Democracy Spraffa

Provision of Floral Displays

Argyll and Bute Council · 31 August 2023
Back to Environment, Development and Infrastructure Committee — 31 August 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE
SERVICES  31 AUGUST 2023 
PROVISION OF FLORAL DISPLAYS 
1.0 INTRODUCTION 
1.1 In 2021 the Council agreed to a savings package of £10,000 relating to the
nursery growing service. This report confirms that a financial saving has been
achieved and also sets out the challenges in delivering spring bedding largely
due to market changes which were not reasonably foreseeable at the time the
savings package was developed. This report also sets out a range of possible
options for dealing with planting beds in future years, including community
involvement. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
i. Consider the options in Table 1 of this report for future service delivery of
floral displays; 
ii. Agree to progress Option 4 in Table 1 based on this being the most
affordable solution for the Council. One-off funding could be met from the
Nature Restoration Fund and a report will be brought to the Policy and
Resources Committee in October in respect of this; and 
iii. In addition to Option 4, agree to also progress Option 6 to continue to
pursue community groups across the Council area to take over
maintenance of floral displays. 
3.0 DETAIL 
HOW THE SAVING HAS BEEN ACHIEVED 
3.1 In 2021 the Council agreed to a savings package of £10,000 relating to the
nursery growing service. A financial saving was achieved through a reduction
in materials budget, comprising reductions in equipment and materials for plant
production no longer required. However, the way in which the saving has been
delivered is different to that originally proposed due to changes in the market
place, availability of plants and price increases. In practice the spring bedding
has not been delivered due to market availability.

Page 2

3.2 The previous in-house service was delivered across two facilities – Ardencraig
Nursery in Rothesay, which provided bedding plants for Bute, and Kilmory
Castle Nursery, which provided bedding plants for the rest of Argyll and Bute.
These facilities grew, from bought in plugs, annual bedding plants used for floral
displays across the council area. 
CURRENT POSITION 
3.3 Over the last two years the procurement process was successful in securing a
supplier for the summer bedding but unfortunately did not secure a supplier for
the spring bedding. This would suggest that the market has changed from when
this initial saving was considered. Whilst we don’t have a full understanding of
what has happened with the market, it is assumed that this is linked to
conditions in respect of availability of workforce and the increased costs of
utilities and heating.  A similar situation had been experienced earlier this year
with many supermarkets having limited availability of some produce which are
not produced in the same volumes in the UK as previously. 
3.4 When this savings option was developed in 2020, there was no indication that
the market would not be able to fulfil our requirement. We had discussions with
a number of other local authorities who source their bedding plants externally
and there was no reason to expect that we would not be able to secure an
external supplier.   
3.5 At the Council Meeting on 29 June 2023, the following motion was agreed:- 
At the budget meeting in February 2021, the Council agreed to a saving of
£10,000 to stop the nursery growing service.  It was agreed that spring and
summer bedding plants would still be provided by being sourced externally.
The previous decision was taken with the best intention, but due to changes in
market and circumstances it has not been successful in practice. 
Carrying out a full procurement exercise only resulted in securing a supplier
for the summer bedding and not both the spring and summer beddings. 
Officers are asked to give consideration to the future arrangements for the
delivery of planting across Argyll and Bute, with particular reference to the
unique circumstances of Rothesay which was served by Ardencraig, and
bring a report back to EDI on 31st August, on options that could be delivered
for 2024. 
3.6  As per this Council decision, officers now present a range of options for future
service delivery of planting.  Existing budgets are under pressure with forecasts
of c£10M of a revenue reduction for 2024/25 and further budget reduction
forecast for future years.  Officers will not be able to deliver all of the Council
services that are currently being delivered.

Page 3

Table 1
Option and
description
Advantages Disadvantages Work required Additional Costs
over current
costs/Potential
Savings
Option 1 –
continue to
purchase annual
bedding as per the
budget savings
option agreed in
2021 but without
spring bedding
which has not
been delivered in
the last 2 years
due to changes in
the market 
No need for in house
growing 
Removes spring bedding
which has limited life with
displays often suffering
due to poor spring weather
conditions. 
In light of current financial
challenges facing the
Council, it could be
considered wasteful with
bedding plants being used
for a time limited period
before being dug up and
composted 
Continuation of existing
arrangements whilst
formalising the removal of
spring bedding, which is
the de facto position due
to current market failure 
Existing budget 
Option 2 – revert
to growing plants
from bought in
plant plugs for
summer bedding
only in both
Kilmory and
Ardencraig. 
Note this option
would remove
spring bedding
Assuming plugs are
available for purchase, the
Council would have control
of growing and supply.   
This option pays due
regard to the Rothesay
plants served by
Ardencraig.   
Resource intense 
High consumption of
energy and water with
increased costs from pre-
pandemic 
Would need to operate two
growing sites across the
Council area 
In light of current financial
challenges facing the
Would need to maintain
growing facilities in two
locations. 
Estimated additional
cost £33.5k 
Increased due to
inflation for materials,
utility costs etc.

