Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 605522
DX 599700 LOCHGILPHEAD 
4 September 2025 
NOTICE OF MEETING 
A meeting of the ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE will
be held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND
BY MICROSOFT TEAMS on THURSDAY, 11 SEPTEMBER 2025 at 10:30 AM, which you are
requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST 
3. MINUTES (Pages 3 - 10)  
Environment, Development and Infrastructure Committee held on 19 June 2025 
4. WINTER SERVICE POLICY 2025/26 (Pages 11 - 54)  
Report by Executive Director with responsibility for Roads and Infrastructure 
5. PAVEMENT PARKING PROHIBITIONS - SERVICE PROCEDURE & EXEMPTIONS
(Pages 55 - 102)  
Report by Executive Director with responsibility for Roads and Infrastructure 
6. TRUNK ROAD LITTER MANAGEMENT RESPONSIBILITIES A82, A83, A85, A828
(Pages 103 - 110)  
Report by Executive Director with responsibility for Roads and Infrastructure 
7. TEMPORARY TRAFFIC REGULATION ORDERS - REVIEW OF CHARGING AND
ADVERTISING (Pages 111 - 126)  
Report by Executive Director with responsibility for Roads and Infrastructure 
8. WASTE COLLECTION POLICY AND OPERATIONAL UPDATES (Pages 127 - 144)  
Report by Executive Director with responsibility for Roads and Infrastructure 
9. REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE (Pages 145 - 162)
Public Document Pack

Page 2

Report by Executive Director with responsibility for Roads and Infrastructure 
10. LOCAL FLOOD RISK MANAGEMENT PLANS - S37 INTERIM UPDATE - TO FOLLOW 
Report by Executive Director with responsibility for Roads and Infrastructure 
11. A816 ARDFERN PERMANENT REPAIR SOLUTION UPDATE (Pages 163 - 204)  
Report by Executive Director with responsibility for Roads and Infrastructure 
12. TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM - LARGE SCALE
PROJECT UPDATE REPORT (Pages 205 - 224)  
Report by Executive Director with responsibility for Development and Economic Growth 
13. ARGYLL AND BUTE COUNCIL'S ECONOMIC STRATEGY ACTION PLAN: 2025-2028
(Pages 225 - 254)  
Report by Executive Director with responsibility for Development and Economic Growth 
14. ECONOMIC GROWTH TEAM ACTIVITIES AND OUTCOMES FOR 2024/25 (Pages 255
- 280)  
Report by Executive Director with responsibility for Development and Economic Growth 
15. REGISTRATION OF AN ECONOMIC DEVELOPMENT SUBSIDY SCHEME TO
FACILITATE COMPLIANCE WITH POST-EU SUBSIDY CONTROL LEGISLATION
(Pages 281 - 322)  
Report by Executive Director with responsibility for Development and Economic Growth 
REPORT FOR NOTING 
16. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE WORK
PLAN 2025/26 (Pages 323 - 326) 
Environment, Development and Infrastructure Committee 
Councillor John Armour (Chair) Councillor Jan Brown
Councillor Graham Hardie Councillor Willie Hume
Councillor Andrew Kain Councillor Jim Lynch
Councillor Tommy MacPherson Councillor Ian MacQuire
Councillor Luna Martin Councillor Liz McCabe
Councillor Ross Moreland (Vice-Chair) Councillor Gary Mulvaney
Councillor Alastair Redman Councillor William Sinclair
Councillor Andrew Vennard Councillor Peter Wallace   
Contact: Julieann Small, Democratic Services Assistant - 01546 604043

Page 3

MINUTES of MEETING of ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
COMMITTEE held ON A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY,
LOCHGILPHEAD AND BY MICROSOFT TEAMS 
on THURSDAY, 19 JUNE 2025 
Present: Councillor John Armour (Chair) 
Councillor Graham Hardie
Councillor Willie Hume
Councillor Andrew Kain
Councillor Jim Lynch
Councillor Ian James MacQuire
Councillor Luna Martin
Councillor Liz McCabe 
Councillor Ross Moreland
Councillor Gary Mulvaney
Councillor Alastair Redman
Councillor William Sinclair
Councillor Andrew Vennard
Councillor Peter Wallace 
Attending: Stephen Hall, Interim Head of Roads and Infrastructure Services 
Fergus Murray, Head of Development and Economic Growth
John Blake, Fleet Waste and Transport Manager
Ishabel Bremner, Economic Growth Manager
Matt Mulderrig, Development Policy and Housing Manager 
Hugh O’Neill, Network and Standards Manager 
Scott Reid, Marine Operations Manager
Jonathan Welch, Rural Growth Deal Programme Manager
Stuart McLean, Committee Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Jan Brown and Tommy
Macpherson. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest 
3. MINUTES 
The Minutes of the meeting of the Environment, Development and Infrastructure
Committee held on 20 March 2025 were approved as a correct record. 
4. EMPTY BUSINESS PROPERTY - UPDATE ON BUSINESS GRANT
SCHEME 
The Committee gave consideration to a report providing an update on the implementation
of Empty Property Relief Policy for Non-Domestic Rates, and to propose an associated
Empty Business Property Grant Scheme. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. considered the content of the paper;  
Page 3 Agenda Item 3

Page 4

2. agreed to the framework and governance arrangements for an Empty Property
Business Grant Scheme; 
3. agreed to delegate authority to the Executive Director with responsibility for
Development and Economic Growth in consultation with the Policy Lead and Chair of
the Area Committee, to approve grants above £25,000 (maximum £50,000) should
circumstances require a grant above £25,000. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 20 May 2025, submitted) 
Councillor MacQuire joined the meeting during consideration of the following item of
business. 
5. HOUSING EMERGENCY UPDATE 
The Committee gave consideration to a report providing an high level synopsis on activity
to tackle the Housing Emergency.   
Decision 
The Environment, Development and Infrastructure Committee considered the content of
the report. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated June 2025, submitted) 
6. COMMUNITY WEALTH BUILDING BILL AND CRUISE SHIP LEVY BILL
CONSULTATONS: ARGYLL AND BUTE COUNCIL OFFICER RESPONSES 
The Committee gave consideration to a report detailing the Argyll and Bute Council officer
responses to the recent ‘call for views’ consultations for the proposed Community Wealth
Building (Scotland) Bill and the Cruise Ship Levy (Scotland) Bill currently progressing
through the Scottish Parliament. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the content of the report;  
2. noted the Argyll and Bute Council officer responses to the questions in both
consultations in Appendix 1 and Appendix 2 of the report. As the deadline for
submission to the Scottish Government was 26th May and 30th May respectively,
officers submitted responses aligned to the requested timetable. The responses were
considered and commentary provided for inclusion in the submissions by members of
the Executive Leadership Team. In addition. the Argyll Islands Sounding Board
considered the response to the Cruise Ship Levy (Scotland) Bill; 
3. agreed to homologate the officer responses; and 
4. noted that as the consultations had closed any additional substantive comments from
members of this committee should be submitted in writing to Tom Arthur, MSP,
Minister for Employment and Investment (where Community Wealth Building is
Page 4

Page 5

included in his portfolio) and on the Cruise Ship Levy to Shona Robison, MSP and
Cabinet Secretary for Finance and Local Government. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 28 May 2025, submitted) 
7. SCOTTISH GOVERNMENT FUNDING - ISLANDS PROGRAMME, CARBON
NEUTRAL ISLANDS CAPITAL FUND AND REGENERATION CAPITAL
GRANT FUND 
The Committee gave consideration to a report outlining the Scottish Government Islands
Programme funding of £5.3m which will be available for the 2025/26 financial year to fund
capital projects on inhabited Scottish islands. A further £1.4m will be available to support
the Carbon Neutral Islands (CNI) in their progression towards net zero. The report outlined
the funds, the respective requirements for applications to each fund and progress made
towards identifying projects for submission. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the process for applying to the Islands Programme and Carbon Neutral Islands
Capital Fund and the 22 July 2025 deadline for applications;  
2. approved the recommended Island Programme projects detailed in paragraph 4.10 of
the report which would form the basis of funding bids to the Scottish Government; 
3. approved the submission of any of the potential CNI Capital Fund Projects listed at
paragraph 4.15 of the report, subject to the project lead determining that this is still a
project that should be progressed; 
4. noted the process for applying to the Regeneration Capital Grant Fund and the 27
June 2025 stage one deadline; 
5. approved the submission of any of the recommended RCGF projects listed at
paragraph 4.22 of the report that would form the Expressions of Interest from Argyll
and Bute Council to the Regeneration Capital Grant Fund for 2026/27; 
6. agreed to delegate authority to the Executive Director with responsibility for
Development and Economic Growth to approve the funding applications prior to
submission to the Scottish Government; and 
7. noted that the Transformational Projects and Regeneration Team would be
responsible for managing expenditure and ensuring compliance with grant funding
conditions for successful projects. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 4 June 2025, submitted) 
8. ARGYLL AND BUTE LOCAL TRANSPORT STRATEGY ISSUES REPORT 
The Committee gave consideration to a report detailing key Argyll and Bute transport
issues that will inform the rationale, content, and future implementation of an Argyll and
Bute Local Transport Strategy within the context of the resources available to us as a rural
Page 5

Page 6

Local Authority together with National and Regional Transport priorities as set out in
National and Regional Transport policy. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. considered and approved the list of Argyll and Bute key transport issues and
associated survey questions, including priority transport projects, collaboration and
partnership working opportunities contained within the report for a six-week period of
public consultation to help inform a future Argyll and Bute Local Transport Strategy;  
2. noted that officers would arrange an Elected Members seminar to take place at the
conclusion of the consultation; and 
3. noted that a further report would be presented at a future committee meeting once
officers had analysed the consultation responses. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 19 June 2025, submitted) 
9. REMEMBERING TOGETHER - CO-CREATING COVID COMMUNITY
MEMORIALS - COMPLETE 
The Committee gave consideration to a report providing a final project update on the
Remembering together programme managed by Greenspace Scotland and delivered by
CHARTS through a partnership with Argyll and Bute Council and Greenspace Scotland. 
Decision 
The Environment, Development and Infrastructure Committee considered the successful
delivery of the Remembering Together Programme. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated May 2025, submitted) 
10. TEMPORARY TRAFFIC REGULATION ORDERS CHARGING AND
ADVERTISING 
The Committee gave consideration to a report detailing recommendations relating to
Temporary Traffic Regulation Orders (TTROs) event charging and advertising and
seeking agreement to undertake a wider review to ensure a consistent approach is
applied to all applications and events. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. agreed that officers carry out a review of the event application costs associated with
TTRO charges and advertising;  
2. agreed that a report outlining the scope and methodology of that review, including
engagement with event organisers, would be reported to the next Environment,
Development and Infrastructure Committee; and 
Page 6

Page 7

3. agreed that the current Fees and Charges in relation to TTROs for events are
suspended and the loss of income estimated to be up to £45,000 in 2025/26 is funded
from the Priorities Investment Fund. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated June 2025, submitted) 
11. REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
The Committee gave consideration to a report providing an update on progress and next
steps in relation to the Roads and Infrastructure Service Review. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. noted the content of the report; 
2. considered the progress made in relation to the Priority Improvement Actions as set
out within Appendix 1 of the report; and 
3. noted that officers would bring a progress report to the September 2025 meeting of this
Committee, which would identify, where possible, how savings would be delivered in
2025/26 and 2026/27. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated June 2025, submitted) 
12. WASTE LANDFILL BAN UPDATE 
The Committee gave consideration to a report providing an update on progress towards
landfill ban compliance. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. considered the content of the report; and 
2. agreed that officers would arrange an Elected Members seminar to take place later in
the year. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated June 2025, submitted) 
13. MARINE OPERATIONS: COUNCIL FERRY SERVICE: HITRANS GRANT 
The Committee gave consideration to a report detailing £1.564m of capital funding
available for allocation to suitable projects with Argyll and Bute Council and internal ferry
operations. 
Decision 
Page 7

Page 8

The Environment, Development and Infrastructure Committee – 
1. agreed that funds be allocated as follows:- 
i. engage with suitable contractors to realise on-site accommodation at Port Askaig; 
ii. to engage with suitable Naval Architects to develop a ‘keel ready’ concept design
for the Eilean Dhiura replacement ferry; and 
iii. to engage with suitable consultants to update and progress plans for the Cuan ferry
infrastructure for use by the Eilean Dhiura and Belnahua vessels; and 
2. in the event that part of the grant remains, approved ringfencing the fund for continued
works on this Priority Strategy. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated June 2025, submitted) 
14. NAMING OF TARBERT PLAYPARK 
The Committee gave consideration to recommendations from the meeting of the Mid
Argyll, Kintyre and the Islands Area Committee held on 19 June 2025 that the Committee
relating to the naming of Tarbert Playpark. 
Decision 
The Environment, Development and Infrastructure Committee – 
1. acknowledged the efforts made by John McAlpine in ensuring that Tarbert’s playpark
was upgraded and improved for the benefit of local young people, alongside the
contributions made by the community as a whole to this much-appreciated local
amenity; 
2. agreed that the Tarbert Playpark should be formally named ‘The John McAlpine
Playpark’; and 
3. asked officers to make the necessary arrangements to formally record the playpark
name as required and for the installation of appropriate signage. 
(Reference: Extract of minute of the Mid Argyll, Kintyre and the Islands Area Committee
held on 19 June 2025, submitted) 
15. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORK PLAN 2025/26 
The Environment, Development and Infrastructure Committee workplan was before the
Committee for noting. 
Decision 
The Environment, Development and Infrastructure Committee noted the content of the
workplan. 
Page 8

Page 9

(Reference: Environment, Development and Infrastructure Committee workplan dated
June 2025, submitted) 
The Committee resolved in terms of Section 50A(4) of the Local Government (Scotland)
Act 1973, to exclude the public from the following item of business on the grounds that it
was likely to involve the disclosure of exempt information as defined in Paragraph 9 of
Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. 
16. WASTE DISPOSAL – OPTIONS POST PPP CONTRACT 
The Committee gave consideration to a report detailing the options that have been
reviewed to achieve service continuity upon the expiry of the Councils PPP contract for
waste disposal. 
Decision 
The Environment, Development and Infrastructure Committee agreed the
recommendations as contained within the submitted report. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated 12 June 2025, submitted) 
Page 9

Page 10

This page is intentionally left blank

Page 11

ARGYLL AND BUTE COUNCIL         ENVIRONMENT, DEVELOPMENT
AND INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE SERVICES        1 SEPTEMBER 2025 
WINTER SERVICE POLICY 2025/26 
1.0 EXECUTIVE SUMMARY 
1.1 Each year Members consider for approval, the Council’s Winter Service Policy. The
format and general content of the Winter Service Policy 2025/26 remains similar to that
of the 2024/25 Policy and is unchanged in general scope since the PPG 2008.        
1.2 The policy sets out priorities for treatment and routes, which will be ‘pre-treated’ in
advance of winter hazards. In prolonged winter conditions, the policy provides for all
roads to be treated, with resources being allocated to focus on the hierarchy of
priorities (i.e. the lower priorities will only be cleared once the higher priorities have
been treated and remain clear of any recurring hazards). 
1.3 The policy is a comprehensive document setting out the management, governance
and operational requirements for the winter service. The policy sets out signing
provision to warn the travelling public of roads which are unsuitable for use during
extreme winter conditions. The policy also provides a protocol for the reduction in use
of salt and preservation of remaining stocks in the event of salt stock replenishment
operations being disrupted. This was introduced following the severe winters of
2009/10 and 2010/11 when national salt supplies were interrupted. 
1.4 It is recommended that the Environment, Development and Infrastructure Committee :- 
• Approves the 2025/26 Winter Maintenance Policy Document at Appendix 1
• Endorses that a further review of the winter maintenance policy is undertaken
prior to the 2026/27 winter maintenance season which includes a review of the
total percentage of the road network that is currently treated and, recognising
this is 10% higher than the average for the rural group authorities, whether
efficiencies on this can be achieved. With an options report back to Committee
during early summer 2026
• Approves the Salt Use Reduction and Preservation of Stocks Protocol at
Appendix 2. 
• Notes the Advisory signing, routes unsuitable in severe conditions at Appendix 3
• Notes the Frontline Treatment Vehicle Fleet 2025-26 at Appendix 4
• Notes the Salt Stocks monitoring and resilience record at Appendix 5
• Notes weather summary from season 2024-25 at Appendix 6 
Page 11 Agenda Item 4

Page 12

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE SERVICES        11 SEPTEMBER 2025 
WINTER SERVICE POLICY 2025/26 
2.0  INTRODUCTION 
2.1 This report presents the Winter Service Policy 2025/26 which remains in a similar
format and covers a similar network to the Policy approved by this Committee in
previous years. This generally remains based on the network and times of the public
bus service with additional priority and resources allocated to strategic highspeed
roads. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Environment, Development and Infrastructure Committee:- 
• Approves the 2025/26 Winter Maintenance Policy Document at Appendix 1 
• Endorses that a further review of the winter maintenance policy is undertaken prior to
the 2026/27 winter maintenance season which includes a review of the total
percentage of the road network that is currently treated and, recognising this is
10% higher than the average for the rural group authorities, whether efficiencies
on this can be achieved. With a report to Committee during early summer 2026
• Approves the Salt Use Reduction and Preservation of Stocks Protocol at Appendix 2 
• Notes the Advisory signing, routes unsuitable in severe conditions at Appendix 3
• Notes the Frontline Treatment Vehicle Fleet 2025/26 at Appendix 4
• Notes the Salt Stocks monitoring and resilience record at Appendix 5
• Notes weather summary from season 2024-25 at Appendix 6 
DETAIL 
4.0 Winter Maintenance Policy 2025/26
4.1 The proposed Winter Maintenance Policy for 2025/26, in terms of treatment
standards and routes, remains largely unchanged from last year. The current
hierarchy of routes in section-4 of the policy, allows for 54.24% of the adopted road
network to be subject to pre-treatment. This is the highest proportion within the seven
authorities in the SCOTS Project Group1(Rural) and 10% above the average for all
Scottish authorities.
4.2 The changes brought in over the previous two seasons have been subject to review
as part of the annual process of end of season assessment and future planning.
Page 12

Page 13

• The second year of the new Weather Forecast contract with Metdesk Ltd was
reviewed at a West of Scotland Group meeting in May 2025. The out-turn
performance figure for accuracy of the Argyll and Bute forecast was above the
industry norm of 90%-92% with an outturn figure of 94.4 % for the season
• Revised routes, implemented over the previous seasons were reviewed for
effectiveness. The Kintyre routes K1-K3, additional L7 Lorn Arc treatment
route and the addition of the road C07 Ardlamont section onto the C6 pre-
treatment route in Cowal were all successfully delivered as planned, within the
parameters of the policy.
• Standby shifts were altered to run from Thursday afternoon to the following
Thursday morning. This allowed operatives in depots with limited numbers,
resulting in “one on – one off” shift patterns to be allowed the potential for a
long weekend Friday – Monday break, without the need for substitute drivers.
This pattern operated successfully all through last winter season and has
continued through the parallel “Summer Standby” out of hours commitment.
The Policy has been adjusted to allow for the Thursday starts for the coming
season.   
4.3 Storm Eowyn crossed Argyll and Bute on 23rd and 24th January and was
considered a severe danger to life. Consequently, operations staff were instructed
to stand-to awaiting an abatement in the conditions, with a maximum gust of
approaching 100mph recorded on the Friday. Once safe to mobilise on Saturday
25th resources were initially engaged in closing roads on safety grounds, due to
dangerous buildings. Through the weekend, works concentrated on the removal of
physical obstructions to the network, with almost all removed by Tuesday 28th
January apart from a small number restricted to single file, controlled by traffic
lights. 
4.4 The advisory signs for alternative routes in severe snow conditions remain similar for
the four routes proposed in previous years. Details on sign configuration and
locations are contained in Appendix 3 of this report. 
4.5 Winter stand-by arrangements will commence on Thursday 30th October 2025 and
will continue until Thursday 16th April 2026. There remains a total of 32 treatment
routes detailed in the policy’s operational planning web-based management tool.
Should weather conditions dictate, it may be necessary to bring forward the start
date and/or push back the finish date. This would be determined operationally
depending on the forecasts received or observed weather conditions. 
4.6 The Winter Treatment Fleet for 2025/26 will be similar to last winter. This will consist
of 17 hired gritters from Econ Ltd. 8 of 26t 9cu.m capacity and 9 of 18t 6cu.m
capacity, retained on a further one year extension. 1 contractor vehicle on Jura and
13 Council vehicles. The Council element consists of the updated frontline winter
capable fleet of Quick-Change Body (QCB) demountable, multipurpose vehicles
procured during 2021. This provides 32 main frontline vehicles with 3 spare 18t
6cu.m capacity multipurpose vehicles and 3 back-up 12t 3.5cu.m multipurpose
vehicles to cover breakdowns. In addition, a further 4 x 7.5 tonne tippers can
accommodate ploughs, giving a total of 10 extra vehicles that can be deployed
together with Contractors’/ Farmers’ tractors and ‘V’ ploughs if conditions demand.   
Page 13

Page 14

4.7 A further review of overall winter capable fleet was carried out after concerns raised
in 2023-24 season on the limited ability to react to the occasional severe frosts on
Tiree and Coll. Additional trailer gritters for use in conjunction with transit pick-up
sized vehicles were procured for Tiree, Coll, Colonsay and Lismore. These facilities
will be in place for the coming season, including parallel towing and salt loading
facilities. Staff on these islands will react to conditions under priority 4 of the Policy. 
4.8 The requirement to manage drivers’ hours within the delivery of all Council Services
directly impacts on the retention of the Council’s Operator Licence. Drivers from
across the operational teams (grounds, waste, roads) deliver the pre-treatment
service, in conjunction with external contractor assistance on the island of Jura. In
extended periods of extreme winter conditions consideration will be given, at an
operational level, to prioritising services to ensure that winter treatments can be
delivered. This may result, for example, in refuse collections and other services being
temporarily suspended in order to prioritise the clearing of ice and snow. Such
measures are only likely in prolonged periods of extreme weather. 
4.9 Steps are taken each year to increase the available driver “pool” by utilising other
council drivers including grounds and waste disposal operatives. Discussions are
ongoing to resource additional resilience by engaging assistance from external
contractors on mainland and island routes where in-house coverage is limited. The
age demographic of operatives within the service, coupled with limitations on
recruitment at local levels, indicates that a deficit in the driver pool may further
develop in several districts, making the delivery of the current policy difficult
to maintain in future years. 
4.10 In extreme and prolonged weather events and where other priority tasks occur (such
as responses to road traffic collisions, collapsed culverts, fallen trees etc) resources
may need to be allocated based on a risk-based priority. 
4.11 Table 1 below indicates the statistical variations in operational activities over the last
eight winter seasons. Weather patterns vary with some years experiencing hazards
more widespread and in others more concentrated on inland and higher routes. The
equivalent Full Fleet runs statistic is used to indicate an approximation to the budget
allowance. The application of salt varies between 10gm2 and 40gm2 depending on a
number of factors including road surface temperature, forecast and residual salt. In
parallel with these methods, grit and sand are applied in snow conditions. The route
with the individual highest number of turn-outs, was consistently the A819 East Lorn
Strategic Route in previous years, due to its North Eastern inland, high level
sections. However, last season A815 Dunoon – Cairndow strategic route pre-
treatment vehicle was mobilised on 109 times, with A819 turned out 105 times. 
Page 14

Page 15

Table 1 
Winter Season 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23  2023/24  2024/25
Equivalent Full Fleet
Runs 
110nr  62nr  78nr  79nr  65nr  66nr   71nr   81nr
Salt used in all
treatments   tonnes 
22,992t  13,059t  12,280t  15,753t  11,030t  12,535t  12,070t  11,755t
Most turned out
Treatment route.   
Mobilisations = nr 
A819 
= 162nr 
A819 
= 109nr 
A819 
= 139nr 
A819 
= 114nr 
A819 
= 107nr 
A819 
= 94nr 
A819 
= 103nr 
A815
= 103nr 
A815
= 109nr
A819
= 105nr 
4.12 It remains a considerable time since we have experienced a large scale snow event.
Even the “Beast from the East” in 2017 only affected the Eastern domains of
Lomond, Bute and Cowal with the rest of Argyll largely untouched. It is likely that
should a longer spell of snow affect the whole of Argyll, a considerable escalation in
resources and hence budget spend will be required to maintain lifeline accesses to
communities.
Appendix 6 to this report provides a summary of the 2024/25 winter conditions. 
4.13 Footways and footpaths will only be treated, in periods of lasting hazard, when it is
considered by the winter management team that the physical condition of the
footways and footpaths makes it necessary and treatments will be effective.
Footways and footpaths will usually only be treated during normal working hours.
Staffing levels are such that we generally do not have sufficient operatives available
to deal with footways and footpaths in parallel with treatments of the carriageway.
The mobilisation of external resources to assist in footway treatments, is a balance of
cost benefit against potential thaw conditions rendering treatments un-necessary.
This winter maintenance policy applies to the public road network and a limited
number of emergency service and public transport routes. Public car parks, access
to council offices, schools etc all being subject to local arrangements out with the
scope of this policy. 
4.14 In specific locations additional information and diversion signing will be erected to
further inform drivers of the hazardous conditions on some routes and advise them of
alternative routes where available resources will concentrate on maintaining
treatments. There are four roads where signing to indicate specific alternative routes
are available. The signs deployed for these road closures are detailed in Appendix3. 
1. A817 “Haul Rd”, Lomond. 
Snow gates at A82 and A814 “central” roundabout 
Diversion via A818 Arden - A814 Garelochhead 
2. C46 Glen Aros / Glenbellart road , Mull 
Signs at Aros Bridge and Dervaig Primary School 
Diversion via A848 Tobermory 
3. C9 Glenfinart Road (The Larach), Cowal   
Signs at Whistlefield Hotel and Sligrachan Bus turning head; 
Diversion via A880 Cot House
Page 15

Page 16

4. C11 Otter Hill road ( Bealach an Drain), Cowal 
Signs at Glendaruel A886 and Otter Ferry B8000; 
Diversion via A8003 Tighnabruaich and Kames. 
4.15 Graph 1 indicates the trend in winter activity spend against budget for the last
decade, in what is essentially, a static Policy. The Council’s Winter Maintenance
budget was increased by £500k in Financial Year 2019/20 to an operational budget
of £2.12M. Despite further budget increases to £2.304M for 2023-24 and £2.673M for
2024-25, further unit cost increases have consistently resulted in annual costs
exceeding budget allowance. The actual cost of winter maintenance is dependent
upon the severity of winter conditions and is a financial risk, in that the service
responds in accordance with set policy to variable weather events, which are not
predictable. The amount of salt used per year will vary, depending on the grams per
sq.m instructed in the individual route plans, for each mobilisation, which are dictated
by the weather forecast and actual observed conditions. 4.11 - Table 1 refers. 
Graph 1 
4.16 Overall the financial out-turn cost for winter 2024-25 was recorded as £2,878,902 at
31st March once accruals were allocated, against a budget of £2,673,368, an excess
of £205,534 equivalent to 8%. This indicates a continuation of the general increase in
the unit costs of winter and hence the average cost of a full fleet mobilisation. 
4.17 Salt stocks totalling 8,884 tonnes were recorded in all stores at the end of season
2023-24. The recorded total of salt purchased last winter amounted to 12,721
tonnes delivered to all stores by a combination of bulk shipping and road deliveries. 
A total of 11,755 tonnes of rock salt was recorded as used in all treatments,
including grit heaps and bins, from mid-October 2024 to late March 2025, with no
positive action required in the remaining period up to mid-April, end of Winter
Standby operations.
4.18 Salt prices are accepted through the Scotland Excel contract from our term supplier
Irish Salt Mining and Exploration Ltd. The price increase agreed in May 2024
amounted to 5% to 6% per tonne overall. These prices were held for last winter,
with the average price £55.29 / tonne, delivered to depots. The unit prices for 2025-
26 are expected through Scotland Excel by September for implementation in
November.
Budget
Page 16

Page 17

4.19 The Gritter Hire Contract with Econ Ltd. has been extended for a further year,
retaining the current fleet of 17nr PMGs for 2025-26. The hire for the core period,
allowing for potential early mobilisation equates to a 6 month period from 15th
October to 16th April. The core period hire costs are estimated at £486,024.00. The
hired PMGs and in-house fleet of frontline treatment vehicles is shown in Appendix
4. 
4.20 The budget for winter 2025-25 is similar the last season at £2,672,426. This allows
the equivalent fleet runs monitoring figure, to be set at 80nr runs for the coming
season.   
4.21 As of July 2025, the Council held a stock of approximately 7,914 tonnes of useable
salt. Provisional orders are in place for a further 3,500 tonnes. Deliveries will be
called forward in October to top up capacity in storage facilities to the target starting
stock of +11,000 tonnes. Salt deliveries will continue to be ordered throughout the
winter period to keep reserves stocked and preserve resilience. Weekly salt stock
lists are submitted to Scottish Government as part of a Scotland wide winter
resilience plan- Appendix 5 
4.22 The Salt Use Reduction and Preservation of Stocks protocol was introduced in
December 2010 in light of severe shipping and material shortages. This was
reviewed and updated in 2020 and is attached at Appendix 2.   
4.23 The assessment of school routes subject to pre-treatment before 08:00hrs, is
covered under Priority 3b of the route hierarchy, in section 4 of the Policy. This is
reviewed each year once the pupil intake for August is confirmed. The policy remains
similar to previous years, where sections of routes not already included under Priority
1 & 2 or P3a Service bus routes, are added to the pre-treatment routes, when at
least 12 pupils are carried on transport provided by the council. 
Transport Scotland 
4.24 Following the decision to trunk the southern section of the A83 in 2014, Transport
Scotland are the roads authority for this section of road Kennacraig – Campbeltown.
The G6 trunk road contract for NW area had a commencement date of 16th August
2022 and was retained by BEAR Scotland Ltd as the Operating Company. 
4.25 BEAR Scotland Ltd confirmed the establishment of their own operational depot at
Machrihanish, for winter 2023-24.  Since then, there has been no further requirement
for A&BC to provide resources to BEAR for winter maintenance on A83 Kintyre. 
4.26 Due to the isolated nature of some sections of the Council network, directly
connected to the trunk road, BEAR Scotland provides assistance in compliance with
the A&BC policy with regards to transport interfaces under Priority 2. Treatments are
delivered by trunk road vehicles on return journeys, after completing their routes. 
• Bridge of Orchy Rail Station road (and Fire station) – Off A82
• Furnace Village Bus Loop - Off A83 
Page 17

Page 18

Winter Policy Review  
4.27 Whilst the budget is effectively the same sum as last year, the governing factor is
related to driver resources, with pressures on the current capability. This trend will
eventually become unsustainable given the age demographic of drivers. The
availability of local contractors to supplement the full time employees, is also subject
to variation and localised pressure. However, for the purpose of this report, Officers
are not requesting any further increase to this year’s budget, at this time. 
5.0  CONCLUSION 
5.1 This report details the Council’s Winter Maintenance Policy for 2025/26 and
highlights the pressures on resources and operational effectiveness due to the
constraints of future funding levels and best practice advice. 
5.2 Committee is asked to approve the Winter Service Policy 2025/26 and note the
details in Appendices 1 – 6. 
5.3 A consultation process will commence in parallel with the 2025-26 operational winter
period, to review the Winter Policy – level of service. This will look at the current
policy based largely on the public bus service routes, with a view to determining fair,
equitable and efficient ways to reduce the winter commitment within the Council’s
obligations for Road Safety and Economic growth. Consideration will be given to
current and predicted physical and financial resources, within the Revenue budget. 
6.0 IMPLICATIONS 
6.1 Policy – It is considered to be good practice for Committee to confirm policy for winter
maintenance activity on an annual basis. This report seeks to achieve the above. 
6.2 Financial – The Council’s Winter Maintenance budget is a similar sum         
£2.672 million (from £2.673 million) for this financial year, to cater for previous and
anticipated unit cost pressures. This provides the capability to deliver the equivalent of
approximately 80 full runs of the treatment fleet over the coming season. The actual
cost of winter maintenance is dependent upon the severity of winter conditions and is
a financial risk in that the service respond s to weather events that are not predictable.
Should the criteria for school bus routes change this will affect the budget required. 
6.3  Legal – The Winter Maintenance Policy sets out the Council’s level of service
provision for winter maintenance, with reference to Section 34 of Roads (Scotland) Act
1984.   
6.4  HR – Staffing levels have reduced over recent years, this can make it challenging to
have sufficient staff to deal with a severe winter event. Processes are in place for
external suppliers to assist in geographic specific locations with additional support
called forward through framework contracts should severe weather persist. 
6.5 Customer service – The winter policy has been designed to maintain access to the
Council’s Strategic Road network and other “lifeline” routes within the confines of the
Page 18

Page 19

available resources. 
6.6  Risk – The proposed policy, is designed to reduce the exposure of the Council to risk. 
6.7  Climate change – In recent years, weather patterns are trending to intermittent storm
events with shorter duration periods of traditional “winter” hazards of snow and ice.
Frequent thaws / wash-off events result in an increase of repeat salting treatments in
marginal conditions. Therefor increasing cost and resource commitments, rather than
reducing them. 
6.8  Fairer Scotland Duty – None. 
6.9  Equalities: protected characteristics – None 
6.10  Consumer duty – None known. 
6.11  Island communities – Island road network hierarchy assessed and included in this
policy. 
6.12 Children’s Rights and Wellbeing – The proposed policy, considers the requirement to
treat routes to schools, within the confines of available resources. 
Executive Director with responsibility for Roads and Infrastructure Services – Kirsty
Flanagan 
Head of Roads and Infrastructure Services – Andy Summers 
Policy Lead – Roads, Transport and Amenity Services - Councillor John Armour 
August 2025 
For further information contact: Stephen Hall - Interim Head of Roads & Infrastructure
Services 01546 604896 
APPENDICES 
1. 2025-26 Winter Service Policy Document
2. Salt Use Reduction and Preservation of Stocks Protocol (2020 revised)
3. Advisory Signing – Road Closures in Severe Conditions
4. Frontline Treatment Vehicle Fleet 2025-2026  
5. Salt stocks – July 2025 – monitoring and resilience record
6. Summary of 2024-25 weather conditions
Page 19

Page 20

This page is intentionally left blank

Page 21

WINTER SERVICE POLICY
2025-26 
Author Assistant Network and Standards Manager
Owner Head of Road and Infrastructure Services
Date 29th July 2025
Version 1.0 
Page 21

Page 22

CONTENTS 
Page No.
Section 1 Introduction  2 
Section 2  Outline Principles   2 
Section 3  Management Arrangements   3 
Section 4  Policy on Treatment Priorities   4 
Section 5  Winter Standby, Standby Procedures and Gritting Guidelines   6 
Section 6  Snow Clearance Strategy   8 
Section 7  Assistance from Other Authority Resources and Contractors   10 
Section 8  Salt, Etc.   10 
Section 9  Plant Resources and Servicing Practices   13 
Section 10  Weather Forecast and Monitoring   13 
Section 11  Operational Communications   13 
Section 12  Instruction and Record Keeping   16 
Page 22

Page 23

1.0  INTRODUCTION 
1.1  Argyll and Bute Council has a statutory obligation, under Section 34 of the
Roads (Scotland) Act 1984, to “...take such steps as it considers reasonable
to, prevent snow and ice endangering the safe passage of pedestrians and
vehicles over public roads” in the Council area, which by definition includes
carriageways, footways, footpaths, pedestrian precincts, etc. 
1.2  Argyll and Bute Council will consider implementation of the recommendations
included in the UK Roads Liaison Group document - Well Managed Highways
Infrastructure, code of practice (first published October 2016) within the
practicalities of resources and geography. The Council, through its officers,
will liaise and take guidance from the Scottish Collaboration of Transportation
Specialists, (SCOTS) - Winter Service Subgroup on the consistent approach
to implementation, in the context of the Geographical and Climatic conditions
relevant to Scotland. 
1.3  It is the aim of Argyll and Bute Council to provide a service with respect to the
above that will:- 
a) Ensure the provision of a standard of treatment appropriate to the
prevailing weather conditions. 
b) Establish patterns of working which will produce the greatest benefit from
the deployed resources, with the view to reducing the level of risk and the
extent of any delays to the public, caused by adverse weather conditions. 
c) At all times comply with the requirements of the Health and Safety at Work
Act 1974. 
2.0  OUTLINE PRINCIPLES 
2.1  The Council, through the Executive Director with responsibility for Roads and
Infrastructure Services, will:-
a) Set policy and strategy and monitor the winter maintenance service. 
b) Arrange weather forecasts to assist the Winter Management team to
determine the daily winter maintenance treatment strategy. 
c) Provide specialist winter maintenance plant. e.g. snow plough
attachments, bulk gritters, demountable gritters, towed gritters and loading
shovels. 
d) Provide salt, grit, grit bins, snow gates and signing. 
e) Provide organise and manage a trained labour force. 
f) Provide non specialist plant e.g. lorries for demountable gritters, pickups,
non-specialist loading equipment, hand tools, tarpaulins and the like. 
Page 23

Page 24

3.0  MANAGEMENT ARRANGEMENTS 
3.1  The Executive Director with responsibility for Roads and Infrastructure
Services is responsible for implementing the Council’s Winter Service Policy. 
3.2  The Head of Road and Infrastructure Services has overall responsibility for
ensuring that the Council’s winter maintenance activities are carried out in line
with the Council’s Winter Service Policy. 
3.3  The Network and Standards Manager is responsible for the appointment of a
Weather Service Provider (forecaster), collection of winter management and
weather data. The provision and maintaining of salt stocks, preparation and
collation of rotas for on-call Managers, Area Supervisors and teams of
Operatives and for communications. 
3.4  The Operations Manager is responsible for the day to day delivery of the
Council’s winter service policy, the appointment of appropriate staff as Winter
& Duty Managers, Supervisors and sufficient Operatives to deliver the policy.
The maintenance of appropriate depots and salt stores to allow the efficient
delivery of the Policy and in conjunction with the Fleet Manager, provision and
maintenance of a fleet of winter capable vehicles in these depots. 
3.5 The appointed Winter Manager on duty is responsible for consulting with the
on-call Duty Manager and approving the draft winter plan of action together
with any subsequent updates to that plan produced after review of conditions. 
3.6  Duty Managers are responsible for analysing forecast data, liaising with the
forecast provider and producing the daily winter maintenance action plan and
gaining approval from the Winter Manager. They will ensure that the daily
winter maintenance action plan is submitted to local areas for action by 15:00
hrs each day. They will monitor the weather information and make any
changes to the action plan as conditions require. 
3.7  The Operations Manager will ensure that the appointed staff in their areas are
aware of and understand the strategies and priorities as stipulated. On
receiving the Duty Manager’s approved daily winter action plan they will
ensure, through the Area Winter Supervisor, that the plan is correctly
implemented. They will ensure, wherever practicable, that adequate
resources are available to fully undertake the Council’s Winter Service Policy. 
3.8  Discussions will take place between Senior Management to monitor
performance, at regular meetings. Any problems highlighted by the Duty
Managers will be resolved at local level, where possible. Duty Managers will
be relieved by other Area Office staff, from any local management
responsibilities, during their weekly duty requirements. 
3.9  Provision of the Winter Service on Council roads will normally run from the
nearest Friday to the 1st November through to 15th April each season.
However, this period may be extended, at either end, to accommodate
prevailing weather conditions.
Page 24

Page 25

4.0  POLICY ON TREATMENT PRIORITIES 
4.1  Carriageway treatment 
4.1.1  Prior to the commencement of each winter the Assistant Network and
Standards Manager will produce carriageway gritting routes based generally
on the following principles:- 
Priority 1
Strategic high speed, main traffic routes
Lomond - A814 Dumbarton- Garelochhead, A818 Arden (A82) - Helensburgh
Cowal - A815 Cairndow – Dunoon Ferry
Lorn / Mid-Argyll - A816 Oban - Lochgilphead, A819 Dalmally – Inveraray 
04:00 – 08:00 hrs 08:00 – 16:00hrs 16:00 – 22:00hrs 22:00 – 04:00hrs
Mon
Sat
- Pre-treat as
required +
reactive
Pre-treat as
required
+ reactive
Pre-treat as
required
+ reactive
Reactive as
reported
conditions dictate
Sun
PH
& Pre-treat as
required +
reactive
Pre-treat as
required
+ reactive
Pre-treat as
required
+ reactive
Reactive as
reported
conditions dictate 
Priority 2
Other “A” and “B” classified roads, 
Except where treatment is categorised under Priority 3 bus routes, or less. 
A814 Garelochhead –Arrochar, A817 Haul Road & B833 Rosneath Peninsula
A815 Dunoon-Toward, A880 to Ardentinny, A885 Sandbank, A886 Strachur–
Colintraive, A8003 Tighnabruaich, A844 / A845 & A886 on Bute 
A846 / A847 on Islay, A846 on Jura 
A848 / A849, A884 & B8073 Tobermory – Dervaig, on Mull 
B828 / B839 to Lochgoilhead, B842 Southend – Carradale, B843 to
Machrihanish, B844 / B8003 to Easdale & Cuan 
B8001 Skipness, B8024 Kilberry Loop, B841 / B8025 Achnamara & Tayvallich.
Plus
Principal Accident and Emergency routes or roads to hospitals and routes to
Police stations, Fire stations and Ambulance depot accesses Other selected
streets in main urban areas e.g. steep hills, etc where route efficiency permits. 
06:00 – 08:00hrs 08:00 – 16:00hrs 16:00 – 22:00hrs 22:00 – 06:00hrs
Mon
-Sat
Pre-treat as
required
+ reactive
Pre-treat in
advance (if
possible) +
reactive
Reactive as
reported
conditions dictate
Reactive - only in
extreme
conditions
Sun
& PH
Pre-treat as
required
+ reactive
Pre-treat in
advance (if
possible) +
reactive
Reactive as
reported
conditions dictate
Reactive - only in
extreme
conditions 
Page 25

Page 26

Priority 3
Any section of public road, outwith P1 & P2 above, subject to :-
Main Public Service bus routes as timetables require that can be met
within operational time bands. 
Should it be impractical to cover a Service then the operator must be notified
or Main School Bus routes prior to or during term days only. 
Designation   06:00 – 08:00
hrs 
08:00 – 16:00 hrs  16:00 – 22:00 hrs  22:00 – 06:00
hrs
Priority 3a 
Service
Route
Mon-
Fri
Pre-treat as
required +
reactive 
Pre-treat in
advance (is
possible) +
reactive 
No treatment
unless stable
conditions
forecast a.m. 
No
treatment 
W/E Pre-treat in advance of journey, if possible, but no
guarantee.     Timetabled days only.  
Priority 3b
School
Route
12 or more
occupied
seats)
Mon-
Fri
Pre-treat as
required
+ reactive
Pre-treat in
advance
+ reactive
No treatment
unless stable
conditions
forecast a.m.
(Not Friday p.m.)
No
Treatment
No treatments out-with School Term days
(apart from Sunday evenings in advance, if stable conditions
forecast Monday a.m.) 
Priority 4
All other public roads
Only as actual conditions dictate and resources are deemed to be effective. 
06:00 –
08:00hrs 
08:00 – 16:00 hrs 16:00 – 22:00 
hrs
22:00 – 06:00 
hrs
Mon - Fri No
treatment
Reactive (may
include pre-treat)
Reactive – only in
extreme conditions
No treatment
W/E & PH No
treatment
Reactive – only in
extreme conditions
No treatment No treatment 
4.1.2  The above route priorities are set around the requirements to pre-treat in
advance of freezing conditions or react to developed hazards within a
reasonably practicable timescale within the confines of the resources
available. Under standard conditions, pre-treatment routes are designed to be
completed within 3 hours of mobilisation. 
4.1.3  Where hazards re-occur after treatment or in conditions where instantaneous
hazards occur, resources may be required to concentrate on re-application of
several treatments prior to moving on. In such circumstances the highest
priority routes, experiencing such conditions, will generally be treated first and
resources will only be released to other priorities once it is determined that
treatments have an expectation of remaining effective. 
Page 26

Page 27

4.2  Footway and Footpath Priorities 
4.2.1  At the start of each winter, the Assistant Network and Standards Manager will
produce footway and footpath treatment routes based generally on the
following principle. 
Priority 1 - Urban Shopping Areas and Precincts 
Priority 2 - Other areas of high pedestrian concentration, e.g. in the vicinity of
hospitals and schools. 
Priority 3 - Steep hills in housing developments and in the vicinity of
residential homes for the elderly. 
4.2.2  Footways and footpaths will only be treated, in periods of lasting hazards,
when the Duty Manager, in consultation with Area staff, considers that their
physical condition makes it necessary and treatments will be effective. They
will usually only be treated during normal working hours. 
4.3  Resources 
4.3.1  Labour
To ensure that an adequate labour resource is available to allow treatment to
be carried out, arrangements are in place with Amenity Services section to
participate in the supply of additional labour when conditions require. 
4.3.2  Plant
Plant to assist with the clearance of snow and spreading of salt has been
provided by Road and Infrastructure Services. Attachments to mowers to
allow footpath ploughing will be fitted at the start of each season, where
practicable. Footway salt spreading barrows are provided for use by available
labour when required. 
4.4  Cycleways 
4.4.1  Only cycleways contiguous with roads and footways will be treated in
conjunction with any planned treatments. 
5.0  WINTER STANDBY, STANDBY PROCEDURES & GRITTING GUIDELINES 
5.1  The formal winter standby period for Council roads will normally be from the
end of the working day on the Thursday nearest to 1st November to the
Thursday nearest to 15th April. This period may be extended at either end as
the prevailing weather conditions dictate. 
5.2  Shift and Standby Procedures 
5.2.1  During the operational period, standby arrangements will be operated on a
formal home standby basis, with call-out as required. Arrangements will be
put in place to allow mobilisation of frontline vehicles within 1 hour of call out.
Page 27

Page 28

5.2.2  Standby rotas will include sufficient drivers to ensure that the priority 1 routes
can be treated within 3 hours of commencing treatment 
5.2.3  On receipt of a weather forecast indicating medium to heavy snow, where
resources allow, sufficient additional operatives will be placed on standby to
cover all priority 1 & 2 routes and any priority 3 routes likely to be affected, as
timetables indicate, by the forecast. 
5.3  Carriageway Treatment 
5.3.1  Carriageways will generally be treated in the order of priority as specified in
section 4. 
By 13:00 each day during the winter months, having considered the most
recent weather forecast, the level of residual salt on the road network
and the available resources, the Duty Manager will compile an Action Plan for
carriageway treatment for the following twenty-four hours. The Winter
Manager will review, recommend any adjustments if needed and then
approve the proposed plan. 
5.3.2  Precautionary treatment for frost and light snow will be spread at a target rate
of 10g/m² of salt. 
5.3.3  Precautionary treatment of 20g/m² for conditions where frost is forecast after
rain should be delayed as long as possible to reduce loss of salt due to wash-
off. This should not preclude the treatment of routes during showers where
freezing of rain on contact has been predicted or is reported. 
5.3.4  Precautionary treatment when heavy snow falls are expected should be at a
rate of between 20 and 40g/m² of salt according to the anticipated severity of
snowfall and confidence level of the forecast. 
5.3.5  In conditions where current snowfall is forecast to continue, substitution of salt
with abrasive materials, sand or grit, will be instigated until such time as
showers cease and any use of de-icing materials are deemed to be more
effective. In extreme or persisting conditions, all material spreading will cease
until there is an expectation that any deposits will remain on the carriageway
and be effective in aiding traction. 
5.3.6  In marginal conditions, consideration will be given to limiting treatment to
known localised areas prone to icing. During periods of prolonged freezing
conditions in the absence of precipitation, spot salting of areas of persistent
seepage will continue while hazards remain. 
5.3.7  Where areas of seepage from adjoining land are recorded on a regular basis,
these will be identified and pre-emptive rectification of the drainage system
will be instigated. 
Page 28

Page 29

Land owners will be notified of their requirement to carry-out such work as it
affects public roads. The Council will take necessary steps to effect repairs, in
the absence of any undertaken by landowners and pursue recovery of costs
accordingly. 
5.4  Footway and Footpath Treatment 
5.4.1  Treatment of footways and footpaths will be by a combination of mechanical
and manual operation. In large urban areas footway salting will be carried out
by purpose built spreader barrows with a nominal design spread rate of
50g/m². 
5.4.2  Salt will only be utilised where ice and frost are the main hazard. In all
snowfall conditions, physical clearance will be the priority with sand / grit
spread thereafter to aid traction. 
5.4.3  Treatment of footways and footpaths will normally only be carried out during
the normal working day as resources permit. In most cases additional
resources should be mobilised at local level as conditions dictate. The Winter
Manager and Duty Manager will be kept informed of all additional resources
mobilised by local management. 
6.0  SNOW CLEARANCE STRATEGY 
6.1  Carriageways 
6.1.1  On receipt of a weather forecast indicating medium to heavy snow,
carriageways should be treated in accordance with section 5.3.5. When the
forecast is for rain turning to snow or the snow prediction is marginal the
salting operations should be delayed accordingly. 
6.1.2  When forecasts indicate that there will be medium or heavy snow falls, the
Duty Manager will instruct that all vehicles capable of being fitted with
ploughing devices will be so equipped. 
6.1.3  Salting should be continued or be restarted when snow is falling, as
conditions warrant however sand / grit must be used to preserve de-icing
materials until such time as it can be used effectively. 
6.1.4  Snow ploughing will commence as soon as it is considered that the operation
will be effective. Generally snow can only be ploughed effectively at depths
exceeding 30mm. 
6.1.5  Spreading treatment of ploughed surfaces will be carried out when it is
considered that the material will have the most beneficial effect. The normal
case on two lane carriageways will be for spreading treatment to be started
when the second lane is being ploughed, generally in the return direction.
However in persisting snow conditions the spreading of materials shall be
delayed until clearance of accumulations is effective. 
Page 29

Page 30

6.1.6  Resources should generally be allocated to clear roads in the order of priority
shown in section 4, but with precedence being given to those areas which
have experienced the heaviest snow falls and drifting 
6.1.7  Where slush is formed it should be ploughed as soon as practicable to avoid
the risk of rutting should there be a further significant drop in temperature
which might result in freezing conditions. 
6.1.8  Where snow hazards are predicted to persist or develop intermittently
throughout the night, consideration will be given to continuing action in some
circumstances. Mainly in cases where a break in operations may result in
hard packed snow or other conditions difficult to treat on resumption.
Individual circumstances, such as access for emergency services or other
lifeline service vehicles will normally take precedent over the above route
priority arrangements. 
6.1.9  Where it is judged that a road cannot be kept open, early closure in liaison
with the Police in a planned manner, should be initiated. Direct consultation at
local level must be maintained where conditions are changeable and in some
circumstances this may mean discussions on site between local Supervisors
and Police officers. 
6.1.10 In specific locations additional information and diversion signing will be
erected to further inform drivers of the hazardous conditions on some routes
and advise them of alternative routes where available resources will
concentrate on maintaining treatments. There are four roads where signing to
indicate specific alternative routes are available. 
1. A817 “Haul Rd”, Lomond, Snow gates at A82 and A814 “central” roundabout
Diversion via A818 Arden - A814 Garelochead 
2. C46 Glen Aros / Glenbellart road, Mull.  Signs at Aros Bridge and Dervaig
Primary School.   Diversion via A848Tobermory 
3. C9 Glenfinart Road (The Larach), Cowal.   Signs at Whistlefield Hotel and
Sligrachan Bus turning head.   Diversion via A880 Cot House 
4. C11 Otter Hill road (Bealach an Drain), Cowal. Signs at Glendaruel A886 and
Otter Ferry B8000; Diversion via A8003 Tighnabruaich and Kames. 
6.1.12 Road closures will be reported to the Executive Director, Head of Service,
Operations and Network & Standards Managers as soon as practicable, with
immediate notification transmitted to Traffic Scotland and local radio stations
where appropriate. 
6.2  Footways and Footpaths 
6.2.1  Where footways and footpaths are covered with light accumulations of snow
i.e. less than 30mm, treatment will consist of the application of Sand or Grit as
described in section 5.4. of this document.
Page 30

Page 31

6.2.2  Where snow depths exceed 30mm, footways clearance will be carried out
where practicable by pedestrian operated or ride on powered footway
ploughs. This will be enhanced by manual clearance when necessary i.e.
where access precludes the use of the above plant. 
6.2.3  Snow clearance of footways will normally only be carried out during the
normal working day and as resources permit. 
7.0  ASSISTANCE FROM EXTERNAL CONTRACTORS 
7.1  Road and Infrastructure Services provide labour and non-specialist plant as
specified. In some districts, mainly islands, resources are limited and private
contractors are used to provide cover to comply with this policy. 
7.2  In areas of the network remote from the main depots, sub-contractors are
engaged to provide the full winter service provision in parallel with the in-
house council resources. 
7.3  In severe weather conditions additional resources can be drafted in from local
private contractors, through the small works framework contract, to
supplement those of the Council. Arrangements are made through the
Operations Manager to contact these contractors in advance to determine
their availability and formulate contingency plans for contact and mobilisation.
The Winter Manager and Duty Manager will be kept informed of all additional
resources mobilised by local management. 
8.0  SALT ETC. 
8.1  Provision of Salt 
8.1.1  Salt or other de-icing materials will be supplied through the Network and
Standards Manager. An annual supply contract shall be let prior to the start of
the winter season. 
8.1.2  Onsite sampling and testing shall be carried out in each area as the Network
and Standards Manager deems necessary. The Network and Standards
Manager will ensure that sufficient stocks of Salt and Abrasive materials are
maintained at each storage location. 
8.2  Storage of Salt 
8.2.1  Where practicable salt shall be stored under cover to prevent leaching,
improve handling and to reduce treatment times. A programme of upgrading
salt stores with permanent roofs will be undertaken as quickly as practicable
and as financial, planning and operational considerations allow. 
8.2.2  Storage facilities will be loaded out prior to the commencement of operations
and stock levels will be monitored weekly to assure optimum supplies are
available throughout the season. Stores will be kept as full as practicable, as
Page 31

Page 32

protection from the weather allows and minimum stock levels will dictate
optimum re-ordering procedures. 
8.2.3  Weekly totals of all salt quantities delivered, transferred or issued as
treatments will be collated for each storage location and e-mailed to HQ for
central collation from 09:00hrs each Friday. 
8.2.4  Requests for additional salt will be included in these weekly e-mails and
calling forward of orders will be co-ordinated centrally through the Roads
Procurement process, with the supply contractor to provide the most efficient
means of optimising stock levels. 
8.3  Use of Salt and Salt / Abrasive Mixtures 
8.3.1  Preservation of salt or other de-icing materials for use where they are most
effective should be a consideration when formulating a treatment plan.
Service resilience must be taken into consideration at all times. 
8.3.2  All routes will be pre-treated with pure rock salt, as the most effective method
of preventing freezing of wet surfaces or melting of previously formed ice.
However on predominantly rural routes affected by snow, grit may be added
at 1:1 salt/grit mix to aid traction and break up compacted layers. In severe
conditions or when supplies are restricted, pure Sand / Grit will be employed
to preserve de-icing stocks. 
In wholly urban areas, salt only should be applied to the carriageway at all
times. Salt should be spread at the designated spread rates as determined by
the Duty Manager. 
8.3.3  The grading of salt and grit for mixtures shall be such that 100% will pass a
6.3mm sieve but less than 1% passing a 2mm sieve. 
8.3.4  Grit bins should be filled with a 3:1 grit/salt mix, initially at the start of the
season. Continued replenishment in times of persisting hazard will be purely
of Sand / Grit to preserve de-icing materials and only when resources permit. 
8.3.5  Provision of Salt to other departments of the Council or other Contractors will
be restricted to maintain the resilience of the Roads and Footways Winter
Service within the terms of the Salt Preservation Protocol. 
8.4  Calibration and control of Salt Rates of Spread 
8.4.1  The Operations Manager will ensure, through the Fleet Manager that all
spreaders, permanent and demountable, are maintained in such a manner as
to optimise the salt feed and regular checks of the calibration shall be carried
out. Records of all tests and alterations to the calibration shall be maintained
for inspection. 
Page 32

Page 33

8.4.2  All spreaders shall have limiting devices fitted such that spread rates cannot
exceed 60g/m². The device may be fitted in such a manner as to allow it to be
temporarily disconnected to assist the clearance of blockages. 
8.5  Grit Bins and Grit Heaps 
8.5.1  Grit heaps and grit bins are normally placed on routes not included on the
Priority 1 – 3 pre-treatment network, or on sections of these routes where
additional self help facilities are considered advantageous. They are provided
to allow the public to use the salt/grit mix to treat localised hazards on
carriageways and footways on the public adopted network. 
8.5.2  Grit heaps will be situated on rural road verges predominantly on bends,
junctions or steep sections. They shall be placed at distances which provide a
reasonable volume of material over the extent of any problem area as, if
material has to be carried too far, it is unlikely to be used. Consideration will
be given to the environmental impact associated with tree roots, hedges and
watercourses. 
8.5.3  Grit Bins will normally be situated in urban areas or where leaching from grit
heaps in rural areas is likely to have an environmental impact. They are
placed similarly to rural grit heaps to provide an additional self help facility in
streets such as at bends, junctions, steep sections of carriageway or footway
or close to schools and other public buildings where delays in planned
treatments may result in persisting hazards. Care must be taken in locating
bins to avoid impeding sight impaired pedestrians or access to public utilities
or roads authority apparatus. Generally where practicable, grit bin sites will
allow material to be carried downhill to treat sections of the public network 
8.5.4  Replenishment of material to grit heaps or bins will be carried out as regularly
as conditions of use require, within the confines of available resources. Sites
in regular use may require more frequent visits and the mix of material may
vary as operational resources and stocks of available materials permit. This
may depend on the overall salt resilience capability of the Council in times of
prolonged severe weather conditions. 
8.5.5  Requests for the locating of additional grit heaps or grit bins in urban areas
will be considered using the following criteria. 
• Is the request relevant to the Council asset of adopted roads and footway
network?
• Is there a genuine need for an additional facility, based on local
knowledge, the type of hazard of concern and any accident history? The
criteria for locations in 8.5.2 & 3 above will apply.
• The proximity of similar facilities will be considered, as provision of bins
and heaps often leads to further requests in similar locations.
• The overall volume of bins and heaps will have an impact on the ability to
provide an effective replenishment operation. 
Page 33

Page 34

8.5.6  A register of grit bins shall be maintained by the Network and Standards
Manager and their location and suitability will be reviewed annually. Grit bins
will be serviced and all debris and litter removed prior to the start of the winter
season. Initial replenishment of heaps and bins will be carried out prior to the
start of the formal standby period, where practicable. 
9.0  PLANT RESOURCES AND SERVICING PRACTICES 
9.1  All winter maintenance plant will be serviced, overhauled and made ready for
use, at least two weeks before the designated start of the winter period. All
servicing and maintenance of specialist winter maintenance plant will be the
responsibility of the Operations Manager. The Council’s Fleet Services
section, maintain all plant and equipment for the user departments. The Fleet
Manager will inform the Operations Manager of any deterioration in the
effectiveness of any items of Winter Maintenance Plant. 
9.2  Any short fall in resources caused by the removal of plant from service, during
the winter period, should be reported to the Operations Manager by the Duty
Supervisor. The Operations Manager will then seek ways to address the
problem. Where additional fleet vehicles are available, these will be prepared
as back-up units, either in advance of operations or as soon as practicable
whenever a shortfall in vehicles arises. 
9.3  The Operations Manager will ensure that all major items of plant are made
operational by the start of the standby period. A programme of trial runs will
be drawn up, to allow all items of plant to be tested and have all their
accessories fitted to ensure readiness for the winter period. The trial runs will
be carried out on a depot by depot basis during normal working hours. 
10.0  WEATHER FORECASTING AND MONITORING 
10.1  MetDesk Ltd. Hale Court, Hale Road, Wendover, have been contracted
through the West of Scotland Local Authority Weather Service Contract, to
provide the road forecast for the period 1st October to 15th May each winter
period. Access to forecast information will be gained via the local area
networks at Council offices during office hours, or by a broadband router link
from Duty Manager’s homes. Information is available on a bespoke website
for weather information and partially backed up by e-mail. 
10.2  The contract with MetDesk Ltd provides for a twenty-four hours consultancy
arrangement. Forecasters are available throughout the winter period by
telephone, to discuss weather matters and clarify details with department
staff. 
10.3  The text forecast is augmented by other services as necessary, including the
use of RADAR and satellite images to study precipitation patterns. There are
fourteen Road Sensor stations, owned by the Council and maintained by
MetDesk’s partner Vaisala Ltd, giving atmospheric and surface conditions,
situated throughout the Argyll and Bute road network. 
Page 34

