ARGYLL AND BUTE COUNCIL   ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE SERVICES      12 SEPTEMBER 2024 
MARINE OPERATIONS: COUNCIL FERRY SERVICE 
1.0 INTRODUCTION 
1.1 This report gives an overview and description of Argyll and Bute Council’s Ferry
Services. 
It describes:
• the current situation regarding the vessels and the communities they
serve;
• funding mechanism pressures and risks;
• Council ferry transfer Policy;
• Vessel and crew legislation;
• Vessel priority strategy;
• Crewing plan; and
• Supporting infrastructure. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that the Environment, Development and Infrastructure
Committee: 
a) Approve the vessel priority strategy as illustrated in table 2 at 3.4.
b) Approve the crewing plan described at 3.5.
c) Approve in principle, extra sailings outwith the published timetables, which are
required to meet demand until capacity can be increased;
d) Agree that the Council continue to pursue the full funding of the service.

Page 2

3.0  DETAIL 
3.1 Current situation
3.1.1 Argyll and Bute Council is responsible for four ferry services to: Jura, Luing,
Easdale and Lismore. Three of the four routes are operated using ageing
vessels and none of them have any vessel redundancy, so that any breakdown
cannot be covered by another Council vessel. The services currently operate at
a significant deficit with Scottish Government settlement required to help bridge
the funding gap.
3.1.2 The service had previously been run on behalf of the Council by a private
company (ASP) as two 3rd party contracts until October 2018 (for the mainland
routes) and March 2019 (for the Jura route), when they were taken over by
Argyll and Bute Council. This was in part due to preparations being undertaken
before a handover of the ferry service operations to Transport Scotland, which
have technically been on hold since. 
Scottish Government, through Transport Scotland, committed to funding the
shortfall for ferry services but as noted later in this report, the shortfall is not fully
funded.   
3.1.3 Jura route: 
This route is the only vehicle link to Jura and is serviced by the MV Eilean
Dhiura. The vessel was built in 1998 and operates a daily timetable of 15 return
sailings per day Monday to Saturday with an additional bookable sailing in the
morning or evening. 7 return sailings per day are timetabled on Sundays. The
vessel has an ‘LSA capacity’ of 50, which is the amount of Life Saving
Apparatus required to be on board and is therefore the maximum number of
persons permitted on board, both crew and passengers. The vessel can carry
approximately 6 cars depending on size and type and up to 40t maximum deck
load. The crew routinely facilitate extra sailings between the timetabled
departures to clear any queues and this can equate to c.40% more runs per
working day.
This route is operated by 2 crews of 3 persons, consisting of 2 licenced vessel
masters and 1 deck crew who operate a 7 day on – 7 day off rota. 
Figure 1:
MV Eilean
Dhiura
departing Dry
Dock.

Page 3

3.1.4 Cuan route: 
This route has a vehicular element and a passenger only element serviced by
the MV Belnahua and the ML Torsa respectively. The Belnahua was built in
1972 and can accommodate 15.45T deck loading which roughly equates to 5
cars, or a small domestic fuel truck, or a small refuse truck. It was designed as a
quarter loading deck system. There are no overnight berthing facilities for the
vessel, which is moored each night to a buoy. This arrangement presents risks,
especially in poor light and weather. 
The ML Torsa is a small open work boat used to transfer the crew to the
Belnahua and as the out of hours’ passenger only service during the winter
timetable. 
The route is operated by 4 licenced vessel Masters in 2 crews of 2 but also
requires 2 additional part-time crew members who assist with the Torsa sailings. 
3.1.5 Lismore route: 
This route is passenger only and is serviced by the MV Lady of Lismore which
was purpose built in 2021 and carries 23 passengers. 
The route is operated by 2 crews of 2, a licenced master and 1 deck crew. 
Figure 3:
MV Lady of
Lismore.
Figure 2:
MV Belnahua
showing the
quarter
loading
arrangement.

