Democracy Spraffa

Helensburgh Waste Transfer Station Project Update

Argyll and Bute Council · 20 March 2025
Back to Environment, Development and Infrastructure Committee — 20 March 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE                                                                           
ROAD AND INFRASTRUCTURE                                            20 MARCH 2025 
HELENSBURGH WASTE TRANSFER STATION PROJECT UPDATE 
1.0 EXECUTIVE SUMMARY
1.1  This report provides an update on the Helensburgh Waste Transfer Station
project following the completion of the Options Appraisal and makes a
recommendation in relation to the next steps for this project and associated
budgets. 
1.2   The requirement for the Council to develop a Waste Transfer Station to
service the Helensburgh and Lomond area was set out in a report to this
Committee on 21 December 2022 as part of a report entitled “Waste PPP
Options Appraisal”. That report provided an initial cost estimate for the project
of £3m. 
1.3   Funding for the development of a Waste Transfer Station to serve the
Helensburgh and Lomond area was approved by Council in February 2023 as
part of the Budget setting meeting. At that meeting Council approved a budget
of £3.5m in relation to preparations for the upcoming Biodegradable Municipal
Waste (BMW) Ban as part of series of additional capital allocations for
“investing in Argyll and Bute’s Priorities”. The Helensburgh Waste Transfer
Station project with an initial estimated cost at that time of £3m was the
largest in a number of projects to be funded from that budget, the other £0.5m
being intended to support the cost of converting the existing Mechanical and
Biological Treatment (MBT) facilities into waste transfer stations. 
1.4   Following budget approval officers undertook the design and other activities
required to move the project to an advanced stage of maturity whereby a full
works tender pack was prepared and planning approval achieved. The project
achieved this level of maturity in early January 2025. 
1.5   Prior to issuing the works tender to the construction market a project review
using the HM Treasury Green Book approach of the production of an Outline
Business Case was undertaken in order to assess that the project remained
the best value for money method through which the Council could be assured
that its waste disposal arrangements in the Helensburgh and Lomond area
are compliant with the upcoming BMW Ban. This project review took place

Page 2

across the period December 2024 to early January 2025. 
1.6   The project review (described at paragraph 1.5 of this report) determined that
the Helensburgh Waste Transfer Station Project no longer provides the
optimum solution to ensure BMW compliant waste disposal arrangements in
the Helensburgh and Lomond area, is not required to ensure BMW
compliance and does not offer a good return on investment (value for money)
for the Council. 
RECOMMENDATIONS 
It is recommended that the Environment, Development and Infrastructure
Committee:- 
1. Notes that the proposed Helensburgh Waste Transfer Station no longer
provides the optimum solution to ensure BMW compliant waste disposal
arrangements in the Helensburgh and Lomond area.   
2. Agrees that officers should not progress further with the development and
delivery of the Helensburgh Waste Transfer Station Project.  
3. Recommends to the Policy and Resources Committee that the remainder of
the £3m of budget earmarked for this project be retained to support other
funding related pressures within the waste service.

Page 3

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE                                                                           
ROAD AND INFRASTRUCTURE                                           20 MARCH 2025 
HELENSBURGH WASTE TRANSFER STATION PROJECT UPDATE 
2.0 INTRODUCTION
2.1 This report provides an update on the Helensburgh Waste Transfer Station
project following the completion of the Options Appraisal and makes a
recommendation in relation to the next steps for this project and associated
budgets.  
3.0 RECOMMENDATIONS
3.1  It is recommended that the Environment, Development and Infrastructure
Committee:- 
1. Notes that the proposed Helensburgh Waste Transfer Station no longer
provides the optimum solution to ensure BMW compliant waste disposal
arrangements in the Helensburgh and Lomond area.   
2. Agrees that officers should not progress further with the development and
delivery of the Helensburgh Waste Transfer Station Project.  
3. Recommends to the Policy and Resources Committee that the remainder of
the £3m of budget earmarked for this project be retained to support other
funding related pressures within the waste service. 
4.0 DETAIL
4.1 The concept of the Council building and operating a Waste Transfer Station in
the Helensburgh area was originally envisaged as a means to respond to the
closure of the local landfill site at Auchencarroch, ensure that waste disposal
operations for this area would be compliant with the upcoming ban on
municipal waste to landfill, and respond to the withdrawal from the market of
the waste off-taker historically utilised by the Council in the Helensburgh area.
Following budget approval by Council in February 2023, the project was
initiated with design, surveys, operational planning and regulatory approvals
progressing.

