Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD
23 November 2023 
NOTICE OF MEETING 
A meeting of the ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE will
be held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND
BY MICROSOFT TEAMS on THURSDAY, 30 NOVEMBER 2023 at 10:30 AM, which you are
requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST (IF ANY) 
3. MINUTES (Pages 3 - 10)  
Environment, Development and Infrastructure Committee held on 31 August 2023. 
4. LATEST UPDATE ON THE SETTLEMENT PROJECT SUPPORT OFFICER
ACTIONS (Pages 11 - 16)  
Report by Executive Director with responsibility for Economic Growth 
5. ARGYLL AND BUTE HOUSING EMERGENCY 
(a) Progress Report (Pages 17 - 26)   
Report by Executive Director with Responsibility for Development and
Economic Growth
*  (b) Project Officer Resource (Pages 27 - 30)   
Report by Executive Director with Responsibility for Development and
Economic Growth 
6. HELENSBURGH WOODEN PIER - UPDATE (Pages 31 - 36)  
Report by Executive Director with responsibility for Development and Economic
Growth 
7. WASTE UPDATE (Pages 37 - 64)
Public Document Pack

Page 2

Report by Executive Director with responsibility for Road and Infrastructure Services 
8. CEMETERY ASSET - ANNUAL REPORT - TO FOLLOW 
Report by Executive Director with responsibility for Roads and Infrastructure Services 
9. PLAY PARK FUNDING - UPDATE REPORT NO 3 (Pages 65 - 70)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
10. OCTOBER 2023 WEATHER EVENT - UPDATE (Pages 71 - 82)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
REPORTS FOR NOTING 
11. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE WORK
PLAN (Pages 83 - 84)
.
Items marked with an “asterisk” are items, on the basis of information available at the time this
Agenda is published, on which the Committee may not have delegated powers to act, and which
may therefore require to be referred to the Council or another Committee, and that referral may
depend on the decision reached at the meeting.
.
Environment, Development and Infrastructure Committee 
Councillor John Armour Councillor Jan Brown
Councillor Garret Corner Councillor Robin Currie (Chair)
Councillor Mark Irvine Councillor Andrew Kain (Vice-Chair)
Councillor Jim Lynch Councillor Tommy MacPherson
Councillor Ian MacQuire Councillor Luna Martin
Councillor Ross Moreland Councillor William Sinclair
Councillor Andrew Vennard Councillor Peter Wallace
Councillor Gary Mulvaney   
Contact: Stuart McLean   Tel:  01436 658717

Page 3

MINUTES of MEETING of ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
COMMITTEE held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY,
LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 31 AUGUST 2023 
Present: Councillor Robin Currie (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Garret Corner
Councillor Mark Irvine
Councillor Andrew Kain
Councillor Jim Lynch
Councillor Tommy MacPherson 
Councillor Ian MacQuire
Councillor Luna Martin
Councillor Ross Moreland
Councillor William Sinclair
Councillor Andrew Vennard
Councillor Peter Wallace
Councillor Gary Mulvaney 
Attending: Kirsty Flanagan, Executive Director
Fergus Murray, Head of Development and Economic Growth
Jim Smith, Head of Roads and Infrastructure Services
Stuart McLean, Committee Manager 
1. APOLOGIES FOR ABSENCE 
There were no apologies for absence. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. MINUTES 
The Minutes of the meeting of the Environment, Development and Infrastructure
Committee held on 1 June 2023 were approved as a correct record. 
4. TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM - LARGE
SCALE PROJECT UPDATE REPORT 
The Committee gave consideration to a report providing an update on the progress of
large-scale, externally funded project work of the Transformational Projects and
Regeneration Team and highlighting key issues that may impact on the successful
delivery of the projects. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the current progress contained within the submitted report; and 
2. agreed to recognise the contribution and to reflect on the role played by third sector
groups, taking a local lead in respect of the Animation of Rothesay Castle, which was
implemented in collaboration with Bute Island Improvement District and the pop-up
Page 3 Agenda Item 3

Page 4

shop in the former Clydesdale Bank, and to note that this success had been driven by
Bute Island Alliance Scottish Charitable Incorporated Organisation. 
(Reference:  Report by Executive Director with responsibility for Development and Economic
Growth dated July 2023, submitted) 
5. LATEST UPDATE ON STAYCATION PROPOSALS 
The Committee gave consideration to a report offering a comprehensive update and
overview of the activities carried out by the Council in relation to the Staycation Project. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the update provided within the submitted report; and 
2. noted that £83,324.64 remained in the Staycation fund and £5,412 in the marketing
fund; and that officers would continue to work with partners to respond to challenges
and opportunities that arise from visitor pressures. 
(Reference:  Report by Executive Director with responsibility for Development and Economic
Growth dated 31 August 2023, submitted) 
6. LATEST UPDATE ON THE SETTLEMENT PROJECT SUPPORT OFFICER
ACTIONS 
The Committee gave consideration to a report providing an update on the work of the
Settlement Project Support Officer since 31 October 2022.  The report detailed key
findings from community engagement visits across the Repopulation Zones, initiatives
introduced by the Settlement Project Support Officer to encourage active relocation, and
the proposed actions for the Argyll and Bute Settlement Project going forward. 
Decision 
The Environment, development and Infrastructure Committee – 
1. noted the content of the submitted report and the updates provided; 
2. endorsed the work undertaken to date by the Settlement Project as outlined in Table 2
within the submitted report; 
3. agreed the proposed Settlement actions going forward as outlined in Table 3 within the
submitted report; and 
4. noted that a further report regarding progress on actions would be reported to the next
meeting of the Environment, Development and Infrastructure Committee. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated August 2023, submitted) 
Page 4

Page 5

7. NATIONAL ISLANDS PLAN REVIEW CONSULTATION 
The Islands (Scotland) Act 2018 requires that a consultation must take place as part of the
review of the National Islands Plan which had been published in 2019. The National
Islands Review Online Consultation had been announced by the Scottish Government on
1 August 2023. The Committee gave consideration to a report proposing that a formal
response to the consultation from the Council be prepared and submitted by the closing
date of 9 October 2023. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the National Islands Plan Review online consultation announced by the Scottish
Government on 1 August 2023, with a closing date of 9 October 2023; and 
2. given the timeline for the response, agreed that the formal response to the consultation
from the Council be prepared and shared with Members of the Argyll Islands Sounding
Board for their views and input, with the final response being delegated to the
Executive Director with responsibility for Development and Economic Growth in
consultation with the Leader, Depute Leader, Leader of the largest Opposition Group
and the Policy Lead for Islands. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated August 2023, submitted) 
8. ARGYLL AND BUTE OFFICER RESPONSE TO THE SCOTTISH
GOVERNMENT'S VISITOR LEVY (SCOTLAND) BILL CONSULTATION 
The Committee gave consideration to a report providing an officer response to the
Scottish Government’s Visitor Levy (Scotland) Bill consultation which had a closing date of
15 September 2023. 
Decision 
The Environment, Development and Infrastructure Committee approved the officer
response to the Scottish Government’s Visitor Levy (Scotland) Bill consultation for
submission by 15 September 2023. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated August 2023, submitted) 
* 9. PROVISION OF FLORAL DISPLAYS 
The Committee gave consideration to a report confirming that a financial saving had been
made following the decision by the Council in 2021 to a £10,000 savings package in
relation to the nursery growing service.  The report set out the challenges in delivering
spring bedding, largely due to market changes which were not reasonably foreseeable at
the time the savings package was developed.  The report also set out a range of possible
options for dealing with planting beds in future years, including community involvement. 
Decision 
Page 5

Page 6

The Environment, Development and Infrastructure Committee agreed to pursue a blended
model of options for the delivery of planting across Argyll and Bute as follows: 
1. agreed to re-open the Ardencraig growing facility to serve the Isle of Bute with annual
summer bedding plants noting that the estimated cost associated with this option was
£13,500; 
2. agreed to continue to purchase annual summer bedding plants for all other areas
across Argyll and Bute, noting that this would deliver a recurring revenue saving of
£6,000; 
3. agreed to progress Option 6 as noted in the report to continue to engage with
community groups across the Council area to take over maintenance of floral displays;
and   
4. agreed to recommend to the Council that as implementation of these measures are
estimated to require additional revenue funding of £7,500 within 2023-24 this is funded
from the unallocated General Fund and built into the budget outlook estimates for
future years.   
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted; and Motion by Councillor Ross Moreland,
seconded by Councillor Peter Wallace, tabled) 
10. STREET LIGHTING COLUMN REPLACEMENT 
The Committee gave consideration to a report providing an update on the LED street
lighting replacement programme which was nearing completion and capital improvement
works to replace columns and cabling prioritised based on condition. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted) 
11. FOOTWAY RECONSTRUCTION PROGRAMME 2023/24 
The Committee gave consideration to a report providing detail of the proposed Footway
Reconstruction Programme for 2023/24. A budget of £750,000 had been allocated as part
of the 2023 budget process and the report advised of how this had been allocated across
the four administrative areas based on the percentage of footways in each area. 
Decisions 
The Environment, Development and Infrastructure Committee – 
1. endorsed the proposed programme of capital works for 2023/24; and 
Page 6

Page 7

2. agreed that details of each Area Committee’s programme would be forwarded on to
individual Elected Members. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated July 2023, submitted)
Councillor Tommy MacPherson left the meeting at this point. 
12. PLAY PARK FUNDING - UPDATE REPORT NO.2 
The Committee gave consideration to a report providing a further update to the Play Park
Report considered by the Committee in March 2023.  The report highlighted the excellent
responses to the play park adult and young people engagement in regards to the funding
award of £938k awarded by Scottish Government for play park renewal to Argyll and Bute
Council until 2025/26.  The report proposed that following analysis of engagement
feedback Area Committees would be provided with a summary, specifically what local
communities had identified as their priorities for play park users. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the engagement numbers of 1054 adults and 408 young people responses and
that the officer managing this project would review each one over the coming weeks; 
2. agreed that once the consultation results had been fully reviewed, a report would go to
each Area Committee to agree the priorities for each play park in their area and
allocation of funding, within the area allocation (based on the number of play parks)
would be allocated to individual play parks; and 
3. agreed the amended timeline as set out in section 4.4 of the submitted report. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted) 
13. UPDATE ON BUDGET INVESTMENTS 
The Council, at the Budget Meeting in February 2023, allocated funding for new vehicles
to support service delivery across Roads and Infrastructure Services.  The Committee
gave consideration to a report providing an update on progress. 
Decision 
The Environment, Development and Infrastructure Committee noted the updates provided
within the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted) 
14. WASTE - PERSISTENT ORGANIC POLLUTANTS (POPS) 
The Committee gave consideration to a report providing an update on Persistent Organic
Pollutants (POPs) and the worldwide concerns surrounding the release of POPs into the
environment.
Page 7

Page 8

Decision 
The Environment, Development and Infrastructure Committee – 
1. agreed to call upon the Scottish Government to introduce a grace period following the
publication of its new guidance on handling POPs rather than requiring immediate
implementation; 
2. formally requested that the Scottish Government provides full funding for Argyll and
Bute Council (whether directly or by seeking this from the UK Government) given the
particular challenges and burdens that fall upon this authority given its remote, rural
and island geography; 
3. noted that the potential cost for Argyll and Bute Council could reach £0.5m in revenue
and capital costs which, given the current pressured financial context, presents real
affordability risks; 
4. agreed that the Policy Lead for Climate Change and Environmental Services write to
the Minister with responsibility for Circular Economy to convey the views of the
Committee; 
5. requested that a further report was brought to the November meeting of the
Environment, Development and Infrastructure Committee to update on any legislation
changes, associated costs and the Scottish Government’s response to the
Committee’s formal request. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted; and Motion by Councillor Robin Currie, seconded
by Councillor Gary Mulvaney, tabled) 
15. WINTER SERVICE POLICY 2023/24 
The Committee gave consideration to a report presenting the Winter Service Policy
2023/24 which remained in a similar format and covered a similar network to the Policy
approved by the Committee in previous years. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. approved the 2023/24 Winter Service Policy Document at Appendix 1 to the submitted
report; 
2. approved the Salt Use Reduction and Preservation of Stocks Protocol at Appendix 2 to
the submitted report; 
3. noted Appendices 3 – 6 of the submitted report; and 
4. noted that a review of the financial position was being carried out and this would be
reported to the Policy and Resources Committee in October. 
Page 8

Page 9

(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted) 
16. REST AND BE THANKFUL UPDATE 
The Committee gave consideration to a report providing an update on the Scottish
Government’s recent announcement on the long term solution for the Rest and Be
Thankful. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated June 2023, submitted) 
17. WASTE PPP UPDATE 
In December 2022, the Committee agreed to pursue a derogation from the Scottish
Government, from the implementation date of the Biodegradable Municipal Waste ban of
1 January 2026 to the end of the Council’s Waste PPP contract in September 2026. The
Committee gave consideration to a report providing an update on a meeting held with the
Minister for Green Skills, Circular Economy and Biodiversity on 26 July 2023 and a
subsequent meeting between Council officers and Scottish Government Officials. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the content of the submitted report; 
2. noted the update from the Minister and Scottish Government Officials; 
3. noted the advice to engage proactively with SEPA; and 
4. requested that an update be provided to the next meeting of the Committee on
discussions with SEPA and Zero Waste Scotland. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated August 2023, submitted) 
18. COMMUNITY EMPOWERMENT (SCOTLAND) ACT 2015 - ALLOTMENTS
WAITING LIST REGISTER 
A report providing an update on the actions that are being undertaken in response to
duties placed on the Council under Part 9 of the Community Empowerment (Scotland) Act
2015 was before the Committee for noting. 
Decision 
Page 9

Page 10

The Environment, Development and Infrastructure Committee noted the Allotments Waiting
List Register update which reflected the duties placed on local authorities arising from Part
9– Allotments of the Community Empowerment (Scotland) Act 2015. 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated August 2023, submitted) 
19. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORK PLAN 
The Environment, Development and Infrastructure Committee work plan was before the
Committee for noting. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
work plan. 
(Reference: Environment, Development and Infrastructure Committee work plan as at
August 2023, submitted)
Page 10

