ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROAD AND INFRASTRUCTURE
SERVICES  19 DECEMBER 2024 
WASTE LANDFILL BAN UPDATE 
1.0 INTRODUCTION 
1.1 This report is to provide members of the Environment, Development and
Infrastructure Committee with an update on the progress towards landfill ban
compliance.  It also provides an update on financial implications in respect of
the landfill ban and other waste issues. 
2.0 RECOMMENDATIONS 
2.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee consider the content of this report.   
3.0 DETAIL 
BMW Landfill Ban 
3.1 The previous report to the Environment, Development and Infrastructure
Committee in September 2024 provided an update on the funding awarded to
Argyll and Bute Council by the Scottish Government to support landfill ban
compliance. Furthermore, information was provided in relation to the Circular
Economy Bill and a recent Waste Composition Analysis which was supported
by Zero Waste Scotland. 
3.2  Officers have progressed a number of matters to ensure that Council
operated Waste sites are moving towards being able to support landfill ban
compliance. Moreover, the sites which are operated by Biffa (formerly
Renewi) which are ready to be landfill ban compliant and sites requiring
changes to comply with the landfill are noted in section 3.4.   
3.3 Argyll and Bute Council operate a number of Waste sites which include Civic
Amenity sites with landfill sites and others locations with closed landfill sites.
The details of all sites and their locations are noted below along with sites
managed through the Waste PPP contract with Biffa. The detail highlights the
sites which are compliant with the landfill ban and the sites which are not
compliant, this is not withstanding the works which are required to make these
locations landfill ban compliant. In addition, the Council has a separate
parallel process relating to the PPP contract handback. This process will be

Page 2

reported separately from the landfill ban.   
3.4     The following table summarises the current position across the council area in
terms of readiness for the BMW ban. 
Area Current position Outstanding Actions to
become BMW compliant
Island sites Currently we have live landfill sites in
both Islay and Mull. These sites
already have infrastructure in place
to facilitate waste transfer activity for
general waste. Post BMW ban,
general waste will be stored in the
waste transfer facilities and bulked
to then be transported off the
islands. Waste material from the
islands is pre-treated and processed
by the contractors.
Vary existing haulage
contracts to include
general waste.  The
varying of the contract is
relatively straightforward,
the main challenge will be
securing ferry space to
transfer the additional
waste. 
Helensburgh
and Lomond
area (H&L)
Existing contract is BMW compliant/
The contract also has provision to
take general waste from other parts
of Argyll and Bute. Both Waste
streams (residual waste and civic
amenity waste) from Tiree and Coll
are bulked, transported and
processed through the same
providers as H&L. The contract for
H&L, inclusive of Tiree and Coll
subsists until December 2025 and
can be extended a further year until
December 2026. The contract is also
flexible enough to accept Waste
streams from Islay and Mull which
can be bulked, transported and
processed through the contract. The
Waste material is pre-treated and
processed by the contractors. No
issues are noted for these contracts
or extensions. 
No direct actions in terms
of complying with the BMW
ban.  A waste transfer
station is being explored
which should provide
operational efficiency,
resilience and also provide
the Council with
opportunities in terms of
market options.  An
Options Appraisal is
currently in progress to
determine if the waste
transfer station is the best
option going forward.  
PPP
Contract
Area
Currently operating Mechanical
Biological Treatment (MBT) plants at
three locations (Oban, Lochgilphead
and Dunoon), waste transfer stations
at Campbeltown and Rothesay and
a number of civic amenity and bring
sites together with a contractual
requirement to run a front loader
commercial waste offering. Any
requirement for pre-treatment of
Waste through the PPP contract will
Conversion of MBT plants
to waste transfer stations
which is to be progressed
by Biffa subject to finalising
Heads of Terms.

