ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
31 AUGUST  2023 
FOOTWAY RECONSTRUCTION PROGRAMME 2023/24 
1.0 INTRODUCTION
1.1 The adopted footway network in Argyll and Bute has been measured at approximately
1 million square metres. Most of this is bituminous surface, with sections of modular
concrete slabs, concrete “monobloc” paviours and granite paving in high amenity areas,
such as the CHORD projects locations etc.
1.2  This report provides details of the proposed Footway Reconstruction Programme for
2023/24. A budget of £750,000 was allocated as part of the 2023 budget process.
Through this report this budget has been allocated across the four administrative areas
based on the percentage of footways in each area. This is the approach which has been
followed with previous footway allocations. 
2.0 RECOMMENDATIONS
2.1 It is recommended that Members of the Environment, Development and Infrastructure
Committee:- 
i. Endorses the proposed programme of capital works for 2023/24; and 
ii. Agree that details of each Area Committee’s programme will be forwarded on to
individual Elected Members.   
3.0 DETAIL
3.1 The Council allocated £750,000 as part of the 2023/24 for footway improvements. This
has been allocated to Area Budgets based on the percentage of footways in each
geographical area. Appendix 1 indicates the share of funding split and draft schemes
list.
3.2 Budget has been allocated across the four administrative areas based on the
percentage of footways in each area. This is the approach which has been followed with
previous footway allocations and is detailed in the table below.

Page 2

3.3 Footway improvement scheme selection was carried out in June with intentions of
programming works from August 2023 onwards.  Consideration has been made in the
work elements of each scheme to improving the quantity and quality of dropped kerb
crossing points, as part of the overall surface improvement works.
3.4  This programme will complement other footway works including limited revenue works,
some active travel schemes and some minor footway resurfacing works which have
resulted through street lighting cable replacement works as part of the street lighting
programme.  
3.5 The works listed in Appendix 1 have been identified from the Inspectors/Team Leaders
based on their local knowledge – this is a combination of officers’ knowledge from their
day to day activities and feedback from Elected Members and the public, including
Community Councils.  
3.6  Following endorsement of the programme, area based programmes will be sent out to
all Elected Members together with programme information posted on the website. 
4.0 CONCLUSION
4.1 This report provides details of the proposed Footway Reconstruction Programme for
2023/24, including the measures taken to deliver the delayed Active Travel Funded
Programme, carried over from 2022/23. 
5.0 IMPLICATIONS
5.1 Policy - Works assessed and carried out under the current Roads and Footways Asset
Management Plan.
5.2 Financial - Programme will be based on capital allocation for year 2023/24.
5.3  Legal – None.  
5.4  HR - Reconstruction works delivered by a combination of in-house roads operations
team and sub-contractors.
5.5  Fairer Scotland Duty: 
Area Capital Footway
% Allocation
based on footway
area
MAKI 18%
OLI 15.3%
BC 33%
HL 33.7%
TOTAL 100%

Page 3

5.5.1   Equalities - protected characteristics – Crossing point access improvements
included in schemes where appropriate. 
5.5.2   Socio-economic Duty – None known. 
5.5.3  Islands – None known.
5.6 Climate Change – it is hoped improvements to the footway network would encourage
walking as opposed to driving short distances by vehicle.
5.7 Risk - Completed works will reduce requirement to repair footways and will halt the
footway deterioration and recurring safety issues.
5.8  Customer Service – Overall improvement in footway surfaces and the quality of  
pedestrian journeys. 
Executive Director with responsibility for Road and Infrastructure Services, 
Kirsty Flanagan 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
July 2023                                      
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
Hugh.ONeill@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – 2023/24 Capital Budget allocation by Area

Page 4

APPENDIX 1 -   2023/24 CAPITAL BUDGET ALLOCATION BY AREA 
FOOTWAY UPGRADE AND RECONSTRUCTION PROGRAMME
CAPITAL ALLOCATION  2023 FOOTWAY SCHEMES  £750,000
MAKI 18.00% £135,000
Campbeltown -  Tomaig Road FW  - With Flooding reinstatement £60,000
Bruaichladdich -   Kerbing and surfacing    £45,000
Bowmore - Slurry Seal  -  Various locations £30,000
£135,000
OLI 15.30% £114,750
Oban  ,  Dunollie  Various - Kerb replacement and surfacing £29,750
Oban ,  Miller Road  - Slab replacement £27,000
Mull ,  Bunessan  Phase 2  £30,000
Mull , Tobermory  -   Prison Brae £28,000
£114,750
B & C  33.00% £247,500
Bute  - Rothesay -  B881 High St     Ministers Brae - Stuart St £54,900
Bute - Rothesay  -  A844 Marine Road  - St Bruoc - Quat St £12,200
Bute  - Rothesay -  B878 Barone Rd  - Extension to Cemetery  £35,600
Cowal - Dunoon -  A815 Bullwood Rd  ph2 Kilmoray-Sunnybrae £14,600
Cowal  - Dunoon  - A885 Argyll St  -Stadium to Bencorrum £13,000
Cowal  - Dunoon -  UC01 Ardenslate Rd Ph 3   - Benc.to Dixon Av  £30,000
Cowal - Dunoon -  UC08 Bencorrum Brae  - A815 to "No1" £6,000
Cowal - Dunoon  - UC25 Edward St  - Auchamore Rd – William St £7,500
Cowal - Dunoon -   UC48 King St  - Jessie Place to McArthur Street  £8,700
Cowal  - Innellan -  Eleanor Lane  £35,000
Cowal - Dunoon -  John St    -  Argyll St to Victoria Road  £6,000
Cowal - Dunoon -  Ferry Brae   -  School Brae to Argyll St £6,000
Cowal - Kirn -   Clyde St  South   - A815 to Hunter St  £18,000
£247,500
H & L  33.70% £252,750
Helensburgh  -   Dalmore Cres    PH 2  £30,000
Cardross A814  -  PH 2 -    t o Crematorium entrance £35,750
Faslane A814  - Ph 2  -   summit to South Gate Junc . £62,000
Colgrain PH2   Guy Mannering & Jeanie Deans £50,000
Clynder -   Straid Bheag   (  and Straid a Cnoc - 2024)  £32,700
Helensburgh -   West   King St  ( James St  -  Sinclair St ) £26,100
Helensburgh -   Grant St  ( East King St  - East Argyle St ) £16,200
£252,750