ARGYLL AND BUTE COUNCIL                               ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                   20 JUNE 2024       
STREET FURNITURE REPLACEMENT UPDATE 
1.0 INTRODUCTION 
1.1  The purpose of this report is to provide Environment, Development and
Infrastructure Committee with an update on the street signage and litter bin
replacement programme, following the allocation of a £200,000 budget at the
Council meeting of February 2021. 
2.0      RECOMMENDATIONS 
2.1 It is recommended that the Environment, Development and Infrastructure Committee
notes the content of this report. 
3.0 DETAIL
3.1 The funding for the street furniture replacement programme was made available
through the Council’s budget process in February 2021. This investment allowed for
a substantial improvement across the Argyll and Bute Council area. 
Street Signage Replacement
3.2 This investment has resulted in the improvement of 437 signs across the Argyll and
Bute Council area, with a total spend of £214,550, with the additional £14,550 being
met from the Roads Operations revenue budget and as part of routine sign
maintenance and replacement. Sign replacement has been carried out on a needs
basis, replacing those in the most deteriorated condition.
3.3 A breakdown of the 437 signs and the budget spend are as follows:
Helensburgh and Lomond 18 signs £8,600
Bute and Cowal 93 signs £48,900
Mid Argyll 80 signs £35,300
Kintyre 46 signs £21,100
Islay 70 signs £49,350
Oban and Lorn 110 signs £34,500
Mull 20 signs £16,800

Page 2

3.4 Appendix 1 provides a detailed breakdown of signage replacement per area.   
Litter Bin Replacement
3.5 This investment has resulted in the improvement of 402 street litter bins and bin
cabinets across the Argyll and Bute Council area, with a total spend of £99,154 to
date.
3.6 A breakdown of the improvement programme across the district and the budget spend
are as follows:
Helensburgh and
Lomond 
No of litter bins 60 £11,040 
No of cabinet housings 32 £10,592
Bute and Cowal No of litter bins 0 £0 
No of cabinet housings 58 £19,198
Mid-Argyll No of litter bins 50 £11,541 
No of cabinet housings  30 £9,930
Kintyre No of litter bins 0 £0 
No of cabinet housings 0 £0
Islay No of litter bins 0 £0 
No of cabinet housings  45 £14,895
Oban and Lorn No of litter bins  0 £0 
No of cabinet housings  34 £11,254
Mull No of litter bins  0 £0 
No of cabinet housings  24 £7,944
Concrete bases for
cabinets across
council area:  
No of bases 69 £2,760   
Note in addition to the above there are a small number of bins which have been
replaced due to damage or wear and tear which have been funded through existing
revenue maintenance budgets. 
4.0 CONCLUSION 
4.1 This investment has resulted in a marked improvement for the travelling public and
the appearance through replacement signage and an improvement in the bin
infrastructure across the area. 
5.0  IMPLICATIONS
5.1 Policy – None known.

Page 3

5.2 Financial – Funding made available through the Council budget process of 2021.
5.3  Legal –  None known.
5.4  HR – None known.
5.5  Fairer Scotland Duty: None known.
5.5.1   Equalities - protected characteristics – None known.
5.5.2   Socio-economic Duty: Improving the appearance of our network and visible signage
available to road users improving their experience of using our roads and improving
safety on the network.
5.5.3 Islands – None known.
5.6 Climate Change – None known.
5.7 Risk – These work highlight other areas of need, however, an ongoing programme
of improving signage when required is managed within the road operational budget. 
5.8  Customer Service – Improve public perception of our network/assets.
5.9 The Rights of the Child (UNCRC) – none known. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour  
May 2024 
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
jim.smith@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
tom.murphy@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – Sign Replacement Programme