Page 35

11.0  OPERATIONAL COMMUNICATIONS 
11.1  Vehicle / Duty Supervisor / Depot Communications 
11.1.1 Winter maintenance vehicles are provided with a cellular telephone, such that
contact may be maintained with the Duty Supervisor or depot at all times.
When it is considered safe to do so, manning of vehicles fitted with effective
communications facilities, will be limited to the driver only. 
11.1.2 The fleet of 32nr frontline, route specifically allocated and other back-up,
winter maintenance vehicles are fitted with satellite tracking and data-
logging equipment, provided by UK telematics Ltd. Vehicles can be monitored
through web access in real time during operations and their actions are
recorded and archived for future reference. One other private contractor
owned vehicle is employed on pre-treatment operations on the Isle of Jura
where in-house resources are limited. 
11.1.3 Throughout the period of winter standby, the Operations Manager will ensure
that staff are available to receive calls from the Police and other appropriate
agencies. Call out rotas will be provided to the Operations Manager, adjacent
authorities, management agents and the Police. 
11.2  Communications with Police Scotland, Roads Policing Section 
11.2.1 It is important that the strong partnership, formed with the Police, is
maintained. Information relating to severe weather conditions will be
communicated to the Police at the earliest possible opportunity. The Duty
Manager will consult fully with the Police when it becomes necessary to
arrange road closures and when there is a need to move abandoned vehicles. 
11.2.2 The “out of hours” emergency rota will be issued to the Police by the
Operations Manager. This will be confirmed to the Police Area Control Room
at Helen Street, Glasgow on the Friday start to each weekly duty shift. 
11.2.3 The Duty Manager will arrange for the daily action plan to be e-mailed to the
four main local Police offices each day. This will also include a confirmation of
the Area Supervisors’ and Duty Manager’s out of hours contact telephone
numbers. 
11.2.4 The Duty Manager will take due regard of all reports received from the Police,
concerning dangerous road conditions and give consideration to them, in line
with the Council Policy, in deciding the action to be taken. 
11.3 Communications with other Agencies and Motoring Organisations 
11.3.1 BEAR Scotland, the North West Trunk Roads term contract operator will be
sent the daily action plan and out of hours contact information, each day
throughout the winter period. 
Page 35

Page 36

11.3.2 The Duty Manager will inform Glasgow City Council ; Roads and Lighting
Faults Call Centre , R.A.L.F. , of the out of  hours contact numbers for  the
following weeks shift and any amendments necessary thereafter. Contacts
with Scottish Fire and Rescue Service and Scottish Ambulance Service,
control rooms are included in this transmittal process. 
11.3.3 The Winter Manager will inform Traffic Scotland when severe weather
conditions are causing delays to traffic movement. 
11.4 Communications with the Public 
11.4.1 The Winter Manager will post details of the 24hour winter treatment plan each
day no later than 1400hrs on the winter maintenance page of the council
website. 
11.4.2 Enquiries from the public will normally be dealt with by the Customer Access
Centre during normal working hours. 
11.4.3 Consideration will be given to the placing of warning signs, alerting drivers to
the possibility that road surface hazards may develop outwith treatment times
will be placed at the interface of Priority 1 to Priority 2 & 3 routes 
11.4.4 Pre-treatment routes booklets and the updated interactive map is published
on the Council Website. Leaflets explaining the extent of treatment routes,
their priority and hours of operation and other seasonal advice for travellers,
will be prepared and where necessary updated, in advance of each season.
These will be distributed by electronic means through the Council webpage
and are available for the public to download and print off as necessary. 
11.4.5 The Winter Manager will ensure that any disruption to the network is reported
through the internal service disruption noticeboard on the council website. 
11.5 Media 
11.5.1 National radio, television and national press enquiries should be dealt with by
the Executive Director or the Head of Service or through the Council’s Press
and Media Relations Office. 
11.5.2 Local radio and press should be dealt with by the Head of Service or by the
Operations or Network & Standards Manager. 
11.5.3 The Head of Service, Operations or Network & Standards Manager will be
advised as soon as practicable if conditions deteriorate such that major routes
have to be closed. 
12.0  INSTRUCTION AND RECORD KEEPING 
12.1  The management of the Instruction, Recording and Archiving of daily winter
Action plans is automated, by use of a bespoke winter maintenance
management tool provided by Vaisala Ltd. This includes an electronic diary
Page 36

Page 37

record of the Winter Managers’ decision making and monitoring process of
the daily treatment plan. 
12.2 Vaisala – Road DSS Manager is the web based system which allows access
by managers and supervisors simultaneously, to post instructions and record
actual activities on each specific pre-treatment route as operations progress.
Details will include some or all of the following:- 
a) Details of the routes treated
b) The start and completion of treatment on a specific route
c) Type of treatment carried out
d) Vehicle Registration number, Driver and other operator details
e) Quantity of materials used
f) The prevailing weather conditions
g) Any contacts by Police regarding reactive requirements
h) Details of any plant breakdowns, accidents or incidents
i) Any other problems 
12.3  In parallel to the above recording system, vehicle activities are recorded on
the “UK telematics ” - vehicle tracking system. Reports and map based
graphical records can be run to confirm and clarify in more detail, the
recorded activities. 
12.4 All records are archived in separate remote servers and can be retrieved
through web access by any authorised user, at any time after a plan has been
completed. 
12.5 Additional records of all telephone calls related to winter operations are kept
by all duty supervisors and managers. These are completed at the end of
each shift, collated and retained for future reference. 
Page 37

Page 38

This page is intentionally left blank

Page 39

APPENDIX 2 -  Salt Use Reduction and Preservation of Stocks Protocol. 
Argyll and Bute Council WINTER SERVICE – OPERATIONS 2025 - 2026     
Protocols for the reduction in use of salt and preservation of remaining stocks. 
Storage Capacity, Stock Transfers and replenishment times 
Storage capacity in all 15 “Operational” salt stores has been increased by 3,500tonnes to
approximately 14,000tonnes, since 2009, through phase 1 of the covered tunnel construction
programme. The 3,000tonne plus capacity Dome in Helensburgh, although an operational store,
has an element of strategic storage. 
For national salt resilience purposes, daily usage is calculated on 2 Priority WRC1-3 network
treatments and one WRC4 “other routes” treatment in each 24hr period. 
This equates to 370 tonnes/day at normal use levels, 600 tonnes/day for heavy snow. 
The West of Scotland Co-ordination Group, Roads sub-group agreed that Roads Authorities should
achieve a minimum storage capacity of equivalent to 70% of the average total salt usage of the last
three severe winters. This equates to a minimum 9,949 tonnes for Argyll and Bute for 2025. 
The target tonnage for the start of each season, 1st November may vary, as replenishment of some
stores are related to shipping capacity and availability, however a minimum 11,000tonnes is
considered reasonable. This equates to 28 continuous days supply at Winter Policy treatment
levels. 
As the national salt supply contract has an allowance of 21days to fulfil delivery from point of order,
the minimum resilience required in normal conditions equates to four weeks operations or
approximately 60% of the new capacity, at 10,000tonnes. In practice, reduced quantities of
6,000tonnes before replenishment are acceptable. This equates to a resilience of 16 days
operations, at normal treatment levels. 
Within this total quantity, material may require to be moved between stores to preserve a degree of
individual resilience in each of the operational stockpiles around the network. Internal transfers
between stores ensure adequate stocks are available as much as practicable to maintain a
consistent treatment regime throughout the network. In this way the hierarchy of route treatments
can be preserved as per the policy, for as long as practicable within any delivery shortage period. 
Operational Decision techniques to Manage Salt use. 
Winter Service Policy already recognises the need to preserve salt primarily for the prevention or
treatment of ice on higher speed carriageways. 3Grit:1Salt mixes are already utilised in Grit Heaps
and Bins and in the reactive treatment of footways. 
Salt preservation techniques can be instigated on carriageway treatments where forecasts or
conditions indicate that a mixture of salt and grit will provide the best treatment to aid traction. The
winter operations decision to use 50/50 mixes should only be for this purpose, rather than to
preserve supplies. In periods of falling snow, Grit only should be used on “return” ploughing legs
until such time as snowfall ceases and there is an expectation that salt will melt any residual snow
after ploughing. 
In settled constant dry conditions Residual Salt levels on carriageways allow the curtailment of
further treatments, as part of the daily operational plan. 
Page 39

Page 40

Reduction in Salt use in treatments, to preserve remaining stocks. 
Where salt stock levels reduce and replenishment activities are doubtful in either quantity or
timescale, the use of salt will be curtailed under the following procedures. 
Salt Preservation level  Circumstances    Authorised by. 
SP1  Total Operational Stocks reduce to 6,000tonnes  Winter Manager 
This level will be reached in conditions of reasonably prolonged hazardous conditions or where
extreme conditions reduce the effectiveness of salt. The supply chain for salt replenishment may
become of national importance and Transport Scotland and West of Scotland Co-Ordination Group
advice may be received. 
First Operation:- Activate replenishment from Strategic Stockpile at Helensburgh Dome
Depending on the likely delay in replenishment, part of the Strategic stockpile may be moved to
other operational stores. The quantity will be determined by the potential delivery date for shipping,
to replenish the Helensburgh store from King George 5th Dock Glasgow and other western
stockpiles, via Argyll ports. The transfer of each 1,000 tonnes of stock will provide a further 4 days
resilience within the operational stores, at normal use rates. 
Resilience:-  4 - 12days at normal use levels 375t/day : 2 - 6 days heavy snow 600t/day 
Second Operation:- Activate Salt Preservation Measures. 
Salt treatments will be reduced. Spread rates adjusted from 40g/m2 to 20g/m2, or 20g/m2 to
10g/m2. Further reductions in the salt content of all carriageway treatments will be achieved by
mixing Grit and Salt together, firstly at 1Grit:1Salt then 2Grit:1Salt. 
In extreme frosts where RSTs remain below -5C all day, and salt is considered to be ineffective,
additional treatments of pure Grit on all routes can be instructed to aid traction. Grit heaps, bins and
footway treatments will remain at 3grit:1Salt. 
Resilience:-  32days at reduced use SP1 = 188t/day : 20days heavy snow 
SP2  Total stocks reduce to 4,000tonnes    Head of Service 
Salting treatments will be curtailed to Priority 1&2 pre-treatment routes only (1233km – rev 2021) 
The SP1 salt mixing techniques will be used in all further SP levels. 
All other treatments will be of pure Grit including replenishment of grit bins / heaps. 
Resilience:- 25 days at reduced use SP2 = 156t/day : 15 days heavy snow 
SP3  Total Stocks reduce to 2,000tonnes    Executive Director 
Salting will be reduced to one treatment per 24hr forecast period, of the Priority 1&2 network,
usually 06:00hrs mornings, in advance of the majority of traffic movements. 
All other treatments will be of pure Grit including replenishment of grit bins / heaps 
Resilience:- 25 days at reduced use SP3 = 78t/day : 15 days heavy snow 
SP4  Total stocks reduce to 1,000tonnes    Chief Executive 
Salting reduced to Priority 1 and Priority 2 “A” class routes only 06:00hrs. (492km) 
All other roads and mobilisation times, Grit only. 
Resilience:- 32 days at reduced use SP4 = 31t/day : 20 days heavy snow 
SP5  Total Stocks reduce to 700 tonnes    Chief Executive 
Effectively 2 days resilience at original policy normal use. The trigger point for application to
Scottish Executive Emergency Salt stockpile. Release of salt, allowing replenishment out with the
normal constraints of the national salt supply contract. 
Resilience:- 22 days at reduced use SP5 = 31t/day : 13 days heavy snow 
Total resilience: SP1 (2nd Op) > SP5 (end) = 68 days : 41 days heavy snow.
Page 40

Page 41

17 
Appendix 3 – Advisory signing, routes unsuitable in severe conditions 
In specific locations additional information and diversion signing will be erected to further
inform drivers of the hazardous conditions on some routes. This advises them of alternative
routes, where available resources will concentrate on maintaining treatments. There are
four roads where signing to indicate specific alternative routes are available. 
1 A817 “Haul Rd” , Lomond.
Snow gates at A82 and A814 “central” roundabout
Diversion via A818 Arden - A814 Garelochead 
2 C46 Glen Aros / Glenbellart road , Mull
Signs at Aros Bridge and Dervaig Primary School
Diversion via A848Tobermory 
3 C9 Glenfinart Road ( The Larach) , Cowal
Signs at Whistlefield Hotel and Sligrachan Bus turning head;
Diversion via A880 Cot House 
4 C11 Otter Hill road ( Bealach an Drain) , Cowal
Signs at Glendaruel A886 and Otter Ferry B8000;
Diversion via A8003 Tighnabruich and Kames. 
Example of typical information sign 
Sign on permanent display during
Winter Season. 
.
Road Closure in conjunction
with temporary signs when
conditions dictate. 
ROAD
CLOSED
AHEAD
ROAD
CLOSED      
Alternative
route
avoiding
hazardous
conditions 
Page 41

Page 42

This page is intentionally left blank

Page 43

APPENDIX 4 -   FRONTLINE TREATMENT VEHILCE FLEET 2025 – 2026     
2025 - 2026 WINTER POLICY , PRE-TREATMENT ROUTES
(Hired Fleet Contract - 1 Year extension  2025-26) HIRED FLEET -  18T GVM -   6cu.m.  PMGs  1 year extension 2025-26 1 Year Ext  @
HIRED FLEET -  26T GVM  -  9cu.m   PMGs 1 year extension  2025-26 1 Year Ext  @
Policy and Pre-Treatment Routes 32 Council pre-treatment routes , IN-HOUSE FLEET -  QCB units  -  18tGVM  c/w  6cu.m demountable hopper/spreader
31 Frontline Vehicles plus 1 S/C with vehicle rev Sept 23 IN-HOUSE FLEET -  Multispreads   -   12t / 7.5 t   GVM - built-in auger and spreader
remeasured
DRAFT WINTER FLEET ALLOCATION  -   29th July 2025 V VEHILE REGISTRATIONS / DESIGNATION
District START DEPOT/ SALT STORE code Pre-treatment route Description tonnes
cu.m
Vehicle Make Reg No. Vehicle Model      c/w Straight offset Plough blade Gritter
Capacity
BUTE Rothesay - Union St B 1 A886 Rubodach and Bute rural 5.64 4.34 DAF - LF260 FA SJ21 LVM Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
Rothesay - Union St B 2  Rothesay town & Bus routes 4.00 3.08 DAF - LF230 FA SJ21 LVO 7.5t ECON Multispread -  demountable spinner 1.5cu.m.
COWAL Dunoon - Victoria Rd C 1 Dunoon A886/A815 to A83 Junction (Cairndow) 6.17 4.75 Merc 2635 ## YK 72 JYJ AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
Dunoon - Victoria Rd C 2 A815 Dunoon - Toward ( & Loch Striven ;  POL depot) 3.08 2.37 DAF - LF260 FA SJ21 LVL Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
Dunoon - Victoria Rd C 3 Dunoon streets 1.43 1.10 DAF - LF230 FA SJ21 LWG 12t ECON Multispread -  demountable spinner 3.5cu.m.
Dunoon - Victoria Rd C 4 A886 Colintraive - Strachur & B836 Glen Lean 5.86 4.51 Merc 2635 YK 72 JYH AROCS 6x4  - ECON spreader PMG -  C/W Plough 9 cu.m.
Re-loading point Lettermay C 5 C1follow-on##  B839/B828-Lochgoilhead,Carrick&Strachur 0.87 0.67 Merc 2635  ## YK 72 JYJ AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
Dunoon - Victoria Rd  - S/C C 6 A8003 Tighnabruich and Portavadie Ferry 4.39 3.38 Merc 1827A WU74 BE AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Dunoon - Victoria Rd C 7 A880 Ardentinny 2.48 1.91 DAF LF260-FA SJ 72 GYW Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
LOMOND Helensburgh - Blackhill H 1 A818 - A817 - A814 South  to  Glen Mallon Jetty  6.44 4.95 Merc 2635 YK 72 JYF AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
Helensburgh - Blackhill H 2 B833 Peninsula & A814 North - Arrochar/Succoth/Luss 4.66 3.58 Merc 2635 YK 72 JYE AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
Helensburgh - Blackhill H 3 Helensburgh West & Rhu 2.91 2.24 DAF - LF230 FA SJ21 LVT 7.5t ECON Multispread -  demountable spinner 1.5cu.m.
Helensburgh - Blackhill H 4 East Helensburgh & Cardross   3.08 2.37 DAF - LF260 FA SJ21 LVN Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
ISLAY Bowmore - Springbank I 1 A846 & B8016 Bridgend - Port Ellen (High & Low Roads) 5.15 3.96 Merc 1827A WU74 BVD AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Bowmore - Springbank I 2 A846 Pt Askaig & A847 Portnahaven 4.18 3.22 DAF - LF260 FA SJ21 LWU Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
KINTYRE Machrihanish  Depot K 1 B842 Carradale & Campbeltown Streets 3.92 3.02 Merc 1827A WU74 BVF AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Machrihanish  Depot K 2 B842/B843 Campeltown - Southend & Machrihanish 3.32 2.55 DAF - LF260 FA SJ21 LWR Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
Machrihanish  Depot K 3 B8001 Redhouse  - Skipness    via Glenbarr & Tayinloan 2.32 1.78 Merc 1827A WU74 BVM AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
LORN East Dalmally Depot L 1 A819 Dalmally - Inveraray 3.02 2.32 Merc 2635 YK 71 JXL  AROCS 6x4  - ECON spreader PMG  - C/W Plough 9 cu.m.
Oban - Jackson's Quarry L 2  B845 Kilchrennan - C29 Dalavich 4.84 3.72 Merc 1827A WU74 BVL AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
LORN West Oban - Jackson's Quarry L 3  A816 Oban - Ardfern  inc Village 3.38 2.60 Merc 2635 YK 72 JYC AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
Oban - Jackson's Quarry L 4 B844 Easdale & Cuan 1.72 1.32 DAF - LF260 FA SJ21 LWW Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
Oban - Jackson's Quarry L 5  C27 Port Appin - B845 Bonawe 2.72 2.09 DAF - LF260 FA SJ21 LYH Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
Oban - Jackson's Quarry L 6  Oban streets 2.02 1.55 DAF - LF230 FA SJ21 LWV 12t ECON Multispread -  demountable spinner 3.5cu.m.
Oban - Jackson's Quarry L 7 Lorn Arc Bus routes 1.19 0.92 DAF - LF230 FA SJ21 LYO 12t ECON Multispread -  demountable spinner 3.5cu.m.
MidARGYLL Lochgilphead-Monydrain MA 1 A816 Lochgilphead - Ardfern & B840 to Ford 3.57 2.75 Merc 3333k YK 72 JYO AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
Lochgilphead-Monydrain MA 2 B841 Acnamara - B8025 Tayvallich 2.58 1.98 Merc 1827A WU74 BVJ AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Lochgilphead-Monydrain MA 3 B8024 Kilberry Loop 3.32 2.55 Merc 1827A WU74 BVK AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Lochgilphead-Monydrain MA 4 Lochgilpead /Ardrishaig/Tarbert Streets 1.22 0.94 DAF - LF260 FA SJ21 LWT Econ - QCB  c/w  6cu.m  ZERO C  Demountable Spreader 6 cu.m.
MULL Tobermory -Baliscate MU 1 A848/A849 Tobermory - Craignure 3.42 2.63 Merc 1827A WU74 BVH AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Tobermory -Baliscate MU 2 Tobermory - Dervaig 2.68 2.06 Merc 1827A WU74 BVG AROCS 4x4 - ECON spreader PMG  - C/W Plough 6 cu.m.
Pennygowan Depot MU 3 A849 Craignure - Kinloch - Fionnphort 5.74 4.42 Merc 2635 YK 72 JYB AROCS 6x4  - ECON spreader PMG - C/W Plough 9 cu.m.
JURA Craighouse Depot(MBC - S/C) J 1 A846 Feolin - Ardlussa   - Jura Sub-contractor vehicles   2.44 1.88 Merc  1318 OU 55 GCY Mercedes Atego 1318 PMG  -  M Boyle S/C 6 cu.m.
Kintyre/Mid-Argyll/Lorn SPARE WEST ( based in Lochgilphead)   -   A819  1:2    pm FLH240 - Chassis Only SF 14 JKX Gully Vehicle - Demountable Gritter 6 cu.m.
Lorm/Mid-Argyll / Cowal SPARE WEST ( based in OBAN) - DAF LF260-FA SJ 72 GYS Gully Vehicle - Demountable Gritter 6 cu.m.
Lomond / Cowal SPARE EAST ( based in Helensburgh) FLH240 - Chassis Only SF 14 JKV Gully Vehicle - Demountable Gritter 6 cu.m.
full mobilisation run
tonnes  at 20g/m2
113.76
Page 43

Page 44

This page is intentionally left blank

Page 45

APPENDIX 5    -   Salt Stock recording and resilience reporting. 
ARGYLL & BUTE COUNCIL WINTER MAINTENANCE OPERATIONS  2025 - 26
SALT STOCK SUMMARY SHEET 09:00hrs on
All quantities in TONNES ROADS OPERATIONS  UNIT    Resilience
TOTAL SALT TONNAGE IN OPERATIONAL DEPOTS AT DATE 7914 21.4 days
OPERATIONAL USAGE 12:00hrs 09:00hrs
Salt quantity used from
( includes  Grit
bins & heaps) 0 tonnes
SALT STORES "IN STOCK" RECORDS CONFIRMED AND ADJUSTED START TOTALS
LOMOND Helensburgh BLACKHILL 2277 Lomond  TOTAL 2277 39.9 days
(Including EAST Strategic capability)
BUTE   & Rothesay - UNION ST 174 Bute TOTAL 174 7.9 days
COWAL Dunoon - VICTORIA RD. 493
MILLHOUSE (re-load only) 100
GLENDARUEL (re-load only) 34
Lochgoilhead- Lettermay  (re-load only tbc) 0 Cowal  TOTAL 627 9.8 days
MID-ARGYLL, Lochgilphead - MONYDRAIN 842
KINTYRE Campbeltown - MACHRIHANISH      946 M-A,K  TOTAL 1788 19.9 days
& ISLANDS Islay  - SPRINGBANK 386
Jura - CRAIGHOUSE 17 Islands  TOTAL 403 10.3 days
OBAN, Oban - JACKSON'S QUARRY 1287
LORN DALMALLY 273 Lorn  TOTAL 1560 25.2 days
and the    Mull  -   PENNYGOWAN 688
ISLES Tobermory  - BALISCATE 397
KINLOCH (re-load only) 0 Mull  TOTAL 1085 30.1 days
STRATEGIC STOCKPILE CONNEL 0  Additional resilience available 0.0 days
Original location unavailable .  New site to be obtained
TOTAL TONNAGE - ALL SALT  AVAILABLE 7914  Tonnes TOTAL RESILIENCE 21.4 days
TONNES Delivered to depots this week
ORDERS PLACED  DATE EXPECTED LOCATIONS ( To be called fwd as req)
IRISH SALT MINING AND EXPLORATION  - Kilroot, NI   ex KG5 by Road , or direct to Ports
1000 tonnes by Road
1000 tonnes by Road
300 tonnes by Road
600 tonnes by Road
600 tonnes by Road
Rothesay - Union St
October / November Shared boat - Islay
October / November Shared Boat - Oban ( BEAR )
October / November Dunoon - Vic Rd / Cowal W
October / November
28 July 2025 Operational
October / November Helensburgh Dome
Page 45

Page 46

This page is intentionally left blank

Page 47

Appendix   6
Season 2024-25 Weather Summary
OCTOBER 2024
Mild conditions, initially with prolonged spells of rain still making their way in from the
Atlantic, but a switch to a more northerly air flows on the 9th brought colder Arctic air
into the UK. On Oct 9th, RSTs dropped down to Minus 1.4C Salachray , Minus 1.2C
Leanach and Minus 1.1C Blaran on dry surfaces. A little less cold on the 10th with
the return of rain, but drier and clearer conditions overnight saw RSTs dip close to
zero more locally. Whilst the 11th and 12th were mild and wet once more, clearer
skies on the night of the 12th saw RSTs falling below zero again with Minus 1.4C
Salachray and a range Minus 0.9C – 0.5C for Mid-Argyll and Lorn sensors. The
following week was unsettled, with areas of low pressure pushing in from the Atlantic
resulting in prolonged spells of rain and blustery winds. The 15th began dry, however
that quickly changed as the overnight period saw heavy downpours, some thundery
and persisted through to Wednesday 16th. It became drier on the 17th as frequent
showers fed in from the west. Further bouts of rain pushed in from the Atlantic on the
18th/19th but on the 20th, the first named storm of the season – Storm Ashley –
brought very strong winds gusting 60- 70mph during the day. Not only was it very
windy, but torrential downpours swept in from the west too. This affected North Argyll
mainly, with coastal flooding in Oban and Tobermory and tide bourn debris affecting
the Slate Islands of Easdale and Luing. Many watercourses were affected by strong
flows for a time but nothing as significant as Oct. 2023.  The 21st saw drier and less
blustery conditions, albeit with showers feeding in from the west. It was a mild week,
and RSTs remained above zero. The 22nd saw sunny spells and showers, with
these showers feeding in on brisk westerly winds. Further showers and longer spells
of rain moved in from the Atlantic over the next few days with RSTs remaining well
above zero. Whilst most of the rain was on the lighter side, a heavier band of rain
pushed in from the west on the 26th, with clearing skies and colder conditions
following in from behind. High pressure settled in for the rest of the period with
cloudy skies and a lot of light rain and drizzle around through to Nov 1st. 
NOVEMBER 2024
The start of official winter standby was subject to autumnal conditions for the first
week with rain of varying intensity and duration as weather fronts in mild southerly
air, passed over Argyll. Minimum overnight RSTs remained in the range Plus 5C to
10C through to 16th , with a slight dip neared to zero on 11th.  A change in air flow
on 17th allowed RSTs and Air to fall sub-zero overnight, with precipitation turning
more wintry in nature. Widespread frosts and light snow affected the area , with
RSTs Minus 6C to Minus 1 C through to 20th. Continuous subzero periods
developed with the highest RST at Leanach at 13:00hrs on 18th recorded as Minus
2C before dropping again overnight, with the lowest overnight RST of the season so
far, Minus 8.2C recoded at Leanach at 03:00hrs on 20th. Leanach and Blaran
Page 47

Page 48

sensors recorded continuous 24hr sub-zero RSTs respectively on 20th &21st and
19th & 22nd. Sleet and Snow fall, of varying intensity continued throughout this
period, with the deeper accumulations on higher, inland routes. Named Storm Bert
passed over the area between 22nd – 25th with maximum wind gusts of 73.2mph
recorded at Ballygrant on 23rd and 74.5mph at Dervaig on 24th, before a further
drop in RSTs, partially on 27th and 29th, with all sensors subzero RSTs early on
28th, in the range Minus 3.3C Ballygrant to Minus 7.2C Leanach . Named Storm
Conall passed through southern England on 27th but there was little effect in Argyll,
with the month ending in a dramatic increase in overnight minimum RSTs, from
Minus 7.2C on 28th to Plus 6.8C by 30th, as rain returned as the prevailing weather
condition. 
DECEMBER 2024
The mild conditions continued into December, with overnight minimum RSTs Plus 8
to 11 Deg C with rain heavy at times overnight into 2nd. Conditions changed in
northerly air streams with marginal positive RSTs before developing in the range
Minus 4.6Deg C Leanach to Minus 0.9C Dervaig on morning of 3rd  with more sub-
zero RSTs on 4th  Minus 2.9C Accurrach to marginal Zero C  Island sensors . 
Intense rain overnight 4th – 5th  caused localised flooding in Bute, Cowal and
Lomond, with further marginal nights into 6th and 7th before the arrival of named
Storm Darrah. The storm centre passed over central England with limited effect as
far north as Argyll. Kintyre and Lomond experienced intense but localised rain, with
watercourses overtopping and drainage systems surcharging early on Saturday 7th,
with resultant partial wash-out of two bridge foundations on B842 Campbeltown –
Carradale. Snow farther north in Argyll was light, short in duration and confined to
higher level sections of the network. Heavy frosts developed over the following
nights, with RSTs Minus 6.5C Leanach, Minus 6.1C Blaran and Minus 5.9C
Salachray through to Minus 2.7C Lochdonhead, by 06:00hrs Monday 9th  with
continuous 24hr sub-zero on many inland sensors through to Tuesday 10th , with the
“mildest” RST at Salachray at 12:00hrs Mon 9th of Minus 3.5C before dipping again
to Minus 7.3C early on Tuesday. Cloud cover allowed most sensors to partially
recover by sunrise, however many places remained sub-zero in shaded sections
with persisting hazards, even after repeat treatments. RSTs again stayed sub-zero
over the next 24hrs at some locations with Leanach Minus 7.9C at 05:00hrs,
Accurrach Minus 6.5C 02:00hrs on 11th with sensors south and east Minus 5.9 to
Minus 3.6C around 22:00hrs on 10th before improving towards dawn. Island sensors
stayed positive RST minimum Plus 1.8C to 3.8C. as cloud and fog conditions
developed early morning. The gradual Eastward drift in improvements in overnight
minimum RSTs continued into 12th , with only central mainland sensors sub-zero ,
Salachray Minus 1C, Haul Rd Minus 2.4C, Accurrach Minus 5.2C and Leanach
Minus 6.7C, although in some areas minimum air temperatures were marginally
lower in fog. By the morning of 13th only Accurrach and Leanach had gone
marginally sub-zero RSTs overnight, as weather fronts moved in from the North
Page 48

Page 49

West. The forecasts did however, continue to indicate long periods overnight where
sub-zero RSTs and Air were possible, mainly in the northern mainland domains. Mild
and wet conditions prevailed 14th – 17th , showers or longer spells of rain, as
weather fronts passed over the area, in generally southerly airflows.  RSTs improved
From Plus 3 to 6 C on 15th to Plus 7 to 9C on 16th / 17th. Heavy rain through central
Argyll recorded 24hrs totals of 30-32mm by the morning of 18th , with strong winds
overnight, resulting in a maximum gust of 66mph recorded at Dervaig at 04:10hrs. 
There was a brief change to Northerly airflow 18th- 19th, which allowed RSTs to drop
sub-zero and showers turn more wintry early morning, with marginal RSTs Minus
1.1C Haul Rd , Minus 0.9C Leanach. This trend continued on 20th with sub-zero
RSTs confined to central sensor sites  Minus 1.9C Leanach to Minus 0.3C Cnoc an
Rath. Milder conditions prevailed as the next warm from passed over on 21st
accompanied by strong winds, gusts of 70mph recorded at Dervaig 12:00hrs , before
the last subzero RSTs of the year Minus2.5C morning of 22nd and Minus 2C on the
morning of 23rd Dec. although generally conditions were wet and mild for the time of
year. The Christmas week through to the end of the month saw RSTs drop no lower
than Plus 3C and generally in the range Plus 5 to 9C. High winds returned from 27th
with gusts of 74.3mph recorded at Derail 06:00hrs on 29th. This resulted in several
incidents of fallen trees affecting routes , where waterlogged roots allowed
overturning. 
JANUARY 2025
The start of the New Year heralded the end of the mild and wet conditions of the
previous two weeks, Minium RSTs by 08:00hrs on 1st were marginal Plus 0.1Deg C
at Accurrach to Plus 4.1 C at Ballygrant which changed over the following 24hrs with
Mininum RSTs Minus 6.6C at Leanach to Minus 2.4C Lochdonhead. Overnight
temperatures fluctuated for the next three days with minimum RSTs between Minus
3.6C and Minus 7C with milder conditions in intermittent clear spells early
afternoons. A more widespread frost developed from Sunday 5th into Monday 6th
January, with clear sunny conditions during the day and open skies overnight
generally, with isolated showers. A widespread frost developed into Tue 7th but cloud
cover and intermittent wintry showers allowed temperatures to fluctuate. Light snow
overnight and a hard frost on Wed 8th resulted in RSTs of Minus 7.1C Leanach ,
Minus 5.8C Salachray , Minus 5.4C Haul Road through to Minus 1.6C Dervaig , with
this sensor being the only one to retain a positive air temperature overnight, in
generally northerly air flows with any showers confined mainly to western coastal
areas and outer islands. All sensors dropped sub-zero by 17:00hrs, minimum RSTs
of Minus 9.2 C Leanach at 08:00hrs Thu 9th with near continuous subzero for next
24hrs through to the coldest recorded RSTs of the season so far, on Friday 10th ,
Minus 10.2C Leanach and Minus 8.0C Accurrach at 08:00hrs , with Blaran Minus 9C
at 03:00hrs and Haul Road Minus 7.4C at 05:00hhrs  before slight recovery. Sat 11th
saw the start of a change, with cloud developing and minimum RSTs of Minus 7.4C
Accurrach , Minus 7.0C Blaran and  Minus 5.9C Leanach as winds turned southerly
Page 49

Page 50

through to Sunday 12th with only localised sub-zero the previous evening and all
sensors marginal positive by 08:00hrs. Heavy rain affected the area, as a warm front
passed over Argyll bringing mild southerly airflows, with RSTs Plus 7C to 10C by
Monday 13th  08:00hrs. The following week was variable cloud and rain, before a
sunny day and clearer night in parts into Thu 16th, with sub-zero RSTs Central/North
sensors only, minimum Minus 0.3 to 1.1 C around 06:00hrs. The following week saw
variable amounts of cloud and precipitation, with positive minimum RSTs until 22nd,
Stewarton Minis 1.2C in a overnight clearance, with northern mainland domains
dropping to between Zero C and Minus 1C briefly on the mornings of on 23rd and
24th. However, the more significant event in this period was the passing of Named
Storm Eowyn over the area. High winds developed overnight into the early hours of
Friday 24th with maximum gusts recorded from mid-morning onwards at the more
exposed sites to the Westerly gales. Maximum Gusts recorded at Haul Rd-Lomond
69.1mph at 10:50hrs, Clachan Hill-Kintyre 81.0mph at 12:40hrs, Ballygrant-Islay
83.2mph at 11:40hrs, Stewarton-Kintyre 88.5mph at 12:20hrs, with the highest gust
recorded at Dervaig-Mull 98.2mph at 16:30hrs, Fri. 24th. before the main storm
centre passed East into central Scotland by afternoon and overnight allowing winds
to ease by Saturday 25th. Winds turned northerly with overnight RSTs dropping in
the range Zero C to Minus 3.8C from 25th through to 29th. The later season pattern
of RSTs dropping overnight to minimum temperatures around dawn, continued with a
low of Minus 4.5C at Leanach 08:20hrs on 30th, with all sensors subzero by early
morning. The last 2 days of the month were variable, with clear spells bringing sun
during the day and marginal frosty conditions overnigh, between bands of rain, as
weather fronts moved east over the area. Localised Minus 0.7C Leanach and Minus
0.2C Blaran on the morning of 31st before a final cold snap in northern mainland and
island domains, down to Minus 3.4C to Minus 1.1C up to mid-night , before all
sensors improved to positive RSTs by 06:00hrs Saturday Feb 1st. 
FEBRUARY 2025
The remnants of a cold snap on the evening of 31st Jan had dissipated by 06:00hrs
Sat 1st with a return to mild southerly airflows and frequent bands of showers
passing over the area. Clear spells during the afternoons of 1st and 2nd but
overnight RSTs remained positive but marginal, minimum Plus 1.4C to 1.6C evening,
before improving into Mon 3rd. Marginal 50mph+ gusts and heavy rain on Monday
and Tuesday led to clearer conditions , sunny periods by day and frosty nights as the
week progressed, with 50mph gusts recorded daily at Dervaig sensor. All sensors
were sub-zero into Friday 7th in the range, Minus 4.8C Leanach , Minus 4.6C
Accurrach, through to urban sensors Lochgilphead Minus 1.2C and Minus 0.6C
Helensburgh. The weather over the weekend and Monday 10th remained that of
generally clear skies with sunny periods by day and frosts overnight, with very little in
the way of precipitation. RSTs dropped within the range Minus 5.4C to Minus 4.7C
Blaran, Leanach and Accurrach to Minus 1C at other rural sites, before partially
recovering on 10th, Minium Minus 2.2C Blaran and Dervaig. Cloud cover over most
Page 50

Page 51

of the area on Tue 11th kept RSTs milder than previous days, a slight dip subzero
the previous evening at Northern censors, returned to positive RSTs all sites prior to
midnight, with air temperatures generally 2-3 Deg C milder. This pattern of marginal
conditions was repeated through to 16th, with only sensors in the north and central
mainland dipping marginally sub-zero Minus 1.6C to Minus 2.4C as the lowest RSTs
overnight.  There was a brief milder period overnight into 17th with only Leanach
dipping to minus 0.2C just before sunrise 08:00hrs. There were further dips in
overnight RSTs on 18th and 19th, with associated isolated wintry showers, before all
sensors showed an improvement, albeit associated with wet and windy weather.
Gusts of 63.1mph were recorded at Ballygrant, 70.0mph at Dervaig on the morning
of 21st. heavy rain on Friday gave way to a clearer spell Saturday 22nd before the
next weather system with heavy rain, most of the day Sunday 23rd. Wind direction
was southerly however, which resulted in very mild conditions overnight, air
temperatures closer to daytime averages for the time of year. The mild,
predominantly southerly, air flows continued through to 26th, minimum RSTs
overnight fluctuating between Plus 3.5C and 2.1C, with cloud cover and spells of
occasionally heavy rain throughout. On Wed 26th winds turned Northwesterly,
allowing a small dip in RSTs early morning, Leanach Minus 0.5C and Accurrach
Minus 0.1C around 04:00hrs before a clear sunny day, with occasional showers
which cleared late afternoon.  RSTs had reached double figures at some sites by
mid-afternoon in clear skies, allowing a sharp drop in temperatures overnight into
Thu 27th , with all sensors subzero by dawn.  RSTs ranged from Minus 3.7C
Leanach and Minus 3.4C Salachary , through to Minus 1 C Stewarton and Dervaig .
Sunny and clear conditions on Thu 27th allowed air and surface temperatures to
recover quickly. Showers developed in the afternoon , some sleety, before a further
clearing overnight into 28th allowed temperatures to drop again steadily towards
dawn , with minimum RSTs Minis 1.8C Cnoc-an-rath Bute ,Minus 1.6 C Salachary-
Mid-Argyll , Minus 1.3C Stewarton -Kintyre  and Minus 1.0C Leanach-Cowal and
Blaran -Lorn E. Cloud cover in the north allowed some sensors in towns and on Mull
to remain positive and the building cloud throughout the final day of the month,
although dry, resulted in milder conditions overnight into 1st March. 
MARCH 2025
A warm front with cloud and rain ushered in the last full month of the standby period
before clearing to sunny spells and a marginal drop in the north of the area in clear
skies overnight. Sensors at A886 Leanach , A816 Blaran , A819 Accurrach and A817
Haul Rd all dipped to between Plus 1C and Zero but only A816 Salachary recorded a
subzero RST, Minus 1.3C briefly at 06:00hrs Sun 2nd .  There them followed a mild
period from the night of 2nd through to 9th March. Weather conditions were a
mixture of clear sunny spells and periods of occasionally heavy rain, as weather
fronts passed over the area. Airflows were generally southerly and mild for the time
of year. Minimum overnight RSTs were fairly constant at Plus 3 or 4 Deg C mainly
centred around northern mainland sensor sites with other sensors one or two
Page 51

Page 52

degrees milder. The wind direction changed to turn progressively northerly, with
minimum RSTs before dawn on 10th March  Plus 1.5 DegC – Leanach , Plus 1.9C -
Stewarton and Haul Rd. Widespread frosty weather returned from Tuesday 11th
March , with RSTs dropping early morning to Minus 3.7C - Leanach , Minus 3.2C to
3.0C Salachray , Blaran , Accurrach through to Minus 0.7C Lochdonhead-Mull ,
before RSTs recovered in clear sunny conditions.  Variable cloud held temperatures
up slightly on 12th with minimum RSTs Minus 2.2C – Leanach through to Minus 0.2C
Accurrach , mainly in Northern inland areas before a further clearance overnight into
the morning of 13th allowed RSTs to drop again to Minus 4.6C Salachray, Minus
4.3C Blaran, Minus 4.2C Leanach through to Minus 1.2C Dervaig-Mull , with urban
sites Minus 1.2C Oban to Minus 0.4C Helensburgh. A minimum air temperature, just
before dawn on 13th , was recorded as Minus 4.8C at Salachray 07:00hrs. This
pattern of reduced freeze and then a return to Minus 4.5C under clear skies, was
repeated Fri 14th , Sat 15th and Sun 16th with a change in wind direction over the
weekend, with localised showers from time to time. This brought milder conditions,
than those forecast, with Minimum RSTs 07:00hrs on Monday 17th  Plus 2.5C
Accurrach to Plus 5.4C Dervaig. Cloud cover was variable over the next week, with
periods of rain between longer spells of clear skies. This brought sunny periods and
higher temperatures to road surfaces by day but allowed RSTs to steadily drop
overnight, to reach minimum temperatures in the period 05:00 to 09:00hrs daily
through to 20th. Minimum RSTs developed early morning through to dawn, northern
domains only on 18th Minus 2.2C – Accurrach to Minus 0.3C – Dervaig. This pattern
was repeated, in clearer air on the morning of 19th , Minus 2.9C-Leanach , Minus
2.8C-Accurrach through to Minus 0.2C-Dervaig and some urban sensors. A similar,
slightly milder pattern developed on the morning of 20th, Minus 2.4C-Leanach,
Blaran and Accurrach, with RSTs recovering from lows around 07:00hrs, after
sunrise. Precipitation was isolated and limited to small bands of rain passing over the
area in predominantly Easterly winds. Conditions changed from 21st, after the Spring
Equinox, with periods of more persistent rain and cloudy conditions in milder airflows
from the South and East. RSTs were significantly milder with overnight minima Plus
2.5C initially, climbing to Plus 5 to 6C, with a slight dip on the morning of 24th to
Minus 0.1C RST at Blaran. The clear skies allowed RSTs to recover, with highs
recorded at A817 Haul Rd PLUS 29.5C at 12:40hrs, Cnoc-an-Rath, Bute PLUS
30.2C at 13:30hrs. This trend towards milder Spring like conditions returned on the
morning of 25th with minimum overnight RSTs recorded as Plus 6.6C to 9.3C.
around 06:30hrs.  Weather fronts brough bands of rain and clear spells which gave
variable conditions up to the end of the month  Heavy and persistent rain arrived on
the Wednesday evening 26th and continued into Thursday 27th. Air temperatures
were marginal, approaching Zero Deg. C allowing Hail to develop in some showers
on Fri 28th between sunny intervals. The month ended with the start of a dry period,
due to the development of a high-pressure system over the country, with clear sunny
conditions by day on 31st with the start of lower overnight temperatures in clear
skies. 
Page 52

Page 53

APRIL
The “unseasonably” early spring weather continued into the final weeks of the
standby. A high-pressure system sat over the country and deflected southerly and
westerly winds and their associated weather fronts. Conditions were generally clear
and sunny throughout the day with clear skies overnight leading to sharp falls in
temperature. Minimum RSTs generally developed between 06:00-08:00hrs each
morning, before recovering after sun rise. RSTs were still marginal dropping to Plus 2
to 3 Deg C, generally on several nights in the first full week of April. The lack of
precipitation over the period allowed road surfaces to stay generally dry, with just
light dew fall and very limited seepage from verges after the dry period from the end
of March. Consequently, there was little risk of the formation of road surface hazards,
with none recorded at any weather sensors during the period. As the high-pressure
system moved away to the South East over Europe, over the weekend 12th /13th
this allowed south-westerly winds to bring weather fronts in off the Atlantic. The air
temperatures were still marginal in cloudier conditions with frequent bands of
showers passing over the area, including localised Hail showers on Sunday 13th in
the Mid-Argyll area. Sunny spells between showers continued through the final
week, towards the end of official Winter Standby mid-day on Thu 17th , change of
standby shift – start of Summer Standby arrangements. The overnight temperatures
continued to be marginal for the remainder of April, with Accurrach dropping briefly to
Minus 0.3Deg C RST at 06:20hrs on 17th   before the start of the Easter Holiday
weekend but as there had been no precipitation, surfaces were dry and hazard free.
Ballygrant sensor dropped to Plus 1.9Deg C on Tuesday 22nd but generally RSTs
improved in mixed cloud cover through to end of April , with minimum RSTs Plus 4 -
5 Deg C before improving to double figures for minimum overnight / early morning
temperatures by the end of the month. 
End of 2024-25 Weather Summary. 
Page 53

Page 54

This page is intentionally left blank

Page 55

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
ROADS & INFRASTRUCTURE SERVICES                    11 SEPTEMBER 2025 
PAVEMENT PARKING PROHIBITIONS – SERVICE PROCEDURE &
EXEMPTIONS 
1.0 EXECUTIVE SUMMARY
1.1 This report provides Members with an overview of the Pavement Parking
Prohibition, primarily focussed on footway parking. 
1.2 A service procedure has been produced which provides detail on the processes
to be followed at each stage; this is attached under Appendix 1.   
1.3 An application form has also been drafted to allow members of the public to
apply for an exemption.   
1.4 The report highlights some of the potential risks should an exemption be
approved. 
1.5 The report also proposes the committee reporting and approval process for
Exemption Orders as per the Council’s Constitution. 
RECOMMENDATIONS: 
The Environment, Development and Infrastructure Committee are asked to:- 
i. Approve the Service Procedure document attached under Appendix 1,
subject to any amendments the Committee wish to make.
ii. Approve the application form which requests an assessment, attached
under Appendix 2 and subject to style changes required for the website.
iii. Note that prior to the making of any Exemption Order, they will be
presented to the Environment, Development and Infrastructure
Committee for approval or otherwise.   
Page 55 Agenda Item 5

Page 56

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
ROADS & INFRASTRUCTURE SERVICES            11 SEPTEMBER 2025 
PAVEMENT PARKING PROHIBITIONS – SERVICE PROCEDURE &
EXEMPTIONS   
2.0 INTRODUCTION
2.1  This report provides Members with an overview of the Pavement Parking
Prohibition, primarily focusing on footway parking. A detailed service procedure
outlining the processes to be followed at each stage has been developed and is
attached as Appendix 1. Additionally, an application form has been drafted to
enable members of the public to apply for exemptions. The report also highlights
some potential risks associated with approving exemptions and notes the
committee reporting and approval process for exemption orders in accordance
with the Council’s Constitution.
3.0 RECOMMENDATIONS
3.1 The Environment, Development and Infrastructure Committee are asked to:- 
i. Approve the document attached under Appendix 1, subject to any
amendments the Committee wish to make.
ii. Approve the application form which requests an assessment, attached
under Appendix 2 and subject to style changes required for the website.
iii. Note that prior to the making of any Exemption Order, they will be
presented to the Environment, Development and Infrastructure
Committee for approval or otherwise. 
4.0 DETAIL
4.1   The pavement parking prohibitions were introduced by the Scottish Government
via the Transport (Scotland) Act 2019 (“the Act”).  The principal aim of this Act is
to improve accessibility, with a particular emphasis on vulnerable road users, by
affording walkers and wheelers the ability to use footways and dropped kerbs
without being impeded by parked vehicles.
4.2  The Act relies on several associated regulations and guidance documents,
which are vital to the interpretation and enforcement of the prohibitions, listed
Page 56

Page 57

below.  Section 68 of the Act states that local authorities must have regard to
any written guidance given by Scottish Ministers.  The key documents for the
pavement parking prohibitions are:
i. The Pavement Parking Prohibition (Exemption Orders Procedure)
(Scotland) Regulations 2022 (“2022 Regulations”)
ii. Transport Scotland “Pavement, Double & Dropped Kerb Parking
Standards Guidance – Pre-Enforcement Chapters”
iii. The Transport (Scotland) Act 2019 (Pavement Parking Prohibition)
(Footway and Associated Carriageway Characteristics) Directions 2022
(“Ministerial Directions”)
iv. The Parking Prohibitions (Enforcement and Accounts) (Scotland)
Regulations 2023 (“2023 Regulations”)
v. Transport Scotland “Pavement, Double & Dropped Kerb Parking
Standards Guidance – Enforcement Chapters”
vi. The Transport (Scotland) Act 2019 (Pavement Parking Prohibition)
(Footway and Associated Carriageway Characteristics) Directions 2022
4.3  This a relatively large number of documents which would be unworkable for use
on a day-to-day basis.  To make this easier to digest and use, officers have
drafted the “Service Procedure for Pavement, Double & Dropped Kerb Parking”
as a one stop shop, however; the definitive source remains the list above should
any dispute arise. It is also intended that this document is uploaded to the
Council’s website to allow members of the public access to the process in as
simple a way as possible and to allow clarity on officers decision making.  To
this end, the Service procedure is written in an easily read format, but it does
lean into more technical language in numerous places to retain the meaning of
the legislation and guidance documents. The document is appended under
Appendix 1. 
4.4 The document is split into seven sections (excluding appendices) with each
section covering a specific topic.  The four sections which address the most
likely common issues by our communities are:
i. Section 3 - Assessment Process
a. Provides an overview of what is considered when assessing an
exemption request.  Appendix 3 within the document includes the
assessment form to be used by Traffic & Development Officers.
ii. Section 4 - Exemption Order Process
a. Details the legal process to be followed when proposing an
exemption.
iii. Section 6 – Enforcement
a. Covers each of the new contravention codes and ‘drive-aways’
iv. Section 7 – Processing of PCNs & Enforcement Notices.
a. The processing and appeals process.  
4.5 It should be noted that Part 6 of the Act also covers double parking and parking
at dropped kerbs (“crossing points”).  The enforcement of all three elements is
expected to lead to safer streets for walkers and wheelers but, at least in the
Page 57

Page 58

short term, pavement parking is likely to continue to be an issue of significant
public interest.. 
4.6 Before looking at pavement parking exemptions, it is important to set out some
of the background essential to any consideration.  Firstly, the Act also relies on
other pieces of legislation regarding previously established definitions.  The
prime example of this is the definition of what a footway or footpath (both are the
legal terms for “pavement”) which is provided within the Roads (Scotland) Act
1984, s151(2)(a).  The definitions are provided below for ease of reference:
• Where the right of passage “is by foot only, the road is:
i. where it is associated with a carriageway, a “footway”; and
ii. where it is not so associated, a “footpath”,”
4.7 The Ministerial Directions, paragraph 3, state that:
“3. (1) A footway may not be specified in an exemption order unless:
a. its layout or character would allow for a width of 1.5 metres of the footway
to remain unobstructed when any part of a vehicle is parked on it, or 
b. the layout or character of the carriageway associated with the footway is
such that the passage of an emergency vehicle would be impeded by the
presence of a vehicle parked on the carriageway. 
(2) The width of 1.5 metres mentioned in paragraph 1(a) is to be measured
from the footway edge which is furthest away from the centre of the
carriageway (however that edge is bounded).” 
4.8 The Transport Scotland guidance (ref. paragraph 4.2(ii)) interprets the Ministerial
Direction as follows: 
“Point 1(a) allows a local authority to consider an exemption order for an area of
footway where there is deemed to be sufficient space to maintain non-vehicular
traffic flow whilst still allowing space for vehicles to park safely on the footway.
The above directions state that a minimum of 1.5 metres of footway must be left
unobstructed. 
Point 1(b) would allow a local authority to exempt an area of footway from the
prohibition to allow the safe passage of emergency vehicles on a carriageway.
For example, this could be in relation to historic/narrow streets where there are
existing footways of insufficient width and access for emergency services needs
to be considered.” 
It is worth noting that most residential developments constructed between 1950-
1987 will likely have sub-standard carriageway widths.  The emergency service
access exemption could probably be used in most circumstances, but this will
undoubtably undermine the aims of the Act and could put pedestrians at risk.
Officers position is that this will likely be the most contentious area of the
legislation for Argyll and Bute Council communities, therefore it will need careful
consideration but once used in one setting it may be difficult to refuse an
exemption in another. 
Page 58

Page 59

4.9 Prior to the implementation of any Exemption Order, the Local Authority must
undertake an appropriate Equality Impact Assessment to ensure the proposals
do not inadvertently discriminate against any protected groups (as defined within
the Equality Act 2010). This will result in an increase workload for officers which
may well require an increase to staffing levels. Officers will monitor this and feed
back through the Executive Director DIS should there be any requirement for
extra staffing.
4.10 Pavement parking exemption orders are permitted within the Act; however, they
are noted as being the measure of last resort.  The document contained
within Appendix 1 provides further detail on the process itself, including an
assessment form to be used by the officers considering a request.  In addition to
this, a sample request form has been provided within Appendix 2 for use by
members of the public.  Subject to agreement by Members, it is intended both
documents will be added to the website for ease of access by the public and to
assist in clarifying officers  recommendations.  The form may require to be
redesigned to suit the requirements of use over the internet , to ensure the form
meets accessibility standards, but no substance will change (again, subject to
any changes agreed by the Committee).
4.11 While the process will be completed by officers, the making, amendment and
revocation of exemption orders under the Act is reserved to the Environment,
Development and Infrastructure Committee within the Council’s Constitution;
Part C - Scheme Of Administration And Delegations, (D) Executive Director Of
Development & Infrastructure Services, Paragraph 61, extracted below:
“To carry out any function conferred on the Council by or under the Transport
(Scotland) Act 2019 (Part 6, Parking Prohibitions) save for the making,
amendment and revocation of exemption orders under s.51 and s.52 of the
said Act which shall be a function reserved to the Environment, Development
and Infrastructure Committee.” 
4.12 Members may also wish to note that unless a footway is exempted it remains
against the law to drive onto a footway and, under the Road Traffic Act
1988 s34(1), an offence to drive onto a footway (the latter being the
responsibility of Police Scotland as the enforcing agency).  
4.13 Finally, officers are obligated to highlight the potential road safety and other
liabilities which could occur where exemptions are promoted.  The following
provides an overview, but is not exhaustive, for Members to consider:
i. How footway parking (in part or full width of footway) may impact
visually impaired or the blind, wheelchair users, pedestrians and
children.  For example, if a footway is exempted over a 100m
section, those in wheelchairs unfamiliar with the route may have to
backtrack to find a dropped kerb and then do the same once past
the footway parking section. This won’t just be in daylight during
the summer months but also in the dark, potentially unlit and
untreated roads during winter. This may well then cause
wheelchair users, visually impaired and others to remain on a live
Page 59

Page 60

carriageway for longer than required thereby placing them at
potentially higher risk of being struck by a moving vehicle. This is
at odds with the legislation for pavement parking.
ii. The impact of footways being inaccessible to wheelchair users or
visually impaired can result in such groups becoming isolated as
they become more anxious or even unwilling to leave their homes.
This is also at odds with the legislation for pavement parking.
iii. If a vulnerable road user (see above) is injured whilst using the
carriageway to bypass footway parking, this may well impose a
liability on the Council which may also affect our public reputation
(advice will be sought from legal colleagues). 
iv. If a footway is exempted, it must be signed in accordance with the
Regulations. Once signage is in place, the Council will be
effectively encouraging footway parking. Bearing in mind that in
most cases the footways will have full height kerbs, there could be
a liability implication placed on the Council (further advice will be
sought from Legal Colleagues).
v. A footway part-exempted may have pedestrians passing as a
vehicle mounts the footway.  This is likely to cause distress to the
pedestrian (including potentially children) but could also pose a
road safety risk.
vi. In almost all cases, footways are constructed to a reduced depth
(typically 350-450mm for carriageways and 210mm for footways). 
Vehicle loadings will (and already have) caused damage to the
footways, including deformation of the ride quality, potholing, wear
and tear and impacting the structural stability of the footway.
vii. Roads are consulted as part of the planning process.  One of the
more common comments / responses submitted by roads is the
provision of off-street parking for developments or conversions. 
On appeal, these are sometimes removed from planning
permissions by PPSL, which is entirely within the agreed
processes and is the right of the Committee to do so, however, it
does add pressure to available on-street parking space availability
and could further impact the requests for exemptions. 
4.14 It may be of interest to Members that a review of complaints, enquires and
Member queries has highlighted that there has been very limited
correspondence relating to this matter.  Officers note that this may not
necessarily reflect wider public opinion,.  In total, there were 26 submissions, of
which 11 could be interpreted as being “against” pavement parking ban (it is
more nuanced than this, of course).  The 15 “for” the pavement parking ban is
a mix of highlighting road safety risks of vehicles parking of footways and
looking for enforcement of same. 
4.15 Members may wish to note that Edinburgh City Council appear to have taken
the stance that no exemptions will be considered or approved.  Although
almost entirely an urban setting, they do have a substantial number of
Page 60

Page 61

“historical” streets which are narrow and where pavement parking has been the
norm.  The following links provide detail on this:
• New parking rules – The City of Edinburgh Council
• New parking rules – The City of Edinburgh Council 
5.0 CONCLUSION
5.1 The Environment, Development and Infrastructure Committee are requested to
approve the Service Procedure document attached as Appendix 1, subject to
any amendments they may wish to propose. Additionally, approval is sought for
the application form requesting an assessment, as set out in Appendix 2, with
the understanding that any necessary stylistic modifications required for the
website will be made. It is further noted that, prior to the issuance of any
Exemption Order, such orders will be submitted to the Environment,
Development and Infrastructure Committee for consideration. 
6.0 IMPLICATIONS
6.1 Policy – New Service procedure for the application of Part 6 of the Transport
(Scotland) Act 2019.
6.2 Financial – None known at this time other than staff and committee time for
the assessment and consideration of exemption orders. There may however
be a financial burden on the council for signage as well as damage to any
exempted footways/footpaths kerbs where vehicles are either damaged or
damage the kerbs themselves. 
6.3  Legal – Changes to the constitution have already been made to include the
Transport (Scotland) Act 2019 under Part C - Scheme Of Administration and
Delegations, (D) Executive Director Of Development & Infrastructure Services,
Paragraph 6.1.
6.4  HR –  Depending on the increased workload this may require additional
staffing to support the small team carrying out the back office work.   
6.5 Customer service – Will required to be updated on Service Procedure and
Assessment request form once uploaded to the website. 
6.6  Risk – Potential reputational, legal and financial should an exemption order
lead to injury or fatality due to pedestrian being forced to walk on live
carriageway. 
6.7  Climate change – None known. 
6.8  Fairer Scotland Duty – Public bodies are required to carry out assessments to
understand how their decisions might affect people experiencing socio-
economic disadvantage. Any exemptions will require to carry out an
Page 61

Page 62

assessment which may well identify that members of our community who
suffer financial disadvantage or are in poverty cannot afford a vehicle and
thereby walk or cycle and any exemptions may well impact their right to
walking safely on our footpaths and footways. 
6.9  Equalities: protected characteristics – Equality Impact Assessments are
required prior to the making of any exemption order.  These must be made for
each case, a coverall assessment is not permitted. 
6.10  Consumer duty – None known. 
6.11  Island communities – None.   
6.12 Children’s Rights and Wellbeing – removing vehicles from footways provides a
safe refuge for children, one of the most vulnerable road user groups. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour
July 2025                                                 
For further information contact: 
Stuart Watson, Assistant Network & Standards Manager
stuart.watson@argyll-bute.gov.uk 
Hugh O’Neill – Network & Standard Manager
hugh.oneill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Service Procedure for Pavement, Double & Dropped Kerb Parking
Appendix 2 – Sample Request Form 
Page 62

Page 63

1 
ROADS AND
INFRASTRUCTURE SERVICES 
Service Procedure for Pavement,
Double & Dropped Kerb Parking 
Transport (Scotland) Act 2019 
Author Stuart Watson
Owner Head of Roads & Infrastructure
Services
Date April 2025
Version Final v0.5 
Page 63

Page 64

2 
Document Information 
Title Service Procedure for Pavement, Double & Dropped Kerb Parking 
Author Stuart Watson
Description Guidance covering the legislation 
Document History 
Version Status Date Author Changes made
0.1 Draft 15/01/2025 Stuart
Watson
New document for the provision set out under
Part 6 (Parking Prohibitions) of the Transport
(Scotland) Act 2019 
0.2 DRAFT 12/02/2025 Stuart
Watson
Amendments – comments from Donna
Lawson, Keith Tennant, Fran Millar
0.3 DRAFT  27/02/2025 Stuart
Watson
Typos etc.
0.4 Draft 27/02/2025 Stuart
Watson
Following review by Susie Sinclair
0.5 Final 16/04/25 Stuart
Watson
HO’N comments 
Page 64