Page 3

be arranged by Biffa. 
3.5 The table above summarises the position in terms of preparation for the 2026
BMW ban. It is noteworthy that in addition to these actions there are a number
of other activities underway including the removal of Compost Like Output
(CLO). CLO is Waste material which has been treated and separated to then
develop a CLO which can be used for the capping and restoration of landfill
cells. Officers have agreed with Biffa that they are responsible for all CLO
prior to March 2022 and the disposal of the same, the Council has assumed
responsibility for all CLO developed post April 2022 with the proviso that
sufficient CLO material is retained for the capping and restoration of landfill
sites up to the date of the landfill ban. Officers will finalise the discussions on
the indexation calculations with Biffa, the indexation calculations are
payments which were wrongly calculated by Biffa and the Council during the
term of the contract. The difference in costs is circa £587k, the Council are
required to make this payment to Biffa to conclude the matter, these actions
will be progressed by Officers.  It should be noted that this amount is not
budgeted for and creates a cost pressure.   
3.6 Following the regulations relating to the landfill ban on municipal waste, it was
unclear if third party commercial waste (e.g. commercial waste uplifted by
other private waste contractors or brought directly to sites by commercials),
could still be landfilled after the implementation of the ban.  It was always
clear to the Council and Biffa (formerly Renewi) that Council municipal waste
would be covered under the ban i.e. Council collected domestic and
commercial waste.  Recent guidance from SEPA suggests that the volume of
the third party commercial waste which will be acceptable for landfill in Argyll
and Bute will be insignificant, therefore making commercial waste landfill sites
uneconomical for the tonnages which are forecast. The guidance from SEPA
has two implications for the authority: 
1. All commercial waste material, whether municipal or third party, will
require to be bulked and transported from the sites and treated through an
EfW process along with general residual waste. 
2. Existing landfill sites, of which Argyll and Bute have 4, 1 on Islay and 1
on Mull (which are operated and maintained currently by the Council) and
separate to these are Lingerton Landfill (by Lochgilphead) and
Dalinlongart Landfill (by Dunoon) (which are currently maintained and
operated through the PPP contract), the expectation from SEPA is that
the sites are restored, capped and closed down. Currently we do not have
a timescale for this and Officers will continue to liaise with SEPA in this
regard. 
3.7 The bullet points below provide a summary of each landfill site in Argyll and
Bute. At the end of the PPP contract in September 2026, the PPP landfill sites
will revert back to the Council who will have direct responsibility for
maintaining, managing and monitoring these sites in line with any SEPA
licensing requirements. Works have been undertaken at Council sites to
enable landfill ban compliance. There is no requirement for any changes to

Page 4

Council operated sites pre-landfill ban or post landfill ban. 
Council Waste sites 
• Cliad Recycling Centre, Isle of Coll – Cliad has a closed landfill site,
and now operates as a Civic Amenity site. Waste materials from this
location are transferred to Tiree and then transported for re-processing
on the mainland. The Cliad site is ready to support delivery of a
compliant solution. 
• Gott Bay site Tiree – Gott Bay has a closed landfill site and operates
as a Waste Transfer Station and Recycling Centre (Civic Amenity site).
Material is transferred from the site for re-processing on the mainland.
The Council have made the Scottish Environment Protection Agency
(SEPA) aware of the changes to the site, i.e. landfill closure, and
shared the Councils plans for restoration and aftercare of the site. The
Council awaits a decision from SEPA on landfill cell closure and the
aftercare plan. The Gott Bay site is ready to support delivery of a
compliant solution. 
• Glengorm, Isle of Mull – Glengorm is a Landfill Site, a Waste Transfer
Station and a Recycling Centre (Civic Amenity site). The conversion of
the original baling shed to a Waste Transfer Station has already taken
place. The operational landfill site will remain open until the landfill ban
date, from 1 Jan 2026. The operational landfill site may close after this
date and it is likely that landfill restoration works would have to be
completed to comply with SEPA requirements by the end of 2027. The
Glengorm site is ready to support delivery of a compliant solution. 
• Bonaveh, Isle of Colonsay – Bonaveh is a Recycling Centre (Civic
Amenity site). Waste material from Bonaveh is transferred to Islay
during the summer and transferred to Oban during the winter months.
Bonaveh has a closed landfill site. The Bonaveh site is ready to
support delivery of a compliant solution. 
• Gartbreck, Isle of Islay – Gartbreck has a landfill cell, a Waste
Transfer Station which was converted from the original baling shed and
a Civic Amenity site (Recycling Centre). The Operational landfill site
will remain open until the start of the landfill ban on the 1 Jan 2026.
The Operational landfill may close after this date and it is likely that
landfill restoration works would have to be completed to comply with
SEPA requirements by the end of 2027. The Gartbreck site is ready to
support delivery of a compliant solution. 
• Blackhill Civic Amenity Site Helensburgh – The Blackhill site in
Helensburgh is a Civic Amenity site (Recycling Centre) and all Waste
material is transported from the site for re-processing. 
• Blackhill Roads depot, Waste Transfer Station
The Council has set funding aside to build a Waste Transfer Station in

