ARGYLL AND BUTE COUNCIL                           ENVIRONMENT, DEVELOPMENT
AND INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             20 JUNE 2024
SERVICES                     
OBAN FLOODING UPDATE 
1.0 INTRODUCTION 
1.1 Historically there have been numerous flooding events within the Oban. The
sources of the flooding consists of water from; coastal, fluvial (water course),
surface water and combined sewer overflows. In some cases the combined
effects of some of these flooding sources has increased severity of the flood
hazard in Oban. One localised flood hotspot affected by combined source flooding
is centred on the Council’s Lochavullin Road Car Park bounded by Soroba Road,
Tesco and Lochavullin Road. 
1.2 Preventing future flooding will require significant works which currently are
unfunded. Through this report it is proposed that all funding opportunities are
explored including lobbying Scottish Government to seek to secure funding to
implement flood prevention works as well as exploring any additional external
funding opportunities. 
1.3 A number of short, medium and long term actions and works identified to help to
mitigate flooding are detailed in this report. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that the Environment, Development and Infrastructure
Committee: 
i. Consider and note this report.
ii. Endorse the proposals by officers to lobby for funding and to explore
external funding opportunities 
3.0 DETAIL 
3.1 SEPA’s Flood maps (Appendices 1,2 and 3) show areas susceptible to Coastal,
Fluvial (watercourse) and Surface Water flooding. Full map coverage available
from  Flood Maps | SEPA - Flood Maps | SEPA 
3.2 Coastal flooding is influenced by high astronomical tides and tidal surges caused
by low atmospheric pressure and storm events. In certain conditions, when high
spring tides are worsened by tidal surge, sea water will flood into the tidal reach

Page 2

of the Black Lynn burn. The combination of tidal and high flows in the Black Lynn
burn cause flooding in adjacent areas. Subject to the necessary permissions it is
proposed that some clearance work is carried out.  Whilst these works will provide
some additional water storage capacity, they are not expected to mitigate against
any significant weather event. 
3.3 In addition to this the Scottish Water combined sewers (drains that contain both
storm water and foul sewerage) can also surcharge adding raw sewerage to the
combined source flood waters. The Lochavullin car park has a pumping system
which copes with low levels of water, however, above a certain level there is
nowhere to pump water to and the pumps become ineffective.   
3.4 The consequences of these flooding events can often result in roads having to be
closed for safety resulting in significant diversions and significant flood damage to
adjacent businesses. 
3.5  Climate change is very likely to increase the severity and frequency of flood
events. Current guidance (SEPA Climate change allowances for flood risk
assessment in land use planning) points to the following changes: 
• By 2100 Peak River Flows in Argyll increase by 59% of the 2017 values 
• By 2080 Peak Rainfall Intensities increase by 46% of the 2017 values
• By 2100 cumulative rise in sea level above 2017 levels will be 0.86m 
3.6 In Cycle 1 of the Highland and Argyll Local Flood Risk Management Plan 2016-
22 Oban was identified as a Potentially Vulnerable Area (PVA) for flooding and
an Action was placed on the Council to carry out a Flood Study and Surface Water
Management Plan. 
3.7    A detailed Flood Study and Surface Water Management Plan (SWMP) was
completed in 2019. The Oban Flood Study and SWMP has identified a number of
mitigation and adaptation measures. These measures will require significant
infrastructure and are likely to require attenuation (creating storage capacity for
water either via a reservoir(s) or in underground tanks) for storm water as well as
creating sea defences to prevent flooding from tidal surge. At present detailed
design has not been progressed however it is reasonable to assume that works
to deal with the flooding issues would run to several millions of pounds. In the
recent past, the Council has been successful in securing funding for flood studies
and physical works such as those underway in Campbeltown. These studies and
physical works have been 80% funded by Scottish Government and 20% by the
Council. At the time of writing, the next round of flood funds has not been released
and it is currently unknown as to what, if any, funding will be available and over
what period of time. 
3.8 On 7-9 October 2023, the flooding in Oban was significant.  Connectivity including
access to hospitals and healthcare, residential property, light industry, commercial
and retail premises were all affected.  Access to shops and food stores was cut
off and general disruption including flooding of the underground fuel tanks at
Tesco superstore which resulted in no fuel being available from this site for a

