Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD 
14 June 2024 
SUPPLEMENTARY PACK 1 
ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE - ON A HYBRID
BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY MICROSOFT
TEAMS on THURSDAY, 20 JUNE 2024 at 10:30 AM 
I enclose herewith item 7 (SECOND DOMESTIC BIN REVIEW 2024) and item 8 (UPDATE -
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25) which were marked to follow on
the Agenda for the above meeting. 
Douglas Hendry
Executive Director 
ITEMS TO FOLLOW 
7. SECOND DOMESTIC BIN REVIEW 2024 (Pages 3 - 8)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
8. UPDATE - ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 
(Pages 9 - 26)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
Environment, Development and Infrastructure Committee 
Councillor John Armour (Chair) Councillor Graham Hardie
Councillor Willie Hume Councillor Andrew Kain
Councillor Jim Lynch Councillor Tommy MacPherson
Councillor Ian MacQuire Councillor Luna Martin
Councillor Liz McCabe Councillor Ross Moreland
Councillor Gary Mulvaney Councillor Alastair Redman
Councillor William Sinclair Councillor Andrew Vennard
Councillor Peter Wallace   
Contact: Hazel MacInnes  Tel: 01546 604269
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

ARGYLL AND BUTE COUNCIL      ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE SERVICES         20 JUNE 2024 
SECOND DOMESTIC BIN REVIEW 2024 
1.0 INTRODUCTION
1.1 In 2016, the Council approved a policy to move to three weekly general waste
(green bin) and fortnightly recycling (blue bin) collections. This policy change
was introduced to encourage more recycling which would bring significant
environmental benefits and also to reduce the amount of general waste taken
to landfill. Landfill has both an environmental and financial implication,
currently landfill tax costs the Council in excess of £3m per annum. 
1.2 With the Biodegradable Municipal Landfill Ban (BMW) coming into place in
January 2026, the advancement in technology and the Council introducing
route optimisation, now is considered to be a good time to consider a review
of all second domestic bins to all householders in all areas of Argyll and
Bute’s waste collection service. 
1.3 A review will provide an opportunity to reduce the number of households
receiving a second domestic waste bin collection, who are not entitled to
receive this service.  Alongside the review, information will also be provided
that gives advice on how to produce less green bin waste by recycling more
and remind customers that they are entitled to an additional blue bin (for co-
mingled recyclable materials excluding glass), free of charge should they
require it.   
1.4 This report provides an update to the report considered by the Environment,
Development and Infrastructure Committee in March 2024 which can be
viewed here at item 9: Agenda for Environment, Development and
Infrastructure Committee on Thursday, 21 March 2024, 10:30 am - Argyll and
Bute Council (argyll-bute.gov.uk) 
2.0 RECOMMENDATIONS
2.1 It is recommended that members of the Environment, Development and
Infrastructure Committee: 
i. endorse the second domestic bin review and; 
ii. note the progress made regarding the publicity and the timeframe and
Page 3 Agenda Item 7

Page 4

that further updates will be provided as the review progresses.   
3.0 DETAIL
3.1  In June 2016, the Council considered a report proposing an operational
service procedure and which provided operational detail to support the Policy
that the Council agreed at its meeting on 11 February 2016 as part of Service
Choices. The full report can be viewed here: ARGYLL & BUTE COUNCIL
(argyll-bute.gov.uk)  and the service procedure is appended to this report at
Appendix 1.
3.2  Disposal of general waste has both environmental and cost implications.
Whilst the existing PPP contract for part of Argyll and Bute processes material
via a Mechanical Biological Treatment plant (which takes out of the waste
stream some materials which can be recycled or composted), this process is
expensive and is not an approved treatment type beyond the BMW Ban. As
such we don’t encourage the use of second green bins because our focus is
on recycling, however, we understand that, for some people, a second
general waste bin may be needed. We will consider a second green bin if: 
• There are five or more people in a household 
• Someone in a household has a medical condition which means more
waste is generated 
3.3 There appears to have been some confusion as to whether households with
babies in nappies are eligible for a second bin.  The criteria noted in the
paragraph above is what we work too and therefore a second green bin is not
provided for households with babies in nappies.   
3.4 Second blue bins (for co-mingled recyclable materials excluding glass) are
available free to all households who are producing more recycling material
than will fit in a single bin. The co-mingled recyclable material is taken to be
processed and reused – this both reduces the amount of virgin materials
which are required and also reduces the amount of material taken to landfill,
both of which have environmental and financial benefits.
3.5 Prior to the roll out of the review, there will be a social media campaign and
additional information added to the Council’s website explaining that the
review of second domestic bins is being progressed with the main aim of
reducing the amount of general waste, encouraging more recycling and as a
result making both environmental and financial savings.   
3.6 A study carried out by the Operations team has highlighted that there are
approximately 3,382 additional domestic bins across all areas, this amounts to
an additional 57,494 uplifts of domestic waste per annum. The information on
the reasons for second bins held in our system only goes back to 2021 and it
notes that there was 146 bins made available to families of 5 or more, 406
bins made available due to medical conditions and 513 bins provided for
Page 4

