Page 1

1
Appendix 1 
ROADS AND INFRASTRUCTURE SERVICES 
Roads Development
Technical Guidance 
Author Stuart Watson
Owner Head of Roads & Infrastructure
Services
Date April 2024
Version v1.7

Page 2

2
Document Information 
Title Roads Development Technical Guidance 
Author Stuart Watson
Description Design guide for roads.  Includes local relaxations, amendments to the
National Roads Development Guide (NRDG), adoption processes, Small
developments, Island specific development guidelines.

Page 3

3
Contents
1.0 INTRODUCTION ............................................................................................................. 4
2.0 SUPPLEMENTARY GUIDANCE TO THE NRDG ................................................................... 5
2.1  NRDG PART 1 ............................................................................................................ 5
2.2  NRDG PART 2 ............................................................................................................ 5
2.3  NRDG PART 3 ............................................................................................................ 9
3.0 DEVELOPMENT CONTRIBUTIONS ................................................................................... 37
4.0 SMALL HOUSING DEVELOPMENTS (FOR USE FOR 1 TO 5 DWELLINGS) .............................. 38
5.0 SMALL HOUSING DEVELOPMENTS (FOR USE FOR 6 TO 10 DWELLINGS) ............................ 46
6.0 VARIATION ON ROAD STANDARDS FOR SPECIFIC ISLANDS .............................................. 48
7.0 ADOPTION OF PRIVATE ROADS OTHER THAN VIA THE RCC PROCESS .............................. 49
8.0 DEVELOPMENTS ON EXISTING PRIVATE ROADS .............................................................. 50
GLOSSARY OF TERMS ....................................................................................................... 53
APPENDIX 1 – CALCULATION OF ROAD BOND ...................................................................... 54
APPENDIX 2 – ROADS CONSTRUCTION CONSENT FORMS ..................................................... 56
APPENDIX 3 – AREA CONTACTS ......................................................................................... 79
APPENDIX 4 – STRATEGIC ROADS ...................................................................................... 81
APPENDIX 5 – STANDARD DETAILS ..................................................................................... 83

Page 4

4 
1.0 Introduction 
The National Roads Development Guide (NRDG) has been produced by the
Society for Chief Officers of Transport in Scotland, supported by Transport Scotland
and Scottish Government Planning and Architecture Division.  The document
follows the same principles introduced in Designing Streets with a change in
national policy to move away from a standards based approach to one where
designers, planners and roads engineers collaborate to develop a design led
solution. 
The Councils Roads Development Technical Guidance has been devised to
compliment the NRDG but takes into account local considerations which, on
occasion, may be different than national guidance.  This document highlights areas
where Argyll and Bute Councils local Policies or Standards differ from the NRDG. 
Argyll and Bute Council area is diverse in nature and character and the Technical
Guidance may not cover every situation. The Council reserves the right to vary
requirements to suit particular local conditions as and when required or considered
appropriate. 
Within Section 2 Supplementary Guidance to the NRDG, where sections of the
NRDG are superseded entirely by guidance in this document this will be indicated
by the term “Replacement Text”.  Similarly, where sections of the NRDG have
been added to this will be indicated by the term “Additional Text”. 
Developers working within Argyll and Bute Council area are required to use this
document alongside the NRDG and cross-reference both documents. Developers
may also require to refer to Designing Streets (DS) and the Design Manual for
Roads and Bridges (DMRB).  Where the NRDG refers to a design standard (e.g.
the DMRB or British Standard) the most up to date version of the standard will be
used.   
This document also provides further detail on the adoption of private roads (other
than through the RCC process), variation of adoptable standards, development
contributions through new developments and development of existing private roads.

Page 5

5
2.0 Supplementary Guidance to the NRDG 
This section specifies the parts of the NRDG which are amended or replaced to
meet the local requirements within Argyll and Bute Council area.  This Scottish
Government (SG) guidance is based on the June 2017 amended version. 
2.1  NRDG Part 1   
Paragraph 1.8: The Need for Consultation  
Following “Consultation should consider items such as, but not necessarily limit to
the following:” add 
Additional Text 
• Geotechnical information – ground investigation, factual and interpretative
reports. 
2.2  NRDG Part 2 
Paragraph 2.1.1: Statutory Consents 
(c) Work on the existing public road (Road Opening Permits): 
Additional Text 
Any work on or adjacent to existing public roads which are on or near structures
shall be subject to prior consultation with Argyll and Bute Council Structures Section
via structures@argyll-bute.gov.uk   
Paragraph 2.1.4: Design Guidance and Adoption Standards  
Following “6 or more individual dwellings should normally be served by a “road”
which will require Construction Consent and the submission of a road bond in a
residential area.” add 
Additional Text 
Refer to Section 5.0 “Small Housing Developments (for use for 6 to 10 dwellings)”
or Section 6.0 “Variation on Road Standards for Specific Islands” of this document
for details regarding a variable adoptable standard for developments of 6 – 10
dwellings. 
A Construction Consent and the submission of a Road Bond may still be required. 
Note, Housing Associations are exempt from the provision of Road Bonds.

Page 6

6
Paragraph 2.2.6: Roads and Lane Widths 
(a) Junction Types and Arrangements 
Additional Text 
Site specific visibility standard sightline distances within Argyll & Bute are detailed
within section 3.1 Road Design, 3.1.1 (c) Junctions of this document 
(d) Integrated Parking 
Following “In addition, the evolution of car design has resulted in increased car
sizes over recent years, rendering much of the previous car parking space guidance
outdated and no longer fit for purpose. Refer to Parking Standards in Part 3” add 
Additional Text 
It is recognised that integral parking provision within residential dwellings may be
converted for other uses (Permitted development). Therefore this parking
arrangement shall not be counted within the required parking standards. 
Refer to Table A8 Car Parking Standards of this document for the parking provision
within Argyll and Bute Council area. 
Paragraph 2.2.7: Street Detail 
(a) Drainage and Sustainable Urban Drainage Systems (SUDS) 
Additional Text 
SUDS schemes must comply with current SEPA guidance and approval process. 
(b) Flood Risk Management 
Additional Text 
Flood management must be in accordance with current guidance and the Councils
flood “policy” 
(c) Utilities 
Additional Text 
Where the proposed new road is a prospective adopted road, provision for (public
utilities) services must be made.  If services are not being installed during the road
construction phase then ducting appropriate to the scale of the development must
be provided.   
In addition to this, where a system of street lighting is not being installed as part of
the initial development ducting must be laid to allow the provision of lighting at a
future date.  Note, ducts must include draw-rope at installation.

Page 7

7
Paragraph 2.3.8: Adoption of Sustainable Urban Drainage Systems (SUDS) for
Roads 
Additional Text 
Where SUDS contains road surface drainage only and is contained within the road
corridor or servitude rights have been granted for areas outwith the road corridor,
the roads authority will adopt the scheme.  The Council, as roads authority, may
enter into agreement with Scottish Water for shared systems. 
Paragraph 2.3.10: Structures Agreements 
Additional Text 
Any agreement involving a structure shall be subject to the Technical Approval
Process as outlined in Paragraph 3.8 of this document. 
Paragraph 2.3.11: Roads Bonds 
Additional Text 
For any prospective adopted road a road bond will be required.  The road bond will
be calculated based on the rates in Appendix 1; rates may be subject to inflation. 
Paragraph 2.4: Applying for Construction Consent 
Additional Text 
The Councils published Fees & Charges (link below) provides detail of the charges
for the processing of RCCs.  Charges may be subject to annual increases under the
Councils budget setting processes. 
https://www.argyll-bute.gov.uk/council-and-government/council-fees-and-charges 
Paragraph 2.4.9:  Construction Consent Forms 
Additional Text 
The Council’s Construction Consent Forms are contained in Appendix 2 of this
Technical Guidance document.  Submissions should be made to the local Traffic &
Development Officer at the addresses listed in Appendix 3. 
The Argyll and Bute Council Construction Consent Forms are contained in
Appendix 2.  Permission is hereby granted for this these forms to the photocopied.

Page 8

8
Paragraph 2.4.12: Inspection Procedures during Construction 
(a) Notice of Commencement
(b) Sub-paragraph (3) Notice of Operations 
Replacement Text 
The developer or his contractor must give the Local Roads Authority representative
a minimum 3 working days’ notice (excluding weekends and public holidays),
unless otherwise agreed with the Roads Authority, of: 
(a) Completion of formation;
(b) Commencement of each pavement layer to the carriageways, cycle track,
footways and footpaths;
(c) Each concrete pour (including blinding) and commencement of steel
fixing where reinforced concrete is used;
(d) Striking of formwork;
(e) Setting out of road lighting plant positions, backfilling of cable trenches
and painting of lighting columns;
(f) Placing and testing of drainage systems. 
It should be noted that these are minimum requirements and that, in certain cases,
the developer may be required to notify the Local Roads Authority’s representative
of additional construction stages. 
Developers should also note that failure to notify the representative as above can
result in covered over work to be exposed for inspection at the developer’s expense
to ensure that the construction complies with the Construction Consent. 
Finally, failure to notify can result in delays to adoption or potentially seriously
compromise the adoption process. 
Sub-paragraph (4) – Charges for Inspection & Testing 
Additional Text 
The Councils published Fees & Charges (link below) provides detail of the charges
for RCC Inspections.  Charges are calculated pro rata based on the Road Bond
Value.  Charges may be subject to annual increases under the Councils budget
setting processes.  Inspections fees shall be paid in full prior to commencement of
works.   
https://www.argyll-bute.gov.uk/council-and-government/council-fees-and-charges

Page 9

9
2.3  NRDG Part 3 
Paragraph 3.1.1: Junctions 
Following “The range of junction types and arrangements are discussed in
Designing Streets (page 36). This section details required junction criteria to enable
a design to function correctly in relation to its user demands.” 
Additional Text 
Note that for all junctions on high speed roads (40mph or above), the guidance in
Designing Streets is not appropriate and the DMRB must be referred to for
guidance. 
Paragraph 3.1.1: Junctions 
(C) Visibility Splay Area 
Replacement and Additional Text 
“Stopping sight distances and visibility requirements are detailed in Designing
Street (pages 33-35).” 
Replace the table with the following tables and add the following text: 
Table A1 – Lightly Trafficked Roads 
Vehicle Speed
(mph) 
60  50  45  40  35  30  20 
Y distance  136  103  84  75  53  42  25 
For Strategic Routes and other routes carrying traffic volumes greater than 3000
Vehicles Per Day (VPD), use figures in Table A2.  The list of Strategic routes and
higher traffic routes is detailed in Appendix 4. 
Table A2 – Strategic and Heavily Trafficked Routes 
Vehicle Speed
(mph) 
60  50  45  40  35  30  20 
Y distance  160  120  95  75  53  42  25

Page 10

10
Traffic volumes are in vehicles per day (VPD) and refer to the total combined flow in
both directions.  Where actual speed falls between the given values the y – distance
may be interpolated by the Roads Authority. 
The  ‘x’ – distance will normally be taken as 2.4m.  Where considered appropriate
by the Roads Authority the following x-distances may be used:
• 4.5 metres for flows up to 3,000 v.p.d.
• 9.0 metre for flows in excess of 3,000 v.p.d. 
The visibility envelope (vertical plane) shall be taken as1.05m (“driver’s eye”) to
0.6m above the carriageway.  The “driver’s eye” may be increased to 2m for lorry
drivers. 
The traffic speed to be used is the mean speed on the public road. This will either
be measured or estimated by the Roads Authority.   
Developers should note that they must either own or obtain control of the land
contained within a visibility splay, except when it is already controlled by the Council
as part of the public road corridor. Control must be obtained through an agreement,
in accordance with Section 75 of the Town and Country Planning (Scotland) Act
1997 to ensure that the visibility splay remains free of obstruction in perpetuity. 
Paragraph 3.1.2: Private Access 
(a) Access Criteria 
Additional Text 
For further detail, including sightline requirements, please refer to Section 4: Small
Housing Developments (for use for 1 to 5 dwellings).   
(C) Individual Dwellings 
Additional Text 
It should be noted that where a vehicular dropped footway crossing is required, the
footway level must be re-profiled over its full width, or in the case of very wide
footways over a minimum width of 2.0m. This prevents an excessively steep lateral
gradient and slipping risk. See Figures A1a, A1b and A1c below.  Note, where the
dropped kerbs are also being used as a pedestrian crossing point the upstand shall
be reduced to no more than 0mm.

Page 11

11

Page 12

12
(D) Access Layouts 
Replacement Text 
Access layouts shown in Figures A2a and A2b.

