Transformational Projects and Regeneration Team - Large Scale Project Update Report

Argyll and Bute Council · 21 March 2024
Back to Environment, Development and Infrastructure Committee — 21 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21 MARCH 2024 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
1. EXECUTIVE SUMMARY
1.1 The purpose of this report is to update the Environment, Development and
Infrastructure Committee on progress of the large-scale, externally funded
project work of the Transformational Projects and Regeneration Team, and to
highlight key issues that may impact on the successful delivery of projects. 
1.2 The last update report was considered by Environment, Development and
Infrastructure Committee in August 2023. 
1.3 The team is currently responsible for the delivery and or management of projects
and or associated grants with a cumulative value of over £45m. Projects the team
delivers and or associated grants the team manages are listed in Appendix A.
It should be noted that following completion of each project the team continues
to have the responsibility for the monitoring and final drawdown and reporting up
until the end of the 12-month defects period or beyond depending on conditions
on the respective grant contracts. 
RECOMMENDATIONS
It is recommended that the Environment, Development and Infrastructure
Committee consider and note the current progress contained within the report.

Page 2

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21 MARCH 2024 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
2. INTRODUCTION
2.1 This report sets out the current position of the large-scale projects, which are
currently being delivered by the team and or where Council and externally
secured grants are being managed by the Transformational Projects and
Regeneration Team. 
2.2 The Transformational Projects and Regeneration Team sits within the Council’s
Development and Economic Growth Service and works region-wide. The team
has a particular focus on ‘place’, heritage regeneration, the creative industries,
renewables and Islands and works closely with colleagues across the Council,
communities, third sector organisations, town centre heritage building owners
and businesses to realise positive change. 
2.3 The team’s work broadly includes the following areas:- 
• Developing and submitting bids to secure external funding of various scale
through a competitive process, such as the new Heritage and Place
Programme previously referred to as the Conservation Area Regeneration
Scheme (CARS) programmes;
• Development and delivery of regeneration projects with a particular
emphasis or theme, such as the suite of measures to encourage shopping
locally;
• Development and delivery of several place-based engagement projects,
working in partnership with the community and key partners, leading to
action plans, such as charrettes, and working with communities to realise
these community ambitions; 
• Development of the economic opportunities for Argyll and Bute across
Film, Creative Industry and Renewable sectors, with the objective of
securing income into the area and delivering local economic benefit,
including support to community organisations working across these
sectors. This work also includes the setting up and management of the
Argyll and Bute Renewable Alliance (ABRA) with partners in HIE; 
• Support to third sector organisations involved in the delivery of their own
individual community led economic regeneration projects, as well as
support to third sector organisations delivering regeneration focused
projects where Council funding is involved and/or where projects align
with Council outcomes, such as Regeneration Capital Grant Funded

Page 3

(RCGF) project funding;
• Drafting and submitting external funding bids to competitive call such as
Regeneration Capital Grant Funded (RCGF) annually. A total of 17
projects have been supported and over £10 million secured through
RCGF; 
• Development and Administration of the Council’s, Strategic Events and
Festivals Grants for which 21 grants were awarded under SEF Rounds 5
and 5.2 (2023/24);
• Overseeing the delivery programme and financial administration of
projects supported through funding from Scottish Government, such as
Place Based Investment Fund (PBI) as well as annual Crown Estate
funding;
• Working closely with the SG Islands team and working with colleagues
and communities in the development of bids to the Islands Programme
(IP) as well as the monitoring and reporting on IP grants that are secured. 
2.4 This paper also seeks to report on key issues that may impact on the current
status of each project, such as any amendments to project scope or timeframe. 
2.5 The large-scale projects currently in delivery, either directly by the team, colleagues
across the Council or by a third party and where the team is responsible for
managing the associated grant, are included within the table in Appendix A, and
have a cumulative total value of over £45m. The individual projects being taken
forward under the PBI and CE are not listed individually in Appendix A. 
3. RECOMMENDATIONS
3.1  It is recommended that the Environment, Development and Infrastructure
Committee consider and note the current progress contained within the report. 
4. DETAILS
4.1 The following sections summarise the progress associated with each of the large-
scale projects that are currently in delivery and are either directly delivered by the
team or there is a grant to the project managed by the Transformational Projects
and Regeneration Team. In addition, the report provides information on annual
funding streams received by the Council (PBI and CE) and managed by the team
as well as annual competitive external funding grants secured and being managed.
The individual projects are listed in Appendix A with the exception of those
individual projects supported through PBI and CE. 
HERITAGE LED REGENERATION PROJECTS 
4.2 The Council is currently responsible for the delivery of four heritage-led area based
regeneration schemes. These are referred to as Conservation Area Regeneration
Schemes (CARS) and each is delivered over a 5 year period. The schemes
currently in progress are based in Rothesay, Helensburgh and Lochgilphead and