Page 11

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH  30 NOVEMBER 2023 
LATEST UPDATE ON THE SETTLEMENT PROJECT SUPPORT OFFICER
ACTIONS 
1.0 INTRODUCTION 
1.1 The purpose of this paper is to provide the Environment, Development and
Infrastructure Committee with an update on the progress of the Settlement Project
Support Officer actions that were approved by the Environment, Development and
Infrastructure Committee on the 31st of August 2023. 
2.0 RECOMMENDATIONS 
2.1 Environment, Development and Infrastructure Committee members are asked to: 
 Note and consider progress on actions agreed by Environment, Development and
Infrastructure Committee on 31 August 2023.  
 Note that a further update will be provided on the work of the Settlement Project
Support Officer at the next Environment, Development and Infrastructure Committee.   
3.0 DETAIL 
3.1 The recent release of Scotland’s Census 2022 (Rounded Population Estimates) has
provided more up-to-date information on Argyll and Bute’s demographic challenges.
Between 2011 and 2022, the population of Argyll and Bute decreased by -2.4%. (See
Appendix 1). 
3.2 As well as a declining population, the 2022 census findings further highlighted an ageing
population. When compared to all other Scottish council areas, Argyll and Bute has the
largest proportion of the population aged 65 and over, 27.2%. (See Appendix 1). 
3.3 With demographic trends across Argyll and Bute continuing to demonstrate an ageing
and declining working-age population, there is a need to address these challenges
through a multi-agency approach and support population retention and growth. 
3.4 The Argyll and Bute Settlement Project Support Officer continues to work closely with the
Settlement Officers in the Western Isles and Northwest Highland, as well as colleagues
from Argyll and Bute Council, HIE, and the Scottish Government Islands Team. Working
Page 11 Agenda Item 4

Page 12

in collaboration to recognise the place-based barriers to population retention and
attraction and support measures to address population decline.   
The Settlement Project Support Officer will be assisting housing colleagues to drive
forward works on the Council’s Housing Emergency.  This will provide the Housing
Emergency works with further resource to drive a more consistent and proactive
approach to facilitating both private and affordable housing developments.   
Update on Settlement Actions Approved at Environment, Development and
Infrastructure Committee 31st August 2023.   
3.5 Table 1 provides an update on the progress of the Settlement Project Support Officer
Actions as approved at Environment, Development and Infrastructure Committee on
the 31st August 2023. The current status of each action is shown using a Red, Amber,
and Green (RAG) indicator.   
Table 1. Update of actions.
Focus Area Action Approved Progress to Date 30th October
2023
Current
Status 
Active
Promotion
of Argyll
and Bute 
Continue to develop
and expand
settlement case
studies for the
abplace2b website
and enhance
marketing
provisions where
appropriate.
All initial settlement content has
been prepared and will be
uploaded to abplace2b and Invest
in Argyll websites. 
The settlement flyer has been
updated with support from the
Argyll and Bute Council’s Graphic
Designer and will be incorporated
into web updates. 
The welcome pack has been
developed working alongside
Settlement Officers in Uist/ NW
Highland. The Argyll and Bute
Council’s Graphic Designer has
provided assistance with layout. 
To date, five case studies have
been drafted, and subject to final
edits may be included in
abplace2b and Invest in Argyll
websites. 
The myjobscotland section specific
to Argyll and Bute Council has
been updated by the
Communications Team to include
improved links to abplace2b. 
Further settlement updates are
planned for myjobscotland,
through collaborative working with
Economic Growth, HR and the
Comms/Web Teams. 
Page 12

Page 13

Supporting
Relocation
Continue to
respond to
relocation queries. 
Set up a relocation
network connecting
new and existing
residents. 
Work with the new
Housing
Improvement
Officer (Empty
Homes) to support
individuals
relocating to
recently refurbished
properties.  
To date, there have been eight
relocation queries received. All
queries have been responded to
accordingly. 
Comprehensive relocation contact
resources have been compiled for
all Resettlement Zones. 
A survey has been created to set
up a relocation network, initially
connecting people who have
relocated to Argyll and Bute. 
Links to access the survey have
been inserted on the flyer and
welcome pack with the assistance
of the Council’s Comms/Web
Teams. 
Settlement support resources will
be passed on to the Housing
Improvement Officer in
collaboration with the Council’s
Communications Team.   
Housing Launch the ‘Make
Your Second Home
Your First Home’
campaign.
Increased energy
support and
signposting across
Argyll and Bute.  
Initial discussions have taken
place with the Argyll and Bute
Housing Team. 
Economic Growth is working with
colleagues in the Housing Team to
refine the ‘Make Your Second
Home Your First Home’ campaign. 
Employment Consider current
empty council-
owned (non-
residential)
properties being
used for remote
working hubs or
creative spaces
(working with other
council colleagues,
as appropriate). 
Engage with key
employers across
the Repopulation
Zones to identify in
detail the number
and nature of
Reached out to council colleagues
to try to determine if there are
council-owned spaces that could
be made available for remote
working/ creative spaces. 
A survey has been drafted for
community groups and businesses
that currently offer remote working/
creative spaces to advise on
available premises. Collaboration
will be required with other teams
across the council to ensure that
this data has not been captured
previously. Survey fatigue also
needs to be considered. 
Monthly reports are being received
from Argyll and Bute Council HR 
Page 13

Page 14

recruitment issues
they have
encountered/
forecast
Team regarding withdrawn and
declined job offers. 
4.0 CONCLUSION 
4.1 Recent data published by the Scottish Census 2022 has provided further insight into
the demographic challenges facing Argyll and Bute, specifically an ageing and
declining population. Census findings show that between 2011 and 2022, Argyll and
Bute’s population has decreased by -2.4%. Moreover, compared to all other Scottish
council areas, Argyll and Bute has the largest proportion of the population aged 65 and
over (27.2%). 
4.2 As previously noted, Table 1 provides an update on the progress of the Settlement
Project Support Officer actions. Work is ongoing to progress these actions and a
further update report will be provided to committee as required. 
5.0 IMPLICATIONS 
5.1 Policy The overarching vision of Argyll and Bute Council’s
current Economic Strategy, 2019-23 is that Argyll and
Bute’s economic success is based on a growing
population. 
5.2 Financial Using funding previously agreed for a staffing resource
in the Restart, Recovery and Renew: Delivering our
Recovery Strategy and Action Plan paper at the P&R
Committee, December 2021. From June 2023, the
Settlement Project Support Officer post has been
extended for 18 months, joint funded by Argyll and
Bute Council and the Scottish Government. 
5.3 Legal All appropriate legal implications will be taken into
consideration. 
5.4 HR Funding from the Scottish Government has allowed the
Settlement Project Support Officer post to be extended
to the end of December 2024. 
5.5 Fairer Scotland
Duty 
The Fairer Scotland Duty, Part 1 of the Equality Act
2010, came into force in April 2018. The duty places a
legal responsibility on particular public bodies in
Scotland, such as Argyll and Bute Council, to pay due
regard to (actively consider) how they can reduce
inequalities of outcome, caused by socio-economic
disadvantage, when making strategic decisions and
how this has been implemented. 
Page 14

Page 15

5.5.1 Equalities All activities will comply with all Equal
Opportunities/Fairer Scotland Duty policies and
obligations. 
5.5.2 Socio-economic
Duty
All project activities will comply with the council’s socio-
economic duty. 
5.5.3 Islands The activities of the Settlement Project Support Officer
covers three islands; Tiree, Coll and Bute. 
5.6 Climate Change None. 
5.7 Risk None 
5.8 Customer Service None. 
Kirsty Flanagan, Executive Director responsible for Development and Economic
Growth 
November 2023 
Policy Lead for Strategic Development: Councillor Robin Currie 
For further information contact: 
Ishabel Bremner, Economic Growth Manager ishabel.bremner@argyll-bute.gov.uk 
Milly Leggett, Settlement Project Support Officer milly.leggett@argyll-bute.gov.uk   
Page 15

Page 16

Appendix 1: Scotland’s Census 2022- Rounded Population Estimates 
Population change, 2011
to 2022, council areas in
Scotland. 
Source: Scotland’s Census
2022
The 65 and over age
group as a proportion of
the population, 2022,
council areas in Scotland. 
Source: Scotland’s Census
2022
Page 16

Page 17

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
30 NOVEMBER 2023 
ARGYLL AND BUTE HOUSING EMERGENCY – PROGRESS REPORT 
1.0 EXECUTIVE SUMMARY 
1.1  In June 2023 the Council’s Environment, Development and Infrastructure
(EDI) Committee declared a Housing Emergency due to a consistent
reduction in supply of housing, a steady increase in demand for housing
across all tenures and increasing levels of un-affordability. 
The Committee approved the following:-
 The intention to update the Local Housing Strategy
 The intention to hold an Argyll and Bute housing summit together with
relevant stakeholders in the Autumn of 2023
 Note the operational officers group will explore and develop a series of
options that will be brought forward to Members for consideration as
and when developed. 
1.2 This report is to update EDI Committee on progress towards these intentions
and generally tackling the Housing Emergency.  
1.3 A wide range of activity has been progressing including arranging a Housing
Summit for November, draft revisions to the Local Housing Strategy Update,
actions of the Officer Housing group, focusing initially on exploring release of
Council Assets suitable for housing, liaison with National House Builders,
exploring facilitation of constrained sites, partnership working with RSLs,
improving the evidence base to justify innovation and intervention, working to
secure Rural Housing Body Status, refining HOMEArgyll letting policy,
exploring changes in the land use planning system; developing worker housing,
and re-evaluation of the ex- Council Stock buy-back scheme. 
RECOMMENDATION 
Members of the Environment, Development and Infrastructure Committee are
asked to:- 
i. note and consider the activity and progress that is ongoing in pursuing
the EDI Committee approved intentions and generally seeking to
address the Housing Emergency. 
Page 17 Agenda Item 5a

Page 18

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
30 NOVEMBER 2023 
ARGYLL AND BUTE HOUSING EMERGENCY – PROGRESS REPORT 
2.0 INTRODUCTION 
2.1 In June 2023 the Council’s EDI Committee declared a Housing Emergency
due to a consistent reduction in supply of housing, a steady increase in
demand for housing across all tenures and increasing levels of un-
affordability. 
2.2 This Committee approved a range of actions and this report is to update the
EDI Committee on progress towards these intentions and generally tackling
the Housing Emergency. 
3.0 RECOMMENDATIONS 
Members of the Environment, Development and Infrastructure Committee are
asked to:- 
i. note and consider the activity and progress that is ongoing in pursuing
the EDI Committee approved intentions and generally seeking to
address the Housing Emergency. 
4.0 DETAIL 
A HOUSING EMERGENCY  
4.1 In June 2023 the Council’s EDI Committee declared a Housing Emergency
due to a consistent reduction in supply of housing, a steady increase in
demand for housing across all tenures and increasing levels of un-
affordability. 
The Committee approved the following:-
 The intention to update the Local Housing Strategy
 The intention to hold an Argyll and Bute housing summit together with
relevant stakeholders in the Autumn of 2023
Page 18

Page 19

 Note the operational officers group will explore and develop a series of
options that will be brought forward to Members for consideration as
and when developed. 
4.2 This report is to update EDI Committee on progress towards these intentions
and generally tackling the Housing Emergency. 
The intention to update the Local Housing Strategy 
4.3 There is a statutory requirement for the Council to produce a Local Housing
Strategy(LHS). The current LHS covers the period 2022-2027. There is also a
requirement to provide annual updates on the progress towards the targets
set in the LHS. On September 19th 2023 the draft annual update was reported
to the Strategic Housing Forum which is the Housing Market Partnership
required to be in place to scrutinise the LHS process. The draft annual update
highlights some of the new issues which have come to the fore; particularly
the need to address issues in the private sector supply of speculative new
build housing, and the need to consider the requirements for regulation of the
existing private stock and its use, particularly second homes and holiday lets.   
4.4 The final LHS update will be produced for February 2024 EDI Committee with
a summary feedback from the housing summit.  A more detailed report on
outputs will follow later, and subsequently the intention will be to amend the
LHS Action Programme with any identified actions coming from the Housing
Summit or other work.  This is likely to be May 2023. 
The intention to hold an Argyll and Bute housing summit together with
relevant stakeholders in the Autumn of 2023 
4.5 The summit will take place on 27th November at the Scottish Association for
Marine Science (SAMS) buildings at Dunbeg. The Council has appointed
Arneil Johnston consultants to assist with the organisation and delivery of the
event.  Initial discussions have taken place with the consultants and 4 broad
themes have been proposed:- 
 Enabling the delivery of more market homes in Argyll and Bute
 Enabling the delivery of more affordable homes in Argyll and Bute
 Enabling the delivery of homes for Argyll and Bute’s workforce
 Making the best use of existing homes in Argyll and Bute
4.6 Within the themes there will be a focus on topics such as tackling the
homeless crisis, dealing with the skills shortage in the construction industry,
encouraging the private sector to build housing in Argyll and Bute, effective
procurement methods, tackling ineffective housing stock in the local authority
area and the summit will also explore the construction methods available to
deliver housing. 
4.7 The following activities were planned in preparation for the event:- 
Page 19

Page 20

 A questionnaire has been issued to the public to get their up to date
views on the housing situation in Argyll and Bute;
 A questionnaire has been issued to businesses to gather up to date
views on the housing situation in Argyll and Bute in relation to business
sustainability and expansion; and
 Pre-summit themed Teams meetings have taken place with
stakeholders within organisations who will be attending the event to
ensure that the summit will have a clear focus on solutions to assist
alleviate the current housing emergency. 
4.8 Speakers are still being finalized but are likely to include  Shelter, Homes for
Scotland and or the House Builders Federation, Scottish Futures Trust & HIE. 
Note the operational officers group will explore and develop a series of
options that will be brought forward to Members for consideration as
and when developed. 
4.9 The Officers Group which has been set up within the Council to assist in
tackling the housing emergency has been meeting on a regular basis
throughout 2023. The early focus has been on Council owned assets and
exploring how they could be used to assist in tackling the housing emergency.
The group also has a remit to discuss Council interventions which could assist
partners to deliver housing in the local authority area. 
4.10 Key actions which have been undertaken or are in progress include:
 The lease of a Council owned 2 bedroom property in Fionnphort, Mull
to the Mull and Iona Community Trust (MICT) for the purpose of
creating worker accommodation. 2 workers now occupy the property –
one worker employed by Historic Environment Scotland and one
worker employed by National Trust Scotland;
 A Council owned flat in Tobermory has been brought back into use for
the Education department;
 Ironsides Farrar have been appointed to undertake initial site
investigations of Council owned sites at Balemartine, Tiree, Crossapol,
Tiree, Arinagour, Coll, Killarow House, Bowmore, Islay and the
Hermitage Primary School Annex, Helensburgh with a view to
enabling housing delivery on these sites; and
 Exploring options for alternative use of office buildings surplus to
requirements in Oban.
4.11 The Council are being supported by an Officer from HubNorth to develop
business cases for some of these potential proposals.  RSLs have expressed
interest in the small island sites which are being investigated. 
National House Builder Liaison 
4.12 Meetings have been held with representatives of National House builders to
discuss their strategic plans and what opportunities there are to unlock
development and how the Council can assist. 
Page 20

