ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
12 SEPTEMBER 2024 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
1. EXECUTIVE SUMMARY
1.1 The purpose of this report is to update the Environment, Development and
Infrastructure Committee on progress of the large-scale, externally funded
project work of the Transformational Projects and Regeneration Team, and to
highlight key issues that may impact on the successful delivery of projects. 
1.2 The last update report was considered by Environment, Development and
Infrastructure Committee in March 2024. 
1.3 The team is currently responsible for the delivery and or management of projects
and associated grants with a cumulative value of over £45m. Projects the team
delivers and associated grants the team manages are listed in Appendix A. It
should be noted that following completion of each project the team continues to
have the responsibility for the monitoring and final drawdown and reporting up
until the end of the 12-month defects period or beyond depending on conditions
on the respective grant contracts. 
1.4 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s Rural Growth Deal (RGD)
Programme.  This follows the merging of this team with the RGD Programme
Management Office (PMO) following the retirement of the previous
Transformation Projects and Regeneration Manager. 
1.5 Jonathan Welch was appointed as Interim Transformation Projects and
Regeneration Manager in April 2024. 
1.6 Notification has been received that both Regeneration Capital Grant Funding
(RCGF) and Place Based Investment (PBI) funding have been paused for
2024/25 due to budget challenges.  The Transformation Projects and
Regeneration Team will continue to respond to emerging Government policy
decisions and future grant funding opportunities

Page 2

RECOMMENDATIONS
It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Consider the current progress contained within the report. 
ii. Members are asked to note that the grant funding landscape remains
extremely challenging.  The Transformation Projects and Regeneration Team
will endeavour to identify alternative match funding opportunities for future
place based regeneration projects.

Page 3

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
12 SEPTEMBER 2024 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
2. INTRODUCTION
2.1 This report sets out the current position of the large-scale projects, which are
being delivered or have externally secured grants being managed by the
Transformational Projects and Regeneration Team. 
2.2 The Transformational Projects and Regeneration Team sits within the Council’s
Development and Economic Growth Service and works region-wide. The team
has a particular focus on ‘place’, heritage regeneration, the creative industries,
renewables and Islands and works closely with colleagues across the Council,
communities, third sector organisations, town centre heritage building owners
and businesses to realise positive change. 
2.3 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s Rural Growth Deal (RGD)
Programme.  This follows the merging of the team with the RGD Programme
Management Office (PMO) due to the retirement of the previous Transformation
Projects and Regeneration Manager. 
2.4 Jonathan Welch was appointed as Interim Transformation Projects and
Regeneration Manager in April 2024. 
2.5 The team’s work broadly includes the following areas:- 
• Developing and submitting bids to secure external funding of various scale
through a competitive process, such as the new Heritage and Place
Programme previously referred to as the Conservation Area Regeneration
Scheme (CARS) programmes;
• Development and delivery of regeneration projects with a particular
emphasis or theme, such as the suite of measures to encourage shopping
locally;
• Development and delivery of several place-based engagement projects,
working in partnership with the community and key partners, leading to
action plans, such as charrettes, and working with communities to realise
these community ambitions; 
• Development of the economic opportunities for Argyll and Bute across
Film, Creative Industry and Renewable sectors, with the objective of
securing income into the area and delivering local economic benefit,
including support to community organisations working across these

