Page 1

Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD
14 March 2024 
NOTICE OF MEETING 
A meeting of the ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE will
be held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND
BY MICROSOFT TEAMS on THURSDAY, 21 MARCH 2024 at 10:30 AM, which you are
requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST (IF ANY) 
3. MINUTES (Pages 3 - 8)  
Environment, Development and Infrastructure Committee held on 30 November 2023 
4. CEMETERY ASSET - UPDATE REPORT OUTLINING PROCEDURES IN PLACE
TO PROTECT REMAINING LAIR SPACE IN CEMETERIES (Pages 9 - 18)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
5. WASTE UPDATE (Pages 19 - 24)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
6. ELECTRIC VEHICLE CHARGING STRATEGY UPDATE (Pages 25 - 36)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
7. ANNUAL STATUS AND OPTIONS REPORT 2024 (Pages 37 - 70)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
8. TRANSPORT (SCOTLAND) ACT 2019 - PAVEMENT, DOUBLE & DROPPED
KERB PARKING STANDARDS (Pages 71 - 76)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
9. SECOND DOMESTIC BIN REVIEW 2024 (Pages 77 - 88)  
Report by Executive Director with responsibility for Roads and Infrastructure Services
Public Document Pack

Page 2

10. LOCAL BRIDGE MAINTENANCE FUND (Pages 89 - 96)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
11. ROUTE OPTIMISATION UPDATE (Pages 97 - 102)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
12. ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 (Pages 103 - 112)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
13. FILM IN ARGYLL - SCREEN INDUSTRIES UPDATE REPORT (Pages 113 - 118)  
Report by Executive Director with responsibility for Development and Economic
Growth 
14. TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM - LARGE
SCALE PROJECT UPDATE REPORT (Pages 119 - 134)  
Report by Executive Director with responsibility for Development and Economic
Growth 
15. ARGYLL AND BUTE COUNCIL'S ECONOMIC STRATEGY REFRESH: 2024-2034
(Pages 135 - 158)  
Report by Executive Director with responsibility for Development and Economic
Growth 
16. ARGYLL AND BUTE HOUSING EMERGENCY - PROGRESS REPORT 
(Pages 159 - 210)  
Report by Executive Director with responsibility for Development and Economic
Growth
REPORTS FOR NOTING 
17. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORKPLAN (Pages 211 - 212) 
Environment, Development and Infrastructure Committee 
Councillor Graham Hardie Councillor John Armour
Councillor Jan Brown Councillor Garret Corner
Councillor Robin Currie (Chair) Councillor Mark Irvine
Councillor Andrew Kain (Vice-Chair) Councillor Jim Lynch
Councillor Tommy MacPherson Councillor Ian MacQuire
Councillor Luna Martin Councillor Ross Moreland
Councillor William Sinclair Councillor Andrew Vennard
Councillor Peter Wallace Councillor Gary Mulvaney   
Contact: Hazel MacInnes  Tel: 01546 604269

Page 3

MINUTES of MEETING of ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
COMMITTEE held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY,
LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 30 NOVEMBER 2023 
Present: Councillor Robin Currie (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Garret Corner
Councillor Graham Hardie
Councillor Andrew Kain
Councillor Jim Lynch
Councillor Tommy MacPherson 
Councillor Ian MacQuire
Councillor Luna Martin
Councillor Ross Moreland
Councillor Gary Mulvaney
Councillor William Sinclair
Councillor Andrew Vennard
Councillor Peter Wallace 
Also Present: Councillor Paul Kennedy 
Attending: Kirsty Flanagan, Executive Director
Fergus Murray, Head of Development and Economic Growth
Jim Smith, Head of Roads and Infrastructure Services
Stuart McLean, Committee Manager
Matt Mulderrig, Development Policy and Housing Manager 
The Chair welcomed Councillor Graham Hardie to his first meeting of the Committee
following his appointment at the Council meeting on 23 November 2023. 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillor Mark Irvine. 
2. DECLARATIONS OF INTEREST 
In relation to item 6 of the agenda (Helensburgh Wooden Pier - Update) Councillor Ian
MacQuire noted a connection due to his membership on the Helensburgh Seafront
Development Trust (HSDT), he advised that as the Group was currently dissolving he
would remain in the meeting during the consideration of this item of Business. 
3. MINUTES 
The Minutes of the meeting of the Environment, Development and Infrastructure
Committee held on 31 August 2023 were approved as a correct record. 
4. LATEST UPDATE ON THE SETTLEMENT PROJECT SUPPORT OFFICER
ACTIONS 
The Committee gave consideration to a report providing an update on the progress of the
Settlement Project Support Officer actions that had been approved by the Committee at
their meeting on 31 August 2023. 
Page 3 Agenda Item 3

Page 4

Decision 
The Environment, Development and Infrastructure Committee noted – 
1. the progress on the actions agreed by the Environment, Development and
Infrastructure Committee on 31 August 2023; and 
2. that a further update would be provided on the work of the Settlement Project Support
Officer at the next Environment, Development and Infrastructure Committee. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated November 2023, submitted) 
Councillor Luna Martin joined the meeting during the consideration of the following item of
Business. 
5. ARGYLL AND BUTE HOUSING EMERGENCY 
(a) Progress Report 
The Committee gave consideration to a report providing an update on progress
towards intentions agreed by the Committee in June 2023 in response to the
Housing Emergency in Argyll and Bute. 
Decision 
The Environment, Development and Infrastructure Committee noted the activity and
progress that was ongoing in pursuing the intentions agreed by the Committee in
June 2023 which sought to address the Housing Emergency. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated October 2023, submitted) 
(b) Project Officer Resource 
The Committee gave consideration to a report proposing the allocation of a Project
Officer to accelerate the progress of the interventions agreed by the Committee in
June 2023 to address the Housing Emergency in Argyll and Bute. 
Decision 
The Environment, Development and Infrastructure Committee agreed to recommend
to the Policy and Resources Committee that the Council recruit a Project Officer to
assist in accelerating the work to address the Housing Emergency, with funding for
the post being drawn from the Council’s Priorities Investment Fund. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated October 2023, submitted) 
Page 4

Page 5

6. HELENSBURGH WOODEN PIER - UPDATE 
The Committee gave consideration to a report providing an update following the decision
to remove Helensburgh Wooden Pier from the project options within the Rural Growth
Deal Tourism and Place Programme. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. accepted the Consultants findings, particularly that a berthing facility at Helensburgh
Pier could not be operated on a revenue neutral basis, particularly where long-term
capital replacement costs were accounted for, and that officers would no longer devote
resources to pursuing a Council funded berthing facility; and 
2. agreed that the Head of Development and Economic Growth would engage with
Helensburgh Community Council and any other appropriate community group(s) who
may express a wish to pursue options, including a potential asset transfer of
Helensburgh Wooden Pier. 
(Reference:  Report by Executive Director with responsibility for Development and
Economic Growth dated November 2023, submitted) 
Councillor Andrew Vennard joined the meeting during the consideration of the following
item of Business. 
7. WASTE UPDATE 
The Committee gave consideration to a report providing an update on a number of waste
related matters including meetings with the Scottish Environment Protection agency
(SEPA) on 4 October 2023, and with Scottish Government officials on 6 October 2023 in
respect of the Waste PPP contract. 
Decision 
The Environment, Development and Infrastructure Committee noted – 
1. the update regarding meetings held with SEPA on the Waste PPP contract; 
2. that officers would conclude conversations which were ongoing regarding the
derogation and would bring a further report to the next meeting of the Committee for a
decision on the way forward for the Council; 
3. the update regarding Persistent Organic Pollutants and noted the date of
implementation of compliance with SEPA mandatory guidance as 1 November 2023; 
4. the bid to the Recycling Infrastructure Fund and officers’ achievement in successfully
securing funding for improvements; 
5. the officer support offered by Zero Waste Scotland; and 
6. the detail provided in the report regarding the Circular Economy Bill. 
Page 5

Page 6

(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated November 2023, submitted) 
8. CEMETERY ASSET - ANNUAL REPORT 
The Committee gave consideration to a report providing an annual update on the current
Argyll and Bute “active” cemetery estate – number of lairs for sale and operational
timescales within the Cemetery Development programme. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
submitted report. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated November 2023, submitted) 
9. PLAY PARK FUNDING - UPDATE REPORT NO 3 
The Scottish Government had allocated £938k for Play Park Funding to Argyll and Bute
Council for investment in play park equipment through to 2025/26.  The Committee gave
consideration to a report providing an update on the engagement process covering local
Elected Members, Community Councils, Education and disability forums. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. endorsed the Area Committee priorities for each play park in their area and the
allocation of funding as per paragraph 1.6 of the submitted report; 
2. noted the updates regarding the Tarbet Play park and the partnership approach to Port
Ellen play park in Islay; and 
3. noted the updated timelines. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated November 2023, submitted) 
10. OCTOBER 2023 WEATHER EVENT - UPDATE 
The Committee gave consideration to a report summarising the rain event that caused
significant travel disruption and damage during the weekend of 7 October 2023.  The
report also summarised the extent of works that had been carried out to repair the
damage and considered what the next steps should be in relation to investment to enable
climate change adaptations to be made. 
Decision 
The Environment, Development and Infrastructure noted the content of the submitted
report.
Page 6

Page 7

(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated November 2023, submitted) 
11. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORK PLAN 
The Environment, Development and Infrastructure Committee work plan was before the
Committee for noting. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
work plan. 
(Reference: Environment, Development and Infrastructure Committee work plan as at
November 2023, submitted) 
Page 7

Page 8

This page is intentionally left blank

Page 9

ARGYLL AND BUTE COUNCIL                      ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                       21 MARCH 2024
SERVICES                     
CEMETERY ASSET – UPDATE REPORT OUTLINING PROCEDURES IN PLACE
TO PROTECT REMAINING LAIR SPACE IN CEMETERIES 
1.0  EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council has a total of 131 Cemetery Locations with 68 cemeteries
considered as “closed”, where all available land for burial lairs has been allocated.
Re-opening of lairs for burials and ashes interments are however still possible.
The remaining 63 “active” cemeteries are those where land is still available for the
purchase of the right of burial, and a lair space can be allocated to the applicant. 
1.2 This report advises of the current procedures in place to further protect our
cemeteries in more rural and island locations which are difficult to extend or
purchase new land and should be read in conjunction with the annual report
submitted in November 2023 to the Environment, Development and Infrastructure
(EDI) Committee (see below link). 
EDI Nov 2023 (See Agenda Item 8) 
1.3 There are currently 9,506 lairs available for sale throughout the cemetery
inventory, sufficient to sustain the burial service overall, for the next 30 years.
However, the number of lairs available varies from over 1,000 in larger cemeteries
to 10 or less depending on the location. These figures are used to prioritise the
cemetery development programme of existing extensions or new sites. 
1.4 The report also provides, in Appendix 1, a list of Cemeteries where measures
have been introduced to allow no pre-sale of lairs, local burials only, in 20
locations across Argyll and Bute. 
RECOMMENDATION 
The Environment, Development and Infrastructure Committee are asked to
consider this report and agree that listed measures in Appendix 1 be endorsed to
further protect the sale of lairs in cemeteries which have a rural/island location, as
well as having limited scope for extension and or a new site locally to build on. 
Page 9 Agenda Item 4

Page 10

ARGYLL AND BUTE COUNCIL                      ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                          21 MARCH 2024
SERVICES                     
CEMETERY ASSET – UPDATE REPORT OUTLINING PROCEDURES IN PLACE
TO PROTECT REMAINING LAIR SPACE IN CEMETERIES 
2.0  INTRODUCTION 
2.1 This report outlines the approach to protect the sale of lairs on some islands, in
more rural areas and locations where officers are finding it difficult to extend the
cemetery site or purchase new land. 
2.2 Argyll and Bute Council, along with other Local Authorities across Scotland, are
experiencing budget cuts and reduced resources as well as increasing pressure
on burial land within its area. The Council is responsible for managing and
maintaining burial grounds within the Council area. There are 131 cemeteries
ranging from small churchyard cemeteries to large ‘municipal’ cemeteries. 
2.3  At the March 2023 EDI Committee a Cemetery Rule change was agreed:- 
‘Remaining lair space in any operational cemetery will be considered critical,
when the current rate of unrestricted lair sales indicates less than 10 years until
all lairs are sold. In such cases sale of lairs will be restricted to “at point of
requirement” for a first interment. There will be no resumption of “pre-purchase”
of lairs, until such time, as additional lair space has been developed and made
available.’ 
2.4  Further to this, there have been historical local agreements agreed at Area
Committee level. These further restricted the sale of lairs to local residents or
Parish members only. An example of this is Luss Church Yard Cemetery which is
very popular and had many requests for the purchase of lairs from non-residents
of Argyll and Bute, and which would have a detrimental effect on local residents
looking to be buried there. In the absence of the further restrictions on lair sales,
it is very likely that the lair availability in Luss would have reached or nearly
reached capacity. 
2.5  Officers have monitored this over the last 10 months and note that whilst the stop
on the pre-sale of lairs has been helpful in allowing time to look at extending
cemeteries or purchasing land, there is a further issue in that islands and some
very localised cemeteries have limited availability. To further support the EDI
Cemetery Rule change from March 2023, officers recommend that where there
are issues with land acquisition or extension in island and outlying cemeteries with
Page 10

Page 11

limited choice for burials nearby, that the local arrangements are sanctioned on
top of the stop on pre-sale of lairs to include sale for local residents/islanders only. 
3.0 RECOMMENDATION 
3.1 The Environment, Development and Infrastructure Committee are asked to
consider this report and agree that listed measures in Appendix 1 be endorsed to
further protect the sale of lairs in cemeteries which have a rural/island location, as
well as having limited scope for extension and or a new site locally to build on. 
4.0  DETAIL 
4.1 There are many requirements which need to be considered when creating a new
cemetery, these include but are not limited to:-   
o 1m clear, below lair depth, to rock or water table (approx. 2.6m below
surface);
o At least 50m from any open body of water or watercourse; 
o At least 250m from any well, borehole or intake for drinking water;
o No course sand or gravel at lair depth. 
4.2 Officers previously carried out a survey on cemeteries and lair availability in 2020
where it was clear from the responses that our communities wanted to be able to
bury family locally. A recurring response theme was, that of families wanting to
have somewhere to go to visit loved ones locally and be able to attend a funeral.
This was particularly evident in the island responses where the community did not
want buried on the mainland. 
4.3 Out of the remaining 63 Cemeteries which are available for lair sales, a total of
20 have been identified as ‘Special’ sites (see Appendix 1) where officers
believe that the no pre-sale of lairs with less than 10 years availability is further
supported by the ’Local Residents/Islanders’ restriction on the sale of lairs.
Effectively each of the sites has limited capacity for expansion or new site
availability is limited or cost prohibitive. 
4.4 The construction of Tobermory (Beadoun) cemetery phase 2 was concluded in
August 2023. This provided a further 210 lair spaces for the town and immediate
area. This site cannot be expanded further due to land tenure and other
constraints. Suitable land in the vicinity of the town is not readily available and
consideration is being given to further cemetery provision in Tobermory. This is
an example of a cemetery which has limited capacity, even after being extended,
where it is necessary to maintain the restrictions on the pre-sale of lairs. 
4.5  A pre-application enquiry to SEPA for a potential phase 3 extension to Lismore
Cemetery concluded that this would not be supported due to groundwater
requirements and private water supplies in the vicinity. Plans are now being
developed to maximise the use of the existing burial ground, by excavating
Page 11

Page 12

shallow rock and re-filling with imported suitable material. Officers are working
with Lismore Community Council on offers of locally won material from various
landowners on the island. In parallel, discussions are in progress with the Church
of Scotland Estates regarding wayleave access to the rear of the cemetery. 
4.6  This would further support the survey responses which clearly identified that
island residents did not want to be buried on the mainland and local residents
wanted to be able to be buried near their family or near their home. 
5.0  CONCLUSION 
5.1 The cemetery estate has sufficient overall capacity for the next 30 years operation
but locally, restrictions are in place to preserve remaining lair space. These
restrictions however can better support our island communities and more rural
communities if a ‘Local Residents/Islanders’ restriction on the sale of lairs was
sanctioned to support this. 
6.0 IMPLICATIONS 
6.1 Policy – The Management Rules for Burials revised policy 2023, provides a
process where lair sales can be restricted when cemeteries have less than 10
years remaining capacity the introduction of the local residents/Islanders
restriction would enhance this. The historical local agreements further protect
our rural sites and islands. 
6.2 Financial – Cemetery extensions and new developments require additional
Capital funding, to provide “ready to use” infrastructure to sustain the burial
service at local levels. 
6.3  Legal – The Council, as Burial Authority, is legally bound to provide at least one
cemetery. 
6.4  HR – None known 
6.5  Fairer Scotland Duty: This would support our duty to provide a fair and
equitable cemetery provision for local islands and rural areas. 
6.5.1   Equalities - protected characteristics – None known 
6.5.2   Socio-economic Duty – Provision of the burial service at local level sustains
the business models of both the Council and private providers and reduces
the overall cost to customers. 
6.5.3 Islands – The programme of cemetery development locations, highlights the
desire for the retention of a local burial service, this would support our duty to
provide a fair and equitable cemetery provision for local islands and rural
areas. 
Page 12

Page 13

6.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise. Future consideration should be given to a Council policy
position on encouraging cremations over burials, given the land requirements
and increasingly challenging prospects of being able to further develop
cemeteries.   
6.7  Risk – Land suitability, availability and development costs, may affect the
viability of retaining a local burial service. 
6.8  Customer Service – Cemetery development programme aims to provide and
maintain the burial service at local level where ever practicable.   
6.9  Rights of the Child (UNCRC) – None arising from this report.   
Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan 
Policy Lead for Climate Change and Environment, Councillor Ross Moreland 
March 2024                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services
jim.smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager 
hugh.oneill@argyll-bute.gov.uk   
APPENDICES: 
Appendix 1 – Restricted Sale of Lairds to Local (Parish) Residents 
Page 13

Page 14

This page is intentionally left blank

Page 15

APPENDIX 1
ARGYLL AND BUTE COUNCIL - EDI – MARCH 2024
NO PRE-SALE OF LAIRS – LESS THAN 10 YEARS OPERATIONAL DURATION
AT AUG. 2023 
HELENSBURGH AND LOMOND
LOCATION REASON FOR NO PRE-
SALE
MITIGATION MEASURES 
Luss Church Yard
and Cemetery
No Pre-sale of lairs due to
restricted land available.
Attractive location – tourist
area
None immediately available -
new location to be considered
if local burial service to be
retained. Sale of lairs
restricted to Luss residents.
No option to expand current
site.
Faslane Cemetery No pre-sale due to restricted
land available within current
boundary. No option to
expand
Cemetery building removed
and other areas converted  - 
a further approx. 40nr lairs
created   Sale restricted to
Faslane parish residents. No
option to expand.
Barbour Cemetery  Less than 10 years available
at current annual rate of sale.
None immediately available –
Adjacent land unsuitable due
to shallow rock depth. No
option to expand. 
BUTE AND COWAL
LOCATION REASON FOR NO PRE-
SALE
MITIGATION MEASURES 
Kingarth cemetery 
South Bute
Less than 10 years available
at current annual rate of sale.
Additional 30nr lairs created
in current ground - adjacent
extension being pursued.
Initial contact with land owner
ongoing at present. 
Cnoc-an-raer
Cemetery  North
Bute
Less than 10 years available
at current annual rate of sale.
Section 2 to be expanded
and developed within owned
land. Ongoing planning work
at present.
Kilmorich
(Cairndow)
Cemetery
Less than 10 years available
at current annual rate of sale.
No adjacent land available –
option for new extension in
wooded ground  – cost
prohibitive. Officer is looking
for alternative areas locally.
Initial meeting with land
owner in late Feb 2024
established trial excavations
can be carried out in March
2024.
Strachur Cemetery Less than 10 years available
at current annual rate of sale.
Additional 15nr lairs by
relocating access road. New
site south of village being
Page 15

Page 16

explored. Initial approval
from land owner – Ground
investigation works to prove
suitability within SEPA regs.
Kilmun Cemetery Less than 10 years available
at current annual rate of sale.
Additional 10nr lairs by
removing access road. No
scope to expand further –
Considering use of
Sandbank Cemetery 
Cowal (Sandbank)
Cemetery
Less than 10 years available
at current annual rate of sale.
Additional drainage and
footpaths to develop 110nr
lairs within current site.
Adjacent land at Torlochan
Site – Dept. responsibility
transferred to RIS. Initial trial
holes carried out in early
2023 - site to be developed
after confirming SEPA regs.
Kilmodan
(Glendaruel)
Cemetery
Less than 10 years available
at current annual rate of sale.
No scope to extend, new
development unlikely - SEPA
water course / Flood plain
restrictions, affecting
planning consent.
Lochgoilhead
Cemetery
Less than 10 years available
at current annual rate of sale. 
No adjacent land available –
option for new extension in
wooded ground  – cost
prohibitive new site to be
investigated in coming 2-5
years. 
MID-ARGYLL, KINTYRE and ISLANDS
LOCATION REASON FOR NO PRE-
SALE
MITIGATION MEASURES 
Kilkerran 
Cemetery
(Campbeltown) 
Less than 10 years available
at current annual rate of sale.
Additional 100nr lairs in
existing “6th Section” by
converting roads and
footpaths. Scope for 120nr
more in unused land within
bounds of cemetery. Further
expansion on adjacent
farmland not possible due to
SEPA regs.  Restrictions on
Planning Approval. Initial
plane was a new site to be
developed West of
Campbeltown, however this
site is no longer available.
Alternative site to the north of
Kilkerran awaiting
confirmation of land
ownership via MOD and
agreement for sale of land in
conjunction with local farmer..
Page 16

Page 17

Patchen Cemetery
Kintyre
Less than 10 years available
at current annual rate of sale
Additional extension in field –
initial site investigation
required to confirm SEPA
compliance.
Bowmore
Cemetery Islay
Less than 10 years available
at current annual rate of sale
Additional extension in field –
initial site investigation
required to confirm SEPA
compliance. 
OBAN, LORN and the ISLES
LOCATION REASON FOR NO PRE-
SALE
MITIGATION MEASURES 
Isle of Iona
Cemetery
Sale restricted to Iona
residents
New site required by 2035
Beadoun
(Tobermory )
Cemetery
No pre-sale restrictions in
place in PH1 Construction
approx. 2008, to remain in
place in new 2023 PH2
extension to preserve Burial
Service in town.
Approximately 210nr lairs
available in new extension.
Release to “open sale” likely
to trigger “10 year rule” after
first 12 months.
No scope to expand further
due to cost prohibitive
construction and land tenure
conditions on adjacent
ground. Third site to be
sought - limited suitable
ground available.
Calgary Cemetery 
Mull
Sale restricted to local parish
residents – at point of
requirement – but in pairs
due to depth
Shallow ground extension in
process of being acquired.
Lairs sold in pairs for single
interments. Additional
material source being
investigated to allow upfill to
multiple depth layers.
Pennygowan
Cemetery , Mull
Less than 10 years available
at current annual rate of sale
Adjacent land – unsuitable
due to shallow rock - limited
scope elsewhere for new site.
Isle of Lismore
Cemetery
Sale restricted to local parish
residents – at point of
requirement 
Rock at shallow depth in
“half” the current cemetery, to
be removed and up-filled to
maintain burial service.
Awaiting Church of Scotland
approval for access through
adjacent field, works
programmed May/June 2024
which will allow approx. 40
years availability of lairs.
SEPA reg restricting further
expansion at this site Limited
suitable land elsewhere.
Kilbrandon (Old) Sale restricted to parish
residents
Limited remaining space.
“New” cemetery operating in
parallel.
Page 17

Page 18

Achnaba
Cemetery
Sale restricted to parish
residents
Gifted Extension approx.
2009, no scope for further
development.
Appin Cemetery Sale restricted to parish
residents Alternative site
explored approx. 2015 but
not taken to conclusion.
Extension constructed 2022
on remaining area of suitable
ground. No scope for
further extension. 
Page 18

Page 19

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE
SERVICES  21 MARCH 2024 
WASTE UPDATE 
1.0 INTRODUCTION 
1.1 Argyll and Bute Council currently has a 3 model waste disposal arrangement in
place. This consists of Island landfill sites which the Council operate, a third
party off taker for the refuse collected in Helensburgh and Lomond and a PPP
contract for the remainder of the Council area which runs until September 2026. 
1.2 At the November 2023 meeting of the Environment, Development and
Infrastructure Committee, Members considered a report covering a number of
work streams regarding recycling and waste disposal. This report provides an
update regarding the Council’s request to Scottish Government for a derogation
for the Council’s PPP contract and also informs Members that the existing third
party off taker for the Helensburgh and Lomond area will cease to trade from
31 March 2024, meaning that new arrangements have to be put in place.   
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
i. Consider and note the update regarding meetings held with Scottish Government
on the Waste PPP contract; and further note the update relating to the derogation
and the drop date set with Scottish Government of the 5 April;
ii. Note that the third party off taker for Helensburgh and Lomond has given notice
that they will cease trading on 31 March 2024;
iii. Note that a further update report will be made available to the Environment,
Development and Infrastructure Committee in June.   
3.0 DETAIL 
3.1  Waste PPP 
3.1.1 In December 2022, the Council’s Environment, Development and
Infrastructure Committee agreed to pursue a derogation from the Scottish
Government, from the implementation date of the Biodegradable Municipal
Waste Ban of 1 January 2026 to the end of the Council’s Waste PPP contract
in September 2026. 
Page 19 Agenda Item 5

Page 20

3.1.2 The Council has in place a 25 year Waste PPP contract which ends in
September 2026. The Waste PPP contract covers Oban and Lorn, Mid Argyll
and Kintyre, Bute and Cowal together with the inner islands. 
3.1.3 The Scottish Government are due to introduce a Biodegradable Municipal
Waste (BMW) landfill ban from the end of December 2025. The last 9 months
of the PPP 25 year contract will not be compliant with the new regulation. 
3.1.4 Argyll and Bute Council is the only Local Authority in Scotland with a PPP
contract, this leaves the Authority in a unique situation whereby it is hampered
by a 25 year contract which was supported by the Scottish Executive in 2001.
To remove itself from the contract has significant financial implications for the
Authority. 
3.1.5 A derogation, if granted, would enable the PPP contract to continue with the
Mechanical Biological Treatment (MBT) process until the contract comes to an
end in September 2026, this being some 9 months after the BMW ban comes
in to place. Note – the islands and Helensburgh and Lomond areas are intended
to be BMW compliant from 1 January 2026. Should a derogation not be
permitted, the Council are seeking funding for additional costs (circa £1.5M)
which would be incurred by the Council in respect of varying the PPP contract
from Scottish Government. 
3.1.6 The Council Leader and officers have held various meetings with the Minister
for Green Skills, Circular Economy and Biodiversity, Scottish Government
officials following the formal request to Scottish Government for a derogation in
December 2022. A further meeting took place between the First Minister,
Council Leader and Chief Executive during Scottish Governments Travelling
Cabinet visit to Inveraray in the Autumn of last year, officers have had a number
of meeting with SEPA who regulate waste legislation in Scotland and numerous
letters and emails have been exchanged. At the time of writing there is no
derogation available to the Council. 
3.1.7 Officers have informed Scottish Government officials that the drop dead date
for a decision regarding the derogation is 5 April 2024. This date has been
specified to enable necessary briefings to be carried out and a report to be
prepared for Members consideration at the June 2024 Environment,
Development and Infrastructure Committee. The Committee will be formally
asked to approve an approach at its June meeting, if a derogation has not been
granted, whereby the contract with Renewi is varied. This contract variation will
involve Renewi converting the existing Mechanical Biological Treatment (MBT)
plants to waste transfer stations in Oban, Lochgilphead and Dunoon. General
waste will then be taken to third party off takers for Energy from Waste (EfW)
feed stock rather than being processed with residual being landfilled. This
approach will also future proof the Council’s waste service in line with the BMW
ban.   
3.1.8 At a meeting between the Executive Director and Head of Service with officials
from Scottish Government on 9 February 2024, Scottish Government officials
Page 20

Page 21

stated that subject to due diligence it would be more likely that some form of
associated grant payment could be forthcoming rather than a derogation. At the
time of writing this has not been confirmed by Scottish Government. 
3.1.9 From the options appraisal carried out in 2022, the additional costs to the
Council for the varying the contract with Renewi is c£1.5M. The options
appraisal is being refreshed as part of a due diligence exercise. However, it is
not expected that the additional costs of £1.5M will be far off the mark. In the
representations to Scottish Government it has been made very clear that should
the derogation not be forthcoming then the Council will seek the additional costs
incurred through the contract. 
3.2  Barr Environmental Limited (BEL) 
3.2.1 BEL issued a notice to the Council on the 10 January 2024 informing the
Council of their intent to withdraw from contracts on 31 March 2024.  The
contracts included the disposal of Persistent Organic Pollutants (POPs) and
Wood from Helensburgh and Lomond, and residual waste from Helensburgh
and Lomond, and Tiree. 
3.2.2  Officers continue to engage with other providers and will have a replacement
provider contracted by 1 April 2024.   
4.0 CONCLUSION 
4.1 In concluding this report, an update on various meetings held with Scottish
Government officials relating to the Council’s request for a time limited
derogation for the Waste PPP area from 1 January 2026 - September 2026 for
the BMW landfill ban which is due to be implemented from 1 January 2026. 
The Committee agreed, in December 2022, to pursue two options and officers
continue to take these forward in tandem. Officers will pursue the derogation
until the drop dead date of 5 April 2024, if a derogation is not granted or suitable
communication from Scottish Government advising that a derogation is agreed,
officers will engage with Renewi to ensure the conversion of the MBT plants to
waste transfer stations takes place.   
5.0 IMPLICATIONS 
5.1 Policy – The Council’s waste strategy will evolve in line with the changes in
legislation relating to the BMW ban of waste to landfill. A derogation will be
sought, failing a successful response the current Renewi contract will be varied
to comply with legislative changes.   
5.2 Financial – Compliance with the 2025 Landfill ban will require financial resource
from the Council. As the Scottish Government are initiating the change, officers
will pursue financial support from the Scottish Government for this change to
provide a long-term financially sustainable solution.   Through lobbying it is
Page 21

Page 22

our intention to seek to recover any additional costs which have resulted from
the changes to legislation, through Scottish Government. However, there
remains a risk that funding is not forthcoming. 
5.3 Legal – The existing PPP contract was not designed or written to accommodate
the changes that the 2025 legislation will require. The contract allows variations
to be made although the process is quite cumbersome. There will be legal
implications, which will need to be resolved, relating to a contract variation
regarding the derogation and/or changes in Renewi’s contract.   
5.4 HR – HR issues will be addressed prior to and during the process of contract
handback. Having sufficient resource will factor into the project demands of
waste management. TUPE will be relevant at the handback and during the
process of progressing to handback should the Council operate the sites
themselves.     
5.5  Fairer Scotland Duty: 
5.5.1   Equalities – None. 
5.5.2   Socio-economic Duty – None. 
5.5.3 Islands – There may be potential ferry capacity issues for bulking and
transporting waste material from islands, this has been raised with Transport
Scotland.   
5.6 Climate Change – Transitioning from Landfill to Energy from Waste (EfW) would
result in a reduction in the annual quantity of Greenhouse Gas Generated in
Argyll and Bute. Additional road miles incurred taking waste to EfW markets will
partly offset the carbon reductions achieved through not landfilling. 
5.7  Risk – There are financial risks associated with no derogation. The costs are
approx. £1.5m, a refresh of all Waste PPP costs will be undertaken. 
5.8  Customer Service – None.   
5.9  Rights of the Child – None arising from this report.   
Executive Director with responsibility for Roads and Infrastructure: Kirsty Flanagan 
Policy Lead for Climate Change and Environment Services, Councillor Ross
Moreland 
February 2024                                           
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services
jim.smith@argyll-bute.gov.uk 
Page 22

Page 23

John Blake, Fleet, Waste and Transport Manager 
john.blake@argyll-bute.gov.uk 
Page 23

Page 24

This page is intentionally left blank

Page 25

ARGYLL AND BUTE COUNCIL         ENVIRONMENT, DEVELOPMENT AND      
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                    21 MARCH 2024 
ELECTRIC VEHICLE CHARGING STRATEGY UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council has increased its network of public Electric Vehicle
Chargers (EVC) since the last time this was reported to Environment,
Development and Infrastructure Committee (EDI) from 28 to 37 thanks mainly to
an investment of nearly £400,000 through the HITRANS FASTER project. Since
formally adopting the EVC expansion plan in December 2022 officers have
engaged with Scottish Government through Transport Scotland with a view to
accessing funds from the £30million Electric Vehicle Infrastructure Fund (EVIF)
but unfortunately, at the time of writing this report, we have not yet had any funding
allocation or formal feedback on our submission. It is understood that no Local
Authorities have yet received funding from the new fund. 
1.2 As EVC becomes increasingly popular, and as the ban on new internal
combustion engine vehicles approaches, there is a clear need for a
comprehensive roll out of charging points and arrangements to sustainably
manage and maintain these. 
1.3 This report provides an update under various headings: 
• EVC expansion plans and the Scottish Government’s Electric Vehicle
Infrastructure Fund (EVIF)
• Maintenance of the current network
• Update on network expansion 
1.4 Background information including previous committee reports is available on the
Council website here. 
1.5 In December 2022 the EDI Committee considered a report on the EVC strategy
and formally agreed the development methodology and expansion list following a
public consultation and development of the expansion list through a Member
Seminar. That reports with its various appendices is available here at agenda item
6. 
Page 25 Agenda Item 6

Page 26

1.6 It is recommend that the Environment, Development and Infrastructure
Committee is asked to:
• Consider and note the ongoing work to develop and manage the EVC
network. 
• Agree that Officers should continue to engage with Transport Scotland on
future funding options through the new Electric Vehicle Infrastructure Fund
and that a specific Member Seminar will be arranged on EVC when there is
clarity on how that fund will operate and be allocated. 
2.0 RECOMMENDATIONS
2.1 The Committee is asked to:
• Consider and note the ongoing work to develop and manage the EVC
network. 
• Agree that Officers should continue to engage with Transport Scotland on
future funding options through the new Electric Vehicle Infrastructure Fund
and that a specific Member Seminar will be arranged on EVC when there is
clarity on how that fund will operate and be allocated. 
3.0 DETAIL 
3.1 EVC expansion plans and national Electric Vehicle Infrastructure Fund (EVIF)
3.1.1 A detailed methodology was presented to the June 2021 meeting of this
committee, then discussed at a Member Seminar in September 2021 which led
to changes to the original proposed methodology. The original draft had sites to
be prioritised large towns to small, whereas feedback from the seminar meant
that we changed the prioritisation to focus on small villages/towns first on the basis
that larger towns already have at least one charger. We had also originally
proposed to cut off at settlements smaller than 1,000 population but following
feedback we included villages with a smaller resident population than that but
acknowledging that tourist traffic is significant. An updated draft list and
methodology was then presented to the December 2021 meeting. 
3.1.2 The agreed draft development methodology and site list went out to public
consultation to ensure that communities had the opportunity to be involved in the
process of deciding where future public EVCs installations should be across the
Council area, and how that network should be developed and prioritised. 
3.1.3 We received 254 responses from across Argyll and Bute; and as well as giving
views on specific questions, respondents also provided more than 500 comments.
The full consultation findings report is appended to the last report to EDI at
Appendix 3 and an overview of themes from the consultation is at Appendix 4 of
that same agenda item. These can be accessed here. 
Page 26

Page 27

3.1.4 The list is based on theoretical locations based on feedback and knowledge to
date. It is anticipated that as the list is worked through there could be infrastructure
limitations due to limited grid capacity across many locations in Argyll and Bute or
technical considerations which may prevent development at a specific site.
Although the development methodology provides for different priority bands, until
such time as there is clarity on the possible future funding options it is not possible
to develop a method to determine how that funding should be allocated to sites
within the priority bands e.g. how sites are prioritised within the priority bands
against available funding. As and when there is clarity on external funding a
further report will come forward for Members to agree funding allocations.
3.1.5 The Environment, Development and Infrastructure Committee at its meeting in
December 2022 agreed the following –
1.    agreed the development and prioritisation methodology at Appendix 1 to
the submitted report, and the 55 site electric vehicle charging expansion
list at Appendix 2 of the submitted report, noting that the expansion plan
was supported by three-quarters of respondents to the electric vehicle
charging public consultation; and
2.    noted that Officers would continue to engage with Transport Scotland on
future funding options through the new Electric Vehicle Infrastructure Fund
and that a specific Member Seminar would be arranged on electric vehicle
charging when there was clarity on how that fund would operate.
3.1.6 Since then Officers have been engaging with Transport Scotland through the
Scottish Futures Trust to understand more about how the national fund will
operate and how we might access it. The Scottish Government’s vision for EVC
expects that £60million of investment will be made in EVC, with that investment
to be 50% publicly funded by Scottish Government, with the other 50% coming
from private finance.  
3.1.7 It is not clear how the private element will work – it is recognised that Local
Authorities should have flexibility to develop a long term delivery model for their
area which takes into account their own circumstances and each Local Authority’s
level of appetite for future involvement in the delivery and management of an EVC
network. In an Argyll and Bute context, what is clear is that there is limited
commercial appetite for large scale EVC development. While we have had the
odd ad hoc approach from private companies these have tended to be somewhat
niche and site specific e.g. a possible pilot venture to convert streetlights to EVC
which did not develop beyond early discussions; and discussions with a private
provider who is seeking to install EV infrastructure in a specific location in order
to support a specific service provision, electric buses from Oban to Edinburgh. On
the face of it, it seems likely that if there were genuine commercial opportunities
of scale available within our area we would have been contact by potential
providers/private sector partners. There are also instances of private
supermarkets providing EVC for their customers in their own car parks, which is
of course welcomed but does not, by its very nature, align with any overarching
public transport development strategy. 
Page 27

Page 28

3.1.8 Our experience of private interest is similar to that of other rural Local Authorities
we are in discussion with through professional networks. In many parts of Argyll
and Bute the infrastructure costs will be high to connect to the grid and/or to
upgrade capacity. It is therefore likely that any vision which includes an equitable
level of provision to ensure that no communities are disadvantaged/face barriers
to EVC access is likely to fall on the public sector. 
3.1.9 We have received informal feedback from Scottish Future Trust in the summer of
2023 that they would like us to provide a greater amount of evidence to show
market failure in Argyll and Bute. With this in mind we have joined a procurement
exercise called a PIN, which stands for Prior Information Notice, with various
Councils across the Northern Roads Collaborative area. We are currently
awaiting feedback from that exercise. 
3.1.10 Our EVIF submission was considered by the EVIF Advisory Panel which
comprises representatives from Transport Scotland, Scottish Future Trust and the
Energy Savings Trust, in October 2023. We have not as yet had any formal
feedback from that meeting although in dialogue with Transport Scotland in early
January they advised that we should receive this shortly.  A feedback letter was
received in mid-February. This letter outlined a completely new formal application
process which we will now work through, along with some generally positive
informal feedback on the information we submitted previously. 
3.1.11 It is unfortunate that we do not yet have clarity on what funding allocation we will
receive from EVIF as the Council is not in a position to make any long-term
decisions on the delivery of EVC in Argyll and Bute without more information on
the amount of funding we will receive. The latest feedback highlighting a
structured application process with guidance notes is, however; to be welcomed.
The recommendation from the December 2022 EDI report regarding a future
Member Seminar once there is clarity on the position is also recommended in this
report as, unfortunately, the position remains largely the same as it was then. 
3.1.12 Officers will urgently look to complete the new EVIF application and will continue
to liaise with Transport Scotland and the Scottish Futures Trust, and will also
continue to explore any private finance options that may be available to us. It is
not possible to say with any certainty what our EVIF allocation might be – it would
be prudent at this stage to begin to consider what the Council may wish to do if
the allocation is less than we might require to deliver our expansion plan. If that is
the case there would be a number of options to consider:
Option Comments
Revise/reduce the scope of the plan It would be sensible to revisit the
strategy when there is clarity on
funding, however; reducing its scope
would not be consistent with the
agenda to decarbonise transport due
to the climate emergency. Across all
public infrastructure we need
significantly more and better EV
Page 28

