Transformational Projects and Regeneration Team - Large Scale Project Update Report

Argyll and Bute Council · 11 September 2025
Back to Environment, Development and Infrastructure Committee — 11 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
11 SEPTEMBER 2025 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
1. EXECUTIVE SUMMARY
1.1 The purpose of this report is to update the Environment, Development and
Infrastructure Committee on current progress of the large-scale, externally
funded project work of the Transformational Projects and Regeneration Team,
and to highlight key issues that may impact on the successful delivery of
projects. 
1.2 The last update report was considered by Environment, Development and
Infrastructure Committee in March 2025. 
1.3 The team is currently responsible for the delivery and or management of
projects and associated grants with a cumulative value of over £100m. The
associated grants the team manages are listed in Appendix A. It should be
noted that following completion of each project, the team continues to have the
responsibility for the monitoring and final drawdown and reporting up until the
end of the 12-month defects period or beyond depending on conditions on the
respective grant contracts. 
1.4 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s Rural Growth Deal (RGD)
Programme.  This follows the merging of this team with the RGD Programme
Management Office (PMO) following the retirement of the previous
Transformation Projects and Regeneration Manager. 
1.5 The team are also leading on the emerging Community Regeneration
Partnership Funding (CRP) from the UK Government.  This funding replaces
the Levelling Up Partnership programme and totals £20.34m for Argyll and Bute
with all funding requiring to be fully committed by 2026/27.  It is anticipated that
the UK Government will officially confirm projects to be funded via the CRP
programme in September 2025. 
1.6 The Council welcome the Scottish Governments commitment to continue both
the Regeneration Capital Grant Funding (RCGF) and Place Based Investment
(PBI) funding in 2025/26 following their suspension by the Scottish Government
in 2024/25 due to budget challenges.  Further detail of successful projects is
included in paragraph 4.8 of this report.

Page 2

1.7   Members are asked to note that the grant funding landscape and delivery of
capital projects remains extremely challenging due to cost of living issues,
budget and resource constraints however, the Transformation Projects and
Regeneration Team will continue to respond to emerging Government policy
priorities and future external grant, funding opportunities. 
RECOMMENDATIONS
It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Consider the current progress contained within the report.
ii. Note that further updates relating to pending funding bids will be brought
back to the Environment, Development and Infrastructure Committee in due
course to update Members.

Page 3

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
11 SEPTEMBER 2025 
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE
SCALE PROJECT UPDATE REPORT 
2.0 INTRODUCTION
2.1 This report sets out the current position of the large-scale projects, which are
currently being delivered on the ground, or have secured external grant funding
that are managed by the Transformational Projects and Regeneration Team. 
2.2 The Transformational Projects and Regeneration Team sits within the Council’s
Development and Economic Growth Service and works region-wide. The team
has a particular focus on ‘place’, heritage regeneration, the creative industries,
renewables and Islands and manages a diverse range of capital projects and
external grants.  The team works closely with colleagues across the Council,
communities, businesses, public agencies, third sector organisations, town
centre heritage building owners and the owners of vacant business property to
realise positive change for our communities. 
2.3 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s Rural Growth Deal (RGD)
Programme and are leading on the emerging Community Regeneration
Partnership (CRP) Funding from the UK Government.   
2.4 CRP funding replaces the Levelling Up Partnership programme and totals
£20.34m for projects in Argyll and Bute with funding to be fully committed by
2026/27. 
2.5 The team’s work broadly includes the following areas:- 
• Developing and submitting bids to secure external funding of various
scale through a competitive process, such as the new Heritage and
Place Programme, previously referred to as the Conservation Area
Regeneration Scheme (CARS) programmes;
• Development and delivery of regeneration projects with a particular
emphasis or theme, such as the suite of measures to encourage
shopping locally;
• Development and delivery of several place-based engagement projects,
working in partnership with the community and key partners, leading to
action plans, such as charrettes, and working with communities to
realise these community ambitions; 
• Development of the economic opportunities for Argyll and Bute across
Film, Creative Industry and Renewable sectors, with the objective of

