Electric Vehicle Charging Strategy Update

Argyll and Bute Council · 21 March 2024
Back to Environment, Development and Infrastructure Committee — 21 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL         ENVIRONMENT, DEVELOPMENT AND      
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE                    21 MARCH 2024 
ELECTRIC VEHICLE CHARGING STRATEGY UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council has increased its network of public Electric Vehicle
Chargers (EVC) since the last time this was reported to Environment,
Development and Infrastructure Committee (EDI) from 28 to 37 thanks mainly to
an investment of nearly £400,000 through the HITRANS FASTER project. Since
formally adopting the EVC expansion plan in December 2022 officers have
engaged with Scottish Government through Transport Scotland with a view to
accessing funds from the £30million Electric Vehicle Infrastructure Fund (EVIF)
but unfortunately, at the time of writing this report, we have not yet had any funding
allocation or formal feedback on our submission. It is understood that no Local
Authorities have yet received funding from the new fund. 
1.2 As EVC becomes increasingly popular, and as the ban on new internal
combustion engine vehicles approaches, there is a clear need for a
comprehensive roll out of charging points and arrangements to sustainably
manage and maintain these. 
1.3 This report provides an update under various headings: 
• EVC expansion plans and the Scottish Government’s Electric Vehicle
Infrastructure Fund (EVIF)
• Maintenance of the current network
• Update on network expansion 
1.4 Background information including previous committee reports is available on the
Council website here. 
1.5 In December 2022 the EDI Committee considered a report on the EVC strategy
and formally agreed the development methodology and expansion list following a
public consultation and development of the expansion list through a Member
Seminar. That reports with its various appendices is available here at agenda item
6.

Page 2

1.6 It is recommend that the Environment, Development and Infrastructure
Committee is asked to:
• Consider and note the ongoing work to develop and manage the EVC
network. 
• Agree that Officers should continue to engage with Transport Scotland on
future funding options through the new Electric Vehicle Infrastructure Fund
and that a specific Member Seminar will be arranged on EVC when there is
clarity on how that fund will operate and be allocated. 
2.0 RECOMMENDATIONS
2.1 The Committee is asked to:
• Consider and note the ongoing work to develop and manage the EVC
network. 
• Agree that Officers should continue to engage with Transport Scotland on
future funding options through the new Electric Vehicle Infrastructure Fund
and that a specific Member Seminar will be arranged on EVC when there is
clarity on how that fund will operate and be allocated. 
3.0 DETAIL 
3.1 EVC expansion plans and national Electric Vehicle Infrastructure Fund (EVIF)
3.1.1 A detailed methodology was presented to the June 2021 meeting of this
committee, then discussed at a Member Seminar in September 2021 which led
to changes to the original proposed methodology. The original draft had sites to
be prioritised large towns to small, whereas feedback from the seminar meant
that we changed the prioritisation to focus on small villages/towns first on the basis
that larger towns already have at least one charger. We had also originally
proposed to cut off at settlements smaller than 1,000 population but following
feedback we included villages with a smaller resident population than that but
acknowledging that tourist traffic is significant. An updated draft list and
methodology was then presented to the December 2021 meeting. 
3.1.2 The agreed draft development methodology and site list went out to public
consultation to ensure that communities had the opportunity to be involved in the
process of deciding where future public EVCs installations should be across the
Council area, and how that network should be developed and prioritised. 
3.1.3 We received 254 responses from across Argyll and Bute; and as well as giving
views on specific questions, respondents also provided more than 500 comments.
The full consultation findings report is appended to the last report to EDI at
Appendix 3 and an overview of themes from the consultation is at Appendix 4 of
that same agenda item. These can be accessed here.