Page 21

Facilitating Existing Constrained Housing Sites 
4.13 Examining potential to tackle infrastructure impediments in Oban,
Helensburgh and Cardross housing sites which could involve Council
intervention through land acquisition and or delivery of infrastructure utilising
the Housing Infrastructure Fund. 
RSL Partnership Working To Deliver Housing Land 
4.14 The Council is working with RSLs to unlock new housing development sites
and lever in funding.  The Council has approved the potential use of CPO
powers to assist deliver of site assembly at unsafe buildings on Clyde Street,
Helensburgh and ACHA would potentially re-develop.  Fyne Homes / the
Council and HES are working to unlock Rothesay Academy site.  West
Highland are exploring potential delivery at Loch Awe.  The Council is working
with RSL partners on many other sites as explained in the Council’s Strategic
Housing Investment Plan. 
Establishing Better Evidence For Decision Making: 
4.15 A Community Planning Survey is being carried out as part of the work to
refresh the Local Outcome Improvement Plan.  A survey of local residents has
already identified that Housing is seen as the second priority behind improved
transportation for our communities.   An in depth sample follow up survey has
been designed focusing on Islay as an example of an area with high demand
and affordability issues. It will seek to identify further detailed understanding of
the views of this group of people and particularly their views about potential
actions and interventions the Council may consider. 
4.16 Consultants are due to complete specialist legal, planning and chartered
surveyor specialist advice regarding the application of occupancy controls
through different legal mechanisms.  This will support any potential choice to
apply requirements for housing to be restricted to primary occupancy as
opposed to holiday homes or short term letting, and or other obligations in
terms of local key workers and or affordability. 
4.17 Consultants are surveying our Island populations, and analysing the Island
private housing market to establish a clear definition and identification of
Market Failure.  This will be a crucial piece of evidence which the Council will
need to rely on if, in identifying potential future interventions in the housing
market, it chooses to use the Council’s Wellbeing Powers.  This might be for
example if the Council builds market housing for sale as is proposed by the
Rural Growth Deal Housing Pilot. 
4.18 Officers have worked in collaboration with other Local Authorities, Scottish
Futures Trust and Brodies LLP to explore the potential options for Council
interventions in the private housing market, the circumstances and
mechanisms which may be appropriate, and the foundations which need to be
put in place to minimise risk and comply with legislation.  
Page 21

Page 22

Rural Housing Body Status 
4.19 The Council applied to Scottish Government for Rural Housing Body Status at
the beginning of 2023.  Scottish Government have carried out in partnership
with the Council’s Housing Service an impact assessment of the proposal. 
This involved surveying local stakeholders that might be affected.   
4.20 Scottish Government has indicated the Council should be awarded Rural
Housing Body status on 29th November 2023.   Doing so gives the Council the
ability to apply Rural Housing Burdens to properties it has constructed,
purchased, or consented.  This will be another potential important tool,
particularly in ensuring the affordable homes remain affordable homes in
perpetuity.  Rural Housing Burdens can be used to introduce property burdens
that will ensure property remains in use for its intended use.  The intended
use could be a range of affordability and or occupancy criteria.  Officers will
explore in more detail proposals for how these Burdens might be used in a
way which best contributes to tackling the Housing Emergency and will report
these to Council for approval. 
Home Argyll Changes 
4.21 In September, Council approved changes to the HOMEArgyll common
allocations policy.  The changes where proposed in response to the Housing
Emergency and in partnership with RSLs. 
4.22 It is hoped the reduction in offers for 200 point housing applications will
streamline and accelerate the process of finding permanent tenancies
particularly for homeless applicants.  The changes also allow for flexibility in
the allocations policy where there are particular pressures identified and
particularly this will allow the allocation of two bedroom properties to single
person households in areas of high pressure including Lorn and Helensburgh.   
4.23 The Council has also requested that the HOMEArgyll partners increase from
50 to 60%, the proportion of allocations to homeless applicants in times where
the Council has been forced to use unsuitable temporary accommodation. 
September PPSL Report 
4.24 A report was presented to September PPSL outlining the areas where the
Land Use Planning Framework might be reviewed to contribute to tackling the
Housing Emergency. ( SEPT PPSL DRAFT HOUSING ISSUES v0.2.pdf
(argyll-bute.gov.uk ).  The report recommended the following actions: 
 Officers explore the options for designation a short-term let control
area/s for all, or parts of the planning authority’s area and report back
to PPSL;
 Officers prepare a Technical Planning Note in support of NPF4 and
LDP2, providing updated guidance on affordable housing delivery
Page 22

Page 23

including its retention in perpetuity and accommodating key workers for
consideration by Members; and
 Officers prepare a draft Technical Note in support of NPF4 and LDP2,
that will provide guidance on how we ensure housing is delivered to
meet the local housing need as identified by the Housing Needs and
Demand Analysis, including potential occupancy restrictions for
consideration by Members. 
Tobermory Worker Housing 
4.25 The Council has submitted a planning application for 12, 2 bedroom cottage
flats on a site owned by the Council at Rockfield Road, Tobermory.  The
intention is to develop the road and infrastructure for this site utilising Rural
and Islands Infrastructure funding as a first phase of development during the
summer of 2024.  The second phase, funded through the Rural Growth Deal,
will be to develop the first block of four 2 bedroomed flats, which will be used
as worker accommodation.  The Council is working in partnership with MICHT
and it is the intention MICHT will act as managers of the premises. 
Buy Back Scheme Re-Evaluation 
4.26 Along with RSL Partners the Council have been operating a buy back scheme
which facilitates the purchase of ex-social housing and its return to RSL use. 
This is funded by Scottish Government, however operation of the scheme has
shown the grant levels do not match the average purchase prices experienced
in much of Argyll and Bute for this type of property.   Discussion with Scottish
Government has resulted in an amendment to understanding of the funding
regime such that no maximum ceiling purchase price will be applied.  It will be
open to RSLs to make a case to justify why any proposed purchase price is
justified in terms of the realities of the local housing market prices, and the
need and demand in that area.  This has the potential to make this scheme
significantly more popular and effective.   
Resource 
4.27  Following the declaration of the Housing Emergency, the Housing Group has met,
and officers continue to work at speed to explore and develop the potential
interventions that have been requested.  There is an emerging need for the
Council to be more consistently proactive in its approach to facilitating housing
sites both affordable and private and to develop innovative proposals in sufficient
detail to enable their robust justification.  The existing resources of the Services
involved are not able to move these forward at the speed required by the
Housing Emergency.  It is suggested that the allocation of a Project Officer will
assist in accelerating progress and this is addressed in another paper on the EDI
agenda. 
Settlement Project Support Officer 
4.28   The Council’s Settlement Project Support Officer has been undertaking a range
Page 23

Page 24

of works following approval from the Environment, Development and
Infrastructure Committee on 31 August 2023 and an update report has been
prepared for the Environment, Development and Infrastructure Committee on
30 November 2023.  Going forward, the Settlement Project Support Officer will
be looking at a wider scope of work including issues relating to the Housing
Emergency declared by the Council, and will be assisting the coordination of
works with the Project Officer for housing.  Future reports of a housing nature
will include works of the Settlement Project Support Officer.   
5.0 CONCLUSION 
5.1 Since the Council’s declaration of a Housing Emergency, considerable activity
has been focused on exploring new methods and solutions to tackle the housing
shortages, and to bring renewed focus to delivering business as usual.  A
Housing Summit has been arranged.  Research has been commissioned. 
Policy changes are being discussed and agreed.  Housing site delivery and
overcoming impediments to delivery is being prioritized.  Many of these actions
are preliminary actions and officers will report further progress once the
Housing Summit has been hosted and further information and consultation has
been collected.   
6.0 IMPLICATIONS 
6.1  Policy  – The ongoing activity is consistent with current Council priorities and
the Local Housing Strategy vision and outcomes which are directly aligned
with the overarching objectives of the Outcome Improvement Plan, in
particular Outcome 2 – we have infrastructure that supports sustainable
growth. 
6.2  Financial – None directly arising from this report but future housing delivery
actions will require additional funding at some stage from the council and our
partners if delivery is to be accelerated. 
6.3   Legal – None.   
6.4    HR – None.   
6.5   Equalities (Fairer Duty Scotland) – The activity outlined in the report is
consistent with aims and objectives set out in the local housing strategy, which
is subject to an EQIA. 
6.5.1  Equalities – Protected Characteristics – There are targets set within the SHIP
to deliver housing which meet the needs of specialist groups. 
6.5.2  Social-Economic Characteristics – The delivery of affordable housing across
Argyll and Bute facilitates socio-economic opportunities for all. The SHIP links
with the Child Poverty Strategy. 
Page 24

Page 25

6.5.3  Islands – The delivery of affordable housing across Argyll and Bute facilitates
socio-economic opportunities for all. The SHIP links with the Child Poverty
Strategy. 
6.6  Risk – The Housing Needs and Demand Assessment process takes full
account of housing need on the islands. 
6.7  Climate Change – New housing in the right location helps reduce carbon
outputs particularly when heating is provided using renewable energy and
utilizing high standards of insulation which can also be applied to existing
stock. 
6.8  Customer Service – None.   
Kirsty Flanagan, Executive Director with Responsibility for Development and
Economic Growth 
Councillor Robin Currie, Policy Lead for Strategic Development 
October 2023 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth   
Fergus.Murray@argyll-bute.gov.uk 
Matt Mulderrig, Development Policy and Housing Manager
Matt.Mulderrig@argyll-bute.gov.uk 
Douglas Whyte, Team Lead – Housing Strategy
Douglas.Whyte@argyll-bute.gov.uk   
Page 25

Page 26

This page is intentionally left blank

Page 27

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
30 NOVEMBER 2023 
HOUSING EMERGENCY – PROJECT OFFICER RESOURCE 
1.0 INTRODUCTION 
1.1 Following the declaration of the Housing Emergency, the Housing Group has met,
and officers continue to work at speed to explore and develop the potential
interventions that have been requested.  There is an emerging need for the
Council to be more consistently proactive in its approach to facilitating housing
sites both affordable and private and to develop innovative proposals in sufficient
detail to enable their robust justification.  The existing resources of the Services
involved are not able to move these forward at the speed required by the
Housing Emergency.  It is suggested that the allocation of a Project Officer will
assist in accelerating progress. 
2.0 RECOMMENDATION 
Members of the Environment, Development and Infrastructure Committee are
asked to:- 
i. agree and recommend to the Policy and Resources Committee that the
Council recruit a Project Officer to assist in accelerating the work of the
Housing Emergency with funding for this post to be drawn down from the
Council’s Priorities Investment Fund.   
3.0 DETAIL  
3.1 Following the declaration of a Housing Emergency, the Housing Group has met
and officers continue to progress the work proposed in the Environment,
Development and Infrastructure (EDI) Committee.   
3.2 As a result of the Housing Emergency an increased focus is being applied to all
matters which will assist accelerated delivery of improved housing options within
Argyll and Bute, and this work is very broad ranging in scope.  In addition, given
the known difficulties in delivering the current housing land supply within the two
main settlements of Oban and Helensburgh, it is likely to get more challenging. 
3.3 There is a need for the Council to be more consistently proactive in its approach
to facilitating housing sites, both affordable and private.  The Council has
Page 27 Agenda Item 5b

Page 28

previously only undertaken such action sporadically, Dunbeg Kirk Road
Improvement being an example. This proactive approach is necessary both
because of the increasing costs and complexities of development, and the
pressures the housing system is under.  To do so consistently, at scale and at
speed is beyond the existing staff resources of the services likely to be involved
(Planning, Roads, Estates, Legal Services). 
3.4 Immediate interventions are the proactive facilitation of existing potential housing
sites through acquisition of land and provision of road improvements via potential
Compulsory Purchase Order (CPO).  Some housing sites exist which have
already been extensively considered and explored and it is likely that the only
feasible solution for each is through the CPO route.   
3.5 The sites have planning support in principle for the delivery of housing and have
been identified in various ways within our LDP and SHIP.  The two sites in Oban
also have notional allocations of HIF funding from Scottish Government to pay for
the infrastructure improvements.  Given the housing emergency, there is a fairly
solid policy argument to justify pursuing a CPO route, albeit it will need to be twin
tracked with ongoing discussion with the developers and landowners.  However
in order to pursue this it is first necessary to establish with more detailed design
work that the proposed outline solutions are physically deliverable before the
Council can be requested to make a firm decision to pursue a Compulsory
Purchase Order (CPO) route, and to consider the legal process in order to
establish that we have laid the necessary justification.  This work can reasonably
be initiated now but will require resources to pursue it.   
3.6 It is requested that a Project Officer be appointed to concentrate on developing
these matters in the first instance.  The Project Officer would likely be, though not
necessarily, a property professional (Surveyor / Planner / Engineer), preferable
with experience of bringing forward development sites and or delivering CPOs or
other land assembly exercise. If this is a temporary post it is suggested 3 years
as a minimum will allow progress on some of the substantive issues.  An
LGE11/12 grade is considered appropriate, along with supporting budget for
laptop/phone/travel, a budget of £200,000 would be required.  In addition it is
anticipated that there may be subsequent requests for research & capital costs as
the various projects are developed, but at present there is insufficient detail to
estimate these. This could be substantial depending on what works are
prioritised and funding cannot be sourced elsewhere i.e. spend to save; RGD;
Scottish Government and Strategic Housing Fund. 
3.7 The continuing work of the Housing group will additionally generate numerous
other work streams to support potential radical interventions in the short to
medium term and the proposed Project Officer can be utilised to contribute to /
lead some or all of these.  Some options include: 
 Exploring a Council buy back and resale scheme of second homes or holiday
lets which come to the market, adding a primary occupancy burden before re-
sale, thus directly bringing properties back in to residential use.  This could
capitalize on the potential effect of short term licensing, the introduction of
Page 28

Page 29

planning control areas, and potential changes to the Council tax and NDR
regimes.
 Facilitating private new build sites through purchase (and re-sale) or
underwriting private units for sale, or delivering infrastructure: Craignure; Port
Ellen, Bowmore Masterplan, and Dunbeg.
 Developing a Council civils contracting arm available to plug the gap in the
local contractor market.
 Supporting specific research for Strategic Land Identification at scale near
Oban & Helensburgh.  PLDP2 commits us to deliver the OSDF and HSDF to
identify land for growth for the next 20-40 years.  Work has started in the
planning policy team but will require support and funding to carry out specialist
research (transport assessments, infrastructure and junction feasibilities,
Flood Studies etc…).  Collectively these studies will be looking to identify land
for as much as 4000 units which would create the scale to justify strategic
infrastructure investment (subject to separate project mandate submission). 
4.0 CONCLUSION 
4.1 Work is underway at pace by the Housing Group, as required by ELT and the
declaration of a Housing Emergency.  There is a need for a more consistent
proactive approach to facilitating both private and affordable housing
development and to continue to investigate and develop the innovative
interventions that are expected, in adequate detail to robustly justify their
recommendation.  The existing resources of the Services involved are not able
to move these forward at the speed required by the Housing Emergency, and it
is suggested the allocation of a Project Officer will assist in accelerating
progress funded from the Council’s Priorities Investment Fund. 
5.0 IMPLICATIONS 
5.1  Policy  – The ongoing activity is consistent with current Council priorities and
the Local Housing Strategy vision and outcomes which are directly aligned
with the overarching objectives of the Outcome Improvement Plan, in
particular Outcome 2 – we have infrastructure that supports sustainable
growth. 
5.2  Financial – The post and supporting budget will cost £200,000 over a 3 year
period with a recommendation that this is funded from the Council’s Priorities
Investment Fund. 
5.3   Legal – None.   
5.4    HR – Creation of a temporary post for a period of 3 years.   
5.5   Equalities (Fairer Duty Scotland) – The activity outlined in the report is
consistent with aims and objectives set out in the local housing strategy, which
is subject to an EQIA. 
Page 29