Page 4

3.1.6 Easdale route: 
This route is passenger only and is serviced by 2 open work boats, the ML
Fladda and the ML Easdale. 
The route is staffed by 2 crews of 2, a licenced master and 1 deck crew.
3.2 Funding Pressures and Risk 
3.2.1 The Ferries Plan 2013-2022 established that Scottish Government was willing to
work with Local Authorities to explore how responsibility for, and therefore
funding of, ferry services could be considered in a different model. It has been
Scottish Government Policy, through Transport Scotland, to fund the shortfall in
operating Local Authority ferry services since Scottish Government funding
support for local authority ferry services became incorporated into the Local
Government financial settlement process and distribution system in 1989 where
it has remained since. 
In 1989-90, the Local Government Funding distribution arrangements changed,
with the previous expenditure-based controls discontinued in favour of a system
of Grant Aided Expenditure (GAE) assessments. The main difference was that
Grant Aided Expenditure represented the aggregate amount of expenditure that
Scottish Ministers considered appropriate to be taken into account in deciding
the level of grant support to be distributed across Scottish local authorities.
Grant Aided Expenditure was intended to be a means for allocating the pre-
determined Spending Review funding totals equitably amongst local authorities. 
The funding support has now changed again to a Specific Grant but this change
from GAE to a Specific Grant has not provided the adjustment that was
anticipated and you will see in Table 1 below that the Council has been required
to top-up the shortfall.   
Table 1: Ferry costs 2016 to 2024  
2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24
Cost £ 1,827 1,694 1,691 1,602 1,501 1,892 1,798 1,695
Grant £ 754 675 768 855 1,182 1,269 1,300 1,708
% Transport
Scotland 41% 40% 45% 53% 79% 67% 72% 101%
% Argyll &
Bute Council 59% 60% 55% 47% 21% 33% 28% -1% 
3.2.2 This year (2024–2025), an estimated funding of £2.316m was required to
maintain the current service levels for the year and the request was submitted to
Transport Scotland in September 2023. 
The amount was comprised of the realistic funding required for 2024-2025 for
Council run ferry services including the essential annual and preventative
maintenance costs for the vessels.

Page 5

The ferry service could expect an income of c. £674k and this was also
accounted for in the calculation. 
The Council will receive £1.708m* this year, which is the same amount as 2023-
2024, leaving a significant shortfall to be accounted for by the Council, for which
there is no budget. 
*The funding provided by the Scottish Government as noted in the finance
settlement was £1.821m, this included funding for Kerrera ferry route, Ulva and
Craighouse to Tayvallich.  £1.708m was for our internal ferry services.
3.2.3 Council Ferry Transfer Policy 
As mentioned above, the Scottish Government through Transport Scotland
expressed a willingness to take responsibility for all lifeline ferry services
operated in Scotland. 
The Draft Ferries plan published in 2011 stated: 
“The Scottish Government is willing to be responsible for all ‘lifeline’ ferry
services in Scotland.” And, 
“The Scottish Government is also willing to work with the relevant Local
Authorities to discuss the possibility of the Scottish Government taking over
responsibility for services currently provided by them.” 
Appendix 5 to the Ferries Plan outlined the ‘Principles for Transferring
Responsibility’ and contains the following points:
• The Local Authority wishing to transfer responsibility for a lifeline ferry
service to the Scottish Government must also be prepared (where
necessary) to transfer ownership of the ports and harbour infrastructure
used.
• …the Scottish Government will only fund services at a level considered
necessary after applying the RSM (Routes and Services Methodology).
Any over provision in services would need to be addressed by the Local
Authority ahead of a transfer or else continue to be funded by the Local
Authority afterwards;
• Agreement will have to be reached about the levels of capital and
revenue funding to be transferred to Scottish Government. In terms of
capital funding, consideration of the current age and condition of the
vessel(s) and harbours/piers will be required, and agreement reached on
the correct level of funding to be transferred. Revenue funding to be
transferred will represent the ‘true’ cost of providing the service. In other
words, funding to be transferred will include funding for the particular ferry
service(s) made available by the Scottish Government, via the local
government block grant, and the additional contribution made by the
Local Authority itself.;
• Agreement must be reached about the correct split of responsibility. The
Scottish Government is keen to discuss shared responsibility. Where the

