Options Assessment Report A816
Bealach Mor 
February 2025

Page 2

2
Options Assessment Report
A816 Bealach Mor 
Project no: GLJ620
Document Title: Options Assessment Report; A816 Bealach Mor
Revision: Rev1
Document Status: DRAFT – For comment
Date: 03/04/25
Client: Argyll and Bute Council
Project Manager/Director: N. McLean
Author: N. Horsburgh 
Document history and status
Revision Date Description Author Checked Approved
Draft
Rev 0
17/02/2025 Draft for Client Comment N.H N.M N.M
Draft
Rev 1
03/04/2025 Draft for Client Comment N.H N.M N.M                   
Contents
1. Introduction ................................................................................................................... 3
2. Existing Conditions ...................................................................................................... 6
3 Option Generation ...................................................................................................... 15
References .............................................................................................................................. 32
APPENDIX A ......................................................................................................................... 33

Page 3

3
Options Assessment Report
A816 Bealach Mor 
1. Introduction
1.1 Background
The A816 through Bealach Mor is a main A class road in Argyll and Bute on the west coast of
the Scottish Highlands. The road is the main connection route between Oban and
Lochgilphead.
The road runs along the northern slope of Creag nam Fitheach (214m), A’ Bheinn (246m).
On the 7th October 2013 as a result of exceptional rainfall, the wettest 2-days in series from
1891, with 100-150mm rain falling widely across Southern and Central Highlands (Kendon,
2023). Approximately a month of rainfall fell in a 36-hour period in a number of areas within
Argyll and Bute.
The heavy rainfall fell onto already saturated ground and triggered 3no. separate but closely
spaced debris flow events (wet saturated landslides that flow) from the steep slope
immediately adjacent to the A816. This deposited approximately 6000 tonnes of material
over nearly 200m length of road, with more debris on the surrounding slopes and fields.
Clearance works removed an estimated 10,000 tonnes of debris, from the original event and
subsequent debris from later smaller events and erosion / wash out of material remaining on
the slope.
Further assessments of the slope during and following clearance highlighted an ongoing risk
of further movement in the landslide areas and a hazard from precarious boulders and
potential for rock fall from previously and newly exposed rock scarps high above the road.
Scaling works (removal of loose rock and boulders) was undertaken on the slope above the
road as far as practicable, but the works required to lower the rockfall risk further involved
significant engineering works. More boulders continue to be exposed and weather out from
the landslide scarps and deposits following rainfall which washes out soil covering them and
holding them in place.
Owing to the ongoing movement and potential for further blocks and/or debris to impact the
road a temporary bypass route was constructed as the fastest and safest way to reopen the
A816. The bypass as opened to the public on the 16th December 2023, following 6 weeks of
construction (Figure 1). Due to landowner, environmental, engineering and archaeological
challenges and constraints the temporary road is built in a restricted narrow corridor resulting
in a single lane with passing places, open ditches with steep side drops, a sharp corner and
very steep incline at the western side.
Built as a temporary road, i.e., not to highway standard, the road is approximately 320m
length and the alignment was chosen to follow existing track and foundation of the military
road to minimise foundation and subsidence issues. The road is constructed to Forestry
Land Scotland specification (as a floating road), as far as practicable, with a covering of
asphalt.

Page 4

4
Options Assessment Report
A816 Bealach Mor 
Figure 1 – Aerial image of the temporary bypass and A816 (south), taken 17/07/24. 
1.2 Purpose of this report
The purpose of this report is to document the development and assessment of options for
the permanent road and to consider the scheme objectives, value, engineering/geohazards,
environmental/archaeological, advantages, disadvantages and constraints of the options
considered.
The DMRB is a collection of documents used to provide requirements and advice for works
and developments of motorways and trunk roads. Although not strictly applicable to the
replacement/upgrade of the section of the A816 at Bealach Mor, it is useful guidance for
Argyll and Bute Council road schemes, although not all of the documents may be applicable.
The DMRB guidance TD 37/93 ‘Scheme Assessment Reporting’ has been withdrawn, and
while is no longer formally used the three stages of assessment are still commonly referred
to as a useful points of reference. This report aims to include the main elements form Stage
1 (Strategic assessment) and Stage 2 (Route option assessment).
As many of the environmental, engineering and economic constraints for the area were
investigated (along with consultation of SEPA, HES/WoSAS, Argyll and Bute Council,
Landowners, Tillhill) during the temporary bypass route the knowledge was utilised for the
gathering of the options assessment. It is suggested that once the options are identified in
this report and preferred option is determined, that further consultation will be required with
the relevant bodies/parties as well as wider public consultation.
This report is restricted to the assessment of the proposed route areas, it should be noted
that geotechnical hazards remain outwith the immediate study area, particularly along the
A816 westwards from Kintaraw towards Salachary. 
1.3 Strategic decisions
The A816 is a main arterial route in Argyll, local communities and deliveries etc., facing large
detours with social and economic impacts to communities of the road being closed.

Page 5

5
Options Assessment Report
A816 Bealach Mor 
Following assessment of the landslide site it became clear that a prolonged closure was
going to be required to remediate the landslide site. The temporary bypass was the preferred
option chosen by Argyll and Bute Council to allow traffic to bypass the works and for
stabilisation works to continue unhindered. The route was chosen as the fastest to deliver
with minimal preparatory works.
Transport Scotland’s vision for Scotland’s transport system for the next 20 years includes
four interconnected priorities: Reduces Inequalities, Takes Climate Action, Helps Deliver
Inclusive Economic Growth and Improves our Health and Wellbeing.
Argyll and Bute Council’s economic strategy and climate action plans address environmental
challenges, including those related to climate change and natural disasters, such as
landslides. Argyll and Bute Council’s refreshed economic strategy for 2024-2034 focuses on
resilience and adaptation to climate change, which includes mitigating risks from severe
weather events.
The STPR2 report (Jacobs, 2020) documents and discusses the current planning and
transport strategy for transport in detail, the reader is referred to this document for further
reading.