Page 30

5.5.1  Equalities – Protected Characteristics – There are targets set within the SHIP
to deliver housing which meet the needs of specialist groups. 
5.5.2  Social-Economic Characteristics – The delivery of affordable housing across
Argyll and Bute facilitates socio-economic opportunities for all. The SHIP links
with the Child Poverty Strategy. 
5.5.3  Islands – The delivery of affordable housing across Argyll and Bute facilitates
socio-economic opportunities for all. The SHIP links with the Child Poverty
Strategy. 
5.6  Risk – Takes longer to progress with interventions to deal with the Housing
Emergency. 
5.7  Climate Change – The Council is committed to working towards net zero. 
5.8  Customer Service – None.     
Kirsty Flanagan, Executive Director with Responsibility for Development and
Economic Growth 
Councillor Robin Currie, Policy Lead for Strategic Development 
October 2023 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth   
fergus.murray@argyll-bute.gov.uk 
Matt Mulderrig, Development Policy and Housing Manager
matt.mulderrig@argyll-bute.gov.uk 
Page 30

Page 31

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
30 NOVEMBER 2023 
HELENSBURGH WOODEN PIER - UPDATE   
1.0 INTRODUCTION 
1.1 This report provides the Environment, Development and Infrastructure
Committee with an update following the decision to remove Helensburgh
Wooden Pier from the project options within the Rural Growth Deal Tourism and
Place Programme. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that the Environment, Development and Infrastructure
Committee:-
a) Accept the Consultants findings, particularly that a berthing facility at
Helensburgh Pier cannot be operated on a revenue neutral basis,
particularly where long-term capital replacement costs are accounted for,
and that officers will no longer devote resources to pursuing a Council
funded berthing facility; and 
b) Agrees that  the Head of Development and Economic Growth engages
with Helensburgh Community Council and any other appropriate
community group(s) who may express a wish to pursue options, including
a potential asset transfer of Helensburgh Wooden Pier.   
3.0 DETAIL 
3.1 Helensburgh Pier is a masonry structure with a timber extension, projecting 245m
from the shoreline. It is a Grade C listed structure however, lack of operational
use and vandalism has resulted to a deterioration of the condition of the pier and
the berth at the pier head has also been subject to siltation. This culminated in the
Council issuing a ‘Notice to Mariners’ in October 2018 advising that the pier is
closed to all vessels. 
3.2 Helensburgh waterfront has been a significant focus of regeneration activity in
recent years, culminating in the opening of the new £25 million leisure centre
and associated public realm improvements in September 2022.  The leisure
Page 31 Agenda Item 6

Page 32

centre development completed the long-running programme of regeneration of
the esplanade, creating an attractive waterfront, which complements the wide
range of independent, and chain retail and leisure facilities in the town.
3.3 Figure 3.1 below, presents an overview of Helensburgh Pier and surrounding
structures. 
Figure 3.1: Helensburgh Pier Overview. 
STANTEC MARKET SCOPING STUDY
3.4 The Council’s Rural Growth Deal Programme Management Office (RGD PMO)
were asked to consider redevelopment of Helensburgh Wooden Pier as part of
the emerging RGD “Tourism – Creating a World Class Visitor Destination”
programme.  In particular, the feasibility of constructing a commercial pontoon /
berthing facility to replace the current Wooden Pier head.  
3.5 Argyll & Bute Council (A&BC) commissioned Stantec UK Ltd and partners Mott
MacDonald to undertake a market scoping study exploring the market for using
Helensburgh Pier and the design and costs of different options for upgrading the
structure. The study is attached in the following link Helensburgh Pier - Market
Scoping Study 
3.6 The purpose of Stantec’s scoping study was to identify whether there was a
case for developing a more comprehensive business case for public sector
investment in a commercial berthing facility at Helensburgh Pier, building on
initial work by members of the local community. This included desk-based
Page 32

Page 33

research and 16 stakeholder interviews to determine the extent of the
prospective market across key sectors. 
3.7 The study considered the construction of a pontoon facility that would extend
100m in a south-south-west orientation (the same as the existing masonry pier)
with a 41m access gangway in order to comply with the Equality Act (2010). A
dredged channel would likely be required to allow vessels to navigate onto the
pontoon berths at all states of the tide.
3.8 The following organisations took part in stakeholder interviews and research:-
 Argyll & Bute Council
 Destination Helensburgh
 European Cruise Services
 Firth of Clyde Boat Tours
 Glasgow City Boats
 Greenheart Wood Traders
 H.M Naval Base Clyde
 King’s Harbour Master
 Loch Lomond & the Trossachs
National Park
 Northern Lighthouse Board
 Peel Ports Limited
 Transport Scotland
 Visit Scotland
 Waverley Excursions
 You & Sea 
3.9 Stantec considered a number of key user groups and a summary of key points
relating to each user group is below-
User Group Key points:
Ferry  There is absence of demand for a ferry service
to use the Pier which would give a regular
source of revenue income to support the
running costs of redeveloped facility
 Transport Scotland have discounted the option
of establishing a cross-Clyde ferry service as
part of STPR2. 
 HMNB Clyde have ruled out the possibility of
ferry transport for staff from HMNB Clyde to
Helensburgh Town Centre.
Cruise  Large cruise liners dock at Greenock and prefer
to use coaches to transport passengers to
attractions and towns. Tendering is not seen as
an attractive option for cruise ships due to
resources required.  
 Limited demand from smaller domestic cruise
ships at “bookends” of season. Demand would
be insufficient to cover operational costs. 
Marine Leisure  The Firth of Clyde is well served by commercial
marinas, a number of which are in close
location to Helensburgh. There is a significant
risk that if a berthing facility were to be
developed by Argyll and Bute Council, there
would be a risk of market distortion and
Page 33

Page 34

potential non-compliance with Subsidy Control
Regulations. 
Tours/Excursions  There is limited demand from operators such
as PS Waverley however due to not-for-profit
status, they do not pay dues at Council ports. 
 The limited demand would be seasonal and
would therefore not provide a regular revenue
stream. 
Operational Vessels  This user group have well established facilities
currently in place and would be unlikely to use
a redeveloped facility with any regularity
therefore could not be relied on to provide a
revenue stream. 
4.0 CAPITAL COSTS OF A NEW BERTHING FACILITY 
4.1 Stantec and Mott MacDonald considered high-level costs associated with a
number of development options at Helensburgh Pier, which are detailed in the
Market Scoping Report.  Stantec considered four high level options for
redevelopment with costs ranging between £517,500 for a lighter touch scheme
to £3m for a scheme which would bring the wooden pier back into operational
use.  Further details are set out in Table 4.1 below:-
Table 4.1 – Helensburgh Pier Cost Estimates 
4.2 Capital costs of a new berthing facility would be in excess of £2.6m and it is
anticipated that a functional berth would accrue operational costs of circa £100k
per annum to cover staff costs, insurances, inspections and overheads such as
power, lighting and service charges. This figure does not include an allowance for
capital replacement or uninsured accidental damage, for which it is recommend
that 20% of income is set aside in a bond / contingency fund.
4.3 On the basis of the costs identified and the lack of a regular, year round user such
as a ferry service, it is considered unlikely that a berthing facility at Helensburgh
Page 34

Page 35

Pier could be operated on a revenue neutral basis, particularly where long-
term capital replacement costs are accounted for.
4.4 The Rural Growth Deal Programme Board made the decision in May 2023 to
remove Helensburgh Pier from consideration for funding under the “Tourism –
Creating a World Class Visitor Destination” Theme of the RGD and re-profile
funding to other projects.  It is considered unlikely that a berthing facility at
Helensburgh would satisfy the requirements of a Treasury 5 business case and
as such, it will not be possible for this project to be considered for RGD funding. 
RGD tourism funding will now focus on the Rothesay Pavilion and Kintyre
Seasports projects.  This decision was endorsed by the Councils Policy &
Resources Committee in August 2023. 
5.0 CONCLUSIONS 
5.1 The Environment, Development and Infrastructure Committee are asked to note
that there remains an aspiration from a sub-group of Helensburgh Community
Council to replace the current wooden pier with a berthing facility.  
5.2 On the basis of the costs identified and the lack of a regular, year round user such
as a ferry service, it is considered unlikely that a berthing facility at Helensburgh
Pier could be operated on a revenue neutral basis, particularly where long-term
capital replacement costs are accounted for.  As such, at present, a viable
business case cannot be made for a commercial berthing facility in Helensburgh.    
6.0 IMPLICATIONS 
6.1  Policy – Helensburgh Wooden Pier was considered during the options appraisal
process for the Rural Growth Deal. 
6.2  Financial – It is unlikely that a berthing facility at Helensburgh Pier could be
operated on a revenue neutral basis. 
6.3  Legal  – Subsidy control implications would require to be considered for a
berthing facility at Helensburgh Pier. 
6.4  HR – None at present. 
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – Equality Impact Assessments
would be required as part of any future project proposals.
6.5.2   Socio-economic Duty – This would require to be considered as part of
future business cases.
6.5.3 Islands – No impact. 
Page 35

Page 36

6.6  Climate Change – Environmental impact assessments might be required for
future redevelopment schemes at Helensburgh Pier, particularly where capital
dredging is required.   
6.7  Risk – Risk associated with further deterioration of Helensburgh wooden pier
sits with the Council. 
6.8  Customer Service – None at present. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Policy Lead for Strategic Development: Councillor Robin Currie 
November 2023                                                  
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
fergus.murray@argyll-bute.gov.uk  
Jonathan Welch, Rural Growth Deal Programme Manager
jonathan.welch@argyll-bute.gov.uk   
Page 36

Page 37

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE
SERVICES  30 NOVEMBER 2023 
WASTE UPDATE 
1.0 INTRODUCTION 
1.1 This report provides an update on a number of waste related matters, which
include meetings held with the Scottish Environment Protection Agency (SEPA)
on 4 October 2023 and with Scottish Government (SG) Officials on 6 October
2023 regarding the Waste PPP contract. 
1.2 Council officers have been planning for the introduction of the guidance relating
to Persistent Organic Pollutants (POPs) which are found within Waste
Upholstered Domestic Seating (WUDS). SEPA released their guidance relating
to disposal of these items on 31 October 2023. 
1.3 The Council has been successful in securing funding from the Recycling
Improvement Fund to support improvements to recycling infrastructure on
Council operated Civic Amenity/ Landfill sites. 
1.4 Argyll and Bute Council’s (ABC) Officers have engaged with Zero Waste
Scotland (ZWS) which links directly to the Council’s Waste Strategy and
provides information on the Circular Economy Bill and high level implications to
the authority, as well as the offer of officer support from Zero Waste Scotland
to progress matters relating to the Biodegradable Municipal Waste Ban to
Landfill, this is inclusive of an options appraisal and a composition analysis,
detailed further in section 3.4.     
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
i. Consider and note the update regarding meetings held with SEPA on the
Waste PPP contract; 
ii. Note that officers will conclude conversations which are ongoing
regarding the derogation and will bring a further report to the next
meeting of this Committee for a decision on the way forward for the
Council; 
iii. Consider the update regarding Persistent Organic Pollutants and note
the date of implementation of compliance with  SEPA mandatory
guidance as 1 November 2023; 
Page 37 Agenda Item 7

Page 38

iv. Note the bid to the Recycling Infrastructure Fund and officers’
achievement in successfully securing funding for improvements; 
v. Note the officer support offered by Zero Waste Scotland; and 
vi. Consider the detail provided in this report regarding the Circular
Economy Bill.   
3.0 DETAIL 
3.1  Waste PPP 
3.1.1 In December 2022, the Council’s Environment, Development and Infrastructure
Committee agreed to pursue a derogation from the Scottish Government, from
the implementation date of the Biodegradable Municipal Waste Ban of 1
January 2026 to the end of the Council’s Waste PPP contract in September
2026. 
3.1.2 The Council has in place a 25 year Waste PPP contract which ends in
September 2026. The Waste PPP contract covers Oban and Lorn, Mid Argyll
and Kintyre, Bute and Cowal together with the inner islands. 
3.1.3 The Scottish Government are due to introduce a Biodegradable Municipal
Waste (BMW) landfill ban from the end of December 2025. The last 9 months
of the PPP 25 year contract will not be compliant with the new regulation. 
3.1.4 Argyll and Bute Council is the only Local Authority with a PPP contract, this
leaves the authority in a unique situation whereby it is hampered by a 25 year
contract which was supported by the Scottish Executive in 2001. To remove
itself from the contract has significant financial implications for the authority. 
3.1.5 A derogation would enable the PPP contract to continue with the Mechanical
Biological Treatment (MBT) process until the contract comes to an end in
September 2026, this being some 9 months after the BMW ban comes in to
place. Note – the islands and Helensburgh and Lomond areas are intended to
be BMW compliant from 1 January 2026. Should a derogation not be permitted,
the Council are seeking funding for additional costs (circa £1.5M) which would
be incurred by the Council in respect of varying the PPP contract from Scottish
Government (SG). 
3.1.6 Council officers met with SEPA Officials to discuss the subject of the derogation
from the BMW landfill ban for a 9 month period until the Waste PPP subsists
on 2 September 2026.  Thereafter, Council officers engaged with SG based
upon the SEPA discussion. The following points were discussed: 
 The Council Leader met with the Minister of Green Skills, Circular
Economy and Biodiversity supported by the Scottish Government
officials and council officers on 26 July 2023.
 Following the meeting, the Minister confirmed that SG officials had
explored opportunities to create a workaround to permit a derogation to
be achieved without a change in law and advised Council officers that it
would not be possible and that the authority should  engage with SEPA;
Page 38

