Democracy Spraffa

Roads Capital Reconstruction Programme 2024/25 - Update Report

Argyll and Bute Council · 20 June 2024
Back to Environment, Development and Infrastructure Committee — 20 June 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL                  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                   20 JUNE 2024
SERVICES                     
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2024/25 – UPDATE
REPORT 
1.0  INTRODUCTION 
1.1 In March 2024, the EDI Committee endorsed a report providing details of the
proposed roads reconstruction programme for 2024-25.  The programme was
based on the 2024-25 allocation of a total of £8.0M.   
1.2 This report provides an update on changes to the programme to be endorsed by
Members.  The programme remains based on the 2024-25 allocation.   
2.0  RECOMMENDATION 
2.1 It is recommended that the Environment, Development and Infrastructure
Committee:   
• Endorses the amended programme of capital works for 2024-25
• Agrees that details of each area committee’s programme will be forwarded on
to individual Elected Members. 
3.0  DETAIL 
3.1  It has come to my attention that the roads reconstruction programme presented
to Members in March 2024 was based on a desktop exercise using various
sources of data as well as having input from Members as part of the Area
Committee business days held last year.  Whilst the desktop exercise provides a
good starting basis for developing the final programme, it doesn’t reflect detailed
local course visual inspections and as noted in the March report, would not reflect
any winter deterioration experienced on the road network.   
3.2 The local course visual inspections and measurements were carried out later than
normal mainly due to resourcing issues as a result of the response to the large-
scale flood and road closure incidents experienced last year from October 2023
and the knock-on effect this has had on workloads, in addition to sickness
absence of some key individuals involved in the process.

Page 2

3.3  The local course visual inspections and measurements now carried out by officers
have identified, in some areas, where the original programme reported in March,
should be amended. All schemes costings have been updated now that
measurements have been carried out.  There are new schemes added into the
programme and schemes that have now become unaffordable that have had to
be de-prioritised; it should be noted that schemes raised by Members at the Area
Business Days have remained in the programme.   Details of the new schemes
and those that are no longer affordable are noted in Appendix 1 and are
summarised below.  The full revised programme is included in Appendix 2.   
MAKI 
A total of 31 Schemes were presented to the EDI Committee totaling £2.48M 
The updated report presents a total of 31 Schemes with the same budget of
£2.48M. However there have been changes to some scheme costings and: 
• 2 schemes added in Mid Argyll and 2 schemes rescheduled. 
• 1 scheme added on Kintyre with 3 rescheduled.
• 2 schemes added on the islands and 1 scheme rescheduled.   
Members are asked to note: 
a. There is an estimated outturn over budget allowance of £33,395.21, for Mid
Argyll, this was because of the urgent need to include the C43 Crinan Canal
works where the Council are responsible for maintaining the surface over Loch
4. Failure to carry out this work may well lead to a malfunction in the bridge
mechanical system which would cause issues for Scottish Canals which we
would potentially be liable for. 
b. There is an estimated outturn over budget allowance of £27,103.49 for Kintyre,
this is preparation work for the 2025-26 Surface Dressing works. 
c. There is an estimated outturn under budget allowance of £8,895.48 for the
island work. Should this remain, the budget will roll into next years island
works. 
If the costs remain in excess of the relevant area budget, we will draw down from
next year’s capital budget as has been done in previous years. 
B&C 
A total of 20 schemes were presented to the March EDI Committee totaling
£1.6M. 
The updated report presents a total of 21 Schemes with the same budget of
£1.6M. However there have been changes to some scheme costing and: 
• 1 Scheme added in Cowal with 3 schemes rescheduled.