Page 13

13
Paragraph 3.1.3: Design Details 
(A) Minimum Traffic Lane Widths 
Replace “The design parameters to be utilised for each type of road within the road
hierarchy are given in Table 3 on the following page.” With: 
Replacement 
The design parameters to be utilised for each type of road within the road hierarchy
are given in Tables A3 and A4 below: 
Table A3 – Urban Road Link Geometry 
Road Type Design
Speed
(kph)
Gradients Vertical Curves K Values
Minimum
(%)
Maximum
(%)
Minimum
Crest
Minimum Sag
Strategic Route DMRB DMRB DMRB DMRB DMRB
Main Distributor DMRB DMRB DMRB DMRB DMRB
Local
Distributor (1)
60 (for
40mph
limit)
1 6 17 13
Local
Distributor (2)
50 (for
30mph
limit)
1 6 10 9
Industrial
Access Road
32
(unless
bus
route)
1 6 10 9
Main
Residential
Street
32
(unless
bus
route)
1 6 6 6
Minor
Residential
Street, Home
Zone and
Cul-de-sac
32
(max.)
1 6 POA POA 
Table A4 – Rural Road Link Geometry 
Road Type Design
Speed
(kph)
Gradients Vertical Curves K Values
Minimum
(%)
Maximum
(%)
Minimum
Crest
Minimum Sag
A-class DMRB DMRB DMRB DMRB DMRB
B-class 85 1 6 55 20
C-class 60 1 6 17 13
Unclassified 60 1 6 17 13
Single Track
Access Road
60 1 6 POA POA

Page 14

14
Notes to Tables A3 & A4 
1. Verge, footways or service strips to be 2m minimum on both sides of the
carriageway.
2. Roads intended for use by buses are subject to a maximum gradient of 6%
3. Roads constructed with modular surfacing are subject to a minimum gradient of
1.25% and a maximum of 5%.
4. In a rural setting private accesses should not be constructed within 90 metres of
a road junction or within 25 metres of an existing private access.  
5. Speed limits may be amended locally dependent on traffic flows and mean
speeds. 
(D) Gradients and Crossfalls 
Under “Maximum Gradients” 
Additional Gradients
Maximum gradients should comply with Tables A3 and A4.  Any departure from this
standard must be agreed in writing by the Roads Authority.  In no circumstances
shall a gradient be greater than 10%. 
Under “Junctions”: 
Replacement 
The maximum gradient rising or falling on the final approach of a minor roads at the
junction shall be limited to 5% for at least 12 metres from the interface with the
major road.   
Under “Vertical Curve Length” 
Replacement 
The length of a vertical curve is based on the difference in gradient multiplied by the
factor K.  Refer to Tables A3 & A4 for the appropriate K value. 
(G) Provision for Public Transport 
Under “Bus Stop Provision” 
Following “Good public transport provision should be available at the initial phase of
any new development, either by linking to existing networks or by establishing new
routes and should therefore be discussed with local transport operators and the
Local Authority’s Transportation manager at an early stage.” 
Additional Text 
In rural areas it may be necessary for the developer to provide hard standing areas
to support bus pick up/drop off points. Consultation with the local Traffic &
Development Officer at an early stage is recommended.

Page 15

15
Additional Text 
(h) Industrial Estates 
General Principles 
1. Industrial developments shall be served by a road that requires Road
Construction Consents.  Industrial access roads shall be designed to
incorporate HGV and Bus traffic.  The applicant should be aware that the
Roads Authority may require some form of financial security (normally a road
bond) to be provided in relation to any prospective adoptable industrial estate
roads; or where significant improvements to the external public road network
are being carried out to make the development feasible or acceptable to the
Roads Authority. 
2. The Road Authority will not normally adopt industrial estate roads. Where the
road is to be adopted this will normally be restricted to the main distributor
road and any turning areas.  Service roads will not be considered for
adoption.   Road Construction Consents (RCC) shall follow the normal
process as detailed in the NRDG, Section 2.4 Applying for Construction
Consent. 
3. An industrial estate road provides frontage or service access to industrial and
commercial premises.   
4. Where service bays or areas associated with industrial or commercial
developments are contiguous with the public road, agreement must be
reached with the Roads Authority as to whether they are to be adopted or
not. There must be clear markings delineating private areas; these should be
of permanent form and require regular maintenance, i.e. not be road
markings.
Design Requirements 
1. The alignment of an Industrial Estate Road will largely depend on its length
but a formal design speed is still considered appropriate for assessing curve
radii and visibility.  The normal maximum speed limit will be 30mph.  If the
proposed estate road will form a part of a bus route then consideration will be
given to speed reductions.  Note that a 30mph speed limit equates to a
60kph design speed. 
2. The carriageway should be a minimum width of 7.3 metres, but it may be
acceptable to reduce this to 6.0 metres where commercial vehicle activity is
likely to be limited, for example a small unit development or where there is
one-way working.  Any variance of carriageway widths are subject to
approval by the Roads Authority.

Page 16

16
3. A minimum 2 metre wide footway shall be provided on both sides of the road,
which will be increased to at least 3.0 metres minimum if shared
footway/cycleway are provided.  The footway or footway/cycleway shall be
separate from the carriageway by a 2 metre verge preferably.  Where the
verge is located at the rear of the footway or footway/cycleway then a
separation strip of no less than 0.6 metre width shall be required for a
segregation strip.  The segregation strip shall be formed of such materials to
clearly show delineation from footway or footway/cycleway area.  Localised
widening of footway/cycleway may be required in the vicinity of bus stops.   
4. Depending on levels of movements and also any surrounding
pedestrian/cycle network, there may be a requirement for pedestrian
crossing facilities. Bus services (new or enhancement) and public transport
infrastructure may also be required.   
5. Where direct frontage access is permitted on to the adopted road network,
turning facilities in-curtilage shall be provided within the development.  This is
to ensure vehicles enter and exit the site in forward gear and no reversing is
carried out within the adopted road network. 
6. Carriageway design shall be to DMRB.  Rigid pavement construction will not
normally be accepted although this may be varied for individual accesses
which will remain private. 
7. Industrial Estate Roads and Access Roads shall be designed to remove
reversing manoeuvres within the road network, including when exiting or
entering the road network from properties.  This may require industrial estate
roads to be designed as through routes (loops) or with a turning area at the
end of a road.  Example of turning layouts can be found in Figure A3.  
Industrial estate roads should be designed to cater for 15.5 metre articulated
vehicles or 11 metre rigid vehicles as a minimum.  Swept path analysis will
be required to prove that proposed layouts work. 
8. Notwithstanding the above paragraphs, it is acknowledged that each
industrial estate may require consideration on its own merits. 
Table A5 – Industrial roads link geometry 
Parameters Industrial Estate Road
Design Speed (kph) (bus route may require a
reduction)
60
Stopping sight distance (m) at interface with
major road
90
Carriageway Width (m) 7.3 
Footway Width (m) 2.0 minimum
Verge Width (m) 2.0 minimum
Gradients Minimum (%) 0.8
Maximum (%) 8

Page 17

17
Vertical Curves K
Values
Minimum Crest 17
Minimum Sag 13
Horizontal Radius Desirable Min. (m)  180 
Absolute minimum – with
c’way widening or overrun
areas at corners *see Table
A6 below
90
In-curtilage turning (see also Figure xx re turning
areas)
Desirable
Frontage Access Yes
On-street lay-by for parking or loading/unloading  Generally no but if
permitted the area will
not be adopted.
Junction from
local distributor to
industrial access
road
Minimum spacing on road
between junctions on same
side (m)
100
Minimum spacing on road 
between junctions on
opposite side (m)
50 
Junction form
industrial access
road to access
road
Minimum spacing on road
between junctions on same
side (m) 
50
Minimum spacing on road 
between junctions on
opposite side (m)
25
Visibility splays at
junctions
SSD “y” distance (m) within
ind. est.
42
Setback “x” distance (m) 4.5
Minimum radii (m) 15 
Table A6 – Industrial roads curve widening
Centreline
Curve Radius
(metres)
Industrial
Estate Road
90 8.5
150 7.9
180 7.3

Page 18

18

Page 19

19
Parking Requirements
1. On street parking will not normally be acceptable.  Off-street parking shall be
designed in such a way as to prevent queues forming on the adopted road
network. 
2. Parking for each site must take into account the following types of parking: 
a. Operational – for service vehicles and staff parking who require to use
their vehicle as part of their day to day activities.
b. Commuter parking – for staff who drive to and from work.
c. Visitor parking – for customer and other visitors. 
3. Parking areas may be required to include landscaping and other measures to
mitigate against vast open, unattractive areas.  This will be advised by planning
guidance. 
4. Parking areas will, however, create additional surface water and this will need to
comply with SUDS and other water management regulation.  Surface water
generated out with the public road network will not be permitted to discharge into
public road surface water drainage system. 
5. Suitable segregation between vehicles and pedestrians must be maintained in
parking areas. 
Table A7 - Industrial Units Parking Requirements 
Reference to m2 is to gross floor
area
A&B Roads minimum**
Wholesale Warehouses 1.1 Space per 100m2
Storage or distribution  4 spaces per 100m2
General Industrial 2 spaces per 100m2
Disabled parking (retail / leisure /
recreation)
3 spaces or 6%  up to 200 space car
park or 4 spaces or 4%  in car parks
with greater than 200 spaces
Disabled parking (places of
employment)
1 space per disabled employee plus 2
spaces or 5% (whichever is greater in
car parks with up to 200 spaces; or 6
spaces plus 2% in car parks over 200
spaces.
Cycle provision 1 cycle space per 8 standard bays for
sole use by bicycles 
** Round up to nearest full number

Page 20

20
Additional Text 
(i) Housing Courts (serve up to 20 dwellings) 
1. A Housing Court is similar in concept to a car park with a shared surface finish
for joint pedestrian and vehicular use. The associated dwellings are located
around the court. A Housing Court will not be adopted by the Roads Authority. 
2. The Court will provide parking spaces relative to the number of dwellings, up to
a maximum of 20 dwellings, and no point within the court should be more than
40 metres from the access point. 
3. The access road to a Housing Court must be a minimum of 5.5 metres wide
over the first 10 metres. A strong physical definition must be provided to indicate
the nature of the layout to the driver and that it is a private area. 
4. Where a Housing Court is provided at the end of a Housing Road cul-de-sac, a
separate turning head must be provided to ensure that drivers do not need to
enter the Court in order to turn. 
Figure N1: Indicative housing court layout 
5. Provision must be made within a Housing Court for servicing where there is a
servicing provision, including postal deliveries. The service vehicle must be able
to enter and leave in a forward gear at all times. 
6. Refuse collection must be arranged so that communal or centralised waste
collection is provided adjacent to the public road.  Underground refuse storage
facilities may be considered as appropriate.

Page 21

21 
7. Statutory Undertakers should be encouraged to use any footways or landscaped
areas outwith the Housing Court, otherwise a wayleave agreement will have to
be reached with the house owners to allow access to apparatus. 
8. As these Housing Courts will not be adopted by the roads authority, all lighting
must be provided and maintained by the developer.
Paragraph 3.1.4: Pedestrians and Cyclists 
(B) Pedestrian Provision 
Under “Width of New Footways 
Additional Text 
The minimum acceptable footway width shall be no less than 2 metres in normal
circumstances.  Where the local environment is constrained such that a 2 metre
footway is not feasible, the roads authority may consider a reduction in width to 1.5
metres.  This will be subject to local conditions including, for example, vehicular
traffic volume, pedestrian volume and the hierarchy of road. 
Under “Obstacle in Pedestrian Desire Line” 
Additional Text 
Relaxations may be permitted depending upon local conditions.  Where the
obstacle is a free standing sign (e.g. A-Board, Barrel sign etc.) the minimum
footway widths must be maintained in accordance with the Councils Advertising &
Signage Policy and its associated application processes. 
Under “Steps or Ramps on Footway” 
Following “Steps should have 0.3 metre permanently nonslip treads and a minimum
clear width of 1.4 metres” 
Additional Text 
Steps shall be formed with a material approved by the Roads Authority. 
Under “Disabled Access to Buildings” 
Additional Text 
Disabled access to buildings will not form part of the adopted road.