Page 6

6
Options Assessment Report
A816 Bealach Mor 
2. Existing Conditions 
2.1 A816 Bealach Mor
Scottish Government 6-fold Urban Rural Classification 2016 and 8-fold Urban Rural
Classification 2016 classes the Bealach Mor area as Remote Rural and Very Remote Rural
respectively.
2.2 Land use
• Residential
The area for all options considered is rural with no residential properties within the
assessment area.
• Commercial (Agricultural) Land
The area is shown on the Land Capability for Agriculture in Scotland mapping (1:250,000) as
Class 6.1: Land is capable of only rough grazing due to intractable physical limitations; the
semi-natural vegetation provides grazing of high value.
There is a commercial forestry planation managed by Tillhill to the north of the existing A816.
The temporary bypass follows an existing forestry road through the south side of the
plantation.
• Development Land
There are no areas of development or active planning applications within the assessment
area. 
2.2 Environment
SNH Landscape Character Type lists the area as Type 43 upland parallel ridges – Argyll. The
landscape comprises a distinctive series of linear ridges aligned in parallel with the south-
west/north-east grain of the coast with key characteristics listed below:
• Upland landscape of long, parallel ridges and narrow, linear lochs and glens.
• Tightly packed ridges follow a south-west/north-east alignment.
• Steep, sharp ridge-tops, with dramatic rocky outcrops.
• Extensive conifer forests.
• Deciduous, largely ancient oak woodland on steep, sheltered slopes of ridges and on
loch edges.
• Small marginal pastures or moorland in isolated patches between the un-
forested ridges.
• Dramatic, scenic upland landscape.
Habitats within the wider area are mixed with large areas of woodlands and open moorland /
grazing. The limit of the desktop search for protected species including badger, otter, pine
marten and red squirrel has been kept at 2 km from the site. Bats and trees and their
foraging routes are more complex. The zone of influence for bats has been set at 10 km as

Page 7

7
Options Assessment Report
A816 Bealach Mor 
they are a mobile species which can be influenced by habitat fragmentation. Otters have
been scoped out of the surveys as there are no watercourses (streams, ditches) nearby.
Designated sites will not be affected by the proposed development due to the topography
and surrounding habitats adjacent to the site however the zone of influence has been set at
2 km for a desktop search.
There are no protective designations within 2 km of the bypass, this would include the areas
for all route options assessed.
A search of the National Biodiversity Network Gateway (NBN) was made for protected
species within 2km of the bypass (10km for bats), the results are presented in Table 1 below.
Table 1 – NBN protected species results 
Common Name Scientific Name
Badger Meles meles
Otter Lutra lutra
Pine marten Martes martes
Red squirrel Sciurus vulgaris
Soprano pipistrelle Pipistrellus pymaeus 
• Phase 1 Habitat Survey
A Preliminary Ecological Appraisal report, including a Phase 1 Habitat Survey was
undertaken for the proposed area (Preston, R., 2025). The standard methodologies (as
found in the ‘Handbook for Phase 1 habitat survey - a technique for environmental audit,
2010 JNCC) was used. A map was produced at a scale of 1:1,000 (Appendix I, Phase I
Habitat Survey). The Phase 1 Habitat Classification and associated field survey technique
provide a standardised system to record semi-natural vegetation and other wildlife habitats.
The approach is designed to cover large areas of countryside relatively rapidly. It presents
the user with a basic assessment of habitat type and potential importance for nature
conservation. Each habitat type/feature is identified by way of a brief description of its
defining features. It is then allocated a specific name, an alpha-numeric code, and unique
mapping colour. Important findings are recorded as target notes and may identify areas
which require more in-depth study.

Page 8

8
Options Assessment Report
A816 Bealach Mor 
Figure 2 – Phase 1 Habitat results and Route Options (Preston, R., 2025). 
Phase 1 Habitat Survey Results 
Results are summarised in Figure 2, the full Preliminary Ecological Appraisal report is
attached within Appendix A 
A1.1.2 Plantation broadleaved woodland
This habitat is found at the eastern extent of the route adjacent to the A816 on the east side
of the route and contains young sessile oak (Quercus petraea). 
A1.2.2 Conifer plantation
Approximately halfway along the proposed grey route it is bounded on either side by
commercial conifer forests with predominantly Sitka spruce (Picea sitchensis), occasional
Japanese larch (Larix japonica), occasional Scots pine (Pinus sylvestris) and edged with
Goat willow (Salix caprea), Grey willow (Salix cinerea) and Downy birch (Betula
pubescens). The age of the forest is at pole stage with severe windblow after the recent
storm. The forest is dense with no understorey. 
A2.1 Dense continuous scrub
The area between the A816 and the western end of the route has a band of continuous
scrub including; Downy birch, Hawthorn (Crataegus monogyna), Rowan (Sorbus aucuparia),
Bramble, Bracken and Gorse (Ulex europaeus). 
B1.2 Semi-improved acid grassland
This habitat is found from the western edge of the conifer plantation to where it meets the
dense scrub adjacent to the A816 and from the eastern edge of the conifer plantation
along the wayleave and has the following species present; Bracken (Pteridium aquilinum),
Bramble (Rubus fruticosus), Creeping buttercup (Ranunculus repens), Foxglove (Digitalis