Page 29

chargers to support the changeover to
electric vehicles 
Council investment in EVC to make up
any shortfall
A business case can be developed to
look at if or how this could be self-
financing across the whole asset
group, with some busier assets likely
to generate a surplus to cross-
subsidise assets which are required in
more rural areas to provide equitable
provision but which by their nature are
likely to operate at a loss This option
would likely need to be accompanied
with a significant increase in EVC fees
for users
Explore externalising the network to a
private provider
There has been limited private interest
so far, but this is something we can
further explore, although Officers have
concerns that such a model would not
provide an equitable provision. We
could explore externalising some sites
and retaining others but this would
lead to a mixed model which could
have the effect of having a two tiered
system of access to EVCs with
different fees in place.   
3.2 Maintenance of the Network/Fault Issues 
3.2.1 Fault reporting is simple for the EVC user; it can be done via the Charge Place
Scotland (CPS) phone number which is on all units or their online form.  Once
received it is assigned a ticket number and various back office troubleshooting is
undertaken to try and bring the unit back into use remotely. If this communication
fails an engineer is scheduled with a Service Level Agreement (SLA) of 48hrs,
unfortunately the SLA is rarely met due to a combination of staff over
commitments and our geography.  This is not uncommon across all Local
Authorities. We are finding that providers price based on the 48hrs service
standard but submit a lower price for a 72hrs standard. Given that the 48hrs is
rarely met we are likely to alter our maintenance contracts in the future to a more
realistic timeline which will also provide best value. If the fault can be fixed within
the warranty agreement this is carried out and if not a quote for the work is
provided directly to the Council for approval and authorisation. Once the fault is
rectified the back office system is updated.  Overall we are seeing improvements
thanks to our approach which provides for continuity between the day to day and
the long term strategy development   
3.2.2 We have been proactive with the management and maintenance of fault and
issues through the Project Officer post which also works on strategy development
as well as supporting other key projects like Route Optimisation.  We are
monitoring faults and adding service disruptions to the Council’s website, liaising
Page 29

Page 30

closely with providers to stay up to date on faults that run longer than the SLA and
have recently brought a number of chargers under a single maintenance contract. 
3.2.3 Due to the nature of funding awards in the past, piecemeal, year on year amounts,
and in the absence of a strategy pre 2021, the network has a mixture of
maintenance arrangements. Transport Scotland have previously provided
funding to extend existing warranty packages, and prior to the strategy being in
place this is what was done. The warranty and maintenance packages have
proven not to be entirely reliable, with part replacement falling out with the
standard contract Terms and Conditions, and costs falling on the Council to bear,
with these costs being managed through the existing budget/fee recovery model.
In effect the warranty and maintenance contracts cover what is internal to the units
but not the items which are external. This year our non-contract spending on EVC
maintenance has been c.£9k. As warranty and maintenance packages have
ended we have looked to bring as many assets as possible under a single
umbrella contract. We have been limited with some of the assets as the units
previously installed could only be maintained by a single company. Over the
course of 2023 we have successfully brought 13 chargers into a single robust all-
encompassing maintenance contract with clear Key Performance Indicators.
3.2.4 Across Scotland Local Authorities are experiencing external funding for
maintenance dry up with the cost burden falling to Local Authorities. With this in
mind we have been planning for the long-term in how to make our network
sustainable, which is why we recommended a fee increase for financial year
24/25. Previously our fee structure covered electricity costs to the Council and a
small element to cover the non-contract spend mentioned above, whereas going
forward our fee structure will need to cover asset management costs in addition
to the other costs of the network. 
3.2.5 The Council’s approach to date has largely been to utilise external money coming
through the Scottish Government, HiTrans etc. It is assumed that Members would
wish to continue with this approach although it may be that Members would
consider investing limited Council resources directly into the provision of
additional charging points. 
3.2.6 The current charge per KwH is £0.29. As part of the Budget process in February,
this charge proposed to increase to increase to £0.45 per hour from April. This
increase covers increased electricity charges from utility companies, ongoing
maintenance and is designed to provide a small surplus which can be reinvested
into replacement of charging units. This moves our charges more towards a
market rate although is still some way short of supermarkets in Argyll and Bute,
for example, who charge 79p per kWh in some cases. Below is a table showing
the 2023/24 EVC tariffs across Local Authorities. . 
Page 30

Page 31

3.3 Update on Network Expansion 
3.3.1 The full, live expansion list is available at Appendix 1 of this report, with changes
colour coded. A summary of the work to expand the network is provided in the
table below, which is in addition to the significant work to develop better day to
day management arrangements for the existing network. The team continue to
liaise with government agencies and other Local Authorities, and represent the
Council on national groups, to ensure they are at the forefront of developments
in what is a fast growing industry. Significant work is also being undertaken with
colleagues in Procurement to let various contracts and look at developments,
liaise with framework suppliers and installers etc. Ultimately we will look to have
a single contract for installs once the position on EVIF is clear, which will drive
consistency across the network. 
Item Funding Comments
HITRANS FASTER
project
c. £400,000 This has delivered 8 rapid
chargers at the following
locations: 
• Two at Dunoon
Coal Pier;
• Two at Rothesay
Pier, Isle of Bute;
• One at Tarbert
Harbour;
• One at Ledaig Car
Park, Tobermory,
Mull; and
• Two at Corran
Halls Public Car
Park, Oban
£0.00£0.10£0.20£0.30£0.40£0.50£0.60£0.70£0.80£0.90
Aberdeen City…
Aberdeenshire…
Angus Council
Argyll &
Bute…
Clackmannanshir…
Dumfries and…
Dundee City…
East…
East Lothian…
Falkirk Council
Fife Council
Glasgow
City…
Inverclyde Council
Midlothian Council
Moray Council
North Ayrshire…
North…
Orkney Island…
Perth and Kinross…
Renfrewshire…
Scottish Borders…
Shetland Island…
South…
Stirling Council
The City of…
The Highland…
West…
West Lothian…
Local Authority EVC Tariff
FAST RAPID
Page 31

Page 32

Council business
chargers
£157,000 from Switched
on Fleets 
Successful installs at
Jackson’s Quarry depot,
Oban, and an additional
unit at Helensburgh Civic
Centre 
Out to tender for installs
at the Hub Offices at
Union Street, Rothesay
and Kintyre House,
Campbeltown to support
the office rationalisation
project. 
These chargers have the
effect of increasing the
public network as it
means there are specific
chargers for Council
business use which
relieves pressure on the
public network. We have
also been working with
NHS and other public
partners about use of
each other’s chargers
with a view to developing
a wider partnership
approach to fleet
decarbonisation. 
Tarbert  £45,000 from SSEN Funding has now been
secured for this and is in
the Council’s accounts.
We are currently out to
tender for this as part of
the same exercise for the
above office installations.  
Tighnabruaich £63,000 from Transport
Scotland
This scheme was
delivered in 2022/23 
4.0 CONCLUSION
4.1  A significant amount of work is ongoing to develop a network which will support
decarbonisation and lead to cleaner, greener transport. How the strategy
develops from this point will largely depend on clarity on future funding and will
need to be the subject of future discussions, report and decisions.   
Page 32

Page 33

5.0 IMPLICATIONS 
5.1 Policy – EVC strategy expansion plan and development methodology has been
formally agreed in December 2022. It may be the case that this needs to be
revisited depending on the outcome of the EVIF application.
5.2 Financial – cost recovery model is covering electricity costs and have been
recommended for adjustment to cover asset management costs which were
previously externally funded; capital costs currently 100% externally funded.
5.3  Legal – None. 
5.4  HR – None.
5.5  Fairer Scotland Duty:
5.5.1   Equalities - protected characteristics – None.  
5.5.2   Socio-economic Duty – None.  
5.5.3   Islands – Gaps in the network are prioritised through the public programme. 
5.6 Climate Change – Implications for climate change through EVC strategy are
very positive. Expanding our public network will encourage people to transition
to electric vehicles, reducing CO2 emissions and moving towards a cleaner,
greener transport system. 
5.7 Risk – In terms of future options, there may be risks associated to a
commercial model.
5.8    Customer Service – Work to ensure a better maintenance and warranty
contract is increasing network reliability and providing a better service for our
customers. 
5.9 The Rights of the Child (UNCRC) – None arising from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure
Policy Lead for Roads and Transport, Councillor Andrew Kain
February 2024                                               
For further information contact: 
Jim Smith, Head of Roads and Infrastructure 
Jim.smith@argyll-bute.gov.uk 
Mark Calder, Project Manager
Mark.calder@argyll-bute.gov.uk 
Page 33

Page 34

Victoria Weir, Project Officer 
Victoria.weir@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – updated EVC expansion list
Page 34

Page 35

Chargers beyond economic life
Sites expected to be delivered in 2024
Sites delivered since last update December 2022
Chargers beyond economic life and replaced as part of FASTER Project
AREA TOWN/VILLAGE EXISTING LOCATION COUNCIL OWNED PROPOSED THEME PRIORITY COMMENTS
STRACHUR MEMORIAL HALL Y 1 x RAPID 1 1
This would provide for a network gap between Dunoon and
Inveraray/Arrochar. This is a third party owned site - we have had
positive initial discussions with the owners
GUILDFORD SQUARE Y 1 x RAPID 1 1
Rapid charging provision has now been provided via the FASTER
project noted below. It may be the case that, with the 2x RAPIDs
provided at Rothesay Harbour, the Guildford Square site needn't be
as high a priority.
GUILDFORD SQUARE Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks
1 x SLOW GUILDFORD SQUARE Y
This charger has reached the end of its economical life and we are
seeking to decommission it and, in time, when funding becomes
available, replace it with a FAST or RAPID charger
CHAPELHILL ROAD CAR PARK Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks
2 x RAPID ROTHESAY HARBOUR Y 1 2
Delivered 2x RAPID chargers as part of HITRANS FASTER project
2023. This provides additional capacity over and above what was
planned, in agreement with HITRANS in order to access and
maximise funding. Also bolsters the provision given the issues with
the Guildford Square charger noted above.
ROTHESAY HARBOUR Y 1 x FAST or SLOW
[TBC] 2 2 Different type of charger at this site to provide for those ferry
passengers who would leave their car.
TIGHNABRUAICH 1x RAPID AND 1x
FAST ROCKBANK Y 1 2 Previousy committed to via 2019/20 TS LAIP funding, now delivered
INNELLAN SANDY BEACH Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
PORT BANNATYNE ON-STREET PARKING BAY [EXACT DETAILS TBC] Y 1 x FAST 2 1 On the basis that there is no off-street car park proposed on street
to meet network gap
1 x FAST AND 1 x
RAPID COAL PIER ALEXANDRA PARADE Y
HANOVER STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
KIRK STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
ARGYLL STRET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
GLENMORAG CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
JANE VILLA CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
MOIR STREET CAR PARK Y 1 x FAST 2 3 Population 5,000 to 10,000 - 50% off street car parks
SANDBANK TSC CAR PARK Y 1 x FAST 2 1
Population 1,000 to 2,000 - one car park. It should be noted here
that there is another car park owned by a local community group
which may provide for a better location [Ardnadam]
LOCHGOILHEAD SHORE ROAD CAR PARK Y 1 x FAST 2 1 Population fewer  than 1,000 but known tourist hotspot
CARDROSS MAIN STREET CAR PARK Y 1 x FAST 2 2 Population of 2,000 to 5,000 - 25% off-street car parks [or at least
one]
ARROCHAR 1 x RAPID LOCH LONG CAR PARK N
This car park has reverted to Luss Estates and we are currently
engaging with framework suppliers to understand the potential
costs of providing a new charger in Glen Loin 2 which the Council
now owns. Currently, access to the Luss Estates car park is at a cost
which makes access to the charger a cost, unlike the rest of our
network. The charger itself is coming to the end of its economical
life so the most prudent course of action would be to install a
completely new one in Glen Loin 2.
KILCREGGAN SHORE ROAD CAR PARK Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
GARELOCHHEAD COMMUNITY CENTRE Y 1 x FAST 2 2
Population of 2,000 to 5,000 - 25% off-street car parks [or at least
one]. Divergence from the 'higher to lower' original criteria of car
parks on the basis of local geography.
FERRY ROAD CAR PARK Y 1 x RAPID 1 2 Filling a network gap c. 30min drive from Helensburgh
FERRY ROAD CAR PARK Y 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
2 x FAST AND 3 x
RAPID WEST CLYDE STREET Y These have been moved within the site as part of the Waterfront
project.
SINCLAIR STREET CAR PARK Y 1 x FAST 2 4 Population greater than 10,000 - all off street car parks
MAITLAND STREET CAR PARK Y 1 x FAST 2 4 Population greater than 10,000 - all off street car parks
KIDSTON PARK CAR PARK Y 1 x FAST 2 4 Population greater than 10,000 - all off street car parks
GRANT STREET PARK AND RIDE Y 1 x FAST or SLOW
[TBC] 2 1 Rail park and ride
LUSS OLD TOLL HOUSE CAR PARK Y 1x FAST 2 1 Population less than 1,000 but known tourist hotspot
PIER, FERRY ROAD Y 1 x RAPID 1 1 To address a rapid charging network gap between Campbeltown
and Lochgilphead [on the public road network for drivers]
TAYINLOAN FERRY FERMINAL Y 1 x RAPID 1 1 Rapid charger to be provided for cars in the ferry queue as opposed
to parked up.
TAYINLOAN FERRY FERMINAL Y 1 x FAST or SLOW
[TBC] 2 1 Second charger at this site to provide for those ferry passengers
who wouldleave their car.
FERRY TERMINAL Y 1 x RAPID 1 2
Rapid charger to be provided for cars in the ferry queue as opposed
to parked up. As part of ongoing works under the Marine Asset
Management Plan we are looking at options for electricity upgrades
for harbour infrastructure which would include capacity for EVC
FERRY TERMINAL Y 1 x FAST 2 2 Second charger at this site to provide for those ferry passengers
who wouldleave their car.
CARRADALE SHORE ROAD CAR PARK Y 1 x RAPID 1 2 To address  a network gap in East Kintyre
CAMPBELTOWN ROAD CAR PARK Y 1 x RAPID 1 1
To address an existing rapid charging network gap between
Campbeltown and Lochgilphead. We have benefitted from 45k of
funding from SSE for use at this location and are currently out to
tender.
1 x FAST CAMPBELTOWN ROAD CAR PARK Y
NEW QUAY CAR PARK y 1 x FAST 2 2
Population of 2,000 to 5,000 - 25% off-street car parks. Divergence
from the 'higher to lower' original criteria of car parks on the basis
of local geography.
1 x RAPID NEW QUAY CAR PARK y
ARDRISHAIG CHALMERS ST No. 2 CAR PARK 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
2 x FAST AND 1 x
RAPID LORNE ST No. 1 CAR PARK Y
2 x FAST MANSE BRAE CAR PARK Y
INVERARAY 1 x FAST AND 1 x
RAPID THE AVENUE Y
COLONSAY COLONSAY AIRPORT Y 1 x FAST or SLOW
[TBC] 2 4
Island airport. Through enabling funding secured from TS we are
working with colleagues in Strategic Transport to explore options
for power upgrades here which would both serve the airport itself,
which currently has no mains power, as well as provide for EVC.
BOWMORE 1 x RAPID AND 1 x
FAST SCHOOL STREET CAR PARK Y
FERRY TERMINAL Y 1 x RAPID 1 2 Rapid charger to be provided for cars in the ferry queue as opposed
to parked up.
FERRY TERMINAL Y 1 x FAST or SLOW
[TBC] 2 2 Second charger at this site to provide for those ferry passengers
who would leave their car.
CRAIGHOUSE ISLAY COUNCIL CAR PARK 1 x FAST 2 3
Proposed instead of Feoilin ferry terminal with a view to providing
for the main service centre, also noting that the ferry crossing is
relatively short and there is provision on the Islay side
OBAN LOCHAVULLIN CAR PARK
Y
1 x FAST
2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
Consideration will need to be given to known flooding at this site
OBAN
1 x FAST AND 1 x
RAPID TWEEDDALE STREET CAR PARK Y
OBAN LONGSDALE ROAD CAR PARK Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
OBAN CORRAN HALLS 1 Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
OBAN NORTH PIER Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
OBAN GANAVAN SANDS Y 1 x FAST 2 2 Population of 5,000 to 10,000 - 50% off-street car parks.
TIREE 1 x RAPID FERRY TERMINAL SCARANISH N
COLL 1 x RAPID COMMUNITY CENTRE, ARINAGOUR N
Key
BUTE & COWAL
HELENSBURGH &
LOMOND
MID-ARGYLL,
KINTYRE AND THE
ISLANDS
DUNOON
ROTHESAY
ROSNEATH
HELENSBURGH
PORT ASKAIG
TAYINLOAN
GIGHA
TARBERT
CAMPBELTOWN
LOCHGILPHEAD
Page 35

Page 36

FIONNPHORT 1 x RAPID COLUMBA CENTRE CAR PARK
Y Whilst this is an existing site, as part of the Iona Fionnport marine
project we are looking at what electricity upgrades we can lever in
to future proof the site for potential expansion
CRAIGNURE
1 x RAPID AND 1 x
FAST CRAIGNURE CAR PARK Y
TOBERMORY 1 x RAPID LEDAIG CAR PARK Y
PORT APPIN FERRY TERMINAL/SLIPWAY Y 1 x RAPID 1 2 Mainland-side ferry
PORT APPIN FERRY TERMINAL/SLIPWAY Y 1 x FAST or SLOW
[TBC] 2 2 Mainland-side ferry
SEIL [ELLENABEAICH] FERRY TERMINAL/SLIPWAY Y 1 x RAPID 1 2 Mainland-side ferry
SEIL [ELLENABEAICH] FERRY TERMINAL/SLIPWAY Y 1 x FAST or SLOW
[TBC] 2 2 Mainland-side ferry
CUAN FERRY [SEIL]
FERRY TERMINAL/SLIPWAY Y 1 x RAPID 1 2 Mainland-side ferry
CUAN FERRY [SEIL]
FERRY TERMINAL/SLIPWAY Y 1 x FAST or SLOW
[TBC] 2 2 Mainland-side ferry
CULLIPOOL FERRY TERMINAL/SLIPWAY N 1 x RAPID 1 3 Island-side ferry
CULLIPOOL FERRY TERMINAL/SLIPWAY N 1 x FAST or SLOW
[TBC] 2 3 island-side ferry
COLL AIRPORT Y 1 x FAST or SLOW
[TBC] 2 4 Island airport
OBAN AIRPORT Y 1 x FAST or SLOW
[TBC] 2 1 Mainland airport
32 53
ADDITIONAL CHARGERS DELIVERED THROUGH HITRANS FASTER PROJECT AUTUMN/WINTER 2023
BUTE AND COWAL DUNOON 2 x RAPID COAL PIER
MID-ARGYLL,
KINTYRE AND THE
ISLANDS TARBERT 1 x RAPID FERRY TERMINAL
OBAN, LORN AND
THE ISLES OBAN 2 x RAPID CORRAN HALLS
37
OBAN LORN AND
THE ISLES
Page 36

Page 37

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE                                                                           
ROAD AND INFRASTRUCTURE                                            21 MARCH 2024 
ANNUAL STATUS AND OPTIONS REPORT 2024 
1.0 EXECUTIVE SUMMARY
1.1  The Annual Status and Options Report (ASOR) provides an overview of road
infrastructure assets within Argyll and Bute Council based on 2022-23 and
2023-24 data for asset condition, previous investment, asset valuation and
other relevant information. The report provides information, based upon
current available data, on the condition of the asset and future options which
can be considered in terms of investment. The report gives an RCI score, the
higher the RCI score means the poorer the road condition is in. 
The ASOR provides details on each of the following assets: 
• Roads
• Footways
• Structures such as Bridges
• Street Lighting and Traffic Signals
• Street Furniture
• EV Chargers 
1.2   It should be noted that the external Road Condition Index (RCI) report did not
survey our full area with most of our Islands missed, we have therefore used
last year’s figures as the most up to date RCI score. The report sets out the
2023 road and associated infrastructure condition and forecasts future
condition based on different proposed levels of investment. 
1.3   The ASOR demonstrates previous investment in the Roads Reconstruction
Programme in 2022-23 which provided a slight improvement to the overall
Road Condition Index (RCI) from 2021-22. Whilst the condition has only
improved slightly, without the increased investment from Council, the road
condition would have continued to deteriorate, resulting in our road network
being in an extremely poor condition. The condition surveys carried out
nationally have a lag of 2 – 4 years (due to not all of the network being
surveyed in one year). Argyll and Bute’s condition survey is indicating a
smaller percentage in the ‘red’ and this position is anticipated to worsen
Page 37 Agenda Item 7

Page 38

should there be a reduction in available investment. Currently Argyll and Bute
Council, although having improved recently, are listed as having the highest
RCI within our family group consisting of roads authorities with similar roads
networks, effectively our roads index is the poorest of the 8 family group
members for rural authorities in Scotland. 
1.4  Within the ASOR report, the respective asset groups are identified with four
investment options presented to allow members to consider appropriate future
funding which will allow a more informed budget setting process for the
maintenance and improvement of Roads and Infrastructure assets.  
1.5  The ASOR links into the Priority Investment Plans (PIPs) (Previously Service
Asset Management Plan (SAMP)) which forms part of the overall Capital budget
decision making process. The ASOR is a useful tool in assisting Members to
make informed strategic decisions regarding investment of our limited Capital
resources. 
RECOMMENDATIONS 
It is recommended that the Environment, Development and Infrastructure
Committee:- 
• Endorses the Annual Status and Options Report and the positive
analytical feedback it provides and agrees to use the information for
future budget setting.   
Page 38

Page 39

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE                                                                           
ROAD AND INFRASTRUCTURE                                           21 MARCH 2024 
ANNUAL STATUS AND OPTIONS REPORT 2024 
2.0 INTRODUCTION
2.1 This report introduces the Annual Status and Options Report which makes an
analytical assessment of the condition of the Council’s road network and
associated infrastructure as well as setting out projected conditions based on
varying levels of investment.  
3.0 RECOMMENDATIONS
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:- 
• Endorses the Annual Status and Options Report and the positive
analytical feedback it provides and agrees to use the information for
future budget setting.   
4.0 DETAIL
4.1 The ASOR is a report which forms part of a suite of documents which are
recommended by SCOTS for local authorities use. The documents have been
developed in collaboration with all Scottish and Welsh authorities and aim to
improve processes and continue the development and implementation of the
wider use of recognised asset management techniques. When authorities have
fully developed the use of these documents they will enable better value for
money to be delivered and prudent stewardship of the road asset to be
demonstrated. 
4.2  SCOTS have focused on carriageway condition including backlog value and
steady state figures due to carriageways being the single most valuable Council
asset. 
4.3  The ASOR is also a tool which elected members can use to help set priorities
for investing the limited resources available to the Council. 
4.4  At the Argyll and Bute Council Budget Meeting in February 2022, an £8M
investment programme for both 2023/24 and 2024/25 roads reconstruction was
Page 39

Page 40

approved. This was further enhanced by a successful bid to the Scottish Timber
Transport Scheme of £387k. This continued investment coupled with the level
of revenue investment over the last few years has helped to improve the steady
state road condition and ensured that we continue to keep over 50% of our road
network in a Green Condition. 
RCI for 2018-20 = 54.2% of roads needing improvement 
RCI for 2020-22 = 49.8% of roads needing improvement 
RCI for 2021-23 = 48.8% of roads needing improvement 
Previous levels of investment have halted the deterioration of the surfacing,
began to improve network condition and acted as a contributory factor in
reducing the number of CAT 1 & 2 defects. The latest RCI survey results (listed
above) clearly reflect the positive impact previous investment has made whilst
contributing to achieving the corporate goals and objectives. 
4.5  The RCI survey data is utilised along with other relevant available data such as
SCRIM (sideway-force coefficient routine investigation machine), Accident
Statistics, Road Hierarchy, Inspection data and local engineering judgement to
develop an initial list of suitable schemes for inclusion in the road reconstruction
programme. The WDM pavement management system interrogates all the
available data to identify and rank potential schemes. Once a draft list is
compiled further analysis is carried out by local staff to establish scheme costs,
treatment options etc. this is then matched to available funding. The selection
process is under regular review and has been steadily improved over time. 
5.0 CONCLUSION
5.1 This ASOR report has been developed in line with the SCOTS Asset
Management Project and provides a useful resource aimed at providing
relevant decision makers with information which will allow a more informed
choice to be made in respect of future investment options. 
6.0 IMPLICATIONS
6.1 Policy – The ASOR contributes towards policy for infrastructure and roads.
6.2 Financial – Current investment levels provide a steady state for the roads
network.  
6.3  Legal – None known.
6.4  HR – None known.
6.5  Fairer Scotland Duty: None known.
6.5.1   Equalities - protected characteristics – None known.
6.5.2   Socio-economic Duty – None known.
Page 40

Page 41

6.5.3 Islands – the reduction in the Ferry Prices (RET) has increased numbers of
vehicles on island roads which has caused more damage to the island road
network.
6.6  Climate Change –the impact of climate change on key infrastructure is expected
to increase in the coming years.   
6.7 Risk – road Network will deteriorate due to underfunding, as such we need to
prioritise roads which may well affect island and more rural communities more.
6.8  Customer Service – None known.  
6.9 The Rights of the Child (UNCRC) – None arising from this report. 
Executive Director with responsibility for Development and Infrastructure:
Kirsty Flanagan
Policy Lead for Roads and Transport: Councillor Andrew Kain 
February 2024                                              
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
jim.smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
hugh.oneill@argyll-bute.gov.uk  
APPENDICES
Appendix 1 – ASOR Report 
Page 41

Page 42

This page is intentionally left blank

Page 43

Bute • Helensburgh • Islay • Oban • Mull • Campbeltown • Iona • Dunoon • Tiree • Lochgilphead • Seil … 
.
ANNUAL STATUS AND
OPTIONS REPORT   
JANUARY 2024
Page 43

Page 44

2  
Contents
Carriageways .................................................................................................................................................................... 3
1.1 Road Length ............................................................................................................................................................ 3
1.2 Condition ................................................................................................................................................................. 3
1.3 Asset Valuation ....................................................................................................................................................... 3
1.4 Investment ............................................................................................................................................................... 4
1.5 Maintenance Backlog .............................................................................................................................................. 5
1.6 Winter Maintenance ................................................................................................ Error! Bookmark not defined.
1.7 Capital Resurfacing Investment Options ................................................................................................................. 5
1.8 Revenue Funded Preventative Maintenance Investment Options.......................................................................... 6
2.0 Footways ..................................................................................................................................................................... 8
2.1 Length ..................................................................................................................................................................... 8
2.2 Condition ................................................................................................................................................................. 9
2.3 Asset Valuation ....................................................................................................................................................... 9
2.4 Investment ............................................................................................................................................................... 9
2.5 Public Liability Claims ........................................................................................................................................... 10
2.6 Investment Options ............................................................................................................................................... 11
3.0 Street lighting ............................................................................................................................................................ 12
3.1 Inventory................................................................................................................................................................ 12
3.2 Condition ............................................................................................................................................................... 12
3.3 Valuation ............................................................................................................................................................... 13
3.4 Investment ............................................................................................................................................................. 13
3.4 Investment (Cont). ................................................................................................................................................. 14
3.5 Energy Consumption ............................................................................................................................................. 14
3.6 Investment Options ............................................................................................................................................... 15
4.0 Structures .............................................................................................................................................................. 16
4.1 Assets .................................................................................................................................................................... 16
4.2 Condition ............................................................................................................................................................... 16
4.3 Asset Valuation ..................................................................................................................................................... 16
4.4 Investment ............................................................................................................................................................. 17
4.5 Maintenance backlog ............................................................................................................................................ 17
4.6 Flood Risk Management ....................................................................................................................................... 17
4.7 Match Funding Opportunities ................................................................................................................................ 18
4.8 Investment Options ............................................................................................................................................... 18
5.0 Traffic Signals ........................................................................................................................................................... 19
5.1 Inventory................................................................................................................................................................ 19
5.2 Valuation ............................................................................................................................................................... 20
5.3 Investment ............................................................................................................................................................. 20
5.4 Investment Options ............................................................................................................................................... 20
6.0 Street Furniture ......................................................................................................................................................... 22
6.1 Assets .................................................................................................................................................................... 22
6.2 Condition ............................................................................................................................................................... 22
6.3 Valuation ............................................................................................................................................................... 23
6.4 Investment ............................................................................................................................................................. 23
Page 44

Page 45

3
6.5 Investment Options ............................................................................................................................................... 24
7. Road and Infrastructure Recent Projects ................................................................................................................ 26
8. Climate Adaptation …………………………………………………………………………………………25 
Carriageways 
1.1 Road Length 
ALL ROUTES (Kms) MAINLAND ISLAND
Road Class Urban Rural Total Urban Rural Total Urban Rural Total
A 120.436 384.854 505.29 58.765 206.345 265.11 61.671 178.509 240.18
B 138.952 474.556 613.508 34.322 350.047 384.369 104.63 124.509 229.139
C  69.067 365.198 434.265 35.934 251.103 287.037 33.133 114.095 147.228
Unclassified 358.588  374.46 733.048 237.848 243.628 481.476 120.74 130.832 251.572
Totals (Km) 687.043 1599.068 2286.11 366.869 1051.123 1417.99 320.174 547.945 868.12 
1.2 Condition 
Road condition is measured by the
Scottish Road Maintenance Condition
Survey (SRMCS) which assesses
parameters such as surface texture and
cracking, smoothness and rutting. This
provides an indication of the residual life of
the road structure.  
The table opposite analyses the various
conditions of road category for an overall
network figure. This is based on a factored
calculated figure produced by SCOTS
which is a percentage of our roads and not
specific lengths. It should be noted that the external Road Condition Index (RCI) report did not survey our full area
with most of our Islands missed, we have therefore used last year’s figures as the most up to date RCI score. We
have been advised that the external provider will endeavour to get the rest of the network surveyed as soon as
possible, the ASOR will be update when this data is received via a covering report. 
1.3 Asset Valuation 
Page 45

Page 46

4 
Carriageways Valuation (These values include the regional and inflation factors for the current year)
Road Classification Gross Replacement
Cost 
Depreciated
Replacement Cost 
Annualised
Depreciation Cost 
Principal (A) Roads (Urban) £243,477,338 £217,077,320 £2,417,584
Principal (A) Roads (Rural) £528,709,818 £492,266,921 £3,087,858
Classified (B) Roads (Urban) £231,543,236 £206,547,686 £2,302,252
Classified (B) Roads (Rural) £382,314,340 £350,208,437 £2,485,939
Classified (C) Roads (Urban) £91,122,828 £79,238,946 £1,021,479
Classified (C) Roads (Rural) £245,600,490 £219,604,424 £1,971,191
Unclassified Roads (Urban) £421,683,747 £353,474,058 £5,884,204
Unclassified Roads (Rural) £200,882,470 £175,900,806 £1,772,881
Total £2,345,334,267 £2,094,318,597 £20,943,387 
1.4 Investment   
The capital reconstruction programme in 2022-23 delivered £7.5m of investment on a range of surfacing projects
aimed at improving network condition across Argyll.  The table details the surfacing quantities and value within each
activity. The percentage split across activities shows the bulk of investment (77%) is attributed to Surface Dressing
(SD) and thin surfacing works to maximise network coverage. The aim being to seal and extend surface life with a SD
treatment and tackle as much deteriorated surface as possible with thin surfacing works so as to help reduce demand
for reactive treatment works.  
Argyll and Bute Council, applies annually for Strategic Timber Transport Scheme (STTS) funding from the Scottish
Government. Since 2005, the Strategic Timber Transport Scheme (STTS) has financed projects that facilitate the
sustainable transport of timber in rural areas of Scotland and deliver benefits for local communities and the
environment through innovative projects and partnerships.
The fund typically contributes 50-70% of the costs of successful applications, with the remainder coming from Local
Authorities and/or forestry sector partners.  The Overall level of funding for 2024-25  is expected to be confirmed at
the February Council Budget meeting. 
Surface Treatment  Length (m)  Cost (£)  Percentage 
Surface Dressing  82389  £2,263,946   % 
Thin/Micro Surfacing (up to 25mm)  1191  £108,125   1% 
Page 46

Page 47

5 
1.5 Maintenance Backlog 
The SCOTS Headline Maintenance Backlog figure is calculated every two years using road condition data collected
via the Scottish Road Maintenance Condition Survey (SRMCS). The calculation uses surveyed condition data with a
surfacing treatment matrix and national average unit rates to determine the extent of surfacing maintenance required
to bring whole network surface to an ‘A1’ condition with no defects. The value of backlog maintenance for Argyll and
Bute’s Road Network is £122.5M.
The backlog maintenance figure is calculated by WDM on behalf of SCOTS using a modelling tool that applies various
surfacing treatments to the whole network based on RCI condition and national average unit rates for treatments. This
produces the Headline Maintenance Backlog (£122.5M) 
The table and graph below predict future RCI values based on four different investment options. The £8M represents
a steady state/slight improvement to the network. This model has effectively been confirmed by the investment in the
road network over recent years and the slight but steady improvement in road condition (RCI). 
The investment values will likely be increased in future modelling to reflect the inflationary increases. However, for the
purpose of the modelling over a 20 year period, these figures provide a good indication of likely future condition.
However, it should be noted that this modelling does not take into account spikes in investment following significant
weather events e.g. the October 2023 weather event.
1.6 Capital Resurfacing Investment Options
The SCOTS cost projection modelling tool enables an indicative illustration of predicted road surface condition in
terms of RCI to be developed for a range of investment options over a 20yr term. This allows comparisons between
various levels of investment. Options 1-4 are illustrated in the table and chart below for £3m, £5m, £8m and £11m
respectively. 
Condition projection based on investment 
Thin Overlay (>25mm to 60mm)  39010  £2,244,509 29.7%
Moderate Overlay (>60mm to
100mm) 
866  £94,181   1% 
Structural Overlay (>100mm)  1130  £146,570   2% 
Thin Inlay (>25mm to 60mm)  9079  £1,250,779   17% 
Moderate Inlay (>60mm to 100mm)  3658  £565,766   8% 
Structural Inlay (>100mm)  1019  £227,842   3% 
Planned Patching  NA £24,366    0.3% 
Reconstruction (250mm+)  3707  £599,584   8% 
Total   £7,525,669  
Page 47

Page 48

6 
Option 1 - £3m annual investment shows
substantial deterioration of network RCI 
Option 2 - £5m annual investment shows
slower deterioration of network RCI 
Option 3 - £8m annual investment shows
steady or slow improvement of network
RCI (steady state) 
Option 4 £11m annual investment shows
greatest improvement rate of network
RCI 
1.7 Winter Maintenance 
Table below identifies the last 8 years of road and winter maintenance revenue budget
Predicted future RCI values based on the four investment options
(i.e. lower % = better condition)  
Year Option 1 Option 2 Option 3 Option 4
0 49.80% 49.80% 49.80% 49.80%
1 50.10% 49.20% 47.01% 45.75%
2 50.84% 49.38% 47.07% 44.63%
3 52.61% 50.49% 47.12% 43.56%
4 54.27% 51.53% 47.16% 42.57%
5 55.83% 52.51% 47.20% 41.63%
6 57.30% 53.43% 47.23% 40.75%
7 58.67% 54.29% 47.26% 39.93%
8 59.97% 55.10% 47.29% 39.16%
9 61.19% 55.86% 47.31% 38.43%
10 62.33% 56.58% 47.33% 37.74%
11 63.41% 57.25% 47.35% 37.09%
12 64.42% 57.88% 47.36% 36.47%
13 65.37% 58.48% 47.37% 35.89%
14 66.27% 59.04% 47.38% 35.34%
15 67.11% 59.57% 47.39% 34.82%
16 67.90% 60.06% 47.39% 34.34%
17 68.64% 60.53% 47.40% 33.88%
18 69.35% 60.97% 47.40% 33.44%
19 70.01% 61.38% 47.40% 33.03%
20 70.63% 61.77% 47.40% 32.65%
Budgets Roads Winter Total Winter %
2015-16 £3,957,298 £1,644,490 £5,601,788 29.36%
2016-17 £3,972,055 £1,836,286 £5,808,341 31.61%
2017-18 £3,832,056 £1,636,828 £5,468,884 29.93%
Page 48

Page 49

7 
Table below shows outturn actual revenue spend on Roads and winter maintenance for the last 8 years. The
proportion of spend on winter within the total revenue outturn shows a fluctuation due to unplanned weather events 
Spend Roads Winter Total Winter %
2015-16 £4,173,702 £1,832,248 £6,005,950 30.51%
2016-17 £4,243,332 £1,885,851 £6,129,183 30.77%
2017-18 £3,926,258 £2,669,341 £6,595,599 40.47%
2018-19 £3,765,604 £1,791,150 £5,556,754 32.23%
2019-20 £3,485,315 £2,165,845 £5,651,160 38.33%
2020-21 £ 3,360,100 £ 2,251,432 £ 5,611,532 40.12%
2021-22 £3,516,984 £2,355,154 £5,872,138 40.10%
2022-23 £3,746,846 £2,661,350 £6,408,196 41.54% 
1.8 Revenue Funded Preventative Maintenance Investment Options 
The value of undertaking adequate preventative maintenance works cannot be overstated. It is the most vital and
fundamental function required to extend infrastructure service life, strengthen network resilience, and minimise
demand for capital investment. 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research, and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  
2018-19 £3,832,056 £1,621,674 £5,453,730 29.74%
2019-20 £3,411,055 £2,122,154 £5,533,209 38.35%
2020-21 £3,506,058 £2,122,618 £5,628,676 37.71%
2021-22 £ 3,422,540 £ 2,119,974 £5,542,514 38.25% 
2022-23
£3,542,940 £2,108,942 £5,651,882 37.31%
Winter Treatment Information  Ten Year Average 
Total number of planned treatment runs ( equiv Full Fleet)  66 Runs 
Total aggregate annual treatment mileage travelled by all gritting vehicles on
all planned routes  105,902 Miles 
Total tonnage of salt used on carriageways  12,535 Tonnes 
Total Winter actual spend carriageways  £2,158,905 Spend 
Page 49