Page 3

3.1.4 The list is based on theoretical locations based on feedback and knowledge to
date. It is anticipated that as the list is worked through there could be infrastructure
limitations due to limited grid capacity across many locations in Argyll and Bute or
technical considerations which may prevent development at a specific site.
Although the development methodology provides for different priority bands, until
such time as there is clarity on the possible future funding options it is not possible
to develop a method to determine how that funding should be allocated to sites
within the priority bands e.g. how sites are prioritised within the priority bands
against available funding. As and when there is clarity on external funding a
further report will come forward for Members to agree funding allocations.
3.1.5 The Environment, Development and Infrastructure Committee at its meeting in
December 2022 agreed the following –
1.    agreed the development and prioritisation methodology at Appendix 1 to
the submitted report, and the 55 site electric vehicle charging expansion
list at Appendix 2 of the submitted report, noting that the expansion plan
was supported by three-quarters of respondents to the electric vehicle
charging public consultation; and
2.    noted that Officers would continue to engage with Transport Scotland on
future funding options through the new Electric Vehicle Infrastructure Fund
and that a specific Member Seminar would be arranged on electric vehicle
charging when there was clarity on how that fund would operate.
3.1.6 Since then Officers have been engaging with Transport Scotland through the
Scottish Futures Trust to understand more about how the national fund will
operate and how we might access it. The Scottish Government’s vision for EVC
expects that £60million of investment will be made in EVC, with that investment
to be 50% publicly funded by Scottish Government, with the other 50% coming
from private finance.  
3.1.7 It is not clear how the private element will work – it is recognised that Local
Authorities should have flexibility to develop a long term delivery model for their
area which takes into account their own circumstances and each Local Authority’s
level of appetite for future involvement in the delivery and management of an EVC
network. In an Argyll and Bute context, what is clear is that there is limited
commercial appetite for large scale EVC development. While we have had the
odd ad hoc approach from private companies these have tended to be somewhat
niche and site specific e.g. a possible pilot venture to convert streetlights to EVC
which did not develop beyond early discussions; and discussions with a private
provider who is seeking to install EV infrastructure in a specific location in order
to support a specific service provision, electric buses from Oban to Edinburgh. On
the face of it, it seems likely that if there were genuine commercial opportunities
of scale available within our area we would have been contact by potential
providers/private sector partners. There are also instances of private
supermarkets providing EVC for their customers in their own car parks, which is
of course welcomed but does not, by its very nature, align with any overarching
public transport development strategy.

Page 4

3.1.8 Our experience of private interest is similar to that of other rural Local Authorities
we are in discussion with through professional networks. In many parts of Argyll
and Bute the infrastructure costs will be high to connect to the grid and/or to
upgrade capacity. It is therefore likely that any vision which includes an equitable
level of provision to ensure that no communities are disadvantaged/face barriers
to EVC access is likely to fall on the public sector. 
3.1.9 We have received informal feedback from Scottish Future Trust in the summer of
2023 that they would like us to provide a greater amount of evidence to show
market failure in Argyll and Bute. With this in mind we have joined a procurement
exercise called a PIN, which stands for Prior Information Notice, with various
Councils across the Northern Roads Collaborative area. We are currently
awaiting feedback from that exercise. 
3.1.10 Our EVIF submission was considered by the EVIF Advisory Panel which
comprises representatives from Transport Scotland, Scottish Future Trust and the
Energy Savings Trust, in October 2023. We have not as yet had any formal
feedback from that meeting although in dialogue with Transport Scotland in early
January they advised that we should receive this shortly.  A feedback letter was
received in mid-February. This letter outlined a completely new formal application
process which we will now work through, along with some generally positive
informal feedback on the information we submitted previously. 
3.1.11 It is unfortunate that we do not yet have clarity on what funding allocation we will
receive from EVIF as the Council is not in a position to make any long-term
decisions on the delivery of EVC in Argyll and Bute without more information on
the amount of funding we will receive. The latest feedback highlighting a
structured application process with guidance notes is, however; to be welcomed.
The recommendation from the December 2022 EDI report regarding a future
Member Seminar once there is clarity on the position is also recommended in this
report as, unfortunately, the position remains largely the same as it was then. 
3.1.12 Officers will urgently look to complete the new EVIF application and will continue
to liaise with Transport Scotland and the Scottish Futures Trust, and will also
continue to explore any private finance options that may be available to us. It is
not possible to say with any certainty what our EVIF allocation might be – it would
be prudent at this stage to begin to consider what the Council may wish to do if
the allocation is less than we might require to deliver our expansion plan. If that is
the case there would be a number of options to consider:
Option Comments
Revise/reduce the scope of the plan It would be sensible to revisit the
strategy when there is clarity on
funding, however; reducing its scope
would not be consistent with the
agenda to decarbonise transport due
to the climate emergency. Across all
public infrastructure we need
significantly more and better EV