Page 9

9
Options Assessment Report
A816 Bealach Mor 
purpurea), Purple moor grass (Molinia caerulea), Scaly male fern (Dryotperis affinis),
Sharp-flowered rush (Juncus acutiflorus), Soft rush (Juncus effuses), Tormentil (Potentilla
erecta), and Tufted hairgrass (Deschampsia cespitosa). 
B5 Marshy grassland
This habitat is found at the east end of the route next to the A816 and ends at the bottom of
a slope to the north west where the land rises to the wayleave and has scattered small
scrubby trees. The wetness likely results from seepage from the stream. The National
Vegetation Classification for this habitat is M28 Iris pseudacorus - Filipendula ulmaria mire.
Blunt-leaved bogmoss (Sphagnum palustre), Bracken (Pteridium aquilinum), Bramble
(Rubus fruticosus), Creeping buttercup (Ranunculus repens), Flag iris (Iris pseudacorus), 
Foxglove (Digitalis purpurea), Goat willow (Salix caprea), Hawthorn (Crataegus
monogyna), Purple moor grass (Molinia caerulea), Sitka spruce (Picea sitchensis), Soft
rush (Juncus effuses), Tormentil (Potentilla erecta), Tufted hairgrass (Deschampsia
cespitosa) and Wild angelica (Angelica sylvestris). 
D5 Dry heath / acid grassland mosaic
This habitat is found on the ride going through the conifer plantation.
Bank haircap moss (Polytrichum formosum), Blaeberry (Vaccinium myrtillus), Bracken
(Pteridium aquilinum), Common heather (Calluna vulgaris), Downy birch (Betula
pubescens), Goat willow (Salix caprea), Greater wood-rush (Luzula sylvatica), Hard fern
(Blechnum spicant) and Purple moor grass (Molinia caerulea). 
No invasive species were observed in any of the survey areas. 
Further detail on the habitats found in each route area are included with the route options for
ease of reference. 
Protected Species Results
• Otter
No otter holts or rest ups were found within the survey areas. 
• Badger
No signs of badger were found. 
• Pine marten
No pine marten dens were found. 
• Red squirrel
No signs of red squirrel including dreys were found. 
• Bats
All trees within the survey areas have negligible roost potential.

Page 10

10
Options Assessment Report
A816 Bealach Mor 
2.3 Geology
• A fault is marked on the map running along the east-west line of the existing A816, from the
coast to Salachary, through Bealach Mor. Further faults are shown to the south as splay faults
originating from the main fault orientated towards the southeast. 
Figure 3 – BGS geology map of the study area. Figure contains British Geological Survey materials © UKRI
2025
The geology though Bealach Mor differs notably to the north and the south of the A816
(Figure 3), due to the presence of the fault. The area is dominate by metamorphic rocks from
the Tayvallich Volcanic and Slate and limestone Formations, and Crinnin Grit Formation

Page 11

11
Options Assessment Report
A816 Bealach Mor 
(Neoproteozoic Era). Crosscut by Dalradian Supergroup - metagabbro and metamicrogabbro
and North Britain Siluro-Devonian calc-alkaline andesite dykes.
No mass movement, artificial ground or borehole records are recorded for the area. 
2.4 Superficial deposits 
Figure 4 – BGS superficial map of the study area. Note the three landslides recorded for the 7th October 2023
event. Figure contains British Geological Survey materials © UKRI 2025.

Page 12

12
Options Assessment Report
A816 Bealach Mor 
The BGS GeoIndex superficial layer (1:50,000) shows peat deposits in the lower lying areas
within the valleys of the study area (Figure 4), the depth of these is not recorded but that
they are present indicates they are substantial and likely to exceed 5m depth. There is also a
deposit of raised marine deposit of sands and gravels on the former raised beach at the
western end of the site. Alluvium deposits are indicated in the vicinity of the Kintraw Burn and
from Lochan na Goirt.
The majority of the soils within the area are shown on the Macaulay Institute for Soil
Research (1:250,000) map as brown forest soils, humic gleys; some peaty gleys and peaty
podzols, while there is a small band of soils close to the coastline shown as humus-iron
podzols, peaty podzols. 
2.5 Rockfall and landslide history
No rockfall or landslide records were found for the area.
There are three landslides recorded on the BGS GeoIndex (Figure 4), but these all relate to
the 7th October 2023 event, no prior incidents are recorded from the site or nearby. 
2.6 Archaeology
Historic Environment Scotland records a Scheduled Monument (NM 83046 04974, Figure 5)
for Kintraw Standing stone and cairns to the west side of the site and the east of the A816 in
a field to the south of the Kintraw burn. Further protected sites are listed on Canmore within
the area and are listed in Table 2 below. 
Figure 5 – Scheduled Monument site recorded by historic Environment Scotland shown in the red highlighted
area. The red location pin denotes the location of the prehistoric fort recorded at the site on Canmore
(Canmore ID 22850).

Page 13

13
Options Assessment Report
A816 Bealach Mor 
Table 2 – Canmore / RCAHMS listed sites within the assessment area.
Listed/ Protected Site Position relative to proposed routes
Kintraw Farmstead (Period Unassigned), Lime Kiln
(Period Unassigned)
North of all proposed works areas
Kintraw Bridge
Road Bridge (18th Century)
North of all proposed works areas
Kintraw
Ring Cairn (Neolithic) - (Bronze Age)
Within the Scheduled Monument Designation
Kintraw
Cairn (Period Unassigned)
Within the Scheduled Monument Designation
Kintraw
Platform (Period Unassigned)
Within the Scheduled Monument Designation
Kintraw
Cairn(s) (Prehistoric), Enclosure (Period Unknown),
Standing Stone (Prehistoric)
Within the Scheduled Monument Designation
Kintraw
Fort (Prehistoric)
Within area of the works – All routes widening the
west end of the temporary bypass and routes around
fort – Yellow, orange, green, red, grey.
Kintraw
Rig And Furrow (Medieval) - (Post Medieval)
Close to A816, covered/destroyed by 2023 landslide.
Barbreck
(Farmstead) (Period Unassigned)
Close to Grey Route
Dun Na Ban-Oige
Fort (Prehistoric)
Close to Grey Route
Kintraw
Cairn (Period Unassigned), Cremation (Period
Unassigned), Field System (Period
Unassigned)(Possible)
Out with area 
2.7 Waterbodies 
• The Kintraw Burn to the north of the site is the main watercourse thought the site. All
watercourses for the area drain to Loch Craignish, a sea loch located to the west of the site
which opens to the Sound of Jura.
• Loch Craignish (15.37km2) is a former designated shellfish growing waterbody, de-
designated in 2012.
• No designated waters are located within the study area. 
2.8 Traffic data
AADT values are provided in Table 3 below.

