ARGYLL AND BUTE COUNCIL 
PPSL Committee                                                      
Development & Economic Growth  16th September 2025 
Development Management Performance Update – FQ1 2025/26 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the performance of the Development
Management Service for the reporting period FQ1 2025/26. 
1.2 The attached document Appendix 1 provides an overview of the current demands
upon the Development Management Service, its output during this period, the
handling of the current backlog of casework, and the average time taken to
determine planning applications.   
2.0 RECOMMENDATIONS 
2.1 It is recommended that PPSL: 
(a) Review and agree the content of the report. 
3.0 DETAIL & BACKGROUND 
3.1  The performance of the Council’s Development Management Service has been
significantly impacted by the legacy effect of the Covid Pandemic upon
interruption to workflow and a subsequent increase in demand for regulatory
activity relating to new development. This situation has been exacerbated by the
Service having previously been down-sized in response to the longer-term wider
financial pressures facing the Council combined with a number of long-term
vacancies that proved extremely difficult to fill as a result of a national shortage of
planning professionals. The determination of planning applications has also been
impacted by the uncertainty created by a changing planning policy backdrop with
the Scottish Government’s adoption of National Planning Framework 4 (NPF4) in
February 2023 with minimal transition arrangements having had a noticeable
adverse impact on FQ4 2022/23 output as a result of a significant volume of
casework requiring to be reassessed prior to its determination.  The cumulative
effect of these extraordinary pressures has given rise to a significant backlog of
planning casework that continues to impact upon the ability of the Council to
deliver the Development Management Service in an efficient and effective
manner at this time, and impacts upon customer service. At FQ4 2022/23 the
backlog of applications amounted to approximately 375 formal applications and
175 pre-application enquiries.

Page 2

Classification: OFFICIAL
3.2 An Improvement Action Plan (IAP) was prepared in early 2023 in response to the
significant decrease in performance and wider issues impacting upon the
resourcing of the service and its interactions with customers. The implementation
of the IAP has ensured the delivery of additional capacity within the Development
Management Service and along with this improvement initially in terms of output
and more latterly improving trends are also now able to be identified in relation to
the making of timely determinations. Building upon the foundation of the IAP, the
Development Management Service Plan and Development Management Charter
approved by PPSL on 18th September 2024 set out updated performance targets
for the Service. These include a wider range of measures that seek to
demonstrate the delivery of individual elements of the IAP and in addition to
timeliness include measures which can be utilised to measure customer
satisfaction, and staff welfare. 
3.3 DEMAND: The Development Management Service receive approximately 2000
planning and related application case work items on an annual basis. The
Development Management Service is resourced with the expectation that
demand will be relatively constant and steady throughout the year. Whilst the
volume of new submissions decreased by approximately 10% during 2020/21
they had returned to and exceeded pre-pandemic levels during 2021/22.
Submission rates have subsequently been maintained at a high level and during
2022/23 were 5% up on pre-pandemic levels. Appendix 1, Sheet 1 shows that
whilst submission rates continued to show an increase in demand during FQ1
2025/26 this has increased slightly from the previous reporting period. 
3.4  During FQ1 2025/26 the DM Service has operated with 2 vacant posts in addition
to impacts arising from unplanned absence, including the impact of work related
stress. In an effort to make further inroads in the backlog of casework, one agency
staff member has been retained to augment the MAKI team. 
3.5 OUTPUT: Reduced availability of professional officer resource within the DM
Service during FQ1 has resulted in a notable dip in output compared to previous
reporting periods. (Appendix 1, Sheet 2). It is anticipated that productivity will
improve once recruitment to vacant posts has been completed although any
bounce back is likely to be delayed as a result of the reduced officer availability
during the Summer holiday period. 
3.6 Notwithstanding the dip in productivity, FQ1 has also seen an increase in the
number of invalid submissions, the consequence of this is that determinations
have kept pace with the number of applications validated during this period
(Appendix 1, Sheet 3). A review of ‘live’ casework has however identified that
whilst there has been a slight increase in the number of ‘legacy’ cases which are
older than 1 year from validation remain ‘live’ and it is noted that thee have
increased from 86 to 90 items during FQ1 (Appendix 1, Sheet 4). Whilst the dip
in productivity is as a result of reduced resource availability in the short-term it is
a matter which gives some cause for concern in terms of immediate performance
but also indicates that the Service has unresolved issues in relation to its
resilience which will be closely monitored moving forward.