Page 65

3 
Contents
1.0 Introduction ........................................................................................................................................... 4
2.0 Governing Legislation ......................................................................................................................... 5
3.0 Assessment Process ........................................................................................................................... 8
4.0 Exemption Order Process ................................................................................................................ 10
5.0 Signing and Lining ............................................................................................................................. 14
6.0 Enforcement ....................................................................................................................................... 17
7.0 Processing of PCNs & Enforcement Notices ................................................................................ 19
8.0 Appendix 1 – Section 55 Exceptions to pavement parking prohibition and double-parking
prohibition ......................................................................................................................................................... 22
9.0 Appendix 2 – The Transport (Scotland) Act 2019 (Pavement Parking Prohibition) (Footway
and Associated Carriageway Characteristics) Directions 2022 ............................................................... 24
10.0 Appendix 3 – Assessment Form ..................................................................................................... 25
11.0 Appendix 4 – Notice of Proposals template ................................................................................... 27
12.0 Appendix 5 – Statement of Reasons template .............................................................................. 28
13.0 Appendix 6 – Form of Order and Plan ............................................................................................ 29
14.0 Appendix 7 – Notice of Making an Exemption Order template ................................................... 33
15.0 Appendix 8 - Route A – PCN Issued under Regulation 4 ............................................................ 34
16.0 Appendix 9 - Route B – PCN Issued under Regulation 5 ............................................................ 36 
Page 65

Page 66

4 
1.0 Introduction 
1.1 The Transport (Scotland) Act 2019 received Royal Assent on 15 November 2019. 
Part 6 of the Act refers to the Pavement Prohibitions.  This includes parking
prohibitions relating to footway, dropped kerb and double parking.   
1.2 The pavement prohibitions are primarily intended to improve accessibility, with a
particular emphasis on vulnerable road users, by affording walkers and wheelers the
ability to use footways and dropped kerbs without being impeded by parked vehicles. 
1.3 This Service Procedure provides guidance on the assessment and implementation of
Exemption Orders, the signing and lining requirements and the enforcement of the
prohibitions (including the issue and processing of Penalty Charge Notices). 
1.4 Where there is any doubt, the legislation and regulations take precedence. 
Page 66

Page 67

5 
2.0 Governing Legislation 
2.1 This guidance document is based on the following:
• The Transport (Scotland) Act 2019 (“the Act”)
• The Pavement Parking Prohibition (Exemption Orders Procedure) (Scotland)
Regulations 2022 (“2022 Regs”)
• The Parking Prohibitions (Enforcement and Accounts) (Scotland)
Regulations 2023 (“2023 Regs”)
• The Transport (Scotland) Act 2019 (Pavement Parking Prohibition) (Footway
and Associated Carriageway Characteristics) Directions 2022 (“Ministerial
Direction 2022”)
• The Traffic Signs Regulations and General Directions 2016 (“TSRGD”)
• The Traffic Signs Manual (“TSM”)
• The Road Traffic Regulation Act 1984 (“RTRA1984”) 
2.2 Recognising the following is written using legal language and may not be easy for
the lay person to interpret, Section 6 of this Service Procedure sets out the
enforcement of the below in plain English. 
2.3 Part 6, Sections 50-69, of the Act covers the Parking Prohibitions.  The following
definitions are provided within Part 6, s69:
• “double parking prohibition” has the meaning given by section 54(1),
• “dropped footway parking prohibition” has the meaning given by section
56(2),
• “exemption order” has the meaning given by section 51(1),
• “footway” has the meaning given by section 50(4),
• “motor vehicle”
o (a)in relation to the pavement parking prohibition, has the meaning
given by section 50(4),
o (b) in relation to the double parking prohibition and the dropped
footway parking prohibition, has the meaning given by section 54(5),
• “pavement” has the meaning given by section 50(4),
• “pavement parking prohibition” has the meaning given by section 50(1),
• “road” has the meaning given by section 151(1) of the Roads (Scotland) Act
1984,
• “traffic authority” means, in relation to a footway, the body which has the
function of making Traffic Regulation Orders under section 1 of the Road
Traffic Regulation Act 1984. 
2.4 Within the Act, the term “pavement parking” refers to parking on a “footway” or
“footpath” as defined within the Roads (Scotland) Act 1984, s151(2)(a).  Paragraph
6.6 provides the definitions of footways and footpaths. 
Pavement Parking 
2.5 Section 50 of the Act requires that a person “…must not park a motor vehicle on a
pavement…”.  It further states that for the purposes of the prohibition:
a. a motor vehicle is parked on a pavement if:
i. it is stationary, and
Page 67

Page 68

6 
ii. one or more of its wheels (or any part of them) is on any part of the
pavement
b. a stationary motor vehicle is parked whether or not:
i. the driver of the vehicle is in attendance at the vehicle, 
ii. the engine of the vehicle is running 
2.6 The Act provides a number of exceptions to this under Section 55, these are
covered within Section 6 of this document. 
2.7 Section 51 of the Act provides a mechanism to exempt a footway/footpath, or parts
thereof, from the prohibition.  This is covered in detail within Sections 3 and 4 of this
document. 
Double Parking
2.8 Section 54 of the Act requires that a person must not park a motor vehicle in such a
manner that “no part of the vehicle is within 50 centimetres of the edge of a
carriageway”.  The edge of the carriageway means:
a. where the edge of the carriageway is marked by a painted solid white line,
the edge of the painted line furthest from the centre of the carriageway,
b. where the edge of the carriageway is not marked by a painted solid white
line and is bounded by a kerb, the edge of the kerb closest to the centre of
the carriageway,
c. in any other case, where the surface of the carriageway meets the verge of
the carriageway, 
2.9 As with the pavement parking prohibition, S54 further states that a stationary motor
vehicle is parked whether or not:
a. the driver of the vehicle is in attendance at the vehicle,
b. the engine of the vehicle is running. 
2.10 A motor vehicle is not considered parked if it is stationary:
a. due to the necessities of traffic, or
b. otherwise as a result of circumstances beyond the driver's control. 
2.11 Again, The Act provides for exceptions to this prohibition as set out under Section
55, these are covered within Section 6 of this document.  For ease of reference, s55
is included within Appendix 1. 
Dropped Footway Parking 
2.12 Section 56 of the Act provides that a person must not park a motor vehicle on a
carriageway adjacent to a footway where, for the purpose of assisting pedestrians
or cyclists to cross the carriageway:
a. the footway has been lowered to meet the level of the carriageway, or
b. the carriageway has been raised to meet the level of the footway. 
2.13 The exceptions provided for regarding dropped footway parking, under s59 of the
Act, are much more limited than that for double or pavement parking.  The
exceptions are:
i. The dropped footway parking prohibition does not apply where:
Page 68

Page 69

7 
a. the person has parked the motor vehicle for the purpose of saving
life or responding to another similar emergency,
b. the achievement of that purpose would be likely to be hindered if the
vehicle were not parked as mentioned in section 56(1),
c. the vehicle is so parked for no longer than is necessary for that
purpose. 
ii. the dropped footway parking prohibition does not apply where the footway
has been lowered, or the carriageway has been raised as described in
section 56(1) for the purpose of access to a driveway or to a garage
(whether on commercial or residential premises).
Page 69

Page 70

8 
3.0 Assessment Process 
3.1 The Legislation has been drafted in such a way to recognise that a one-size-fits-all
may not work everywhere and allows a degree of local context. 
3.2 Notwithstanding this, it is a key part of the Act, Regulations and associated
guidance note that any exemptions to the pavement parking prohibition are not the
norm and will, indeed, be the exception.  An Exemption Order should only be used
where it is necessary and no other solutions can be employed to maintain vehicular
access (for example, using normal Traffic Regulation Orders to implement parking
restrictions, designate bays, one ways streets, double yellows, etc.).  For the sake
of clarity, there should be a presumption against exemptions except where they are
absolutely needed, i.e. the impact on the travelling public or emergency services is
so adverse that it justifies the removal of space from the most vulnerable road users
to mitigate against it. 
3.3 Another item that must be considered for any exemption is the completion of a
Socio-Economic Impact Assessment to ensure that no protected group is
inadvertently discriminated against.  These will be completed on case by case
basis. 
3.4 Finally, the Scottish Ministers issued Ministerial Directions under s67(1) of the Act. 
The Ministerial Directions 2022 is included in Appendix 2 for reference, however,
the key points are: 
1. A footway may not be specified in an exemption order unless:
a. its layout or character would allow for a width of 1.5 metres of the
footway to remain unobstructed when any part of a vehicle is parked
on it, or
b. the layout or character of the carriageway associated with the
footway is such that the passage of an emergency vehicle would be
impeded by the presence of a vehicle parked on the carriageway. 
2. The width of 1.5 metres mentioned in paragraph 1(a) is to be measured from
the footway edge which is furthest away from the centre of the carriageway
(however that edge is bounded). 
3.5 On confirmation that the exemption is needed and that the minimum characteristics
outlined in 3.4 are retained, the assessment process can commence.  The
assessment will normally be carried out by the local Traffic & Development Officers
but may be carried out by other officers with appropriate training. 
3.6 The following provides the minimum assessment criteria: 
1. Collation of the road layout, including the number of footways, their width
and the width of the carriageway 
2. Provision of street lighting
3. Are there existing restrictions (e.g. double yellow lines)
4. What is the roads primary function (shopping precinct, residential area,
strategic route etc.)
5. Speed limit
Page 70

Page 71

9 
6. Current or future plans for the road space (e.g. is there already consultation
or implementation in regard to Active Travel route)
7. Parking provision (driveways, off-street car parks, on-street parking bays)
8. Traffic flows (including general pedestrian and cyclist use)
9. Accessibility considerations for all road users (motorised and non-motorised)
10. Displacement issues
11. Road Safety
12. Both a daytime and nighttime visit to assess different use at both periods of
the day
13. Collation of location of all iron works within carriageway and footway;
including utility chambers and noting that, typically, covers within non-
vehicular areas are not designed to take vehicles loadings (e.g. A class
versus D class) 
3.7 A template assessment form is provided for use in Appendix 3. 
3.8 Consideration should also be given to the presence of identified “Safe Routes to
school” and the impact an Exemption Order may have on the safety of school
children using the route. 
3.9 Once the assessment has been completed, it shall be forwarded to the Service
Officer – Traffic to commence the Exemption Order process. 
3.10 Note, it is not appropriate to promote widespread or blanket exemptions. Each
street must be considered on its own merit.
Page 71

Page 72

10 
4.0 Exemption Order Process 
4.1 Section 51 of the Act provides the power to a Local Authority to promote Exemption
Orders.  It is very clear that it may not do so unless the characteristics outlined in
the Ministerial Directions 2022 are met.  Section 52 of the Act permits the Scottish
Ministers to make regulations in respect to Exemption Orders and, to this end, The
Pavement Parking Prohibition (Exemption Orders Procedure (Scotland) Regulations
2022 came into force on 9 December 2022.  In addition to the 2022 Regulations,
Transport Scotland have published further guidance within their document
Pavement, Double & Dropped Kerb Parking Standards Guidance”. 
4.2 Furthermore, an Exemption Order:
a) may apply to all or part of a footway,
b) must apply:
i. at all times, and
ii. to all motor vehicles,
c) may not be subject to conditions. 
4.3 There is a need beyond what is set out above for exemptions to be carefully
considered against the national ban.  As noted elsewhere, the norm must be for a
presumption against but balancing this beside the need for traffic flows to work
(again motorised and non-motorised).  The approach must be consistent across the
Council area but mindful of that being carried out in other Local Authorities to
ensure consistency, so that drivers and other road users can understand and
comply with the pavement parking prohibition. 
4.4 Once the assessment has been completed satisfactorily, the following paragraphs
set out the Exemption Order process. 
Consultation and Publication 
4.5 Unlike Orders promoted under the RTRA1984, there is no requirement to publish
Notices etc. within traditional press / media.  As a general rule, however, it should
be done regardless to ensure best coverage.   
4.6 Prior to making an Exemption Order, the Council must: 
a. Publish a Notice on its website (containing the information as set out in
Appendix 4 – Notice of the Proposals Template)
b. Publish a Statement of Reasons why the Order should be made on the
Council’s website (a template is provided in Appendix 5)
c. Publish, on the Council’s website, an outline of the proposals, including as a
minimum:
i. The section of footway, or part thereof, to which the proposal relates
ii. A map showing the section of footway, or part thereof, to which the
proposal relates
d. A template for a draft Exemption Order has been included in Appendix 6. 
4.7 In addition to publication on the website, the Notice and Statement of Reasons for
the proposals should be published in paper circulating in the area affected.
Page 72

Page 73

11 
4.8 The Council must also make the information, outlined n para 4.6 a-c, available for
inspection at the appropriate office during normal operating office hours.  The
Council can include additional places as it considers appropriate (for example, a
post office). 
4.9 The Notices must also be displayed in a prominent position at each end of the
footway to which the exemption order proposal relates.  Furthermore, additional
Notices to be displayed as the authority thinks necessary to ensure adequate
information is provided to those using the footway.  The authority must also take all
reasonable steps to ensure the Notice remains legible and is displayed until the end
of the representation period. 
4.10 Beyond the publication and display of Notices etc. as outlined above, the Council
must also consult with the following persons: (REG2(3)) 
• The Chief Constable of the Police Service of Scotland
• Any Transport Partnership (where the proposal is within the region
represented)
• The appropriate Crown Authority where the proposal relates to a Crown
Road
• Any Health Board (where the proposal is within the region represented)
• The Scottish Fire and Rescue Service (where it appears to the Council that
proposals(s) are likely to affect the passage of fire fighting vehicles)
• The Traffic Authority (where the proposal relates to a road which is not
under the control of the Council, e.g. a trunk road)
• Other person as the Council considers appropriate.  This is similar to that
included within the normal Traffic Regulation Order consultation.  Officers
will need to make a judgement on the extent of this on each case but, as a
minimum, properties situated on the road affected by the proposals should
be consulted with; this could take the form of a letter drop with the Notice
etc. included or pointing to the website.  Publishing in traditional media
outlets (e.g. newpapers) would also satisfy this part. 
4.11 Although not mandated within the Legislation, the related guidance document does
state that it would be good practice for a Local Authority to retain an accessible
archive of all Exemption Orders on its archive to allow members of the public to
view them as needed.  It also notes that this may be useful for the public to review
alongside new proposals as mooted. 
4.12 Finally, the consultation period must be at least 28 days commencing from the
publication of the Notice (2022 Regs, Schedule 1, Part 1, paragraph 5).  The Local
Authority can extend this period as it considers necessary. 
Representations 
4.13 Representations can be made by any person before the end of the period specified
in the Notice. 
4.14 Representations must, however:
Page 73

Page 74

12 
i. Contain a statement of the grounds on which representations are made, and
ii. Be intimated to the Authority as set out within the Notice (i.e. within the
timescale and to the address listed in the Notice). 
4.15 The Council may consider representations received after the closing date as it
considers appropriate. 
Hearings 
4.16 The Local Authority can choose to conduct a hearing prior to making an Exemption
Order.  The Legislation does not impose this as a mandatory function, however, in
some cases in may be reasonable to hold a hearing.  For example, if the Local
Authority proposes an Exemption Order and the proposal received hundreds of
representations against it, it could be considered maladministration not to hold a
hearing. 
4.17 Notwithstanding the above, where a hearing is proposed, the following applies:
i. A “Reporter” will be appointed to conduct the hearing.
ii. The hearing can look at the whole Order or any part thereof.
iii. A Reporter must be either a member of staff of the Scottish Ministers or
selected from a panel provided by the Scottish Ministers.
iv. The hearing must be held in public. 
4.18 The Reporter must give notice in writing to:
i. Those consulted under Regulation 2(3).
ii. Those whose submitted representations.
iii. Any other person from whom the Reporter wishes to hear in relation to
specified matters. 
4.19 The Notice issued must note that those wishing to be heard must respond in writing
to the Reporter within 14 days of receiving the Notice.  The Notice must also clearly
outline that if they do not reply, then they will not be entitled to appear at the
hearing.  The Reporter must also provide the date, time and location of the hearing,
however; these can be altered and, where this is the case, the Reporter must
confirm amendments to those persons entitled to appear. 
4.20 The procedure at hearing is outlined under Regulation 8.  One of the key points to
note is that the procedure at hearing is as the Reporter determines, within the
bounds of the Regulations. 
Making of the Order 
4.21 Part 4 of the 2022 Regulations sets out the process of the making of an Exemption
Order. 
4.22 Prior to making an Order, the Local Authority must consider any representations
made and, where a hearing has been held, the recommendations made by the
Reporter. 
4.23 Analogous to the normal TRO process, the Local Authority may:
i. Make the Order without modification
Page 74

Page 75

13 
ii. Make the Order with modification
iii. Decide to not make the Order 
4.24 Where the Local Authority agrees to make the Order with modification(s) which
amount to a substantial change to the proposals; there is a requirement to notify
each person who is likely to be affected by the change, to allow a period to respond
and to, again, consider any representations made. The substantial change element
is subject to the opinion of the Local Authority, i.e. that it is the Local Authority’s
view that any changes are substantial.  This must be an objective assessment, and
the reasons recorded, particularly where the decision is that it is not a substantial
change. 
4.25 The Form of the Exemption Order (Regulation 11) must: 
i. Specify the footway, or part thereof, to which it relates
ii. Provide a map indicating the footway, or part thereof, to which the order
relates
iii. Specify the date on which the Order comes into effect. 
4.26 Within 14 days of making an Exemption Order, the Local Authority must:
a. Give notice in writing of the making of the Exemption Order to the Chief
Constable of the Police Service of Scotland,
b. Give notice in writing to each person consulted under regulation 2(3), and to
each person who made representations under regulation 3(1), of the Local
Authority’s reasons for making the Exemption Order,
c. Publish on the Local Authority’s website a notice of the making of the
Exemption Order containing the information specified in Part 2 of schedule
1, (template provided in Appendix 7)
d. Publish the Exemption Order and accompanying map and, where
applicable, the report following the holding of a hearing under regulation 4,
on the Local Authority’s website,
e. Make a copy of everything mentioned in sub-paragraphs (a) to (d) available
for inspection at their offices during normal office hours, and (if the Local
Authority thinks fit) at such other places within its area and during such times
at those places as it may determine,
f. Display notices containing the information set out in Part 2 of schedule 1,
displayed in accordance with paragraphs 1 and 3 of schedule 2, in any
footway to which the Exemption Order relates,
g. Take such other steps as it considers appropriate for ensuring that adequate
publicity about the making of the Exemption Order is given to persons likely
to be affected by it. 
4.27 Exemption Orders can be amended or revoked.  The process for doing either of
these requires that the full process is followed, as outlined from paragraph 4.6
onwards.  Within the 2022 Regulations, this includes r2-r12. 
4.28 An archive of Exemption Orders will be maintained on the Local Authority’s website. 
Page 75

Page 76

14 
5.0 Signing and Lining 
5.1 Once the Exemption Order process is complete, it will be a requirement to mark the
appropriate signs and lines.  These must be installed in compliance with the Traffic
Signs Regulations and General Directions and The Traffic Signs Manual.  The
Traffic Signs Manual, Chapter 3, s13.19 refers. 
5.2 The TSRGD and TSM, Chapter 3 permits footway parking to have time period.  As
noted earlier, in Scotland under the 2019 Act this is not permitted.  A pavement
parking exemption must apply at all times. 
5.3 Where a footway or section of a footway has been exempted by Order, the area
must be clearly marked with signs and lines.  The signs and lines used must make it
clear to both drivers and pedestrians that the footway is subject to a pavement
parking Exemption Order. 
5.4 It is particularly important, in the interest of fairness, that the markings and signs are
clear to drivers as they may be subject to a Penalty Charge Notice (PCN) if they
park out with the exempted area.  The maintenance of the signs and lines in good
order is vital to the success of any exemption.   
5.5 Table 1, below, provides an overview of the signs which may be used. 
Table 1 
TSRGD Ref.  Sign image
Schedule 7, Part 2, Item 12, Diag. 667 
Vehicles may be parked partially on the
footway 
An arrow pointing to the left or to the right
may be added 
Schedule 7, Part 2, Item 13, Diag. 668 
Vehicles may be parked wholly on the
footway 
An arrow pointing to the left or to the right
may be added 
Schedule 7, Part 2, Item 14, Diag. 667.1 
Vehicles may be parked partially on the
footway. 
Note: the time period is not permitted in
Scotland.   
Page 76

Page 77

15 
The lower panel can be amended to
include with an arrow pointing to the left or
to the right may be added in the lower
panel; or, amended to the text “in marked
bays”. 
Schedule 7, Part 2, Item 15, Diag. 668.1 
Vehicles may be parked wholly on the
footway. 
Note: the time period is not permitted in
Scotland.   
The lower panel can be amended to
include with an arrow pointing to the left or
to the right may be added in the lower
panel; or, amended to the text “in marked
bays”. 
Schedule 7, Part 2, Item 16, Diag. 667.2 
End of area where vehicles may be parked
partially on the footway.  
Schedule 7, Part 2, Item 17, Diag. 668.2 
End of area where vehicles may be parked
wholly on the footway. 
5.6 The TSM, Chapter 3, s13.19, Figure13.59 provides indicative layout markings (as
shown below).   
Page 77

Page 78

16 
5.7 These markings are made in accordance with the TSRGD, Schedule 7, Part 4, Item
6: Diagram 1028.4, Table 2 below refers: 
Table 2 
TSRGD Ref. Sign image
Schedule 7, Part 4, Item 6, Diag. 1028.4 
a) at the edge of the carriageway and
situated wholly on the footway; or
b) partly on the carriageway and partly
on the footway 
Refer to TSM, Ch3, Figure13.59. 
5.8 The TSM, Ch3, Figure 13.60 also provides an indicative layout for footway parking,
extract below for ease of reference: 
Page 78

Page 79

17 
6.0 Enforcement 
6.1 The 2019 Act differs from slightly from the Road Traffic Act 1991 and the DPE
powers.  One of the main differences is the ability to issue PCNs to “drive aways”
but there are also some changes to terminology 
6.2 Under the 2023 Regulations, enforcement officers may issue a PCN under either
R4 or R5. 
6.3 Regulation 4 is similar to a PCN issued under DPE in that, where the officer has
reason to believe that a breach has occurred, a PCN may be fixed to the vehicle or
handed to the person appearing to be in charge of the vehicle. 
6.4 Regulation 5, however, permits a PCN to be issued for one of two reasons: 
i. Where either the enforcement officer has attempted to issue a PCN under
Reg 4 but was prevented from doing so by any person, or
ii. Where an enforcement officer has begun to prepare a PCN, but the vehicle
was driven away before the officer had finished preparing the Notice or
being able to issue under R4. 
6.5 Neither Scottish Ministers nor Transport Scotland have powers to undertake parking
enforcement.  The Local Authority are able, however, to carry out enforcement on
the Trunk Road Network (those section of it within the Local Authority area).  For
the most part, this is likely to be within urban areas but could impact both the trunk
and local road rural networks.  Where there are requests or identified demands for
rural enforcement, a risk assessment and method statement may be needed to
ensure the safety of the enforcement staff (e.g. working on high-speed roads). 
6.6 The 2019 Act defined footways and footpaths in accordance with the Roads
(Scotland) Act 1984, s151(2)(a) (extracted below for ease of reference).  This
definition is not limited to adopted footways or footpaths only but to where there is a
public right of passage.  This means that the Pavement Parking Ban applies to both
adopted and private roads. 
For the purpose of this Act, where over a road the public right of passage referred to
in the definition of “road” in subsection (1) above— 
a) is by foot only, the road is:
i. where it is associated with a carriageway, a “footway”; and
ii. where it is not so associated, a “footpath”. 
6.7 It may also be possible to enforce the Pavement Parking Ban for vehicles parking
on a verge.  This is limited to very specific conditions, namely that the verge is
located between a carriageway and a footway.  It is not possible to enforce parking
on a verge in any other circumstance. 
6.8 Neither the 2019 Act nor the 2023 Regulations appear to limit the number of PCNs
that can be issued in a 24-hour period, however, one per calendar day is
reasonable and should be the norm.  One exception to this may be where a vehicle
Page 79

Page 80

18 
has received a PCN but has then moved to another location where it is once again
breaching the 2019 Act.  In these situations, it is appropriate to issue a further PCN. 
6.9 The contravention codes to be used under the 2019 Act are: 
Code Description
100 Parked on a pavement
101 Parked adjacent to dropped kerb at a
known crossing point
102 Parked where no part of the vehicle is
within 50 centimetres of the edge of the
carriageway 
6.10 Section 2 Governing Legislation provides the legal definitions for each of the
prohibitions. 
6.11 The assessment for contravention 100 is the simplest of the three new codes.  If a
vehicle is parked on a footway or footpath, that has not been subject to an
Exemption Order, then a PCN may be issued.    There may also be grounds for
appeal if the keeper of the vehicle has been subject to criminal proceedings,
however, this is covered under Section 7.0 Processing of PCNs. 
6.12 For contravention 101, the crossing point (note, kerbs can be raised or dropped to
facilitate crossing) must be a crossing point and not, for example, a dropped kerb
for a vehicular access.  There may be circumstances where there is no dropped
kerb on the one side of the crossing but could still be considered a “crossing point”.   
6.13 Within contravention 102, “double parking”, the edge of the carriageway means: 
a. Where the edge of the carriageway is marked by a painted solid white line,
the edge of the painted line furthest from the centre of the carriageway
b. Where the edge of the carriageway is not marked by a painted solid white
line and is bounded by a kerb, the edge of the kerb closest to the centre of
the carriageway
c. In any other case, where the surface of the carriageway meets the verge of
the carriageway.
Page 80

Page 81

19 
7.0 Processing of PCNs & Enforcement Notices 
PCNs issued by enforcement officer 
7.1 The following process shall be used for PCNs issued under Regulation 4 of the
2023 Regulations: 
7.1.1 This is where the PCN has been issued by the enforcement officer and either
affixed to the vehicle or handed to the person appearing to be in charge of the
vehicle. 
A PCN is paid without representation being made
7.1.2 If the payment is received within 14 days, the 50% discount is applied.
7.1.3 If payment is received within 28 days but after the 14 days, the charge is at
the normal undiscounted rate. 
Where Payment is not made within 28 days
7.1.4 If no payment is made within 28 days, an enquiry to the DVLA seeking keeper
details is made.  Within 14 days of receipt of the DVLA information, an
Enforcement Notice is issued.
7.1.5 If payment is made within 28 days of the Enforcement Notice, the case is
closed, if not, the Charge is increase by 50% and a Charge Certificate is
issued. 
7.1.6 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action. 
Where Representation is made (within 28 days)
7.1.7 If the Appeal is accepted, the case is closed.
7.1.8 If the Appeal is rejected, a Notice of Rejection (NoR) is issued.
7.1.9 If no subsequent Appeal is made within 28 days of NoR, the Charge is
increased by 50% and a Charge Certificate is issued.
7.1.10 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action. 
Where subsequent Representation is made to First-tier or Upper
Tribunal
7.1.11 If an Appeal is Upheld by the First-Tier Tribunal then the case is closed.
7.1.12 If an Appeal to the First-tier Tribunal is made (must be within 28 days of NoR)
and the Appeal is withdrawn and no payment is made within 14 days of the
appellant withdrawing the Appeal, then the Charge is increased by 50% and a
Charge Certificate is issued.
7.1.13 If an Appeal to the First-tier Tribunal is made (must be within 28 days of NoR)
and the Appeal is rejected and no further Appeal is made to the Upper
Tribunal or no payment is made within 28 days of the appellant being sent the
decision of the First-tier Tribunal, then the Charge is increased by 50% and a
Charge Certificate is issued.
7.1.14 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action.
7.1.15 Where a further Appeal is made to the Upper Tribunal and Upheld, the case
is closed.
Page 81

Page 82

20 
7.1.16 If an Appeal is rejected by the Upper Tribunal and payment is made, the case
is closed.
7.1.17 If an Appeal is rejected by the Upper Tribunal and no payment has been
made within 28 days of the appellant being sent the decision of the Upper
Tribunal, then the Charge is increased by 50% and a Charge Certificate is
issued.
7.1.18 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action. 
7.2 A workflow is contained under Appendix 8 for the PCNs issued under Regulation 4. 
Enforcement Notices where PCN could not be issued by enforcement officer 
7.3 The following processed shall be used for Enforcement Notices issued under
Regulation 5 of the 2023 Regs: 
7.3.1 This is where the enforcement officer has started preparing a PCN but has
either been prevented from affixing it to the vehicle or the vehicle has been
driven away before it could be completed. 
7.3.2 An Enforcement Notice must be issued before the end of the 28-day period
beginning with contravention date.  There is one exception to this, where a
request for keeper details has been made to the DVLA within 14 days of the
contravention, but this not been received within the 28-day period.  Where
this is the case, an Enforcement Notice must be issued within 14 days,
commencing from the date the requested information is received. 
Enforcement Notice is paid without Representation being made
7.3.3 If the payment is received within 14 days, the 50% discount is applied.
7.3.4 If payment is received within 28 days but after the 14 days, the charge is at
the normal undiscounted rate. 
Where Payment is not made within 28 days
7.3.5 If no payment is made within 28 days, the Charge is increase by 50% and a
Charge Certificate is issued. 
7.3.6 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action. 
Where Representation is made (within 28 days)
7.3.7 If the Appeal is accepted, the case is closed.
7.3.8 If the Appeal is rejected, a Notice of Rejection is issued.
7.3.9 If no subsequent Appeal is made within 28 days of NoR, the Charge is
increased by 50% and a Charge Certificate is issued.
7.3.10 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action. 
Where subsequent Representation is made to First-tier or Upper
Tribunal
7.3.11 If an Appeal is Upheld by the First-Tier Tribunal then the case is closed.
7.3.12 If an Appeal to the First-tier Tribunal is made (must be within 28 days of NoR)
and the Appeal is withdrawn and no payment is made within 14 days of the
Page 82

Page 83

21 
appellant withdrawing the Appeal, then the Charge is increased by 50% and a
Charge Certificate is issued.
7.3.13 If an Appeal to the First-tier Tribunal is made (must be within 28 days of NoR)
and the Appeal is rejected and no further Appeal is made to the Upper
Tribunal or no payment is made within 28 days of the appellant being sent the
decision of the First-tier Tribunal, then the Charge is increased by 50% and a
Charge Certificate is issued.
7.3.14 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action.
7.3.15 Where a further Appeal is made to the Upper Tribunal and Upheld, the case
is closed.
7.3.16 If an Appeal is Rejected by the Upper Tribunal and payment is made, the
case is closed.
7.3.17 If an Appeal is Rejected by the Upper Tribunal and no payment has been
made within 28 days of the appellant being sent the decision of the Upper
Tribunal, then the Charge is increased by 50% and a Charge Certificate is
issued.
7.3.18 On issue of the Charge Certificate, if payment is received within 28 days then
the case is closed, if not, the case is referred for collective action. 
7.4 A workflow is contained under Appendix 9 for the PCNs issued under Regulation 5. 
Circumstances where a PCN is not payable 
7.5 The 2023 Regulations, Regulation 8 states: 
1. No penalty charge is payable in relation to a contravention where the
conduct in respect of which the penalty charge is imposed is the subject of:
a) criminal proceedings,
b) a fixed penalty notice (within the meaning of section 52(1) (fixed
penalty notices) of the Road Traffic Offenders Act 1988), or
c) a penalty charge notice issued under section 66(1) (parking penalties
in London) of the Road Traffic Act 1991(as applied by an order under
paragraph 1 or 2 of schedule 3 of that Act).
2. Where, despite paragraph (1):
a) a penalty charge is paid in respect of a contravention, and
b) the conduct in respect of which the penalty charge is imposed is the
subject of proceedings or a notice as mentioned in paragraph (1)(a) to
(c),
the local authority must, as soon as reasonably practicable after the
circumstances in sub-paragraph (b) come to its notice, refund the amount of
the penalty charge which has been paid.
7.6 In the above circumstances a PCN should not be issued (when the circumstances
are known) but, where a PCN has been issued, the amount must be refunded. 
Page 83

Page 84

22 
8.0 Appendix 1 – Section 55 Exceptions to pavement parking prohibition and double-parking
prohibition 
1) This section sets out exceptions to the Pavement Parking Prohibition and the Double
Parking Prohibition. 
2) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where
the motor vehicle:
a) is being used:
i. For police purposes, including for the purposes of the National Crime
Agency,
ii. For ambulance purposes or for the purpose of providing a response to an
emergency at the request of the Scottish Ambulance Service Board,
iii. For or in connection with the exercise of any function of the Scottish Fire and
Rescue Service or Her Majesty’s Coastguard, or
iv. For naval, military or air force purposes,
b) The achievement of the purposes, or the exercise of the function, would be likely to
be hindered if the vehicle were not parked on a pavement or, as the case may be, as
mentioned in section 54(1), and
c) No part of the vehicle is within 1.5 metres of the pavement edge which is furthest
away from the centre of the carriageway (however that edge is bounded). 
3) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where
the motor vehicle:
a. Is being used for or in connection with:
i. The undertaking of works in roads,
ii. The removal of an obstruction to traffic,
iii. The collection of waste by or on behalf of a Local Authority,
iv. Postal services (within the meaning of section 125(1) of the Postal Services
Act 2000),
b. Cannot reasonably be so used without being parked on a pavement or, as the case
may be, as mentioned in section 54(1),
c. Is so parked for no longer than is necessary for that use, and
d. No part of the vehicle is within 1.5 metres of the pavement edge which is furthest
away from the centre of the carriageway (however that edge is bounded). 
4) In subsection (3)(a)(i), “works in roads” includes:
a. Road works within the meaning given by section 107(3) of the New Roads and Street
Works Act 1991,
b. Works for roads purposes within the meaning given by section 145(2) of that Act,
c. Major works for roads purposes with the meaning given by section 145(3) of that Act,
d. Cleaning, placing, removing or adjusting by or on behalf of a Roads Authority (within
the meaning given by section 151(1) of the Roads (Scotland) Act 1984) of any
equipment or structure which is placed on or over a road. 
5) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where:
a. The motor vehicle is being used by a registered medical practitioner, registered nurse
or registered midwife for or in connection with the provision of urgent or emergency
health care,
b. The provision of the care would be likely to be hindered if the vehicle were not parked
on a pavement or, as the case may be, as mentioned in section 54(1),
c. The vehicle is so parked for no longer than is reasonable in connection with the
provision of the care, and
Page 84

Page 85

23 
d. No part of the vehicle is within 1.5 metres of the pavement edge which is furthest
away from the centre of the carriageway (however that edge is bounded). 
6) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where:
a. The motor vehicle is, in the course of business
i. Being used for the purpose of delivering goods to, or collecting goods from,
any premises, or
ii. Being loaded from or unloaded to any premises,
b. The delivery, collection, loading or unloading cannot reasonably be carried out
without the vehicle being parked on a pavement or, as the case may be, as
mentioned in section 54(1),
c. No part of the vehicle is within 1.5 metres of the pavement edge which is furthest
away from the centre of the carriageway (however that edge is bounded),
d. The vehicle is so parked for no longer than is necessary for the delivery, collection,
loading or unloading and in any event for no more than a continuous period of 20
minutes. 
7) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where
the motor vehicle is parked wholly within a parking place that is:
a. Authorised by order under section 32(1)(b) of the Road Traffic Regulation Act 1984,
or
b. Designated by order under section 45 of that Act. 
8) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where
the motor vehicle is parked in accordance with permission given by a constable (within the
meaning given by section 99(1) of the Police and Fire Reform (Scotland) Act 2012) in
uniform. 
9) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where:
a. The person has parked the motor vehicle for the purpose of saving life or responding
to another similar emergency,
b. The achievement of that purpose would be likely to be hindered if the vehicle were
not parked on a pavement or, as the case may be, as mentioned in section 54(1),
and
c. The vehicle is so parked for no longer than is necessary for that purpose. 
10) The Pavement Parking Prohibition and the Double Parking Prohibition do not apply where:
a. The person has parked the motor vehicle for the purpose of providing assistance at
an accident or breakdown,
b. The assistance could not be safely or reasonably provided if the vehicle were not
parked on a pavement or, as the case may be, as mentioned in section 54(1),
c. The vehicle is so parked for no longer than is necessary for that purpose, and
d. No part of the vehicle is within 1.5 metres of the pavement edge which is furthest
away from the centre of the carriageway (however that edge is bounded). 
11) In this section, “carriageway” has the meaning given by section 51(6). 
12) The Scottish Ministers may by regulations modify this section.   
Page 85

Page 86

24 
9.0 Appendix 2 – The Transport (Scotland) Act 2019 (Pavement Parking Prohibition)
(Footway and Associated Carriageway Characteristics) Directions 2022 
Page 86

Page 87

25 
10.0 Appendix 3 – Assessment Form 
Parking Standards - Road Assessments
Data Requirements/Checklist
Day Visit Night Visit
(after 1900
preferably)
Date:
Time: General Width
(m)
Minimum Width
(if different) (m)
Carriageway
Town:
Footway
North or West
(delete as
applicable)
Street:
Footway
South or East
(delete as
applicable)
Feature Yes No
Bus Stops
School vicinity
Residential Only
Shopping / 
Commerical
Mix of
Residential/Other
Cycle Lane(s)
(please provide
details e.g location
and if continuous)
Speed Limit
(mph)
Traffic Calming
(please provide
details e.g. speed
bumps,vehicle
activated sign)
Two Way or
One Way
Current waiting
restrictions Single Yellow Double
Yellow
Double Yellow
at Junction White H-Bars None
North or West
South or East
No. of Bays
North or West
South or East
North or West
South or East
North or West
South or East
Parking Bays
Loading Bays
Disabled Bays
Functionality of Road
Nature of
road
(e.g. local
access road,
distributor road)
Road Characteristics
Restriction
Current Footway
Furniture &
Ironwork
(please specify e.g.
post box, electricity
box, bins, A-boards,
Class of manhole
covers)
Comments/Details
Comments
Page 87

Page 88

26 
North or West South or East North or West South or East
No
Safe Route to School
(eis this an assessed route, if so, details
of sue and impact of any cahnge)
Double Parking
(parking more than 50cm from edge of carriageway)
No. of Instances Where <1.5m Usuable Due to Footway Parking
Minimum Clear Footway (m)
Minimum Clear Footway (m)
General Comments Following
Night Visit
(e.g. decrease in parking likely due to
opening hours of industrial park)
Additional Comments on
Observations
(e.g. presence of vulnerable road
users)
Please indicate if any of the
above vehicles were parked
on/across a dropped kerb (please
specify type of parking and no. of
instances)
Pedestrian Crossing Point
No. of Vehicles
Type of Vehicles
Driver in Attendance
Impact of Footway Parking
Legislation
(e.g. need for displacement of vehicles
onto neighbouring roads)
Potential Options
(e.g. waiting restrictions, formalise
parking, maintain status quo and
exempt)
Is there available capacity to
accommodate vehicle
displacement?
(If yes, please provide details e.g.
location(s), capacity and if pay and
display)
Day
Parking
No. of  Observed Vehicles
Type of Vehicle(s)
No. of Instances Where <1.5m Usuable Due to Footway Parking
Two-wheel Footway Parking
Night
Commerical Access
Day Night
Potential Options
Do Parked Vehicles Currently
Affect Traffic Flow?
(e.g. restricts two way flow)
Yes (please, provide details)
Nature of Observed Traffic Flow
(e.g. too low to observe two way flow
or free-flowing but need to giveway at
pinchpoints)
Residential Driveway
Type of Vehicle(s)
No. of Observed Vehicles
Four-wheel Footway Parking
Usage
Page 88

Page 89

27 
11.0 Appendix 4 – Notice of Proposals template 
DEVELOPMENT AND INFRASTRUCTURE SERVICES 
Argyll and Bute Council (C62 Oban Road) (Southern Footway) Pavement Parking
Prohibition Exemption Order 2025 
Argyll and Bute Council propose to make an Exemption Order, the effect of which will be
to exempt the southern footway on the C62 Oban road from the Pavement Parking
Prohibition.  The proposed exemption would permit footway parking from a point 75
metres west of the extended kerbline of the C62 Argyll Street to a point 125 metres west
of the extended kerbline of the C62 Argyll Street, a distance of 50 metres or thereby. 
Full details of the proposal together with a Plan, and a Statement of Reasons for
proposing to make the Exemption Order can be viewed by logging on to the Council’s
website at www.argyll-bute.gov.uk or viewed during normal office hours at the following
locations: 
1. Customer Service Point, 1a Manse Brae, Lochgilphead, between the hours of
0900 and 1200
2. Argyll and Bute Council Offices, Kilmory Castle, Kilmory, Lochgilphead, between
the hours of 0900 and 1700 
Any person wishing to make representations to the proposed exemption may do so by
sending details of the grounds for representation, in writing, providing their name and
address, to the Head of Legal & Regulatory Support, Argyll and Bute Council, Kilmory,
Lochgilphead, Argyll, PA31 8RT, by [28 days minimum from date of publication of notice] 
Head of Roads & Infrastructure Services, Kilmory Castle, Kilmory, Lochgilphead,
PA31 8RT               
Page 89

Page 90

28 
12.0 Appendix 5 – Statement of Reasons template 
DEVELOPMENT AND INFRASTRUCTURE SERVICES 
Argyll and Bute Council (C62 Oban Road) (Southern Footway) Pavement Parking
Prohibition Exemption Order 2025_ 
Statement of Reasons for proposing to make the Exemption Order 
The above-named Exemption Order is proposed for facilitating the free flow of vehicular
traffic on the road to which the order relates. 
Head of Roads & Infrastructure Services, Kilmory Castle, Kilmory, Lochgilphead,
PA31 8RT 
Page 90

Page 91

29 
13.0 Appendix 6 – Form of Order and Plan 
Argyll and Bute Council (C62 Oban Road) (Southern Footway) Pavement Parking
Prohibition Exemption Order 2025 
Argyll and Bute Council in exercise of the powers conferred on them by the Transport
(Scotland) Act 2019, Part 6 and having complied with The Pavement Parking Prohibition
(Exemption Orders Procedure) (Scotland) regulations 2022, hereby make the following Order: 
1. This Exemption Order may be cited as “Argyll and Bute Council (C62 Oban Road)
(Southern Footway) Pavement Parking Prohibition Exemption Order 2025” and shall
come into operation on Monday the twenty fourth of March Two Thousand and
Twenty-Five. 
2. Interpretation 
a. The Interpretation Act 1978 shall apply for the interpretation of this Order as it 
applies for the interpretation of an Act of Parliament. 
b. In this Order, except where the context otherwise requires, the following
expressions have the meanings hereby respectively assigned to them:
▪ “the 2019 Act” means the Transport (Scotland) Act 2019; 
▪ “the 1984 Act” means the Road Traffic Regulation Act 1984; 
▪ “the 1991 Act” means the Road Traffic Act 1991; 
▪ “the 2022 Regulations” means The Pavement Parking Prohibition
(Exemption Orders Procedure) (Scotland) Regulations 2022; 
▪ “the 2023 Regulations” means The Parking Prohibitions (Enforcement
and Accounts) (Scotland) Regulations 2023; 
▪ “authorised enforcement officer” has the same meaning as in Section
58(6) of the 2019 Act; 
▪ “contravention” means, as the case may be, a contravention of the
pavement parking prohibition, as s50(1) of the 2019 Act; 
▪ “Council” means Argyll and Bute Council constituted under the
provisions of the Local Government etc (Scotland) Act 1994 and having
its Chief Office at Kilmory, Lochgilphead, Argyll, PA31 8RT; 
▪ “driver” means the person driving or having control or charge of the
vehicle at any given time and in particular in relation to a vehicle waiting
on a road the person driving at the time it was left in that location; 
▪ “enforcement notice” means a notice served under regulation 5 or 6 of
the 2023 Regulations; 
▪ “pavement parking” means a footway as defined with s151(2) of the
Roads (Scotland) Act 1984; 
Page 91

Page 92

30 
▪ “plan” means the plan annexed to this Exemption Order and which
forms part of this Exemption Order. 
▪ “registered keeper” means, in relation to a penalty charge imposed in
connection with a motor vehicle, the person in whose name the vehicle
is registered under the Vehicle Excise and Registration Act 1994 at the
time of the contravention to which the penalty charge relates. 
▪ “relevant vehicle” means the motor vehicle in respect of which the
contravention occurred. 
▪ “schedule” means the schedule annexed to this Exemption Order and
which forms part of this Exemption Order. 
c. In so far as any provision of this Exemption Order conflicts with any provision
which is contained in an Exemption Order made or having effect as if made
under the 2019 Act or by or under any other enactment, then the provisions of
this Exemption Order shall prevail. 
Pavement Parking Exemption 
3. The section of footway specified in the Schedule to this Exemption Order is exempted
from the pavement parking prohibition. 
4. The limits of the exempted footway shall be indicated in such manner as the Council
may determine by lines or other indications.  Markings and signs shall be compliant
with The Traffic Signs Regulations and General Directions 2016. 
Manner of standing within the exempted areas 
5. A vehicle parked on an exempted footway shall park within the marked area.  No part
of the vehicle shall park on the marked lines or beyond the permitted parking area. 
Responsibility of Registered Keeper 
6. The responsibility for payment of any penalty charge rests with the registered keeper. 
If the registered keeper was not the driver at the time when it was parked out with the
permitted parking area specified in the schedule in contravention of any of the
provisions of this Order it remains her/his responsibility to pay the penalty charge. 
Contravention of this Order 
7. If a vehicle is parked in contravention of any of the Articles, provisions and
requirements of this Order then a contravention shall have occurred, and a penalty
charge shall be payable. A penalty charge notice may then be issued by a parking
attendant. 
8. Where a vehicle remains in a position so as to incur a penalty charge on the issue of a
penalty charge notice, a further penalty charge notice may be issued on each calendar
day thereafter. 
Sealed with the Common Seal of the Argyll and Bute Council and subscribed for them and on
their behalf by David Logan, Head of Legal & Regulatory Support, Argyll and Bute Council,
Page 92

Page 93

31 
Kilmory, Lochgilphead, Argyll, PA31 8RT at Lochgilphead on Monday Twenty Fourth day of  
March 2025 
Signed ……………………………………………… 
Date    ……………………………………………… 
This is the Schedule referred to in the foregoing Exemption Order the “Argyll and Bute Council
(C62 Oban Road) (Southern Footway) Pavement Parking Exemption Order 2025“ 
SCHEDULE
PAVEMENT PARKING PROHIBITION EXEMPTION 
Length of Road in Lochgilphead Side of road to which
the restriction applies
From a point 75 metres west of the extended kerbline of the C62
Argyll Street to a point 125 metres west of the extended kerbline
of the C62 Argyll Street, a distance of 50 metres or thereby.
South   
Signed ……………………………………………… 
Date    ……………………………………………… 
Page 93

Page 94

32 
This is the Schedule referred to in the foregoing Exemption Order the “Argyll and Bute Council (C62 Oban Road) (Southern Footway)
Pavement Parking Prohibition Exemption Order 2025” 
Page 94

Page 95

33 
14.0 Appendix 7 – Notice of Making an Exemption Order template 
DEVELOPMENT AND INFRASTRUCTURE SERVICES 
Argyll and Bute Council (C62 Oban Road) (Southern Footway) Pavement Parking
Prohibition Exemption Order 2025 
On Monday 24 February 2025, Argyll and Bute Council made the above named 
Exemption Order in terms of the Transport (Scotland) Act 2019. 
The Exemption Order, which comes into effect on Monday 24 March 2025, permits motor
vehicles to park on the southern footway of the C62 Oban Road.  The exemption is from a
point 75 metres west of the extended kerbline of the C62 Argyll Street to a point 125
metres west of the extended kerbline of the C62 Argyll Street, a distance of 50 metres or
thereby. 
A copy of the Exemption Order and companying plan [where there has been a Hearing,
add also the report] can be inspected by logging on to the Council’s website at
www.argyll-bute.gov.uk or viewed during normal office hours at the following locations: 
1. Customer Service Point, 1a Manse Brae, Lochgilphead, between the hours of
0900 and 1200
2. Argyll and Bute Council Offices, Kilmory Castle, Kilmory, Lochgilphead, between
the hours of 0900 and 1700 
Head of Roads & Infrastructure Services, Kilmory Castle, Kilmory, Lochgilphead,
PA31 8RT 
Page 95

Page 96

34 
15.0 Appendix 8 - Route A – PCN Issued under Regulation 4 
PCN issued by
enforcement
officer               
No payment
received within 28
days       
Representation
correspondence
received (within 28
days) 
Payment received
-  (if within 14 days
50% discount
applied) - Case
Ended                                         
DVLA enquiry for
keeper details    
Accept
Representation      
Reject
Representation                                     
Issue Enforcement
Notice (within 28
days of
contravention or
within 14 days of
DVL supplying
relative
information    
Issue Notice of
Acceptance -
Case Closed      
Issue Notice of
Rejection                                       
Payment
Received - Case
Closed  
If no response
within 28 days
increase Charge
and issue Charge
Certificate    
If no appeal within
28 days increase
Charge and issue
Charge Certificate     
Appeal to First-tier
Tribunal within 28
days  
Payment
Received - Case
Ended   
Payment
Received - Case
Closed  
If no payment
received within 28
day, proceed to
collective action  
If no payment
received within 28
day, proceed to
collective action 
Appeal rejected /
withdrawn & no
further appeal to
Upper Tribunal
within 28 days      
Appeal Rejected &
Further appeal to
Upper Tribunal 
Appeal Upheld -
Case Ended                             
Increase Charge
and issue Charge
Certificate    
Upper Tribunal
Appeal Rejected  
Upper Tribunal
Appeal Upheld -
Case Ended 
If no payment
received within 28
day, proceed to
collective action  
Payment
Received - Case
Ended  
Increase Charge
and issue Charge
Certificate     
If no payment
received within 28
day, proceed to
collective action  
Payment
Received - Case
Ended   
Page 96

Page 97

35 
This page is intentionally blank 
Page 97

Page 98

36 
16.0 Appendix 9 - Route B – PCN Issued under Regulation 5        
Prevented from issuing PCN when preparation already
underway                                       
DVLA application for keeper details (within 14 days of
contravention)                                       
Issue Enforcement Notice by recorded delivery (within 28
days of contravention or within 14 days of DVLA supplying
relative information                                                                                 
No payment received within 28 days       Representation correspondence
received within 28 days 
Payment
Received - Case
Ended                                                                   
Increase Charge
and issue Charge
Certificate  
Accept
Representation        
Reject
Representation                                                                     
Payment
Received - Case
Ended 
If no Payment
Received within
28 days, proceed
to collective action 
Issue Notice of
Acceptance -
Case Ended        
Issue Notice of
Rejection                                       
If no appeal within
28 days increase
Charge and issue
Charge Certificate       
Appeal to First-tier
Tribunal within 28
days 
Payment
Received - Case
Ended 
If no Payment
Received within
28 days, proceed
to collective action 
Appeal rejected /
withdrawn & no
further appeal to
Upper Tribunal
within 28 days      
Appeal Rejected &
further appeal to
Upper Tribunal  
Appeal Upheld -
Case Ended 
Increase Charge
and issue Charge
Certificate    
Upper Tribunal
Appeal Rejected  
Upper Tribunal
Appeal Upheld -
Case Ended 
If no Payment
Received within
28 days, proceed
to collective action  
Payment
Received - Case
Ended 
Increase Charge
and issue Charge
Certificate                                 
If no Payment
Received within
28 days, proceed
to collective action  
Payment
Received - Case
Ended 
Page 98

Page 99

37 
Page 99

Page 100

This page is intentionally left blank

Page 101

Appendix 2 – Sample Request Form 
Argyll and Bute Council  - Request a pavement parking exemption assessment 
Part 6 of the Transport (Scotland) Act 2019 introduced the statutory framework for a national
ban on pavement parking, double parking and parking at dropped kerbs (at known crossing
places) to make it easier for local authorities to ensure our pavements and roads are safer
and more accessible to all. 
Some exemptions apply to the pavement parking ban, such as: 
• To allow for the normal operation of the emergency services, or medical practitioners
in emergency situations
• To allow the response to an emergency or accident
• To allow for certain deliveries and collections
• Vehicles used for undertaking works on roads or removal of obstructions 
These exceptions are only valid if specific criteria is met and there is no other reasonable
parking available. Full details of the exceptions are contained within the 2019 Act. 
Local Authority Exemptions 
The Local Authorities in Scotland have powers to exempt certain areas of pavement from the
national ban, should they feel it necessary. 
In general, local authorities can consider an exemption only where one of two criteria are
met. 
An area of pavement can only be considered for exemption if: 
1. its layout or character would allow for a width of 1.5 metres of the footway to remain
unobstructed when any part of a vehicle is parked on it, or
2. the layout or character of the carriageway associated with the footway is such that
the passage of an emergency vehicle would be impeded by the presence of a vehicle
parked on the carriageway. 
Be aware that an exemption must apply at all times and for any class of vehicle.  
Please use this form to request an assessment for an exemption from the pavement parking
ban for a pavement or section of a pavement within Argyll and Bute Council area.   
In order to consider an assessment, we require you to provide the following details.  We are
requesting a contact phone number and/or email to allow staff to contact you should the
details provided be insufficient to identify the requested location. 
1. Where would you like an assessment for an exemption to be carried out? 
2. Please provide street name, if known: 
3. Please provide a location description: 
Page 101

Page 102

Appendix 2 – Sample Request Form 
4. As noted above, an area of pavement can only be considered for exemption if: 
i. its layout or character would allow for a width of 1.5 metres of the footway to
remain unobstructed when any part of a vehicle is parked on it, or
ii. the layout or character of the carriageway associated with the footway is such
that the passage of an emergency vehicle would be impeded by the presence
of a vehicle parked on the carriageway. 
Does the area of pavement you are requesting be assessed allow for a width of 1.5
metres of the footway to remain unobstructed when any part of a vehicle is parked on
it? (tick as appropriate) 
Yes 
No 
Maybe 
Page 102

Page 103

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND  
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
TRUNK ROAD LITTER MANAGEMENT RESPONSIBILITIES A82, A83, A85, A828 
1.0 EXECUTIVE SUMMARY 
1.1 This report has been drafted following correspondence received from East
Lothian Council seeking support from COSLA and other local authorities with
truck roads within their areas for a national review of trunk road litter
management responsibilities. This report recommends that Argyll and Bute
Council support the concept of a national review. 
1.2 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) Agree that the Chief Executive writes to Scottish Ministers requesting a review
of litter management responsibilities for the trunk roads within Argyll and Bute
(A82, A83, A85, A828)
b) Agree that the Chief Executive confirms to those other local authorities with
trunk road litter management responsibilities and COSLA that Argyll and Bute
Council support the proposal initially raised by East Lothian Council that there
should be a review of litter management responsibilities for trunk roads across
Scotland. 
Page 103 Agenda Item 6

Page 104

ARGYLL AND BUTE COUNCIL     ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 September 2025 
TRUNK ROAD LITTER MANAGEMENT RESPONSIBILITIES A82, A83, A85, A828 
2.0 INTRODUCTION 
2.1 This report has been drafted following correspondence received from East
Lothian Council seeking support from COSLA and other local authorities with
truck roads within their areas for a national review of trunk road litter management
responsibilities.
2.2 East Lothian Council, at it’s meeting on 29th April 2025, agreed recommendations
in relation to the trunk road within their area as follows: 1) That the Chief Executive
writes to Scottish Ministers requesting a review of litter management
responsibilities for the full section of the A1 and a move towards consistency with
areas part of the special roads order to allow the Council to focus resources on
population centres, local road network and area of ownership/responsibility. 2)
That the Chief Executive writes to other local authorities with trunk road litter
management responsibilities and COSLA, providing information on the local
context and seeking support for the requested review.
2.3  In response to the request from the Chief Executive of East Lothian Council that
Argyll and Bute consider supporting the request for a national review of trunk litter
management responsibilities officers have considered the issues and are now
seeking Member support to the recommendations set out this report. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) Agree that the Chief Executive writes to Scottish Ministers requesting a review
of litter management responsibilities for the trunk roads within Argyll and Bute
(A82, A83, A85, A828)
Page 104

Page 105

b) Agree that the Chief Executive confirms to those other local authorities with
trunk road litter management responsibilities and COSLA that Argyll and Bute
Council support the proposal initially raised by East Lothian Council that there
should be a review of litter management responsibilities for trunk roads across
Scotland. 
4.0 DETAIL 
4.1 Council resource relating to cleansing and litter management is contained
within the Operations, Roads and Infrastructure Services budgets. There is no
specific allocation of budget explicitly for litter prevention or collection along
the trunk road network. Litter is not caused by the Council but by the
behaviour of individuals. This contributes to the pressures on local services. 
4.2 Cleansing and litter picking services prioritise areas based on the factors
identified in the Act with a focus on population centres and areas of highest
footfall. 
4.3 Due to the speed and volume of traffic litter picking at the side of trunk roads
presents a generally higher level of safety risk to Council staff than does litter
picking at the side of Council managed roads, many of which have slower
average traffic speeds and where litter picking is almost entirely focused on
the points that these roads travel through centres of population. As a
consequence the measures required to ensure the safety of Council staff
during these activities are more costly. As the Council only undertakes litter
picking and not any other maintenance activities it is not often possible to co-
ordinate litter picking with other maintenance activities that could be done
jointly under one set of traffic management and thereby increase the efficiency
and cost effectiveness of the operations overall.
4.4 A national review of litter picking responsibilities in relation to trunk roads
would create the opportunity to consider whether the current approach
whereby local Councils undertake this duty offers the best value for money
overall to the public purse. Or whether transferring this duty to the companies
contracted by Transport Scotland to manage and maintain the truck road
network could offer improved efficiencies while also enabling Councils to
focus our available resources on local priorities.
4.5 The Council has received correspondence that demonstrates at least one
other Council, Dumfries and Galloway, have written to Scottish Ministers
supporting a request for a national review of litter picking responsibilities in
relation to trunk roads. 
Page 105

Page 106

5.0 CONCLUSION
5.1 This Report seeks to approval to request of Scottish Ministers a national review
of duties in relation to litter picking at trunk roads. 
6.0 IMPLICATIONS
6.1 Policy – The recommendations in this report aim to support the Council to
better fulfil duties under the Environmental Protection Act 1990: Code of
Practice on Litter and Refuse (CoPLAR).
6.2 Financial – The recommendations in this report are unlikely to lead to budget
savings.
6.3  Legal – Any legal implications would be required to be considered as part of
the proposed national review.
6.4  HR –  None identified at this time.  
6.5 Customer service – None identified at this time.  
6.6  Risk – None identified at this time.  
6.7  Climate change – None identified at this time.  
6.8  Fairer Scotland Duty - None identified at this time.  
6.9  Equalities: protected characteristics – None identified at this time.  
6.10  Consumer duty – None identified at this time.  
6.11  Island communities – None identified at this time.  
6.12 Children’s Rights and Wellbeing – None arising directly from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and 
Infrastructure
Councillor John Armour, Policy Lead for Roads, Transport and Amenity 
Services 
June 2025                                                  
For further information contact:
Andy Summers, Head of Roads and Infrastructure Service 
Andy.Summers@argyll-bute.gov.uk 
Appendix 1 – Letter from East Lothian Council to Cabinet Secretary for Transport 
Page 106

Page 107


John Muir House
Haddington
East Lothian
EH41 3HA
Tel 01620 827827
eastlothian.gov.uk 
Our Ref: LR/EH/090525 
9 May 2025 
Ms F Hyslop MSP
Cabinet Secretary for Transport
The Scottish Parliament
Edinburgh 
Via email: Fiona.Hyslop.msp@parliament.scot 
Dear Ms Hyslop 
Re: A1 Road Network – Litter Management Responsibilities 
Under the Environmental Protection Act 1990: Code of Practice on Litter and Refuse
(CoPLAR), the Council understands its duty to ensure land under our control is kept
clear of litter and ensure public roads, for which the Council are responsible, are kept
clean, so far as is practicable.   
At East Lothian Council on 29th April 2025, a report regarding Litter Management
Responsibilities on the A1 Road Network was considered and available here - A1
Road Network - Litter Management Responsibilities. 
The majority of the A1 in East Lothian has been delivered under special orders with
Scottish Ministers (and their appointed contractor currently BEAR Scotland)
responsible under the Act.  There are two sections not part of the special roads order: 
a. From the border with Edinburgh Council to Old Craighall.
b. From Thistly Cross to the border with Scottish Borders Council. 
The Council has maintenance responsibility of section a. above as Roads Authority. 
Section b. is not held in Council ownership and there is no responsibility for roads
maintenance, repairs or grass cutting which is undertaken by BEAR Scotland.   This
section has therefore not been zoned by the Council; however, the Council undertakes
litter management by default as it has not been included in the special order contract. 
Council resource relating to cleansing and litter management is contained within the
Amenity Services, Environmental Health and Community Protection budgets.  There
is no specific allocation of budget explicitly for litter prevention strategies and the
Council will determine priority of spend from within available resource on a case-by-
case basis. 
Litter is not caused by the Council but by the behaviour of individuals. This contributes
towards the pressures on local services. 
Page 107