Page 14

14
Options Assessment Report
A816 Bealach Mor 
Table 3 – AADT values for the A816. 
direction_of_travel
pedal_cycles
two_wheeled_motor_vehicles
cars_and_taxis
buses_and_coaches
lgvs
hgvs_2_rigid_axle
hgvs_3_rigid_axle
hgvs_4_or_more_rigid_axle
hgvs_3_or_4_articulated_axle
hgvs_5_articulated_axle
hgvs_6_articulated_axle
all_hgvs
all_motor_vehicles
2013 Manual
Count  N  1  12  765  5  140  38  3  11  2  15  3  72  994
2013 Manual
Count  S  0  6  740  6  147  32  5  6  5  3  9  60  959
2022 Estimate N 1 11 680 4 211 44 4 15 3 13 3 82 988
2022 Estimate S 0 6 657 5 221 37 6 8 7 3 10 71 960 
2.9 Social and economic context
A recent report by Jacobs / AECOM for Transport Scotland :STPR2: Initial Appraisal: Case
for Change - Argyll & Bute Region 2020 details much of the social and economic context for
the area and the reader is referred to this more in-depth document for further information.

Page 15

15
Options Assessment Report
A816 Bealach Mor 
3 Option Generation
3.1 Overview
This study examined numerous potential route options. Route corridors utilising long and/or
remote areas from the A816 were rejected for further investigation and the option process
since these did not meet the objectives of the project. The anticipated costs and potential
environmental impacts of each route were considered disproportionate to the problems faced
by the existing alignment of the A816.
Eight options were taken forward for assessment. These range from a do minimum
approach, utilising the existing A816 and bypass to a complete realignment of the road.
Initially longer (>10km) options were proposed that would bypass the slopes and other
potential future issues along the Bealach Mor stretch of the A816. These were discounted for
further assessment in discussion with Argyll and Bute Council as beyond the scope and
remit of the project.
The following section summarises the options and presents the best assumptions of a
route path / alignment, but it should be noted that changes or refinements may be
required at a later stage of assessment.
• Option 1: A816 (Purple Route)
• Option 2 & 2a: A816 and bypass (Orange Route)
• Option 3: A816 Realigned and bunded (Pink Route)
• Option 4: Bypass with retaining wall/revetment (Yellow Route)
• Option 5: Bypass with realigned turn (Blue route)
• Option 6: Bypass and lower field (Green Route)
• Option 7: Bypass around fort (Red Route)
• Option 8: Alternative bypass (Grey Route) 
The last two of the options (Red and Grey Routes) considered require to passing through or
very close to sites of archaeological significance (Scheduled Monument and Fort), these
were deemed unlikely to gain necessary permissions and to carry a large risk of impact to
programme or budget should works uncover archaeological significant finds, these were
discounted from further assessment but remain included for completeness.
An overview of the route option locations is provided on Figure 6 and individual routes are
shown within the relevant tables below. 
3.2 Cost estimates
Previous upgrades of trunk road schemes recently completed in similar environments are
listed below for comparison to the current proposed routes
Costs are based on the available information and cover geotechnical investigation, design
and construction. It is only possible at this stage without detailed route ground investigation
and design to provide outline costings, these have been based on relatively pessimistic
ground conditions. Land acquisition costs would be additional to the costs provided.
Relocation of services are not factored within the cost estimates and may attract significant
additional costs where required.

Page 16

16
Options Assessment Report
A816 Bealach Mor 
Additional estimates have been provided to address further potential geotechnical hazards
which if not addressed may result in road closure of the A816. There are two areas identified:
• The lower embankment below the existing A816 (Figure 7) is overstep made ground with
potential for failure and assessment is recommended with remediation if required,
estimated at £1.5 - £2M. All the options pass over this area (with the exception of Green
Route – Option 6).
• There is a large tension crack (around 25m in length) noted on the slope above the A816
where the existing bypass meets the A816 (Figure 8). This is a surface expression of a larger
instability, thought to be a larger slip feature affecting the carriageway. This will need to be
stabilised/remediated to prevent ongoing damage to the road foundation and surface. There
is also potential for further slope failure above the road at this location, remediation works is
estimated at £1.5M. 
Figure 6 – Overview of the eight route options displayed on aerial imagery for the area. Purple (Option 1),
Orange (Option 2), Pink (Option 3), Yellow (Option 4), Blue (Option 5), Green (Option 6), Red (Option 7) and
Grey (Option 8). The location of the lower embankment discussed above is shown by the no1. while the
tension crack/slip location is shown by the no2.

Page 17

17
Options Assessment Report
A816 Bealach Mor 
Figure 7 – Aerial photograph (taken on the 17/07/24) showing the embankment below the A816 discussed in the
text. 
Figure 8 – Aerial photograph (taken on the 17/07/24) showing the tension crack and slip area. Inset
photograph of the tension crack from the bypass tie in looking south (taken 26/08/24).
Lower embankment

