Democracy Spraffa

Review of Roads and Infrastructure Services - Update

Argyll and Bute Council · 20 March 2025
Back to Environment, Development and Infrastructure Committee — 20 March 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND  
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        20 MARCH 2025 
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to provide Members of the Environment,
Development and Infrastructure Committee with an update on progress and
next steps in relation to the Roads and Infrastructure Service Review (RIS
Review). 
1.2 In providing this update reference is made to information contained in the
previous report to this Committee in relation to the RIS Review dated 19
December 2024 and to the actions taken in the intervening period. 
1.3 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) note the content of this report.
b) agree to endorse the priority improvement actions set out within this report.
c) agree to receive a further report on progress of the RIS Review in June 2025.

Page 2

ARGYLL AND BUTE COUNCIL     ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE         20 MARCH 2025 
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update to Members of this Committee on progress of the
Roads and Infrastructure Service Review (RIS Review). 
3.0 RECOMMENDATIONS 
3.1      It is recommended that Members of the Environment, Development and       
Infrastructure Committee:- 
a) note the content of this report.
b) agree to endorse the priority improvement actions set out within this
report.
c) agree to receive a further report on progress of the RIS Review in June
2025.  
4.0 DETAIL 
4.1 At the December 2024 meeting of this Committee, Members received a report
entitled “Review of Roads and Infrastructure Services - Update”. That report
provided a summary of key aspects of Stage 1 of the RIS Review and provided
an update on progress with the further development and implementation of
these. The report in December 2024 set out that progress with the RIS Review
was being overseen by the RIS Review Project Board Chaired by Executive
Director Kirsty Flanagan with Vice Chair Executive Director Douglas Hendry and
this remains the case. The report in December 2024 also set out that a review of
the Stage 1 recommendations had been completed and that the work required
to conclude Stage 2 of the review process would be completed shortly and result

Page 3

in the development of a set of priority improvement actions with the intention of
delivering change in a phased and prioritised manner.
4.2 The report in December 2024 set out that a consultant had been appointed in
November 2024 to take forward the next phase of the RIS Review. Following the
departure of the previous Head of Service in December 2024, the consultant
has been appointed as Interim Head of Service and is fulfilling both this role and
leading the implementation of the RIS Review while recruitment for the
substantive Head of Service takes place. The recruitment process for the new
Head of Service has commenced with interviews scheduled for 27 March 2025.
4.3 The RIS Review has been structured around 4 stages of activity as illustrated
below: 
4.4 Stage 2 of the RIS Review has now been completed. Having reviewed the
activities required in stages 3 and 4 an opportunity has been identified to move
both these stages forward at the same time. Taking this “twin track” approach to
stages 3 and 4 will enable the improvements identified by the RIS Review to be
delivered more quickly. As noted above the key output from Stage 3 is a revised
target operating model for the service, this has been designed in the form of a
new organisation structure for the service which has now matured to the point
that formal engagement with Trade Unions and the affected staff is ready to
commence. Stage 4 of the RIS Review process entails the development and
implementation of an agreed set of actions to transform the service. The table
below sets out these actions which have been called “Priority Improvement
Actions”. The first of the priority improvement actions is to “develop and
implement a revised organisation structure for Roads and Infrastructure
Services”, delivering this will in effect complete Stage 3 of the process.
Implementing a revised organisation structure for the service is a key enabler to
ensure the success of the other Priority Improvement Actions, but as illustrated
in the table below work to begin progressing many of the other actions has
already commenced. A total of 12 Priority Improvement Actions have been
identified and these are summarised in the table below:

Page 4

Workstream Priority
Improvement Action
Rationale and Detail
Organisational
Design and
People
Develop and
implement a revised
organisation
structure for Roads
and Infrastructure
Services.
This action will deliver Stage 3 of the RIS
Review process and is fundamental to
enabling the success of all other
improvement related activities and will form
the foundations for a refreshed Roads and
Infrastructure Service. The existing
organisation structure does not provide
optimal levels of clarity and accountability
and in some areas appears to lack the
capacity required to effectively respond to
near term challenges. The need for change
to the management structure is not
universal with some teams requiring only
limited change. 
Progress to date: A new organisation
structure has been produced to the level of
maturity necessary to enable engagement
with Trade Unions and affected staff to
commence. Draft revised Job Descriptions
and Person Specifications have been
produced and the process of job evaluation
in relation to these is progressing. The
intention is to take forward the reshaping
exercise in two stages. Stage 1 will see
changes implemented at tier 3 (Service
Managers), following this those changes
required at subsequent tiers will be taken
forward. Taking a 2 stage approach ensures
that service managers can be actively
involved in the implementation of the
revised organisation structure and operating
model for the service. The intention is to
commence formal engagement in relation to
stage 1 of the reshaping as soon as the job
evaluation process for the tier 3 posts is
completed and it is hoped that this will be
possible no later than April 2025.
Data, Digital
and Customer
Review the scope
and effectiveness of
service specific
technology systems
used for asset &
works management
and the interface
between these and
core corporate
systems. 
Stage 1 and 2 of the review process
identified that the core asset and
information management system used by
the service in relation to roads, amenities
and environmental assets is not optimally
configured and is not offering the maximum
value possible.  This system also interacts
with a service specific finance system which
is coming to its end of life and with the
corporate customer relationship