Page 4

sectors. This work also includes the setting up and management of the
Argyll and Bute Renewable Alliance (ABRA) with partners in HIE; 
• Support to third sector organisations involved in the delivery of their own
individual community led economic regeneration projects, as well as
support to third sector organisations delivering regeneration focused
projects where Council funding is involved and/or where projects align
with Council outcomes, such as Regeneration Capital Grant Funded
(RCGF) project funding;
• Drafting and submitting external funding bids to competitive calls such as
the Island’s Programme; 
• Development and Administration of the Council’s, Strategic Events and
Festivals Grants for which 15 grants were awarded under SEF Round 6
(2024/25);
• Overseeing the grant to the Oban 2024 Royal National Mòd (RNM);
• Overseeing the delivery programme and financial administration of
projects supported through funding from Scottish Government, such as
annual Crown Estate funding;
• Working closely with the SG Islands team and working with colleagues
and communities in the development of bids to the Islands Programme
(IP) and associated Carbon Neutral Islands funding.
• Development and delivery of projects within the Council’s RGD
programme. 
2.6 This paper also seeks to report on key issues that may impact on the current
status of each project, such as any amendments to project scope or timeframe. 
2.7 The large-scale projects currently in delivery, either directly by the team, colleagues
across the Council or by a third party and where the team is responsible for
managing the associated grant, are included within the table in Appendix A, and
have a cumulative total value of over £45m. The individual projects being taken
forward under PBI and CE are not listed individually in Appendix A. 
3. RECOMMENDATIONS
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Consider the current progress contained within the report. 
ii. Members are asked to note that the grant funding landscape remains
extremely challenging.  The Transformation Projects and Regeneration
Team will endeavour to identify alternative match funding opportunities for
future place based regeneration projects.

Page 5

4. DETAILS
4.1 The following sections summarise the progress associated with each of the large-
scale projects that are currently in delivery or have grants managed by the
Transformational Projects and Regeneration Team. In addition, the report provides
information on annual funding streams received by the Council (PBI and CE) and
managed by the team as well as annual competitive external funding grants
secured and being managed. The individual projects are listed in Appendix A with
the exception of those individual projects supported through PBI and CE. 
HERITAGE LED REGENERATION PROJECTS 
4.2 Rothesay Townscape Heritage Phase 2 (2017 – March 2024) Project Status -
GREEN 
Rothesay TH Phase 2 started in 2017 and closed in March 2024. The partnership
project was funded by NLHF (£1,888,500), HES (£500k), Argyll and Bute Council
(£200k), HIE (£70,249), LEADER (£65,800) and Sustrans (£21,500).   
Five priority buildings were identified and comprehensive repairs undertaken. 
These were:- 
• 37 Victoria Street / 1 Tower Street 
• 39-43 Victoria Street 
• 69-72 Victoria Street  
• 73-77 Victoria Street   
• The Winter Gardens Discovery Centre 
In addition to the comprehensive repairs to priority buildings, additional
improvements were supported including:- 
• Shopfront restorations to five properties;
• Small grants for work at 18-19 Argyle Street, 8 Tower Street and St Paul’s
Church (Deanhood Hall);
• Window repair grants to four properties at 12 Argyle Street for the
restoration of traditional timber sash and case windows. 
Despite the completion of the Rothesay TH project, it is recognised that the job
of regeneration and preservation is only partially complete and there remain a
number of empty properties in Rothesay’s centre, including the Royal Hotel,
Albert Pier and the Pavilion.  The Transformation Projects and Regeneration
Team are actively supporting efforts to address some of these priority buildings
including:- 
• £9m of RGD funding allocated to Stages 2 and 3 of Rothesay Pavilion. 
• Supporting local social enterprise with funding applications to HES, a
condition survey and business plan for the Royal Hotel;
• £200k of CE funding allocated for demolition of vacant building on Albert Pier;