Page 5

children in nappies (which as noted above, is not one of the core criteria).  We
will make contact with all of these households, to check the information
remains current and in the case of children in nappies, advise that a second
bin will not be uplifted.   
3.7 Given that the Council collect bins from over 48,000 households, the process
of no longer collecting non-eligible second bins will be challenging, however,
when the routine optimisation system is functioning, it will be easier to identify
locations where second bins are eligible.  Where second bins are present, but
not eligible, residents will be notified and the second bins will not be collected.  
3.8 The service has been working closely with colleagues in the Council’s
Customer Engagement and Transformational Team to create a new function
that will allow automatic reviews for the need for a second domestic waste bin
to take place. Automated templates have been created which will record
information including customer responses and reasons for additional bin.
3.9 Phase 1 of the review will commence on 1 July 2024, this will be a small batch
of 50 to 60 households, this will allow us to gauge the number and type of
enquiries received and identify any issues raised. Further phases will proceed
on 1 August, 1 September and 1 October. 
Review Timeline
Stage Completion Date
Ongoing liaison with Customer Services
via a workshop session regarding
possibilities and to also understand
current levels of demand
Commenced and ongoing
Updating of records for all approved
second green bins, where possible due
diligence on ongoing eligibility for second
green bins
Commenced and ongoing
Publicity and timeframe for roll out to be
prepared 
June EDI Committee
Publicity campaign advising of any agreed
output from EDI Committee
To commence following EDI
Committee June 2024
Checking and verifying of second green
bins and where second bins are not
eligible
July 2024 onwards
Notification batches go out with a
two week completion / return
date. With a minimum of 5
batches to be sent July – October
we have to allow for the
applications to be returned and
verified.
Page 5

Page 6

Review to be completed by end of
2024.
Rollout of notification for any non-approved
second green bins and actively managing
this through the deployment of warden
resource.
Estimated start January 2025
Completion date to be confirmed
pending no. of unauthorised
second green bins to be dealt
with. 
3.10 Zero Waste Scotland, on behalf of Argyll and Bute Council, have recently
carried out a waste composition analysis on Islay and in Oban. The draft
report from this is currently being considered and will be shared with Members
in due course. The purpose of the composition analysis is to provide an
understanding of the typical waste that is being disposed of in residential bins.
This intelligence can then be used in marketing and publicity campaigns to
further reduce the amount of general waste and increase recycling levels.
Composition analysis also provides information which would be required by
SEPA to confirm whether or not the general waste collected in Argyll and Bute
can be processed in Energy from Waste (EfW) plants without any pre-
treatment requirement. In addition, we are in the process of procuring
specialist Artificial Intelligence (AI) cameras which will be trialed on a small
number of refuse collection vehicles. These cameras will record information
and will provide further intelligence of the composition of our waste stream. 
4.0 CONCLUSION
4.1 This report proposes that a review of second bins is carried out and in line with
the Policy agreed in June 2016. All eligible second green bins must be identified
and non-eligible second domestic bins will cease to be collected. This will help to
reduce the amount of domestic waste presented at kerbside, encourage
residents to increase recycling and reduce the amount of material which is
currently processed for landfill. 
4.2 Further updates on the review will be presented to future meetings of the
Environment, Development and Infrastructure Committee. 
5.0  IMPLICATIONS
5.1 Policy – As per the Policy agreed in June 2016 at the introduction of 3 weekly
waste collections.
5.2 Financial – It is expected that there will be future waste collection and disposal
savings as a result of this exercise.  
5.3  Legal – None known.
5.4  HR – None known.
5.5  Fairer Scotland Duty: None known.
5.5.1   Equalities - protected characteristics – None known.
5.5.2   Socio-economic Duty: None known.
Page 6