Page 4

Dunoon. Dunoon CARS formally finished in July 23 and we are currently in the
process of evaluation and closing the scheme down. The CARS schemes have all
been secured via a competitive process and the total value of the four schemes
represents in excess of £10m of investment into the built heritage of these towns
and is largely comprised of funding from Historic Environment Scotland (HES) with
match funding from the Council and private owners. The Rothesay scheme also
has funding from National Lottery Heritage Fund (NLHF) and for that reason is
referred to as a Townscape Heritage (TH) scheme as well as a CARS. 
4.3 It is worth noting that since 2007 the Council has successfully secured, through a
competitive process, eight rounds of CARS funding, equating to £6.6m of CARS
funding, and which totals £27m of investment made into 6 key Argyll and Bute
town centres, The CARS schemes operate as grant administration programmes
which is administered by the Council. This programme offers grants to property
owners to help them repair and safeguard their historic buildings. Many building
owners have, and continue to benefit from the funding, which has delivered a
significant level of investment into the area since 2007. 
4.4 Due to the cost of repairing traditional buildings, many of these owners would have
been unable to undertake the level of repairs required without grant assistance and
their properties would have continued to deteriorate. Had deterioration continued,
the Council may well have had to step in to undertake emergency work to these
buildings. CARS grants have also helped to safeguard existing businesses, and
new businesses have opened because of the regeneration, helping to create jobs
within the community. 
4.5 Such investment has and continues to change the physical appearance of our key
town centres for the better, making them more attractive places in which to live,
learn, work, invest and do business. Details of the current CARS projects are
provided below. 
4.6 Rothesay Townscape Heritage Phase 2 (2017 – March 2024) Project Status -
GREEN 
Rothesay TH is a £2.75m project is in the final few months of the scheme and is
due to complete 31 March 2024. The partnership project is funded by NLHF
(£1,888,500), HES (£500k), Argyll and Bute Council (£200k), HIE (£70,249),
LEADER (£65,800) and Sustrans (£21,500). Project staff are fully funded for the
project duration. 
The project has been given a final extension to 31st March 2024, to allow for the
completion of priority building and shopfront restoration which have experienced
delays. Of the 5 priority building repair projects, 4 are complete, 1 is due to
complete by mid February 2024. 4 shopfront restorations have been completed,
with the final shopfront due due to complete by mid February 2024. A series of
window repair grants have also been provided for the restoration of traditional
timber sash and case windows. 
The project seeks to facilitate traditional skills development and host events that
celebrate the island’s heritage. To date a maintenance awareness raising event,