Page 4

securing income into the area and delivering local economic benefit,
including support to community organisations working across these
sectors. This work also includes the setting up and management of the
Argyll and Bute Renewable Alliance (ABRA) with partners in HIE; 
• Support to third sector organisations involved in the delivery of their own
individual community led economic regeneration projects, as well as
support to third sector organisations delivering regeneration focused
projects where Council funding is involved and/or where projects align
with Council outcomes, such as Regeneration Capital Grant Funded
(RCGF) project funding;
• Drafting and submitting external funding bids to competitive calls such as
the Island’s Programme, RCGF and Carbon Neutral Islands Programme; 
• Development and administration of the Argyll and Bute Council’s
Strategic Events and Festivals Fund for which 12 grants have been
awarded for Round 7 (2025/26);
• Progressing the offer to host the 2028 Royal National Mòd (RNM);
• Overseeing the delivery programme and financial administration of
projects supported through funding from Scottish Government, such as
annual Crown Estate (CE) funding and the Place Based Investment
Programme (PBI);
• Working closely with the SG Islands team and working with colleagues
and communities in the development of bids to the Islands Programme
(IP) and associated Carbon Neutral Islands funding.
• Supporting the owners of empty business properties through grant aid
funded by NDR income.
• Development and delivery of projects within the Council’s RGD
programme and Community Regeneration Partnership. 
2.6 This paper also seeks to report on key issues that may impact on the current
status of each project, such as any amendments to project scope or timeframe. 
2.7 The large-scale projects currently in delivery, either directly by the team,
colleagues across the Council or by a third party and where the team is
responsible for managing the associated grant, are included within the table in
Appendix A, and have a cumulative total value of over £100m. The individual
projects being taken forward under PBI and CE are not listed individually in
Appendix A. 
3.0 RECOMMENDATIONS
3.1 It is recommended that the Environment, Development and Infrastructure
Committee:- 
i. Consider the current progress contained within the report.
ii. Note that further updates relating to pending funding bids will be brought
back to the Environment, Development and Infrastructure Committee in due
course to update Members.

Page 5

4.0 DETAILS
4.1 The following sections summarise the progress associated with each of the large-
scale projects that are currently in delivery or have grants managed by the
Transformational Projects and Regeneration Team. In addition, the report
provides information on annual funding streams received by the Council and
managed by the team as well as annual competitive external funding grants
secured and being managed. The individual projects are listed in Appendix A
with the exception of those individual projects supported through PBI and CE. 
HERITAGE LED REGENERATION PROJECTS 
4.2 Rothesay Regeneration 
Following a decade of Townscape Heritage Initiatives, and £7.5m investment in
the town centre, regeneration effort continues to tackle dereliction in Rothesay.
The Transformation Projects and Regeneration Team are actively supporting
efforts to address key landmark buildings including:- 
• £9m of RGD funding allocated to Stages 2 and 3 of Rothesay Pavilion. 
• Supporting local social enterprise with funding applications to HES, a
condition survey and business plan for the Royal Hotel;
• £40k of CE funding allocated for demolition of vacant building on Albert Pier.
A further £100k of funding allocated via PBI for resurfacing and lining works
on Albert Pier with a focus on enhanced parking for coaches.
• Up to £4m of funding via the UK Government’s Community Regeneration
Partnership to support the regeneration of the Royal Hotel in Rothesay
(subject to approval of UKG).  Partnership project with George Hanson, HIE,
and UKG.  Funding application made to Scottish Governments Islands
Programme for £400k to support pre-construction phases of this project. 
4.3 Helensburgh CARS (2021 – March 2026) 
Helensburgh CARS is a £2.4m project in final year of delivery. The partnership
project is funded by Argyll and Bute Council (£500k) and HES (£1.24m) with
owner's personal contributions completing the funding.  A fully funded project
officer is employed to deliver the project for its duration, and the project also
supports a modern apprentice. 
Works to the first two priority buildings commenced on site in September 2024
and will be completed later this year. Works to the third and fourth priority
buildings, at the time of writing this report, are due to commence in August
2025. One small repair grant has also been awarded to refurbish the windows
in the Grade A listed Macintosh Club and another for roof and amenity deck
repairs to make several commercial properties within 22-34 Sinclair Street
watertight.   
Two shopfronts are complete. Two lime mortar training courses have been
held, and a modern apprentice position was filled in September 2024. An online