Page 4

Council, it could be
considered wasteful with
bedding plants being used
for a time limited period
before being dug up and
composted 
More pressure on
operational team –
currently limited resilience 
There would be cost
pressures on existing
budgets, reinstating this
option would cost
significantly more than the
original saving due to
inflationary pressures 
Option 3 – revert
to growing plants
from bought in
plant plugs for
summer bedding
only at Kilmory
(Kilmory has
sufficient capacity
to serve the whole
of Argyll and Bute)
Assuming plugs are
available for purchase, the
Council would have control
of growing and supply 
Focusing on one growing
site will bring economies of
scale 
Additional costs incurred in
terms of original savings
and also additional costs
incurred due to price
increases 
The Kilmory nursery
would still be able to
achieve this with the solar
panel array in place
although existing
functional greenhouses at
top of nursery complex
would need to be located. 
Estimated additional
cost £20k. 
Option 4 – plant
out all existing
beds with
perennials/shrubs
Invest to save option 
Improved carbon
credential removing the
Plants would take 1 or 2
seasons to get
established, although with
careful choice of planting,
Plant out all beds with
perennials as an invest to
save initiative. 
One off investment
required – circa £80k. 
Potential savings of

Page 5

Examples of
perennial displays
can be seen in
Appendix 5. Note
these images have
been taken from
existing council
beds in Hermitage
Park and
community
maintained beds in
Campbeltown.
need to dispose/compost
annual plants each year 
Plants remain all year
round with varying
displays. In winter months
particularly perennials will
brighten up the bedding
areas which would be
empty with only bare soil
with the existing annual
planting. 
Ability to repurpose both
nursery complexes 
Reduction in utility costs 
Reduction in fuel costs and
transport 
Utilise staff on keeping
beds tidy rather than
annual planting providing
improved resilience 
Perennial plants provide a
habitat for insects, bird and
other mammals year round
providing biodiversity
benefits. This also aligns
with SG’s Nature
colourful displays should
be available in the first
season. 
This initiative may be
eligible for funding
through SGs Nature
Restoration Fund. 
£31k per annum
(current cost of
purchase of plants). 
This assumes care
and maintenance
remains at similar
level. However,
potential savings
which will be better
understood post
implementation.

Page 6

Restoration Funding
requirements.
Option 5 – plant
out all existing
beds with
perennials/shrubs,
in all areas other
than Bute, and
reopen Ardencraig
growing facility to
serve the Isle of
Bute for annual
summer bedding
plants 
Note this option
would remove
spring bedding
This option pays due
regard to the Rothesay
plants served by
Ardencraig.   
Reduced recurring
revenue saving. 
Inequity of provision
across the Council area. 
Loss of other opportunities
to repurpose Ardencraig
nursery.
Plant out all beds with
perennials as an invest to
save initiative (as Option
4). 
Reopening of Ardencraig
growing facility and
purchase of plant plugs. 
One off investment
required – circa £65k. 
Potential savings of
£31k per annum
(current cost of
purchase of plants). 
Estimated cost
associated with
reopening Ardencraig
and growing plants
£13.5k.
Option 6 –
continue to pursue
community groups
across the Council
area to take over
maintenance of
floral displays.
Note this option
could be
progressed in
conjunction with
Options 1- 5
above.
No need to grow in-house
bedding plants. Allows for
a better utilisation of
Council staff and reduction
in fuel costs. 
Sustainability.  Officer time
in setting up agreements
however once set up only
infrequent contact should
be required. 
Setting up agreements
with established groups.
Carry out agreed actions
whether supplying the
necessary materials or
planting the area for the
community partner to
maintain. 
Unable to quantify
until agreements in
place.

Page 7

3.7 Officers have appraised the various options listed in Table 1 and from a delivery
and sustainability perspective, the option to provide perennial plants across the
council area is the recommended option (Option 4). However, it is recognised
that Bute has historically benefitted from extensive annual bedding which have
been nurtured locally from externally supplied plant plugs and therefore, this
has been included as another option for consideration (Option 5). 
3.8 Appendices 1 - 4 detail all council maintained planting beds across the council
area with the exception of Hermitage Park which has been excluded due to the
Heritage Lottery Fund capital grant for its redevelopment which is contingent
on a specification as per existing planting within the park. 
3.9 Appendix 5 shows a range of images of perennial plants. Note these images
have been taken from existing council beds in Hermitage Park and community
maintained beds in Campbeltown and Cowal.  
3.10  The Nature Restoration Fund is a fund launched by the Scottish Government, and
aims to support large-scale, multi-year, multi-partner projects which deliver
transformative change to drive forward nature recovery.  Local Authorities are
provided with a share of that funding, and officers believe that the recommended
option presented in this paper would fit with the criteria for this fund.   
4.0 CONCLUSION 
4.1 This report confirms the budget savings for bedding plants agreed in 2021
which has been achieved and recommends that we move to a model using
perennial planting which would provide a more sustainable model and also
provide year round displays enhancing the current offer from annual bedding
plants. 
5.0 IMPLICATIONS 
5.1 Policy – this report provides a number of options for the delivery of planting
across Argyll and Bute.   
5.2 Financial – the preferred option carries comes at a one-off cost of £80k and it
is suggested that this if funded from the Nature Restoration Fund.  An annual
revenue saving of £31k is also anticipated.   
5.3 Legal – none known. 
5.4 HR – none known. 
5.5  Fairer Scotland Duty: none known. 
5.5.1   Equalities – none known. 
5.5.2   Socio-economic Duty – none known.

Page 8

5.5.3 Islands – none known. 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise. There is scope to reduce carbon footprint associated with
planting through the introduction of perennials.   
5.7  Risk – none known. 
5.8  Customer Service – none known. 
Executive Director with responsibility for Road and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Climate Change and Environment Services, Councillor Ross
Moreland 
August 2023                     
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
Jim.Smith@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
Tom.Murphy@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 Flower bed locations Mid-Argyll and Kintyre
Appendix 2 Flower bed locations Oban and Lorn
Appendix 3 Flower bed locations Bute and Cowal
Appendix 4 Flower bed locations Helensburgh and Lomond
Appendix 5 Examples of perennial plants