Page 7

5.5.3 Islands – None known.
5.6 Climate Change – Reducing waste currently processed for landfill and
increasing recycling. There should also be a slight reduction in fuel used for
vehicles used in the waste collection and disposal process.
5.7 Risk – Representation from individuals who may lose a second bin service
5.8  Customer Service – Residents may have become dependent on their second
general waste bin. Detailed communications will need to be carried out to
keep citizens involved with this proposal and the reasons it is being
progressed.
5.9 The Rights of the Child (UNCRC) – refuse collection and recycling can have
environmental benefits and contribute to the positive future of young people. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
May 2024 
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
jim.smith@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
tom.murphy@argyll-bute.gov.uk 
Page 7

Page 8

This page is intentionally left blank

Page 9

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                   20 JUNE 2024
SERVICES                     
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 – UPDATE
REPORT 
1.0  INTRODUCTION 
1.1 In March 2024, the EDI Committee endorsed a report providing details of the
proposed roads reconstruction programme for 2024-25.  The programme was
based on the 2024-25 allocation of a total of £8.0M.   
1.2 This report provides an update on changes to the programme to be endorsed by
Members.  The programme remains based on the 2024-25 allocation.   
2.0  RECOMMENDATION 
2.1 It is recommended that the Environment, Development and Infrastructure
Committee:   
• Endorses the amended programme of capital works for 2024-25
• Agrees that details of each area committee’s programme will be forwarded on
to individual Elected Members. 
3.0  DETAIL 
3.1  It has come to my attention that the roads reconstruction programme presented
to Members in March 2024 was based on a desktop exercise using various
sources of data as well as having input from Members as part of the Area
Committee business days held last year.  Whilst the desktop exercise provides a
good starting basis for developing the final programme, it doesn’t reflect detailed
local course visual inspections and as noted in the March report, would not reflect
any winter deterioration experienced on the road network.   
3.2 The local course visual inspections and measurements were carried out later than
normal mainly due to resourcing issues as a result of the response to the large-
scale flood and road closure incidents experienced last year from October 2023
and the knock-on effect this has had on workloads, in addition to sickness
absence of some key individuals involved in the process.   
Page 9 Agenda Item 8

Page 10

3.3  The local course visual inspections and measurements now carried out by officers
have identified, in some areas, where the original programme reported in March,
should be amended. All schemes costings have been updated now that
measurements have been carried out.  There are new schemes added into the
programme and schemes that have now become unaffordable that have had to
be de-prioritised; it should be noted that schemes raised by Members at the Area
Business Days have remained in the programme.   Details of the new schemes
and those that are no longer affordable are noted in Appendix 1 and are
summarised below.  The full revised programme is included in Appendix 2.   
MAKI 
A total of 31 Schemes were presented to the EDI Committee totaling £2.48M 
The updated report presents a total of 31 Schemes with the same budget of
£2.48M. However there have been changes to some scheme costings and: 
• 2 schemes added in Mid Argyll and 2 schemes rescheduled. 
• 1 scheme added on Kintyre with 3 rescheduled.
• 2 schemes added on the islands and 1 scheme rescheduled.   
Members are asked to note: 
a. There is an estimated outturn over budget allowance of £33,395.21, for Mid
Argyll, this was because of the urgent need to include the C43 Crinan Canal
works where the Council are responsible for maintaining the surface over Loch
4. Failure to carry out this work may well lead to a malfunction in the bridge
mechanical system which would cause issues for Scottish Canals which we
would potentially be liable for. 
b. There is an estimated outturn over budget allowance of £27,103.49 for Kintyre,
this is preparation work for the 2025-26 Surface Dressing works. 
c. There is an estimated outturn under budget allowance of £8,895.48 for the
island work. Should this remain, the budget will roll into next years island
works. 
If the costs remain in excess of the relevant area budget, we will draw down from
next year’s capital budget as has been done in previous years. 
B&C 
A total of 20 schemes were presented to the March EDI Committee totaling
£1.6M. 
The updated report presents a total of 21 Schemes with the same budget of
£1.6M. However there have been changes to some scheme costing and: 
• 1 Scheme added in Cowal with 3 schemes rescheduled.
Page 10