Page 3

number of weeks. In addition there were a number of commercial properties,
some Council owned that were affected on the Lochavullin site. 
Future Actions 
3.9  Short term actions during a flood event:- 
The Council will continue to respond as required assisting emergency services
and others where possible to do so.  In addition to ensuring the pumping system
for Lochavullin car park is functioning, the Council’s input during a flood event is
likely to include providing the necessary signage, posting service disruption
notices via the website and working closely with Partners through the Local
Resilience Partnership and responding and assisting where possible.  An Oban
Local Flood Resilience Group has been established by volunteers with an initial
meeting held with Council officers. This local community group is a good point of
contact and it is understood that they are linked in with the Scottish Flood
Resilience Forum. Officers will work collaboratively with this group. 
3.10 Medium term actions include:- 
• Watercourse inspection of Black Lynn Burn and its tributaries;
• Clearance of obstructions (trees, trolleys etc) noted during inspection;
• Topographic and Bathymetric surveys carried out for the area immediately
surrounding Black Lynn Burn (this shall be commissioned to a specialist
consultant); 
• Hydrologic study to be carried out for the Black Lynn Burn (this is being
commissioned to a specialist consultant); 
• Repair the existing pumping system at Lochavullin car park:
o Existing control unit repaired / replaced as required and raised on a
plinth to reduce risk of future water damage;
o Existing pumps replaced as required;
o Investigate whether existing pump outfall can be moved downstream 
• Consult with SEPA on consents for watercourse clearance and repair works
following watercourse inspection (it has since been noted that Japanese
Knotweed is present along the Black Lynn Burn, which will need to be
considered, including any Japanese Knotweed upstream);
• Secure quotes for proposed works to identify if funding can be identified
within available budgets or otherwise secured;
• Further collaboration with Scottish Water regarding sewer flooding and
identify options to share resources and reduce this source of flooding;
• Make representations to Scottish Government seeking to make available
funding to accelerate flood prevention works at Oban;
• Explore all opportunities for securing any available funding to accelerate
flood prevention works at Oban. 
3.11 Long term actions include:- 
• Long term works will be significant and likely to run into tens of millions
of pounds requiring attenuation/water storage and general climate

Page 4

change adaptation measures aimed at mitigating or minimising
disruption from severe weather events;
• Currently SEPA prioritise residential property above businesses in terms
of assessment and allocation of funding. The Council will lobby to seek
to secure funding to accelerate flood prevention works at Oban;
• No identified funding for major works;
• Currently SEPA have a public consultation underway regarding Oban
Potential Vulnerable Area (PVAs) which runs until 24 June. This
consultation is covered on another agenda item for this meeting;  
• The impact of revised PVAs on future LFRMP Actions is uncertain at
present, as information becomes available further updates will be
brought forward to Members;
• NOTE – PVAs highlight the potential risk of flooding, this will enable any
development to take flooding into consideration and ‘build in’ flood
mitigation by raising levels, adding in flood defence etc.  PVAs also help
in seeking external funding to mitigate against flooding. 
Impact on Local Businesses and Council Tenants 
3.12 Some of the properties in Oban which have been affected by the recent flooding
are owned by the Council and are leased to commercial tenants. These
properties are located within the Lochavullin area where the Council leases
premises in Mill Lane, Millpark Road and Crannog Lane.  Some of the
properties have been affected by flooding before but the tenants have reported
that the recent flooding events have been worse than previously experienced. 
3.13  A number of tenants have contacted the Council to seek compensation or rent
reductions to reflect the impact of the flooding on their businesses.  However,
there are also businesses in the same area who either own or privately lease
their premises and it would not be fair if compensation or rent reductions were
only offered to Council tenants. Accordingly it is considered that only a
centralised support scheme made available through the Scottish Government
would offer an equitable response to the impact of the recent flooding events. 
3.14  As part of the wider flood prevention works being investigated and undertaken
by the Council, additional survey work of the drainage systems around the
Lochavullin area has been instructed by the Estates Section. This is to assess
if there are any short term measures which could be taken to make
improvements to address specific issues some tenants are having. The
drainage systems have been altered over the years by a number of tenants and
understanding how this impacts on the wider network will assist to determine if
any short term measures will improve matters. There may also be a role in this
exercise for Scottish Water depending on the outcome of the surveys and it
should be noted that these works will not address the larger scale flooding
events which require a larger flood prevention scheme as outlined elsewhere
within the report. 
Other Affected Locations 
3.15  There are a number of sites already included within a list of potential flood

