Page 1

AtkinsRéalis - Baseline / Référence
B8035 GRIBUN
ROCKFALLS -
GEOTECHNICAL
RISK
MANAGEMENT 
B8035 - Mull Rockfall
Final Options Report  
12 November 2025

Page 2

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 2 
AtkinsRéalis - Baseline / Référence
Notice
This document and its contents have been prepared and are intended solely as information for Argyll and Bute
Council and use in relation to B8035 Gribun Rockfalls – Geotechnical Risk Management
AtkinsRéalis UK Limited assumes no responsibility to any other party in respect of or arising out of or in connection
with this document and/or its contents.
This document has 28 pages including the cover. 
Document history
Document title: B8035 - Mull Rockfall Final Options Report
Document reference: B8035 - Mull Rockfall Final Options Report
Revision Purpose description Originated Checked Reviewed Authorised Date
1.0 Draft for comment E Norris
M Smith
C Parry A Koe A Koe 03/11/2025
2.0 Update following first
draft
E Norris C Parry A Koe A Koe 12/11/2025       
Client signoff
Client  
Project B8035 Mull Rockfall
Job number  
Client
signature/date

Page 3

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 3 
AtkinsRéalis - Baseline / Référence
Contents
Executive Summary ..................................................................................................................................................... 5
1. Introduction ...................................................................................................................................................... 6
2. Updated Hazard & Risk Assessment............................................................................................................. 6
2.1 Methodology .......................................................................................................................................... 6
2.1.1 P(H) – Likelihood of hazard .................................................................................................................. 7
2.1.2 E – Elements at risk .............................................................................................................................. 8
2.1.3 V – Vulnerability of elements at risk ...................................................................................................... 8
2.1.4 Ex – Exposure ....................................................................................................................................... 9
2.1.5 RAMMS Rockfall Modelling .................................................................................................................. 9
2.1.6 Rockfall Modelling Results .................................................................................................................. 10
2.2 Updated Risk Assessment - Results ................................................................................................... 12
2.2.1 Limitations for this Preliminary Risk Assessment ............................................................................... 13
3. Options Development & Appraisal .............................................................................................................. 14
3.1 Road closure except for local access ................................................................................................. 14
3.2 Road closure during high rainfall events ............................................................................................. 14
3.3 Earthwork Bund ................................................................................................................................... 16
3.4 Rockfall Barriers .................................................................................................................................. 16
3.5 Rock Stabilisation Netting ................................................................................................................... 16
3.6 Inspection and Scaling ........................................................................................................................ 17
3.7 Reopen the road with additional signage ............................................................................................ 18
3.8 Options Summary ............................................................................................................................... 19
4. Conclusion ..................................................................................................................................................... 21
5. References ..................................................................................................................................................... 22
Appendix A. Road chainage .................................................................................................................................. 24
Appendix B. Geotechnical Risk Register ............................................................................................................. 25 
Tables
Table 2-1 - RAMMS Rockfall modelling results ........................................................................................................... 10
Table 2-2 - Updated quantitative risk assessment results ........................................................................................... 13
Table 3-1 - Updated quantitative risk assessment results ........................................................................................... 17
Table 3-2 - Risk reduction options summary ............................................................................................................... 20

Page 4

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 4 
AtkinsRéalis - Baseline / Référence
Figures
Figure 2-1 - RAMMS rockfall modelling block endpoint locations showing deposition of blocks within a channel in the
slope, matching actual blocks visible within the drone imagery .................................................................................... 8
Figure 2-2 - 0.5 m block used during RAMMS rockfall modelling (left), Examples of blocks observed on site (right) 10
Figure 2-3 - RAMMS rockfall modelling output – 0.5 m block trajectory showing rock jump heights. ......................... 11
Figure 2-4 - RAMMS rockfall modelling block runout results ...................................................................................... 11
Figure 2-5 - Risk tolerability and the ALARP concept (modified from HSE, 1992) ..................................................... 12
Figure 3-1 - Precipitation data during July/August 2025. Note SEPA gauges record daily data from 9am to 9am, and
the Argyll and Bute Council gauges record data from 6am to 6am, therefore rainfall between these times may show
on different days. ......................................................................................................................................................... 15
Figure A-1 - Road chainage ......................................................................................................................................... 24

Page 5

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 5 
AtkinsRéalis - Baseline / Référence
Executive Summary
This report presents the final appraisal of geotechnical risks and mitigation options for
the B8035 at Gribun, Isle of Mull, following recent rockfall incidents that have impacted
the carriageway and posed significant safety risks to road users.
An updated quantitative risk assessment has been presented, further considering the
impact of reducing the number of journeys, or reducing the frequency of rockfall events
impacting the road. This updated QRA indicates that for a high frequency of events (e.g.
10 blocks per year), journeys would need to be reduced to below 20 journeys per day for
single occupancy vehicles to reduce the risk to within the ALARP (As Low As
Reasonably Practicable) region, and that for multi-occupancy vehicles the risk remains
unacceptably high.
Potential remediation options including operational measures, and engineering
interventions have been presented. Full slope engineering interventions are likely to
result in the greatest risk reduction, however many of these interventions are likely to be
time consuming, and present significant costs and technical challenges. 
Targeting interventions to areas that potentially present higher risk, such as sections
where sightlines are reduced, or there is potentially a higher frequency of rockfall events
depositing on the road may reduce the level of risk to within the ALARP or acceptable
levels in a more cost-effective manner.