Page 6

webinar co-hosted with Under One Roof aimed at property owners in
Helensburgh is scheduled for October 2025. This will give expert advice and
guidance on owner's associations, common repairs and how to deal with issues
that arise from absent owners and missing shares with a Q&A session.       
4.4 Lochgilphead CARS (2020 – Mar 2026) 
Lochgilphead CARS is a £2.2m partnership project with HES (£969,700) in its
sixth year of delivery.  The project is due to conclude in March 2026. 
Four priority building projects have been completed and work is progressing
well on another two.   
A number of small repair grant/shopfront improvement projects have also been
delivered.  This includes three significant shopfront reinstatement projects that
were completed in July. 
Local stakeholders are benefiting from a number of traditional skills training
courses and educational activities that have been funded and delivered via the
scheme. This includes; specialist training in Lochgilphead for local contractors
and building professionals; traditional skills Demo Days for local school pupils
and a Shop Window Art Project delivered in partnership with a local artist and
Lochgilphead High School. 
4.5 Tarbert Heritage Regeneration Scheme (TBC) Project status 
On 26 June 2025, Council agreed that applications be submitted to National
Lottery Grants for Heritage (NLHF), and Historic Environment Scotland’s
(HES), Heritage and Place Programme (HPP), for a 5-year Tarbert Heritage
Regeneration Scheme.  Bids will be submitted on 6th and 29th August 2025
respectively, with decisions expected in January 2026.  Both are subject to a
competitive process and as such a delivery phase is not guaranteed. The
application to NLHF is for £850,000 and the application to HES is for £999,997. 
WIDER REGENERATION FOCUSED PROJECTS 
4.6 Tarbert / Lochgilphead Regeneration Fund 
In its 2016/17 budget, Council allocated £3m from reserves to support
regeneration and economic development in the settlements of Tarbert,
Lochgilphead and Ardrishaig. 6 projects were identified to proceed to Full
Business Case (as ratified by Policy and Resources Committee on 19th
October 2017).  The following projects are complete: 
• Gleaner (Phase 1 only) - completed summer 2019.
• Tarbert Harbour – shore side facilities completed in May 2019, car park
completed in March 2021.
• Barmore/Garvel Road junction improvements - completed February

Page 7

2020.
• Colchester Square/Argyll Street, Lochgilphead – completed May 2021.
• Lochgilphead Front Green – completed August 2022.
• Ardrishaig North Public Realm – completed April 2023. 
The only remaining allocation of funding relates to a second phase of
development on the former Gleaner Oil site in Ardrishaig.  This funding totals
£250,000 and we have had discussions with Scottish Canals about bringing
forward a business case for approval 2025/26. Scottish Canals are in
negotiations with a potential private sector developer which could result in a
significant private sector investment for this part of Ardrishaig. 
4.7 Regeneration Capital Grant Funding (RCGF) 
An update on the current RCGF projects is provided below and is followed by a
table of all current grant contract awards (Table 1) 
• Port Ellen Community Hub, Islay – the additional funding, reported in
the last update, has enabled works to recommence and the project is
progressing towards completion, expected late Summer 2025.
• Kilmory Business Park, Lochgilphead – work is progressing with
M&K MacLeod on the proposed Kilmory Business Park.  Works are on
site and are expected to be completed in December 2025.  This public
investment has also attracted signficant private sector investment.
• Aros Waterfront Development, Mull – outdoor activity hub – a
contract was awarded in January 2024 and works are ongoing. 
Table 1 – RCGF Grant Projects 
RCGF Project Grant
Awarded
Year
Awarded
Balance
Remaining /
Yet to Drawdown
Port Ellen Community hub, Islay  £1,046,223 2021/22 £0
Kilmory Business Park in
Lochgilphead 
£829,000 2021/22 £581,988
Ulva Ferry Shore Facilities Building -
Doras Caolas Ulbha
£602,590 2022/23 £3,671
Aros Waterfront outdoor activity hub £403,500 2023/24 £0
Nonhebel Light Industrial Park
Expansion
£654,000 2023/24 £1,948
Fyne Futures Local Food Production
and Training Centre, Bute
£250,000 2025/26 £250,000
Isle of Luing Community Owned
Slate Quarry
£1,747,936 2025/26 £1,747,936     
The following stage 1 expression of interest applications were submitted to the
Scottish Government in June 2025 for consideration for RCGF funding in
2026/27.  It should be noted that the RCGF funding process is undertaken in 2

