ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND       
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             20 JUNE 2024 
PUBLIC CONVENIENCE DOOR ACCESS CONTROL PROJECT UPDATE 
1.0 INTRODUCTION 
1.1 The Council had previously agreed as part of a budget exercise to introduce
charging at 16 high footfall public conveniences. This project has progressed
over the past few months and at the time of writing there are nine sites where
the charging system has been installed. The purpose of this report is to provide
an update on the progress of the project.
1.2 There have been a number of implementation issues experienced during the
install process and there remain 7 locations to be fitted plus 2 possible additional
sites as outlined within this report. 
2.0 RECOMMENDATIONS 
Members are asked to:
2.1 Note the update provided within this report.  
2.2 Consider whether it would be appropriate to defer the remaining site installations
until after the summer season to ensure we have further detail on the reliability
of the installations.  Note that any delay should not impact on the budgeted
income target as it is anticipated that this should be achieved from the current
sites that are operational.   
2.3 Agree that the Rothesay Victoriana and Moir Street/Riverside facilities which
have now returned to the Council should be categorised as high use and quotes
sought for charging installations at these sites. 
3.0 DETAIL 
Background
3.1 The Council had previously agreed to allocate £100,000 to a door access
control project to install charging infrastructure at 16 high footfall public

Page 2

conveniences on the basis of offsetting some of the costs of providing 60 public
conveniences across Argyll and Bute. The provision of public conveniences is a
non-statutory service for which the Council receives no specific Grant Aided
Expenditure Allocation (GAE) from the Scottish Government. 
3.2 To help identify high footfall PCs we had previously purchased a dozen counting
devices with the intention of rotating these across the estate.   The counters
provided figures of such a huge variance that the data could not be considered
to be accurate, and it was therefore not robust enough to form part of any
decision making process. As an alternative, officers utilised the knowledge and
expertise of local operatives who are familiar with the PCs in their area
(materials used; requirements for cleaning; complaints; damage etc.). This
was a straightforward way to establish footfall into three broad categories –
high; medium; low.
3.3 A procurement exercise progressed and a single return was received from
Healthmatics, who are a sector-leading provider of access systems for toilets,
parks, recreation grounds and public buildings across the UK 
3.4 That return was significantly higher than the budget so additional funding was
sought and approved from Crown Estate monies. £200,000 was allocated at
the October 2022 meeting of the Policy and Resources Committee, giving a
total project budget of £300,000. The total contract value is £270,000,
however the Oban North Pier scheme was quoted as a full install but is only a
retrofit of a contactless payment option onto the existing system, so a small
saving will be made there. 
3.5 The contract was awarded to Healthmatics. Due to the geographic spread of
sites the contract was awarded on a phased basis, with the original intention
that the full programme be delivered between September and December
2023. The mobilisation period between contract award and works on site was
much longer than we would have liked. 
Installations 
3.6 The contractor mobilised to site at the end of September 2023. There were a
number of issues with the delivery of the infrastructure works which prevented
the activation of the installed systems before Christmas and delayed the roll-out
of the full programme. The issues included the contractor initially delivering the
wrong doors and subsequently there were issues with the supporting software.
3.7 Defects and snagging issues were worked through in January 2024 and the
Phase One sites were activated on a rolling basis at the end of January and
beginning of February. 
System issues
3.8 Over the weekend of 17th February customers were paying but were unable to
access the facilities. Council staff on site and staff in the project team came in
over that weekend to set the systems to free and open each site up to ensure
customers could gain access. Due to the significance of the issues the system