Page 5

prevention schemes that may receive funding from future Scottish
Government allocations.  There are also additional sites that have been prone
to recent flooding that are not included in Scottish Government’s list of
schemes, these include Ledaig car park at Tobermory and Kilmichael Glen.
Both of these locations have been subject to recent flooding. 
4.0 CONCLUSION 
4.1 This report provides the Environment, Development and Infrastructure Committee
with an update on flooding in Oban and potential medium and long term
adaptation options.  This report also acknowledges other sites across Argyll and
Bute which do not currently feature on any flood plans.  The report also proposes
to seek external funding with the intention of bringing flood prevention works
forward whilst also recognising that the works required to mitigate flooding in
Oban will be significant. 
5.0 IMPLICATIONS 
5.1 Policy – In line with existing Council policies and in line with the Flood Risk
Management (Scotland) Act 2009. 
5.2 Financial – No funding identified for long term solution, this report proposes that
lobbying is taken forward with a view to securing funding. 
5.3  Legal – The Council has four key responsibilities under the Flood Risk
Management (Scotland) Act 2009:
• Prepare maps of bodies of water etc
• Assess bodies of water
• Prepare local flood risk management plans and carry out the Actions
identified in the LFRMP
• Carry out clearance and repair works. 
5.4  HR – None known. 
5.5  Fairer Scotland Duty: None known. 
5.5.1   Equalities - protected characteristics – An EqSEIA will be required as and
when long term solutions can be progressed.
5.5.2   Socio-economic Duty – None known.
5.5.3 Islands – None known. 
5.6 Climate Change – Due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.   
5.7  Risk – None known. 
5.8  Customer Service – None known.

Page 6

5.9 The Rights of the Child (UNCRC) – None known. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour
May 2024 
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services
jim.smith@argyll-bute.gov.uk 
Elsa Simoes, Infrastructure Design Manager 
elsa.simoes@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 - Plan shows the SEPA River flood hazard. 
Appendix 2 - Plan shows the SEPA Coastal flood hazard 
Appendix 3 -   Plan shows the SEPA Surface Water flood hazard

Page 7

Appendix 1 - Plan shows the SEPA river flood map  - Search Location - Tesco PA34 4HP
0.1% = 1 in 1000 year chance of flooding 
0.5% = 1 in 200 year chance of flooding
1% = 1 in 10 year chance of flooding

Page 8

Appendix 2 - Plan shows the SEPA coastal flood map  Search Location – Tesco PA34 4HP
0.1% = 1 in 1000 year chance of flooding 
0.5% = 1 in 200 year chance of flooding
1% = 1 in 10 year chance of flooding

Page 9

Appendix 3 - Plan shows the SEPA coastal flood map  Search Location – Tesco PA34 4HP
0.1% = 1 in 1000 year chance of flooding 
0.5% = 1 in 200 year chance of flooding
1% = 1 in 10 year chance of flooding