Page 6

Local Authority retains a level of responsibility for defining services, the
Scottish Government will be looking for them to also retain a degree of
funding responsibility; 
In March 2013 Argyll and Bute Council agreed the proposal to undertake the
Routes and Services Needs Assessment and subsequent Business Case
Process that would allow the Council and Transport Scotland to consider the
transfer of responsibilities for the four council operated ferry services. 
(Ref: Report by the Executive Director of Development and Infrastructure dated
13 March 2013, submitted and extracts from three Area Committees, submitted,
additional report by the Executive Director of Development and Infrastructure,
tabled) 
Further, in 2019 The Council considered a recommendation by the Policy and
Resources Committee of 16 May 2019 regarding progress in relation to the
potential transfer of council operated ferries to Transport Scotland. Its decision
was that it - 
1. Agreed that the Council continue to pursue the transfer of ferries to Transport 
Scotland. 
2. Agreed that the transfer should be on the basis of ‘no transfer of revenue
funding’. 
However, following primary discussions between Transport Scotland and Argyll
and Bute Council no agreement was reached although Transport Scotland
undertook that the lifeline ferry services operated by Argyll and Bute Council
should in theory be fully revenue funded by Scottish Government. 
As recognised in the Transport Scotland ‘Principles for Transferring
Responsibility’ document it is generally agreed that the day-to-day operation and
responsibility of services still best sits with the Local Authority as it is closer to
and more accessible to the needs of the Communities. Therefore, the Council
has continued to pursue the full funding of the service by Transport Scotland. 
It is perhaps worth noting here that those discussions also included the desire
from Transport Scotland to transfer some of the Council’s harbours. To date the
Council has not supported the selective transfer of some harbours because the
income from the busier ports is required for prudential borrowing repayments
which in turn facilitates the upkeep and upgrading of the marine infrastructure.
3.2.4 The ‘Ferries Plan’ mentioned above came to an end in 2022 to be replaced by
the, as yet unfinished, Islands Connectivity Plan (ICP) being produced by
Transport Scotland. 
The ICP deals with the CalMac services and excludes Local Authority run
services. To ensure our communities who rely on Council ferry services are
considered in a similar analysis, the Council has recently undertaken a Ferry
Study carried out by Caledonian Economics.

Page 7

That ‘Argyll & Bute Council Ferry Report’ concentrates on the three mainland
ferry routes and has now been completed to final draft. It will be presented to
Members shortly. It also forms the first part of the associated Crown Estates
funded Feasibility study and specification work for pier infrastructure at
Ellenabeich and Easdale which would support the ongoing provision of the
council ferry service. 
Among other things the report looks at the longer-term cost analysis of fixed
links versus ferries with some mixed results from the community engagements.
Fixed links must be considered however in the long-term planning of our ferry
services, with a comparison against the increasing costs of building and
maintaining vessels over a comparable lifespan.
3.3 Vessel and Crew Legislation
When looking at shipping operations and particularly passenger carrying vessels
it is perhaps helpful if there is an understanding of the rules governing our ferry
services. 
The summary below gives an idea of the vast field of UK and Local Regulations,
Directives, Guidance and Safety Notes which cover everything from vessel
construction, surveys, repairs, modifications, stability, crewing and operations.
It may go some way to explain why it is not always a simple task to amend
timetables or modify vessels.
3.3.1 Service Certification
Our ferry operations are permitted through a system of checks and audits
carried out by the UK Maritime and Coastguard Authority (MCA). Every year we
undergo a rigorous audit resulting in the revalidation of our Document of
Compliance (DOC).
These checks ensure that the administration and certification comply with
legislation and are correct.
3.3.2 Waterways and Vessel Categorisation 
The Merchant Shipping (Passenger Ships on Domestic Voyages) Regulations
2000 implements Council Directive 98/18/EC on “Safety Rules and Standards
for Domestic Passenger Ships”.
These regulations identify four domestic passenger ship classifications, the
waters where they permitted to operate and whether that permission is summer
only or year-round.
Three of the four ferry routes serviced by Argyll and Bute Council are
categorised as ‘not sea’ which means they are in some way sheltered enough
that they can operate under relaxed rules and codes like the ‘Inland Waters
Small Passenger Boat Code’.
For our ferries the most significant consequence of these rules is that the Jura
ferry is considered to operate at ‘sea’ with the full significance of that definition.