Page 5

Helensburgh.  This was prior to Barr Environmental ceasing business
and the Council entering into a new contract that provides a compliant
solution for Helensburgh waste albeit at a distance in Paisley.  An
Options Appraisal is currently being progressed to assess the financial
and operational benefits of continuing to progress with a Waste
Transfer Station or other solution.  It is expected that the Options
Appraisal should be completed by the end of December 2024.   
Biffa managed Waste sites (formerly Renewi) 
• Moleigh, Oban – Moleigh manages co-mingled waste and has a
closed landfill with Civic Amenity site (Recycling Centre). Moleigh has a
Mechanical Biological Treatment (MBT) plant which will require
conversion to a Waste Transfer Station for all Waste material. Biffa will
coordinate and manage the conversion of the MBT plant. Once the
works are complete, Moleigh will be ready to support delivery of a
compliant solution. 
• Lingerton, Lochgilphead – Lingerton currently has an operational
landfill site, it is a Civic Amenity site and a co-mingled transfer station.
To comply with the landfill ban the current Mechanical Biological
Treatment plant requires to be converted to a Waste Transfer Station
to facilitate the tipping on of all Waste material for re-processing. The
Operational landfill site will remain open until the start of the landfill ban
on the 1 Jan 2026. The Operational landfill may close after this date
and it is likely that landfill restoration works would have to be
completed to comply with SEPA requirements by the end of 2027. 
• The Roading, Campbeltown - The Roading is a Civic Amenity site
and has a Waste Transfer Station. The site will be ready to support
delivery of a compliant solution. 
• Westlands, Rothesay - Westlands is a closed landfill, with a Waste
Transfer Station for Waste and recycling material and a Civic amenity
site. Westlands will be ready to support delivery of a compliant solution. 
• Bogleha, Dunoon - Bogleha has a Civic Amenity site and will be ready
to support delivery of a compliant solution. 
• Dalinlongart, Dunoon – Dalinlongart is a recycling and waste disposal
site for Dunoon and Cowal. The site has an operational landfill site, a
co-mingled Waste transfer station and a Mechanical Biological
Treatment plant which will require conversion to a Waste Transfer
Station to be compliant with the landfill ban. Biffa will coordinate and
manage the changes to the site. The Operational landfill site will
remain open until the start of the landfill ban on the 1 Jan 2026. The
Operational landfill may close after this date and it is likely that landfill
restoration works would have to be completed to comply with SEPA
requirements by the end of 2027.

Page 6

3.8 Biffa have allocated a Project Manager to lead on the conversion of the MBT
plants to Waste Transfer Stations at Dalinlongart, Lingerton and Moleigh once
the Head of Terms have been agreed by the Council. 
3.9 Officers have provided a summary of all outstanding actions and timescales to
Members within Appendix 1 of this report. 
Landfill Ban/Other Waste Issues Financials 
3.10 This section outlines financial implications in respect of the landfill ban and
other waste issues. 
3.11 In the latest budget outlook report that was reported to the Policy and
Resources Committee on 5 December, a cost pressure of £462k in 2025-26
rising to £925k from 2026-27 onwards.  Members were advised that we had
recently received an updated financial appraisal from the consultants who
prepared the options appraisal presented to Committee in December and
officers were working through the update figures, taking into consideration
inflationary pressures built into the outlook also.  It has become apparent that
the costs in relation to haulage and new Energy from Waste contracts were
not included in previous estimates post PPP contract and figures have also
been updated in line with cost increases since December 2022.  It is
understood that additional cost pressures of circa £96k in 2025-26, £2.112m
in 2026-27 and £2.684m from 2027-28 will require to be built into future years
estimates and clarification is being sought from the consultants that our
interpretation of the updated financials is correct.  Once clarification is
received this will be fed into the budget process for 2025-26.   
3.12 The Council has set aside £3m towards the creation of a Waste Transfer
Station (WTS) in Helensburgh.  As the Helensburgh area now has a compliant
disposal solution it is considered necessary to carry out an options appraisal
as to whether the Helensburgh WTS is still required.  A WTS will offer benefits
in terms of resilience of waste disposal by enabling the Council to bulk waste
and therefore being at less risk if it has to take waste further than at present
for disposal. Construction of the WTS may also enable revised and lower cost
shift patterns to be adopted by the waste collection teams.  The options
appraisal will consider whether these efficiency and resilience gains are
sufficient to justify the level of capital investment required.  A further update
will be provided to a future EDI Committee.   
3.13 One of the actions within the RIS review was to secure arrangements for
waste disposal beyond the current PPP contract expiring in September 2026. 
We are progressing to procure specialist consultants with detailed sector
knowledge to produce an options appraisal for consideration by the Council in
order to determine the preferred set of new arrangements with the available
options being: In-source, re-procure or establishment of a local authority
owned company or variations on these three main options. As part of the
commission the specialist consultants should be tasked to advise on the
further resources needed by the Council for it to develop and implement the
chosen model.  At present the Council pay Biffa (formerly Renewi) to deliver