Page 3

Classification: OFFICIAL
3.7 PRE-APPLICATION ENQUIRIES: Demand for pre-application advice remains
high however Pre-application turnover is currently on track. Performance during
FQ1 has met demand from new submissions. A commitment has been provided
to review and improve the pre-application process, this will include the provision
of enhanced information on the Council website to allow a greater proportion of
customers to ‘self-serve’; development and roll out of a new pre-application
service has been identified as a priority project for 2025. 
3.8 ‘HOUSEHOLDER’ DEVELOPMENT: The performance of the Development
Management Service is also measured in terms of the time taken to determine
applications as it is recognised that failure to provide timely decisions can create
uncertainty and be detrimental to the delivery of development across the Council
area. Overall ‘time-taken’ measures have been skewed for sometime by the
determination of a high volume of older ‘legacy’ applications that have accrued as
part of the planning backlog. The increasing proportion of older applications being
determined from FQ3 2022/23 onwards is identified in the bar graphs that provide
a breakdown of application age within the average time measures (Appendix 1,
Sheet 5 and Sheet 6) and demonstrate that ‘legacy’ applications are successfully
being targeted for determination. FQ1 has seen 2 of the remaining ‘legacy’
‘householder’ items determined providing confirmation that the significant
improvement to underlying performance is becoming more evident in the overall
average time measures as 2025/26 progresses. 
3.9 The determination of ‘legacy’ applications for the time being does however
continue to have adverse consequences for overall average time performance
measures as the determination of a relatively small number of older applications
significantly impacts upon these KPIs. This is particularly evident again within the
‘householder’ average time measure (Appendix 1, Sheet 5) where despite 95%
of all householder determinations being determined in an average time of 8.1
weeks this measure is significantly impacted by the determination of just 2 older
applications that have cumulatively added 2.3 weeks to the average time period
for determination of this KPI. The overall reduction in ‘legacy’ items has however
allowed for improvement of the headline KPI from 14.2 weeks in FQ 4 2024/25 to
10.1 weeks in FQ1 2025/26. It is also highlighted that this position relates to ‘raw’
data and does not factor in delays which have arisen as a result of matters outwith
the control of the Council, or applications that have been subject to processing
agreements. During FQ1 the Council determined a number of legacy applications
which have impacted on the raw data relating to the average time period, including
items that were delayed largely due to matters outwith the control of the Council.
Whilst the data sets are not directly comparable it is still helpful to reference the
SG Returns as a benchmark. In this respect the national average for householder
applications at FQ2 2024/25 was 8.7 weeks. 
3.10 ‘LOCAL’ DEVELOPMENT: The determination of ‘legacy’ applications had a
similar impact upon the average time taken measure applied to all other ‘local’
planning applications (Appendix 1, Sheet 6) where the determination of 15
‘legacy’ applications during FQ1 cumulatively added 9.8 weeks to an average
time measure that reports on the determination of 128 applications in total. During
FQ1 88% of all other ‘local’ applications determined were less than 1 year old at

Page 4

Classification: OFFICIAL
the time of their determination and were determined in an average of 17.9 weeks
(previously 86% in 15.6 weeks at FQ4 2024/25). 63% of the total were less than
6 months old and determined in 10.2 weeks on average (previously 75% in 12.2
weeks in FQ4 2024/25). The average time taken to determine ‘all other local
applications’ has decreased slightly during FQ1 from 26.4 weeks to 26.7 weeks.
This slight reduction in performance is caused by the overall dip in productivity
which has seen a lower volume of new applications determined during this
reporting period. It is again highlighted that this position relates to ‘raw’ data and
does not factor in delays which have arisen as a result of matters outwith the
control of the Council, or applications that have been subject to processing
agreements. During FQ1 the Council determined a number of legacy applications
which have impacted on the raw data relating to the average time period, including
items that were delayed largely due to matters outwith the control of the Council.
Whilst the data sets are not directly comparable it is still helpful to reference the
SG Returns as a benchmark. In this respect the national average for local
applications (excluding householder) at FQ2 2024/25 was 14.8 weeks. 
3.11 CONCLUSION: Whilst it is expected that headline performance on ‘householder’
items should return within target as we progress through 2025/26, the
determination of extant ‘legacy’ items will continue to impact on ‘local’ application
performance until such time as the remaining 90 items have been determined,
and subject to appropriate action which prevents new ‘legacy’ items from
accruing. Analysis of the granular data shows that average time periods for
determining applications are in general continuing to reduce and that despite
headline figures that might raise alarm, the majority of applications continue to be
processed within much faster timescales that are showing improvement over time
and which within the target of being within 10% of the national average. The slight
degradation to performance during FQ1 as a result of reduced availability of officer
resource underlines the importance of ensuring that the Development
Management Service is adequately resourced as recent improvement in
performance has been attained through the reduction in individual officer’s
caseloads to manageable levels with limited exceptions. 
4.0 IMPLICATIONS 
4.1 Policy - None
4.2 Financial - None
4.3  Legal - None
4.4  HR – None
4.5 Customer Service – Requirement to manage customer expectations in
the determination planning and related applications
4.6 Risk – Failure to determine planning and related applications in
efficient and effective manner would have potential to adversely impact

Page 5

Classification: OFFICIAL
upon the local economy, delivery of housing, and health and wellbeing
of individuals.
4.7 Climate Change - None
4.8  Fairer Scotland Duty - None 
4.9 Equalities - protected characteristics - None 
4.10    Consumer Duty - None 
4.11 Island Communities - None
4.12 Children’s Rights and Wellbeing - None 
Executive Director with responsibility for Development and Economic Growth:
Kirsty Flanagan
Policy Lead: Cllr Kieron Green
8th September 2025                                                  
For further information contact: Peter Bain – 01546 604204 
APPENDICES 
Appendix 1 – FQ1 2025/26 DM performance report