Page 5

community engagement event and 14 workshops have been held. In addition, a
substantial amount of audience development analysis has been undertaken,
resulting in recommendations to support the visitor market and enhance the end-
to-end visitor experience. The potential for a WASPS style studio has been
analysed, Rothesay Castle has been lit up in animation, and the pilot pop-up
shop in the former Clydesdale Bank has successfully continued beyond the
scope of the TH funding. 
4.7 Dunoon CARS (2017 – July 2023) Project Status - GREEN 
Dunoon CARS, a £2m project is now complete. A fully funded project officer was
employed to deliver the project for its duration. 
The envelope restoration of 4 priority buildings and 32 shopfronts have been
completed. 
Working in partnership with Dunoon Community Development Trust, CHARTS,
Dunoon Grammar School and Tacit Tacit, a complementary scheme of skills
development was successfully delivered with courses and workshops in
stonemasonry, woodworking, painting and lime mortar. An additional grant from
the Castle Knowledge Trust in 2023, allowed for archaeological geophysical
surveys to be undertaken on the Scheduled Monument Castle site in Dunoon. 
The Dunoon CARS evaluation report is currently being prepared by consultants
to evaluate the impact of the CARS funding in Dunoon and a final audit is being
undertaking prior to the project being formally closed down. 
4.8 Helensburgh CARS (2021 – March 2026) Project Status - GREEN 
Helensburgh CARS is a £2.4 million pound project in the third year of delivery.
The partnership project is funded by Argyll and Bute Council (£500k) and HES
(£1.24m) with owner's personal contributions completing the funding.  A fully
funded project officer is employed to deliver the project for its duration. 
Two priority buildings have contracted with the Conservation Architect and a
tender document is currently being prepared with an expectation of return by Mid
February 2024.  The third priority building has decided not to proceed.   A fourth
priority building has been sourced and a survey has been commissioned via the
Conservation accredited Architect. 
One shop front grant has been completed (November 2023) with owners
reporting an increase in footfall. Planning permission has been granted for a
second shop front. 
Two lime mortar courses are being procured and these are programmed for May
and September 2024.  An apprenticeship training programme for a young person
is being investigated. 
4.9 Lochgilphead CARS (2020 – Mar 2026) Project Status – GREEN

Page 6

Lochgilphead CARS is a £2m partnership project with HES (£969,700) in its
fourth year of delivery.  The project is due to end in March 2026. 
The first two priority building projects are almost complete.  All grant funding has
been approved for the remaining two priority buildings and work is due to start in
March 2024. 
A high-level repair project at Poltalloch Street has been completed and other
small repair grant cases are being progressed. 
Three shopfront reinstatement projects are being developed for delivery in 2024. 
Local stakeholders are benefiting from several traditional skills training courses
and educational activities, delivered via the scheme.  The latest event was a
Maintenance and Retrofit event for tenement owners, delivered in partnership
with Under One Roof. 
4.10 Hermitage Park, Parks for People (2016 – June 23) Project Status - ORANGE     
Whilst the project delivery itself is complete this project awaits a decision on the
outcome of the potential location of the skate park in Helensburgh in order to
complete the final financial draw down of £100,578. National Lottery Heritage
Fund, the main funder of this £3.7million project, have confirmed that locating the
skate park in Hermitage Park may breach the purposes of the £2.3m grant and
is therefore a risk to the project.  For reference, the final project evaluation
highlights were in the November 2023 EDI Committee and the Park Manager
post ended in June 2023. 
4.11 Tarbert Heritage Regeneration Scheme (TBC) Project status - GREEN 
A new funding stream has been launched called Heritage and Place Programme
(HPP). HPP is a competitive fund run by HES and supersedes the Conservation
Area Regeneration Scheme (CARS) funding, which HES made available over
eight rounds between 2007 and 2019. Policy and Resource Committee agreed
on 16 June 2022 to support the submission of an Expressions of Interests
application to HES to the first call of the Heritage and Place Programme, and
National Heritage Lottery Fund of the Grants for Heritage Programme to support
the Tarbert Heritage Regeneration Scheme. 
Expressions of Interest to both funds were successful, with invitations made to
apply for an initial Development Phase. A development application to Historic
Environment Scotland was submitted on 17 November 2022 seeking £40,000,
and to the National Heritage Lottery Fund on 15 December 2022, also seeking
£40,000. The Council has sought £80,000 from both funding programmes, with
£60,000 of Council match funding to support a Development Phase at the total
cost of £140,000. The outcome of both applications were successful and
following approval from Full Council on 29 June 23 a project officer was recruited
and the development phase is now progressing in close liaison with the funders
and the community. Due to delays in the appointment of consultants to undertake