Page 18

18
Options Assessment Report
A816 Bealach Mor 
Detailed descriptions of the route options, cost estimates, engineering requirements, geotechnical considerations
are included for each option in Tables 4 to 12 below:
Table 4 – Purple Route, Option 1.
Route Option 1: A816 – Do nothing (Purple Route)
Description Keep existing arrangement (i.e. use of the A816 under single lane
traffic controlled by traffic lights with on-road barrier in place and move
traffic to the temporary bypass during adverse weather or events).
• 460 m length 
Cost Estimate • £17,000 per month (£204,000 PA), dropping to £10,000 (£120,000
PA) after mains power is installed. Operational costs for A816 /
bypass only any event clearance/remediation would be additional.
• Not including repairs (if required) for below road steep
embankment at north side and deep-seated slip to the west.
Engineering
Assessment
• The existing and temporary road surfacing will need upgrading and
the risk of closure of the A816 remains high. Increasing instability
may result in closure and/or increasing risk to road users.
• Ongoing TM / Install of permanent TM required.
• Maintenance / clearance will be required following events.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• The barrier installed was placed in the road to quickly resolve
landowner consent issues, this is not the optimal placement, and
the barrier placed was the largest appropriate for the availability of
space and function. The barrier does not provide full protection of
the area covered and the residual risk remains moderate.
• Topography and road layout is such that the option would be of
ongoing substantial cost, especially if repeated events occur.
• High risk to keep open during heavy rainfall / storms or slope
instability – move to bypass.
Geotechnical
Hazard
• Hazard from the slope above remains, it is likely that ongoing
maintenance costs will be high if ongoing from the geohazards of
landslides and rock fall. There will be additional maintenance and
clearance costs following events.
• The on-road barrier offers protection only to a section
approximately 100m in length. The remaining road to the east has

Page 19

19
Options Assessment Report
A816 Bealach Mor 
no mitigation and may be impacted by landslide/debris flow or rock
fall from above.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• There is a large tension crack (around 25m in length) noted on the
slope above the A816 where the existing bypass meets the A816.
This is a surface expression of a larger instability, thought to be a
larger slip feature affecting the carriageway. This will need to be
stabilised/remediated to prevent ongoing damage to the road
foundation and surface. There is also potential for further slope
failure at this location.
• Assessment of the lower embankment of the existing A816 is
recommended is recommended due to this being overstep made
ground with potential for failure.
Environmental
Assessment
Minimal environmental impact as this utilises the existing road layout.
Discussion/
recommendation
Future events from the slope are highly likely. Incidents of intense
rainfall are likely to increase because of climate change, this is
expected to lead to more frequent and larger volume events. This is
what has been observed at other landslide prone sites in Scotland,
e.g. Rest and Be Thankful. 
The area is only partially protected from rock fall and landslide/debris
flow as the in-road barrier does not run the full length of the slope
vulnerable to instability. 
This option and the orange options have the highest ongoing costs. 
Table 5 – Orange Route 1, Option 2.
Route Option 2: A816 and bypass (Orange Route 1)
Description Move to gyratory flow arrangement (northbound traffic on bypass/
southbound traffic on A816) with roads as existing.
• 890 m length
Cost Estimate £5M - £6M

Page 20

20
Options Assessment Report
A816 Bealach Mor 
Not including repairs (if required) for below road and west deep-seated
slip
Engineering
Assessment
• There are space restrictions at the north joining point and
complications due to significant height differences from the
bypass/A816.
• To allow turning of HGV/long vehicles would need the whole road
width. Roundabouts would potentially provide a logistical way to
transition to the gyratory flow and allow the larger vehicles the
space required.
• In order to build to the west, significant volume of fill would be
required to accommodate any widening.
• Further acquisition of grazing land would be required.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• Topography and road layout is such that the option would be of
ongoing substantial cost, especially if repeated events occur.
• Difficult to keep open during heavy rainfall / storms – move to
bypass.
• The barrier installed was placed in the road to quickly resolve
landowner consent issues, this is not the optimal placement, and
the barrier placed was the largest appropriate for the availability of
space and function. The barrier does not provide full protection of
the area covered and the residual risk remains moderate.
• High risk to keep A816 open during heavy rainfall / storms or slope
instability – move to bypass. If there are weather forecasts or
events impacting the A816 traffic may need to be moved to the
bypass (as Purple Route – Option 1).
• Road closure or further temporary bypass would be required to
accommodate the construction works.
• Construction programme estimated at 8 months.
Geotechnical
Hazard
• Hazard from the slope above remains, it is likely that ongoing
maintenance costs will be high if ongoing from the geohazards of
landslides and rock fall. There will be additional maintenance and
clearance costs following events.
• The on-road barrier offers protection only to a section
approximately 100m in length. The remaining road to the east has
no mitigation and may be impacted by landslide/debris flow or rock
fall from above.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• Assessment of the lower embankment of the existing A816 is
recommended is recommended due to this being overstep made
ground with potential for failure.
• There is a large tension crack (around 25m in length) noted on the
slope above the A816 where the existing bypass meets the A816.
This is a surface expression of a larger instability, thought to be a
larger slip feature affecting the carriageway. This will need to be
stabilised/remediated to prevent ongoing damage to the road
foundation and surface. There is also potential for further slope
failure at this location.
Environmental
Assessment
The orange route follows the previous by-pass road and at the
western extent bends slightly southwest through a patch of semi-

Page 21

21
Options Assessment Report
A816 Bealach Mor 
improved acid grassland and roadside scrub. The impact of the route
would be low, with works restricted to the tie in sections.
Discussion/
Recommendation
Flow in this direction requires crossing of vehicles at both end tie ins.
Roundabouts would be the best option to allow space for turning
vehicles (especially HGV) southbound onto the bypass as a large
swing is required. Roundabouts could also accommodate the crossing
of traffic back onto the left at the east tie in.
Future events from the slope are highly likely. Incidents of intense
rainfall are likely to increase because of climate change leading to
more frequent and larger volume events.
There is a risk of injury, fatality to the travelling public or vehicle
damage from landslide/debris flow or rock fall. The barrier in place
lowers the hazard at locations covered but does not fully negate the
potential for a serious incident at the site. 
The area is only partially protected from rock fall and landslide/debris
flow as the in-road barrier does not run the full length of the slope
vulnerable to instability. 
This option and the Purple Route have the highest ongoing costs. 
It is considered high risk to maintain the A816 open during potential
instability if, as in Purple Route move to bypass is required, a method
of switching traffic to two-way on bypass should be considered. 
Table 6 – Orange Route, Option 2a.
Route Option 2a: A816 and bypass (Orange Route 2)
Description Move to gyratory flow arrangement (northbound traffic on A816 /
southbound traffic on bypass) with bypass & A816 upgraded at joining
points to mitigate issues at northbound end of bypass.
• 890m length
Cost Estimate • £5 – 6.5M

