ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
20 MARCH 2025 
OCTOBER 2023 WEATHER EVENT UPDATE 
1.0 INTRODUCTION 
1.1 This is a follow up to the report presented to the Policy and Resources
Committee on 5 December 2024 in respect of the October 2023 weather event.   
Policy and Resources Committee - October 2023 Weather Event (Item 9) 
2.0 RECOMMENDATIONS
2.1 It is recommended that the Environment, Development and Infrastructure
Committee: - 
a. Notes the updates on the current position of the projects. 
3.0 DETAIL
3.1 The table overleaf summarises the current status of the infrastructure repair
and reconstruction projects arising from the weather event in October 2023 as
at February 2025.  Those works coloured green are complete.

Page 2

Update on Works Progress, Scheduled Completion & Estimated Total Costs 
LOCATION ONGOING
WORKS/PROGRESS
UPDATE
SCHEDULED
COMPLETION 
ESTIMATED TOTAL
COSTS 
A816-110
Cuilfail Hotel
Bridge,
Kilmelford  
Upstream training walls,
bridge parapets,
pedestrian walkway,
scour protection and
upstream debris barrier
works largely completed
November 2024. 
Some final work required
in Spring 2025 due to
SEPA delays and
changed advice received
in final week of in-water
works, additional SEPA
Licencing now required. 
No additional costs
identified at this stage.
Majority of works
completed by January
2025. 
Parapet copes due for
completion Spring 2025. 
Upstream north training
wall works expected to
be completed in
Summer 2025
(previously anticipated
to be Spring). 
£200k (revenue) 
£2.086m (capital)
- NO CHANGE
B844-010
Kilninver
Bridge 
Phase 1 
Phase 1 works
completed October
2023. 
Phase 1 – October 2023
- WORKS COMPLETED 
£180k (revenue) – 
B844-010
Kilninver
Bridge 
Phase 2 
Designs for Phase 2
works being carried out
in-house with a view to
works being tendered
mid 2025.   
Any risks incurred from
the delays to the Phase
2 works are being
monitored and controlled
to ensure the road
network remains safe.
Phase 2 - Late Summer
2026
- NO CHANGE
Phase 2 works being
incorporated into
Bridge Replacement
scheme already
funded
- NO CHANGE
C30 Ford to
Malevich   
Works completed and
road fully reopened.  
July 2024
- NO CHANGE 
- WORKS COMPLETED
£864k (revenue)
- NO CHANGE 
- FINAL COSTS

Page 3

B836-060
Balliemore
Bridge, Glen
Lean 
Further to significant
delays and additional
costs incurred from
diversion of OpenReach
apparatus within
damaged bridge,
demolition of the existing
bridge is ongoing – due
to be completed late
2024. 
New bridge construction
planned early 2025.
Programmed for
completion Spring 2025
- NO CHANGE 
£1.150m (revenue) 
£1.448m (capital)
- NO CHANGE 
It is anticipated that
there may be some
increases in cost on
this project but these
have been accounted
for within the wider
bridge strengthening
programme with
budget confirmed as
available to support
these costs. 
A816 Bealach
Mor, Kintraw,
Ardfern Works
to February 
2024
Initial response including
clearance and quarry
works.
Further clearance and
scaling/stabilisation
works
Construction of Bypass 
and Loop road.
February 2024
- WORKS COMPLETED 
£2.285m (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern Works
March to
September
2024
Stability, drainage and
safety works. 
Standing by and ongoing
maintenance. 
Traffic management to
September. 
Contractor Project
Management Costs
September 2024
- WORKS COMPLETED 
£1.995m (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern Works
to 
Ongoing works to
bypass road continue for
vehicle safety barrier,
edge markers. 
Monitoring of Kintraw
hillside in place to
manage movement of
traffic onto bypass route
when necessary. 
Bypass road works
programmed for
completion by 
March 2025 (previously
anticipated to be
December 2024)
£220k (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern
Rockfall protection
barriers have been
installed within the road

Page 4

Rockfall
barrier
corridor and traffic has
been moved back to the
A816 under traffic lights
without a convoy
system. 
End of September 2024
- WORKS COMPLETED 
£400k (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern
convoy system
‘v’ fixed traffic
lights
Traffic has been moved
back to the A816 under
traffic lights without a
convoy system. 
Removal of Convoy
system - End of
September 2024  
- NO CHANGE
- COMPLETED 
£255k (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern
convoy system
‘v’ fixed traffic
lights
Traffic lights operating
on generator power until
mains electric supply
secured. 
Mains electric
connection being
progressed for traffic
lights. 
Ongoing traffic lights
operation until new,
permanent road
alignment.
Generator power – to
end of March 2025
- NO CHANGE 
New mains power
connection by end of
March 2025
- NO CHANGE 
Traffic Light operation –
ongoing until
permanent, new road
- NO CHANGE 
A816 Bealach
Mor, Kintraw,
Ardfern –
permanent
diversion onto
a widened
alignment of
the emergency
route   
Following receipt of a
high value quotation
from the existing
Specialist Contractor to
deliver scheme in full
accordance with design
standards, we are
assembling a feasibility
options report with the
aim of being in a
informed position to

Page 5

select the optimum
permanent solution
design. 
Once the preferred
option has been
approved, a ground
investigation and
consultations with
stakeholders will take
place to inform the
design and build
contract. 
A design and build
contract shall be
prepared and tendered
ensuring best value is
secured.
3 – 5 years
- NO CHANGE
£1.1m (capital)
- At this time there is
no change to report
however it is noted that
there is significant
variance between the
original cost estimate
of £1.1m provided by
the specialist
contractor employed to
undertake the
temporary works. A
key purpose of the
options study currently
being progressed is to
arrive at a more
accurate cost estimate
and enable the
selection of a preferred
option which provides
the highest value for
money overall. 
4.0 CONCLUSION
4.1 This report summarises and provides update on the works that have been
undertaken and completed and those that are ongoing in relation to the extreme
weather event which occurred on the weekend of 7 October 2023 and which
was the wettest 2-day period on record for Scotland since 1891 in which Argyll
and Bute was the worst affected area.   
5.0 IMPLICATIONS 
5.1 Policy – Policies in place for climate change, coast protection etc where
applicable these policies are being worked to.
5.2 Financial – No further financial implications identified at this time.  
5.3  Legal – Various land agreements necessary for individual locations.   
5.4  HR – None known.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – None known. 
5.5.2   Socio-economic Duty – None known. 
5.5.3  Islands – None known.

Page 6

5.6 Climate Change – The impact of the storm is very closely linked to climate
change and the October event has highlighted to need for further adaptation
to be made to infrastructure to increase our resilience to future weather
events. The level of investment to improve resilience is expected to be
significant.  
5.7 Risk – Significant risk of similar future events impacting our infrastructure.  
5.8  Customer Service – None known.  
5.9 Rights of the Child (UNCRC) – Investment to improve our road network will
contribute to a safer environment for young people to thrive in. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure Services 
Councillor John Armour, Policy Lead for Roads, Transport and Amenity
Services 
26 February 2025 
For further information contact: 
Stephen Hall, Interim Head of Roads and Infrastructure Service 