Page 7

the necessary works required as part of the grant contract it is now anticipated
that this will be an 18 month development phase. A report will be brought back
to Council prior to any delivery phased bid being submitted. 
WIDER REGENERATION FOCUSED PROJECTS 
4.12 Tarbert / Lochgilphead Regeneration Fund Project Status – GREEN 
In its 2016/17 budget, Council allocated £3m from reserves to support
regeneration and economic development in the settlements of Tarbert,
Lochgilphead and Ardrishaig. 6 projects were identified to proceed to Full
Business Case (as ratified by Policy and Resources Committee on 19th October
2017).  The following projects are complete: 
• Gleaner (Phase 1 only) - completed summer 2019.
• Tarbert Harbour – shore side facilities completed in May 2019, car park
completed in March 2021.
• Barmore/Garvel Road junction improvements - completed February
2020.
• Colchester Square/Argyll Street, Lochgilphead – completed May 2021.
• Lochgilphead Front Green – completed August 2022.
• Ardrishaig North Public Realm – completed April 2023. 
The only remaining allocation of funding is in relation to the remaining part of the
former Gleaner Oil site in Ardrishaig. Both Scottish Canals and Argyll and Bute
Council are in discussions with a potential occupier of the site. No details have
been confirmed to date but we are hoping that this can progress during 2024/25. 
4.13 Regeneration Capital Grant Funding (RCGF) Project Status – GREEN 
Over the past seven years, a total of £10.72m RCGF funding has been secured
from Scottish Government to support 17 projects across the area. Although
RCGF can support community projects, the Fund is only open to local authorities,
and as all 32 local authorities are eligible to apply, this makes for a highly
competitive process. The team has responsibility for applying to RCGF each year
through a competitive process and when successful then managing the
respective grant awards and reporting back to Scottish Government as well as
supporting any third party receiving the funding. 
An update on the current ongoing RCGF projects is provided below and is
followed by a table of all current grant contract awards (Table 1) 
• Kilmartin Museum Redevelopment – following a number of delays the
museum reopened in September 2023 following the completion of the
construction and fit out works. We are continuing to work with Kilmartin
Museum as they work through the final stage of the formal close down
of the redevelopment project.
• Port Ellen Community Hub, Islay – a contractor was appointed for the
project in March 2023 and works are progressing. It is expected that they
will be ongoing until at least May 2024.

Page 8

• Scalasaig business units, Colonsay - A contractor is in place and
construction is underway.  Project end date has now been delayed until
mid March 2024
• Kilmory Business Park, Lochgilphead – work is progressing with M&K
MacLeod on the proposed Kilmory Business Park.  Tender process is
underway with contract award expected late January 2024.
• Obair Ùr Thirodh Tiree Community Business Hub – a contractor was
appointed for the project in March 2023 and works are ongoing.  It is
expected that they will be ongoing until February 2024.  
• Kerrera Old School - Community Hub Final Phase – Works commenced
early in 2023 and are expected to complete late January 2024.
• Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha – A contract
was awarded early in 2023 and construction works are progressing,
works are expected to complete in July 2024.
• Aros Waterfront Development, Mull – outdoor activity hub – a contract
was awarded in January 2024 and works are commencing.
• Nonhebel Light Industrial Park Expansion, Mull – construction works
have commenced.  Project completion expected in March 2024. 
Table 1 
RCGF Project Grant
Awarded
Year
Awarded
Balance
Remaining /
Yet to Drawdown
Kilmartin Museum  £275,000 2019/20 £0
MACPool  £400,000 2020/21 £0
Port Ellen Community hub, Islay  £1,046,223 2021/22 £608,444
Scalasaig business units, Colonsay  £335,000 2021/22 £689
Kilmory Business Park in
Lochgilphead 
£829,000 2021/22 £829,000
Obair Ùr Thirodh – Tiree Community
Business Hub
£565,000 2022/23 £86,175
Kerrera Old School - Community
Hub Final Phase  
£285,000 2022/23 £0
Ulva Ferry Shore Facilities Building -
Doras Caolas Ulbha
£602,590 2022/23 £33,957
Aros Waterfront outdoor activity hub £403,500 2023/24 £403,500
Nonhebel Light Industrial Park
Expansion
£654,000 2023/24 £296,886       
The following stage 2 applications were submitted to the RCGF Round 11
2024/25:
• Fyne Futures Local Food Production and Training Centre, Bute 
• Isle of Luing Community Owned Slate Quarry 
The Council has been advised that there has been a delay in any decision being
made on RCGF Round 11 due to budgetary considerations.