Page 22

22
Options Assessment Report
A816 Bealach Mor 
• Not including repairs (if required) for below road and west deep-
seated slip
Engineering
Assessment
• There are space restrictions at the north joining point and
complications due to significant height differences and tight corner
from the bypass/A816.
• To allow turning of HGV/long vehicles southbound on the bypass
at the north corner they need greater road width. Flow in these
directions would be difficult to manage as HGV or longer vehicles
need to swing out onto the opposite lane to make the turn. Road
widening would be required to the west and/or traffic lights or
similar installed to manage priorities.
• In order to build to the west, significant volume of fill would be
required to support any widening to accommodate widening.
• Further acquisition of grazing land would be required.
• Road closure or further temporary bypass would be required to
accommodate the construction works.
• Construction programme estimated at 8 months.
Geotechnical
Hazard
• Hazard from the slope above remains, it is likely that ongoing
maintenance costs will be high if ongoing from the geohazards of
landslides and rock fall. There will be additional maintenance and
clearance costs following events.
• The on-road barrier offers protection only to a section
approximately 100m in length. The remaining road to the east has
no mitigation and may be impacted by landslide/debris flow or rock
fall from above.
• Impact to the public on an ongoing basis with no resolution is
highly likely.
• Lower slope and deep-seated slip are recommended to
assessment / remediation.
Environmental
Assessment
• The orange route follows the previous by-pass road and at the
western extent bends slightly southwest through a patch of semi-
improved acid grassland and roadside scrub. The impact of the
route would be low, with works restricted to the tie in sections.
Discussion/
Recommendation
Flow in this direction is optimal at the east side of the route as it allows
vehicles to remain on the ‘correct’ side of the road. At the west side
without road widening, it requires traffic lights to holding northbound
traffic to allow space for turning vehicles (especially HGV) southbound
onto the bypass as a large swing is required. 
Future events from the slope are highly likely. Incidents of intense
rainfall are likely to increase because of climate change leading to
more frequent and larger volume events.
The area is only partially protected from rock fall and landslide/debris
flow as the in-road barrier does not run the full length of the slope
vulnerable to instability. 
There is a risk of injury, fatality to the travelling public or vehicle
damage from landslide/debris flow or rock fall. The barrier in place
lowers the hazard at locations covered but does not fully negate the
potential for a serious incident at the site.
This option and the Purple Route have the highest ongoing costs.

Page 23

23
Options Assessment Report
A816 Bealach Mor 
It is considered high risk to maintain the A816 open during potential
instability if, as in Purple Route move to bypass is required, a method
of switching traffic to two-way on bypass should be considered. 
Table 7 – Pink Route, Option 3.
Route Option 3: A816 Realigned and
bunded
(Pink Route)
Description • Move of the A816 approximately 5-10m to the north and
construction of a large pit/bund structure (potentially with additional
rock fall barriers on top) to protect the road.
• 525 m length 
Cost Estimate • £5.5 - £6.75M
• Not including repairs (if required) for below road £1.5M for
additional deep-seated slip
Engineering
Assessment
• The road would be moved north approximately 5-10m and a large
bund constructed, approximately on the current A816 alignment.
• Traffic flows could be maintained on the temporary road to assist
the construction program.
• Landslide/debris flow and rock fall risk will be lowered but may not
be removed entirely.
• There is an overhead power line that would require relocation that
runs 205m along the approximate line of the proposed road to the
south of the most southerly plantation block shown on the aerial
image above.
• Rock excavation required though the existing rock cut.
• Construction programme estimated at 8 months
Geotechnical
Hazard
• There is potential for rock fall and landslide/debris flow to impact
the A816 and modelling would be required to determine if
additional mitigation measures, such as rock fall/debris barriers
were required in addition to the bund.
• Peat deposits are shown on the BGS mapping (Figure 4) in the
alignment, this may require additional foundation
• Lower slope and deep-seated slip are recommended for
assessment / remediation.

Page 24

24
Options Assessment Report
A816 Bealach Mor 
Environmental
Assessment
The habitats adjacent to the pink route are semi-improved acid
grassland and scattered trees including rowan (Sorbus aucuparia),
Goat willow and Downy birch.
Discussion/
Recommendation
The relocation of the road to the north would allow space to construct
bunds large enough to prevent debris from reaching the A816. There
is an additional hazard of potential rock fall from the slope, this is from
rock crags and rock pillars high on the slope and from eroding blocks
from landslide scarps and eroding gully side walls. To mitigate this risk
rock fall barriers are likely to be required along the top of the bunds.
The presence of the overhead power lines along the south of the
forestry block complicates this route option as the cost and
agreements for moving this will add time and budget uncertainty, this
cost is not included in the costing. 
Additionally, the Pink Route would incur ongoing maintenance costs,
particularly following events, clearance and repair to the bund and
fence would be required. 
Table 8 – Yellow Route, Option 4.
Route Option 4: Bypass with retaining
wall/revetment
(Yellow Route)
Description Widening and upgrade of the existing temporary bypass route.
Removal of the sharp, steep corner and realignment of the joining to
the A816.
• 460 m length 
Cost Estimate • £3.75M - £5M
• Further £2M for lower road, £1.5M for additional deep-seated slip
Engineering
Assessment
• To remove the sharp corner and overly steep gradient at the north
end of the bypass this section would be rerouted along the west
side of the fort hill along the line of the former drove road.
• This would require the construction of a retaining wall or revetment
structure to support the road width required.
• The retaining wall is likely to need to extend out to the centre of the
existing road and it is probable that the lower slope would need
additional strengthening works to support the additional weight.

