Council’s Economic Strategy Refresh 
Project Initiation Document 
Version 1.1 
Author:  Ishabel Bremner
Economic Growth Manager
(Key input from the Economic Strategy Refresh Officers’ Working Group)

Page 2

Project Initiation Document
Council’s Economic Strategy Refresh 
2
Contents: 
1. Project Initiation Document History
1.1 Document Location     3 
1.2 Revision History     3 
1.3 Approvals      3 
1.4 Distribution      3 
2. Introduction
2.1 Purpose of Document    4 
2.2 Background      4 
3. Project Definition
3.1 Aims and Objectives    4 
3.2 Project Scope     4 
3.3 Method of Approach    5 
3.4 Project Governance and Control   5 
3.5 Project Team – Roles and Responsibilities 7 
4. Project Deliverables and Associated Timescales 9 
5. Risk Log       11 
6. Key Stakeholders
6.1 Communications     12 
6.2 Stakeholder analysis    12 
7. Budget       13 
8. Quality Plan 
8.1 Quality Expectations    13 
8.2 Quality Criteria     13 
9. Project Controls
9.1 Control      13 
9.2 Configuration Management    14 
9.3 Tolerances      14 
9.4 Exception Process     14 
10. Acceptance Criteria      
10.1 Acceptance Criteria     14

Page 3

Project Initiation Document
Council’s Economic Strategy Refresh 
3
1. Project Initiation Document History 
1.1 Document Location 
This document is only valid on the day it was printed.
The source of the document will be found on the project manager’s PC in
location. 
1.2 Revision History 
Revision date Version No Summary of Changes   Changes marked
04/05/23 1.1 Completion of full PID,
including addressing
feedback from the Executive
Leadership Team meeting on
25/04/23
All sections of PID
now completed     
1.3 Approvals 
This document requires the following approvals. 
Name Signature Title  Date of
Issue
Version     
1.4 Distribution 
This document has been distributed to:- 
Name  Title Date of Issue Version
Fergus Murray Head of Development and
Economic Growth
04/05/23 1.1
Kirsty Flanagan Executive Director 04/05/23 1.1

Page 4

Project Initiation Document
Council’s Economic Strategy Refresh 
4
2. Introduction 
2.1 Purpose of Document 
The purpose of this Project Initiation Document (PID) is to:
a) To set out the aims, objectives and outcomes of the project.
b) To define the scope of the project.
c) Set out the workstreams, key stages, activities, resources and
responsibilities
d) Set out the arrangements for governance and management of risks,
issues and dependencies. 
2.2 Background 
A refreshed Argyll and Bute economic strategy must be ambitious for our area,
focused on priority actions, inclusive and developed from a solid and defensible
evidence base. Continued focus is required on the medium to longer-term
economic and social recovery agenda for Argyll and Bute in response to the
economic shocks of the last three years. In particular, the pandemic, EU Exit
and the cost of living, including the cost of doing business, crises. The strategy
should be forward looking, with a place-based and business/person centred
approach, to secure a fair, inclusive, and a prosperous future for the area, more
resilient to external factors including the rapid advances in technology and
increasing impacts of climate change. 
3. Project Definition 
3.1 Aims and Objectives 
To develop and deliver an economic strategy for Argyll and Bute that is
ambitious, targeted on our priorities, inclusive and forward looking. 
3.2 Project Scope 
The new Argyll and Bute Council Economic Strategy will be prepared with a
strong focus on collaborative working with partner agencies and stakeholders
across Argyll and Bute and externally. Highlands and Islands Enterprise (HIE) is
also reviewing its strategy. HIE has been invited to assist in the development of
this strategy as a critical delivery partner to ensure synergies and
complementary of the strategic direction and associated actions with the HIE
Strategy. The outcome will be the development of a deliverable strategy
matched to the available resources that will generate the desired impact.