Page 5

chargers to support the changeover to
electric vehicles 
Council investment in EVC to make up
any shortfall
A business case can be developed to
look at if or how this could be self-
financing across the whole asset
group, with some busier assets likely
to generate a surplus to cross-
subsidise assets which are required in
more rural areas to provide equitable
provision but which by their nature are
likely to operate at a loss This option
would likely need to be accompanied
with a significant increase in EVC fees
for users
Explore externalising the network to a
private provider
There has been limited private interest
so far, but this is something we can
further explore, although Officers have
concerns that such a model would not
provide an equitable provision. We
could explore externalising some sites
and retaining others but this would
lead to a mixed model which could
have the effect of having a two tiered
system of access to EVCs with
different fees in place.   
3.2 Maintenance of the Network/Fault Issues 
3.2.1 Fault reporting is simple for the EVC user; it can be done via the Charge Place
Scotland (CPS) phone number which is on all units or their online form.  Once
received it is assigned a ticket number and various back office troubleshooting is
undertaken to try and bring the unit back into use remotely. If this communication
fails an engineer is scheduled with a Service Level Agreement (SLA) of 48hrs,
unfortunately the SLA is rarely met due to a combination of staff over
commitments and our geography.  This is not uncommon across all Local
Authorities. We are finding that providers price based on the 48hrs service
standard but submit a lower price for a 72hrs standard. Given that the 48hrs is
rarely met we are likely to alter our maintenance contracts in the future to a more
realistic timeline which will also provide best value. If the fault can be fixed within
the warranty agreement this is carried out and if not a quote for the work is
provided directly to the Council for approval and authorisation. Once the fault is
rectified the back office system is updated.  Overall we are seeing improvements
thanks to our approach which provides for continuity between the day to day and
the long term strategy development   
3.2.2 We have been proactive with the management and maintenance of fault and
issues through the Project Officer post which also works on strategy development
as well as supporting other key projects like Route Optimisation.  We are
monitoring faults and adding service disruptions to the Council’s website, liaising

Page 6

closely with providers to stay up to date on faults that run longer than the SLA and
have recently brought a number of chargers under a single maintenance contract. 
3.2.3 Due to the nature of funding awards in the past, piecemeal, year on year amounts,
and in the absence of a strategy pre 2021, the network has a mixture of
maintenance arrangements. Transport Scotland have previously provided
funding to extend existing warranty packages, and prior to the strategy being in
place this is what was done. The warranty and maintenance packages have
proven not to be entirely reliable, with part replacement falling out with the
standard contract Terms and Conditions, and costs falling on the Council to bear,
with these costs being managed through the existing budget/fee recovery model.
In effect the warranty and maintenance contracts cover what is internal to the units
but not the items which are external. This year our non-contract spending on EVC
maintenance has been c.£9k. As warranty and maintenance packages have
ended we have looked to bring as many assets as possible under a single
umbrella contract. We have been limited with some of the assets as the units
previously installed could only be maintained by a single company. Over the
course of 2023 we have successfully brought 13 chargers into a single robust all-
encompassing maintenance contract with clear Key Performance Indicators.
3.2.4 Across Scotland Local Authorities are experiencing external funding for
maintenance dry up with the cost burden falling to Local Authorities. With this in
mind we have been planning for the long-term in how to make our network
sustainable, which is why we recommended a fee increase for financial year
24/25. Previously our fee structure covered electricity costs to the Council and a
small element to cover the non-contract spend mentioned above, whereas going
forward our fee structure will need to cover asset management costs in addition
to the other costs of the network. 
3.2.5 The Council’s approach to date has largely been to utilise external money coming
through the Scottish Government, HiTrans etc. It is assumed that Members would
wish to continue with this approach although it may be that Members would
consider investing limited Council resources directly into the provision of
additional charging points. 
3.2.6 The current charge per KwH is £0.29. As part of the Budget process in February,
this charge proposed to increase to increase to £0.45 per hour from April. This
increase covers increased electricity charges from utility companies, ongoing
maintenance and is designed to provide a small surplus which can be reinvested
into replacement of charging units. This moves our charges more towards a
market rate although is still some way short of supermarkets in Argyll and Bute,
for example, who charge 79p per kWh in some cases. Below is a table showing
the 2023/24 EVC tariffs across Local Authorities. .