Page 11

• 4 Schemes added in Bute with 1 scheme rescheduled. 
Members are asked to note: 
a. There is an estimated outturn under budget allowance of £9,406.04 and
£9,406.64 respectively for Bute and Cowal, if the costs remain unspent this
will roll over into next years Bute and Cowal Budget. 
OLI 
There have been no schemes added or removed in OLI, however some schemes
have been re-costed to deliver best value. The budget remains the same at
£2.8M.   
Members are asked to note: 
a. There is an estimated outturn over budget allowance of £18,089.23, Oban and
Lorn, this was due to more accurate estimates when officers carried out
course visual inspections. 
b. There is an estimated outturn under budget allowance of £7,285.27 for the
Isles, this was due to more accurate estimates when officers carried out
course visual inspections. 
If the costs remain in excess of the relevant area budget, we will draw down from
next year’s capital budget as has been done in previous years. If costs remain
under budget these will be rolled onto next years budget as has been done in
previous years. 
H&L 
There has been 1 scheme added due to available budget after re costings in
Helensburgh and Lomond, and some schemes have been re-costed to deliver
best value. The budget remains the same at £1.12M. 
Members are asked to note: 
a. There is an estimated outturn under budget allowance of £1,842.17 for
Helensburgh and Lomond, if the costs remain unspent this will roll over into
next years Bute and Cowal Budget. 
3.4  It should be noted that any amendments seek to deliver better value for money,
this being the approach over the last decade where we have carefully applied
a strategy of delivering revenue and capital funding collectively and delivering
a series of works designed to minimise reactive work, carry out right first-time
repairs wherever possible and to deliver surfacing techniques and
specifications which maximises the amount of repairs and resurfacing which is
Page 11

Page 12

delivered.  Members will be aware that the investment that the Council has
made over a number of years and the approach to allocating the funds has had
a positive impact on the Council’s overall Roads Condition Index.   
3.5  The roads reconstruction programme will continue to be delivered by a mixed
economy model with the Councils in-house team delivering carriageway
reconstruction and patching works. The surface dressing element of the
programme will be delivered by an external contractor. This enables the maximum
surface area to be covered which will help to seal carriageway cracks, prevent the
ingress of water and reduce the amount of reactive maintenance for potholes. 
3.6  In 2023-24 there was also a grant from the Strategic Timber Transport Scheme
(STTS) totaling £387k. This grant was significantly less than in previous years and
officers expected this to continue in the current frugal economic climate. Officers
have now been informed that our bids for 2024-25 funding have been rejected
and no funding will be available through STTS for this financial year. This is a
similar position being experienced by other Councils across Scotland. 
3.7  The programme for each of the administrative areas will be forwarded to Area
Committee Members if endorsed by the Committee today. The programme will
also be available on the council website with key scheme status and dates. 
4.0  CONCLUSION 
4.1  This report provides an update on changes to the roads reconstruction
programme to be endorsed by Members.   
5.0  IMPLICATIONS 
5.1  Policy - works assessed and carried out under the current Roads Asset 
Management Plan. 
5.2  Financial - programme will be based on capital allocation for year 2024-25. 
5.3  Legal – None known. 
5.4  HR - reconstruction works delivered by a combination of in-house roads 
operations team and sub-contractors. 
5.5  Fairer Scotland Duty: None known. 
5.5.1  Equalities - protected characteristics – None known. 
5.5.2  Socio-economic Duty – None known. 
5.5.3  Islands – None known. 
5.6  Climate Change – due regard will be given to climate change with a view to 
minimising any climate change impact and these will be considered as and 
Page 12

Page 13

when they arise. 
5.7  Risk - completed works will reduce requirement to repair roads and will arrest 
the carriageway/footway deterioration. 
5.8  Customer Service - overall improvement in road surfaces and the quality of 
driven journeys. 
5.9  The Rights of the Child (UNCRC) – the investment to improve our road network 
will contribute to a safer environment for young people to thrive in. 
Executive Director with responsibility for Roads and Infrastructure: 
Kirsty Flanagan 
Policy Lead for Roads and Transportation:
Councillor John Armour 
June 2024  
For further information contact: 
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
jim.smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
hugh.oneill@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
tom.murphy@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Changes to Programme reported in March 2024 
Appendix 2 – Amended Roads Reconstruction Programme 2024-25 
Page 13

Page 14

This page is intentionally left blank

Page 15

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
This appendix includes the list of new schemes or schemes that are no longer part of
this year’s capital programme (subject to approval).   
The schemes where the estimate is different to March are not included in this
Appendix.  The full revised programme is included in Appendix 2.   
The schemes above the red line are in the programme and those below are no longer
part of the programme.   
MID ARGYLL, KINTYRE AND THE ISLANDS
MID ARGYLL 
Scheme
Location, Road
Number/Name
Works Type Estimated
Cost 
March EDI
Updated
Estimated
Cost June
EDI
Reason for
being added or
rescheduled
U38 Barmolloch
(Upper
Kilmichael Glen) 
Overlay New
Scheme
Added
£115,816.03 The local
Operations
team reviewed
this and
believed this
scheme was
required as a
priority.
C43 – 010 Lock 4
Bridge Deck
(Material to be
confirmed)
Deck Surface
Replacement
New
Scheme
Added
£30,000.00 The local
Operations
team reviewed
this site and it is
classed as a
major issue as
our asset was
affecting the
Scottish Canals
asset and there
is a risk of
damaging it. 
UC12 Union
Street -
Lochgilphead
Inlay £99.733.33 £56,515.36 Rescheduled
due to other
schemes being
more of a
priority. This
scheme can be
managed
through the
revenue budget.
Page 15

