APPENDIX 2 - SALT USE REDUCTION AND PRESERVATION OF STOCKS PROTOCOL 
Argyll and Bute Council WINTER SERVICE – OPERATIONS 2024 - 2025     
Protocols for the reduction in use of salt and preservation of remaining stocks. 
Storage Capacity, Stock Transfers and replenishment times 
Storage capacity in all 15 “Operational” salt stores has been increased by 3,500tonnes to
approximately 14,000tonnes, since 2009, through phase 1 of the covered tunnel construction
programme. The 3,000tonne plus capacity Dome in Helensburgh, although an operational store,
has an element of strategic storage. 
For national salt resilience purposes, daily usage is calculated on 2 Priority WRC1-3 network
treatments and one WRC4 “other routes” treatment in each 24hr period. 
This equates to 370 tonnes/day at normal use levels, 600 tonnes/day for heavy snow. 
The West of Scotland Co-ordination Group, Roads sub-group agreed that Roads Authorities should
achieve a minimum storage capacity of equivalent to 70% of the average total salt usage of the last
three severe winters. This equates to a minimum 9,949 tonnes for Argyll and Bute for 2024. 
The target tonnage for the start of each season, 1st November may vary, as replenishment of some
stores are related to shipping capacity and availability, however a minimum 11,000tonnes is
considered reasonable. This equates to 28 continuous days supply at Winter Policy treatment
levels. 
As the national salt supply contract has an allowance of 21days to fulfil delivery from point of order,
the minimum resilience required in normal conditions equates to four weeks operations or
approximately 60% of the new capacity, at 10,000tonnes. In practice, reduced quantities of
6,000tonnes before replenishment are acceptable. This equates to a resilience of 16 days
operations, at normal treatment levels. 
Within this total quantity, material may require to be moved between stores to preserve a degree of
individual resilience in each of the operational stockpiles around the network. Internal transfers
between stores ensure adequate stocks are available as much as practicable to maintain a
consistent treatment regime throughout the network. In this way the hierarchy of route treatments
can be preserved as per the policy, for as long as practicable within any delivery shortage period. 
Operational Decision techniques to Manage Salt use. 
Winter Service Policy already recognises the need to preserve salt primarily for the prevention or
treatment of ice on higher speed carriageways. 3Grit:1Salt mixes are already utilised in Grit Heaps
and Bins and in the reactive treatment of footways. 
Salt preservation techniques can be instigated on carriageway treatments where forecasts or
conditions indicate that a mixture of salt and grit will provide the best treatment to aid traction. The
winter operations decision to use 50/50 mixes should only be for this purpose, rather than to
preserve supplies. In periods of falling snow, Grit only should be used on “return” ploughing legs
until such time as snowfall ceases and there is an expectation that salt will melt any residual snow
after ploughing. 
In settled constant dry conditions Residual Salt levels on carriageways allow the curtailment of
further treatments, as part of the daily operational plan.

Page 2

Reduction in Salt use in treatments, to preserve remaining stocks. 
Where salt stock levels reduce and replenishment activities are doubtful in either quantity or
timescale, the use of salt will be curtailed under the following procedures. 
Salt Preservation level  Circumstances    Authorised by. 
SP1  Total Operational Stocks reduce to 6,000tonnes  Winter Manager 
This level will be reached in conditions of reasonably prolonged hazardous conditions or where
extreme conditions reduce the effectiveness of salt. The supply chain for salt replenishment may
become of national importance and Transport Scotland and West of Scotland Co-Ordination Group
advice may be received. 
First Operation:- Activate replenishment from Strategic Stockpile at Helensburgh Dome
Depending on the likely delay in replenishment, part of the Strategic stockpile may be moved to
other operational stores. The quantity will be determined by the potential delivery date for shipping,
to replenish the Helensburgh store from King George 5th Dock Glasgow and other western
stockpiles, via Argyll ports. The transfer of each 1,000 tonnes of stock will provide a further 4 days
resilience within the operational stores, at normal use rates. 
Resilience:-  4 - 12days at normal use levels 375t/day : 2 - 6 days heavy snow 600t/day 
Second Operation:- Activate Salt Preservation Measures. 
Salt treatments will be reduced. Spread rates adjusted from 40g/m2 to 20g/m2, or 20g/m2 to
10g/m2. Further reductions in the salt content of all carriageway treatments will be achieved by
mixing Grit and Salt together, firstly at 1Grit:1Salt then 2Grit:1Salt. 
In extreme frosts where RSTs remain below -5C all day, and salt is considered to be ineffective,
additional treatments of pure Grit on all routes can be instructed to aid traction. Grit heaps, bins and
footway treatments will remain at 3grit:1Salt. 
Resilience:-  32days at reduced use SP1 = 188t/day : 20days heavy snow 
SP2  Total stocks reduce to 4,000tonnes    Head of Service 
Salting treatments will be curtailed to Priority 1&2 pre-treatment routes only (1233km – rev 2021) 
The SP1 salt mixing techniques will be used in all further SP levels. 
All other treatments will be of pure Grit including replenishment of grit bins / heaps. 
Resilience:- 25 days at reduced use SP2 = 156t/day : 15 days heavy snow 
SP3  Total Stocks reduce to 2,000tonnes    Executive Director 
Salting will be reduced to one treatment per 24hr forecast period, of the Priority 1&2 network,
usually 06:00hrs mornings, in advance of the majority of traffic movements. 
All other treatments will be of pure Grit including replenishment of grit bins / heaps 
Resilience:- 25 days at reduced use SP3 = 78t/day : 15 days heavy snow 
SP4  Total stocks reduce to 1,000tonnes    Chief Executive 
Salting reduced to Priority 1 and Priority 2 “A” class routes only 06:00hrs. (492km) 
All other roads and mobilisation times, Grit only. 
Resilience:- 32 days at reduced use SP4 = 31t/day : 20 days heavy snow 
SP5  Total Stocks reduce to 700 tonnes    Chief Executive 
Effectively 2 days resilience at original policy normal use. The trigger point for application to
Scottish Executive Emergency Salt stockpile. Release of salt, allowing replenishment out with the
normal constraints of the national salt supply contract. 
Resilience:- 22 days at reduced use SP5 = 31t/day : 13 days heavy snow 
Total resilience: SP1 (2nd Op) > SP5 (end) = 68 days : 41 days heavy snow.