Page 50

8
`
2.0 Footways 
2.1 Length 
Footways/Footpaths Cycleways Quantities by Hierarchy
Footway Hierarchy Length (m) Area (sqm)
Higher Amenity Footways 41,977 117,536
Other Footways 470,174 1,001,471
Total 512,151 1,119,006
All Footpaths 9,349 11,219
Benefits Drawbacks Considerations
Less maintenance works afforded Doesn`t support corporate objectives
Increased asset deterioration Difficult to demonstrate value
Greater demand for expensive reactive works Future demand for capital investment far greater than
initial savings realised
May compromise current internal service delivery
Benefits Drawbacks Considerations
Maintains existing budget No council budget saving Supports some corporate goals
Retains internal service delivery Requires change in approach Training to focus efforts on prioitised  business needs
Need more focus on planned works Needs commitment to deliver Some investment in better mobile technology
Need better data capture and analysis Development of appropriate service standards
Better value works can be afforded Additional resources needed to implement any changes
Benefits Drawbacks Considerations
Better control of costs No Council budget savings Supports council objectives
Delivers better value maintenance
services
Potential increased budget required Implementing  SCOTS Asset Management recommended
practices
Requires significant cahnges Investment in better mobile technology
More informed decision making Needs commitment to deliver Staff training & Additional resources to implement
Benefits Drawbacks Considerations
Vital maintenance activities delivered Compliance with capital investment rules Supports council objectives
Ability to demostrate value May impact capital investment on other assets Implementing  SCOTS Asset Management recommended
practices
Improved asset management Investment in better mobile technology
Staff training & Additional resources to implement
OPTION 1 Increased pressure on council budgets and the need to realise savings may reduce current investment levels for preventative maintenance 
activities. This needs careful consideration and will impact the quantity of works afforded necessary to provide adequate protection to vital road
assets. It will increase demand for more expensive reactive works which is the vicious cycle essential maintenance activities are currently experiencing.
It will increase future demand for capital investment far greater than initial savings realised.
Delivers short term budget savings
OPTION 2 Maintain existing investment levels  and consider prioritising  activity funding using a risk based approach. Prioritised activities  should be
delivered through a planned programme of works to maximise value for money through appropriate service standards.  Combined with improved
recording of maintenance works asset information can be enhanced to assist driving an improved asset management approach that can break the
current vicious  cycle of reactive maintenance demands.
OPTION 3 Maintain or increase investment levels through a zero based budget approach. This would essentially allocate a percentage budget for
reactive maintenance with the balance of funding allocated through planned schedules and programmes of works to effectively justify and approve
funding allocation against a measured works quantity to meet appropriate service standards. This would refocus effort on delivering measured work
packages  whilst improving capture of asset information to assist delivery of  the benefits from implementing recognised asset management practices.
OPTION 4 Consider funding some maintenance activities using a capital funding allocation. Preventative maintenance is a critical activity some of which
can be easily quantified (Ditching, Gully cleaning, Patching etc.). Delivering planned measurable works would greatly enhance ability to demonstarte
value and prudent stewardship of assets.
Page 50

Page 51

9
Total 9,349 11,219
Cycle Lanes 0 0 
2.2 Condition 
Asset condition surveys for our Footways are not currently undertaken due to limited resources and cost implications.  
2.3 Asset Valuation 
Table 2.3 Footway Valuation by Hierarchy       
`Footway Hierarchy Gross Replacement
Cost 
Depreciated
Replacement Cost
Annualised
Depreciation Cost 
Higher Amenity Footways £11,057,091 £9,386,342 £71,308
Other Footways £94,796,737 £73,596,142 £934,977
Total £105,853,828 £82,982,484 £1,006,285 
2.4 Investment 
Footways investment of £1m over previous 3 years has tackled some of the worst identified sections of the network
aimed at reducing reactive maintenance demands. The planned capital investment for 2021/22 was £900k and a
further £500k for 2022/23 Table 2.4a details the extent of capital works undertaken 2019-20.   
2.4a Footways   
Treatment  Length (m)  Cost (£) 
Surface Treatment  802  £20,641.74 
Resurfaced  1,913  £139,205.57 
Reconstruction    471  £74,045.90 
Totals  3,186  £233,893.21 
Page 51

Page 52

10
2.5 Public Liability Claims 
Page 52

Page 53

11
2.6 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research, and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources. Investment options should be inked to the long-
term maintenance strategy for the asset.. 
Page 53

Page 54

12
3.0 Street lighting 
3.1 Inventory 
Street Lighting Quantities  Other Street Lighting Assets
Column Material Quantity Other Street Lighting Assets Quantity 
Non Galvanised  Steel 2,209 Wall Bracket 1,196
Galvanised  Steel 9,196 Wooden Pole 110
Concrete 29 High Mast Column 0
Aluminium (pre 2000) 1,119 Control Cabinet 751
Aluminium (post 2000) 0 Other 0
Stainless Steel 8 Total 2,057
Cast Iron 0 Cable Assets (Estimated) Quantity (m)
Total 12,561 Cable under Carriageway (10%) 43,050
Luminaires Quantity Cable under Footway (50%) 215,250
All 13,896 Cable under Verge (40%) 172,200
Total 13,896 Total 430,500 
Illuminated Sign Assets
Illuminated Signs Quantity
Signs 433
Bollards 46
Total 479 
3.2 Condition 
The condition of street lighting columns was assessed as part of the LED Luminaire replacement programme using a
four level condition rating as shown in the table below. 
Street Lighting Columns
Condition Rating % Total Asset  
1- V. Good 4708 33.95%
2 - Good 8869 63.96%
3 - Fair 174 1.25%
4 - Poor 116 0.84%
Total 13867   
Page 54

Page 55

13
3.3 Valuation 
Street Lighting Valuation
Column Assets Gross Replacement
Cost 
Depreciated
Replacement Cost 
Annualised
Depreciation Cost 
Non Galvanised  Steel £3,979,085 £394,493 £159,163
Galvanised  Steel £16,599,396 £6,668,805 £553,313
Concrete £28,748 £958 £958
Aluminium (pre 2000) £1,147,178 £60,664 £28,679
Aluminium (post 2000) £0 £0 £0
Stainless Steel £7,919 £7,240 £113
Cast Iron £0 £0 £0
Cable Assets      
Cable under Carriageway £3,694,864 £2,003,337 £61,581
Cable under Footway £16,514,690 £8,955,182 £275,245
Cable under Verge £11,197,303 £6,071,123 £186,622
Other Street Lighting Assets      
Wall Bracket £622,116 £519,553 £15,553
Wooden Pole £108,882 £23,954 £2,178
High Mast Column £0 £0 £0
Control Cabinet £218,473 £100,602 £4,369
Total £54,118,652 £24,805,911 £1,287,775
Luminaires Assets      
Total £2,862,063 £2,121,491 £143,103
Illuminated Signs Assets      
Signs £249,879 £122,527 £9,995
Bollards £17,908 £8,892 £716
Total £267,787 £131,419 £10,711      
All Assets Total £57,248,502 £27,058,821 £1,441,590 
3.4 Investment 
Funding 
Current Year Anticipated Investment (£m)
Funding
source  2023-24 (£m) 2024-25 2025-26 2026-27
Block Allocation Scottish
Government £150k  £150k   TBC TBC 
Block Allocation Carried
Forward
Scottish
Government Nil      
Additional Council Allocation Council £740k      
Prudential Borrowing Council
£674k 
(Not New Legacy –
Over) 
Page 55

Page 56

14
3.4 Investment (Cont). 
The replacement of deteriorated assets that have reached the end or beyond their expected service life is currently
not part of a longer term maintenance strategy or plan. For many years the need to deliver investment savings has
over ridden the need for asset renewals. This reduced funding has delayed asset renewal projects creating an even
older and more fragile asset base leading to a growing backlog of outages and reactive maintenance demands on
very limited resources.  
The LED project highlighted the condition of assets and the growing need for action to develop a longer term
maintenance strategy for investment in asset renewals. Table 3.4 provides and indicative treatment cycle based on
current average expected asset renewal and clearly illustrates the present investment strategy is unsustainable. 
Table 3.4 Street lighting Column and Cable Treatment Cycle    
Treatment  Expected Service Life
(Yrs) 
Annual
Quantity
(Ave)  
Inventory (No.)  Treatment  Cycle
(Years) 
Column Replacement 30  25 No.  13047  522 
Cable replacement  60  750 Lin m.  430,500 (Lin.m)  574 
Luminaire (LED)       20  N/A  14640  All new assets 
3.5 Energy Consumption 
Table  3.5 Annual Energy Consumption 
Year  Total   Unit 
2015/16  6325655.3  kWh 
2016/17  6119183.7  kWh 
2017/18  4288415.2  kWh 
2018/19  3267835.1  kWh 
2019/20  3232557.7  kWh 
2020/21 3228999 kWh
2021/22 3224175         kWh
2022/23 3224175 kWh
Year  Carbon Total  Units 
2015/16  3140  tonnes
CO2 
2016/17  2733  tonnes
CO2 
2017/18  1636  tonnes
CO2 
2018/19  996  tonnes
CO2 
2019/20  889  tonnes
CO2 
2020/21 810 tonnes
Co2
2021/22 738 Tonnes
Co2
2022/23 673 Tonnes
Co2
Page 56

Page 57

15
3.6 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research, and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options should be linked to
development of a long-term maintenance strategy for the asset. 
Benefits Drawbacks Considerations
Continues service delivery for defects Continued long tern asset deterioration Adopting risk based approach to managing the asset
Growing demands for capital investment Resource condition survey of asset to gain information on
asset inventory, condition Etc.
Rising number of public liability claims Development of long term maintenance strategy for the 
asset group
Reactive maintenance is expensive and poor
value
Resource development of a prioritised list of planned
works
Benefits Drawbacks Considerations
Investment tackles worst asset
deterioration
limited asset information and condition data Implementing SCOTS asset management recommended
practices
Planned works deliver better value resources required to identify and quantify 
works
Current use, Is it needed? Can it be removed?
Reduced demand for reactive works Level of works limited within available revenue
budget allocation
Resource development of a prioritised list of planned
works
Less complaints Development of long term maintenance strategy for asset
group
Benefits Drawbacks Considerations
Investment tackles deterioration and
gradually improves whole asset
limited asset information and condition data Development of long term maintenance strategy for asset
group
Demonstrates prudent stewardship of
assets
resources required to identify scope of works Investment in mobile technology to capture asset data
Supports corporate objectives Requires increased levels  investment Implementing SCOTS asset management recommended
practices
Benefits Drawbacks Considerations
Whole asset approach to maintenance requires substantial capital investment Use of SCOTS asset management tools
Requires significant improvement in asset data Investment in mobile technology
Deveolpment of appropriate maintenace strategy
Option 1  Undertake maintenance on a reactive basis to repair defects within existing revenue budget allocation.
Option 2      Increased investment in planned revenue maintenance activities
Option 3    Develop a business case for investment through capital budget for replacement of obsolete, damaged and deteriorated assets particularly
vehicle safety barriers. Align the business case to a suitable long term maintenance strategy for the asset group.
Option 4   Business case development for capital investment in conjunction with other asset groups that aligns with the Road Asset management Plan
(RAMP) and council priorities.
Page 57

Page 58

16
4.0 Structures 
4.1 Assets 
Table 4.1 : Structures Inventory 
Quantity 
Road Bridges  890 
Footbridges  11 
Unusual Structures  2 
Retaining Walls  1888 
Height, Sign and Signal Gantry 0 
Culverts   294 
Subways  0 
Total  3085  
4.2 Condition 
Our bridges and structures are
inspected and assessed to comply with
the “Well-managed highway
infrastructure” Code of Practice. Data
gathered from bridge inspections is
used to calculate a Bridge Stock
Condition Indicator value which can
enable analysis and trending of
condition information. The condition
results since 2012/13 are illustrated in
the chart below which shows a steady
decline in overall bridge stock condition
from a reduction in capital investment
with revenue investment being
prioritised towards reactive repairs. The
long term trend line in blue shows a
continued deterioration of assets with
condition of less critical structures expected to decline further without increased levels of investment.  
There are currently 53 structures subject to special monitoring precautions and 28 bridges that have failed the
European standard assessment (prior to restrictions). 15 bridges are currently subject to acceptable weight
restrictions.
Bridges are subject to regular inspections with principal inspections every 6 years and general inspections every 2
years.
4.3 Asset Valuation 
Table 5.5 Structures Valuation Summary
Structure Type
Gross Replacement
Cost 
Depreciated
Replacement Cost 
Annualised
Depreciation Cost 
Road Bridges £115,251,542 £108,769,286 £1,268,947
Footbridges £2,934,648 £2,924,575 £2,117
Unusual Structures £2,286,856 £1,876,450 £18,390
Retaining Walls £166,492,505 £166,442,331 £20,470
Height, Sign and Signal Gantries £0 £0 £0
Culverts   £3,533,754 £3,528,339 £294
Subways £0 £0 £0
TOTALS £290,499,306 £283,540,981 £1,310,218 
Page 58

Page 59

17
4.4 Investment 
PLANNED INVESTMENT    
2022-
23
2023-
24
2024-
25
2025-
26 Comments
CAPITAL
Bridge
Strengthening/Replacement
Programme
£350k £350k £350k  
Bridge & Retaining Wall:
• Strengthening
• Replacement 
Previous Years BSRP
Slippage £999k      
Local Bridge Maintenance
Fund – Grant Funding
Secured *
£244k £4,972k  
Coastal Protection  £100k £100k   Coastal Protection
Strengthening repairs
Ardbeg Seawall / Bute Sea
Wall Repairs £67k £683k      Repairs of asset following
December 2021 storm damage
Coastal Change Adaptation £1k £159k     Secured funding for   Coastal
Change Adaptation
REVENUE
Structural Maintenance £231k £231k £231k £231k
Bridges & Retaining Walls:
• Maintenance & Repair,
• Inspection,
• Asset Management
• Abnormal Load Monitoring,
• Technical Approval
Budget confirmed Annually
Structural Assessment £64k £64k £64k £64k
Assessment of Bridges &
Retaining Walls. 
Budget confirmed Annually
Coastal Protection £180k £180k £180k £180k
Inspections, Maintenance &
Repairs,  Asset Management 
Budget confirmed Annually
• Note contract price increases due to a number of factors, which are reported elsewhere to March EDI
Committee, mean that there is a significant shortfall with the available Scottish Government Local Bridge
Maintenance Fund. 
4.5 Maintenance backlog 
Headline Backlog Figure   Steady State Figure  Source 
£29.2m   N/A  Argyll and Bute Council Asset Management
Reporting 
4.6 Flood Risk Management
Argyll and Bute Council has a statutory duty under the Flood Risk Management Act (Scotland) 2009 to reduce the
overall flood risk through Local Flood Risk Management Plans subject to funding availability. This includes Flood
Incident Investigation, Waterbody Assessments, Provision of Flood Consultancy (General Flood Advice), Clearance
and Repair Works, Mapping, Flood Risk Assessments, Flood Studies, Flood Monitoring Network, Production and
Update of Local Flood Risk Management Plans. These works are undertaken in conjunction with the Scottish
Environment Protection Agency (SEPA) and other responsible authorities as defined under the Act. The current
budget allocation for flood risk management are: 
Page 59

Page 60

18
PLANNED INVESTMENT    
2022-23 2023-24 2024-25 2025-26 Comments
FLOOD RISK MANAGEMENT
CAPITAL
Flood Protection £12k £838k £305k  £155k
• Tigh Dearg
• Rothesay FPS
Performance
Helensburgh Flood
Mitigation £1k  £431k      
Campbeltown Flood
Protection Scheme £4.114m £9.729m £0.029m £0.33m
Design & Construction of
Flood Protection
Scheme.
80% of costs at contract
award funded by Scottish
Government.
All other costs funded by
ABC.
REVENUE
Flood Management £222k £222k £222k £222k
• Flood Incident
Investigation 
• Waterbody
Assessments 
• Provision Of Flood
Consultancy
(General Flood
Advice) 
• Clearance and
Repair Works
• Mapping
• Flood Risk
Assessments
• Flood Studies
• Flood Monitoring
Network
• Production and
Update of Local
Flood Risk
Management Plans
Budget confirmed
Annually
Flooding Direct Costs £100k £100k £100k £100k
Works by ABC
Operational Services
Budget confirmed
Annually 
4.7 Match Funding Opportunities 
The Scottish Government currently offers 80% funding opportunity for local authorities towards development of
necessary flood protection schemes. The actions defined in section 4.6 ensure the Council meets the Scottish
Government’s defined process to enable capture of any potential funding for Argyll.
4.8 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options be linked to development of
a long term maintenance strategy for the asset. 
Page 60

Page 61

19 
5.0 Traffic Signals 
5.1 Inventory
Traffic Signal Types Quantity  Other Traffic Management
System Types Quantity 
Traffic Signal (Junction)    Information Systems 2
Benefits Drawbacks Considerations
Continues service delivery for defects Continued Asset deterioration Development of a long term maintenance strategy
Increased risk of more  weight restrictions or
road closures
Strengthen the business case for investment
Impacts Economy and vital transport links Explore funding opportunities Etc. (Flood prevention Etc)
Reactive maintenance is expensive and poor
value
Benefits Drawbacks Considerations
Continues service delivery for defects Asset deterioration remains  greater than
investment
Development of a long term maintenance strategy
Tackles some preventative maintenance
backlog
Impacts Economy and vital transport links Strengthen the business case for investment
Contributes to lowering  risk of more 
weight restrictions or road closures
Reactive maintenance is expensive and poor
value
Explore funding opportunities Etc. (Flood prevention Etc)
Benefits Drawbacks Considerations
Contributes to development of more
sustainable asset management regime
Requires investment Development of a long term maintenance strategy
Planned preventative maintenance
programme of works
Requires resource to develop business case Strengthen the business case for investment
More sustainable asset condition Explore funding opportunities Etc. (Flood prevention Etc)
Supports corporate objectives Resources to undertake increased workload
Benefits Drawbacks Considerations
Sustaniable asset management regime Requires substantial level of investment Development of a long term maintenance strategy
Improves asset condition Requires resource to develop successful business
case
Resources to undertake/ manage increased workload and
projet design and development.
Reduced weight restrictions May require additional data capture to support
business case development
Explore funding opportunities Etc. (Flood prevention Etc)
Supports corporate objectives
Option 1   Undertake maintenance only on a reactive basis to repair defects within existing revenue budget allocation
Option 2       Increased investment in revenue planned maintenance activities
Option 3 Develop business case for investment through capital budget for strengthening and refurbishment of structures. Development and
implementation of an appropriate long term maintenance strategy for the asset group. Continued improvement in asset management.
Option 4 Development of a successful business case for investment to tackle deterioration and improve overall asset condition as part of a developed
asset management process.
Page 61

Page 62

20
Minor Junction  0 Safety Cameras 0
Medium Junction  11 Variable Message Signs 2
Major Junction  0 Vehicle Activated Signs 18
Complex Junction 0 Real Time Passenger Information 0
Traffic Signal (Pedestrian Crossing)       
Single Carriageway 14    
Double Carriageway 0    
Total 25 Total 22 
5.2 Valuation 
Traffic Signal Types Quantity  Gross
Replacement Cost 
Depreciated
Replacement Cost
Annualised
Depreciation
Cost
Junctions 11 £571,923.00 £335,788.13 £23,830.13
Pedestrian Crossings 14 £323,512.00 £142,547.48 £14,153.65     
Total 25 £895,435.00 £478,335.60 £37,983.78 
5.3 Investment 
Traffic management systems require specialist contractors to undertake regular inspection and necessary
maintenance. Increasing reactive maintenance costs are being incurred as some assets are functioning beyond their
expected service lives and when problems arise replacement of obsolete parts is difficult to procure. 
Many traffic management assets have had essential works postponed over time due to budget restrictions. Although it
is the smallest asset group, delays in asset renewal particularly electronic hardware can lead to parts becoming
obsolete as advances in technology become available. A recent survey has highlighted the need for some urgent
repairs to bring systems up to date. Historically junctions and pedestrian crossing have been replaced ad hoc in
response to system failures or inability to obtain replacement components. Generally this equates to approx. one
junction or crossing per year.  The table below provides an indicative illustration of the asset renewal cycle. 
Planned Investment Budgets  
2023-24 2024-25 2025-26
Capital  £-Nil £-Nil £-Nil
Revenue £45k £45k £45k
Total Budget £45k £45k £45k 
5.4 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options should be linked to
development of a long term maintenance strategy for the asset. 
Page 62

Page 63

21 
Benefits Drawbacks Considerations
Maintains existing service Specialised works undertaken by external
contractors Revised tender for routine inspection and maintenance
Deteriorated asset base drives increasing reactive
maintenance costs
Requires additional resource to develop appropriate
business case.
Requires occaissional capital investment to
replace obsolete /defective equipment.
Benefits Drawbacks Considerations
Improved asset relaiability Requires investment Resource and staff training to improve asset knowledge
Reduced maintenance costs Requires resource to develop suitable business
case for investment using capital budget
Development of a suitable maintenance strategy for asset
Requires rescoure to procure tenders and
administer/supervise potential contract works
Benefits Drawbacks Considerations
Modernises asset to meet current
standards
Requires investment
Resource to manage and supervise works
Improves reliability Requires resource to develop suitable business
case for investment using capital budget
resource required to procure tender documentation and
administration of same
reduces reactive maintenance costs Use SCOTS Asset management tools
Improves user experience
Benefits Drawbacks Considerations
Modernises asset to meet current
standards
Requires investment
Resource to manage and supervise works
Improves reliability Requires resource to develop suitable business
case for investment using capital budget
Resource required to procure tender documentation and
administration of same
reduces reactive maintenance costs Use SCOTS Asset management tools
Improves user experience
Assess need for individual assets. Can they be removed?
Are alternative control measures available?
Option 1    Continue to fund Traffic Signals within existing annual allocation of £45k revenue budget
Option 2           Utilise latest condition survey data to develop an appropriate business case for investment in renewal of apparatus
Option 3    Produce a business case based on latest survey data to upgrade all apparatus to meet  compliance with current standards over a three to
five year period
Option 4      Utilise latest condition survey data to identify asset needs. Address any priority repairs and progress a maintenance strategy as part of the
RAMP to develop a long term investment plan over next three - five years to bring asset condition to meet compliance with current standards.
Page 63

Page 64

22
6.0 Street Furniture 
6.1 Assets 
Table 6.1 Street Furniture Quantities
Street Furniture Assets Quantity of Assets Unit
Traffic Signs (non-illuminated) 5,013 Number
Safety Fences 61,629 Length (m)
Road Blockers 0 Number
Hostile Vehicle Barriers 0 Length (m)
Pedestrian Barriers 197 Length (m)
Street Name Plates Currently no data in system Number
Bins Currently no data in system Number
Bollards 276 Number
Bus Shelters 315 Number
Grit Bins 584 Number
Cattle Grids 162 Number
Gates Currently no data in system Number
Trees  Currently no data in system Number
Seating Currently no data in system Number
Verge Marker Posts 2,322 Number
On-Street Parking Meter 92 Number
Electric Car Charging Points 30 Number
Milestones Currently no data in system Number
Information Boards Currently no data in system Number
Bike Parking Lockers 0 Number
Bike Parking Stands Currently no data in system Number
Automatic Trash Screens 0 Number
Watercourse Telemetry Currently no data in system Number
Weather Stations 14 Number 
6.2 Condition
Asset condition surveys are not currently undertaken due to limited resources and cost implications.  
The condition of vehicle safety barriers has been reported previously and requires substantial investment to address.
Initial local officer estimates indicate £2.5m investment needed which requires resource to develop an appropriate
business case. It should be noted that vehicle barriers are a specialist work requiring appropriate national certification
and staff training to enable progress. There is currently no staff resource with required certification so design works
will need external consultants to survey and quantify full extent of works.   
6.3 Electric Vehicle Charging  
There is growing demand for the installation of electric vehicle charging points across Argyll.  A number of units have
already been installed since 2017 as detailed in tables below. Future installations are also shown based on current
funding until 2021. Consideration is required on the ongoing management and future maintenance and inspection of
these assets. This will require resource and budget allocation moving forward together with an associated
maintenance strategy for an asset that is likely to see accelerated growth over future years.   
Page 64

Page 65

23 
6.4 Valuation 
Street Furniture Valuation
Street Furniture Assets Gross Replacement
Cost
Depreciated
Replacement Cost 
Annualised
Depreciation Cost 
Traffic Signs (non-illuminated) £158,244.37 £79,126.92 £7,912.22
Safety Fences £4,668,248.84 £2,334,158.51 £233,412.44
Road Blockers £0.00 £0.00 £0.00
Hostile Vehicle Barriers £0.00 £0.00 £0.00
Pedestrian Barriers £14,922.28 £7,338.43 £596.89
Street Name Plates £0.00 £0.00 £0.00
Bins £0.00 £0.00 £0.00
Bollards £17,424.87 £8,557.13 £696.99
Bus Shelters £3,861,156.16 £1,933,642.49 £193,057.81
Grit Bins £73,730.33 £38,119.25 £4,915.36
Cattle Grids £818,124.21 £401,385.88 £32,724.97
Gates £0.00 £0.00 £0.00
Trees  £0.00 £0.00 £0.00
Seating £0.00 £0.00 £0.00
Verge Marker Posts £58,620.03 £30,289.54 £3,908.00
On-Street Parking Meter £382,668.48 £191,750.18 £19,133.42
Electric Car Charging Points £668,491.33 £367,670.23 £66,849.13
Milestones £0.00 £0.00 £0.00
Information Boards £0.00 £0.00 £0.00
Bike Parking Lockers £0.00 £0.00 £0.00
Bike Parking Stands £0.00 £0.00 £0.00
Automatic Trash Screens £0.00 £0.00 £0.00
Watercourse Telemetry £0.00 £0.00 £0.00
Weather Stations £249,913.02 £128,526.70 £12,495.65
Total £10,971,543.91 £5,520,565.25 £575,702.89 
6.5 Investment 
The street furniture asset consists of many different individual assets all of which deteriorate at different rates.
Generally, assets deteriorate to the point where they stop performing their intended function and are replaced with
new items in line with available funding. Table 6.4 below provides an indication of the renewal cycle for some street
Asset Inventory 
Type No.
Rapid  11 
Fast  10 
Unknown 7
Planned Future Installation
Year Type of  Unit 
Fast  Rapid 
2019-20  2  2 
2020-21 1  1 
2021-22  1  1
2022-23  
2023-24  
Electric Vehicle     
Charging points 
Year Units
2017  4 
2018  3 
2019  8 
2020  1 
2021 
2022 
2023 
Page 65

Page 66

24
furniture assets based on previous year budget allocation and estimated asset renewal rates to calculate an indicative
renewal cycle based on current funding allocation. 
Table 6.4 Indicative Treatment Cycle for Asset Renewals 
Item 
Budget Allocation   
2023-20 
Current Inventory
Data 
Annual Replacement
Quantity 
Indicative Renewal
cycle 
Cattle Grid  £24,000  162  1.6  101 
Traffic Signs  £52,000  5010  173  29 
Vehicle Safety Fence  £100,000  616289  653  94 
6.6 Investment Options 
Below are a number of initial revenue budget investment options for consideration. These will all require further
investigation, research, and development to progress more detailed information on which option is best suited to
support council objectives within the confines of available resources.  Investment options should be linked to
development of a long-term maintenance strategy for the asset. 
Page 66

Page 67

25 
Benefits Drawbacks Considerations
Continues service delivery for defects Continued long tern asset deterioration Adopting risk based approach to managing the asset
Growing demands for capital investment Resource condition survey of asset to gain information on
asset inventory, condition Etc.
Rising number of public liability claims Development of long term maintenance strategy for the 
asset group
Reactive maintenance is expensive and poor
value
Resource development of a prioritised list of planned
works
Benefits Drawbacks Considerations
Investment tackles worst asset
deterioration
limited asset information and condition data Implementing SCOTS asset management recommended
practices
Planned works deliver better value resources required to identify and quantify 
works
Current use, Is it needed? Can it be removed?
Reduced demand for reactive works Level of works limited within available revenue
budget allocation
Resource development of a prioritised list of planned
works
Less complaints Development of long term maintenance strategy for asset
group
Benefits Drawbacks Considerations
Investment tackles deterioration and
gradually improves whole asset
limited asset information and condition data Development of long term maintenance strategy for asset
group
Demonstrates prudent stewardship of
assets
resources required to identify scope of works Investment in mobile technology to capture asset data
Supports corporate objectives Requires increased levels  investment Implementing SCOTS asset management recommended
practices
Benefits Drawbacks Considerations
Whole asset approach to maintenance requires substantial capital investment Use of SCOTS asset management tools
Requires significant improvement in asset data Investment in mobile technology
Deveolpment of appropriate maintenace strategy
Option 1  Undertake maintenance on a reactive basis to repair defects within existing revenue budget allocation.
Option 2      Increased investment in planned revenue maintenance activities
Option 3    Develop a business case for investment through capital budget for replacement of obsolete, damaged and deteriorated assets particularly
vehicle safety barriers. Align the business case to a suitable long term maintenance strategy for the asset group.
Option 4   Business case development for capital investment in conjunction with other asset groups that aligns with the Road Asset management Plan
(RAMP) and council priorities.
Page 67

Page 68

26
7. Road and Infrastructure Recent Projects 
Photographs below showing some of the works projects undertaken by Roads and Infrastructure teams illustrating the
diverse scope of works particularly during increased demands clearing and rectifying network damage following recent
storm events. 
Kilmelford Bridge
Landslip ArdfernLandslip Ardfern
Lochgilphead Town Centre
Page 68

Page 69

27
8.0 Climate Adaptation 
We are seeing an increasing number of weather events locally, nationally and internationally no doubt linked to climate
change which compromise the transport network.  The most recent event was experienced in October 2023 and over
recent years in Argyll and Bute we have had several weather events including:
• West of Mull bridge wash out At the foot of Ben More July 2012;
• Clachan snow event March 2013 – significant snow fall blocked the road and the weight of frozen snow on
power lines resulted in power lines breaking and several thousand households being without power;
• Beast from the east February 2018;
• Sea wall wash out Bute December 2021;
• Numerous flood events in locations such as Lochavullin Oban, East and West Clyde Street Helensburgh,
Rothesay, Campbeltown (flood prevention works underway) Lochgilphead Front Green etc.
• October 2023 – severe heavy rainfall resulted in transport connections into and out of Argyll and Bute were
severely compromised on Saturday 7 October and for a period of time, all of the trunk roads and many of the
local roads were impassable. Numerous people became stranded due to flood waters, landslips and damaged
structures. Mountain rescue were deployed along with the coastguard who arranged ground units and a
helicopter to support the response to assist Police Scotland who were coordinating the responses in line with
protocol for major incident response. 
Adaptations have been carried out including reinforcement to bridge abutments, reinforcement and rebuilding of
embankments, provision of temporary roads to avoid unstable slopes with a long term proposal to divert the road near
Ardfern on a permanent basis. Furthermore, adaptation is being incorporated into various other works including sea
defence, flood prevention works etc. 
The following images provide a snapshot of some of the damage caused during the October 2023 event. 
The photo to the left shows the Ardfern landslip on the
A816 – c.15000 tonnes of material blocked the road. 
The image to the right shows the extent of the Ardfern slip in
green (at least 3 separate slip events took place) the purple
shading is the ditch/pit which would catch any future flow, the
blue line is a bund to keep the majority of any future flow in the
ditch and the red is the proposed emergency road which takes
traffic away from the slip affected area and provides a safe
alternative route during future weather events. 
Page 69

Page 70

28 
There is significant additional content and photographs available to Elected Members from the various presentations
given immediately following the October 2023 weather event.
Environmental science provides the evidence that climate change is resulting in changing weather patterns. These
weather patterns and also rising sea levels mean that increasingly we are having to adapt infrastructure to
accommodate the demands of climate change. Such adaptation comes with significant cost and future investment to
our infrastructure is likely to see an increasing percentage of funding directed towards climate adaptation. 
Page 70

Page 71

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT                    
AND INFRASTRUCTURE COMMITTEE 
ROAD & INFRASTRUCTURE SERVICES                                            21 MARCH 2024 
TRANSPORT (SCOTLAND) ACT 2019 - PAVEMENT, DOUBLE & DROPPED KERB
PARKING STANDARDS 
1.0 INTRODUCTION
1.1 Argyll and Bute Council operates under Decriminalised Parking Enforcement
(DPE) and, as such, already have a small team of wardens carrying out
enforcement on our roads and in our car parks. Obstructive parking on
footways, until recently, remained a matter for Police Scotland.  
1.2 The Scottish Government has been working to improve parking legislation in
Scotland in order to tackle the impact of inconsiderate and obstructive parking
and ensure that our roads and pavements are accessible for all.
1.3 As part of this work, the Transport (Scotland) Act 2019 bans pavement parking,
double parking and parking at dropped kerbs. The 2019 Act gives Local
Authorities the relevant powers to enforce these new provisions.  The Act also
gives Local Authorities the power to exempt footways from the pavement
parking prohibition in certain circumstances and in accordance with Ministerial
Directions. 
2.0 RECOMMENDATION 
2.1 It is recommended the Environment, Development and Infrastructure Committee:- 
i. Considers and notes the changes in legislation; and 
ii. Notes that implementation date for Argyll and Bute is yet to be finalised
and a timeline will be provided to a future Environmental, Development
and Infrastructure Committee once more information becomes
available, including details of any additional resource which may be
required to discharge these additional powers.   
3.0 BACKGROUND 
3.1 The new powers give Local Authorities the tools to be able to tackle the issues
of inconsiderate and obstructive parking which, alongside a planned
Page 71 Agenda Item 8

Page 72

Government led media campaign, will highlight the problems that inconsiderate
parking creates in our everyday lives.  To support these provisions, a suite of
secondary legislation is necessary to bring new legislation into force and
support its operation in practice. The below link gives access to the legislation:-
Transport (Scotland) Act 2019 Part 6 Pavement Parking Prohibition 
3.2 These changes to Regulation will essentially provide three new features to parking
regulation and enforcement:- 
i. Provision for issuing Penalty Charge Notices (PCNs) where double parking
takes place – this is where a vehicle is parked more than 500mm from the
kerb when parallel parked.
ii. The ability to take forward a Traffic Order to permit footway parking provided
1.5m of clear footway space can be maintained. Photo 1 (Appendix 1) below
provides an example of this. Note, we are not expecting this to be a common
feature in Argyll and Bute.
iii. Issuing of PCNs for vehicles parking on footways where an Exemption Order
is not in place to permit this or when obstructing a pedestrian crossing (not
a driveway) as shown in Photo 2 (Appendix 1) below.
3.3 The Regulations received Parliamentary assent and came into force on 11th
December 2023. Transport Scotland have confirmed that this is a power rather
than a duty within the legislation provided to Local Authorities to enforce the
Pavement Parking Prohibitions, however it was widely accepted that not ALL
Local Authorities would be in a position to commence enforcement on 11th
December 2023. It is understood that Edinburgh City Council went live in
January 2024 but the majority of other Scottish Authorities are yet to implement
these changes. 
3.4 Argyll and Bute Council already operates under Decriminalised Parking
Enforcement (DPE) and, as such, already have a small team of wardens
carrying out enforcement on our roads and in our car parks.  We also have the
back office function which allows us to administer the various processes
attached to DPE.  Due to this, we are already effectively set-up to manage the
additional functions outlined in the Transport (Scotland) Act 2019 (specifically,
footway parking, parking at crossing points and double parking), however, we
need to amend our processes which are supported by an externally provided
software system which a number of Councils also use.  This work is currently
underway between our Parking Team, IT colleagues and our software provider.
An implementation date is yet to be finalised and a timeline will be provided to
a future Environmental, Development and Infrastructure Committee once more
information becomes available. This future report will also include any additional
resource which may be required to discharge these additional powers. 
3.5 Once the software has been amended which will enable the relevant ticketing
to be issued, officers intend to carry out a soft start whereby advisory notes will
be issued for a period of two weeks but with repeat offenders being issued with
a PCN i.e. only one warning per vehicle. Prior to any roll out and following the
next report to Environment, Development and Infrastructure Committee, a
detailed Member briefing and communications will be arranged.
Page 72

Page 73

4.0 CONCLUSION 
4.1 This report highlights the changes in legislation in relation to inconsiderate and
obstructive parking and details additional parking enforcement which the Council
will be able to carry out as part of its DPE activity. 
5.0  IMPLICATIONS 
5.1  Policy – This report identifies changes to national legislation which the Council as
Traffic Authority are provided with powers to enforce contraventions. 
5.2  Financial – no estimated financial implications at this time. 
5.3  Legal – changes in Regulations as identified in the report. 
5.4  HR – no known implications at this time. 
5.5  Fairer Scotland Duty: no known implications at this time.   
5.5.1  Equalities - protected characteristics – the new powers available to the Council
will help to reduce the number of blocked crossings or footways caused by
inconsiderately parked vehicles. 
5.5.2  Socio-economic Duty – no known implications at this time. 
5.5.3  Islands – no known implications at this time 
5.6  Climate Change – due regard will be given to climate change with a view to 
minimising any climate change impact and these will be considered as and 
when they arise. Safeguarding footways and clearing obstructions to pedestrian
crossing points should help to encourage more individuals to walk. This, in turn,
may help to reduce the reliance on travel by motor vehicle. 
5.7  Risk – insufficient availability of wardens to effectively provide enforcement patrols
across the full Council area. 
5.8  Customer Service - no known implications at this time. 
5.9 The Rights of the Child (UNCRC) – the new powers available to the Council to
enforce against parking on footways and at crossing points will provide a safer
walking environment for young people 
Executive Director with responsibility for Roads and Infrastructure: Kirsty Flanagan 
Policy Lead for Roads and Transportation: Councillor Andrew Kain 
February 2024
Page 73

Page 74

For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
jim.Smith@argyll-bute.gov.uk 
Stuart Watson, Assistant Network and Standards Manager
stuart.watson@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – Examples of inconsiderate and obstructive parking 
Page 74

Page 75

APPENDIX 1 – EXAMPLES OF INCONSIDERATE AND OBSTRUCTIVE PARKING 
Photo 1 Example of permitted parking where a Traffic Regulation Order is in place
allowing parking with one wheel ‘on the kerb’. Note this is an example of parking
arrangements outside of Argyll and Bute 
Page 75

Page 76

Photo 2 parking which obstructs pedestrian dropped crossing points (regardless of
there being double yellow line as in this example) become a contravention and a PCN
can be issued under the changes detailed in the report. 
Page 76

Page 77

ARGYLL AND BUTE COUNCIL      ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE SERVICES      21 MARCH 2024 
SECOND DOMESTIC BIN REVIEW 2024 
1.0 INTRODUCTION
1.1 The existing policy for second domestic bins (green bins which take general waste)
came into place in 2016 and there has been limited opportunity for this to be
reviewed since its introduction. A review may provide an opportunity to reduce the
numbers of households receiving a second domestic waste bin collection, who are
not entitled to receive this service. 
1.2 With the Biodegradable Municipal Landfill Ban (BMW) coming into place in January
2026, the advancement in technology and the Council introducing route
optimisation, now is considered to be a good time to consider a review of all second
domestic bins to all householders in all areas of Argyll and Bute’s waste collection
service. 
1.3 The Council, working with Zero Waste Scotland, are carrying out waste composition
analysis which will identify the types and percentages of material being disposed of
in the general waste stream. This exercise will help to inform campaigns to increase
recycling and therefore reduce some of the material which is currently ending up in
the general waste system. 
2.0 RECOMMENDATIONS 
It is recommended that members of the Environment, Development and Infrastructure
Committee: 
2.1 Agree to a review being progressed with further information regarding publicity and a
timeframe being reported back to the June Committee.   
3.0 DETAIL
3.1  In June 2016, the Council considered a report proposing an operational service
procedure and which provided operational detail to support the Policy that the
Council agreed at its meeting on 11 February 2016 as part of Service Choices. The
full report can be viewed here: ARGYLL & BUTE COUNCIL (argyll-bute.gov.uk) 
and the service procedure is appended to this report at Appendix 1.
Page 77 Agenda Item 9