Page 9

4.14 Scottish Government Place Based Investment Funded projects 2021 – 2024 
Town Centre Funding has been superseded by Place Based Investment (PBI)
funding, which the Scottish Government has committed to allocating on an
annual basis over a five-year period. Argyll and Bute’s allocation for 2021/22 was
£821,000 and for 2022/23 the allocation was £712,000. The allocation for
2023/24 has been confirmed as £496,000 and a report went forward to August
Policy and Resources Committee seeking member’s approval to support a total
of 8 projects. No confirmation has been received of any award for 24/25. 
At their respective meetings of 24th June 2021, 12th August 2021, and 2nd
September 2021, Argyll and Bute Council, the Policy and Resources Committee
and Environment, Development and Infrastructure Committee agreed to use PBI
towards 8 projects that support a living well locally concept, have climate friendly
ambitions, and which have stemmed from the community through design-led
consultation activity or through needs identified by key partner organisations. 
Of the 8 projects approved for 2021/22, 7 have been fully completed and 1 is due
for completion in 2024. 
As stated above the Councils PBI allocation for financial year 2022/23 from
Scottish Government was £712,000. Of the projects approved in 2022/23, 3 are
fully complete and 3 are due for completion in 2024. 
At the meeting of the Policy and Resources Committee on 10 August 2023,
members agree to allocate £496,000 of the PBI funding to 8 projects listed below: 
• Dunoon Burgh Hall Trust – Phase 2 to enhance outdoor area -
£74,5000
• Dunoon CARS/LACER approach – flexible fund to support businesses
with capital improvements to shopfronts/buildings - £49,500
• Helensburgh CARS Shopfronts - £44,000
• Helensburgh Skatepark - £80,000
• Tobermory Worker Accommodation – £50,000
• Bid4Oban – Shopfronts and Oban Signage - £60,000
• Lochgilphead CARS Shopfronts and high-level amenity project –
£100,000 
• Steel Beam Project/LACER Shopfronts in Campbeltown - £38,000
All the projects above are progressed to the point that the funding is secured. 
4.15 Scottish Crown Estate Revenue Allocation Funding 21/22, 22/23 & 23/24 
In financial years 21/22 & 22/23 the Council has received a total of £3,122,803
and this funding has been allocated to a total of 22 projects which involve a
mixture of Council and third-party projects. The Councils allocation for this
financial year (2023/24) is £1,590,409. The formal notification of the allocation
was not received until 30 November 2023. In advance of confirmation of the

Page 10

2023/24 allocation a total of 7 projects were agreed through the delegated
process amounting to the full £1million prudent estimate. A report will be
considered at Policy and Resources Committee on 15 Feb recommending the
allocation of the remaining funding of £590,409 to a number of additional
projects.  Because of the sheer number of CE projects involved the full list of
projects are not included in this report however the total is included in Appendix
A. All projects are being monitored. 
4.16 Scottish Government Islands Programme Funded projects 2021/22, 22/23
& 23/24 
The Scottish Government wrote to Councils on 17 December 2021 advising of
the distribution of the 2021-22 Islands Infrastructure Fund (IIF). Argyll and Bute
Council’s share of the funding was £740,000. The fund was for capital works and
required to be committed via a grant contract or contract award by 31 March
2022. At the Policy and Resources Committee meeting on 17 Feb 2022 members
agreed to allocate the IIF to 11 projects, 9 of which were third party projects. Of
the 11 projects, 7 are now fully complete and 4 are due for completion in 2024. 
In regard to the £4million Island programme for 2022/23 the Scottish Government
(SG) decided to introduce a competitive bidding process for all 6 island
authorities as opposed to a direct allocation. The Council was successful in
securing funding for the following 2 projects: 
1. Island Community Halls Digital Hubs – Islay, Iona, Tiree and Coll - £100,000.
-  All equipment installed.  All community engagement visits to the islands are
expected to be completed by March 2024. 
2. Tobermory Seawall and Railings project - £250,000. - In progress, due for
completion April 2024.          
The Council submitted a total of 2 bids to the IP 2023/24 and successfully     
secured funding for both projects: 
1. Infrastructure for Worker Accommodation, Tobermory, as part of the Rural
Growth Deal - £700,000. Planning permission has been secured and road
construction consent is in progress. A procurement exercise is also live at
the time of writing. Subject to successful completion of these activities, it is
anticipated that works on site will commence during summer 2024.
2. Tiree Community Care Hub, HSCP, - £450,000.  Works have commenced. 
Confirmation is still awaited in respect of any Islands Programme funding round for
2024/25. 
4.17 Scotland Loves Local Projects Oct 21 - 2024 
Argyll and Bute Gift Card - The gift card for Argyll and Bute formally launched in
October 2021. To date, over 325 Argyll and Bute businesses have registered to
accept the card as a means of payment for goods and services. At the full Council
meeting of 28th April 2022, members agreed to commit a share of the Local

