ARGYLL AND BUTE COUNCIL                    ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             1 JUNE 2023
SERVICES                     
ROUTE OPTIMISATION UPDATE 
1.0 INTRODUCTION 
1.1 The purpose of this report is to provide Members with an update on the
development of the route optimisation project following the report to this
Committee on the same subject in March. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
 Note the progress with the Route Optimisation project;
 Agree that a Member Seminar will be arranged in the Autumn to
present the system and possible scenarios; and 
 Note that a further update report will be brought back to the December
Environment, Development and Infrastructure Committee meeting.   
3.0 DETAIL 
Background 
3.1 The Council has appointed Webaspx, a leading waste management software
solutions company, to provide us with a route optimisation solution, following
an open tender process which ran in 2022. 
3.2 A £100,000 budget was previously approved for this project. The funding can
be used to fund the start-up costs and a large part of the first year software
support, with the remaining software support costs being absorbed within
current budgets.  The contracted upfront costs are approximately £70k with an
annual service cost of approximately £50k. The contract is a rolling contract
for up to 5 years. It is anticipated that Co2 savings will be made which will not
be known until after full implementation. 
3.3 As the project develops we will consider options for funding the remainder of
the agreed 5 year contract, potentially based on efficiencies realised as a

Page 2

result of having the system in place. 
Progress 
3.4 Since the report to the Environment, Development and Infrastructure
Committee in March, the project is now underway, using the Council’s normal
project governance methodology. The Head of Roads and Infrastructure is the
Senior Responsible Officer for the project, and a project team with officers
from across the Council has been established and meets on a weekly basis.
Different levels of input will be required from officers across the lifetime of the
project – there is no specific dedicated resource working exclusively on route
optimisation. 
3.5 In line with good practice for contract management, regular meetings are in
place between Webaspx and the Council’s Project Team. The project will go
forward in phases. The first phase is setting up the Easy Route software,
creating the detailed digital model of our road network, our domestic bin
collection, disposal operation and is being reported as Phase One. Thereafter
there will be a second phase to set up and utilise the in-cab or Digital Depot
technology and to consider how this integrates with existing customer service
systems. 
3.6 The below provides Members with an indicative outline works programme for
Phase One: 
Route optimisation Phase One – Easy Route software
Title Description Date Status
Inception
Inception meeting Agree
requirements/
constraints/
deadlines
March 2023 Complete
Data
Roads OS data on road
network 
April 2023 Complete
Properties UPRN information
on all 48,000
households
April 2023 Complete
Routes Uploading existing
bin route
information
April 2023 Complete
Resources Information on
vehicles to cross
reference with
route and property
data
April 2023 Complete
Performance Weighbridge
information from
the different off-
takers
April 2023 Complete

Page 3

Merging data  Cleansing and
formatting various
data sets
May 2023 Ongoing at the
time of writing
Model development and review
Initial build Webaspx build
software
installation of
EasyRoute
May 2023 On track
Training ABC staff training June 2023 On track
Model as-is routes Create calibrated
models of current
collections across
all areas
June 2023 On track
Review as-is
routes
Ensure As-Is
models reflect
current collections
July 2023 On track
Tactical modelling Model routes and
other options
against different
scenarios
August 2023 On track 
NOTE: possible
Member Seminar
at this stage
Review tactical
modelling
Review
remodelled routes
September 2023 On track
Operational
modelling
Create fully
implementable
model(s) for each
scenario 
October 2023 On track
Operational review Review and revise
possible new
designs
October 2023 On track
Decision gateway
Decision stage Determine next
steps and lead in
to Phase Two
December 2023 On track 
4.0 CONCLUSION 
4.1 The new route optimisation system is a powerful tool and, once built will
provide opportunities to model different options, with this firstly being used for
the bin collection routes.  Revised routes will be able to be planned in a few
hours whereas this currently can take several weeks due to the complexity of
the modelling.   
4.2 The initial data upload, review, cleansing stage is very much an iterative
process that requires a reasonable resource commitment from the Council,
particularly given the different waste models used across the area.

Page 4

5.0 IMPLICATIONS 
5.1 Policy – There are no direct policy implications arising from this report.   
5.2 Financial – This project is funded from a previous funding allocated by the
Council. 
5.3  Legal – None known. 
5.4  HR – None known.   
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – works from this project will be
accompanied by a socio and economic impact assessment.   
5.5.2   Socio-economic Duty – none arising from this report.  
5.5.3 Islands – this project will look at both the mainland and islands and there is
not deemed to be any adverse impact to island communities from this work.   
5.6 Climate Change – There is potential to reduce the mileage covered by some
vehicles, which would help to work towards reducing the Council’s carbon
footprint.  It is anticipated this will result in CO2 savings however this will not be
fully known until the system is fully implemented. 
5.7  Risk – None arising from this report.   
5.8  Customer Service – None arising from this report.   
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Head of Roads and Infrastructure: Jim Smith 
Policy Lead for Roads and Transport: Councillor Andrew Kain   
May 2023                                                  
For further information contact: 
Mark Calder, Project Manager
Mark.Calder@argyll-bute.gov.uk