Page 3

• 4 Schemes added in Bute with 1 scheme rescheduled. 
Members are asked to note: 
a. There is an estimated outturn under budget allowance of £9,406.04 and
£9,406.64 respectively for Bute and Cowal, if the costs remain unspent this
will roll over into next years Bute and Cowal Budget. 
OLI 
There have been no schemes added or removed in OLI, however some schemes
have been re-costed to deliver best value. The budget remains the same at
£2.8M.   
Members are asked to note: 
a. There is an estimated outturn over budget allowance of £18,089.23, Oban and
Lorn, this was due to more accurate estimates when officers carried out
course visual inspections. 
b. There is an estimated outturn under budget allowance of £7,285.27 for the
Isles, this was due to more accurate estimates when officers carried out
course visual inspections. 
If the costs remain in excess of the relevant area budget, we will draw down from
next year’s capital budget as has been done in previous years. If costs remain
under budget these will be rolled onto next years budget as has been done in
previous years. 
H&L 
There has been 1 scheme added due to available budget after re costings in
Helensburgh and Lomond, and some schemes have been re-costed to deliver
best value. The budget remains the same at £1.12M. 
Members are asked to note: 
a. There is an estimated outturn under budget allowance of £1,842.17 for
Helensburgh and Lomond, if the costs remain unspent this will roll over into
next years Bute and Cowal Budget. 
3.4  It should be noted that any amendments seek to deliver better value for money,
this being the approach over the last decade where we have carefully applied
a strategy of delivering revenue and capital funding collectively and delivering
a series of works designed to minimise reactive work, carry out right first-time
repairs wherever possible and to deliver surfacing techniques and
specifications which maximises the amount of repairs and resurfacing which is

Page 4

delivered.  Members will be aware that the investment that the Council has
made over a number of years and the approach to allocating the funds has had
a positive impact on the Council’s overall Roads Condition Index.   
3.5  The roads reconstruction programme will continue to be delivered by a mixed
economy model with the Councils in-house team delivering carriageway
reconstruction and patching works. The surface dressing element of the
programme will be delivered by an external contractor. This enables the maximum
surface area to be covered which will help to seal carriageway cracks, prevent the
ingress of water and reduce the amount of reactive maintenance for potholes. 
3.6  In 2023-24 there was also a grant from the Strategic Timber Transport Scheme
(STTS) totaling £387k. This grant was significantly less than in previous years and
officers expected this to continue in the current frugal economic climate. Officers
have now been informed that our bids for 2024-25 funding have been rejected
and no funding will be available through STTS for this financial year. This is a
similar position being experienced by other Councils across Scotland. 
3.7  The programme for each of the administrative areas will be forwarded to Area
Committee Members if endorsed by the Committee today. The programme will
also be available on the council website with key scheme status and dates. 
4.0  CONCLUSION 
4.1  This report provides an update on changes to the roads reconstruction
programme to be endorsed by Members.   
5.0  IMPLICATIONS 
5.1  Policy - works assessed and carried out under the current Roads Asset 
Management Plan. 
5.2  Financial - programme will be based on capital allocation for year 2024-25. 
5.3  Legal – None known. 
5.4  HR - reconstruction works delivered by a combination of in-house roads 
operations team and sub-contractors. 
5.5  Fairer Scotland Duty: None known. 
5.5.1  Equalities - protected characteristics – None known. 
5.5.2  Socio-economic Duty – None known. 
5.5.3  Islands – None known. 
5.6  Climate Change – due regard will be given to climate change with a view to 
minimising any climate change impact and these will be considered as and

Page 5

when they arise. 
5.7  Risk - completed works will reduce requirement to repair roads and will arrest 
the carriageway/footway deterioration. 
5.8  Customer Service - overall improvement in road surfaces and the quality of 
driven journeys. 
5.9  The Rights of the Child (UNCRC) – the investment to improve our road network 
will contribute to a safer environment for young people to thrive in. 
Executive Director with responsibility for Roads and Infrastructure: 
Kirsty Flanagan 
Policy Lead for Roads and Transportation:
Councillor John Armour 
June 2024  
For further information contact: 
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
jim.smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
hugh.oneill@argyll-bute.gov.uk 
Tom Murphy, Operations Manager
tom.murphy@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Changes to Programme reported in March 2024 
Appendix 2 – Amended Roads Reconstruction Programme 2024-25