Page 78

3.2  Disposal of general waste has both environmental and cost implications. Whilst the
existing PPP contract for part of Argyll and Bute processes material via a
Mechanical Biological Treatment plant (which takes out of the waste stream some
materials which can be recycled or composted), this process is expensive and is not
an approved treatment type beyond the BMW Ban. As such we don’t encourage the
use of second green bins because our focus is on recycling, however, we
understand that, for some people, a second general waste bin may be needed.
Generally speaking we will consider a second green bin if: 
• There are five or more people in your household 
• Someone in your household has a medical condition which means more  
waste is generated 
By contrast second blue bins (for co-mingled recyclable materials excluding glass)
are available free to all households who are producing more recycling material than
will fit in a single bin.
3.3 Officers propose to carry out a second domestic bin review, this will ensure that only
those households who meet the criteria have a second domestic general waste bin
collected. This should also reduce the amount of general waste collected and in
theory increase the amount of recyclable material collected. These changes are likely
to facilitate changes to future collection routes. This review, coupled with additional
information relating to recycling, will be designed to reduce general domestic waste
and increase recycling.
3.4 The purpose of this exercise would be to review all recorded second domestic
waste bins and establish if the household are still eligible for a second bin uplift.
Where the Policy criteria is not met, we will confirm to residents that only one bin
will be lifted in the future.  It should be noted that whilst some second bins have
been provided by the Council, a number of bins have been purchased directly by
residents from other suppliers. This exercise will identify where second bins fall
within Policy and those which do not.   
3.5 Prior to the roll out of the review, there will be a social media campaign and
additional information added to the Council’s website explaining that the review of
second domestic bins is being progressed to reduce the amount of general waste
having to be collected, encourage recycling percentages to be increased and to
make both environmental and financial savings. 
3.6 Given that the Council collect bins from over 48,000 households, this process will
be complex, although, with the introduction of the route optimisation system it
should be easier to identify locations where second bins are eligible for collection.
Where second bins are presented, but not eligible for collection, residents will be
notified and ultimately these second general waste bins will not be collected.
Further reports will be brought back to the Environment, Development and
Infrastructure Committee detailing progress of this exercise. 
3.7 The Service have been working closely with colleagues in the Council’s Customer
Engagement and Transformational Team to create a new function that will allow
automatic reviews for the need for a second domestic waste bin to take place at the
appropriate date of the customer’s review. This will cause minimal disruption in the
Page 78

Page 79

future with more manageable workloads for both the Customer Services Contact
Centre and Operations Administration Team.
Stage Completion Date
Ongoing liaison with Customer Services via a
workshop session regarding possibilities and to
also understand current levels of demand
Commenced and ongoing
Updating of records for all approved second
green bins, where possible due diligence on
ongoing eligibility for second green bins
Commenced and ongoing
Publicity and timeframe for roll out to be prepared  June EDI Committee
Publicity campaign advising of any agreed output
from  EDI Committee
To commence following
EDI Committee June 2024
Checking and verifying of second green bins and
where second bins are not eligible
July 2024 onwards
Estimated completion date
tbc – this will be dependent
on the number of
unauthorised second bins,
resourcing and prioritisation
of other competing
demands. Further
information to be included
in June EDI report.
Rollout of notification for any non-approved second
green bins and actively managing this through the
deployment of warden resource. Further detail of
process and proposals to be reported to June EDI
Committee.
Estimated start October
2024
Completion date to be
confirmed pending no. of
unauthorised second green
bins to be dealt with. 
4.0 CONCLUSION 
4.1 This report proposes that a review of second bins is carried out and in line with the
Policy agreed in June 2016.  Non-eligible second domestic bins will cease to be
collected. This will help to reduce the amount of domestic waste presented at
kerbside, encourage residents to increase recycling and reduce the amount of
material which is currently processed for landfill. 
5.0  IMPLICATIONS
5.1 Policy – As per the Policy agreed in June 2016 at the introduction of 3 weekly waste
collections.
5.2 Financial – It is expected that there will be future waste collection and disposal
savings as a result of this exercise.  
5.3  Legal – None known.
Page 79

Page 80

5.4  HR – None known.
5.5  Fairer Scotland Duty: None known.
5.5.1   Equalities - protected characteristics – None known.
5.5.2   Socio-economic Duty: None known.
5.5.3 Islands – None known.
5.6 Climate Change – Reducing waste currently processed for landfill and increasing
recycling. There should also be a slight reduction in fuel used for vehicles used in
the waste collection and disposal process.
5.7 Risk – Representation from individuals who may lose a second bin service
5.8  Customer Service – Residents may have become dependent on their second
general waste bin. Detailed communications will need to be carried out to keep
citizens involved with this proposal and the reasons it is being progressed.
5.9 The Rights of the Child (UNCRC) – refuse collection and recycling can have
environmental benefits and contribute to the positive future of young people. 
Executive Director with responsibility for Roads and Infrastructure, Kirsty Flanagan 
Policy Lead for Climate Change and Environment, Councillor Ross Moreland 
5th February 2024                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
Jim.Smith@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
Tom.Murphy@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Three Weekly Refuse Collection Service Procedure
Page 80

Page 81

DEVELOPMENT AND
INFRASTRUCTURE SERVICES
Three Weekly Refuse Collection
Operational Service Procedure
Author Amenity Performance Manager
Owner Head of Roads & Amenity Services
Date June 2016
Version 1.2
Page 81

Page 82

1. Objectives
Argyll and Bute Council is committed to increasing recycling
By recycling more we are helping to save the planet’s natural resources, save
energy, reduce landfill costs and reduce the effects of climate change.
2. Introduction
From date tbc for launch we will operate a new waste collection model for
householders which has an even greater focus on our key priority – recycling.
We will now collect general waste (the green bin) on a three-weekly basis and
recyclable waste (blue bin) fortnightly. Where we collect food waste and glass we will
continue to collect at the published frequency. 
Page 82

Page 83

This document sets out our procedures and the standards we expect to achieve for
our residents.
Public Health
We sought public health advice from the Scottish Environmental Protection Agency
(SEPA) when we were thinking about a three-weekly model. They advised us and
other councils that there should not be any increased risk to public health as long as
the existing common sense standards are followed: wrapping waste and keeping the
lid of your bin firmly closed.
3. Wheeled bin identification 
Our waste team needs to be able to identify which bin belongs to which property so
that we can track and monitor waste collections and identify where improvements
can be made. We would encourage people to clearly mark their bins with their house
name or number within two months of the new waste collections starting. 
4 Green bins for general household waste
Green bins are for household waste that cannot be recycled in any of the other bins
we provide.
Every household gets one green (general waste) bin.
5. Blue bins for mixed dry recyclables
We provide a blue bin for mixed dry recyclables. This bin can either be 140 or 240
litres depending on what the customer needs. 
Mixed recyclables are:
 paper
 cardboard
 aluminium cans
 tins
 plastic cartons. 
The blue bin is not for glass, food waste or polyethene wrap or carrier bags.
Further information on what may be recycled can be found on the council website at:
www.argyll-bute.gov.uk/planning-and-environment/recycling
6. Grey bins for glass
Where we are able to collect glass we provide a grey bin.
Page 83

Page 84

We can’t provide this service across all of Argyll and Bute because it just isn’t cost
effective to do so, but we do provide customers with another option. You can take
your glass to a number of bottle banks or to your local civic amenity site.
Information on where these sites are is also available on the website at:
www.argyll-bute.gov.uk/planning-and-environment/recycling
Only glass bottles and jars can be recycled. 
Other glass items don’t break down in the same way so can’t be recycled.
7. Green caddies for food waste
In Helensburgh and Lomond we also provide a caddy (small bin) for food waste. This
is a government requirement due to the population in Helensburgh.
You need to use bin liners in the food waste bin; these can be sourced from the Civic
Centre, Helensburgh Library and the Victoria Halls.
Like the glass collections we can’t provide this service in the rest of the area
because the rural geography makes it both impractical and very costly.
8. Nappies and other sanitary items
We would ask people, in the interests of hygiene, to take a common-sense approach
to binning nappies and other sanitary items by securely bagging them before placing
them in their green bin.
9. If your bin is lost, stolen or damaged
If we damage any of your bins in the course of our work then we will, of course,
repair it where possible or replace it if necessary.
If your green bin is lost or damaged you will have to pay to have it repaired or
replaced.
We will repair or replace any lost, stolen or damaged recycling bin free of charge.
We don’t charge for this because we want to maximise recycling and reduce the
amount of waste going to landfill.
10. Putting your bins out
On your scheduled collection day we would ask that you put your bin out at the
kerbside by 6am in Helensburgh, Oban and Dunoon and by 7.30am in all other
areas, with the lid properly closed.
Please try and put your bin at the side of the footpath so it isn’t causing an
obstruction.
Page 84

Page 85

If your bin is found to be repeatedly causing an obstruction we’ll give you a call to
see if there is any way we can help you put your bin out safely.
We would ask people to put their bins out in the morning rather than the night before
but understand that this may not be possible for everyone.
Our waste teams start work early to get round their routes; if your bin isn’t out in time
they won’t have time to come back for it later.
If your bin is overloaded then we won’t be able to empty it. If it’s too heavy our waste
team could hurt themselves moving it and it could damage the lifting machinery on
the bin lorry.
Extra waste will also fill the lorry up quicker, meaning there is no room for other
peoples’ bins to be emptied.
We would ask that our customers be considerate and not overfill their bins. For the
same reasons we will not take additional waste left in boxes, bin bags etc.at the side
of the bin.
If your collection day needs to change we will put information out well in advance.
11. Collections on unadopted roads
We will collect bins from unadopted roads providing that the road is safe for the bin
lorry.
The driver will decide on the day whether the road is safe. 
If your road is found not to be safe then we will arrange with you a suitable collection
point, most likely at the end of your road where it joins the public highway.
12. Contaminated bins
Contaminated means that the recycling bin has items in it which can’t be recycled.
We can’t take bins with non-recyclable items because the entire lorry load would
then be rejected when we take it to the recycling plant, meaning it would have to go
to landfill, defeating the purpose and incurring a hefty charge to the council.
The more fines we get for contaminated lorry loads and the more we have to pay in
landfill costs the less money we have to deliver other council services that people
rely on.
If your bin is contaminated we will put a tag handle to let you know. We would ask
that you remove the offending items before next putting your bin out.
13. Assisted collection
Some people may be physically unable to put their bins out safely. If you are
someone who struggles with your bin then we have a service to help you.
Page 85

Page 86

Please call 01546 605514 and speak to one of our helpful customer service agents
about an assisted collection service. Once you fill in an application one of our officers
will visit you and see what they can do to help.
If it’s found that you do need a little extra help we’ll agree with you a suitable location
for your bins to be emptied from and returned to. To make sure everything is
operating as it should do and you’re getting the help you need, we’ll review this on
an annual basis.
Of course if you have any problems before your annual review please don’t hesitate
to get in touch with us.
14. Other options
Other options for residents include:-
You can also take your waste to any of our civic amenity sites. Often people will do
this when the have a lot of extra waste coming from a clear out, garden work etc.
Going to the recycling pages on the council website shows the location of the sites:
www.argyll-bute.gov.uk/planning-and-environment/recycling
You can also arrange a special uplift, which comes at a cost because it is an
additional service. Please call 01546 605514 to arrange this.
15. Service Disruptions
If we are having any problems emptying your bin then we’ll let you know through our
website, Facebook and Twitter.
Disruption can be caused by the weather, road closures, vehicle breakdowns and
other circumstances outwith our control. 
If a scheduled service is disrupted we would ask you to put your bin out for 6am the
next day (even if the next day is a Saturday) until advised otherwise.
16. Second green bins
We don’t encourage the use of second green bins because our focus is on recycling,
however, we understand that, for some people, a second general waste bin may be
needed.
You can apply for a second green bin by calling our helpful customer service staff on
01546 605514. If your enquiry can be dealt with over the phone it will be but if not
then one of our officers will visit you and see what we can do to help.
If you are eligible for a second bin then this will be provided free of charge.
Page 86

Page 87

Generally speaking we will consider a second green bin if:
 There are five or more people in your household
 Someone in your household has a medical condition which means more
waste is generated
Your second green bin will be identified as such by a red lid.
We’ll review this on an annual basis to make sure your second bin is still needed. If
it’s found that your second green bin is being used for recyclables rather than
general waste we will remove it and encourage you to use your blue bin for recycled
material.
If you feel your current 140litre green bin isn’t big enough we will provide you with a
240litre one instead.
17. Home composting
We would encourage people to compost suitable garden and uncooked vegetable
waste. More information on home comporting is available at:
www.argyll-bute.gov.uk/content/home-composting-advice
18. Commercial waste
We collect commercial waste but charge for it. This is because commercial
properties don’t pay council tax.
More information on this is available on our website at:
www.argyll-bute.gov.uk/forms/commercial-waste-enquiry-form
Like householders, we would encourage businesses to recycle their waste where
possible.
Page 87

Page 88

This page is intentionally left blank

Page 89

ARGYLL AND BUTE COUNCIL                    ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                           21 MARCH 2024
SERVICES                     
LOCAL BRIDGE MAINTENANCE FUND 
1.0 INTRODUCTION 
1.1 This report provides an update on the £5.450M of funding secured through a
highly competitive bid process from Scottish Government’s £32million Local
Bridge Maintenance Fund. 
1.2 At the Environment, Development and Infrastructure Committee held in June
2022 a report was presented detailing the funding award for the replacement of 4
bridges and strengthening of a further 5. 
1.3 At the Environment, Development and Infrastructure Committee held in June
2023 an update report was presented detailing the negotiations regarding land
(for new bridges), ground investigation and design work has been progressing
well. 
1.4 Work at Ardchonnel Bridge commenced in November 2023 and has been
completed in February 2024. The works to Ardchonnel Bridge include
strengthening the abutments. This work being urgently required to prevent any
further deterioration and increased costs. 
1.5 Work at Whitestone Bridge has been awarded and is scheduled to commence in
March 2024 and is scheduled to complete in May 2024. Similar to Ardchonnel
Bridge, Whitestone Bridge was required to be progressed to strengthen the
abutments and reduce any further deterioration and increased costs. Whitestone
Bridge wasn’t considered to be quite as urgent as Ardchonnel, however, it is still
necessary to progress these works with minimal delay. 
1.6 Designs for Claonaig, Glenegedale (2), Lochgoilhead, Oude, Pennyghael Bridge
are currently progressing. Estimated costs have now been established for all
bridges through a feasibility study outlining preferred design options. Public
Consultations have been carried out for Oude Bridge and Glenegedale (2) Bridge
and are being incorporated into the final feasibility report. 
1.7 Since the bid was submitted to Scottish Government and as detailed in this report,
there have been significant price increases to construction contracts. These
increases mean that the allocated funding is not sufficient to deliver the
programme originally intended. Officers will be engaging with officials at Scottish
Page 89 Agenda Item 10

Page 90

Government to establish if other funding is available and to understand Scottish
Government’s position regarding the affordability of the original programme which
funding was allocated for. 
1.8 If additional funds are not forthcoming then the projects not delivered will be held
back pending additional funding coming from either external sources of council
capital programmes. Note all bridges will continue to be monitored as part of our
ongoing cycle of bridge inspections to ensure that our bridges are safe and
proportionate to use. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee consider this report and note that officers will be
engaging with Scottish Government regarding the increased costs. 
3.0 DETAIL 
3.1 The fund will be used to undertake proportionate works (from strengthening to
comply with ‘construction and use’ weight limits to full off-line rebuilds) on bridges
in need of repair, identified through our inspection programme/ records. Bridges
provide critical transport (often lifeline) connections for some communities and are
a vital part of the wider road network. 
3.2 The table at Appendix 1 details the list of bridges which have received funding
along with indicative site start dates. 
3.3 As noted in Appendix 1 a grant amount of £5.45M was secured based on pre
COVID estimates but the most updated cost estimations show that a cost of
approximately £12.5M will be required. There are seven principal reasons for
this significant increase in costs for the projects: 
• COVID – Cost estimations used to secure grant funds were completed
prior to the full extents of Covid to the economy being understood. The
impact to the Construction Industry resulted in large increased costs to
tender returns.
• Inflation – Although inflation is considered, the severity of it since 2021
could have not been reasonably predicted.
• Brexit – This brought further increase to costs as Contractors need to
charge more due to increase material costs because of import duties
and lack of availability of materials. 
• War in Ukraine – This had a knock-on effect regarding project costs due
to increasing fuel costs and increased cost of production. 
• PAS2080 (2023) – Due to recent environmental legislation as part of the
design/construction process we must consider steps to reduce/manage
carbon output for our projects which have economic repercussions.
• Active Travel Routes – To allow future sustainable transport links we
must include active travel routes on each bridge replacement project
Page 90

Page 91

therefore increasing the width of each deck by 3.5m and any new
approach roads therefore increasing the overall construction costs.
However, we are also considering the cost to maintain existing bridges
to accommodate the active travel traffic. This potentially could reduce
the initial investment although the whole life costs are likely to be similar.
• Feasibility studies – Prior to submitting an application for each bridge
there was inadequate time to carry out a full feasibility study in order to
accurately estimate each project. Minimal design had occurred and
some of the main design constraints were unknown prior to the
application for funding. 
3.4 Due to the identified funding shortfall, all schemes have been prioritised.  The
prioritisation considers, network criticality, design life remaining of existing
structures, current condition of existing structure and cost. The outcome of the
prioritisation process is as follows: 
Bridge Cost 
1 (=) 00019-05 B842-150 Whitestone Bridge  £115,385
1 (=) 00019-29 B839-050 Lochgoilhead Bridge  £472,000
3 (=) 00019-38 B840-140 Ardchonnel Bridge  £93,353
3 (=) 00019-04 B842-010 Claonaig Bridge  £325,000
3 (=) 00019-30 A815-230 Cothouse Bridge  £662,000
6 (=) 00019-12 B844-010 Kilninver Bridge  £2,490,000 
--------------------------------------------------------------------------------------------------------
The bridges above the red line are affordable based on the available
funding. 
6 (=) 00019-37 A849-280 Pennyghael Bridge  £4,575,000
8 00019-25 A846-270 Glenegedale (2)  £1,620,000
9 00019-36 A816-120 Oude  £2,185,000 
3.5 We propose to write to the Scottish Government to alert them to the funding
shortfalls, clarifying the current position and to seek additional funding to progress
all schemes.  In the meantime work to progress the lowest ranked scheme, Oude
Bridge shall be paused. The total revised cost for all schemes above the line is
£4.158M. 
3.6 Location plans for each bridge can be found in Appendix 2. Regular updates
on these works as they progress will be provided through our weekly
members briefing. 
Page 91

Page 92

3.7 Legislation, Standards, Codes of Practice:
Replacement (new) structures are designed in accordance with: 
• Roads (Scotland) Act 1984 Legislation
• Design Manual for Roads and Bridges (DMRB) document “CD 350 -
The design of highway structures” and associated document series
“Highway Structures & Bridges”
• “CIHT 'Well-managed highway infrastructure' Code of Practice” Section
C6 and associated documentation.
• PAS  2080 - Carbon management in infrastructure and built
environment. 
Strengthening (maintenance) works to structures are designed, where
appropriate, in accordance with:
• Roads (Scotland) Act 1984 Legislation
• Design Manual for Roads and Bridges (DMRB) document series
“Highway Structures & Bridges”
• “CIHT 'Well-managed highway infrastructure' Code of Practice” Section
C6 and associated documentation. 
4.0 CONCLUSION 
4.1 This report provides an update on the £5.450M of funding secured in highly
competitive bid process from Scottish Government’s £32 million Local Bridge
Maintenance Fund. 
5.0 IMPLICATIONS 
5.1 Policy – projects are being taken forward to align with key policies like the Local
Outcome Improvement Plan and the Roads Asset Management Plan. Bridge
designs in terms of strength and resilience are required to follow nationally set
construction specifications. 
5.2 Financial – funded from grant funding. The successful award of grant funding
helps to reduce the backlog maintenance figure for the Council’s transport
infrastructure. Note, the original grant allocation is not now adequate to deliver
the full programme. 
5.3  Legal – the Council has statutory duties to maintain infrastructure set out in
various legislation like the Roads Scotland Act 1984. 
5.4  HR – None known. 
5.5  Fairer Scotland Duty: None known. 
5.5.1   Equalities - protected characteristics – an EqSEIA will be completed which
tease out and identify any equality issues which need to be considered for
new bridges.
5.5.2   Socio-economic Duty – none known.
Page 92

Page 93

5.5.3 Islands – the programme will bring benefits to island communities which will
see two bridges being replaced which will help provide additional resilience to
the island’s transportation infrastructure. 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  The provision for pedestrian facilities will be included as part
of the design for new build bridges together consideration for the projected
increase in sea levels due to climate change. 
5.7  Risk – None known. 
5.8  Customer Service – None known. 
5.9 The Rights of the Child (UNCRC) – the investment to improve our bridge
network will contribute to a safer environment for young people to thrive in. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads and Transport: Councillor Andrew Kain   
February 2023                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
jim.smith@argyll-bute.gov.uk 
Elsa Simoes, Infrastructure Design Manager 
elsa.simoes@argyll-bute.gov.uk 
Appendices: 
Appendix 1 – Bridge work details, prioritisation and cost
Appendix 2 – Bridge location plans  
Page 93

Page 94

Appendix 1 – Bridge work details, priorities and cost 
Prioritisation Bridge Name
Asset
sustainability or
asset
improvement
Description of Works
2021 Grant
Amount based
on pre COVID
estimates 
Estimated
Cost @ 2024
Site
Start
Date
Estimated
Completion
Date
=1 B842-150 Whitestone Bridge Sustainability Additional retaining buttress structure constructed on
downstream face of existing bridge. Works required to
be progressed to reduce further deterioration and
increase costs.
£40,000 £115,385 Mar 24 May 24
=1 B839-050 Lochgoilhead Bridge Sustainability Strengthening of arch barrel, including waterproofing,
temporary traffic diversion and drainage works.
£198,000 £472,000 Apr 25 Mar 26
=3 B840-140 Ardchonnel Bridge Sustainability Works started due to safety requirements.
Additional retaining buttress structure constructed on
downstream face of existing bridge.  Works required to
be progressed to reduce further deterioration and
increase costs.
£40,000 £93,353 Nov
23
Feb 24
=3 B842-010 Claonaig Bridge Sustainability Strengthening of wing walls, realignment of road and
drainage works.
£477,000 £325,000 Jan 25 May 25
=3 A815-230 Cothouse Bridge Sustainability Installation of deck waterproofing system (under road
surface), installation of new expansion joints, joint
sealings, concrete repair works, drainage works,
vehicle barrier partial replacement, vegetation removal
£517,000 £662,000 Aug
24
Jun 25
=6 B844-010 Kilninver Bridge Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway)).  
Feasibility Study largely completed
Public Consultation being progressed early 2024.
£1,194,000 £2,490,000 Aug
25
Aug 26 
Affordable schemes from Local Bridge Maintenance Funding subject to Scottish Government
confirming the change in programme
£4,157,738 Subtotal of schemes
above
=6 A849-280 Pennyghael Bridge Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway) downstream / seawards.  
Feasibility Study largely completed
Public Consultation being progressed early 2024.
£1,193,000 £4,575,000 Aug
25
Jul 27
8 A846-270 Glenegedale (2) Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway) in same location. 
A public consultation has been completed.
Feasibility Study identifies preferred option to progress.
£597,000 £1,620,000 Jun 25 Dec 25
9 A816-120 Oude Bridge Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway) upstream / northwards.  
A public consultation has been completed.
Feasibility Study identifies preferred option to progress.
Project in abeyance due to funding shortfalls. 
£1,194,000 £2,185,000 Mar 26 Aug 28
Total   £5,450,000 £12,537,738  
Page 94

Page 95

INFRASTRUCTURE DESIGN,
MANSE BRAE, LOCHGILPHEAD, ARGYLL,PA31 8RD
TITLE
Head of Roads and Infrastructure Services
Jim Smith
DATE
DRAWING NUMBER:
SCALE:
ARGYLL & BUTE COUNCIL --- DEVELOPMENT AND INFRASTRUCTURE SERVICES
© Crown copyright and database right 2023 All right reserved. Ordnance
Survey Licence number 100023368
Not to Scale
00019-4LBMF/001
N
B840-140 Ardchonell Bridge
ISLAY
KINTYRE
BUTE
COWAL
LORN
LOMOND
MULL
ARRAN
MID
ARGYLL
B842-010 Claonaig Bridge
A815-230 Cothouse Bridge
A846-270 Glenegedale (2)
B844-010 Kilninver Bridge
B839-050 Lochgoilhead Bridge
A816-120 Oude Bridge
A849-280 Pennyghael Bridge
B842-150 Whitestone Bridge
Location Plan
Not to Scale
Local Bridge Maintenance Fund
Location Plan for 9 Bridges
16/05/2023
Page 95

Page 96

This page is intentionally left blank

Page 97

ARGYLL AND BUTE COUNCIL                    ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                         21 MARCH 2024
SERVICES                     
ROUTE OPTIMISATION UPDATE 
1.0 INTRODUCTION 
1.1 The Council has invested in a Route Optimisation system which will enable
existing cyclic activities (bin collection, grass cutting, winter gritting etc) to be
tested for efficiency and, where possible, remodel routes to be more efficient
and effective. The system will enable modeling for potentially different service
delivery policy options providing a range of options much quicker than
conventional ‘manual’ modelling processes. At an operational level the system
will provide works supervisors the flexibility to change routing in the event of
vehicle breakdowns, road closures etc. The system is scheduled to be rolled
out in August 2024 following ongoing system building and testing. The
purpose of this report is to provide Members with an update on the
development of the Route Optimisation project following the report to this
Committee in June 2023. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
• Consider and note the progress with the Route Optimisation project;
• Agree to a seminar being arranged for all Members following the
summer recess to demonstrate the functionality and opportunities
available through the system. 
• Note that a further update report will be brought back to the December
2024 Environment, Development and Infrastructure Committee meeting.   
3.0 DETAIL 
Background 
3.1 The Council has appointed Webaspx through a competitive procurement
process. Webaspx are a leading Route Optimisation company who provide
specialist software solutions in routing vehicles and individuals carrying out
cyclic activities including waste management and general municipal activity. 
Page 97 Agenda Item 11

Page 98

3.2 Route Optimisation provides a system which enables routing of cyclic activity
to be efficiently and effectively delivered. The Webaspx system the Council has
invested in, provides various capabilities, including, but not limited, to the
following modules: 
• Route Optimisation - enables new/alternative routes (bin collections
and other cyclic activity) to be designed more efficiently whilst ensuring
deliverability to reduce the risk of service disruption. This will enable
existing collection routes to be tested for efficiency with the opportunity
for replacement routes cutting down travel, costs and carbon emissions.
Different scenarios for collection frequencies will be much easier and
faster to model. This is expected to be hugely beneficial for the
Biodegradable Municipal Landfill Ban, improvements to recycling
percentages etc. Whilst the initial focus will be on modelling refuse
collection routes the system is ideally suited for other activities such as
winter maintenance, street sweeping etc which are intended to be
subsequently modelled. 
• Digital Depot – replaces paper and spreadsheet routes with cloud
based data and automated workflows. 
• In-cab – replaces paper route cards with touch screen tablets providing
the crew and driver with the information they need to work both safely
and efficiently. The in-cab technology also provides information to and
from the back office which will bring customer service benefits in terms
of being able to provide up-to-date information to our citizens. The
system will also enable vehicles to be re-routed at an operational level
to accommodate vehicle breakdowns, road closures etc. 
• Commercial waste - gives the ability to plan and operate commercial
waste services efficiently whilst also enabling customer accounts to be
managed allowing contracts to be easily updated and invoices issued. 
3.3 Bin collection is being progressed as the first activity to be modelled. In doing
so the system will be populated with all address points and collection locations
allowing much of this data to be used for modelling of other activities. Bin
collections also have the potential to offer a significant efficiency, this has been
confirmed from feedback from other Councils and the system supplier. 
Progress 
3.4 The implementation of the Route Optimisation system is progressing well with
existing routes, all 48,000 households, civic amenity sites and tipping points
loaded into the system. Initial training has been carried out with staff. The
ongoing work (tactical modelling) tests the model which includes data cleansing
and adding data such as the location and pick up frequencies for the Civic
Amenity sites etc. 
3.5 In line with good practice for contract management, regular meetings are in
Page 98

Page 99

place between Webaspx and the Council’s Project Team. The project is being
progressed in phases. The first phase was setting up the Easy Route software,
creating the detailed digital model of our road network, our domestic bin
collection, disposal operation is well advanced being reported as phase one.
Thereafter there will be a second phase to set up and utilise the in-cab or digital
depot technology with a forecast go live date of August 2024 following trials and
systems testing. 
3.6 The table below provides Members with an updated outline works programme
to that presented to Environment, Development and Infrastructure Committee
in June 2023. Please note that some stages of the project have changed due
to adding commercial addresses and civic amenity sites in addition to the
residential properties. Any changes to dates/timescales have been noted in the
table, although, the overall completion date remains unchanged: 
Route optimisation Phase One – Easy Route software
Title Description Date Status
Inception
Inception meeting Agree
requirements/
constraints/
deadlines
March 2023 Complete
Data
Roads OS data on road
network 
April 2023 Complete
Properties UPRN information
on all 48,000
households
April 2023 Complete
Routes Uploading existing
bin route
information
April 2023 Complete
Resources Information on
vehicles to cross
reference with
route and property
data
April 2023 Complete
Performance Weighbridge
information from
the different off-
takers
April 2023 Complete
Merging data  Cleansing and
formatting various
data sets
May 2023 Ongoing at the
time of writing
Model development and review
Initial build Webaspx build
software
installation of
EasyRoute
May 2023 Complete,
domestic
properties have
been input and this
element of the
project is
Page 99

Page 100

complete.
Commercial
properties are
scheduled to be
input by end of
March 2024 
Training ABC staff training June 2023 Complete, initial
training is
complete and
additional training
will be carried out
as required.
Model as-is routes Create calibrated
models of current
collections across
all areas
Revised
completion April
2024 
Originally
scheduled for June
2023
On track for
revised date, this
is currently
ongoing and
involving area
teams, ensuring
employee buy in.
Additional
familiarisation and
roll out of the
system’s
functionality.
Review as-is
routes
Ensure As-Is
models reflect
current collections
Revised
completion April
2024 
Originally
scheduled for July
2023
On track for
revised date, this
is currently
ongoing and
involving area
teams, ensuring
employee buy in.
Tactical modelling Model routes and
other options
against different
scenarios
Revised
completion April
2024 
Originally
scheduled for
August 2023
On track for
revised date, this
is the next stage.
The tactical
modelling will take
place on
completion of all
waste routes being
uploaded into the
system (including
commercial and
civic amenity sites
– this being in
addition to
residential
properties). 
Review tactical
modelling
Review remodeled
routes
May 2024  On track
Page 100

Page 101

Operational
modelling
Create fully
implementable
model(s) for each
scenario 
June 2024 On track
Operational review Review and revise
possible new
designs
August 2024 On track
Decision gateway
Operational
Review
Determine next
steps and lead in
to Phase Two
including other
services to be
modeled
October 2024 On track 
4.0 CONCLUSION 
4.1 The new Route Optimisation system is a powerful tool and, once rolled out, will
provide opportunities to model different options, with this firstly being used for
the bin collection routes followed by a wider range of cyclic activities.   
4.2 The initial data upload, review and cleansing stage is very much an iterative
process that requires a reasonable resource commitment from the Council,
particularly given the different waste models used across the area.   
5.0 IMPLICATIONS 
5.1 Policy – There are no direct policy implications arising from this report.   
5.2 Financial – This project is funded from previous funding allocated by the
Council. Future revenue costs are expected to be self-funding from efficiencies. 
5.3  Legal – None known. 
5.4  HR – None known.   
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – Works from this project will be
accompanied by a socio and economic impact assessment.   
5.5.2   Socio-economic Duty – None arising from this report. 
5.5.3 Islands – This project will look at both the mainland and islands and there is
not deemed to be any adverse impact to island communities from this work.   
Page 101

Page 102

5.6 Climate Change – There is potential to reduce the mileage covered by some
vehicles, which would help to work towards reducing the Council’s carbon
footprint.  It is anticipated this will result in CO2 savings however this will not be
fully known until the system is implemented. 
5.7  Risk – None arising from this report.   
5.8  Customer Service – the Route Optimisation system is expected to bring
customer service benefits in terms of being able to provide up-to-date
information to our service users 
5.9 The Rights of the Child (UNCRC) – None arising from this report. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads and Transport: Councillor Andrew Kain and Policy Lead for
Environment and Climate Councillor Ross Moreland   
March 2024                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
Jim.smith@argyll-bute.gov.uk 
Tom Murphy, Operations Manager 
Tom.murphy@argyll-bute.gov.uk 
Page 102

Page 103

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                  21 MARCH 2024
SERVICES                     
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 
1.0  EXECUTIVE SUMMARY 
1.1 The Roads Reconstruction Programme has been structured in line with the Roads
Asset Management and Maintenance Strategy. The focus has been to arrest the
rate of decline and provide an overall improvement in condition as has been
demonstrated in the Annual Status and Options Report. In previous years this has
been achieved through the delivery of a mix of carriageway resurfacing, edge
strengthening, patching/surface dressing and in-situ road surface recycling.
These treatments have been designed to seal the road to stop the ingress of
water, improve ride quality and reduce the number of reactive repairs. This has
resulted in an overall improvement in road conditions. Without this investment and
works there would have been a significant deterioration in condition and a
detriment to the travelling public, economic opportunity and tourism. 
1.2 Attached to this report is a draft programme for roads reconstruction schemes for
2024/25. This programme has been designed using the current Road Condition
Index (RCI) which is produced by the national road condition survey data. In
addition to the RCI data, information such as road traffic collisions, known
development, activities such as timber harvesting and skid condition (of the
carriageways surface) which is measured by a separate survey are also
considered together with information brought forward from Elected Members
during agreed Area Business Days with officers from Roads and Infrastructure
Service. This information is considered at officer level when appropriate
engineering judgement is also applied to ensure that maximum benefit can be
derived from the available investment. 
1.3 As per previous years any post winter deterioration may result in some adjustment
to the programme to ensure that the best rates of return in terms of whole life
costs can be achieved. 
1.4 It is recommended that the Environment, Development and Infrastructure
Committee:- 
• Endorses the proposed programme of capital works for 2024/25
• Agrees that details of each area committee’s programme will be forwarded on
to individual Elected Members.    
Page 103 Agenda Item 12

Page 104

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                  21 MARCH 2024
SERVICES                     
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 
2.0  INTRODUCTION 
2.1 This report provides details of the proposed roads reconstruction programme for
2024/25. The programme is based on the 2024/25 allocation of a total of £8.0M. 
2.2 The additional funding allocated at the Council meeting on 23 February 2023
meant that there was an £8M programme for both this financial year and for last
year. This level of investment is welcomed and enables substantial programmes
of works to be delivered across the road network focusing on arresting
deterioration and where possible improving road condition.   
3.0  RECOMMENDATION 
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:-   
• Endorses the proposed programme of capital works for 2024/25
• Agrees that details of each area committee’s programme will be forwarded on
to individual Elected Members.   
4.0  DETAIL 
4.1  The focus of the roads reconstruction programme has been to recover the
network through the delivery of a mix of carriageway resurfacing schemes,
patching/surface dressing and in-situ road surface recycling, which follow the
principles set out within the Roads Asset Management Plan. 
4.2  This Council has approximately £122M of backlog maintenance (based on figures
produced by SCOTS) across the road network. This means that over £122M
would need to be invested to bring the road network up to an ‘A1’ standard. Most
councils are in a very similar position. During these challenging financial times, it
is very unlikely we will benefit from the level of investment required to bring the
road network up to an ‘A1’ condition. However, over the last decade there has
been a carefully applied strategy of delivering revenue and capital funding
collectively and delivering a series of works designed to minimise reactive work,
carry out right first time repairs wherever possible and to deliver surfacing
Page 104

Page 105

techniques and specifications which maximises the amount of repairs and
resurfacing which is delivered. As with almost all council services there is
insufficient funding available to treat all the sections of road that we would like to
do, the focus being on treating sections where we can maximise the financial
return and in so doing reduce the amount of reactive repairs carried out. However,
the investment levels that the Council has made over a number of years have
made a positive impact on the council’s road condition. This has been detailed in
the Road Condition Index which is included in the Annual Status and Options
report. 
4.3  As in previous years, the proposed schemes have been selected using the
Councils Roads Asset database WDM Pavement Management System (PMS)
using the information collected from the SCANNER Survey carried out in summer
months, other information mentioned above and engineering judgement. The
SCANNER surveys are carried out by a single contract for all 32 Councils in Argyll
and Bute. Unfortunately, this year a small number of councils, including Argyll and
Bute, have not received a full network survey. In Argyll and Bute, the majority of
the islands have not been surveyed and this means that previous year’s data has
been used and qualified from safety inspection intelligence. Whilst this is not ideal,
Members should note that full network surveys are not carried out on an annual
basis, the frequency of surveys is detailed below: 
100% of the A Class roads are surveyed (in one direction)  
50% of the B Class roads  
25% of the C Class roads  
10% of the Unclassified road network  
4.4 The survey data will categorise roads from red to green, with red being in worst
condition and green not requiring attention. In-line with industry best practice,
investment is not necessarily concentrated on all the red roads but instead has
been aligned to focus on a combination of red and amber roads to arrest
deterioration. This effectively provides a stitch in time approach and ensures that
we get the best rate of return from the investment available. Red roads are roads
requiring attention currently, amber roads are roads which will require attention in
the not too distant future and green roads are roads which require no attention.
By progressing schemes which will provide the best rate of return, taking
consideration of the survey results and associated data, the Council is able to
deliver a programme of schemes which maximises the benefits to the travelling
public from the available investment. There is also a consideration applied that
reflects route classification and hierarchy together with the Road Condition Index. 
4.5  Surface dressing schemes are selected on the basis that, either the skid
resistance of the road surface is poor, or the road surface requires sealing before
it fails. Surface dressing can range from a standard binder with 6mm chippings
through to polymer modified binders with more than one layer of chippings. 
4.6  Following a presentation to Members in January 2023 and reports to EDI
Committee in June 2023, officers carried out Members Business days in
October/November 2023 to enable opportunity for Members to bring forward
priorities for consideration in the 2024-25 Capital Roads Programme. 
Page 105

Page 106

4.7  As in previous years, the roads reconstruction programme will be delivered by a
mixed economy model with the Councils in-house team delivering carriageway
reconstruction and patching works. The surface dressing element of the
programme will be delivered by an external contractor. This enables the maximum
surface area to be covered which will help to seal carriageway cracks, prevent the
ingress of water and reduce the amount of reactive maintenance for potholes. 
4.8  The table below details the total of the 2024/25 allocation following the 2023
February Budget meeting. The capital budget allocation for 2024/25 has been
split in line with the pre-agreed percentage formula which is based on road area
and population. There are a number of schemes being carried forward for various
reasons including ferry availability to transport materials. These have been shown
at the bottom of the area programmes and are in addition to the £8M funding for
2024-25. 
Area  Area Total 
OLI (35%)  £2,800,000
MAKI (31%) £2,480,000 
B&C (20%) £1,600,000 
H&L (14%) £1,120.000 
Total  £8,000,000 
4.9  As can be demonstrated in the below table, over the last 10 years, where the
Council has seen average investment of at least £8 Million on Roads
Reconstruction, Road and Infrastructure Services have been able to improve
the road condition which in turn improves visitor numbers/local businesses as
well as supporting our communities daily commute. Last year for the first time
since we have been recording road conditions we were able to improve our
roads to have over 50% in the good condition category. This is purely down to
investment and the support provided by members allowing the Service to
manage the network effectively. 
Year Capital &
Revenue
Survey year RCI
2014-15  £8,896,996  2014-16  54.4 
2015-16  £6,799,499  2015-17  55.3 
2016-17  £5,821,104  2016-18  55.5 
Page 106

