Appendix A – Actions 
Actions relating to Target Areas
Actions which cover the whole Local Plan District (LPD). 
Columns C (RAG Status) and D (RAG status comment) have been populated with
current standing / status on actions from the Flood Risk Management Team. 
Contributions and review by Planning and Civil Contingencies team where
appropriate. 
Next step is to provide this information to Highland Council for inclusion in the
formalised S37 Interim Report.

Page 2

Classification: OFFICIAL#
LPD Target area
ID
Local
authority Target area name Action_ID Action type General description (called 'action' in final target area datasheets) Description of Action  for Cycle 2 Indicative
Delivery Co-ordination Funding Delivery Lead RAG status -
Interim Report
RAG status comment
Clyde and
Loch
Lomond
26 Argyll and
Bute
Helensburgh 2601 Property flood resilience
scheme
The proposed scheme to provide resilience measures against flooding for
individual buildings is to be taken forward to help prevent water entering
the property and to minimise flood damage.
As part of the Helensburgh Flood Protection Scheme property flood
resilience and resistance measures will be implemented.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and Bute Council  will co-ordinate with
Helensburgh Community Council and
individual business and property owners
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 3 = Medium.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Clyde and
Loch
Lomond
26 Argyll and
Bute
Helensburgh 2602 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the development of the shoreline management plan for the
Argyll and Bute coastline.
2026-2027 ABC to identify internal and external
stakeholders in accordance with Coastal
Change Adaptation Guidance
Capital ABC GREEN Flood Risk Management Team have secured additional ring-fenced
capital funding from Scottish Government's Coastal Change
Adaptation fund to conduct a case study at Helensburgh.  This was
based on actions identified for development of Shoreline
Management Plans and Coastal Adaptive Plans by the Local Flood
Risk Management Plan Cycle 2. 
Tender being progressed 2025 to allow Consultant to be appointed
for 2026-27 delivery.
Clyde and
Loch
Lomond
26 Argyll and
Bute
Helensburgh 2605 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
are to be identified. These priority areas will provide a baseline for the
identification of next steps in managing water ponding or over-whelmed
drainage systems. This should guide adaptive planning to allow for the
impacts of climate change to be monitored, understood and managed.
Develop and implement a surface water management plan to reduce the
risk of flooding from surface water and small watercourses in
Helensburgh. The impacts of climate change on flood risk should be
assessed. The results of the sewer flood risk assessment should be
considered. Opportunities to disconnect surface water from the
sewerage system should be identified. The surface water management
plan should be reviewed and updated regularly.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and Bute Council  will co-ordinate with
Helensburgh Community Council and
individual business and property owners
Capital plus any available
external funding
ABC AMBER LFRMP - for Cycle 2 -
Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
26 Argyll and
Bute
Helensburgh 2607 Flood scheme or
works design
The selected preferred approach for managing flood risk is to be
designed following the completion of the flood study, including
consideration of the long-term impacts of climate change. These can
include small scale works or works to improve catchment management.
This should guide adaptive planning to allow for the impacts of climate
change to be monitored, understood and managed.
Develop the detailed design of the flood protection scheme in
Helensburgh based on the preferred option from the flood study. The
preferred option consists of an initial cycle of property flood resistance
and resilience measures followed by construction of new revetments, as
well as set-back walls.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
2028-2034 Argyll and Bute Council  will co-ordinate with
Helensburgh Community Council and
individual business and property owners
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 3 = Medium.
This action is scheduled for Cycle 3 within SEPA FRMP Cycle 2.
Part of the process is adaptive solutions- the first being Property
Flood Resilience then structural solutions.
Clyde and
Loch
Lomond
26 Argyll and
Bute
Helensburgh 2608 Community
engagement
Community engagement is to continue to be carried out in the area by
the responsible authorities to raise awareness of flood risk.
The responsible authorities to continue to engage with the community,
with particular focus on the detailed design of the flood protection
scheme.