Page 22

22
Paragraph 3.15: Servicing 
(G) Refuse Collection 
Additional Text 
The Councils preferred refuse collection model is through communal or centralised
waste collection where appropriate.  Consideration may also be given underground
refuse storage facilities. 
Bin collection points or facilities must not be more than 30 metres from the relevant
residence.  The bin storage facilities must be within 10 metres of the proposed
vehicle collection. 
Where the development is mixed (e.g. commercial and residential) separate waste
facilities must be provided. 
Reversing manoeuvres must be designed out as far as reasonably practicable. 
Where this cannot be achieved then reversing distance must be kept to a maximum
of 10 metres. 
Paragraph 3.1.6: Statutory Undertaker Services 
(K) Planting and Service Strips  
Replacement Text 
No structures, walls, fences, or planting (other than low maintenance fauna as
agreed with the Roads Authority) are permitted to be located within the service
strips.   
In general the Roads Authority will not permit any planting within the proposed
roads corridor and will not adopt any maintenance or ownership of planting (other
than grass verges).  This stipulation may be waived if the planting forms part of a
SUDS design, however, note that the adopted road corridor shall not be artificially
widened to accommodate SUDS.  In addition to this, the Roads Authority will not
normally adopt SUDS or other drainage installed in private land.  If cases where the
SUDS or other drainage schemes in private land are adopted by the local authority,
these must provide safe vehicular access for maintenance and appropriate
servitude rights in perpetuity. 
(L) Road Opening Consultation and Consents 
Following “…must be obtained from the Road Authority before any excavation is
undertaken in a public road” 
Additional Text 
Windfarm developers in particular should ensure that discussions regarding national
grid connections and cable routing are undertaken early in the design process and

Page 23

23
are ideally run in parallel with the Planning and Road Construction Consent
process. 
(M) Provision of EV Charger facilities 
Additional Text 
Ducting for future provision of EV chargers or charging shall be provided, where
appropriate, to the scale of the development and to the satisfaction of the Roads
Authority. 
Paragraph 3.1.7: Rural Areas 
(C)  Road Widths 
Under “Developing on Existing Roads” 
Following “Note this requires statutory consents such as a Section 56 Roads
(Scotland) Act 1984." 
Additional Text 
It should be noted that widening or increasing traffic volumes on existing roads can
present significant issues if structures are affected, in such cases the application
shall be the subject to the  Technical Approval process as outlined in Section 3.8 of
this document. 
Under “Speed Visibility Relationship” 
Replacement Text 
Replace Tables 8 & 9 in the NRDG with Tables A1 & A2 contained in this
document. 
Paragraph 3.1.9:  Additional Considerations 
After “(d) Fire Fighting”, add 
Additional Text 
(e) Windows, doors and gates 
Where the building line is at or near the road corridor (verge, footway or
carriageway etc.) any windows and doors facing the road must open inwards. 
Gates on the boundary of the public road should open away from the road corridor. 
(f) Carriageway Edge Restraint 
In general, it is expected that developments within urban areas will include
carriageway edge restraint (normally pre-cast concrete kerbing), however; rural
developments, including any improvements to the existing public road are, are not

Page 24

24
always subject to the same requirements.  This section sets out the reasons for
utilising edge restraint in a rural environment: 
• Edge restraint supports the carriageway structure and prevents edge
deformation and ”spreading” 
• The use of kerbing, or other agreed measures, acts as a demarcation
between vehicular traffic and pedestrians of rural footways or verges;
• Where an upstand is provided the kerb acts as a check to prevent vehicles
leaving the carriageway; 
• Again, using an upstand allows a channel to be formed at the interface
between the kerb and carriageway edge which allows surface water to be
effectively drained. 
Paragraph 3.4.1: Geotechnical Considerations 
(b) Supporting Technical Documentation 
Following “Where it is proposed to locate a road over land previously used for
industrial purposes or waste disposal, it is essential that chemical analysis and gas
monitoring information is submitted in addition to standard laboratory testing to BS
5930: 1999 and BS 1377: 1990.” 
Additional Text 
Current technical standards for ground investigation and testing are to be used. 
Following (g) CBR 
Additional Text 
(h) Slope Stability 
Where there are soil slopes within influencing distance above or below the roads,
footpaths or verge slope stability analyses will be required. 
(i) Embankment and Fill 
Embankments and areas of up fill may require to be monitored over a period of time
to demonstrate that settlement is complete before adoption. 
Paragraph 3.4.4: Carriageway Construction 
(a) Pavements 
Replacement Text 
Carriageway Pavement design should be in accordance with the Design Manual for
Roads and Bridges. This requires details of the ground bearing capacity and the
traffic type and volumes to be identified to arrive at a suitable load spreading
pavement. A composite construction may be acceptable providing agreement with
the road authority is sought in advance.

Page 25

25 
BS 7533 for block paving and the additional qualifications and exceptions listed
here. 
Capping Layer
Where the CBR value is less or equal to 5%, a capping layer is required as per 
Figure 29. 
NB: The design California Bearing Ratio (CBR) should be obtained either by testing
or by measurement of the plasticity index of the subgrade material. In the case of
CBR testing, the method described in the laboratory test in accordance with BS
1377-4:1990, clause 7 should be used and is only relevant in natural soils and
cannot be used for pavement design in fill materials. By their nature fills are random
and highly variable in density and CBR testing in them only assesses the quality of
the material at the locus of the test. Therefore for pavement construction on fill
materials, unless the fill material is equivalent to or better than the specified capping
material, a full capping layer is required. 
Frost Susceptibility
It is possible for roads designed to have a total bituminous thickness of 170 mm
and, with a CBR value < or + to 2%, a 150 mm sub-base and 600 capping layer. In
such circumstances the upper 130 mm of the capping layer should be non frost-
susceptible. In practical terms this effectively means that the sub-base becomes
280 mm with a capping layer of 470 mm. For a 2%<CBR<or+5% where the total
bituminous thickness and sub-base thickness together are less than 450 mm the
same principle applies (ie the sub-base is increased to achieve 450 mm of non frost
susceptible material and the capping layer can be correspondingly reduced). This 
need not be done if the capping layer is non frost-susceptible. 
Increased Capping Layer Thickness
Although Table 10.1 gives various thicknesses of capping layer dependent upon
CBR, where CBR is significantly below 2%, these thicknesses may require to be

Page 26

26
increased dependent upon site and weather conditions prevailing at the time of
construction. This requirement will be accompanied by an additional CC8 Engineers
report to certify the design. Additional material may require to be removed and
replaced by more suitable material. Although the new material may be of good
quality, the subgrade shall be assumed to be equivalent to one of a CBR just under
2% and requiring 600 mm of capping layer. The developer should consult the 
Roads Authority for advice in these circumstances. 
Formation on Rock
Where the formation is on rock, the granular sub-base will act as a 150 mm depth
regulating layer. 
Carriageway Construction
Where suitable technical facilities exist it is recommended that the specific
circumstances of each site are catered for by designing the road in accordance with
the criteria stipulated above, subject to a minimum construction as required to carry
0.5 Million Standard Axles (MSA), for all roads. In this circumstance it will be
necessary to complete and return form CC8 ‘Carriageway Design Certificate 
(d) Clay, Natural Stone or Block Paving Pavements 
Additional Text 
Unless otherwise agreed with the Roads Authority, adopted or prospective adopted
carriageways and shared surfaces shall be bituminous material.  Where the Roads
Authority considers that block paving may be appropriate the following restrictions
will apply: 
i. In carriageways or shared surfaces Clay Pavers shall not be permitted for
use.  
ii. Concrete Block Pavers may be considered for use in these areas but must
have a minimum depth of 100mm. 
iii. Permeable block pavers will not be accepted by the Roads Authority.  
iv. The bedding layer must be drained but shall not be used for storage of
surface water.
v. The use of block paving is restricted to development with a maximum of 20
dwellings.  
vi. The use of block paving will also take into consideration the long term
maintenance liability in recognition of declining roads maintenance
budgets. 
Paragraph 3.4:7: Kerbs and Edging 
(a) Materials / Construction 
Replacement Text 
All carriageways, footways and footpaths should be provided with precast concrete
kerb or edging. Alternatively and with the approval of Argyll & Bute Council natural
stone kerbs may be acceptable.

Page 27

27 
On conventional roads, kerbs should be set 125mm above finished carriageway
level at the channel, except at pedestrian and vehicular crossings where this
dimension is reduced to 0mm maximum and 10mm maximum respectively. Edging
at heel of footways should be 50mm upstand whereas footpaths it should be set
flush with the walking surface. On shared surfaces, an upstand of 20mm, with a
suitably contrasted colour, should normally be provided, except at junctions with
footpaths and private accesses where kerbs should be set at 10mm upstand for
vehicles or 0mm for pedestrians 
A delineation kerbline at the rear of the verge may be required to identify the extent
of the adopted road corridor.   
(b) Remote Areas (not contiguous with the carriageway) 
Replacement Text
In remote areas, and with the agreement of Argyll & Bute Council, cycleways may
be constructed without kerb edgings, where the sub base is laid 500mm wider than
the surfacing to provide shoulders. 
Paragraph 3.4:8: Accesses 
Replacement 
(a) Driveways 
Vehicular access crossings of footways for individual dwellings should comply with
Figure A1a of this document and be constructed as per NRDG Paragraph 3.4.6. 
Future maintenance requirements preclude the use of slab footway construction for
vehicle crossings. 
Replacement 
(b) Other Access Details 
Where vehicular access, other than individual dwellings, is taken then Figures A2a
and A2b shall be used and accesses shall be constructed in bituminous material
unless otherwise agreed with the Roads Authority.  Note:
i. Subject to agreement by the Roads Authority, an absolute minimum
access width may be reduced to 3.6 metres.  Wider accesses may be
required dependent on function and environment.
ii. Radii at the interface with the public road may be required to be reduced
to assist in controlling vehicle speed.  
(c) Pedestrian Access/Crossings 
Replace paragraph “Figure 32 details the requirement for dropped kerbs where
pedestrian routes cross the carriageway from adjacent footways, e.g. at T-junctions
and pelican crossings. Pedestrian crossings of a carriageway with an adjacent
grass verge should comply with Figure 31 except that the dropped kerb should be

Page 28

28
set flush, or not more than 6mm upstand, with the carriageway and extend for a
minimum length of 1.8 metres.”, with: 
Replacement Text 
Figure A4 details the requirement for dropped kerbs where pedestrian routes cross
the carriageway from adjacent footways.  Pedestrian crossings of a carriageway
with an adjacent grass verge should comply with Figure A1c except that the
dropped kerb should be set at no greater than a 5mm upstand with the carriageway
and extend for a minimum length of 1.8 metres. 
Paragraph 3.4:9: Road Drainage and SUDS 
(a)  Specification Best Management Practices 
Sustainable Urban Drainage Systems 
Following “The final design of the drainage system must be to the satisfaction and
meet the requirements of the local Roads Authority, the appropriate Water Authority
and Scottish Environmental Protection Agency (SEPA) 
Additional Text
Contact Argyll & Bute Council’s Flood Risk Management section who will provide on
request a copy of the Council’s Sustainable Drainage Systems (SUDS) Design
Criteria Guidance Note.

Page 29

29
(b)  Gully Spacing 
Following “Advice on these matters should be sought from the local Roads Authority
who should be consulted at an early stage by a developer wishing to carry out a full
drainage design.” 
Additional Text 
It should be noted that Argyll & Bute Council require double gullies to be installed
with independent tails at low points of any sags, traffic calming features and at
turning areas / termination points on public roads. 
In regard to the gradients set out in Table 10 of the NRDG, note that minimum
gradients should reflect those stated in Tables A3 & A4 of this document. 
Replacement 
Figure 33 Road Gullies replaced with Figure 33a Road Gullies, below.

Page 30

30 
Under Figure 34 Chamber Construction

Page 31

31
Additional Text 
A polymer modified mortar shall be used for all brickwork and bedding of covers
and frames.  
(h)  Chambers 
Replacement 
Chambers should be constructed in accordance with Clause 507 of the
Specification. Manhole covers and frames shall be non-rock and comply with BS
EN 124 and be Class D400 (minimum clear opening 600 mm dia or equivalent,
minimum depth of frame 100 mm) except in non-contiguous car parks or verges
where the use of Class B125 (minimum clear opening 600 mm dia or equivalent,
minimum depth of frame 100 mm) may be permissible. 
Paragraph 3.4:10: Landscape Treatment 
(a)  General Issues 
Additional Text 
It should be noted that Argyll & Bute Council will generally not adopt landscaped
areas within development sites. These should be subject to formal factoring
arrangements. We will however, adopt grassed service strips and landscaping
associated with A&B Council’s adopted SUDS features. 
Paragraph 3.4.11 Lighting Design 
(c) Network Manager  
Additional Text 
A system of street lighting may not be required in every setting, for example with
rural locations.  Prior to commencing lighting design, early engagement is
encouraged with the local Traffic & Development Officers to ascertain the general
requirements or otherwise. 
Paragraph 3.5: Parking Considerations 
Additional Text 
Argyll and Bute Council has a maximum parking standard, as outlined in the LDP,
however, given the need to take account of parking issues in rural or semi-rural
areas it also has minimum parking standards which are detailed in Table A8 below. 
1. Where a proposed development is not specified within Table A8, the Roads
Authority will select the nearest type of land use as a basis for assessing parking
requirements. 
2. Each car parking space must measure no less than 2.5 metres by 5 metres.