Page 5

management system. This Priority
Improvement Action will see these systems
reviewed with targeted improvements made
to maximise benefit and ensure a
replacement for the finance element is in
place prior to the expiry of the existing
product. 
This work will include reviewing the
opportunities for artificial intelligence to add
greater value and enable staff to spend a
greater proportion of their time on higher
value-added activities. 
Progress to date: Significant progress has
been made since this issue was identified at
stage 1 of the RIS Review. The existing
system has been successfully migrated onto
cloud hosting which has enabled a number
of improvements in functionality. Key areas
of improvement that have been delivered
include: bridges and structures
management, road inspections, road works
instructions, accessibility of asset data and
overall user experience of the system.
Further improvement activity will target 4
priority areas: 1) customer relationship
management, 2) financial recording and
reporting, 3) improving the functionality of
the system for amenity services and 4)
utilisation of the system for the management
of land and environment maintenance. An
Officer Steering Group has been
established and a Project Manager
identified to lead this work.
Organisation
Design and
People
Workstream
Drive forward the
selection and
development, by
the Council, of the
organisational
arrangements to
come into place for
waste disposal at
the end of the
current PPP
contract.
With the current PPP contract expiring in
September 2026, a key area of focus is to
increase the pace at which the
organisational arrangements that will be
required after the end of the contract are
developed and put into operation. In the
short-term additional capacity is being
added to the Council’s existing waste team
through external specialist consultancies. As
the future arrangements become clearer the
capacity of the Council’s waste team will be
further reviewed. 
Progress to date: external consultants
have been appointed to lead the Options

Page 6

Appraisal for future organisational
arrangements and to add capacity to the
Council’s waste team as we prepare for the
end of the PPP contract. A number of
existing commercial and contractual matters
in relation to the PPP contract are being
progressed along with matters that relate to
the impact of the upcoming ban on
Municipal Bio-degradable Waste to Landfill.
Organisation
Design and
People
Workstream
Improve
consistency of
approach to project
management.
While there is a strong emphasis on
managing the design and construction
phases of projects the process of business
case development and assurance within
RIS can be improved and strengthened and
brought into better alignment with the
Council wide approach of the Project
Pipeline and adoption of best practice
through the Treasury Green Book business
case approach. 
Progress to date: This improvement action
has begun with the approach applied to the
proposed Helensburgh Waste Transfer
Station project. The outcomes of a project
review using this methodology is the subject
of another report on today’s agenda. All
current and potential future projects from
RIS are being reviewed in line with the
Council’s “project pipeline” approach. In
addition the organisational re-shape
described earlier in this table will embed
specific project management roles more
clearly within the structure.
Organisation
Design and
People
Workstream
Review the impact
of a potential future
reduction in roads
maintenance capital
budget on the
overall operating
approach and of the
service. 
This action was initially developed in
response to the anticipated significant
reduction in the level of capital funding for
2025/26. The decision at Council to award a
capital budget of £10m for roads
reconstruction in 2025/26 has reduced the
urgency of this action. However with
ongoing pressure to Council budgets and no
guarantee that the current level of capital
funding can be maintained in future years, it
remains necessary for the service to review
how a potential future reduction in the
capital budget would impact on the current
operating model and balance between
activities delivered by in-house resource
and those delivered by contractors.