Page 6

4.3 Dunoon CARS (2017 – July 2023) Project Status - GREEN 
Dunoon CARS, a £2m project is now complete. A fully funded project officer was
employed to deliver the project for its duration. 
The envelope restoration of 4 priority buildings and 32 shopfronts have been
completed. 
Working in partnership with Dunoon Community Development Trust, CHARTS,
Dunoon Grammar School and Tacit Tacit, a complementary scheme of skills
development was successfully delivered with courses and workshops in
stonemasonry, woodworking, painting and lime mortar. An additional grant from
the Castle Knowledge Trust in 2023, allowed for archaeological geophysical
surveys to be undertaken on the Scheduled Monument Castle site in Dunoon. 
The Dunoon CARS evaluation report is currently being prepared by consultants
to evaluate the impact of the CARS funding in Dunoon and a final audit is being
undertaken prior to the project being formally closed down. 
4.4 Helensburgh CARS (2021 – March 2026) Project Status - GREEN 
Helensburgh CARS is a £2.4 million pound project in the third year of delivery.
The partnership project is funded by Argyll and Bute Council (£500k) and HES
(£1.24m) with owner's personal contributions completing the funding.  A fully
funded project officer is employed to deliver the project for its duration. 
Two priority buildings signed contracts and works will be on site around 19th
August 2024 with works being completed around Mid April 2025. A tender
document for the third priority building is currently being prepared with an
expectation of return by Mid February 2024.   A fourth priority building has been
identified and negotiations are ongoing. 
One shop front grant has been completed (November 2023) with owners
reporting an increase in footfall. The second shop front works are in progress
and will be completed by Mid-September 2024. 
Lime mortar courses were delivered successfully on 30/31st May 2024 and a
further lime mortar course is programmed for 19/20 September 2024.   An
apprenticeship training programme for a young person is now live on
Myjobscotland. This is a two-year contract with SVQ Qualifications on
completion. 
4.5 Lochgilphead CARS (2020 – Mar 2026) Project Status – GREEN 
Lochgilphead CARS is a £2.2m partnership project with HES (£969,700) in its
fifth year of delivery.  The project is due to end in March 2026. 
Two priority building projects are almost complete, and work is progressing well
on another two.  A fifth priority building project is currently being developed.

Page 7

A number of small repair grant/shopfront improvement projects have been
delivered and work is due to start on three shopfront reinstatement projects. 
Local stakeholders are benefiting from several traditional skills training courses
and educational activities, delivered via the scheme.  The next activity planned
is a Keeping Warm in Older Homes drop-in event in late September.   
4.6 Hermitage Park, Parks for People (2016 – June 23) Project Status - ORANGE     
The risks regarding the potential location of a skatepark in Hermitage Park has
been deemed acceptable and subsequently a letter has been drafted for
consideration by National Lottery Heritage Fund (NLHF).  Subject to approval by
NLHF the project can now proceed with closure and drawdown of the final
funding of £100,578.  NLHF are the main funder of the project, and had earlier 
confirmed that locating the skate park in Hermitage Park may breach the
purposes of their £2.3m grant.  For reference, the final project evaluation
highlights were reported to the November 2023 EDI Committee and the Park
Manager post ended in June 2023. 
4.7 Tarbert Heritage Regeneration Scheme (TBC) Project status - GREEN 
A new funding stream has been launched called Heritage and Place Programme
(HPP). HPP is a competitive fund run by HES and supersedes the Conservation
Area Regeneration Scheme (CARS) funding, which HES made available over
eight rounds between 2007 and 2019. The Council’s Policy and Resource
Committee agreed on 16 June 2022 to support the submission of an Expressions
of Interest application to HES for the first call of the HPP, and National Heritage
Lottery Fund’s Grants for Heritage Programme to support the Tarbert Heritage
Regeneration Scheme. 
Expressions of Interest to both funds were successful, with invitations made to
apply for an initial Development Phase. A development application to HES was
submitted on 17 November 2022 seeking £40,000, and a further application
submitted to the National Heritage Lottery Fund on 15 December 2022, also
seeking £40,000. In addition to the £80,000 sought from both funding
programmes, the Council have commited £60,000 of match funding to support a
Development Phase totalling £140,000. The outcome of both applications were
successful and following approval from Full Council on 29 June 2023 a project
officer was recruited and the development phase is now progressing in close
liaison with the funders and the community. 
Due to delays appointing consultants, it is now anticipated that this project will
required an 18 month development phase. A report will be brought back to Full
Council prior to any delivery phase bids being submitted. 
WIDER REGENERATION FOCUSED PROJECTS 
4.8 Tarbert / Lochgilphead Regeneration Fund Project Status – GREEN 
In its 2016/17 budget, Council allocated £3m from reserves to support