Page 32

32 
3. Parking layouts must include circulation aisles with a minimum width of 6 metres. 
4. Assessments for the required number of spaces, based on Table A8 below, must be
rounded up to the nearest whole number. 
5. Where the Roads Authority considers it appropriate there may be a requirement to
provide suitable cycle storage facilities. 
6. Within town centres, parking requirements may be reduced where there is good
public transport provision. 
Table A8 – Car Parking Standards 
Car Parking Standards
Reference to m2 is to Gross Floor
Area
Argyll and Bute Minimum Parking
Standard
Retailing (food) (Use Class 1)
1000m2 upwards 1 space per 25m2
Retailing (non-food) (Use Class 1)
1000m2 upwards 1 space per 30m2
Wholesale Warehouses  1.1 space per 100m2
Business (Use Class 4) 1 space per 50 m2
Cinemas (Use Class 11 (a)) 1 space per 10 seats
Conference Facilities 1 space per 10 seats
Stadia n/a
Leisure (other than Cinemas and
Stadia 1 space per 22 m2
Hotels and Hostels 1 space per 3 staff plus 1.2 spaces per
room  
Bed and Breakfasts Housing Standards plus 1 space per
letting room
Higher and Further Education 1 space per 2 staff plus 1 space per 15
students
Schools
1 space per staff member plus 1 space
per 25 pupils.  Provision must also be
made for school transport (buses etc.) as
appropriate.
Storage and Distribution
4 spaces per 100 m2 
General Industrial
2 spaces per 100m2 
Open Air Markets 1 space per 50m2 site area
Restaurants (Use Class 3) Hot Food
Takeaways and Public Houses 2 spaces per 22m2
Housing (Use Class 9) and Flatted
Dwellings
1 space per 1 bedroom unit
2 spaces per 2-3 bedroom unit

Page 33

33
3 spaces per 4 or more bedroom
units
Visitor parking 0.25 spaces per
unit
Residential Institutions: 
Homes 
Sheltered Housing 
1 space per 2 staff plus 1 space per 4
units/bedrooms 
1 space per warden plus 0.5 to 0.8
spaces per dwelling
Town Centre: Housing (Use Class 9)
(all Scales) and Flatted Dwellings
(over 5 units)
0.5 spaces per unit
Hospital
1 space per doctor; 1 space per 3 staff
plus 1 space per 3 beds; Day clinics and
out patients 3 spaces per 100m2
Non Residential Institutions 1 space per 2 staff plus 3 spaces per
100m2
Houses of Worship 1 space per 10 seats
Crematoria  1 space per seat
Disabled Car Parking Provision
Minimum standards (retail, leisure and
recreation):-
3 spaces or 6% (whatever is greater) in
car parks with up to 200 spaces; or 
4 spaces plus 4% in car parks with more
than 200 spaces. 
Places of employment:-
1 space per disabled employee plus 2
spaces or 5% (whichever is greater in car
parks with up to 200 spaces; or 6 spaces
plus 2% in car parks over 200 spaces. 
Paragraph 3.5.11: Provision for Disabled Parking 
Replacement 
The requirements detail within the table included under this section of the NRDG is
replaced by the parking provision detailed in Table A8 of this document.

Page 34

34
Paragraph 3.6.2: Vehicles 
(b)  Layout of Parking Areas 
Additional Figure & Table 
For two way flows, minimum aisle width is 5m.   
Table A9 Permitted Dimension Variations for Fig.A5 
Aisle Width 
(m)
Bay Width 
(m)
6 2.5
5.5 2.5
5.3 2.75
5.0 2.8
4.8 2.9
4.5 2.95
4.0 3.1
3.5 3.2 
Paragraph 3.6.3: Disabled Parking Design 
(c)  Disabled Parking Design Consideration 
Additional Text 
For on-street disabled parking spaces the Traffic Signs Regulations and General
Directions 2016 shall be used.

Page 35

35
Paragraph 3.6.4:  Residential Parking Design  
Applies to sub-paragraphs a to e 
Additional Text 
Refer to Table A8 Car Parking Standards 
The LDP sets out circumstances where zero parking provision may be acceptable. 
Any variations to the parking standards must be evidence based and subject to
approval. 
(f)  Garage Provision and Size 
Additional Text 
Integral garages will not be counted towards parking provision. Free standing
garages of at least 6m x 3m within 30m of the dwelling can be counted unless there
is a site specific reason not to. 
Car ports will generally be counted as spaces. 
Paragraph 3.7:  Parking Standards for Use Classes 
Replacement Text 
Argyll and Bute Councils parking standards are detailed in para 3.5 and Table A8 of
this document.   
Any variations to the parking standards must be evidence based and subject to
approval. 
Paragraph 3.8: Structures Technical Approval 
Replacement Text 
Structures Technical Approval Requirements 
All structural design and assessment shall be subject to the Technical Approval
procedures outlined in CG300; Technical approval of highway structures of the
DMRB. 
Argyll and Bute Council are the Technical Approval Authority (TAA) for all road
structures and pedestrian footbridges that are the responsibility of Argyll and Bute
Council (independent of maintenance responsibility). 
Whilst the scope of CG300 and CD622 fully apply, Structures requiring technical
approval are summarised below:
• All road retaining structures with an effective retained height of greater than
or equal to 1.0m require technical approval in accordance with CG300.

Page 36

36
• All culverts and bridges with a clear span or internal diameter greater than
0.9 m in diameter require technical approval in accordance with CG300.
• Any geotechnical works (i.e. embankments) “which may pose a risk to the
general public, Argyll and Bute Council and/or Argyll and Bute Council’s
asset” require Technical Approval in accordance with CD622. 
It is highly recommended that early involvement with Argyll and Bute Council’s
Structures team is established for all schemes involving the above at
structures@argyll-bute.gov.uk

Page 37

37
3.0 Development Contributions 
3.1There may be applications where a development proposal is deemed acceptable
but is unable to proceed due to either deficiencies in roads infrastructure or that
the development may impact roads infrastructure (including impact on traffic flow,
public transport etc.) in the wider context of the area.  In such cases, the Council,
as Roads Authority, may require the developer to either carry out improvement
works as required or, by agreement, to provide cash sums to allow the Council to
carry out the works at its discretion. 
3.2 Further to paragraph 3.1, the Roads Authority may request that sums are
commuted for schemes which have a potential high cost future maintenance, for
example complex SUDS, remote cycle paths or schemes with block paving as the
running surface of the carriageway.  Typically commuted sums would take into
consideration the estimated maintenance costs for an appropriate period of time
post-adoption to ensure such matters are appropriately addressed. 
3.3 The main legislation where agreements may be made are governed by the Town
and Country Planning Act 1997, as amended, Section 75, the Local Government
(Scotland) Act 1973 Section 69 and the Roads (Scotland) Act 1984 Section 48. 
There are other legislation and regulations which may be used if considered
appropriate. 
3.4 The Planning (Scotland) Act 2019 may provide further powers under s54 to create
an infrastructure levy through subsequent Regulations.  This matter will require to
be considered as any Regulations are introduced. 
3.5 While s75 agreements would be related to any grant of Planning Permission; s69
would require to be settled prior to the release of Planning Permission.  Section 96
agreements may form part of the RCC process, particularly if the risk is linked to
the construction phase, but should be highlighted within the Roads comments
during the planning application process. 
3.6 Any Section 75 agreements will require to accord with the advice set out in the
Scottish Government Circular 3/2012 - Planning Obligations and Good Neighbour
Agreements.   
3.7 A typical legal agreement will include articles including but limited to the following: 
▪ the parties to the agreement; e.g. the Council, Applicant, etc.;
▪ the development to which the Legal Agreement relates; 
▪ the contributions requiring to be paid; 
▪ when the contribution is required to be paid i.e. settlement trigger
point;
▪ whether the contribution should be paid in one or multiple instalments;
▪ the consequences should the contribution not be settled when agreed; 
▪ the purpose for which the contribution will be spent or applied by ABC; 
▪ the deadline by which the contribution will be spent or applied by ABC;
▪ the terms of contribution return if the scheme is withdrawn

Page 38

38
4.0 Small Housing Developments (for use for 1 to 5 dwellings) 
Introduction 
4.1 This section provides guidance for developers seeking planning permission for
small residential developments of 1 to 5 dwellings within the Argyll and Bute
Council area. This includes that part of Argyll & Bute within the Loch Lomond and
The Trossachs National Park.   
4.2 Compliance with roads requirements and standards is only part of the planning
process and in no way guarantees that a development will be granted planning
approval. 
4.3 The requirements laid out in this document apply to private accesses joining the
public road.  Private accesses are also referred to as private driveways. 
4.4  Any retaining structures, adjacent to the public road, to be constructed as part of
the development, must be designed in accordance with current good practice. A
design certificate will be required. 
4.5 Further consultation or information is available by contacting Network & Standards
Officers, contact details are listed in Appendix 3 of this Technical Guidance
document. 
4.6  Where a proposed development takes access to the public road network onto a
Trunk Road, contact should be made with the Trunk Roads Authority.   
Visibility Requirements 
4.7  The provision of a new or improved access from a private access onto a public
road must include adequate visibility. This is essential to enable drivers emerging
from the private access to see and be seen by drivers proceeding along the public
road. To achieve this, unobstructed visibility is needed within the shaded areas in
Figures A10, A11, A12 & A13. These requirements are referred to as visibility
splays and are defined by: the ‘y’ dimension  measured along the near edge of the
public road from the centre line of the private access, to both left and right; and the
‘x’ dimension measured from the edge of the public road along the centre line of
the proposed access   For clarity, the edge of the public road will be considered as
the carriageway edge in most circumstances; the exception to this is where access
is taken from a Strategic Road (as detailed in Appendix 4) where the edge of the
public road shall be taken as the back of footway or verge (i.e. the curtilage of the
property).  The Roads Authority may use discretion where it considers it
appropriate.

Page 39

39 
Figure A10: Visibility Splays - Visibility is required over the shaded area shown in
Figure A10 
4.8  Where the access is on the outside of a bend, an additional area will be necessary
to provide splays which are tangential to the road edge as shown on Figure A11.   
When accesses are located on bends a check must be made to ensure vehicle
divers have adequate forward visibility, i.e. they are able to see approaching traffic
on the public road to allow them to complete their manoeuvre safely.  (Figure A13) 
Figure A11: Visibility Splays for Accesses on the Outside of Bends

Page 40

40 
Figure A12:  Visibility Splays for Accesses on Inside of Bends 
The normal requirements for visibility distances are set out below. 
X – distance (m) 
The  ‘x’ – distance will normally be taken as 2.4m.  Where considered appropriate
by the Roads Authority, the following x-distances may be used: 
• 4.5 metres for flows up to 3,000 v.p.d. 
• 9.0 metre for flows in excess of 3,000 v.p.d. 
Y – distance (m) and Forward Sight Distance (m) 
The ‘y’ distance is based on a) the speed of the traffic on the public road, to 
ensure drivers can react in time to avoid a collision and b) the expected traffic flow
on the public road, to avoid the need for traffic on the public road to slow down or
stop in order to avoid a collision.   
The visibility envelope (vertical plane) shall be taken as1.05m (“driver’s eye”) to
0.6m above the carriageway.  The “driver’s eye” may be increased to 2m for lorry
drivers. 
For quiet roads, Table A1 should be used (repeated below for ease). For Strategic
Routes and other routes carrying traffic volumes greater than 3000 vehicles per
day (vpd), use Table A2 (repeated below for ease). See Appendix 4 for a list of
Strategic Routes and those carrying higher volumes of traffic.