Page 108

As a local authority experiencing significant housing and population growth set in
National Planning Frameworks, the demand for our Services continue to grow.  This
is expected to impact our future capacity required to adhere to the standards identified
based on the range of priorities and areas requiring attention under the act.  We
prioritise areas based on the factors identified in the act with a focus on population
centres of high footfall.   
The provision of additional local resource is extremely challenging within the current
backdrop of public sector finance, and it is therefore likely that any future expenditure
on litter prevention and clearance will be required to be managed within existing
resource. 
The Council is part of an A1 Litter Coordination Group organised in conjunction with
BEAR Scotland, Transport Scotland, City of Edinburgh Council and Scottish Borders
Council. 
We have worked in collaboration to undertake litter picks of section b. (above) in March
2023, April 2024 and April 2025.   
The Council has a regularly reviewed risk assessment for litter picking and a Safe
Operating Procedure (SOP) for this task on the A1.  Bins are strategically located in
laybys and cleared daily by Council staff.  Litter picking verges adjacent to the A1
carriageway carries a higher risk to staff than other areas due to the proximity to and
speed of traffic. Measures including lane closures have been identified as required
mitigations under the Council SOP.  Transport Scotland have funded lane closures
solely for the purpose of litter management to allow the Council’s safe operating
procedure to be adhered to.   
BEAR Scotland undertake litter management on the rest of the A1 between Old
Craighall and Thistly Cross.  The BEAR risk assessment allows the specialist road
contractor to undertake litter picking on other sections without the need for a lane
closure or in conjunction with other cyclical maintenance and planned closures for
other purposes. 
At Council on 29th April, it was agreed to write requesting a review of responsibilities
for the full section of the A1.  We would welcome a move towards consistency with
areas part of the special roads order and the transfer of litter management to the
specialist road contractor BEAR.  This would allow the Council to focus resources on
population centres, local road network and area of ownership and responsibility.   
Under the current arrangements, having different operators on the trunk road presents
logistical and practical challenges.  A Review may wish to consider whether the current
model and responsibilities creates a higher combined cost across public sector
agencies and best use of resources. 
Sections of the A1, and other trunk roads sit within Scottish Local Authority
boundaries.  A review may consider a consistent approach across all trunk roads.  I
have therefore copied this letter to other Local Authority Chief Executives and COSLA
who may wish to consider their local context and provide additional information
regarding this subject.  
Page 108

Page 109

I trust that the information contained within this letter helps provide the context.  We
are happy to engage in further dialogue with partners to consider this matter and look
forward to your response. 
Yours sincerely 
Laurence Rockey
Chief Executive 
c.c    Councillor Norman Hampshire, Council Leader
Paul McLennan, MSP
Colin Beattie, MSP
Martin Whitfield, MSP
Craig Hoy, MSP
Chief Executives – Scottish Local Authorities
Chief Executive - COSLA
Chief Executive – Transport Scotland
Page 109

Page 110

This page is intentionally left blank

Page 111

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &  
INFRASTRUCTURE COMMITTEE 
ROADS & INFRASTRUCTURE SERVICES                                11 SEPTEMBER 2025 
TEMPORARY TRAFFIC REGULATION ORDERS – REVIEW OF CHARGING AND
ADVERTISING 
1.0 EXECUTIVE SUMMARY
1.1 The Environment, Development and Infrastructure Committee, at its meeting
held on 19 June 2025 agreed: 
I. that officers carry out a review of the event application costs associated
with Temporary Traffic Regulation Order (TTRO) charges and advertising.
II. that a report outlining the scope and methodology of that review, including
engagement with event organisers, would be reported to the next
Environment, Development and Infrastructure Committee; and
III. that the current Fees and Charges in relation to TTROs for events are
suspended and the loss of income estimated to be up to £45,000 in
2025/26 is funded from the Priorities Investment Fund 
1.2 This report provides Members with an update on the above decision including a
background on the current TTRO charges and setting out two options as the
basis for engagement with event organisers. 
1.3 The report provides an initial “desktop” options appraisal for Members to
consider and sets out a questionnaire for the engagement exercise. 
RECOMMENDATIONS 
1.4 The Committee are asked to: - 
i. agree to the outline options as the basis for consultation with event
organisers and community councils.
ii. agree that the questionnaire attached in Appendix 2 is used to gather the
organisers and community councils views on these options.
iii. Agree that the consultation period is a minimum of six weeks.
iv. Note that the results are expected to be reported to the Committee by 
March 2026; however, subject to analysis being completed sooner, may
be reported to the Committee by December 2025. 
v. agree that the minimum timescales for application for TTROs or
Temporary Restriction by Traffic Notice (TRTNs) are those listed in the
end columns of Appendix 3.
Page 111 Agenda Item 7

Page 112

vi. agree that the list below are the newspapers which will be used to
advertise the notice of TTROs.
a. Argyllshire Advertiser
b. Dunoon Observer
c. Helensburgh Advertiser
d. Oban Times
e. Campbeltown Courier 
Page 112

Page 113

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT &
INFRASTRUCTURE COMMITTEE 
ROADS & INFRASTRUCTURE SERVICES            11 SEPTEMBER 2025 
TEMPORARY TRAFFIC REGULATION ORDERS – REVIEW OF CHARGING AND
ADVERTISING 
2.0 INTRODUCTION
2.1  This report provides Members with a background on the current TTRO charges
and sets out two options as the basis for engagement with event organisers.
2.2 The report provides an initial “desktop” options appraisal for Members to consider
and sets out a questionnaire for the engagement exercise. 
3.0 RECOMMENDATIONS
3.1 The Environment, Development and Infrastructure Committee are asked to: - 
i. agree to the outline options as the basis for consultation with event
organisers and community councils.
ii. agree that the questionnaire attached in Appendix 2 is used to gather the
organisers and community councils views on these options.
iii. Agree that the consultation period is a minimum of six weeks.
iv. Note that the results are expected to be reported to the Committee by 
March 2026; however, subject to analysis being completed sooner, may
be reported to the Committee by December 2025. 
v. agree that the minimum timescales for application for TTROs or
Temporary Restriction by Traffic Notice (TRTNs) are those listed in the
end columns of Appendix 3.
vi. agree that the list below are the newspapers which will be used to
advertise the notice of TTROs.
a. Argyllshire Advertiser
b. Dunoon Observer
c. Helensburgh Advertiser
d. Oban Times
e. Campbeltown Courier 
Page 113

Page 114

4.0 DETAIL
4.1   The Environment, Development and Infrastructure Committee, at its meeting held
on 19 June 2025 agreed:
i. that officers carry out a review of the event application costs associated
with TTRO charges and advertising.
ii. that a report outlining the scope and methodology of that review, including
engagement with event organisers, would be reported to the next
Environment, Development and Infrastructure Committee; and
iii. that the current Fees and Charges in relation to TTROs for events are
suspended and the loss of income estimated to be up to £45,000 in
2025/26 is funded from the Priorities Investment Fund.
4.2 The last point above has been introduced already and is in place for this financial
year, the remainder of this report focusses on points (i) and (ii).  The report aims
to:
• set out the current level of charges
• the impact of events on staff resource
• outline information pertinent to any further review of charges and 
• to offer initial options for consideration by the Committee.
4.3  Officers have carried out a “desktop” review of the current level of charges.  This
includes a benchmarking exercise, comparing our current level of charges to 12
other Local Authorities.  It should be noted that from the information gathered
from other local authorities there is no single approach to how TTRO charges
are set and there is no ‘national guidance’ or regulations regarding this.
4.4 The team responsible for Traffic Regulation Orders (TROs), Temporary Traffic
Regulation Order (TTROs) and Temporary Restriction by Traffic Notice (TRTNs)
has only two members of staff.  The senior officer is graded at LGE11 and the
assistant is graded at LGE7.  The gross cost to the Council (excluding
departmental overheads), including Superannuation and National Insurance, for
the team is £100,219 per annum.  Excluding advertisement fees, the income
from TTROs and TRTNs (averaged over the period 2022-2024) is £80,486. 
Advertisement fees are excluded from this calculation as the service charges
these to applicants at net cost (i.e. they pay what we are charged by the
newspapers).  
4.5 The Road Traffic Regulation Act 1984 (RTRA 1984) provides power to
roads/traffic authorities to place temporary restrictions on the road under S14
and S16A.  Broadly, these are implemented through either a TRTN or a TTRO.
A TRTN is restricted to a maximum 5-day duration and are used for road works. 
A TTRO can be used to implement restrictions for either roadworks or an event
(the first under s14, the second under s16A).
4.6 Whilst the RTRA 1984 provides the power to restrict or prohibit use of a road,
roads authorities use these for several purposes.  This includes assuring safe
passage of traffic (including pedestrians) and ensuring road safety is maintained
through effective and proportionate traffic management.  The roads authority
Page 114

Page 115

must be satisfied that any TTRO, for events, is provided to allow the event to
proceed with sufficient measures in place to ensure the safety of those attending
the events and those affected by the event. 
4.6 Benchmarking Argyll and Bute Council to 12 other Local Authorities which had
charging details readily available on their websites, we have averaged the
charges and highlighted them in Table 1, below.  Also included, in the bottom
line, is an adjustment made for advertisements (3 of the 12 benchmarked LAs
absorb the advertisement charges within their costs).  The adjustment figure is
£270, which is the average cost of advertisement within Argyll and Bute area in
2024 (note, adverts are only charged for TTROs).  Finally, Argyll and Bute
Council appear to be the only LA (certainly within the group compared against)
which offers a discount for annual events in their 2nd year, and thereafter. 
Table 1 TTRO
TTRO for
Annual Events
(2nd year and
thereafter) 
Extension
of TTRO TRTN
Argyll and Bute Council £1,180 £591 £591 £591
Average charges comparator £1,429 - £858 £659
Average charges comparator
with advertisement adjustment £1,367 - - - 
4.7 There are some standouts, however, that should be highlighted.  
• Moray Council offer a unique set of charges to events. 
o Commercial events £252
o Community events £120
o Street parties / parades £27
o Remembrance Day Services are free
o It’s not clear if advertisements are charges for separately or
absorbed by the council. 
• Edinburgh City Council offer the highest charges across the comparison
group
o Small event £2,500
o Medium event £3,000
o Large event £4,000
o Complex event £6,000
o Advertisements are charged in a similar way to Glasgow City
Council and ABC
• Glasgow City
o Events £3,009
o The above figure is not inclusive of adverts
4.8 Organisations requesting the waiving of charges for their event often cite that
they are a Registered Charity.   The Scottish Charity Regulator (OSCR, OSCR |
Home) notes that all charities in Scotland must meet the “charity test”, including
the fulfilment of defined “charitable purposes”.  Appendix 1 contains detail on
what these are but can also be found on the OSCR website.  
Page 115

Page 116

4.9 Appendix 1 highlights the breadth of activities which Registered Charities can
carry out.  Should a view be taken that fees should be waived for charities, very
few or no events would be subject to any charge.  In this case, to fully recover
staff costs, s14 TRTNs & TTROs would need to be increased by 192.5%. 
Officers view is that this would place an unfair burden to Statutory Undertakers
and others, and as such no option regarding this has been proposed.  The other
point to be aware of is that if events charges are reduced to nil or close to nil, it is
likely the service would receive an upsurge in the number of events.  While this
might be beneficial to the economy and communities, it would be unachievable
for the existing staff resource to deliver, as it has been resourced to meet current
demand.
4.10 There has also been correspondence submitted to the Council over the use of
community newspapers / newsletters rather than the traditional local
newspapers. It remains the view of officers that the recognised local papers
(listed below) continue to be used but note that, where appropriate, the
community newspapers and newsletters may be used in addition to them
dependent on the scale and impact of the proposed event. While community
newpapers/letters may be more widely read within a community, the local
newspapers cover a much wider geographical area.  A good example of this is
the Helensburgh Advertiser which covers Arrochar, Luss, Rosneath,
Garelochhead as well as Helensburgh and its close environs.  An event with
closures held in Helensburgh could impact these outlying areas, as residents
may shop or work within Helensburgh and need to be aware of any closures or
restrictions which may affect their journey.
• Local newspaper:
o Argyllshire Advertiser
o Dunoon Observer
o Helensburgh Advertiser
o Oban Times
o Campbeltown Courier
4.11 The initial desktop review of charging proposes two options, as outlined below.  It
is proposed that these models form the basis of the further review with event
organisers and community councils.  The questionnaire, under Appendix 2, is
used to garner views on the proposals.
4.12 Option 1 is to maintain the status quo but amending the fees & charges to clarify
no events are exempt (including Oban Charities Day).  
4.13 Option 2 seeks to rebalance costs and clarify timescales.  The detail is contained
within Appendix 3, but briefly, where proper notice is given by the applicants (4
weeks for TRTN, 6 weeks for a s14 TTRO and 12 weeks for a s16A TTRO), they
pay the minimum cost, however; each weekly reduction in the application period
for the event date results in a 25% increase in the charge.  Note, there are
minimum timescales which officers cannot reduce further without placing an
unreasonable pressure on a very small staff resource (two officers) or risking a
breach of the legislative requirements for advertisement, Notice and consultation. 
The 25% increase is on the baseline figure (not 25% on each subsequent
Page 116

Page 117

increase) but is for illustrative purposes only, i.e. this figure is not set in stone but
is open for discussion.  The principal reason for the weekly increase is to
encourage applicants to apply for restriction as early as possible to allow a
limited staff resource to manage the workload effectively and to minimise the risk
of refusal by the Council due to legislative restrictions.  The charges are all
exclusive of advertisement charges.
4.14 Subject to the approval of the Committee, it is intended to commence the
consultation by the end of September 2025.  The consultation is expected to last
for a minimum of six weeks inline with advice from the Communications team. 
Following the consultation, a full analysis of submissions will be carried out and
the results are expected to be reported back to the Committee by March 2026.  If
analysis is complete sooner, the results may be reported to the Committee at its
meeting in December 2025. 
4.15 Lastly, s16A (events) TTROs sometimes require consent from Scottish Ministers
(with Transport Scotland acting on their behalf). This is set out in the Road
Traffic Regulation Act 1984 but is summarised in the list below but “iv” is the
most common reason for application.  Transport Scotland require a minimum of
4 weeks to consider the application.
i. When the closure includes a request to restrict a trunk road or motorway,
for which the Scottish Ministers are the traffic authority.
ii. When the order will be in force for more than three days.
iii. When an existing order is required to continue for longer than the
anticipated period, Scottish Ministers may direct that an order can
continue in force.
iv. When the closure relates to the same length of road which has been
subject to a previous section 16 order, within the same calendar year
5.0 CONCLUSION
5.1 The Environment, Development and Infrastructure Committee are requested to
agree to the outline options as the basis for consultation with event organisers
and community councils, note the consultation period & reporting timescales,
and agree that the questionnaire attached in Appendix 2 is used to gather the
organisers views of the same.
5.2 The Environment, Development and Infrastructure Committee are requested to
agree that while additional community based newspaper / newsletters may be
used from time to time as additional media, the list below contains the
newspapers used for advertisement for notices of TTROs.
o Argyllshire Advertiser
o Dunoon Observer
o Helensburgh Advertiser
o Oban Times
o Campbeltown Courier 
Page 117

Page 118

6.0 IMPLICATIONS
6.1 Policy – No current policy for TTROs or TRTNs.  There is a procedural
document (“Traffic Regulation Orders Procedural Document”) which may
require amendments to reflect changes over the last number of years
(including legislative amendments).  
6.2 Financial –  The Service needs to ensure staff and third party costs are
recovered as far as practicable.   
6.3  Legal –  None.
6.4  HR – None, provided any loss of income is covered by other funding, however
if this is not covered then staff costs will not be met for the relevant
post(s) 
6.5 Customer service – Fees & Charges, events guidance and websites will need
to be amended following the conclusion of the review. 
6.6  Risk – Potential financial damage to the Council through loss of income, 
should costs not be recovered.   Reputational damage is also possible from
both event organiser and  statutory undertakers should they consider they are
being treated unfairly or carrying disproportionate charges.  
6.7  Climate change – n/a. 
6.8  Fairer Scotland Duty – None known. 
6.9  Equalities: protected characteristics – None known. 
6.10  Consumer duty – None. 
6.11  Island communities – None.   
6.12 Children’s Rights and Wellbeing – None known. 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour
July 2025                                                 
For further information contact: 
Stuart Watson, Assistant Network & Standards Manager
stuart.watson@argyll-bute.gov.uk 
Hugh O’Neill – Network & Standard Manager
Page 118

Page 119

hugh.oneill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Charity Test and Purposes 
Appendix 2 – Questionnaire 
Appendix 3 – Option 2, Fees & Charges
Page 119

Page 120

Appendix 1 – Charity Test and Purposes 
Charity Test:
• Have only charitable purposes
• Provide public benefit
• Use their funds and property only for charitable purposes
• Allow fair access to the benefit they provide
• Not be, or exist to advance, a political party.
Charitable Purposes:
a. The prevention or relief of poverty
b. The advancement of education
c. The advancement of religion
d. The advancement of health
e. The saving of lives
f. The advancement of citizenship or community development
g. The advancement of the arts, heritage, culture or science
h. The advancement of public participation in sport
i. The provision of recreational facilities, or the organisation of
recreational activities, with the object of improving the conditions of life
for the persons for whom the facilities or activities are primarily intended
j. The advancement of human rights, conflict resolution or reconciliation
k. The promotion of religious or racial harmony
l. The promotion of equality and diversity
m. The advancement of environmental protection or improvement
n. The relief of those in need by reason of age, ill health, disability,
financial hardship or other disadvantage
o. The advancement of animal welfare
p. Any other purpose that may reasonably be regarded as analogous to
any of the preceding purposes 
Page 120

Page 121

Appendix 2 - Questionnaire 
Argyll & Bute Council
Roads & Infrastructure Services 
Review of Fees & Charges for Events   
The Environment, Development & Infrastructure Committee, at its meeting held on 11
September 2025 agreed to review the fees & charges structure for events (charges for
Temporary Traffic Regulation Orders (TTROs)) This questionnaire seeks to gather views
on the options outlined below and your response is vital to allow a thorough and robust
exercise to be completed. 
Note – the charges outlined below are based on the published Network Management
Fees and Charges for 2025/26 (Network management and public transport fees and
charges | Argyll and Bute Council) 
Option 1 Maintain the current suite of charges (refer to Annex 1) with clarification
that no events are exempted, and media advertisement fees are in
addition to the Councils Fees & Charges. 
Option 2 Introduces a tiered structure for charges, separating out events with or
without commercial elements.  This option highlights preferred and
minimal timelines and introduces an increase per week for less notice to
encourage early engagement.  This allows the workstream to be better
managed within a limited staff resource.  The increase per week has
been set at 25% (on baseline not subsequent weeks) but is an indicative
figure at this point.  Full detail is laid out in Annex 2. 
Organisation responding: 
Address: 
Name of representative: 
Telephone Number: 
Email: 
Q1 How many events does your organisation hold per
year in the Argyll and Bute area? 
Q2 How many of these events are held on the road or
otherwise require a TTRO? 
Q3 Do you agree that Option 1 is the best way to
manage TTROs for events?
Yes / No 
If no, please set out your reasons for this: 
Page 121

Page 122

Q4 Do you agree that, under Option 1, all events should
be charged?
Yes / No 
If no, please set out your reasons for this: 
Q5 Do you agree that Option 2 is best to manage
TTROs for events?
Yes / No 
If no, please set out your reasons for this: 
Q6 Do you agree that increasing charges per less week
of notice to the Council is fair, bearing in mind the
limited staff resource in the team that manages
TTROs?
Yes / No 
If no, please set out your reasons for this: 
Q7 Do you agree that events which are commercial or
partly commercial should pay more than events that
are solely community benefit?
Yes / No 
If no, please set out your reasons for this: 
Q8 Is there anything else you would like to add?   
Q9 Are there any events you would expect to be exempt from requiring a TTRO?   
Q9a Can you provide your reasoning for the above?   
Page 122

Page 123

Annex 1 – Option 1, current Fees & Charges 
Description
Net
VAT Rate
VAT Gross
£ Notes/Comments
£ £ £
Temporary Traffic Regulation
Orders - Provision of
Temporary TRO
1,180.00 Outwith the Scope 0 1,180.00 67 Plus cost of advert plus cost of traffic
management
Temporary Traffic Regulation
Orders - Provision of
Temporary TRO for Annual
Events (2nd year and
thereafter)
591 Outwith the Scope 0 591 33
1 - Temporary Traffic Regulation
Orders (TTRO) costs should be met in
full by the organiser promoting the
event. Fees include minimal
administration costs from the Council
and advertising costs from local
newspapers. 
Temporary Traffic Regulation
Orders - Provision of
Extension of Temporary TRO
591 Outwith the Scope 0 591 33  
Temporary Traffic Regulation
Orders - Provision of
Emergency Notice TRO
591 Outwith the Scope 0 591 33
2 - Cost of adverts will vary
depending on the publication in which
they are placed. In some
circumstances, events may require to
be advertised in multiple publications,
where this is the case the applicant
will be required to meet these costs. 
Page 123

Page 124

Annex 2 – Option 2 
Restrictions required for Emergencies (RTRA, s14)
3-weeks
advance
notice
2-weeks
advance
notice
1-weeks
advance
notice 
Temporary Restriction by Emergency Notice (21 day max. duration, can be extended once
only) £591 £739 £887    
Extend Temporary Restriction by Emergency Notice (21 day max. duration) £591 £739 £887    
Extend Temporary Restriction by Emergency Notice by TTRO (advertising costs not
included)
as Temporary Traffic Regulation
Order charges below            
Restrictions required for Planned Works (RTRA, s14)
10-
weeks
advance
notice 
9-weeks
advance
notice 
8-weeks
advance
notice 
7-weeks
advance
notice 
6-weeks
advance
notice 
5-weeks
advance
notice 
4-weeks
advance
notice 
Temporary Restriction by Traffic Notice (5-day day max. duration) - - - - £591 £739 £887
Temporary Traffic Regulation Order (advertising costs not included) £1,180 £1,475 £1,770 £2,065 £2,655 n/a n/a
Extend Temporary Traffic Regulation Order (advertising costs not included) £591 £739 £887 £1,034 £1,182 - -        
Restrictions requested for Events (RTRA, s16A)
16-
weeks
advance
notice 
15-
weeks
advance
notice 
14-
weeks
advance
notice 
13-
weeks
advance
notice 
12-
weeks
advance
notice 
Commercial or partly commercial purposes (advertising costs not included), first year £1,400 £1,750 £2,100 £2,450 £2,800  
Commercial or partly commercial purposes (advertising costs not included), second year and
thereafter £700 £875 £1,050 £1,225 £1,400  
Community benefit events but with no commercial elements (advertising costs not included),
first year £800 £1,000 £1,200 £1,400 £1,600  
Community benefit events but with no commercial elements (advertising costs not included),
second year and thereafter £400 £500 £600 £700 £800   
Page 124

Page 125

Appendix 3 – Option 2, Fees & Charges
Restrictions required for Emergencies (RTRA, s14)
3-weeks
advance
notice
2-weeks
advance
notice
1-weeks
advance
notice 
Temporary Restriction by Emergency Notice (21 day max. duration, can be extended once
only) £591 £739 £887    
Extend Temporary Restriction by Emergency Notice (21 day max. duration) £591 £739 £887    
Extend Temporary Restriction by Emergency Notice by TTRO (advertising costs not
included)
as Temporary Traffic Regulation
Order charges below            
Restrictions required for Planned Works (RTRA, s14)
10-
weeks
advance
notice 
9-weeks
advance
notice 
8-weeks
advance
notice 
7-weeks
advance
notice 
6-weeks
advance
notice 
5-weeks
advance
notice 
4-weeks
advance
notice 
Temporary Restriction by Traffic Notice (5-day day max. duration) - - - - £591 £739 £887
Temporary Traffic Regulation Order (advertising costs not included) £1,180 £1,475 £1,770 £2,065 £2,655 n/a n/a
Extend Temporary Traffic Regulation Order (advertising costs not included) £591 £739 £887 £1,034 £1,182 - -        
Restrictions requested for Events (RTRA, s16A)
16-
weeks
advance
notice 
15-
weeks
advance
notice 
14-
weeks
advance
notice 
13-
weeks
advance
notice 
12-
weeks
advance
notice 
Commercial or partly commercial purposes (advertising costs not included), first year £1,400 £1,750 £2,100 £2,450 £2,800  
Commercial or partly commercial purposes (advertising costs not included), second year and
thereafter £700 £875 £1,050 £1,225 £1,400  
Community benefit events but with no commercial elements (advertising costs not included),
first year £800 £1,000 £1,200 £1,400 £1,600  
Community benefit events but with no commercial elements (advertising costs not included),
second year and thereafter £400 £500 £600 £700 £800   
Page 125

Page 126

This page is intentionally left blank

Page 127

ARGYLL AND BUTE COUNCIL   ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE
SERVICES                          11  SEPTEMBER 2025 
WASTE COLLECTION POLICY AND OPERATIONAL UPDATES 
1.0 EXECUTIVE SUMMARY 
Over recent months a number of operational and policy areas of the waste collection
service have been progressing with a view to improving consistency of customer
experience and efficiency of service delivery. These activities have previously been
reported to this Committee under three separate projects:
• Route Optimisation,
• Second Domestic Bin Review, and
• Assisted Bin Uplift Review.
As these projects have progressed it has become increasingly clear that they are better
reviewed together as this provides a clearer picture of change within the waste
collection service. In particular the route optimisation project is an important enabler for
both these other projects and for wider changes in the waste collection service,
including some which are outlined in the Roads and Infrastructure Service Review
Update Report being considered by this Committee today.
The purpose of this report is to provide and update on the progress of the three
projects listed above, to seek approval of revised policies in relation to the approval of
second domestic waste bins and assisted bin uplifts and to seek approval to a re-
naming of the route optimisation project to better reflect the anticipated outcomes from
this work.   
Page 127 Agenda Item 8

Page 128

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE 
SERVICES                           11 SEPTEMBER 2025   
WASTE COLLECTION POLICY AND OPERATIONAL UPDATES 
2.0 INTRODUCTION 
2.1 Over recent months a number of operational and policy areas of the waste
collection service have been progressing with a view to improving consistency
of customer experience and efficiency of service delivery. These activities
have previously been reported to this Committee under three separate
projects:
• Route Optimisation,
• Second Domestic Bin Review, and
• Assisted Bin Uplift Review.
As these projects have progressed it has become increasingly clear that they
are better reviewed together as this provides a clearer picture of change
within the waste collection service. In particular the route optimisation project
is an important enabler for both these other projects and for wider changes in
the waste collection service, including some which are outlined in the Roads
and Infrastructure Service Review Update Report being considered by this
Committee today.
The purpose of this report is to provide and update on the progress of the
three projects listed above, to seek approval of revised policies in relation to
the approval of second domestic waste bins and assisted bin uplifts, to seek
endorsement that the existing policy requiring all waste and recycling bins be
clearly identified with the property number / name be robustly implemented
Page 128

Page 129

and to seek approval to a re-naming of the route optimisation project to better
reflect the anticipated outcomes from this work.  
3.0 RECOMMENDATIONS 
It is recommended that members of the Environment, Development and
Infrastructure Committee: 
3.1 Approve the revised Second Domestic Waste Bin Policy set out at 4.4. 
3.2 Approve the revised Assisted Bin Uplift Policy set out at 4.10.
3.3 Endorse that officers commence the activity outlined at 4.12 – 4.14 to ensure full
implementation of the agreed policy that all household waste and recycling bins
are clearly marked to identify the house name / number to which they belong
including endorsing that following a suitable period of pro-active communication
bins will no longer be uplifted where they are not identified with the house name
/ number.
3.4 Agree to rename the Route Optimisation Project as the Digitally Enabled
Operational Services Project and note the changes in anticipated project
benefits and project timeline set out at 4.15 to 4.18. 
4.0 DETAIL 
Second Domestic Bin Review 
4.1 In December 2024 this Committee approved a proposal that the Council should
consult with the public in relation to the criteria that should be in place to
determine eligibility for a second domestic waste bin.
4.2 The public consultation commenced on the 3rd April 2025 and ran for a period
of 6 weeks with a closing date of the 15th May 2025. In total 821 responses
were received to the consultation, providing valuable feedback from
communities. In addition to the public engagement officers undertook a survey
of the approach taken by other Councils in Scotland receiving 13 returns on a
questionnaire sent to all 32 Councils. Table 1 below sets out a summary of the
responses received to the public consultation; these are illustrated in graphic
format at appendix 1. 
Page 129

Page 130

Table 1:
Question Yes  No  Depends 
Don’t
Know   Blank
Summary of
Results
Some local authorities
charge for a second green
bin for general waste. Do you
think that Argyll and Bute
Council should charge for
this service to offset
additional costs?
106
(12.91%)
573
(69.79%)
136       
(16.56%) 0 6          
(0.73%)
A significant
majority of
respondents
would not support
the Council
charging for this
service.
Do you think the criteria
below for providing an
additional general waste bin,
free of charge, are correct?
Households of 5+ people
566
(68.94%)
201        
(24.48%) 0 30        
(3.65%)
24        
(2.92%)
A significant
majority of
respondents
support the
current policy of
households with
over 5 residents
can access a
second green bin
free of charge.
Do you think the criteria
below for providing an
additional general waste bin,
free of charge, are correct?
Households with a child /
children in nappies
633
(77.10%)
137   
(16.68%) 0 27      
(3.28%)
24         
(2.92%)
A significant
majority of
respondents
support that
households with a
child / children in
nappies can
access a second
green bin free of
charge.
Do you think the criteria
below for providing an
additional general waste bin,
free of charge, are correct?:
Medical conditions that
result in increased
household waste
733 
(89.28%)
59      
(7.18%) 0 16        
(1.94%)
13       
(1.58%)
A significant
majority of
respondents
support that
households with a
resident with a
medical condition
resulting in
increased waste
should be able to
access a second
green bin free of
charge.
We propose asking you every
two years if you still require
your second green bin. Do
agree with this?
588
(71.61%)
191
(23.26%) 0 31        
(3.77%)
11         
(1.33%)
A significant
majority of
respondents
agreed that the
Council should
check every 2-
years if
households still
Page 130

Page 131

require a second
green bin. 
4.3 The results of the benchmarking with other Councils is illustrated in table 2
below.
Table 2:
Question Responses
Do you collect more than one general
waste wheel bin from domestic properties? 
8 offer a second domestic waste bin. 
5 offer increased capacity of 360L as
opposed to 240L. 
Does your approval criteria include medical
requirements?
7 requested medical certificates. 
Does your approval criteria include babies
in nappies, if so, how many babies 1 or 2? 
1 based on 1 or more.
11 based on 2 or more.
How often do you review approved bins?  2 authorities review annually. 
6 authorities review bi-annually.
2 authorities review every three years. 
3 don’t review.
Do you charge for a second domestic
general waste wheel bin?
None of the responding Councils charge
for an additional general waste bin. 
4.4  The proposed policy for the approval of a second domestic waste (green) bins is
set out below:  
“Argyll and Bute Council aim to deliver a household waste collection service that
appropriately balances the needs of households with our responsibilities to the
environment. To do this the Council works with residents and communities to
reduce waste and maximise recycling. While it is important that households
have access to domestic waste collection that meets their needs it is also
important that we work to continuously reduce the amount of residual waste and
increase our rates of recycling. The Council’s Second Domestic Waste Bin
Policy is intended to strike this balance.
Where a household requests a second domestic waste bin the first step will be
for the Council to provide information around how to recycle as much as
possible, while at the same time informing the household of the eligibility criteria
they must meet to be approved to receive a second domestic waste bin. This will
help identify any additional actions that can be taken to increase recycling or to
make better use of the bin capacity available. As part of this advice household
will be offered an additional recycling bin if they consistently have more
Page 131

Page 132

recyclable material than will fit in the standard recycling bin. This additional
recycling bin will be supplied free of charge. 
For households that still require an additional domestic waste bin the following
qualifying criteria will apply: 
• For those households with children using disposable nappies there must be 2 or
more children under the age of 4 years of age for whom the household is their
home address. Once the number drops below 2 then the second bin should be
removed or replaced with a standard 240 litre wheeled bin. The Council will
review the additional bins every 24 months.
• One or more resident in the household, for whom it is their home address, has a
medical condition that results in increased volumes of domestic waste as a
result of clinical/medical waste. In the case of a resident with clinical or medical
waste needs the Authority would require a form filled out by a medical
professional. There will be no requirement for the medical professional to
disclose the nature of the condition, simply to confirm that the individual has a
condition that necessitates additional domestic waste disposal. The form should
be filled out by a G.P., Consultant or other registered health professional.
• There are 6 or more people resident in the household for whom this is their
home address.
A Council Environment Warden may be required to visit the customer to see if there
is any further recycling that the household can carry out, this may include a waste
analysis of the current non-recyclable waste bin.
The Council will review the provision of additional domestic waste bin with the
household every 2 years. The Council reserves the right to remove the additional
non-recyclable waste bin, where the above criteria no longer applies or if the
household is not fully recycling.
Additional non-recyclable waste bins will be recorded in the Council’s back-office
system which highlights to the crew on the in-cab system those properties with an
authorised additional bin. Additional bins will only be collected from those properties
identified on this system.”
4.5 Implementing the policy set out above will ensure the Council provides a
consistent approach to the authorisation and provision of additional domestic
waste bins in all areas. Once approved the new policy will immediately be
applied to all new requests for additional domestic waste bins.
4.6 A study carried out by the Operations team, and highlighted to this Committee in
June 2024 set out that at that time there were approximately 3,380 additional
domestic bins across all areas, amounting to an additional 57,494 uplifts of
domestic waste per annum. Unfortunately the information on the reasons for
second bins having been approved only goes back to 2021 meaning that we do
not hold records for all these additional bins that enable us to determine the
Page 132

Page 133

reasons they were authorised and thereby compare that reason to the policy set
out at 4.4. Therefore a rolling programme of contact by email or letter with the
circa 3,380 households which have these bins will take place over the remainder
of 2025 to ensure the bins are being provided in line with the new policy. Where
a second bin is no longer required or the household does not meet the qualifying
criteria set out at 4.4 the additional bin will cease to be collected, a minimum of
1-months’ notice will be provided to the household where this is the case.
Assisted Bin Uplift Policy
4.7 At present the Council provides an assisted uplift service for 1,860 customers.
While a defined list of questions is asked to determine eligibility for an assisted
uplift the interpretation of these is open to a level of interpretation that risks
causing inconsistencies in customer service. As part of work to standardise and
improve our customer service offer an opportunity to clarify the eligibility criteria
exists.
4.8 The existing assessment of eligibility for an assisted uplift asks the following
questions:
• Reason for the request?
• Do you live alone?
• Do you have a neighbour or relative who could help on a regular basis?
• Where is bin situated?
• Is it more than 30m from the kerbside?
• What are the types of bins at the property?
4.9 In order to inform the adoption of a clear set of criteria the service carried out a
benchmarking exercise on the assisted pull-out collection services being
offered by other local authorities, fifteen of the thirty-two local authorities in
Scotland responded to our questionnaire. The questions asked and summary
responses were as set out in table 3 below.
Table 3
Question Yes No Number
Do you offer an assisted uplift 15 0 N/A
Do you require a medical certificate, or
supporting evidence
4 11 N/A
How often do you review this service   Annual -
2
2 years –
6
3 years -
6
Is there an age limit for applicants 4 11 
Page 133

Page 134

Do you ask the applicants if they have anybody
who can assist?
12 3 
Is there a maximum distance from the kerbside
for uplift?
5 10 
If yes how far? Varies from 10m to 100m  
4.10 Based on the review of our existing assisted bin pull out service and
benchmarking with other Councils it is proposed that a new assisted bin uplift
policy is adopted as set out below: 
“Argyll and Bute Council aim to provide assistance to those customers who
are physically unable to present their waste and recycling bins at kerbside for
collection. The following criteria will be used to determine eligibility for this
service:
• The householder is not physically able to present their bin for collection at
kerbside as a result of age, poor health or disability. The Council reserves the
right to request documentary proof for example a medical certificate in order
to ensure eligibility and will seek this where reasonable need for further
evidence of eligibility is believed to exist. 
• The collection point for the bin within the property is within 30 metres of the
kerbside.
• A risk assessment, where deemed necessary, determines there are no
unacceptable safety risks, for example significant slopes / uneven surfaces /
high friction surfaces within the property that would impede the safe collection
and return of the bin to and from kerbside by our staff.
• That the household can enable unimpeded access to the bin on collection
day.
• That the household confirm there is no other householder, neighbour or social
care assistant who could assist them in placing and retrieving the bin from
kerbside.
• That the household consent to being contacted every two years to enquire as
to whether they continue to need the service and undertake to contact the
Council at the earliest opportunity should they no longer require the service.”
4.11 Implementing the policy set out above will ensure the Council provides a
consistent approach to the authorisation and provision of additional domestic
waste bins in all areas. Once approved the new policy will immediately be
applied to all new requests for assisted bin uplifts and a rolling programme of
contact will be made with all households at the 2-year anniversary of the
assisted uplift being approved to check that they still require the service as per
the eligibility criteria set out in the policy. As there are currently a high number of
assisted uplifts that have been in place for over 2-years it will be necessary to
stage contact with residents in relation to these historic agreements due to
resource availability. 
Page 134

Page 135

Identification of Waste and Recycling Bins
4.12 It is an existing requirement that households clearly mark their waste and
recycling bins with the property name / number. This has been a requirement
since 2016. It is however a requirement that has not been strictly enforced with
refuse collection teams continuing to collect bins that are not clearly identified
with a property name / number. 
4.13 The lack of strict enforcement of this requirement over the years has been done
with the best of intentions in order to provide a good quality of service to our
communities. However not enforcing this requirement leads to a number of
unintended consequences that make it much more difficult and potentially
impossible to ensure agreed Council policy is being properly implemented.
Examples of this include the correct implementation of the proposed second
domestic waste bin and assisted bin uplift policies contained within this report. In
order to ensure these services are delivered in line with the policies set out
above it is essential that refuse collection crews can identify each waste and
recycling bin to the specific property to which it belongs. In addition our efforts to
improve the commercial waste collection service, which is set out within the
Roads and Infrastructure Service Review Update report being considered by
this committee today are in part reliant on being able to identify with certainty
those bins which belong to non-domestic properties and for which a commercial
waste service agreement is required. Without enforcing the existing policy of all
waste and recycling bins being clearly identified to the property it is impossible to
be certain that bins which belong to commercial entities are not being
inadvertently collected free of charge as part of the domestic waste collection
service, thereby resulting in the Council losing out on valuable income and
creating lack of equity.
4.14 Should Members endorse this change in practice a communication campaign
will be developed to communicate the requirement to clearly identify waste and
recycling bins which provides plenty of time for households to do this prior to the
operational change being implemented whereby unidentified bins will not be
uplifted. It is anticipated that it would be approximately 3-months before this
operational change is implemented, with the exact date being dependent upon
progress of the route optimisation project as it is important that the in-cab
technology is operational prior to this change being implemented.
Route Optimisation Project
4.15 The intent behind the route optimisation project is to improve the efficiency of
a range of cyclic maintenance tasks by replacing existing paper-based
systems for planning and recording activities with a digital solution that can be
modified and updated far more easily and efficiently. The work has, to date,
been focused within the waste collection service. The digital solution which is
being implemented is a product called Routeware. This system has the ability
to optimise the journey planning of waste collection routes and it was initially
Page 135

Page 136

the intention of the project that journey optimisation would be a major
beneficial outcome of the work, hence the naming of the “Route Optmisation
Project”. As the project has progressed it has become increasingly clear that
the efficiency gains from the journey optimisation element are likely to be
marginal. This results from two key factors: firstly the nature of the road
network means that in many areas there are limited options for alternative
routes to be planned, secondly the experience of local teams means that over
the years they have already worked hard to develop routes which are the
most efficient that they can be. While it was initially hoped that this could lead
to tangible improvements in journey efficiency (reduced mileage and travel
times) and thereby deliver financial savings experience now suggests any
savings as a result of journey efficiency will be limited.
4.16 The implementation of the system is, however, still a priority as it is key digital
enabler for systematic service improvements that will positively impact both
customer service and financial efficiency. Through the installation of in-cab
digital devices to manage waste collection activity the system is key to
delivering the following service improvements:
• The delivery of assisted bin uplifts: the system will identify to collection
crews those properties in receipt of an assisted bin uplift and also enable
refuse collection staff to record that this service has been delivered in real
time during the collection round. Thereby improving the consistency of this
service. This will improve customer service.
• The implementation of the second domestic waste bin policy. By having
those properties approved to be in receipt of a second waste bin identified
in the system this information will be available to collection crews in real
time helping ensure that only authorised additional bins are uplifted. This
will improve both customer service and efficiency.
• Improvements in the commercial waste service resulting in significant
increases in income to the Council. Further detail on the changes that
have and continue to be implemented in the commercial waste collection
service are outlined in a separate report “Roads and Infrastructure Service
Review Update” being considered by Committee today. To fully realise the
benefits outlined in relation to that work it is essential that refuse collection
crews have accurate live information in relation to which commercial waste
bins have contracts in place for their collection. This digital system will
ensure this information is recorded and available to collections crews via
the in-cab device and will enable them to record exactly which bins have
been collected. This supports the delivery of significant financial benefits
and improvements in customer service. 
• Through use of the in-cab device collection crews will record in real time
those bins that have been uplifted. This will improve customer service in
relation to instances where customers complain that their bins have not
been uplifted as an accurate real time record will be available.
Page 136

Page 137

4.17 Given the greater understanding that now exists of the benefits to be derived
form this work it is proposed to re-name this project as the “Digitally Enabled
Operational Services Project”.
4.18 Progress of this project has been delayed due a number of factors including:
limited 4G connectivity increasing the amount of manual uploading of
information required, weaknesses in existing information and discrepancies in
different data sets, delays in the installation of in-cab technology particularly in
more remote locations. As a result of these delays a revised set of target
milestones is illustrated in table 4 below: 
Table 4 
Activity Previous Timescale Updated Estimated
Timescale
In-cab installations December/January
2025
Complete (to all areas
other than Tiree – which is
imminent)
Completion of design
files
November/December
2024
Complete 
Training and
familiarisation
June 2023  Complete 
System go live in pilot
area
February/March 2025 Complete
Revised design files
based on learning
from Pilot.
April/May 2025 August 2025
Wider rollout From May 2025
onwards
September 2025 
5.0 CONCLUSION
5.1 This report proposes that Operations continue to provide second domestic bins
free of charge to households where there are medical conditions that result in
increased household waste.  It is also recommended that the service continues
to provide second domestic bins to households with 2 or more children in
nappies.
5.2 It is also proposed that the service ceases to provide second domestic bins to
households of 5 or less.   
Page 137

Page 138

6.0 IMPLICATIONS
6.1   Policy – This report seeks approval to 2 refreshed policies.
6.2 Financial – This report contains details of projects that will over time improve
the financial efficiency of existing services and that are important to the
maximisation of income from commercial activities.
6.3  Legal – There are no known legal implications.
6.4  HR – Projects outlines within this report will require minor changes to day-to-
day activities in some roles but these are not regarded as significant.
6.5 Customer Service – A number of the projects outlined within this report aim to
improve the standard and consistency of customer service.
6.6 Risk – There a number of risks to the activities outlines in this report. These
include: people who are no longer eligible for a second domestic waste bin
raise complaints, people who are no longer eligible for an assisted uplift raise
complaints, that households that do not clearly identify their bins are unhappy
at the point in time that these cease to be collected.
6.7 Climate Change – Projects outlined in this report aim to maximise recycling
and minimise residual waste which is positive for the environment and climate
change. Projects also aim to ensure operational driving is undertaken with the
maximum efficiency thereby minimising the emission of greenhouse gases.
6.8  Fairer Scotland Duty – None Known.
6.9 Equalities - protected characteristics – The changes to the second domestic
bin policy and assisted uplift policy have been designed to be fair and
transparent and aim to promote equitable access to waste collection services.
An Integrated Equalities Impact Assessment has been undertaken.
6.10 Consumer Duty – None known.
6.11 Island Communities – None known.
6.12 Children’s Rights and Wellbeing – refuse collection and recycling can have
environmental benefits and contribute to the positive future of young people. 
Kirsy Flanagan
Executive Director with responsibility for Roads and Infrastructure Services
Policy Lead, Councillor John Armour
May 2025       
Page 138

Page 139

For further information contact: 
Stephen Hall
Roads and Infrastructure Service Review Lead
Stephen.hall@argyll-bute.gov.uk 
Tom Murphy
Operations Manager
Tom.Murphy@argyll-bute.gov.uk 
Page 139

Page 140

Appendix 1
Q.1. Some local authorities charge for a second green bin for general waste.
Do you think Argyll and Bute Council should charge for this
service to offset the additional costs? 
Q.2 Would you like to comment? Recurring themes in comments made:
• 22% -  Council Tax should cover the 2nd bin 
• 17% -  2nd green bins not needed if waste uplift was more frequent 
• 14% -  No to charging for bins needed due to medical conditions 
Q.3. Do you think the criteria below for providing an additional general waste
bin, free of charge, are correct? 
Page 140

Page 141

Q.4. Would you like to comment on the criteria for additional green bins?
Recurring themes:
• 19% - Increase bin uplift - then no need for extra bins 
• 12% - Criteria is fair and reasonable 
• 12% - Households 5+ - comments split on whether criteria should be
households of 4 or 6. 
Q.5 We propose asking you every two years if you still require your second
green bin. Do agree with this? 
Q.6 Would you like to comment on us contacting you every two years?
Comments are split between contacting every 2 years and annually 
Q.7 Is there any other information [in addition to Rubbish and Recycling] we
could provide that would help you recycle more?   
Page 141

Page 142

Q.8 What other information about recycling would you find useful?
- Make it easier to get information about what and where to recycle:
o Regular social media promotion 
o Stickers for bins with up-to-date information 
o What plastics can be recycled
o Make the bin calendar on the website easier for mobile phones
o What can we recycle at supermarkets?
- Give incentives to recycle 
o Tell us about the benefits of recycling – why we should
o Show that it’s worth our efforts i.e show us that the council recycles
what we recycle; tell us what the council does with the recycling you
collect from us
o Collect recycling bins more often than general waste bins, and tell us
about disruptions to our bin collections
o Make it possible to recycle more: glass, food, garden waste 
Q.9 Longer term, we propose replacing two green bins, where people have
this, with one larger bin to make bin uplifts more efficient. Do you have any
comments?    
Recurring comments:
• 47% - Too Heavy – for older people / bin men.  Difficult to move up and down
steps and rural tracks / longer drives. Will lead to increase in assisted uplifts
• 30% - Good idea 
• 19% - Storage an issue – difficult to fit through gates, won’t fit existing bin
storage, may have to stay permanently on the streets
• 7.5% - More bin uplifts rather than bigger / 2nd bins 
Page 142

Page 143

Page 143

Page 144

This page is intentionally left blank

Page 145

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND  
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to provide Members of the Environment,
Development and Infrastructure Committee with an update on progress and
next steps in relation to the Roads and Infrastructure Service Review (RIS
Review). 
1.2 In providing this update reference is made to information contained in the
previous report to this Committee in relation to the RIS Review in June 2025
and to the actions taken in the intervening period. 
1.3 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) consider the progress made in relation to the priority improvement actions,
including the financial impacts of these, and; 
b) agree to receive a further report on progress of the RIS Review in December
2025. 
Page 145 Agenda Item 9

Page 146

ARGYLL AND BUTE COUNCIL     ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update to Members of this Committee on progress of the
Roads and Infrastructure Service Review (RIS Review), since the last update in
June 2025. 
3.0 RECOMMENDATIONS 
3.1      It is recommended that Members of the Environment, Development and       
Infrastructure Committee:- 
a) consider the progress made in relation to the priority improvement actions,
including the financial impacts of these, and; 
b) agree to receive a further report on progress of the RIS Review in December
2025.  
4.0 DETAIL 
4.1 The RIS Review has been structured around 4 stages of activity as illustrated
below:
Page 146

Page 147

4.2 As set out in previous reports to this Committee the opportunity is being taken
to deliver the planned improvement activities from stages 3 and 4
concurrently. This results in a number of priority improvement actions being
progressed at the same time as the development and implementation of the
revised target operating model and organisation structure for the service.
4.3 Appendix 1 provides a comprehensive update on progress with each of the
current 12 priority improvement actions. As set out in the previous update to
this Committee a staged approach is being taken to the implementation of the
approved priority improvement actions in order to ensure that the service
improvement activity does not place an unsustainable burden on an already
busy service. In addition senior leadership capacity for the RIS Review has
been limited over the past 8 months as a result of the external resource
appointed to lead this process covering the role of Head of Service on an
interim basis. This limitation on leadership capacity has now been overcome
with the commencement in post on 11th August of the new Head of Roads and
Infrastructure, Andy Summers. This enables the external resource to now
focus specifically on moving the implementation of the RIS Review forward
and is anticipated to lead to accelerated progress being made over the
coming months. A summary of the key areas of strategic progress since the
last update in June are set out below:
• Organisation Re-shape: The first phase of the reshaping, which affects
posts at tier 3 in the structure is nearing completion with an agreed
structure and job descriptions finalised. The final step is the
implementation of the appointment process which will be completed in
early September. A draft organisation structure for all other tiers 3 has
been produced and is in the state of maturity necessary to enable staff
engagement on this third stage of the re-shaping to commence shortly
after the appointment of the tier 3 roles has been concluded. 
• Waste Disposal Post-PPP Arrangements: This has been an extensive
area of activity over the last 3 months. The key aims of this work are to
Page 147

Page 148

ensure service continuity of the waste disposal service at the end of the
term of this major contract and to do so in a manner that ensures future
arrangements are compliant with the upcoming ban on municipal waste
going to landfill. Key areas of progress include:
o Work to convert the existing mechanical and biological treatment
plants to waste transfer stations has, following extensive
negotiations between the Council and BIFFA been contractually
concluded with works commencing. This is an essential change to
support the required change in waste disposal methodology from
the current model of producing “Compost Like Output” material and
landfilling residual waste to the bio-ban compliant solution of closing
the landfill sites and transporting waste to energy from waste plants.
o Two significant historic contractual matters that exist between the
Council and the PPP Project Company have been brought to
commercial conclusion subject to final approvals required for one
element from the Scottish Environmental Protection Agency. Once
received this will enable these matters to be contractually closed
between the parties.
o Procurement for the new services required at the end of the PPP-
contract has continued to progress with initial market engagement
informing the final specifications and contracting approach which
will go live for bidders at the end of September tender returns are
due at the start of November with contract award programmed for
January.
o The Council is making good progress to secure energy from waste
off-take for the period from January 2026 onwards to ensure
municipal bio-ban compliance. 
• Roads Information and Asset Management Improvement Project: As
set out in the June update the highest priority of this project has been to
secure the replacement of an existing tool that is essential to the process
of budgeting for road maintenance works, with the existing tool becoming
unsupported in March next year. An alternative product has been sourced
and work has now commenced to undertake the necessary development
to ensure this is available and functioning by March 2026. The key
outcomes of this work will be improved back-office efficiency,
implementation of the digital systems needed for future service
improvements, sustainability of the existing systems and improvements in
customer service. 
• Waste Collection Projects: In the June update report two projects were
described which aim to improve the efficiency and customer experience of
the waste collection service. These were the “Route Optimisation Project”
and the “Second Domestic Waste Bin Review”. Over the last 3 months
through the RIS Review these projects have been taken forward with the
anticipated project benefits subjected to further due diligence. This process
Page 148

Page 149

has resulted in a report being reviewed by this Committee today entitled
“Waste Collection Policy and Operational Updates” which seeks support
for a number of changes in policy and operational practice designed to
improve customer experience, encourage further recycling and reduce
residual waste and support work to ensure the Council maximises the
legitimate income it receives through the commercial waste collection
service. The key aims of this work is to improve and standardise customer
service and reduce cost to the Council by further encouraging recycling. 
• Review of Commercial Waste Income: this has been another significant
area of activity over the last 3 months. In June the first of two projects
intended to ensure the Council recovers all legitimate income from the
collection of commercial waste was just beginning. That project has now
led to additional contracts being entered into resulting in a projected
increase in income of over £270k. Since then a second project has been
mobilised which involves contacting all properties across Argyll and Bute
paying non-domestic rates to determine if they require a contract for
commercial waste. This is a significant task which due to resource
constraints is being progressed on a progressive basis i.e. not all
properties can be contacted at the same time. To date indications suggest
an increase in income of over £500k should be anticipated in the current
financial year. Over the next period further work will be undertaken, as a
priority, to assess further activities that might further improve the Councils
financial return on this commercial service. The key outcomes of this work
are to increase the income of the Council, thereby contributing to financial
sustainability in the long term and to ensure that all customers receive an
equitable service.
4.5 In addition to the priority improvement actions approved by this Committee in
March of this year, work has continued where possible to take forward other
service improvements and to seek new opportunities for improvement where
they arise. A brief review suggests that of the total of the 129 recommendations
from stage 1 a total of 29 have now been implemented or in small number of
cases have been rejected as not representing good return on the effort required
to implement them.
4.6 One of the recommendations from stage 1 that does not yet feature as a priority
improvement action is the recommendation to “Develop a robust asset
management data base for the grounds maintenance activities, street cleansing
activities and for the cleansing of public conveniences, to ensure the work
requirements can be accurately measured, operational resources can be
designed, and a clear budget envelope agreed.” A particular area of focus over
recent months has been in relation to the public convenience estate with a
review being conducted by officers which has looked at the condition of the
public conveniences, the level of use, the cost of maintaining these on an annual
basis and locational factors such as proximity to key transport hubs or key tourist
destinations. The review proposes a future categorisation of public
Page 149

Page 150

conveniences based on their level of usage and strategic importance that would
result in differentiated levels of future investment and proposals being developed
for Member consideration in relation to a programme of community asset
transfers or potential closure of those facilities which offer very poor value for
money as a result of having a very low level of use, not being strategically
located, or having other and better quality public conveniences closely located to
them. The intention is to bring forward a further report as part of the future
budget development process to set out how the Council could enhance
strategically important facilities while lowering the overall financial burden. 
4.7 The savings budgeted from the RIS Review consist of £200k for 24/25 which
was not achieved and rolled forward and a further £300k in 25/26 resulting in a
total of £500k. With an additional £700k of increased income from improvements
in the commercial waste service also budgeted for 25/26. Income from
commercial waste is on track to achieve or slightly exceed this target but to date
the RIS review has not yet delivered the savings budgeted. Further work is
ongoing to determine areas of savings that can be implemented to contribute to
the achievement of these budgeted savings. 
5.0 CONCLUSION
5.1 This report provides an update on the implementation of the 12 Priority
Improvement Actions as developed under Stage 4 of the RIS Review process.
6.0 IMPLICATIONS
6.1 Policy – No direct policy implications within this report. A number of the priority
improvement actions result in changes to existing policies, where this is the
case further reports are being considered by Committee in relation to these.
6.2 Financial – A number of the priority improvement actions aim to increase
efficiency and deliver financial benefits to the Council.
6.3  Legal – Legal aspects are being reviewed as part of each of the priority
improvement actions.
6.4  HR – The proposals to reshape the organisation structure of the Roads and
Infrastructure Service have implications for staff. All relevant Council policies
and procedures are being followed in this regard.
6.5 Customer Service – A number of the priority improvement actions aim to
improve customer experience.
6.6 Risk – Risks are being managed in relation to each of the priority
improvement actions.
6.7 Climate Change – None identified at this time.
6.8  Fairer Scotland Duty: None identified at this time.
Page 150

Page 151

6.9  Equalities – Will be considered as part of each of the priority improvement
actions as these progress.
6.10 Consumer Duties – None identified at this time.
6.11 Islands – None identified at this time.
6.12  Children’s Rights and Wellbeing – None arising directly from this report.             
Kirsty Flanagan, Executive Director with responsibility for Roads and 
Infrastructure
Councillor John Armour, Policy Lead for Roads, Transport and Amenity 
Services 
June 2025                                                  
For further information contact:
Stephen Hall, Consultant, Roads and Infrastructure Service Review 
Stephen.hall@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Summary of Priority Improvement Actions  
Page 151

Page 152

This page is intentionally left blank

Page 153

Appendix 1
Roads and Infrastructure Service Review – Priority Workstream Update
Organisational Design and People
Priority
Improvement
Action
Rationale and Detail Status Progress Update
Organisational
Reshape: Develop
and implement a
revised organisation
structure for RIS
This action will deliver Stage 3 of the RIS Review
process and is fundamental to enabling the
success of all other improvement related
activities and will form the foundations for a
refreshed Roads and Infrastructure Service. The
existing organisation structure does not provide
optimal levels of clarity and accountability and in
some areas, it appears to lack the capacity
required to effectively respond to near-term
challenges. The need for change to the
Management structure is not universal with
some teams requiring only limited change.
In progress Phase 1: 
On course to be complete during September 2026. 
Phase 2:
Draft organisation structure has been completed
ready for finalisation in draft once tier 3 managers
are appointed to enable engagement with the
affected staff.
Waste Post PPP
Arrangements:
Drive forward the
section and
development, by the
Council, of the
organisational
arrangements to
come into place for
waste disposal at the
With the current PPP contract expiring in
September 2026, a key area of focus is to
increase the pace at which the organisational
arrangements that will be required after the end
of the contract are developed and put into
operation. In the short-term additional capacity
is being added to the Council’s existing waste
team through external specialist consultants. As
the future arrangements become clearer the
In Progress There has been a high level of activity over the last
3 months and this is summarised below:
• Conversion of the MBT plants: Deed of             
Variation signed 07.08.25. BIFFA have
awarded contracts with the contractors to
undertake the MBT conversion works with
mobilisation now commenced. This work is
on track to ensure bio-ban compliance by
January 2026.
Page 153

Page 154

end of the current
PPP contract.
capacity of the Council’s waste team will be
further reviewed.
• Historic CLO: BIFFA have reached
commercial agreement with an off taker.
Providing required level of assurance on the
content of the material to the regulator
(SEPA) is required to finally conclude this
matter. 
• Procurement programme progressing well
for formal tender to commence in
September leading to contract award in
January 2026.
• Work has started to develop the
specification of works required for capping
and closure of the existing landfill sites both
within and out with the PPP area.
Infrastructure
Capital Programme
Management:
Improve consistency
of approach to
project
management.
While there is a strong emphasis on managing
the design and construction phases of projects,
the process of business case development and
assurance within RIS can be improved and
strengthened and brought into better alignment
with the Council wide approach of the Project
Pipeline and adoption of best practice through
the Treasury Green Book business case
approach.
In Progress Work is ongoing to align project management
within RIS with the corporate Project Pipeline
Approach. As new projects are coming through
these are adopting the refreshed corporate
approach e.g. A816 Ardfern project being
considered by Committee at this meeting.
Respond to
Reduced Roads
Asset Maintenance
Budget: Review the
impact of the
reduction in roads
maintenance capital
This action was initially developed in response to
the anticipated significant reduction in the level
of capital funding for 2025/26. The decision at
Council to award a capital budget of £10m for
roads reconstruction in 2025/26 has reduced the
urgency of this action. However, with ongoing
pressure to Council budgets and no guarantee
Timeframe
to be
aligned with
timetable
for wider
Council
Savings and
This is not being progressed at the current time
until a clearer indication of likely future capital
maintenance budget is available.
Page 154