Page 6

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 6 
AtkinsRéalis - Baseline / Référence
1. Introduction
This final options report presents the updated results on a geohazard risk assessment carried out along as section
of the B8035 at Gribun, Isle of Mull, following on from an interim appraisal published on 10/10/2025.
The assessment was initiated in response to recent rockfall activity affecting the carriageway, posing a risk to road
users.
The site is characterised by steep exposure of the Mull Lava Group, comprised of basalt, which exhibit varying
degrees of weathering and structural complexity.
The purpose of this report is to present an updated risk assessment and present an appraisal of potential
remediation options.
Detail from the initial assessment has not been reproduced in this report. This report should be read in conjunction
with the initial hazard evaluation in the B8035 – Mull Rockfall Interim Assessment. As this report has not been
written as a standalone document.
2. Updated Hazard & Risk Assessment
Building upon the initial hazard evaluation in the Interim Assessment, this section presents a refined assessment of
the risks posed by rockfall events along the B8035 at Gribun. The updated analysis incorporates new data from
RAMMS rockfall modelling, and revised assumptions regarding road user exposure and rockfall frequency.
2.1 Methodology
As recommended in CIRIA C810 (Koe, et al., 2023), the following relationship has been used to evaluate the risk
posed by rockfall at the site.
𝑅𝑠 = 𝑃(𝐻𝑖) × Σ(𝐸 × 𝑉 × 𝐸𝑥)
Where:
𝑅𝑠 = specific risk due to a particular magnitude of landslide 𝐻𝑖 occurring within a specified area over a given period
of time.
𝑃(𝐻𝑖)= probability of a particular magnitude of hazard 𝐻𝑖 within a specific area and time frame
𝐸  = Elements at risk
𝑉 = Vulnerability of elements at risk
𝐸𝑥 = Exposure
This assessment considers the detachment of blocks with a maximum dimension of 0.5 m  (0.5 x 0.5 x 0.5 m) which
represents a common block size observed on site, indicating that this is a frequent event magnitude, to 2 m  (2 x 2 x
2 m) which represents larger blocks observed on site which are assumed to be a lower frequency event.
A 1 km section has been selected as a nominal region to allow the risk to be compared between scenarios and to
other sites. 
This includes assessment of a vehicle collision with a recently fallen block of rock.

Page 7

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 7 
AtkinsRéalis - Baseline / Référence
2.1.1 P(H) – Likelihood of hazard
P(H) considers the probability of a hazard reaching the area being considered (e.g. how likely is it that a block will
detach from the cliff face and reach the road). This can be calculated using the following equation:
𝑃(𝐻) = 𝑝𝐷 × 𝑝𝑇
Where:
𝑝𝐷 = Probability of detachment
𝑝𝑇 = Probability of travel
2.1.1.1 Probability of detachment
While there is limited data on confirmed rockfall events, due to fresh blocks (little to no lichen) being present
throughout the site area, and anecdotal data from local road users indicating that material is regularly cleared from
the road, values of between 1 and 10 blocks per annum have been considered in this assessment. Engineering
interventions including the installation of rockfall fences, and scaling of loose material from the rock face can reduce
the frequency of rockfalls reaching the road. Reduced frequencies of 0.1 (10-year return period) and 0.01 (100-year
return period) have been considered to demonstrate the impact of reduced frequency on risk levels.
Larger blocks are observed to be present across the site less frequently than smaller blocks, as rockfall frequency
typically decreases with increasing magnitude of event. Frequencies of 0.1 (10-year return period) and 0.01 (100-
year return period) have been considered within the risk assessment as potential frequencies for higher magnitude
events, however it should be noted that the relationship between magnitude and frequency is site dependant and
has not been determined at this location due to the limited information available.
Fresh blocks were observed at various locations across the site, both at the location of the 2025 rockfall events, and
outwith this area. Larger numbers of blocks can be observed within the central 500 m surrounding the recent
rockfall (chainage 700 – 1200 (Figure A-1)) indicating that this area could potentially have a higher frequency of
events than other sections or have a greater proportion of blocks depositing adjacent to the road. However, the
presence of fresh blocks indicates that the frequency of rockfalls is relatively high across the whole site.
2.1.1.2 pT - Probability of travel
RAMMS rockfall modelling has been undertaken (detailed in Section 2.1.5) to give a greater understanding of
potential block runout paths. The results of the modelling have shown that 80% of 0.5 m blocks, and 93% of 2 m
blocks reach the B8035, therefore a value of 0.8 has been selected.
Rockfall runout modelling indicates that the likelihood of any detached blocks reaching the road is broadly
consistent across the site, with the exception of the channel located at chainage 1250, where 0.5 m blocks are
modelled to deposit within the channel, and within a depression adjacent to the channel. 2 m blocks are modelled to
reach the road within this area. Within the drone imagery and site photographs many boulders are deposited in
these areas, matching the modelling results, as seen in Figure 2-1.