2028-2034 Argyll and bute Council  will co-ordinate with
Helensburgh Community Council and
individual business, property owners and
landowners
Revenue ABC GREEN 2608 is Cycle 3 therefore not listed in LFRMP Cycle 2 as C&LL do
not list Cycle 3.
Clyde and
Loch
Lomond
67 Argyll and
Bute
Kilcreggan 6701 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Progress the flood works based on the detailed design. The works involve
refurbishment of an existing surface water channel and a new pipe
network which discharges to a watercourse.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
2025 Argyll and bute Council  co-ordinated with
Scottish Water,Kilcreggan Community Council
and individual  property and land owners
Capital ABC GREEN Tigh Dearg Road Flood Alleviation Scheme substantially complete
and scheduled for certtified completion in 2025.
Clyde and
Loch
Lomond
67 Argyll and
Bute
Kilcreggan 6702 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
have been identified. Next steps in managing such water ponding or over-
whelmed drainage systems have been identified and should be
implemented. The plan is to be reviewed and updated as needed. 
Implement the surface water management plan. The plan should be
reviewed and updated regularly.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
Scottish Water, Kilcreggan Community Council
and individual  property and land owners
Capital / Revenue ABC AMBER Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
88 Argyll and
Bute
Rothesay and
Port Bannatyne
8801 Flood study An understanding of flood risk and associated issues in the area is to be
developed, which may include surveys and modelling and should
consider the impacts of climate change on flood risk. In areas where
flood risk is confirmed, a range of possible options to manage flood risk
are to be identified, including natural flood management actions where
suitable, and a preferred approach is to be chosen. This should include
adaptive planning to allow for the impacts of climate change to be
monitored, understood and managed.
A flood study should be carried out to address coastal and surface water
flood risk in Rothesay and Port Bannatyne. Using the best understanding
of current coastal processes and anticipated changes due to climate
change, flood modelling should be undertaken to review the standard of
protection offered by the coastal defences. Surface water flood
modelling should also be progressed and include the Lade area. The
impacts of climate change on flood risk should be evaluated. The
interactivity between coastal flooding and surface water flooding should
be assessed. If flood risk is confirmed, scoping of the next steps should be
completed.
Rothesay - 2024
Port Bannatyne -
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  coordinated / will co-
ordinate with Scottish Water, Community
Council and individual  property and land
owners
Capital/ Revenue plus any
available external funding
ABC AMBER Rothesay Flood Study completed (using  Revenue Funding)
Progress on Port Bannatyne Flood Study is dependent on
confirmation of existing committed expenditure schemes against
currently available funding .  Confirmation of this is anticipated by
December 2025.
Clyde and
Loch
Lomond
88 Argyll and
Bute
Rothesay and
Port Bannatyne
8802 Flood defence
maintenance
The existing flood defences are to be maintained by the asset owner to
ensure they are in good condition. 
Maintenance to the Rothesay Flood Protection Scheme should continue
and updates to the maintenance regime be made based on the findings
of the flood study.
Ongoing ABC internal stakeholders Infrastructure
Design and Roads Operations
Revenue ABC GREEN Ongoing & in hand
Clyde and
Loch
Lomond
100 Argyll and
Bute
Sandbank 10001 Flood scheme or
works design
The selected preferred approach for managing flood risk is to be
designed following the completion of the flood study, including
consideration of the long-term impacts of climate change. These can
include small scale works or works to improve catchment management.
This should guide adaptive planning to allow for the impacts of climate
change to be monitored, understood and managed.
Further development of the preferred option may be required prior to
commencing with the detailed design. Argyll and Bute Council to develop
the detailed design of the flood protection works in Sandhaven,
Sandbank based on the preferred option from the surface water
management plan. The preferred option identified to mitigate surface
water flooding is a small embankment with discharge to open channel.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
Sandbank Community Council and individual 
property and land owners
Capital ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 1 = Very High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Clyde and
Loch
Lomond
100 Argyll and
Bute
Sandbank 10002 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Progress the flood works based on the detailed design.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
Sandbank Community Council and individual 
property and land owners
Capital ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 1 = Very High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Clyde and
Loch
Lomond
100 Argyll and
Bute
Sandbank 10003 Community
engagement
Community engagement is to continue to be carried out in the area by
the responsible authorities to raise awareness of flood risk.
