ARGYLL AND BUTE COUNCIL      ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE SERVICES    19 DECEMBER 2024 
ROADS RECONSTRUCTION BUDGET 
1.0 INTRODUCTION
1.1  This report provides an update to the Environment, Development and Infrastructure
Committee on future forecast capital funding for roads reconstruction and
improvements. 
1.2 With the reduction in available capital funding it is expected that the roads
reconstruction funding will be significantly reduced in the coming financial year. This
will have an impact on road condition. 
2.0 RECOMMENDATIONS
2.1 It is recommended that members of the Environment, Development and Infrastructure
Committee consider and note the contents of this report including the allocation of the
provisional budget set out in the table at paragraph 3.6. 
3.0 DETAIL
3.1  Argyll and Bute’s road network has improved over the last decade likely as a result
from prudent investment of capital funding. Figure 1 below details the Road
Condition Index (RCI) which is measured by a survey method used by all 32
Scottish Councils. The RCI value represents the percentage of roads requiring
treatment, the lower the number the better condition the road network is in. Without
the capital investment over the last decade or so the condition of our roads would
have deteriorated significantly. 
Figure 1 – Road Condition Index (RCI)

Page 2

55.6
54.4 55.3 55.5
54.4 54.2 54.2
49.8 49.79 49.79
44
46
48
50
52
54
56
58
60
RCI
3.2 The Scottish Collaboration of Transportation Specialists (SCOTS) Headline
Maintenance Backlog figure is calculated every two years using road condition data
collected via the Scottish Road Maintenance Condition Survey (SRMCS). The
calculation uses surveyed condition data with a surfacing treatment matrix and
national average unit rates to determine the extent of surfacing maintenance
required to bring whole network surface to an ‘A1’ condition with no defects. The
value of backlog maintenance for Argyll and Bute’s Road Network is £122.5M.
Whilst the backlog figure is useful to help understand current road condition and the
magnitude of making significant improvements there needs to be a realistic
appreciation that fully funding and therefore having a network in A1 condition is not
affordable or achievable. 
3.3 The recent investment has been an average of £7.2M per year which includes
welcomed capital investment from council funds and some external funding. The
broad strategy followed to achieve the modest but steady improved Road Condition
Index (RCI) comes from the council agreed Road Maintenance and Management
Strategy. This strategy being based on well-maintained Highways which is a
nationally recognised document focusing on sustainable road maintenance. 
Table 1 – Capital Investment to date
Fin.Year Annual "Budget" Capital Invest. STTS Other Comment
2011-12 £5,147,793 £4,295,000 £852,793
2012-13 £8,706,321 £8,137,000 £569,321
2013-14 £8,012,160 £6,165,640 £599,909 £1,246,611 add Cap
2014-15 £6,922,089 £6,822,000 £100,089
2015-16 £4,440,987 £4,367,487 £73,500
2016-17 £4,693,612 £4,616,612 £77,000
2017-18 £3,616,443 £3,000,000 £616,443
2018-19 £9,747,042 £8,382,000 £1,365,042
2019-20 £7,867,469 £6,243,388 £1,624,081
2020-21 £6,918,222 £4,828,509 £1,255,568 £834,145 add Cap - Covid Deferred
2021-22 £10,809,462 £6,900,000 £1,299,462 £2,610,000 add Cap - Incl. Covid c/o
2022-23 £9,354,571 £8,096,126 £958,445 £300,000 Coastal Communities.
2023-24 £7,401,608 £7,014,264 £387,344
TOTAL £93,637,779 £78,868,025 £9,778,997 £4,990,756 2011 -2024
£7,202,906 Average annual investment - Roads reconstruction and re-surfacing
ROAD RE-CONSTRUCTION AND RE-SURFACING BUDGETS 2011-2024

Page 3

3.4 The level of Capital funding available for 2025/26 previously agreed as part of the 3
year capital plan is £3.628M for all the activities carried out by Roads and
Infrastructure, other than externally grant funded activity and piers and harbours
investment. The latter of which is generally funded through prudential borrowing
with loans charges being serviced from revenue generated from marine fees and
charges. It should be noted that there are restrictions under Harbour legislation
which limits the use of harbour generated income. 
3.5 The £3.628M mentioned above covers capital investment for roads reconstruction,
vehicle replacement, coastal protection, grounds and cemeteries, flooding, bridge
replacement, lighting and other investment streams. It is estimated that, based on
the £3.628M block allocation, that only around £2M would be available for roads
reconstruction works, with other funding being used to cover other capital demands
across the RIS portfolio. 
3.6 It is proposed that the breakdown of the £3.628M capital block is distributed across
the Roads and Infrastructure Services as set out in the table below. 
Activity Budget Allocation 
Coastal Protection £0.426M
Flood Protection/Climate Change £0.426M
Vehicles and Plant £0.426M
Cemeteries, Playing Fields and Open Spaces £0.1M
Bridges, Structures and Culverts £0.25M
Roads Reconstruction £2M
Total £3.628M 
3.7 Officers have worked up different investment scenarios for roads reconstruction
based on £2M, £3.5M, £5M and £8M investment. From the budget allocation and
forecasts it is anticipated that the actual available funding will be at the lower end of
the scale of the scenarios. Lower levels of investment will inevitably mean that there
is less work carried out and that type of work is likely to differ based on ensuring
that best value can be achieved from the available funding. This will generally result
in thin surface treatments such as surface dressing, right first time patching and
only limited opportunity for inlay and overlay resurfacing (traditional full road width
resurfacing with hot material). The lower level of funding will not support many
traditional overlays and inlay. Table 2 below provides an illustration of what each of
the investment levels is likely to deliver.  This is very much indicative to illustrate
that the likely treatments deliverable at the different levels of funding, funding levels,
winter deterioration, RCI etc. would determine an actual programme. 
Table 2 - different funding scenarios and what this could deliver 
Value of
Investment 
Typical works affordable  Impact on road
condition – see also
graph of an
illustration of
deterioration