Page 8

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 8 
AtkinsRéalis - Baseline / Référence 
Figure 2-1 - RAMMS rockfall modelling block endpoint locations showing deposition of blocks within a
channel in the slope, matching actual blocks visible within the drone imagery
2.1.2 E – Elements at risk
This variable considers the number of elements at risk (i.e. how many people are exposed to the risk). For the
considered rockfall scenarios, a single person in a car, and 4 people in a car (e.g. a family on holiday) have been
considered.
2.1.3 V – Vulnerability of elements at risk
This variable considers the likelihood of fatality should an element at risk be impacted by or collide with a rockfall in
the considered scenarios. As it is assumed that road users will be in a car there is likely a low chance of a fatality
occurring, therefore a value of 0.01 has been selected.
Vulnerability is likely to be variable due to a number of factors such as the age and health of road users, the vehicle
they are travelling in, and the speed that they are travelling at with elderly people, those in more exposed vehicles
such as motorcycles, and those travelling at a greater speed having a higher vulnerability. Walkers and cyclists are
expected to have a higher vulnerability to impact from a rockfall. However, as they are not exposed to the risk of

Page 9

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 9 
AtkinsRéalis - Baseline / Référence
collision with rockfall debris, and they are expected to be less common than those in vehicles, their risk is expected
to be relatively low.
2.1.4 Ex – Exposure
This variable considers the exposure of an element at risk to the considered rockfall hazard.
This section of the B8035 is designated national speed limit, however due to the width of the road it is likely that
vehicles will be moving slower than this. Local road users familiar with the road are likely to be driving significantly
faster than tourists unfamiliar with the area.
A speed of 30 mph has been chosen for this scenario. At this speed a standard car will have a stopping distance of
23 m (The AA, 2024) and will cross the 1 km of road being considered in 75 seconds. This results in a spatial
probability of 0.023, and a temporal probability of 2.36 x 10-6 per year.
Argyle and Bute Council traffic monitoring recorded 330 vehicles using the road daily on average during June 2022.
While this likely represents a peak in road usage, at similar vehicle volumes this results in 120450 traffic movements
per year. 
Further scenarios with 100 journeys per day, and 20 journeys per day have been considered to demonstrate the
impact of reducing the number of journeys has on the level of risk.
2.1.5 RAMMS Rockfall Modelling
Three-dimensional rockfall modelling was undertaken using RAMMS:Rockfall software to assess potential rockfall
trajectories and better understand the dynamics of rockfall events across the site. This modelling provided detailed
outputs on rockfall trajectories, kinetic energy, velocities, and bounce heights, which are critical for informing the
design and placement of mitigation measures.
The rockfall model was constructed using the DSM (Digital Surface Model) generated during the drone survey
conducted on 30/09/2025 at a resolution of 0.25 m.
A seeder line was drawn along the top of the cliff section, and blocks were released at randomly generated points
along this line to give an understanding of runout paths and block velocities across the site. Following this initial
model, additional point locations were specified to cover areas of interest within the site (e.g. below a channel within
the cliff as boulders released above this were diverted down the channel).
The terrain within the model was categorised into two primary types; the cliff face was assigned the “bedrock”
terrain type, while the lower slope was designated as “vegetated talus.” The terrain type dictates how deformable
the terrain is when impacted by a block, and the amount of drag force that an impacting block experiences.
At each release location, two blocks were released at 10 randomly generated orientations. A larger and smaller
block was selected to give an understanding on the impact of block size on runout, bounce height, and kinetic
energy. A block with maximum dimensions of 0.5 m, and a volume of 0.06 m3 (0.5 x 0.5 x 0.5 m) was selected to
represent an average block size observed on site. 
A larger block with maximum dimensions of 2 m, and a volume of 4.3 m3 (2 x 2 x 2 m) was selected to represent the
upper end of likely rockfall events. For both blocks, a “real” rock type was selected (Figure 2-2), as this has more
irregular faces than standard shape blocks (e.g. cube, sphere) and will result in more realistic behaviour. Equant
block shapes were chosen as these have been deemed representative of many of the blocks observed on site, and
are likely to have a greater runout, allowing for a more conservative estimate of block behaviour.

Page 10

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 10 
AtkinsRéalis - Baseline / Référence 
Figure 2-2 - 0.5 m block used during RAMMS rockfall modelling (left), Examples of blocks observed on site
(right)
2.1.6 Rockfall Modelling Results
The model results for a 25 m buffer zone upslope of the road were calculated and are shown in Table 2-1 below.
This allows the block jump height, velocity, and kinetic energy to be estimated within the vicinity of the road. As the
modelling trajectories include an initial free-fall of up to 47 m from the cliff, analysing the results for the whole slope
area would result in unrealistically high values. An example block trajectory can be seen in Figure 2-3. 
0.5 m max dimension block 2 m max dimension block
Whole Modelling Area
Mean/Maximum jump height (m) 0.6 / 3.9 2.1 / 10.0
Mean/Maximum block velocity (m/s) 7.2 / 18.2 13.0 / 26.5
Mean/Maximum block kinetic energy (kJ) 5.8 / 28.6 1357.3 / 4714.1
Assumed High Frequency Area (ch. 700 - 1200)
Mean/Maximum jump height (m) 0.5 / 2.5 2.0 / 6.1
Mean/Maximum block velocity (m/s) 6.2 / 15.7 13.1 / 26.5
Mean/Maximum block kinetic energy (kJ) 4.5 / 22.0 1356.0 / 4714.1
Table 2-1 - RAMMS Rockfall modelling results

Page 11

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 11 
AtkinsRéalis - Baseline / Référence 
Figure 2-3 - RAMMS rockfall modelling output – 0.5 m block trajectory showing rock jump heights.
2.1.6.1 Rockfall runout distance
Within the modelling area, the vast majority of modelled blocks reach the B8035, as seen in Figure 2-4. 87% of total
modelled blocks reach the road with larger blocks being more likely (93%) than smaller blocks (80%). 
Figure 2-4 - RAMMS rockfall modelling block runout results