The responsible authorities to continue to engage with the community,
with particular focus on the detailed design of the flood protection
works.
Ongoing Argyll and bute Council  will co-ordinate with
Sandbank Community Council and individual 
property and land owners
Revenue ABC AMBER No progression with scheme limits engagement with stakeholders
Clyde and
Loch
Lomond
100 Argyll and
Bute
Sandbank 10005 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
have been identified. Next steps in managing such water ponding or over-
whelmed drainage systems have been identified and should be
implemented. The plan is to be reviewed and updated as needed. 
Implement the surface water management plan. The plan should be
reviewed and updated regularly.
Ongoing Argyll and bute Council  will co-ordinate with
Scottish Water, Sandbank Community Council
and individual  property and land owners
Capital / Revenue ABC AMBER No progression with schemes identified in Cycle 1. Other  hot spots
identified since Cycle 1 need to be investigated and added to
SWMP.
Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
105 Argyll and
Bute
Cardross 10501 Flood study An understanding of flood risk and associated issues in the area is to be
developed, which may include surveys and modelling and should
consider the impacts of climate change on flood risk. In areas where
flood risk is confirmed, a range of possible options to manage flood risk
are to be identified, including natural flood management actions where
suitable, and a preferred approach is to be chosen. This should include
adaptive planning to allow for the impacts of climate change to be
monitored, understood and managed.
A flood study should be carried out to improve understanding of coastal,
river and surface water flood risk in Cardross. The interactivity between
sources of flooding should be assessed. The impacts of climate change on
flood risk should be evaluated. If flood risk is confirmed, scoping of the
next steps should be completed. Data collection may also be included.
Argyll and Bute Council to consider installing rain and river monitors on
Kilmahew Burn.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
Scottish Water,Cardross Community Council
and individual  property and land owners
Capital ABC AMBER Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
105 Argyll and
Bute
Cardross 10502 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the development of the shoreline management plan for the
Argyll and Bute coastline.
2026-2027 ABC to identify internal and external
stakeholders in accordance with Coastal
Change Adaptation Guidance
Capital ABC GREEN Flood Risk Management Team have secured additional ring-fenced
capital funding from Scottish Government's Coastal Change
Adaptation fund to conduct a case study at Cardross.  This was
based on actions identified for development of Shoreline
Management Plans and Coastal Adaptive Plans by the Local Flood
Risk Management Plan Cycle 2. 
Tender being progressed 2025 to allow Consultant to be appointed
for 2026-27 delivery.
Clyde and
Loch
Lomond
107 Argyll and
Bute
Dunoon 10701 Flood scheme or
works design
The selected preferred approach for managing flood risk is to be
designed following the completion of the flood study, including
consideration of the long-term impacts of climate change. These can
include small scale works or works to improve catchment management.
This should guide adaptive planning to allow for the impacts of climate
change to be monitored, understood and managed.
Further development of the preferred option may be required prior to
commencing with the detailed design. Argyll and Bute Council to develop
the detailed design of the flood protection works in Black Park (Ash Park),
Dunoon based on the preferred option from the surface water
management plan. The preferred option identified to mitigate flooding is
a filtration trench discharging to the combined sewer.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
Scottish Water,Utilities, Dunoon Community
Council and individual  property and land
owners
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 1 = Very High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Clyde and
Loch
Lomond
107 Argyll and
Bute
Dunoon 10702 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Argyll and Bute Council to progress the flood works based on the detailed
design.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
Scottish Water,Utilities, Dunoon Community
Council and individual  property and land
owners
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 1 = Very High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Clyde and
Loch
Lomond
107 Argyll and
Bute
Dunoon 10703 Community
engagement
Community engagement is to continue to be carried out in the area by
the responsible authorities to raise awareness of flood risk.
