ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE 18 DECEMBER 2025 
UPDATE ON MEASURES TO PROTECT AGAINST ROCKFALLS ON B8035,
GRIBUN, MULL 
1.0 EXECUTIVE SUMMARY 
1.1 The B8035 at Gribun links a number of remote communities and is a popular
tourist destination. It is also a key location for local events such as the Mull
Rally.
1.2 In July 2025, the first of three significant rockfalls occurred on the B8035 at
Gribun, Isle of Mull.
1.3 Further rockfalls followed in August and September, prompting immediate
closure of the road.
1.4 Since closure of the road, drone and geotechnical surveys have been
conducted on the hillside above the road. The reports arising from these
surveys have been received by the council and are currently being evaluated
by council officers
1.5 A number of options have been identified by these reports ranging from “do
nothing” to the installation of rockfall fences, and scaling of loose material
from the rock face.
1.6 This report explores these options, their cost and the impact of the closure on
local communities 
1.7 RECOMMENDATIONS 
Members of the Environment, Development and Infrastructure Committee are
invited to - 
1. Note the options outlined in Table 4.1, and agree that officers continue to
work with partners to identify an option that keeps risk as low as
reasonably practicable having regard to:

Page 2

i. the likelihood and
ii. the impact of any rockfall versus the cost of prevention. 
2. Note that a further update report will be brought to a future EDI Committee
as soon as a preferred option and costings have been identified.

Page 3

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE 18 DECEMBER 2025 
UPDATE ON MEASURES TO PROTECT AGAINST ROCKFALLS ON B8035,
GRIBUN, MULL 
2.0 INTRODUCTION 
2.1 The B8035 at Gribun links a number of remote communities and is a popular
tourist destination. It is also a key location for local events such as the Mull
Rally.
2.2 The road has been vulnerable to rockfalls since it was built, although these
have not been recorded until recently.
2.3 In the summer of 2025, three rockfalls / landslides were reported to the
council. The road has been closed since August of this year to protect road
users from serious injury, and to allow officers to develop long term options for
the safe use of the road.
2.4 This report outlines these options, as well as the impact that the current road
closure is having on nearby communities 
3.0 RECOMMENDATIONS 
3.1 Members of the Environment, Development and Infrastructure Committee are
invited to - 
1. Note the options outlined in Table 4.1, and agree that officers continue to
work with partners to identify an option that keeps risk as low as
reasonably practicable having regard to:
iii. the likelihood and
iv. the impact of any rockfall versus the cost of prevention. 
2. Note that a further update report will be brought to a future EDI Committee
as soon as a preferred option and costings have been identified.

Page 4

4.0 DETAIL 
4.1 Since the council closed the B8035 at Gribun on the Isle of Mull in August
2025, geotechnical surveys have taken place to identify
• Potential causes of the rockfalls and landslides,
• The frequency at which these happen,
• The potential impacts that they could have on road users, and
• The preventative measures that should be considered, and their cost.
4.2 We have been working with local famers and the NFU, and local members have
been kept informed, particularly regarding impacts on local events such as the
Mull Rally. Public updates are provided via the council’s website and social
media channels. Engagement with residents and businesses continues to
ensure awareness of the closure, the reasons for it and the diversion route.
4.3 In the meantime, a diversion has been put in place via the A849 Kinloch–
Craignure–Salen route. This route is approximately 22 miles long.
4.4 The implementation of preventative measures is complicated by the remote
location involved, and the confined nature of the site being located next to the
sea and at the bottom of a cliff.
4.5 The most recent report by our geotechnical consultants, Atkins Realis, was
received by the council on 12th November 2025. 5. The updated hazard
modelling, incorporating rockfall modelling and site-specific observations,
confirms that the estimated frequency of rockfalls poses a risk level that is on the
boundary of Tolerable / Unacceptable. Under certain conditions or
circumstances such as increased rainfall or increased vehicle movements, this
is likely to move into the Unacceptable level of risk, especially in areas: 
• That may have higher rockfall frequency, or 
• Where the cliff face is directly adjacent to the carriageway with reduced
lines of sight. 
4.6 The quantitative risk assessment is preliminary and there are a number of
factors that have been simplified, such as annual rockfall frequency and some
factors such as drivers' reaction to avoid fallen rocks that have not been taken
into account. Mitigation options which are likely to reduce the level of risk to an
acceptable level have been presented in Table 4.1 below.

