MINUTES of MEETING of ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
COMMITTEE held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY,
LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 2 MARCH 2023 
Present: Councillor Andrew Kain (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Garret Corner
Councillor Mark Irvine
Councillor Donald Kelly
Councillor Jim Lynch
Councillor Tommy MacPherson 
Councillor Ian MacQuire
Councillor Luna Martin
Councillor Ross Moreland
Councillor William Sinclair
Councillor Andrew Vennard
Councillor Peter Wallace 
Attending: Kirsty Flanagan, Executive Director
Jim Smith, Head of Roads and Infrastructure Services
Fergus Murray, Head of Development and Economic Growth
Stuart McLean, Committee Manager
Hugh O’Neill, Network and Standards Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillor Robin Currie. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest intimated. 
3. MINUTES 
The Minutes of the meeting of the Environment, Development and Infrastructure
Committee held on 1 December 2022 were approved as a correct record. 
Councillor Luna Martin joined the meeting during the consideration of the following item of
business. 
4. ROADS RECONSTRUCTION CAPITAL PROGRAMME 
The Committee gave consideration to a report providing details on the proposed roads
reconstruction programme for 2023/24.  The programme was based on the 2023/24
allocation of a total of £8.0M, which included £754k brought forward from 2022/23. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. endorsed the proposed programme of capital works for 2023/24; 
2. agreed that details of each area committee’s programme would be forwarded on to
individual Elected Members;

Page 2

3. noted that following the budget decision on 23 February 2023, a programme of footway
works would be presented to a future meeting of the Environment, Development and
Infrastructure Committee. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated February 2023, submitted) 
5. ANNUAL STATUS AND OPTIONS REPORT 2022 
The Committee gave consideration to a report introducing the Annual Status and Options
Report which set out an analytical assessment of the condition of the Council’s road
network and associated infrastructure as well as setting out projected conditions based on
varying levels of investment. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. endorsed the Annual Status and Options Report and the positive analytical feedback it
provided; and 
2. noted that the Annual Status and Options Report informs key elements of the
Development and Infrastructure Asset Management Plan. 
(Reference:  Report by Executive Director with responsibility for Development and
Infrastructure dated 15 December 2022, submitted) 
6. ROUTE OPTIMISATION UPDATE 
The Committee gave consideration to a report providing an update on the introduction of a
route optimisation system that would seek to improve the operational management of
certain services operated via vehicles providing specific services. 
Decision 
The Environment, Development and Infrastructure Committee noted the update provided
in the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated February 2023, submitted) 
7. REST AND BE THANKFUL UPDATE (Pages 7 - 8) 
The Committee gave consideration to a report providing an update following the
announcement by the Transport Minister in December 2022 in respect of improvements to
the Old Military Road as a medium term solution to improve the resilience of the
temporary diversion route to the A83, should it be closed. 
Decision 
The Environment, Development and Infrastructure Committee –

Page 3

1. reaffirmed the Council’s long-established position that a permanent solution for the
A83 Rest and Be Thankful must be identified and, crucially, put in place as soon as
possible, as first agreed in this new Council term through a motion to Council in
September 2022 and subsequently embedded within the Priorities for the Council
agreed in November 2022; 
2. noted the confirmation from the Transport Minister that funding would remain
available for both the medium and long-term solutions for the route; 
3. noted the timescales set out in the report and that the aim was to have both lanes
of the A83 reopened, with traffic signals removed, by June or July of this year; 
4. noted that there was a further meeting of the A83 Taskforce due to take place in
June 2023; and 
5. in light of the timescales at (3) and (4) above, requested that officers bring a further
update to the Environment, Development and Infrastructure Committee meeting on
31 August 2023, for consideration of any further lobbying action that may be
required. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated January 2023, submitted; and Motion by Councillor Andrew Kain,
seconded by Councillor Donald Kelly, tabled) 
8. CEMETERY ASSET REPORT - UPDATE 
The Committee gave consideration to a report providing an update on the current Argyll
and Bute cemetery provision and detailing options for reviewing the current Management
Rules for Burial Grounds as well as management of the cemetery assets in the context of
current needs and future demands in each administrative area. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the Area Committee Business Days arranged; 
2. noted that officers propose to review cemetery numbers annually;   
3. noted the updated lair availability in each available cemetery with associated updates
in regards to works carried out and proposed as detailed in Appendix 1 to the
submitted report; 
4. endorsed and approved the change in policy for the Management Rules for Burial
Grounds which have less than 10 years availability to restrict the pre-sale of lairs to
protect the cemetery capacity as well as the other updates as detailed in paragraph
3.2.3 of the submitted report; and 
5. noted the future capital investment required in this asset group. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated January 2023, submitted)

Page 4

9. CARDROSS CREMATORIUM INSPECTION 
The Committee gave consideration to a report presenting the findings of a recent
inspection of Cardross Crematorium. 
Decision 
The Environment, Development and Infrastructure Committee endorsed the findings of the
inspection on Cardross Crematorium. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated February 2023, submitted) 
10. PLAY PARK FUNDING - UPDATE REPORT 
The Committee gave consideration to a report outlining a suggested process and
timelines for proposing further engagement with other groups, including youth forums and
relevant Community Councils in relation to the Play Park Funding Award of £938k which
had been awarded by the Scottish Government for the 28 play parks being renewed in
Argyll and Bute until 2025/26. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted that Area Committee Business Days were underway, where officers were
engaging with Elected Members; and 
2. agreed the proposed timeline as set out in section 4.4 of the submitted report. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated February 2023, submitted) 
11. FILM IN ARGYLL - SCREEN INDUSTRIES UPDATE REPORT 
The Committee gave consideration to a report providing an update of the work of the
Council’s Film in Argyll service in attracting inward investment into Argyll and Bute from
the screen industries and the economic benefits that this had brought to the local
economy, including opportunities to promote and market the area. 
Decision 
The Environment, Development and Infrastructure Committee noted the contents of the
submitted report, including the fact that the sector was still recovering from the impact of
the pandemic, and the continued positive economic impact the screen industry had on
Argyll and Bute. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 10 December 2022, submitted) 
Councillor Donald Kelly left the meeting during the consideration of the following item of
business.

Page 5

12. TRANSFORMATIONAL PROJECTS & REGENERATION TEAM - LARGE SCALE
PROJECT UPDATE REPORT 
The Committee gave consideration to a report providing an update on progress of the
large scale, externally funded project work of the Transformational Projects and
Regeneration Team.  The report highlighted key issues that could impact on the
successful delivery of projects. 
Decision 
The Environment, Development and Infrastructure Committee noted the current progress
detailed within the submitted report. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated 9 January 2023, submitted) 
13. STRATEGIC TRANSPORT PROJECTS REVIEW 2 (STPR2) - OUTCOMES 
The Strategic Transport Projects Review (STPR2) was developed to inform transport
investment in Scotland for the next 20 years (2022-2042).  The final STPR2 was published
on 8 December 2022.  The Committee gave consideration to a report providing
information on the outcomes of the review and advising that Argyll and Bute Council had
been poorly served through the outcomes of the document despite initial assurances and
having been fully engaged throughout the process. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the Transport Scotland Strategic Transport Projects Review 2 that had been
published on 8 December 2022. 
2. requested that the Leader of the Council write to the Scottish Government expressing
the Council’s disappointment with the STPR2 process and its outcomes in relation to
Argyll and Bute. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated 22 January 2023, submitted) 
14. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORK PLAN 
The Environment, Development and Infrastructure Committee work plan was before the
Committee for noting. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
work plan. 
(Reference:  Environment, Development and Infrastructure Committee Work Plan dated