The responsible authorities to continue to engage with the community,
with particular focus on the detailed design of the flood protection
works.
Ongoing Argyll and bute Council  will co-ordinate with
Scottish Water,Utilities, Dunoon Community
Council and individual  property and land
owners
Capital plus any available
external funding
ABC GREEN Various ABC teams involved including Infrastructure Design, Roads
Operations, Community Resilience and Estates
Clyde and
Loch
Lomond
107 Argyll and
Bute
Dunoon 10704 Flood study An understanding of flood risk and associated issues in the area is to be
developed, which may include surveys and modelling and should
consider the impacts of climate change on flood risk. In areas where
flood risk is confirmed, a range of possible options to manage flood risk
are to be identified, including natural flood management actions where
suitable, and a preferred approach is to be chosen. This should include
adaptive planning to allow for the impacts of climate change to be
monitored, understood and managed.
Argyll and Bute Council to carry out a flood study to address flood risk
from the Milton Burn in Dunoon. This includes a review of the Milton
Burn Flood Protection Scheme (2012) and Kilbride Road, Dunoon Flood
Prevention Scheme (2007). The impacts of climate change on flood risk
should be evaluated. If flood risk is confirmed, scoping of the next steps
should be completed.
See LFRMP
Delivery
Statement -
progression of
scheme
dependent upon
budget availability
Argyll and bute Council  will co-ordinate with
SEPA, Scottish Water,Utilities, Dunoon
Community Council and individual  property
and land owners
Capital plus any available
external funding
ABC AMBER Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
107 Argyll and
Bute
Dunoon 10705 Flood defence
maintenance
The existing flood defences are to be maintained by the asset owner to
ensure they are in good condition. 
Continue to maintain the Milton Burn Flood Protection Scheme (2012),
Kilbride Road, Dunoon Flood Prevention Scheme (2007) and other
existing flood defences in Dunoon.
Ongoing ABC internal stakeholders Infrastructure
Design and Roads Operations
Revenue ABC GREEN Ongoing & in hand
Clyde and
Loch
Lomond
107 Argyll and
Bute
Dunoon 10707 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
have been identified. Next steps in managing such water ponding or over-
whelmed drainage systems have been identified and should be
implemented. The plan is to be reviewed and updated as needed. 
Argyll and Bute Council to implement the surface water management
plan. The plan should be reviewed and updated regularly.
Ongoing Argyll and bute Council  will co-ordinate with
Scottish Water, Sandbank Community Council
and individual  property and land owners
Capital / Revenue ABC AMBER Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
111 Argyll and
Bute
Garelochhead 11101 Flood study An understanding of flood risk and associated issues in the area is to be
developed, which may include surveys and modelling and should
consider the impacts of climate change on flood risk. In areas where
flood risk is confirmed, a range of possible options to manage flood risk
are to be identified, including natural flood management actions where
suitable, and a preferred approach is to be chosen. This should include
adaptive planning to allow for the impacts of climate change to be
monitored, understood and managed.
A flood study should be carried out to improve understanding of coastal
flood risk in Garelochhead. The interactivity between coastal and other
sources of flooding should be assessed. The impacts of climate change on
flood risk should be evaluated. If flood risk is confirmed, scoping of the
next steps should be completed. Data collection may also be included.
2026-2027 ABC to identify internal and external
stakeholders in accordance with Coastal
Change Adaptation Guidance
Capital ABC AMBER Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Clyde and
Loch
Lomond
111 Argyll and
Bute
Garelochhead 11102 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the development of the shoreline management plan for the
Argyll and Bute coastline.
2026-2027 ABC to identify internal and external
stakeholders in accordance with Coastal
Change Adaptation Guidance
Capital ABC GREEN Flood Risk Management Team have secured additional ring-fenced
capital funding from Scottish Government's Coastal Change
Adaptation fund to conduct a case study at Garelochhead.  This
was based on actions identified for development of Shoreline
Management Plans and Coastal Adaptive Plans by the Local Flood
Risk Management Plan Cycle 2. 
