ARGYLL AND BUTE COUNCIL                    ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                           21 MARCH 2024
SERVICES                     
LOCAL BRIDGE MAINTENANCE FUND 
1.0 INTRODUCTION 
1.1 This report provides an update on the £5.450M of funding secured through a
highly competitive bid process from Scottish Government’s £32million Local
Bridge Maintenance Fund. 
1.2 At the Environment, Development and Infrastructure Committee held in June
2022 a report was presented detailing the funding award for the replacement of 4
bridges and strengthening of a further 5. 
1.3 At the Environment, Development and Infrastructure Committee held in June
2023 an update report was presented detailing the negotiations regarding land
(for new bridges), ground investigation and design work has been progressing
well. 
1.4 Work at Ardchonnel Bridge commenced in November 2023 and has been
completed in February 2024. The works to Ardchonnel Bridge include
strengthening the abutments. This work being urgently required to prevent any
further deterioration and increased costs. 
1.5 Work at Whitestone Bridge has been awarded and is scheduled to commence in
March 2024 and is scheduled to complete in May 2024. Similar to Ardchonnel
Bridge, Whitestone Bridge was required to be progressed to strengthen the
abutments and reduce any further deterioration and increased costs. Whitestone
Bridge wasn’t considered to be quite as urgent as Ardchonnel, however, it is still
necessary to progress these works with minimal delay. 
1.6 Designs for Claonaig, Glenegedale (2), Lochgoilhead, Oude, Pennyghael Bridge
are currently progressing. Estimated costs have now been established for all
bridges through a feasibility study outlining preferred design options. Public
Consultations have been carried out for Oude Bridge and Glenegedale (2) Bridge
and are being incorporated into the final feasibility report. 
1.7 Since the bid was submitted to Scottish Government and as detailed in this report,
there have been significant price increases to construction contracts. These
increases mean that the allocated funding is not sufficient to deliver the
programme originally intended. Officers will be engaging with officials at Scottish

Page 2

Government to establish if other funding is available and to understand Scottish
Government’s position regarding the affordability of the original programme which
funding was allocated for. 
1.8 If additional funds are not forthcoming then the projects not delivered will be held
back pending additional funding coming from either external sources of council
capital programmes. Note all bridges will continue to be monitored as part of our
ongoing cycle of bridge inspections to ensure that our bridges are safe and
proportionate to use. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee consider this report and note that officers will be
engaging with Scottish Government regarding the increased costs. 
3.0 DETAIL 
3.1 The fund will be used to undertake proportionate works (from strengthening to
comply with ‘construction and use’ weight limits to full off-line rebuilds) on bridges
in need of repair, identified through our inspection programme/ records. Bridges
provide critical transport (often lifeline) connections for some communities and are
a vital part of the wider road network. 
3.2 The table at Appendix 1 details the list of bridges which have received funding
along with indicative site start dates. 
3.3 As noted in Appendix 1 a grant amount of £5.45M was secured based on pre
COVID estimates but the most updated cost estimations show that a cost of
approximately £12.5M will be required. There are seven principal reasons for
this significant increase in costs for the projects: 
• COVID – Cost estimations used to secure grant funds were completed
prior to the full extents of Covid to the economy being understood. The
impact to the Construction Industry resulted in large increased costs to
tender returns.
• Inflation – Although inflation is considered, the severity of it since 2021
could have not been reasonably predicted.
• Brexit – This brought further increase to costs as Contractors need to
charge more due to increase material costs because of import duties
and lack of availability of materials. 
• War in Ukraine – This had a knock-on effect regarding project costs due
to increasing fuel costs and increased cost of production. 
• PAS2080 (2023) – Due to recent environmental legislation as part of the
design/construction process we must consider steps to reduce/manage
carbon output for our projects which have economic repercussions.
• Active Travel Routes – To allow future sustainable transport links we
must include active travel routes on each bridge replacement project

Page 3

therefore increasing the width of each deck by 3.5m and any new
approach roads therefore increasing the overall construction costs.
However, we are also considering the cost to maintain existing bridges
to accommodate the active travel traffic. This potentially could reduce
the initial investment although the whole life costs are likely to be similar.
• Feasibility studies – Prior to submitting an application for each bridge
there was inadequate time to carry out a full feasibility study in order to
accurately estimate each project. Minimal design had occurred and
some of the main design constraints were unknown prior to the
application for funding. 
3.4 Due to the identified funding shortfall, all schemes have been prioritised.  The
prioritisation considers, network criticality, design life remaining of existing
structures, current condition of existing structure and cost. The outcome of the
prioritisation process is as follows: 
Bridge Cost 
1 (=) 00019-05 B842-150 Whitestone Bridge  £115,385
1 (=) 00019-29 B839-050 Lochgoilhead Bridge  £472,000
3 (=) 00019-38 B840-140 Ardchonnel Bridge  £93,353
3 (=) 00019-04 B842-010 Claonaig Bridge  £325,000
3 (=) 00019-30 A815-230 Cothouse Bridge  £662,000
6 (=) 00019-12 B844-010 Kilninver Bridge  £2,490,000 
--------------------------------------------------------------------------------------------------------
The bridges above the red line are affordable based on the available
funding. 
6 (=) 00019-37 A849-280 Pennyghael Bridge  £4,575,000
8 00019-25 A846-270 Glenegedale (2)  £1,620,000
9 00019-36 A816-120 Oude  £2,185,000 
3.5 We propose to write to the Scottish Government to alert them to the funding
shortfalls, clarifying the current position and to seek additional funding to progress
all schemes.  In the meantime work to progress the lowest ranked scheme, Oude
Bridge shall be paused. The total revised cost for all schemes above the line is
£4.158M. 
3.6 Location plans for each bridge can be found in Appendix 2. Regular updates
on these works as they progress will be provided through our weekly
members briefing.