Page 4

4.2  By mid-January 2024 the project was a relatively mature stage with detailed
design complete and tender information ready to be issued to market for
purposes of procuring a construction contractor with planning approval for the
project having been secured (subject to a number of conditions as would
normally be the case for a project of this nature). In progressing the project to
this stage of maturity in the region of £190k had been expended on design
and other related fees. 
4.3  In the period between the initiation of this project following the February 2023
Council meeting and January 2025, the Council had successfully procured
and implemented waste disposal arrangements for the Helensburgh and
Lomond are that are BMW Ban compliant. These arrangements involve the
Council’s Refuse Collection Vehicles travelling to a waste off-taker in Linwood
(Paisely). As this is a circa 2-hour round trip these arrangements are less
efficient than the previous arrangements whereby residual waste was taken to
the Auchencarroch landfill site, but it is a BMW Ban compliant solution. As a
BMW Ban compliant waste disposal solution has been secured the rationale
for this project changed from being one that was required to ensure BMW Ban
compliance to one that would be desirable provided it can be demonstrated to
offer financial efficiencies to the Council when compared to the current
arrangements. 
4.4  At the direction of the Waste Strategy Project Board a project review was
undertaken to determine the value for money of this proposed project. To
progress this review consultants were appointed to produce an “Outline
Business Case” in line with HM Treasury Green Book standards and in line
with the Councils “Projects Pipeline” approach. The Outline Business Case
was utilised by the Interim Head of Roads and Infrastructure to inform a
review of the value for money of the proposed project.  
4.5  The project review identified that the estimated cost of delivering the project
stood at circa £3.6m, which is £0.6m higher cost than the currently available
budget. The review also looked in detail at the financial savings that the
project could achieve, for example through lowered vehicle fuel use, and
compared these against the additional new costs of operating a Waste
Transfer Station. This exercise determined that the running costs for the new
facility would lead to an increase in the annual revenue costs for the service of
between £110,704 and £207,326. In calculating this increase in costs two
scenarios were considered: scenario 1) the efficiency in staff time would not
be taken as a cashable saving with the staff being re-deployed to other
activities, and scenario 2) the efficiency in staff time being taken as a
cashable saving. As would be expected scenario 1 leads to the highest overall
increase in costs. The table below shows a summary of the savings,
additional new costs and overall cost increase in each scenario.

Page 5

4.6 In order to demonstrate the total cost to the Council of the proposed project the
review modelled the revenue consequences of borrowing to fund the capital
investment. While the financing approach for the capital investment may
necessarily have required borrowing specifically for this project the benefit of
developing this model is that it demonstrates the real-life cost of the capital
investment. In line with standard Argyll and Bute Council methodology and HM
Treasury Green Book guidance, the life of the asset and hence financing period
has been assumed at a 60-year period at an assumed interest rate of 5.1%. This
exercise determined that when both the additional running costs of the facility
and the true cost of the capital are included the project would result in a total of
between £304,082 and £400,704 as shown in the table below. As in the table
above the difference between the two figures is a result of the scenarios
described above in relation to staffing efficiency. 
4.7 The project review recognised that constructing a Waste Transfer Station would
bring benefits in relation to service resilience. In order to better understand the
relative importance of these benefits an exercise was undertaken through
market intelligence to assess the alternative waste off-take arrangements that
would be open to the Council in the areas should the existing arrangements be
put at risk at a future point. This exercise determined that there are other off-take
Table 1.9 Ongoing Revenue Implications 
Cost per annum
Fuel savings for fleet -£50,000
Increased fees from commercial waste -£11,821
Costs of waste transfer i.e. cost of hiring larger
vehicles for transport to processing
+£104,000
Additional staffing +£40,000
Reduction in Staffing -£96,622
Running costs inclusive of utilities, inspections,
etc.
+£125,148
Total with retained staffing +£207,326
Total with reduced staffing +£110,704 
Table 1.10 Ongoing Revenue Implications with Capital Repayments 
Cost per annum
Fuel savings for fleet -£50,000
Increased fees from commercial waste -£11,821
Costs of waste transfer i.e. cost of hiring larger
vehicles for transport to processing
+£104,000
Additional staffing +£40,000
Reduction in Staffing -£96,622
Running costs inclusive of utilities, inspections,
etc.
+£125,148
Capital Repayment +£193,378
Total with retained staffing +£400,704
Total with reduced staffing +£304,082