Page 39

 Council officers met with SEPA and advised the agency that the Scottish
Government (SG) had informed Council officers that they were not in a
position to fund the cost associated with not achieving a derogation (circa
£1.5M) and the change would require a change in law which they
wouldn’t be supporting;
 The SEPA meeting was arranged on 4 October 2023 where a  request
was made to SEPA to allow a derogation until the contract end date in
2026;
 SEPA advised that SEPA’s regulatory remit in relation to the BMW ban
is clear, and that they were preparing to fully implement the ban in line
with the legislation and within their enforcement policy, ultimately
informing the Council that they must comply with the BMW ban;
 This information was fed back to SG officials who are going to arrange a
follow up meeting with the Council Leader and SEPA senior officials
based upon the Council Leaders letter requesting the derogation, no
date is set for this meeting yet;  
 A subsequent meeting between Council officers and SG officials was
due to take place on 13 October 2023 however this is being rescheduled. 
The meeting will focus on Council officers requesting an update from SG
regarding the meeting with the Council Leader and SEPA senior officials.
 On 14 November a strategic meeting took place including the Council
Leader, Chief Executive, Executive Director and Head of Service and
senior officials from SEPA. At the time of writing SEPA have not
confirmed their position regarding the Council’s request for a derogation. 
3.1.7 Officers continue discussions relating to the derogation as previously discussed
at the Environment, Development and Infrastructure Committee and will
conclude those discussions with Government officers.  Officers from the
Council’s Waste Service will bring a further update to the next meeting of this
Committee to provide detail on engagement with SG, and to ensure the Council
have a compliant solution going forward. 
3.2  Persistent Organic Pollutants (POPs) 
3.2.1  SEPA have now confirmed that POPs guidance takes effect from 1st November
2023. Council officers have been planning for the processing of POPs material
to comply with legislative changes but also to support the three distinct waste
models operated by the Council. The changes have seen investment in storage
for the material at all Council locations and also changes will be implemented
by the Council contractors for the Waste PPP and the H&L Waste model.
Summarised below are some points in relation to POPs. 
3.2.2 The UK has signed up to Worldwide Environmental Legislation (Stockholm
Convention) which bans POPs (above a certain threshold) from landfill. 
 The Environment Agency (EA) in England discovered that POPs is
contained within fire retardant foam for domestic seating (made prior to
2019), exceeded the threshold for landfill disposal;
 The EA in 2022 wrote to all Councils in England stating that by the end of
Page 39

Page 40

2022 waste domestic seating (containing POPs) could no longer be
landfilled and instead would have to go to an Energy from Waste (EFW)
plant for incineration;
 In 2023, SEPA notified Councils that a similar landfill ban on Waste
Upholstered Domestic Seating was likely to come into Scotland during
2023 with draft guidance issued to Councils;
 SEPA notified Councils mid-October that they expected formal guidance to
be issued on 31 October 2023 but that they expect Councils and landfill
operators to already be in compliance and that the formal guidance will not
differ much from the draft;
 SEPA have also indicated that they will expect compliance of not landfilling
the material on day 1 (i.e. 1 November 2023) of the formal guidance being
issued and will also issue enforcement timescales for non-compliance;
 SEPA formal guidance was issued on 31 October 2023;
 Compliance will incur additional requirements on the Council and its waste
disposal contractors which will result in additional costs to the Council. A
report highlighting the issue was brought to the August EDI Committee
which included a range of costing options;
 At the moment, the mid-range costs estimates of circa revenue £173k per
annum and one–off capital costs of £110k, appear to be a reasonable
estimate;
 One of the Councils waste disposal contractors is already asking that
WUDS items are segregated ASAP to ensure SEPA compliance, this
started from 1 November 2023. 
3.2.3 Waste Upholstered Domestic Seating typical items containing POPs which
have been historically disposed of in landfill and are likely to have to be
transitioned to EfW include but are not limited to:- 
 Sofas;
 Sofa beds;
 Armchairs;
 Kitchen and dining room chairs;
 Stools and foot stools;
 Home office chairs;
 Futons, bean bags, floor and sofa cushions; and 
 Leather, synthetic leather, other fabric and foam. 
3.2.4  SEPA wrote to the Council on 17 October 2023 to confirm that their intention
was to publish their guidance on 31 October 2023 – a copy of this is attached
at Appendix 1. SEPA also published information which clearly signposts the
regulatory support available to enable operators who currently have a waste
management authorisation to continue to store and treat WUDS (Waste
Upholstered Domestic Seating) containing POPs whilst working towards full
compliance with the requirements outlined in the guidance document. 
3.2.5  SEPA’s guidance makes it very clear that at the point at which an item of
upholstered domestic seating becomes waste (WUDS), it is an offence for it
(or any waste arising from its treatment) to be disposed of by landfilling, or in
Page 40

Page 41

any other way that is not one of the appropriate disposal routes.   
3.2.6  Within SEPA’s communication on 17 October 2023, SEPA confirmed that
whilst it is necessary for Scottish Local Authorities to comply with the landfill
ban without delay, SEPA will not take enforcement action in respect of any
failure to do so before 31 January 2024. 
3.3  Zero Waste Scotland (ZWS) – Recycling Improvement Fund 
3.3.1 Council Officers engage with ZWS in relation to all recycling matters and
submitted an application to the Recycling Improvement Fund (RIF) which is
managed by ZWS with funding approvals given by Scottish Ministers.  In
summary, the application was for funding from the Recycling Improvement
Fund to support improvements to recycling infrastructure at six Household
Waste Recycling Centres (HWRC) on the islands and the Helensburgh and
Lomond area. The improvements will increase the quality and quantity of
recyclate material captured by the Council and provide further re-use
opportunities for items deposited at these sites.   
3.3.2  On 12 October 2023, Zero Waste Scotland confirmed that the Council had
been successful in securing funding through the Recycling Improvement
Fund, The funding awarded is £891,945.12.  A breakdown of the works being
undertaken and the timescales of the work are noted within the table which is
attached at Appendix 2.   
3.4  Zero Waste Scotland (ZWS) Resource 
3.4.1 Following discussions between the Council and ZWS, it has been agreed that
ZWS will supply technical staff time to Argyll and Bute Council.  This will be in
the form of up to two days a week to support and the focus will be: 
 The preparation for, and completion of recycling and waste
management projects, including waste compositional analysis (waste
composition analysis is a process of physically separating, weighing
and categorising waste and can be used both to determine total
amounts of food, loss and waste (FLW) and to categorise the different
types of foods that have been discarded (fruits, vegetables, meat) or
distinguish between food and inedible parts); 
 Options appraisal on recycling – looking at how we better recycle, 
what options are open to the Council to improve recycling activities with
the outcome being the production of a revised Waste Strategy;
 Preparation for the forthcoming ban on landfilling Biodegradable
Municipal Waste (BMW);
 Energy from Waste works in liaison with West Dunbartonshire Council. 
This support will be for a six month period and commence as soon as the
Council have confirmed their agreement. It may be extended subject to
agreement on both sides.  
Page 41

Page 42

3.4.2  This resource is notwithstanding the offer of funding to conduct a waste
composition analysis at Moleigh and to support a Council options appraisal
once the requirements of the authority are determined. This will be funded by
ZWS in this financial year.  It should be noted that Moleigh is the only site
where there is sufficient space to do this piece of work.  ZWS will assist with
data templates and other items. 
3.5  Circular Economy Bill (CEB) 
3.5.1 The Circular Economy Bill (CEB) was published on 14th June 2023 with its
purpose being to move Scotland closer to more sustainable levels of
consumption, which aligns with policies on climate change and biodiversity.   
3.5.2  In June 2023, Parliament agreed a motion for consideration.  The CEB is at
Stage 1 of the Scottish Government process. On 28 June 2023, Parliament
agreed a motion that consideration of the Circular Economy (Scotland) Bill at
stage 1 be completed by 26 January 2024.  S6M-09754 | Scottish Parliament
Website   
3.5.3 The CEB makes provision for circular economy policy and targets, littering, fly
tipping and improving Councils’ household waste recycling services. The latter
is based in large parts on the Scottish Government previous consultations on
a Scottish waste route map “Scotland's circular economy - route map to 2025
and beyond: consultation2”. https://www.gov.scot/publications/consultation-
delivering-scotlands-circular-economy-route-map-2025-beyond/ 
3.5.4  The Bill requires Scottish Ministers to introduce measures to help develop a
circular economy, which includes:- 
 Publishing a Circular Economy Strategy;
 Developing Circular Economy Targets; 
 Reducing Waste; 
 Increasing penalties for littering from vehicles; 
 Making sure individual householders and businesses get rid of waste in
the right way; 
 Improving waste monitoring. 
3.5.5 More important to Local Government are the provisions for recycling and
enforcement. For household waste, giving local authorities a package of new
responsibilities and powers: 
 Establishing a new fixed penalty notice procedure and concurrent civil
penalty regime for Councils to tackle recycling contamination; 
 Requiring Councils to comply with a Code of Practice on recycling; 
 Giving powers to Scottish Ministers to set recycling targets for local
authorities; 
Page 42

Page 43

 Deter littering from vehicles by establishing a new civil penalty regime that
will make the keeper of a vehicle, rather than an individual, liable to pay a
penalty charge in respect of a littering offence committed from that vehicle;
 Deter fly tipping by improving enforcement against fly-tipping and other
waste crime through a power allowing the Scottish Environment Protection
Agency (SEPA) and Local Authorities to seize vehicles involved in specified
waste crime;
 Prevent fly tipping by requiring householders to transfer their waste to an
authorised person.
3.5.6 COSLA supports the general policy intent of the CEB to move Scotland closer
to a circular economy and sustainable levels of consumption. The Waste
Managers Network feed directly into COSLA and the opinions are reflected in
responses from COSLA to the SG. Points from the most recent COSLA report
are noted below for information:- 
 The CEB only sets the framework for the delivery of future waste policy
which means that much of the detail, including the full financial implications
of the new powers, will not be realised for some years. Household waste
recycling in particular will depend on financial decisions made as part of the
extended producer responsibility scheme and in future Scottish budgets;
 In general, the measures in the CEB will not be successful unless they are
supported by significant new investment;
 Recognition to the co-design of the new Code of Practice and local waste
targets with Local Government, this commitment will only be credible if it can
be evidenced that there are sufficient resources available to deliver the
changes which are necessary;
 This commitment to co-design also does not bind any future Scottish
Government to work in this way with Local Government, this is a concern as
much of the CEB will not be delivered until long after the next Scottish
elections; 
 The Bill grants powers to impose targets on Local Authorities without a clear
commitment that the investment required to achieve these targets will be
fully funded. COSLA believe this is especially problematic as the Scottish
Government is also seeking power to impose a liability on a local authority
to pay a penalty if a target imposed under the regulations is not achieved.
COSLA do not believe that seeking this measure is consistent with the Verity
House Agreement signed by the Scottish Government.
3.5.7  The view of officers is that there are a number of risks associated with the
Circular Economy Bill in terms of waste management for the Council, the risks
are noted below.  
 The Council has to comply with a statutory Code of Practice for waste and
recycling that results in additional revenue and capital costs;  
 Statutory recycling targets are imposed in future which result in fines by
the Scottish Government if the targets are not achieved; 
Page 43

Page 44

 Councils are not resourced with the available staff to carry out the significant
number of requirements in the Bill including enforcement staff in relation to
the new powers granted to Councils for domestic waste. 
4.0 CONCLUSION 
4.1 In concluding this report, an update on various meetings held with the Minister, 
Scottish Government Officials and SEPA, relating to the Council’s request for a
time limited derogation for the Waste PPP area from 1 January 2026 -
September 2026 for the BMW landfill ban which is due to be implemented from
1 January 2026.  The Committee agreed, in December 2022, to pursue two
options and officers continue to take these forward in tandem.   
4.2  Officers will continue to monitor and review updates from SEPA regarding
Persistent Organic Pollutants and report verbally when the formal guidance has
been made available. This report highlights further, the cost implications which
will be incurred by the authority.   
4.3  This report informs the Committee of the commitment made by Zero Waste
Scotland and also adds insight into the CEB and raises concerns identified by
COSLA.   
5.0 IMPLICATIONS 
5.1 Policy – The Council’s waste strategy will evolve in line with the changes in
legislation relating to the BMW ban of waste to landfill. A derogation will be
sought, failing a successful response the current Renewi contract will be varied
to comply with legislative changes.   
The Council’s waste strategy will evolve in line with the changes in legislation
relating to the Persistent Organic Pollutants.   
5.2 Financial – Compliance with the 2025 Landfill ban will require financial resource
from the Council. As the Scottish Government are initiating the change, Officers
will pursue financial support from the Scottish Government for this change to
provide a long-term financially sustainable solution.   Through lobbying it is
our intention to seek to recover any additional costs which have resulted from
the changes to legislation, through Scottish Government. However, there
remains a risk that funding is not forthcoming. 
Implications are prevalent with regard to both revenue and capital
expenditure.  The best case scenario would see the Council have additional
costs of £78,500. The Mid-Range scenario is £173,000 and the worst case
costing range is £366,000 of additional revenue costs. The three costs ranges
also have capital expenditure implications which are approx. £110,000 this
would be a one off cost. Based upon the three scenarios the mid-range
estimates seem most likely. 
Page 44

Page 45

The Council have received funding from the Recycling Improvement Fund of
£891,945.12 to support improvements to recycling infrastructure.   
5.3 Legal – The existing PPP contract was not designed or written to
accommodate the changes that the 2025 legislation will require. The contract
allows variations to be made although the process is quite cumbersome.
There will be legal implications, which will need to be resolved, relating to a
contract variation regarding the derogation and/or changes in Renewi’s
contract. 
Based upon the initial information provided by COSLA, the Council will be
given additional powers for enforcement and to deter waste crime. Councils
will have to comply with the Code of Practice on recycling. The introduction of
the CEB applied targets to local authorities, liabilities and penalties are also
notable. 
5.4 HR – HR issues will be addressed prior to and during the process of contract
handback. Having sufficient resource will factor into the project demands of
waste management. TUPE will be relevant at the handback and during the
process of progressing to handback should the Council operate the sites
themselves.   
HR issues may have relevance due to insufficient resource being available
should the CEB changes be enforced upon the Council.  Additional resources
are being provided by ZWS, however this is only for two days per week, for a
six month period.   
5.5  Fairer Scotland Duty: 
5.5.1   Equalities – None. 
5.5.2   Socio-economic Duty – None. 
5.5.3 Islands – There may be potential ferry capacity issues for bulking and
transporting waste material from islands, this has been flagged to Transport
Scotland.   
5.6 Climate Change – Transitioning from Landfill to Energy from Waste would result
in a reduction in the annual quantity of Greenhouse Gas Generated in Argyll
and Bute. However, the additional road miles incurred taking waste to EFW
markets will partly offset the carbon reductions achieved through not landfilling.
Incineration is the only way to dispose of POP’s Waste material. Transitioning
from Landfill to Energy from Waste would result in a reduction in the annual
quantity of Greenhouse Gas Generated in Argyll and Bute. However, the
additional road miles incurred taking POP’s waste to EFW markets may partly
offset the carbon reductions achieved through not landfilling. 
5.7  Risk – there are financial risks associated with no derogation. 
Page 45

Page 46

As in section 5.2 of this report, there are financial risks associated with POPs
waste material.   
There are potential financial risks associated with the CEB based on the
information available. SG should be lobbied for financial support through
COSLA.   
5.8  Customer Service – None. 
Executive Director with responsibility for Road and Infrastructure Services,
Kirsty Flanagan 
Jim Smith, Head of Road and Infrastructure Services 
Policy Lead for Climate Change and Environment Services, Councillor Ross
Moreland 
November 2023                     
For further information contact: 
John Blake, Fleet, Waste and Transport Manager
John.Blake@argyll-bute.gov.uk 
APPENDICES:
Appendix 1 – SEPA Guidance on Persistent Organic Pollutants
Appendix 2 – Recycling Infrastructure Fund – breakdown of works and timescales 
Page 46

