Roads Capital Programme - Member Engagement

Argyll and Bute Council · 1 June 2023
Back to Environment, Development and Infrastructure Committee — 1 June 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL                    ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             1 JUNE 2023
SERVICES                     
ROADS CAPITAL PROGRAMME – MEMBER ENGAGEMENT 
1.0 INTRODUCTION 
1.1 This report sets out proposals for additional Member and Area Committee
engagement for the development of the annual roads capital programme.   
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee endorse the proposals for additional Member and Area
Committee engagement in the roads capital programme.   
3.0 DETAIL 
3.1 The roads capital programme is informed using the Road Condition Index which
is produced via a machine based survey measuring over 30 attributes of the roads
condition. The Council’s Annual Status and Options Report produces an analysis
of road condition, which has shown a small but steady improvement in condition
over the last few years. This has largely been achieved by the level of investment
made available and by developing a programme based on:- 
 Information from machine based surveys (RCI) etc
 Safety related information from Police Scotland from killed and
seriously injured collisions (KSIs)
 Economic and tourism opportunities
 Known developments and additional traffic
 Information from Members
 Engineering judgement
 External funding opportunities 
 Information from communities 
3.2  Over the last 12 years the Council has invested over £86M in roads reconstruction
including some £9M from the Strategic Timber Transport Fund. This has provided
an average annual investment of just over £7M per year. This level of investment
has seen a slow but steady increase in road condition, although, it should be noted
that there is approximately £120M worth of backlog road maintenance meaning

Page 2

that we are unable to treat every section of carriageway which we would ideally
like to do. The roads capital programme is progressed with a view to providing the
best level of return from the available investment, taking into consideration the
various inputs detailed in paragraph 3.1, whole life costs and value for money. 
3.3  Audit Scotland produced a report on ‘Maintaining Scotland’s Roads’ in 2011
where they stated “Scotland’s roads are important for economic prosperity and
for the quality of life of its people”. Similar statements have been made by Audit
Scotland in subsequent audit reports. 
3.4  A member seminar was held on 17 January 2023 to provide an overview of
roads asset management. The presentation covered survey methods, backlog
maintenance, investment modelling, scenarios based on different investment
levels/treatment types, Road Condition Index, and how programmes are
developed and implemented. The presentation can be viewed in the Members
area on the Hub here:- ELECTED MEMBER SEMINARS 2023 | The Hub 
3.5  At the members seminar, introducing further member engagement into the
process of developing the roads capital programme, through a series of area
based Business Day meetings was discussed. The table below sets out how we
propose to implement this into the process timeline.   
Action Date
Road Condition Index data received Generally late
summer but dates
can vary
Scheme Manager produces initial list of
schemes for consideration
September/October   
Initial lists are reviewed by officers against
KSI collision data, engineering judgement
etc. 
September/October 
Initial draft programme prepared and shared
with Elected Members for comments/input
October 
Draft programmes are considered by Area
Committees
December
Budget confirmed at February Budget
meeting and programme adjusted based on
investment
February
Programme considered by EDI Committee March
Agreed programme confirmed to all
members and made available to public
March 
3.6 The Member engagement will provide an additional opportunity for Members to
discuss and comment on the programme whilst it is being developed. The
framework for developing the programme is set out at a high level in paragraph
3.5 and takes into consideration numerous factors. The final draft programme will
be reported the Environment Development and Infrastructure Committee at its

Page 3

March meeting. Following approval by the Environment, Development and
Infrastructure Committee, the programme will be issued to all Members on an
Area Committee basis. The programme will also be publicised on the Council
website. 
3.7 As in previous years, it is possible that changes will require to be made to the
programme following publication.  This is to take into account winter deterioration,
however any changes will be reported to Members. 
3.8 Updates on the Capital programme will be available on our website and also
through our weekly members briefings. 
4.0 CONCLUSION 
4.1 This report proposes formalising member engagement to the process of
developing the Roads Capital Programme to incorporate member engagement. 
5.0 IMPLICATIONS 
5.1 Policy – There are no direct policy implications arising from this report – Member
engagement will provide an additional opportunity for Members to discuss and
comment on the programme whilst it is being developed.   
5.2 Financial – capital funding allocation. 
5.3  Legal – the Council has statutory duties to maintain infrastructure set out in
various legislation like the Roads Scotland Act 1984. 
5.4  HR – none known. 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known.
5.5.2   Socio-economic Duty – none known.
5.5.3 Islands – none known. 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.   
5.7  Risk – none known. 
5.8  Customer Service – none. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan

Page 4

Policy Lead for Roads and Transport: Councillor Andrew Kain   
May 2023                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services