Page 41

41
Table A1 – Lightly Trafficked Roads 
Vehicle Speed
(mph) 
60  50  45  40  35  30  20 
Y distance  136  103  84  75  53  42  25 
Table A2 – Strategic and Heavily Trafficked Routes 
Vehicle Speed
(mph) 
60  50  45  40  35  30  20 
Y distance  160  120  95  75  53  42  25 
For Strategic Routes and other routes carrying traffic volumes greater than 3000
vpd, use figures in Table A2.  Refer to Appendix 4 or a list of Strategic routes and
higher traffic routes.  
4.9  Traffic volumes are in vehicles per day (vpd) and refer to the total combined
flow in both directions. 
4.10 Where actual speed falls between the given values the y – distance may be
interpolated by the Roads Authority. 
4.11  The traffic speed to be used is the mean speed on the public road. This will be
measured or estimated by the Roads Authority. 
4.12 Applicants should note that they must either own or obtain control of the land
contained within a visibility splay, except when it is already controlled by the
Council as part of the public road corridor. Control must be obtained through
an agreement, in accordance with Sect 75 of the Town and Country Planning
(Scotland) Act 1997, to ensure that the visibility splay remains free of
obstruction in perpetuity. 
Visibility on the Public Road 
4.13 It will be necessary to check that forward visibility is not obscured. Vehicle
drivers waiting to turn into private access should be able to see the road is
clear before commencing the turning manoeuvre. Equally, following traffic
must be able to see vehicles waiting to make a turning manoeuvre.

Page 42

42   
Figure A13: Forward Visibility Splays 
4.14  The area within visibility splays (both those beside the private road and those
required for forward visibility) must be cleared of all obstructions to view,
higher than 1050mm above the level of the adjacent carriageway.  Minor
departures from this requirement, such as the retention of a single slender pole
or column, may be permitted as long as visibility is not materially affected.
Visibility splays must be kept clear in perpetuity. 
4.15 Visibility in a vertical plane must normally be provided from a driver’s eye
height of 1.05 metre to an object height of 0.6 metre.  For accesses taken from
Strategic Routes the driver’s eye height of 1.05 metres to an object height of
0.26 metres above the carriageway may be used; Figure A14 below is
provided for clarity.   
Figure A14 – envelope of visibility 
4.16 The Roads Authority will not introduce or extend a speed limit simply to
facilitate a new private access. 
Location of Accesses 
4.17 The access should usually be located a minimum of 25 metres away from the
nearest adjacent junction. However, a relaxation may be permitted depending
on the local conditions. 
4.18 Accesses for adjacent houses should generally be shared to avoid proliferation
of accesses.

Page 43

43 
Drainage 
4.19 Drainage shall be provided where necessary to prevent water from the access
flowing onto the public road. Similarly, when an access is being constructed
the existing road drainage must either be maintained or an effective alternative
provided, to the satisfaction of the Roads Authority. 
Layout of Access for Single or Paired Dwellings   
4.20 Where the frontage of a development site consists of a footway parallel to the
public road, accesses will be formed by lowering the kerbs and footway, in
accordance with standard detail SD 08/ 005 Rev. B (see Appendix 5). 
4.21 Where the speed limit is greater than 30 mph, any entrance gates should
usually be sited at least 6 metres from the edge of the carriageway to allow an
entering vehicle to stop clear of the carriageway when the gates are closed.
Gates must be hung so that they do not open towards the carriageway. 
4.22 Where the speed limit is 30mph or less, the gate must be hung so that they
cannot open towards the footway, verge or carriageway.   
4.23 The gradient of the access should not normally exceed 5% over the first 5
metres from the edge of the public road. The remainder of the access should
not exceed a gradient of 12.5% .Steeper accesses can lead to problems with
parking, traction in winter and control of drainage. 
4.24 Where the access crosses a footway, it is important to have intervisibility
between drivers and pedestrians, particularly small children. In these
circumstances there should normally be visibility between a driver’s viewpoint
(1.05m above carriageway level) 2.4 metres back in to the access to an object
0.6 metre above the footway and 2.4m on either side, along the back of the
footway.   
Access Construction 
4.25 The access shall be surfaced with a bituminous material for the first 5 metres
from the edge of the carriageway or back of any local road widening; other
material may be considered.  Reference should be made the standard details
in Appendix 5. 
For clarity, Unbound Roads (Type 1) shall not be accepted as an appropriate
adoptable standard road.  This remains the case even in circumstances where
the road will not be adopted. 
4.26 Standard detail SD 08/002 Rev. B (see Appendix 5) will normally be used
where there are more than two new properties serviced from a single access
off a double track road. 
4.27 Standard detail SD 08/004 Rev. B (see Appendix 5) will normally be used
where the access joins a single track road.

Page 44

44
4.28 Standard detail SD 08/005 Rev. B (see Appendix 5) shows an access across a
footway.   
4.29 Standard detail SD 08/006 Rev. B (see Appendix 5) shows a service bay and
may be required by the Roads Authority on faster double track roads.   
4.30 Road Opening Permits must be obtained before any work is carried out in
forming accesses.   
4.31 Accesses must be constructed in accordance with the Roads Authority
specification; on satisfactory completion the area within the road corridor will
become part of the public road. 
Parking Provision 
4.32 Argyll and Bute Councils parking standards are detailed Table A8 of this
document 
Any variations to the parking standards must be evidence based and subject to
approval. 
4.33 Each car parking space should normally measure no less than 2.5 metres by 5
metres. 
4.34 Integral garages will not be counted towards parking provision. Free standing
garages of at least 6m x 3m within 30m of the dwelling can be counted unless
there is a site specific reason not to. 
Car ports will generally be counted as spaces. 
Private Accesses – Commensurate Improvements 
4.35 Where there is an existing access serving a small number of properties it may
be acceptable to allow additional properties to be constructed without the
requirement for major upgrade works.  The main principle behind any
agreement by the Roads Authority will always be road safety. 
Example: 
An existing private access serving two dwellings, the Roads Authority may
allow up to a further three dwellings; the maximum permitted dwellings
serviced by this type of access will be five.  Dependent on the local
environment commensurate improvements may include: improvements to the
junction layout; visibility splays; surfacing of junction; passing places;  turning
head at the end of the private access  drainage; surface condition of the
private access. 
4.36 Where an existing private access served six dwellings and an application was
submitted for another dwelling, the Roads Authority may consider permitting
this on the condition that no further development is allowed.  In the case where
further development was confirmed to be prohibited or the land remaining was
undevelopable, it may be considered unreasonable for the Roads Authority to

Page 45

45
ask for a road to adoptable standard.  Notwithstanding this, improvements may
still be requested on the grounds of road safety improvements.  Any further
application would be subject to a road to adoptable standard. 
4.37 A “road to adoptable standard” is for the Roads Authority to define.  The
variation may include road widths or construction depth, for example,
commensurate to the scale of the development, however; Unbound roads
(Type 1) shall not be accepted as an appropriate adoptable standard road.

Page 46

46
5.0 Small Housing Developments (for use for 6 to 10 dwellings) 
The following clauses must be referred to by developers proposing to reduce standards for
proposed developments between 6 to 10 dwellings.
A. In normal circumstance the road must be constructed as per the normal processes
outlined in Section 2 of this document or otherwise as per the National Roads
Development Guide.  An RCC will be required, and a Road Bond will be required as
appropriate. 
B. Where there is a desire or requirement for the proposed road to be adopted but
there are justifiable technical or planning reasons that wouldn’t allow fully compliant
road infrastructure to be developed:
i. A reduced road standard may be acceptable.  
ii. Any deviations from standard road construction must not compromise road
safety.  In this regard reduced visibility splays will not be acceptable.  
iii. Any other proposed departure from standards must be submitted to the
Roads Authority for consideration. Early engagement is encouraged.
iv. Any agreement to a departure from standard must take into consideration the
local roads environment.
v. Financial considerations will not be considered as a justifiable technical
reason to vary standards. 
Note: an RCC will be required and a Road Bond will be required as appropriate.
C. Where the developer does not wish the road to be adopted as the proposal is
unable to meet the principles set out above, then the following may be acceptable,
subject to agreement with the Planning Authority:
i. As noted above, road safety must not be compromised, even where the
proposed road is not to be adopted. 
ii. The access shall be surfaced with a bituminous material for the first 5 metres
from the edge of the adopted carriageway or back of any local road
widening.  The construction depth shall be as per the detail below
(construction may be revised subject to appropriate CBR values being met): 
iii. The first 10m shall be 5.5m wide at the junction, thereafter the width may be
3.7m with intervisible passing places.  A turning area at or near the end of

Page 47

47
the road as per the details below must be provided.  The maximum length of
road shall not exceed 150 linear metres. 
iv. The remainder of the road can be a bound surface or other material as
approved, however; Unbound Roads (Type 1) will not be accepted as an
appropriate standard road.  The depth of construction may vary dependent
on local ground conditions.  As a minimum, a typical construction detail
should include 200mm Type 1 sub-base and 100mm of bituminous material. 
Planings may be used outwith the adopted road section. 
v. A service bay and communal bin storage area shall be provided at or near
the access.  Note, refuse collection vehicles shall not drive onto private roads
and, therefore, not collect bins from individual properties on private roads. 
vi. In rural or semi-rural locations there may not be a requirement for a system
of street lighting to be installed; however, note the following: 
a. If a lighting system is installed on a private road, the lighting shall also
remain private and will not be maintained by the Roads Authority.  
b. A requirement to install suitable ducting at construction phase may be
required even where no proposed system of street lighting is included
in the design.  This is allow future upgrades while minimising costs. 
vii. Parking provision shall be as per the detail set out in Section 2 of this
document. 
viii. An RCC or similarly controlled document and associated Road Bond may be
required. 
ix. Road Opening Permits must be obtained before any work is carried out in
forming accesses at the public road interface.   
x. Arrangements must be made providing assurance that a maintenance
agreement for the road will be included as a burden on the Title Deeds for
each property in perpetuity.

Page 48

48
Note:  Financial considerations will not be considered as a justifiable technical
reason to vary standards. 
6.0 Variation on Road Standards for Specific Islands 
6.1  This section is only applicable to applications sited on the Islands of Colonsay,
Coll, Tiree and Jura.  The exceptions provided for within this section are made
primarily due to the extreme difficulties in accessing hot material from
mainland quarries.   
6.2 The construction standard may be varied to allow concrete or unbound (Type
1) roads to be constructed.  Other material types may be considered. 
6.3 The provision of footways & verges may still apply. 
6.4 Where the proposed road has a carriageway of less than 5.5m width, there
may be a requirement for intervisible passing places. 
6.5  This variation only applies up to a maximum of five dwellings served by a
single access.  Subject to approval by the Roads Authority, this may be
extended to developments of up to 10 dwellings for new developments. 
6.6 The road will remain private and will not be adopted onto the Public List of
Roads. 
6.7 The access shall be surfaced with a bound material for the first 5 metres from
the edge of the carriageway or back of any local road widening.  The access
shall be formed as per the appropriate standard detail drawing
(SD/08/004/Rev.B, refer to Appendix 5).   
6.8 Road Opening Consent will be required. 
6.9 Notwithstanding the above, it remains the preference of the Roads Authority
that new roads are constructed in-line with normal adoptable standards and
subsequently adopted onto the Public List of Roads.

Page 49

49
7.0 Guidance on the Adoption of Private Roads other than via the RCC
Process 
7.1 The adoption of a new road is covered elsewhere within this document and the
decision to adopt or not is generally made at time of application through the
Roads Construction Consent process.  There are, however, a number of
private roads - roads which have not been added to the Public List of Roads -
within Argyll and Bute.   The adoption policy for the latter is covered within the
Policy set out in 2012 which can be found at https://www.argyll-
bute.gov.uk/moderngov/ieListDocuments.aspx?CId=257&MId=5320&Ver=4
under Item 19.     
7.2 There are specific legal requirements regarding the adoption of a private road
onto the Council's List of public roads.  These are: 
i. The Road must be a road as defined by the Roads (Scotland) Act
1984 Section 151.   
ii. In order for an application to be considered by the roads authority it
must be supported by a majority of the frontagers (based on actual %
of frontage not the number of frontagers) of the land along both sides
of the road being offered for adoption. 
iii. The proposed road must meet Argyll and Bute Councils road
adoption standards.   
7.3  In general, the road adoption standard will be those set out in the National
Roads Development Guide or their variations set out in this Technical
Guidance, however, exemptions may be considered, for example street
lighting may not be required depending on local environment, particularly in
rural settings. 
7.4 An application for road adoption must provide detail including: 
i. Existing road layout. 
ii. Proposed improvements to meet roads adoption standards including
as a minimum (list not exhaustive):
a. Drainage;
b. Lighting;
c. Roads width;
d. Gradients
e. Services;
f. Extent of proposed adoption. 
iii. Evidence confirming those frontagers who support the application.