Page 107

2017-18  £5,233,219  2017-19  54.4 
2018-19  £11,502,343 2018-20  54.17 
2019-20 £9,472,398 2019-21 54.2
2020-21 £8,426,346 2020-22 52.5
2021-2022 £12,415,060 2021-23 49.8
2022-2023 £10,809,660 2022-24 TBC
Average Spend  £8,920,309 Average  53.99 
4.10  In 2023/24 there was also a grant from the Strategic Timber Transport Scheme
(STTS) totaling £387k. This grant was significantly less than in previous years
and officers expect this to continue in the current frugal economic climate. This
funding was used to match fund existing schemes on the council network where
timber extraction was programmed to be carried out. It is officers’ intention to
make further bids to the STTS for 2024/25 which, if successful, will provide
additional investment for the road network. 
4.11  The capital programme presented is based on carriageway condition late
autumn/early winter. With the effect of winter this programme may need to be
adjusted to ensure that any investment takes into consideration any winter
deterioration. 
4.12  The programme for each of the administrative areas will be forwarded to Area
Committee Members and updates to Area Committees as the programme
progresses. The programme will also be available on the council website with key
scheme status and dates. 
5.0  CONCLUSION 
5.1  This report provides details of the proposed roads reconstruction programme for
2024/25. 
6.0  IMPLICATIONS 
6.1  Policy - works assessed and carried out under the current Roads Asset 
Management Plan. 
6.2  Financial - programme will be based on capital allocation for year 2024/25. 
6.3  Legal – None known.
Page 107

Page 108

6.4  HR - reconstruction works delivered by a combination of in-house roads 
operations team and sub-contractors. 
6.5  Fairer Scotland Duty: None known. 
6.5.1  Equalities - protected characteristics – None known. 
6.5.2  Socio-economic Duty – None known. 
6.5.3  Islands – None known. 
6.6  Climate Change – due regard will be given to climate change with a view to 
minimising any climate change impact and these will be considered as and 
when they arise. 
6.7  Risk - completed works will reduce requirement to repair roads and will arrest 
the carriageway/footway deterioration. 
6.8  Customer Service - overall improvement in road surfaces and the quality of 
driven journeys. 
6.9 The Rights of the Child (UNCRC) – the investment to improve our road network
will contribute to a safer environment for young people to thrive in. 
Executive Director with responsibility for Roads and Infrastructure: Kirsty Flanagan 
Policy Lead for Roads and Transportation: Councillor Andrew Kain 
February 2024  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
jim.smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
hugh.oneill@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
tom.murphy@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – MAKI Proposed Roads Reconstruction Programme 2024/25
Appendix 2 – OLI Proposed Roads Reconstruction Programme 2024/25
Appendix 3 – B&C Proposed Roads Reconstruction Programme 2024/25
Appendix 4 – H&L Proposed Roads Reconstruction Programme 2024/25
Page 108

Page 109

APPENDIX 1 - MID ARGYLL, KINTYRE AND THE ISLANDS
MID ARGYLL, KINTYRE AND THE ISLANDS SHARE OF £8M Budget  2,480,000£          
2024/25 draft schemes based on the historic % split of the current £8M budget
MID ARGYLL 33%
Scheme Location, Road number/Name Works Type Estimated Cost
A819 Electric Cottage PH 4 Widening/Surfacing £200,000
U47 Crinan Loop  inc  Drainage improvements C39 Overlay £90,000
B8002  Ardfern to Craignish ( 4 sites = 1815 Lin.m) Overlay £162,000
UC01 - Brodie Cres - Lochgilphead Inlay £20,000
UC12 - Union St - Lochgilphead Inlay £99,733
C30 Ford - Kilmaha  inc Balure Spur Pre-SD 2024 £30,000
C30 Ford - Kilmaha  inc Balure Spur Laying 2024 £150,000
2025 Pre-SD U18 Drimvore - Crinan ferry - Moss area Pre-SD 2025 £66,667
District Total £818,400
KINTYRE 33%
Scheme Location, Road number/Name Works Type Estimated Cost
Meadows Ave West side Inlay £46,205
u15 Crosshill Ave @ Range Rd junction Inlay £87,164
Davaar Ave  - Albyne Ave to Calton hill Inlay £34,161
UC09 Calton Ave  - Albyne Ave to Davaar Ave Inlay £35,394
B842 Campbeltown Esplanade Inlay £130,000
B842  - Main St to New Quay St Inlay £41,127
John St- whole length Inlay £25,443
Shore St  - Main St to New Quay St Inlay £69,109
Stewart Rd  -  John St to New Quay St Inlay £36,452
C22 Gigha Ardminish Overlay £35,461
Tomaig road - Campbeltown Inlay £55,515
2024 Pre -SD  U17 Pre-SD 2024 £50,000
2024 SD  - U17 A83 - Upperballywilline Laying 2024 £105,704
2025 Pre-SD U17 Gobbagrennan & U18 Tangy Pre-SD 2025 £66,667
District Total £818,400
ISLANDS 34%
Scheme Location, Road number/Name Works Type Estimated Cost
A846 Steam Mill  to Clachan Cottage -Bowmore Overlay £240,083
A846 Bunanuisg to Cruach Rd - Bowmore Inlay £220,760
A847 Gowanlea to Seaview - Bruichladdich, including
structural repairs to Burnside
Inlay / Overlay /
Structural Repair £65,794
A847 Bruach Gorm to Sewage Works - Pt Charlotte Inlay / Overlay £213,373
B8085 Colonsay Overlay £36,525
2025 Pre-SD B8085 & B8086 / U48  Colonsay Pre-SD 2025 £66,667
District Total £843,200
2023/24 schemes re-scheduled for delivery in 2024/25
Scheme Location, Road number/Name Works Type 2023/24 allocated
budget C/F
B8001 Achmeanach farm  ( Cloanaig Slip site) Slope Stabilisation £464,000
Islay  - A846 - Corrary Hill - Island Ho  ( ferry delay) Overlay £167,134
Islay  - C12 - S of Barr to W of Cattadle ( ferry delay) Overlay £95,414
Page 109

Page 110

APPENDIX 2 - OBAN, LORN AND THE ISLES
OBAN, LORN AND THE ISLES SHARE OF £8M Budget  £2,800,000
2024/25 draft schemes based on the historic % split of the current £8M budget
OBAN & LORN 55%
Scheme Location, Road number/Name Works Type Estimated Cost
C29 - Kilmelford-Drissaig   - Lochavich Overlay £220,000
U17 McCaig Road - Oban Inlay £112,804
C32 Glencruitten Road  Overlay £63,000
U28 - Achnacloich - Connel Overlay £25,460
U32 Craig Road - Dalmally Overlay £16,973
U48 Shore Street - Oban Inlay £116,582
U58 Lower Gylen to Little Horse Shoe Bay KERRERA Overlay £84,865
U 76 Shore Road - Connel Overlay £21,824
B845 - Glen Salach Overlays £50,000
A819 - Accurrach (re-assessed  CLADDICH PH 3 North) Strategic Widening £115,000
U22 Achavaich Road Major Maintenance £55,000
U 51 Dunuran Road  - Oban Inlay £25,000
U 135 Pulpit Drive -Oban Inlay £45,000
U 45 High St - Oban inlay £45,000
U 16 Laurel Road - Oban Inlay £63,492
2024 laying operations -  North Shian - C27 Pt Appin SD 2024 £200,000
2024 laying operations -  North Shian - U42 - Inverfolla SD 2024 £160,000
U25 Musdale Road Pre-SD 2025 £60,000
U14 Scammadale Road Pre-SD 2025 £60,000
District Total £1,540,000
ISLES 45%
Scheme Location, Road number/Name Works Type Estimated Cost
B8073  Calgary area  -  Mull Overlay £124,865
B8035 Gruline North - Mull Overlay £50,000
B8035 Gruline South - Mull Overlay £50,000
B8065 Tiree Overlay £200,000
U14 Grasspoint Overlay £50,000
U16 Croggan Road Overlay £64,149
B8073 Tobermory  - Dervaig Overlay £84,865
B 8073 Balligowan Overlay £124,865
B 8073 Killichronan Overlay £84,865
B 8073 Killiemore Overlay £50,000
C 54  Loch Buie Road Overlay £64,149
C 54 Lay-by improvement works Overlay £50,000
A848  Additional Passing Places - Salen - Gulan Dubh construction £99,243
U82 Leiter Road Overlay £25,000
U80 Java Road Inlay £18,000
C46 Glen Bellart / Glen Aros Pre-SD 2025 £120,000
District Total £1,260,000
2023/24 schemes re-scheduled for delivery in 2024/25
Scheme Location, Road number/Name Works Type 2023/24 allocated
budget C/F
A816  Blaran widening Reconstruction £67,115
C 68 Breadalbane St Tobermory Widen / Wall / FW £249,304
Isle of Coll - B8027 Sorisdale Road ( ferry delays ) Overlay £247,294
Page 110

Page 111

APPENDIX 3 - BUTE AND COWAL
BUTE AND COWAL SHARE OF £8M Budget  £1,600,000
2024/25 draft schemes based on the historic % split of the current £8M budget
COWAL 70%
Scheme Location, Road number/Name Works Type Estimated Cost
C7 -  from B8000 to Tank Landing - Kames Overlay £120,000
A886 Ardachuple cutting - Colintaive Overlay £78,815
A8003  Royal brae - Tighnabruaich Inlay £26,695
A886 North of Communications Mast Overlay £60,000
A886 Dunans House Northwards Overlay £200,000
B8000 Largiemore Fish farm - Peir Ho Overlay £99,000
C57 Glenbranter Overlay £60,000
B839 / B828 Passing Place improvements construction £56,066
U22 West Glendaruel Overlay £99,000
A815 Var location below  PSD Pre-SD 2024 £40,000
A815 Coylet  - Inverchapel Laying 2024 £91,140
A815 Alexandar Parade  - marine P- Pt Riddle Laying 2024 £36,260
A815 Braemar Cottage  - Kelani  Toward Laying 2024 £73,024
U27 Millhouse  /  U19 Couston Pre-SD 2025 £80,000
District Total £1,120,000
BUTE 30%
Scheme Location, Road number/Name Works Type Estimated Cost
A844   East Princess St & Battery place Inlay £164,229
U39 /U69  Gowanfield Place to St Brides Rd Inlay £80,000
U58  Serpentine Rd - to B881 Bishop St Inlay £135,000
UC5 Glecknabae -  Lenie hall - Pipers Cave Inlay £50,771
C1 Bruchag Road 2025 Pre-SD £50,000
District Total £480,000
2023/24 schemes re-scheduled for delivery in 2024/25
Scheme Location, Road number/Name Works Type 2023/24 allocated
budget C/F
A8003 Tighnabruaich Ph 7 Reconstruction £108,817
Page 111

Page 112

APPENDIX 4 - HELENSBURGH AND LOMOND
HELENSBURGH AND LOMOND SHARE OF £8M Budget  £1,120,000
2024/25 draft schemes based on the historic % split of the current £8M budget
HELENBURGH AND LOMOND
Scheme Location, Road number/Name Works Type Estimated Cost
C 69 Glen Douglas hairpin bends to A82 Overlay £30,000
B832 Muirlands  - Cross Keys - A82 Overlay £100,000
U71 Colquhoun St - W Argyle St - W King St inlay £30,000
U262  Shore Road - Helensburgh inlay £100,000
B872  Whistlefield Road - Garelochead inlay £105,000
U62  Church Road - Rhu inlay £25,000
U101 East King - Charlotte St to Grant St inlay £35,000
U13 Ardencaple Quadrant inlay £80,000
U177 Kirk Brae - Shandon inlay £30,000
U105 East Princes St - Henry Bell St - George St inlay £150,000
A814 Whistlefield Roundabout kerb & surface £30,000
U 306 Victoria Road - Helensburgh inlay £60,000
U133 Forestry Houses - Succoth inlay £50,000
U72 Columba St - Helensburgh inlay £25,000
2024 Pre -SD A814 - sites below Pre-SD 2024 £80,000
A814 - Whistlefield to Finnart Laying 2024 £80,000
A814  - South of Glen Douglas Laying 2024 £60,000
2025 Pre-SD Pre-SD 2025 £50,000
District Total £1,120,000
2023/24 schemes re-scheduled for delivery in 2024/25
Scheme Location, Road number/Name Works Type 2023/24 allocated
budget C/F
A814 Haul Rd (A817) Middle roundabout Kerbing  and surface £37,000
Page 112

Page 113

ARGYLL AND BUTE COUNCIL              ENVIRONMENT, DEVELOPMENT
AND INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH                              21 MARCH 2024 
FILM IN ARGYLL – SCREEN INDUSTRIES UPDATE REPORT 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update of the work of the Council’s Film in Argyll service
in attracting inward investment into Argyll and Bute from the screen industries
and the economic benefits that this brings to the local economy, including the
opportunities to promote and market the area. This report covers the period
January 2023 to January 2024. 
1.2 For the period January 2023 to January 2024, Argyll and Bute Council received
90 film enquiries and there were 31 productions filmed during this period. This
has led to an estimated local production spend of £1.3M. This compares
favourably to the 2022 estimated local production spend of £580,000 and in
addition it should be noted that the quality of productions and length of time
productions have filmed in the area has significantly increased in 2023.  The
upward trend over the last 2 years is highly likely to be a direct reflection of the
continued recovery from the pandemic and the establishment of more studios in
the central belt. 
RECOMMENDATIONS 
It is recommended that the Environment, Development and Infrastructure
Committee consider the contents of this report and the continued positive
economic impact the screen industry has on Argyll and Bute. 
Page 113 Agenda Item 13

Page 114

ARGYLL AND BUTE COUNCIL              ENVIRONMENT, DEVELOPMENT
AND INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH                                21 MARCH 2024 
FILM IN ARGYLL – SCREEN INDUSTRIES UPDATE REPORT 
2.0 INTRODUCTION 
2.1 This report provides an update of the work of the Council’s Film in Argyll service
in attracting inward investment into Argyll and Bute from the screen industries
and the economic benefits that this brings to the local economy, including the
opportunities to promote and market the area. This report therefore covers the
period January 2023 to January 2024. 
2.2 Argyll and Bute continues to reap the rewards of its geographical position in
relation to the central belt and the number of film studios and productions using
Glasgow/Edinburgh as a base. This means that more productions are able to
use Argyll and Bute for location filming and for increased lengths of time which
has significant economic benefits for the area. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Environment, Development and Infrastructure
Committee consider the contents of this report and the continued positive
economic impact the screen industry has on Argyll and Bute. 
4.0 DETAIL 
4.1 Development of screen industries is a key growth sector for both UK and
Scottish Government.  Screen Scotland has the overarching role of growing
the sector in Scotland in partnership with a range of organisations, including
the enterprise agencies amongst others.  In recognition of the key role the
screen industries plays in the economy, both the UK and Scottish
Governments disburse a number of funds to grow indigenous talent and
attract productions, including providing tax incentives aimed at productions
which represent significant investment in the UK. 
4.2 This growth and the potential for growth was highlighted in a recently
Page 114

Page 115

published report, ‘The Economic Value of the Screen Sector in Scotland’
(EVSSS).  This stated that the screen sector GVA in 2021 was continuing to
grow and had increased from £567.6 million in 2019 to £627m in 2021, on
track for a potential growth to £1 billion by 2030.  The GVA figures in the
EVSSS report are made up of development and production, tv broadcast,
distribution, exhibitions and festivals, talent and skills development,
infrastructure and screen tourism.  The biggest increase within this was in
High End TV Production, supported by UK tax relief and public service
broadcasting, with production more than doubling between 2019 and 2021.   
4.3 There are now a number of studio spaces, mainly in central Scotland with
Pyramid Business Park in Bathgate being the most recent.  These studios
continue to offer the potential for more location shoots in Argyll and Bute as a
result of the accessibility of Argyll and Bute to the central belt.  More recently
however both the writers and the actors strike have impacted on screen
production and have delayed production. 
4.4 The key economic benefits of the screen industries for Argyll and Bute include
income from hire of locations and ancillary services such as accommodation
providers, caters etc.  Economic impact also includes: indigenous production
companies and freelancers; cinemas in the area (there are more independent
cinemas in Argyll and Bute than anywhere else in Scotland); film festivals of
which there are currently two, Dunoon Film Festival and Sea Change on Tiree;
film tourism and the publicity and subsequent visits to the area as a result of
productions which feature Argyll and Bute. 
4.5 To assist in growing the sector and the associated benefits, Argyll and Bute
Council Transformation, Projects and Regeneration officers work with Screen
Scotland. Screen Scotland facilitates a Screen Locations Network made up of
mostly local authority film officers, who work to an agreed protocol. This
protocol is based on providing information on locations, crew etc. and
facilitating productions in the area as well as promotion of locations. Screen
Scotland Locations (SSL) work closely with The British Film Commission
(BFC) and British Film Industry to promote production in the UK.  International
enquiries are fed into CSL, who in turn pass this on to local film offices. All the
above frameworks, recent developments and funding could directly benefit
Argyll and Bute through increased production and inward investment within
our area. 
4.6 Core to the Council’s Film in Argyll service is providing confidential advice and
support as a “one stop shop” to the industry through a single point of contact
(www.filminargyll.co.uk). The “one stop shop” supports the production’s needs
in many ways including, liaising with other council departments (for road
closures, access to land/property including car parks etc.), providing locations
to film enquiries, landownership queries, local knowledge and connecting
productions to local services such as Gaelic speakers and community groups. 
4.7 Delivering this screen industries development meets with our Outcome
Improvement Plan objective of ‘Our Economy is Diverse and Thriving, our
Economic Strategy objective under the “Place and People” outcome “Creating
Page 115

Page 116

a vibrant, cultural experience and strong creative industry”.  In response to the
pandemic, Argyll and Bute’s Economic Recovery Plan published in August
2020 also highlights council action to “Continue to support cultural activity
including film and TV locational work” under the key Scottish Government
theme, Place and People.  It is also an excellent opportunity to showcase
Argyll and Bute to a national and, in some cases, international audience. 
4.8 The screen industries continues to have the potential to not only bring production
spend to the local economy but to be a catalyst for the growth of the tourism
industry in Argyll and Bute. Liaising with Visit Scotland, Film in Argyll has
supported film tourism by supporting the “Set in Scotland” guide which provides
an overview of film locations throughout Scotland and highlights many high
profile productions that have filmed in the area over the years. As part of Argyll
and Bute’s economic recovery process from the coronavirus pandemic, the
Development and Economic Growth Service will continue to work across Council
services and with key partners to promote filming in Argyll and Bute.   
4.9 For the period January 2023 to January 2024, Argyll and Bute Council received
90 film enquiries and there were 31 productions filmed during this period. This
has led to an estimated local production spend of £1.3M. Compared to the 2022
estimated local production spend of £580,000, the upwards trend over the last 3
years are a direct reflection of the continued recovery from the pandemic. It
should be noted that the quality of productions and the length of time
productions have filmed in the area has significantly increased in 2023 however
industry figures do vary year on year and can change dramatically due to the
fact that one large budget production can significantly increase figures in one
year. 
4.10 The type of enquiries and productions coming into Argyll and Bute has
changed compared to pre pandemic years, whereby Film in Argyll is seeing a
decrease in unscripted TV small scale productions, and an increase in larger
productions with a cast and crew of 30+ with a higher budget and filming for
longer periods of time. There could be various factors responsible this change,
but it is highly likely that the work and opportunities that are being created at a
Scottish level around creating more studio space in the central belt, is having
a positive economic impact on surrounding areas. Film in Argyll continues to
work closely with our key partners in Screen Scotland and the Scottish
Location Network to champion Scotland as a top location for filming. 
4.11  Within the period January 2023 to January 2024 examples of productions
include:                
• Argyll and Bute featured as a key location in the new Channel 4
– GP’s in the Wild series. The documentary aims to explore the
unique challenges, opportunities and case types/medical needs,
experienced by GPs in remote communities. Filming took place
in May 2023 across a number of weeks.
• Float Season 2, a six part BBC Drama series filmed in the former
Helensburgh Swimming Pool returned to film the demolition of
Page 116

Page 117

the building as part of the series and surrounding areas in
Helensburgh. Filming took place in June 2023.
• Sacred Islands with Ben Fogle, an eight part series where Ben
travels across Scotland’s remotest islands, Filming took place in
the summer last year and included islands such as Iona, Islay
and Jura. 
▪ Harvest, the 2013 Booker Prize adaptation drama filmed in
August 2023 until the start of October 2023 in Oban and
surrounding areas. This production filmed in the Argyll and Bute
area for a significant period of time and included a full set build
on location.
▪ Post Malone "Mourning" Music Video, was filmed in the Loch
Lomond area in May 2023. 
• The Isle of Bute featured as a key location for The Hairy Bikers
(Go West), where the best local restaurants with the most
innovative local suppliers where highlighted. Filming took place
in June 2023.
• Bollywood Feature, a large scale Bollywood feature filmed in the 
Arrochar area in December 2023. 
5.0 CONCLUSION
5.1 The screen industries continues to have the potential to not only bring production
spend to the local economy but to be a catalyst for the growth of the tourism
industry in Argyll and Bute. As part of Argyll and Bute’s economic recovery
process from the pandemic, the Film in Argyll service will continue to work
across Council services and with key partners such as Screen Scotland and the
Scottish Locations Network to take advantage of the newly developed film
studios and ensure the sector continues to grow in Argyll and Bute. 
6.0 IMPLICATIONS
6.1 Policy – Supports Outcome Improvement Plan, Economic Strategy and
Economic Recovery Plan under Place and People theme.
6.2 Financial – Provides income for Development and Economic Growth. Film in
Argyll service covered by core staff.
6.3  Legal – Film Location Agreements put in place when filming takes place on
Council owned land or asset.
6.4  HR – None.  
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – None.   
6.5.2   Socio-economic Duty – None.  
Page 117

Page 118

6.5.3  Islands – None.  
6.6 Climate Change – None.   
6.7 Risk – None.  
6.8  Customer Service - If we do not continue to respond to enquiries timeously and
develop Film in Argyll we could lose productions to other areas in Scotland and
beyond.
6.9  Rights of the Child (UNCRC) – None.   
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth
Policy Lead for Islands and Business Development – Councillor Liz McCabe
5th February 2024                                                  
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
fergus.murray@argyll-bute.gov.uk 
Arlene Cullum, Transformation, Projects and Regeneration Team
arlene.cullum@argyll-bute.gov.uk 
Page 118

Page 119

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21 MARCH 2024 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
1. EXECUTIVE SUMMARY
1.1 The purpose of this report is to update the Environment, Development and
Infrastructure Committee on progress of the large-scale, externally funded
project work of the Transformational Projects and Regeneration Team, and to
highlight key issues that may impact on the successful delivery of projects. 
1.2 The last update report was considered by Environment, Development and
Infrastructure Committee in August 2023. 
1.3 The team is currently responsible for the delivery and or management of projects
and or associated grants with a cumulative value of over £45m. Projects the team
delivers and or associated grants the team manages are listed in Appendix A.
It should be noted that following completion of each project the team continues
to have the responsibility for the monitoring and final drawdown and reporting up
until the end of the 12-month defects period or beyond depending on conditions
on the respective grant contracts. 
RECOMMENDATIONS
It is recommended that the Environment, Development and Infrastructure
Committee consider and note the current progress contained within the report. 
Page 119 Agenda Item 14

Page 120

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21 MARCH 2024 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
2. INTRODUCTION
2.1 This report sets out the current position of the large-scale projects, which are
currently being delivered by the team and or where Council and externally
secured grants are being managed by the Transformational Projects and
Regeneration Team. 
2.2 The Transformational Projects and Regeneration Team sits within the Council’s
Development and Economic Growth Service and works region-wide. The team
has a particular focus on ‘place’, heritage regeneration, the creative industries,
renewables and Islands and works closely with colleagues across the Council,
communities, third sector organisations, town centre heritage building owners
and businesses to realise positive change. 
2.3 The team’s work broadly includes the following areas:- 
• Developing and submitting bids to secure external funding of various scale
through a competitive process, such as the new Heritage and Place
Programme previously referred to as the Conservation Area Regeneration
Scheme (CARS) programmes;
• Development and delivery of regeneration projects with a particular
emphasis or theme, such as the suite of measures to encourage shopping
locally;
• Development and delivery of several place-based engagement projects,
working in partnership with the community and key partners, leading to
action plans, such as charrettes, and working with communities to realise
these community ambitions; 
• Development of the economic opportunities for Argyll and Bute across
Film, Creative Industry and Renewable sectors, with the objective of
securing income into the area and delivering local economic benefit,
including support to community organisations working across these
sectors. This work also includes the setting up and management of the
Argyll and Bute Renewable Alliance (ABRA) with partners in HIE; 
• Support to third sector organisations involved in the delivery of their own
individual community led economic regeneration projects, as well as
support to third sector organisations delivering regeneration focused
projects where Council funding is involved and/or where projects align
with Council outcomes, such as Regeneration Capital Grant Funded
Page 120

Page 121

(RCGF) project funding;
• Drafting and submitting external funding bids to competitive call such as
Regeneration Capital Grant Funded (RCGF) annually. A total of 17
projects have been supported and over £10 million secured through
RCGF; 
• Development and Administration of the Council’s, Strategic Events and
Festivals Grants for which 21 grants were awarded under SEF Rounds 5
and 5.2 (2023/24);
• Overseeing the delivery programme and financial administration of
projects supported through funding from Scottish Government, such as
Place Based Investment Fund (PBI) as well as annual Crown Estate
funding;
• Working closely with the SG Islands team and working with colleagues
and communities in the development of bids to the Islands Programme
(IP) as well as the monitoring and reporting on IP grants that are secured. 
2.4 This paper also seeks to report on key issues that may impact on the current
status of each project, such as any amendments to project scope or timeframe. 
2.5 The large-scale projects currently in delivery, either directly by the team, colleagues
across the Council or by a third party and where the team is responsible for
managing the associated grant, are included within the table in Appendix A, and
have a cumulative total value of over £45m. The individual projects being taken
forward under the PBI and CE are not listed individually in Appendix A. 
3. RECOMMENDATIONS
3.1  It is recommended that the Environment, Development and Infrastructure
Committee consider and note the current progress contained within the report. 
4. DETAILS
4.1 The following sections summarise the progress associated with each of the large-
scale projects that are currently in delivery and are either directly delivered by the
team or there is a grant to the project managed by the Transformational Projects
and Regeneration Team. In addition, the report provides information on annual
funding streams received by the Council (PBI and CE) and managed by the team
as well as annual competitive external funding grants secured and being managed.
The individual projects are listed in Appendix A with the exception of those
individual projects supported through PBI and CE. 
HERITAGE LED REGENERATION PROJECTS 
4.2 The Council is currently responsible for the delivery of four heritage-led area based
regeneration schemes. These are referred to as Conservation Area Regeneration
Schemes (CARS) and each is delivered over a 5 year period. The schemes
currently in progress are based in Rothesay, Helensburgh and Lochgilphead and
Page 121

Page 122

Dunoon. Dunoon CARS formally finished in July 23 and we are currently in the
process of evaluation and closing the scheme down. The CARS schemes have all
been secured via a competitive process and the total value of the four schemes
represents in excess of £10m of investment into the built heritage of these towns
and is largely comprised of funding from Historic Environment Scotland (HES) with
match funding from the Council and private owners. The Rothesay scheme also
has funding from National Lottery Heritage Fund (NLHF) and for that reason is
referred to as a Townscape Heritage (TH) scheme as well as a CARS. 
4.3 It is worth noting that since 2007 the Council has successfully secured, through a
competitive process, eight rounds of CARS funding, equating to £6.6m of CARS
funding, and which totals £27m of investment made into 6 key Argyll and Bute
town centres, The CARS schemes operate as grant administration programmes
which is administered by the Council. This programme offers grants to property
owners to help them repair and safeguard their historic buildings. Many building
owners have, and continue to benefit from the funding, which has delivered a
significant level of investment into the area since 2007. 
4.4 Due to the cost of repairing traditional buildings, many of these owners would have
been unable to undertake the level of repairs required without grant assistance and
their properties would have continued to deteriorate. Had deterioration continued,
the Council may well have had to step in to undertake emergency work to these
buildings. CARS grants have also helped to safeguard existing businesses, and
new businesses have opened because of the regeneration, helping to create jobs
within the community. 
4.5 Such investment has and continues to change the physical appearance of our key
town centres for the better, making them more attractive places in which to live,
learn, work, invest and do business. Details of the current CARS projects are
provided below. 
4.6 Rothesay Townscape Heritage Phase 2 (2017 – March 2024) Project Status -
GREEN 
Rothesay TH is a £2.75m project is in the final few months of the scheme and is
due to complete 31 March 2024. The partnership project is funded by NLHF
(£1,888,500), HES (£500k), Argyll and Bute Council (£200k), HIE (£70,249),
LEADER (£65,800) and Sustrans (£21,500). Project staff are fully funded for the
project duration. 
The project has been given a final extension to 31st March 2024, to allow for the
completion of priority building and shopfront restoration which have experienced
delays. Of the 5 priority building repair projects, 4 are complete, 1 is due to
complete by mid February 2024. 4 shopfront restorations have been completed,
with the final shopfront due due to complete by mid February 2024. A series of
window repair grants have also been provided for the restoration of traditional
timber sash and case windows. 
The project seeks to facilitate traditional skills development and host events that
celebrate the island’s heritage. To date a maintenance awareness raising event,
Page 122

Page 123

community engagement event and 14 workshops have been held. In addition, a
substantial amount of audience development analysis has been undertaken,
resulting in recommendations to support the visitor market and enhance the end-
to-end visitor experience. The potential for a WASPS style studio has been
analysed, Rothesay Castle has been lit up in animation, and the pilot pop-up
shop in the former Clydesdale Bank has successfully continued beyond the
scope of the TH funding. 
4.7 Dunoon CARS (2017 – July 2023) Project Status - GREEN 
Dunoon CARS, a £2m project is now complete. A fully funded project officer was
employed to deliver the project for its duration. 
The envelope restoration of 4 priority buildings and 32 shopfronts have been
completed. 
Working in partnership with Dunoon Community Development Trust, CHARTS,
Dunoon Grammar School and Tacit Tacit, a complementary scheme of skills
development was successfully delivered with courses and workshops in
stonemasonry, woodworking, painting and lime mortar. An additional grant from
the Castle Knowledge Trust in 2023, allowed for archaeological geophysical
surveys to be undertaken on the Scheduled Monument Castle site in Dunoon. 
The Dunoon CARS evaluation report is currently being prepared by consultants
to evaluate the impact of the CARS funding in Dunoon and a final audit is being
undertaking prior to the project being formally closed down. 
4.8 Helensburgh CARS (2021 – March 2026) Project Status - GREEN 
Helensburgh CARS is a £2.4 million pound project in the third year of delivery.
The partnership project is funded by Argyll and Bute Council (£500k) and HES
(£1.24m) with owner's personal contributions completing the funding.  A fully
funded project officer is employed to deliver the project for its duration. 
Two priority buildings have contracted with the Conservation Architect and a
tender document is currently being prepared with an expectation of return by Mid
February 2024.  The third priority building has decided not to proceed.   A fourth
priority building has been sourced and a survey has been commissioned via the
Conservation accredited Architect. 
One shop front grant has been completed (November 2023) with owners
reporting an increase in footfall. Planning permission has been granted for a
second shop front. 
Two lime mortar courses are being procured and these are programmed for May
and September 2024.  An apprenticeship training programme for a young person
is being investigated. 
4.9 Lochgilphead CARS (2020 – Mar 2026) Project Status – GREEN 
Page 123

Page 124

Lochgilphead CARS is a £2m partnership project with HES (£969,700) in its
fourth year of delivery.  The project is due to end in March 2026. 
The first two priority building projects are almost complete.  All grant funding has
been approved for the remaining two priority buildings and work is due to start in
March 2024. 
A high-level repair project at Poltalloch Street has been completed and other
small repair grant cases are being progressed. 
Three shopfront reinstatement projects are being developed for delivery in 2024. 
Local stakeholders are benefiting from several traditional skills training courses
and educational activities, delivered via the scheme.  The latest event was a
Maintenance and Retrofit event for tenement owners, delivered in partnership
with Under One Roof. 
4.10 Hermitage Park, Parks for People (2016 – June 23) Project Status - ORANGE     
Whilst the project delivery itself is complete this project awaits a decision on the
outcome of the potential location of the skate park in Helensburgh in order to
complete the final financial draw down of £100,578. National Lottery Heritage
Fund, the main funder of this £3.7million project, have confirmed that locating the
skate park in Hermitage Park may breach the purposes of the £2.3m grant and
is therefore a risk to the project.  For reference, the final project evaluation
highlights were in the November 2023 EDI Committee and the Park Manager
post ended in June 2023. 
4.11 Tarbert Heritage Regeneration Scheme (TBC) Project status - GREEN 
A new funding stream has been launched called Heritage and Place Programme
(HPP). HPP is a competitive fund run by HES and supersedes the Conservation
Area Regeneration Scheme (CARS) funding, which HES made available over
eight rounds between 2007 and 2019. Policy and Resource Committee agreed
on 16 June 2022 to support the submission of an Expressions of Interests
application to HES to the first call of the Heritage and Place Programme, and
National Heritage Lottery Fund of the Grants for Heritage Programme to support
the Tarbert Heritage Regeneration Scheme. 
Expressions of Interest to both funds were successful, with invitations made to
apply for an initial Development Phase. A development application to Historic
Environment Scotland was submitted on 17 November 2022 seeking £40,000,
and to the National Heritage Lottery Fund on 15 December 2022, also seeking
£40,000. The Council has sought £80,000 from both funding programmes, with
£60,000 of Council match funding to support a Development Phase at the total
cost of £140,000. The outcome of both applications were successful and
following approval from Full Council on 29 June 23 a project officer was recruited
and the development phase is now progressing in close liaison with the funders
and the community. Due to delays in the appointment of consultants to undertake
Page 124

Page 125

the necessary works required as part of the grant contract it is now anticipated
that this will be an 18 month development phase. A report will be brought back
to Council prior to any delivery phased bid being submitted. 
WIDER REGENERATION FOCUSED PROJECTS 
4.12 Tarbert / Lochgilphead Regeneration Fund Project Status – GREEN 
In its 2016/17 budget, Council allocated £3m from reserves to support
regeneration and economic development in the settlements of Tarbert,
Lochgilphead and Ardrishaig. 6 projects were identified to proceed to Full
Business Case (as ratified by Policy and Resources Committee on 19th October
2017).  The following projects are complete: 
• Gleaner (Phase 1 only) - completed summer 2019.
• Tarbert Harbour – shore side facilities completed in May 2019, car park
completed in March 2021.
• Barmore/Garvel Road junction improvements - completed February
2020.
• Colchester Square/Argyll Street, Lochgilphead – completed May 2021.
• Lochgilphead Front Green – completed August 2022.
• Ardrishaig North Public Realm – completed April 2023. 
The only remaining allocation of funding is in relation to the remaining part of the
former Gleaner Oil site in Ardrishaig. Both Scottish Canals and Argyll and Bute
Council are in discussions with a potential occupier of the site. No details have
been confirmed to date but we are hoping that this can progress during 2024/25. 
4.13 Regeneration Capital Grant Funding (RCGF) Project Status – GREEN 
Over the past seven years, a total of £10.72m RCGF funding has been secured
from Scottish Government to support 17 projects across the area. Although
RCGF can support community projects, the Fund is only open to local authorities,
and as all 32 local authorities are eligible to apply, this makes for a highly
competitive process. The team has responsibility for applying to RCGF each year
through a competitive process and when successful then managing the
respective grant awards and reporting back to Scottish Government as well as
supporting any third party receiving the funding. 
An update on the current ongoing RCGF projects is provided below and is
followed by a table of all current grant contract awards (Table 1) 
• Kilmartin Museum Redevelopment – following a number of delays the
museum reopened in September 2023 following the completion of the
construction and fit out works. We are continuing to work with Kilmartin
Museum as they work through the final stage of the formal close down
of the redevelopment project.
• Port Ellen Community Hub, Islay – a contractor was appointed for the
project in March 2023 and works are progressing. It is expected that they
will be ongoing until at least May 2024.
Page 125

Page 126

• Scalasaig business units, Colonsay - A contractor is in place and
construction is underway.  Project end date has now been delayed until
mid March 2024
• Kilmory Business Park, Lochgilphead – work is progressing with M&K
MacLeod on the proposed Kilmory Business Park.  Tender process is
underway with contract award expected late January 2024.
• Obair Ùr Thirodh Tiree Community Business Hub – a contractor was
appointed for the project in March 2023 and works are ongoing.  It is
expected that they will be ongoing until February 2024.  
• Kerrera Old School - Community Hub Final Phase – Works commenced
early in 2023 and are expected to complete late January 2024.
• Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha – A contract
was awarded early in 2023 and construction works are progressing,
works are expected to complete in July 2024.
• Aros Waterfront Development, Mull – outdoor activity hub – a contract
was awarded in January 2024 and works are commencing.
• Nonhebel Light Industrial Park Expansion, Mull – construction works
have commenced.  Project completion expected in March 2024. 
Table 1 
RCGF Project Grant
Awarded
Year
Awarded
Balance
Remaining /
Yet to Drawdown
Kilmartin Museum  £275,000 2019/20 £0
MACPool  £400,000 2020/21 £0
Port Ellen Community hub, Islay  £1,046,223 2021/22 £608,444
Scalasaig business units, Colonsay  £335,000 2021/22 £689
Kilmory Business Park in
Lochgilphead 
£829,000 2021/22 £829,000
Obair Ùr Thirodh – Tiree Community
Business Hub
£565,000 2022/23 £86,175
Kerrera Old School - Community
Hub Final Phase  
£285,000 2022/23 £0
Ulva Ferry Shore Facilities Building -
Doras Caolas Ulbha
£602,590 2022/23 £33,957
Aros Waterfront outdoor activity hub £403,500 2023/24 £403,500
Nonhebel Light Industrial Park
Expansion
£654,000 2023/24 £296,886       
The following stage 2 applications were submitted to the RCGF Round 11
2024/25:
• Fyne Futures Local Food Production and Training Centre, Bute 
• Isle of Luing Community Owned Slate Quarry 
The Council has been advised that there has been a delay in any decision being
made on RCGF Round 11 due to budgetary considerations. 
Page 126