Page 11

Authority COVID Economic Recovery (LACER) Fund to the Gift Card. The
approved options were:-
• Issue Scotland Loves Local Gift Card to households in receipt of
Council Tax Reduction Scheme - £797,720;
• Fully fund Gift Card for 2022/2023 into 2023/2024 - £30,000;
• Marketing budget to promote the Gift Card. 
The roll out of the LACER funded Scotland Loves Local Gift Card began in
December 2022 and was sent out to 6,800 eligible households in Argyll and Bute.
In addition to this, the Council issued a further issued 1,244 cards worth just
under £150,000 in total to eligible islands households to help low-income
households with the ongoing cost of living. In November 2023, 1,200 cards were
given to households in receipt of council tax reduction on the islands to the value
of £85. 
The contract was awarded to Miconex to continue the facilitation of the Argyll and
Bute Card in 2022/2023 and 2023/24 which will enable the Shop Local campaign
to gain momentum and support local businesses over the next two years. 
The marketing budget has funded the creation of 6 promotional films, to promote
business registration, help awareness of the card and showcase local areas.
Local businesses across Argyll and Bute were invited to become Business
Ambassadors for the card, with promotional films rolled out from November 2022
into December 2022 to coincide with the festive season and roll out of the LACER
funded cards. The promotional films were successfully shared across social
media platforms and can be viewed on the Council’s YouTube page:
ArgyllandButeCouncil - YouTube. In April 2023, the Council provided 16 of our
local Business Ambassadors with a £50 Argyll and Bute Gift Card to run a
competition on their social media channels. The social media posts from our
Business Ambassadors garnered a total of 1,553 likes, 1,303 shares and 1,309
comments helping to spread further awareness of the card. In October 2023, the
Council ran a photography competition for the design of the new Argyll and Bute
Gift Card. The winning entry won a £50 Gift Card and the new design will be
featured on the cards in April 2024. 
In July 2023, the Council piloted its first sales point for the Argyll and Bute Gift
Card at Keeping it Local, Campbeltown. In December 2023, the second sales
point for the Gift Card was established in the Lochgilphead Post Office (also know
as the Bank Store), Lochgilphead. Cards can be purchased in-store from  £5 and
spent within over the 325 businesses across the area. 
The Argyll and Bute Gift Card can be purchased online as follows: Argyll & Bute
Gift Card | Scotland Loves Local Gift Cards (scotlandgiftslocal.com) 
Inclusive of the LACER funded cards, as of 17 January 2024, a total of 8,932
cards have been purchased to the value of £957,225.