Page 25

25
Options Assessment Report
A816 Bealach Mor 
• Traffic management will need to be extended to accommodate the
tie in on the north side.
• Construction programme estimated at 8 months
Geotechnical
Hazard
Deep-seated slips are recommended for assessment / remediation.
Works to retain the lower slope below the existing A816 are likely to be
required to support the additional weight of the road and revetment.
Environmental
Assessment
This route follows the previous by-pass going through the plantation
forest then is proposed to bend down towards the north before
rejoining the A816 going through semi natural acid grassland (B1.2).
Discussion/
Recommendation
The main length of the route is based around widening the existing
temporary bypass with the main engineering section where the bypass
turns north along the former drove road. The change to alignment
would allow the removal of the sharp corner and reduce the steep
gradient on the transition between the A816 and bypass area. In order
to support the road would require fill with a retaining wall/revetment
estimated to extend to around the centre line of the current road.
Additional works may be required to stabilise the lower embankment
to support the additional weight. 
The yellow option requires some excavation at the corner area but
much less than other options and the risk to programme and budget
due to archaeology finds/permissions is considered less than other
options requiring greater excavation close to archaeological features
and more deviation from current road positions (e.g. Red Route, Grey
Route, Blue Route). 
The overhead power line crosses the temporary bypass around the
mid-section where the road exits the forest block and minor
realignment/height change may be required. This is not included in the
costing. 
The Yellow Route is considered favourable as it is lower budget and
environmental impact than other options while addressing the sharp
corner and gradient issues effectively. The road is moved away from
the unstable slope and ongoing maintenance costs are lower than
other options close to the unstable slope. 
Table 9 – Blue Route, Option 5.
Route Option 5: Bypass with realigned turn (Blue Route)
Description Widening and upgrade of the existing temporary bypass route.
Removal of the sharp, steep corner by realigning the eastern side of
the bypass to the south.
• 405m length

Page 26

26
Options Assessment Report
A816 Bealach Mor 
Cost Estimate • £5 - £6M
• Not including repairs (if required) for below road, £1.5M for
additional deep-seated slip
Engineering
Assessment
• Significant excavation is required to accommodate this route. The
height difference of the existing bypass and the A816 tie in point is
approximately 3m (higher at the bypass). The ground in the centre
of the mounded area the route is crossing is approximately 5m
higher than the bypass, this would require substantial reprofiling to
accommodate the area required for the turn.
• There will still be a substantial corner on the route but the gradient
and more favourable curve/turn.
• Construction programme estimated at 5-6 months.
Geotechnical
Hazard
• This option moves the road towards the main slope and within the
run out for landslides/debris flows and rock fall. If the ground is
levelled and lowered in height the road also becomes increasingly
vulnerable to these hazards.
• Assessment of the lower embankment of the existing A816 is
recommended is recommended due to this being overstep made
ground with potential for failure.
• Lower slope and deep-seated slip are recommended for
assessment / remediation.
Environmental
Assessment
The blue route will go through a short section of semi-improved acid
grassland and require a large volume of bedrock excavation.
Discussion/
Recommendation
The main length of the route is based around widening half of the
existing temporary bypass with a new section of road turning to the
south to accommodate a less tight turn back to the north and tie into
the A816. 
The topography is elevated between the bypass and A816 tie in
points, this will require large volume of excavation (assumed to be
mostly rock). The extensive excavation is likely to require
archaeological permissions for excavations and would possibly be
controlled i.e. watching brief, controlled methodology and full
archaeological excavation of any new find areas. Discovery of
archaeology would increase price and affect programme.

Page 27

27
Options Assessment Report
A816 Bealach Mor 
The Blue Route takes the bypass back towards the unstable slope and
the excavation of the ground to accommodate the road increases the
potential for large landslide/debris flow events to impact on the route.
In comparison to the Yellow Route, the Blue Route is has greater
residual risk from the slope, higher environmental impact and the
alignment is less favourable for increased cost. 
The overhead power line crosses the temporary bypass around the
mid-section where the road exits the forest block and minor
realignment/height change may be required. This is not included in the
costing. 
Table 10 – Green Route, Option 6.
Route Option 6: Bypass and lower field (Green Route)
Description Widening and upgrade of the existing temporary bypass route for the
eastern section of the route. A new western section would be
constructed from the corner of the
• 580m length (approximately 190m of new road construction) 
Cost Estimate • £7M - £8.5M
• Not require for below road £1.5M for additional deep-seated slip
Engineering
Assessment
• Extensive volume/importation of material would be required for the
construction of the new section of road across the field. There is a
30m height difference from the west corner of the A816 where the
road would start to the tie in point on the existing bypass.
• Requires land purchase of land currently used for grazing.
• Off-line construction of the majority of the road.
• Construction programme estimated at 7-8 months
Geotechnical
Hazards
• Height difference would require large volume of fill to be placed,
ground conditions would be required to be adequate to support the
weight, there are some softer areas within the field where
additional foundations engineering may be required.
• Detailed ground investigation would be required for the new
section of road.