Page 47

OFFICIAL
OFFICIAL
Guidance on the management of Waste
Upholstered Domestic Seating (WUDS)
containing Persistent Organic Pollutants
(POPs)
October 2023
1.0 Background
A recent study1 commissioned by the Environment Agency in England has highlighted the
presence of Persistent Organic Pollutants (POPs) in upholstered domestic seating.
The study highlighted that the average concentration of Brominated Flame Retardants, and
other POPs, found in items of upholstered domestic seating can be four times higher than the
legal concentration limit – or threshold limit - of 1000 mg/kg. 
This means that on becoming waste, these items of upholstered domestic seating (UDS), are
covered by existing legislative requirements specific to wastes containing POPs.  
This guidance will support waste holders in classifying and assessing their Waste Upholstered
Domestic Seating (WUDS) and help ensure that it is managed in an appropriate manner.
2.0 Persistent Organic Pollutants – Legislative Framework
POPs are organic chemical substances which pose a risk to human health and the environment
due to their persistence in the environment, bioaccumulation through the food chain and long-
range environmental transport across a wide geographical range.  
1 (WRc) www.wrcplc.co.uk
APPENDIX 1 – SEPA GUIDANCE ON PERSISTENT ORGANIC POLLUTANTS
Page 47

Page 48

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs)
2
OFFICIAL
Any wastes containing levels of POPs above threshold limits specified within the Stockholm
Convention must be managed in such a way as to destroy or irreversibly destroy the POPs
content.
The Stockholm convention and the EU POPs Regulation (EU 2019/1021) are implemented in the
UK via the UK Persistent Organic Pollutants Regulations 2007 and it's subsequent amendments
for which SEPA is the competent and enforcing authority in Scotland. 
Producers and waste holders must comply with the following duties, any failure to do so would be
deemed an offence under the regulations:   
• Producers and holders of waste shall undertake all reasonable efforts to avoid, where
feasible, contamination of other wastes with POPs waste (Reg. 7(1)).
• POPs waste shall be disposed of or recovered, without undue delay, in such a way as to
ensure that the POP content is destroyed or irreversibly transformed so that the remaining
waste and releases do not exhibit the characteristics of POPs (Reg. 7(2)).
• Disposal or recovery operations that may lead to recovery, recycling, reclamation or re-use
on their own of POPs shall be prohibited. (Reg. 7(3)).
Following this guidance will enable to comply with these duties.
In addition to the POPs specific legislation, existing requirements, under other legislation, are still
applicable, including those duties required under Section 34 of the Environmental Protection Act
1990 commonly referred to as the Duty of Care.
Under section 34, anyone who produces, keeps, imports or manages controlled waste must store
waste properly so that it does not escape from their control, transfer waste only to an appropriate
person, provide an accurate and full description of waste, and take reasonable measures to
ensure that your waste does not cause pollution or harm to human health.
Page 48

Page 49

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs)
3
OFFICIAL
3.0 POPs in WUDS
Many items of upholstered domestic seating (UDS) can contain elevated levels of POPs such
as: 
• Decabromodiphenyl Ether (DecaBDE);
• Pentabromodiphenyl Ether (PentaBDE);
• Tetrabromodiphenyl Ether (TetraBDE);
• Hexabromocyclododecane (HBCD).
In addition, the following hazardous chemicals are likely to be present:
• Antimony Trioxide, a carcinogenic synergist often used with DecaBDE;
• Medium Chain Chlorinated Paraffins (MCCP), often used in synthetic leather to make it
flexible;
• Other flame retardants, and hazardous components of PVC may also be present in some
items.
Evidence2 suggests that the average concentration for some of these POPs in items of UDS,
can be four times the legal concentration limit of 1000mg/kg, therefore the items require
destruction on becoming waste (WUDS).
4.0 What WUDS this guidance covers
For the purposes of this guidance WUDS is taken to mean waste:
• Sofas
• Sofa beds
• Armchairs
2  Assessing pollutants in soft furnishing waste for the Environment Agency | WRc (wrcgroup.com)
Page 49

Page 50

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
4
OFFICIAL
• Kitchen and dining room chairs
• Stools and foot stools
• Home office chairs
• Futons, bean bags and, floor and sofa cushions 
• Electrical recliner chairs3 
This list includes any part made of or containing leather, synthetic leather, other fabric, or foam. 
WUDS includes any item of seating of a household type from households or businesses.
Upholstered domestic seating from, for example, pubs, hotels, cafes and hospitals that is of a
household type should be assumed to contain POPs.
This guidance does not cover the following items as these are unlikely to contain POPs:
• non-upholstered items, such as wooden chairs without a cushioned or textile back, seat,
or arms;
• deckchairs;
• wastes from manufacturing new domestic seating that the manufacturer can
demonstrate do not contain POPs. 
5.0 You must not
You must not landfill items of WUDS, or wastes arising from their treatment, that may contain
POPs.
This includes: 
• segregated items of WUDS; 
3 Electrical recliner chairs are considered outside of scope of the Waste Electrical and Electronic Equipment (WEEE) Regulations 2013 (as
amended). Due to their potential to contain POPs they are required to be treated so that the POPs are destroyed. All foam and textiles must be
classified as POPs waste and sent for destruction.
Page 50

Page 51

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
5
OFFICIAL
• mixed waste containing items of WUDS;
• shredded or broken up waste arising from the treatment of waste containing items of
WUDS (including refuse-derived fuel (RDF) and solid recovered fuel (SRF));
• trommel fines from processes treating waste containing items of WUDS, including the
dust from air filtration systems. 
If you operate a landfill site, your waste acceptance procedures should include appropriate
checks to identify and exclude WUDS containing POPs. Any WUDS containing POPS which are
accepted should be quarantined prior to being sent to an appropriate facility for destruction.
Incinerator operators need to put contingency plans in place to manage WUDS containing POPs
for destruction. They cannot send this waste to landfill in the event of a planned or unplanned
shutdown. 
6.0 What you must do
If you collect, store or treat WUDS you need to have confidence that you are compliant with the
law. You should: 
• check if the WUDS, including stockpiles, contains POPs; 
• classify your waste correctly;  
• comply with the guidance on collection; 
• comply with the guidance on storage; 
• treat and dispose of WUDS appropriately. 
These points are expanded in the following five sections of guidance. 
6.1 Checking if WUDS contain POPs 
For items of WUDS, there will be no Material Safety Data Sheet (MSDS) and the date of
manufacture will be largely unknown. Therefore, you will need to rely on analytical methods such
Page 51

Page 52

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
6
OFFICIAL
as X -Ray Fluorescence (XRF) Scanners or laboratory analysis to assess the POPs content of
your WUDS. 
If you are unsure or unable to confirm the presence of POPs in the WUDS a precautionary
approach must be adopted, and you should assume that the waste contains POPs and the
relevant associated hazardous chemicals and manage the waste accordingly. 
6.2 Classification of WUDS containing or assumed to contain POPs
Under Section 34 of the Environmental Protection Act 1990 waste holders have a duty to describe
their waste fully, to ensure that it is handled appropriately, therefore where the presence of POPs
has been confirmed or should be assumed, the WUDS must be described as “20 03 07 – waste
domestic seating containing POPs”, on the waste transfer note 
This description should be accompanied with a list of all the POPs and other chemicals present
(or likely to be present) in the waste. If compositional analysis is not available, you can refer to
the POPs and other substances of concern detailed in the introduction section of this guidance
when describing your waste. 
Those receiving WUDS should have robust waste acceptance procedures in place to ensure that
the items containing POPs are not accepted. When receiving WUDS classified as not containing
POPS it is recommended, with a precautionary approach in mind, that you verify that
classification, for example, laboratory reports, XRF readouts or a waste classification report. The
lack of any evidence could suggest that the WUDS has been wrongly classified.
If a load of mixed waste that includes WUDS containing or assumed to contain POPs is taken to
a site then provided the operator has a permit that allows them to accept mixed residual and
bulky waste (20 03 01), or bulky waste (20 03 07) and there are no other issues, they can
accept it. 
Page 52

Page 53

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
7
OFFICIAL
Everyone dealing with the waste have a legal duty to comply with the POPS Regulations. We
encourage operators to advise their suppliers of the requirement not to mix waste and direct
them to the guidance.
If a carrier or producer is sending WUDS containing or assumed to contain POPs mixed with
other waste but not classifying it as POPs waste, then their details should be passed to SEPA
allowing us to follow up any potential non-compliance. 
6.3 Collection of WUDS containing POPs (POPs WUDS)
Producers and holders of waste are required to undertake all reasonable efforts to avoid, where
feasible, contamination of non-POPs waste with POPs waste. Failure to do so is an offence.  
By avoiding contamination of non-POPs waste, you will minimise the impact of handling, storing
and disposing of any POPs waste and the associated costs.
Where mixing occurs, the whole load of ‘mixed waste’ should be considered as being POPs
contaminated waste. If the POPs WUDS cannot be removed, the ‘mixed waste’ should be
deemed a POPs waste and sent for destruction even if the mixing has diluted the POPs content
to below the concentration limit.
Where separate collection is not feasible, POPs WUDS can be collected in the same vehicle as
other waste items as long as they: 
• Are not damaged, 
• Are not mixed with other waste, and;
• Are segregated from other waste during transfer and when unloaded; 
Page 53

Page 54

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs)
8
OFFICIAL
Please note that ‘on board’ segregation can be fixed or changeable however any measures
implemented during transport should be done so with the aim of ensuring that the above criteria
are met and must be appropriate for the waste type and the vehicle.
To prevent escape during transport, vehicles or containers used during the transportation of
whole WUDS or shredded WUDs and/or fines should be appropriate for the waste type, be
suitable for holding the waste, not overloaded and where appropriate covered.
As they rely on compaction, it is recommended that Refuse Collection Vehicles (RCVs) are not
used for the collection of POPs WUDs and collection in vans, lorries and caged vehicles is
preferable to RCVs because the WUDS are not compacted and damaged in these types of
vehicles. 
The use of vehicles other than RCVs also minimises the potential release of particulates which
may contain POPs because WUDS are much easier to load and unload from vans, lorries and
caged vehicles.
However, where WUDS are collected using an RCV it must:
• Not mix WUDS with any other wastes during the collection round;
• be able to contain any particulates and debris generated during the compaction within the
body of the vehicle.
If you choose to compact POPs WUDS you must take reasonable steps to prevent, contain and
collect any releases of POPs contaminated material or dust that the compaction produces.
If you choose to compact POPs WUDS it is recommended that the waste is compacted slowly to
confine all materials within the container where compaction occurs and the surrounding area. 
You must regularly check for particulates to make sure they are not released during compaction.
You can control particulate release by:
• misting and using sprays over the container;
Page 54

Page 55

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
9
OFFICIAL
• using suitably placed mobile dust suppression cannons; 
• spraying the surface of the waste before compaction using a backpack sprayer.   
Waste should be lightly misted not deluged to prevent the generation of POPs contaminated
water that will be problematic and costly to dispose of.
When compacted WUDS are being deposited from an RCV operators should ensure:
• a dedicated bay within a building is allocated for the WUDS, and
• a dust suppression system is in place to contain and control any particulates created
when the WUDS are ejected from the RCV and subsequently handled. 
Where possible the RCV should be dedicated to the collection of WUDS only. However, if the
RCV is used to collect other wastes as well as collecting WUDS then it should be cleaned
before it is used to collect loads of non-POPs waste. This can be done for example by using a
dedicated vacuum cleaner to remove foam, textiles and particulates from within the vehicle
body.  
Where compaction of WUDS is carried out using mobile plant within a building misting sprays
and other particulate control measures should be in place to minimise particulate generation and
prevent contamination of other wastes.
Any compacted WUDS, contaminated material or fines must be sent for destruction (see section
on Treatment below).
6.4 Storage of WUDS containing POPs (POPs WUDS)
If authorised to accept household mixed residual and bulky waste (20 03 01) or bulky waste (20
03 07) then you can accept POPs WUDS however you must meet the following storage criteria.
Where possible POPS WUDS should be segregated and kept separate from other wastes. 
You must sort and store POPs WUDS in a way that does not damage the WUDS so as to cause
release of POPs or contaminate other waste. 
Page 55

Page 56

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
10 
OFFICIAL
Storage should be on an impermeable surface or in such a way to prevent any release to the
environment.
Where the foam, cover, lining or wadding materials are exposed or released, cross
contamination with non-POPs WUDS or any other items of waste is possible. Where such ‘cross
contamination’ occurs, the ‘mixed waste’ should be considered as being a POPs contaminated
waste and sent for destruction.  For example, cross contamination could occur as a result of the
storage of damaged POPs WUDS with Non-POPs WUDs. 
6.5 Treatment of WUDS containing POPs (POPS WUDS)
6.5.1 Overall Treatment Objective
You must ensure that you manage POPs WUDS, and any other associated wastes, such as
POPs contaminated wastes produced because of mis-segregation etc, in such a way that the
POPs are destroyed or irreversibly transformed. You must destroy the POPs contaminated
waste even if the mixing has diluted the POPs concentration below the relevant limits.
At the time of publication of this guidance, based on best available research and international
guidance6, treatment for POPs WUDS is limited to destruction via municipal waste incinerator,
hazardous waste incinerator or cement kiln.  
Before transferring your waste to an operator for treatment or destruction you must ensure that
the chosen method of treatment and/or disposal is appropriate for the POPs chemical(s)
contained in the waste.
Please note that if the treatment does not destroy the POPs, any waste that results from the
treatment, and which contains these POPs, is also POPs waste. You must destroy the POPs in
this treated waste even if dilution has lowered the POPs concentration below the relevant limits.   
Page 56

Page 57

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
11 
OFFICIAL
6.5.2 Separating POPs from other materials
Separating materials containing POPs from other materials is regarded as a treatment
operation. Foam and textiles containing POPs can be removed from other materials in items of
WUDS where the separation activity is covered by a suitable waste management authorisation. 
For manual processes, you should ensure that:
• all foam and textiles are completely removed, and you manage any part of the item of
WUDS with foam and textile attached to it as a POPs waste;
• you prevent or contain any dust, or fragments of foam and textile released from the
WUDS and you must manage the dust and fragments as POPs waste;
• you store separated material containing POPs inside a building, under cover, or in a
sealed container;
• no POPs are released to the sewer or surface water. 
For mechanical treatment processes, you should also follow the guidance in the treatment
section, below.
6.5.3 Shredding of POPs WUDS 
Operators have expressed an interest in shredding POPs WUDS before destruction by
incineration. This requires an authorisation.
Shredded material that has been prepared so that it meets the specification required for
destination incinerator or cement kiln may be coded 19 12 10 but must be clearly described as
containing POPs from WUDS.
If shredding POPs WUDS you should meet the following criteria to mitigate fugitive emissions to
air and to prevent particulates collecting in site drainage systems and being released into
surface water, groundwater or the wider environment either directly or indirectly:
• shredding plant should be located on an impermeable surface inside a building or under
cover;
Page 57