Page 5

Project Initiation Document
Council’s Economic Strategy Refresh 
5
3.3 Method of Approach 
The project will be taken forward by an Officers’ Working Group (OWG) and
with input from an Industry Advisory Forum, both with clear terms of reference,
including regularly meetings and ongoing feedback to ELT and Policy Leads
throughout 2023 via regular highlight reports and committee reports as
appropriate. 
3.4 Project Governance and Control  
Role Resource Key Responsibilities and Activities
Political Input Elected members  To provide appropriate feedback and input
through Policy Lead and committee reports on
the economic strategy throughout 2023.
Project
Sponsor 
Executive Leadership
Team (ELT) 
 To be accountable for successful delivery of the
project:
 achievement of desired outcomes
 realisation of expected benefits
 Internal and external promotion of project
 Consideration and feedback on six weekly
highlight reports from the Project Manager
 Liaison with Senior Responsible Officer (SRO)
and Project Manager.
SRO and
Project
Manager
SRO: Fergus Murray,
Head of Development
and Economic Growth 
Project Manager:
Ishabel Bremner,
Economic Growth
Manager
 Chair Officer Working Group (OWG) meetings.
 Admin resource required - to be confirmed.
 Ensure OWG meets its remit.
 Ensure Argyll Economic Resilience Forum is
reinvigorated to become the Industry Advisory
Forum with clear terms of reference.
 Provide six weekly progress highlight reports to
ELT – Policy Lead and committee reports as
appropriate throughout 2023.
 Internal and external collaborative promotion of
the strategy development aligned to clear
community engagement and communication
plan/approach.
 To be accountable for successful delivery of the
economic strategy – the driving force behind it.
 Successful achievement of agreed deliverables
 Empowered to direct the project overall, to take
decisions and resolve escalated issues.
 To own the vision for the project. 
 To manage key strategic risks.

Page 6

Project Initiation Document
Council’s Economic Strategy Refresh 
6
Officers’
Working
Group
Membership:
Council Officers from
Development and
Economic Growth and
Community
Development 
HIE, Argyll and the
Islands, Area Manager.
 Provide visible leadership and commitment to
the Project. 
 Endorse and support the Project Manager on
an ongoing basis.
 Attendance at OWG to be held on a three
weekly basis throughout 2023 - if necessary,
nominate a proxy.
 Reach agreement of the PID and ongoing
update of plans.
 Provide all resources and facilities required for
the project – admin and financial support.
 Reach agreement of the milestone
achievements.
 Undertake regular reviews of scope and
identification of benefits to ensure the continued
alignment to business continuity and corporate
priorities.
Industry
Forum 
Meetings as and when
required throughout
2023. 
 It is proposed that the OWG reinvigorates the
Argyll Economic Resilience Forum to become
the Industry Advisory Forum, complete with
additional industry contacts as appropriate, to
complement the work of the OWG and help to
shape and influence the strategy’s direction and
development. 
 This will be concluded by the end of May 2023.

Page 7

Project Initiation Document
Council’s Economic Strategy Refresh 
7
3.5 Project Team – Roles and Responsibilities 
Role Resource Responsibility
SRO/Project
Manager
Staff time -
officers and
admin resource
 Overall management and first point of
contact.
 To operationally manage the project, co-
ordinating and delivery of all project
products.
 Ongoing project planning and management.
 Six weekly highlight reports to ELT for
consideration and feedback.
 Policy Lead and committee reports as
appropriate throughout 2023.
 To operate the governance framework,
including management of benefits,
stakeholders, risks and issues, resources,
quality, planning and control.
 Develop and issue work packages.
Officers’ Working
Group
Staff time –
officers and
admin resource
and finance for
third party
support to be
considered as
appropriate.
 Develop a refreshed Argyll and Bute
Economic Strategy that is ambitious for our
area, focused on priority actions and
developed from a solid and defensible
evidence base. The strategy should be
forward looking, with a place-based and
business/person centred approach, to secure
a fair, inclusive, and a prosperous future for
the area, more resilient to external factors
including the rapid advances in technology
and increasing impacts of climate change.
 Focus on the medium to longer-term (next
five to ten years) economic and social
recovery agenda for Argyll and Bute in
response to the economic shocks of the last
three years. In particular, the pandemic, EU
Exit and the cost of living, including the cost
of doing business, crises.
 Develop an associated Action Plan
(reviewed annually) to include the
requirement to monitor and evaluate the
performance and impact of the Economic
Strategy over time.
 Foster collaboration and a joined-up
approach to the strategy’s preparation,
working closely with the Community
Development Team who are currently