Page 7

the waste arrangements within PPP area, however, there is an unknown as to
whether the current budget will be sufficient to pay for the new arrangement
post PPP contract.   
3.14 Paragraph 3.6 outlines that recent guidance from SEPA suggests that the
volume of the third party commercial waste which will be acceptable for landfill
in Argyll and Bute will be insignificant, therefore making commercial waste
landfill sites uneconomical for the tonnages which are forecast.  It is therefore
likely SEPA will advise that the current sites are restored, capped and closed
down and this will come at a significant one-off cost.  We do not have a
timescale for this nor an accurate costing and it is likely that this issue will be
picked up in the options appraisal referred to above.   
3.15 Extended Producer Responsibility (EPR) is an environmental policy approach
that holds producers responsible for the entire lifecycle of their products,
including the post-consumer phase. This means that producers are required
to manage the disposal, recycling, or reuse of products after consumers are
done with them. EPR aims to reduce waste, encourage recycling, and
minimize the environmental impact of products, particularly packaging and
electronics.  In practice, EPR typically requires producers to either directly
take back their products or pay into a collective system to fund recycling and
waste management. This policy shifts the financial and logistical burden of
waste management from governments and consumers to producers. 
Regulations are planned to come in from January 2025 and we have recently
received notice of our estimated payment for 2025-26 and this amounts to
£3.847m.   It should be noted that this is an estimated payment and at this
time it is unclear whether submission of detailed information to comply with
the regulations will create a resource pressure that will require to be funded
from the payment.  This amount is in addition to the Scottish Government
financial settlement for 2025-26 on the proviso that it must be spent on waste
related activities.  Whilst there should be ongoing payments in respect of
EPR, it is unclear whether the Scottish Government will amend the settlement
in future years.  It is recommended that the payment could go towards 2025-
26 cost pressures in relation to waste but due to the uncertainty over the total
amount of income, it is recommended that the remainder is earmarked whilst
further clarity if sought and to also help with future years pressures in respect
of waste, as noted in the preceding paragraphs.   
4.0 CONCLUSION
4.1 In concluding this report, an update on the journey towards landfill ban
compliance has been shared with Members. Furthermore, site compliance
information relating to the landfill ban and essential work streams and relevant
completion dates are noted, along with other Waste related activities in
Appendix 1. Council operated Waste sites are ready to support delivery of a
compliant solution. The Waste PPP managed sites are ready to support
landfill ban compliance apart from Dalinlongart, Lingerton and Moleigh.
Dalinlongart, Lingerton and Moleigh require the current Mechanical Biological
Treatments plants to be converted to Waste Transfer Stations to fulfill the
requirement for landfill ban compliance. The conversion of the relevant sites