Tender being progressed 2025 to allow Consultant to be appointed
for 2026-27 delivery.
Clyde and
Loch
Lomond
116 Argyll and
Bute
Kilchattan Bay 11602 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the development of the shoreline management plan for the
Argyll and Bute coastline.
2026-2027 ABC to identify internal and external
stakeholders in accordance with Coastal
Change Adaptation Guidance
Capital ABC GREEN Flood Risk Management Team have secured additional ring-fenced
capital funding from Scottish Government's Coastal Change
Adaptation fund to conduct a case study at Kilchattan Bay.  This
was based on actions identified for development of Shoreline
Management Plans and Coastal Adaptive Plans by the Local Flood
Risk Management Plan Cycle 2. 
Tender being progressed 2025 to allow Consultant to be appointed
for 2026-27 delivery.
Highland
and Argyll
346 Argyll and
Bute
Campbeltown 34602 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
have been identified. Next steps in managing such water ponding or over-
whelmed drainage systems have been identified and should be
implemented. The plan is to be reviewed and updated as needed. 
Implement the Campbeltown Surface Water Management Plan which
will help to manage residual surface water and sewer flood risk. In the
Meadows and Burnside Square areas road gullies will be disconnected
from the combined sewer network with drainage held in above ground
and below ground storage basins, for a controlled release back into the
combined system. Additional properties are targeted for property level
flood resilience.
2023-2025 Land and property owners Capital Funded ABC GREEN Campbeltown Flood Protection Scheme main works contract
completed May 2024.  Included Meadows & Burnside Square SuDS
schemes.
Property level flood resilience measures ongoing
Highland
and Argyll
346 Argyll and
Bute
Campbeltown 34603 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the shoreline management plan. This should consider the
impacts of sea level rise on future flood risk. The need for an adaptation
plan should be assessed.
Ongoing Council stakeholders including Corporate
Resilience, Land UsePlanning, Roads
Operations, Network and standards, Economic
Development, Marine Operations, Coastal
Development Estates and Property, Local
Biodiversity, Climate Change Officer     
External stakeholders including SEPA, Nature
Scot, ACHA, NTS, MOD, Community Council,
HIE, Community Council
Capital  plus any available
external funding
ABC GREEN Flood Risk Management Team have secured additional ring-fenced
capital funding from Scottish Government's Coastal Change
Adaptation fund to conduct a case study at Campbeltown.  This
was based on actions identified for development of Shoreline
Management Plans and Coastal Adaptive Plans by the Local Flood
Risk Management Plan Cycle 2. 
Tender being progressed 2025 to allow Consultant to be appointed
for 2026-27 delivery.
August 2025 developing stakeholder engagement and project
governance
#OFFICIAL

Page 3

Classification: OFFICIAL#
Highland
and Argyll
346 Argyll and
Bute
Campbeltown 34604 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Progress the Campbeltown Flood Protection Scheme. As built drawings
should be made available to SEPA, for consideration in the Scottish Flood
Defence Asset Database, flood map improvements and flood warning
scheme updates.
Complete Land and property owners Capital  plus any available
external funding
ABC GREEN Campbeltown Flood Protection Scheme main works contract
completed May 2024.  Included Millknowe Flood Storage Reservoir
and Dalaruan Culvert.
As Built Records being incorporated into ne WebFRMS asset
managemnt system and shall be available to SEPA for SFDAD
replacement.
Highland
and Argyll
347 Argyll and
Bute
Taynuilt and
Brochroy
34702 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the development of the shoreline management plan for the
Argyll and Bute coastline.
2028 - 2034 Argyll and Bute Council will co-ordinate with
internal and external stakeholders in
accordance with Scottish Government Coastal
Change Adaptation Guidance.
Capital plus any available
external funding
ABC GREEN Cycle 3 action.