Page 7

Progress to date: an initial high-level
review has been undertaken outlining the
types of both capital and revenue works that
would be prioritised under different funding
scenarios – this work will be further
progressed over the coming year.
Policy and
Procedure
Workstream
Commence
programme of
strategic change to
parking and
enforcement related
activity.
A strategic review of parking services and
options for change should be developed for
consideration by Members as a co-
ordinated package of service changes. 
Progress to date: this work has not
progressed beyond the Stage 1
recommendations and Stage 2 due
diligence at this time due to capacity.
Policy and
Procedure
Workstream
Develop and
implement a
package of changes
to school transport
including ASN
transport.
This is a policy area that, nationally, has
been under significant financial strain for a
number of years as a result of increases in
demand. A package of changes will be
developed including:
• Reviewing the approach to
procurement in targeted areas.
• Strengthening co-ordination between
Council services in education and
RIS in relation to planning for the
transport requirements of children
and young people with ASN. 
Progress to date: Initial scoping meeting
has been held between senior officers in
education and RIS to map out potential
improvements. 
A significant study into the future proprieties
for public transport across Argyll and Bute
has been commissioned and will shortly
move the stage of public and stakeholder
engagement. There is a very significant
overlap between public bus transport and
school transport which means the results of
this study are likely to have a significant
influence on future models for school
transport including ASN transport in the
future.
Commercial
Opportunities
Workstream
Further review the
options for
increased
commercial activity
in the fleet
Stage 1 of the review reached conclusions
in relation to the potential to generate
additional income through fleet services.
The Stage 2 due diligence did not fully
support the conclusion as they did not take
account of the local context of Argyll and

Page 8

maintenance
workshops.
Bute including our highly rural nature,
topography and long distances between
vehicle operating centres (depots). However
opportunities are believed to exist to further
review medium to long term options to
increase efficiency and / or generate
additional commercial income. 
A further and more detailed review of
capacity that involves looking at both
existing capacity available for commercial
work will be progressed. 
Progress to date: This work will be
progressed when officer capacity allows
following the back-filling of a key vacancy in
the fleet team, recruitment to which is
currently ongoing.
Policy and
Procedure
Workstream
Continue to
progress route
optimisation project.
This project is fundamental to having
improved customer service and
performance metrics to drive efficiency in
the waste collection service. 
Progress to date: Staff training and
installation of the in-cab technology is
progressing well.
Organisation
Design and
People
Workstream
Project Gateway
Review of the
Helensburgh Waste
Transfer Station
(WTS) Project.
This priority improvement action is the
subject of a separate report on Committee’s
agenda today. 
Progress to date: Subject to decision of
this Committee – Complete.
Commercial
Opportunities
Workstream
Progress a review
of commercial
waste services to
ensure optimum
efficiency, service
consistency and
income generation.
A review of back-office and operational
procedures will be implemented to provide
assurance that this area of service is
operating to optimum levels. 
Progress to date: a project team has been
identified and has started to review the
scope for improvements.
Policy and
Procedure
Workstream
Continue to
progress the
second domestic
waste bin review
and seek to reduce
residual waste
collection in line
with the volume
recommended in
the Code of
To reduce waste disposal volumes and
increase recycling and re-use, thereby
supporting achievement of environmental
strategies and targets and reducing revenue
cost of waste disposal and waste collection
services. This work, alongside the route
optimisation project will be driven forward
with increased pace to deliver
improvements in both efficiency and
customer service.

Page 9

Practice for
Household
Recycling while
also increasing the
rate of recycling
across the area. 
Progress to date: A public survey has been
prepared in order to gauge the views of the
public to inform the next steps in this project
– this will be live mid-March. 
5.0 CONCLUSION
5.1 This report provides an update on the implementation of Stage 2 of the RIS
Review process. 
6.0 IMPLICATIONS
6.1 Policy – No direct policy implications within this report. A number of the priority
improvement actions may result in changes to existing policies, where this is
the case further reports seeking approval for new or changed policies will
come to Committee.
6.2 Financial – A number of the priority improvement actions aim to increase
efficiency and deliver financial benefits to the Council.
6.3  Legal – Legal aspects are being reviewed as part of each of the priority
improvement actions.
6.4  HR – The proposals to reshape the organisation structure of the Roads and
Infrastructure Service have implications for staff. All relevant Council policies
and procedures are being followed in this regard.
6.5  Fairer Scotland Duty:
6.5.1  Equalities – Will be considered as part of each of the priority improvement
actions as these progress.
6.5.2  Socio-economic Duty – None identified at this time.
6.5.3  Islands – None identified at this time. 
6.6  Climate Change – None identified at this time.
6.7  Risk – Risks are being managed in relation to each of the priority improvement
actions. 
6.8  Customer Service – A number of the priority improvement actions aim to
improve customer experience. 
6.9  Rights of the Child (UNCRC) – None arising directly from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and 
Infrastructure

Page 10

Councillor John Armour, Policy Lead for Roads, Transport and Amenity 
Services 
March 2025                                                  
For further information contact:
Stephen Hall, Interim Head of Roads and Infrastructure Service 
Stephen.hall@argyll-bute.gov.uk 
APPENDICES
N/A