Page 8

stages.  Projects that are successful at Stage 1 will go forward to the more
detailed Stage 2 application process for submission in Autumn 2025. 
Table 2: RCGF 2026/27Stage 1 Funding Bids 
Project Value Lead Organisation 
Kintyre Sea Sports  £800,000 Kintyre Sea Sports
Lighting Up the Shore
Station - A Sustainable
Hub for Tiree  
£760,000  The Hynish Trust
Nonhebel Park (Final
Phase)
£595,000 MICT
Sonas Childcare £900,000 South Islay Development
Tarbert Harbour
Community Water
Sports and Activity Hub
£850,000 Tarbert Harbour
Authority
Tighnabruaich
Community Refuelling
and Business Hub
£120,000 The Tighnabruaich
District Development
Trust 
The confirmation of potential RCGF monies in 2026/27 is welcome as this has
been an important source of external capital funding for both the Council and
community projects over the past decade. We await further notification as to
whether RCGF funding will be available in future years.  
4.8 Scottish Government Place Based Investment Funded projects 2021 – 2024 
When Place Based Investment (PBI) funding was introduced by the Scottish
Government, allocations were provided over a five-year period and to date
have been received as follows.  
• 2021/22 - £821,000 
• 2022/23 - £712,000
• 2023/24 - £496,000 
Unfortunately, the Council’s 2024/25 allocation of £496,000 was not made
available. Following further consideration by the Scottish Government the
council has now been informed that PBI will be made available for 2025/26.
This will be provided in 2 tranches with £388,368 of funding in tranche 1 and a
further £107,632 later in the financial year subject to the Scottish Governments
budget position.  
Table 3 below, sets out projects to be delivered using PBI funding in 2025/26. 
These projects were endorsed by the Council’s P&R Committee in August
2025.

Page 9

Table 3: 2025/26 PBI Projects 
Project Tranche 1  Tranche 2
Albert Pier  £100,000  
Victoria Hall,
Campbeltown
£100,000  
Shopfront and
Business Support  
£56,000
CCTV Upgrades  £100,000  
Helensburgh Outdoor
Museum
£80,000  
Rockfield Centre,
Oban  
£60,000
TOTAL £380,000 £116,000 
4.9 Scottish Crown Estate Revenue Allocation Funding 
In financial year 2024/25 the Council received Crown Estates funding totalling 
£1,818,715.  The Council is still awaiting confirmation of the allocation for this
financial year (2025/26) and it is unclear as to when formal written notification
will be received from the Scottish Government. However, based on previous
years allocations, a prudent estimate of £0.8m of anticipated funding in 2025/26
has been assumed and the projects set out in Table 4 will be considered by the
Council’s P&R Committee in August 2025.   
Table 4: 2025/26 Crown Estates Projects 
Project Delivery by Crown Estate
Allocation
Inveraray Avenue Screen
refurbishment 
Development & Economic
Growth 
£120,000 
Gallanach Road - Rock Slope
Protection
Road and Infrastructure
Services  
£300,000 
Tarbert Heritage and Place
Programme - Match Funding
(note this was agreed by Council
in June and is noted here for
information) 
Development & Economic
Growth
£115,000 for the
next 4 years*
CARS Projects - flexible fund to
support businesses with capital
improvements to
shopfronts/buildings building on
previous CARS investment 
Development & Economic
Growth
£150,000

Page 10

Victoria Hall, Campbeltown –
repair and refurbish entire front
elevation.  
Development & Economic
Growth
£50,000
Dunoon Public Realm  Development & Economic
Growth 
£65,000
TOTAL   £800,000 
4.10 Scottish Government Islands Programme and Carbon Neutral Islands
Capital Fund 2025/26 
The Scottish Government has announced that Islands Programme funding of
£5.3m will be available for the 2025/26 financial year to fund capital projects on
inhabited Scottish islands. A further £1.4m is available to support the Carbon
Neutral Islands (CNI) in their progression towards net zero.  Both of these funds
are subject to a competitive bidding process. 
Following approval of the following Island’s Programme Funding bids by EDI
Committee in June 2025, the following applications were submitted in July:- 
Table 5: 2025/26 Islands Programme Funding Bids 
Project Name - description Project Lead IP funding
request
Total project
value
Former Royal Hotel,
Rothesay – Detailed design
works
Transformation
Projects and
Regeneration
£400,000 £7,600,000
Community Digital Hubs
Phase 2
Strategic
Transportation
£125,000 £125,000
Unlocking Ulva – Landing
Craft Project 
North West Mull
Community
Woodland
Company
£536,020 £536,020
Skerryvore Lighthouse Shore
Station - The Lighthouse
Cottages
Hynish Trust £306,050 £330,050 
In addition to the Island’s Programme, a £1.4m Carbon Neutral Island Capital
Fund was announced for 2025/26, also previously considered by EDI
Committee. Funding bids have been submitted for the following projects: 
Table 6: 2025/26 CNI Funding Bids 
Project Name - description Project Lead CNI funding
request
Castlehill Solar Array Expansion IET £195,000
Additional Measures - Community
Buildings Phase 2
IET £401,843