Page 16

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
UC01 - Brodie
Cres -
Lochgilphead
Inlay £20,000.00 £21,956.75 Rescheduled
due to other
schemes being
more of a
priority and
locally this can
be managed
through the
revenue budget. 
KINTYRE
Scheme
Location, Road
Number/Name
Works Type Estimated
Cost 
March EDI
Updated
Estimated
Cost June
EDI
Reason for
being added
or
rescheduled
2025 Pre
Surface
Dressing Isle of
Gigha 
Pre Surface
Dressing work
prior to 2025
Capital
Programme
works
New Scheme
added
£66,667.00 This has been
reviewed by
local
Operations
team and will
require to be
carried out
before any
major surface
dressing works
are carried out
from next
years budget. 
Stewart Road.
St John Str to
New Quay
Street
Inlay £35968 £36,452.00 This scheme
was
rescheduled as
it was ranked
as a lower
priority within
the CVI
process. 
John Street –
Whole Length
Inlay £37,905.54 £25,443.00 This scheme
was
rescheduled as
it was ranked
as a lower
priority within
the CVI
process.
C22 Gigha
Ardminish
Overlay £39,251.54 £35,461.00 This scheme is
now
superseded by
Page 16

Page 17

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
the full network
pre SD and SD 
over the next
18 months. 
ISLANDS
Scheme
Location, Road
Number/Name
Works
Type
Estimated
Cost 
March EDI
Updated
Estimated
Cost June
EDI
Reason for
being added
or
rescheduled
U16 Flora Street Inlay  New Scheme
added 
£113,456.59 This scheme
has been
added as the
Operations
Team leader
visited the
island and
confirmed this
is one of the
worst roads on
the island and
in need of
urgent repair
works.
UC10 North of
Ardnahoe
Overlay New Scheme
added
£39,449.94 This work will
be carried out
on the back of
Distillery works
which are
planned as part
of the distillery
development
and is a
partnership
approach. 
A846 Steam Mill
to Clachan
Cottage
Bowmore
Overlay £240,083.00 £212,418.60 This scheme
has been
rescheduled as
the work is not
as significantly
needed as the
other Bowmore
Scheme at
Flora Street.
There is not as
much HGV use
and can be
Page 17

Page 18

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
regulated
through surface
dressing. 
Page 18

Page 19

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
BUTE AND COWAL
BUTE
Scheme
Location, Road
Number/Name
Works
Type
Estimated
Cost 
March EDI
Updated
Estimated
Cost June
EDI
Reason for
being added or
rescheduled
A844 Stewarthill
to Milton farm
Overlay New Scheme
added
£75,022.43 This has been
scheduled due
to winter
deterioration.
A844 Meikle
Kilmory
Overlay New Scheme
added
£51,096.82 This has been
scheduled due
to winter
deterioration.
Ascog Roslin to
High Bogany
Farm
Overlay New Scheme
added
£61,095.08 This has been
scheduled due
to winter
deterioration.
Glenburn Road Inlay New Scheme
added
£34,919.72 Having attended
the location
officers
described the
section of road
as a “Disaster
Area” and
required urgent
work to prevent
danger. This
work has been
carried out
already as a
priority. 
UC5 Glecknabae
– Lenie Hall –
Pipers cave
Inlay £50,000.00 £55,148.27 This scheme
was
rescheduled as
works were not
seen as a
priority over
urgent work
which was
required at
Glenburn Road,
as well as works
Page 19