Page 8

regeneration and economic development in the settlements of Tarbert,
Lochgilphead and Ardrishaig. 6 projects were identified to proceed to Full
Business Case (as ratified by Policy and Resources Committee on 19th October
2017).  The following projects are complete: 
• Gleaner (Phase 1 only) - completed summer 2019.
• Tarbert Harbour – shore side facilities completed in May 2019, car park
completed in March 2021.
• Barmore/Garvel Road junction improvements - completed February
2020.
• Colchester Square/Argyll Street, Lochgilphead – completed May 2021.
• Lochgilphead Front Green – completed August 2022.
• Ardrishaig North Public Realm – completed April 2023. 
The only remaining allocation of funding has been relates to a second phase of
development on the former Gleaner Oil site in Ardrishaig. There is currently
private sector interest in this site and Scottish Canals and Argyll and Bute Council
are in negotiations with a potential developer.  This has the potential to provide
significant inward investment on a number of vacant sites in Ardrishaig. 
4.9 Regeneration Capital Grant Funding (RCGF) Project Status – AMBER 
An update on the current RCGF projects is provided below and is followed by a
table of all current grant contract awards (Table 1) 
• Kilmartin Museum Redevelopment – following a number of delays the
museum reopened in September 2023 following the completion of the
construction and fit out works. We are continuing to work with Kilmartin
Museum as they work through the final stage of the formal close down
of the redevelopment project.
• Port Ellen Community Hub, Islay – a contractor was appointed for the
project in March 2023 and works are progressing. It is expected that they
will be ongoing until winter 2024.
• Scalasaig business units, Colonsay – Project is now complete.
• Kilmory Business Park, Lochgilphead – work is progressing with M&K
MacLeod on the proposed Kilmory Business Park.  Works are expected
to complete in March 2025.
• Obair Ùr Thirodh Tiree Community Business Hub – Project is now
complete. Final RCGF funds to be drawn down in August 2024.
• Kerrera Old School - Project is now complete.
• Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha – A contract
was awarded early in 2023 and construction works are progressing,
works are expected to complete in August 2024.
• Aros Waterfront Development, Mull – outdoor activity hub – a contract
was awarded in January 2024 and works are due to complete in October
2024.
• Nonhebel Light Industrial Park Expansion, Mull – Project is now
complete.  Final RCGF funds to be drawn down in August 2024.

Page 9

Table 1 – RCGF Grant Projects 
RCGF Project Grant
Awarded
Year
Awarded
Balance
Remaining /
Yet to Drawdown
Port Ellen Community hub, Islay  £1,046,223 2021/22 £608,444
Scalasaig business units, Colonsay  £335,000 2021/22 £0
Kilmory Business Park in
Lochgilphead 
£829,000 2021/22 £829,000
Obair Ùr Thirodh – Tiree Community
Business Hub
£565,000 2022/23 £22,309
Kerrera Old School - Community
Hub Final Phase  
£285,000 2022/23 £0
Ulva Ferry Shore Facilities Building -
Doras Caolas Ulbha
£602,590 2022/23 £3,671
Aros Waterfront outdoor activity hub £403,500 2023/24 £193,295
Nonhebel Light Industrial Park
Expansion
£654,000 2023/24 £1,948       
The following stage 2 applications were submitted to the RCGF Round 11
2024/25:
• Fyne Futures Local Food Production and Training Centre, Bute 
• Isle of Luing Community Owned Slate Quarry 
The Council has subsequently been advised that there is no longer budget
available to fund RCGF and as such, Stage 2 applications will no longer be
progressed. Furthermore, there has been no notification of funding for the
2025/26 financial year, this application process would normally commence
during the early summer 2024. It is uncertain if RCGF funding will be available in
future years and moving forward, this could be a significant barrier to the Councils
ability to fund large scale regeneration projects.  
4.10 Scottish Government Place Based Investment Funded projects 2021 – 2024
- AMBER 
When Place Based Investment (PBI) funding was introduced by the Scottish
Government, allocations were provided over a five-year period and to date have
been received as follows. 
• 2021/22 - £821,000 
• 2022/23 - £712,000
• 2023/24 - £496,000 
Unfortunately indications from the Scottish Government are that the Council’s
expectations to receive a further £496,000 of funding for the 2024/25 financial
year are unlikely to be realised. As yet there has been no formal confirmation of
this however, the delay in formal notification will impact the Counicl’s ability to
deliver projects which might otherwise have been supported.