Page 155

budget on the overall
staffing structure -
with particular
emphasis on the
impact of front-line
operational staffing
(due to existing
approach to capital
recharging of a
proportion of
operative staff time).
that the current level of capital funding can be
maintained in future years, it remains necessary
for the service to review how a potential future
reduction in the capital budget would impact on
the current operating model and balance
between activities delivered by in-house
resource and those delivered by contractors.
Budgets
options
process
Helensburgh Waste
Transfer Station
(WTS) Project: 
subject to project
gateway review to re-
baseline the benefits
in the context of
whether it can offer
opportunities to
increase efficiency in
waste collection and
resilience in waste
disposal of sufficient
magnitude to justify
the required capital
investment.
The proposed Helensburgh WTS is no longer
required to ensure the Council has a bio-ban
compliant disposal solution in this area. The
project does however offer benefits in terms of
resilience of waste disposal by enabling the
Council to bulk waste and therefore being at less
risk if it has to take waste further than at present
for disposal. Construction of the WTS may also
enable revised and lower cost shift patterns to be
adopted by the waste collection teams. However
it is not clear that these efficiency and resilience
gains are sufficient to justify £3.6m of capital
investment.
Complete Following agreement of the Environment,
Development and Infrastructure Committee on
20th March 2025 that officers should not progress
further with the development and delivery of the
Helensburgh WTS and the subsequent agreement
of the Policy & Resources Committee on 8th May
2025 that the remainder of the £3m of budget
earmarked for this project could be retained for
other funding related pressures within the Waste
Service, this Priority Improvement Action has now
been concluded. 
Page 155

Page 156

Roads and Infrastructure Service Review – Priority Improvement Workstream
Data, Digital and Customer
Priority
Improvement
Action
Rationale and Detail Status Progress Update
RIAMS
Improvement:
Establish cross
service project team
with involvement
from corporate,
digital and finance to
fundamentally
review WDM and
Total systems to
determine and drive
forward a plan to
either re- configure it
replace both
(recognising existing
Total product must
be replaced due to
product soon to
become
unsupported).
Stage 1 and 2 of the review process identified
that the core asset and information
management system used by the service in
relation to roads, amenities and environmental
assets is not optimally configured and is not
offering the maximum value possible. This
system also interacts with a service specific
finance system which is coming to its end of life
and with the corporate customer relationship
management system. This Priority Improvement
Action will see these systems reviewed with
targeted improvements made to maximise
benefit and ensure a replacement for the finance
element is in place prior to the expiry of the
existing product.
This work will include reviewing the
opportunities for artificial intelligence to add
greater value and enable staff to spend a greater
proportion of their time on higher value-added
activities.
In Progress Finance Module:
As set out in the June update the highest
priority of this project has been to secure
the replacement of an existing tool that is
essential to the process of budgeting for
road maintenance works, with the existing
tool becoming unsupported in March next
year. An alternative product has been
sourced, and work has now commenced to
undertake the necessary development to
ensure this is available and functioning by
March 2026. The key outcomes of this work
will be improved back-office efficiency,
implementation of the digital systems
needed for future service improvements,
sustainability of the existing systems and
improvements in customer service. 
CRM:
Work has been underway on making some
improvements to WDM aimed at enhancing
the customer experience and improving
efficiencies for our inspectors. A key
improvement is that faults can no longer be
Page 156

Page 157

logged on non-adopted roads and trunk
roads as of Monday 7th July. 
ELM:
This work has progressed at the pace
anticipated due to staff prioritising other
activities. A review of the plan for this work
will be undertaken shortly. 
Page 157

Page 158

Roads and Infrastructure Service Review – Priority Workstreams
Policy and Procedure
Priority Improvement
Action
Rationale and Detail Status Progress Update
Commence program
of strategic change to
parking and
enforcement related
activity.
A strategic review of parking services and
options for change should be developed for
consideration by Members as a coordinated
package of service changes.
Not yet
commenced
Resource availability and other parking
related priorities such as pavement parking
ban and events TTRO review has meant that
progress has not begun with priority action.
Implement a Package
of changes to school
transport including
ASN transport.
Significant financial strain for a number of
years as a result of increases in demand. A
package of changes will be developed
including:
• Reviewing the approach to
procurement in targeted areas.
• Strengthening co-ordination between
council services in Education and RIS
in relation to planning for the transport
requirements of children and young
with ASN.
In Progress Work has begun to improve the co-ordination
of decision making and information sharing
between education officer and the RIS
transportation team. A key staff resource gap
within RIS has held up progress in this area.
Household Residual
Waste Collection
Reduction
This project has been triggered as part of the
RIS Review. This project brings together two
existing related but separate projects into a
single project. In doing so this project
subsumes its predecessors and provides a
greater level of aspiration for the outcomes
and benefits of the project.
The existing projects replaced by this project
are:
In Progress A report is being considered by EDI
committee today setting out progress and
recommendations in relation to this priority
improvement action. The report includes:
• A new second domestic waste bin
policy,
• A new assisted bin uplift policy,
Page 158

Page 159

1)Second Domestic Bin Review
2)Waste Service Route Optimisation Project
• A review and re-positioning of the
route optimisation project,
• Requests members endorse a
programme to require and enforce
mandatory identification of household
bins. 
Page 159

Page 160

Roads and Infrastructure Services Review – Priority Workstreams
Commercial Opportunities
Priority Improvement
Action
Rationale and Detail Status Progress Update
Further review the
options for increased
commercial activity in
the fleet maintenance
workshops.
Stage 1 of the review reached conclusions in
relation to the potential to generate
additional income through fleet services. The
Stage 2 due diligence did not fully support the
conclusion as they did not take account of
the local context of Argyll and Bute including
our highly rural nature, topography and long
distances between vehicle operating centres
(depots). However, opportunities are believed
to exist to further review medium to long term
options to increase efficiency and / or
generate additional commercial income. 
A further and more detailed review of
capacity that involves looking at both existing
capacity available for commercial work will
be progressed.
Not yet
commenced
Resourcing challenges within the fleet and
transport team have resulted in challenges in
progressing this workstream.
Progress the initial
review of commercial
waste income to
ensure that all
commercial waste
services are charged
for the service of
The initial work suggests a very significant
amount of income is not being collected. The
data also suggests significant disparities with
some businesses paying appropriately while
others are not and are in effect in receipt of a
service free of charge.
In Progress This has been another significant area of
activity over the last 3-months. In June the
first of two projects intended to ensure the
Council recovers all legitimate income from
the collection of commercial waste was just
beginning. That project has now led to
additional contracts being entered into
resulting in a projected increase in income of
Page 160

Page 161

which they are in
receipt.
over £270k. Since then, a second project has
been mobilised which involves contacting all
properties across Argyll and Bute paying non-
domestic rates to determine if they require a
contract for commercial waste. This is a
significant task which due to resource
constraints is being progressed on a
progressive basis i.e. not all properties can be
contacted at the same time. To date
indications, suggest an increase in income of
over £500k should be anticipated in the
current financial year. Over the next period
further work will be undertaken, as a priority,
to assess further activities that might further
improve the Councils financial return on this
commercial service. The key outcomes of this
work are to increase the income of the
Council, thereby contributing to financial
sustainability in the long term and to ensure
that all customers receive an equitable
service. 
Page 161

Page 162

This page is intentionally left blank

Page 163

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND  
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
A816 ARDFERN PERMANENT REPAIR SOLUTION UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on progress towards a permanent repair of the
A816 at Ardfern which was damaged during the severe weather event in
October 2023. 
RECOMMENDATIONS 
It is recommended that Members of the Environment, Development and
Infrastructure Committee:-
a) Agree that the existing budget allocation of £1.1m be used to progress the
next phase of detailed business case development required to provide a
recommended option with a further and more highly developed budget
estimate and outline delivery programme.
b) Note the difference in the current cost estimate and that originally produced
and reported to Members in February 2024 and the reasons for this set out in
the body of the report. 
Page 163 Agenda Item 11

Page 164

ARGYLL AND BUTE COUNCIL     ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
A816 ARDFERN PERMANENT REPAIR SOLUTION UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on progress towards a permanent repair of the
A816 at Ardfern which was damaged during the severe weather event in
October 2023.
2.2 This report sets out the findings of an options assessment commissioned by the
Council and undertaken by specialist consultants. The options assessment
provides a number of potential options for a re-constructed road which have
been further reviewed by Council officers to create a shortlist of preferred
options that it is now proposed are subjected to further more detailed review in
order to arrive at a single option which can be recommended to be taken
forward. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) Agree that the existing budget allocation of £1.1m be used to progress the
next phase of detailed business case development required to provide a
recommended option with a further and more highly developed budget
estimate and outline delivery programme.
b) Note the difference in the current cost estimate and that originally produced
and reported to Members in February 2024 and the reasons for this set out in
the body of the report. 
4.0 DETAIL 
4.1 The A816 through Bealach Mor is a main ‘A’ class road and is the main
connection route between Oban and Lochgilphead. The road runs along the
northern slope of Creag nam Fitheach (214m), A’ Bheinn (246m). 
Page 164

Page 165

4.2  On the 7th October 2023 as a result of exceptional rainfall, the wettest 2-days in
series from 1891, with 100-150mm rain falling widely across Southern and
Central Highlands (Kendon, 2023). Approximately a month of rainfall fell in a 36-
hour period in a number of areas within Argyll and Bute. 
4.3 The heavy rainfall fell onto already saturated ground and triggered 3no. separate
but closely spaced debris flow events (wet saturated landslides that flow) from
the steep slope immediately adjacent to the A816. This deposited approximately
6000 tonnes of material over nearly 200m length of road, with more debris on
the surrounding slopes and fields. 
4.4 Clearance works removed an estimated 10,000 tonnes of debris, from the
original event and subsequent debris from later smaller events and erosion /
wash out of material remaining on the slope.
4.5 Owing to the ongoing movement and potential for further blocks and/or debris to
impact the road a temporary bypass route was constructed as the fastest and
safest way to reopen the A816. The bypass opened to the public on the 16th
December 2023, following 6 weeks of construction (Figure 1). Due to landowner,
environmental, engineering and archaeological challenges and constraints the
temporary road is built in a restricted narrow corridor resulting in a single lane
with passing places, open ditches with steep side drops, a sharp corner and
very steep incline at the western side. Built as a temporary road, i.e., not to
highway standard, the road is approximately 320m length and the alignment
was chosen to follow existing track and foundation of the military road to
minimise foundation and subsidence issues. The road is constructed to Forestry
Land Scotland specification (as a floating road), as far as practicable, with a
covering of asphalt.
4.6 Following the completion of clearance works, construction of protective barrier
systems and the implementation of a temporary traffic light system to control
single lane running traffic was returned to the original route of the A816 and the
temporary diversion road closed on 13th September 2024. 
Page 165

Page 166

4.7 In order to investigate the options available for a permanent road re-instatement
the Council commissioned a consultant to undertake an options assessment
and report. The study examined numerous potential route options with nine
options were taken forward for assessment. These range from a do minimum
approach, utilising the existing A816 and bypass through to a complete
realignment of the road. 
4.8 The consultants have used cost data from recent upgrades of trunk road
schemes in similar environments to produce initial cost estimates. It is only
possible at this stage without detailed route ground investigation and design to
provide outline costings and these are likely to be subject to change as further
design development takes place. It is noted that the A816 may not be
constructed to the same standard as the projects used for cost comparison but
at the current point in time utilizing cost data from recently completed trunk road
schemes is believed to provide the best available comparison. 
4.9  Prior to the Options Assessment to which this report relates an initial and very
early cost estimating exercise was undertaken in early 2024 in order to provide a
broad order of cost magnitude. This exercise suggested a cost of £1.1m and this
was identified as a requirement for the project in the Council Budget Pack in
February 2024 where on page 166 at 3.5.6 it was stated “As a result of a
significant weather event on 7 October 2023, Argyll and Bute Council activated
the Bellwin scheme in relation to the recovery costs associated with the incident.
The funding from this scheme is welcomed however eligibility criteria of costs
are restrictive. Capital expenditure does not qualify therefore any long term
replacements to infrastructure such as bridges cannot be claimed through the
scheme. Works to the value of £3.248m have been identified in the short term
with future long term works costing circa £1.1m being identified, both will
require capital funding.” Without the benefit of a full options study this provisional
estimate was based on widening the temporary bypass road from circa 3m to
6m (to allow two-way traffic) along an approximately 320m length. At this earlier
stage an indicative cost of £1,500/m plus additional costs for consents, licenses,
ground investigations, design fees, plus a contingency allowance of 20% to
produce a high-level estimated cost of £1.1m.   
4.10 In the course of developing the options report the external consultants identified
two further significant geotechnical issues that will need to be addressed as part
of the works to construct a permanent repair to the A816. These additional
issues, which were not known at the time of the initial budget estimated in
February 2024, and consist of: 
• The risk of failure of steep ground on the lower embankment of the A816 just to
the north of the area immediately impacted by the landslip in October 2023. The
cost of repairing this is estimated at up to £2m.
• A large tension crack (around 25m in length) on the slope above the A816
where the existing bypass meets the A816 i.e. just to the south of the area
directly impacted by the landslip in October 2023. This is a surface expression of
a larger instability, thought to be a larger slip feature affecting the carriageway
Page 166

Page 167

which will need to be remediated to prevent ongoing damage to the road
foundation and surface. The cost of repairing this issue is estimated at up to
£1.5m. 
4.11 The options put forward within the consultants report have been reviewed by
officers and a shortlist of options for further consideration has been produced.
These options and a summary of the rationale is set out in Table 1 below
(numbering and naming are as per the consultants report at Appendix 1):
Table 1 - Options for Further Consideration:
Option Description Estimated Cost –
Option plus
Additional
Described at 2.9 
Status and Rationale
Option 3:
Pink Route
Move the A816
approximately 5-
10m to the north
and
construct a large
pit/bund structure
(potentially with
additional rock fall
barriers on top) to
protect the road. 
Length: Approx.
525 m 
£7m - £8.75m  Not preferred at this
stage due to ongoing
maintenance liabilities. 
Option 4:
Yellow
Route
Widening and
upgrade of the
existing temporary
bypass route with
removal of the
£7.25m - £8.5m  Preferred at this stage
due to relocating road
away from residual
hazard.
Page 167

Page 168

sharp, steep corner
and realignment of
the joining to the
A816. 
Length: Approx.
460 m 
Option 5:
Blue Route
Widening and
upgrade of the
existing temporary
bypass route with
removal of the
sharp, steep corner
by realigning the
eastern side of the
bypass to the
south. 
Length: Approx.
405m
£6.5m - £7.5m  Not preferred due to risk
from future landslips,
archaeological risks and
poor road alignment. 
Page 168

Page 169

Option 6:
Green
Route
Widening and
upgrade of the
existing temporary
bypass route for
the eastern section
of the route. A new
western section
would be
constructed from
the corner of the
A816 north of the
bypass 
Length: Approx.
580m
(approximately
190m of new road
construction) 
£8.5m - £10m  Not preferred due to high
cost. 
Page 169

Page 170

4.12 Due to the level of investment estimated to be required it is important that the
shortlisted options are subjected to further review and business case
development in line with the Councils Project Pipeline approach. With a large
number of significant infrastructure projects currently either in design or
delivery the Council does not have available the personnel with the correct
experience and knowledge to do this. Therefore it will be necessary to procure
the services of a specialist consultancy to take forward the business case
development initially to Strategic Outline Business Case and preferred option
stage and then subsequently, subject to further Member approvals and budget
allocation to Outline Business Case and Final Business Case. Consultants will
be procured such that they can be retained for the full project life-cycle from
the current point through to final completion to augment the capacity of
Council staff to manage this project. 
5.0 CONCLUSION 
5.1 This report recommends next steps in relation to the delivery of a permanent
repair to the section of the A816 at Ardfern damaged during the October 2023
severe weather event. 
6.0 IMPLICATIONS 
6.1 Policy – None identified.
6.2 Financial - The estimated costs of this project are outlined in the body of the
report. It is estimated that the current capital allocation of £1.1m will be
insufficient to enable completion of this project. The current budget of £1.1m
is estimated to be sufficient for the next phase of project development
included in the recommendations.
6.3  Legal - There will be a range of legal matters related to this project including
land ownership and contractual matters.
6.4  HR – None identified.
Page 170

Page 171

6.5 Customer Service – None identified at this time.
6.6 Risk - A range of risks are related to this project in terms of affordability,
timescale, land related and issues related to regulatory approvals. There is a
risk of further landslips at this location due to the topography and geology –
this is an important consideration in finalizing the preferred route option in
order to mitigate as far as reasonably practicable future risks to the travelling
public and future risks to transport connectivity.
6.7 Climate Change - By removing the need for traffic lights at this location this
project should lead to minor lowering of transport related CO2 outputs through
removing vehicle idling. The construction of the project will however represent
embodied CO2 as do all construction projects.
6.8  Fairer Scotland Duty – None identified at this time.
6.9 Equalities - protected characteristics – None identified at this time.
6.10 Consumer Duty – None identified at this time.
6.11 Island Communities - The A816 is an important transport corridor that links
points of connection to the islands by ferry services.
6.12 Children’s Rights and Wellbeing – None arising directly from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and 
Infrastructure 
Councillor John Armour, Policy Lead for Roads, Transport and Amenity 
Services 
September 2025                                                  
For further information contact:
Andy Summers, Head of Roads and Infrastructure Service 
Andrew.Summers@argyll-bute.gov.uk 
Elsa Simoes, Infrastructure Design Manager
Elsa.simoes@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
Hugh.oneill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Options Assessment Report A816 
Page 171

Page 172

This page is intentionally left blank

Page 173

Options Assessment Report A816
Bealach Mor 
February 2025
Page 173

Page 174

2
Options Assessment Report
A816 Bealach Mor 
Project no: GLJ620
Document Title: Options Assessment Report; A816 Bealach Mor
Revision: Rev1
Document Status: DRAFT – For comment
Date: 03/04/25
Client: Argyll and Bute Council
Project Manager/Director: N. McLean
Author: N. Horsburgh 
Document history and status
Revision Date Description Author Checked Approved
Draft
Rev 0
17/02/2025 Draft for Client Comment N.H N.M N.M
Draft
Rev 1
03/04/2025 Draft for Client Comment N.H N.M N.M                   
Contents
1. Introduction ................................................................................................................... 3
2. Existing Conditions ...................................................................................................... 6
3 Option Generation ...................................................................................................... 15
References .............................................................................................................................. 32
APPENDIX A ......................................................................................................................... 33
Page 174

Page 175

3
Options Assessment Report
A816 Bealach Mor 
1. Introduction
1.1 Background
The A816 through Bealach Mor is a main A class road in Argyll and Bute on the west coast of
the Scottish Highlands. The road is the main connection route between Oban and
Lochgilphead.
The road runs along the northern slope of Creag nam Fitheach (214m), A’ Bheinn (246m).
On the 7th October 2013 as a result of exceptional rainfall, the wettest 2-days in series from
1891, with 100-150mm rain falling widely across Southern and Central Highlands (Kendon,
2023). Approximately a month of rainfall fell in a 36-hour period in a number of areas within
Argyll and Bute.
The heavy rainfall fell onto already saturated ground and triggered 3no. separate but closely
spaced debris flow events (wet saturated landslides that flow) from the steep slope
immediately adjacent to the A816. This deposited approximately 6000 tonnes of material
over nearly 200m length of road, with more debris on the surrounding slopes and fields.
Clearance works removed an estimated 10,000 tonnes of debris, from the original event and
subsequent debris from later smaller events and erosion / wash out of material remaining on
the slope.
Further assessments of the slope during and following clearance highlighted an ongoing risk
of further movement in the landslide areas and a hazard from precarious boulders and
potential for rock fall from previously and newly exposed rock scarps high above the road.
Scaling works (removal of loose rock and boulders) was undertaken on the slope above the
road as far as practicable, but the works required to lower the rockfall risk further involved
significant engineering works. More boulders continue to be exposed and weather out from
the landslide scarps and deposits following rainfall which washes out soil covering them and
holding them in place.
Owing to the ongoing movement and potential for further blocks and/or debris to impact the
road a temporary bypass route was constructed as the fastest and safest way to reopen the
A816. The bypass as opened to the public on the 16th December 2023, following 6 weeks of
construction (Figure 1). Due to landowner, environmental, engineering and archaeological
challenges and constraints the temporary road is built in a restricted narrow corridor resulting
in a single lane with passing places, open ditches with steep side drops, a sharp corner and
very steep incline at the western side.
Built as a temporary road, i.e., not to highway standard, the road is approximately 320m
length and the alignment was chosen to follow existing track and foundation of the military
road to minimise foundation and subsidence issues. The road is constructed to Forestry
Land Scotland specification (as a floating road), as far as practicable, with a covering of
asphalt.
Page 175

Page 176

4
Options Assessment Report
A816 Bealach Mor 
Figure 1 – Aerial image of the temporary bypass and A816 (south), taken 17/07/24. 
1.2 Purpose of this report
The purpose of this report is to document the development and assessment of options for
the permanent road and to consider the scheme objectives, value, engineering/geohazards,
environmental/archaeological, advantages, disadvantages and constraints of the options
considered.
The DMRB is a collection of documents used to provide requirements and advice for works
and developments of motorways and trunk roads. Although not strictly applicable to the
replacement/upgrade of the section of the A816 at Bealach Mor, it is useful guidance for
Argyll and Bute Council road schemes, although not all of the documents may be applicable.
The DMRB guidance TD 37/93 ‘Scheme Assessment Reporting’ has been withdrawn, and
while is no longer formally used the three stages of assessment are still commonly referred
to as a useful points of reference. This report aims to include the main elements form Stage
1 (Strategic assessment) and Stage 2 (Route option assessment).
As many of the environmental, engineering and economic constraints for the area were
investigated (along with consultation of SEPA, HES/WoSAS, Argyll and Bute Council,
Landowners, Tillhill) during the temporary bypass route the knowledge was utilised for the
gathering of the options assessment. It is suggested that once the options are identified in
this report and preferred option is determined, that further consultation will be required with
the relevant bodies/parties as well as wider public consultation.
This report is restricted to the assessment of the proposed route areas, it should be noted
that geotechnical hazards remain outwith the immediate study area, particularly along the
A816 westwards from Kintaraw towards Salachary. 
1.3 Strategic decisions
The A816 is a main arterial route in Argyll, local communities and deliveries etc., facing large
detours with social and economic impacts to communities of the road being closed. 
Page 176

Page 177

5
Options Assessment Report
A816 Bealach Mor 
Following assessment of the landslide site it became clear that a prolonged closure was
going to be required to remediate the landslide site. The temporary bypass was the preferred
option chosen by Argyll and Bute Council to allow traffic to bypass the works and for
stabilisation works to continue unhindered. The route was chosen as the fastest to deliver
with minimal preparatory works.
Transport Scotland’s vision for Scotland’s transport system for the next 20 years includes
four interconnected priorities: Reduces Inequalities, Takes Climate Action, Helps Deliver
Inclusive Economic Growth and Improves our Health and Wellbeing.
Argyll and Bute Council’s economic strategy and climate action plans address environmental
challenges, including those related to climate change and natural disasters, such as
landslides. Argyll and Bute Council’s refreshed economic strategy for 2024-2034 focuses on
resilience and adaptation to climate change, which includes mitigating risks from severe
weather events.
The STPR2 report (Jacobs, 2020) documents and discusses the current planning and
transport strategy for transport in detail, the reader is referred to this document for further
reading.
Page 177

Page 178

6
Options Assessment Report
A816 Bealach Mor 
2. Existing Conditions 
2.1 A816 Bealach Mor
Scottish Government 6-fold Urban Rural Classification 2016 and 8-fold Urban Rural
Classification 2016 classes the Bealach Mor area as Remote Rural and Very Remote Rural
respectively.
2.2 Land use
• Residential
The area for all options considered is rural with no residential properties within the
assessment area.
• Commercial (Agricultural) Land
The area is shown on the Land Capability for Agriculture in Scotland mapping (1:250,000) as
Class 6.1: Land is capable of only rough grazing due to intractable physical limitations; the
semi-natural vegetation provides grazing of high value.
There is a commercial forestry planation managed by Tillhill to the north of the existing A816.
The temporary bypass follows an existing forestry road through the south side of the
plantation.
• Development Land
There are no areas of development or active planning applications within the assessment
area. 
2.2 Environment
SNH Landscape Character Type lists the area as Type 43 upland parallel ridges – Argyll. The
landscape comprises a distinctive series of linear ridges aligned in parallel with the south-
west/north-east grain of the coast with key characteristics listed below:
• Upland landscape of long, parallel ridges and narrow, linear lochs and glens.
• Tightly packed ridges follow a south-west/north-east alignment.
• Steep, sharp ridge-tops, with dramatic rocky outcrops.
• Extensive conifer forests.
• Deciduous, largely ancient oak woodland on steep, sheltered slopes of ridges and on
loch edges.
• Small marginal pastures or moorland in isolated patches between the un-
forested ridges.
• Dramatic, scenic upland landscape.
Habitats within the wider area are mixed with large areas of woodlands and open moorland /
grazing. The limit of the desktop search for protected species including badger, otter, pine
marten and red squirrel has been kept at 2 km from the site. Bats and trees and their
foraging routes are more complex. The zone of influence for bats has been set at 10 km as
Page 178

Page 179

7
Options Assessment Report
A816 Bealach Mor 
they are a mobile species which can be influenced by habitat fragmentation. Otters have
been scoped out of the surveys as there are no watercourses (streams, ditches) nearby.
Designated sites will not be affected by the proposed development due to the topography
and surrounding habitats adjacent to the site however the zone of influence has been set at
2 km for a desktop search.
There are no protective designations within 2 km of the bypass, this would include the areas
for all route options assessed.
A search of the National Biodiversity Network Gateway (NBN) was made for protected
species within 2km of the bypass (10km for bats), the results are presented in Table 1 below.
Table 1 – NBN protected species results 
Common Name Scientific Name
Badger Meles meles
Otter Lutra lutra
Pine marten Martes martes
Red squirrel Sciurus vulgaris
Soprano pipistrelle Pipistrellus pymaeus 
• Phase 1 Habitat Survey
A Preliminary Ecological Appraisal report, including a Phase 1 Habitat Survey was
undertaken for the proposed area (Preston, R., 2025). The standard methodologies (as
found in the ‘Handbook for Phase 1 habitat survey - a technique for environmental audit,
2010 JNCC) was used. A map was produced at a scale of 1:1,000 (Appendix I, Phase I
Habitat Survey). The Phase 1 Habitat Classification and associated field survey technique
provide a standardised system to record semi-natural vegetation and other wildlife habitats.
The approach is designed to cover large areas of countryside relatively rapidly. It presents
the user with a basic assessment of habitat type and potential importance for nature
conservation. Each habitat type/feature is identified by way of a brief description of its
defining features. It is then allocated a specific name, an alpha-numeric code, and unique
mapping colour. Important findings are recorded as target notes and may identify areas
which require more in-depth study.
Page 179

Page 180

8
Options Assessment Report
A816 Bealach Mor 
Figure 2 – Phase 1 Habitat results and Route Options (Preston, R., 2025). 
Phase 1 Habitat Survey Results 
Results are summarised in Figure 2, the full Preliminary Ecological Appraisal report is
attached within Appendix A 
A1.1.2 Plantation broadleaved woodland
This habitat is found at the eastern extent of the route adjacent to the A816 on the east side
of the route and contains young sessile oak (Quercus petraea). 
A1.2.2 Conifer plantation
Approximately halfway along the proposed grey route it is bounded on either side by
commercial conifer forests with predominantly Sitka spruce (Picea sitchensis), occasional
Japanese larch (Larix japonica), occasional Scots pine (Pinus sylvestris) and edged with
Goat willow (Salix caprea), Grey willow (Salix cinerea) and Downy birch (Betula
pubescens). The age of the forest is at pole stage with severe windblow after the recent
storm. The forest is dense with no understorey. 
A2.1 Dense continuous scrub
The area between the A816 and the western end of the route has a band of continuous
scrub including; Downy birch, Hawthorn (Crataegus monogyna), Rowan (Sorbus aucuparia),
Bramble, Bracken and Gorse (Ulex europaeus). 
B1.2 Semi-improved acid grassland
This habitat is found from the western edge of the conifer plantation to where it meets the
dense scrub adjacent to the A816 and from the eastern edge of the conifer plantation
along the wayleave and has the following species present; Bracken (Pteridium aquilinum),
Bramble (Rubus fruticosus), Creeping buttercup (Ranunculus repens), Foxglove (Digitalis
Page 180

Page 181

9
Options Assessment Report
A816 Bealach Mor 
purpurea), Purple moor grass (Molinia caerulea), Scaly male fern (Dryotperis affinis),
Sharp-flowered rush (Juncus acutiflorus), Soft rush (Juncus effuses), Tormentil (Potentilla
erecta), and Tufted hairgrass (Deschampsia cespitosa). 
B5 Marshy grassland
This habitat is found at the east end of the route next to the A816 and ends at the bottom of
a slope to the north west where the land rises to the wayleave and has scattered small
scrubby trees. The wetness likely results from seepage from the stream. The National
Vegetation Classification for this habitat is M28 Iris pseudacorus - Filipendula ulmaria mire.
Blunt-leaved bogmoss (Sphagnum palustre), Bracken (Pteridium aquilinum), Bramble
(Rubus fruticosus), Creeping buttercup (Ranunculus repens), Flag iris (Iris pseudacorus), 
Foxglove (Digitalis purpurea), Goat willow (Salix caprea), Hawthorn (Crataegus
monogyna), Purple moor grass (Molinia caerulea), Sitka spruce (Picea sitchensis), Soft
rush (Juncus effuses), Tormentil (Potentilla erecta), Tufted hairgrass (Deschampsia
cespitosa) and Wild angelica (Angelica sylvestris). 
D5 Dry heath / acid grassland mosaic
This habitat is found on the ride going through the conifer plantation.
Bank haircap moss (Polytrichum formosum), Blaeberry (Vaccinium myrtillus), Bracken
(Pteridium aquilinum), Common heather (Calluna vulgaris), Downy birch (Betula
pubescens), Goat willow (Salix caprea), Greater wood-rush (Luzula sylvatica), Hard fern
(Blechnum spicant) and Purple moor grass (Molinia caerulea). 
No invasive species were observed in any of the survey areas. 
Further detail on the habitats found in each route area are included with the route options for
ease of reference. 
Protected Species Results
• Otter
No otter holts or rest ups were found within the survey areas. 
• Badger
No signs of badger were found. 
• Pine marten
No pine marten dens were found. 
• Red squirrel
No signs of red squirrel including dreys were found. 
• Bats
All trees within the survey areas have negligible roost potential.
Page 181

Page 182

10
Options Assessment Report
A816 Bealach Mor 
2.3 Geology
• A fault is marked on the map running along the east-west line of the existing A816, from the
coast to Salachary, through Bealach Mor. Further faults are shown to the south as splay faults
originating from the main fault orientated towards the southeast. 
Figure 3 – BGS geology map of the study area. Figure contains British Geological Survey materials © UKRI
2025
The geology though Bealach Mor differs notably to the north and the south of the A816
(Figure 3), due to the presence of the fault. The area is dominate by metamorphic rocks from
the Tayvallich Volcanic and Slate and limestone Formations, and Crinnin Grit Formation
Page 182

Page 183

11
Options Assessment Report
A816 Bealach Mor 
(Neoproteozoic Era). Crosscut by Dalradian Supergroup - metagabbro and metamicrogabbro
and North Britain Siluro-Devonian calc-alkaline andesite dykes.
No mass movement, artificial ground or borehole records are recorded for the area. 
2.4 Superficial deposits 
Figure 4 – BGS superficial map of the study area. Note the three landslides recorded for the 7th October 2023
event. Figure contains British Geological Survey materials © UKRI 2025.
Page 183

Page 184

12
Options Assessment Report
A816 Bealach Mor 
The BGS GeoIndex superficial layer (1:50,000) shows peat deposits in the lower lying areas
within the valleys of the study area (Figure 4), the depth of these is not recorded but that
they are present indicates they are substantial and likely to exceed 5m depth. There is also a
deposit of raised marine deposit of sands and gravels on the former raised beach at the
western end of the site. Alluvium deposits are indicated in the vicinity of the Kintraw Burn and
from Lochan na Goirt.
The majority of the soils within the area are shown on the Macaulay Institute for Soil
Research (1:250,000) map as brown forest soils, humic gleys; some peaty gleys and peaty
podzols, while there is a small band of soils close to the coastline shown as humus-iron
podzols, peaty podzols. 
2.5 Rockfall and landslide history
No rockfall or landslide records were found for the area.
There are three landslides recorded on the BGS GeoIndex (Figure 4), but these all relate to
the 7th October 2023 event, no prior incidents are recorded from the site or nearby. 
2.6 Archaeology
Historic Environment Scotland records a Scheduled Monument (NM 83046 04974, Figure 5)
for Kintraw Standing stone and cairns to the west side of the site and the east of the A816 in
a field to the south of the Kintraw burn. Further protected sites are listed on Canmore within
the area and are listed in Table 2 below. 
Figure 5 – Scheduled Monument site recorded by historic Environment Scotland shown in the red highlighted
area. The red location pin denotes the location of the prehistoric fort recorded at the site on Canmore
(Canmore ID 22850).
Page 184

Page 185

13
Options Assessment Report
A816 Bealach Mor 
Table 2 – Canmore / RCAHMS listed sites within the assessment area.
Listed/ Protected Site Position relative to proposed routes
Kintraw Farmstead (Period Unassigned), Lime Kiln
(Period Unassigned)
North of all proposed works areas
Kintraw Bridge
Road Bridge (18th Century)
North of all proposed works areas
Kintraw
Ring Cairn (Neolithic) - (Bronze Age)
Within the Scheduled Monument Designation
Kintraw
Cairn (Period Unassigned)
Within the Scheduled Monument Designation
Kintraw
Platform (Period Unassigned)
Within the Scheduled Monument Designation
Kintraw
Cairn(s) (Prehistoric), Enclosure (Period Unknown),
Standing Stone (Prehistoric)
Within the Scheduled Monument Designation
Kintraw
Fort (Prehistoric)
Within area of the works – All routes widening the
west end of the temporary bypass and routes around
fort – Yellow, orange, green, red, grey.
Kintraw
Rig And Furrow (Medieval) - (Post Medieval)
Close to A816, covered/destroyed by 2023 landslide.
Barbreck
(Farmstead) (Period Unassigned)
Close to Grey Route
Dun Na Ban-Oige
Fort (Prehistoric)
Close to Grey Route
Kintraw
Cairn (Period Unassigned), Cremation (Period
Unassigned), Field System (Period
Unassigned)(Possible)
Out with area 
2.7 Waterbodies 
• The Kintraw Burn to the north of the site is the main watercourse thought the site. All
watercourses for the area drain to Loch Craignish, a sea loch located to the west of the site
which opens to the Sound of Jura.
• Loch Craignish (15.37km2) is a former designated shellfish growing waterbody, de-
designated in 2012.
• No designated waters are located within the study area. 
2.8 Traffic data
AADT values are provided in Table 3 below.
Page 185

Page 186

14
Options Assessment Report
A816 Bealach Mor 
Table 3 – AADT values for the A816. 
direction_of_travel
pedal_cycles
two_wheeled_motor_vehicles
cars_and_taxis
buses_and_coaches
lgvs
hgvs_2_rigid_axle
hgvs_3_rigid_axle
hgvs_4_or_more_rigid_axle
hgvs_3_or_4_articulated_axle
hgvs_5_articulated_axle
hgvs_6_articulated_axle
all_hgvs
all_motor_vehicles
2013 Manual
Count  N  1  12  765  5  140  38  3  11  2  15  3  72  994
2013 Manual
Count  S  0  6  740  6  147  32  5  6  5  3  9  60  959
2022 Estimate N 1 11 680 4 211 44 4 15 3 13 3 82 988
2022 Estimate S 0 6 657 5 221 37 6 8 7 3 10 71 960 
2.9 Social and economic context
A recent report by Jacobs / AECOM for Transport Scotland :STPR2: Initial Appraisal: Case
for Change - Argyll & Bute Region 2020 details much of the social and economic context for
the area and the reader is referred to this more in-depth document for further information.
Page 186

Page 187

15
Options Assessment Report
A816 Bealach Mor 
3 Option Generation
3.1 Overview
This study examined numerous potential route options. Route corridors utilising long and/or
remote areas from the A816 were rejected for further investigation and the option process
since these did not meet the objectives of the project. The anticipated costs and potential
environmental impacts of each route were considered disproportionate to the problems faced
by the existing alignment of the A816.
Eight options were taken forward for assessment. These range from a do minimum
approach, utilising the existing A816 and bypass to a complete realignment of the road.
Initially longer (>10km) options were proposed that would bypass the slopes and other
potential future issues along the Bealach Mor stretch of the A816. These were discounted for
further assessment in discussion with Argyll and Bute Council as beyond the scope and
remit of the project.
The following section summarises the options and presents the best assumptions of a
route path / alignment, but it should be noted that changes or refinements may be
required at a later stage of assessment.
• Option 1: A816 (Purple Route)
• Option 2 & 2a: A816 and bypass (Orange Route)
• Option 3: A816 Realigned and bunded (Pink Route)
• Option 4: Bypass with retaining wall/revetment (Yellow Route)
• Option 5: Bypass with realigned turn (Blue route)
• Option 6: Bypass and lower field (Green Route)
• Option 7: Bypass around fort (Red Route)
• Option 8: Alternative bypass (Grey Route) 
The last two of the options (Red and Grey Routes) considered require to passing through or
very close to sites of archaeological significance (Scheduled Monument and Fort), these
were deemed unlikely to gain necessary permissions and to carry a large risk of impact to
programme or budget should works uncover archaeological significant finds, these were
discounted from further assessment but remain included for completeness.
An overview of the route option locations is provided on Figure 6 and individual routes are
shown within the relevant tables below. 
3.2 Cost estimates
Previous upgrades of trunk road schemes recently completed in similar environments are
listed below for comparison to the current proposed routes
Costs are based on the available information and cover geotechnical investigation, design
and construction. It is only possible at this stage without detailed route ground investigation
and design to provide outline costings, these have been based on relatively pessimistic
ground conditions. Land acquisition costs would be additional to the costs provided.
Relocation of services are not factored within the cost estimates and may attract significant
additional costs where required.
Page 187

Page 188

16
Options Assessment Report
A816 Bealach Mor 
Additional estimates have been provided to address further potential geotechnical hazards
which if not addressed may result in road closure of the A816. There are two areas identified:
• The lower embankment below the existing A816 (Figure 7) is overstep made ground with
potential for failure and assessment is recommended with remediation if required,
estimated at £1.5 - £2M. All the options pass over this area (with the exception of Green
Route – Option 6).
• There is a large tension crack (around 25m in length) noted on the slope above the A816
where the existing bypass meets the A816 (Figure 8). This is a surface expression of a larger
instability, thought to be a larger slip feature affecting the carriageway. This will need to be
stabilised/remediated to prevent ongoing damage to the road foundation and surface. There
is also potential for further slope failure above the road at this location, remediation works is
estimated at £1.5M. 
Figure 6 – Overview of the eight route options displayed on aerial imagery for the area. Purple (Option 1),
Orange (Option 2), Pink (Option 3), Yellow (Option 4), Blue (Option 5), Green (Option 6), Red (Option 7) and
Grey (Option 8). The location of the lower embankment discussed above is shown by the no1. while the
tension crack/slip location is shown by the no2. 
Page 188

Page 189

17
Options Assessment Report
A816 Bealach Mor 
Figure 7 – Aerial photograph (taken on the 17/07/24) showing the embankment below the A816 discussed in the
text. 
Figure 8 – Aerial photograph (taken on the 17/07/24) showing the tension crack and slip area. Inset
photograph of the tension crack from the bypass tie in looking south (taken 26/08/24).
Lower embankment 
Page 189

Page 190

18
Options Assessment Report
A816 Bealach Mor 
Detailed descriptions of the route options, cost estimates, engineering requirements, geotechnical considerations
are included for each option in Tables 4 to 12 below:
Table 4 – Purple Route, Option 1.
Route Option 1: A816 – Do nothing (Purple Route)
Description Keep existing arrangement (i.e. use of the A816 under single lane
traffic controlled by traffic lights with on-road barrier in place and move
traffic to the temporary bypass during adverse weather or events).
• 460 m length 
Cost Estimate • £17,000 per month (£204,000 PA), dropping to £10,000 (£120,000
PA) after mains power is installed. Operational costs for A816 /
bypass only any event clearance/remediation would be additional.
• Not including repairs (if required) for below road steep
embankment at north side and deep-seated slip to the west.
Engineering
Assessment
• The existing and temporary road surfacing will need upgrading and
the risk of closure of the A816 remains high. Increasing instability
may result in closure and/or increasing risk to road users.
• Ongoing TM / Install of permanent TM required.
• Maintenance / clearance will be required following events.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• The barrier installed was placed in the road to quickly resolve
landowner consent issues, this is not the optimal placement, and
the barrier placed was the largest appropriate for the availability of
space and function. The barrier does not provide full protection of
the area covered and the residual risk remains moderate.
• Topography and road layout is such that the option would be of
ongoing substantial cost, especially if repeated events occur.
• High risk to keep open during heavy rainfall / storms or slope
instability – move to bypass.
Geotechnical
Hazard
• Hazard from the slope above remains, it is likely that ongoing
maintenance costs will be high if ongoing from the geohazards of
landslides and rock fall. There will be additional maintenance and
clearance costs following events.
• The on-road barrier offers protection only to a section
approximately 100m in length. The remaining road to the east has
Page 190

Page 191

19
Options Assessment Report
A816 Bealach Mor 
no mitigation and may be impacted by landslide/debris flow or rock
fall from above.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• There is a large tension crack (around 25m in length) noted on the
slope above the A816 where the existing bypass meets the A816.
This is a surface expression of a larger instability, thought to be a
larger slip feature affecting the carriageway. This will need to be
stabilised/remediated to prevent ongoing damage to the road
foundation and surface. There is also potential for further slope
failure at this location.
• Assessment of the lower embankment of the existing A816 is
recommended is recommended due to this being overstep made
ground with potential for failure.
Environmental
Assessment
Minimal environmental impact as this utilises the existing road layout.
Discussion/
recommendation
Future events from the slope are highly likely. Incidents of intense
rainfall are likely to increase because of climate change, this is
expected to lead to more frequent and larger volume events. This is
what has been observed at other landslide prone sites in Scotland,
e.g. Rest and Be Thankful. 
The area is only partially protected from rock fall and landslide/debris
flow as the in-road barrier does not run the full length of the slope
vulnerable to instability. 
This option and the orange options have the highest ongoing costs. 
Table 5 – Orange Route 1, Option 2.
Route Option 2: A816 and bypass (Orange Route 1)
Description Move to gyratory flow arrangement (northbound traffic on bypass/
southbound traffic on A816) with roads as existing.
• 890 m length
Cost Estimate £5M - £6M
Page 191

Page 192

20
Options Assessment Report
A816 Bealach Mor 
Not including repairs (if required) for below road and west deep-seated
slip
Engineering
Assessment
• There are space restrictions at the north joining point and
complications due to significant height differences from the
bypass/A816.
• To allow turning of HGV/long vehicles would need the whole road
width. Roundabouts would potentially provide a logistical way to
transition to the gyratory flow and allow the larger vehicles the
space required.
• In order to build to the west, significant volume of fill would be
required to accommodate any widening.
• Further acquisition of grazing land would be required.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• Topography and road layout is such that the option would be of
ongoing substantial cost, especially if repeated events occur.
• Difficult to keep open during heavy rainfall / storms – move to
bypass.
• The barrier installed was placed in the road to quickly resolve
landowner consent issues, this is not the optimal placement, and
the barrier placed was the largest appropriate for the availability of
space and function. The barrier does not provide full protection of
the area covered and the residual risk remains moderate.
• High risk to keep A816 open during heavy rainfall / storms or slope
instability – move to bypass. If there are weather forecasts or
events impacting the A816 traffic may need to be moved to the
bypass (as Purple Route – Option 1).
• Road closure or further temporary bypass would be required to
accommodate the construction works.
• Construction programme estimated at 8 months.
Geotechnical
Hazard
• Hazard from the slope above remains, it is likely that ongoing
maintenance costs will be high if ongoing from the geohazards of
landslides and rock fall. There will be additional maintenance and
clearance costs following events.
• The on-road barrier offers protection only to a section
approximately 100m in length. The remaining road to the east has
no mitigation and may be impacted by landslide/debris flow or rock
fall from above.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• Assessment of the lower embankment of the existing A816 is
recommended is recommended due to this being overstep made
ground with potential for failure.
• There is a large tension crack (around 25m in length) noted on the
slope above the A816 where the existing bypass meets the A816.
This is a surface expression of a larger instability, thought to be a
larger slip feature affecting the carriageway. This will need to be
stabilised/remediated to prevent ongoing damage to the road
foundation and surface. There is also potential for further slope
failure at this location.
Environmental
Assessment
The orange route follows the previous by-pass road and at the
western extent bends slightly southwest through a patch of semi-
Page 192

Page 193

21
Options Assessment Report
A816 Bealach Mor 
improved acid grassland and roadside scrub. The impact of the route
would be low, with works restricted to the tie in sections.
Discussion/
Recommendation
Flow in this direction requires crossing of vehicles at both end tie ins.
Roundabouts would be the best option to allow space for turning
vehicles (especially HGV) southbound onto the bypass as a large
swing is required. Roundabouts could also accommodate the crossing
of traffic back onto the left at the east tie in.
Future events from the slope are highly likely. Incidents of intense
rainfall are likely to increase because of climate change leading to
more frequent and larger volume events.
There is a risk of injury, fatality to the travelling public or vehicle
damage from landslide/debris flow or rock fall. The barrier in place
lowers the hazard at locations covered but does not fully negate the
potential for a serious incident at the site. 
The area is only partially protected from rock fall and landslide/debris
flow as the in-road barrier does not run the full length of the slope
vulnerable to instability. 
This option and the Purple Route have the highest ongoing costs. 
It is considered high risk to maintain the A816 open during potential
instability if, as in Purple Route move to bypass is required, a method
of switching traffic to two-way on bypass should be considered. 
Table 6 – Orange Route, Option 2a.
Route Option 2a: A816 and bypass (Orange Route 2)
Description Move to gyratory flow arrangement (northbound traffic on A816 /
southbound traffic on bypass) with bypass & A816 upgraded at joining
points to mitigate issues at northbound end of bypass.
• 890m length
Cost Estimate • £5 – 6.5M
Page 193

Page 194

22
Options Assessment Report
A816 Bealach Mor 
• Not including repairs (if required) for below road and west deep-
seated slip
Engineering
Assessment
• There are space restrictions at the north joining point and
complications due to significant height differences and tight corner
from the bypass/A816.
• To allow turning of HGV/long vehicles southbound on the bypass
at the north corner they need greater road width. Flow in these
directions would be difficult to manage as HGV or longer vehicles
need to swing out onto the opposite lane to make the turn. Road
widening would be required to the west and/or traffic lights or
similar installed to manage priorities.
• In order to build to the west, significant volume of fill would be
required to support any widening to accommodate widening.
• Further acquisition of grazing land would be required.
• Road closure or further temporary bypass would be required to
accommodate the construction works.
• Construction programme estimated at 8 months.
Geotechnical
Hazard
• Hazard from the slope above remains, it is likely that ongoing
maintenance costs will be high if ongoing from the geohazards of
landslides and rock fall. There will be additional maintenance and
clearance costs following events.
• The on-road barrier offers protection only to a section
approximately 100m in length. The remaining road to the east has
no mitigation and may be impacted by landslide/debris flow or rock
fall from above.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• Lower slope and deep-seated slip are recommended to
assessment / remediation.
Environmental
Assessment
• The orange route follows the previous by-pass road and at the
western extent bends slightly southwest through a patch of semi-
improved acid grassland and roadside scrub. The impact of the
route would be low, with works restricted to the tie in sections.
Discussion/
Recommendation
Flow in this direction is optimal at the east side of the route as it allows
vehicles to remain on the ‘correct’ side of the road. At the west side
without road widening, it requires traffic lights to holding northbound
traffic to allow space for turning vehicles (especially HGV) southbound
onto the bypass as a large swing is required. 
Future events from the slope are highly likely. Incidents of intense
rainfall are likely to increase because of climate change leading to
more frequent and larger volume events.
The area is only partially protected from rock fall and landslide/debris
flow as the in-road barrier does not run the full length of the slope
vulnerable to instability. 
There is a risk of injury, fatality to the travelling public or vehicle
damage from landslide/debris flow or rock fall. The barrier in place
lowers the hazard at locations covered but does not fully negate the
potential for a serious incident at the site.
This option and the Purple Route have the highest ongoing costs.
Page 194

Page 195

23
Options Assessment Report
A816 Bealach Mor 
It is considered high risk to maintain the A816 open during potential
instability if, as in Purple Route move to bypass is required, a method
of switching traffic to two-way on bypass should be considered. 
Table 7 – Pink Route, Option 3.
Route Option 3: A816 Realigned and
bunded
(Pink Route)
Description • Move of the A816 approximately 5-10m to the north and
construction of a large pit/bund structure (potentially with additional
rock fall barriers on top) to protect the road.
• 525 m length 
Cost Estimate • £5.5 - £6.75M
• Not including repairs (if required) for below road £1.5M for
additional deep-seated slip
Engineering
Assessment
• The road would be moved north approximately 5-10m and a large
bund constructed, approximately on the current A816 alignment.
• Traffic flows could be maintained on the temporary road to assist
the construction program.
• Landslide/debris flow and rock fall risk will be lowered but may not
be removed entirely.
• There is an overhead power line that would require relocation that
runs 205m along the approximate line of the proposed road to the
south of the most southerly plantation block shown on the aerial
image above.
• Rock excavation required though the existing rock cut.
• Construction programme estimated at 8 months
Geotechnical
Hazard
• There is potential for rock fall and landslide/debris flow to impact
the A816 and modelling would be required to determine if
additional mitigation measures, such as rock fall/debris barriers
were required in addition to the bund.
• Peat deposits are shown on the BGS mapping (Figure 4) in the
alignment, this may require additional foundation
• Lower slope and deep-seated slip are recommended for
assessment / remediation.
Page 195

Page 196

24
Options Assessment Report
A816 Bealach Mor 
Environmental
Assessment
The habitats adjacent to the pink route are semi-improved acid
grassland and scattered trees including rowan (Sorbus aucuparia),
Goat willow and Downy birch.
Discussion/
Recommendation
The relocation of the road to the north would allow space to construct
bunds large enough to prevent debris from reaching the A816. There
is an additional hazard of potential rock fall from the slope, this is from
rock crags and rock pillars high on the slope and from eroding blocks
from landslide scarps and eroding gully side walls. To mitigate this risk
rock fall barriers are likely to be required along the top of the bunds.
The presence of the overhead power lines along the south of the
forestry block complicates this route option as the cost and
agreements for moving this will add time and budget uncertainty, this
cost is not included in the costing. 
Additionally, the Pink Route would incur ongoing maintenance costs,
particularly following events, clearance and repair to the bund and
fence would be required. 
Table 8 – Yellow Route, Option 4.
Route Option 4: Bypass with retaining
wall/revetment
(Yellow Route)
Description Widening and upgrade of the existing temporary bypass route.
Removal of the sharp, steep corner and realignment of the joining to
the A816.
• 460 m length 
Cost Estimate • £3.75M - £5M
• Further £2M for lower road, £1.5M for additional deep-seated slip
Engineering
Assessment
• To remove the sharp corner and overly steep gradient at the north
end of the bypass this section would be rerouted along the west
side of the fort hill along the line of the former drove road.
• This would require the construction of a retaining wall or revetment
structure to support the road width required.
• The retaining wall is likely to need to extend out to the centre of the
existing road and it is probable that the lower slope would need
additional strengthening works to support the additional weight.
Page 196

Page 197

25
Options Assessment Report
A816 Bealach Mor 
• Traffic management will need to be extended to accommodate the
tie in on the north side.
• Construction programme estimated at 8 months
Geotechnical
Hazard
Deep-seated slips are recommended for assessment / remediation.
Works to retain the lower slope below the existing A816 are likely to be
required to support the additional weight of the road and revetment.
Environmental
Assessment
This route follows the previous by-pass going through the plantation
forest then is proposed to bend down towards the north before
rejoining the A816 going through semi natural acid grassland (B1.2).
Discussion/
Recommendation
The main length of the route is based around widening the existing
temporary bypass with the main engineering section where the bypass
turns north along the former drove road. The change to alignment
would allow the removal of the sharp corner and reduce the steep
gradient on the transition between the A816 and bypass area. In order
to support the road would require fill with a retaining wall/revetment
estimated to extend to around the centre line of the current road.
Additional works may be required to stabilise the lower embankment
to support the additional weight. 
The yellow option requires some excavation at the corner area but
much less than other options and the risk to programme and budget
due to archaeology finds/permissions is considered less than other
options requiring greater excavation close to archaeological features
and more deviation from current road positions (e.g. Red Route, Grey
Route, Blue Route). 
The overhead power line crosses the temporary bypass around the
mid-section where the road exits the forest block and minor
realignment/height change may be required. This is not included in the
costing. 
The Yellow Route is considered favourable as it is lower budget and
environmental impact than other options while addressing the sharp
corner and gradient issues effectively. The road is moved away from
the unstable slope and ongoing maintenance costs are lower than
other options close to the unstable slope. 
Table 9 – Blue Route, Option 5.
Route Option 5: Bypass with realigned turn (Blue Route)
Description Widening and upgrade of the existing temporary bypass route.
Removal of the sharp, steep corner by realigning the eastern side of
the bypass to the south.
• 405m length
Page 197

Page 198

26
Options Assessment Report
A816 Bealach Mor 
Cost Estimate • £5 - £6M
• Not including repairs (if required) for below road, £1.5M for
additional deep-seated slip
Engineering
Assessment
• Significant excavation is required to accommodate this route. The
height difference of the existing bypass and the A816 tie in point is
approximately 3m (higher at the bypass). The ground in the centre
of the mounded area the route is crossing is approximately 5m
higher than the bypass, this would require substantial reprofiling to
accommodate the area required for the turn.
• There will still be a substantial corner on the route but the gradient
and more favourable curve/turn.
• Construction programme estimated at 5-6 months.
Geotechnical
Hazard
• This option moves the road towards the main slope and within the
run out for landslides/debris flows and rock fall. If the ground is
levelled and lowered in height the road also becomes increasingly
vulnerable to these hazards.
• Assessment of the lower embankment of the existing A816 is
recommended is recommended due to this being overstep made
ground with potential for failure.
• Lower slope and deep-seated slip are recommended for
assessment / remediation.
Environmental
Assessment
The blue route will go through a short section of semi-improved acid
grassland and require a large volume of bedrock excavation.
Discussion/
Recommendation
The main length of the route is based around widening half of the
existing temporary bypass with a new section of road turning to the
south to accommodate a less tight turn back to the north and tie into
the A816. 
The topography is elevated between the bypass and A816 tie in
points, this will require large volume of excavation (assumed to be
mostly rock). The extensive excavation is likely to require
archaeological permissions for excavations and would possibly be
controlled i.e. watching brief, controlled methodology and full
archaeological excavation of any new find areas. Discovery of
archaeology would increase price and affect programme.
Page 198

Page 199

27
Options Assessment Report
A816 Bealach Mor 
The Blue Route takes the bypass back towards the unstable slope and
the excavation of the ground to accommodate the road increases the
potential for large landslide/debris flow events to impact on the route.
In comparison to the Yellow Route, the Blue Route is has greater
residual risk from the slope, higher environmental impact and the
alignment is less favourable for increased cost. 
The overhead power line crosses the temporary bypass around the
mid-section where the road exits the forest block and minor
realignment/height change may be required. This is not included in the
costing. 
Table 10 – Green Route, Option 6.
Route Option 6: Bypass and lower field (Green Route)
Description Widening and upgrade of the existing temporary bypass route for the
eastern section of the route. A new western section would be
constructed from the corner of the
• 580m length (approximately 190m of new road construction) 
Cost Estimate • £7M - £8.5M
• Not require for below road £1.5M for additional deep-seated slip
Engineering
Assessment
• Extensive volume/importation of material would be required for the
construction of the new section of road across the field. There is a
30m height difference from the west corner of the A816 where the
road would start to the tie in point on the existing bypass.
• Requires land purchase of land currently used for grazing.
• Off-line construction of the majority of the road.
• Construction programme estimated at 7-8 months
Geotechnical
Hazards
• Height difference would require large volume of fill to be placed,
ground conditions would be required to be adequate to support the
weight, there are some softer areas within the field where
additional foundations engineering may be required.
• Detailed ground investigation would be required for the new
section of road.
Page 199

Page 200

28
Options Assessment Report
A816 Bealach Mor 
• Deep-seated slip is recommended for assessment / remediation,
lower embankment works would be included within the works,
wider embankment is not used by this option.
Environmental
Assessment
This route starts off adjacent to dense scrub with gorse (Ulex
europaeus) at its northern extent then passing through heavily grazed
neutral grassland with Sheep’s fescue (Festuca ovina).
Discussion/
Recommendation
The Green Route is cost prohibitive due to the volume of imported fill
required. There would be a large volume of road traffic required to
transport the materials required and the option is considered low rating
for sustainability. The project would also require a detailed ground
investigation to be undertaken to inform the design process to ensure
suitability. 
The embankment required would be much greater in scope than
required for the Yellow Route. 
The route passes over heavily used grazing land which would be
expensive and potentially protracted to obtain.
The overhead power line crosses the temporary bypass around the
mid-section where the road exits the forest block and minor
realignment/height change may be required. This is not included in the
costing. 
Table 11 – Red Route, Option 7.
Route Option 7: Bypass around fort (Red Route)
Description The red route passes along the existing bypass track at the eastern
side for approximately 170m before heading northwards though the
plantation forest for 205m and then around the north side of the fort
and tying into the A816 at the north corner close to/within the
Scheduled Monument.
• 640m length 
Discussion/
Recommendation
• £9.5M - £10.5M
• No lower embankment works required, additional cost for
remediation of deep-seated slip.
Page 200

Page 201

29
Options Assessment Report
A816 Bealach Mor 
Engineering
Assessment
• The red route passes to the east and north side of an identified
prehistoric hillfort (Canmore ID 22850). Permissions for
excavations in the area is likely to be denied or heavily controlled
i.e. watching brief, controlled methodology and full archaeological
excavation of any new find areas.
• Western tie in is located within/close to the Scheduled Monument
site and due to topography, there are no suitable alternative routes
in the area.
• Construction programme estimated at 12 months.
Environmental
Assessment
• The red route passes through conifer plantation (A1.1.2) with both
Sitka spruce and Larch and severe windblow before joining the
grey route running through semi-acid grassland
(B1.2) and ending at a band of dense scrub (A2.1).
• The impact on the environment would be high as the
approximately 480m of the route would be newly constructed.
Discussion The tie in location at the western end of the site passes though/close
to the Scheduled Monument and is unlikely to be granted permissions
or with such stringent restrictions to be prohibitive. 
The route is additionally at high risk of price increase and programme
delay potentially as result of any archaeological finds and/or conditions
to pass around the fort and surrounding previously undisturbed areas. 
The land required for the route is currently plantation forestry and
grazing land. 
Due to the archaeological restrictions, long section of new road and
budget cost this option is discounted.
The overhead power line passes northbound along the west side of
the forest block and minor realignment/height change may be
required. This is not included in the costing. 
Table 12 – Grey Route, Option 8.
Route Option 8: Alternative longer bypass (Grey Route)
Description • The grey route is the longest route considered and passes to the
north of the existing bypass and main plantation blocks to pass
around the north side of the fort and tying into the A816 at the
north corner close to/within the Scheduled Monument.
• 760m length
Page 201

Page 202

30
Options Assessment Report
A816 Bealach Mor 
Cost Estimate • £10.5M – £12M
Engineering
Assessment
• The grey route passes to the east and north side of an identified
prehistoric hillfort (Canmore ID 22850). Permissions for
excavations in the area is likely to be denied or heavily controlled
i.e. watching brief, controlled methodology and full archaeological
excavation of any new find areas.
• Western tie in is located within/close to the Scheduled Monument
site and due to topography there are no suitable alternatives.
• The grey route is the only route to avoid both the lower
embankment at the west end of the site and the deep-seated slip
at the east side.
• The route has the longest new road construction length at 760m.
Geotechnical
Hazard
• There are areas of very deep peat and marsh land that would
require additional foundation stabilisation works.
• Detailed ground investigation would be required along the route.
Environmental
Assessment
• The grey route passes through marshy grassland, a ground water
dependent terrestrial ecosystem (GWDTE) and as such is a
protected habitat.
• The impact on the environment would be high as the entire 760m
route would be newly constructed.
Discussion/
Recommendation
Although the route avoids the deep-seated slip at the east side of the
area by tying into the A816 further east the additional cost of building
in the peat/marsh area combined with the protected status of the
GWDTE area makes it likely that even if permissions could be gained
to allow works the costs would be greater than those to remediate the
slip. 
The tie in location at the western end of the site passes though/close
to the Scheduled Monument and is unlikely to be granted permissions
or with such stringent restrictions to be prohibitive. 
The route is additionally at high risk of price increase and programme
delay potentially as result of any archaeological finds and/or conditions
to pass around the fort.
Due to the archaeological and environmental restrictions, long section
of new road and budget cost this option is discounted.
Page 202