Page 20

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
having been
done there
recently. 
COWAL 
Scheme
Location, Road
Number/Name
Works
Type
Estimated
Cost 
March EDI
Updated
Estimated
Cost June
EDI
Reason for
being added or
rescheduled
A886 Baycrofts to
A815 junction
Strachur
Inlay New Scheme
Added
£89,264.10 This scheme is a
strategic road
which carries
more traffic and
has deteriorated
significantly over
the winter. 
A8003 Royal Brae
Tighnabruaich
Inlay £26,695.00 £61,425.35 Rescheduled
due to other
schemes being
more of a priority
and revised cost
was too high for
the budget
available.
U22 West
Glendaruel
(Camquart Bridge)
Overlay £99,000.00 £60,033.99 Rescheduled
due to other
schemes being
more of a priority
and previous
work has been
carried out here
recently.
C57 Glenbranter –
North Scheme
Overlay £60,000.00 £43,341.35 Rescheduled
due to other
schemes being
more of a priority
and cost was too
high for the
budget
available.
Page 20

Page 21

APPENDIX 1 – CHANGES TO PROGRAMME REPORTED IN MARCH 2024 
HELENSBURGH AND LOMOND 
Scheme
Location, Road
Number/Name
Works Type Estimated
Cost 
March EDI
Updated
Estimated
Cost June
EDI
Reason for
being added or
rescheduled
A817 Haul Road
at A814
Roundabout –
High Friction
Surface
Treatment
Promoted
scheme
£24,000.00 This is a high-
speed road
which requires a
high friction
surface to
improve road
safety. This
work has been
able to be
promoted due to
re-assessment
of the previous
programme
works which
delivered
savings. 
Page 21

Page 22

This page is intentionally left blank

Page 23

APPENDIX 2 – AMENDED ROADS RECONSTRUCTION PROGRAMME 2024-25
EDI UPDATE - JUNE 2024
MAKI
2023/24 agreed schemes Budget re-scheduled  into 2024/25
Scheme Location, Road number/Name Works Type* 2023/24 allocated
budget C/F
B8001 Achmeanach farm  ( Cloanaig Slip site) Slope Stabilisation £464,000
Additional work content  Achmeanach Farm slip Temporary works £780,000
Islay  - A846 - Corrary Hill - Island Ho  ( ferry delay) Overlay £167,134
Islay  - C12 - S of Barr to W of Cattadle ( ferry delay) Overlay £95,414
Carry Over budget 1,506,548.50£             
MAKI SHARE OF £8M Budget  2,480,000.00£             
MID-ARGYLL M-A  33%  =  £818,400
2024/25 draft schemes based on the historic % split of the current £8M budget
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing and Preparation
C30 Ford - Kilmaha  inc Balure Spur Pre-SD 2024 34,271.29£                  
C30 Ford - Kilmaha  inc Balure Spur Laying 2024 197,955.00£                
2025 Pre-SD    U18 Drimvore - Crinan ferry - Moss area Pre-SD 2025 61,846.17£                  
Bituminous Surfacing Schemes.
A819 Electric Cottage  -  PH 4 Widening/Surfacing £                206,486.90
B8002  Ardfern to Craignish ( 4 sites = 1815 Lin.m) Overlay £                136,655.46
U38 Barmolloch   (Upper  Kilmicheal glen ) Overlay £                115,816.03 
U47 Crinan Loop  inc  Drainage improvements C39 Overlay £                  68,764.36
C43-010 Canal -  Lock 4 Bridge deck  ( Material tbc) Deck surface replace £                   30,000.00
Estimated Total 851,795.21£                
KINTYRE - Campbeltown Kintyre   33%  =  £818,400
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing and Preparation
2024 Pre -SD  U17 Pre-SD 2024 £                   15,000.00
2024 SD  - U17 A83 - Upperballywilline Laying 2024 £                173,342.82
2025 Pre-SD    Isle of Gigha  ( whole network) Pre-SD 2025 £                   66,666.67
Bituminous Surfacing Schemes.
B842  - Main St to New Quay St Inlay £                  73,819.72
u15 Crosshill Ave @ Range Rd junction Inlay £                101,614.64
Meadows Ave West side Inlay £                  51,606.41
Tomaig road - Campbeltown Inlay £                  80,771.42 
B842 Campbeltown Esplanade Inlay £                125,146.91
Davaar Ave  - Albyne Ave to Calton hill Inlay £                  47,687.01 
UC09 Calton Ave  - Albyne Ave to Davaar Ave Inlay £                  58,058.34
Shore St  - Main St to New Quay St Inlay £                  51,789.55
Estimated Total 845,503.49£                
ISLANDS Islands   34%   =    £ 843,200
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing Preparation
2025 Pre-SD B8085 & B8086 / U48  Colonsay Pre-SD 2025 £                  92,382.54
Bituminous Surfacing Schemes.
See  2nr carryover schemes 2023 - ferry delays (table 1) Overlay c/o budget 
B8085 Colonsay Overlay £                  48,263.01 
A846 Bunanuisg to Cruach Rd  - Thru' Bowmore Inlay £                278,801.19 
Uc16 Flora Street Inlay £                113,456.59 
A847 Bruach Gorm to Sewage Works - Pt Charlotte Inlay / Overlay £                217,496.79 
Uc10 North of Ardnahoe Overlay £                  39,449.94 
A847 Gowanlea to Seaview - Bruichladdich 700linm Inlay / Overlay £                  44,454.46
Estimated Total 834,304.52£                
Page 23