Page 7

3.3 Update on Network Expansion 
3.3.1 The full, live expansion list is available at Appendix 1 of this report, with changes
colour coded. A summary of the work to expand the network is provided in the
table below, which is in addition to the significant work to develop better day to
day management arrangements for the existing network. The team continue to
liaise with government agencies and other Local Authorities, and represent the
Council on national groups, to ensure they are at the forefront of developments
in what is a fast growing industry. Significant work is also being undertaken with
colleagues in Procurement to let various contracts and look at developments,
liaise with framework suppliers and installers etc. Ultimately we will look to have
a single contract for installs once the position on EVIF is clear, which will drive
consistency across the network. 
Item Funding Comments
HITRANS FASTER
project
c. £400,000 This has delivered 8 rapid
chargers at the following
locations: 
• Two at Dunoon
Coal Pier;
• Two at Rothesay
Pier, Isle of Bute;
• One at Tarbert
Harbour;
• One at Ledaig Car
Park, Tobermory,
Mull; and
• Two at Corran
Halls Public Car
Park, Oban
£0.00£0.10£0.20£0.30£0.40£0.50£0.60£0.70£0.80£0.90
Aberdeen City…
Aberdeenshire…
Angus Council
Argyll &
Bute…
Clackmannanshir…
Dumfries and…
Dundee City…
East…
East Lothian…
Falkirk Council
Fife Council
Glasgow
City…
Inverclyde Council
Midlothian Council
Moray Council
North Ayrshire…
North…
Orkney Island…
Perth and Kinross…
Renfrewshire…
Scottish Borders…
Shetland Island…
South…
Stirling Council
The City of…
The Highland…
West…
West Lothian…
Local Authority EVC Tariff
FAST RAPID

Page 8

Council business
chargers
£157,000 from Switched
on Fleets 
Successful installs at
Jackson’s Quarry depot,
Oban, and an additional
unit at Helensburgh Civic
Centre 
Out to tender for installs
at the Hub Offices at
Union Street, Rothesay
and Kintyre House,
Campbeltown to support
the office rationalisation
project. 
These chargers have the
effect of increasing the
public network as it
means there are specific
chargers for Council
business use which
relieves pressure on the
public network. We have
also been working with
NHS and other public
partners about use of
each other’s chargers
with a view to developing
a wider partnership
approach to fleet
decarbonisation. 
Tarbert  £45,000 from SSEN Funding has now been
secured for this and is in
the Council’s accounts.
We are currently out to
tender for this as part of
the same exercise for the
above office installations.  
Tighnabruaich £63,000 from Transport
Scotland
This scheme was
delivered in 2022/23 
4.0 CONCLUSION
4.1  A significant amount of work is ongoing to develop a network which will support
decarbonisation and lead to cleaner, greener transport. How the strategy
develops from this point will largely depend on clarity on future funding and will
need to be the subject of future discussions, report and decisions.

Page 9

5.0 IMPLICATIONS 
5.1 Policy – EVC strategy expansion plan and development methodology has been
formally agreed in December 2022. It may be the case that this needs to be
revisited depending on the outcome of the EVIF application.
5.2 Financial – cost recovery model is covering electricity costs and have been
recommended for adjustment to cover asset management costs which were
previously externally funded; capital costs currently 100% externally funded.
5.3  Legal – None. 
5.4  HR – None.
5.5  Fairer Scotland Duty:
5.5.1   Equalities - protected characteristics – None.  
5.5.2   Socio-economic Duty – None.  
5.5.3   Islands – Gaps in the network are prioritised through the public programme. 
5.6 Climate Change – Implications for climate change through EVC strategy are
very positive. Expanding our public network will encourage people to transition
to electric vehicles, reducing CO2 emissions and moving towards a cleaner,
greener transport system. 
5.7 Risk – In terms of future options, there may be risks associated to a
commercial model.
5.8    Customer Service – Work to ensure a better maintenance and warranty
contract is increasing network reliability and providing a better service for our
customers. 
5.9 The Rights of the Child (UNCRC) – None arising from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure
Policy Lead for Roads and Transport, Councillor Andrew Kain
February 2024                                               
For further information contact: 
Jim Smith, Head of Roads and Infrastructure 
Jim.smith@argyll-bute.gov.uk 
Mark Calder, Project Manager
Mark.calder@argyll-bute.gov.uk

Page 10

Victoria Weir, Project Officer 
Victoria.weir@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – updated EVC expansion list