Page 6

contractors in the area and while the costs may potentially be higher any
increase would not be anticipated to be as high as the total cost (Capital and
Revenue) associated with the development of the proposed Waste Transfer
Station.
4.8 Recognising that the proposed project would be likely to result in fuel savings
the review undertook an assessment of the likely reduction in transport related
pollutants that would be expected to result from the construction of a waste
transfer station and the bulking of waste from refuse collection vehicles onto
articulated HGV’s. The results of this exercise are shown in the table below,
while this demonstrates beneficial environmental gains these are not particularly
high when considering the level of investment required to achieve them.  
Tonnes Value per
tonne
Annual value
Carbon Reduction 197 £256 £50,349
Nitrous Oxide Reduction 0.78 £7,120 £5,584
Fine particulate Reduction 0.06 £81,847 £5,136 
4.9  In order to complete the value for money assessment a Benefits Costs Ratio
(BCR) was undertaken for both the Blackhill Waste Transfer Station and an
alternative proposal for a facility at Sandhill Point. The results are shown
below. A BCR of more than 1 shows positive value for money and it usually
anticipated that a BCR well above 1 would be required for most projects.  
Present Value
Costs
Present
Value Net
GVA
BCR
Option 4:
Sandpoint
Marina
Argyll & Bute £3.6m £2.8m 0.94
Scotland £3.6m £2.3m 0.78
Option 6a:
Blackhill– Staff
redeployment
Argyll & Bute £7.7m £5.9m 0.77
Scotland  £7.7m £7.1m 0.92
Option 6a:
Blackhill– Staff
reduction
Argyll & Bute £5.8m £2.8m 0.49
Scotland  £5.8m £4.7m 0.82 
4.10  There are a number of wider cost pressures facing the waste service in the
short-term. These include costs associated with resolving historic issues within
the PPP contract with Biffa, and include:- 
• indexation and the disposal of excess Compost Like Output (CLO) Material from
the MBT plants;

Page 7

• additional cost pressures resulting from ensuring compliance with the BMW Ban
including the conversion of the existing MBT sites to Waste Transfer Stations;
and 
• the cost of capping and restoration of the current landfill sites to meet the
requirements of the BMW Ban and regulatory requirements for these sites once
they are no longer in use. 
While initial estimates only of these costs are available at the current time, they
are anticipated to be significantly higher than the currently available budgets
even once taking into account the £1.5m in capital funding from the Scottish
Government provided to support the costs of BMW ban compliance. 
5.0 CONCLUSION
5.1 Having assessed the project from a number of different angles the review has
concluded that the construction of a new Waste Transfer Station does not
offer value for money to the Council. While the project does offer benefits in
terms of operational efficiency, resilience and carbon reduction it is difficult to
argue that these are of sufficient magnitude to justify either the initial capital
investment or the ongoing revenue investment. If at a future point in time the
operational circumstances change significantly then the project could be
revisited and if required revived. With detailed design completed, planning
approval (subject to conditions) achieved, and a construction tender pack
compiled the project would be cable of being re-mobilised at a future time,
recognising of course that planning and other approvals are time limited and
may require to be re-visited. 
5.2 With the waste service facing significant financial pressures in relation to BMW
Ban compliance and the end of the PPP contract, as set out at 4.10, it is
proposed that the remainder of the £3m initially earmarked for the development
of the Helensburgh Waste Transfer Station project be re-allocated to support
these wider cost pressures. Re-allocating the remainder of the earmarked
budget for this project to these purposes would ensure this investment remains
available for the purposes expressed by Council at its meeting in February 2023
when setting aside a budget of £3.5m in relation to preparations for the
upcoming Biodegradable Municipal Waste (BMW) Ban as part of series of
additional capital allocations for “investing in Argyll and Bute’s Priorities”.  
6.0 IMPLICATIONS
6.1 Policy – None arising from this report.
6.2 Financial – The financial implications are set out in the body of this report.
6.3  Legal – None arising from this report.
6.4  HR – None arising from this report.
6.5  Fairer Scotland Duty: None known.

Page 8

6.5.1   Equalities - protected characteristics – None known.
6.5.2   Socio-economic Duty – None known.
6.5.3 Islands – None arising from this report.
6.6  Climate Change – The climate change considerations have been set out in the
body of this report. 
6.7 Risk – The risks associated with future service resilience in relation to the
waste off-take market in the Helensburgh and Lomond area have been set out
in the body of this report.
6.8  Customer Service – None arising from this report.  
6.9 The Rights of the Child (UNCRC) – None arising from this report. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan
Policy Lead for Roads, Transport and Amenity: Councillor John Armour 
February 2025                                              
For further information contact: 
Stephen Hall, Interim Head of Road and Infrastructure Services 
stephen.hall@argyll-bute.gov.uk 
John Blake, Fleet Waste and Transport Manager
john.blake@argyll-bute.gov.uk