Page 24

APPENDIX 2 – AMENDED ROADS RECONSTRUCTION PROGRAMME 2024-25
EDI UPDATE - JUNE 2024
OLI
2023/24 agreed schemes Budget re-scheduled  into 2024/25
Scheme Location, Road number/Name Works Type* 2023/24 allocated
budget C/F
A816  Blaran widening  ( No STTS award 2024) Reconstruction £67,115
C 68 Breadalbane St Tobermory Widen / Wall / FW £249,304
Isle of Coll - B8027 Sorisdale Road ( ferry delays ) Overlay £247,294
Carry Over budget 563,713.00£                  
OLI SHARE OF £8M Budget  2,800,000.00£               
OBAN & LORN Lorn 55% =   £1,540,000
2024/25 draft schemes based on the historic % split of the current £8M budget
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing and Preparation
2024 laying operations -  North Shian - C27 Pt Appin SD 2024 £                  201,450.00
2024 laying operations -  North Shian - U42 - Inverfolla SD 2024 £                  159,526.00
U25 Musdale Road Pre-SD 2025 £                    70,171.63
U14 Scammadale Road Pre-SD 2025 £                    66,968.54
Bituminous Surfacing Schemes.
C29 - Kilmelford-Drissaig   - Lochavich Overlay £                  240,686.79 
U48 Shore Street - Oban Inlay £                    79,691.16 
U17 McCaig Road - Oban Inlay £                  123,800.56 
U 51 Dunuran Road  - Oban Inlay £                    24,831.46 
U 45 High St - Oban inlay £                    29,572.10 
B845 - Glen Salach    ( Blarcreen & Summit ) Overlays £                    53,349.50
A819  CLADDICH PH 3 -(Reassessed -  O/lay Ph 1&2 ) Overlays £                  114,652.19 
U58 Lower Gylen to Little Horse Shoe Bay KERRERA Overlay £                  104,434.90 
U 16 Laurel Road - Oban Inlay £                    63,521.01 
U22 Achavaich Road Major Maintenance £                    44,379.41 
C32 Glencruitten Road  Overlay £                    54,323.65 
U28 - Achnacloich - Connel Overlay £                    27,593.77 
U32 Craig Road - Dalmally Overlay £                    23,885.97 
U 76 Shore Road - Connel Overlay £                    25,986.70 
U 135 Pulpit Drive -Oban Inlay £                    49,263.87
Estimated Total 1,558,089.23£               
ISLES Isles  45%   =    £1,260,000
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing Preparation
C46 Glen Bellart / Glen Aros Pre-SD 2025 122,866.00£                 
Bituminous Surfacing Schemes
B8073  Calgary area  -  Mull Overlay £                  131,179.99
B8073 Tobermory  - Dervaig Overlay 98,177.72£                    
B 8073 Balligowan Overlay 126,421.29£                 
B 8073 Killichronan Overlay 98,213.12£                    
B 8073 Killiemore Overlay 62,827.95£                     
U82  Leiter Rd Overlay 24,173.10£                    
C 54  Loch Buie Rd Overlay 72,158.80£                    
U16 Croggan Road Overlay 75,022.24£                    
U14 Grasspoint Overlay 63,208.95£                    
C 54 Lay-by improvement works Overlay 34,098.40£                    
B8035 Gruline North - Mull Overlay 63,138.45£                    
B8035 Gruline South - Mull Overlay 61,252.45£                     
U80 Java Road Inlay 19,466.28£                     
A848  Additional Passing Places - Salen - Gulan Dubh construction 34,450.60£                    
B8065 Tiree Overlay 166,059.41£                 
Estimated Total 1,252,714.73£               
Page 24

