience and arresting deterioration 
whilst extending asset service life.
Likely to require initial capital investment over 3 
years to bring assets up to standard and develop 
an asset management approach to drive         
continuous improvement.
Review of existing verge maintenance regime to enable 
support for delivery of improved drainage maintenance.
Option 1  Reduce existing budget allocation for drianage maintenance
Option 2     Maintain existing budget allocation for drainage maintenance
Option 3  Moderately increased investment in drainage maintenance based on measurable outputs aimed at improved service delivery
Option 4   Substantial investment in drainage maintenance based on implementing data driven approach through improved data capture in terms of 
inventory, condition, maintenance records Etc.