Page 50

50 
8.0 Developments on existing Private Roads 
8.1 While in most circumstances a new development of more than 5 dwellings will
require to be served by a public road (i.e. an adopted road), there are
occasions where a planning application will require the roads authority to
consider further development from an existing private track or access road. 
8.2 The Councils Local Development Guide, Supplementary Guidance TRAN4
provides guidance where this kind of development may be acceptable subject
to the following clauses: 
i. the access is capable of commensurate improvements considered by
the Roads Authority to be appropriate to the scale and nature of the
proposed new development and that takes into account the current
access issues (informed by an assessment of usage); AND the
applicant can;
ii. Secure ownership of the private road or access to allow for
commensurate improvements to be made to the satisfaction of the
Planning Authority; OR,
iii. Demonstrate that an appropriate agreement has been concluded
with the existing owner to allow for commensurate improvements to
be made to the satisfaction of the Planning Authority. 
8.3 Points (ii) and (iii) are for the Planning Authority to determine, this section
deals with point (i) and the general minimum requirements which will be sought
by the Roads Authority.  These will normally be made in reference to road
safety, sustainability, emergency and service access, economic feasibility
(commensurate to the scale of the proposed development). 
8.4 Unlike new developments there is no defined upper limit on the number of
dwellings that may be served by an existing private access; each application
will be considered on its own merits and principally based on environment,
local context and predicted access requirements (for example, deliveries, and
refuse collection).  Where feasible, commensurate improvements may be
required to allow further development.  Where the required commensurate
improvements are beyond what could be reasonably considered as
appropriate to the scale of the development, the Roads consultee response
must be a refusal.  Road safety must not be compromised. 
8.5  The following will be considered for any application to develop existing private
access roads; note this is not an exhaustive list: 
i. Junction interface with the public road
a. Access must be safe;
b. Sightlines will be assessed on the posted speed limit,
however; this may be reduced pending a traffic/speed
survey and subject to suitably robust data on mean speeds;
c. Formed bellmouth with radii appropriate to access
requirements (e.g. deliveries);
d. A service bay will, in most cases, be required.

Page 51

51
e. Where possible, the private access should be widened out
to 5.5m for the first 10m.
f. The access shall be surfaced with a bituminous material for
the first 10 metres.
g. In some cases, it may be necessary for the developer to
carry out works on the public road along the frontage of the
development, including carriageway widening works,
footways etc.
h. Junctions must be improved to ensure that no water, debris
(mud, stone, gravel etc.), filth or any other offensive matter
spills onto the public road. 
ii. Refuse collection / bin stores
a. Where the private road has poor geometry or carriageway
width it may not be appropriate or safe for refuse collection
vehicles;
b. It remains the Councils general position that RCVs will not
use private access roads.
c. The developer may be required to construct a bin store /
collection point contiguous with the public road (via a
service bay) for all properties served by the road.  This may
include existing dwellings.
iii. Carriageway widths
a. To accommodate access for service and delivery vehicles,
carriageway widths should be no less than 3.5m
b. In line with Fire Scotland and nation building standards
guidelines, this carriageway width shall be widened out to
3.7m adjacent to low rise buildings, increasing to 4.5m
where buildings are in excess of 9m high.   This is to
facilitate the deployment of firefighting equipment.
iv. Gradients
a. Must be no more than 5% over the first 10 metres from the
edge of the public road;
b. Away from the public road interface, maximum gradients
must not exceed 8%.  The gradient on the approach to the
public road must also take cognisance of the horizontal
alignment; further measures may be required to prevent
runaway vehicles crossing onto the public road at speed, for
example, introduce a series of measures to slow vehicles
down on the approach to the public road.
v. Drainage
a. Positive surface water drainage and/or SUDS may be
required;
vi. General Road layout
a. Where the private access interfaces with a single track
adopted road network, it may be acceptable for the private
road to also be single track.
b. Where a. applies, there may be a requirement for localised
widening, including corner widening, to ensure safe access
for larger vehicles.

Page 52

52
c. Where this is the case, intervisible passing places will be
required.  Inclusive of the carriageway width, passing places
at their widest point shall be no less than 5.5m wide.
d. On single track private roads, intervisible passing places to
be provided at 100 metre centres (maximum distance).
vii. Turning head / areas;
a. Turning arrangements appropriate to predicted use will be
required to minimise or remove entirely reversing
manoeuvres in the interest of road safety.
viii. Dwelling accesses
a. For new developments, no access shall be constructed
within 25m of the junction with the public road network.
b. Within the private road network, accesses should be located
a minimum of 25 metres away from the nearest adjacent
junction.
ix. Other Road Safety:
a. Where there are no footways then verges must be of
sufficient quality to provide good, safe step-offs. 
b. The development may require to provide a walked route
assessment or similar for the section of private road from
the development to its interface with the public road.  
c. At the junction with the public road a safe pick up point /
drop off point must be provided. 
8.6 Arrangements must be made providing assurance that a maintenance
agreement for the road will be included as a burden on the Title Deeds for
each property in perpetuity.  It may not be possible to apply this retrospectively
to existing properties, where this is the case, the burden of the maintenance of
the whole private road length must be placed on the new development.  If this
cannot be done, the Roads Consultee response must be a refusal. 
8.7 Further to the above requirements, it may also be a requirement that servitude
or wayleave arrangements are in place to allow access for public utilities. 
8.8 The above requirements may be extrapolated to cover commercial and
industrial developments.  This may lead to increases in minimum standards;
for example, an increased radii at the public road to incorporate swept paths
for HGVs. 
8.9 The Applicant will submit a plan providing detail of the proposed
commensurate improvements for written approval by Roads, prior to the
Planning Decision Notice being issued. The Roads consultee response will
normally be deferred until agreement has been reached.   
8.10 Drawings showing the junction (at the interface with the public road) sightlines
within the site edged red. If the land is not under the Applicant’s control then a
Section 75 Legal Agreement shall be required. 
8.11 No work shall commence on site until all of the commensurate improvements
have been carried out to the satisfaction of the Roads Authority.

Page 53

53
Glossary of Terms 
Adopted Road The extent of the road which is added to the Public List of
Roads.  For new roads this should be agreed at RCC
stage.
Carriageway Where the public right of way which includes use by
vehicle. 
Cycleway Public right of passage by pedal cycle contiguous with the
carriageway.  Normally forms part of the adopted road
corridor where the carriageway is adopted
Cyclepath Public right of passage by pedal cycle which is remote
from the carriageway.  Normally not adopted.
Footpath Public right of passage which is remote from the
carriageway.  Normally not adopted.
Footway Public right of passage contiguous with the carriageway. 
Normally forms part of the adopted road corridor where the
carriageway is adopted
Frontage  The length of land where the road corridor abuts
neighbouring land, property or buildings.
Frontager   In relation to a road or proposed road, means the owner of
any land fronting or abutting it.
Frontage Access  Where there is direct vehicular access from a property to
an adopted road.
Private Road Means any road other than a public road which the public
may have a right of access over.
Private Access An access which the public are not normally expected to
have a right of access over.
Proposed or
prospective adopted
road
A road built under RCC which is expected to be adopted
upon satisfactory completion; pending 12 month or other
specified maintenance period. 
Public Road Means a road which a roads authority have a duty to
maintain and which has been added to the Pubic List of
Roads.
Road Corridor The sum parts of the road; carriageway, footways, verges,
ditches, structures or any other relevant item.
Traffic Includes pedestrians, vehicles and animals.
Verge Grassed margin contiguous with the carriageway or
footways within the adopted road corridor.

Page 54

54 
Appendix 1 – Calculation of Road Bond

Page 55

55 
SCHEDULE OF ROAD CONSTRUCTION COSTS
FOR ESTIMATING AMOUNT OF ROAD BOND 2020 
Item Price (£) per 1m of road Remarks 7.3m 6.0m 5.5m 3.5m 2.0m
Carriageway (flexible)
Full Construction (Stages
1, 2 and 3)
1,049 885 812 518 - Stage Construction
Stage 1: Construction up to and including sub-
base, allowing for removal of up to 100mm
unsuitable material and replacement with
imported fill.       
Stages 2 and 3 only 920 751 691 440 - Stage 2: Construction from sub-base upwards
including kerbs but excluding surface course.       
Stage 3 only 151 131 118 76 - Stage 3: Surface Course only.       
Shared Surface            
(Block Paving)
- - 735 467 - Includes for removal of up to 50mm unsuitable
material and replacement with imported fill.       
Soft Verge (grassed) - - - - 24 
Footway (flexible) - - - - 221 Includes provision of heel kerb (1 no.)       
Footpath (flexible)      Includes provision of edge kerbs (2 no.)
Footway and Footpath prices include for
removal of up to 50mm unsuitable material and
replacement with imported fill.  Increased
widths to be calculated pro-rata.       
Lighting 76 72 72 72 72 
Drainage      Manhole depths not exceeding 1.5m
Gullies at 20m ctrs 223 223 223 223 - Includes for manhole at 80m centres
Gullies at 40m ctrs 172 172 172 172 - Includes for manhole at 120m centres.       
Turning “T” (flexible) Residential Dimensions 7471 Cost is for that area additional to the normal
road width.  It does not include footways and is
a lump sum.
(Block Paving) Residential Dimensions 8246
Turning “O” (flexible) Residential Dimensions 24067  
7(Block Paving) Residential Dimensions 28528 
Notes:
1. These figures already include an allowance for inflation over a three year period (the
minimum duration of a construction consent). 
2. The costs are based on the Council doing all the work.  Obviously it is more costly to take
over someone else’s job and complete it; to compensate for this the following procedure
should be adopted: 
a. Add 25% where the estimated cost is less than £10,000; 
b. Add 15% where the estimated cost is between £10,000 and £25,000; 
c. Add 10% where the estimated cost is between £25,000 and £50,000.
3. Where the bond has to cover such items as major structures, or substantial amounts of
excavation or fill, full details should be sent to Roads HQ who will carry out the estimate. 
Elaborate SUDS schemes will need to be considered in their own merit and should be
priced individually.

Page 56

56 
Appendix 2 – Roads Construction Consent Forms

Page 57

57 
APPLICATION TO ROADS AUTHORITY FOR CONSTRUCTION CONSENT TO CONSTRUCT OR    
EXTEND A ROAD 
To be completed in accordance with the provisions of the Road & Infrastructure Services Roads Development
Technical Guidance by any person wishing to construct or extend a road irrespective of whether or not it is to
be subsequently maintained by the Roads Authority. 
1             I/We (insert full name and address of applicant)   
Postcode 
apply under Section 21 of the Roads (Scotland) Act 1984 for Construction Consent for the              
(state nature of operation e.g.  new construction or extension of existing road) 
at (insert address of site) 
of which I am/we* are (state interest in land, e.g. owner, tenant) 
all in conformity with the plans, detailed drawings and specification submitted herewith and doqueted and    
signed as relative hereto. 
2        I/we* hereby declare that no other party has an interest in the land.  The attached form CC2 details all other       
parties having an interest in the land* 
Signed
(applicant) 
Name 
Date 
*delete as appropriate 
for office use only 
Reference number  ………/………  Work commenced ………………………………….. 
Received ……………………………………… Work completed …………………………………….. 
Objections ……………………………………. Start of maintenance ………………………………… 
Objections cleared ……………………………. Adopted as public …………………………………… 
CC Granted …………………………………… 
CONSTRUCTION CONSENT APPLICATION     CC1

Page 58

58 
Reference number ………/……………..         
for office use only 
DOCQUETS OF SERVICE 
1         I/We certify that on (insert date) 
day of  20 
a notice of the lodging of this application has been served by the applicant upon the undernoted proprietors
being the owners of all lands or heritages fronting, abutting or comprehended in the proposed new road or
extension of the existing road and further certify that such notice contained an intimation that plans and other
relevant particulars could be examined at the office located at 
Postcode 
and that objections to the applicant should be lodged with the Roads Authority within Twenty-eight days from
the date of the notice. 
Signed
(Applicant of agent) 
Name 
Address 
Postcode 
Date 
List of proprietors referred to 
Name  Address   
Docquets of ServiceCC2

Page 59

59 
Reference number ……………………..         
for office use only 
1      Notice for service on owner of land fronting, abutting or comprehended in new road or extension of               
existing road) 
Roads (Scotland) Act 1984 Notice under Section 21 (2) of application for Construction Consent 
Proposed Road Construction at a. 
Take notice that application is being made to b. 
by c. 
For construction consent to d. 
If you wish to make representations about the application you should make them in writing not later than 
e. 
To the Roads Authority 
f. 
Signed 
On behalf of 
Date 
a. Insert address or location of proposed road construction
b. Insert name of authority
c. Insert name of applicant
d. Insert description of proposed road construction
e. Insert date 28 days later than the date on which the notice is served
f. Insert appropriate address at which the application is being lodged 
Notice of ServiceCC3