Page 203

31
Options Assessment Report
A816 Bealach Mor 
The overhead power line passes northbound along the west side of
the forest block and minor realignment/height change may be
required. This is not included in the costing.
Page 203

Page 204

32 
Classification: OFFICIAL
References
AADT Traffic https://roadtraffic.dft.gov.uk/local-authorities/44 Accessed 07/01/25
British Geological Survey (BGS), GeoIndex Onshore,
https://mapapps2.bgs.ac.uk/geoindex/home.html, accessed 04/02/25
Jacobs AECOM. 2020. STPR2: Initial Appraisal: Case for Change - Argyll & Bute Region. Kendon, M.,
2023. Exceptional rainfall in Scotland, 6 to 7 October 2023, s.l.: Met Office.
Nature Scotland National Biodiversity Network Gateway https://data.nbn.org.uk/ Nature
Scot Site Link.
Preston, R., 2025 Bealach Mor. Preliminary Ecological Appraisal.
Scottish Government Urban Rural Classification (Scottish Government 2016) 2. Overview -
Scottish Government Urban Rural Classification 2016 - gov.scot Accessed 16/01/25
SNH National Landscape Character Assessment. LCT 043 - Upland Parallel Ridges - Argyll -
Final pdf.pdf, 1:50,000 Republished in 2019
SNH Sitelink http://gateway.naturescot.gov.uk/sitelink/searchmap.jsp Accessed
07/02/25 Soil Survey of Scotland Staff (1981). Soil maps of Scotland at a scale of
1:250 000.
Macaulay Institute for Soil Research, Aberdeen.
Soil Survey of Scotland Staff (1981). Land Capability for Agriculture maps of Scotland at a
scale of 1:250 000. Macaulay Institute for Soil Research, Aberdeen. 
Page 204

Page 205

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
11 SEPTEMBER 2025 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
1. EXECUTIVE SUMMARY
1.1 The purpose of this report is to update the Environment, Development and
Infrastructure Committee on current progress of the large-scale, externally
funded project work of the Transformational Projects and Regeneration Team,
and to highlight key issues that may impact on the successful delivery of
projects. 
1.2 The last update report was considered by Environment, Development and
Infrastructure Committee in March 2025. 
1.3 The team is currently responsible for the delivery and or management of
projects and associated grants with a cumulative value of over £100m. The
associated grants the team manages are listed in Appendix A. It should be
noted that following completion of each project, the team continues to have the
responsibility for the monitoring and final drawdown and reporting up until the
end of the 12-month defects period or beyond depending on conditions on the
respective grant contracts. 
1.4 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s Rural Growth Deal (RGD)
Programme.  This follows the merging of this team with the RGD Programme
Management Office (PMO) following the retirement of the previous
Transformation Projects and Regeneration Manager. 
1.5 The team are also leading on the emerging Community Regeneration
Partnership Funding (CRP) from the UK Government.  This funding replaces
the Levelling Up Partnership programme and totals £20.34m for Argyll and Bute
with all funding requiring to be fully committed by 2026/27.  It is anticipated that
the UK Government will officially confirm projects to be funded via the CRP
programme in September 2025. 
1.6 The Council welcome the Scottish Governments commitment to continue both
the Regeneration Capital Grant Funding (RCGF) and Place Based Investment
(PBI) funding in 2025/26 following their suspension by the Scottish Government
in 2024/25 due to budget challenges.  Further detail of successful projects is
included in paragraph 4.8 of this report.   
Page 205 Agenda Item 12

Page 206

1.7   Members are asked to note that the grant funding landscape and delivery of
capital projects remains extremely challenging due to cost of living issues,
budget and resource constraints however, the Transformation Projects and
Regeneration Team will continue to respond to emerging Government policy
priorities and future external grant, funding opportunities. 
RECOMMENDATIONS
It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Consider the current progress contained within the report.
ii. Note that further updates relating to pending funding bids will be brought
back to the Environment, Development and Infrastructure Committee in due
course to update Members. 
Page 206

Page 207

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
11 SEPTEMBER 2025 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
2.0 INTRODUCTION
2.1 This report sets out the current position of the large-scale projects, which are
currently being delivered on the ground, or have secured external grant funding
that are managed by the Transformational Projects and Regeneration Team. 
2.2 The Transformational Projects and Regeneration Team sits within the Council’s
Development and Economic Growth Service and works region-wide. The team
has a particular focus on ‘place’, heritage regeneration, the creative industries,
renewables and Islands and manages a diverse range of capital projects and
external grants.  The team works closely with colleagues across the Council,
communities, businesses, public agencies, third sector organisations, town
centre heritage building owners and the owners of vacant business property to
realise positive change for our communities. 
2.3 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s Rural Growth Deal (RGD)
Programme and are leading on the emerging Community Regeneration
Partnership (CRP) Funding from the UK Government.   
2.4 CRP funding replaces the Levelling Up Partnership programme and totals
£20.34m for projects in Argyll and Bute with funding to be fully committed by
2026/27. 
2.5 The team’s work broadly includes the following areas:- 
• Developing and submitting bids to secure external funding of various
scale through a competitive process, such as the new Heritage and
Place Programme, previously referred to as the Conservation Area
Regeneration Scheme (CARS) programmes;
• Development and delivery of regeneration projects with a particular
emphasis or theme, such as the suite of measures to encourage
shopping locally;
• Development and delivery of several place-based engagement projects,
working in partnership with the community and key partners, leading to
action plans, such as charrettes, and working with communities to
realise these community ambitions; 
• Development of the economic opportunities for Argyll and Bute across
Film, Creative Industry and Renewable sectors, with the objective of
Page 207

Page 208

securing income into the area and delivering local economic benefit,
including support to community organisations working across these
sectors. This work also includes the setting up and management of the
Argyll and Bute Renewable Alliance (ABRA) with partners in HIE; 
• Support to third sector organisations involved in the delivery of their own
individual community led economic regeneration projects, as well as
support to third sector organisations delivering regeneration focused
projects where Council funding is involved and/or where projects align
with Council outcomes, such as Regeneration Capital Grant Funded
(RCGF) project funding;
• Drafting and submitting external funding bids to competitive calls such as
the Island’s Programme, RCGF and Carbon Neutral Islands Programme; 
• Development and administration of the Argyll and Bute Council’s
Strategic Events and Festivals Fund for which 12 grants have been
awarded for Round 7 (2025/26);
• Progressing the offer to host the 2028 Royal National Mòd (RNM);
• Overseeing the delivery programme and financial administration of
projects supported through funding from Scottish Government, such as
annual Crown Estate (CE) funding and the Place Based Investment
Programme (PBI);
• Working closely with the SG Islands team and working with colleagues
and communities in the development of bids to the Islands Programme
(IP) and associated Carbon Neutral Islands funding.
• Supporting the owners of empty business properties through grant aid
funded by NDR income.
• Development and delivery of projects within the Council’s RGD
programme and Community Regeneration Partnership. 
2.6 This paper also seeks to report on key issues that may impact on the current
status of each project, such as any amendments to project scope or timeframe. 
2.7 The large-scale projects currently in delivery, either directly by the team,
colleagues across the Council or by a third party and where the team is
responsible for managing the associated grant, are included within the table in
Appendix A, and have a cumulative total value of over £100m. The individual
projects being taken forward under PBI and CE are not listed individually in
Appendix A. 
3.0 RECOMMENDATIONS
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Consider the current progress contained within the report.
ii. Note that further updates relating to pending funding bids will be brought
back to the Environment, Development and Infrastructure Committee in due
course to update Members. 
Page 208

Page 209

4.0 DETAILS
4.1 The following sections summarise the progress associated with each of the large-
scale projects that are currently in delivery or have grants managed by the
Transformational Projects and Regeneration Team. In addition, the report
provides information on annual funding streams received by the Council and
managed by the team as well as annual competitive external funding grants
secured and being managed. The individual projects are listed in Appendix A
with the exception of those individual projects supported through PBI and CE. 
HERITAGE LED REGENERATION PROJECTS 
4.2 Rothesay Regeneration 
Following a decade of Townscape Heritage Initiatives, and £7.5m investment in
the town centre, regeneration effort continues to tackle dereliction in Rothesay.
The Transformation Projects and Regeneration Team are actively supporting
efforts to address key landmark buildings including:- 
• £9m of RGD funding allocated to Stages 2 and 3 of Rothesay Pavilion. 
• Supporting local social enterprise with funding applications to HES, a
condition survey and business plan for the Royal Hotel;
• £40k of CE funding allocated for demolition of vacant building on Albert Pier.
A further £100k of funding allocated via PBI for resurfacing and lining works
on Albert Pier with a focus on enhanced parking for coaches.
• Up to £4m of funding via the UK Government’s Community Regeneration
Partnership to support the regeneration of the Royal Hotel in Rothesay
(subject to approval of UKG).  Partnership project with George Hanson, HIE,
and UKG.  Funding application made to Scottish Governments Islands
Programme for £400k to support pre-construction phases of this project. 
4.3 Helensburgh CARS (2021 – March 2026) 
Helensburgh CARS is a £2.4m project in final year of delivery. The partnership
project is funded by Argyll and Bute Council (£500k) and HES (£1.24m) with
owner's personal contributions completing the funding.  A fully funded project
officer is employed to deliver the project for its duration, and the project also
supports a modern apprentice. 
Works to the first two priority buildings commenced on site in September 2024
and will be completed later this year. Works to the third and fourth priority
buildings, at the time of writing this report, are due to commence in August
2025. One small repair grant has also been awarded to refurbish the windows
in the Grade A listed Macintosh Club and another for roof and amenity deck
repairs to make several commercial properties within 22-34 Sinclair Street
watertight.   
Two shopfronts are complete. Two lime mortar training courses have been
held, and a modern apprentice position was filled in September 2024. An online
Page 209

Page 210

webinar co-hosted with Under One Roof aimed at property owners in
Helensburgh is scheduled for October 2025. This will give expert advice and
guidance on owner's associations, common repairs and how to deal with issues
that arise from absent owners and missing shares with a Q&A session.       
4.4 Lochgilphead CARS (2020 – Mar 2026) 
Lochgilphead CARS is a £2.2m partnership project with HES (£969,700) in its
sixth year of delivery.  The project is due to conclude in March 2026. 
Four priority building projects have been completed and work is progressing
well on another two.   
A number of small repair grant/shopfront improvement projects have also been
delivered.  This includes three significant shopfront reinstatement projects that
were completed in July. 
Local stakeholders are benefiting from a number of traditional skills training
courses and educational activities that have been funded and delivered via the
scheme. This includes; specialist training in Lochgilphead for local contractors
and building professionals; traditional skills Demo Days for local school pupils
and a Shop Window Art Project delivered in partnership with a local artist and
Lochgilphead High School. 
4.5 Tarbert Heritage Regeneration Scheme (TBC) Project status 
On 26 June 2025, Council agreed that applications be submitted to National
Lottery Grants for Heritage (NLHF), and Historic Environment Scotland’s
(HES), Heritage and Place Programme (HPP), for a 5-year Tarbert Heritage
Regeneration Scheme.  Bids will be submitted on 6th and 29th August 2025
respectively, with decisions expected in January 2026.  Both are subject to a
competitive process and as such a delivery phase is not guaranteed. The
application to NLHF is for £850,000 and the application to HES is for £999,997. 
WIDER REGENERATION FOCUSED PROJECTS 
4.6 Tarbert / Lochgilphead Regeneration Fund 
In its 2016/17 budget, Council allocated £3m from reserves to support
regeneration and economic development in the settlements of Tarbert,
Lochgilphead and Ardrishaig. 6 projects were identified to proceed to Full
Business Case (as ratified by Policy and Resources Committee on 19th
October 2017).  The following projects are complete: 
• Gleaner (Phase 1 only) - completed summer 2019.
• Tarbert Harbour – shore side facilities completed in May 2019, car park
completed in March 2021.
• Barmore/Garvel Road junction improvements - completed February
Page 210

Page 211

2020.
• Colchester Square/Argyll Street, Lochgilphead – completed May 2021.
• Lochgilphead Front Green – completed August 2022.
• Ardrishaig North Public Realm – completed April 2023. 
The only remaining allocation of funding relates to a second phase of
development on the former Gleaner Oil site in Ardrishaig.  This funding totals
£250,000 and we have had discussions with Scottish Canals about bringing
forward a business case for approval 2025/26. Scottish Canals are in
negotiations with a potential private sector developer which could result in a
significant private sector investment for this part of Ardrishaig. 
4.7 Regeneration Capital Grant Funding (RCGF) 
An update on the current RCGF projects is provided below and is followed by a
table of all current grant contract awards (Table 1) 
• Port Ellen Community Hub, Islay – the additional funding, reported in
the last update, has enabled works to recommence and the project is
progressing towards completion, expected late Summer 2025.
• Kilmory Business Park, Lochgilphead – work is progressing with
M&K MacLeod on the proposed Kilmory Business Park.  Works are on
site and are expected to be completed in December 2025.  This public
investment has also attracted signficant private sector investment.
• Aros Waterfront Development, Mull – outdoor activity hub – a
contract was awarded in January 2024 and works are ongoing. 
Table 1 – RCGF Grant Projects 
RCGF Project Grant
Awarded
Year
Awarded
Balance
Remaining /
Yet to Drawdown
Port Ellen Community hub, Islay  £1,046,223 2021/22 £0
Kilmory Business Park in
Lochgilphead 
£829,000 2021/22 £581,988
Ulva Ferry Shore Facilities Building -
Doras Caolas Ulbha
£602,590 2022/23 £3,671
Aros Waterfront outdoor activity hub £403,500 2023/24 £0
Nonhebel Light Industrial Park
Expansion
£654,000 2023/24 £1,948
Fyne Futures Local Food Production
and Training Centre, Bute
£250,000 2025/26 £250,000
Isle of Luing Community Owned
Slate Quarry
£1,747,936 2025/26 £1,747,936     
The following stage 1 expression of interest applications were submitted to the
Scottish Government in June 2025 for consideration for RCGF funding in
2026/27.  It should be noted that the RCGF funding process is undertaken in 2
Page 211

Page 212

stages.  Projects that are successful at Stage 1 will go forward to the more
detailed Stage 2 application process for submission in Autumn 2025. 
Table 2: RCGF 2026/27Stage 1 Funding Bids 
Project Value Lead Organisation 
Kintyre Sea Sports  £800,000 Kintyre Sea Sports
Lighting Up the Shore
Station - A Sustainable
Hub for Tiree  
£760,000  The Hynish Trust
Nonhebel Park (Final
Phase)
£595,000 MICT
Sonas Childcare £900,000 South Islay Development
Tarbert Harbour
Community Water
Sports and Activity Hub
£850,000 Tarbert Harbour
Authority
Tighnabruaich
Community Refuelling
and Business Hub
£120,000 The Tighnabruaich
District Development
Trust 
The confirmation of potential RCGF monies in 2026/27 is welcome as this has
been an important source of external capital funding for both the Council and
community projects over the past decade. We await further notification as to
whether RCGF funding will be available in future years.  
4.8 Scottish Government Place Based Investment Funded projects 2021 – 2024 
When Place Based Investment (PBI) funding was introduced by the Scottish
Government, allocations were provided over a five-year period and to date
have been received as follows.  
• 2021/22 - £821,000 
• 2022/23 - £712,000
• 2023/24 - £496,000 
Unfortunately, the Council’s 2024/25 allocation of £496,000 was not made
available. Following further consideration by the Scottish Government the
council has now been informed that PBI will be made available for 2025/26.
This will be provided in 2 tranches with £388,368 of funding in tranche 1 and a
further £107,632 later in the financial year subject to the Scottish Governments
budget position.  
Table 3 below, sets out projects to be delivered using PBI funding in 2025/26. 
These projects were endorsed by the Council’s P&R Committee in August
2025. 
Page 212

Page 213

Table 3: 2025/26 PBI Projects 
Project Tranche 1  Tranche 2
Albert Pier  £100,000  
Victoria Hall,
Campbeltown
£100,000  
Shopfront and
Business Support  
£56,000
CCTV Upgrades  £100,000  
Helensburgh Outdoor
Museum
£80,000  
Rockfield Centre,
Oban  
£60,000
TOTAL £380,000 £116,000 
4.9 Scottish Crown Estate Revenue Allocation Funding 
In financial year 2024/25 the Council received Crown Estates funding totalling 
£1,818,715.  The Council is still awaiting confirmation of the allocation for this
financial year (2025/26) and it is unclear as to when formal written notification
will be received from the Scottish Government. However, based on previous
years allocations, a prudent estimate of £0.8m of anticipated funding in 2025/26
has been assumed and the projects set out in Table 4 will be considered by the
Council’s P&R Committee in August 2025.   
Table 4: 2025/26 Crown Estates Projects 
Project Delivery by Crown Estate
Allocation
Inveraray Avenue Screen
refurbishment 
Development & Economic
Growth 
£120,000 
Gallanach Road - Rock Slope
Protection
Road and Infrastructure
Services  
£300,000 
Tarbert Heritage and Place
Programme - Match Funding
(note this was agreed by Council
in June and is noted here for
information) 
Development & Economic
Growth
£115,000 for the
next 4 years*
CARS Projects - flexible fund to
support businesses with capital
improvements to
shopfronts/buildings building on
previous CARS investment 
Development & Economic
Growth
£150,000
Page 213

Page 214

Victoria Hall, Campbeltown –
repair and refurbish entire front
elevation.  
Development & Economic
Growth
£50,000
Dunoon Public Realm  Development & Economic
Growth 
£65,000
TOTAL   £800,000 
4.10 Scottish Government Islands Programme and Carbon Neutral Islands
Capital Fund 2025/26 
The Scottish Government has announced that Islands Programme funding of
£5.3m will be available for the 2025/26 financial year to fund capital projects on
inhabited Scottish islands. A further £1.4m is available to support the Carbon
Neutral Islands (CNI) in their progression towards net zero.  Both of these funds
are subject to a competitive bidding process. 
Following approval of the following Island’s Programme Funding bids by EDI
Committee in June 2025, the following applications were submitted in July:- 
Table 5: 2025/26 Islands Programme Funding Bids 
Project Name - description Project Lead IP funding
request
Total project
value
Former Royal Hotel,
Rothesay – Detailed design
works
Transformation
Projects and
Regeneration
£400,000 £7,600,000
Community Digital Hubs
Phase 2
Strategic
Transportation
£125,000 £125,000
Unlocking Ulva – Landing
Craft Project 
North West Mull
Community
Woodland
Company
£536,020 £536,020
Skerryvore Lighthouse Shore
Station - The Lighthouse
Cottages
Hynish Trust £306,050 £330,050 
In addition to the Island’s Programme, a £1.4m Carbon Neutral Island Capital
Fund was announced for 2025/26, also previously considered by EDI
Committee. Funding bids have been submitted for the following projects: 
Table 6: 2025/26 CNI Funding Bids 
Project Name - description Project Lead CNI funding
request
Castlehill Solar Array Expansion IET £195,000
Additional Measures - Community
Buildings Phase 2
IET £401,843 
Page 214

Page 215

Further updates on the funding bids set out in Tables 5 and 6 will be brought
back to a future meeting of the EDI Committee following the outcome of the
Scottish Governments Investment Panel in August.   
4.11 Scotland Loves Local Projects Oct 21 – 2025 
Argyll and Bute Gift Card - The gift card for Argyll and Bute formally launched in
October 2021. To date, over 350 Argyll and Bute businesses have registered to
accept the card as a means of payment for goods and services. The Council
has continued to issue cards to eligible islands households supported by the
Scottish Government’s Island Cost Crisis fund.
.
Inclusive of the LACER funded cards, as of 31 July 2025, a total of £990,825
has been redeemed through the gift card. 
Funding for the Gift Card has now been expended and we are in the process of
assessing the anticipated costs and benefits of continuing with the scheme, a
separate report will be provided to Policy and Resources Committee in due
course. 
4.12 Islands Cost Crisis Emergency Fund 2025 
On 6 May 2025, the Scottish Government announced that Islands Cost Crisis
Emergency funding (ICCEF) of £1 million would be available for the 2025/26
financial year. The funding will be distributed to the six Local Authorities with
responsibility for islands through the 2025/26 Local Government Revenue
Grant.  The fund will be administered by Scottish Futures Trust (SFT) on behalf
of the Scottish Government. 
The funding for Argyll and Bute Council is £145,000 for financial year 2025/26. 
The Council’s P&R Committee endorsed the project options for this funding in
August 2025 and table 7 below, sets out the proposed funding allocation; 
Table 7: ICCEF 2025/26 Allocation  
ICCEF 2025/26 Distribution 
Targeting Fuel Poverty with ALI
energy’s Affordable Warmth Service
£120,000
Food Bank Grants   £25,000
TOTAL ICCEF 25/26 £145,000 
The proposed funding allocation will increase vital funding support to 5 island
food banks.  The Council are also intending to trial a scheme working in
partnership with ALI energy to extend their Affordable Warmth service.  This
supports residents most at risk of fuel poverty and the scheme will be
available to residents on all our island communities.  Fuel poverty rates are
generally higher on Scottish islands and this is exacerbated in households
with low incomes.  
Page 215

Page 216

4.13 Helensburgh Former Skating Pond (Skating Pond) Feb 2025- May 2026 
Helensburgh Former Skating Pond is a Local Nature Conservation Site and
part of the open space protection area which forms part of the Green Network
and Core Path Plan in the Green Belt bordering Helensburgh.  It is regularly
used as a walk/part of walks however over time the Skating Pond itself and
other areas within the site have become filled with invasive species.  In addition
the paths, built circa 2000 require repair and improvement. 
The site is owned by Argyll and Bute Council who have £50k funding from the
Nature Conservation Fund to consider how to improve and address issues of
management and maintenance of the site for public access, as well as
providing opportunities for environmental interpretation and learning
opportunities.  It is recognised that there is not enough funding to undertake
any capital works at this stage and that an initial assessment of the site is
required first.  To this end, consultants have been appointed and interim
findings produced as well as first stage community consultation and
engagement with local primary schools.   A final report with preliminary costs
will identify a preferred option for consideration. 
5.0 RURAL GROWTH DEAL     
5.1 The Rural Growth Deal Full Deal Agreement was signed on 10th March 2025
by the First Minister, Secretary for State for Scotland and the Council Leader.
The RGD will deliver £50m of investment from the Scottish and UK
Governments for projects that are a driver for inclusive and transformational
economic growth across the region.  The Council and key delivery partners
will also provide a minimum of £20m of match funding throughout the 10-year
Deal programme.    
5.2 The Rural Growth Deal has now entered year 2 of a 10 year programme of
project delivery. A total of £1.6m has been claimed from Government since
March 2025. The claimed funds all relate to the renovation of Rothesay
Pavilion, which remains the only project to have a Full Business Case
endorsed by central government.
5.3 A total of £6,025,000 has been awarded from Government for FY2025/26. Up
to £4m of this is allocated to the renovation of Rothesay Pavilion, with Kintyre
Sea Sports and Enabling Worker Accommodation projects receiving £1m
each and £25,000 for Highland and Islands Enterprise’s Business Skills
programme. These projects are developing their Full Business Cases for
appraisal by Government. 
5.4 It should be noted that no Rural Growth Deal funding can be drawn down in
advance of endorsement of full business cases by Central Government.  This
Page 216

Page 217

process can take up to 9 months to complete and requires RGD partners to
spend project development funding at risk.
6. COMMUNITY REGENERATION PARTNERSHIP
6.1 In the 2024 Autumn Statement the UK Government committed to delivering a
package of support to Argyll and Bute Council in order to improve outcomes
across the region in line with the Government’s core missions and priorities. 
Community Regeneration Partnership Funding will build upon previous work
and engagement undertaken by the Ministry of Housing, Communities and
Local Government (MHCLG) under the banner of Levelling Up.
6.2 As part of the core funding package, there is up to £20m capital funding and
£250k revenue available for the CRP. Funding is profiled for payment in
financial year 2026-27 and is subject to business case approvals by UKG
Ministers. A further capacity payment of £45k will be provided to support staff
resourcing. This will be paid in FY25-26 and follows a separate capacity
payment which was transferred at the beginning of FY24-25.
6.3 A draft list of priority projects was approved by the Council’s P&R Committee
on the 20th February 2025 and this has formed the basis of negotiations with
the UK Government. Civil servants have also undertaken local engagement
with a number of external stakeholders and community groups during spring
2025.  UK Government officials are currently drafting the programme level
business case which will require ministerial approval prior to an official funding
announcement.  The Council have been advised that the UK Government
hope to confirm successful projects in September 2025 (subject to approval of
the business case). 
6.4 Further updates will be brought back to the EDI Committee in the next project
update report.
7. EMPTY BUSINESS PROPERTY GRANTS
7.1 Empty Property Relief was devolved to Scottish Local Authorities on 1 April
2023. At their meeting of 23 November 2023, Council subsequently agreed
that from 1 April 2024, 50% Non-Domestic Rates (NDR) relief could be
granted to business properties which are empty for a maximum of three
months.  In cases where business properties remain empty beyond three
months, 10% relief can be awarded for up to an additional nine-month period.
Following this, should a business property remain empty beyond a twelve-
month period, no further NDR relief would be awarded, and 100% Non-
Domestic Rates would begin to be charged. 
7.2    On 23 November 2023, Council also agreed that the remaining Empty Property
Relief funding from Scottish Government be used towards an Empty Property
Business Grant Scheme, the aim of which would be to assist owners to return
properties to productive use. An Empty Business Property Officer has since
been appointed to support the distribution of funds, which amount to in the
region of £300k for 2025/26.
Page 217

Page 218

7.3 On 8th May 2025, the council’s Policy and Resources Committee approved 
Extended Empty Property Relief, whereby non-domestic rates relief will be 
extended for property owners who are actively working to bring their
properties back into use. Owners may apply for 100% relief for up to 12 
months at any time after the property becomes vacant, provided the 
conditions are met. 
7.4  A further paper providing an update on the Empty Business Property grant 
scheme was presented to the EDI committee on 19th June 2025. The 
committee approved the Empty Business Property Grant Scheme with an 
anticipated budget of up to £785,000 for the financial year 2025/26. 
7.5 Members are asked to note that the number of vacant business properties is 
now being recorded as part of the Councils Area Performance Reporting.   
7.6 At this time, Scottish Government funding is not committed beyond 31 March 
2026 and Scottish Government will have to review arrangements for devolved  
Empty Property Relief prior to financial year 2026/27. As a result, a further 
update on Empty Business Property Grants will be brought back to the EDI 
Committee in due course. 
8.  CONCLUSION 
8.1 This report provides an update to the Environment, Development and
Infrastructure Committee on progress with large-scale, externally funded
project work being delivered by the Transformational Projects and
Regeneration Team.  Currently this involves over £100m of external funding
across Argyll and Bute with further bids in progress. 
8.2 The projects and grants detailed within this report will result in assisting the
economic recovery of Argyll and Bute, helping to sustain numerous small
businesses, community organisations, making our places more investor ready
and improving our towns and villages as places to live, work and visit. 
8.3 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s RGD Programme and the
team are also managing the emerging CRP programme.  Combined, these
programmes will deliver in excess of £70m of external funding to the region.   
8.4 Members are asked to note that the grant funding landscape and delivery of
capital projects remains extremely challenging due to budget and resource
constraints however, the Transformation Projects and Regeneration Team will
continue to respond to emerging Government policy decisions and future
grant funding opportunities. 
Page 218

Page 219

9. IMPLICATIONS
9.1  Policy - The delivery of these projects fits with the Council’s Corporate Plan,
Argyll and Bute Local Outcome Improvement Plan and the Economic
Development Action Plan. The economic outcomes from this project will
contribute to the Government’s Economic Strategy. 
9.2  Financial - All funding has been approved for the projects detailed in the
report. The funding comes from the Council and from external funding
sources, some from highly competitive processes.  We will continue to review
costs and assess budgets. 
9.3  Legal - Each project will have differing legal and procurement requirements
depending on the grant funder and the associated grant contract conditions
and we are working closely with colleagues to identify the support required
and to allow this to be factored into future work plans. 
9.4  HR - The resources required to deliver the projects will be continually
monitored. The management of these externally funded projects as well as
the management of the Council, PBI, CE, IP and RCGF grants requires a
significant amount of resources from the team to ensure that all the necessary
due diligence and financial management is undertaken and risk is minimised
to the Council. 
9.5  Customer Service – None 
9.6 Risk - Construction projects by their very nature are challenging given issues
that can arise relating to site conditions, managing contractors/the design
team and associated budgets and meeting funder’s requirements. We
continually seek to minimise the risk through strong project management
processes, however until the projects are fully delivered on site there remains
a risk. Other areas of risk relate to the potential for limited uptake in regard to
CARS grants and also over-run on costs for third party projects. In regard to
the latter this is a high risk particularly as the Council is not the responsible
body for the projects or their delivery on the ground. The setting up of regular
benefits realisation group meetings and building good working relationships
with the third parties assists in identifying where issues may arise and where
additional support may be required. Cost inflation continues to impact the
construction industry and this is exacerbated by limited supply chain options
in rural areas.  Robust procurement and contract management processes will
reduce the risk of cost escalation on projects.   
9.7  Climate Change - It is an ambition of our project work to work towards net zero
by adopting a carbon conscious approach throughout.  Some grant funding
directly supports the transition to net zero (e.g. CNI).   
Page 219

Page 220

9.8 Fairer Scotland Duty: Socio Economic Duty – Grant funding can support
projects which are a catalyst for economic growth and well-being, particularly
on some of our most fragile communities. 
9.9 Equalities – protected characteristics – Projects can be a driver for inclusion. 
9.10 Customer Duty – Delivery of external grant funding will ensure the Council are
supporting local communities and households across Argyll and Bute. 
9.11 Island Communities – some of the funds directly support local island
communities e.g. Islands Programme, CNI, ICCEF. 
9.12 Childrens rights and wellbeing – Some funding will directly support projects 
that aim to provide positive outcomes for children and young people.  This will 
include those at greatest risk of poverty and households with children. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Leader of the Council: Councillor Jim Lynch
Policy Lead for Business Development: Councillor Math Campbell-Sturgess 
August 2025 
For further information - please contact: 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Jonathan Welch, Transformation Projects and Regeneration Manager
jonathan.welch@argyll-bute.gov.uk 
Appendices: 
Appendix A – List of Council and Third Party projects that the team is either
responsible for delivering directly or for managing the grants given by the Council to
a third party organisation.
Page 220

Page 221

APPENDIX A - LIST OF COUNCIL AND THIRD PARTY PROJECTS 
Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Tarbert Lochgilphead Regeneration Fund (Remaining Balance) £250,000 £250,000 £0 TBC Ongoing (Gleaner
Site)
Port Ellen Community hub, Islay RCGF grant  £1,570,259 £0 £1,096,223 2021/22 2025
Kilmory Business Park in Lochgilphead RCGF grant  £1,980,000 TBC £979,000 2021/22 2025/26
Lochgilphead CARS (Includes 22/23 PBI Grant) £2,200,782 £750,551 £1,269,731 2020 2026
Helensburgh CARS £2,400,000 £500,000 £1,240,000 2021 2026
Events and Festivals grants £114,700 £114,700 - 2024/25 2025/26
Royal National Mòd (provisional) £45,000 £45,000 £0 2024/25 2024/25
Crown Estate Funding Award 23/24 £1,590,409 £0 £0 23/24 Ongoing
Crown Estate Funding Award 24/25 £1,818,715 £0 £0 24/25 Ongoing
Community Regeneration Funding  £20,340,000 £TBC £TBC 25/26 Ongoing
Scotland Loves Local £46,000 £0 £46,000 2022/23 2025/26
Aros Waterfront outdoor activity hub – RCGF Grant     £414,565 £0 £403,500   2023/24 2025/26
Islands Programme 2023/24 - Rockfield Road, Tobermory Phase 1 (also
PBI and Crown Estate) £1,105,796 £250,000 £855,796 2023/24 2025/26
Islands Programme 2023/24 - Tiree Care Home £1,250,000 £580,000 £450,000 2023/24 2024/25
Islands Cost Crisis Emergency Funding £145,000 £0 £145,000 2025/26 2025/26
Tarbert Heritage Regeneration Scheme – Development Phase £140,000 £60,000 £80,000 2023/24 2024/25
CNI Capital Fund 24/25 - Decarbonisation of Community Buildings  £246,444 £0 £246,444 2024/25 2025/26
CNI Capital Fund 24/25 - Islay Forestry Initiative Phase 3 £354,116 £0 £142,285 2024/25 2025/26
Isle of Luing Slate Quarry – RCGF 25/26 £2,000,000 £0 £1,747,936 2025/26 2026/27
Page 221

Page 222

Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period) 
Rural Growth Deal – Kintyre Seasports £2,300,000 £200,000 £2,100,000 2025/26 2026/27
Rural Growth Deal – Rothesay Pavilion (Stage 2b/2c) £22,000,000 £10,749,000 £11,700,000 2025/26 2026/27
Rural Growth Deal – Low Carbon Economy – Isle of Islay £3,000,000 £24,129 £3,000,026 2032/33 2033/34
Rural Growth Deal – Rural Skills Accelerator Programme – Dunoon
STEM Hub £3,362,728 £77,455 £3,240,000 2025/26 2026/27
Rural Growth Deal – Rural Skills Accelerator Programme – SAMS STEM
Hub £2,500,000 £0 £2,500,000 2026/27 2027/28
Rural Growth Deal – Rural Skills Accelerator Programme – UHI Argyll
Estate Enhancements Lochgilphead  £1,500,000 £0 £1,500,000 2029/30 2029/30
Rural Growth Deal – Housing to Attract Economic Growth – Isle of Mull £1,500,000 £125,300 £1,500,000 2025/26 2026/27
Rural Growth Deal – Housing to Attract Economic Growth – Isle of Islay £1,500,000 £37,959 £1,500,000 2028/29 2028/29
Rural Growth Deal – Clyde Engineering and Innovation Centre £7,000,000 £59,566 £199,820 2029/30 2031/32
Rural Growth Deal – West Coast UAV Logistics and Training Hub £4,000,000 £21,886 £420,000 2031/32 2032/33
Rural Growth Deal – Marine Industry Training Centre £7,830,000 £0 £7,830,000 2027/28 2029/30
Rural Growth Deal – Centre for Seaweed and Shellfish Innovation and
Development  £3,330,000 £0 £3,330,000 2027/28 2028/29
Rural Growth Deal – Machrihanish Innovation Campus £3,840,000 £0 £3,840,000 2026/27 2027/28
Total £101,674,514 £13,395,546 £51,361,761     
Page 222

Page 223

Page 223

Page 224

This page is intentionally left blank

Page 225

1 
ARGYLL AND BUTE COUNCIL                ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH               11 SEPTEMBER 2025 
ARGYLL AND BUTE COUNCIL’S ECONOMIC STRATEGY ACTION PLAN: 2025-2028 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this paper is to provide members of the Environment Development
and Infrastructure Committee with an updated Economic Strategy Action Plan
(ESAP) (see Appendix 1) to implement and deliver of the Argyll and Bute Council
Economic Strategy, 2024-2034, covering the short-term period 2025-2028. 
1.2 A key requirement of the ESAP is that the actions are SMART (Specific, Measurable,
Achievable, Realistic, Time-bound) and delivers opportunities that drive inclusive,
economic growth and a fair and inclusive wellbeing economy across the four agreed
strategic pillars: people, place, planet and prosperity. 
1.3 The ESAP aligns the overarching aim of Argyll and Bute Council that Argyll and Bute’s
economy and population need to grow. Each of the council’s priorities drive the
actions and success measures across the document’s four strategic pillars. 
1.4 It is important that ESAP is considered to be a working document that takes account
of changes in the direction of government economic policy, prioritises our resources
to make the greatest impact, acknowledges and responds to advances in
technology that are accelerating, the need for productivity gains and sustainable
economic growth with a clear focus on actions taken over the next three years,
2025-2028, to deliver longer term key outcomes. 
1.5 Progress on actions during 2024-2025 under each of the four strategic pillars are also
outlined in Appendix 1. A short film has been produced to showcase these outcomes
and will be played to members at the meeting. 
1.6 It is recommended that Members of the Environment, Development and Infrastructure
Committee: 
• Note the progress on actions during 2024-2025 and appropriate outcomes for 2034,
as outlined in Appendix 1. 
• Consider and approve the Economic Strategy Action Plan (ESAP), 2025-2028.  
Page 225 Agenda Item 13

Page 226

2 
ARGYLL AND BUTE COUNCIL                ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH             11th SEPTEMBER 2025 
ARGYLL AND BUTE COUNCIL’S ECONOMIC STRATEGY ACTION PLAN: 2025-2028 
2.0 INTRODUCTION 
2.1 A successful economy is essential to delivering and achieving many of our council
priorities, including the delivery of worker housing, delivering inclusive economic
growth and population sustainability – all of which contribute to our quality of life as a
place to live, work, learn and visit. With the pace of global economic change,
technology and uncertainty accelerating, there is a clear need to update our
Economic Strategy Action Plan (ESAP) and reaffirm our strategic intent over the
next three years, 2025-2028. 
2.3 A key requirement of ESAP is that it is an ongoing working document that contains
actions that are SMART (Specific, Measurable, Achievable, Realistic, Time-bound)
and delivers opportunities that drive economic growth and a fair and inclusive
wellbeing economy across the four strategic pillars: people, place, planet and
prosperity. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and Infrastructure
Committee: 
• Note the progress on actions during 2024-2025 and appropriate outcomes for 2034,
as outlined in Appendix 1. 
• Consider and approve the Economic Strategy Action Plan (ESAP), 2025-2028. 
4.0 DETAIL 
4.1 The need for collaboration and the interplay between economy, environment and
community has never been stronger. Argyll and Bute, as a predominately rural
region of Scotland, is particularly well placed to benefit from the potential of the
area’s natural capital resources and the role it can play in providing a range of
employment opportunities including green jobs and achieving net zero across key
industries. 
4.2 The ESAP aligns the overarching aim of Argyll and Bute Council that Argyll and Bute’s
economy and population need to grow to sustain public services and people’s quality of
life. Each of the council’s priorities drive the actions and success measures across the
document’s four strategic pillars as depicted in Table 1 below. 
Page 226

Page 227

3 
Table 1: ESAP and Argyll and Bute Council Priorities 
Argyll and Bute Council Priorities ESAP Four Strategic Pillars
Communities: empowered and
resilient.
Place: vibrant and dynamic
communities. 
Prosperity: empowering communities
through delivering external funding and
providing advice (public, private and
third sectors) to increase their
resilience, provide community services
and generate income.
Housing: working to ensure that
everyone who needs a home can find
one that they can afford, in the right
place, and at the right time.
Economic Growth: shared prosperity
and sustainable business growth in
Argyll and Bute.
Population: people are Argyll and
Bute’s most important asset in driving
forward opportunities for growth and
vibrant local economies.
Place: Delivering the actions of the
Housing Emergency.
People, Place, Planet and Prosperity: 
unlocking economic growth
opportunities through public sector
intervention and private sector
investment.
People: addressing the continuing
decline in our economically active
population, improving workforce skills
and attracting key workers, promoting
equal access to education opportunity,
and supporting job opportunities in
emerging and new industries.
Children and Young People: making
Argyll and Bute an attractive choice for
families.
People: improving education, boosting
skills and training opportunities for all
ages that are aligned to higher paid
employment and/or self-employment
opportunities, with embedded Fair Work
First principles. NOLB focus on the
child poverty agenda.
Place: investing in our towns, rural and
remote rural communities, including our
islands and peninsulas, to attract new
people and businesses.
Transport, Infrastructure and Digital
Connectivity: Keeping people,
businesses, goods and services moving
through Argyll and Bute
Place: lobbying for and investment in
critical transport infrastructure; lobbying
for better digital connectivity through
R100 and Gigabyte.
Environment: the Council has already
declared a climate emergency and
must continue to keep this issue as a
primary consideration,
Planet: delivering net zero and
improving our biodiversity by supporting
the sustainable growth of clean energy
production (i.e. hydro, solar, wind and
biomass), woodland, peat and marine
habitat restoration, encouraging green
industries to develop in our area that
generate community benefits and
ownership options. 
Page 227

Page 228

4 
Table 1: ESAP and Argyll and Bute Council Priorities (continued)
Argyll and Bute Council Priorities ESAP Four Strategic Pillars
Sustainable Service Delivery: we
want to provide the best services we
can for the money and resources
available – and make clear the
standards that our communities can
expect. We know that this is important
to local people.
This is a driving factor for actions
across the four strategic pillars of
People, Place, Planet and Prosperity.
Focus on attracting external income
and investment in our area. Improving
people’s skills, employment opportunity,
and increasing income opportunities for
local communities. 
Speaking Up for Argyll and Bute:
collective, as well as collaborative,
action is necessary to deliver growth on
the scale that Argyll and Bute needs.
Participating in Government
consultations, lobbying for additional
investment and making the place
investable as place to do business. 
This is a driving factor for our actions
across the four strategic pillars of
People, Place, Planet and Prosperity. 
4.3 Many of the actions within the ESAP, 2025-2028, will not be fully realised until the
medium term, where their delivery depends on strong collaboration and a joined-up
approach, working closely with internal council colleagues across services, the
Argyll and Bute Community Planning Partnership (CPP), both Governments, partner
agencies and key stakeholders across Argyll and Bute at both a regional and
national level. 
4.4 With limited resources there is a need to focus on the key interventions where we
can make the greatest impact. A core focus of the updated action plan is for Argyll
and Bute to be an inclusive and wellbeing economy through embedding a
Community Wealth Building approach that enables people of all abilities to reach
their full potential. Key sectors for our area include tourism, food and drink, defense
industries and clean energy production with the increasing importance of private
sector investment and SMEs in the local economy creating employment
opportunities associated with our natural and built environment that seeks to retain
and generate wealth in our communities. 
5.0 CONCLUSION 
5.1 The Argyll and Bute economy is undergoing significant changes, presenting both
distinct short and longer-term opportunities and challenges to overcome. The
actions outlined in Appendix 1 are intended to provide a renewed focus to
celebrate and deliver on our key strengths as an area and embrace the
opportunities of our rural, natural resource-based economy for short term delivery in
the first instance. 
5.2 A short film has been produced to showcase in-year progress for 2024-2025 and will
be played to members at the meeting.  
Page 228

Page 229

5 
6.0 IMPLICATIONS 
6.1 Policy – endorsed Argyll and Bute Economic Strategy 2024-34, Local Outcome
Improvement Plan (LOIP), 2024-2034 and National Strategy for Economic
Transformation (NSET- 10-year duration to 2032). 
6.2 Financial – resources will be required to deliver the strategic intent articulated in the
Economic Strategy Action Plan in Appendix 1. 
6.3 Legal - all appropriate legal implications have been taken into consideration. 
6.4  HR – staff required to support delivery of the actions to realise appropriate
outcomes and impacts for residents and communities across Argyll and Bute. 
6.5 Customer Service – none. 
6.6 Risk - buy-in by key partner agencies and stakeholders to assist with the delivery of
short-term strategic actions (up to three years) could be challenging due to the
uncertainty around future funding streams; many budgets are still decided on an
annual basis. 
6.7 Climate Change – the economic actions under planet have been framed to address
the net zero transition agenda. 
6.8 Fairer Scotland Duty - the Fairer Scotland Duty, Part 1 of the Equality Act 2010,
came into force in April 2018. The duty places a legal responsibility on particular
public bodies in Scotland, such as Argyll and Bute Council, to pay due regard to
(actively consider) how they can reduce inequalities of outcome, caused by socio-
economic disadvantages, when making strategic decisions and how this has been
implemented. 
6.9 Equalities (protected characteristics) - all activities will comply with all Equal
Opportunities policies and obligations. 
6.10 Consumer Duty - all activities will comply with the council’s Consumer Duty. 
6.11 Island Communities - actions have been and will be delivered across the whole of
Argyll and Bute including the island communities. 
6.12 Children’s Rights and Wellbeing – none. 
Kirsty Flanagan, Executive Director responsible for Development and Economic
Growth 
Policy Lead for Business Development: Councillor Math Campbell-Sturgess 
14th August 2025 
Page 229

Page 230

6 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
Tel: 01546 604293 and e-mail: fergus.murray@argyll-bute.gov.uk 
Ishabel Bremner, Economic Growth Manager
Tel: 01546 604375 and e-mail: ishabel.bremner@argyll-bute.gov.uk 
APPENDICES
Appendix 1: Argyll and Bute Council SMART Economic Strategy Action Plan 2025-2028 
Page 230

Page 231

7 
Appendix 1 
Argyll and Bute Council SMART Economic Strategy Action Plan 2025-2028 
(WORKING DOCUMENT)  
Page 231

Page 232

8 
PEOPLE: Addressing the continuing decline in our economically active
population, improving workforce skills and attracting key workers,
promoting equal access to education opportunity, and supporting job
opportunities in emerging and new industries. 
The SMART actions noted in the PEOPLE tables below: 
• Increase the economically active population by investing in skills
development. 
• Work with partners to enable equal access to education, both
academic and vocational. 
• Focus on STEM education. 
• Promote increased adaptability and skills development for both
existing and new staff including Argyll and Bute Council and local
businesses. 
Page 232

Page 233

9 
PEOPLE: Education, skills and training opportunities for all ages are aligned to higher paid employment and/or self-employment opportunities, with embedded Fair
Work First principles.
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025 Resources Outcome by 2034
1. Council services through the
Argyll and Bute Employability
Partnership (ABEP) (DEG,
Education, DYW) to map out all
support for vocational
education and training
opportunities across all key
sectors to share with schools,
parents and all residents.   
2. ABEP to align with the current
work of the partners on
increasing awareness of
occupational opportunities
across Argyll and Bute Council. 
1. HIE, SE, SDS, UHI
Argyll, UHI, SAMS,
University West of
Scotland, third sector
providers and
employers to assist
the council with this
mapping exercise, as
members of the
ABEP. 
2. HIE to progress with
establishing the new
private sector driven
Economic Forum. 
1. Completion of an online
directory by the ABEP of all
support for vocational
education and training
opportunities, with web
links to relevant
information, by 31st March
2027. 
2. Economic Forum to be
established by 31st March
2026.
1. Online directory is an
ongoing activity. 
2. Prosper workshop
held on 8th May 2025
to take forward an
Argyll and Bute
Economic Forum; still
to be formalised led
by the private sector. 
1. In-kind support
from all
partners. 
2. Funding
opportunities
for individuals
and skills will be
identified by
web links to
current
support. 
Raised awareness
of all occupational
employment
opportunities for all
ages across Argyll
and Bute.
1. ABEP to work with the Scottish
Qualifications Authority (SQA)
representative on the ABEP to
explore tailored modern
apprenticeship schemes for
areas of skill shortages,
including Planning and
Environmental Health through
investing in council officers with
transferable skills. 
1. More employers to
consider
opportunities to
undertake work
tasters/placements
and apprenticeship
training for adults
aligned to current
funding opportunities
until end 31st March
2026. 
1. Agreement from SQA to
increase tailored modern
apprenticeship schemes for
areas of skill shortages, such
as Planning and/or
Environmental Health aby
31st March 2028. 
2. Current funding work
taster/placement caseloads
available to employers to be
committed and spent by 31st
March 2026.
1. Ongoing activity. 
2. Ongoing activity. 
1. Use existing UK
Shared
Prosperity
Fund and No
One Left
Behind (NOLB). 
2. Council to
invest to save
to alleviate the
skills gap with
appropriate /
improved
access to the
Apprenticeship
Levy funding.
Sustained work
taster placements
and created Adult
Apprenticeship
schemes to address
critical Argyll and
Bute Council skills
shortages. 
Page 233

Page 234

10 
PEOPLE: Education, skills and training opportunities for all ages are aligned to higher paid employment and/or self-employment opportunities, with embedded Fair
Work First principles.
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025 Resources Outcome by 2034
1. DYW, Education and
Economic Growth to
focus on the
increasing the range
of Foundation
Apprenticeships for
senior pupils across
Argyll and Bute
schools aligned with
industry demand. 
1. SDS to assist in increasing the
range of Foundation
Apprenticeships with
sustainable job opportunities. 
2. Check all activity with partners
on the Argyll and Bute
Employability Partnership
(ABEP). 
3. Scottish Government and the
Scottish Funding Council to
reduce the necessary class size
due to rurality for Foundation
Apprenticeship delivery. 
1. Council to increase the range
of Foundation
Apprenticeship
programme(s) available by
10% by 31st March 2028 to
alleviate some skills
shortages. 
2. Council to increase the
uptake of senior phase
pupils undertaking
Foundation Apprenticeship
by 15% by 31st March 2028.
1. Ongoing activity.  1. Council to
invest to save to
alleviate the
skills gap with
appropriate /
improved
access to the
Apprenticeship
Levy funding.
A greater range of
Foundation
Apprenticeship
schemes available
across all Argyll and
Bute schools to
address training and
employment within
key existing and
emerging sectors. 
1. Economic Growth to
liaise with SDS and
HIE to focus on the
delivery of Graduate
Apprenticeships for a
variety of occupations
across Argyll and Bute
aligned with industry
demand. 
1. SDS and HIE to work with
Economic Growth to encourage
industry recruitment of
Graduate Apprenticeships
aligned to funding
opportunities. 
2. Check all activity with partners
on the Argyll and Bute
Employability Partnership
(ABEP). 
3. HIE to conclude the delivery of
the Graduate Placement
programme funded by the UK
Shared Prosperity Fund.
1. 10% increase in the uptake
of Graduate
Apprenticeships supported
by Argyll and Bute
businesses across a variety
of occupations by 31st
March 2028. 
2. 2 out of 13 Graduate
Apprentices employed by
12 enterprises under the
HIE Graduate Placement
Programme funded by the
UK Shared Prosperity Fund
to be concluded by the end
of March 2026.
1. Ongoing activity. 
2. 11 Graduate
Apprentice
Placements concluded
through the HIE
Graduate Placement
Programme by end of
2024/25.
1. Council to
invest to save to
alleviate the
skills gap with
appropriate /
improved
access to the
Apprenticeship
Levy funding. 
2. UK Shared
Prosperity
Transition Fund
2025/26.
Sustain and grow
the number of
Graduate
Apprenticeship
schemes available
across Argyll and
Bute within existing
and emerging
sectors.
Page 234

Page 235

11 
PEOPLE: Education, skills and training opportunities for all ages are aligned to higher paid employment and/or self-employment opportunities, with embedded Fair
Work First principles.
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025 Resources Outcome by 2034
1. Focus on improving
the skills of existing
staff and the
recruitment of new
council officers
equipped with
transferable skills
that can move across
teams to support
funded
projects/themes
and/or council
priorities. 
2. Economic Growth
support to
businesses through
Business Gateway
and Employability
teams using UK
Shared Prosperity
Fund monies.
1. HIE and SE to share approaches
to business interventions to
complement local authority
delivery. 
1. 5% increase in the
recruitment of staff with
transferable skills. 
2. Achieve outcomes associated
with UK Shared Prosperity
Fund interventions by end of
March 2026. 
(For all businesses supported,
increase in turnover by 30%
and increase in job creation
by 26% - see Overarching
Economic Key Outcomes
table below). 
1. Ongoing activity. 
2. The Council’s
Employability Team
supported:
• 68 unemployed’
economically
inactive residents
into work
placements with
48 employers,
where 62% have
secured
employment post
work placement.
• 60 unemployed’
economically
inactive and 26
low-income
residents into
training where
42% are in
employment post
training. 
Invest to save. 
UK Shared
Prosperity
Transition Fund
2025/26.
Skills development
mainstreamed for
both existing and
new council staff
and local business
staff to better
capitalise on
changing economic
opportunities. 
Page 235

Page 236

12 
PEOPLE: Education, skills and training opportunities for all ages are aligned to higher paid employment and/or self-employment opportunities, with embedded Fair
Work First principles.
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. On approval of the
Rural Skills
Accelerator
Programme (RSAP)
Outline Business
Case, ensure 3 of the
4 Full Business Cases
are concluded
aligned to the Rural
Growth Deal (RGD)
projected delivery
timeframe for RGD
projects. 
2. Creation, co-delivery
and ongoing KPI
monitoring of the
STEM Hub South
(Dunoon), including
mobile and outreach
activity. led by the
Council’s Economic
Growth and
Education services. 
3. Assist the delivery of
the STEM Hub North
at SAMS through in-
kind staff support
from Economic
Growth and
Education services.
1. SAMS to manage the delivery
of the STEM Hub North,
including mobile and outreach
activity. 
2. HIE to manage and deliver the
Business Leadership Skills
programme, part of the RSAP. 
3. UHI Argyll to manage and
deliver the enhancement of
the college accommodation in
Lochgilphead. 
1. a) 3 of the 4 Full Business
Cases for the RSAP approved
by both governments by the
end of March 2027. 
b) HIE to commence and start
the delivery of the Business
Leadership Skills Programme
from April 2026. 
2. Co-delivery of the STEM Hub
South by Economic Growth
and Education by the of
March 2027. 
3. Delivery of the STEM Hub
North by SAMS through
liaison with Economic
Growth, Argyll and Bute
Council by the end of March
2028.
1. 3 of the 4 Outline
Business Cases for the
RSAP have been
approved. 
2. Staged approach to the
creation of the STEM
Hub South continues. 
3. Approach for the STEM
Hub South shared with
the STEM Hub North to
enable shared learning.
Building secured for
future STEM hub at
SAMS.
RSAP – RGD
funding (£7m),
plus Clyde
Mission &
Crown Estate
Scotland
(digital
connectivity)
and Council
funding
(£762,500).
STEM education and
skills has enabled a
digitally driven
pathway to learning
opportunities.
Page 236

Page 237

13 
PEOPLE: Reducing Barriers to work through Employability
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025 Resources Outcome by 2034
1. Economic Growth to prepare the
Argyll and Bute Employability
Partnership (ABEP) Annual
Investment Plan for 2025/26 based
on successful bids aligned on a
scoring matrix. 
2. Economic Growth to present a paper
on a truncated ABEP Delivery Plan,
prepared by ABEP members, for
endorsement by the Community
Planning Partnership Management
Committee. 
3. Focus on all-age employability
support and tackling child poverty
with a 'no wrong path' approach to
prepare the required Annual
Investment Plan for No One Left
Behind (NOLB) Scottish Government
funding, complete with details of
delivery interventions by the council
and partners. 
4. Joint messaging about the benefits
of investment in early prevention of
poor health and how improving
people’s health and wellbeing
supports the local workforce and
reduces health care costs over the
medium and longer terms.  
1. Partners, in particular
members of the ABEP,
to deliver all age and
child poverty
interventions, funded
by the NOLB for
2025/26. 
2. Partners, in particular
members of the Argyll
and Bute
Employability
Partnership, to deliver
all age and child
poverty interventions,
funded by the NOLB
for 2025/26. 
3. To utilise levers for
direct investment to
support wellbeing
outcomes. 
1. ABEP truncated Delivery Plan
and full Annual Investment
Plan to be endorsed by the
CPP Management Committee
by the end of September
2025. 
2. Council and all delivery
partners to achieve in-year
spend and outcomes detailed
in the Annual Investment Plan
by the end of March 2026.. 
3. Measurement of wellbeing
outcomes, such as individuals
supported to move into
sustainable employment
through case studies from
ABEP members. 
4. Developing a pilot approach
to place making that
incorporates public health
outcomes. This is a
partnership initiative
supported by Hub North with
NHS Highland as a key
partner. 
1. Annual Investment
Plan 2025/26
prepared by the
Employability Team,
Economic Growth
with input from
ABEP. 
2. Workshop delivered
by ABEP on a
truncated ABEP
Delivery Plan on 20th
May 2025. 
3. With Scottish
Government NOLB
funding the
Employability Team,
Economic Growth
and third sector
delivery partners
supported 472
participants in
2024/25. 
4. Hub North proposal
now being
considered by ELT
and NHS Highland
prior to member
approval. 
Scottish
Government
NOLB funding.
Deliver the
employability
agenda, with
embedded Fair
Work First
principles to assist
people with
multiple barriers
into sustainable
employment. 
Page 237

Page 238

14 
PLACE: Investing in our towns, rural and remote rural communities,
including our islands and peninsulas, to attract new people and
businesses, pursuing external funding opportunities, investing in critical
economic infrastructure such as housing, land for business development,
reuse of land and buildings for community benefit, digital connectivity
and transport (principally roads, ports and ferries). 
The SMART actions noted in the PLACE tables below:
• Secure future investment from cross sector partners and external
funding streams into our towns, rural and island communities.
• Recognise the strengths of community resilience across Argyll and
Bute.
• Work with strategic partners to support communities in the
development and facilitation of transformational regeneration
projects including community ownership of assets and wealth
creation.
• Increase focus on areas of opportunity through better place
making. 
Page 238

Page 239

15 
PLACE: Better Place Making
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by
2034
1. Continued development and
delivery of built heritage
investment schemes. 
2. Continued delivery of the
vibrant and living spaces
projects funded through the
UK Shared Prosperity
Transition Fund, 2025/26 
3. Continued delivery of the
Community Regeneration
Partnership funding for
project activity throughout
2025/26. 
4. Continue delivery of Rural
Growth Deal programme and
draw down of funding. 
Complete FBCs necessary to
enable endorsement of
projects by central
governments. 
5. Further promotion of the
#ABplace2b campaign. 
1. Establish a
collaborative
partnership
between central
governments,
Argyll and Bute
Council, CPP
partners,
communities and
funders. 
1. a) Complete Lochgilphead CARS
programme by end June 2026;
Complete Helensburgh CARS
programme by end June 2026;
Secure £1.8m funding for a
Tarbert Heritage Regeneration
Scheme by end March 2026.
b) Delivery of new artworks in
Helensburgh Outdoor Museum. 
2. Delivery of the 8 Vibrant and
Living Spaces projects with a
total investment of £292,290.24
by the end of March 2026. 
3. Commence all Community
Regeneration Partnership
projects by the end of March
2026. 
4. Rural Growth Deal (RGD) signed
10th March 2025 with ongoing
compliance, such as the drawn
down of funding, for the
remaining 9 financial years of the
RGD. 
5. Continue Love Local promotion
and increase #ABplace2b
followers by 10% from its launch
to the end of March 2026. 
1. Ongoing activity that
is on track. 
2. Ongoing activity.
Funding fully
committed. 
3. Ongoing activity. On
track. 
4. Signing of the Rural
Growth Deal in
Rothesay by Argyll
and Bute Council,
the UK Government
and the Scottish
Government took
place on 10th March
2025. 
5. Ongoing activity. On
track. 
CARS multi-annual
funding. 
UK Shared Prosperity
Transition Fund for
Vibrant and Living
Spaces projects. 
Community
Regeneration
Partnership
Programme, £20m. 
Rural Growth Deal circa
£70m investment over
10 years. 
Scottish Government
Place based funding. 
Historic Environment
Scotland, National
Lottery Heritage Fund,
Crown Estate and Rural
Tourism Infrastructure
Fund strategic
investments. 
HIE capital funding. 
Creation of a
distinct sense
of place
through the
delivery of an
outstanding
built
environment
making our
towns, rural
and island
communities
across Argyll
and Bute
attractive
places to live,
work, visit and
invest in.
Page 239