Page 8

3.3.3 Crew Certification
All Officers and crew serving on UK Merchant vessels are required to have a
minimum level of certification which is regulated by the MCA and must be re-
validated at a cost on a regular basis. 
Alongside this is the ‘Minimum Safe Manning’ level, which states the legal
minimum crew and their certification required for each vessel.
Depending on the water category and the size of the vessel there are therefore
restrictions on which Officers can move from route to route and can effectively
curtail career advancement and resilience.
3.3.4 Vessel Certification 
Every commercial vessel is required to be certified by both a Flag State (e.g.
United Kingdom, USA, Panama etc.) and a Classification Society (e.g. Lloyds,
DNV, Bureau Veritas etc.). The rules by which the vessel is constructed,
modified, run commercially, maintained and eventually disposed of are
determined by these authorities. If any vessel does not at any time comply with
the ‘rules’ it will not be certified and cannot be insured or ‘work’. 
Passenger ships operating in the UK domestic areas must also adhere to
specific codes of practice and standards (e.g. Merchant Shipping (Passenger
Ships on Domestic Voyages) Regulations 2000). These regulations ensure the
safe operation and navigation of passenger ships which include our ferries and
includes a mandatory annual ‘Out of Water’ survey with MCA.
A further important point to understand is what is commonly known as the
“Grandfather Rights” Regulations. The current ‘Rules’ evolve and change over
time, leaving existing vessels following out of date regulations until a cut off point
is reached. For our older vessels The Merchant Shipping (Safety Standards for
Passenger Ships on Domestic Voyages) (Miscellaneous Amendments)
Regulations 2022 apply to domestic passenger vessels operating as Classes III
to VI (A) vessels. These regulations came into force on December 29, 2022, and
meant that even the oldest vessels must now comply with the modern standards
and in our case, modifications must be completed by April 2025.
Equality Act (EA) compliance is a matter that affects our plans with the
‘mainland’ ferry routes. 
Any changes to these services will require new vessels with accessible ramps or
walkways, representing a step change in the cost and provision of the services.

Page 9

3.4 Vessel Strategy
3.4.1 The Road Equivalent Tariff (RET) is a distance based fares structure for
passengers, cars (including small commercial vehicles) and coaches. It was
introduced in a series of steps from 2008 to 2015 as part of the ‘Ferries Plan’.
Generally, RET has been a huge success in stimulating demand for travel to
those islands where the cost significantly reduced as a result of the intervention,
but the lag in increasing ferry capacity through new vessels is still limiting the
benefit and impeding mainland travel to islands. 
New vessels and the associated marine infrastructure to accommodate them at
our ports are both expensive and have lengthy lead times. 
It is therefore important for us to not only have a long-term strategy for vessel
replacement but also to look at the longer term needs of the island communities
served by our ferries. 
Table 2 below illustrates a vessel strategy, which represents a realistic and Best
Value approach to gain the most benefit from resources as they become
available.
Table 2: Ferry Service Priorities 
Priority Description Benefits
1 On-site accommodation at Port
Askaig. Present situation requires
Officers and crew to be residents of
Islay as well as suitably qualified.
Along with the market supplement
and the 7-day rota, this will allow
the recruitment of suitably certified
Officers required for resilience
and new vessel minimum
manning levels.
2 Funding for concept design to ‘Keel
Ready’ for the new Jura vessel.
To identify capacity levels; fuel
type; crew size and infrastructure
upgrade requirements. Also
allows for a more accurate
assessment / estimate of build &
certification costs.
Figure 4:
ML Easdale.
The other
open work
boats are of
the same
design.