Page 12

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 12 
AtkinsRéalis - Baseline / Référence
2.1.6.2 Rockfall Modelling limitations
The rockfall modelling was focused on the main area of concern surrounding the recent rockfall events, where
overhanging blocks adjacent to the 2025 failures that could potentially fail further are located and it is assumed that
there could be a higher frequency of rockfall events.
The area east of the modelled area consists of a near-vertical rock face immediately adjacent to the road, indicating
that any detached blocks in this area are extremely likely to reach the road in this location by falling directly down,
as evidenced by the blocks noted to be present on the verge.
The area south-west of the modelled area has very similar topography to the modelled area. This indicates that
detached blocks are likely to behave in a similar manner, reaching the road, as evidenced by the large number of
boulders located adjacent to and downslope of the road. While there is the potential for larger magnitude rockfall
events in this area, overhanging blocks that are now unsupported due to recent failures were not observed on site.
2.2  Updated Risk Assessment - Results
As seen in Figure 2-5, an annual risk of fatalities below 1 x10-6 is considered by the Health and Safety Executive
(HSE) to be broadly acceptable for the public and workers. Risk levels between 1 x10-6 and 1x10-4 per annum is
considered to be within the ALARP (As Low As Reasonably Practicable) region and can be allowed if it is
demonstrated that interventions to reduce the level of risk are likely to be disproportionate to the level of benefit
gained. Risk levels above 1 x10-4 are considered unacceptable to the public and intervention to lower the risk to a
more acceptable level is required. 
Figure 2-5 - Risk tolerability and the ALARP concept (modified from HSE, 1992)  
Tolerable 1x10-4 / Annum for Public 
Broadly acceptable 1x10-6 / Annum, for Public and workers

Page 13

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 13 
AtkinsRéalis - Baseline / Référence
The updated risk values are presented within Table 2-2, showing the impact of reducing the number of journeys,
and reducing the frequency of rockfall events.
Considering 1 person per vehicle:
Frequency 330 Journeys per
day
100 Journeys per
day
20 Journeys per
day
10 rocks per year 5.2 x10 -4 1.6 x10 -4 3.2 x10 -5
1 rock per year 5.2 x10 -5 1.6 x10 -5 3.2 x10 -6
Considering 4 people per vehicle:
Frequency 330 Journeys per
day
100 Journeys per
day
20 Journeys per
day
10 rocks per year 2.1 x10 -3 6.4 x10 -4 1.3 x10 -4
1 rock per year 2.1 x10 -4 6.4 x10 -5 1.3 x10 -5
Table 2-2 - Updated quantitative risk assessment results
At higher levels of rockfall frequency (between 1 and 10 blocks per year), the level of risk is still unacceptable or
within the ALARP region for both single, and multiple occupancy vehicles, even when the number of journeys
through the considered area is reduced to an average of 20 journeys per day throughout a given year. 
This shows that the number of journeys through the site area would need to be significantly reduced to lower the
risk to ALARP or acceptable levels or there would need to be a significant reduction of the frequency of rockfall
events reaching the B8035 through the installation of mitigation measures. 
2.2.1 Limitations for this Preliminary Risk Assessment
This preliminary risk assessment considers the risk per annum and therefore does not take into account daily and
seasonal variations that affect risk levels. The number of vehicles using the road does change seasonally and daily.
This has not been taken into account for this assessment. The data provided is based on vehicles using an adjacent
road during the summer and is likely to incorporate a significant amount of tourist traffic. Over the winter months
traffic levels are likely to decrease, and the number of journeys is likely to vary between 20 and 100.
Storm events are usually a main cause of rockfall events in the UK. These typically occur during the winter months
and while this would increase the risk, the number of vehicles using the road is expected to be less.
It is likely that the risk level overnight decreases significantly as the number of vehicles using the road decreases.
Climate modelling by the Met Office (UKCP18 - (Met Office, 2022)) very generally indicates warmer winters with
prolonged rainfall events, and hotter summers with shorter intense rainfall events. The effects of climate change will

Page 14

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 14 
AtkinsRéalis - Baseline / Référence
vary locally, and this assessment has not taken these into account, but the risk will change with changing
conditions.
This risk assessment does not take into account any measures a driver may take to avoid a falling block. It is likely
that if a block is seen it may be avoided either by breaking or swerving out of the way if possible. As a result, the
risk may be lower than shown. As this is a preliminary risk assessment this level of detail has not been included.
Taking the above factors into account, it is considered that the level of risk sits predominantly in the boundary
between unacceptable and tolerable but under certain conditions it is likely to move into unacceptable levels of risk.
It should be noted that the level of risk is only considered tolerable if methods of risk reduction are considered
impractical or if the cost is grossly disproportionate to the level of improvement gained. Some potential options to
reduce the risk are discussed below with high level estimated budget costs. 
3. Options Development & Appraisal
In response to the identified rockfall hazards along the B8035 corridor, a range of mitigation strategies have been
developed and appraised to reduce the risk to road users. This section outlines the engineering and operational
options considered, including physical interventions such as rockfall barriers and stabilisation netting, as well as
traffic management measures like road closures and enhanced signage. Each option has been evaluated based on
its effectiveness in reducing risk, estimated cost, long-term maintainability, and implementation timescale.
The costs presented in this report are approximate estimates to assist in helping to identify likely remedial options
that are not disproportionate in terms of cost to the benefit gained. The costs will change subject to market
conditions, availability of materials and resources, and will also vary with the design approach, hence they should
not be relied upon for setting budgets. We recommend that the costs be revised at each stage of the design
process. Should an accurate estimate for budgeting purposes be required, a suitable cost exercise should be
undertaken by an appropriately qualified quantity surveyor/estimator.
3.1 Road closure except for local access
Restricting access to the B8035 corridor to local traffic only is expected to reduce the overall risk to road users by
limiting the number of journeys through the identified rockfall hazard zone. As demonstrated in the updated risk
assessment, this reduction in exposure correlates with a lower probability of fatality; however, at the upper end of
the assumed rockfall frequency (i.e. 10 rockfall events per year), the residual risk remains unacceptable for vehicles
carrying four occupants and falls within the ALARP zone for single-occupant vehicles. 
Installation of gates to allow for local access while preventing access to the public would be required.
Following closure of the road, it would need to be ensured that adequate information on the remaining risks to local
road users is communicated to allow for informed decision making on usage of the road.
3.2 Road closure during high rainfall events
Closing the road during storm or high rainfall events where rockfall events are potentially more likely to occur would
reduce the risk to road users by ensuring that they are not within the at-risk area during a rockfall and allowing for
the road to be inspected before opening, reducing the likelihood of vehicles colliding with rockfall debris.