Page 10

Of the 8 projects approved for 2021/22, 7 have been fully completed and 1 is due
for completion in 2024. 
Of the projects approved in 2022/23, all 6 are fully complete. 
The 2023/24 PBI funding of £496,000 is allocated to 8 projects listed below: 
• Dunoon Burgh Hall Trust – Phase 2 to enhance outdoor area - £74,500
• Dunoon CARS/LACER approach – flexible fund to support businesses
with capital improvements to shopfronts/buildings - £49,500
• Helensburgh CARS Shopfronts - £44,000
• Tobermory Worker Accommodation – £90,000
• Nonhebel Park Phase 2 - £40,000
• Bid4Oban – Shopfronts and Oban Signage - £60,000
• Lochgilphead CARS Shopfronts and high-level amenity project –
£100,000 
• LACER Shopfronts in Campbeltown - £38,000
All the projects above are progressed to the point that the funding is secured. 
4.11 Scottish Crown Estate Revenue Allocation Funding 21/22, 22/23 & 23/24 
In financial years 21/22 & 22/23 & 23/24 the Council has received a total of
£4,713,212 and this funding has been allocated to 32 projects. The Councils
allocation for this financial year (2024/25) will not be known until approximately
December 2024. 
4.12 Scottish Government Islands Programme Funded projects 2021/22, 22/23
& 23/24    
The Council submitted 2 bids to the Island’s Programme in 2023/24 and
successfully secured funding for the following projects: 
1. Infrastructure for Worker Accommodation, Tobermory, as part of the Rural
Growth Deal - £700,000. Works commenced on site in Spring 2024 and are
expected to be ongoing throughout 2024.
2. Tiree Community Care Hub, HSCP, - £450,000.  Works have commenced. 
In June 2024, we received notification of the Islands Programme funding round
for 2024/25. The budget has been reduced to £3m and again a competitive
funding process has been put in place. A separate paper has been presented to
the August Policy and Resources Committee outlining the projects which are
being promoted for funding and further information is included in Table 2. 
Table 2 – Proposed Islands Programme Funding Bids 2024/25

Page 11

Project Name - description Project Lead IP funding
request
Total
project
value
Thomson Court – increase
capacity of care facility by 2
bed spaces 
HSCP £390,000 £900,000
Jura Ferry – concept design
for new vessel
Roads and
Infrastructure
Services
£300,000 £300,000
Jura Ferry Bunkhouse –
conversion of Port Askaig pier
building into crew bunk house  
Roads and
Infrastructure
Services
£80,000 £748,000 
It is expected that a decision on these applications will be made in Autumn 2024
with financial commitment of expenditure to be in place before the end of the
financial year.  These timescales are extremely challenging and projects
therefore require to be suitably developed in order to be eligible for funding, in
particular the deliverability criteria. 
In addition to the Island’s Programme, a £1m Carbon Neutral Island Capital Fund
was announced to support those islands previously included in the Carbon
Neutral Islands Programme.  This funding will support communities to implement
their Climate Action Plans. Islay is one of 6 Scottish islands included in the
Carbon Neutral Island’s Programme and the Transformation Projects and
Regeneration Team have been supporting Islay Energy Trust with funding
applications for the projects identified in Table 3 below:- 
Table 3: Proposed Carbon Neutral Islands Funding Bids 2024/25
Project Name - description Project Lead CNI
funding
request
Total
project
value
Solar Islay – a project to install
photovoltaic solar panels on 7
community buildings 
IET £246,444 £246,444
Cornabus Forest Development
– purchase of equipment to
process wood fuel, tree
nursery and community
orchard
Islay
Development
Initiative
£142,285 £354,116
Electric minibuses – purchase
of 2 electric vehicles to
facilitate community transport
IET £82,932 £149,282 
4.13 Scotland Loves Local Projects Oct 21 - 2024 
Argyll and Bute Gift Card - The gift card for Argyll and Bute formally launched in
October 2021. To date, over 325 Argyll and Bute businesses have registered to
accept the card as a means of payment for goods and services. At the full Council