Page 58

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
12 
OFFICIAL
• Misting and spray systems must be used to control particulates, however these should be
operated so that they do not create large amounts of contaminated water;
• there should be no unabated point source or fugitive emissions of particulate from the
plant or the building. Fugitive emissions of particulates should be controlled with one of
the following: 
o local extraction to abatement;
o full building extraction under negative pressure to abatement;
• Shredding should be located away from drains. Drain mats and blockers could be used to
prevent runoff entering drains should leaks etc occur;
• Bag filters on abatement plant should be designed to release particulates below 5mg/m3.
They should be fitted with continuous and alarmed pressure monitoring to make sure the
filters are working correctly. 
If storing shredded POPS WUDS it should be on an impermeable surface and either inside a
building or under cover, or in sealed containers, or baled and securely wrapped. 
If shredded WUDS are stored loose in open fronted bays under cover, particulate generation
could be minimised by using a binder such as calcium magnesium acetate, minimising handling
and if necessary, using windbreaks.
When open fronted bays are used for storage and there is a risk of particulates being generated
during loading and depositing the shredded WUDS the impacts can be mitigated by using
suitably placed mobile dust suppression cannons or lightly misting the surface of the waste.
The only time you can blend segregated POPs WUDS with other waste is prior to destruction at
the point of treatment, for example, to make loading easier, control calorific value or optimise
combustion. You should blend in such a way that uses the least amount of non-POPs waste
necessary to avoid release of particulates containing POPs and contaminating more waste than
necessary.
Where blending occurs operators should have contingency plans in place to ensure that any
mixed waste containing POPS waste which is unable to be destroyed can be managed in
Page 58

Page 59

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs)
13
OFFICIAL
appropriate manner for example diverted elsewhere for destruction or stored on site until it can
be destroyed.
Where the shredding of WUDS removes metal and produces a visually clean metal waste that is
not contaminated with WUDS i.e., does not contain fragments of foam or textiles and other non-
metal waste. it can be treated as metal waste and coded 19 12 02.
Where the metal fraction still contains fragments of foam or textiles from the WUDS and other
non-metal waste it can be described 19 12 12 and stored in the manner set out below.
Note that the 19 12 12 code has been agreed for the metal from shredded WUDs only. It is
based on the analysis information within the 2021 WRC report on POPs in waste domestic
seating and may be subject to review, should further analysis or information emerge indicating
the hazardous thresholds for MCCP or Antimony Trioxide or other hazardous substances are
breached.
POPs may leach or wash out in particulates from this waste so it should be stored either:
• under weatherproof covering; or
• in covered skips or containers or,
• In skips/containers under weatherproof covering.
This waste must be characterised in accordance with WM3, coded either 19 12 11* or 19 12 12
and described as containing POPs if it contains other non-metallic wastes including items of
foam and fabric that may contain POPs. This waste stream can be sent for smelting at a suitably
permitted site, or for further processing to remove the POPs fraction from the metal fraction.
Where metal is sent to an intermediate site to further process and segregate the metal from
POPS waste the operator of that site should be made aware that:
• The load contains POPs;
• The load should be stored and handled it in a manner that prevents any releases to air,
land, sewer or groundwater;
Page 59

Page 60

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs) 
14 
OFFICIAL
• The non-metal waste must be described as containing POPs and sent for RDF or
incineration. 
All fines and particulates produced when shredding or handling POPS WUDS must be sent for
incineration. 
Fines must be characterised in accordance with WM3, coded either 19 12 11* or 19 12 12 and
described as containing POPs from domestic seating. 
Fines should be packaged to prevent particulate release and either stored in a building or under
cover.
This guidance applies only in Scotland. The terms of this guidance may be subject to
periodical review and be changed or withdrawn in light of technological, regulatory or
legislative changes, future government guidance or experience of its use. SEPA reserves
its discretion to depart from the guidance outlined here and to take appropriate action to
avoid any risk of pollution or harm to human health or the environment 
Page 60

Page 61

Guidance on the management of Waste Upholstered Domestic Seating (WUDS) containing
Persistent Organic Pollutants (POPs)
15
OFFICIAL
For information on accessing this document in an alternative format or language, please contact
SEPA by emailing equalities@sepa.org.uk
If you are a user of British Sign Language (BSL), the Contact Scotland BSL service gives you
access to an online interpreter, enabling you to communicate with us using sign language.
contactscotland-bsl.org
Page 61

Page 62

This page is intentionally left blank

Page 63

APPENDIX 2 – RECYCLING INFRASTRUCTURE FUND – BREAKDOWN OF
WORKS AND TIMESCALES 
Recycling Infrastructure Fund – breakdown of works and timescales 
Item No. Year and
quarter of
planned
expenditure
Item Description Funding
Award (excl.
VAT)
C1 Q2 / 2025/26 New Hard Standing (concrete area for
containers and new bays)
£278,402.40
C2 Q2 / 2025/26 New Site Access Areas £187,012.80
C3 Q4 / 2024/25 Directional recycling centre signs (one sign per
site)
£892.80
C4 Q4 / 2024/25 Magnetic skip signs for each site (17 signs per
site, 6 sites)
£4,111.20
C5 Q1 / 2025/26 New wood and garden waste bays at Gott Bay
(Tiree), Glengorm (Mull) and Gartbreck (Islay) (6
bays altogether using Quikblocs)
£119,052.00
C6 Q1 / 2025/26 6 x WEEE 40ft Containers (1 per site, 6 sites) £55,440.00
C7 Q1 / 2025/26 4 x New Reuse Containers at Bonaveh Isle of
Colonsay, Cliad Isle of Coll, Gartbreck Isle of
Islay, and Gott Bay Isle of Tiree.
£17,280.00
C8 Q1 / 2025/26 Improvements to existing Reuse Containers at
Glengorm (Mull) and Blackhill (Helensburgh),
including repaint, shelves and rails, and shelves
and rails for new containers
£4,668.00
C9 Q2 / 2025/26 3 x Loading Ramps (one each at Gott Bay
(Tiree), Glengorm (Mull) and Gartbreck (Islay))
£144,000.00  
Sub-total £810.859.20  
Contingency at 10% to cover for increases in
construction materials due to current market
conditions
£81,085.92
Total: £891,945.12 
Page 63

Page 64

This page is intentionally left blank

Page 65

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                   30 NOVEMBER 2023
SERVICES                     
PLAY PARK FUNDING – UPDATE REPORT NO 3 
1.0 EXECUTIVE SUMMARY 
1.1 At the December 2022 Environment, Development and Infrastructure Committee
(EDI), a Play Park Funding report was noted by members with an agreement that
officers would submit a further report outlining the suggested process and
timelines proposing further engagement with other groups, including Youth
Forums and relevant Community Councils. The original report can be found at
the following link: December 2022 EDI Play Park Funding Report 
1.2 Subsequent update reports were presented to the March 2023 and August EDI
Committees as per the following links: March 2023 EDI Play Park update Report.
August 2023 EDI Play Park Update report 2 
1.3 In August 2022, the Scottish Government confirmed a full 5 year funding package
to all Scottish Local Authorities from 2020/21 through to 2025/26.  Argyll and Bute
Council will receive a total of £938k for Play Park funding. All Scottish Councils
have received funding through the Capital Allocation for Renewal of Play Parks
Fund for investment in play park equipment. 
1.4 The March 2023 EDI Committee gave consideration to a report outlining a
suggested process and timelines for proposing further engagement with other
groups, including Youth Forums and relevant Community Councils in relation
to the Play Park Funding Award of £938k which had been awarded by the
Scottish Government for the 28 play parks being renewed in Argyll and Bute in
a programme running until 2025/26. The EDI Committee also agreed the
proposed timeline. 
1.5 The Scottish Government commitment was to ensure that all children have
access to quality play in their own community and the budget was specific in
that the funding was for renewing existing play parks. A definition/scope of
investment was also issued as part of the grant offer and is as below:- 
 The agreed definition of an eligible play park is one which is local
authority owned, managed or maintained sites, designated for play,
which are free to access and open to all. Play parks in private ownership,
those that require an entry fee or those only available to specific groups
/ with conditions for entry would be outwith scope. We would expect that
play parks with equipment (swings, slides etc) aimed at children aged 0-
Page 65 Agenda Item 9

Page 66

14 would be included as would other facilities used by the same age
group (e.g. pump tracks), but MUGAs (Multi Use Game Areas) or
dedicated sports fields would be outwith scope. 
1.6 Area Committee Business days with Elected members have already taken place
and a further business day for each area took place over recent weeks where
members agreed to funding and a priority list for each play park as listed below:   
AREA PLAY PARK  
Allocation of funding based on
estimated costs. 
Helensbur
gh and
Lomond
Total
budget
£368,500
Hermitage £30k
Kirkmichael £25k 
Red Guantlet £20k 
Arrochar £40k (High Priority Park)
Bendarroch £40k (High Priority Park)
Howie £40k
Kidston £20k
Kilcreggan/C
ove
£40k
Rhu £50k (Medium Priority Park)
Tarbet £20k
Cardross £15k
Bute and
Cowal
Total
Budget
£167,500 
Meadows £25k (Medium Priority Park)
Port
Bannatyne
£30k
Sandbank £30k (High Priority Park)
Glen Morag £40k (Medium Priority Park)
Dunoon
Skate Park
£25k
Mid Argyll,
Kintyre
and the
Islands
Total
Budget
£368,500 
Ardrishaig
KGV
£33k (High Priority Park)
Bayview £25k
Tarbert Already has £80k for new play
park and will be supplemented
by £20k funding. (High Priority
Park)
Page 66

Page 67

Kinloch £5k, however proposal to
remove this park as Lochend in
approx. 150metres away. This
needs to be agreed locally first.
Lochend £33k (Medium Priority Park)
Hillside £33k
Meadows  £50k
Stewarton £20k
Jock’s Boat £50k
Bengullion
Road Skate
Park
£10k
Ramsay Hill,
Port Ellen
£30k – in partnership with
South Islay Development who
are part funding the movement
and refitting of the play park
nearby.
Oban,
Lorn and
the Isles
Total
Budget
£33,500 
Tobermory £33.5k 
1.7 Whilst this has been agreed at Area Committee, Community Councils and
Disability Forums will now be contacted to inform them of the proposed spend on
equipment and groundworks to ensure maximum engagement locally. 
1.8 The officer managing this project has already been in touch with the Tarbert
Community Council who have advised that the initial plan to redevelop the play
park was not what the local community wanted.  As such a revised approach has
been agreed to tender a new design incorporating the equipment requested by
the local Tarbert Play Park Group as well as the community councils’ suggestions.
This will be progressed as a priority. 
1.9 A partnership approach has been agreed with South Islay Development (SID)
who are in the process of redeveloping the Ramsay Hall Area which will
incorporate the play park. The supplementary funding of £30k will allow a better
more improved play park and the SID are currently reviewing their initial plans and
will come back in the new year with a suggested location plan of equipment and
materials for agreement. 
1.10 It is intended to tender for all play parks, however suitable priority can be agreed
in line with the previously agreed priority parks when tenders are returned. The
reason for this is that previously we have tried tendering for the first two years with
Page 67

Page 68

limited budgets with no success, and it is understood that a larger budget will
encourage more tender bids. 
1.11 Should there be further issues with no tender bids received officers are already
looking at a mixed model of delivery in house or in partnership with local
businesses. This must however be done in line with strict legislative restrictions
on children’s play park equipment carried out by qualified individuals. 
1.12  Officers suggest the following updated timeline is appropriate:- 
ACTION  TIMESCALE 
Engagement with Community Councils and
Education Department 
Commenced March-May 2023 Now
complete.
Engagement with Disability Forums  Commencing – Winter 2023
Procurement process which may need to 
include a mixed model delivery of the
equipment and fitting and depends on
tender bids (which will last in the region of 8
– 12 weeks) 
Expected to commence early 2024
Installations Expected to commence Spring 2024
(dependent on procurement process
as above) 
2.0  RECOMMENDATIONS 
2.1  It is recommended that the Environment, Development and Infrastructure
Committee:- 
 Endorse the Area Committee priorities for each play park in their area and
allocation of funding as per 1.6 above.
 Note and consider the updates regarding the Tarbet Play park and the
partnership approach to Port Ellen play park in Islay. 
 Note the updated timelines.   
3.0   CONCLUSION 
3.1   The Scottish Government has allocated a total of £938k for Play Park funding to 
Argyll and Bute Council for investment in play park equipment through to 2025/26
from the Capital Allocation for Renewal of Play Parks Fund. This report updates
on the engagement process covering local Elected Members, community
councils, education and disability forums. 
Page 68

Page 69

4.0  IMPLICATIONS 
4.1 Policy – In line with previous decision and will also pay regard to procurement
policy. 
4.2 Financial – Mainly funded from Scottish Government play park capital grant,
supplemented by other small pots of funding. 
4.3  Legal – None known. 
4.4  HR – None known. 
4.5  Fairer Scotland Duty: None known. 
4.5.1   Equalities - protected characteristics – Engagement will take place with
appropriate groups, including the disability forum, to provide a positive impact
on our young people. 
4.5.2   Socio-economic Duty – None known. 
4.5.3 Islands – Elements of renewal on all council owned play parks, which
therefore will not adversely affect islands. 
4.6 Climate Change – We will endeavour to minimise carbon footprint of this
project. 
4.7  Risk – Failure to deliver within the allotted Scottish Government timescales may
result in losing the budget allocated. 
4.8  Customer Service – The intention of this funding is to provide better facilities for
our customers. 
Executive Director with responsibility for Road and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Climate Change and Environment Services, Councillor Ross
Moreland 
November 2023                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager 
Hugh.ONeill@argyll-bute.gov.uk 
Page 69