Page 10

3 Jura New Build (and associated
infrastructure at Feolin & Port Askaig).
Fit for purpose and the future
vessel to support the Jura
community for the next 20 – 30
years.
4 Eilean Dhiura is re-deployed to the
Cuan / Luing route (and associated
slipway upgrades on the route).
A marked upgrade for the island
capable of refuse collection, HGV
and capacity increase from c.15t
to c.40t.
Due to life extension on Belnahua
(2024) and Eilean Dhiura (2022)
service expects to make savings
by utilising Belnahua as relief
vessel (for Dry dock) etc.
5 Easdale work boat replacement with
landing craft type vessel.
TBD 
3.4.2 The Jura route has been identified as the priority for a replacement vessel and
therefore funding, based on this cascade of vessels plan. 
The vessel plan uses the available resources and maximises the return from
investments on vessel life extension works. It gives a service improvement in
terms of redundancy and resilience while minimising the new build timescales.
This will also allow time to assess future needs and fixed link opportunities for
each community. 
It is imperative given the timescales involved that step 1 above is progressed
with some urgency as duration estimates could well be in terms of years before
a new vessel is on service at Jura.
3.4.3 Age and lifespan of vessels 
When comparing services and comparable costs it may be helpful to explain
why there is routine repair and maintenance and there is also ‘Life Extension’
works. 
The life of a vessel will depend greatly on how that vessel is worked and the
location of that work. The lifespan will also depend on how conscientiously the
routine maintenance, surveys and inspections are carried out. 
Generally, we should consider 15 years as the benchmark however with care it
is occasionally possible to have a vessel like Belnahua reaching over 50 years
and still working. This, however, should be recognised as an extreme exception.
3.4.4 Issues with this include:
• The ‘Grandfather’ regulations will eventually result in the modifications
required outweighing the costs of a new build or younger second-hand
tonnage that already comply;
• The capacity and performance of the vessel decreases over time as the
analysis of the stability is re-determined;

Page 11

• Engine emissions and fuel consumption are outstripped by new
technology and regulations;
• It is much more expensive to repair or replace obsolete parts and replace
worn steel; and
• The risk and consequences of breakdown greatly increase.
There have been recent examples of the results and consequences to island
and remote communities of older fleet breakdowns including the Corran Ferries
and the well-publicised CalMac issues.
3.4.5 In the Council’s fleet, life extension works including new engines have been
completed on Eilean Dhiura (2022) and Belnahua (2024). The result of this work
is that fuel efficiency, emissions and performance have all improved along with
confidence in reliability. This is particularly important because for Luing and
Jura, our ferries are the only transport link on and off the islands and there is
currently no redundancy with these services. 
3.4.6 Cost benefit from the plan 
A further benefit from the life extension work and cascade plan will follow the
new build Jura vessel entering service. 
Currently, a significant part of the docking and maintenance costs are for relief
vessels. 
The service must find a vessel that:
• Physically fits with the existing port infrastructure;
• Is suitable for the island traffic needs, HGV etc.
• Can operate in the conditions to the timetable;
• Is available at the same time as the dock is available for our own vessel;
and
Figure 4:
MV Belnahua
during Life
Extension
works
showing the
old and the
replacement
engines.

Page 12

• Is legally permitted and certified to operate in our waters.
Recent figures for relief vessels show just how expensive meeting those
conditions are, with costs in the region of £2,250 per day for the Cuan route and
€4,500 per day for the Jura route. The suitable replacement vessel for Jura had
to deploy from Ireland and agree to additional certification surveys before being
awarded a contract, which takes time and presents uncertainty and risk during
the planning phase.
Following the arrival of a new Jura vessel however, the plan to redeploy Eilean
Dhiura on the Cuan route means it will be available to take over at Jura during
any breakdown or dry-docking period for the new vessel. Keeping the Belnahua
at Cuan means that route is also covered while the Eilean Dhiura was
redeployed at Jura or during a dry dock period.
The plan also, therefore, gives some much needed reassurance, redundancy
and savings as well as maintenance planning flexibility.
3.4.7 Term Contracts 
As described above the service has a mid to long term plan for the vessels,
improving value for money and improved maintenance planning. 
For the shorter term we are currently working towards awarding term contracts
with vessels and dry-docking facilities to cover a three to five year period. 
This will allow us to charter a suitable vessel at a more competitive rate and
programme in dry docking plans, spare part ordering, timetables, surveys etc. in
advance. 
Figure 5:
MV Eilean
Dhiura.