Progression will be dependent on available budget
Highland
and Argyll
347 Argyll and
Bute
Taynuilt and
Brochroy
34703 Flood study An understanding of flood risk and associated issues in the area is to be
developed, which may include surveys and modelling and should
consider the impacts of climate change on flood risk. In areas where
flood risk is confirmed, a range of possible options to manage flood risk
are to be identified, including natural flood management actions where
suitable, and a preferred approach is to be chosen. This should include
adaptive planning to allow for the impacts of climate change to be
monitored, understood and managed.
The results of the shoreline management plan and revised flood maps
should be reviewed. The influence of high tides and surge on flooding
from the River Nant should be assessed. The impacts of sea level rise and
climate change on flood risk should be considered.
2028 - 2034 Argyll and Bute Council will co-ordinate with
internal and external stakeholders in
accordance with Scottish Government Coastal
Change Adaptation Guidance.
Capital plus any available
external funding
ABC GREEN Cycle 3 action.
Progression will be dependent on available budget
Highland
and Argyll
353 Argyll and
Bute
Clachan 35301 Flood scheme or
works design
The selected preferred approach for managing flood risk is to be
designed following the completion of the flood study, including
consideration of the long-term impacts of climate change. These can
include small scale works or works to improve catchment management.
This should guide adaptive planning to allow for the impacts of climate
change to be monitored, understood and managed.
Develop the detailed design of the flood protection works in Clachan
based on the preferred option from the flood study. The preferred option
includes removal of a weir structure from the Clachan Burn and property
flood resilience.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
To be confirmed -
progression
dependent upon
budget availability
West Kintyre Community Counciland property
owners
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 3 = Medium.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
353 Argyll and
Bute
Clachan 35302 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Progress the flood protection works in Clachan based on the detailed
design. As built drawings should be made available to SEPA, for
consideration in the Scottish Flood Defence Asset Database, flood map
updates and flood warning scheme updates.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
To be confirmed -
progression
dependent upon
budget availability
Land and property owners Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 3 = Medium.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
353 Argyll and
Bute
Clachan 35303 Community
engagement
Community engagement is to continue to be carried out in the area by
the responsible authorities to raise awareness of flood risk.
Argyll and Bute Council completed three community consultation events
during the flood study and during the appraisal of options. The
responsible authorities to continue to engage with the community and
the community flood group, with particular focus on the detailed design
of the flood protection works.
Ongoing Argyll and Bute Council will work with
Community flood resilience group/ West
Kintyre Community Council , land and
property owners.
Revenue ABC GREEN Ongoing
Highland
and Argyll
353 Argyll and
Bute
Clachan 35305 Community flood alert A community river level alerting system is to be installed to provide
information on the potential for localised flooding.
A river level alerting system is being installed with the help of the
Scottish Flood Forum.
Complete Argyll and Bute councilCommunity resilience
group/ West Kintyre Community Council
Community Council, land and property owners
Revenue ABC GREEN ABC to liaise with SFF and West Kintyre Community Council.
Highland
and Argyll
361 Argyll and
Bute
Tarbert 36101 Flood scheme or
works design
The selected preferred approach for managing flood risk is to be
designed following the completion of the flood study, including
consideration of the long-term impacts of climate change. These can
include small scale works or works to improve catchment management.
This should guide adaptive planning to allow for the impacts of climate
change to be monitored, understood and managed.
Further development of the preferred option may be required prior to
commencing with the detailed design. Develop the detailed design of the
Tarbert Flood Protection Scheme based on the preferred option from the
flood study. The preferred option consists of flood defence walls and
demountable defences. Property flood resilience is to be provided
outwith the scheme extent.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
To be confirmed -
progression
dependent upon
budget availability
Argyll and Bute Council will work with Tarbert
& Skipness Community Council and individual
property owners to deliver the scheme.
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 3 = Medium.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
361 Argyll and
Bute
Tarbert 36102 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Progress the Tarbert Flood Protection Scheme based on the detailed
design. As built drawings should be made available to SEPA, for
consideration in the Scottish Flood Defence Asset Database, flood map
updates and flood warning scheme updates.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
To be confirmed -
progression
dependent upon
budget availability
Argyll and Bute Council will work with Tarbert
& Skipness Community Council and individual
property owners to deliver the scheme.