Page 60

60 
Reference number …CC2/01…………………..
CONSTRUCTION CONSENT TO CONSTRUCT OR EXTEND A ROAD 
Construction Consent by…Argyll & Bute Council (hereinafter referred to as ‘the Council’)…… as to the
construction/extension of roads in connection with the proposed development, 
The Council, acting under and by virtue of Section 21 of the Roads (Scotland) Act 1984 hereby grant construction
consent as follows 
The Council Grant authority to 
for roadworks in connection with 
in accordance with 
a. the plans submitted to and approved by the Council which plans are docqueted and signed by the Roads Authority
as relative hereto
b. the particulars set forth in the schedule annexed and signed as relative hereto and
c. the relative provisions of the said Roads (Scotland) Act 1984, on the following conditions(s): 
i. All works are to be completed within a period of  …3… years …0… months from the date of this Consent. 
ii. Construction of roads shall not be commenced until you have provided the Council with
Security for an amount to meet the cost of constructing/completing the construction of the
road(s) in accordance with the Construction Consent, in terms of the “security for Private
Roadworks (Scotland) Regulations 1985.   
iii. All details, specifications etc., are to be in accordance with the Councils “Roads Development
Technical Guidance” unless otherwise stated. 
Signed
(on behalf of the
Roads
Authority) 
Date 
Schedule referred to 
Roads Description 
Development at   Length 
CONSTRUCTION CONSENT  CC4

Page 61

61 
Reference number ……………………..         
for office use only 
AGREEMENT TO TAKE OVER FOOTPATH(S) ASSOCIATED WITH DEVELOPMENT
(to be completed only in respect of footpath(s) which will subsequently be maintained by the Roads Authority) 
Agreement in terms of Section 18 of the Roads (Scotland) Act 1984 between 1 
(hereinafter referred to as “the Council”) and 2 
of 3 
(herinafter referred to as “the developer”) 
Whereby the footpath(s) constructed by the Developer in accordance with 
Construction Consent number ……/…… 
Granted by the Council on 4 
As set forth in the Schedule annexed and signed as relative hereto will, following their satisfactory completion, be
added to the Council’s list of public roads. 
Provided that, should the developer fail to complete the said footpath(s) to the satisfaction of the Council within a
period of 5 
from the date of this Agreement, the Council may itself complete the footpath(s) and recover from the Developer such
expenses as are reasonably incurred in so doing. 
Signed
(on behalf of the
Roads Authority) 
Date 
Signed
(on behalf of the
Roads Authority) 
Date 
Schedule referred to: 
Footpath Description (this may be done by reference to a plan)         
Length   
Notes  1. Insert name of authority  
2. Insert name of applicant  
3. Insert address of applicant  
4. Insert date construction consent granted  
5. Insert period for completion                                          
Footpath Agreement CC5

Page 62

62 
APPLICATION BY A DEVELOPER FOR THE ADDITION OF ROAD(S) AND/OR FOOTPATH(S) TO THE
ROADS AUTHORITY’S LIST OF PUBLIC ROADS 
I/We (insert name of applicant) 
of (insert name of applicant) 
apply 
1* under section 16(2) of the Roads (Scotland) Act 1984, in respect of the road(s) listed in Schedule A annexed and
constructed in accordance with 
Construction Consent number …/…  Granted to me/us* on 
and/or 
2* under section 18(1) of the roads (Scotland)( Act 1984, in respect of the footpath(s)* listed in Schedule B and the
Agreement annexed and constructed and constructed in accordance with 
Agreement number FA/…./…. dated 
For the addition to the Roads Authority’s list of public roads of the said road(s)* and/or footpath(s)* all as shown in
colour on the plan(2)* submitted herewith and docqueted and signed as relative hereto 
Signed
(applicant) 
Date 
*delete as appropriate 
Schedule A referred to: 
Roads Description (this may be done by reference to a plan)         
Length   
Schedule B referred to: 
Footpath Description (this may be done by reference to a plan)         
Length   
for office use only 
Reference number  CC/………/………  Adoption Inspection …………………………….. 
Received ………………………………………  Added to List …………………………………….                                          
Adoption CertificateCC6

Page 63

63 
Reference number …CC/3/1………………….. 
We, 
Name of 
Bank etc. 
Guarantee 
Finance 
CONSIDERING THAT 
Developer 
Has been granted Construction Consent Ref. …………………… no. dated . …………………… 
By the . …………………… (enter council name) (hereinafter referred to as the Council) as local Roads Authority in
terms of Section 21 of the Roads (Scotland) Act, 1984 for the construction of a private road(s) or part thereof in
connection with 
Development 
all as is more fully detailed in the said Construction Consent and the plans and Schedule relative thereto, considering
further that the estimated cost of constructing the said private road(s) or part thereof in accordance with the said
Construction Consent and others is 
Sum of Money 
And that the said (Developer) 
Has requested us to grant security for such sum to the said Council by means of a bond in terms of the Security for
Private Roads Works (Scotland) Regulations 1985, do hereby as cautioners and sureties bind and oblige ourselves and
our successors to pay to the said Council and its successors or assignees, on receiving from the said Council a demand
in writing, such sum not exceeding 
Sum of Money 
Which the said Council states in the said demand to be the costs incurred by it in construction, or rectifying defects, in
the said private roads(s) or part thereof in accordance with the Regulation 13 of the said 1985 Regulations: and we
consent to the registration hereof for prevention and execution: IN WITNESS WHEREOF 
Road Bond       CC7

Page 64

64 
Instructions: 
Construction of private road(s) shall not commence until you have provided the Council with financial security for an
amount of 
£………………………….. 
being sufficient to meet the cost of construction/completing the construction of the road(s) in accordance with the
Construction Consent, in terms of the “Security for Private Roadworks (Scotland) Regulations 1985”. 
The Road Bond should be signed by an authorised signatory on behalf of the guarantor (who is normally the bank,
building society or insurance society) and the signature should be witnessed by two witnesses. Please note that you
should advise me of the date that the bond was signed. 
To enable you to lodge your security I enclose the following documents. 
a. One copy of form CC7 to be completed and returned to this office with your security. 
b. One copy of the “Cautionary Obligation” in favour of …………………………………… (enter council name).  If
you intend to lodge your security in the form of a bond you may use this document. 
c. One copy of “Directions for Signing Deeds” incorporating a signing schedule which you are required to complete
and return with the bond. 
d. One copy of guidance notes for developers. 
Road Bond           CC7 
Road Bond       
Road Bond     
cc7

Page 65

65 
Roads (Scotland) Act 1984
Security for Private Works (Scotland) Regulations 1985
Guidance notes for developers 
In terms of Section 17 of the Roads (Scotland) Act, 1984 and the Security for Private Roadworks (Scotland)
Regulations 1985 (S.I. 2080) you, as a developer, are required to make financial provision with the Council, as Local
Roads Authority in order to safeguard the completion of housing development roads which are the subject of a
Construction Consent.  Such Provision, as required by the Regulations, may be the form of a Road Bond or deposit and
this will serve to protect prospective house purchasers from having to bring incomplete roads up to adoptable standards. 
You are unable to commence building works adjacent to any road permitted by a Construction Consent until you have
met the requirements to the above regulations which came into effect on 1 April 1986. 
In terms of Regulation 6, the security shall be an amount to meet the cost of constructing or completing the construction
of the said roads.  Also to calculate the amount of that security by objecting estimating and negotiation. 
In terms of Regulation 5, that security shall be either a bond in favour of the Council or a cash deposit of a sum equating
to that security.  Such bond or deposit shall be lodged with the Council at the office where your construction consent
was issued. 
In terms of Regulation 16, any person who carried out building works in contraction of these regulations, shall be guilty
of an offence.  It would, therefore, be in your interests to make early contact with the Roads Authority, who will be able
to advise you fully on these procedures.  Copies for form CC7 should be completed and returned with the security. 
Copies of the regulations are also available for inspection at the appropriate office. 
Road Bond       CC7

Page 66

66 
DIRECTIONS FOR SIGNING DEEDS 
Before signing please read carefully 
Every party to the deed must sign on the (insert page) ………….including the inventory and plan, if any, with his or her
usual signature where his or her usual signature where his or her initials are marked in pencil. 
Each Witness to the execution of the deed required to sign on the (insert page) ……… at the pencil mark X, adding
after his or her signature the word “Witness”.  Two witnesses are required to the signature, of each party, but provided
parties sign at the same time, the same persons may witness all the signatures and only require to sign once. 
The witnesses must be above fourteen years of age.  They should know the parties which signatures they are witnessing
personally or at last have credible information as to their identity.  No person interested in the deed should act as a
witness, and one spouse should not be a witness to signature of the other. 
The parties must not insert any blanks in the Deed. 
When the Deed is signed the subjoined Schedule should be filled up in BLOCK LETTERS and returned along with the
Deed.  The schedule may be filled up by anyone.  A female witness should state in the Schedule whether she should be
styles Mrs, Mr or Miss. 
SCHEDULE to be filled up and returned 
Name of party signing Place where signed Date of signing Full Name (including
middle names, if any).
Occupation, and Address
of First Witness
Full Name (including
middle names, if any).
Occupation, and Address
of Second Witness   
PLEASE USE BLOCK LETTERS     
Road Bond       CC7

Page 67

67 
Reference number …………………….. 
Project 
Description of roads 
Location and other details 
Soils - CBR  %  Chainage Limits  to 
Source document(s)   date 
date 
Traffic Information - ADT   At opening year   % commercial 
Source document(s)    date 
date 
Design 1 – way AADF commercial   initial   final 
Life  yrs(n)  Damage factor  n/2 MSA  (Cum total) 
Technical reference(s) 
Thickness of layers in possible construction – (Clause no) mm 
Flexible       Rigid
Surface course     
Binder     Slab
Upper Base     Depth
Lower Base     =
Sub-base     
Capping layer     
Total     
Designed by    date 
Checked by    date 
Carriageway Design Certificate       CC8

Page 68

68 
Reference number ……………………..         
for office use only
Developer 
Scheme 
Check number  
Date Checked   
Result* OK 
Meeting arranged for …../…../….. 
Letter sent on …../…../….. after above meeting 
Letter sent on …../…../….. without meeting 
Submitted  
Drawings 
*delete as appropriate                          
Construction Consent ChecklistCC9

Page 69

69 
CC1  n/a yes no 
Completed correctly?     
Signed by Applicant , not agent?     
CC2  n/a yes no 
Required?     
Completely correct?     
Associated drawings provided?     
Signatures of all notifiable parties?     
CC4  n/a yes no 
Required? (are there any adoptable footpaths?)       
   
Safety Audit  n/a yes no 
Stage 1     
Stage 2     
Stage 3     
Street Lighting Specification  n/a yes no 
2 (number) copies included?     
Docqueted, signed and dated?     
Geotechnical Information  n/a yes no 
Factual ground investigation report     
Interpretative report     
CBR positions relevant to roads?     
CBRs at correct/adequate spacing (25m)?     
Capping layer required?     
If yes, 600/350/combination     
Report from Coal Authority/Mining Consultant?     
Report from British Geological Society?     
Structures  n/a yes no 
Any structures involved?     
Design Certificates (certificate No.)     
Check certificates (certificate No.)     
1 (no) velograph and 3 (no) paper prints of all drawings?    
Docqueted, signed and dated?     
Layout Plan  n/a yes no 
Location Plan (1:1250 or 1:1200) included?     
Proposed road to be adopted shown coloured?     
Scale 1:500, 1:200 for Shared Surface?     
Centre, building and kerb lines shown?     
All curve radii shown?     
All corner radii shown?     
Minimum curve size ok?     
Curve widening required?     
Setting-out information adequate?     
Turning areas of correct dimensions?    

Page 70

70 
Shared Surface transitions dimensioned ?     
continued over 
Layout Plan (continued)  n/a yes no 
Drop kerb vehicle access shown?     
Drop kerb pedestrian crossings shown?     
Cycle track shown?     
Cycle lanes?     
Provision for buses?     
Traffic calming, appropriate spacing for road hierarchy     
Legislation?     
Signing?     
Lining?     
Visibility splays shown?     
Cut and fill shown?     
Carriageway and footway widths shown?     
Resident parking adequate?     
Visitor parking adequate?     
Parking bays correctly sited and grouped?     
(outwith visibility splays etc)     
Courtyard parking behind footway crossing?     
Parking bays dimensioned?     
Road type and width OK for number of houses?     
Road hierarchy satisfied for house totals?     
Driveway gradients OK? (not >10%)     
Areas of different carriageway construction shown?     
Driveway width, and angle OK for carriageway width?     
PU Service access off narrow (3.5m) sections?     
Drainage  n/a yes no 
All crossfalls, superelevation and cambers shown?
(blockwork to have 2.5% crossfall) 
   
Gullies at correct spacing?     
Drainage system and discharge points shown?     
Gully tails shown?     
Double gullies at low points?     
Double gullies with individual tails?     
Gullies at TPs and not unction corners?     
Gullies just upstream of TP at junctions?     
Gullies at traffic calming?     
Gully at point of removal of adverse camber?     
Pipes 150mm minimum?     
Adjacent areas likely to drain into roads?     
If so, have land drains been included?
(NB Land drains to connect to SW system via silt traps)        
Drainage of irregular areas adequate?     
Are non-adoptable area adequately drained?
(NB if not, might issue onto public roads)        
Pipes and culverts under road hydrological study?     
Pipes and culverts under road hydraulic design?     
Gullies off driveways where possible?     
Landscaping OK?    