Page 25

APPENDIX 2 – AMENDED ROADS RECONSTRUCTION PROGRAMME 2024-25
EDI UPDATE - JUNE 2024
B&C
2023/24 agreed schemes Budget re-scheduled  into 2024/25
Scheme Location, Road number/Name Works Type* 2023/24 allocated
budget C/F
A8003 Tighnabruaich Ph 7  (no STTS award 2024 ) Reconstruction £108,817
B & C  SHARE OF £8M Budget  1,600,000.00£           
COWAL Cowal 70% =  £1,120,000
2024/25 draft schemes based on the historic % split of the current £8M budget
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing and Preparation
A815 Var location below  PSD Pre-SD 2024 40,000.00£                
A815 Coylet  - Inverchapel Laying 2024 91,140.00£                
A815 Alexandar Parade  - Marine P- Pt Riddle Laying 2024 36,260.00£                
A815 Braemar Cottage  - Kelani  Toward Laying 2024 73,024.00£                
U27 Millhouse  /  U19 Couston Pre-SD 2025 80,000.00£                
Bituminous Surfacing  Schemes
C7 -  from B8000 to Tank Landing - Kames Overlay £              147,416.49
A886 Dunans House Northwards   (2 sites) Overlay £              155,836.79
A886 North of Communications Mast ( Leanach) Overlay £              131,898.61 
A886 Ardachuple cutting - Colintaive  ( 2 sites) Overlay £              121,330.38
A886 Baycroft to A815 junction  - Strachur Inlay £                89,264.10
B839 / B828 Passing Place improvements construction £                56,066.15
B8000 Largiemore ( C11 Junction) Overlay £                88,356.84
Estimated Total 1,110,593.36£           
BUTE BUTE    30%   =  £480,000
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing Preparation
C1 Bruchag Road 2025 Pre-SD  £                 60,000.00
Bituminous Surfacing Schemes
A844   East Princess St & Battery place to Glenburn  rd Inlay £              111,502.37
A844 Stewarthall  to Milton Farm o/lay £                75,022.34
A844  Meikle Kilmory o/lay £                51,096.82
U58  Serpentine Rd - to B881 Bishop St Inlay £                24,407.86 
U39 /U69  Gowanfield Place to St Brides Rd Inlay £                52,549.77
Ascog    Roslin  to High Bogany Farm o/lay £                61,095.08
Glenburn Rd inlay £                 34,919.72
Estimated Total 470,593.96£              
Page 25

Page 26

APPENDIX 2 – AMENDED ROADS RECONSTRUCTION PROGRAMME 2024-25
EDI UPDATE - JUNE 2024
H&L
2023/24 agreed schemes Budget re-scheduled  into 2024/25
Scheme Location, Road number/Name Works Type* 2023/24 allocated
budget C/F
A814 (@ Haul Road - A817) Middle roundabout Kerbing  and
surface £37,000
H & L  SHARE OF £8M Budget  1,120,000.00£            
Helensburgh and Lomond HL = £ 1,120,000
2024/25 draft schemes based on the historic % split of the current £8M budget
Scheme Location, Road number/Name Works Type* Estimated Cost
Surface Dressing and Preparation
2024 Pre -SD A814 - sites below Pre-SD 2024 80,000.00£                 
A814 - Whistlefield to Finnart Laying 2024 80,000.00£                 
A814  - South of Glen Douglas Laying 2024 60,000.00£                 
2025 Pre-SD Pre-SD 2025 50,000.00£                 
Bituminous Surfacing Schemes 
C 69 Glen Douglas hairpin bends to A82 Overlay 34,320.60£                 
B832 Muirlands  - Cross keys - A82  (5 SITES) Overlay 106,722.63£               
U71 Colqhoun st   W Argyle st - W King St inlay 33,938.06£                 
U262  Shore road - Helensburgh    PH 1 inlay 90,790.96£                 
U177 Kirk Brae - Shandon inlay 33,437.29£                 
U72 Columba St - Helensburgh inlay 23,080.10£                 
A814 Whistlefield Roundabout kerb & surface 35,261.16£                 
U 306 Victoria Road - Helensburgh inlay 68,114.83£                 
U105 East Prices st   Henry Bell st -  Geo St inlay 132,028.87£               
B872  Whistlefield road - Garelochead inlay 84,263.58£                 
U62  Church Road - Rhu inlay 43,583.92£                 
U101 East King - Charlotte St to Grant st inlay 36,689.02£                 
U13 Ardencaple Quadrant inlay 66,180.89£                 
U133 Forestry Houses - Succoth (Loch Long) inlay 39,430.26£                 
A817 Haul Rd  @  A814 Roundabout  - High Friction Surface Treatment 24,000.00£                 
Estimated Total 1,121,842.17£            