Page 4

3.7 Legislation, Standards, Codes of Practice:
Replacement (new) structures are designed in accordance with: 
• Roads (Scotland) Act 1984 Legislation
• Design Manual for Roads and Bridges (DMRB) document “CD 350 -
The design of highway structures” and associated document series
“Highway Structures & Bridges”
• “CIHT 'Well-managed highway infrastructure' Code of Practice” Section
C6 and associated documentation.
• PAS  2080 - Carbon management in infrastructure and built
environment. 
Strengthening (maintenance) works to structures are designed, where
appropriate, in accordance with:
• Roads (Scotland) Act 1984 Legislation
• Design Manual for Roads and Bridges (DMRB) document series
“Highway Structures & Bridges”
• “CIHT 'Well-managed highway infrastructure' Code of Practice” Section
C6 and associated documentation. 
4.0 CONCLUSION 
4.1 This report provides an update on the £5.450M of funding secured in highly
competitive bid process from Scottish Government’s £32 million Local Bridge
Maintenance Fund. 
5.0 IMPLICATIONS 
5.1 Policy – projects are being taken forward to align with key policies like the Local
Outcome Improvement Plan and the Roads Asset Management Plan. Bridge
designs in terms of strength and resilience are required to follow nationally set
construction specifications. 
5.2 Financial – funded from grant funding. The successful award of grant funding
helps to reduce the backlog maintenance figure for the Council’s transport
infrastructure. Note, the original grant allocation is not now adequate to deliver
the full programme. 
5.3  Legal – the Council has statutory duties to maintain infrastructure set out in
various legislation like the Roads Scotland Act 1984. 
5.4  HR – None known. 
5.5  Fairer Scotland Duty: None known. 
5.5.1   Equalities - protected characteristics – an EqSEIA will be completed which
tease out and identify any equality issues which need to be considered for
new bridges.
5.5.2   Socio-economic Duty – none known.

Page 5

5.5.3 Islands – the programme will bring benefits to island communities which will
see two bridges being replaced which will help provide additional resilience to
the island’s transportation infrastructure. 
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  The provision for pedestrian facilities will be included as part
of the design for new build bridges together consideration for the projected
increase in sea levels due to climate change. 
5.7  Risk – None known. 
5.8  Customer Service – None known. 
5.9 The Rights of the Child (UNCRC) – the investment to improve our bridge
network will contribute to a safer environment for young people to thrive in. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads and Transport: Councillor Andrew Kain   
February 2023                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
jim.smith@argyll-bute.gov.uk 
Elsa Simoes, Infrastructure Design Manager 
elsa.simoes@argyll-bute.gov.uk 
Appendices: 
Appendix 1 – Bridge work details, prioritisation and cost
Appendix 2 – Bridge location plans

Page 6

Appendix 1 – Bridge work details, priorities and cost 
Prioritisation Bridge Name
Asset
sustainability or
asset
improvement
Description of Works
2021 Grant
Amount based
on pre COVID
estimates 
Estimated
Cost @ 2024
Site
Start
Date
Estimated
Completion
Date
=1 B842-150 Whitestone Bridge Sustainability Additional retaining buttress structure constructed on
downstream face of existing bridge. Works required to
be progressed to reduce further deterioration and
increase costs.
£40,000 £115,385 Mar 24 May 24
=1 B839-050 Lochgoilhead Bridge Sustainability Strengthening of arch barrel, including waterproofing,
temporary traffic diversion and drainage works.
£198,000 £472,000 Apr 25 Mar 26
=3 B840-140 Ardchonnel Bridge Sustainability Works started due to safety requirements.
Additional retaining buttress structure constructed on
downstream face of existing bridge.  Works required to
be progressed to reduce further deterioration and
increase costs.
£40,000 £93,353 Nov
23
Feb 24
=3 B842-010 Claonaig Bridge Sustainability Strengthening of wing walls, realignment of road and
drainage works.
£477,000 £325,000 Jan 25 May 25
=3 A815-230 Cothouse Bridge Sustainability Installation of deck waterproofing system (under road
surface), installation of new expansion joints, joint
sealings, concrete repair works, drainage works,
vehicle barrier partial replacement, vegetation removal
£517,000 £662,000 Aug
24
Jun 25
=6 B844-010 Kilninver Bridge Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway)).  
Feasibility Study largely completed
Public Consultation being progressed early 2024.
£1,194,000 £2,490,000 Aug
25
Aug 26 
Affordable schemes from Local Bridge Maintenance Funding subject to Scottish Government
confirming the change in programme
£4,157,738 Subtotal of schemes
above
=6 A849-280 Pennyghael Bridge Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway) downstream / seawards.  
Feasibility Study largely completed
Public Consultation being progressed early 2024.
£1,193,000 £4,575,000 Aug
25
Jul 27
8 A846-270 Glenegedale (2) Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway) in same location. 
A public consultation has been completed.
Feasibility Study identifies preferred option to progress.
£597,000 £1,620,000 Jun 25 Dec 25
9 A816-120 Oude Bridge Improvement/new
structure
Full bridge replacement (with an active travel route –
footway/cycleway) upstream / northwards.  
A public consultation has been completed.
Feasibility Study identifies preferred option to progress.
Project in abeyance due to funding shortfalls. 
£1,194,000 £2,185,000 Mar 26 Aug 28
Total   £5,450,000 £12,537,738