October Weather Event Update - Appendix 1

Argyll and Bute Council · 30 November 2023
Back to Environment, Development and Infrastructure Committee — 30 November 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Ardfern Slip A816 – rock stabilisation and emergency by-pass scheduled to
open mid-December, opening of main A816 still to be confirmed
The emergency phase of this project
is still very much underway.
Thousands of tonnes of material
which flowed from the hillside onto
the road have been moved to a
disused quarry in the ownership of
Forest and Land Scotland. Full
SEPA consents have been obtained
for this landfill/quarry restoration
work. Material continues to flow
down the hillside, particularly in wet
conditions and the clean-up
continues. Parts of the hillside have
been ‘scaled’ of loose rocks
however, many rocks have yet to be
moved and more rocks are emerging following rain which washes away the slurry
covering some of the rocks and exposes more with soils and silt washing down the
hillside changing its shape and
presenting ever new challenges. To
date the largest of the rocks has
been measured at 220 + tonnes.
Once the debris flow material is
sufficiently cleared a bund will be
formed at the side of the existing
road which is designed to hold back
future debris flow material. Modelling work will be
undertaken to forecast future slope flow and the
bund will be built accordingly.
The likelihood of future debris flow events is so
high that we are also progressing with an
alternative emergency route as per the plan
below. This emergency route will be used when
weather conditions are such that the original road
is not safe. The land agreement for the road is in
place and works are underway. Archaeological

Page 2

and ecology appraisals have already been carried out. 
The land agreement for the emergency route has been completed and currently we
are on target for the emergency route to be complete by 15 December with a caveat
that extreme weather conditions may delay works on the ground. We anticipate the
emergency route will be available before we are able to safely reopen the original road. 
Medium to long term we will progress the emergency route to be upgraded to become
a permanent route moving traffic away from the problematic hillside. A permanent road
will take 2 – 5 years for the consents and permissions hence the reason for
progressing with an emergency road which will have a smaller footprint and is
buildable in weeks rather than years due to the emergency situation. It is expected
that the emergency road will only be utilised when weather is such that there is a risk
of further landslide. Similar to the process used by Transport Scotland and BEAR
Scotland, we will have a risk matrix in place which uses factors such as saturation
levels on the hillside, forecast rainfall with this also being supplemented by CCTV
cameras which enable remote monitoring of the hillside. These safety measures will
enable the original route on the A816 to be used as the normal route with the
emergency road only being mobilised when there is a risk of landslide.
Top image showing the extent of the landslip and debris flow from 7 October, middle
image of typical rocks which been ‘falling’ from the hillside - these will be used in
forming the bund to help to catch material from future flows and bottom image of a
large rock being broken up using a hydraulic pecker attached to a large excavator. 
The image to the right shows the extent of
the Ardfern slip in green (at least 3
separate slip events took place) the purple
shading is the ditch/pit which would catch
any future flow, the blue line is a bund to
keep the majority of any future flow in the
ditch and the red is the proposed
emergency road which takes traffic away
from the slip affected area and provides a
safe alternative route during future
weather events. 
Loch Awe C30 – rock/soil nails and stabilisation
The embankment supporting the road at the C30 washed away near Kilmaha. The
slope is very steep and the material forming the embankment is not particularly strong. 
Initial stabilisation works have been carried out including some rock infill and soil
nailing (large diameter bolts which are drilled and grouted into the ground). Geological
engineering design works are ongoing alongside the physical works on site. The
design works will finalise the design of slope remedial work for the washed out
supporting embankment.

Page 3

Glen Lean – B836 – Temporary Bridge
A temporary bridge is on
target to be built on the
alignment of the old bridge by
24th November. This will allow
the Glen Lean road to be
reopened whilst the bridge
damaged in the October rain
event is demolished and a
new bridge rebuilt. This target
date is subject to reasonable
weather conditions and no
other issues coming to light on
site. 
The image above shows where the temporary bridge will go which is to the north of
the storm damaged bridge. 
Lochgoilhead – B828 Slope stabilisation and bridge works
Emergency bridge works to deal with scour
damage (water eroding the bridge
abutment/foundation) have been
completed and work is currently underway
stabilising the embankment, which
supports the road. There are a number of
locations along the B828 where rock nailing
and support beams are being installed. 
Image above detailing diversion of river flow and over
pumping to allow concrete to be laid to support the
bridge structure with the concrete replacing masonry
washed away with the force of the river. 
Bottom left image shows reinforced concrete edge
beam being constructed to support the carriageway.

Page 4

Scammadale – retaining structure and
stabilisation
The damage the Scammadale road
embankment was due to exceptionally high
river levels washing away the embankment.
The repair to this embankment is complex and
design works are nearing completion with site
works commencing over the next couple of
weeks. In the meantime we continue to liaise
with the residents regarding vehicles over 3.5
tonnes accessing the glen. Work is due on site by the
end of November. 
Top image of barriers to keep traffic from the weak
edge and right image showing the extent of the affected
banking – note the road is at the top of the embankment
and this shot was taken before the barriers shown on
the right were installed. 
Kilninver Bridge
Kilninver Bridge is downstream from the
Scammadale embankment slip, on the River
Euchar, which is fed from Loch Scammadale. 
The bridge suffered significant abutment scour
during the rain event. Extensive emergency
works have been carried out and some rock
armour protection work will be carried out in due
course to the upstream side of the bridge. The
initial works were carried out at pace in order to
save the bridge from further scour damage to
the bridge’s abutment. Any further damage would have very likely resulted in the
bridge being lost.

Page 5

Initially a weight limit reduction was applied to the bridge. This has now been lifted and
the bridge is open to 44 tonne vehicles. 44 tonne
being heaviest vehicle allowed on UK roads
unless an abnormal load exemption is issued.
Top image showing the wooden formwork in
place which supported the fibre reinforced
concrete until it set. Bottom image on the right
showing the formwork being erected. The
carpenters in the shot help to give scale to the
repair works. 
Kilmelford Bridge 
The initial emergency phase commenced on
Thursday 19 October when a major defect was
found on the bridge. The defect was so
significant there was only one option – to
demolish the bridge for public safety.
The initial plan was to demolish the old bridge
and put in place a temporary ‘forest’ type
corrugated steel pipe type bridge. However, we
were very fortunate and found a number of
concrete culvert/bridge sections in Highland
which were the correct size and were available. This enabled a rapid construction
phase which had the road open to 44 tonne vehicles in an impressive 2 weeks’ time
period. 
With the bridge and road now open to all traffic
we have commenced work to carry out a
hydrology study. This is a complex and
technical piece of works which is required to
design the training walls (the walls which direct
the water flow into and out of the bridge
structure), to satisfy SEPA in terms of
retrospective consents and to ensure that the
bridge will not have any adverse effect on the
river. There is additional design work to carry
out in terms of adding a segregated pedestrian route and finishing off the surfacing
and parapet (edge of bridge) walls. So whilst the initial emergency phase of the bridge
works is complete there remains much design, liaison with consenting bodies and
physical works

Page 6

Top image showing the damage to the bridge and the bottom picture detailing the new
concrete bridge sections prior to the reinforced concrete slab and surfacing being
placed. 
Slope Stability – hillsides above the A815
A contract has been put in place with
a geological engineering expert for
ongoing monitoring of the scars left on
the A815. In addition to the monitoring
the contacted works include advising
on future flow mitigation measures –
these at their most basic will be
deeper ‘climate adapted’ drainage
channels to intercept small flow
events. The image to the right shows
some of the scars on the hillside above the A815 which are being monitored.