Page 8

will take place in time for compliance with the landfill ban. 
4.2 The report also updates Members on a number of waste related issues that
have financial implications, some of which are unknown at this stage.  Further
updates will be provided to Members as and when available. 
5.0 IMPLICATIONS 
5.1 Policy – The Council’s Waste Strategy will evolve in line with the changes in
legislation relating to the landfill ban and circular economy bill. There will be a
requirement for the current Biffa contract to be varied to enable works to be
undertaken to comply with the landfill ban. The Councils Waste strategy will
be updated to reflect any changes. 
5.2 Financial – Compliance with the Landfill ban by the end of 2025 will require
financial resource from the Council. The Council have set aside £3m in capital
funds to build the Helensburgh Waste Transfer Station and £0.5m as a
contribution towards the conversion of the MBT plants at three Biffa sites, to
Waste Transfer Stations. In addition, the Scottish Government has committed
capital funding of £1.5m to support the authority with compliance of the landfill
ban. 
5.3 Legal – The existing PPP contract was not designed or written to
accommodate the changes at the end of the landfill ban. The contract allows
variations to be made although the process is quite cumbersome. There will
be legal implications, which will need to be resolved, relating to a contract
variation regarding the changes in Biffa’s contract.   
5.4 HR – HR issues will be addressed prior to and during the process of contract
handback. Having sufficient resource will factor into the project demands of
waste management. TUPE will be relevant at the handback and during the
process of progressing to handback should the Council operate the sites
themselves.     
5.5  Fairer Scotland Duty: None. 
5.5.1   Equalities – None. 
5.5.2   Socio-economic Duty – None. 
5.5.3 Islands – There may be potential ferry capacity issues for bulking and
transporting waste material from islands, this has been raised with Transport
Scotland.   
5.6 Climate Change – Transitioning from Landfill to Energy from Waste (EfW)
would result in a reduction in the annual quantity of Greenhouse Gas
generated in Argyll and Bute. Additional road miles incurred taking waste to
EfW markets will partly offset the carbon reductions achieved through not
landfilling.

Page 9

5.7  Risk – A refresh of all Waste PPP costs have been undertaken. The costs
reflect the previous financial analysis with the only increase being inflationary
costs. 
5.8  Customer Service – None.   
5.9  Rights of the Child – None arising from this report.   
Executive Director with responsibility for Roads and Infrastructure: Kirsty
Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
December 2024                               
For further information contact:   
John Blake, Fleet, Waste and Transport Manager 
john.blake@argyll-bute.gov.uk 
APPENDICES 
Appendix 1 – Summary of Waste sites – Working towards Landfill ban compliance

Page 10

APPENDIX 1 – SUMMARY OF WASTE SITES – WORKING TOWARDS LANDFILL BAN COMPLIANCE 
Location Status Actions Timescale for completion
Island sites Mull and Islay: waste transfer
stations complete and can
accommodate general waste and
co-mingled waste. All waste
material can  accommodated
through existing contracts when the
landfill ban is implemented, i.e. 1
January 2026 
No actions required Complete
Coll, Tiree and Colonsay: general
waste materials can be
accommodated through existing
contracts when the landfill ban is
implemented,  i.e. 1 January 2026
No actions required Complete 
Plans for the closure of landfill sites
at Gartbreck, Islay and Glengorm,
Mull post 2026
Appoint a consultant to plan for the
closure of the operational landfill
sites at Gartbreck and Glengorm.
Capping and restoration of sites will
be required
March 2025
Helensburgh
and Lomond
Complaint solution currently in
place with options to extend the
contract
No actions required for disposal  Complete 
PPP contract –
Renewi/Biffa
Sites operating MBT technology
introduced to divert material from
landfill
• Instruct Biffa to remove MBT
plant and equipment and convert
sheds to waste transfer facilities
• Instruct Biffa to dispose of the
excess of CLO, off site, as per
the proposals drafted by Renewi
• Scope out the opportunity for a
01 December 2024
31 December 2025 completion of
works for three sites 
1 December 2024 – excess CLO
removed by 31 December 2025

Page 11

contract extension to the PPP
contract, this would be varied to
operate waste transfer stations
at Dalinlongart, Lingerton and
Moleigh and also restoration of
landfill sites. This is based on
being able to achieve realistic
and competitive rates/prices and
also being compliant with
procurement legislation.
• Close down and agree
indexation discussions based on
advice received from legal
services regarding contract
obligations.
• Close down and agree
contractual requirements relating
to Void Space.
• Determine what provision would
be required and how this would
be delivered in relation to the
commercial waste collection
requirements contained within
the original contract.  
• Continue to progress handback
discussions with Biffa
• Further detailed options
appraisal to be undertaken
based on the best operating
model for the PPP sites post
contract – note earlier
recommendation for a contract
April 2025 
30 November 2024 
31 December 2025 
Ongoing until September 2026 
Ongoing until September 2026 
30 April 2025

Page 12

extension based on efficiency
following SEPA confirmation of
commercial landfill permitted
materials