Page 28

28
Options Assessment Report
A816 Bealach Mor 
• Deep-seated slip is recommended for assessment / remediation,
lower embankment works would be included within the works,
wider embankment is not used by this option.
Environmental
Assessment
This route starts off adjacent to dense scrub with gorse (Ulex
europaeus) at its northern extent then passing through heavily grazed
neutral grassland with Sheep’s fescue (Festuca ovina).
Discussion/
Recommendation
The Green Route is cost prohibitive due to the volume of imported fill
required. There would be a large volume of road traffic required to
transport the materials required and the option is considered low rating
for sustainability. The project would also require a detailed ground
investigation to be undertaken to inform the design process to ensure
suitability. 
The embankment required would be much greater in scope than
required for the Yellow Route. 
The route passes over heavily used grazing land which would be
expensive and potentially protracted to obtain.
The overhead power line crosses the temporary bypass around the
mid-section where the road exits the forest block and minor
realignment/height change may be required. This is not included in the
costing. 
Table 11 – Red Route, Option 7.
Route Option 7: Bypass around fort (Red Route)
Description The red route passes along the existing bypass track at the eastern
side for approximately 170m before heading northwards though the
plantation forest for 205m and then around the north side of the fort
and tying into the A816 at the north corner close to/within the
Scheduled Monument.
• 640m length 
Discussion/
Recommendation
• £9.5M - £10.5M
• No lower embankment works required, additional cost for
remediation of deep-seated slip.

Page 29

29
Options Assessment Report
A816 Bealach Mor 
Engineering
Assessment
• The red route passes to the east and north side of an identified
prehistoric hillfort (Canmore ID 22850). Permissions for
excavations in the area is likely to be denied or heavily controlled
i.e. watching brief, controlled methodology and full archaeological
excavation of any new find areas.
• Western tie in is located within/close to the Scheduled Monument
site and due to topography, there are no suitable alternative routes
in the area.
• Construction programme estimated at 12 months.
Environmental
Assessment
• The red route passes through conifer plantation (A1.1.2) with both
Sitka spruce and Larch and severe windblow before joining the
grey route running through semi-acid grassland
(B1.2) and ending at a band of dense scrub (A2.1).
• The impact on the environment would be high as the
approximately 480m of the route would be newly constructed.
Discussion The tie in location at the western end of the site passes though/close
to the Scheduled Monument and is unlikely to be granted permissions
or with such stringent restrictions to be prohibitive. 
The route is additionally at high risk of price increase and programme
delay potentially as result of any archaeological finds and/or conditions
to pass around the fort and surrounding previously undisturbed areas. 
The land required for the route is currently plantation forestry and
grazing land. 
Due to the archaeological restrictions, long section of new road and
budget cost this option is discounted.
The overhead power line passes northbound along the west side of
the forest block and minor realignment/height change may be
required. This is not included in the costing. 
Table 12 – Grey Route, Option 8.
Route Option 8: Alternative longer bypass (Grey Route)
Description • The grey route is the longest route considered and passes to the
north of the existing bypass and main plantation blocks to pass
around the north side of the fort and tying into the A816 at the
north corner close to/within the Scheduled Monument.
• 760m length

Page 30

30
Options Assessment Report
A816 Bealach Mor 
Cost Estimate • £10.5M – £12M
Engineering
Assessment
• The grey route passes to the east and north side of an identified
prehistoric hillfort (Canmore ID 22850). Permissions for
excavations in the area is likely to be denied or heavily controlled
i.e. watching brief, controlled methodology and full archaeological
excavation of any new find areas.
• Western tie in is located within/close to the Scheduled Monument
site and due to topography there are no suitable alternatives.
• The grey route is the only route to avoid both the lower
embankment at the west end of the site and the deep-seated slip
at the east side.
• The route has the longest new road construction length at 760m.
Geotechnical
Hazard
• There are areas of very deep peat and marsh land that would
require additional foundation stabilisation works.
• Detailed ground investigation would be required along the route.
Environmental
Assessment
• The grey route passes through marshy grassland, a ground water
dependent terrestrial ecosystem (GWDTE) and as such is a
protected habitat.
• The impact on the environment would be high as the entire 760m
route would be newly constructed.
Discussion/
Recommendation
Although the route avoids the deep-seated slip at the east side of the
area by tying into the A816 further east the additional cost of building
in the peat/marsh area combined with the protected status of the
GWDTE area makes it likely that even if permissions could be gained
to allow works the costs would be greater than those to remediate the
slip. 
The tie in location at the western end of the site passes though/close
to the Scheduled Monument and is unlikely to be granted permissions
or with such stringent restrictions to be prohibitive. 
The route is additionally at high risk of price increase and programme
delay potentially as result of any archaeological finds and/or conditions
to pass around the fort.
Due to the archaeological and environmental restrictions, long section
of new road and budget cost this option is discounted.

Page 31

31
Options Assessment Report
A816 Bealach Mor 
The overhead power line passes northbound along the west side of
the forest block and minor realignment/height change may be
required. This is not included in the costing.

Page 32

32 
Classification: OFFICIAL
References
AADT Traffic https://roadtraffic.dft.gov.uk/local-authorities/44 Accessed 07/01/25
British Geological Survey (BGS), GeoIndex Onshore,
https://mapapps2.bgs.ac.uk/geoindex/home.html, accessed 04/02/25
Jacobs AECOM. 2020. STPR2: Initial Appraisal: Case for Change - Argyll & Bute Region. Kendon, M.,
2023. Exceptional rainfall in Scotland, 6 to 7 October 2023, s.l.: Met Office.
Nature Scotland National Biodiversity Network Gateway https://data.nbn.org.uk/ Nature
Scot Site Link.
Preston, R., 2025 Bealach Mor. Preliminary Ecological Appraisal.
Scottish Government Urban Rural Classification (Scottish Government 2016) 2. Overview -
Scottish Government Urban Rural Classification 2016 - gov.scot Accessed 16/01/25
SNH National Landscape Character Assessment. LCT 043 - Upland Parallel Ridges - Argyll -
Final pdf.pdf, 1:50,000 Republished in 2019
SNH Sitelink http://gateway.naturescot.gov.uk/sitelink/searchmap.jsp Accessed
07/02/25 Soil Survey of Scotland Staff (1981). Soil maps of Scotland at a scale of
1:250 000.
Macaulay Institute for Soil Research, Aberdeen.