Page 11

Further updates on the funding bids set out in Tables 5 and 6 will be brought
back to a future meeting of the EDI Committee following the outcome of the
Scottish Governments Investment Panel in August.   
4.11 Scotland Loves Local Projects Oct 21 – 2025 
Argyll and Bute Gift Card - The gift card for Argyll and Bute formally launched in
October 2021. To date, over 350 Argyll and Bute businesses have registered to
accept the card as a means of payment for goods and services. The Council
has continued to issue cards to eligible islands households supported by the
Scottish Government’s Island Cost Crisis fund.
.
Inclusive of the LACER funded cards, as of 31 July 2025, a total of £990,825
has been redeemed through the gift card. 
Funding for the Gift Card has now been expended and we are in the process of
assessing the anticipated costs and benefits of continuing with the scheme, a
separate report will be provided to Policy and Resources Committee in due
course. 
4.12 Islands Cost Crisis Emergency Fund 2025 
On 6 May 2025, the Scottish Government announced that Islands Cost Crisis
Emergency funding (ICCEF) of £1 million would be available for the 2025/26
financial year. The funding will be distributed to the six Local Authorities with
responsibility for islands through the 2025/26 Local Government Revenue
Grant.  The fund will be administered by Scottish Futures Trust (SFT) on behalf
of the Scottish Government. 
The funding for Argyll and Bute Council is £145,000 for financial year 2025/26. 
The Council’s P&R Committee endorsed the project options for this funding in
August 2025 and table 7 below, sets out the proposed funding allocation; 
Table 7: ICCEF 2025/26 Allocation  
ICCEF 2025/26 Distribution 
Targeting Fuel Poverty with ALI
energy’s Affordable Warmth Service
£120,000
Food Bank Grants   £25,000
TOTAL ICCEF 25/26 £145,000 
The proposed funding allocation will increase vital funding support to 5 island
food banks.  The Council are also intending to trial a scheme working in
partnership with ALI energy to extend their Affordable Warmth service.  This
supports residents most at risk of fuel poverty and the scheme will be
available to residents on all our island communities.  Fuel poverty rates are
generally higher on Scottish islands and this is exacerbated in households
with low incomes.

Page 12

4.13 Helensburgh Former Skating Pond (Skating Pond) Feb 2025- May 2026 
Helensburgh Former Skating Pond is a Local Nature Conservation Site and
part of the open space protection area which forms part of the Green Network
and Core Path Plan in the Green Belt bordering Helensburgh.  It is regularly
used as a walk/part of walks however over time the Skating Pond itself and
other areas within the site have become filled with invasive species.  In addition
the paths, built circa 2000 require repair and improvement. 
The site is owned by Argyll and Bute Council who have £50k funding from the
Nature Conservation Fund to consider how to improve and address issues of
management and maintenance of the site for public access, as well as
providing opportunities for environmental interpretation and learning
opportunities.  It is recognised that there is not enough funding to undertake
any capital works at this stage and that an initial assessment of the site is
required first.  To this end, consultants have been appointed and interim
findings produced as well as first stage community consultation and
engagement with local primary schools.   A final report with preliminary costs
will identify a preferred option for consideration. 
5.0 RURAL GROWTH DEAL     
5.1 The Rural Growth Deal Full Deal Agreement was signed on 10th March 2025
by the First Minister, Secretary for State for Scotland and the Council Leader.
The RGD will deliver £50m of investment from the Scottish and UK
Governments for projects that are a driver for inclusive and transformational
economic growth across the region.  The Council and key delivery partners
will also provide a minimum of £20m of match funding throughout the 10-year
Deal programme.    
5.2 The Rural Growth Deal has now entered year 2 of a 10 year programme of
project delivery. A total of £1.6m has been claimed from Government since
March 2025. The claimed funds all relate to the renovation of Rothesay
Pavilion, which remains the only project to have a Full Business Case
endorsed by central government.
5.3 A total of £6,025,000 has been awarded from Government for FY2025/26. Up
to £4m of this is allocated to the renovation of Rothesay Pavilion, with Kintyre
Sea Sports and Enabling Worker Accommodation projects receiving £1m
each and £25,000 for Highland and Islands Enterprise’s Business Skills
programme. These projects are developing their Full Business Cases for
appraisal by Government. 
5.4 It should be noted that no Rural Growth Deal funding can be drawn down in
advance of endorsement of full business cases by Central Government.  This