Page 12

4.18 Budget 
The above project and grant updates are predominantly in relation to the
externally funded projects for which the team are responsible for firstly securing
and then delivering as per external grant requirements and or overseeing the
specific budget claiming and monitoring process where these relate to Council
as well as third party project. A number of these projects include a proportion of
Council funding as well as sources such as PBI, IP, RCGF or CE funding. There
is a set budget for each project, and each is subject to specific outcomes and
timelines, as agreed with respective funders. In most instances the externally
funded elements of the project costs can only be claimed once proof of all
necessary information has been provided to the respective funder. Each funder
has a different criteria against which delivery is measured, and the Council has
entered into formal grant contracts with all funders involved. 
5. CONCLUSION
5.1 Place based investments are taking place across much of Argyll and Bute
making significant improvements to the quality of life of local people and our
communities. Much of the work is externally funded adding to the capital funding
committed by the Council to enable this investment to happen. The successful
delivery of the projects requires careful monitoring and close working with
colleagues, partners and community stakeholders. There continues to be an
impact from Covid-19 pandemic, the impact from the UK having left the EU and
the current cost of living crisis all of which set a background that often creates
a challenging environment in which to work and to deliver capital projects.
Prices are still high, due mainly to supply chain issues, but also shortages in
labour and rising electricity and wider cost of living costs. The team therefore
adopts a pragmatic approach to delivering projects, ensuring that these are as
meaningful as possible using the budget available however the environment in
respect of project delivery is a very challenging one. The team continues to
support third sector organisation wherever possible to ensure the successful
delivery of community projects where Council funding has been committed or
the Council has secured external funding on behalf of these organisations
through competitive funding streams such as RCGF. 
5.2 The projects and grants detailed within this report will result in assisting the
economic recovery of Argyll and Bute, helping to sustain numerous small
businesses, community organisations, making our places more investor ready,
improving our towns and villages as places to live, work and visit together with
adding to the significant regeneration works that are being taken forward across
Argyll and Bute, and seek to make an improved and lasting difference to the area. 
6. IMPLICATIONS
6.1  Policy - The delivery of these projects fits with the Council’s Corporate Plan,
Argyll and Bute Local Outcome Improvement Plan and the Economic

Page 13

Development Action Plan. The economic outcomes from this project will
contribute to the Government’s Economic Strategy. 
6.2  Financial - All funding has been approved for the projects detailed in the report.
The funding comes from the Council and from external funding sources some
from highly competitive processes.  We will continue to review costs and assess
budgets. 
6.3  Legal  Each project will have differing legal and procurement requirements
depending on the grant funder and the associated grant contract conditions and
we are working closely with colleagues to identify the support required and to
allow this to be factored into future work plans. 
6.4  HR - The resources required to deliver the projects will be continually
monitored. The management of these externally funded projects as well as the
management of the Council, PBI, CE and IP and RCGF grants requires a
significant amount of resources from the team to ensure that all the necessary
due diligence and financial management is undertaken and the risk is
minimised to the Council. 
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – None.
6.5.2   Socio-economic Duty – None.
6.5.3 Islands – None. 
6.6  Climate Change - It is an ambition of our project work to work towards net zero
by adopting a carbon conscious approach throughout.   
6.7  Risk - Construction projects by their very nature are challenging given issues
that can arise relating to site conditions, managing contractors/the design team
and associated budgets and meeting funder’s requirements. The effects of
Covid-19 and the current cost of living crisis has added even more challenges
both in regard to the development/delivery phases of projects. We continually
seek to minimise the risk through strong project management processes,
however until the projects are fully delivered on site there remains a risk. Other
areas of risk relate to the potential for limited uptake in regard to CARS/TH
grants and also over-run on costs for third party projects. In regard to the latter
this is a high risk particularly as the Council is not the responsible body for the
projects or their delivery on the ground. The setting up of regular benefits
realisation group meetings and building good working relationships with the
third parties assists in identifying where issues may arise and where additional
support may be required. Covid-19 and the resulting impact on the construction
industry and costs is an additional risk to the delivery of these projects and we
are reviewing all costs and working with funders to minimise the impact and
manage the risk as much as we can. 
6.8  Customer Service – None. 
6.9  Rights of the Child (UNCRC) – None.

Page 14

Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Policy Lead for Strategic Development: Councillor Robin Currie 
Policy Lead for Economic Growth, Communities and Corproate Services:
Councillor Alastair Redman 
February 2024 
For further information - please contact: 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Audrey Martin, Transformation Projects and Regeneration Manager
Audrey.Martin@argyll-bute.gov.uk 
Appendices: 
Appendix A – List of Council and Third Party projects that the team is either
responsible for delivering directly or for managing the grants given by the Council to a
third party organisation.