Page 3

was completely deactivated at all sites to eliminate any further inconvenience to
the public. 
3.9 Following these issues we urgently engaged with the contractor and asked them
to investigate the issues and provide a reactivation plan. 
3.10 The contractor advised that the overarching issues were as a result of an
unintended software update to the cellular modems which control the doors
on each site. This seems to have resulted in communication being lost to the
online portal because it caused a loss of data connection. The contractor
visited each site and cleared this fault, and locked the routers to a long term
support version which they advise means there will be no more of these
issues. 
Reactivation
3.11 Given the scale of the issues, we reactivated the systems on a phased
approach, site by site initially, and closely monitored their operation to ensure
that we were confident that the system was reliable. The reactivation dates
are noted in the below table:
Site Date
Ardrishaig  26 March
Lochgilphead 2 April 
Glenmorag 16 April
Sandbank 16 April
Helensburgh 29 April 
Inveraray 29 April 
Colintraive 30 April
Tighnabruaich 30 April
Port Bannatyne 30 April 
3.12 At the time of writing this report (12 June) since reactivation the systems are
operating as expected 92.5% of the time. There have been isolated incidents
recorded on 1.5% of operating days and the systems have had to be
deactivated because of problems on 5.9% of operating days (the latter being
across four sites – Ardrishaig, Port Bannatyne, Lochgilphead and Inveraray
where the systems were temporarily deactivated.) At the time of writing this
report eight of the nine sites are operating and the one site which is not is
being attended to by the contractor. The contractor has been responsive to
any issues which have arisen since reactivation. 
Income
3.13 We do not yet have figures for cash collected across all sites as at the time of
writing this report it has not all been banked/processed. Across the sites (four)
that the cash has been banked, the Council has taken in £3,398.  The
contactless payments have generated £7,135 as at 30th May. Once the
system has operated reliably for a season across all sites we will be able to
show income per site and model possible future income.

Page 4

3.14 The Oban North Pier site has an existing cash charging system which
generated £10,418 last year. In addition we have honesty boxes at a number
of other sites, which raised £1,486 in the same period. 
Next steps
3.15 The remaining sites identified for installations are:
Area Site
Lorn Oban North Pier (contactless retrofit) 
Ganavan
Islay Bowmore 
Port Ellen 
Bridgend
Mull Fionnphort 
Bute Chapel Hill (held over from Phase One) 
3.16 We have asked the contractor to provide a new programme for these
installations. Members may wish to take a view on the timing of the next
phase given the issues experienced in the first phase. It may be prudent to
allow the first phase sites to run for the season at least to have a greater
amount of data to assess the overall reliability of the system. 
3.17 Since the original list was developed, two sites have come back to the Council
from third parties – Moir Street (the Riverside in Dunoon) and the Rothesay
Victoriana. These are both clearly well used facilities and in addition to the
agreed Phase Two sites we have asked the contractor for a quote to install
the systems at these sites. In the case of Rothesay Victoriana, any proposal
would need to be sensitive to the building’s listed status and be appropriate
and in keeping with the setting. In addition to charging for access to the toilets
we can also look at a charging system for the showers. It is expected that,
these additional schemes would be able to be delivered from available funds. 
4.0 CONCLUSION
4.1 The door access control project is progressing. There have been a number of
issues with the installations which the project team has worked through with the
contractor. Presently the new systems are operating at over 90% reliability. 
5.0 IMPLICATIONS
5.1 Policy – the Council has an existing position to charge for access to high use
public conveniences (PCs).

Page 5

5.2 Financial – there is an income target of £70,000 against PCs and given the
initial set of income figures from the nine active sites it is expected that this
figure should be achieved as long as the system continues to operate reliably. 
5.3  Legal – none known.
5.4  HR – operatives use PCs for welfare purposes – access cards have been
arranged and one is placed in each relevant vehicle. 
5.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – none known. 
6.5.2   Socio-economic Duty – the system has a cash payment option. 
6.5.3  Islands – none known.
5.6 Climate Change – none known. 
5.7 Risk – there is a reputational risk if the system fails and customers cannot
gain access. This is being closely monitored.
5.8  Customer Service – the project team are responding to any customer
complaints/queries. 
5.9 The Rights of the Child (UNCRC) – the system has a cash payment option. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity: Councillor John Armour 
June 2024                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services 
jim.smith@argyll-bute.gov.uk 
Mark Calder, Project Manager
mark.calder@argyll-bute.gov.uk