Page 12

meeting of 28th April 2022, members agreed to commit a share of the Local
Authority COVID Economic Recovery (LACER) Fund to the Gift Card. The
approved options were:-
• Issue Scotland Loves Local Gift Card to households in receipt of
Council Tax Reduction Scheme - £797,720;
• Fully fund Gift Card for 2022/2023 into 2023/2024 - £30,000;
• Marketing budget to promote the Gift Card. 
The roll out of the LACER funded Scotland Loves Local Gift Card began in
December 2022 and was sent out to 6,800 eligible households in Argyll and Bute.
In addition to this, the Council issued a further issued 1,244 cards worth just
under £150,000 in total to eligible islands households to help low-income
households with the ongoing cost of living. In November 2023, 1,200 cards were
given to households in receipt of council tax reduction on the islands to the value
of £85. 
The marketing budget has funded the creation of 6 promotional films, to promote
business registration, help awareness of the card and showcase local areas. The
promotional films were successfully shared across social media platforms and
can be viewed on the Council’s YouTube page: ArgyllandButeCouncil -
YouTube.  A social media promotion campaign is being planned to coincide with
Scotland Loves Local Week which runs from August 26th to September 1st 2024. 
In July 2023, the Council piloted its first sales point for the Argyll and Bute Gift
Card at Keeping it Local, Campbeltown. In December 2023, the second sales
point for the Gift Card was established in the Lochgilphead Post Office (also know
as the Bank Store), Lochgilphead. Cards can be purchased in-store from  £5 and
spent within over the 325 businesses across the area. 
Inclusive of the LACER funded cards, as of 17 January 2024, a total of 8,932
cards have been purchased to the value of £957,225. 
5. RURAL GROWTH DEAL 
5.1 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s RGD Programme. The RGD
will deliver £50m of investment from the Scottish and UK Governments for
projects that are a driver for inclusive and transformational economic growth
across the region.  The Council and key delivery partners will also provide a
minimum of £20m of match funding throughout the 10-year Deal programme.  
5.2     The Council, UK and Scottish Governments agreed the ‘Heads of Terms’ for the
RGD on the 11th February 2021. The Heads of Terms Agreement sets out the
general areas for investment and the Full Deal Agreement builds upon this in
more detail.  
5.3 Signing of the Full Deal Agreement is the next key milestone for the RGD
programme and this was scheduled for 7th June 2024 however required to be
postponed at short notice due to the UK General Election. The RGD PMO are

Page 13

liaising with Civil Servants at both the UK and Scottish Government to agree a
revised date for Full Deal Signing.  It is considered that this will take place in
September 2024.
5.4 Following signing of the Full Deal Agreement the Council will enter year 1 of a
10 year programme of delivery.  The Rothesay Pavilion project represents the
majority of the first 2 years of RGD funding draw down and the Council are
currently working to secure a conditional funding endorsement from Central
Government for £9m of RGD funding towards the costs of Stages 2 and 3 of
this project.  It is hoped to award contracts for the remaining construction stages
by September 2024.
5.5 Table 6 sets out details of all projects currently included in the RGD programme
and the proposed split of funding from Central Government.  It should be noted
that projects require endorsed Treasury 5 Full Business Cases in advance of
any funding drawdown from the RGD programme.  The RGD PMO are currently
working with project partners to progress business cases on all RGD projects.
Table 6 – RGD Project Summary 
Project Name Funding
Committed
UK
Government
Scottish
Government
Tourism  Rothesay Pavilion £9m £4.5m £4.5m
KSS £2m - £2m
Creating a low carbon economy £3m £1.5m £1.5m
Rural Skills Accelerator Programme
Dunoon STEM Hub £2.5m - £2.5m
SAMS STEM Hub £2.5m - £2.5m
Business Skills £0.5m - £0.5m
Built Environment Argyll College UHI  £1.5m - £1.5m
Housing  £3m - £3m
CEIC £7m £7m -
UAV Logistics & Training Hub £4m £4m -
Marine Aquaculture Programme
Machrihanish Innovation Campus £3.84m £3.84m -
SAMS International Seaweed and
Shellfish Industry R&D Centre £3.33m £2.33m £1m
Marine Industry Training Centre £7.83m £1.83m £6m
Total Funding £50m £25m £25m 
6. CONCLUSION 
6.1 This report provides an update to the Environment, Development and
Infrastructure Committee on progress with large-scale, externally funded
project work being delivered by the Transformational Projects and
Regeneration Team.