Page 15

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 15 
AtkinsRéalis - Baseline / Référence
Due to the lack of information on the timing of rockfalls beyond the known events in summer 2025, the correlation
between rockfall events and high rainfall cannot be confirmed. 
The known 2025 events show limited correlation with high rainfall values.
Data from a SEPA rainfall gauge located in Tobermory (19 km away - North), and gauges managed by Argyll and
Bute Council located in Dervaig (16 km away - North), and Lochdonhead (26 km away - East) is shown in Figure 3-
1. 
During the initial rockfall event on 02/07/2025 values between 0.1 and 7.0 mm were recorded. Rainfall values of up
to 25.6 mm were recorded in the preceding days indicating that rainfall may have contributed to this event.
During the second rockfall on 06/08/2025 values between 6.0 and 15.3 mm were recorded. This rockfall event
showed slightly increased rainfall (up to 31.1mm) in the preceding days. However, these values were recorded at
the Lochdonhead gauge which is furthest from the site location. 
Figure 3-1 - Precipitation data during July/August 2025. Note SEPA gauges record daily data from 9am to
9am, and the Argyll and Bute Council gauges record data from 6am to 6am, therefore rainfall between these
times may show on different days.
While increased rainfall is likely to increase the risk of rockfall, it is not possible to establish a direct relationship with
the currently available information on rockfall frequency. Freeze-thaw effects on the cliff face are likely to be another
significant triggering factor for rockfall and would need to be considered, likely resulting in significant closures over
winter.
Climate modelling indicates that Scotland is projected to experience an increase in rainfall during the winter and
decrease during the summer. Summer precipitation is projected to decrease overall. However, heavy rainfall events
are expected to increase in intensity, with extreme events indicated to increase in frequency. The convective
(summer storm) season is projected to extend into autumn, giving an increase in heavy hourly rainfall events into
the autumn (Rivington & Jabloun, 2022). These higher intensity rainfall events may have an increased risk of
rockfall events occurring.
This option would likely have minimal installation costs; however, it would require monitoring of predicted rainfall
events, and personnel to attend site to close the road and conduct an inspection of the road prior to opening. A
rainfall monitoring gauge would be required to be installed on site to improve the accuracy of precipitation data as
the closest available data is located within Dervaig, 16 km from the site. A rockfall management plan would be
required to be developed to confirm the weather thresholds needed to trigger closure of the road.
0
10
20
30
40
50
60
21/06/2025
28/06/2025
05/07/2025
12/07/2025
19/07/2025
26/07/2025
02/08/2025
09/08/2025
16/08/2025
23/08/2025
30/08/2025
Precipitation (mm)
B8073 Dervaig SEPA Tobermory A849 Lochdonhead Rockfall

Page 16

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 16 
AtkinsRéalis - Baseline / Référence
3.3 Earthwork Bund
Given the energy levels of the falling blocks, indicated by the rockfall modelling presented in Section 2.1.5, it is likely
that a substantial earthwork bund would require a height between 4 to 8 m in height. The practicality of constructing
this at the toe of the slope is likely to be problematic. There would also be a requirement to import a substantial
amount of material to form the bund, which could be a significant cost. As a result, this option has not been
considered further.
3.4 Rockfall Barriers
The installation of rockfall catch fences across the site would significantly reduce the risk of rockfalls reaching the
road by intercepting and containing falling debris. 
To cover the total site area, approximately 1800 m of fencing would be required, as fences are not suitable in areas
where the rockface is immediately adjacent to the road. Overlap of individual fences would be required to provide
full coverage of the road so the exact length of fencing required would be determined during detailed design.
Assuming a cost of £2000 per m of fence, this would result in an estimated cost of £3.6 million, not accounting for
mobilisation costs. 
A reduced fence length of 500 m, focused on the central section of the site near the 2025 rockfall location, would
target the area with the highest observed concentration of boulders adjacent to the road. This targeted approach is
estimated to cost approximately £1 million.
The installation of catch fences would result in ongoing inspection and maintenance costs. Manufacturers such as
Geobrugg recommend annual inspections under normal environmental conditions, with additional inspections
following any reported rockfall events. Automated systems which can alert asset owners of rockfall impacts to
fences are available with associated additional installation and monitoring costs.
As holding rockfall material will reduce the potential capacity of installed rockfall fences, removal of material would
be required following larger rockfall events. Several components of rockfall fences are designed to extend during
rockfall impact to absorb energy and these components are likely to need replacement following rockfalls. Due to
the sites coastal location, it is likely that an installed rockfall fence will experience an increased rate of corrosion,
therefore increased maintenance, or corrosion resistant material, will be required.
Design and installation of 500 m of rockfall fences would be typically expected to take approximately 6 months to
complete.
Should the targeted length of rockfall fences be chosen, scaling works would be required to remove loose material
across the rest of the site area to reduce the likelihood of a rockfall event occurring, particularly within areas where
lines of sight are reduced around corners, as the risk is likely to remain high within these areas 
It is also likely that inspection and scaling of any loose material would be required within the fenced area to reduce
the risk to workers during construction.
3.5 Rock Stabilisation Netting
The installation of stabilisation netting across the rock face would significantly reduce the risk of rockfalls impacting
the adjacent road by limiting the frequency and volume of material reaching the carriageway. A stabilisation system
or system with a closed base would be required as opposed to an open draped system as it is likely that  blocks
reaching the base of a draped system would roll down the slope and reach the road.