Page 127

4.14 Scottish Government Place Based Investment Funded projects 2021 – 2024 
Town Centre Funding has been superseded by Place Based Investment (PBI)
funding, which the Scottish Government has committed to allocating on an
annual basis over a five-year period. Argyll and Bute’s allocation for 2021/22 was
£821,000 and for 2022/23 the allocation was £712,000. The allocation for
2023/24 has been confirmed as £496,000 and a report went forward to August
Policy and Resources Committee seeking member’s approval to support a total
of 8 projects. No confirmation has been received of any award for 24/25. 
At their respective meetings of 24th June 2021, 12th August 2021, and 2nd
September 2021, Argyll and Bute Council, the Policy and Resources Committee
and Environment, Development and Infrastructure Committee agreed to use PBI
towards 8 projects that support a living well locally concept, have climate friendly
ambitions, and which have stemmed from the community through design-led
consultation activity or through needs identified by key partner organisations. 
Of the 8 projects approved for 2021/22, 7 have been fully completed and 1 is due
for completion in 2024. 
As stated above the Councils PBI allocation for financial year 2022/23 from
Scottish Government was £712,000. Of the projects approved in 2022/23, 3 are
fully complete and 3 are due for completion in 2024. 
At the meeting of the Policy and Resources Committee on 10 August 2023,
members agree to allocate £496,000 of the PBI funding to 8 projects listed below: 
• Dunoon Burgh Hall Trust – Phase 2 to enhance outdoor area -
£74,5000
• Dunoon CARS/LACER approach – flexible fund to support businesses
with capital improvements to shopfronts/buildings - £49,500
• Helensburgh CARS Shopfronts - £44,000
• Helensburgh Skatepark - £80,000
• Tobermory Worker Accommodation – £50,000
• Bid4Oban – Shopfronts and Oban Signage - £60,000
• Lochgilphead CARS Shopfronts and high-level amenity project –
£100,000 
• Steel Beam Project/LACER Shopfronts in Campbeltown - £38,000
All the projects above are progressed to the point that the funding is secured. 
4.15 Scottish Crown Estate Revenue Allocation Funding 21/22, 22/23 & 23/24 
In financial years 21/22 & 22/23 the Council has received a total of £3,122,803
and this funding has been allocated to a total of 22 projects which involve a
mixture of Council and third-party projects. The Councils allocation for this
financial year (2023/24) is £1,590,409. The formal notification of the allocation
was not received until 30 November 2023. In advance of confirmation of the
Page 127

Page 128

2023/24 allocation a total of 7 projects were agreed through the delegated
process amounting to the full £1million prudent estimate. A report will be
considered at Policy and Resources Committee on 15 Feb recommending the
allocation of the remaining funding of £590,409 to a number of additional
projects.  Because of the sheer number of CE projects involved the full list of
projects are not included in this report however the total is included in Appendix
A. All projects are being monitored. 
4.16 Scottish Government Islands Programme Funded projects 2021/22, 22/23
& 23/24 
The Scottish Government wrote to Councils on 17 December 2021 advising of
the distribution of the 2021-22 Islands Infrastructure Fund (IIF). Argyll and Bute
Council’s share of the funding was £740,000. The fund was for capital works and
required to be committed via a grant contract or contract award by 31 March
2022. At the Policy and Resources Committee meeting on 17 Feb 2022 members
agreed to allocate the IIF to 11 projects, 9 of which were third party projects. Of
the 11 projects, 7 are now fully complete and 4 are due for completion in 2024. 
In regard to the £4million Island programme for 2022/23 the Scottish Government
(SG) decided to introduce a competitive bidding process for all 6 island
authorities as opposed to a direct allocation. The Council was successful in
securing funding for the following 2 projects: 
1. Island Community Halls Digital Hubs – Islay, Iona, Tiree and Coll - £100,000.
-  All equipment installed.  All community engagement visits to the islands are
expected to be completed by March 2024. 
2. Tobermory Seawall and Railings project - £250,000. - In progress, due for
completion April 2024.          
The Council submitted a total of 2 bids to the IP 2023/24 and successfully     
secured funding for both projects: 
1. Infrastructure for Worker Accommodation, Tobermory, as part of the Rural
Growth Deal - £700,000. Planning permission has been secured and road
construction consent is in progress. A procurement exercise is also live at
the time of writing. Subject to successful completion of these activities, it is
anticipated that works on site will commence during summer 2024.
2. Tiree Community Care Hub, HSCP, - £450,000.  Works have commenced. 
Confirmation is still awaited in respect of any Islands Programme funding round for
2024/25. 
4.17 Scotland Loves Local Projects Oct 21 - 2024 
Argyll and Bute Gift Card - The gift card for Argyll and Bute formally launched in
October 2021. To date, over 325 Argyll and Bute businesses have registered to
accept the card as a means of payment for goods and services. At the full Council
meeting of 28th April 2022, members agreed to commit a share of the Local
Page 128

Page 129

Authority COVID Economic Recovery (LACER) Fund to the Gift Card. The
approved options were:-
• Issue Scotland Loves Local Gift Card to households in receipt of
Council Tax Reduction Scheme - £797,720;
• Fully fund Gift Card for 2022/2023 into 2023/2024 - £30,000;
• Marketing budget to promote the Gift Card. 
The roll out of the LACER funded Scotland Loves Local Gift Card began in
December 2022 and was sent out to 6,800 eligible households in Argyll and Bute.
In addition to this, the Council issued a further issued 1,244 cards worth just
under £150,000 in total to eligible islands households to help low-income
households with the ongoing cost of living. In November 2023, 1,200 cards were
given to households in receipt of council tax reduction on the islands to the value
of £85. 
The contract was awarded to Miconex to continue the facilitation of the Argyll and
Bute Card in 2022/2023 and 2023/24 which will enable the Shop Local campaign
to gain momentum and support local businesses over the next two years. 
The marketing budget has funded the creation of 6 promotional films, to promote
business registration, help awareness of the card and showcase local areas.
Local businesses across Argyll and Bute were invited to become Business
Ambassadors for the card, with promotional films rolled out from November 2022
into December 2022 to coincide with the festive season and roll out of the LACER
funded cards. The promotional films were successfully shared across social
media platforms and can be viewed on the Council’s YouTube page:
ArgyllandButeCouncil - YouTube. In April 2023, the Council provided 16 of our
local Business Ambassadors with a £50 Argyll and Bute Gift Card to run a
competition on their social media channels. The social media posts from our
Business Ambassadors garnered a total of 1,553 likes, 1,303 shares and 1,309
comments helping to spread further awareness of the card. In October 2023, the
Council ran a photography competition for the design of the new Argyll and Bute
Gift Card. The winning entry won a £50 Gift Card and the new design will be
featured on the cards in April 2024. 
In July 2023, the Council piloted its first sales point for the Argyll and Bute Gift
Card at Keeping it Local, Campbeltown. In December 2023, the second sales
point for the Gift Card was established in the Lochgilphead Post Office (also know
as the Bank Store), Lochgilphead. Cards can be purchased in-store from  £5 and
spent within over the 325 businesses across the area. 
The Argyll and Bute Gift Card can be purchased online as follows: Argyll & Bute
Gift Card | Scotland Loves Local Gift Cards (scotlandgiftslocal.com) 
Inclusive of the LACER funded cards, as of 17 January 2024, a total of 8,932
cards have been purchased to the value of £957,225. 
Page 129

Page 130

4.18 Budget 
The above project and grant updates are predominantly in relation to the
externally funded projects for which the team are responsible for firstly securing
and then delivering as per external grant requirements and or overseeing the
specific budget claiming and monitoring process where these relate to Council
as well as third party project. A number of these projects include a proportion of
Council funding as well as sources such as PBI, IP, RCGF or CE funding. There
is a set budget for each project, and each is subject to specific outcomes and
timelines, as agreed with respective funders. In most instances the externally
funded elements of the project costs can only be claimed once proof of all
necessary information has been provided to the respective funder. Each funder
has a different criteria against which delivery is measured, and the Council has
entered into formal grant contracts with all funders involved. 
5. CONCLUSION
5.1 Place based investments are taking place across much of Argyll and Bute
making significant improvements to the quality of life of local people and our
communities. Much of the work is externally funded adding to the capital funding
committed by the Council to enable this investment to happen. The successful
delivery of the projects requires careful monitoring and close working with
colleagues, partners and community stakeholders. There continues to be an
impact from Covid-19 pandemic, the impact from the UK having left the EU and
the current cost of living crisis all of which set a background that often creates
a challenging environment in which to work and to deliver capital projects.
Prices are still high, due mainly to supply chain issues, but also shortages in
labour and rising electricity and wider cost of living costs. The team therefore
adopts a pragmatic approach to delivering projects, ensuring that these are as
meaningful as possible using the budget available however the environment in
respect of project delivery is a very challenging one. The team continues to
support third sector organisation wherever possible to ensure the successful
delivery of community projects where Council funding has been committed or
the Council has secured external funding on behalf of these organisations
through competitive funding streams such as RCGF. 
5.2 The projects and grants detailed within this report will result in assisting the
economic recovery of Argyll and Bute, helping to sustain numerous small
businesses, community organisations, making our places more investor ready,
improving our towns and villages as places to live, work and visit together with
adding to the significant regeneration works that are being taken forward across
Argyll and Bute, and seek to make an improved and lasting difference to the area. 
6. IMPLICATIONS
6.1  Policy - The delivery of these projects fits with the Council’s Corporate Plan,
Argyll and Bute Local Outcome Improvement Plan and the Economic
Page 130

Page 131

Development Action Plan. The economic outcomes from this project will
contribute to the Government’s Economic Strategy. 
6.2  Financial - All funding has been approved for the projects detailed in the report.
The funding comes from the Council and from external funding sources some
from highly competitive processes.  We will continue to review costs and assess
budgets. 
6.3  Legal  Each project will have differing legal and procurement requirements
depending on the grant funder and the associated grant contract conditions and
we are working closely with colleagues to identify the support required and to
allow this to be factored into future work plans. 
6.4  HR - The resources required to deliver the projects will be continually
monitored. The management of these externally funded projects as well as the
management of the Council, PBI, CE and IP and RCGF grants requires a
significant amount of resources from the team to ensure that all the necessary
due diligence and financial management is undertaken and the risk is
minimised to the Council. 
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – None.
6.5.2   Socio-economic Duty – None.
6.5.3 Islands – None. 
6.6  Climate Change - It is an ambition of our project work to work towards net zero
by adopting a carbon conscious approach throughout.   
6.7  Risk - Construction projects by their very nature are challenging given issues
that can arise relating to site conditions, managing contractors/the design team
and associated budgets and meeting funder’s requirements. The effects of
Covid-19 and the current cost of living crisis has added even more challenges
both in regard to the development/delivery phases of projects. We continually
seek to minimise the risk through strong project management processes,
however until the projects are fully delivered on site there remains a risk. Other
areas of risk relate to the potential for limited uptake in regard to CARS/TH
grants and also over-run on costs for third party projects. In regard to the latter
this is a high risk particularly as the Council is not the responsible body for the
projects or their delivery on the ground. The setting up of regular benefits
realisation group meetings and building good working relationships with the
third parties assists in identifying where issues may arise and where additional
support may be required. Covid-19 and the resulting impact on the construction
industry and costs is an additional risk to the delivery of these projects and we
are reviewing all costs and working with funders to minimise the impact and
manage the risk as much as we can. 
6.8  Customer Service – None. 
6.9  Rights of the Child (UNCRC) – None.  
Page 131

Page 132

Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Policy Lead for Strategic Development: Councillor Robin Currie 
Policy Lead for Economic Growth, Communities and Corproate Services:
Councillor Alastair Redman 
February 2024 
For further information - please contact: 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Audrey Martin, Transformation Projects and Regeneration Manager
Audrey.Martin@argyll-bute.gov.uk 
Appendices: 
Appendix A – List of Council and Third Party projects that the team is either
responsible for delivering directly or for managing the grants given by the Council to a
third party organisation.
Page 132

Page 133

APPENDIX A - LIST OF COUNCIL AND THIRD PARTY PROJECTS 
Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Dunoon CARS  £1,949,965 £500,000 £1,002,348 2017 2023
Rothesay TH2 £3,244,856 £200,000 £2,508,781 2017 2024
Tarbert Lochgilphead Regeneration Fund (Includes TCF Grant) £6,666,112 £3,140,000 £2,473,534 2018 Ongoing
Hermitage Park (Includes TCF and PBI Grant) £3,932,314 £553,317 £3,378,817 2016 2023
Kilmartin Museum RCGF & Council Grant  £7,663,403 £400,000 £275,000 2019 2023/24
Port Ellen Community hub, Islay RCGF grant  £1,570,259 £0 £1,096,223 2021/22 2024
Scalasaig business units, Colonsay RCGF grant  £480,481 £0 £335,000 2021/22 2024
Kilmory Business Park in Lochgilphead RCGF grant  £1,980,000 TBC £979,000 2021/22 2024
Lochgilphead CARS (Includes 22/23 PBI Grant) £2,200,782 £750,551 £1,269,731 2020 2026
Helensburgh CARS £2,400,000 £500,000 £1,240,000 2021 2026
Events and Festivals grants (including annual Mod) £165,150 £165,150 - 2023/24 2023/24
Place Based Investment 21/22* £260,000 £0 £260,000 2021/22 2022/23
Place Based Investment 22/23** £259,000 £0 £259,000 2022/23 2022/23
Placed Based Investment 23/24 £496,000 £0 £496,000 2023/24 2023/24
Placed Based Investment 24/25 £496,000 £0 £496,000 2024/25 2024/25
Crown Estate Funding 21/22 £1,634,604 £0 £0 21/22 Ongoing
Crown Estate Funding 22/23 £1,488,199 £0 £0 22/23 Ongoing
Crown Estate Funding 23/24 £1,590,409 £0 £0 23/24 Ongoing
Obair Ùr Thirodh – Tiree Community Business Hub - RCGF Grant £1,190,000 £0 £605,000 2022 2024
Kerrera Old School - Community Hub Final Phase - RCGF Grant £548,424 £0 £285,000 2022 2024
Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha - RCGF Grant £652,590 £0 £602,590 2022 2024
Islands Infrastructure Fund 21/22 £201,419 £0 £201,419 2021/22 2023/24
Page 133

Page 134

Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Scotland Loves Local £46,000 £0 £46,000 2022/23 2024/25
LACER Fund £40,000 £0 £40,000 2022/23 2023/24
Islands Programme 22/23 - Island Community Halls Digital Hubs £100,000 £0 £100,000 2022/23 2023/24
Islands Programme 22/23 - Tobermory Seawall and Railings £450,000 £0 £450,000   2022/23 2023/24
Aros Waterfront outdoor activity hub – RCGF Grant      £414,565 £0 £403,500   2023/24 2024/25
Nonhebel Light Industrial Park Expansion – RCGF Grant   £1,004,000 £0     £654,000   2023/24 2024/25
Islands Programme 2023/24 - Rockfield Road, Tobermory Phase 1 £855,796 £0 £855,796 2023/24 2024/25
Islands Programme 2023/24 - Tiree Care Home £1,250,000 £580,000 £450,000 2023/24 2023/24
Tarbert Heritage Regeneration Scheme – Development Phase £140,000 £60,000 £80,000 2023/24 2023/24
Total £45,370,328 £6,849,018 £20,842,739     
* See separate 12th August 2021 Policy and Resources committee report for proposed breakdown of projects and values. The full award was £812,000 but
many of these projects are now complete.
** Full award for 22/23 was £712,000.  This figure has had the £200,000 awarded to Lochgilphead CARS deducted.  See separate 16th June 2022 Policy
and Resources committee report for proposed breakdown of projects and values.  3 of these projects are now complete. 
Page 134

Page 135

1 
 
ARGYLL AND BUTE COUNCIL              ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH         21st MARCH 2024 
ARGYLL AND BUTE COUNCIL’S ECONOMIC STRATEGY REFRESH: 2024-2034 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this paper is to provide the Environment, Development and
Infrastructure Committee with a refreshed Argyll and Bute Council Economic
Strategy, covering the period 2024-2034, as outlined in Appendix 1. 
1.2 This refreshed economic strategy is both ambitious and forward looking, with a place-
based and business/person-centred approach, to secure a fair, inclusive, and
prosperous future for the area, more resilient to external factors including the rapid
advances in digital technology and increasing impacts of climate change. 
1.3 The document unites purpose, with a focus on partnership and collaboration as the
cornerstones of delivery. Informed through consultation and by available economic
and population data, the drivers of economic growth will be across four strategic key
pillars: people, place, planet and prosperity. 
1.4 The associated action plan will be prepared for consideration by the committee
members at the meeting on 20th June 2024. 
1.5 It is recommended that members of the Environment, Development and Infrastructure
Committee: 
 Provide commentary on the refreshed Economic Strategy as outlined in Appendix
1. 
 Endorse the refreshed Economic Strategy, with an associated Action Plan to be
considered at the next committee meeting in June 2024. 
Page 135 Agenda Item 15

Page 136

2 
 
ARGYLL AND BUTE COUNCIL              ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH         21st MARCH 2024 
ARGYLL AND BUTE COUNCIL’S ECONOMIC STRATEGY REFRESH: 2024-2034 
2.0 INTRODUCTION 
2.1 The success of the Argyll and Bute economy is fundamental to our future quality of
life. The pace of change has been accelerating globally and nationally which has
required Argyll and Bute Council to refresh its economic strategy. 
2.2 The refreshed Argyll and Bute economic strategy is ambitious for our area.
Continued focus is required on the medium to longer-term economic and social
recovery agenda for Argyll and Bute in response to the economic shocks of recent
years. In particular, the pandemic, EU Exit and the cost of living, including the cost
of doing business, crises. 
2.3 The document unites purpose, with a focus on partnership and collaboration as the
cornerstones of delivery. Informed through consultation and by available economic
and population data, the drivers of economic growth will be across four strategic key
pillars: people, place, planet and prosperity. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that members of the Environment, Development and Infrastructure
Committee: 
 Provide commentary on the refreshed economic strategy as outlined in Appendix
1. 
 Endorse the refreshed economic strategy, with an associated action plan to be
considered at the next committee meeting in June 2024. 
4.0 DETAIL 
4.1 The need for collaboration and the interplay between economy, environment and
community has never been stronger. Argyll and Bute is particularly well placed to
benefit from the potential of the area’s natural capital resources and the role it can
play in providing green jobs and achieving net zero across key industries.
Page 136

Page 137

3 
 
4.2 The refreshed economic strategy has been prepared with a strong focus on
collaboration and a joined-up approach, working closely with the Community
Development Team who are currently revising the Local Outcome Improvement Plan
(LOIP) on behalf of the Argyll and Bute Community Planning Partnership, partner
agencies and stakeholders across Argyll and Bute and externally. 
4.3 A core focus of the strategy is for Argyll and Bute to be a wellbeing economy through
embedding a Community Wealth Building approach. The outcome is to increase the
flow of wealth and opportunity for the benefit of the people who live and work in the
area through improving our places and local access to economic opportunity,
including community ownership, reducing inequalities, tackling poverty through
providing higher value, well-paid, jobs and supporting employers to take forward the
Fair Work First principles. 
5.0 CONCLUSION 
5.1 The Argyll and Bute economy is undergoing significant changes, presenting both
distinct short and longer-term opportunities and challenges to overcome. The existing
economic strategy has been updated post the COVID-19 pandemic in the context of
economic recovery, but due to the rapidly changing global economy, with the added
implications of EU Exit and the cost of living crisis, a renewed focus is now required
to acknowledge the issues that are with us, celebrate our key strengths as an area
and embrace the opportunities of our rural, natural resource based economy. 
6.0 IMPLICATIONS
6.1 Policy - current Argyll and Bute Economic Strategy, LOIP and National Strategy for
Economic Transformation refresh (NSET – 10 year duration).
6.2 Financial – resources will be required to deliver the strategic intent and will be
considered under the action plan discussions in June 2024.
6.3 Legal - all appropriate legal implications have been taken into consideration
6.4  HR – none.
6.5 Fairer Scotland Duty - the Fairer Scotland Duty, Part 1 of the Equality Act 2010,
came into force in April 2018. The duty places a legal responsibility on particular
public bodies in Scotland, such as Argyll and Bute Council, to pay due regard to
(actively consider) how they can reduce inequalities of outcome, caused by socio-
economic disadvantage, when making strategic decisions and how this has been
implemented 
6.5.1  Equalities - all activities have complied with all Equal Opportunities/Fairer
Scotland Duty policies and obligations 
6.5.2  Socio-economic Duty - all strategic pillars, priorities and project activities will
comply with the council’s socio-economic duty
Page 137

Page 138

4 
 
6.5.3  Islands - a refreshed economic strategy will include priorities and actions that
will be delivered across the whole of Argyll and Bute including the island
communities.
6.6 Climate Change - strategic priorities and activities will address the net zero transition
agenda. 
6.7 Risk - buy-in by key partner agencies and stakeholders to the medium to longer-term
strategic priorities could be challenging due to the uncertainty around future funding
streams; many budgets still decided on an annual basis.
6.8  Customer Service – none.
6.9 The Rights of the Child (UNCRC) – none. 
Kirsty Flanagan, Executive Director responsible for Development and Economic
Growth 
Policy Lead for Economic Growth, Communities and Corporate Services,
Councillor Alastair Redman 
14th February 2024 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
Tel: 01546 604293 and e-mail: fergus.murray@argyll-bute.gov.uk 
Ishabel Bremner, Economic Growth Manager
Tel: 01546 604375 and e-mail: ishabel.bremner@argyll-bute.gov.uk 
APPENDICES
Appendix 1: Economic Strategy Refresh 
Page 138

Page 139

5 
 
APPENDIX 1: DRAFT ECONOMIC STRATEGY REFRESH 
Argyll and Bute Council Economic Strategy Refresh, 2024-2034 
1.0 Strategic Vision
1.1 The success of the Argyll and Bute economy is fundamental to our future quality of
life. The pace of change has been accelerating globally and nationally which has
required Argyll and Bute Council to refresh its economic strategy. 
1.2 The strategy is both ambitious and forward looking, with a place-based and
business/person centred approach, to secure a fair, inclusive, and prosperous future
for the area, more resilient to external factors including the rapid advances in digital
technology and increasing impacts of climate change. 
1.3 The issues identified above will be achieved through the core focus of Argyll and
Bute being a wellbeing economy through embedding a Community Wealth Building
approach. The outcome is to increase the flow of wealth and opportunity for the
benefit of the people who live and work in the area through improving our places and
local access to economic opportunity, including community ownership, reducing
inequalities, tackling poverty through providing higher value, well-paid, jobs and
supporting employers to take forward the Fair Work First principles. 
1.4 The Argyll and Bute economy is undergoing significant changes, presenting both
distinct short and longer-term opportunities and challenges to overcome. The existing
economic strategy has been updated post the COVID-19 pandemic in the context of
economic recovery, but due to the rapidly changing global economy, with the added
implications of EU Exit and the cost of living crisis, a renewed focus is now required
to acknowledge the issues that are with us, celebrate our key strengths as an area
and embrace the opportunities of our rural, natural resource based economy. 
1.5 Our ambitious economic strategy for Argyll and Bute (2024 – 2034) unites purpose,
with a focus on partnership and collaboration as the cornerstones of delivery.
Informed through consultation and by available economic and population data, the
drivers of economic growth will be across four strategic key pillars: PEOPLE,
PLACE, PLANET and PROSPERITY. 
• PEOPLE: Addressing the continuing decline in our economically active
population, improving workforce skills and attracting key workers, promoting
equal access to education opportunity, and supporting job opportunities in
emerging and new industries. 
• PLACE: Investing in our towns, rural and remote rural communities, including
our islands and peninsulas, to attract new people and businesses, pursuing
external funding opportunities, investing in critical economic infrastructure such
as housing, land for business development, reuse of land and buildings for
Creating a place-based and people-centred economy that delivers
shared prosperity and sustainable business growth through innovation
and collaboration.
Page 139

Page 140

6 
 
community benefit, digital connectivity and transport (principally roads, ports
and ferries). 
• PLANET: Delivering net zero and improving our biodiversity by supporting the
sustainable growth of clean energy production (i.e. hydro, solar, wind and
biomass), woodland, peat and marine habitat restoration, encouraging green
industries to develop in our area, nature-based solutions and community
ownership. 
• PROSPERITY: Creating higher wage opportunities, seizing opportunities in the
net-zero economy, improving productivity and innovation through increasing
business efficiency including  the use of digital technology, empowering
communities through ownership and wealth creation, sustaining public services,
promoting the blue and green economies, enabling the sustainable growth of
key sectors such as food and drink together with revitalising the tourism and
hospitality sectors and supporting the growth of the creative industries . 
1.6 Argyll and Bute is predominantly a resource-based economy taking advantage of our
abundant natural resources to create a resilient, prosperous and wellbeing economy
with empowered communities at its heart. 
2.0 Argyll and Bute Geographical Context 
2.1 Argyll and Bute is the second largest council area in Scotland and is home to a rich
and varied natural landscape and coastline comprising a significant expanse of
Scotland’s mainland, as well as the southern group of the Inner Hebridean Islands,
currently consisting of 23 inhabited islands. 
Page 140

Page 141

7 
 
2.2 Our varied and complex geography has contributed to creating vast disparities in
terms of access to essential services both public and private, employment
opportunity, business efficiency and-economic outcomes. Most notably between the
region’s main population centres, our rural and island communities owing to the often
isolated nature of the area and reliance on ferries. 
Page 141

Page 142

8 
 
3.0 Baseline Analysis
3.1 Presented below is the summarised baseline analysis for the four strategic pillars of PEOPLE, PLACE, PLANET and
PROSPERITY. 
Page 142

Page 143

9 
 
Page 143

Page 144

10 
 
Page 144

Page 145

11 
 
4.1 Key messages from the evidence base have fed into a Strengths, Weaknesses, Opportunities and Threats (SWOT) analysis,
The SWOT analysis will be included in a separate baseline report to support this document. The diagram below outlines the
opportunities for Argyll and Bute and drives the focus of this ambitious refreshed economic strategy and the ongoing
preparation of an associated action plan.
4.0 Opportunities 
Page 145

Page 146

12 
 
5.0 PEOPLE
5.1 People are Argyll and Bute’s most important asset
in driving forward the local economy and opportunities for
future growth. However, our region has a relatively tight
labour market arising from consistently higher levels of
participation and low unemployment, with critical skills
gaps in public services and key business sectors, such as
hospitality and construction. A situation that has been
exacerbated in recent years by a declining working-age population, limited in
migration and higher levels of economic inactivity particularly in the over fifties. 
5.2 Over the next decade the following opportunities and challenges will require
concerted action from the council working in collaboration with strategic
partners from the public, private and third sectors. This includes sharing of data
insights across partners. 
5.3 Opportunities: 
 Retention and attraction of young people: to attract and retain young
people to the area will require extensive collaboration and continued
targeted interventions and ongoing support. 
 Self-employment: there is recognition that Argyll and Bute has a high
level of self-employment and the majority of businesses that employ 0 to 4
employees are often family owned and operated. There is a requirement
to support this strong entrepreneurial approach of local people which can
act as a catalyst to strengthen local supply chains, embed a circular
economy at a local level and tackle market failure. 
 Skills development: there is a need for a continued focus on improving
people’s work skills, through upskilling and reskilling given the world of
work is changing at an ever-increasing pace. There is a constant need to
keep up to date with the demands of the future economy that will be
driven increasingly by the blue, green and digital agendas. STEM
(Science, Technology, Engineering and Maths) education will feature
highly here and there is need to be creative by helping companies adapt
quickly to change and take full advantage of the many new opportunities
that will present themselves in the future. 
 Access to further and higher education and training: increase
opportunities for parity of participation across all parts of Argyll and Bute
for all ages and stages, including school curriculum, access to modern
apprenticeships, further and higher education, and workforce training and
development to ensure that no one is left behind. 
 Resettlement programmes: diversifying communities and bringing new
skills.  
Page 146

Page 147

13 
 
5.4 Challenges: 
 Increase in the economically active population: there is a requirement
to increase the economically active population across the whole of Argyll
and Bute so that local businesses, or potential investors, can access the
people they need to sustain or grow their business. External factors, such
as leaving the EU has limited the flow of new workers through in migration
seeking employment in the area. It is recognised that the availability and
cost of housing is a key barrier to people coming to Argyll and Bute. This
is being addressed through the council declared a Housing Emergency in
June 2023 (not just for in-migrants) and is taking forward a housing action
plan as a matter of urgency. 
 Unemployment and Underemployment: across most of Argyll and Bute
unemployment rates remain lower than the national average. That said, a
large number of people of working age are underemployed in either part
time, or lower paid jobs, or a combination of both. 
5.5 To address the opportunities and challenges under PEOPLE the refreshed
economic strategy action plan needs to deliver clear SMART actions as follows:   
 Increase the economically active population by investing in skills
development (upskilling and reskilling) and
training for those actively seeking work or
interested in a change of career in the new and
emerging occupations aligned to sectors such as
space, the blue and green economy includng the
use of our natural capital for low carbon and
clean energy options. 
 Work with partners to enable equal access to
education (academic and vocational) including
work skills development opportunities for all,
especially in emerging industries with significant
growth potential. 
 Focus on STEM education to prepare for an increasingly, digitally driven
and green economy, delivered through the Rural Growth Deal STEM
Hubs, Marine Industry Training Centre and Clyde Engineering Cluster
proposals and monitored through the key performance indictors outlined
in their Full Business Cases. 
 Promote increased adaptability
and skills development for both
existing and new staff among
local businesses to better
capitalise on changing economic
opportunities.  
 
“I am learning every day and now 
getting the chance to use the skills 
I have learnt from college and 
helping experienced trades people. 
I also have a few quid to be able to 
go out and socialise with my 
friends which I couldn’t really 
afford before.” 
 
“Just to let you know I passed my HGV
driving test this afternoon!! It still feels like
a dream. I'm still in shock. Just wanted to
say thanks so much for what you did. I
couldn’t have done this without you.” 
Page 147

Page 148

14 
 
6.0 PLACE 
6.1 Argyll and Bute has distinct, vibrant and dynamic town
centres with a strong and distinct cultural heritage coupled
with an outstanding natural and built environment. To build on
these strengths our places continue to need further investment
to adapt to the demands of a rapidly changing economy. The
future success of our main towns and key settlements is
critical for retaining and attracting people. They need to offer
the services, functions and spaces people expect to see, albeit
with a recognition that most of our communities are not of a scale that can offer
everything. Further active travel investment in walking and safe cycling routes
is one key factor in the development of a wellbeing economy. In addition, critical
transport and digital infrastructure have been identified by our businesses and
communities (island and mainland) as crucial economic enablers. 
6.2 Opportunities: 
 Vibrant and dynamic communities: building on the success of our Love
Local Card our towns, places and communities need further development
in their vibrancy and attractiveness to encourage private sector
investment and to build on the success of securing external funding.
External funding is critical to the future success of our town centres, rural
and island communities by securing investment to enable key issues to be
addressed, including improvements to critical economic infrastructure,
transport (including public transport networks) and digital connectivity, the
public and built fabric, addressing and harnessing the opportunities with
derelict and under-utilised buildings, delivering local living opportunities,
having sufficient fit for purpose housing choices and sufficient land to start
and sustain new business start-ups. 
 Community Led Local Development: focusing on local delivery of
projects and interventions for communities across Argyll and Bute. Where
communities are well placed to embed Community Wealth Building and a
wellbeing economy, such as encouraging active travel, and a community
first approach. 
 Growth of the third sector: such partners have a key role of retaining
and recycling wealth back into communities. 
 Distinctive cultural and heritage assets: enhancing and safeguarding
the strong culture and heritage that underpins communities coupled with a
high quality built environment.  
Page 148

Page 149

15 
 
6.3 Challenges: 
 Competition for investment: competition to attract and secure external
funding is high and increasing with a continued west to east shift
nationally. The availability of match funding that is either required, or
desirable, to secure external finance is also in short supply. 
 Fragile communities: the COVID-19 pandemic had a significant impact
on social connections, local economies and the capacity of community
support organisations. 
6.4 To address the opportunities and challenges under PLACE the refreshed
economic strategy action plan needs to deliver clear SMART actions as
follows: 
 The correct tools and support are required to build back socio-economic
connectedness, support a sense of belonging, post the COVID-19
pandemic. This will be done
through recognising the strengths
of community resilience across
Argyll and Bute. 
 Work with strategic partners to
support communities in the
development and facilitation of
transformational regeneration
projects including community
ownership of assets and wealth
creation. 
 Secure future investment from
cross sector partners and
external funding streams into our
towns, rural and island communities to enhance and
improve the built fabric for residents and to attract businesses,
investors and visitors and support shop local. 
 An increasing focus on areas of opportunity,
particularly, but not exclusively, in Dunoon,
Rothesay, and Campbeltown, by fostering
community partnerships, identifying key place-
based actions and co-ordinating investment to
achieve wellbeing outcomes. 
“This is to congratulate the council, and its partners, 
on the highly successful delivery of a key part of 
Lochgilphead’s regeneration. The sheer quality and 
improvement already achieved is of a high order and 
will endure …investment in the Front Green – where I 
walked this morning – adds to the streetscape 
improvement of the town.”    
We are encouraging people to live in 
Argyll and Bute by delivering homes 
and infrastructure for the future, 
promoting local living and helping to 
shape thriving, sustainable, 
communities. 
Page 149

Page 150

16 
 
7.0 PLANET 
7.1 Delivering net zero and mitigating the impacts of climate
change is key to Argyll and Bute’s society and future prosperity.
The area is playing a significant role in achieving this through
the increasing production of clean energy, the expansion of our
forests, and the restoration of our native woodlands, peatlands
and marine habitats. 
7.2 The council has a number of different strategies to help
mitigate climate change. At the heart of all these strategies and plans are the
people who live here and make a sustainable living from our abundant natural
resources. There is a compelling need however to strengthen the link with our
natural environment and the retention of more of the wealth we generate locally
within our local communities and at the same time increase our actions to
mitigate against the growing impacts of climate change and improve our
biodiversity as a place. In short, Argyll and Bute is well placed to make a
significant contribution to both Scotland and the UK’s Net Zero ambitions. 
7.3 Opportunities: 
 Clean energy: supporting the increase of clean energy through onshore
and offshore wind, grid enhancement, pumped storage hydro and other
forms of renewable energy such as solar, tidal and biomass where
appropriate. In the next decade there is the potential to increase clean
energy production from just over one gigawatt to five gigawatts bringing
with it a large number of temporary construction jobs and ultimately
service jobs in the energy sector. This will require considerable investment
in our grid infrastructure making its smarter to deal with the local
production of energy and using it locally as well as exporting it. Being
mindful of our landscape and communities, and delivering local living
opportunities through strategic housing investment, will also be key going
forward and promoting our area as a place where new industries and
supply chains can be established through a Community Wealth Building
approach to make use of this enormous clean energy potential. 
 Low carbon: there is also a need to improve our infrastructure to offer low
carbon options for people including active travel routes, improved digital
connectivity, UAV technology, improved insulated housing and premises,
green hydrogen production, and EV charging points. 
 Community land ownership: this an important aspect as our forests
expand, become more diverse and where investment in our natural
habitats will improve our biodiversity and at the same time generate local
job opportunities in managing the land and sustainable tourism. 
Page 150

Page 151

17 
 
 Investment in new green industries: success will be demonstrated by
the investment of new industries to our area attracted by green energy
availability, but this will require additional investment in key areas of
infrastructure such as grid, digital connectivity and data links. Importantly
the creation of new and emerging industries including space, data centres
and high intensity agriculture/aquaculture. 
 Nature based solutions: these will need to become the norm for our area
helping us to deal with increasing climate change impacts and improving
our biodiversity. Projects must provide multiple benefits for the place we
live in and importantly create livelihoods for the people who want to live
and work in Argyll and Bute. 
 Marine/Blue economy: the marine environment can also play a critical
role through the development of existing and emerging industries such as
seaweed farming, marine research and marine tourism. 
7.4 Challenges: 
 Doing nothing: if no action is taken to address the ongoing and current
impacts of climate change, this will continue to create existential threats
and challenges for Argyll and Bute’s natural assets and capital. 
 Unlocking private sector resources: more needs to be done to prevent
further decline in our carbon outputs through unlocking the resources of
the private sector to reduce our use of fossil fuels and improve our
biodiversity. 
7.5 This refreshed economic strategy needs to be supported by SMART actions for
our PLANET that: 
 Lead efforts to achieve net zero through
increased clean energy production, forestry
expansion, and marine habitat restoration. 
 Embrace clean energy opportunities and
work with partners and utilities to secure
investment in grid infrastructure that provide
better local outcomes. 
 Develop low-carbon infrastructure to enable
alternatives to private transport including
active travel, better digital connectivity, and
sustainable housing. 
 Foster nature-based solutions for increased climate change resilience and
biodiversity enhancement. 
 Support sustainable industries like seaweed farming, marine research and
green energy.
Home insulation at no cost through a 
non‐means tested grant from Argyll and 
Bute Council Home Energy Efficiency 
Team funded by the Scottish 
Government’s Energy Efficient Scotland ‐ 
Area Based Scheme.  
Page 151

Page 152

18 
 
 Unlock the potential of the marine/blue economy by opening controlled
sites for broader use.  
The Aros waterfront development is a long‐
term, multi‐phase project with an overarching 
objective to create a hub for community well‐
being, outdoor activities, and educational 
opportunities, as well as opportunities for new 
enterprises and sustainable outdoor tourism 
experiences. The initial phase of works has 
focused on making safe and bringing back into 
use the existing pier as well as providing a 
pontoon and slipway. 
Page 152

Page 153

19 
 
8.0 PROSPERITY 
8.1 Argyll and Bute has particular economic strengths and
opportunities to take advantage of in the next decade. Further
advancements in automation, real-time data technologies and
artificial intelligence will provide opportunities for enterprises and
public services to diversify and develop new commercial models
that embrace change - a key enabler to improve local prosperity
and productivity. Increased productivity can mean people have a
significant boost to their household income helping them to cope with higher
inflation and the cost-of-living crisis. The drive to net zero and climate
adaptation can bring with it new opportunities for green jobs through taking a
circular economy approach. Inspiring our young people to take full advantage of
new innovative opportunities in the green and blue economies is an action that
is vital for the area’s future, coupled with reskilling existing staff. Creating
opportunities for better wages and higher industrial outputs will help local
people increase their income potential and quality of life indicators. 
8.2 Opportunities: 
 Existing sectors: there is a requirement to maximise the value of our
existing well-established sectors such as tourism; food and drink including
aquaculture; together with our creative industries with examples below
aligned to hospitality, whisky/spirits and culture: 
• Tourism and hospitality: Tourism and the hospitality industry remains
a key sector for Argyll and Bute, with a number of outstanding and
award-winning businesses and products. A strong rebound has been
witnessed, given that this was one of the hardest hit sectors during the
pandemic, with a focus on realising its former growth ambitions. The
sector continues to innovate and respond to the changing demands of
its customers by adapting and introducing new products. This includes
opportunities for low carbon development that makes used of our
natural assets such as leisure walking and cycling. Argyll and Bute
Council recognises the importance of the tourist sector to the economy,
but also understands the pressures the industry is facing from the cost-
of-living crisis, infrastructure deficiencies, and government legislative
changes, 
• Whisky/spirits: Argyll and Bute produces world class products
including whisky. Two distinct whisky regions are contained in our area,
Islay and Campbeltown. This sector has experienced remarkable
growth in recent years, and this looks set to continue as the demand for
this world class product escalates. Our challenge is to ensure that this
growth continues in a sustainable way that maximises supply chain
benefits through the Community Wealth Building agenda. 
• Culture: Creative industries and our Gaelic heritage could be an
economic driver for the region given its popularity with tourists including
Page 153