Page 14

6.2 The projects and grants detailed within this report will result in assisting the
economic recovery of Argyll and Bute, helping to sustain numerous small
businesses, community organisations, making our places more investor ready
and improving our towns and villages as places to live, work and visit. 
6.3 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s RGD Programme.   
6.4 Members are asked to note that the grant funding landscape remains extremely
challenging and the Transformation Projects and Regeneration Team will
continue to respond to emerging Government policy decisions and future grant
funding opportunities. 
7. IMPLICATIONS
7.1  Policy - The delivery of these projects fits with the Council’s Corporate Plan,
Argyll and Bute Local Outcome Improvement Plan and the Economic
Development Action Plan. The economic outcomes from this project will
contribute to the Government’s Economic Strategy. 
7.2  Financial - All funding has been approved for the projects detailed in the report.
The funding comes from the Council and from external funding sources some
from highly competitive processes.  We will continue to review costs and assess
budgets. 
7.3  Legal - Each project will have differing legal and procurement requirements
depending on the grant funder and the associated grant contract conditions and
we are working closely with colleagues to identify the support required and to
allow this to be factored into future work plans. 
7.4  HR - The resources required to deliver the projects will be continually
monitored. The management of these externally funded projects as well as the
management of the Council, PBI, CE and IP and RCGF grants requires a
significant amount of resources from the team to ensure that all the necessary
due diligence and financial management is undertaken and the risk is
minimised to the Council. 
7.5  Fairer Scotland Duty: 
7.5.1   Equalities - protected characteristics – None.
7.5.2   Socio-economic Duty – None.
7.5.3 Islands – None. 
7.6  Climate Change - It is an ambition of our project work to work towards net zero
by adopting a carbon conscious approach throughout.

Page 15

7.7  Risk - Construction projects by their very nature are challenging given issues
that can arise relating to site conditions, managing contractors/the design team
and associated budgets and meeting funder’s requirements. The effects of
Covid-19 and the current cost of living crisis has added even more challenges
both in regard to the development/delivery phases of projects. We continually
seek to minimise the risk through strong project management processes,
however until the projects are fully delivered on site there remains a risk. Other
areas of risk relate to the potential for limited uptake in regard to CARS/TH
grants and also over-run on costs for third party projects. In regard to the latter
this is a high risk particularly as the Council is not the responsible body for the
projects or their delivery on the ground. The setting up of regular benefits
realisation group meetings and building good working relationships with the
third parties assists in identifying where issues may arise and where additional
support may be required. Covid-19 and the resulting impact on the construction
industry and costs is an additional risk to the delivery of these projects and we
are reviewing all costs and working with funders to minimise the impact and
manage the risk as much as we can. 
7.8  Customer Service – None. 
7.9  Rights of the Child (UNCRC) – None.   
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Leader of the Council,  Councillor Jim Lynch
Policy Lead for Business Development: Councillor Math Campbell-Sturgess 
August 2024 
For further information - please contact: 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Jonathan Welch, Transformation Projects and Regeneration Manager
jonathan.welch@argyll-bute.gov.uk 
Appendices: 
Appendix A – List of Council and Third Party projects that the team is either
responsible for delivering directly or for managing the grants given by the Council to a
third party organisation.