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 3 = Medium.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
361 Argyll and
Bute
Tarbert 36103 Community
engagement
Community engagement is to continue to be carried out in the area by
the responsible authorities to raise awareness of flood risk.
The responsible authorities to continue to engage with the community,
with particular focus on the detailed design of the flood protection
scheme.
Ongoing Argyll and Bute Council liaises with Tarbert &
Skipness Community Council  and land and
property owners
Revenue ABC GREEN Various ABC teams involved including Infrastructure Design, Roads
Operations, Community Resilience and Estates
Highland
and Argyll
361 Argyll and
Bute
Tarbert 36105 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
are to be identified. These priority areas will provide a baseline for the
identification of next steps in managing water ponding or over-whelmed
drainage systems. This should guide adaptive planning to allow for the
impacts of climate change to be monitored, understood and managed.
Develop and implement a surface water management plan. This should
be reviewed and updated regularly. The impacts of climate change on
flood risk should be assessed. The results of the sewer flood risk
assessment should be considered. Opportunities to disconnect surface
water from the sewerage system should be identified. The plan should be
reviewed and updated regularly.
To be confirmed -
progression
dependent upon
budget availability
Argyll and Bute Council will work with Tarbert
& Skipness Community Council and land and
property owners
Capital plus any available
external funding
ABC AMBER Progress dependent on confirmation of existing committed
expenditure schemes against currently available funding . 
Confirmation of this is anticipated by December 2025.
Highland
and Argyll
364 Argyll and
Bute
Inveraray 36402 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the shoreline management plan. This should consider the
impacts of sea level rise on future flood risk. The need for an adaptation
plan should be assessed.
2028 - 2034 Argyll and Bute Council will co-ordinate with
internal and external stakeholders in
accordance with Scottish Government Coastal
Change Adaptation Guidance.
Capital plus any available
external funding
ABC GREEN Cycle 3 (2028-2034)
Progression will be dependent on available budget
Highland
and Argyll
365 Argyll and
Bute
Lochgilphead 36501 Property flood resilience
scheme
The proposed scheme to provide resilience measures against flooding for
individual buildings is to be taken forward to help prevent water entering
the property and to minimise flood damage.
The Lochgilphead Flood Study (2019) identified property flood resilience
as the preferred option for managing the risk of flooding. (There were no
economically viable options for river flooding). Argyll and Bute Council
presented implementation of a property flood protection scheme on a
grant basis with homeowner maintenance. Argyll and Bute Council to
progress this in combination with community engagement and
promotion of self help. The responsible authority proposes this action as
the best viable option for managing flood risk in this community. The
delivery of this action is subject to capital funding being made available.
To be confirmed -
progression
dependent upon
budget availability
Argyll and Bute Council will work with
Lochgilphead Community Council and
individual property owners
Capital plus any available
external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 2 = High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
365 Argyll and
Bute
Lochgilphead 36503 Shoreline management
plan (coastal adaptive
plan)
An assessment of coastal flood and erosion risk is to be carried out. The
plan should include assessment of climate change and develop adaptive
approaches to allow for the impacts of climate change to be monitored,
understood and managed.
Progress the development of the shoreline management plan for the
Argyll and Bute coastline.
2028 - 2034 Argyll and Bute Council will co-ordinate with
internal and external stakeholders in
accordance with Scottish Government Coastal
Change Adaptation Guidance.
Capital plus any available
external funding
ABC GREEN Cycle 3 (2028-2034)
Progression will be dependent on available budget
Highland
and Argyll
365 Argyll and
Bute
Lochgilphead 36504 Flood study An understanding of flood risk and associated issues in the area is to be
developed, which may include surveys and modelling and should
consider the impacts of climate change on flood risk. In areas where
flood risk is confirmed, a range of possible options to manage flood risk
are to be identified, including natural flood management actions where
suitable, and a preferred approach is to be chosen. This should include
adaptive planning to allow for the impacts of climate change to be
monitored, understood and managed.