Page 154

20 
 
bilingual events, visitor centre information and branding within the
business or product name. 
 Transformational growth sectors: there is a requirement to maximise
the value of other existing sectors that have economic growth and
regional transformational potential such as energy transition (marine,
green hydrogen, offshore wind), life sciences and the emerging space
sector. 
 Business growth: many of the area’s micro to small and medium sized
businesses have potential to grow, supported by appropriate business
support, infrastructure and land for business development. 
 Community Wealth Building and empowerment: there is a requirement
to start to embed Community Wealth Building as the key mechanism to
deliver a wellbeing economy, economic development, growth and
prosperity across all communities across Argyll and Bute. Not every part
of Argyll and Bute will be able to create additional employment
opportunities through the activities of the private and third sectors. Public
services are under increasing pressure to sustain themselves and
communities will inevitably have to do more to provide the types of
services they need. This needs to be done in a way that can generate
income for a community and add to the many successful examples of this
approach across Argyll and Bute. The Community Wealth Building
approach will provide a strong framework for collaboration and partnership
working to be made across with the public, private and third sectors. 
8.3 Challenges: 
 Transport connectivity: lifeline routes and transport assets in need of
substantial investment to secure future safe access particularly in light of
increased climate change impacts. 
 Inability to access to the coast: Argyll and Bute looks well placed to
access the marine environment, but many sites are controlled by single
users, are at capacity, or are no longer usable for modern requirements.
To realise the full potential of the blue economy this will need to change,
otherwise opportunities will pass us by. 
 Household income: remains below the average of Scotland. This
situation is worsening, exacerbated by the cost-of-living crisis, and local
wages not keeping pace with inflation. Through the Fair Work First
framework/principles, raising and adopting the real living wage will be a
key aspect, as will improving people’s skills to improve their job prospects
and potential to progress their careers in industries that can offer higher
wages. Higher wages also pose issues for business survivability. 
8.4 This refreshed strategic needs to be supported by actions for PROSPERITY
that: 
Page 154

Page 155

21 
 
 Capitalise on net-zero opportunities for green jobs and improve living
standards. 
 Focus on productivity improvements through digital technology. 
 Empower the public, private and third sectors to provide services,
participate in shared management of civic spaces and generate income. 
 Revitalise our key sectors such as the tourism and hospitality industry,
through addressing industry challenges including transport connectivity. 
 Leverage natural and cultural assets to drive sustainable business growth
and overall economic growth. 
Argyll 
Yacht 
Rigger 
 
“Starting your own 
business, especially in a 
rural area, can be 
daunting. The support of 
Business Gateway has 
been vital to success.” 
Argyll Yacht Rigger 
 
“The site is being operated by MICT, a social 
enterprise, generating a sustainable income for 
the trust in addition to enabling private sector 
investment through the creation and expansion of 
businesses.” Mull and Iona Community Trust on 
the development of Nonhebel Industrial Park 
Page 155

Page 156

22 
 
9.0 CROSS-CUTTING THEMES 
9.1 Achieving a wellbeing economy. 
Achieving a wellbeing economy is a key priority of the council and our partners.
A healthy population is fundamental to a thriving economy. The purpose of
economic growth should be to benefit the people who are part of that economy,
and a wellbeing economy is one that structures the economy in a way that
delivers wider wellbeing benefit. This requires collaboration across local
authority services, business and the third sector to invest in preventative
measures that improve people’s wellbeing. The wellbeing outcomes we are
seeking to achieve are set out in the Local Outcome Improvement Plan and
align with the Place and Wellbeing Outcomes. 
This strategy has been informed by consideration of the Place and Wellbeing
Outcomes (themed by Movement, Spaces, Resources, Civic and Stewardship);
a consistent and comprehensive focus for where place impacts on the
wellbeing of people and planet. A Place and Wellbeing Assessment of the
strategy using the Outcomes as a framework considered how to maximise the
positive impact on wellbeing and highlighted the need for strategic alignment of
plans which impact on a place, co-ordination of investment in strategic
infrastructure and the importance of partnership working to delivery. 
9.2 Partnership and collaborative working 
Reaching our full economic potential lies beyond the resources of the council
on its own. Working in partnership is increasingly important across all sectors to
pool resources and expertise in realising economic opportunity, co-ordinating a
holistic approach to planning places and addressing barriers to economic
growth. The council will work with other enterprise agencies such as Highlands
and Islands Enterprise and Scottish Enterprise to align plans and to operate as
a cohesive regional team where possible. Stronger and more collaborative
partnership working, focused on a place-based person-centred approach, will
help to ensure suitable opportunities for individuals of all ages and capabilities
through tackling socio-economic disadvantage, inequalities and removing
multiple barriers to securing sustainable employment and appropriate housing.
Working with large scale employers in the statutory and private sector will
support delivering on wellbeing outcomes for connectivity and housing in
particular. 
9.3 Public sector sustainability 
Public sector sustainability is of key importance to ensure that appropriate
services continue to be delivered to the dispersed urban, rural, remote rural and
island communities across the whole of Argyll and Bute. Through partnership
working ongoing consideration needs to be given to added value investment,
improvements that could be made to public services and the generation of
income to enhance limited budgets across the council. 
Page 156

Page 157

23 
 
9.4 Maximising external funding opportunities 
Our financial resources are limited and the availability of match funding for our
council is a major issue. That said, the council will continue to build on its
strong track record of attracting external funding to Argyll and Bute and
realising economic opportunities and addressing identified barriers to economic
growth and resilience. 
9.5 Economic intelligence and data gathering 
Our area has particular economic needs and opportunities. If this is to be
efficiently addressed at both a local and national level, we will have to have
sufficient data in place to convince potential strategic partners and investors to
be part of our future economic prosperity. Partnership working to map, identify
and share relevant data will be required. 
9.6 Governance and accountability 
There is a need to ensure that we comply with the latest Scottish and UK
Government legislation and the requirements of external funding partners and
programmes to realise opportunities with a focus on good governance and
strong financial accountability to demonstrate best value. 
9.7 Monitoring our progress. 
The council and with input from our strategic partners will monitor the progress
of the refreshed Argyll and Bute Economic Strategy through the outcome based
SMART Action Plan and the associated updated Argyll and Bute Outcome
Improvement Plan indicators. Where the strategy is delivered through separate
plans or strategies e.g. The Strategic Housing Strategy the existing monitoring
arrangements will remain in place and not be duplicated. The Economic
Strategy has been prepared to capture critical regional issues and themes that
will be considered in the preparation and delivery of an Economic Strategy for
the Highlands and Islands Regional Economic Partnership.
Page 157

Page 158

This page is intentionally left blank

Page 159

1.0 EXECUTIVE SUMMARY 
1.1  In June 2023 the Council’s Environment, Development and Infrastructure
(EDI) Committee declared a Housing Emergency due to a consistent
reduction in supply of housing, a steady increase in demand for housing
across all tenures and increasing levels of un-affordability. 
The Committee approved the following:-
• The intention to update the Local Housing Strategy
• The intention to hold an Argyll and Bute housing summit together with
relevant stakeholders in the Autumn of 2023
• Note the operational officers group will explore and develop a series of
options that will be brought forward to Members for consideration as
and when developed. 
1.2 This report is to update the EDI Committee on progress towards these
intentions and generally tackling the Housing Emergency. 
1.3 A wide range of activity has been progressing including: holding a Housing
Summit in November, preparing a Local Housing Strategy Update, actions of
the Officer Housing Group, focusing initially on exploring release of Council
Assets suitable for housing, liaison with National House Builders, exploring
facilitation of constrained sites, partnership working with RSLs, improving the
evidence base to justify innovation and intervention, securing Rural Housing
Body Status, operating a refined HomeArgyll letting policy, exploring changes
in the land use planning system; developing worker housing, supporting
delivery of worker housing and community delivered housing. 
RECOMMENDATION 
Members of the Environment, Development and Infrastructure Committee are
asked to consider and note the activity and progress that is ongoing in pursuing
the EDI Committee approved intentions and generally seeking to address the
housing emergency.   
ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21st MARCH 2024 
ARGYLL AND BUTE HOUSING EMERGENCY – PROGRESS REPORT 
Page 159 Agenda Item 16

Page 160

2.0 INTRODUCTION 
2.1 In June 2023 the Council’s EDI Committee declared a Housing Emergency
due to a consistent reduction in supply of housing, a steady increase in
demand for housing across all tenures and increasing levels of un-
affordability. 
2.2 This Committee approved a range of actions and this report is to update the
EDI Committee on progress towards these intentions and generally tackling
the Housing Emergency. 
3.0  RECOMMENDATIONS 
3.1 Members of the Environment, Development and Infrastructure Committee are
asked to consider and note the activity and progress that is ongoing in pursuing
the EDI Committee approved intentions and generally seeking to address the
housing emergency. 
4.0  DETAIL 
A HOUSING EMERGENCY  
4.1 In June 2023 the Council’s EDI Committee declared a Housing Emergency
due to a consistent reduction in supply of housing, a steady increase in
demand for housing across all tenures and increasing levels of un-
affordability. 
ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21st MARCH 2024 
ARGYLL AND BUTE HOUSING EMERGENCY – PROGRESS REPORT 
Page 160

Page 161

The Committee approved the following:-
• The intention to update the Local Housing Strategy
• The intention to hold an Argyll and Bute housing summit together with
relevant stakeholders in the Autumn of 2023
• Note the operational officers group will explore and develop a series of
options that will be brought forward to Members for consideration as
and when developed. 
4.2 This report is to update the EDI Committee on progress towards these
intentions and generally tackling the Housing Emergency. 
The intention to update the Local Housing Strategy 
4.3 There is a statutory requirement for the Council to produce a Local Housing
Strategy(LHS). The current LHS covers the period 2022-2027. As is required,
an annual update has been produced and this can be found at: LHS Annual
Update 2023  The update highlights some of the new issues which have come
to the fore; particularly the need to address issues in the private sector supply
of speculative new build housing, and the need to consider the requirements
for regulation of the existing private stock and its use, particularly second
homes and holiday lets.   
4.4 The intention is to amend the LHS Action Programme to reflect the
appropriate actions coming from the Housing Summit Action Programme, and
this is likely to be September 2024. 
The intention to hold an Argyll and Bute Housing Summit together with
relevant stakeholders in the Autumn of 2023 
4.5 Declaring a housing emergency in Argyll and Bute is a call to action for
government, public bodies and partners. It is intended as the catalyst to bring
partners, stakeholders, investors and communities together to prioritise and
commit to the collective action needed to tackle housing shortage. The Council
are fully committed to working with partners to programme a broad range of
activities, both in the short term and long term, to target this collective action
where it is needed most. 
Page 161

Page 162

4.6 The Housing Emergency Summit was held on 27th November 2023 at the
SAMS Campus, Oban and 92 delegates attended.  The purpose of the Summit
was to bring partners together to forge commitments aimed at tackling housing
shortage by maximising resources, pursuing innovation, coordinating planning
and targeting delivery capacity. Delegates attending the Emergency Housing
Summit included: 
• Senior decision makers in local and national public sector bodies
including the NHS, Scottish Futures Trust and Highland and Islands
Enterprise
• Senior decision makers in Argyll and Bute Council
• Housing developers both commercial builders and Housing Associations
• Representatives from the Community Housing Network
• Local business leaders and funding bodies
• Third sector organisations and support agencies.
4.7 The Summit was designed to focus partnership activity on prioritising and
programming emergency responses across the following four themes: 
4.8 Summit delegates were presented with background information on the extent
and nature of housing shortage, as well as potential solutions and
interventions.  The day was spent testing, assessing and prioritising these in
terms of their potential impact and deliverability with a total of 39 housing
emergency actions being prioritised at the end of the day.  An indication of
some of the priority actions is shown below, and full details can be seen in
the Appendix 1, Housing Emergency Summit Report. 
Page 162

Page 163

4.9 The outcomes of the Housing Emergency Summit will be used to develop a
Housing Emergency Summit Action Plan as the basis of ongoing planning,
activity, investment and partnership. Housing Emergency Action points will be
refined, partnership commitments focused, timescales proposed, and
resources commitment scoped in early 2024.  The Housing Summit Action Plan
will be presented to the EDI Committee in June 2024.  The Housing Summit
Action Plan will not be the sole ownership of the Council but will reflect the
commitments of all stakeholders who attended the Housing Summit.  The
intention is to distil from the Housing Summit Action Plan the activities and
commitments which are relevant and within the gift of the Council, and to
include those within an updated LHS Action Programme.  This will give those
elements a formal position within Council policy going forward. 
Note the operational officers group will explore and develop a series of
options that will be brought forward to Members for consideration as
and when developed. 
4.10 The Officers Group which has been set up within the Council to assist in
tackling the housing emergency remains focused on Council owned assets
and exploring how they could be used to assist in tackling the housing
emergency.  The Strategic Housing Fund is being utilised to resource the
necessary site investigations as outlined below. 
4.11 Key actions which have been undertaken or are in progress include:
• Ironsides Farrar have been completed initial site investigations of
Council owned sites at Balemartine, Tiree, Crossapol, Tiree,
Arinagour, Coll.  Further development option appraisal work is
ongoing.  RSLs have confirmed in principle interest in these sites. 
Officers are working to establish more firm development options prior to
Proposed Housing Emergency Solution On the
Table
Off the
Table
Pursue a more flexible approach to infrastructure, roads and design requirements in rural
and island housing developments 98% 2%
Dramatically increase the number of college places for construction skills development in
Argyll & Bute 100% 0%
Deliver self-build plots and mortgages 86% 14%
Freedom to use Scottish Government housing funding more flexibly and as an allocation
with local administrative control 92% 8%
Create a ring-fenced Infrastructure Fund for housing development 90% 10%
Pursue Council funded housing development of low-cost homes for rent or sale 79% 21%
Support mixed tenure community led housing development through asset transfer and
delivery support 77% 23%
Pursue modern methods of construction to boost affordable housing delivery 94% 6%
Deliver more MMR and low-cost homes for sale via the SHIP 91% 9%
Deliver short term workforce housing options including modular, temporary and tiny 73% 27%
Extend the use of rural housing burdens across Housing Market Areas in Argyll & Bute to
maintain primary occupancy and or affordability 92% 8%
Pursue Short Term Let control areas 66% 34%
Lobby the Scottish Government to create a private sector duty for large development
projects to invest in workforce housing 66% 34%
Page 163

Page 164

formally exploring interest with RSL partners.  These are small sites but
would provide a significant housing contribution in remote communities.
• Preliminary site investigations have been carried out at Hermitage
Primary School Annex, Helensburgh.   HubNorth are producing an
options appraisal which will consider the options for housing delivery
including potential specialist accommodation / care in partnership with
HSCP;
• Hubnorth are appointed to produce an options appraisal for Killarow
House, Bowmore, Islay and a preliminary site investigation has been
completed.  The options appraisal will explore potential housing re-
development and or reuse options of the building and site, and the
potential to facilitate further development land to the rear.
• Hubnorth are producing an options appraisal for Lorn House, Oban
which is currently unoccupied.  This will explore housing re-use and
redevelopment options for the building and site.
• Progress is being made at Rothesay Academy in terms of agreeing a
route to demolish the building which will facilitate housing
redevelopment potentially in partnership with Fyne Homes.  Funding
options are currently being explored to finance the demolition and site
clearance. 
National House Builder Liaison 
4.12 Officers continue to engage directly with National House builders to discuss
their strategic plans and what opportunities there are to unlock development
and how the Council can assist. 
Facilitating Existing Constrained Housing Sites 
4.13 The Officer Housing Group is exploring detailed proposals to overcome
infrastructure impediments at Glencruitten, Oban and Kirkton Farm, Cardross. 
When finalised, these proposals may involve Council intervention through
land acquisition and or delivery of infrastructure utilising the Housing
Infrastructure Fund. 
Funding of Housing Emergency Project Officer 
4.14 The Council has approved the funding of a Project Officer for an initial three
year period.  This officer will be a property professional based in Commercial
Services, but will be focused on assisting delivery of housing related projects,
including but not limited to those outlined above in paras. 4.10 and 4.13 as
agreed at Policy and Resources Committee on 15th February 2024.   
RSL Partnership Working To Deliver Housing Land 
4.15 The Council continues to work with RSLs to unlock new housing development
sites and lever in funding.  The Council is working with RSL partners on many
other sites as explained in the Council’s Strategic Housing Investment Plan. 
Page 164

Page 165

In total the Council has granted planning consent for 223 houses between
June and November of 2023. 
Establishing Better Evidence For Decision Making: 
4.16 A Community Planning Survey was carried out as part of the work to refresh
the Local Outcome Improvement Plan.  A survey of local residents identified
that Housing is seen as the second priority behind improved transportation for
our communities.   The Argyll and Bute Outcome Improvement Plan 2024-34
will identify where the Community Planning Partnership could be most
effective at making a difference for communities facing housing inequalities 
4.17 To inform the considerations and ouput of the Housing Emergency Summit,
an extensive online household survey was carried out in October 2023 which
received 688 responses by residents and community groups.  This provides
essential evidence for actions going forwards.  Key headlines of this survey
are summarised below: 
Page 165

Page 166

4.18 Consultants are due to complete specialist legal, planning and chartered
surveyor advice regarding the application of occupancy controls through
different legal mechanisms.  This will support any potential choice to apply
requirements for housing to be restricted to primary occupancy as opposed to
holiday homes or short term letting, and or other obligations in terms of local
key workers and or affordability. 
4.19 During the Autumn of 2023, consultants have surveyed our Island
populations, and analysed the Island private housing market to establish a
clear definition and identification of Market Failure. Initial draft findings are
that:
• Island communities face unique challenges in delivering enough housing
to meet local need and demand. Capital build costs (including
infrastructure costs) are considerably higher, and land values lower,
meaning that the traditional private sector led model of housebuilding
Page 166

Page 167

does not occur and no speculative housing development takes place on
the islands.
• A lack of affordable housing is one of the most pressing issues facing
island communities. This is particularly problematic in terms of attracting
and retaining people to live and work on the islands and sustaining a
virtuous cycle of economic activity. Indeed, a survey conducted by
Highlands and Islands Enterprise found that for many parts of the region,
strong economic growth prospects are endangered by a lack of
affordable housing of all tenures. 
• A range of recommendations are made which include direct public
interventions to address the identified market failure.  When the report is
finalised, it will be reported to the EDI Committee along with output from
the Housing Summit Action Programme, and ultimately will be
incorporated in to the LHS Action Programme later this year. 
Rural Housing Body Status 
4.20    The Council was awarded Rural Housing Body status on 29th November
2023.   Doing so gives the Council the ability to apply Rural Housing Burdens
to properties it has constructed, purchased, or consented. As part of the
revised LHS Action Programme, officers will develop proposals for how Rural
Housing Burdens will be used.   
Home Argyll Changes 
4.21 Changes to the HOMEArgyll common allocations policy made in the Autumn
of 2023 are now in effect.  Although at an early stage they are beginning to
have an effect in terms of more flexibly supporting the allocation of RSL
properties to homeless applications in areas of highest need.   
Planning Policy Changes 
4.22 A report will be presented to March / April PPSL which will: 
• map out a timetable for explore the options for designation a short-term
let control area/s for all, or parts of the planning authority’s area;
• present a revised Technical Planning Note in support of NPF4 and
LDP2, providing updated guidance on affordable housing delivery
including its retention in perpetuity and accommodating key workers for
consideration by Members; and
• present a draft Technical Note in support of NPF4 and LDP2, that will
provide guidance on how we ensure housing is delivered to meet the
local housing need as identified by the Housing Needs and Demand
Analysis, including potential occupancy restrictions for consideration by
Members. 
Page 167

Page 168

Revised Road Guidelines
4.23 Officers have been working on a consolidated Roads and Transportation
Guidelines document.  This will provide a comprehensive and crucially more
flexible set of guidelines for developers and will be a key element of
addressing concerns expressed since declaring the Housing Emergency. 
This will be presented to members before the end of the year.   
Worker Housing 
4.24 The Council has been granted planning consent and roads construction
consent for twelve 2 bedroom cottage flats on a site owned by the Council at
Rockfield Road, Tobermory.  A contract to carry out the infrastructure works
for the site (road and services) is out to tender and it is planned to be
appointed by 31st March 2024 so that construction can be completed during
2024/25. This will be funded by Rural and Island Infrastructure Funding,
supported by the Strategic Housing Fund if required as a contingency. 
4.25 An Outline Business Case has been submitted for Rural Growth Deal Funding
to deliver the first block of four 2 bedroomed flats, which will be used as
worker accommodation.  The Council is working in partnership with MICHT
and it is the intention MICHT will act as managers of the premises. 
4.26 The Strategic Housing Fund is being used to resource HubNorth and SFT to
develop an options appraisal which will help to identify the exact operating
model of this block, and how the remainder of the site should be delivered. 
4.27 The Council has additionally agreed £460k from the Strategic Housing Fund
to support short term delivery of housing for HSCP workers on Tiree, Coll and
at Connel.  This will deliver up to 5 properties being brought back in to use to
support lifeline services in remote areas. 
Strategic Development Frameworks 
4.28 The Council has agreed to allocate £450k of its priorities funding to support the
development of Strategic Development Frameworks for Oban and Helensburgh
which will plan for future development over a 20-40 year time period. 
Production of these is a complex task, but is essential to delivering planned
infrastructure investment, land release, and the resultant population growth.  It
will also be a key part of addressing the Housing Emergency ultimately enabling
the delivery of housing at scale. 
Holiday Homes / Short Term Lets  
4.29 The Council implemented a Short Term Let Licensing Scheme in October 2023. 
To date there have been 2928 licenses applied for.  Officers have begun work on
analysing this information, including mapping it, so that we can begin to
understand the geographical spread and differences in types of accommodation. 
This will allow us to feed evidence in to decision making on potential short term
let planning control areas.
Page 168

Page 169

4.30 The Council has committed to increase the Council Tax to 200% on second
homes.  It is anticipated this will have make some contribution to preventing a
further increase in the number of second homes and may assist in bringing some
of those homes back into use for primary occupancy.   
Empty Property 
4.31 In November 2023, Council agreed a new approach to Empty Property Rates
Relief and the creation of a two year Empty Business Property Officer post. 
Officers are developing a Business Grant Scheme.   It is hoped that this work will
encourage the reuse / redevelopment of empty property, some of which may
include conversion to residential use. 
4.32 The expanded Housing Service Empty Property Team is now working closely with
the HSCP to target properties for their use.  The team have brought 15 residential
properties back into use between April and December 2023. 
Community Housing Development 
4.33 Officers are working with Communities to support their own delivery of housing. 
A regular forum of Community Housing Trusts has been formed to facilitate best
practice and learning of experiences. A tool kit has been created to support
communities in demonstrating their own localised housing needs, which is
crucial for drawing in funding. 
4.34 The Strategic Housing Fund has directly supported delivery of community
housing on Colonsay by granting a loan to bridge a funding gap that emerged
due to increased construction costs.  Officers continue to work with Colonsay
Community Development Trust to ensure the project is completed successfully
and officers are continuing to work with the Trust to support this project 
Settlement Project Support Officer 
4.35 The Council’s Settlement Project Support Officer continues to work in
collaboration with the Settlement Officers in the Western Isles and Northwest
Highland, as well as colleagues from Argyll and Bute Council, HIE, and the
Scottish Government Islands Team to recognise the place-based barriers to
population retention and attraction and support measures to address population
decline.   
4.36 The Settlement Project Support Officer is assisting Housing colleagues to drive
forward works on the Council’s Housing Emergency. This has included
supporting the completion of the Addressing Depopulation Action Plan funding
application of £60k. This application is intended to help address the shortage
of housing and encourage repopulation across Argyll and Bute, through a
pathfinder ‘Private Sector Housing Officer post’. This post will help support
private property owners to transition property from short term lets, holiday
homes and or empty property in to primary home occupancy.  The outcome of
Page 169

Page 170

this funding application has not yet been announced but it is expected in
March 2024, with the fund operational from April 2024. 
4.37 Other completed and planned activity of the Settlement Officer is detailed at
Appendix 2. 
5.0 CONCLUSION 
5.1 Since the Council’s declaration of a Housing Emergency, considerable activity
has been focused on exploring new methods and solutions to tackle the
housing shortages, and to bring renewed focus to delivering business as usual
in an accelerated fashion.  A Housing Summit has been held and work is
ongoing to develop an Action Programme.  Research has been commissioned
and draft reports have been received.  Policy changes are being developed and
will be presented to members shortly.  Housing site delivery and overcoming
impediments to delivery is being prioritised.  Many of these actions are
preliminary actions and officers will report further progress as it occurs and as
the LHS Action Programme is revised later in the year. 
6.0 IMPLICATIONS 
6.1  Policy  - The ongoing activity is consistent with current Council priorities and
the Local Housing Strategy vision and outcomes which are directly aligned
with the overarching objectives of the Outcome Improvement Plan, in
particular Outcome 2 – we have infrastructure that supports sustainable
growth. 
6.2  Financial - None directly arising from this report but future housing delivery
actions will require additional funding at some stage from the Council and our
partners if delivery is to be accelerated. 
6.3   Legal – None.   
6.4    HR – None.   
6.5   Equalities (Fairer Duty Scotland) - The activity outlined in the report is
consistent with aims and objectives set out in the local housing strategy, which
is subject to an EQESIA.
6.5.1  Equalities – Protected Characteristics - There are targets set within the SHIP
to deliver housing which meet the needs of specialist groups.
6.5.2  Social-Economic Characteristics - The delivery of affordable housing across
Argyll and Bute facilitates socio-economic opportunities for all. The SHIP links
with the Child Poverty Strategy.
6.5.3  Islands - The delivery of affordable housing across Argyll and Bute facilitates
socio-economic opportunities for all. The SHIP links with the Child Poverty
Strategy.
6.6  Risk - The Housing Needs and Demand Assessment process takes full
account of housing need on the islands.
Page 170

Page 171

6.7  Climate Change – New housing in the right location helps reduce carbon
outputs particularly when heating is provided using renewable energy and
utilising high standards of insulation which can also be applied to existing
stock. 
6.8  Customer Service – None. 
6.9 Rights of the Child (UNCRC) – None.   
Kirsty Flanagan, Executive Director with Responsibility for Development and
Economic Growth 
Councillor Robin Currie, Policy Lead for Strategic Development 
February 2024 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth   
Fergus.Murray@argyll-bute.gov.uk 
Matt Mulderrig, Development Policy and Housing Manager
Matt.Mulderrig@argyll-bute.gov.uk 
Douglas Whyte, Team Lead – Housing Strategy
Douglas.Whyte@argyll-bute.gov.uk   
APPENDICES 
Appendix 1 – Housing Emergency Summit Report 
Appendix 2 – Settlement Officer Detailed Activities Update  
Page 171

Page 172

This page is intentionally left blank

Page 173

Donna Milton (MCIH)
Managing Director 
Elaine Byrne (CPFA)
Director of Housing Consultancy 
Argyll & Bute Council
Housing Emergency
Summit Report
February 2024
Page 173

Page 174

Argyll & Bute Council
Housing Emergency Summit 
Table of Contents
1 Introduction .............................................................................................................................. 3
2 Background to Housing Emergency Summit ............................................................................ 5
2.1 Call to Action: Building a Bold and Progressive Emergency Response ............................. 7
2.2 Pre-Summit Housing Emergency Workshops ................................................................... 8
3 Housing Emergency Summit Programme ................................................................................ 9
3.1 The Housing Emergency Response: Scoping Solutions ................................................. 10
4 Housing Emergency Responses: Option Appraisal ................................................................ 12
4.1 Workshop 1: Enabling the Delivery of More Market Homes in Argyll & Bute ................... 12
4.2 Workshop 2: Enabling the Delivery of More Affordable Homes in Argyll & Bute .............. 17
4.3 Workshop 3: Enabling the Delivery of More Homes for Argyll & Bute’s Workforce .......... 21
4.4 Workshop 4: Making the Best Use of Existing Homes in Argyll & Bute ........................... 26
5 Housing Emergency Partner Pledges .................................................................................... 32
6 Housing Emergency Summit Outcomes & Next Steps ........................................................... 33 
Appendix 1: Housing Emergency Summit Attendance List
Appendix 2: Housing Emergency Summit Event Presentation
Appendix 3: Partner Pledge Matrix 
Arneil Johnston
Falkirk Business Hub
45 Vicar Street
Falkirk
FK1 1LL
Page 174

Page 175

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 3
1 Introduction
In June 2023, Argyll and Bute Council declared a Housing Emergency due to the acute shortage of
housing in the area. This emergency is driven by a complex range of issues including rising house
prices and rents, reducing household incomes, growing construction costs, a drop in the number of
new homes being built, a shrinking private rented sector and a local population which is both ageing
and declining. The scale of housing shortage and housing system pressure evident in Argyll & Bute
is illustrated by the following statistics: 
Declaring a housing emergency in Argyll & Bute is a call to action for government, public bodies and
partners. It is intended as the catalyst to bring partners, stakeholders, investors and communities
together to prioritise and commit to the collective action needed to tackle housing shortage. The
Council are fully committed to working with partners to programme a broad range of activities, both
in the short term and long term, to target this collective action where it is needed most. 
To build and harness this collective action, a Housing Emergency Summit was held on Monday 27th
November 2023 at the SAMS Campus, Oban. The purpose of the Summit was to bring partners
together to forge commitments aimed at tackling housing shortage by maximising resources,
pursuing innovation, coordinating planning and targeting delivery capacity. Delegates attending the
Emergency Housing Summit included:
• Senior decision makers in local and national public sector bodies including the NHS, Scottish
Futures Trust and Highland & Islands Enterprise
• Senior decision makers in Argyll & Bute Council
• Housing developers both commercial builders and Housing Associations
• Representatives from the Community Housing Network
• Local business leaders and funding bodies
• Third sector organisations and support agencies.
The Housing Emergency Summit was designed to focus partnership activity on prioritising and
programming emergency responses across the following four themes:
Page 175

Page 176

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 4 
Summit delegates were presented with background information on the extent and nature of housing
shortage, as well as potential solutions and interventions. Appendix A provides full details of the
stakeholders who attended and participated in the Summit programme. In total, 92 delegates
attended and participated in the Argyll & Bute Housing Emergency Summit. 
This report details the outcomes of Summit activity including the shortlisting and appraisal of
housing emergency responses and the collective partnership pledge to act on each response.
Page 176

Page 177

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 5
2 Background to Housing Emergency Summit
In advance of the Housing Emergency Summit, extensive analysis was prepared to evidence the
extent and nature of the housing emergency in Argyll & Bute and to detail current planning and
activity underway to tackle housing shortage. Partners were invited to explore this evidence and
consider the extent of action and innovation needed to develop an appropriate emergency response,
by engaging with the following interactive briefings:
https://youtu.be/YHGcGm92ZDs?si=CSm6Pof609hwd02W
https://youtu.be/0f0uNOFmsls?si=o3DSX8SOIF_-vl2P
https://youtu.be/pl9-GMWbqeI?si=o01q2eask_uOdF3Z
https://youtu.be/1Q37pQq62JQ?si=g4z6ROZfxKjwPO9e
Briefings detailed the scale and complexity of housing emergency across each of the four Summit
themes, stressing the need for brave and bold emergency responses to the following key issues: 
Page 177

Page 178

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 6 
Furthermore, to identify and evidence the action that local communities and residents would prioritise
to tackle housing shortage, an extensive online household survey was launched in October 2023,
promoted across the Council’s social media channels. To inform how the housing emergency should
be tackled, the survey was intended to gather the views of local households enabling better
understanding of how housing shortage affects their lives, livelihoods and communities. In total, 688
responses were provided by residents and community groups, providing essential evidence to be
considered by delegates at the Housing Emergency Summit. Key headlines of this survey can be
summarised as follows: 
Page 178

Page 179

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 7 
2.1 Call to Action: Building a Bold and Progressive Emergency Response
The housing emergency response arising from the Summit should build on the ambitious action plan
currently under delivery within the Argyll & Bute Local Housing Strategy, as well as the work
underway nationally to tackle housing shortage in rural areas.
National activity includes the recently published Scottish Government Rural and Islands Action Plan.
The Plan sets out a range actions to improve access to high quality affordable and market housing,
enabling rural communities to live, work and thrive. The action plan includes:
• the delivery of 11,000 affordable homes in rural communities
Page 179

Page 180

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 8
• a £30M Rural and Island Housing Fund for community led housing, and £25M rural affordable
homes funding for workforce housing
• new local authority powers to apply higher Council Tax rates for second homes, plus the
extended use of rural housing burdens and reform to compulsory purchase legislation. 
At a local level, the Argyll and Bute Local Housing Strategy outlines the vision and investment
priorities for tackling housing need between 2022 and 2027, including:
• the delivery of 1,000 affordable homes over the next 5 years
• workforce housing projects in Tobermory and Bowmore, 
• community-led housing models in Colonsay, Ulva, Ulva Ferry and Gigha
• the creation of a Rural Housing Body to enable the use of rural housing burdens
• plans for short term let control zones 
• doubling the Council Tax on second homes.
Despite the opportunity and proactive local response, the call for action inspired by the Housing
Emergency declaration acknowledges that the Council and partners need to go further to tackle the
scale of housing shortage faced by local communities. As a result, the Summit called for partners to
take bold and progressive action, inspiring extraordinary responses to an extraordinary challenge. 
2.2 Pre-Summit Housing Emergency Workshops
To ensure that the Summit focused on the collective action partners must take to tackle housing
shortage, delegates were invited to attend a programme of pre-Summit workshops focusing on each
Housing Emergency theme. The focus of each workshop was to assess the barriers to tackling
housing shortage and to generate ideas on potential solutions and interventions to increase supply. 
Partners worked together to identify and assess housing emergency responses and interventions,
defining a long-list of ideas and options. This options list formed the basis of scrutiny and option
appraisal at the Emergency Housing Summit.
This approach ensured that the Housing Emergency Summit was firmly focused on building a
collective response to the housing emergency in Argyll & Bute, not simply debating the issues that
have caused it.
Page 180

Page 181

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 9
3 Housing Emergency Summit Programme
The purpose of the Housing Emergency Summit was to bring partners together to forge
commitments aimed at tackling housing shortage which maximise resources, pursue innovation,
coordinate planning and target delivery. The Summit event was therefore structured around the
nature of the emergency response needed, critically appraising solutions to ensure that only the
most impactful and deliverable action is prioritised for delivery. The aim of the Summit was to enable
partners to pledge commitment to delivering housing emergency actions and to enable the delivery
of an action plan aimed at tackling housing shortage. 
The programme for Housing Emergency Summit was as follows: 
Appendix B provides a full Housing Emergency Summit presentation materials detailing all plenary
sessions.
The Summit commenced with introductions from the Leader of Argyll & Bute Council (Councillor
Robin Currie) and from the Council’s Head of Development and Planning (Fergus Murray). Opening
remarks detailed evidence of housing shortage, its impact on Argyll & Bute’s community and
economy, and a call to collective action to build bold emergency responses and progressive
partnership groups.
Opening remarks were followed by a panel session led by partners from Scottish Futures Trust, the
Scottish Building Federation, Highlands and Islands Enterprise and Shelter Scotland, who provided
perspectives on the housing emergency and suggestions on the extent and nature of emergency
action that should be prioritised. 
Summit delegates were then invited to test with whether emerging responses should be ‘on the table’
or ‘off the table’ as an initial reaction test to a sample of the options defined in pre-Summit workshops.
Informed by this, a programme of interactive session were then facilitated where delegates were
asked to systematically assess a long list of options generated to tackle the housing emergency
across each of the four Summit themes. Each workshop involved shortlisting the most valuable
emergency response options and then carrying out an interactive option appraisal to assess the
extent to which each would be impactful and deliverable. Four interactive workshops were hosted
simultaneously across two rounds, enabling all delegates to participate in two interactive option
appraisals. The outcome of this option appraisal was the creation of a set of housing emergency
action lists for each of the four Summit themes.
Page 181

Page 182

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 10
The final session of the Housing Emergency Summit involved asking partners to pledge commitment
to tackling the housing emergency in Argyll & Bute by considering each emergency response action
and pledging delivery support where appropriate. During this networking session, partners were
urged to review the list of fellow delivery partners and make introductions and connections across
fellow ‘emergency responders’ as the first stage building partnership networks aimed at tackling
Argyll & Bute’s housing emergency.
3.1 The Housing Emergency Response: Scoping Solutions
Following initial plenary sessions, delegates were asked to consider emerging housing emergency
responses to determine which should be prioritised for inclusion within a Housing Emergency Action
Plan. Using an interactive polling system, delegates were asked whether each emergency response
should ‘on the table’ or ‘off the table’ in the strategic plan to tackle housing shortage.
The sample of solutions under consideration was generated across each of the four pre-Summit
workshops and represented some of the most popular ideas emerging from the debates. The
outcome of this initial reaction test was intended to assess the appetite for action across a range of
delivery agendas and to gauge the extent of partner consensus on priorities for action.
The outcome of the interactive voting session was as follows: 
Table 3.1: Interactive polling outcomes for Housing Emergency Scoping Solutions session
A majority of partners suggested that every housing emergency response should be ‘on the table’,
with the top 5 most popular action points identified as follows:
• Dramatically increase the number of college places for construction skills development in Argyll
& Bute
• Pursue a more flexible approach to infrastructure, roads and design requirements in rural and
island housing developments
• Pursue modern methods of construction to boost affordable housing delivery
Proposed Housing Emergency Solution On the
Table
Off the
Table
Pursue a more flexible approach to infrastructure, roads and design requirements in rural
and island housing developments 98% 2%
Dramatically increase the number of college places for construction skills development in
Argyll & Bute 100% 0%
Deliver self-build plots and mortgages 86% 14%
Freedom to use Scottish Government housing funding more flexibly and as an allocation
with local administrative control 92% 8%
Create a ring-fenced Infrastructure Fund for housing development 90% 10%
Pursue Council funded housing development of low-cost homes for rent or sale 79% 21%
Support mixed tenure community led housing development through asset transfer and
delivery support 77% 23%
Pursue modern methods of construction to boost affordable housing delivery 94% 6%
Deliver more MMR and low-cost homes for sale via the SHIP 91% 9%
Deliver short term workforce housing options including modular, temporary and tiny 73% 27%
Extend the use of rural housing burdens across Housing Market Areas in Argyll & Bute to
maintain primary occupancy and or affordability 92% 8%
Pursue Short Term Let control areas 66% 34%
Lobby the Scottish Government to create a private sector duty for large development
projects to invest in workforce housing 66% 34%
Page 182

Page 183

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 11
• Freedom to use Scottish Government housing funding more flexibly and as an allocation with
local administrative control
• Extend the use of rural housing burdens across Housing Market Areas in Argyll & Bute to
maintain primary occupancy and or affordability.
Partners were particularly supportive of options which focus on boosting construction industry
capacity, protecting homes as ‘principal residencies’ and enabling more flexibility in the planning
and delivery of new build homes. 
Housing emergency solutions which were raised by partners but required further discussion to take
forward included: 
• Pursue Council funded housing development of low-cost homes for rent or sale
• Support mixed tenure community led housing development through asset transfer and delivery
support
• Deliver short term workforce housing options including modular, temporary and tiny homes
• Pursue Short Term Let control areas
• Lobby the Scottish Government to create a private sector duty for large development projects
to invest in workforce housing.
The final two solutions, focusing on Short-term Let controls and private sector housing contributions,
show the greater hesitation of partners in balancing the needs of the housing system in Argyll & Bute
with needs of the local economy.
Overall, this polling exercise offered positive evidence of the appetite to pursue bold interventions in
tackling housing shortage in Argyll & Bute, and gave a good indication of the extent of partner
consensus to drive new delivery partnerships. Following this initial reaction test, partners were then
invited to join interactive breakout workshops to prioritise and then systemically appraise the long
list of options defined to tackle housing shortage under each of the four housing emergency themes.
Page 183