Page 240

16 
PLACE: Better Place Making (continued)
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
6. Secure future investment from
cross sector partners and
external funding streams
including both the Scottish and
UK Governments. 
7. Dissemination and delivery of
the Community Led Local
Development (CLLD) Fund for
2025/26 through the Argyll and
the Islands CLLD Local Action
Group (LAG) supported by the
council as the Accountable
Body. 
2. New partners to
become
members of a
renewed CLLD
Argyll and the
Islands Local
Action Group for
2025/26. 
6. Continue to lobby and influence
the Scottish and UK Governments
and key partners for cross-
sectoral place-based funding. 
7. All CLLD Fund spend and
outcomes for 2025/26 to be
realised by the end of March
2026. 
6. Ongoing activity.
Community
Regeneration
Partnership funding
to be announced in
November 2025. 
7. £599k of CLLD Fund
support to 20
projects during
2024/25 against a
total project cost of
£793k, leveraging in
£194k of match
funding. 
For every £1 invested
in CLLD Projects in
2024/25, the social
value return was
£5.11. 
Private sector
investment. 
CLLD Fund from
the Scottish
Government for
2025/26.
Creation of a
distinct sense of
place through the
delivery of an
outstanding built
environment
making our towns,
rural and island
communities across
Argyll and Bute
attractive places to
live, work, visit and
invest in.  Page 240

Page 241

17 
PLACE: Increasing Community Resilience and Wellbeing through Identifying and Delivering Income Streams
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Adopt a Community Wealth
Building (CWB) approach / CWB
Action Plan (as per proposed CWB
(Scotland) Bill to ensure the
economic success of Argyll and
Bute is based on a wellbeing
economy. 
2. Council to continue to work and
engage with partners and
communities to create the
opportunity for the use of
community assets, empty spaces
and co-production through the
application of Place Based
Wellbeing Principles such as
accessibility and inclusion. 
3. Partnership working with the
Community Planning Partnership
and Health and Social Care
Partnership prevention agenda. 
4. The Empty Business Property Grant
Scheme will seek to support the
owners and prospective tenants of
empty business properties to
return these to productive use
with a view to enhancing the look,
feel and vitality of our places,
growing businesses and job
opportunities, and attracting
inward investment.
1. HIE, SE, third sector
partners (including
the Improvement
Service) and external
funders engage with
the council and other
stakeholders to
maximise the
wellbeing economy
agenda for Argyll and
Bute. 
2. Communities to
develop shared
management of civic
spaces and natural
assets. 
3. Input from
community councils
and development
trusts to support
community
developments and
co-production.   
4. Publish and
implement actions of
the Community
Wealth Strategy. 
1. Establish a multi partner
and cross council
departmental approach to
CWB to prepare a CWB
Action Plan. 
2. Increase the number of
community owned
buildings and land assets
by 5% including a renewed
focus on job creation, by
the end of March 2028. 
3. Embed appropriate Place
and Wellbeing Principles,
including the prevention
agenda, into project
delivery. 
4. Continue to lobby Scottish
Government to maintain
budgets for community led
projects e.g. Community
Led Local Development
(CLLD) Fund, Regeneration
Capital Grant Fund (RCGF),
Scottish Land Fund, and
Rural Tourism
Infrastructure Fund (RTIF)
from 2025/26 onwards
1. CWB CPP Working
Group formed with
members from the
Council’s Economic
Growth and
Community
Development
Teams, TSI Argyll,
NHS Highland and
HIE. 
2. Request for CWB
staff resource in
Argyll and Bute
Council officer
response to the
CWB (Scotland Bill) –
submitted 23rd May
2025. 
3. Examining
prevention activities
as part of the
budget process. 
4. RCGF, Place based
funding, RTIF, Islands
Infrastructure Fund,
CLLD fund all
reinstated. 
UK Government
Asset Transfer
fund/UKSPF. 
Scottish
Government
Community
Empowerment –
Asset Transfer
Fund. 
Empty Business
Property Grants
funded from NDR
income.
Greater
community
resilience and
wellbeing has
created a better
sense of belonging
and prosperity
through the access
to external
investment that
has driven
transformational
opportunities,
community
ownership and
innovation. 
Page 241

Page 242

18 
PLACE: Improving Connectivity
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions 
2024-2025
Resources Outcome by
2034
1. Further to the Strategic
Transport Projects Review
2 (STRP2) response,
continue to lobby the
Scottish Government for
a permanent and fully
funded solution for the
Rest and Be Thankful. 
2. Prepare and deliver an
Argyll and Bute Local
Transport Strategy that
identifies the key local
transport priorities. 
3. Lobby and influence the
UKG, SG, BT and private
contractors to deliver the
R100 Programme moving
into Project Gigabit 2030. 
4. To map phase 1 mobile
phone coverage at an
individual premises level. 
5. Prepare an Argyll and
Bute Active Travel
Strategy to achieve a
healthier and more
productive workforce. 
1. Continue to lobby the
Scottish Government
for a permanent and
fully funded solution
for the Rest and Be
Thankful. 
2. Continue to lobby for
increased active
travel, public
transport, airport, air
service, ferry and
ports infrastructure
investments. 
3. Industry and public
sector collaboration
to secure basic
critical infrastructure.
Key partners:
• Scottish
Government
• UK Government
• Transport
Scotland
• HITRANS
• BT Openreach
• Virgin
• Digital Scotland
• SPT.
1. Full commitment by
Scottish Government to
deliver a fully funded
solution for the Rest and Be
Thankful. 
2. Approve and publish an
Argyll and Bute Local
Transport Strategy that
identifies the key local
transport priorities. 
3. R100 achieved with 85% of
premises with potential
access to modern ultrafast
broadband speeds; 85%
coverage of 4G across Argyll
and Bute. 
4. Conclude the mapping of
mobile phone coverage by
December 2025. 
5. Approve and publish an
Argyll and Bute Active Travel
Strategy. 
1. Ongoing activity. Ground
investigation works for
preferred solution ongoing;
round table discussions on
impacts of works scheduled. 
2. Ongoing activity. Local
Transport Issues Paper
approved for public
consultation; Hi-Trans
Regional Transport Strategy
approved. 
3. Ongoing activity working with
BT Openreach. Provisional
allocation of £200m UK
Government funding for
Argyll and Bute area, subject
to UK Government
confirmation and rapid
delivery and positive support
by Argyll and Bute Council. 
4. Mobile phone coverage
mapping nearing completion
with data now released for
most of Argyll and Bute
Council area. 
5. Active Travel Strategy out to
public consultation.
Lobby, influence
and invest.
Working with
Industry and
public sector
partners to secure
basis critical
infrastructure. 
• Scottish
Government
• UK
Government –
previous
levelling up
agenda
monies and
new future
schemes
• Transport
Scotland
• HITRANS
• SPT
• BT Openreach
• Virgin
• Digital
Scotland
• CMal/CalMac
• Scotrail
• Bus
companies.
Existing routes
to market
(roads, rail,
ferries, ports
and air) and
local
employment
opportunities
are secured
through
increased
investment in
our critical
transport and
digital
infrastructure. 
Page 242

Page 243

19 
PLACE: Housing Emergency
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Reflect the endorsed
Housing Emergency
Action Plan (with a focus
on increasing the supply
of key worker housing).in
the annual update of the
local Housing Strategy. 
2. Complete mapping of
second homes and short-
term lets to inform the
delivery of Planning
Control Zones (PCZs). 
3. Deliver the 2 Strategic
Development
Frameworks for
Tobermory to Dalmally
Growth Corridor (TDGC)
and Helensburgh &
Lomond Growth Area
(HLGA). 
1. Ongoing
engagement and
delivery of specific
actions in the
Housing Emergency
Action Plan will
involve the
following partners:
• Scottish
Government.
• CPP partners,
including HIE.
• Housing
Associations.
• Private sector
builders.
• Highlands and
Islands
Economic
Partnership.
• Community
Housing Trusts. 
1. Publish Housing Emergency
Action Plan outcomes by the of
June 2025. 
2. 20 key worker houses by end of
March 2028. (10 completed by
May 2025). 
3. Approve PCZs informed by up-
to-date housing data by end of
March 2028. 
4. Approve the 2 Strategic
Development Frameworks for
TDGC and HLGA. To be
published as part of the
Proposed Local Development
Plan 3, potentially January
2028. 
5. Deliver the Community
Regeneration Partnership Fund
housing related projects.
1. Outcomes published.
Alignment of the Housing
Strategy and Housing
Emergency Action Plan has
been completed. Work
ongoing on identified
actions. Officer Housing
Delivery Group established
focused on releasing sites
for housing. 
2. Site works completed for
Rockfield Worker Housing
site for 12 units. 
3. Mapping of second homes
and short term lets
completed. This is being
used to inform potential
Planning Control Zones
location in Argyll and Bute
Council area. 
4. Consultants engaged for
both Strategic
Development Frameworks
about to commence public
consultation on options. 
5. Awaiting UK Government
announcement of
Community Regeneration
Programme projects.
1. Lobby Scottish
and UK
Governments
for additional
flexibility and
funding. 
2. Strategic
Housing Fund. 
3. £450k for
Strategic
Development
Frameworks of
TDGC and HLGA.
Consultants now
appointed for
both
frameworks). 
4. £5m of housing
funding from
the Community
Regeneration
Fund, UK
Government
(awaiting UK
Government
approval). 
Affordable homes
of all tenure have
been built or
brought back in to
use to meet the
needs of our
communities
including
attracting new
economically
active residents to
Argyll and Bute to
take up
employment
opportunities and
to help expand
established local
businesses and /
or to establish
new businesses.  
Page 243

Page 244

20 
PLANET: Delivering net zero and improving our biodiversity by
supporting the sustainable growth of clean energy production (i.e.
hydro, solar, wind and biomass), woodland, peat and marine habitat
restoration, encouraging green industries to develop in our area,
nature-based solutions and community ownership. 
The SMART Actions noted in the PLANET tables below:
• Achieve net zero through increased clean energy production,
forestry expansion, and marine habitat restoration.
• Embrace clean energy opportunities and work to provide better
local outcomes, including job retention and creation.
• Develop low-carbon infrastructure to enable alternatives to private
transport including active travel, better digital connectivity, and
sustainable housing.
• Foster nature-based solutions for increased climate change
resilience and biodiversity enhancement.
• Support emerging sustainable industries like seaweed farming,
marine research and green energy.
• Unlock the potential of the marine economy to create sustainable
economic growth opportunities across Argyll and Bute.
Page 244

Page 245

21 
PLANET: Delivering Net Zero by 2045 through Economic Actions 
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Prepare a Local Area
Energy Plan for Argyll and
Bute. 
2. Work with our Community
Planning Partners,
community groups, trusts
and bodies to delivery
environmental, carbon
neutral, projects. 
3. Develop low-carbon
infrastructure to enable
alternatives to private
transport including active
travel, better digital
connectivity*, and
sustainable housing**.
(*digital connectivity see
PLACE: Improving
Connectivity actions and
**sustainable housing see
PLACE: Housing
Emergency). 
1. Strong collaboration
required from all
Community Planning
Partner stakeholders and
the private sector –
community climate hubs. 
2. Argyll and the Isles Coast
and Countryside Trust
(ACT) leading on the
delivery of an expanded
North Atlantic Rain
Forest and expanded
restoration of peat bogs. 
3. Strategic partners to
lobby for funding, build
political and community
support to delivery Net
Zero. 
1. Deliver a Local Area Energy
Plan (LEAP) for Argyll and
Bute by December 2026. 
2. Ensure economic
opportunities through the
production of a Regional
Climate Change Strategy
and Action Plan by the end
of March 2028. 
3. a) Adoption of an Active
Travel Strategy by the end
of March 2028. 
b) Preparation of the full
business case by Hub North
for the West Coast UAV
Logistics and Training Hub at
Oban Airport by March
2027.
c) Continue the delivery of
the Home Energy Efficiency
Programme for Scotland
(HEEPS) and new build
(energy efficient) social
housing 
(*for target, 20 key worker
houses, see PLACE: Housing
Emergency).
1. Discussions ongoing
with Hub North on
securing funding for
LAEP. 
2. Work ongoing by
Commercial Services. 
3. a) Active Travel Strategy
out for public
consultation.
b) Oban Airport Business
Park moving to
development stage
following business case
approval and securing
additional TIF funding.
Awaiting Community
Regeneration
Programme funding
announcement. 
c) HEEPs ongoing work
secured a £2.2m grant
for this financial year.
ECO4 status secured. 
Funding via the
UK and Scottish
Governments
Net Zero
agenda. 
Renewables,
forest expansion
and energy
conservation. 
Private sector
community
benefits.
Argyll and Bute
established as a
leading low carbon
economy and
taking best
advantage of our
natural capital. 
Page 245

Page 246

22 
PLANET: Expanding Green / Clean Energy Production
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Lead efforts to achieve net
zero through clean energy
production. 
2. Consideration of green
energy production on Islay
to unlock economic
opportunity.  
3. To continue to lobby SSE
networks for grid
improvements to and from
Islay to take advantage of
new offshore wind
opportunities and assist in
the decarbonisation of the
Islay economy; and to
lobby SSE Networks and
Scottish Power Energy
Networks for better grid
connectivity for
communities experiencing
grid constraints. 
1. HIE and SE to support
carbon sequestration
activity and relevant
funding. 
2. Community groups to
maximise returns for clean
energy community benefits. 
3. Argyll and Bute Renewables
Alliance (ABRA) and other
relevant partners to support
the sustainable growth of
the renewables and clean
energy sectors across Argyll
and Bute. 
4. To sign off by 2027 the
Hebrides and Orkney Whole
System Uncertainty
mechanism (HOWSUM) to
act as a framework for a
modern fit for purpose
electricity distribution
network across our island
communities.
1. Increasing clean energy
production by 500 MWs. 
2. Completion of Rural Growth
Deal full business case for
‘Creating a low carbon
economy on Islay’ by March
2027. Continue to bid for
carbon neutral funding for
Islay. 
3. To continue to lobby
OFGEM and network
operators to create SMART
use of the grid and approve
grid improvements –
ongoing. 
4. Increase community benefit
returns by 10% by 2027.
1. Ongoing activity 13 on
shore wind farms
submitted 24/25 plus
several battery storage
schemes. 
2. Re-examining Islay
Business case following
feedback from
Governments. Carbon
Neutral funding bids
submitted annually. 
3. Argyll and Bute Council
has responded to
several Government
consultations on the
grid investment. 
4. Draft Economic and
Social Charter being
prepared for
committee. 
Community benefits
being monitored. SSEN
Argyll Local fund now
live.
UK and
Scottish
Government
funding. 
Private sector
investment.
Deliver clean
energy sectoral
opportunities and
infrastructure
across Argyll and
Bute. 
Page 246

Page 247

23 
PROSPERITY: Creating higher wage opportunities, seizing opportunities
in the net-zero economy, improving productivity and innovation through
increasing business efficiency including  the use of digital technology,
empowering communities through ownership and wealth creation,
sustaining public services, promoting the marine and green economies,
enabling the sustainable growth of key sectors such as food and drink
together with revitalising the tourism and hospitality sectors and
supporting the growth of the creative industries. 
The SMART Actions noted in the PROSPERITY tables below:
• Capitalise on net-zero opportunities for green jobs and improve
living standards.
• Focus on productivity improvements through digital technology.
• Empower the public, private and third sectors to provide services,
participate in shared management of civic spaces and generate
income.
• Revitalise our key sectors such as the tourism and hospitality
industry.
• Leverage natural and cultural assets to drive sustainable business
growth and overall economic growth. 
Page 247

Page 248

24 
PROSPERITY: Supporting Business Start-up and Growth
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Lobby and influence the UK
Government and the Scottish
Governments on future funding
decisions to continue business
support funding across local
government and partner agencies.
Council Officer Funding Group
established to collate information on
existing and future funding that will
facilitate lobbying. 
2. Influence and facilitate business
creation, retention and growth
through tailored support by teams
and funding within Economic Growth,
such as Business Gateway and the
Rural Tourism Infrastructure Fund
(RTIF) respectively. and other council
departments with sectoral remits. 
3. Encourage organisations to consider
alternative business models, with a
particular focus on succession
planning. Business Gateway signpost
relevant information and resources. 
4. Focus on business productivity
improvements through digital support
and reviews through current Expert
Help Business Gateway interventions,
funded by the UKSPF Transition
funding for 2025/26.
1. Collaborative
working by UK and
Scottish
Governments
working with local
authorities through
Scottish Local
Authorities
Economic
Development
(SLAED) group. 
2. Complementary
business start-up
and growth support
from HIE and SE. 
3. Complementary
support on the
adoption of
alternative business
models to assist
with succession
planning and
business retention
from HIE and SE. 
4. Complementary
support on business
productivity
improvements from
HIE and SE.
1. Ongoing lobbying activity
on future business
support funding with
external partners such as
SLAED. 
2. Commit and spend all
business support grants
funded by the UKSPF by
the end of March 2026,
which includes the UKSPF
transition funding for
2025/26. 
3. HIE to provide 2 cases
studies by the end of
March 2027 to
demonstrate the adoption
by local businesses of
alternative business
models. 
4. Publish all outcomes from
the digital support and
reviews and Expert Help
by end of June 2026.
1. Between June 2023
and March 2025
Business Gateway,
Economic Growth,
delivered a
programme of
additional support
worth £516,521 fully
funded through the
UKSPF. 165 unique
businesses were
supported, via:
• 87 small business
development
grants
• 75 start-up grants
• 16 training, trade
fair, accreditation
or digital grants
• 9 expert help
• 6 participants on
intensive business
support
programme. 
2. Impact of UKSPF – see
infographic in
Economic Growth
Activities and
Outcomes paper, EDI
Committee, 11th
September 2025..
UK
Government
funding (RGD
& Community
Regeneration
Partnership
Funding) and
Scottish
Government
funding (RGD,
Business
Gateway and
HIE).
Argyll and Bute
established as the
natural choice for
ambitious,
emerging,
productive and
innovative new
SMEs and
industries to grow
and flourish.
Page 248

Page 249

25 
PROSPERITY: Supporting Key Sectors and Productivity
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Lobby and influence the UK
Government (e.g. UKSPF successor
programme) and the Scottish
Government (e.g. CLLD Fund) future
funding decisions to support our key
sectors such as tourism, food and drink,
creative industries, renewables and
marine with multi-annual funding
models. 
2. Promote our creative industries and
their expansion across Argyll and Bute.
Approve in principle, the hosting of the
Royal National Mod Oban 2028. 
3. Progress the development of the
Kilmory Business Park Phase 2, Colgrain
Business Park and Oban Airport
Business Park. 
1. Collaborative
working by UK and
Scottish
Governments with
local authorities. 
2. CHARTS to attract
external funding
and support the
sustainable growth
of the sector
including Gaelic
culture as a means
to boost business
growth. 
3. Relevant private
sector companies;
HUB North; Scottish
Future Trust (SFT),
HIE and SE to
support the
Council’s
Procurement Team
to publicise the
supply chain
opportunities from
Kilmory Phase 2 and
Oban Airport
Business Park.
1. Secured sectoral funding
for 2025/26 and beyond
through external funding
sources. 
2. Deliver the Kilmory
Business Park, Phase 2 by
early of 2025/26; finalise
the Colgrain Business Park
Full Business Case by the
end of March 2026;
delivery Oban Airport
Business Park by spring
2027. 
1. Council Officer
Funding Group
established to collate
information on
existing and future
funding to facilitate
lobbying. 
2. CHARTS awarded
development
funding from
Creative Scotland
during 2024/25
which may lead to
them achieving
Regularly Funded
Organisation status. 
3. Kilmory Business
Park 2 under
construction. Site
investigation works
ongoing for Colgrain
Business Park. Oban
Business Park
approaching
development phase. 
UK
Government
funding (RGD
&
replacement
programme
for levelling
up) and
Scottish
Government
funding (RGD,
CLLD &
RCGF); Crown
Estate
Scotland; Tax
Incremental
Finance (TIF)
model (Argyll
and Bute
Council),
Historic
Environment
Scotland
(HES) and
Heritage
Lottery Fund
(HLF);
Creative
Scotland; HLF. 
Argyll and Bute
established as the
natural choice for
ambitious,
emerging,
productive and
innovative new
SMEs and
industries to grow
and flourish across
the key sectors
such as tourism,
food and drink,
creative industries,
renewables and
marine. 
Page 249

Page 250

26 
PROSPERITY: Supporting Key Sectors and Productivity (continued)
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
4. Create a world class visitor destination
through the delivery of Rural Growth
Deal projects such as the Rothesay
Pavilion and Kintyre Seasports. 
5. Facilitate private sector investment in
tourism accommodation and facilities. 
6. Promote the strengths and
opportunities of Argyll’s two current
whisky regions, Islay and Campbeltown.
4. Argyll and the Isles
Strategic Tourism
Partnership to
work collectively to
support the
sustainability and
growth of the
sector. 
5. HIE to engage with
a range of inward
investors with a
focus on the
distilling sector.
3. Complete the restoration
of the Rothesay Pavilion
with the creation of 14
FTEs and deliver the
Kintyre Seasports project,
both by end of March
2027. 
4. Expected to facilitate the
leverage of £0.5bn of
private sector capital
investment in our key
sectors by March 2028. 
5. To facilitate the
sustainable growth of
Argyll and Bute’s current 2
distinct whisky regions
(Islay and Campbeltown)
that maximises local
supply chain benefits by
the end of March 2028. 
4. New Strategic
Tourism Partnership
Strategy published
August 2025. 
5. Rothesay Pavilion on
track for completion.
Kintyre Full Business
Case being
developed. £200k
secured for planning
start. 
6. Ongoing activity with
several new
distilleries on site
and bonded
warehouses under
construction. 
UK
Government
funding (RGD
&
replacement
programme
for levelling
up) and
Scottish
Government
funding (RGD,
CLLD &
RCGF); Crown
Estate
Scotland; Tax
Incremental
Finance (TIF)
model (Argyll
and Bute
Council),
Historic
Environment
Scotland
(HES) and
Heritage
Lottery Fund
(HLF);
Creative
Scotland; HLF. 
Argyll and Bute
established as the
natural choice for
ambitious,
emerging,
productive and
innovative new
SMEs and
industries to grow
and flourish across
the key sectors
such as tourism,
food and drink,
creative industries,
renewables and
marine. 
Page 250

Page 251

27 
PROSPERITY: Empowering Communities (public, private and third sectors) to Increase their Resilience, Provide Services and Generate Income
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by 2034
1. Through collaborative and
partnership working ensure
the CWB approach is
embedded in the delivery of
all council projects. 
2. Engage and align with the
Highlands and Islands
Regional Economic
Partnership (HIREP)
Community Benefit sub-
group activity and proposed
outcomes. 
3. Further to a detailed 12-
week consultation period in
the final quarter of 2024/25,
collate a Visitor Levy
Consultation Report for
elected member
consideration. 
4. Focus on addressing areas of
deprivation, particularly in
Dunoon, Rothesay and
Campbeltown, by fostering
community partnerships. 
1. The CPP, and other
key cross sector
stakeholders, to
support the delivery
of the CWB
approach, with a
focus on the recent
CPP research on
CWB. 
2. HIE to support the
delivery of
community-led
projects to support
resilience and create
local wealth
generating
opportunities. 
3. Key partners across
the Highlands and
Islands are members
of the HIREP
Community Benefit
sub-group with a
focus on benefits
pertinent to their
own geographical
areas as well as the
Highlands and
Islands.
1. Collective CWB approach
embedded in all council
project/ programme delivery. 
2. Assist in the delivery of the
community benefit proposals
developed by HIREP, with a
focus on Argyll and Bute
communities. 
3. Consultation completed. To
reach a decision on whether
to introduce an Argyll and
Bute Visitor Levy by the early
autumn 2025. 
4. Identify clear economic
functions for Dunoon,
Rothesay and Campbeltown
by March 2027. Working with
BIDs and CDTS in particular,
with Dunoon and Rothesay to
deliver improved buildings,
remove dereliction, and
public realm enhancements
1. Tobermory Business Site
phase 2, Port Ellen
Community Hub, Colonsay
and Tiree Business units
completed. 
2. Ongoing activity active
member of HIREP. 
3. Supporting potential
Dunoon Data Centre bid for
AI Growth status across
Argyll and Bute. 
4. Ongoing activity. Major
capital works being
progressed for Rothesay
and Dunoon. Focus on
assisting SMEs to establish
businesses in both areas. 
.
UK
Government
and Scottish
Government
funding. 
Private sector
community
benefit
contributions. 
Community
Benefit
funding
disseminated
through
working with
and HIREP. 
Communities are
equipped to
improve their
resilience through
achieving local
economic
outcomes and
social benefits that
retain economic
prosperity locally. 
Page 251

Page 252

28 
PROSPERITY Maximise the Potential of the Marine Economy
Council Actions Partner Actions Short-term success measures
(up to 3 years)
Progress on Actions
2024-2025
Resources Outcome by
2034
1. Unlock the potential sites for
development with direct
water access. 
2. Support SMEs (through the
Business Gateway service) to
access supply chain
opportunities aligned to the
marine economy. 
3. Provide support for new
products including
renewables linked to the
RGD funded Marine Industry
Training Centre (MITC) e.g.
hydrogen, biofuels,
bioplastics and to the
Machrihanish Innovation
Centre (MIC). 
4. Ensure that the Rural Growth
Deal (RGD) Marine
Aquaculture Programme
(MAP) delivers benefits for
the whole marine industry
and supports the expansion
of new industries such as
seaweed farming. 
5. Unlock the potential of the
North Lorn Port. 
1. HIE, SE, the Loch Lomond & the
Trossachs National Park Authority
and Crown Estate Scotland are key
partners to unlock potential sites. 
2. HIE and SE to support SMEs to
access supply chain opportunities.  
3. HIE, in partnership with SAMS
supports marine sector growth
through:
a) HIE led development of Phase 2
of the European Marine Science
Park, “Camas House”.
b) HIE led development of the
business cluster through
development and delivery of a
strategy marketing plan. 
4. HIE, in partnership with the
council, SAMS, UHI, UHI Argyll and
University of Stirling, to support
marine economic opportunities
realised through the MAP,
specifically:
a) RGD – MAP – SAMS led Centre for
Seaweed and Shellfish Innovation and
Development (CSSIDe).
b) RGD – MAP – Argyll UHI led Marine
Industry Training Centre (MITC).
c) RGD – MAP – Uni of Stirling-
Machrihanish Innovation Centre
(MIC).
1. Site options appraisal and
feasibility work completed by
end of March 2027. 
2. Supply chain opportunities
realised and promoted
through preparation of up to
5 case studies. 
3. a) Completion of Camas
House, European Marine
Science Park (EMSP) Phase 2
during 2025/26.
b) Growth in the number of
marine organisations at the
EMSP by 5%.
c) CSSIDe business case
completed; CCSIDe design
development undertaken by
the end of March 2027. 
4. a) MITC full business case
completed; MITC design
development undertaken by
the end of March 2027.
b) MIC full business case
completed: MIC design
development undertaken by
the end of March 2027. 
5. Undertake a feasibility study
into North Lorn Port.
1. Camas House
nearing completion
at the EMSP.
Awaiting CRP fund
decision on fitting
out of second floor. 
2. MITC full business
being reappraised
with partners. 
UK and Scottish
Government
funding.
Council and HIE
staff resource. 
3. a) HIE GIA
(General
Investment
Accounts) with
external
funding sought
for fit-out.
b) HIE GIA and
council funded
Business
Gateway.
c) SAMS, RGD
and match
funding. 
4. a) UHI Argyll
and RGD.
b) University of
Stirling, RGD
and match
funding. 
Council or
future external
funding
opportunities. 
Delivery of
marine
economy
opportunities
across Argyll
and Bute.
Page 252

Page 253

29 
Overarching Economic Key Outcomes for Argyll and Bute by the end of March 2028   
Data sources: Office for National Statistics, Scottish Annual Business Survey (data often reported two years in arrears) and Skills Development Scotland Regional Skills Assessments. 
These overarching economic outcomes can only be achieved through a strong focus on collaboration and a joined-up
approach, working closely with the Community Planning Partnership, complete with the revised Local Outcome
Improvement Plan (LOIP) and proposed future Community Wealth Building Action Plan (once CWB (Scotland) Bill
progresses through the Scottish Parliament during 2025 to become an Act), partner agencies and stakeholders across
Argyll and Bute and at both a regional and national level. 
1. Increase the rate of economic activity for the 16-64 cohort to 76% (i.e. an increase of 360 individuals).
2. Grow the Argyll and Bute workforce by 600 individuals.
3. Secure a 5% uplift in place-based investment.
4. Increase in turnover by 30% and increase in job creation by 26% for all supported businesses.
5. Deliver 20 key worker homes.
6. Retention of 60 FTEs and the creation of 30 FTEs.
Page 253

Page 254

30 
GLOSSARY of ACRONYMS
COUNCIL DEPARTMENTS AND PARTNER ORGANISATION DEVELOPMENT PROJECTS / PROGRAMMES EXTERNAL FUNDS 
DEG: Development & Economic Growth, Argyll and Bute Council RGD: Rural Growth Deal UKSPF: UK Shared Prosperity Fund
DYW: Developing the Young Workforce, Argyll and Bute Council RSAP: Rural Skills Accelerator Programme NOLB: No One Left Behind
HR: Human Resources, Argyll and Bute Council STEM: Science, Technology, Engineering and Maths RCGF: Regeneration Capital Grant Fund
SG: Scottish Government CWB: Community Wealth Building  RTIF: Rural Tourism Infrastructure Fund
UKG: UK Government UAV: Unmanned aerial vehicle CLLD: Community Led Local Development Fund
HIREP: Highlands and Islands Regional Economic Partnership PCZ: Planning Control Zones LACER: Local Government COVID Economic Recovery
ABEP: Argyll and Bute Employability Partnership TDGC: Tobermory to Dalmally Growth Corridor HLF: Heritage Lottery Fund
OFGEM: Office of Gas and Electricity Markets HLGA: Helensburgh & Lomond Growth Area  HIE GIA: Highlands and Islands Enterprise General
Investment Accounts
HIE: Highlands and Islands Enterprise HEEPS: Home Energy Efficiency Programme for
Scotland 
SE: Scottish Enterprise CSSIDe: Centre for Seaweed & Shellfish Innovation &
Development (CSSIDe). 
SDS: Skills Development Scotland MAP: Marine Aquaculture Programme 
UHI:  University of the Highlands and Islands MITC: Marine Industry Training Centre 
UHI Argyll: University of the Highlands and Islands in Argyll MIC: Machrihanish Innovations Centre 
SAMS: Scottish Association for Marine Science EMSP: European Marine Science Park 
HITRANS: Highlands and Islands Transport Partnership  
SPT: Strathclyde Partnership for Transport  
BT: British Telecommunications  
ACT: Argyll and the Isles Coast and Countryside Trust  
ABRA: Argyll and Bute Renewables Alliance  
HES: Historic Environment Scotland  
BIDS: Business Improvement Districts  
CDTs: Community Development Trusts   
Page 254

Page 255

1 
ARGYLL AND BUTE COUNCIL                ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH             11 SEPTEMBER 2025 
ECONOMIC GROWTH TEAM ACTIVITIES AND OUTCOMES FOR 2024/25 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this paper is to provide members of the Environment, Development
and Infrastructure Committee with an update on the delivery of services and
associated outcomes by the overarching Economic Growth Team, within the
Development and Economic Growth Service, during 2024/25, which aligns with the
council’s priority of Housing, Economic Growth and Population. 
1.2 The overarching Economic Growth Team comprises of an Economic Growth Manager
who has oversight over four teams as follows. 
• Opportunities and Growth
• UK and External Policy
• Business Gateway
• Employability 
1.3 The content of this paper has been summarised into an infographic, see Appendix
1. 
1.4 It is recommended that Members of the Environment, Development and Infrastructure
Committee consider and agree the update on the delivery of services in 2024/25 by
the Economic Growth Team. 
Page 255 Agenda Item 14

Page 256

2 
ARGYLL AND BUTE COUNCIL                ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH             11 SEPTEMBER 2025 
ECONOMIC GROWTH TEAM ACTIVITIES AND OUTCOMES FOR 2024/25 
2.0 INTRODUCTION 
2.1 The purpose of this paper is to provide members of the Environment, Development
and Infrastructure Committee with an update on the delivery of services and
associated outcomes by the overarching Economic Growth Team, within the
Development and Economic Growth Service, during 2024/25. 
2.2 Collaboration and partnership working intra Economic Growth, with other council
teams/services and with external partners are critical to the effective and efficient
delivery of the interventions by the Economic Growth teams. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and Infrastructure
Committee consider and agree the update on the delivery of services in 2024/25 by
the Economic Growth Team: 
4.0 DETAIL 
4.1 The work of the Economic Growth teams predominantly supports and adds value to
the council’s priorities of ‘Housing, Economic Growth and Population’ and
‘Communities’, in particular:
• Shared prosperity and sustainable business growth in Argyll and Bute, 
• People are Argyll and Bute’s most important asset in driving forward
opportunities for growth and vibrant local economies.
• Empowered and resilient communities. 
4.2 The thematic focus and priorities of the Economic Growth Manager and the four
teams is outlined in Figure 1 below. The diagram includes the number of staff per
team, details on the number of full-time equivalent posts that are funded from
external sources and key service interventions and activities delivered in a
complementary and collaborative manner e.g. businesses being informed of
employability funding to assist with recruiting specific targeted individuals/groups. 
Page 256

Page 257

3 
Figure 1   
Page 257

Page 258

4 
KEY ACTIVITIES AND OUTCOMES 
4.3 The key activities and outcomes by the teams within Economic Growth are outlined
in the appended infographic (see Appendix 1) complete with geographical spread
of activity (as appropriate) testimonials and case studies from project and
programme beneficiaries. Some notable outcomes and impacts of the interventions
delivered directly and indirectly (e.g. management of funding schemes) by the
teams within Economic Growth are outlined as follows: 
Opportunities and Growth:
• £1.9 million of direct economic impact on the local economy from the Clipper
Round the World Yacht Race 2024 which contributed to the recognition of
Oban towards the Town of the Year Award 2024.
• Although delivery suspended during 2024/25, the Rural Tourism
Infrastructure Fund is now up and running again with the three projects,
totaling £1.25 million, now awarded funding (Round 4/5). 
UK and External Policy:
• From the UK Shared Prosperity Fund Investment Plan spend, 2022-25, of
£2.56 million the outcomes derived are:
➢ 17 jobs created
➢ 256 volunteering opportunities supported
➢ 254 people participated in Multiply (numeracy) funded courses
➢ 103 people in employment including self-employment
➢ 106 enterprises received
➢ 11 assets or facilities created or improved.
• £599k of Community Led Local Development (CLLD) funding delivered to
support 20 projects against total project costs of £793k leveraging in £194k of
match funding; with a social return on investment of £5.11 for every £1
invested in CLLD projects in 2024/25. 
Argyll and Bute Business Gateway:
• 152 new start-up businesses supported with a combined projected turnover
of £6.06 million in year 1 and creating 173 jobs.
• customer satisfaction of Argyll and Bute Business Gateway 94% compared to
a national average of 81%, with 92% of recipients reported their business will
benefit and 97% of recipients reported they would recommend the Business
Gateway service. 
Employability:
• 48 employers in Argyll and Bute supported to host work placements with 68
unemployed/economically inactive residents supported to take part in a work
placement. 
• 42 participants secured employment at the end of their work placement
(62%).
• 472 participants were supported in 2024/25 by the Council’s Employability
Team and third sector delivery partners with tailored support on their journey
into work through No One Left Behind funding from the Scottish Government. 
• Job starts across Argyll and Bute is 44% compared with 31% Scotland wide.
Page 258

Page 259

5 
5.0 CONCLUSION 
5.1 The purpose of this paper is to provide members of the Environment, Development
and Infrastructure Committee with an update on the wide-ranging activities of the
overarching Economic Growth Team during 2024/25, including delivery of the
services and associated outcomes in compliance with funding requirements. 
5.2 There is an underlying theme of collaboration, facilitation and complementary work
across the teams within Economic Growth, with extensive collaboration with other
council teams, the third sector, government agencies and commercial companies. A
lot has been achieved during 2024/25 by small teams of staff. 
6.0 IMPLICATIONS 
6.1 Policy – Argyll and Bute Economic Strategy 2024-34, Local Outcome Improvement
Plan (LOIP), 2024-2034 and National Strategy for Economic Transformation (NSET-
10-year duration to 2032). 
6.2 Financial – numerous external funding streams, as detailed in the paper. 
6.3 Legal - all appropriate legal implications have been taken into consideration. 
6.4  HR – staff required to support delivery of the actions to realise appropriate outcomes
and impacts for residents and communities across Argyll and Bute. 
6.5 Customer Service – none. 
6.6 Risk - ongoing delivery of opportunities afforded by external funding has only been
possible with associated revenue funding. However, many funding sources are only
for one year, which makes staff recruitment and retention difficult, particularly in an
area such as Argyll and Bute with many remote rural and island communities.
Through various officer networks, such as Scottish Local Authorities Economic
Development (SLAED) group, focus has been given to the need to influence funding
bodies on the benefit of sustainable multi-annual funding streams. 
6.7 Climate Change – there were a number of net zero and climate resilience
interventions supported within the Argyll and Bute UK Shared Prosperity Fund
Investment Plan, 2022-2025 and ongoing for the 2025/26 UK Shared Prosperity
Transition Plan. 
6.8 Fairer Scotland Duty - the Fairer Scotland Duty, Part 1 of the Equality Act 2010,
came into force in April 2018. The duty places a legal responsibility on particular
public bodies in Scotland, such as Argyll and Bute Council, to pay due regard to
(actively consider) how they can reduce inequalities of outcome, caused by socio-
economic disadvantages, when making strategic decisions and how this has been
implemented. 
6.9 Equalities (protected characteristics) - all activities will comply with all Equal
Opportunities policies and obligations. 
Page 259

Page 260

6 
6.10 Consumer Duty - all activities will comply with the council’s Consumer Duty. 
6.11 Island Communities - interventions have been delivered across the whole of Argyll
and Bute including the island communities. 
6.12 Children’s Rights and Wellbeing – none. 
Kirsty Flanagan, Executive Director responsible for Development and Economic
Growth 
Policy Lead for Business Development: Councillor Math Campbell-Sturgess 
27th August 2025 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
Tel: 01546 604293 and e-mail: fergus.murray@argyll-bute.gov.uk 
Ishabel Bremner, Economic Growth Manager
Tel: 01546 604375 and e-mail: ishabel.bremner@argyll-bute.gov.uk 
APPENDICES
Appendix 1: Economic Growth Activities and Outcomes 2024/2025 
Page 260

Page 261

7 
Appendix 1
Page 261

Page 262

8 
Page 262

Page 263

9 
Page 263

Page 264

10 
Page 264

Page 265

11 
Page 265

Page 266

12 
Page 266

Page 267

13 
Page 267

Page 268

14 
Page 268

Page 269

15 
Page 269

Page 270

16 
Page 270

Page 271

17 
Page 271

Page 272

18 
Page 272

Page 273

19 
Page 273

Page 274

20 
Page 274

Page 275

21 
Page 275

Page 276

22 
Page 276

Page 277

23 
Page 277

Page 278

24 
Page 278

Page 279

25 
Page 279

Page 280

26 
Page 280

Page 281

ARGYLL AND BUTE COUNCIL                ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH             11 SEPTEMBER 2025 
REGISTRATION OF AN ECONOMIC DEVELOPMENT SUBSIDY SCHEME TO
FACILITATE COMPLIANCE WITH POST-EU SUBSIDY CONTROL LEGISLATION 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this paper is for members of the Environment, Development and
Infrastructure Committee to approve the registration of a subsidy scheme to facilitate
the delivery of economic development projects and ensure legal compliance with
subsidy control legislation. The proposed subsidy scheme documents can be
reviewed in Appendix 1 and Appendix 2 of this paper. 
1.2 A subsidy is where a public authority provides support to a business, or other
organisation. Any such assistance is subject to an assessment under control
legislation. An important point to note is that the registration of a subsidy scheme
does not in itself confer any subsidy on any organisation or spend or commit
any council funds or resources – it is simply an administrative tool which will
facilitate compliance when the council chooses to grant subsidy. All subsidies will
still be subject to assessment, consideration, and often legal oversight, using
existing council processes. 
1.3 Should the committee not approve the registration of this scheme, forthcoming
projects will continue to be potentially subject to a full and lengthy individual
assessment process as well as a 30-day challenge period with resulting delays and
staff resource implications. 
1.4 The registration of the proposed subsidy scheme will significantly reduce the
administrative burden on council officers and partners. It will also reduce delay. This
is a significant efficiency, and will allow the council to be nimbler, taking advantage
of project and funding opportunities in a less bureaucratic way. 
1.5 It is recommended that Members of the Environment, Development and Infrastructure
Committee: 
• Consider and note the Argyll and Bute Economic Development Subsidy Scheme
document, see Appendix 1 and the associated Principles Assessment document
see Appendix 2. 
• Endorse that a subsidy control scheme be registered with the Competition and
Markets Authority (CMA) called the ‘Argyll and Bute Council’s Economic
Development Scheme’. 
Page 281 Agenda Item 15

Page 282

ARGYLL AND BUTE COUNCIL                ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH             11th SEPTEMBER 2025 
REGISTRATION OF AN ECONOMIC DEVELOPMENT SUBSIDY SCHEME TO
FACILITATE COMPLIANCE WITH POST-EU SUBSIDY CONTROL LEGISLATION 
2.0 INTRODUCTION 
2.1 A paper was originally presented to the Directorate Management Team of
Development and Infrastructure in May 2021, outlining the significant changes in
subsidy control legislation which came about as the Brexit transition period ended on
the 31st of December 2020. It asked that the changes be noted and recommended
various actions including the setting up of an internal officers’ Subsidy Control Working
Group to lead on work in this area. 
2.2 Since this paper, a new regime has been introduced in the form of the Subsidy Control
Act 2022. The internal officers’ Subsidy Control Working Group has been working to
increase awareness of the legislation across the council, supporting officers to assess
subsidies against the legislation where needed, and keeping up to date with changes
to procedure and practice in the area. 
2.3 As with any new area of legislation, there is significant uncertainty, and best practice is
developing within both the council and public authorities across the UK. Members of
the internal officers’ Subsidy Control Working Group have been working
collaboratively to share best practice, particularly as part of a working group organised
by the Scottish Local Authorities Economic Development (SLAED) Funding Group
and a subsidy control sub-group established for the Highlands and Islands Regional
Economic Partnership (HIREP). 
2.4 Following the departure of the UK from the European Union (EU), a new Subsidy
Control Act (2022) created a domestic subsidy control regime in the UK, replacing
EU State Aid legislation. The act places significant duties on public authorities
(including the council) when granting subsidy in order to ensure the UK remains
compliant with its international legal obligations and to further its strategic interests. 
2.5 Subsidy can take the form of a grant, a tax break, a loan or guarantee on favourable
terms, or the use of facilities or provision of services below market price. Such
subsidies are commonly used by the council to meet its objectives, such as
encouraging economic development, delivering community facilities, or supporting
organisations and enterprises carrying out activity which benefits communities
across Argyll and Bute. Much of the external funding which is provided to or
Page 282

Page 283

administered by the council, often in the millions of pounds per year, is subject to
subsidy control legislation. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and Infrastructure
Committee: 
• Consider and note the Argyll and Bute Economic Development Subsidy Scheme
document, see Appendix 1 and the associated Principles Assessment document
see Appendix 2. 
• Endorse that a subsidy control scheme be registered with the Competition and
Markets Authority (CMA) called the ‘Argyll and Bute Council’s Economic
Development Scheme’. 
4.0 DETAIL 
4.1 The new subsidy control regime obliges the council to consider if many activities it
undertakes may be considered subsidy under the law and, if they are, to undertake
a time-consuming process of assessment prior to registering subsidy on a
transparency database managed by the CMA. Subsidy on this database is then
subject to a 30-day period in which they are open to legal challenge. This process
can take weeks or months, adding significant delays to projects, potentially even
putting them at risk should they be time sensitive; for example where external
funding is time-limited. It also time-consuming for council officers and is specialised
work often involving multiple officers and advice from the legal and regulatory
support colleagues. It will often need sign-off at a senior level. 
4.2 Recognising the work involved, the legislation allows for the registration of a subsidy
scheme. A scheme is an administrative framework which, once registered, allows
multiple subsidies to granted under it (if they fit the definitions and conditions of the
scheme). The scheme itself must be uploaded on to the transparency database and
is subject to a single 30-day challenge period. However, subsequent subsidies
registered under the scheme are not subject to challenge and can undergo a much
faster and simpler internal process of assessment. 
4.3 The purpose of schemes under the legislation is to provide this streamlined route for
compliance, and as a result, the advantages have been recognised by many local
authorities. At the time of writing, public authorities have registered 1,299 subsidy
schemes. This includes a significant number of schemes by Scottish local authorities,
and schemes for comparable purposes, such as that set up to administer the Belfast
City Deal. Council officers have been working closely with such authorities to ensure
the sharing of best practice and advice. 
4.4 In December 2024, the SLAED Funding Group suggested the creation of a subsidy
control scheme to be registered by the Scottish Government which could be used by
all public authorities working in the Highlands and Islands Regional Economic
Partnership area when undertaking subsidy activity to undertake community economic
development.
Page 283

Page 284

4.5 Argyll and Bute Council officers were involved in this HIREP working group and
worked collaboratively to draw up and scheme and the necessary scheme documents
over the early part of 2025. Unfortunately, when the scheme (known as the Highlands
and Islands Community Empowerment Subsidy Scheme – HICESS) was at an
advanced stage, it become apparent that the Scottish Government Subsidy Control
Unit was unable to register the scheme as originally intended. As the Scottish
Government is the only body that can register schemes for use by a range of public
authorities at a national level by law, this left the original plan for the HICESS scheme
at an impasse. 
4.6 Given that so much work had already been undertaken to create the scheme
documents, and the fact that much of it is easily transferable, several public authorities
who are members of the Highlands and Islands Regional Economic Partnership have
decided to modify the draft HICESS scheme and register it individually for their own
use. So far, Highlands and Islands Enterprise has registered a scheme. It is
understood other local authorities are also progressing this but Argyll and Bute
Council would be the first to do so. 
4.7 Preparing a scheme involves drawing up a scheme document (Appendix 1), which
would be made publicly available on the CMA transparency database at the time of
registration of the scheme. A detailed principles assessment (Appendix 2) must also
be undertaken and is held internally. These have been created by adapting work
previously undertaken for the HICESS scheme and are appended as noted. The
proposed Argyll and Bute Economic Development Subsidy Scheme would have the
following policy objectives: 
• Mitigate the regional inequality and socio-economic disadvantage experienced
in Argyll and Bute, recognising the region’s distinctive culture and unique
challenges. 
• Support the delivery of Argyll and Bute Council’s Economic Strategy 2024-2034
and the associated short-term Action Plan 2025-2028 (which is updated
annually).
• Preserve and create new employment to retain population across the region,
strengthening communities and underpinning the region’s place-based
approach to development. 
• Contribute to the Scottish Government’s National Strategy for Economic
Transformation (NSET) vision for a wellbeing economy thriving across
economic, social and environmental dimensions and its ambition to promote
entrepreneurial activity in every sector in our economy. 
4.8 Subsidies proposed under the scheme must be assessed to be delivering these
objectives, as well as meeting detailed eligibility and compliance requirements set out
in the documents. A third document, internal scheme guidance, will be drawn up to
assist council officers in the process. This will be integrated with existing processes,
such as those being developed as part of the Project Pipeline. This will introduce
further efficiencies as the subsidy control process continues to be integrated into
developing internal project planning processes. 
Page 284

Page 285

4.9 The potential benefits to registering the scheme are significant and are recognised by
council officers who work with subsidy, such as those involved in grant-giving and in
delivering externally funded infrastructure or community development projects. The
advantages are that subsidies issued under a scheme can:
• Undergo the necessary assessment to ensure compliance with subsidy control
legislation much more quickly and with less staff resource than those which
would need to be assessed and registered individually, significantly reducing
delays.
• Allow the council and partners receiving subsidy to have more confidence that
they are in compliance with the law. 
• Allow well-informed decisions to be taken sooner, internally, and also remove
the need for the compulsory 30-day challenge period which can cause delays. 
• The streamlined process, when undertaken with guidance and support from the
Argyll and Bute Council Officers’ Subsidy Control Working Group, can be
delivered by a wider range of council officers with less need for specialist input. 
4.10 The scheme also potentially significantly reduces risk. The subsidy control scheme
itself is subject to a 30-day challenge period, meaning its robustness is tested at this
stage. Subsequent subsidies issued under the scheme are not then subject to
individual legal challenge. The council must still ensure that any subsidies are
compliant with the scheme (and indeed internal auditing), and ensure due diligence is
undertaken. Robust internal processes and support are available to ensure this.
However the result is a significant reduction in the risk of legal challenge, improving
confidence in decision-making and preventing delays. 
4.11 The proposed scheme would run for 10 years from the point of registration. A review
of the scheme, its effectiveness, and the subsidies issued under it would be
undertaken at five years and any necessary changes made. An unlimited number of
subsidies could be issued under it, although an overall monetary cap is given, both for
individual subsidies awarded under the scheme and for the scheme as a whole. The
scheme therefore has potential to deliver benefits over a significant period of time and
across multiple projects. 
5.0 CONCLUSION 
5.1 The registration of an Argyll and Bute Economic Development Subisidy Scheme has
the potential to result in significant efficiencies when delivering subsidies of various
kinds over the next ten years. It will cut bureaucracy significantly, ensure legal
compliance, and aid decision-making. The scheme has come about as a result of
effective collaborative working between the council and other public authorities and
can be considered an example of best practice within the area of subsidy control. 
6.0 IMPLICATIONS 
6.1 Policy – aligns with the Argyll and Bute Economic Strategy 2024-34 and associated
short-term Economic Strategy Action Plan, 2025-2028, National Strategy for
Economic Transformation vision for a wellbeing economy thriving across economic,
social and environmental dimensions and its ambition to promote entrepreneurial
activity in every sector in our economy and potential ongoing implications for the
Page 285

Page 286

council’s Economic Development Subsidy Control Scheme aligned to revised
legislation and/or policy. 
6.2 Financial – potential implications on subsidy which may be awarded in future.
6.3 Legal – a new subsidy control scheme must be legally compliant, and then there
may be on-going potential implications as subsidy is awarded. 
6.4  HR – assessments will be undertaken by existing staff. 
6.5 Customer Service – none. 
6.6 Risk - the proposal should have positive implications for risk, as legal risk will be
reduced through using the proposed subsidy control scheme, as long as all
procedures and conditions are followed. 
6.7 Climate Change – none. 
6.8 Fairer Scotland Duty - the Fairer Scotland Duty, Part 1 of the Equality Act 2010,
came into force in April 2018. The duty places a legal responsibility on particular
public bodies in Scotland, such as Argyll and Bute Council, to pay due regard to
(actively consider) how they can reduce inequalities of outcome, caused by socio-
economic disadvantage, when making strategic decisions and how this has been
implemented. This is integral to the Argyll and Bute Economic Development Subsidy
Scheme policy objectives. 
6.9 Equalities (protected characteristics) - all activities will comply with all Equal
Opportunities policies and obligations. 
6.10 Consumer Duty - all activities will comply with the council’s Consumer Duty. 
6.11 Island Communities - none. 
6.12 Children’s Rights and Wellbeing – none. 
Kirsty Flanagan, Executive Director responsible for Development and Economic
Growth 
Policy Lead for Business Development: Councillor Math Campbell-Sturgess 
23rd July 2025 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
Tel: 01546 604293 and e-mail: fergus.murray@argyll-bute.gov.uk
Ishabel Bremner, Economic Growth Manager
Tel: 01546 604375 and e-mail: ishabel.bremner@argyll-bute.gov.uk 
Kevin Grant, Senior Development Officer, UK and External Policy Team
Tel: 01546 604491 and e-mail: kevin.grant@argyll-bute.gov.uk   
Page 286

Page 287

APPENDICES
Appendix 1: Argyll and Bute Economic Development Subsidy Scheme, Scheme Document
(draft)
Appendix 2: Argyll and Bute Economic Development Subsidy Scheme, Principles
Assessment (draft) 
Page 287

Page 288

This page is intentionally left blank

Page 289

1 
Argyll and Bute
Council
Economic Development
Subsidy Scheme
Scheme Document 
Page 289

Page 290

Page 2 of 13 
Contents 
1. Introduction and compliance with the subsidy control principles ............................................ 3
2. Purpose ................................................................................................................................. 3
3. Budget of scheme ................................................................................................................. 3
4. General definitions ................................................................................................................ 4
5. General conditions ................................................................................................................ 5
6. Type of subsidy and calculation of the subsidy value............................................................. 6
7. Eligible enterprises ................................................................................................................ 6
8. Eligible sectors ...................................................................................................................... 6
9. Eligible activities .................................................................................................................... 7
10. Ineligible activities ............................................................................................................. 7
11. Subsidy ratios and maximum award amounts ................................................................... 7
12. Cumulation ........................................................................................................................ 7
13. Misuse of subsidies ........................................................................................................... 8
SCHEDULE 1 ................................................................................................................................... 9
Measure 1 - Support for capital investment ................................................................................... 9
Measure 2 - Support for capacity building ................................................................................... 11
Measure 3 – Operating support ................................................................................................... 12
SCHEDULE 2 ................................................................................................................................. 13 
Page 290

Page 291

Page 3 of 13 
1. Introduction and compliance with the subsidy control principles 
1.1. This Scheme is made by Argyll and Bute Council (referred to hereafter as ‘the Council’) as a
public authority in accordance with section 10(3)(e) and 10(2)(a) of the Subsidy Control Act
(2022). It can be used by the Council to give subsidies to enterprises that meet the eligibility
criteria and conditions of the Scheme. 
1.2. The Scheme has been designed in consideration of the Subsidy Control Principles meaning
public authorities can give subsidies under the Scheme without assessing them against the
principles. Accompanying Scheme Guidance is provided to help the Council interpret and
comply with its conditions. 
1.3. The Scheme is made on [date] 2025 
1.4. The Scheme may be used by Argyll and Bute Council to support eligible beneficiaries and
activity in the Scheme area on or after 1 April 2025  until  31 March 2035. 
2. Purpose 
2.1. The Scheme provides for the giving of subsidies to stimulate and support the growth of
enterprises and organisations in the scheme area. Such subsidies shall fall within the
following categories set out in the Schedule 1:
a) Support for investment in capital assets
b) Support for capacity building
c) Operating support 
2.2. Subsidies given under the Scheme must comply with paragraphs 5 to 14 and the relevant
requirements in Schedule 1. 
2.3. The Scheme covers the local authority area of Argyll and Bute, as shown in schedule 2. 
3. Budget of scheme
The overall budget for the scheme is £200 million. The budget was calculated by looking at the
expenditure of grants in recent years which may have been eligible for consideration within this
scheme. A rough average amount per year was calculated and then projected forward. In
addition, consideration was given to known upcoming grants schemes, some of which
individually may result in tens of millions of pounds of activity. Although not all of this activity may
be deemed to be subsidy, this figure is considered a maximum possible amount. This is by its
nature an estimate as future grant and budget availability cannot be predicted, but it is based on
the experience of council officers with significant experience of this area of work within the local
authority.   
Page 291

Page 292

Page 4 of 13 
4. General definitions
4.1. “the Act” means the Subsidy Control Act 2022.
4.2. “ailing or insolvent enterprise” has the meaning defined in section 24(1) of the Act i.e. an
enterprise that (a) would almost certainly go out of business in the short to medium term
without subsidies, (b) is unable to pay its debts as they fall due, or (c) the value of its assets is
less than the amount of its liabilities, taking into account its contingent and prospective
liabilities.
4.3. “beneficiary” means the legal entity enterprise in receipt of the subsidy.
4.4. capital expenditure” means:
a) the buying of equipment, land or buildings;
b) or the construction of buildings for the purpose of the production of the relevant goods or
the provision of the relevant services;
c) or the adaptation of equipment, land or buildings for the same purposes;
d) or a combination of the purchase and the adaptation of equipment, land or buildings for
the same purposes;
e) for these purposes, this may include professional fees and consenting costs directly
relevant to the project to the extent these will be capitalised in the enterprise’s balance
sheet; also
f) for these purposes, this may include rental of equipment, land or buildings, where the
subsidy covers rental costs for 3 years or less; 
g) this may also include the purchase or licensing of intangible assets such as intellectual
property rights or software.
4.5. “eligible costs” means those costs defined in paragraphs 2, 6 and 10 in Schedule 1.
4.6. “enterprise” has the meaning given by section 7 of the Act.
4.7. “initial investment costs” means the initial outlay costs for a new project.
4.8. “obligation period” means the period over which the council places a legal requirement on
the subsidy beneficiary to fulfil the purpose of the subsidy.
4.9. “professional advisory fees” means the costs of purchasing any consultancy or professional
business services.  This excludes services that are needed for the ordinary administration of an
enterprise, to ensure compliance with legal obligations such as accountancy services to meet
annual reporting requirements.
4.10. “public authority” has the meaning under section 6 (1) of the Act.
4.11. “project” means an activity or activities conducted to a method or plan with a view to
achieving a specified end goal.
4.12. “project costs” means those costs incurred and paid for by the enterprise arising directly
from the delivery of the specific project for which they are seeking subsidy.
4.13. “project start” means when the activities directly related to the project, being subsidised
under the Scheme, begin.
4.14. “related projects" means projects or activities being carried out by the same legal entity, for
the same or substantially the same specific purposes set out in measures in Schedule 1.
Projects may be considered unrelated if they have entirely different objectives and could be
undertaken independently of one another.
4.15. “Sensitive sectors” means those defined in the schedule to the Subsidy Control (Subsidies
and Schemes of Interest and Particular Interest) Regulations 2022. These include
Page 292

Page 293

Page 5 of 13 
manufacture of iron and steel, production or aluminium and copper, manufacture of motor
vehicles, motorcycles, and air/spacecraft machinery, building ships and floating structures,
and production of electricity. 
4.16. “subsidised debt finance” means a loan, quasi-equity or equity investment that is provided
on terms that are more favourable than commercially available terms, such as lower interest
rates, collateral requirements, agreed share of profits.
4.17. “subsidy database” means the database of subsidies established under section 32 of the
Act.
4.18. “Subsidy of Particular Interest" has the meaning given in Section 3. (2),(3),(4) or (5) of the
Subsidy Control (Subsidies and Schemes of Interest and Particular Interest) Regulations 2022.
4.19. “training costs” means the fees of trainers and training providers, the hire of venues in which
to do training, the cost of equipment used exclusively for training purposes and the wage
costs of workers for the time spent in training.
4.20. “wage costs” means the gross wage payable by the beneficiary to the employee before tax
and includes the beneficiary’s compulsory contributions such as mandatory pension
contributions and national insurance. This excludes any voluntary benefits or allowances
given to the employee. 
5. General conditions
5.1. Before giving a subsidy to an enterprise under the scheme, the Council must obtain the
following information from the enterprise:
a) The name and legal entity status of the enterprise
b) A description of the proposed project or activity assistance is requested for including:
i. The location of the activity
ii. Start and end dates
iii. Expected outcomes
iv. Anticipated costs (excluding recoverable VAT if the enterprise is VAT registered)
supported by sufficient current documentation to evidence the costs. 
5.2. The council may not give a subsidy for a project or activity that has started unless:
a) it has provided written authorisation to the enterprise that the project or activity can be
started before the subsidy is given, and
b) it is of the view the project or activity would not be viable unless it starts before the subsidy
is given, or
c) it is of the view the scope of the project or activity is being widened or the project or activity
is being accelerated. 
5.3. The Council must award subsidies using objective and transparent selection criteria that are
available to potential recipients in advance of giving the subsidy. 
When giving subsidies using the Scheme, the council is responsible for ensuring they are compliant
with the scope and conditions of the Scheme.  The council will follow its own internal policies and
procedures, they must carry out an appropriate level of due diligence and investigation
commensurate with the value of the subsidy and the risk of creating market distortion, and
Page 293

