ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND  
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
A816 ARDFERN PERMANENT REPAIR SOLUTION UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on progress towards a permanent repair of the
A816 at Ardfern which was damaged during the severe weather event in
October 2023. 
RECOMMENDATIONS 
It is recommended that Members of the Environment, Development and
Infrastructure Committee:-
a) Agree that the existing budget allocation of £1.1m be used to progress the
next phase of detailed business case development required to provide a
recommended option with a further and more highly developed budget
estimate and outline delivery programme.
b) Note the difference in the current cost estimate and that originally produced
and reported to Members in February 2024 and the reasons for this set out in
the body of the report.

Page 2

ARGYLL AND BUTE COUNCIL     ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE        11 SEPTEMBER 2025 
A816 ARDFERN PERMANENT REPAIR SOLUTION UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on progress towards a permanent repair of the
A816 at Ardfern which was damaged during the severe weather event in
October 2023.
2.2 This report sets out the findings of an options assessment commissioned by the
Council and undertaken by specialist consultants. The options assessment
provides a number of potential options for a re-constructed road which have
been further reviewed by Council officers to create a shortlist of preferred
options that it is now proposed are subjected to further more detailed review in
order to arrive at a single option which can be recommended to be taken
forward. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) Agree that the existing budget allocation of £1.1m be used to progress the
next phase of detailed business case development required to provide a
recommended option with a further and more highly developed budget
estimate and outline delivery programme.
b) Note the difference in the current cost estimate and that originally produced
and reported to Members in February 2024 and the reasons for this set out in
the body of the report. 
4.0 DETAIL 
4.1 The A816 through Bealach Mor is a main ‘A’ class road and is the main
connection route between Oban and Lochgilphead. The road runs along the
northern slope of Creag nam Fitheach (214m), A’ Bheinn (246m).

Page 3

4.2  On the 7th October 2023 as a result of exceptional rainfall, the wettest 2-days in
series from 1891, with 100-150mm rain falling widely across Southern and
Central Highlands (Kendon, 2023). Approximately a month of rainfall fell in a 36-
hour period in a number of areas within Argyll and Bute. 
4.3 The heavy rainfall fell onto already saturated ground and triggered 3no. separate
but closely spaced debris flow events (wet saturated landslides that flow) from
the steep slope immediately adjacent to the A816. This deposited approximately
6000 tonnes of material over nearly 200m length of road, with more debris on
the surrounding slopes and fields. 
4.4 Clearance works removed an estimated 10,000 tonnes of debris, from the
original event and subsequent debris from later smaller events and erosion /
wash out of material remaining on the slope.
4.5 Owing to the ongoing movement and potential for further blocks and/or debris to
impact the road a temporary bypass route was constructed as the fastest and
safest way to reopen the A816. The bypass opened to the public on the 16th
December 2023, following 6 weeks of construction (Figure 1). Due to landowner,
environmental, engineering and archaeological challenges and constraints the
temporary road is built in a restricted narrow corridor resulting in a single lane
with passing places, open ditches with steep side drops, a sharp corner and
very steep incline at the western side. Built as a temporary road, i.e., not to
highway standard, the road is approximately 320m length and the alignment
was chosen to follow existing track and foundation of the military road to
minimise foundation and subsidence issues. The road is constructed to Forestry
Land Scotland specification (as a floating road), as far as practicable, with a
covering of asphalt.
4.6 Following the completion of clearance works, construction of protective barrier
systems and the implementation of a temporary traffic light system to control
single lane running traffic was returned to the original route of the A816 and the
temporary diversion road closed on 13th September 2024.

Page 4

4.7 In order to investigate the options available for a permanent road re-instatement
the Council commissioned a consultant to undertake an options assessment
and report. The study examined numerous potential route options with nine
options were taken forward for assessment. These range from a do minimum
approach, utilising the existing A816 and bypass through to a complete
realignment of the road. 
4.8 The consultants have used cost data from recent upgrades of trunk road
schemes in similar environments to produce initial cost estimates. It is only
possible at this stage without detailed route ground investigation and design to
provide outline costings and these are likely to be subject to change as further
design development takes place. It is noted that the A816 may not be
constructed to the same standard as the projects used for cost comparison but
at the current point in time utilizing cost data from recently completed trunk road
schemes is believed to provide the best available comparison. 
4.9  Prior to the Options Assessment to which this report relates an initial and very
early cost estimating exercise was undertaken in early 2024 in order to provide a
broad order of cost magnitude. This exercise suggested a cost of £1.1m and this
was identified as a requirement for the project in the Council Budget Pack in
February 2024 where on page 166 at 3.5.6 it was stated “As a result of a
significant weather event on 7 October 2023, Argyll and Bute Council activated
the Bellwin scheme in relation to the recovery costs associated with the incident.
The funding from this scheme is welcomed however eligibility criteria of costs
are restrictive. Capital expenditure does not qualify therefore any long term
replacements to infrastructure such as bridges cannot be claimed through the
scheme. Works to the value of £3.248m have been identified in the short term
with future long term works costing circa £1.1m being identified, both will
require capital funding.” Without the benefit of a full options study this provisional
estimate was based on widening the temporary bypass road from circa 3m to
6m (to allow two-way traffic) along an approximately 320m length. At this earlier
stage an indicative cost of £1,500/m plus additional costs for consents, licenses,
ground investigations, design fees, plus a contingency allowance of 20% to
produce a high-level estimated cost of £1.1m.   
4.10 In the course of developing the options report the external consultants identified
two further significant geotechnical issues that will need to be addressed as part
of the works to construct a permanent repair to the A816. These additional
issues, which were not known at the time of the initial budget estimated in
February 2024, and consist of: 
• The risk of failure of steep ground on the lower embankment of the A816 just to
the north of the area immediately impacted by the landslip in October 2023. The
cost of repairing this is estimated at up to £2m.
• A large tension crack (around 25m in length) on the slope above the A816
where the existing bypass meets the A816 i.e. just to the south of the area
directly impacted by the landslip in October 2023. This is a surface expression of
a larger instability, thought to be a larger slip feature affecting the carriageway