Page 8

Project Initiation Document
Council’s Economic Strategy Refresh 
8
Role Resource Responsibility
revising the Local Outcome Improvement
Plan on behalf of the Argyll and Bute CPP,
partner agencies and stakeholders across
Argyll and Bute and externally.
 Re-invigorate the Argyll Economic Resilience
Forum to become the Industry Advisory
Forum, to complement the work of the OWG
and help to shape and influence the
strategy’s direction and development.
 Share and communicate information with the
ELT through six weekly highlight reports,
with elected members through ongoing
committee papers, the first going to the EDI
Committee, 1st June 2023 and ongoing
updates with relevant Policy Leads and CPP
Strategic Partners, as appropriate. Feedback
sought on key development milestones.
 Share consultation/engagement/
communication approach and events with
that for the Local Outcome Improvement
Plan (LOIP).

Page 9

Project Initiation Document
Council’s Economic Strategy Refresh 
9
4. Project Deliverables and Associated Timescales 
Deliverable Estimated
completion date
Responsibility
Project Inception and Engagement
Stage 1: Establish the Officers’
Working Group (OWG) and Industry
Advisory Forum with clear terms of
reference – to meet regularly, with
ongoing feedback to ELT and Policy
Leads throughout 2023.
End of May 2023 Project Manager
Stage 2: OWG gathering of an
evidence base – feed in
repopulation analysis and
Community Development survey
sense of direction (consideration
given to commissioning consultancy
support aligned to specific stages of
work e.g. collaborative community
engagement and communication).
End of May 2023 Officers’ Working Group
Outcome Stages 1-2: Initial
Baseline End of May 2023 Officers’ Working Group
Strategic Pillars/Objectives and Priorities
Stage 3: OWG preparation of draft
pillars/objectives, priorities and
SWOT analysis.  End of June 2023 Officers’ Working Group
Stage 4: Shared consultation/
engagement/communication events
for strategy and LOIP –
pillars/objectives, priorities and
SWOT to understand drivers of
outcomes and impacts.
End of June 2023 Officers’ Working Group
Stage 5: Identify ways to prioritise
and/or target interventions to create
and enable an ambitious wellbeing
economy.
End of June 2023 Officers’ Working Group
Outcome Stages 3-5: Agreed
Strategic Pillars/Objectives and
Priorities
End of August 2023 Officers’ Working Group
Further Consultation, Engagement, Communication and Prioritisation
Stage 6: Further deep dive and
meaningful engagement – by
themes and appropriate
geographical areas. 
End of August 2023 Officers’ Working Group

Page 10

Project Initiation Document
Council’s Economic Strategy Refresh 
10
Deliverable Estimated
completion date
Responsibility
Stage 7: Map out the prioritised
policies, projects and programmes
to be delivered in an Action Plan.
End of September
2023 Officers’ Working Group
Stage 8: Further consultation &
engagement and communication on
the associated Action Plan
complete with a measurement
framework, with clear outcomes &
impacts.
End of September
2023 Officers’ Working Group
Outcome Stages 6-8: Draft
Economic Strategy for Senior
Management scrutiny End of October 2023 Officers’ Working Group
Finalise Economic Strategy and Associated Action Plan
Stage 9: Preparation of EDI
Committee paper. End of November 2023 Project Manager/Officers’
Working Group
Stage 10: Address pre- agenda
commentary on Economic Strategy.  End of November 2023 Project Manager/Officers’
Working Group
Outcome Stages 9-10: Final sign off
of the Economic Strategy by the
EDI Committee End of December 2023 EDI Committee

Page 11

Project Initiation Document
Council’s Economic Strategy Refresh 
11
5. Risk Log 
Ref  Risk Area of Risk Inherent  Inherent  Inherent Risk Mitigation Residual  Residual Residual Actions Planned      
risk risk Risk per Procedures/Controls risk risk Risk per        
Impact Probability  matrix in place Impact Probability  Matrix        
(1-3) (1-3) (1-9)   (1-3) (1-3) (1-9)  
1 Delivery
Significant
slippage in
timescales and
stages.
2 3 6
Establish Officers’
Working Group (OWG)
Inaugural meeting on
4th May discussed the
terms of reference,
future meetings,
governance framework
agreed at ELT,
required third party
support and
reinvigoration of the
Argyll Economic
Resilience Forum to
become the Industry
Advisory Forum.
2 1 2
OWG has put in place a clear
terms of reference (inc.
governance framework – see
section 3.5) and a programme
of meetings throughout 2023 to
ensure that a refreshed
Economic Strategy and
associated Action Plan is
finalised for delivery from early
2024 to 2029. 
2 Financial
Securing a
budget to take
forward
required
external
support.
2 3 6 Discussed at OWG on
4th May 2023. 2 1 2
A detailed budget plan will be
prepared and submitted in due
course