Page 13

process can take up to 9 months to complete and requires RGD partners to
spend project development funding at risk.
6. COMMUNITY REGENERATION PARTNERSHIP
6.1 In the 2024 Autumn Statement the UK Government committed to delivering a
package of support to Argyll and Bute Council in order to improve outcomes
across the region in line with the Government’s core missions and priorities. 
Community Regeneration Partnership Funding will build upon previous work
and engagement undertaken by the Ministry of Housing, Communities and
Local Government (MHCLG) under the banner of Levelling Up.
6.2 As part of the core funding package, there is up to £20m capital funding and
£250k revenue available for the CRP. Funding is profiled for payment in
financial year 2026-27 and is subject to business case approvals by UKG
Ministers. A further capacity payment of £45k will be provided to support staff
resourcing. This will be paid in FY25-26 and follows a separate capacity
payment which was transferred at the beginning of FY24-25.
6.3 A draft list of priority projects was approved by the Council’s P&R Committee
on the 20th February 2025 and this has formed the basis of negotiations with
the UK Government. Civil servants have also undertaken local engagement
with a number of external stakeholders and community groups during spring
2025.  UK Government officials are currently drafting the programme level
business case which will require ministerial approval prior to an official funding
announcement.  The Council have been advised that the UK Government
hope to confirm successful projects in September 2025 (subject to approval of
the business case). 
6.4 Further updates will be brought back to the EDI Committee in the next project
update report.
7. EMPTY BUSINESS PROPERTY GRANTS
7.1 Empty Property Relief was devolved to Scottish Local Authorities on 1 April
2023. At their meeting of 23 November 2023, Council subsequently agreed
that from 1 April 2024, 50% Non-Domestic Rates (NDR) relief could be
granted to business properties which are empty for a maximum of three
months.  In cases where business properties remain empty beyond three
months, 10% relief can be awarded for up to an additional nine-month period.
Following this, should a business property remain empty beyond a twelve-
month period, no further NDR relief would be awarded, and 100% Non-
Domestic Rates would begin to be charged. 
7.2    On 23 November 2023, Council also agreed that the remaining Empty Property
Relief funding from Scottish Government be used towards an Empty Property
Business Grant Scheme, the aim of which would be to assist owners to return
properties to productive use. An Empty Business Property Officer has since
been appointed to support the distribution of funds, which amount to in the
region of £300k for 2025/26.

Page 14

7.3 On 8th May 2025, the council’s Policy and Resources Committee approved 
Extended Empty Property Relief, whereby non-domestic rates relief will be 
extended for property owners who are actively working to bring their
properties back into use. Owners may apply for 100% relief for up to 12 
months at any time after the property becomes vacant, provided the 
conditions are met. 
7.4  A further paper providing an update on the Empty Business Property grant 
scheme was presented to the EDI committee on 19th June 2025. The 
committee approved the Empty Business Property Grant Scheme with an 
anticipated budget of up to £785,000 for the financial year 2025/26. 
7.5 Members are asked to note that the number of vacant business properties is 
now being recorded as part of the Councils Area Performance Reporting.   
7.6 At this time, Scottish Government funding is not committed beyond 31 March 
2026 and Scottish Government will have to review arrangements for devolved  
Empty Property Relief prior to financial year 2026/27. As a result, a further 
update on Empty Business Property Grants will be brought back to the EDI 
Committee in due course. 
8.  CONCLUSION 
8.1 This report provides an update to the Environment, Development and
Infrastructure Committee on progress with large-scale, externally funded
project work being delivered by the Transformational Projects and
Regeneration Team.  Currently this involves over £100m of external funding
across Argyll and Bute with further bids in progress. 
8.2 The projects and grants detailed within this report will result in assisting the
economic recovery of Argyll and Bute, helping to sustain numerous small
businesses, community organisations, making our places more investor ready
and improving our towns and villages as places to live, work and visit. 
8.3 From April 2024, The Transformation Projects and Regeneration Team also
includes responsibility for delivery of the Council’s RGD Programme and the
team are also managing the emerging CRP programme.  Combined, these
programmes will deliver in excess of £70m of external funding to the region.   
8.4 Members are asked to note that the grant funding landscape and delivery of
capital projects remains extremely challenging due to budget and resource
constraints however, the Transformation Projects and Regeneration Team will
continue to respond to emerging Government policy decisions and future
grant funding opportunities.