Page 5

which will need to be remediated to prevent ongoing damage to the road
foundation and surface. The cost of repairing this issue is estimated at up to
£1.5m. 
4.11 The options put forward within the consultants report have been reviewed by
officers and a shortlist of options for further consideration has been produced.
These options and a summary of the rationale is set out in Table 1 below
(numbering and naming are as per the consultants report at Appendix 1):
Table 1 - Options for Further Consideration:
Option Description Estimated Cost –
Option plus
Additional
Described at 2.9 
Status and Rationale
Option 3:
Pink Route
Move the A816
approximately 5-
10m to the north
and
construct a large
pit/bund structure
(potentially with
additional rock fall
barriers on top) to
protect the road. 
Length: Approx.
525 m 
£7m - £8.75m  Not preferred at this
stage due to ongoing
maintenance liabilities. 
Option 4:
Yellow
Route
Widening and
upgrade of the
existing temporary
bypass route with
removal of the
£7.25m - £8.5m  Preferred at this stage
due to relocating road
away from residual
hazard.

Page 6

sharp, steep corner
and realignment of
the joining to the
A816. 
Length: Approx.
460 m 
Option 5:
Blue Route
Widening and
upgrade of the
existing temporary
bypass route with
removal of the
sharp, steep corner
by realigning the
eastern side of the
bypass to the
south. 
Length: Approx.
405m
£6.5m - £7.5m  Not preferred due to risk
from future landslips,
archaeological risks and
poor road alignment.

Page 7

Option 6:
Green
Route
Widening and
upgrade of the
existing temporary
bypass route for
the eastern section
of the route. A new
western section
would be
constructed from
the corner of the
A816 north of the
bypass 
Length: Approx.
580m
(approximately
190m of new road
construction) 
£8.5m - £10m  Not preferred due to high
cost.

Page 8

4.12 Due to the level of investment estimated to be required it is important that the
shortlisted options are subjected to further review and business case
development in line with the Councils Project Pipeline approach. With a large
number of significant infrastructure projects currently either in design or
delivery the Council does not have available the personnel with the correct
experience and knowledge to do this. Therefore it will be necessary to procure
the services of a specialist consultancy to take forward the business case
development initially to Strategic Outline Business Case and preferred option
stage and then subsequently, subject to further Member approvals and budget
allocation to Outline Business Case and Final Business Case. Consultants will
be procured such that they can be retained for the full project life-cycle from
the current point through to final completion to augment the capacity of
Council staff to manage this project. 
5.0 CONCLUSION 
5.1 This report recommends next steps in relation to the delivery of a permanent
repair to the section of the A816 at Ardfern damaged during the October 2023
severe weather event. 
6.0 IMPLICATIONS 
6.1 Policy – None identified.
6.2 Financial - The estimated costs of this project are outlined in the body of the
report. It is estimated that the current capital allocation of £1.1m will be
insufficient to enable completion of this project. The current budget of £1.1m
is estimated to be sufficient for the next phase of project development
included in the recommendations.
6.3  Legal - There will be a range of legal matters related to this project including
land ownership and contractual matters.
6.4  HR – None identified.

Page 9

6.5 Customer Service – None identified at this time.
6.6 Risk - A range of risks are related to this project in terms of affordability,
timescale, land related and issues related to regulatory approvals. There is a
risk of further landslips at this location due to the topography and geology –
this is an important consideration in finalizing the preferred route option in
order to mitigate as far as reasonably practicable future risks to the travelling
public and future risks to transport connectivity.
6.7 Climate Change - By removing the need for traffic lights at this location this
project should lead to minor lowering of transport related CO2 outputs through
removing vehicle idling. The construction of the project will however represent
embodied CO2 as do all construction projects.
6.8  Fairer Scotland Duty – None identified at this time.
6.9 Equalities - protected characteristics – None identified at this time.
6.10 Consumer Duty – None identified at this time.
6.11 Island Communities - The A816 is an important transport corridor that links
points of connection to the islands by ferry services.
6.12 Children’s Rights and Wellbeing – None arising directly from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and 
Infrastructure 
Councillor John Armour, Policy Lead for Roads, Transport and Amenity 
Services 
September 2025                                                  
For further information contact:
Andy Summers, Head of Roads and Infrastructure Service 
Andrew.Summers@argyll-bute.gov.uk 
Elsa Simoes, Infrastructure Design Manager
Elsa.simoes@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager
Hugh.oneill@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Options Assessment Report A816