Page 12

Project Initiation Document
Council’s Economic Strategy Refresh 
12
6. Key Stakeholders 
6.1 Communications and Community Engagement   
Communications/engagement will be managed by the OWG in close liaison with the Community Development Team. It will be
the responsibility of the OWG to ensure a regular flow of informative and timely communications to all stakeholders.   
The OWG will use already identified communication/engagement frameworks/toolkits and online mechanisms as a means for
undertaking wider communication and consultation. This will be aligned with the communication/community engagement
schedule for the revised LOIP and the work of the council’s new Community Engagement Strategy Group. Members of the
OWG sit on the Community Engagement Strategy Group. 
6.2 Stakeholder analysis 
To shape and influence the strategy’s direction and development will require engagement and communication with a number
of key stakeholders. The OWG has identified some initial stakeholders, as listed below, and this will feed into ongoing
discussions on the appropriate mechanism/varying approaches to gather feedback from specific stakeholders/organisations. 
Stakeholders are as follows:
 Residents/communities of Argyll and Bute
 Inward investors across key sectors e.g. whisky, renewables, tourism, etc.
 Local businesses
 Visitors to Argyll and Bute
 CPP strategic partners
 Elected members
 Community Councils
 Third sector organisations/trusts/social enterprises, etc.
 Utility providers.

Page 13

Project Initiation Document
Council’s Economic Strategy Refresh 
13
7. Budget 
A detailed budget plan will be prepared and submitted in due course. 
8. Quality Plan 
8.1 Quality Expectations 
Approach  In accordance with best value principles 
Deliverables  The Project Manager and SRO will be responsible for assuring
the quality and availability of the project products and the
documentation underpinning the project.
Consultation Consultation with stakeholders must be comprehensive and
facilitated by use of methods to record, quantify and analyse
the outcomes of such consultation.
Standards Prince2 is the standard project management methodology
employed throughout the project.
Installed equipment should meet relevant Industry Standards
for safety and design and be accompanied by relevant
certificates and documentation. 
8.2 Quality Criteria 
Project documentation will be in a consistent format using standard templates
and configuration management rules within shared directories. 
Every work package issued will specify the acceptance quality criteria. Subject
matter experts will be consulted in the development and completion of key
products. Customer input will be sought wherever possible on customer facing
elements. 
9. Project Controls 
9.1 Control 
SRO/Project Manager will hold regularly meetings with the OWG to review
progress against plan. A six-weekly highlight report will be presented at ELT
meetings.

Page 14

Project Initiation Document
Council’s Economic Strategy Refresh 
14
9.2 Configuration Management 
The Project Manager will be responsible for version control. The Project
Manager will ensure that a library of project products, records of meetings,
technical documentation and any other relevant documentation will be held in
dedicated MS Teams space for access by all OWG members. 
9.3 Tolerances 
Once the PID has been agreed the following tolerances will apply: 
Time:
Delay of project project milestone of more than one week must be reported by
the project manager to the SRO.
Delay of a project milestone of more than three weeks must be reported to ELT. 
Cost:
Increase in project costs (once budget agreed) by more than 10% must be
reported to ELT. 
9.4 Exception Process 
If the timescales or cost of the project is likely to exceed the agreed tolerance
levels, the Project Manager will produce an exception report which will be sent
ELT. All Change Requests will be submitted as Exception Reports. 
The Exception Report will include:
 A description of the cause of the deviation from plan.
 The consequences of the deviation.
 The available options.
 The effect of each option on the business case, risks, project and stage
tolerances.
 The Project Manager’s recommendations.  
10. Acceptance Criteria 
10.1 Acceptance Criteria 
The criteria for acceptance of the project are the delivery and sign off of all the
deliverables to the satisfaction of the ELT and finally by the EDI Committee in
December 2023.