Page 15

9. IMPLICATIONS
9.1  Policy - The delivery of these projects fits with the Council’s Corporate Plan,
Argyll and Bute Local Outcome Improvement Plan and the Economic
Development Action Plan. The economic outcomes from this project will
contribute to the Government’s Economic Strategy. 
9.2  Financial - All funding has been approved for the projects detailed in the
report. The funding comes from the Council and from external funding
sources, some from highly competitive processes.  We will continue to review
costs and assess budgets. 
9.3  Legal - Each project will have differing legal and procurement requirements
depending on the grant funder and the associated grant contract conditions
and we are working closely with colleagues to identify the support required
and to allow this to be factored into future work plans. 
9.4  HR - The resources required to deliver the projects will be continually
monitored. The management of these externally funded projects as well as
the management of the Council, PBI, CE, IP and RCGF grants requires a
significant amount of resources from the team to ensure that all the necessary
due diligence and financial management is undertaken and risk is minimised
to the Council. 
9.5  Customer Service – None 
9.6 Risk - Construction projects by their very nature are challenging given issues
that can arise relating to site conditions, managing contractors/the design
team and associated budgets and meeting funder’s requirements. We
continually seek to minimise the risk through strong project management
processes, however until the projects are fully delivered on site there remains
a risk. Other areas of risk relate to the potential for limited uptake in regard to
CARS grants and also over-run on costs for third party projects. In regard to
the latter this is a high risk particularly as the Council is not the responsible
body for the projects or their delivery on the ground. The setting up of regular
benefits realisation group meetings and building good working relationships
with the third parties assists in identifying where issues may arise and where
additional support may be required. Cost inflation continues to impact the
construction industry and this is exacerbated by limited supply chain options
in rural areas.  Robust procurement and contract management processes will
reduce the risk of cost escalation on projects.   
9.7  Climate Change - It is an ambition of our project work to work towards net zero
by adopting a carbon conscious approach throughout.  Some grant funding
directly supports the transition to net zero (e.g. CNI).

Page 16

9.8 Fairer Scotland Duty: Socio Economic Duty – Grant funding can support
projects which are a catalyst for economic growth and well-being, particularly
on some of our most fragile communities. 
9.9 Equalities – protected characteristics – Projects can be a driver for inclusion. 
9.10 Customer Duty – Delivery of external grant funding will ensure the Council are
supporting local communities and households across Argyll and Bute. 
9.11 Island Communities – some of the funds directly support local island
communities e.g. Islands Programme, CNI, ICCEF. 
9.12 Childrens rights and wellbeing – Some funding will directly support projects 
that aim to provide positive outcomes for children and young people.  This will 
include those at greatest risk of poverty and households with children. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Leader of the Council: Councillor Jim Lynch
Policy Lead for Business Development: Councillor Math Campbell-Sturgess 
August 2025 
For further information - please contact: 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Jonathan Welch, Transformation Projects and Regeneration Manager
jonathan.welch@argyll-bute.gov.uk 
Appendices: 
Appendix A – List of Council and Third Party projects that the team is either
responsible for delivering directly or for managing the grants given by the Council to
a third party organisation.