Page 15

APPENDIX A - LIST OF COUNCIL AND THIRD PARTY PROJECTS 
Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Dunoon CARS  £1,949,965 £500,000 £1,002,348 2017 2023
Rothesay TH2 £3,244,856 £200,000 £2,508,781 2017 2024
Tarbert Lochgilphead Regeneration Fund (Includes TCF Grant) £6,666,112 £3,140,000 £2,473,534 2018 Ongoing
Hermitage Park (Includes TCF and PBI Grant) £3,932,314 £553,317 £3,378,817 2016 2023
Kilmartin Museum RCGF & Council Grant  £7,663,403 £400,000 £275,000 2019 2023/24
Port Ellen Community hub, Islay RCGF grant  £1,570,259 £0 £1,096,223 2021/22 2024
Scalasaig business units, Colonsay RCGF grant  £480,481 £0 £335,000 2021/22 2024
Kilmory Business Park in Lochgilphead RCGF grant  £1,980,000 TBC £979,000 2021/22 2024
Lochgilphead CARS (Includes 22/23 PBI Grant) £2,200,782 £750,551 £1,269,731 2020 2026
Helensburgh CARS £2,400,000 £500,000 £1,240,000 2021 2026
Events and Festivals grants (including annual Mod) £165,150 £165,150 - 2023/24 2023/24
Place Based Investment 21/22* £260,000 £0 £260,000 2021/22 2022/23
Place Based Investment 22/23** £259,000 £0 £259,000 2022/23 2022/23
Placed Based Investment 23/24 £496,000 £0 £496,000 2023/24 2023/24
Placed Based Investment 24/25 £496,000 £0 £496,000 2024/25 2024/25
Crown Estate Funding 21/22 £1,634,604 £0 £0 21/22 Ongoing
Crown Estate Funding 22/23 £1,488,199 £0 £0 22/23 Ongoing
Crown Estate Funding 23/24 £1,590,409 £0 £0 23/24 Ongoing
Obair Ùr Thirodh – Tiree Community Business Hub - RCGF Grant £1,190,000 £0 £605,000 2022 2024
Kerrera Old School - Community Hub Final Phase - RCGF Grant £548,424 £0 £285,000 2022 2024
Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha - RCGF Grant £652,590 £0 £602,590 2022 2024
Islands Infrastructure Fund 21/22 £201,419 £0 £201,419 2021/22 2023/24

Page 16

Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Scotland Loves Local £46,000 £0 £46,000 2022/23 2024/25
LACER Fund £40,000 £0 £40,000 2022/23 2023/24
Islands Programme 22/23 - Island Community Halls Digital Hubs £100,000 £0 £100,000 2022/23 2023/24
Islands Programme 22/23 - Tobermory Seawall and Railings £450,000 £0 £450,000   2022/23 2023/24
Aros Waterfront outdoor activity hub – RCGF Grant      £414,565 £0 £403,500   2023/24 2024/25
Nonhebel Light Industrial Park Expansion – RCGF Grant   £1,004,000 £0     £654,000   2023/24 2024/25
Islands Programme 2023/24 - Rockfield Road, Tobermory Phase 1 £855,796 £0 £855,796 2023/24 2024/25
Islands Programme 2023/24 - Tiree Care Home £1,250,000 £580,000 £450,000 2023/24 2023/24
Tarbert Heritage Regeneration Scheme – Development Phase £140,000 £60,000 £80,000 2023/24 2023/24
Total £45,370,328 £6,849,018 £20,842,739     
* See separate 12th August 2021 Policy and Resources committee report for proposed breakdown of projects and values. The full award was £812,000 but
many of these projects are now complete.
** Full award for 22/23 was £712,000.  This figure has had the £200,000 awarded to Lochgilphead CARS deducted.  See separate 16th June 2022 Policy
and Resources committee report for proposed breakdown of projects and values.  3 of these projects are now complete.