Page 294

Page 6 of 13 
document the outcome.  In particular, the council must assess the additionality of each
intervention and record the outcome of the assessment in their project documentation. In addition,
the council must ensure that the schemes are compliant with the conditions of any grant scheme
from which part or all of the funding originates. 
5.4. All eligible costs must be incurred directly as a result of the project or activity. 
5.5. All eligible costs should be limited to those strictly necessary for the project or activity, and in
respect of revenue costs, limited to the time period of the project or activity. 
5.6. The Council may not give a subsidy under the Scheme that would, but for section 30(1) of the
Act, be subject to any of the prohibitions and other requirements contained in sections 15–29
of the Act. 
6. Type of subsidy and calculation of the subsidy value 
6.1. Subsidies under the Scheme may be given in any form of financial assistance. 
6.2. For the purposes of any paragraph in the Scheme that contains a financial amount, the
following will apply:
a) If a subsidy is provided in cash, the gross cash amount given is to be used in
determining the amount of the subsidy.
b) If a subsidy is provided otherwise than in cash, the amount of the subsidy given is to be
determined by reference to the gross cash equivalent of the subsidy.
c) The gross cash amount and gross cash equivalent amount are to be determined in
accordance with the Subsidy Control (Gross Cash Amount or Gross Cash Equivalent)
Regulations 2022. 
7. Eligible enterprises 
7.1. Enterprises as defined in the act (7.1-5) of any size may be eligible including private, public,
and third-sector enterprises:
a) Third and public sector organisations could include, but are not limited to social
enterprises, community organisations, charitable trusts, public sector arms-length
organisations (ALOs), public authorities, voluntary organisation intermediaries acting on
behalf of public authorities to deliver their social policies.
b) Private enterprises may be classed as an SME (by reference to the Companies Act
2006, S382 and S465) or a large enterprise.
c) Enterprises need not be based in the scheme area but the project or activity must be
delivered within, and only within the Scheme area. 
8. Eligible sectors 
Page 294

Page 295

Page 7 of 13 
All activity will be considered against the prohibitions as set out in the act (sections 2.14-31), as well
as their suitability for the exemptions set out in the legislation (sections 2.36-42). Subsidy relating to
sectors defined as “sensitive” may be given under the scheme, provided they do not exceed the
threshold where they become a Subsidy of Particular Interest and require mandatory referral to the
Competition and Markets Authority Subsidy Advice Unit for review. The list of sensitive sectors is set
out in the guidance which accompanies the act (sections 10.9 – 10.15). This guidance is subject to
on-going review and therefore all subsidies will be checked against the most recent iteration of the
guidance and list of sensitive sectors at time of assessment. 
9. Eligible activities
A broad range of projects or activities which support economic development and community
resilience, in line with Argyll and Bute Council’s ongoing policies and objectives. 
10. Ineligible activities
The Council may not give subsidy for any of the following:
a) Activity classed as prohibited subsidies in sections 15-29 of the Act.
b) Projects promoting political or religious beliefs.
c) Projects concerned with gambling or other activity that might bring the public authorities
or Scheme into disrepute.
d) Projects concerning activity that could be considered illegal. 
11. Subsidy ratios and maximum award amounts
Recognising that the distortive nature of subsidy is highly dependent on the nature of the enterprise
it is being given to subsidies given under the scheme are capped at variable amounts depending on
organisation type:
a) For third and public sector enterprises they must not exceed 100% of eligible costs; 
b) For private sector enterprises classed as SMEs, they must not exceed 80% of eligible
costs
c) For private sector enterprises classed as large enterprises (employing over 250 people),
they must not exceed 50% of eligible costs
d) In all cases subsidies must be capped at the maximum award amount for the measure
used.
e) Public authorities must identify other public funding contributing towards the same
eligible costs and consider the cumulation conditions of the scheme as well as the
Statutory Guidance at Chapter 3, (3.15 to 3.26), and Chapter 9 (9.3 to 9.7). 
12. Cumulation 
12.1. When applying the subsidy ratios and maximum award amounts set out in the measures in
Schedule 1, public authorities must consider the cumulative amount of subsidies received
by the enterprise for each project or activity, whether given under the Scheme or otherwise.
A subsidy given under the Scheme which falls below the maximum award amounts, must
Page 295

Page 296

Page 8 of 13 
not cause the subsidy ratio or maximum award amounts to be exceeded on a cumulative
basis. 
12.2. Other subsidies must be cumulated with the proposed subsidy, if the subsidy meets all the
following conditions and was given:
a) to the same enterprise by any public authority;
b) for the same project or activity under the relevant measure in Schedule 1;
c) for the same or substantially the same specific purposes as set out under the
relevant measure in Schedule 1; and
d) within the last three financial years - that is the lapsed part of the current financial
year from 1st April and the two preceding financial years. 
12.3. Where a project or activity’s duration will extend beyond three years, the full value of the
subsidy is counted at the date of award.  A new cumulation period does not start after three
years. 
12.4. The subsidy ratio or maximum award amounts may not be circumvented by artificially
splitting up a single project into several constituent projects with similar characteristics or
objectives. 
13. Misuse of subsidies 
The Council shall  ensure that any subsidy given under the Scheme is given subject to a condition
allowing the Authority to recover the whole or part of the subsidy amount to the extent that the
subsidy is used for a purpose other than the purpose for which it was given. 
14. Reporting 
Public authorities using the scheme must meet the Scheme reporting requirements established by
Scottish Government to monitor the Scheme’s use and budget and to evaluate if the Scheme is
serving its intended purpose.  The reporting requirements may be amended from time to time at the
sole discretion of Scottish Government. 
15. Transparency 
Public authorities using the Scheme must meet the transparency requirements set out in Chapter 3
of Part 2 of the Act and upload any subsidy given under the Scheme to the subsidy database where
required by the Act. 
Page 296

Page 297

Page 9 of 13 
SCHEDULE 1 
Measure 1 - Support for capital investment 
1. Scope
Subsidies under this measure may be given for defined projects being carried out in the Scheme
area that will assist beneficiaries to invest in capital assets. 
2. Eligible costs 
2.1. Subsidies may only be awarded under this measure for the following initial investment
project costs:
a) Purchase of land, buildings or other heritable assets.
b) Civil engineering and construction costs to repurpose, regenerate, upgrade or extend
capital assets.
c) Purchase of equipment, fixtures, fittings or furniture.
d) Professional advisory fees, consenting costs and design development fees where these
will be capitalised in the enterprise’s balance sheet.
e) Rental costs of equipment, land or buildings subject to a maximum subsidised period of
three years.
f) Purchase or licensing of intangible assets such as software or intellectual property
rights. 
3. Subsidy ratios and maximum award amount 
3.1. Recognising that the distortive nature of subsidy is highly dependent on the nature of the
enterprise it is being given to subsidies given under the scheme are capped at variable
amounts depending on organisation type: For third and public sector enterprises they must
not exceed 100% of eligible costs; for private sector enterprises classed as SMEs, they
must not exceed 80% of eligible costs; for private sector enterprises classed as large
enterprises, they must not exceed 50% of eligible costs
3.2. The subsidy limit to a single enterprise for a project or combination of related projects is
£10m.
3.3. Where the subsidy is given in the form of subsidised debt finance the gross cash equivalent
shall not exceed £10m.
3.4. The subsidy maximums may not be circumvented by artificially splitting up a single project
into several constituent projects with similar characteristics or objectives. 
4. Further conditions 
4.1. The beneficiary for subsidy under this measure must be the legal entity that will own the
asset for which assistance is given.  Where an asset that is leased is to be developed or
upgraded, the council must ensure there is a reasonable term remaining on the lease for
the economic benefits of the project to be realised.  As a minimum, the lease should endure
Page 297

Page 298

Page 10 of 13 
until the end of the obligation period. The specific conditions of any grant or subsidy should ,
if appropriate, allow a  security to be placed on any assets where deemed appropriate to do
so and / or outline a clawback provision for the subsidy in the event of an asset transfer,
sale or disposal   or where the subsidy is not  used in accordance with the relevant grant
conditions. 
4.2. The Council must include conditions in the legal subsidy award stating when the project
should be completed and an obligation period to maintain it for the purpose intended.  The
obligation period should be for a minimum of three years. 
Page 298

Page 299

Page 11 of 13 
Measure 2 - Support for capacity building
5. Scope
Subsidies under this measure may be given for defined projects that will strengthen the capabilities
of beneficiaries. This may include, but is not limited to, strengthening their governance, improving
efficiency, expanding current operations, entering new markets or introducing new products or
services. 
6. Eligible costs 
6.1. Subsidies may be awarded for:
a) Wage costs - including the beneficiary’s employer’s mandatory contributions.
b) External consultancy and professional advisory fees.
c) Training costs – provider fees, materials, venue costs, travel and accommodation.
d) Costs associated with historic or cultural assets owned by the organisation, such as
archiving, display, or conservation
e) Marketing, distribution and promotional activity. 
7. Subsidy ratios and maximum award amounts 
7.1. Recognising that the distortive nature of subsidy is highly dependent on the nature of the
enterprise it is being given to subsidies given under the scheme are capped at variable
amounts depending on organisation type: For third and public sector enterprises they must
not exceed 100% of eligible costs; for private sector enterprises classed as SMEs, they
must not exceed 80% of eligible costs; for private sector enterprises classed as large
enterprises, they must not exceed 50% of eligible costs
7.2. The subsidy limit to a single enterprise for a project or combination of related projects is
£3m.
7.3. Where the subsidy is given in the form of subsidised debt finance the gross cash equivalent
shall not exceed £3m.
7.4. The subsidy maximums may not be circumvented by artificially splitting up a single project
into several constituent projects with similar characteristics or objectives. 
8. Further conditions 
8.1. Subsidies using this measure must relate to a new project or activity with defined objectives,
start and end dates that is additional to the enterprise’s business-as-usual activities.
8.2. Where wage costs of employees are included, these will only be eligible for the period the
employee is engaged in the capacity building project.  Where an existing employee is
engaged for part of their employment on the project, and part on their normal duties, the
council must obtain appropriate evidence from the enterprise to confirm the eligible project
costs.
8.3. Training costs may apply to the training of employees as well as the non-executive
governing personnel of the enterprise.
8.4. Marketing and promotional activity costs under this measure are limited to costs associated
with new capital, product or service developments and not to the enterprises business-as-
usual promotional activities.  
Page 299

Page 300

Page 12 of 13 
Measure 3 – Operating support
9. Scope
Subsidies under this measure may be given for to support business-as-usual operating costs over a
specified period. 
10. Eligible costs 
10.1. Subsidies may be awarded for:
a) Wage costs- including the beneficiary’s mandatory employer’s contributions.
b) The enterprise’s costs linked to periodic activities including exhibitions, events or
educational activity, increasing accessibility to and provision of services.
c) Operating costs such as rent, running costs, maintenance, insurance costs, travel
expenses, marketing, materials and supplies.
d) Ongoing reduction of/discounted public fees, rates or service costs. 
11. Subsidy ratios and maximum award amounts
11.1. Recognising that the distortive nature of subsidy is highly dependent on the nature of
the enterprise it is being given to subsidies given under the scheme are capped at variable
amounts depending on organisation type: For third and public sector enterprises they must
not exceed 100% of eligible costs; for private sector enterprises classed as SMEs, they
must not exceed 80% of eligible costs; for private sector enterprises classed as large
enterprises, they must not exceed 50% of eligible costs
11.2. The subsidy limit to a single enterprise is £3m per annum.
11.3. Where the subsidy is given in the form of subsidised debt finance the gross cash equivalent
shall not exceed £3m.
11.4. Where the subsidy is given to support costs relating to 10.1 a), b) or c), they must be
limited to what is necessary to cover the projected operating losses over the relevant
period. These shall be determined ex-ante, based on reasonable projections. 
12. Further conditions
12.1. As support for business-as-usual costs is highly distortive, assistance using this measure
must be carefully considered and the council should keep a record of the justification for
the support.
12.2. Where the subsidy is given to support costs relating to 10.1 a), b) or c), the council must
carefully consider the phasing of payments to avoid paying out in advance of need or over-
subsidising. They should follow the grant guidance in the Scottish Public Finance Manual.
They may also consider including provision in the legal offer to reconcile the projected and
actual losses at the end of the relevant period with claw-back provisions to recover any
excess subsidy or as provided for at 4.1 (transfer, sale or disposal of assets).
12.3. This measure must not be used to subsidise an ailing and insolvent enterprise as defined in
section 24(1) of the Act.
Page 300

Page 301

Page 13 of 13 
SCHEDULE 2
Geographical scope of the scheme
The geographical area covered by this scheme is shown in the map below. It covers the area of
Argyll and Bute local authority. The local authority is the second largest in Scotland, covering
around 9% of Scotland’s landmass. It is bounded by the Clyde and Loch Lomond to the east,
the Mull of Kintyre to South, Atlantic Islands to the West, and the Sound of Mull and Appin to the
North. It includes 23 inhabited islands, more than any other local authority. Its geography of
long sea-lochs and peninsulas give it an extremely long coastline, and create unique challenges
for organisations, public, bodies and enterprises operating in the area. 
Page 301

Page 302

This page is intentionally left blank

Page 303

Argyll and Bute
Council
Economic Development
Subsidy Scheme
Principles Assessment 
Page 303

Page 304

1 
Contents 
Contents ....................................................................................................................... 1
Project summary and subsidy award description........................................................... 2
SUBSIDY ASSESSMENT ..................................................................................................... 3
Step 1 – Policy Objective .............................................................................................. 3
1.1.i Existence and significance of the market failure and/or the equality concern the
subsidy seeks to address. ............................................................................................. 3
1.1.ii How the subsidy will remedy the market failure (provide a more efficient outcome)
and/or address the equity objective (reduce an inequality) ............................................ 6
Step 1.1.iii The desired outcomes of the scheme .......................................................... 8
Step 1.2 – Appropriateness of the subsidy .................................................................... 8
Step 2.1 – Baseline analysis ......................................................................................... 9
Step 2.2 – Additionality assessment............................................................................ 10
Step 3 – Proportionality and minimising distortion within the UK [Statutory Guidance
3.72 – 3.108] ............................................................................................................... 12
3.1 The nature of the instrument [Statutory Guidance 3.80 to 3.82] ............................ 12
3.2 The breadth of beneficiaries and the selection process [Statutory Guidance 3.83 to
3.85]............................................................................................................................ 12
3.4 Timespan [Statutory Guidance 3.94 to 3.97.] ........................................................ 13
3.5 Nature of costs covered [Statutory Guidance 3.98 to 3.99].................................... 13
3.6 Performance criteria [Statutory Guidance 3.100 to 3.101] ..................................... 13
3.7 Monitoring and evaluation [Statutory Guidance 3.104 to 3.106] ............................ 14
Step 4 – Balancing exercise ........................................................................................ 15
4.1 Negative effects .................................................................................................... 15
4.2 Benefits of the subsidies and scheme ................................................................... 15
4.3 Why negative effects are outweighed .................................................................... 16
APPENDIX 1 – Map of scheme area ................................................................................... 18
APPENDIX 2 – Reference links and summary statistics table ............................................. 19 
Page 304

Page 305

2
Project summary and subsidy award description 
Argyll and Bute Council is making this scheme using its powers under with section
10(3)(e) and 10(2)(a) of the Subsidy Control Act (2022) (SCA) . 
The policy objective is to: 
• Mitigate the regional inequality and socio-economic disadvantage experienced in
Argyll and Bute, recognising the region’s distinctive culture and unique challenges. 
• Support the delivery of Argyll and Bute Council’s Economic Strategy 2024-2034
and the associated short-term Action Plan, 2025-2028 (which is updated
annually).
• Preserve and create new employment to retain population across the region,
strengthening communities and underpinning the region’s place-based approach
to development. 
• Contribute to the Scottish Government’s National Strategy for Economic
Transformation (NSET) vision for a wellbeing economy thriving across economic,
social and environmental dimensions and its ambition to promote entrepreneurial
activity in every sector in our economy. 
The purpose of the scheme is to make a simplified route for the council to give financial
assistance to enterprises operating in the scheme area. Support can take the form of
investment in capital assets up to £10m, projects to build the capacity of the social
enterprise sector (up to £3m), and operating support over a limited period (up to £3m).
Assistance must comply with the scheme conditions. 
Subsidies can be awarded as indirect, direct or repayable grants or subsidised loan, or a
combination thereof. The maximum subsidy limit will be 100% of eligible costs for third
and public sector organisations, 80% for SMEs, and 50% for large enterprises
(enterprises employing over 250 people). The purpose, terms and conditions of each
subsidy will be set out in a grant offer and legal agreement with the recipient. The
subsidies will not be subject to any exemption in section 43 – 51 of the SCA and will not
be subsidies of interest. Information regarding sections (q) to (x) of Regulation 3 of The
Subsidy Control (Subsidy Database Information Requirements) Regulations 2022 is not
provided as these are not applicable. 
Page 305

Page 306

3
SUBSIDY ASSESSMENT 
Step 1 – Policy Objective
[Statutory Guidance 3.32 to 3.34] 
The policy objective is to:
• Mitigate the regional inequality and socio-economic disadvantage experienced in
Argyll and Bute, recognising the region’s distinctive culture and unique challenges. 
• Support the delivery of Argyll and Bute Council’s Economic Strategy 2024-2034
and the associated short-term Action Plan, 2025-2028 (which is updated
annually).
• Preserve and create new employment to retain population across the region,
strengthening communities and underpinning the region’s place-based approach
to development. 
• Contribute to the Scottish Government’s National Strategy for Economic
Transformation (NSET) vision for a wellbeing economy thriving across economic,
social and environmental dimensions and its ambition to promote entrepreneurial
activity in every sector in our economy. 
[Statutory Guidance 3.35 – 3.53]
1.1.i Existence and significance of the market failure and/or
the equality concern the subsidy seeks to address. 
Equality concern 
Argyll and Bute Council is second largest local authority area in Scotland by landmass
and is home to a rich and varied natural landscape and coastline comprising a significant
expanse of Scotland’s mainland, as well as the southern group of the Inner Hebridean
Islands, currently consisting of 23 inhabited islands which are home to 17% of the
region’s population. 41.8% of Argyll and Bute’s population live in rural and remote rural
areas. 
The local authority area is part of the wider Highlands and Islands region, which is a large
landmass (52% of Scotland or 18.4% of the UK) with a small population (approx.
490,000) much of which is located in a rural environment. It has been viewed as lagging
behind that of the rest of Scotland, the UK and much of Europe. Many of the issues faced
in Argyll and Bute are common to this wider region, and the equality concerns discussed
here (and indeed throughout the assessment) are therefore put into that wider context.   
The challenging geography and the distance from key markets are amongst the issues
contributing to the area as a whole facing a declining population, but there are particular
challenges in Argyll and Bute. The distinctive geographical character of the region with
many islands and deeply indented sea lochs creating many peninsulas creates a unique
challenge for transportation. This means there is high reliance on ferries for both
mainland and island communities. The overall depopulation trend and difficulties in
attracting talented people to work in the region are also influenced by the lack of
appropriate and affordable housing, lower than average salaries, under provision of
affordable childcare and transport challenges. Conversely, some areas of the local
authority are in very close proximity to the central belt, particularly Glasgow and suffer
from issues such as de-industrialisation. This variety creates its own challenges.  
Page 306

Page 307

4 
For decades, the Highlands and Islands as a whole (including Argyll and Bute) have been
subject to distinct policy approaches to alleviate some of these issues, such as the
formation of distinct development and enterprise agency and a range of specific
strategies such as the Scottish Government’s Action Plan to address depopulation
(2024). 
Argyll and Bute Council’s Economic Strategy recognises these challenges, for example
the cost of doing business and the high cost of living, as the distinctive impact on the loca
authority area by recent economic shocks such as the pandemic, EU Exit, and severe
weather incidents which are increasing in frequency due to climate change. It sets out a
ambitious plan to meet the area’s unique challenges and opportunities. It has a particular
focus on arresting population decline, attracting and upskilling workers. It also
emphasises investment in rural and remote communities, delivering net zero and seizing
potential economic opportunities which are particularly well-suited to communities like
those in Argyll and Bute. 
The Highlands and Islands Regional Economic Partnership (HIREP) work across the
wider region, and are currently preparing a short-term delivery plan to address the biggest
challenges in the region. Prior to the UK’s exit from the EU on 1 January 2021, the
Highlands and Islands had Assisted Area status because of the lower comparative GDP
and sparsely populated areas. This created a particular reliance on European funding for
investment. Post Brexit, this has meant reduced funding and heightened uncertainty
about future funding settlements.
Through a wide range of activity by numerous local and regional parties many of the
issues impacting on the region’s economy and social wellbeing have been tackled and
improvements have been made in a variety of sectors and geographical areas. However
challenges remain. In November 2024, the Scottish Human Rights Commission (SHRC)
published a report Economic, Social and Cultural Rights in the Highlands and Islands
cover the whole of the region, including four case studies within Argyll and Bute. Its
findings are relevant to Argyll and Bute, and included, ‘The human rights of its
people…are not all being fulfilled, with big challenges to the full enjoyment of their
economic, social, and cultural rights.’ The Commission raised specific concerns for the
following areas: lack of affordable and quality housing; limited access to sufficient and
nutritious food, inaccessible health care services, fuel poverty, access to technology or
poor internet connectivity, poverty related attainment gap in education, transport
connectivity to essential public services and supplies. 
In 2023 and 2024 Highlands and Islands Enterprise gave evidence to the UK Parliament
Scottish Affairs Committee highlighting issues relating to the inequality faced by the
populations across the Highlands and Islands area as a whole, which are also relevant to
Argyll and Bute. In addition to the issues referenced above, HIE documented challenges
around cost of living; fuel costs in unhospitable climate; and lack of viability of key
services resulting in part from low population density. 
A number of factors negatively impact or exacerbate the cost of living in Argyll and Bute–
structural disadvantage (e.g. limited access to high quality broadband), higher than
average levels of fuel and transport poverty, poor and declining access to services.  Work
by the Scottish Government in 2021 on a Minimum Income Standard for Remote Rural
Scotland, concluded that the cost of living is higher in remote rural parts of Scotland than
elsewhere across the UK. The dominant additional cost is the cost of travel reflecting the
longer distances people must routinely travel, particularly to work. 
Page 307

Page 308

5
Reliance on transport – Average fuel prices (petrol and diesel) tend to be higher in Argyll
and Bute than for Scotland overall. Given the distance from and to markets and services
creating higher reliance on transport, transport costs for businesses and residents are
higher. Transport poverty is also a factor with a lack of alternative options to mitigate the
impact of increased fuel prices. A particular issue is also the fragility of transport routes in
Argyll and Bute, with ferries vulnerable to disruption and a small number of key road
routes frequently closed due to landslides and flooding, creating long and difficult
diversions. 
Access to services – More people in rural areas are outwith a reasonable drive time to
key services (e.g. GPs and shops) compared to the rest of Scotland. This puts
communities in rural areas at a disadvantage even before accounting for changes and
challenges as a result of the recent cost-of-living crisis. 
Housing - A key issue across the region is securing quality housing. Argyll and Bute
Council was the first in Scotland to declare a housing emergency, in June 2023. Access
to appropriate and affordable housing is a constraint to both population attraction and
economic growth. High and increasing construction costs are a disincentive to
housebuilding. There is a high rate of second home ownership in the area which drives
up house prices and further limits supply for local residents.  In addition to the inadequate
supply of housing, there are issues with quality of the existing housing stock, relating to
improving energy efficiency, addressing fuel poverty and contribution to reducing
greenhouse gas emissions. Fit for purpose and affordable housing, across all types and
tenures, in the right locations, underpins realisation of Argyll and Bute’s transformational
economic opportunities by ensuring that worker accommodation is available. It is also
critical to community cohesion and resilience, given the importance of housing availability
for residents and those providing key services. 
The need for Regeneration - The low population density, demographic changes and
pockets of deprivation as identified on the Scottish Index of Multiple Deprivation, can
mean that despite there being a housing crisis, property and housing can be of a low
market value. Combined with a lack of private investment, this can result in a lack of
investment in key buildings, such as tenements, multi-use buildings, or even large
community buildings such as churches, concert halls, or theatres in town centres. Many
of these buildings were built at a time prior to population decline when populations were
larger, or when large industries supported thriving and highly localised economies, such
as tourism on the clyde coast or fishing. These structures often contribute significantly to
the public amenity of towns and are a crucial part of their historic environment –
especially in small communities which have few large buildings. Often, the conservation
deficit (when the cost of renovation, particularly to a high conservation standard, is
greater than the buildings resulting value to its owner) will not be met by the market.
Without subsidy this can result in derelict or poorly maintained buildings and a poor built
environment. Although conservation deficits can be an issue in many areas, it is
particularly challenging in rural areas such as Argyll and Bute which have been subject to
depopulation and fewer economic opportunities than more urban, central areas. 
One of the strengths of Argyll and Bute is its varied and distinctive historic environment,
particularly in settlements characterised by late 19th century or 20th century tourism
around the Clyde, planned historic settlements such as Inveraray or Lochgilphead, the
legacy of an extensive whisky industry, or a varied range of vernacular rural buildings
which reflect the agricultural history of the region. Working with partners on the ground
(including private owners) to subsidise the cost of restoring a listed building may be the
only way of securing its long term future – one example of this approach is the highly
successful Conservation Area Restoration Scheme. Delivering targeted investment also
leads to the sustainable reuse and management of historic buildings. Public funding,
Page 308

Page 309

6
often in the form of grants, can be used to cover or alleviate the conservation deficit and
ensure that the heritage asset is brought back into beneficial and economically viable
use. 
The region has distinctive cultures and enjoys well-established brand recognition with
strengths in areas such as heritage and Gaelic and minority languages. However the
SHRC report noted there were limited opportunities for engagement in cultural life and
that these were deteriorating across the region. The HIREP strategy notes that the region
has a major opportunity to build on cultural and heritage assets. 
The above challenges are recognised across the region and this is reflected in the joint
strategy being produced by the Highland and Islands Rural Economic Partnership
(HIREP) as well as in the strategies of individual partners. Argyll and Bute Council
engages collaboratively with both the other local authorities in the region and partners
operating at regional and national levels. 
1.1.ii How the subsidy will remedy the market failure (provide
a more efficient outcome) and/or address the equity objective
(reduce an inequality) 
Across Argyll and Bute it is common for organisations to be established to provide
activities and services supporting the economic and social wellbeing of the area. Equally,
the remote, and often fragile nature of some communities means that private enterprises
can become crucial to community survival and may be the only enterprises serving crucial
community needs.  Local solutions, utilising available partner organisations, are
commonly sought to address the inequalities experienced across the region. This subsidy
scheme aims to reduce the burden on such organisations by reducing administrative and
financial challenges, therefore allowing focus on delivery of core activity. 
The area has a long history of taking a place-based approach. The Highlands and Islands
as a whole have pioneered community-led development, empowering communities to be
active participants and partners in community wealth-building. As a result the region has
unrivalled levels of community asset ownership, community participation and social
enterprise development. This is also particularly the case for Argyll and Bute. It is not
surprising therefore that the region boasts a high number of social enterprises and
community organisations operating across a wide range of markets. The SEC Scotland
2021 recorded 6,047 social enterprises operating in Scotland, with 257 located in Argyll
and Bute, a 4.5% increase from the 246 social enterprises recorded in 2017. Commercial
businesses in the region represent just 13% of all Scottish businesses. There are 30
social enterprises per 10,000 people in Argyll and Bute compared with a figure of 11
nationally. (A+BC SEC 2021) 
The Scottish Government has acknowledged in their social enterprise action plan and
report on inclusive and democratic business models the important role of social
enterprises in offering new, nimble and collaborative responses to the cost of living crisis.
Social enterprises are being established in response to local market failure or to support
the communities within which they live, creating businesses, securing jobs and delivering
services and these organisations have an essential role to play in supporting the delivery
of the outcomes in Scottish Government’s National Performance Framework. 
The 2021 SEC highlighted the importance of non-profit making organisations to the
region with social enterprises contributed £47.3m GVA and supported 1,482 FTE
Page 309

Page 310

7
employees in Argyll and Bute (A+BC SEC 2021). Further it highlighted the wide range of
sectors in which these organisations were involved increasingly reflects community asset
ownership and offers new opportunities to support community wealth building. 
With increasing pressure on public funds, resulting in cuts to services and in grants to
those who provide external services, it is a particularly challenging time for social
enterprises to remain viable. The majority of these organisations rely on public support for
establishment, development and (on occasion) continuing operations. Increasingly they
are being expected to accept cuts to service level agreements and from the traditional
sources and search for new sources of support. 64% of Argyll and Bute social enterprises
reported insecure or declining funding in 2021, a significant increase from 50% reporting
this in 2017.(A+BC SEC 2021). Thus precious volunteer resources are being used to
source funding and can be diverted from the core purpose of the enterprise, reducing the
opportunity to contribute to the regional economy. 
The SCHR report recommended that to address the inequalities it highlighted there is a
need to review the impact of current policies and carefully examine how resources are
used to achieve maximum impact therefore improving services and meeting core
obligations. In a time of ever tightening public budgets, one way forward is for greater
support of local-based solutions. SCHR report notes increasing lack of funding or
complete removal of services and tendency to take a one size fits all approach. In the
Scottish Government Action Plan – Social Enterprise: Driving a Wellbeing Economy for
Scotland a key action was enhancing support and coordination for social enterprises
looking to access funding or business support. This subsidy scheme aims to simplify
access of organisations to public support. 
HIREP’s strategy sets out approaches to tackle the inequalities experienced across the
region. In so doing it references recent work by the OECD on innovation in rural areas
highlighting the powerful impact of social innovation on development in the region and
solid foundation on which to build, and particularly mentioning the role of social
enterprises in service provision, especially across remote mainland and island
communities. 
Innovative, local approaches will also often involve the private sector. In many of the
remote, small or fragile communities within Argyll and Bute, close working with the private
sector is essential for the sustainability of communities . The private sector in Argyll and
Bute has a distinctive make-up, with a particularly high concentration of small and micro
enterprises, which make up over 98% of enterprises and workplaces in the region
(NOMIS). Although many of these small businesses, often based in remote locations, can
be nimble and react to community demand, they can also be fragile and have limited
capital for investment. 
The remote nature of many communities within Argyll and Bute make them vulnerable to
particular market failure. Communities may be highly reliant on private businesses
delivering vital support – for example, an island community may need to rely on the local
fish farm using its service vessels to undertake deliveries as a favour where there is no
publicly funded car-ferry. In other areas, it may not be possible to secure contractors for
building work as they may not quote to undertake works in an area which is difficult and
unreliable to access. Therefore, a community may be highly reliant on a single local
contractor. There may also be communities which are so small or lacking in permanent
residents, that working closely with private owners and businesses is the only viable way
of delivering certain developments where third-sector organisations lack capacity or are
too fragile. In these cases it may also be difficult for third sector organisations to get grant
funding, as funders identify them as high-risk. 
Page 310

Page 311

8 
At a time when there is an increasing focus in Scotland and beyond on a Community
Wealth Building approach, it could be said that Argyll and Bute of Scotland has been
‘ahead of the curve’ with a variety of approaches taken to find local, bottom-up solutions
to challenges faced working with the third, public, and private sectors. Argyll and Bute’s
Economic Strategy emphasises the need for collaboration and a joined up approach,
working with key partner agencies and stakeholders as well as the need to take a
Community Wealth Building Approach.The scheme will help sustain and develop this
community-led approach. 
This subsidy scheme proposes a route where the challenge of providing subsidy support
is streamlined and becomes less onerous to the council by reducing the need to prepare
individual Subsidy Principles Assessments.  The Scheme should simplify access to public
support by coordinating the information applicants need to provide when applying to
multiple funders. It will also give applicants greater certainty that the subsidy received is
compliant with legislation. Decisions on funding priorities and distribution will rest with
both the council and bodies awarding grant, however, the scheme will support the policy
objective by allowing support to beneficiaries delivering a range of activities, from health
and social care to development of property assets and supporting cultural and heritage
activities. 
Step 1.1.iii The desired outcomes of the scheme 
In summary the scheme is expected to achieve the policy objective by providing:
• A more efficient means of awarding subsidies that are considered low risk due to their
predominantly local market impact and minimal displacement effect.
• Reduce the burden of bureaucracy to the Council and its partners by providing a more
efficient route for assessing subsidy, as well as giving confidence which will help to
plan and time-table projects.
• A practical demonstration of how public sector partners can collaborate to achieve
best practice, for example taking a Community Wealth Building Approach 
Step 1.2 – Appropriateness of the subsidy
[Statutory Guidance 3.54 – 3.56] 
The scheme has been designed to provide a range of financial assistance including direct
or indirect grants, non-financial interventions (i.e. free or subsidised training or advisory
services) and subsidised loans. These are considered the most appropriate forms of
subsidy for the type of client beneficiary and the range of goods, but mainly
community/social services, they deliver. The following alternatives have been considered
and ruled out as inappropriate. 
Regulation – It is difficult to see how regulation would resolve the population and other
socio-economic challenges the policy objective seeks to address.  The third sector
already has some tax exemptions and would benefit from further concessions (such as
relief from the recent increase to ENIC) however, most of these tax-raising powers are
not devolved to enable the Scottish Government to consider making them. The Scottish
and UK Governments are currently consulting on investment zones, in particular NDR
investment zone and on sites for defence investment to feed into the Defence Industrial
Strategy. Whilst these and other regulatory approaches, such as a potential Community
Wealth Building regulation may help to deliver the policy objectives set out in this
assessment, they will not resolve the issues nor remove the need for subsidy on many
occasions.
Page 311

Page 312

9 
Direct provision – The range of social enterprise activities supported by the scheme is
anticipated to be very broad – everything from local heritage, cultural and Gaelic
language facilities to training and employability services, development and investment in
buildings and assets, community-led tourism initiatives, community woodlands and local
amenities, social care and mental health projects.  Many of these could be (and perhaps
were) provided by the public sector but the fact is that austerity measures and inflationary
pressure over the years has meant PAs have had to withdraw direct provision or establish
ALOs that can provide services more efficiently.  In some cases PAs will not have the
expertise nor the very localised resources needed to provide the services on the ground. 
More significantly, the third or private sector may be able to deliver the services more cost
effectively than the public sector who generally have higher wages, pension contributions
and overheads. 
Equity – The nature of the eligible beneficiaries will preclude equity options.  Most will not
have share capital and the minority that do are unlikely to pay dividends preferring to
reinvest them in the social purposes or further economic development in the local area. 
Such organisations are also unlikely to generate the level of return on exit that would
make them an attractive proposition for public sector investment. 
Step 2.1 – Baseline analysis
[Statutory Guidance 3.57 -3.62] 
Community organisations and social enterprises often rely on financial support from
public organisations and others. There is an increasingly challenging funding
environment, where less monies are available, and they become more burdensome to
access. Without access to public subsidy there would be a severe negative impact on the
operation and development of social enterprises which would have a knock-on effect on
delivery outcomes and, in some cases, their very existence.  The social enterprise birth
rate would be particularly depressed without public subsidy to support acquisition or
transfer of capital assets and start-up costs. 
The biennial Social Enterprise Census provides a useful barometer for the health and
strength of the non-profit-distributing sector and helpful insight into their sources of
income.  Dependency on grant has been decreasing steadily since 2017 when it was
39.2% to 25.7% in 2021. The grant data does not differentiate between public and private
sector grants, but it would be safe to assume that public grant accounts for the largest
proportion (A+BC SEC 2021). Total income of the social enterprise sector was £106m in
2021, an increase of 22% compared to 2017, similar to the national trend (27%). (A+BC
SEC 2021). Grant funding is the largest source of external finance (79%) for Argyll and
Bute’s social enterprises. (A+BC SEC 2021) 
In the absence of grant support and other forms of subsidy it is highly likely that the social
enterprise sector will struggle to grow through diversification or expansion, which could
lead to some organisations stagnating or even closing.  56% of Argyll and Bute social
enterprises reported having seen costs increase between 2019 and 2021. (A+BC SEC
2021). The burden of higher costs has fallen disproportionately on smaller organisations
who have more limited scope to lower fixed costs, reduce services or adjust discretionary
spending.   
A decline in the activity of social enterprises and community organisations across Argyll
and Bute would impact on a wide range of sectors and services.  The Highlands and
Islands SEC 2021 lists the following key sectors as the most common areas of social
Page 312

Page 313

10
enterprise activity: community centres and halls; property, energy, utilities and land;
health and social care, early learning and childcare; environment and recycling; transport. 
The level of community-led development across the area is high and a reduction in this
activity, as a result of no or reduced subsidies, would have a detrimental effect on socio-
economic performance. 
Ultimately if there is a continued decline in local services, this will make remote
communities less attractive places to live and work and reduce local job opportunities.
These are two key factors influencing population decline which in turn will negatively
impact the regional economy. 
Step 2.2 – Additionality assessment
[Statutory Guidance 3.63 – 3.71] 
The Scheme Guidance will reinforce the point that each subsidy should be assessed as
to the extent of the additionality of the assistance and the change in behaviour it will bring
about – that is, whether it is absolute (i.e. the project would not happen at all without the
subsidy) or if it is partial in terms of the scale or scope of the project, the quality of the
outcome or significantly bringing forward the timing.  The Council will follow its own
internal appraisal and recording procedures, however the scheme guidance will specify
that they must ensure their additionality assessment is proportionate for the level of
subsidy proposed and their rationale is clearly recorded. Ensuring a project meets the
eligibility criteria of any originating grant will also be an important part of due diligence
and consideration. The Council will normally include performance conditions as part of
their grant offers to ensure that projects are delivered in accordance with the application
and project plan – these usually include ensuring projects are completed within specified
timescales and reports on outcomes are provided. The Scheme Guidance will advise that
performance conditionality and monitoring requirements should be applied, but they
should be commensurate with the subsidy value and project risk profile. 
The beneficiaries eligible for subsidy under the scheme will mostly have a tightly defined
geographic focus therefore, when the scale or scope is affected, it is more likely to
influence the size or specification of a building project or the range of activities or users
that can be supported. Providing subsidy timeously to prevent project delays has become
increasingly important in recent years, especially in capital projects.  High inflation has
meant that delaying projects can lead to significant uplifts in construction tender prices
which can then put the price out of reach and risk the whole project. 
The scheme is eligible to all enterprises as defined in the act (7.1 – 7.5). As set out in the
statutory guidance (3.90) subsidy should be considered in terms of the size of the
recipient. It has been considered that the type of enterprise also has a significant potential
impact on the distortive nature of any subsidy. In line with the guidance (3.92) caps have
been set both as an absolute value and a proportion of costs (intervention rate). Given
the extent and nature of market failure, and the need to address significant policy
concerns in the area, it is often necessary to intervene at a high rate in order to deliver
viable projects. This is even more urgent in the context of an increasing reliance on grant
funding by many social enterprises, as well as challenging economic conditions. 
For this reason the cap for third and public sector bodies has been set at 100%,
recognising that subsidy should normally be the lowest amount possible to deliver the
change of behaviour desired by the policy objectives. For SMEs the percentages has
been capped at 80%. The statutory guidance suggests that “higher intervention rates (for
example, more than 70% of project costs) are more likely to distort competition and
investment within the UK, and international trade and investment”. Given the extent of
Page 313

Page 314

11
market failure in some areas and based on the experience of council officers in managing
previous subsidy, the maximum cap has been calibrated in order to ensure viable projects
can proceed. For large enterprises, the intervention is cappeded at 50%. This is to
recognise that subsidy to large enterprises is far more likely to have a distortive effect on
competition, particularly as they are far more likely to be traditing across a wider
geographical area, including internationally.  In all cases, individual subsidies are capped
at £10m, the limit beyond which subsides must be referred to the CMA. 
For projects assisted through Measure 1- Support for Capital Investment and Measure 2
– Support for Capacity Building, a high level of additionality is anticipated in all cases. The
Council and its partners have considerable experience of providing financial assistance to
social, private, and community enterprises and are confident that without the intervention
of the public sector these projects would either not proceed at all or be significantly
curtailed.  This would severely impede the growth of the enterprises and the social value
they deliver. Although there are windfarm community benefit funds available in some
areas and numerous private charitable trusts targeting various charitable activities, it is
rare that a project can secure 100% funding from private sources. Experience also shows
that a minority of social/community enterprises generate sufficient revenue and operating
profit to fully fund further development from their own resources, and they are unable to
service sufficient commercial or social enterprise borrowing. Similarly, many SMEs in the
area may struggle to receive private investment funding to deliver projects which have
significant community benefits. 
Measure 1 - Capital investment is aimed at supporting new investments for example: the
acquisition, redevelopment or expansion of land or buildings; fixtures, fittings, furniture
and equipment.  Only initial investment costs will be eligible under this scheme measure
to ensure that regular business-as-usual activity is not subsidised by this measure. 
Measure 2 – Support for capacity building is aimed at supporting “one-off” or discrete
projects with a defined start and end date rather than indefinite, ongoing running costs.
Examples might include training initiatives, professional adviser or consultancy fees, fixed
term project officers engaged to develop new project ideas, or existing staff for the time
assigned to a clearly defined project. While these projects may include staff costs and
overheads among the eligible costs, they will be distinguishable from business-as-usual
activity as the core activities of the organisations will not be dependent on them and will
not be funded through this measure. 
Measure 3 - Operating Support – will provide scope to support running costs and
operating losses on business-as-usual costs. This sort of subsidy is considered important
and justified to support the social and community enterprises that are the target audience
for the scheme, however, assisting running costs presents a greater risk of distortion than
other subsidies. The scheme has been designed to mitigate this by applying a lower
subsidy limit of £3m per annum to this measure. The Scheme Guidance will specify that
the council should carefully assess assistance using this measure and keep a record of
their justification and how this links to the scheme’s policy objective, for example:
• preserving a locally significant organisation or keeping services in the market; or
• necessary to overcome a specific business continuity event or economic shock;
and
• realistic financial projections demonstrating the organisation is capable of, or will
return to, being self-financing.
This scheme and measure are not intended to be used to prop up ailing and insolvent
enterprises as defined in Annex 5 of the Statutory Guidance.
Page 314

Page 315

12 
Step 3 – Proportionality and minimising distortion within the UK
[Statutory Guidance 3.72 – 3.108] 
Very few of the beneficiaries eligible for subsidy under the scheme will be operating in
markets beyond their local area.  A small number may offer goods or services online but
usually in niche markets such as Gaelic language or small volumes of goods in buoyant
market segments. The Council will assess the potential displacement impact of each
application and consider the following characteristics. 
3.1 The nature of the instrument [Statutory Guidance 3.80 to
3.82]
The scheme has been designed to allow a range of subsidy interventions including
free/subsidised services, direct grants, repayable grants or subsidised loans. The
justification for these forms of subsidy and exclusion of equity have been discussed at 1.2
setting out why direct provision and equity are not appropriate alternatives. The Council
and its partners, such as funding bodies, are experienced in undertaking funding options
appraisals as part of the due diligence to determine the least distortive and optimum
value for money solution to give a return on the public pound. Where loan is being
considered, the scheme guidance will require the Council to follow SI 2022 no. 1186 thein
calculating the subsidy value of the loan. 
3.2 The breadth of beneficiaries and the selection process
[Statutory Guidance 3.83 to 3.85]
The number of beneficiaries that will be eligible for subsidy under the scheme will be high.
The range of beneficiaries is extremely broad in terms of the product and service markets
they operate in, for example, tourism, culture and heritage, Gaelic language services,
training and employability services, social care, community land, forestry, transport and
housing and many more. Most will be micro or SMEs with a tiny minority classed as large
enterprises if they are ALOs or public authorities. The Council may use the scheme in
response to individual applications as well as for competitive calls for themed funding. In
all cases, each application will be assessed on its own merit against the council’s internal
funding criteria and strategic priorities, the criteria of any relevant grant-awarding body,
then the scheme criteria and contribution towards the policy objective. 
3.3 Size of the subsidy [Statutory Guidance 3.87 to 3.93]
Subsidies awarded under the scheme will vary in size. The largest proportion are
expected to be very small and under £100,000, with most small at under £1m but with the
potential to help some large projects. The latter are likely to involve projects where
cumulation of multi-agency public funding brings the combined funding to a higher level.
To support this assumption an analysis of Highlands and Island’s Enterprise’s subsidies
to the sector across the Highlands and Islands since January 2023 reveals that 83%
(117) were for amounts under £100,000, 14% (19) were between £101,000 and £1m with
just 3% (4) over £1m.  Awards under the scheme will be capped below £10m, the
Subsidies of Particular Interest threshold, and £5m for Subsidies of Interest in sensitive
sectors. In other words, no awards will be given through the scheme that involve a
mandatory referral to the CMA Subsidy Advice Unit for review. 
The size of the subsidies will, in general, be very small relative to the relevant product or
service market at a UK or international level. They may be more significant at a local
Page 315

Page 316

13
market level because they will primarily be plugging a gap or under-provision in that local
market. 
The larger subsidy awards given under the scheme are likely to be significant in relation
to the size of the recipient for the very fact that social and community enterprises in the
geographical region are predominantly SMEs and don’t have the earning or equity-raising
power of private sector enterprises; therefore, they require subsidy to support their
development. Subsidy becomes more critical to de-risk investments and incentivise the
change in behaviour the Council is seeking, to achieve the policy objective. 
3.4 Timespan [Statutory Guidance 3.94 to 3.97.]
The additionality section at Step 2.2 describes the three measures and main types of
subsidies that will be given under the scheme. It is anticipated that the majority of awards
will be give under Measures 1 and 2 which will be time-limited to the implementation
period for a capital project and a defined project period for a capacity-building support. 
Even with Measure 3 – Operating Support - the scheme conditions will not allow indefinite
or unlimited support for running costs. Delivery objectives for the period of support will be
clearly set out and financial assistance capped at the scheme limit per annum (see also
3.6). Where recurring subsidies are being considered, the scheme guidance will require
the Council to fully assess the displacement effect on existing competitors as well as
potential market entrants and record the outcome of their appraisal.  In addition the
Council will be required to assess and confirm that the subsidy provides the most efficient
means of achieving the policy objective. 
The scheme duration is set at ten years in anticipation that Argyll and Bute is likely to
continue to have a high reliance on the voluntary, non-profit-distributing and public
sectors to deliver essential community services, retain employment in disadvantaged
areas and maintain a wellbeing economy.  An interim review will be conducted after the
first 5 years of the scheme’s operation to measure its success and consider if it should
continue as it is, or be amended, be discontinued or replaced. 
3.5 Nature of costs covered [Statutory Guidance 3.98 to 3.99]
As discussed at 2.2 and 3.4 above, the type of costs supported through the scheme will
largely comprise support for one-off capital projects, initial investments to build capacity,
with a minority of investments covering operating costs which are potentially more
distortive.  The council also recognises that the scheme needs to include scope to
support running costs, where the intervention can be justified, and any displacement is
considered acceptable. 
3.6 Performance criteria [Statutory Guidance 3.100 to 3.101]
The council will follow its own internal performance management procedures and issue
the legal agreements typically used.  The council will adhere to the Scottish Public
Finance Manual (SPFM) which lays down certain conditions that should be attached to
grant offers including:
• Grants should be subject to binding agreements ring-fencing the subsidy for a
clear purpose.
• Grant offers should include standard conditions including schedules covering
claims and payment arrangements.
• Grant should not be paid in advance of need unless clearly justified.
• Grant payments should not normally be issued until the recipient has incurred the
expenditure and submitted a competent claim.
• Where grant is provided to acquire or improve capital assets, the grant giver’s
position should be protected in the event of disposal.
Page 316

Page 317

14
• Granting authorities are responsible for ensuring grants are spent for the specific
purpose they were awarded for.
• Practical and proportionate steps should be taken to monitor assisted
organisations progress in implementing the project and identify early warning
signs of project failure or costs escalations.
• Assistance to private sector organisations should be made on clear terms within
Subsidy Controls. 
Annex 2 of the SPFM provides a more detailed framework for performance monitoring
and financial control of third-party grants. The council will also follow local and national
guidance when providing funding such as the Public Pound Code of Practice and any
Community Wealth Building legislation or guidance which may become applicable during
the course of the scheme 
In addition to the above, the scheme guidance requires the Council to specify in grant
offers that the award is made under the scheme and which measure applies to the
subsidy.  This will enable recipients to make accurate declarations to other/future funders
to ensure the scheme’s cumulation thresholds are not exceeded. 
3.7 Monitoring and evaluation [Statutory Guidance 3.104 to
3.106]
Monitoring and evaluation of individual subsidies given under the scheme will be the
responsibility the council following its own internal policies and the SPFM framework. 
The method and timing of ongoing monitoring and evaluation will vary according to the
nature of the project assisted, the size of the subsidy, and the obligation period applied to
the assistance.  For example, following a large grant towards a capital project, in addition
to viewing the completed physical asset(s), there would be annual monitoring over a
number of years to check that the planning activities and outcomes resulting from the
investment are also being achieved.  In contrast, lower value support for a training project
would involve a shorter follow-up to confirm the numbers trained and applying their new
skills. 
As mentioned at 3.4, the intention is to evaluate the scheme at the end of year five to
assess whether it should continue, be adapted or close. An evaluation will therefore take
place no later than give years after the scheme commences. It will consider the following: 
• All subsidies awarded under the scheme by measure type and value.  The latter
being crucial to monitor the total value of awards against the overall scheme
budget.
• The number of unique enterprises assisted by legal entity type, market activity and
geographical location.
• The actual outputs and outcomes achieved compared to those planned.
• The contribution the scheme is making to the policy objective e.g.:
o New community and social enterprises start-ups supported.
o New jobs created and existing jobs preserved.
o Enterprise growth in terms of diversified activity, increased turnover.
• The experience of the council and partners of using the scheme – whether it is
proving more efficient and is it providing appropriate subsidy cover.
• Satisfaction levels of subsidy recipients and whether the enterprises are finding
any difference in accessing support. 
Page 317

Page 318

15
Step 4 – Balancing exercise
[Statutory Guidance 3.109 to 3.117] 
4.1 Negative effects 
The scheme is required because the new Limb D test relating to domestic competition is
capturing many more beneficiaries operating in markets which could potentially be
distorted. In practice, it is anticipated that there will be very few subsidies given where the
financial assistance could cause actual material harm to competitors. 
Based on historic trends and evidence from the 2021 SEC, a minority of beneficiaries are
likely to be involved in the production of goods.  These products will span several markets
and could be sold locally or beyond. The volume and value of products is so small in
comparison to the size of these markets overall, HIREP has not attempted to identify
every possible market and effect. In the SEC 2021, 4% of Argyll and Bute’s social
enterprises reported that they had exported within the last 12 months (up from 2% in
2017, but lower than the 2021 Scottish figure of 7%). (A+BC SEC 2021) It is reasonable
to assume that these are predominantly active within one or more fields of tourism,
heritage, festivals, arts or creative industries. For example, some Gaelic language and
music provision is available online as well as genealogy services. 
Most beneficiaries (68%) are providing mainly services, and 70-80% of these, within
localised geographies. The SEC 2021 data shows that 54% of Argyll and Bute’s social
enterprises operate within a single neighbourhood or community, 14% within a local
authority area, 10% across more than one LA area, 2% at a Scottish level, and 10% each
at a UK and international level. (A+BC SEC 2021) 
Many community and social enterprises are established to fill gaps where services don’t
exist or preserve services that are being withdrawn by the public or private sectors,
however, there is sometimes local competition or an element of activity which could
foreseeably overlap with alternative local provision. For example community centres or
village halls may be competing with local hotels or venues that have function space for
hire, community trusts/hubs renting out office space may have some local competition,
and a third sector early years and childcare (EYC) setting may be operating in an area
where there are school nurseries and childminders.  When it comes to community tourism
and cultural heritage facilities, they will often be competing alongside other community or
private provision for a share of visitors who have decided to visit Argyll and Bute. In many
small communities in Argyll and Bute, SMEs may be the only enterprise providing a
service locally or, be part of a small local economy which is a mixture of private and third-
sector enterprises, and where subsidy that acts to drive economic development or
tourism will across to benefit all enterprises and the wider economy, especially those
which deliver policy or strategic objectives. 
Community-led initiatives usually emerge through Local Development/Place Plans and
rarely spring up without a great deal of consultation by community activists to ensure local
support. In addition, applications for grant usually involve significant due diligence and the
creation of project or business plans or briefs. This enables the scope of projects to be
designed to mitigate harmful displacement as far as possible. 
4.2 Benefits of the subsidies and scheme 
Page 318

Page 319

16
These subsidies have proved successful in the past and are expected to continue to be
essential in supporting local economic development and community wealth building,
across a region with many of the most disadvantaged communities in Scotland and the
UK.  They stimulate a wide range of investments including: 
• Continuing the region’s proud history of community-led development and action. 
Local decision-making is fundamental to a successful place-based approach to socio-
economic development and a powerful mechanism for population retention.
• Supporting communities and entrepreneurs to design, develop and start-up new
ventures in response to local needs and opportunities.
• Helping enterprises to grow, diversify and seek appropriate commercial opportunities
to ensure their financial sustainability.
• Building the capacity and resilience of community organisations through access to
professional advice and training and implementing efficiencies – whether that be
energy efficiency measures or adoption of digital technologies.
• Providing key local services and facilities that are the lifeblood of thriving communities
– everything from village halls and sport facilities, preserving built heritage, social
care, housing and cultural activities – and are essential to attract and retain
population.
• Creating valuable local employment 
• Preserving and exploiting our unique cultural heritage and identity by promoting the
Gaelic language, celebrating our music, interpreting our rich history and archaeology
and advocating responsible enjoyment of our natural landscapes.
• Nurturing a more inclusive economy for the wellbeing of communities and health of
the environment. 
The key benefit of this scheme will be increased efficiency and compliance with the UK
Subsidy Control regime. It will provide a simplified route to the Council for awarding low-
risk subsidies.  As indicated in previous sections this means being able to support
organisations across a broad spectrum of sector activities and often with high
percentages of subsidy.  A fundamental aspect to achieving the efficiencies is reducing
the additional work (and time) involved in making standalone awards and preparing
Subsidy Principles Assessments. In some cases these have been for subsidies below
£10k, presumably where the beneficiary has no Minimal Financial Assistance available.
This scheme is part of a suite of schemes developed by the Highlands and Islands
Regional Economic partnership, which will be registered by relevant Pas in future.
Although each scheme is slightly different to be best-suited to the relevant organisation, it
will be much easier for different funders to cooperate and agree the subsidy approach
given the commonalities between these schemes. 
This aligned approach will simplify and streamline the process for beneficiaries applying
for subsidy and provide them with greater assurance that the subsidy being offered is
compliant. It should reduce instances where funders are seeking vastly different levels of
information and result in quicker decisions on funding applications. 
4.3 Why negative effects are outweighed 
The Council considers that these subsidies will have very little foreseeable harms on
international or UK competitors and local displacement will be carefully assessed to
ensure it is low and manageable.  The geographical scope of the scheme is wide due to
the large-land mass of Argyll and Bute, however most subsidies will be awarded to
support activity that will have a purely local impact. Recognition of the need to support
areas lagging behind has been evidenced by the previous UKG commitment to “levelling
Page 319

Page 320

17
up” and ring-fencing of Shared Prosperity Funds and as well as the shared investment
between Scottish and UK Governments in Growth Deals of which the scheme area has
benefitted, including the Rural Growth Deal for Argyll and Bute. The current Government
has confirmed it will honour these commitments until they establish new regeneration
programmes. 
The opportunity costs and distributional impacts are mitigated by budget constraints and
the competing priorities PAs are faced with. 
The SEC 2021 demonstrates the important contribution the social enterprise sector
makes to the economy of Argyll and Bute with £47.3m GVA added in 2021, supporting
1,482. The sector is mature and strong with Argyll and Bute’s social enterprises having an
average age of 22 years - 81% have been operating for over 10 years while 7% are
young enterprises less than 5 years old. (A+BC SEC 2021) However they are more
reliant on grant support than their counterparts across Scotland. 
Without the social enterprise sector delivering vital local services and contributing to the
cultural, social, health and economic wellbeing of our communities, the region will fail to
stem the predicted depopulation and retain vibrant neighbourhoods. 
In the foreword to Scotland’s Social Enterprise Action Plan 2024-2026 Tom Arthur,
Minister for Employment and Investment, said in November 2024 “The latest social
enterprise census confirms that the number of social enterprises in Scotland is growing
and operating in sectors right across our economy. Social enterprises are contributing to
fair, green growth with purpose: to create good jobs and promote fair work, to eradicate
child poverty and improve living standards, and to boost tax revenues and sustain high-
quality public services” 
Page 320

Page 321

18 
APPENDIX 1 – Map of scheme area 
Geographical scope of the scheme
The geographical area covered by this scheme is shown in the map below. It covers the area of Argyll and
Bute local authority. The local authority is the second largest in Scotland, covering around 9% of Scotland’s
landmass. It is bounded by the Clyde and Loch Lomond to the east, the Mull of Kintyre to South, Atlantic
Islands to the West, and the Sound of Mull and Appin to the North. It includes 23 inhabited islands, more
than any other local authority. Its geography of long sea-lochs and peninsulas give it an extremely long
coastline, and create unique challenges for organisations, public, bodies and enterprises operating in the
area. 
Page 321

Page 322

19 
APPENDIX 2 – Reference links and summary
statistics table 
The Principles Assessment has drawn on the following references to evidence the need for
the scheme. 
• Social Enterprise in Scotland – Census 2021 (published 2023)
• 2021 Social Enterprise Data for the highlands and Islands Region
• Scottish Human Rights Commission – Economic, Social and Cultural Rights in the
Highlands and Islands Nov. 2024
• OECD Rural Discontent Nov 2024
• Scottish Government review Developing Scotland’s Economy: Increasing The Role Of
Inclusive And Democratic Business Models September 2024 
• Social Enterprise Driving a wellbeing economy for Scotland – Action Plan 2024-26
Scottish Government
• Institute of Fiscal Studies Report on Employment and Earnings in Scotland Oct 23
• HIE Rural and Regional Disadvantage in the H&I May 2022
• HIE submission to UK parliament on cost of living and rural communities June 2023
• Cost of living: impact on rural communities in Scotland  Scottish Affairs Committee UK
Gov first report 2023-24
• Scottish Gov The cost of remoteness – higher living costs and fuel poverty September
2021
• HIREP Regional Economic Strategy – Draft June 2024
• Scottish Government report on Short Life Working group on Economic and Social
Opportunities for Gaelic (published June 2023)
Page 322

Page 323

Environment, Development and Infrastructure Committee Work Plan 2025/26 
This is an outline plan to facilitate forward planning of reports to the Environment, Development and Infrastructure Committee. 
Date  Title Service/Officer Date Due Comments
11 September 2025 
Transformational
Projects and
Regeneration Team
– Large Scale
Project Update
Report
Development and
Economic Growth
19 August 2025 
Registration of an
Economic
Development
Subsidy Scheme to
Facilitate
Compliance with
Post-EU Subside
Control Legislation 
Development and
Economic Growth
19 August 2025 
Argyll and Bute
Council’s Economic
Strategy Action
Plan: 2025-28
Development and
Economic Growth
19 August 2025 
Economic Growth
TEAM Activity and
Outcomes for
2024/25
Development and
Economic Growth
19 August 2025 
Winter Service
Policy 2025/26
Roads and Infrastructure
Services
19 August 2025 
Pavement Parking
Prohibitions –
Service Procedure
& Exemptions 
Roads and Infrastructure
Services
19 August 2025 
Page 323
Agenda Item
16

Page 324

Environment, Development and Infrastructure Committee Work Plan 2025/26 
Review of Roads
and Infrastructure
Services – Update 
Roads and Infrastructure
Services
19 August 2025 
Trunk Road Litter
Management
Responsibilities
A82, A83, A85,
A828
Roads and Infrastructure
Services
19 August 2025 
Local Flood Risk
Management Plans
– S37 Interim
Update 
Roads and Infrastructure
Services
19 August 2025 
Temporary Traffic
Regulation Orders –
Review of Charging
and Advertising 
Roads and Infrastructure
Services
19 August 2025 
A816 Ardfern
Permanent Repair
Solution Update
Roads and Infrastructure
Services
19 August 2025 
Waste Collection
Policy and
Operational
Updates
Roads and Infrastructure
Services
19 August 2025 
18 December 2025 
Annual Status and
Options Report
(ASOR)
Roads and Infrastructure
Services
25 November 2025 
Community
Empowerment
(Scotland) Act 2015
- Allotments Waiting
List Register
Legal and Regulatory
Support
25 November 2025 
19 March 2026     
Transformation
Projects and
Development and
Economic Growth
24 February 2026 
Page 324

Page 325

Environment, Development and Infrastructure Committee Work Plan 2025/26
Regeneration 6
monthly update
report 
Annual Status and
Options Report  
Roads and Infrastructure
Services
24 February 2026 
18 June 2026     
Waste Update Roads and Infrastructure
Services
26 May 2026 
Future Items     
Shared Prosperity
Fund
Development and
Economic Growth   
Roads Development
Framework 
Roads and Infrastructure
Services 
EVC Tariffs Roads and Infrastructure
Services 
Agreed 21.03.24 
Footway
reconstruction
Programme
Roads and Infrastructure
Services 
Cemetery Asset
Update
Roads and Infrastructure
Services   
Active Travel
Strategy
Development and
Economic Growth   
Page 325