Page 71

71 
Long Section  n/a yes no 
Vertical alignment details shown?     
Gradients OK?     
Vertical curve lengths correct?     
SW drain gradients shown and correct?     
Manhole positions shown?     
Substrata details to 1.00m below formation?     
Chainages shown?     
Proposed and existing levels shown?     
Typical Sections and Details 
Carriageways and Footway Section  n/a yes no 
Carriageway construction OK?     
Footways construction OK?     
Footway chippings included and detailed?     
Crossfalls detailed?     
Kerb type specified and correct?     
Kerb upstand shown and correct?     
Kerb log correct?     
Kerb log mortar bed shown and correct?     
Heel kerb correct and with 50mm upstand?     
Capping layer shown and correct?     
Materials fully specified? (Specification clauses appendices)     
Shared Surface and service Verge Section  n/a yes no 
Carriageway construction OK?     
Crossfalls detailed?     
Kerb type specified and correct?     
Kerb upstand shown and correct?     
Kerb log correct?     
Kerb log mortar bed shown and correct?     
Continuous demarcation of service strip shown and
detailed?        
Materials fully specified? (Specification clauses)     
Blockwork colour shown and OK?     
Is shared surface steep enough to justify a bedding of
bituminous sand?        
Rumble strip shown and correct?     
Ramp shown and correct?     
Bollards included and correct?     
Footway Section  n/a yes no 
Width if adoptable?     
Footpath construction OK?     
Crossfall detailed?     
Edging correct and flush?     
Foundation correct?     
Materials fully specified? (Specification clauses)     
Drainage included and correct?     
If so, shown on plan?    

Page 72

72 
Gully/Silt/Manhole Cover an Frame Detail  n/a yes no 
Size and grade of cover and frame shown?     
25mm mortar bed shown?      
Services cross-section OK         
Footway crossing with verge OK         
Footway crossing without verge OK         
Pedestrian crossing point OK         
CDM Safety file required before adoption       

Page 73

73 
Reference number ……………………..         
for office use only 
FORM OF COMPLETION AND INSPECTION CERTIFICATE
(as prescribed in the IEE Regulations for Electrical Installation)
(1) (see notes Page 4) 
Details of the Installation New    Alteration to existing    Addition to existing    
Client:  
Address:     
Design 
I/We being the person(s) responsible (as indicated by my/our signatures below), for the Design of electrical installation,
particulars of which are described on page 3 of this form CERTIFY that the said work for which I/we have been
responsible is to the best of my/our knowledge and belief in accordance with the Regulations for Electrical Installations
published by the Institution of Electrical Engineers, (current edition) except for the departures, if any stated in this
Certificate. 
The extent of liability of the Signatory is limited to the work described above a the subject to this Certificate. 
For the Design of the installation: 
Name (Block Letters):  Position 
For and on behalf of 
Address 
(2) Signature  (3) Date 
Lighting Completion and Inspection Certificate   CC10

Page 74

74 
Construction 
I/We being the person(s) responsible (as indicated by my/our signatures below) for the Construction of the electrical
installation, particulars of which are described on page 3 of this form CERTIFY that the said work for which I/we have
been responsible is to the best of my/our knowledge and belief in accordance with the Regulations for Electrical
Installations published by the Institution of Electrical Engineers, (current edition) except for the departures, if any
stated in this certificate. 
The extent of liability for the Signatory is limited to the work described as the subject to this Certificate 
For the Construction of the installation: 
Name (Block Letters)  Position 
For and on behalf of  
Address 
(2) Signature  (3) Date 
Inspection and Test 
I/We being the person(s) responsible (as indicated by my/our signatures below) for the Inspection and Test of the
electrical installation, particulars of which are described on page 3 of this form CERTIFY that the said work for the
which I/we have been responsible is to the best of my/our knowledge and belief in accordance with the Regulations for
Electrical Installations published by the Institution of Electrical Engineers, (current edition) except for the departures, is
any stated in this Certificate. 
The extent of liability for the Signatory is limited to the work described as the subject to this Certificate 
For the Inspection and test of the installation: 
Name (Block Letters)  Position 
For and on behalf of  
Address 
I recommend that this installation be further inspected and tested after an interval of not more that 6 years. 
(2) Signature  (3) Date

Page 75

75 
Explanatory Notes 
1 This document is intended for the initial certification of a new installation or of an alteration or addition to an
existing installation and of an inspection.  An original is to be given to the Client.  The Duplicate should be
retained by the Contractor. 
2 The signatures appended are those of the Competent persons authorised by the companies executing the work
of design, construction and inspection and testing respectively.  A signatory authorises to certify more than one
category of work should sign in each of the appropriate places. 
3 Date to be inserted. 
4 Where particulars of the installation recorded herein constitute a sufficient schedule for the purpose of
Regulation 514-09-01 further drawings/schedules need not be provided.  For other installations the additional
drawings/schedules listed below apply. 
5 The page numbers of each sheet should be indicated together with the total number of sheets involved. 
6 The designer shall prepare Page 3(Particulars of the Installation) and subsequent pages for each Highway
Distribution unit or Terminal Pillar. 
7 The electrician shall complete this page.  It can be used on its own for an existing installation which had not
altered (LMC). 
(4) Schedule of Additional Records 
Drawing/Schedule  Description

Page 76

76 
Particulars of the Installation
(Delete or complete items as appropriate) 
Highway Distribution Unit/Termination Pillar (6) 
Pillar No  Supply Column No 
Location 
Type of Installation  New/Alteration/to existing installation 
Type of Earthing (312-03)  TN-C  TN-S  TN-C-S  TT  IT
(indicate in the box)           
Earth Electrode   Location 
Resistance   ohms    
(only as required) 
Characteristics of the supply at the origin of the installation (313-01) 
No of phases   ascertained
by
enquiry
determined
by
calculation
measured 
Supply voltage    volts 
Prospective short –circuit current    kA 
Earth fault loop impedance (Ze)    ohms 
Maximum demand    Amps per phase 
Overcurrent protective device – Type BS  Rating  A 
Main Switch or circuit breaker (460-0-02) Type BS  Rating  A No of Poles 
if an r.c.d rated residual operating current I n  mA 
Main equipotential bonding conductors (413-02-01/02, 547-02-01): Size  mm2 
Schedule of Test Results: Continuation  pages 
Details of departures (if any) from the wiring regulations (120-04, 120-5) 
Comments on existing installation where applicable (743091-01)

Page 77

77
HIGHWAY DISTRIBUTION UNIT NETWORK                                 
H.D.U. No     Supply Column No. Location      Area                        
SUPPLY  NUMBER OF   HEATER   Source  Optional Items  
SCOTTISH POWER    PHASES   WATTAGE   E.F.L.I   Earth Electrode Resistance (Lighting protection only)
S.R.C.            Ze (Ohms)  Circuit Location Resistance Method of      
LIVE    MAIN SWITCH  P.S.C.C.  No.  Ohms Measurement      
SWITCHED   Raiting    kA                
No. Poles   Voltage     
Type of Earthing       V      
TN-C TN-S TN-C-S TT IT   MAIN FUSE                  
Rating                    
Type       R.C.D. 
MAIN EQUIPOTENIAL               Operating   
BONDING CONDUCTOR MM              Current mA   
Circuit Conductor Protective Device Circuit Insulation Resistance Polarity Remote Full Load Remote End Remote Comments 
Size (mm) Fuse MCB Rating Breaking Satisfactory M.Ohms Satisfactory EFLI Current Voltage Col No. 
Phase No. Ph N CPC BS No. Type in Capacity Y N Ph-E N-E Ph-N Y N Ohms A V                       
I/We being the person(s) responsible (as indicated by my/our signatures below) for the inspection and Test of the electrical installation, particulars of which are described above. 
Certify that the said work which I/We have been responsible is to the best of my/our knowledge and belief in accordance with the regulations for Electrical Installations published by 
the Institution of Electrical Engineers,16th Edition, (BS 7671) (current edition) except for departures, if any, stated in this certificate.  The extent of liability of the signatory is limited 
to the work described above as the subject of this Certificate.                                 
For the inspection and test of the installation:                                   
Name (in block letters):       Position:    G39 Authorisation Level     
For and on behalf of:

Page 78

78
Address:                   
Signature:        Date:   (5) Page  of  Pages     
This page is intentionally blank

Page 79

79 
Appendix 3 – Area Contacts

Page 80

80 
Area Contacts 
Bute & Cowal Area
Traffic & Development Officer
Milton House 
Milton Avenue
Dunoon
PA23 7DU 
Helensburgh & Lomond Area
Traffic & Development Officer
Civic Centre 
38 East Clyde Street
Helensburgh 
G84 7PG 
Mid Argyll, Kintyre & Islay Area
Traffic & Development Officer
1a Manse Brae
Lochgilphead 
PA31 8RD 
Oban, Lorn & the Isles Area
Traffic & Development Officer
Jacksons Quarry Roads Depot
Millpark Road
Oban
PA34 4NH 
Assistant Network & Standards Manager
1a Manse Brae
Lochgilphead
PA31 8RD

Page 81

81 
Appendix 4 – Strategic Roads

Page 82

82
Primary Routes in Argyll   
Trunk Roads: 
A82  Glasgow to Fort William and Inverness
A83  Tarbet to Campbeltown
A85  Perth to Lochearnhead to Crianlarich and Tyndrum to Oban
A828  Connel to Ballachulish 
Applications where access onto the public road network will be onto a Trunk Road should
be referred to Transport Scotland for approval and may be subject to different criteria.   
Strategic Roads Maintained by Argyll & Bute Council as Roads Authority: 
A814  Dumbarton to Arrochar
A815  Cairndow (A83) to Dunoon to Toward
A816  Lochgilphead to Oban
A818   Arden Roundabout (A82) to Helensburgh
A819  Inveraray to A85 at Dalmally
A885  Dunoon to Sandbank
A886  Rhubodach-Kames Castle Road
A844  Bute Circular Port Bannatyne
A886  Colintraive to Strachur
A817  Haul Road
A848  Salen to Tobermory
A849  Craignure to Salen
B833  Rosneath Peninsula
B872  Garelochhead Road
B838  Church Road Arrochar
U48  Shore St, Oban (Unclassified Road but serves Oban Ferry Terminal)
C34  Albany St, Oban (C Class Road but serves Oban Ferry Terminal) 
Other routes are classified as being lightly trafficked routes. However, the higher standard
of visibility requirement may be required under certain circumstances e.g. when there are
very high traffic flows at certain times of the day which are not reflected in the Annual
Adjusted Daily Flows. (AADF).  This judgement will be made by the Roads Authority.

Page 83

83   
Appendix 5 – Standard Details

Page 84

84
SD 08 001 Revision B - Forest Access Road

Page 85

85
SD 08 002 Revision B – Private Drive Way (from un-kerbed road)

Page 86

86
SD 08 003 Revision B – Typical Passing Place Detail 
SD 08 004 Revision B – Access from a Single Track Road (from an un-kerbed road)

Page 87

87

Page 88

88 
SD 08 005 Revision B – Driveway Access Across Public Footway 
SD 08 006 Revision B – Service Bay Detail

Page 89

89

Page 90

90 
Bute & Cowal Area
Traffic & Development Officer
Milton House 
Milton Avenue
Dunoon
PA23 7DU 
Helensburgh & Lomond Area
Traffic & Development Officer
Civic Centre 
38 East Clyde Street
Helensburgh 
G84 7PG 
Mid Argyll, Kintyre & Islay Area
Traffic & Development Officer
1a Manse Brae
Lochgilphead 
PA31 8RD 
Oban, Lorn & the Isles Area
Traffic & Development Officer
Jacksons Quarry Roads Depot
Millpark Road
Oban
PA34 4NH 
Assistant Network & Standards Manager
1a Manse Brae
Lochgilphead
PA31 8RD