Page 184

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 12
4 Housing Emergency Responses: Option Appraisal
As the Housing Emergency Summit was focused on a call to action to tackle housing shortage, the
main purpose of the event was to bring expert partners together to systematically assess and agree
the key activity that should be prioritised as the basis of Argyll & Bute’s emergency response. To
ensure that Summit discussion focused purely on the need for action, four pre-Summit partner
workshops were held to discuss the extent and nature of housing emergency, the barriers to tackling
housing shortage, and the ideas and options which should be considered to overcome these barriers.
Each workshop was attended by subject matter experts, with the outcome of each, a long-list of
ideas and options for tackling the housing emergency.
The Summit option appraisal sessions were designed to shortlist from this bank of options ensuring
that a focused and manageable action list was defined which could then be subject to more detailed
option appraisal. Using option appraisal techniques, each option was subject to outcome analysis,
appraising both the scale of impact which could be achieved and its potential deliverability. The
outcome of this appraisal was to define the most deliverable and impactful options in tackling housing
shortage. These options were then prioritised as the basis of a partner pledge exercise where
delegates, committed to supporting delivery and influencing change, would come together to commit
their time, expertise and other resources to the implementation of each.
At the outset of each option appraisal workshop, delegates were asked to review the long list of
options generated at pre-Summit workshops, working together to define whether options should be
‘in-scope’ or ‘out of scope’. ‘In scope’ options would then be plotted on a matrix to assess the extent
to which they were most or least deliverable (on the x-axis) and high or low impact (on the y-axis).
Options which were considered to be both high impact and most deliverable were elevated for
consideration by partners for inclusion within the Housing Emergency Action Plan.
Delegates were given the opportunity to attend at two of the four interactive sessions, with two
rounds of activity held across four workshops running simultaneously. The outcomes of each option
appraisal session are detailed below.
4.1 Workshop 1: Enabling the Delivery of More Market Homes in Argyll & Bute
Partners in Workshop 1 began the session by critically assessing the long-list of options identified to
enable the delivery of more market homes in Argyll & Bute. The in-scope/out scope exercise defined
a clear shortlist of options with both Group 1 and 2 unanimously agreeing that they should be
considered for inclusion within a more detailed option appraisal analysis. In scope options were seen
as instrumental in overcoming delivery barriers to increasing speculative building in the area, with
the need for more rural-centric planning regulations, infrastructure funding, construction training and
Council capacity to progress planning approvals, seen as key interventions in achieving this.
Partnership activity to develop funding and investment models which could manage risk and enable
infrastructure delivery, were also seen as essential as were the wider use of rural housing burdens
on new build homes.
Full details of the ‘in-scope’/’out scope’ exercise, including partner rationale for each assessment is
set out in Table 4.1 below:
Page 184

Page 185

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 13
Workshop 1 Option List In Scope Out of
Scope Scoring rationale
Implement a more flexible approach
to infrastructure, roads and design
requirements on (rural) development
sites
IN IN
Both groups unanimously agreed that this option was a major priority given the planning
constraint barriers that are delaying and sometimes precluding development. Wording
changed to ‘implement’ by Group 1 (accepted by Group 2). Also removed reference to 'rural'
sites as this could apply to any development in Argyll & Bute
Assemble credible evidence of
housing demand and affordability to
build funder and developer
confidence
OUT IN
Priority for Group 2 as this was seen as a foundation action which would be essential in
enabling developer confidence. Group 1 viewed this as a business as usual activity which
could be usefully integrated into the LHS
Increase capacity within Council
services key to housing development
inc. Planning, Roads, Building
Standards
IN IN
Major priority for both Groups and seen as a major factor in addressing development
approval delays - "This is the big problem, solve this and that's half the battle", "There's no
continuity, you deal with one officer and then they're unavailable and then you're starting
from scratch with someone else", "We need to be creative with the recruitment offer we
make - if that needs to include accommodation, then that's what should be offered"
Dramatically increase the number of
college places for construction skills
development in Argyll & Bute
IN IN
Seen as having a major impact on enabling more market supply by both groups but not a
short term solution to the emergency faced. Nevertheless, this is a crucial action to build
sustainability in the local construction industry longer term, and needs to be pursued
Use the CITB Impact Fund to enable
industry-led solutions to stimulate
development
OUT OUT
Low level priority for both groups - The scheme is seen as being very challenging to access
and unlikely to have the scale of impact needed
Include SEPA and Nature Scotland
as pre-planning application
consultees as standard
OUT IN
Priority for Group 2. Group 1 would simply add SEPA and Nature Scot into the statutory
consultees who will collaborate in the proposed Construction Forum
Implement a Rural & Island Housing
Standard including specific
infrastructure, roads and design
standards
OUT OUT
Popular in both Groups (this is perceived as a major barrier to market development) but
seen as duplication of first option on implementing a more flexible approach to development
requirements 
Create an empowered Construction
Forum bringing together all planning
consultees to speed up approvals
IN OUT
Group 1 viewed this option at having much potential in "creating a culture which is 'will do'
towards development and crucial in forging relationships that will speed up the development
approval process. Seen by Group 2 as 'yet another planning group?' 
Page 185

Page 186

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 14
Create a list of stalled developed
sites for consideration by a Housing
Delivery Task Force
OUT OUT
Group 1 viewed this option as 'business as usual' ("is this not precisely what the housing
land process should be doing?"). Group 2 saw this option as useful foundation activity to
drive better collaboration in seeking development approvals and merged both options
Map development opportunities
where capacity is greatest and create
a list of stalled development sites
OUT IN
Develop funding and risk sharing
models to enable infrastructure
investment in housing sites
IN IN
Seen by both Groups as having major potential in unlocking development constraints, with
SFT and Scottish Government support to blend funding sources and create partnership
development agreements seen as crucial
Repurpose vacant spaces/derelict
buildings to deliver affordable and
low cost homes for sale
IN IN
Both Groups unanimously agreed this option should be in scope as it has the potential to
deliver a stronger impact than new build development. This is in relation to cost, unit
numbers and environmental impact.
Compel utility companies to complete
Island Community Impact
Assessments on infrastructure plans
OUT OUT
Perceived as useful but unlikely to have major short-term impact on the scale of emergency
faced. Group 1 suggested that the inclusion of utility companies within a collaborative
construction forum could encourage a shift to this practice 
Use rural housing burdens and
RDG/PSRF funding enabling
developers to offer principal homes
at a fixed price
IN IN
Seen as a useful mechanisms by both groups in de-risking speculative development and
also ensuring new build units are retained as principal homes
Create supplementary planning
guidance to bring forward sites for
speculative building not allocated in
the LDP
IN IN
In-scope for both Groups with high levels of support from market developers. Given the
development cycle associated with LDP timescales, this option would enable identified sites
to be released for speculative development
Deliver self-build plots and
mortgages OUT OUT Seen by both groups as useful but with a limited impact on the housing emergency
response in the short term 
Council grants to fill the gap between
new build prices and mortgage
affordability
IN OUT
Group 1 viewed this option as in-scope and as a useful approach in building developer
confidence and enabling the delivery of principle homes. Group 2 however questioned its
value - "if the problem we're facing is a lack of speculative development, then how will
offering mortgage support help? People don't need a mortgage on homes that aren't being
built in the first place"
Page 186

Page 187

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 15
Council under-writing or pre-
purchase of private speculative
market housing in remote rural areas
IN OUT
Group 1 viewed this option as in-scope and as a useful approach in building developer
confidence and enabling the delivery of principal homes. Again, Group 2 questioned its
value as a catalyst for more speculative development 
Table 4.1: Workshop 1 ‘In Scope’/’Out Scope’ options for Enabling the Delivery of More Market Homes in Argyll & Bute
Each Group then used ‘in-scope’ options to assess the extent to which suggested actions were both impactful and deliverable. The outcomes of this
impact exercise is detailed below:
Page 187

Page 188

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 16 
Page 188

Page 189

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 17
Using the outcomes of the option appraisal session, and focusing on actions screened as having the
potential to be both impactful and deliverable, a list of actions was developed as the basis of
developing the Housing Emergency Action Plan to ‘enable the delivery of more market homes’ as
follows:
1. Implement a more flexible approach to infrastructure, roads and design requirements on
development sites
2. Increase capacity within Council services key to housing development inc. Planning, Roads,
Building Standards
3. Dramatically increase the number of college places for construction skills development in Argyll
& Bute
4. Develop funding and risk sharing models to enable infrastructure investment in housing sites
5. Repurpose vacant spaces/derelict buildings to deliver homes for sale or rent
6. Use rural housing burdens and RDG/PSRF funding enabling developers to offer principal
homes at a fixed price
7. Create supplementary planning guidance to bring forward sites for speculative building not
allocated in the LDP
8. Create an empowered Construction Forum bringing together all planning consultees to speed
up decision making.
4.2 Workshop 2: Enabling the Delivery of More Affordable Homes in Argyll & Bute
Partners in Workshop 2 began the session by critically assessing the long-list of options identified to
enable the delivery of more affordable homes in Argyll & Bute. The in-scope/out scope exercise
defined a clear shortlist of options with both Group 1 and 2 unanimously agreeing that they should
be considered for inclusion within a more detailed option appraisal analysis. 
In scope options were seen as instrumental in overcoming delivery barriers to Strategic Housing
Investment Plan delivery, including improving infrastructure planning, planning policy and master-
planning development and more flexibility in funding management. Enabling the delivery of more
community led housing and intermediate housing projects were also identified as important delivery
activities.
Full details of the ‘in-scope’/’out scope’ exercise, including partner rationale for each assessment
are set out in Table 4.2 below:
Page 189

Page 190

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 18
Workshop 2 Option List In
Scope
Out of
Scope Scoring rationale
Develop collaborative funding models
which achieve scale and a long-term
affordable housing pipeline
IN OUT Group 1 agreed that there was a need to test further innovative funding mechanisms to
enable more affordable homes to be built but scored it as least deliverable as part of the
matrix. Partners in Group 2 did not include this within scope as it was suggested that the
issue was more to do with land assembly and testing this option would not produce fast
results. 
Create standard housing design types to
speed up procurement and planning
approvals
IN IN Consensus in both Group 1 and 2 that the development of standard housing types could
help deliver change and speed up procurement and planning processes. It could fast-track
design stages and is proven to work in the private sector so therefore is deliverable. 
Create procurement frameworks across
affordable developers with support for
SME engagement
OUT OUT Group 1 felt that procurement frameworks were already in place and barriers were as a
result of contractors choosing to tender for more profitable sites (in the central belt). Group
2 agreed that it would be difficult to change legislation and barriers were more about
contractor appetite.
Create a ring fenced infrastructure fund
for Argyll & Bute similar to the Highland
Council model
IN IN Both Group 1 and 2 agreed this would provide more flexibility and target resources.
However, it was noted that the Ring Fenced Budget was not always successfully
implemented in Highland Council. It was also highlighted in Group 2 that the Scottish
Housing Fund could be applied more flexibly. 
Improve infrastructure planning across
agencies with more flexibility in planning
requirements for rural sites
IN IN Both Group 1 and 2 noted that one of the greatest obstacles was lead in times for
infrastructure and agreed a more collaborative approach across agencies could
significantly improve timescales. 
Pursue modern methods of construction
for affordable housing and assess
feasibility of developing a modular factory
IN OUT Majority of partners in Group 1 felt that modern methods were being piloted with lessons
still to be learned, therefore there is a degree of risk with this activity. Group 2 stated that
there would be difficulties in the short to medium term to find a site and base a factory in
Argyll & Bute. There were mixed views in Group 2, particularly from the Modular
Construction Sector asserting that this action could have a significant impact on delivery. 
Create an outcome focused planning
system and culture across consultees to
increase affordable completions
IN IN Both Group 1 and 2 were in favour of a more collaborative outcome focused approach to
avoid silo working and speed up processes. Group 1 thought that this would take longer to
deliver while Group 2 ranked this as both high impact and most deliverable. 
Freedom to use Scottish Government
housing funding more flexibly and as an
allocation with local administrative control
IN IN Both Group 1 and 2 agreed that more freedom to use SG housing fund could target
resources more to a local and community level but acknowledged it would require
legislative change which could be time consuming and less deliverable. 
Page 190

Page 191

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 19
Fast track the planning process for
affordable housing projects which support
economic growth and repopulation
initiatives
IN IN Both Group 1 and 2 agreed that in theory this could assist with delivery of more homes
with Group 1 suggesting it would be less deliverable than Group 2. Group 1 highlighted
that this activity could impact on the delivery of more market homes which were also
important 
Use Rural Housing Body status to enable
land assembly, master planning and
infrastructure investment
IN IN Partners in Group 1 and 2 agreed that as Rural Housing Body status has now been
confirmed by the Scottish Government, that this option should be taken forward as a key
priority to assist with land assembly.
Develop emergency planning policies
which tackle the housing crisis e.g.
exception policies, AHP contributions,
rural burdens
IN  IN Both Groups 1 and 2 agreed that there is a need to review all planning policies in the
context of the Housing Emergency declaration in Argyll & Bute to ensure they are targeted
at the delivery of more affordable homes and that gaps are identified and addressed. 
Create a revolving fund for Community
Housing Trusts to finance feasibility
studies and approval process
IN IN Partners in Group 1 and 2 who had been involved in Community-led Housing Models
agreed that a revolving fund could assist with scaling up the development of affordable
housing by Community Development Trusts 
Use Rural & Island Housing Fund to offer
professional support for Community
Housing Trusts 
IN IN Partners in Group 1 and 2 who have been involved in community-led development agreed
that funding for professional support could have a significant impact. However, both
Groups felt that the options for revolving funding and professional support should be one
activity. 
Support mixed tenure community led
housing development through asset
transfer and delivery support
OUT OUT Group 1 felt that the was already being delivered and Group 2 did not choose this to be in
scope. 
Deliver more MMR and low-cost homes
for sale via the SHIP
IN IN Agreed that this option was required, but that a requirement to evidence the demand for
MMR as an initial action is essential.
Evidence the demand for Mid-Market
Rent housing to enable an RSL
development pipeline
IN IN There was agreement that there was a need for more detailed analysis of the demand for
MMR to help inform future provision across Argyll & Bute. Both Group 1 & 2 agreed that
both options should be one activity with delivery building on a better understanding
demand. 
Develop a Joint Venture model for
Council Building for Rent and Sale
(CBRS) in partnership with market
developers
OUT OUT Neither Group 1 or 2 put this option in scope as partners considered it would take too long
to implement due to legal uncertainty and furthermore would be unlikely to work in Argyll &
Bute 
Page 191

Page 192

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 20
Table 4.2: Workshop 2 ‘In Scope’/’Out Scope’ options for Enabling the Delivery of More Affordable Homes in Argyll & Bute
Each Group then used ‘in-scope’ options to assess the extent to which suggested actions were both impactful and deliverable. The outcomes of
this impact exercise is detailed below: 
Page 192

Page 193

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 21
Using the outcomes of the option appraisal session, and focusing on actions screened as having the
potential to be both impactful and deliverable, a list of actions was developed as the basis of
developing the Housing Emergency Action Plan to ‘enable the delivery of more affordable homes’
as follows:
1 Create standard housing design types to speed up procurement and planning approvals
2 Create a ring fenced infrastructure fund for Argyll & Bute similar to the Highland Council model
3 Improve infrastructure planning across agencies
4 Freedom to use Scottish Government housing funding more flexibly and as an allocation with
local administrative control
5 Fast track the planning process for affordable housing projects which support economic
growth and repopulation initiatives
6 Use Rural Housing Body status to enable land assembly, master planning and infrastructure
investment
7 Develop emergency planning policies which tackle the housing crisis e.g. exception policies,
AHP contributions, rural burdens
8 Create a revolving fund for Community Housing Trusts to finance feasibility studies and
approval process
9 Use Rural & Island Housing Fund to offer professional support for Community Housing Trusts 
10 Evidence the demand for Mid-Market Rent housing to enable an RSL development pipeline.
4.3 Workshop 3: Enabling the Delivery of More Homes for Argyll & Bute’s
Workforce
Partners in Workshop 3 began the session by critically assessing the long-list of options identified to
enable the delivery of more workforce housing in Argyll & Bute. The in-scope/out scope exercise
defined a clear shortlist of options with both Group 1 and 2 unanimously agreeing that they should
be considered for inclusion within a more detailed option appraisal analysis. 
These options were seen as instrumental in overcoming delivery barriers to enabling the supply of
workforce housing including building evidence of housing need across employment sectors,
improving strategic planning, and supporting the delivery of short term, temporary and seasonal
workforce housing options. Creating opportunities for workforce housing via building reuse and Mid-
Market Rent delivery models were also identified as important delivery activities.
Full details of the ‘in-scope’/’out scope’ exercise, including partner rationale for each assessment
are set out in Table 4.3 below:
Page 193

Page 194

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 22
Workshop 3 Option List In Scope Out of
Scope Scoring rationale
Work with LAR Housing Trust to
increase the delivery of workforce
housing in Argyll & Bute
IN OUT Group 1 were keen to explore using the LAR model but noted this can also be delivered
by other agencies and providers
Assess potential of student
accommodation model and
nomination agreements to deliver
workforce housing
OUT IN Group 2 noted this type of model is not suitable for relocating families. Both Groups noted
they would like to see the delivery of more tied housing that is linked to employment
although that can create complexities when people change employer.
Deliver seasonal and temporary
workforce accommodation using short
term occupancy agreements
IN IN Both Groups felt this could free up permanent housing for full time residents. There is
currently no legal basis for Short Term Occupancy agreements in Scotland so this would
need a different mechanism. Pursuing this option would show there is demand for this
type of housing.
Develop a strategic approach to
evidencing the need for workforce
housing in the public sector
IN IN Group 1 emphasised the need to understand where the data gaps are, why this insight is
needed and who would use it, but acknowledged it does underpin all the other actions.
Lots of information is already available but perhaps not widely shared. Group 2 stressed
the need for Argyll & Bute specific evidence as this would help with funding bids. It was
suggested this activity is more about about continuing with the evidence gathering that
already exists rather than developing new data.
Develop an HMO partnership model
which enables employers to invest in
workforce housing units
OUT OUT Both Groups agreed that this is not a long term sustainable housing solution or a
desirable option for working age households.
Match empty home owners to
essential workers and provide interim
rent payments during improvement
period
OUT IN Group 1 suggested that this option would essentially reward owners who fail to invest and
maintain their homes. There are better uses for public sector funding
Deliver emergency workforce housing
options including the use of modular,
temporary and tiny homes
IN IN Group 1 were keen to remove the reference to temporary housing. Both Groups were
supportive of using the Glasgow Commonwealth Games approach where housing legacy
was created from temporary homes. This option requires fast track planning to work and
there would be a need to house construction workers first who can then build the rest.
Page 194

Page 195

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 23
Deliver a Council funded Mid-Market
Rent workforce housing programme
via powers to advance wellbeing
IN IN Group 1 noted this option should not just focus on Council funded development but use
wider partners. It was noted however that reduced subsidy levels could be detrimental to
this. Group 2 suggested that the demand for MMR is linked to market failure. We need to
understand and demonstrate clearly where there is demand. The LAR approach could be
considered as a delivery model.
Explore opportunities for public sector
organisations to use pension funds to
invest in workforce housing
IN OUT Group 1 noted that public and private sector organisations should be considered for the
use of pension funds. Group 2 observed that this option would be rating reliant. It was
suggested that funding is not the biggest barrier to delivery and that there are other
funding mechanisms available to support the delivery of workforce housing.
Create a rural resettlement fund to
enable households to relocate to
Argyll & Bute
OUT OUT Partners in Group 1 reported that this option had been tried and tested before and didn't
deliver the outcomes needed, in fact "it needs to be off the board completely". Group 2
partners also referred to a previous model which was considered too restrictive – “it
wasn't inter regional so didn’t support those wishing to move within Argyll & Bute”. Those
moving to the area needed to have a job offer before accessing support.
Map public sector land and buildings
which could provide workforce
housing via repurposing and change
of use
IN IN Partners suggested this option should consider not just public sector land and buildings
but private sector too and that it needs to be part of a wider master planning approach.
Land mapping is in progress in Argyll & Bute but needs completion. It should be noted
that there are positive climate change implications but that landfill costs/disposals may be
a barrier especially on islands.
Use the Partnership Support for
Regeneration Fund to enable private
sector workforce housing models
IN IN This mechanism currently exists but needs better promotion. Group 2 suggested that
there is a need for a better understanding of the capabilities and potential scale that could
be delivered from this funding scheme. It was noted that there is an example in the south
of Skye recently that would be worth reviewing but that it was likely that limited funds
would be available and sole use for workforce housing may be a barrier.
Reintroduce the Rural Home
Ownership Grant model for working
households in partnership with
Community Housing Trusts
IN IN Whilst supportive, Group 1 noted that this option would need to deliver a redesigned
scheme as previous versions were an ‘administrative nightmare’ and too restrictive. There
is a potential to pilot this model in Tiree and work with Crofting Commission. Group 2
asserted that a just reintroduction of RHOG was needed and could combine with local
housing burdens to safeguard affordable homes for working age households. 
Develop shared accommodation
models across public/private sector
employers via asset contribution and
investment funding
OUT IN Group 2 were supportive of this option noting it could maximise existing funding if
partners could blend from different sources.
Page 195

Page 196

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 24
Lobby the Scottish Government to
create a private sector duty for large
development projects to invest in
workforce housing
IN IN Whilst both Groups were supportive, Group 2 noted this option could stifle investment. It
should also be noted that employers are already interested in helping to solve the
problem so they can secure the workforce they need. Perhaps this option is more about
community benefit clauses attached to planning rather than a duty?
Develop a social enterprise company
focused on developing and
maintaining workforce housing
OUT OUT Partners suggested that the last thing needed is another group to be set up and
governed. RSLs already have powers to do this. 
Test market appetite for Build to Rent
models linked to the Rural Growth
Deal that could deliver workforce
housing
IN IN Whilst both Groups were supportive of this option, it was noted that this activity was
already progressing in Argyll & Bute
Unblock the ready to go sites stopped
as a result of infrastructure constraints
IN N/A This option was added as new workforce housing solution in the Group 1 workshop  Page 196

Page 197

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 25
Table 4.3: Workshop 3 ‘In Scope’/’Out Scope’ options for Enabling the Delivery of More Homes for Argyll & Bute’s Workforce
Each Group then used ‘in-scope’ options to assess whether suggested actions were both impactful and deliverable. The outcomes of this impact
exercise is detailed below: 
Page 197

Page 198

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 26
Using the outcomes of the option appraisal session, and focusing on actions screened as having the
potential to be both impactful and deliverable, a list of actions was developed as the basis of
developing the Housing Emergency Action Plan to ‘enable the delivery of more homes for Argyll &
Bute’s workforce’ as follows:
1 Deliver seasonal and temporary workforce accommodation using short term occupancy
agreements (SFT focus)
2 Develop a strategic approach to evidencing the need for workforce housing in the public sector
3 Deliver emergency workforce housing options including the use of modular, temporary and
tiny homes
4 Deliver a Council funded Mid-Market Rent workforce housing programme via powers to
advance wellbeing
5 Map Identify public sector land and buildings which could provide workforce housing via
repurposing and change of use
6 Use the Partnership Support for Regeneration Fund to enable private sector workforce
housing models
7 Reintroduce the Rural Home Ownership Grant model for working households in partnership
with Community Housing Trusts.
4.4 Workshop 4: Making the Best Use of Existing Homes in Argyll & Bute
Partners in Workshop 4 began the session by critically assessing the long-list of options identified to
enable better use of existing homes in Argyll & Bute. The in-scope/out scope exercise defined a
clear shortlist of options with both Group 1 and 2 unanimously agreeing that they should be
considered for inclusion within a more detailed option appraisal analysis. In scope options were seen
as instrumental in making the best use of existing homes in Argyll & Bute through enabling building
reuse and refurbishment, plus improving housing options through allocation policy development and
specialist housing models. Reducing the number of ineffective homes in Argyll & Bute and creating
opportunities to maximise the number of existing dwellings for use as a primary occupancy was also
seen as central to maximising the impact of existing homes in the area.
Full details of the ‘in-scope’/’out scope’ exercise, including partner rationale for each assessment
are set out in Table 4.4 below:
Page 198

Page 199

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 27
Workshop 4 Option List In Scope Out of
Scope Scoring rationale
Further reform CPO processes to
tackle abandoned homes more
effectively
IN IN Both Group 1 and 2 unanimously agreed the CPO process is long, laborious and urgently
needs to be reviewed. This is also the case for Compulsory Sales Orders too.
Create a multi-agency team enabling
mixed tenure refurbishment and
regeneration projects
IN IN
Partners agreed that this option needs more than just a single multi agency team - it
needs collaboration across all partners, owners and geographies. The right partners must
be in the room contributing to investment decisions, including a multi-agency approach to
net zero compliance issues
Reduce disabled grant title conditions
from 10 to 5 years to improve take up
of adaptations
OUT OUT Option not perceived to assist with the housing emergency by either Group 1 or 2
Use Rural & Islands Housing Fund to
enable PRS refurbishment with end
use as affordable housing
IN IN
Whilst some partners questioned providing funding to private landlords (‘it should be their
responsibility to carry out the work required’), the counter-argument suggests that we
need to retain and support private landlords. The struggle to achieve national standards
in older properties is forcing landlords leave the sector. Partners agreed for the need to
lobby government to review the taxation framework for the PRS, as well as property
standards.
Reintroduce an equity loans scheme
to enable property improvements in
private sector homes
OUT OUT
The general view in both Groups was that most households are vary about considering
equity loans particularly in such an unstable economic period and that this option would
not be effective
Adapt void or long term empty RSL
stock to meet accessibility standards OUT OUT
Partners noted that there are not many long term void properties and that property buy
backs may work better rather than converting hard to let homes. Furthermore, not all
empty properties may be suitable for adaptations or extensions e.g. flats.
Develop a housing model that offers
apprenticeships with tenancies to
keep young people in Argyll & Bute
IN IN
This option was positively received by both Group 1 and 2. Partners agreed that more
flexibility is needed in the allocations policy to do this but that this could be put in place
quickly. It was noted that partnership working between social landlords and further
education institutions would be instrumental in making this option a success
Create more choice and flexibility
within the Home Argyll policy to
address identified housing pressures
IN IN
This option is already in progress (e.g. allowing single applicants to be offered 2 bed
properties). Having said that, partners suggested further flexibility would allow other
actions to be introduced i.e. the apprenticeship/home scheme
Page 199

Page 200

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 28
Increase the number of Empty Homes
Officers with more flexibility to
assemble funding
IN IN
This option was assessed as in scope for both Group 1 and 2. The work of the empty
homes team is recognised as making a significant impact in bringing properties back into
use in Argyll & Bute and the more resources involved the better. This option is already
underway by Argyll & Bute Council
Develop a better range of housing
options for older people to encourage
movement in existing housing stock
IN IN
Despite a discussion around housing for older people in Oban which is difficult to let,
partners acknowledged that this option could be successful if demand is evidenced. Both
Group 1 and 2 were keen to progress this option, not just focusing on sheltered or
amenity housing but also other adapted properties. It was also acknowledged that further
discussion is needed around incentive to move schemes for current tenants who are
under occupying their tenancy to allow them to move on and free up family
accommodation
Introduce STL control areas in
pressured housing market areas IN IN
This option was assessed as in scope for both Group 1 and 2 although both groups were
clear that a completely evidenced based approach to restrictions would be necessary. It
was acknowledged that this analysis is underway with data is being gathered to
determine which areas should be considered as future control zones.
Double the Council Tax on Second
Homes IN IN
Partners noted that this option will be implemented from April 2024, but questions remain
over how will this impact on the housing system and whether further increases can be
considered
Develop a coordinated advice, finance
and support model to encourage PRS
landlords to enter and remain in the
sector
OUT OUT
This option was assessed as out of scope for both Group 1 and 2. Partners noted that
this options does not represent the real problem facing the PRS which is driven by the
taxation framework for landlords and the condition and energy standards imposed on the
sector by the Scottish Government. Landlords are struggling to achieve property
standards given the current economics of the PRS.
Council purchase of second homes
and short term lets to re-sell on the
open market with primary occupancy
burden
IN IN
Whilst partners were very supportive of this option, it was noted that it is already being
delivered to a degree with RSL's buying back homes through open market purchases to
achieve a majority share in common dwellings.
Enable second homeowners to offer
seasonal or temporary
accommodation options to essential
workers
OUT IN
Questions were raised by Group 1 over how this option would work including the needs
for licenses, policies and leasing agreements. Group 2 were more supportive of this idea
but question how could this could be achieved given that short assured tenancies have
been replaced by private residential tenancies.
Page 200

Page 201

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 29
Map public sector land and buildings
which could provide affordable
housing via repurposing and change
of use
IN IN Group 2 suggested adding ‘private’ as well as public to enhance the potential impact of
this option.
Extend the use of rural housing
burdens across Housing Market Areas
to maintain primary occupancy and/or
affordability
IN IN Both Group 1 and 2 were supportive of this option and achievement of rural housing body
status for Argyll & Bute Council should make the deliverability of this option high.
Table 4.: Workshop 3 ‘In Scope’/’Out Scope’ options for Enabling the Delivery of More Homes for Argyll & Bute’s Workforce 
Each workshop Group then used ‘in-scope’ options to assess whether suggested actions were both impactful and deliverable. The outcomes of
this impact exercise is detailed below: Page 201

Page 202

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 30 
Page 202

Page 203

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 31
Using the outcomes of the option appraisal session, and focusing on actions screened as having
the potential to be both impactful and deliverable, a list of actions was developed as the basis of
developing the Housing Emergency Action Plan to ‘make the best use of existing homes in Argyll &
Bute’ as follows:
1 Further reform CPO processes to tackle abandoned homes more effectively
2 Create a multi-agency teams enabling mixed tenure refurbishment and regeneration projects
3 Develop a housing model that offers apprenticeships with tenancies to keep young people in
Argyll & Bute
4 Create more choice and flexibility within the Home Argyll policy to address identified housing
pressures
5 Increase the number of Empty Homes Officers with more flexibility to assemble funding
6 Develop a better range of housing options for older people to encourage movement in existing
housing stock
7 Map public sector land and buildings which could provide affordable housing via repurposing
and change of use
8 Introduce STL control areas in pressured housing market areas
9 Double the Council Tax on Second Homes
10 Council purchase of second homes and short term lets to re-sell on the open market with
primary occupancy burden.
Page 203

Page 204

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 32
5 Housing Emergency Partner Pledges
As the Housing Emergency Summit was intended as a partnership call to action, the most important
aspect of the event focused on a partner pledge activity. Following the appraisal and priority
assessment of options, delegates were invited to review the shortlist of housing emergency actions
and to commit their planning and delivery support to those they were most keen to see implemented. 
The shortlists of housing emergency actions were presented on exhibition boards for delegate
review. Partners were invited to review each shortlist and to place a partner pledge sticker against
the actions they were most committed to delivering.
Partners were also encouraged to network during this interactive session, identifying fellow delivery
partners who could form new partnership groups working on specific programmes as part of the
wider Housing Emergency Action Plan. 
The outcomes of this session are detailed in Appendix C which sets out partner pledges against
each housing emergency action.
Undoubtedly this exercise proved to be successful in building strong partnership networks focused
on the collection action needed to tackle the housing emergency in Argyll & Bute. 
In total, 425 partnership pledges were received across four Housing Emergency
themes including: 
These partnership pledges will inform the delivery of a Housing Emergency Action Plan which
details the activity, timescales, committed resources and partnership networks associated with
each action.
Page 204

Page 205

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 33
6 Housing Emergency Summit Outcomes & Next Steps
The Argyll & Bute Housing Emergency Summit was the first event of its kind in Scotland. It was
designed to bring partners together as a response to the Council’s call to action to tackle housing
shortage. The Summit acknowledged the scale and impact of the housing emergency on Argyll &
Bute’s communities and economy and encouraged partners to commit to collective action across a
diverse partnership of house builders, landlords, funders, business leaders and public sector bodies.
To that end, partnership delivery planning prioritised the implementation of 39 housing emergency
actions aimed at tackling housing shortage.
Furthermore, over 400 partnership pledges were made by delegates committed to taking the bold
and progressive action needed to address the housing emergency.
At the close of the Summit, partners were invited to share their views of the extent to which the event
created a positive start to the process of collectively tackling the housing emergency in Argyll & Bute.
Using an interactive polling tool, partners were invited to evaluate the outcomes achieved and offer
their expectations for the future. The outcomes of this evaluation exercise is detailed below: 
Page 205

Page 206

Argyll & Bute Council
Housing Emergency Summit
Summit Outcomes Report February 2024 34
These evaluation outcomes suggest that the Summit was successful in coordinating the collective
and bold action needed to tackle housing shortage, as follows:
• 100% of Summit delegates leaving with an improved understanding of the housing emergency
response needed to tackle housing shortage
• 97% of Summit delegates satisfied that the Summit has been successful in scoping solutions
and forging partnerships
• 88% Summit delegates rating new partnership development opportunities as ‘excellent’ or
‘good’
• 93% of Summit delegate showing some confidence that the emergency responses identified
can tackle housing shortage.
The outcomes of the Housing Emergency Summit will be used to develop an Action Plan as the
basis of ongoing planning, activity, investment and partnership. Housing Emergency Action points
will be refined, partnership commitments focused, timescales proposed, and resources commitment
scoped in early 2024.
A final version of the Argyll & Bute Housing Emergency Action will be launched across Housing
Summit partners by Spring 2024.
Page 206

Page 207

APPENDIX 2 – SETTLEMENT OFFICER DETAILED ACTIVITIES UPDATE 
Table 1: Update of Actions
Focus Area Action Approved Progress to Date 21st March 2024 Current
Status 
Active
Promotion
of Argyll
and Bute 
Continue to develop
and expand
settlement case
studies for the
abplace2b website
and enhance
marketing
provisions where
appropriate.
All settlement content has been
uploaded to the abplace2b and
Invest in Argyll websites. 
The settlement flyer is available to
download on abplace2b. 
The welcome pack is available to
download on abplace2b. 
Five case studies have been
written and are available to read on
abplace2b here.  
The myjobscotland section specific
to Argyll and Bute Council has
been updated here. 
The settlement flyer has been
passed on to colleagues in HR to
be distributed alongside offers of
employment. 
Supporting
Relocation
Continue to
respond to
relocation queries. 
Set up a relocation
network connecting
new and existing
residents. 
Work with the new
Housing
Improvement
Officer (Empty
Homes) to support
individuals
relocating to
recently refurbished
properties.  
To date, there have been 10
relocation queries received. All
queries have been responded to
accordingly. 
(See Appendix 2). 
The Relocation Network has gone
live. 
Settlement support resources have
been passed on to the Housing
Improvement Officer to be
distributed.   
Housing Launch the ‘Make
Your Second Home
Your First Home’
campaign. 
The ‘Make Your Second Home
Someone’s First Home’ campaign
has been paused until the findings
from the Argyll and Bute Housing
Summit have been finalised. 
Page 207

Page 208

Increased energy
support and
signposting across
Argyll and Bute.  
Energy support and signposting
resources have been incorporated
into abplace2b web updates here.  
The SPSO continues to assist
housing colleagues to drive
forward work on the Council’s
Housing Emergency. 
Employment Consider current
empty council-
owned (non-
residential)
properties being
used for remote
working hubs or
creative spaces
(working with other
council colleagues,
as appropriate). 
Engage with key
employers across
the Repopulation
Zones to identify in
detail the number
and nature of
recruitment issues
they have
encountered/
forecast
The current focus for remote
working spaces is to map existing
facilities across Argyll and Bute.
A survey has been created for
individuals, businesses, and
organisations to provide details of
their current working spaces.
Working with the Communications
and Web Teams this will be
released to the public. 
Monthly reports continue to be
analysed from the Argyll and Bute
Council HR Team regarding
withdrawn and declined job offers. 
Funding was provided to Isle
Develop CIC on Tiree to develop a
custom WordPress site, an
integrated booking system,
refreshed logo, and design assets
for the Hynish Trust on Tiree. This
project will enable Isle Develop
CIC to train their trainees in
advanced website management
and social media integration. The
project will run from January to
March 2024. 
Table 2: SPSO Proposed Actions
Focus Area Proposed Action
Active
Promotion of
Argyll and Bute
Further develop the ‘Why Argyll and Bute?” section on
abplace2b, showcasing existing good news stories from
across Argyll and Bute. 
Scope the potential to collaborate with UHI students to
commission a number of promotional articles for abplace2b. 
Page 208

Page 209

Supporting
Relocation
Develop a ‘plan your move section’ on abplace2b including: 
o A comprehensive checklist for those relocating.
o A guide to relocating to Argyll and Bute from inside/
outside the UK. 
o Downloadable relocation guides for each administrative
area in Argyll and Bute. Containing place-based
information relating to:
o Transport
o Housing 
o Education
o Employment  
o Healthcare 
o Leisure and things to do
Housing Continue to support Housing colleagues and help to drive
forward work on the Council’s Housing Emergency. 
Working with colleagues in Housing progress the ‘Make
Your Second Home Someone’s First Home’ campaign. 
Employment Scope the potential to run six-week paid internships for
students within a business or organisation based in Argyll
and Bute that supports the use of Gaelic language and
tradition in the workplace. 
Explore the potential for existing council-owned office
equipment that is no longer used, to be provided to
community organisations looking to develop purpose-built
remote working spaces across Argyll and Bute. 
Knowledge
Gathering
Share findings from the Repopulation Zone Survey with the
relevant communities. 
Page 209

Page 210

This page is intentionally left blank

Page 211

Environment, Development and Infrastructure Committee Work Plan 2024/25 
This is an outline plan to facilitate forward planning of reports to the Environment, Development and Infrastructure Committee. 
Date  Title Service/Officer Date Due Comments
21 March 2024 
Cemetery Asset -  Update
Report Outlining
Procedures In Place To
Protect Remaining Lair
Space In Cemeteries
Road and Infrastructure
Services
27 February 2024 
Waste Update Road and Infrastructure
Services   
Electric Vehicle Charging
Strategy Update
Road and Infrastructure
Services   
Annual Status and Options
Report (ASOR)
Roads and Infrastructure
Services 
Footway Parking Ban Road and Infrastructure
Services   
Second Domestic Bin
Review 2024
Road and Infrastructure
Services   
Local Bridge Maintenance
Fund
Road and Infrastructure
Services   
Route Optimisation Update  Roads and Infrastructure
Services   
Roads Capital
Reconstruction Programme
2024/25
Road and Infrastructure
Services   
Film in Argyll – Screen
Industries Update Report
Development and
Economic Growth 
Transformational Projects
Regeneration Team Large
Scale Projects Update  
Development and
Economic Growth 
Six monthly update 
Page 211
Agenda Item
17

Page 212

Environment, Development and Infrastructure Committee Work Plan 2024/25 
Argyll and Bute Council’s
Economic Strategy Refresh
2024 - 2034
Development and
Economic Growth 
Email from Stuart Green 19.12.23 
Argyll and Bute Housing
Emergency Progress
Report
Development and
Economic Growth  
20 June 2024 
PC Door Installation Update  Roads and Infrastructure
Services 
28 May 2024 
Waste Update Roads and Infrastructure
Services   
Digital Update  Development and
Economic Growth 
Housing Summit Action
Plan
Development and
Economic Growth  
12 September 2024 
Footway reconstruction
Programme
Roads and Infrastructure
Services 
20 August 2024 
Winter Service Policy Roads and Infrastructure
Services 
Cemetery Asset Update Roads and Infrastructure
Services  
19 December 2024 
Route Optimisation  Roads and Infrastructure
Services
26 November 2024 
Future
Items     
Shared Prosperity Fund Development and
Economic Growth   
Page 212