Page 13

3.5 Crewing Plan
3.5.1 Along with the vessel plans there have been recruitment and retention issues
particularly on our Jura route that have required addressing to maintain the ferry
service. 
In contrast to the 3 ‘mainland’ routes the Jura service is island to island so
requires that the crew live on Islay to ensure the vessel can be sailed on the first
sailing. 
In recent times the council has seen the movement of qualified staff from its
services to CalMac services and the skills shortage in remote rural and   island
locations means that the two organisations are often in direct completion when
recruiting for staff. 
A new shift rota has been introduced with a 7 day on – 7 day off duty cycle that
mirrors similar conditions with CalMac. This allows our crew to have an
improved work / life balance, pursue other opportunities during their time off and
eventually will be able to live elsewhere when accommodation is available at or
near the port. 
There is a need to progress accommodation at or near Port Askaig as shown in
the ‘Table 2: Ferry Service Priorities’ above. This would be a sea change for this
service as we would be able to employ qualified seafarers living out with Islay,
utilising the new duty rota.
3.5.2 When we have successful recruitment and with existing crew we have issues
concerning training, career advancement & retention. 
It is our ambition to recruit into positions where we can commit to training and
having qualified Officers able to move better between the routes if possible.
3.5.3 Part of the solution to our crewing issues is in addressing the pay and
conditions, particularly for those staff operating in competition with CalMac and
distillery employment on Islay. 
There have been potential solutions presented including contracts with arm’s
length companies and continued ‘Market Premium’ (sometimes referred to as
Market Supplement or Plussage). 
The service currently supplements vessel Masters on Eilean Dhiura to ensure a
closer parity with similar contracts offered by CalMac, but all and any retention
ideas will be need to be assessed to find solutions. 
3.6 Supporting Infrastructure
3.6.1 It is important to remember that with the vessels and the crews there is also a
requirement to ensure shore side infrastructure is upgraded and maintained fit
for purpose and the vessels that use them. 
Slipways at Port Askaig and Feolin will be required to be upgraded for the
design of the new vessel.

Page 14

Slipways will also need to be modified on the Cuan route to accommodate the
Eilean Dhiura when it is redeployed there following delivery of a new vessel at
Jura. 
Argyll and Bute Council’s Marine Asset Management Plan will be updated at the
appropriate time to facilitate these changes. 
In addition to these points it might be helpful here to note that we still have the
intention to consolidate the Council’s Harbour Orders (with the exception of
Oban) into one combined Order. It is incumbent on a Harbour Authority to
review and update its legislation and this exercise will modernise ours to ensure
it remains effective and fit for purpose. 
It is intended that this will commence on completion of the Oban HRO work. 
4.0 CONCLUSION
4.1 This report gives and overview and description of Argyll and Bute Council’s
Ferry Services.
4.2 It describes:
• The current set up regarding the vessels and the communities they
serve;
• Funding mechanism pressures and risks;
• Council ferry transfer Policy;
• Vessel and crew legislation;
• Vessel strategy;
• Crewing plan; and
• Supporting infrastructure. 
5.0 IMPLICATIONS
5.1 Policy - Agreed consensus on transfer of ferry services to Scottish
Government / Transport Scotland.
5.2 Financial - Risk that subsidy will reduce or be removed
5.3  Legal - All associated crew and vessel legislation.
5.4  HR - Crew contracts and pay.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics, Easdale vessels accessibility. 
5.5.2   Socio-economic Duty - Lifeline ferries with no other means to travel to /
from islands. 
5.5.3  Islands - True Lifeline services, school, health and business, Islands
Connectivity Plan.

Page 15

5.6 Climate Change - Rising water levels on infrastructure, more extreme weather
events. 
5.7 Risk -  Insufficient subsidy and infrastructure decline.
5.8  Customer Service - Complaints about current service levels will increase as
vessels age.
5.9 The Rights of the Child (UNCRC) - Education and social access to mainland
facilities and services. 
Executive Director with responsibility for Roads and Infrastructure: Kirsty
Flanagan
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
27 August 2024                                                  
For further information contact: 
Jim Smith, Head of Road and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Scott Reid, Marine Operations Manager
Scott.Reid@argyll-bute.gov.uk