Page 16

APPENDIX A - LIST OF COUNCIL AND THIRD PARTY PROJECTS 
Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Dunoon CARS  £1,949,965 £500,000 £1,002,348 2017 2023
Rothesay TH2 £3,244,856 £200,000 £2,508,781 2017 2024
Tarbert Lochgilphead Regeneration Fund (Includes TCF Grant) £6,666,112 £3,140,000 £2,473,534 2018 Ongoing
Hermitage Park (Includes TCF and PBI Grant) £3,932,314 £553,317 £3,378,817 2016 2023
Kilmartin Museum RCGF & Council Grant  £7,663,403 £400,000 £275,000 2019 2023/24
Port Ellen Community hub, Islay RCGF grant  £1,570,259 £0 £1,096,223 2021/22 2024
Scalasaig business units, Colonsay RCGF grant  £480,481 £0 £335,000 2021/22 2024
Kilmory Business Park in Lochgilphead RCGF grant  £1,980,000 TBC £979,000 2021/22 2024
Lochgilphead CARS (Includes 22/23 PBI Grant) £2,200,782 £750,551 £1,269,731 2020 2026
Helensburgh CARS £2,400,000 £500,000 £1,240,000 2021 2026
Events and Festivals grants £114,700 £114,700 - 2024/25 2024/25
Royal National Mòd (provisional) £45,000 £45,000 £0 2024/25 2024/25
Place Based Investment 21/22* £260,000 £0 £260,000 2021/22 2022/23
Place Based Investment 22/23** £259,000 £0 £259,000 2022/23 2022/23
Placed Based Investment 23/24 £496,000 £0 £496,000 2023/24 2023/24
Crown Estate Funding Award 21/22 £1,634,604 £0 £0 21/22 Ongoing
Crown Estate Funding Award 22/23 £1,488,199 £0 £0 22/23 Ongoing
Crown Estate Funding Award 23/24 £1,590,409 £0 £0 23/24 Ongoing
Obair Ùr Thirodh – Tiree Community Business Hub - RCGF Grant £1,190,000 £0 £605,000 2022 2024
Kerrera Old School - Community Hub Final Phase - RCGF Grant £548,424 £0 £285,000 2022 2024
Ulva Ferry Shore Facilities Building - Doras Caolas Ulbha - RCGF Grant £652,590 £0 £602,590 2022 2024
Islands Infrastructure Fund 21/22 £201,419 £0 £201,419 2021/22 2023/24

Page 17

Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Scotland Loves Local £46,000 £0 £46,000 2022/23 2024/25
LACER Fund £40,000 £0 £40,000 2022/23 2023/24
Islands Programme 22/23 - Island Community Halls Digital Hubs £100,000 £0 £100,000 2022/23 2023/24
Islands Programme 22/23 - Tobermory Seawall and Railings (also PBI) £450,000 £0 £450,000   2022/23 2023/24
Aros Waterfront outdoor activity hub – RCGF Grant     £414,565 £0 £403,500   2023/24 2024/25
Nonhebel Light Industrial Park Expansion – RCGF Grant   £1,004,000 £0     £654,000   2023/24 2024/25
Islands Programme 2023/24 - Rockfield Road, Tobermory Phase 1 (also
PBI and Crown Estate) £1,105,796 £250,000 £855,796 2023/24 2024/25
Islands Programme 2023/24 - Tiree Care Home £1,250,000 £580,000 £450,000 2023/24 2024/25
Tarbert Heritage Regeneration Scheme – Development Phase £140,000 £60,000 £80,000 2023/24 2024/25
Total £45,118,878 £7,093,568 £19,758,139     
* See separate 12th August 2021 Policy and Resources committee report for proposed breakdown of projects and values. The full award was £821,000.
** Full award for 22/23 was £712,000.  This figure has had the £200,000 awarded to Lochgilphead CARS deducted.  See separate 16th June 2022 Policy
and Resources committee report for proposed breakdown of projects and values.