Page 5

4.7 To take the project onto the next stage, Atkins Realis recommend that the
council undertakes a review and determines the most appropriate two remedial
options or combined options (e.g. signage and scaling of specific areas) that
manage our risks at a tolerable level. These two options can then be progressed
to enable a budget to be set for the project, and detailed consultation with
appropriate stakeholders. The most beneficial option, in terms of cost,
programme, and risk reduction could then be taken forward to the next stages of
implementation.
Table – Summary of options
Mitigation Option Effectiveness Estimated Cost Long term
maintainability
Estimated
timescale
Reopening with
additional signage
Low – unlikely to
reduce risk and liability
Low – limited to cost
of signage
Limited maintenance
required
Weeks /
months
Road closure with local
access
Removes the risk to the
public accessing the
site with vehicles. Risk
remains to those
accessing on foot or
cycling.
Cost of permanent
barrier installation at
each end of closure
plus cost of
implementing new
Traffic Regulation
Order (TRO)
Limited maintenance
required. Ongoing
monitoring and staffing
required to close the
barrier
At least 3
months,
dependant on
TRO process
Road closure during
rainfall events
Low without further
rockfall monitoring to
increase understanding
of relationship between
weather and rockfalls /
landslides 
Costs for developing
rockfall management
plan and installing
barrier. Staffing costs
for monitoring and
closing barrier
Limited maintenance
required. Ongoing
monitoring and staffing
required to close the
barrier
Weeks /
months
Earthwork bund Not considered due to expansive prohibitive costs
Rockfall fences – whole
slope
High – reduces
likelihood of detached
rocks reaching the road
£3.6 million with
subsequent
maintenance and
inspections costs
Regular inspections
and maintenance
following rockfall events
1 – 2 years
Rockfall fences -
targeted
Moderate – reduces
likelihood of detached
rocks reaching the road
within the assumed
higher frequency area
£1 million with
subsequent
maintenance and
inspections costs
Regular inspections
and maintenance
following rockfall events
6 – 8 months
Rock Stabilisation
Netting – Whole slope
High – prevents
detached rocks from
reaching the road
£65 million with
subsequent
maintenance and
inspections costs
Regular inspections
and maintenance
following rockfall events
1 – 2 years
Rock Stabilisation
Netting – Targeted
(example 500m)
Moderate - prevents
detached rocks from
reaching the road
£20 million with
subsequent
maintenance and
inspections costs
Regular inspections
and maintenance
following rockfall events
6 – 12
months
Scaling – full slope High – reduces the
number of detached
rocks thereby reducing
risk
£2 million with
subsequent regular
scaling and
inspection work costs
High cost of initial
scaling. Required
further work at regular
intervals. However, this
will be significantly
lower than initial costs
1 – 2 years
for initial
inspection
and scaling
Scaling - targeted Moderate – the number
of detached rocks
thereby reducing risk
within assumed higher
risk areas
£500,000 with
subsequent regular
scaling and
inspection work costs
High cost of initial
scaling. Required
further work at regular
intervals. However, this
will be significantly
lower than initial costs
6 – 12
months

Page 6

4.8 It should be noted that the proposals, costs and timescales are extremely high
level and are only indicative. Further work will be required by council officers
working in conjunction with specialist quantity surveyors to develop preferred
options and costings. In the meantime, the road will remain closed until a final
decision is made on implementation of a preferred option.
5.0 CONCLUSION
5.1 Local feedback has been received which outlines that the community and
specifically the local farmer believe that the Council have been overprotective
in the closing of the road and there has been instances where the road
closure barriers have been removed and vehicles are using the road despite it
being closed. This has been reported to Police Scotland for further
investigation.
5.2  The council is taking a safety-first approach to addressing the issues presented
by the rockfalls and landslides at the cliffs at Gribun. The closure of the B8035 is
a necessary precaution while expert assessments are completed. 
5.3 The council is committed to identifying a solution that balances risk, affordability
and access for the communities affected. In the meantime, diversions and
community engagement are being maintained to minimise disruption.
6.0 IMPLICATIONS
6.1 Policy – none.
6.2 Financial – the cost of undertaking the surveys completed to date will be
£22,400. No further financial commitments have been made at this time, and
will be dependent on a preferred option being identified and agreed.
6.3  Legal – the principal legislation covering road safety in Scotland is the Roads
(Scotland) Act 1984. This Act defines management and maintenance
obligations as follows: 
a. Maintain all public roads 
Councils must manage and maintain roads listed in their list of public roads.
The Act Includes powers to reconstruct, alter, widen, improve, or renew roads. 
b. Risk-based maintenance approach 
While there is no statutory maintenance standard, councils are expected to
adopt best practice (e.g., SCOTS guidance and UK Code of Practice) for
inspections and repairs. It recommends risk-based regimes for addressing
defects like potholes, prioritising based on safety risk rather than fixed
intervention levels.
6.4  HR – none.
6.5 Customer Service – stakeholders including elected members and

Page 7

communities have been kept up to date on the council’s actions to address
the issues at Gribun via a dedicated page on the council’s website. 
6.6 Risk – this is currently being addressed using the powers and responsibilities
within the Roads (Scotland) Act 1984 as identified in paragraph 6.3.
6.7 Climate Change – whilst there is reference in the geotechnical report by
Atkins Realis to the impacts that climate change will have on future incidents
at Gribun, the action currently being taken have no direct impact on the
council’s climate change activities.
6.8  Fairer Scotland Duty – none.
6.9 Equalities - protected characteristics – none.
6.10 Consumer Duty – none.
6.11 Island Communities – none at this time.
6.12 Children’s Rights and Wellbeing – none.
Kirsty Flanagan
Executive Director with responsibility for Development and Infrastructure
Services
Policy Lead John Armour
30 November 2025                                                  
For further information contact:
Andy Summers, Head of Roads and Infrastructure Services
Hugh O’Neill, Network and Standards Manager 
APPENDICES
Appendix 1 – Geotechnical Report from AtkinsRealis, 12 November 2025