Page 4

£2M • Localised surface dressing to seal
and bind the road surface
• Jet patcher repairs
• Right first time structural patching 
• Limited overlay and inlay works
Significant
Deterioration 
£3.5M As above with the addition of:
• Larger surface dressing schemes
• Small increase in overlay and inlay
works 
Deterioration
£5M As above with the addition of:
• Larger surface dressing schemes
• Greater increase in overlay and inlay
works
Deterioration 
£8M As above with the addition of:
• Larger surface dressing schemes
• Significantly more overlay and inlay
works
Slight deterioration 
3.8 The modelling for future years RCI based on different investment scenarios is
illustrated in Figure 2 below. It should be noted that these figures are based on a
model and may change based on vehicular volumes, weather conditions, climate
change etc. From the model projections we can see that: 
• £8M investment will see a slight deterioration, this investment level
previously having been sufficient to achieve a marginal
improvement/steady state. Inflationary increases mean that we now get
less for our pound and the £8M investment is insufficient to hold a steady
state condition.
• Deterioration is increasing as the funding for each scenario reduces. The
model forecasts up to over a 12% RCI reduction based on £2M per year
investment over a 7 year period. 
Figure 2 projected RCI condition based on investment levels

Page 5

40.00%
45.00%
50.00%
55.00%
60.00%
65.00%
2023/25 2024/26 2025/27 2026/28 2027/29 2028/30 2029/31 2030/32
All Roads RCI Projection
Current £2M £3.5M £5M £8M
3.9 It also worthy of note that as capital reduces and road condition deteriorates there
will be a corresponding increase in revenue expenditure due to an increase in
responses to deteriorating road condition through pot holes and larger sections of
surface failure. 
3.10 Capital and Revenue programmes will continue to be delivered side by side
allowing a holistic view of roads maintenance to be applied whilst ensuring that
capital monies are invested within the permitted parameters expected by Audit
Scotland. As capital funds reduce it will be increasingly important that this holistic
approach is taken with some activities potentially being stopped to enable an
investment   strategy which focuses on minimising network deterioration – this may
differ from location to location e.g. peat founded roads may have a different
approach to other locations, rock face and slope stability may be a focus in other
areas etc. 
3.11 A significantly reduced capital budget will result in smaller areas of carriageway
being treated with planned structural patching, surface sealing etc. being the
primary treatments carried out. The exact locations and the treatment types likely to
be largely determined by a combination of winter deterioration and RCI scoring. 
3.12 The works delivered by national suppliers and SMEs will reduce with the majority of
works being delivered in house. There is a core workforce of 82 road workers
supplemented with staff from the wider operations team in refuse, grounds and
cemeteries required in order to deliver winter maintenance. These numbers,
particularly for HGV drivers is already below the optimum with third party suppliers
being used to ensure resilience and service delivery. Figure 3 below details the
model used by RIS to deliver many activities. As funding levels reduce so will the
amount of work delivered by both SMEs and national contractors with a greater
proportion of works being delivered in house. The staff that carry out resurfacing
works and road works through the summer months are essentially the same staff
who carry out winter maintenance (pre-treatment, snow and ice clearance) with
additional staff being deployed from Grounds and Refuse Collection. With a
reduction is capital funding, the amount of road works carried out will reduce with a

Page 6

corresponding reduction in staffing numbers. Delivering the bulk of a reduced
capital roads service in house will help to preserve staffing levels required for the
winter function, this being subject to achieving good value. 
Figure 3 Mixed economy model 
4.0 CONCLUSION
4.1 Contained within this report is a summary of the reduced amount of roads
reconstruction work as a result of significantly reducing capital funds. The reduced
funding will result in a deterioration to our road condition which in turn will increase
the demand on reactive repairs to pot holes and other surface defects. Signage is
anticipated warning of uneven road surfaces and in extreme circumstances roads
may need to be temporarily closed if deemed unsafe to use. 
5.0  IMPLICATIONS
5.1 Policy – As per the Roads Management and Maintenance Strategy 2012 and the
Roads Asset Management Plan
5.2 Financial – agreed and projected future capital budgets are a significant reduction
on recent years’ investment. Reduced investment is expected to increase reactive
revenue spend in order to keep the road network safe.
5.3  Legal – the Council has duty under Roads (Scotland) Act 1984 to maintain the road
network in a safe condition.
5.4  HR – None known.
5.5  Fairer Scotland Duty: None known.
5.5.1   Equalities - protected characteristics – None known.
5.5.2   Socio-economic Duty: None known.
5.5.3 Islands – None known.
5.6 Climate Change – we have seen over recent years an increase in damage to the
road network, much of which can be attributed to climate change
5.7 Risk – reduced capital investment will result in a deterioration of the road network
likely to result in an increase in safety related defects occurring.

Page 7

5.8  Customer Service – deteriorating road network is likely to increase complaints and
third party insurance claims
5.9 The Rights of the Child (UNCRC) – None known 
Executive Director with responsibility for Roads and Infrastructure, Kirsty Flanagan 
Policy Lead for Roads, Amenity and Transport, Councillor John Armour 
November 2024                                                  
For further information contact: 
Hugh O’Neill, Network and Standards Manager 
hugh.oneill@argyll-bute.gov.uk