1.0 EXECUTIVE SUMMARY 
1.1 The Council has in place a 25 year Waste PPP contract with Renewi which
ends in September 2026. The waste PPP contract covers Oban and Lorn,
Mid Argyll and Kintyre, Bute and Cowal together with the inner islands. The
contract provides a disposal solution for general waste through a
Mechanical Biological Treatment (MBT) process, with residual waste being
landfilled. The contract also provides a transfer facility and haulage for co-
mingled recycling. 
1.2 Scottish Government are due to introduce a Biodegradable Municipal
Waste (BMW) landfill ban from the end of December 2025.  The last 9
months of the PPP 25 year contract will not be compliant with the new
regulation. 
1.3 This report provides the Environment, Development and Infrastructure
Committee (ED&I) with an update on the Waste PPP, and information
relating to the continuation of engagement with Scottish Government
regarding the derogation. Further discussion is taking place with Renewi
as part of the considerations of the options appraisal (options noted below)
reported to ED&I in December 2022. 
RECOMMENDATIONS 
It is recommended that the Environment, Development and
Infrastructure Committee:-   
Consider and endorse the content of this report and that further
updates will be provided for September ED&I Committee.

Page 2

ARGYLL AND BUTE COUNCIL    ENVIRONMENT, DEVELOPMENT
& INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE SERVICES       1 JUNE 2023 
WASTE PPP UPDATE   
2.0 INTRODUCTION 
2.1 This report provides an update on Waste projects and engagement taking
place with Scottish Government and Renewi following report presented to
ED&I committee on 1st December 2022. 
3.0  RECOMMENDATIONS
3.1 Consider and endorse the content of this report and that further
updates will be provided for September ED&I Committee.     
4.0  DETAIL 
4.1  The December ED&I report recommended two options for pursuance
which are noted below and being progressed by Officers. 
 Option 3 – request a time limited derogation from the Scottish
Government for the Waste PPP area from 1st January 2026  -
September 2026 for the municipal solid waste landfill ban which is
due to be implemented from 1st January 2026. The Council has
formally written to the Scottish Government regarding this request. 
 Option 4 – commence PPP contract discussions with Renewi
(Waste PPP Contractor) regarding landfill ban compliance from 1st
January 2026, should a time limited derogation not be granted by
The Scottish Government. The Council has commenced such
discussions with Renewi and this process in on-going.
4.2  Argyll and Bute Council Officers have engaged with Scottish Government
officials regarding the request for a 9 month derogation to coincide with the
Renewi contract end date of 2nd September 2026. 
4.3  The Council Leader has been engaging with the relevant Scottish
Government Minister to formally discuss the possibility of a time limited
derogation. The Council Leader received communication stating that the
Minister would meet with the Council Leader and Argyll and Bute Council
officials. However, this original arrangement has now changed and

Page 3

Scottish Government have approached the Scottish Environment
Protection Agency (SEPA) asking for their view on the December ED&I
report and options appraisal. The purpose of the derogation is to align the
introduction of a BMW compliant solution with the natural end of the PPP
contract in September 2026, a delay of 9 months. 
4.4  Regardless of the derogation request being successful or not it is intended
that the islands and the Helensburgh and Lomond areas, out with the PPP
contract, would become BMW ban compliant from 1 January 2026.
4.5  Officers have engaged with Renewi through workshops regarding potential
changes to the current contract to be compliant with the landfill ban, this is
notwithstanding the infrastructure changes required to accommodate the
ban implementation date, Renewi have been advised accordingly and
funds set aside for the conversion of the MBT plants at Dalinlongart,
Lingerton and Moleigh. The Council has set aside £3.5m for the
development of a Waste Transfer Station in Helensburgh and the
conversion of three MBT plants at the aforementioned sites to Waste
Transfer Stations.  
4.6  Members should note that we are not in a position to ask for a decision on
the options proposed within the December ED&I report until such a time
that a decision has been given by either Scottish Government or SEPA
regarding the derogation. A further report will be taken to ED&I in
September on the position at that time to allow Members to take an
informed decision.   
4.7  Officers continue to progress all Waste related matters and have noted
below the next steps that are being taken with regard to the Waste PPP
contract. 
 To seek to obtain a derogation from the Scottish Government, of
limited term and scope, from the implementation date of 1st
January 2026, with officers and the Council’s political leadership
working together to engage the Scottish Government at officer
and Ministerial level in this regard;  
 Continue to engage with Renewi to ensure that there is a suitable
alternative  for landfill ban compliance should Scottish
Government not agree to a derogation;
 Bring forward a further report to the ED&I committee in
September 2023 at which time Members would make a final
determination on the aforementioned two points;  
 In the event of a derogation not being forthcoming, the Council
engage with Scottish Government to seek funding for this
additional burden and the additional high costs which would be
incurred by the Council.

Page 4

5.0 CONCLUSION
5.1 In concluding this report, officers will continue to engage with Scottish
Government and Renewi to enable a report to be presented to ED&I
committee in September 2023. At this time, it is hoped that the authority
should have a definitive response on whether a derogation will be made
available to us or whether the option is to continue pursuance of
compliance with Renewi for the introduction of the BMW landfill ban and
alterations made to infrastructure on the three main sites, Dalinlongart,
Lingerton and Moleigh. 
6.0 IMPLICATIONS
6.1 Policy – The council’s waste strategy will evolve in line with the changes
in legislation relating to the BMW ban of waste to landfill. A derogation
will be sought, failing a successful response the current Renewi contract
will be varied to comply with legislative changes.     
6.2 Financial – Compliance with the 2025 Landfill ban will require financial
resource and capital funds were set aside as part of the budget in
February 2023. As the Scottish Government are initiating the change,
we should continue to pursue financial support from the Scottish
Government for this change to provide a long-term financially
sustainable solution.   
6.3 Legal – The existing PPP contract was not designed or written to
accommodate the changes that the 2025 legislation will require. The
contract allows variations to be made although the process is quite
cumbersome. There will be legal implications, which will need to be
resolved, relating to a contract variation relating to the derogation and/or
changes in Renewi’s contract. 
6.4  HR – HR issues will be addressed prior to and during the process of
contract handback. Having sufficient resource will factor into the project
demands of waste management. TUPE will be relevant at the handback
and during the process of progressing to handback should the Council
operate the sites themselves. 
6.5  Fairer Scotland Duty:   
6.5.1   Equalities - protected characteristics – None
6.5.2   Socio-economic Duty – None
6.5.3 Islands – There may be potential ferry capacity issues for
bulking and transporting waste material from islands, this has been
highlighted to Transport Scotland.   
6.6  Climate Change – Transitioning from Landfill to Energy from Waste
would result in a reduction in the annual quantity of Greenhouse Gas
Generated in Argyll and Bute. However, the additional road miles

Page 5

incurred taking waste to EFW markets will offset the carbon reductions
achieved through not landfilling. 
6.7 Risk – There are financial risks associated with no Scottish
Govrenment with a derogation. This was noted within the December
ED&I report.   
6.8  Customer Service – None. 
Kirsty Flanagan, Executive Director with responsibility for Road and
Infrastructure Services 
Jim Smith, Head of Road and Infrastructure Services 
Councillor Ross Moreland, Policy Lead for Climate Change and
Environment Services 
For further information contact: 
John Blake - Fleet, Waste & Transport Manager 
john.blake@argyll-bute.gov.uk