Page 17

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 17 
AtkinsRéalis - Baseline / Référence
To cover the entire site area an estimated 160 000 m2 of netting would be required. Based on an indicative unit cost
of approximately £400 per m2, would be estimated to cost around £65 million. However, this figure could be reduced
by adopting a targeted approach, focusing on high-risk areas identified during detailed design and geotechnical
assessment.
Installing netting to the central 500 m with an assumed higher frequency would require approximately 50 000 m2 of
netting, at an approximate cost of £20 million.
Should the targeted length of rock stabilisation netting be chosen it is likely that scaling works would be required to
remove loose material across the rest of the site area. It is also likely that inspection and scaling of any loose
material would be required within the netting area to reduce the risk to workers during construction.
3.6 Inspection and Scaling
Regular inspection of the rock face and scaling to remove loose material would reduce the risk to the road by
reducing the potential number of rocks reaching the road. The level of risk from the reduction in rockfall frequency
can be seen in Table 3-1 below.
Considering 1 person per vehicle:
Frequency 330 Journeys per
day
100 Journeys per
day
20 Journeys per
day
0.1 rocks per year (every 10 years) 5.2 x10 -6 1.6 x10 -6 3.2 x10 -7
0.01 rocks per year (every 100 years) 5.2 x10 -7 1.6 x10 -7 3.2 x10 -8
Considering 4 people per vehicle:
Frequency 330 Journeys per
day
100 Journeys per
day
20 Journeys per
day
0.1 rocks per year (every 10 years) 2.1 x10 -5 6.4 x10 -6 1.3 x10 -6
0.01 rocks per year (every 100 years) 2.1 x10 -6 6.4 x10 -7 1.3 x10 -7
Table 3-1 - Updated quantitative risk assessment results
A reduction in the frequency of events to below 0.1 per year would result in the level of risk being acceptable or
within the ALARP region for all considered number of journeys for both single and multiple occupancy vehicles.
Given the extensive area of exposed rock within the site, the initial scaling works are anticipated to be a major
undertaking. The scale of the task is such that it is likely to represent one of the largest rock scaling projects
undertaken in the UK. The process is expected to be slow and logistically complex due to the limited available
workforce and difficulty of access to much of the rock face.

Page 18

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 18 
AtkinsRéalis - Baseline / Référence
A preliminary estimate suggests that the initial scaling programme could extend over a period exceeding 12 months.
Based on an assumed unit cost of approximately £10 per square metre for light scaling using hand tools, the total
cost to scale the entire rock face is estimated at approximately £2 million. This does not account for heavy scaling
which requires the use of machinery such as jacks or expanding grout, which is expected to cost approximately
£300 per m2. 
Regular scaling is expected to be required to maintain the stability of the rock face. Initially an intensive, and higher
cost, programme of scaling would be required to inspect the whole site area and remove any high-risk material. The
intensity, and cost, of scaling required would then decrease as unstable material is removed. Ongoing weathering
processes would then contribute to areas of instability meaning that periodic intensive, and higher cost, intervention
would be required. This process would be a repeat cycle. 
Targeted areas of scaling to reduce risk could be undertaken, for example, the initial section of the rock face
adjacent to the road, between chainages 0–200, where the road alignment includes tight bends and reduced
stopping distances, presents a higher risk and could be prioritised. Scaling in this area is estimated to cost
approximately £50 000. Scaling of the 500 m assumed higher frequency area would cost approximately £500 000.
Additional scaling would likely be required for other proposed interventions where workers are likely to be present
during construction.
3.7 Reopen the road with additional signage
Reopening the road with additional signage warning road users of the high rockfall risk and to proceed at their own
risk has been considered. If drivers are aware, they may be more prepared to take appropriate actions (if possible)
to avoid falling and fallen blocks, however this is hard to quantify.  It is assumed that additional signage is unlikely to
reduce the liability to Argyll and Bute Council should there be a serious injury or fatality due to rockfall. 
Should Argyll and Bute Council wish to pursue this option, it is recommended that additional measures such as
scaling of cliffs next to the road should also be included to reduce the risk. It is also recommended that the potential
legal implications and liabilities associated with road user safety be reviewed in consultation with Argyll and Bute’s
legal team.