A flood study should be carried out to further investigate the feasibility of
potential options to manage river flood risk in Lochgilphead.
2028 - 2034 Argyll and Bute Council will work with
Lochgilphead Community Council and
individual property owners to deliver the
scheme.
Capital plus any available
external funding
ABC GREEN Cycle 3 (2028-2034)
Progression will be dependent on available budget
Highland
and Argyll
366 Argyll and
Bute
Oban 36601 Flood scheme or
works design
The selected preferred approach for managing flood risk is to be
designed following the completion of the flood study, including
consideration of the long-term impacts of climate change. These can
include small scale works or works to improve catchment management.
This should guide adaptive planning to allow for the impacts of climate
change to be monitored, understood and managed.
Develop the detailed design of the Oban Flood Protection Scheme based
on the preferred option from the flood study. The preferred option
consists of a combined flood storage and direct defence solution to
protect against flooding from the Black Lynn and property flood
resilience to protect against coastal flooding. Some more work is
required on the surface water element.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
In accordance with the flood risk management plan, as part of the
scheme or works, the responsible authority should aim to ensure the
action will not have an adverse effect on the integrity of the Inner
Hebrides and the Minches Special Area of Conservation.
To be confirmed -
progression
dependent upon
budget availability
Argyll and Bute Council will work with Scottish
Water, Oban Community Council, Forestry
and Land Scotland,  land and property owners
to deliver the scheme.
Capital/ Revenue plus any
available external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 2 = High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
366 Argyll and
Bute
Oban 36602 Flood scheme or works
implementation
The flood scheme/works is to be built following agreement of the design,
costs and timescales.
Progress the Oban Flood Protection Scheme based on the detailed
design. As built drawings should be made available to SEPA, for
consideration in the Scottish Flood Defence Asset Database, flood map
updates and flood warning scheme updates.
The responsible authority proposes this action as the best viable option
for managing flood risk in this community. The delivery of this action is
subject to capital funding being made available.
To be confirmed -
progression
dependent upon
budget availability
Argyll and Bute Council will work with Scottish
Water, Oban Community Council, Forestry
and Land Scotland,  land and property owners
to deliver the scheme. As Built drawings will
be provided to SEPA to support any flood map
or flood warning updates.
Capital/ Revenue plus any
available external funding
ABC RED Scope, timescales and funding arrangements for Cycle 2 and 3
externally capital funded schemes are not yet confirmed.  Previous
(Cycle 1) capital funding was 80% Scottish Government with
Council being responsible for 20% (plus any additional spend over
budget estimate).
Scheme was submitted to SEPA for prioritisation in 2019.
Benefit Cost Ratio classification is 2 = High.
Unlikely to progress in Cycle 2 (2022-2028) due to capital funding
not being secured.
Highland
and Argyll
366 Argyll and
Bute
Oban 36603 Community
engagement
Community engagement is to continue to be carried out in the area by
the responsible authorities to raise awareness of flood risk.
The responsible authorities to continue to engage with the community,
with particular focus on the detailed design of the flood protection
scheme.
Ongoing Argyll and Bute Council liaises with Oban
Community Council and land and property
owners
Revenue ABC GREEN Various ABC teams involved including Infrastructure Design, Roads
Operations, Community Resilience and Estates
Highland
and Argyll
366 Argyll and
Bute
Oban 36604 Surface water
management plan
Areas at risk of heavy or prolonged rainfall causing flooding due to water
ponding on man-made surfaces or overwhelming the drainage system
have been identified. Next steps in managing such water ponding or over-
whelmed drainage systems have been identified and should be
implemented. The plan is to be reviewed and updated as needed. 
Implement the surface water management plan. The plan should be
reviewed and updated regularly.
Ongoing Scottish Water  along with Land and Property
Owners
Capital/ Revenue plus any
available external funding
ABC AMBER Maintenance works carried out at Lochavullin (Target Area).
Larger projects in the SWMP are dependent on securing additional
capital funding.