Page 1

ARGYLL AND BUTE COUNCIL                    ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             1 JUNE 2023
SERVICES                     
LOCAL BRIDGE MAINTENANCE FUND 
1.0 INTRODUCTION 
1.1 This report provides an update on the £5.450M of funding secured through a
highly competitive bid process from Scottish Government’s £32million Local
Bridge Maintenance Fund. 
1.2 At the Environment, Development and Infrastructure Committee held in June
2022 a report was presented detailing the funding award for the replacement of 4
bridges and strengthening of a further 5. Since then negotiations regarding land
(for new bridges), ground investigation and design work has been progressing
well. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee endorse the programme of bridge works. 
3.0 DETAIL 
3.1 The fund will be used to undertake proportionate works (from strengthening to
comply with ‘construction and use’ weight limits to full off-line rebuilds) on
bridges in need of repair, identified through our inspection programme/ records.
Bridges provide critical transport (often lifeline) connections for some
communities and are a vital part of the wider road network. 
3.2 The table below details the list of bridges which have received funding along with
indicative key dates. 
Bridge Name Grant
Amount
Site Start
Date
Estimated
Completion
Date
1 B840-140 Archonnell Bridge £40,000 Sep 23 Jan 24
2 B842-010 Claonaig Bridge £477,000 Jan 24 May 24
3 A815-230 Cothouse Bridge £517,000 Aug 23 Jun 24
4 A846-270 Glenegedale (2) £597,000 Jun 24 Dec 24

Page 2

3.3 Location plans for each bridge in the table above are in Appendix 1. Regular
updates on these works as they progress will be provided through our weekly
members briefing. 
3.4 Description of the works proposed: 
3.4.1 - B840-140 Archonnell Bridge 
Additional retaining buttress structure constructed on downstream face
of existing bridge. 
3.4.2 - B842-010 Claonaig Bridge 
Strengthening of wing walls, realignment of road, waterproofing, and
drainage works. 
3.4.3 - A815-230 Cothouse Bridge 
Installation of deck waterproofing system (under road surface),
installation of new expansion joints, joint sealings, concrete repair
works, drainage works, vehicle barrier partial replacement, vegetation
removal 
3.4.4 - A846-270 Glenegedale (2) 
Full bridge replacement (with footway) in same location. 
3.4.5 - B844-010 Kilninver Bridge 
Full bridge replacement (with footway).  Options Appraisal Report (due
shortly) shall determine preferred alignment. 
3.4.6 - B839-050 Lochgoilhead Bridge 
Strengthening of arch barrel, including waterproofing, temporary traffic
diversion and drainage works. 
3.4.7 - A816-120 Oude 
Full bridge replacement (with footway) upstream / northwards.  Options
Appraisal Report (due shortly) shall determine preferred alignment. 
3.4.8 - A849-280 Pennyghael Bridge 
Full bridge replacement (with footway) downstream / seawards. 
Options Appraisal Report (due shortly) shall determine preferred
alignment. 
3.4.9 - B842-150 Whitestone Bridge
Additional retaining buttress structure constructed on downstream face
5 B844-010 Kilninver Bridge £1,194,000 Aug 24 Aug 25
6 B839-050 Lochgoilhead Bridge £198,000 Apr 24 Mar 25
7 A816-120 Oude £1,194,000 Mar 25 Aug 26
8 A849-280 Pennyghael Bridge £1,193,000 Aug 24 Jul 26
9 B842-150 Whitestone Bridge £40,000 Nov 23 Mar 24
Total £5,450,000

Page 3

of existing bridge. 
3.5 Legislation, Standards, Codes of Practice:
Replacement (new) structures are designed in accordance with: 
 Roads (Scotland) Act 1984 Legislation
 Design Manual for Roads and Bridges (DMRB) document “CD 350 -
The design of highway structures” and associated document series
“Highway Structures & Bridges”
 “CIHT 'Well-managed highway infrastructure' Code of Practice” Section
C6 and associated documentation. 
Strengthening (maintenance) works to structures are designed, where
appropriate, in accordance with:
 Roads (Scotland) Act 1984 Legislation
 Design Manual for Roads and Bridges (DMRB) document series
“Highway Structures & Bridges”
 “CIHT 'Well-managed highway infrastructure' Code of Practice” Section
C6 and associated documentation. 
4.0 CONCLUSION 
4.1 This report provides an update on the £5.450M of funding secured in highly
competitive bid process from Scottish Government’s £32 million Local Bridge
Maintenance Fund. 
5.0 IMPLICATIONS 
5.1 Policy – projects are being taken forward to align with key policies like the Local
Outcome Improvement Plan and the Roads Asset Management Plan. Bridge
designs in terms of strength and resilience are required to follow nationally set
construction specifications. 
5.2 Financial – funded from grant funding. The successful award of grant funding
helps to reduce the backlog maintenance figure for the Council’s transport
infrastructure. 
5.3  Legal – the Council has statutory duties to maintain infrastructure set out in
various legislation like the Roads Scotland Act 1984.   
5.4  HR – None known.   
5.5  Fairer Scotland Duty: None known.   
5.5.1   Equalities - protected characteristics – an EqSEIA will be completed which
tease out and identify any equality issues which need to be considered. 
5.5.2   Socio-economic Duty – None known.

Page 4

5.5.3 Islands – the programme will bring benefits to island communities which will
see two bridges being replaced which will help provide additional resilience to
the islands transportation infrastructure. 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  The provision for pedestrian facilities will be included as part
of the design for new build bridges together consideration for the projected
increase in sea levels due to climate change. 
5.7  Risk – None known. 
5.8  Customer Service – None known. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Head of Roads and Infrastructure – Jim Smith 
Policy Lead for Roads and Transport: Councillor Andrew Kain  
April 2023                                                  
For further information contact: 
Elsa Simoes – Infrastructure Design Manager or Jim Smith, Head of Roads and
Infrastructure Services 
Appendices:
Appendix 1 – Bridge location plans