Page 19

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 19 
AtkinsRéalis - Baseline / Référence 
3.8 Options Summary
Mitigation Option Effectiveness Estimated Cost Long-term Maintainability Estimated Timescale
Reopening with additional
signage
Low – unlikely to reduce risk
and liability
Cost of sign installation Limited maintenance
required
Weeks - months
Road closure with local
access
Removes the risk to the
public accessing the site
within vehicles. Risk remains
to those accessing on foot or
cycling; however, this risk is
expected to be lower
Cost of permanent barrier
installation and legal process
to close the road
No maintenance costs. 3 months + dependant on
legal process
Road closure during rainfall
events
Low without further rockfall
monitoring to increase
understanding of rainfall
relationship
Costs for developing a
rockfall management plan
and installing a barrier.
Staffing costs for monitoring
and closing the barrier. 
Limited maintenance
required. Ongoing
monitoring and staffing
required to close the barrier
Weeks - months
Earthwork Bund Not considered further due to constructability issues
Rockfall Fences - Whole
slope
High – reduces likelihood
detached rocks from
reaching the road
£3.6 million Regular inspections and
maintenance following
rockfall events
1-2 years
Rockfall Fences – Targeted
(example 500m)
Moderate – reduces
likelihood detached rocks
from reaching the road
within the assumed higher
frequency area
£1 million Regular inspections and
maintenance following
rockfall events
6-8 months

Page 20

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 20 
AtkinsRéalis - Baseline / Référence
Mitigation Option Effectiveness Estimated Cost Long-term Maintainability Estimated Timescale
Rock Stabilisation Netting –
Whole slope
High – prevents detached
rocks from reaching the road
£65 million Regular inspections and
maintenance following
rockfall events
1-2 years
Rock Stabilisation Netting –
Targeted (example 500m)
Moderate - prevents
detached rocks from
reaching the road
£20 million Regular inspections and
maintenance following
rockfall events
6-12 months
Scaling – full slope High – reduces the number
of detached rocks, reducing
risk
£2 million (£10/m2 light
scaling, increases with any
required heavy scaling)
High cost of initial scaling.
Required further work at
regular intervals however
this will be significantly lower
than initial costs
1-2 years for initial
inspection and scaling
Scaling – Targeted (example
500m)
Moderate - reduces the
number of detached rocks,
reducing risk within assumed
higher risk areas
£500 000 High cost of initial scaling.
Required further work at
regular intervals however
this will be significantly lower
than initial costs
6-12 months
Table 3-2 - Risk reduction options summary

Page 21

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 21 
AtkinsRéalis - Baseline / Référence
4. Conclusion
This final options report presents an updated assessment of the geohazard risks posed to users of the B8035. The
updated hazard modelling, incorporating RAMMS rockfall modelling and site-specific observations, confirms that the
likely frequency of rockfall events pose a risk level that is probably on the boundary of Tolerable / Unacceptable
regions but under certain conditions / circumstances is likely to move into the Unacceptable level of risk, especially
in areas that may have higher rockfall frequency, or where the cliff face is directly adjacent to the carriageway with
reduced lines of sight.
The Quantitative risk assessment is preliminary and there are a number of factors that have been simplified, such
as annual rockfall frequency and some factors such as drivers reaction to break or avoid fallen rocks that have not
been taken into account.
Mitigation options which are likely to reduce the level of risk to an acceptable or ALARP level have been presented
in Table 3-2. To take the project onto the next stage we recommend that Argyll and Bute Council undertake a
review and determine the most appropriate two remedial options or combined options (e.g. signage and scaling of
specific areas) that manage their risks at a tolerable level. These two options could then be progressed further to
enable a budget to be set for the project, and detailed consultation with appropriate stakeholders. The most
beneficial option, in terms of cost, programme, and risk reduction could then be taken forward to the next stages of
implementation.

Page 22

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 22 
AtkinsRéalis - Baseline / Référence 
5. References
Koe, A., Murphy, W., Parry, S., Daykin, A., Smith, J., & Battye, S. (2023). Natural slopes and landslides - condition,
assessment, and mitigation. C810. London, UK: CIRIA.
Met Office. (2022). UK Climate Projections: Headline Findings (Version 4, August 2022). Exeter: Met Office.
Rivington, M., & Jabloun, M. (2022). Climate Trends and Future Projections in Scotland. Deliverable D2.1a for the
Project D5-2 Climate Change Impacts on Natural Capital. Aberdeen, Scotland: The James Hutton Institute.
The AA. (2024, July 09). Closer than you think: Know your stopping distances. Retrieved October 06, 2025, from
https://www.theaa.com/breakdown-cover/advice/stopping-distances

Page 23

AtkinsRéalis - Baseline / Référence
APPENDICES

Page 24

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 24 
AtkinsRéalis - Baseline / Référence
Appendix A. Road chainage 
Figure A-1 - Road chainage

Page 25

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 25 
AtkinsRéalis - Baseline / Référence
Appendix B. Geotechnical Risk Register
A Geotechnical Risk Register has been created to identify geotechnical hazards and establish a method for their
management for the B8035 Gribun rockfall.
Risk is a function of probability that a hazard may occur and its potential impact. The Risk Register reflects the
current level of understanding of the geotechnical aspects of the scheme and will be subject to revision as the
project progresses when further information becomes available.
The risk rating used in the risk register follows the principle;
Risk Rating (RR) = Likelihood (L) x Severity (S)
Likelihood
Severity
1 2 3 4 5
Minor Moderate Serious Major Catastrophic
1 Extremely unlikely 1 2 3 4 5
2 Unlikely 2 4 6 8 10
3 Likely 3 6 9 12 15
4 Extremely Likely 4 8 12 16 20
5 Almost Certain 5 10 15 20 25 
Potential severity of harm occurring
1 Minor Minor damage or loss – (no human injury)
2 Moderate Moderate damage or loss – (slight injury or illness)
3 Serious Substantial damage or loss – (serious injury or illness)
4 Major Major damage or loss – (fatal injury)
5 Catastrophic Catastrophic damage or loss – (multiple fatalities) 
Risk Classification
Low (1-8) Ensure assumed control measures are maintained and reviewed as necessary.
Medium (9-19) Additional control measures needed to reduce risk rating to a level that is
tolerable.
High (20-25) Activity not permitted. Hazard to be avoided or risk to be reduced to tolerable
level.