Page 70

This page is intentionally left blank

Page 71

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND
INFRASTUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
30 NOVEMBER 2023 
OCTOBER 2023 WEATHER EVENT – UPDATE 
1.0 INTRODUCTION
1.1 Following a period of wet weather which left ground conditions very wet and in many
cases saturated, over a months’ worth of rain fell over a 36 hour period starting Friday
6 October 2023 and running into Saturday 7 October 2023. 
1.2 Conditions was so severe that by mid-morning on Saturday 7 October, Police Scotland
had declared a major incident and a multiagency tactical response was assembled to
ensure that the incident could be managed across the many agencies and communities
involved. 
1.3 Transport connections into and out of Argyll and Bute were severely compromised on
Saturday 7 October and for a period of time, all of the trunk roads and many of the local
roads were impassable. Numerous people became stranded due to flood waters,
landslips and damaged structures. Mountain rescue were deployed along with the
coastguard who arranged ground units and a helicopter to support the response to assist
Police Scotland who were coordinating the responses in line with protocol for major
incident response. 
1.4 The Council response was significant with reception centres and catering put in place
to accommodate individuals who were unable to get home, together with many staff
from Roads and Infrastructure assisted by several contractors involved in responding to
the chaos and disruption to public infrastructure caused by the event. 
2.0 RECOMMENDATIONS
2.1 It is recommended that Members of the Environment, Development and Infrastructure
Committee consider and note this report. 
3.0 DETAIL
3.1 We are seeing an increasing number of weather events locally, nationally and
internationally no doubt linked to climate change.  In recent years in Argyll and Bute we
have had several weather events including: 
 West of Mull bridge wash out At the foot of Ben More July 2012;
Page 71 Agenda Item 10

Page 72

 Clachan snow event March 2013 – significant snow fall blocked the road and
the weight of frozen snow on power lines resulted in power lines breaking and
several thousand households being without power;
 Beast from the east February 2018;
 Sea wall wash out Bute December 2021;
 Numerous flood events in locations such as Lochavullin Oban, East and West
Clyde Street Helensburgh, Rothesay, Campbeltown (flood prevention works
underway) Lochgilphead Front Green etc.
3.2 The map below shows each of the locations where there was disruption caused across
Argyll and Bute’s road network on 7 October 2023. It is interesting to note that the
weather band was very localised sweeping through the central part of Argyll and Bute,
this is illustrated with the damage caused. Also, and perhaps quite unusual, is that the
majority of damage caused took place inland rather than on the coast. This very local
weather and damage is peculiar to this storm event. As Members will be all too familiar
with, often Argyll and Bute, with over 3000 miles of coastline, regularly suffers coastal
damage during storms, the recent example being the sea wall on Bute where around
100m was extensively damaged in December 2021. 
The map below shows each of the locations where there was disruption caused across
Argyll and Bute’s road network on 7 October 2023 
Page 72

Page 73

3.3  The second map below shows the 214kmof the Council’s road network which is within
25m of the sea and vulnerable to coastal damage. 
Map of Argyll and Bute showing areas where the centre line of public roads is within
25cm of Mean High Water Springs in plan view.  Note that only roads where Argyll and
Bute Council is Roads Authority (as at 4 September 2014) are shown.   
3.4 Regular updates have been provided to Members and the public following the October
rain event and on Monday 6 November a presentation was given to Members. This
presentation can be viewed here: ELECTED MEMBER SEMINARS 2023 | The Hub 
3.5 The works carried out by Roads and Infrastructure following the rain event were
extensive with dozens of locations requiring attention from simple cleansing of a small
drain to significant landslides and bridge replacements. Appendix 1 details some of the
works undertaken/ongoing. This is not an exhaustive list, these are just examples of the
many issues which Argyll and Bute were faced with. 
3.6 Whilst the costs incurred from this weather event are ongoing, we expect to see a final
cost exceeding £8M. Some of these costs will be eligible for funding through the Bellwin
Scheme although many costs may well fall to the Council. 
Page 73

Page 74

Next Steps
3.7 Our initial focus is to complete the various works still outstanding and to continue to
monitor slopes where debris flows may affect the road network. These works continue
and regular updates will be provided on the Council’s website and also through the RIS
weekly briefings to Members.
3.8 Climate change is a significant challenge to the Council for a number of reasons but not
least it is a challenge for the road and transport infrastructure. This report highlights
some of the challenges faced recently and over the last decade or so. The road and
wider transport system provides the economic backbone for our communities. We need
to have infrastructure which is fit for purpose and sufficiently resilient to withstand the
increasing weather challenges we are experiencing which are linked closely to climate
change. The building of a bypass on the A816, strengthening bridges, and modifying
roadside ditches are all adaptations being progressed to better accommodate some of
the climate changes we are seeing. However, more will be needed to be done and whilst
the works mentioned above will increase our infrastructure’s resilience to future weather
events, the network overall is fragile and unable to cope with significant weather events. 
3.9 It will be necessary to see more infrastructure investment put in place to enable climate
change adaptations to be made. The level of investment will be significant and the
Council will need to consider how its funding can be assembled and what lobbying can
be progressed with Scottish and UK Governments. 
4.0 CONCLUSION
4.1 This report summarises the rain event which caused significant travel disruption and
damage during the weekend of 7 October. The report and appendix also summarises
the extent of works that have been carried out to repair the damage and considers what
our next steps should be as detailed in paragraph 3.9 above.   
5.0 IMPLICATIONS
5.1 Policy - policies in place for climate change, costal protection etc where applicable these
policies are being worked to.
5.2 Financial - new costs pressures have no identified funds to respond to the infrastructure
damage. A Bellwin claim is being progressed for eligible costs and works not eligible for
Bellwin will need to be funded.
5.3  Legal – various land agreements necessary for individual locations.   
5.4  HR – none known.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known. 
5.5.2   Socio-economic Duty – none known. 
5.5.3  Islands – none known.
Page 74

Page 75

5.6 Climate Change – the impact of the storm is very closely linked to climate change and
the October event has highlighted to need for further adaptation to be made to
infrastructure to increase our resilience to future weather events. The level of
investment to improve resilience is expected to be significant.  
5.7 Risk – significant risk of similar future events impacting our infrastructure.  
5.8  Customer Service – none known.   
Kirsty Flanagan, Executive Director with responsibility for Roads and Infrastructure 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
November 2023                                      
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
Jim.Smith@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – October Weather Event Update 
Page 75

Page 76

This page is intentionally left blank

Page 77

Ardfern Slip A816 – rock stabilisation and emergency by-pass scheduled to
open mid-December, opening of main A816 still to be confirmed
The emergency phase of this project
is still very much underway.
Thousands of tonnes of material
which flowed from the hillside onto
the road have been moved to a
disused quarry in the ownership of
Forest and Land Scotland. Full
SEPA consents have been obtained
for this landfill/quarry restoration
work. Material continues to flow
down the hillside, particularly in wet
conditions and the clean-up
continues. Parts of the hillside have
been ‘scaled’ of loose rocks
however, many rocks have yet to be
moved and more rocks are emerging following rain which washes away the slurry
covering some of the rocks and exposes more with soils and silt washing down the
hillside changing its shape and
presenting ever new challenges. To
date the largest of the rocks has
been measured at 220 + tonnes.
Once the debris flow material is
sufficiently cleared a bund will be
formed at the side of the existing
road which is designed to hold back
future debris flow material. Modelling work will be
undertaken to forecast future slope flow and the
bund will be built accordingly.
The likelihood of future debris flow events is so
high that we are also progressing with an
alternative emergency route as per the plan
below. This emergency route will be used when
weather conditions are such that the original road
is not safe. The land agreement for the road is in
place and works are underway. Archaeological
Page 77

Page 78

and ecology appraisals have already been carried out. 
The land agreement for the emergency route has been completed and currently we
are on target for the emergency route to be complete by 15 December with a caveat
that extreme weather conditions may delay works on the ground. We anticipate the
emergency route will be available before we are able to safely reopen the original road. 
Medium to long term we will progress the emergency route to be upgraded to become
a permanent route moving traffic away from the problematic hillside. A permanent road
will take 2 – 5 years for the consents and permissions hence the reason for
progressing with an emergency road which will have a smaller footprint and is
buildable in weeks rather than years due to the emergency situation. It is expected
that the emergency road will only be utilised when weather is such that there is a risk
of further landslide. Similar to the process used by Transport Scotland and BEAR
Scotland, we will have a risk matrix in place which uses factors such as saturation
levels on the hillside, forecast rainfall with this also being supplemented by CCTV
cameras which enable remote monitoring of the hillside. These safety measures will
enable the original route on the A816 to be used as the normal route with the
emergency road only being mobilised when there is a risk of landslide.
Top image showing the extent of the landslip and debris flow from 7 October, middle
image of typical rocks which been ‘falling’ from the hillside - these will be used in
forming the bund to help to catch material from future flows and bottom image of a
large rock being broken up using a hydraulic pecker attached to a large excavator. 
The image to the right shows the extent of
the Ardfern slip in green (at least 3
separate slip events took place) the purple
shading is the ditch/pit which would catch
any future flow, the blue line is a bund to
keep the majority of any future flow in the
ditch and the red is the proposed
emergency road which takes traffic away
from the slip affected area and provides a
safe alternative route during future
weather events. 
Loch Awe C30 – rock/soil nails and stabilisation
The embankment supporting the road at the C30 washed away near Kilmaha. The
slope is very steep and the material forming the embankment is not particularly strong. 
Initial stabilisation works have been carried out including some rock infill and soil
nailing (large diameter bolts which are drilled and grouted into the ground). Geological
engineering design works are ongoing alongside the physical works on site. The
design works will finalise the design of slope remedial work for the washed out
supporting embankment. 
Page 78

Page 79

Glen Lean – B836 – Temporary Bridge
A temporary bridge is on
target to be built on the
alignment of the old bridge by
24th November. This will allow
the Glen Lean road to be
reopened whilst the bridge
damaged in the October rain
event is demolished and a
new bridge rebuilt. This target
date is subject to reasonable
weather conditions and no
other issues coming to light on
site. 
The image above shows where the temporary bridge will go which is to the north of
the storm damaged bridge. 
Lochgoilhead – B828 Slope stabilisation and bridge works
Emergency bridge works to deal with scour
damage (water eroding the bridge
abutment/foundation) have been
completed and work is currently underway
stabilising the embankment, which
supports the road. There are a number of
locations along the B828 where rock nailing
and support beams are being installed. 
Image above detailing diversion of river flow and over
pumping to allow concrete to be laid to support the
bridge structure with the concrete replacing masonry
washed away with the force of the river. 
Bottom left image shows reinforced concrete edge
beam being constructed to support the carriageway. 
Page 79

Page 80

Scammadale – retaining structure and
stabilisation
The damage the Scammadale road
embankment was due to exceptionally high
river levels washing away the embankment.
The repair to this embankment is complex and
design works are nearing completion with site
works commencing over the next couple of
weeks. In the meantime we continue to liaise
with the residents regarding vehicles over 3.5
tonnes accessing the glen. Work is due on site by the
end of November. 
Top image of barriers to keep traffic from the weak
edge and right image showing the extent of the affected
banking – note the road is at the top of the embankment
and this shot was taken before the barriers shown on
the right were installed. 
Kilninver Bridge
Kilninver Bridge is downstream from the
Scammadale embankment slip, on the River
Euchar, which is fed from Loch Scammadale. 
The bridge suffered significant abutment scour
during the rain event. Extensive emergency
works have been carried out and some rock
armour protection work will be carried out in due
course to the upstream side of the bridge. The
initial works were carried out at pace in order to
save the bridge from further scour damage to
the bridge’s abutment. Any further damage would have very likely resulted in the
bridge being lost.
Page 80

Page 81

Initially a weight limit reduction was applied to the bridge. This has now been lifted and
the bridge is open to 44 tonne vehicles. 44 tonne
being heaviest vehicle allowed on UK roads
unless an abnormal load exemption is issued.
Top image showing the wooden formwork in
place which supported the fibre reinforced
concrete until it set. Bottom image on the right
showing the formwork being erected. The
carpenters in the shot help to give scale to the
repair works. 
Kilmelford Bridge 
The initial emergency phase commenced on
Thursday 19 October when a major defect was
found on the bridge. The defect was so
significant there was only one option – to
demolish the bridge for public safety.
The initial plan was to demolish the old bridge
and put in place a temporary ‘forest’ type
corrugated steel pipe type bridge. However, we
were very fortunate and found a number of
concrete culvert/bridge sections in Highland
which were the correct size and were available. This enabled a rapid construction
phase which had the road open to 44 tonne vehicles in an impressive 2 weeks’ time
period. 
With the bridge and road now open to all traffic
we have commenced work to carry out a
hydrology study. This is a complex and
technical piece of works which is required to
design the training walls (the walls which direct
the water flow into and out of the bridge
structure), to satisfy SEPA in terms of
retrospective consents and to ensure that the
bridge will not have any adverse effect on the
river. There is additional design work to carry
out in terms of adding a segregated pedestrian route and finishing off the surfacing
and parapet (edge of bridge) walls. So whilst the initial emergency phase of the bridge
works is complete there remains much design, liaison with consenting bodies and
physical works 
Page 81

Page 82

Top image showing the damage to the bridge and the bottom picture detailing the new
concrete bridge sections prior to the reinforced concrete slab and surfacing being
placed. 
Slope Stability – hillsides above the A815
A contract has been put in place with
a geological engineering expert for
ongoing monitoring of the scars left on
the A815. In addition to the monitoring
the contacted works include advising
on future flow mitigation measures –
these at their most basic will be
deeper ‘climate adapted’ drainage
channels to intercept small flow
events. The image to the right shows
some of the scars on the hillside above the A815 which are being monitored.
Page 82

Page 83

Environment, Development and Infrastructure Committee Work Plan 2023/24 
This is an outline plan to facilitate forward planning of reports to the Environment, Development and Infrastructure Committee. 
Date  Title Service/Officer Date Due Comments
30 November 2023 
Helensburgh Wooden Pier -
Update
Development and
Economic Growth   
Argyll and Bute Housing
Emergency – Progress
Report
Development and
Economic Growth 
Argyll and Bute Housing
Emergency – Project
Officer Resource
Development and
Economic Growth   
Cemetery Asset – Annual
Report 
Road and Infrastructure
Services 
Play Parks Update  Road and Infrastructure
Services   
Waste Update Road and Infrastructure
Services   
Latest Update on the
Settlement Project Support
Officer Actions
Development and
Economic Growth   
October 2023 Weather
Event – Update
Road and Infrastructure
Services  
21 March 2024 
Roads Reconstruction
Capital Programme
Road and Infrastructure
Services   
Waste Update Road and Infrastructure
Services   
Annual Status and Options
Report (ASOR) Annual
Report 
Roads and Infrastructure
Services 
Route Optimisation  Roads and Infrastructure
Services  
Page 83
Agenda Item
11

Page 84

Environment, Development and Infrastructure Committee Work Plan 2023/24 
Update on the Settlement
Project Support Officer
Actions
Development and
Economic Growth   
Housing Emergency
Update 
Development and
Economic Growth   
Digital Update  Development and
Economic Growth 
Footpath Improvements  Roads and Infrastructure
Services 
Transformational Projects
Regeneration Team Large
Scale Projects Update  
Development and
Economic Growth 
Six monthly update 
20 June 2024 
Roads Capital Programme
Member Engagement 
Roads and Infrastructure
Services 
7 May 2024 
PC Door Installation Update  Roads and Infrastructure
Services 
Future
Items     
Shared Prosperity Fund Development and
Economic Growth   
EVC Update  Roads and Infrastructure
Services 
Roads Development
Framework 
Roads and Infrastructure
Services 
Page 84