Page 17

APPENDIX A - LIST OF COUNCIL AND THIRD PARTY PROJECTS 
Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period)
Tarbert Lochgilphead Regeneration Fund (Remaining Balance) £250,000 £250,000 £0 TBC Ongoing (Gleaner
Site)
Port Ellen Community hub, Islay RCGF grant  £1,570,259 £0 £1,096,223 2021/22 2025
Kilmory Business Park in Lochgilphead RCGF grant  £1,980,000 TBC £979,000 2021/22 2025/26
Lochgilphead CARS (Includes 22/23 PBI Grant) £2,200,782 £750,551 £1,269,731 2020 2026
Helensburgh CARS £2,400,000 £500,000 £1,240,000 2021 2026
Events and Festivals grants £114,700 £114,700 - 2024/25 2025/26
Royal National Mòd (provisional) £45,000 £45,000 £0 2024/25 2024/25
Crown Estate Funding Award 23/24 £1,590,409 £0 £0 23/24 Ongoing
Crown Estate Funding Award 24/25 £1,818,715 £0 £0 24/25 Ongoing
Community Regeneration Funding  £20,340,000 £TBC £TBC 25/26 Ongoing
Scotland Loves Local £46,000 £0 £46,000 2022/23 2025/26
Aros Waterfront outdoor activity hub – RCGF Grant     £414,565 £0 £403,500   2023/24 2025/26
Islands Programme 2023/24 - Rockfield Road, Tobermory Phase 1 (also
PBI and Crown Estate) £1,105,796 £250,000 £855,796 2023/24 2025/26
Islands Programme 2023/24 - Tiree Care Home £1,250,000 £580,000 £450,000 2023/24 2024/25
Islands Cost Crisis Emergency Funding £145,000 £0 £145,000 2025/26 2025/26
Tarbert Heritage Regeneration Scheme – Development Phase £140,000 £60,000 £80,000 2023/24 2024/25
CNI Capital Fund 24/25 - Decarbonisation of Community Buildings  £246,444 £0 £246,444 2024/25 2025/26
CNI Capital Fund 24/25 - Islay Forestry Initiative Phase 3 £354,116 £0 £142,285 2024/25 2025/26
Isle of Luing Slate Quarry – RCGF 25/26 £2,000,000 £0 £1,747,936 2025/26 2026/27

Page 18

Council & Third Party Regeneration Projects  Project Value  Council
Funding
Contribution
External
Funding
secured by
ABC
Delivery
Start
Delivery End -
(Excludes 12
month defect
and monitoring
period) 
Rural Growth Deal – Kintyre Seasports £2,300,000 £200,000 £2,100,000 2025/26 2026/27
Rural Growth Deal – Rothesay Pavilion (Stage 2b/2c) £22,000,000 £10,749,000 £11,700,000 2025/26 2026/27
Rural Growth Deal – Low Carbon Economy – Isle of Islay £3,000,000 £24,129 £3,000,026 2032/33 2033/34
Rural Growth Deal – Rural Skills Accelerator Programme – Dunoon
STEM Hub £3,362,728 £77,455 £3,240,000 2025/26 2026/27
Rural Growth Deal – Rural Skills Accelerator Programme – SAMS STEM
Hub £2,500,000 £0 £2,500,000 2026/27 2027/28
Rural Growth Deal – Rural Skills Accelerator Programme – UHI Argyll
Estate Enhancements Lochgilphead  £1,500,000 £0 £1,500,000 2029/30 2029/30
Rural Growth Deal – Housing to Attract Economic Growth – Isle of Mull £1,500,000 £125,300 £1,500,000 2025/26 2026/27
Rural Growth Deal – Housing to Attract Economic Growth – Isle of Islay £1,500,000 £37,959 £1,500,000 2028/29 2028/29
Rural Growth Deal – Clyde Engineering and Innovation Centre £7,000,000 £59,566 £199,820 2029/30 2031/32
Rural Growth Deal – West Coast UAV Logistics and Training Hub £4,000,000 £21,886 £420,000 2031/32 2032/33
Rural Growth Deal – Marine Industry Training Centre £7,830,000 £0 £7,830,000 2027/28 2029/30
Rural Growth Deal – Centre for Seaweed and Shellfish Innovation and
Development  £3,330,000 £0 £3,330,000 2027/28 2028/29
Rural Growth Deal – Machrihanish Innovation Campus £3,840,000 £0 £3,840,000 2026/27 2027/28
Total £101,674,514 £13,395,546 £51,361,761

Page 19