Page 26

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 26 
AtkinsRéalis - Baseline / Référence 
No. Location Hazard Consequence
Before
Control Design Measures to Eliminate
Hazards Design Measures to Reduce risk
Residual Risk
L S RR L S RR
Natural Terrain Hazards
1
Whole scheme Rockfall from crags and
exposures.
Blocked public access.
Damage to B8035 Road.
Road closures resulting in emergency response,
traffic flow disruptions, ongoing maintenance and
long diversions.
Unstable ground caused by landslide / rockfall
events.
Delays to programmes and additional cost
Injury/death of public and/or workers.
5 5 25
It is not possible to eliminate the
identified hazard.
Refer to report Section 3.
4 2 8
2
Whole scheme Landslides from slope
above B8035. 
Blocked public access.
Damage to B8035 Road.
Road closures resulting in emergency response,
traffic flow disruptions, ongoing maintenance and
long diversions.
Unstable ground caused by landslide / rockfall
events.
Delays to programmes and additional cost
Injury/death of public and/or workers.
3 3 9
It is not possible to eliminate the
identified hazard.
Detailed geohazard assessment considering
possible failure locations, volumes of material and
travel velocities.
Installation of rockfall fences to protect the road and
users from rockfall. Installation of rock stabilisation
netting to capture rockfall at source locations.
Ongoing monitoring of slope for further deterioration
and increased instability. 
Ensure level of residual risk is understood by all
parties. Constructability review with input from
contractors as required.
3 2 6
3
Whole scheme Challenging terrain and
complex topography
Complex topography requiring complicated
earthworks designs, structures and foundations as
well as significant temporary works, with slope
stabilisation required during construction.
Injury/death of workers.
Additional costs for plant delivery or large-scale
enabling works
5 4 20
It is not possible to eliminate the
identified hazard.
Early contractor involvement.
Detailed geohazard assessment considering
possible failure locations, volumes of material and
travel velocities.
Detailed drone surveys at regular intervals to
provided high resolution data to contractor and
inform understanding of topographical changes with
time. 
5 3 15
4
Whole scheme Unstable ground created
from landslide, debris flow
or site works upslope.
Debris reaching the route and impacting the road and
construction operations. 
Road closures resulting in emergency response,
disruption in traffic flows, ongoing maintenance and
lengthy diversions. 
Damage to existing road and proposed resilience
measures. 
Damage/erosion of hillside downslope of B8035.
3 5 15
It is not possible to eliminate the
identified hazard.
Design of slope stabilisation measures and
protection measures, as required.
Ensure level of residual risk is understood by all
parties.
Constructability review with input from contractors
as required.
2 4 8

Page 27

B8035 - Mull Rockfall Final Options
Report
2.0 | 12 November 2025 27 
AtkinsRéalis - Baseline / Référence 
No. Location Hazard Consequence
Before
Control Design Measures to Eliminate
Hazards Design Measures to Reduce risk
Residual Risk
L S RR L S RR
Geotechnical risks
5
Whole scheme Unforeseen ground
conditions
Ground unsuitable for earthworks or structure
foundations. 
Delays to programme and additional cost.
3 3 9
Identify areas where more
information is required. 
Provide representative ground
investigation coverage across
the site, based on an
understanding of the
geomorphological processes
that have influenced the geology
of the route.  
Ground investigation undertaken
(where needed), testing and
walkovers to confirm ground
conditions across the study
area.
Ongoing site walkovers and drone surveys to
identify any areas of change. 
2 3 6
6
Whole scheme Variable/uncertain depth
to rockhead
Delays to programme and additional cost for breaking
out /
over dig and mobilisation of suitable equipment.
4 4 16
Ground investigation undertaken
to confirm depth to bedrock
including surface geophysical
surveys and exploratory holes
with adequate coring to confirm
weathered horizons and
potential boulders. 
It is not possible to eliminate the
identified hazard.
Sensitivity assessment for foundation and slope
designs to account for rockhead variation.
Detailed excavatability assessments as required.
Design for observational approach to slope
stabilisation and foundation requirements. 2 3 6
7
Whole scheme Steep slope gradients Difficult access for construction.
5 4 20
It is not possible to eliminate the
identified hazard.
Constructability review with input from contractors
as required. 2 4 8
8
Whole scheme Site conditions corrosive
to steel and/or concrete
Shortened lifespan of buried steel and/or concrete
elements, leading to increased maintenance costs.
Corrosion of steel components due to coastal
location 3 2 6
It is not possible to eliminate the
identified hazard.
Use of corrosion resistant materials 
Perform GI to confirm ground conditions.
Undertake geochemical testing and appropriate
concrete class design.
Employ appropriate mitigation measures during
design. 
2 2 4

Page 28

AtkinsRéalis - Baseline / Référence 
Craig Parry
AtkinsRéalis UK Limited
2 Atlantic Square
York Street
Glasgow
G2 8NJ 
<contact info> 
© AtkinsRéalis UK Limited except where stated otherwise