ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE SERVICES        18 DECEMBER 2025 
REST AND BE THANKFUL ROUNDTABLE DISCUSSIONS REPORT 
1.0 EXECUTIVE SUMMARY 
1.1 Landslips on the A83 at the Rest and Be Thankful have been a recurring issue for
decades. They became a major and persistent problem in the mid-2000s 
1.2 The first widely reported closures occurred in October 2007 and September 2009,
following heavy rain, caused significant disruption and long diversions. These
events highlighted the vulnerability of the route to debris flows and slope
instability. 
1.3 Since 2010, landslides have occurred more frequently and with greater impact,
prompting Transport Scotland to invest in mitigation measures such as debris
fences and catch pits. 
1.4 Two unprecedented landslides in August and September 2020 deposited 6,000
and 10,000 tonnes of material on the road, leading to prolonged closures and
accelerating plans for a long-term solution (including a proposed debris flow
shelter). 
1.5 Despite mitigation, landslips continue regularly, with notable incidents in 2023,
2024, and 2025, including closures after heavy rainfall and debris flows of
hundreds of tonnes. The frequency and intensity have increased due to climate-
related factors like more intense rainfall. 
1.6 In summary: Landslips have affected the A83 for at least 20 years, but the
problem has become critical since 2007 and particularly severe since 2020.

Page 2

1.7 The Scottish Government is in the process of reviewing short, medium and long
term plans for the Rest and Be Thankful. This report gives details on the solutions
being presented as well as local concerns raised via a Round Table Group
sanctioned by the Transport Secretary for Transport Fiona Hyslop and Chaired
by Jenni Minto MSP. 
1.8 Currently there are three stages being taken forward by Transport Scotland as
mitigation measures for the issues being experienced at the Rest and be Thankful
for many years which have adversely affected local businesses in Argyll and Bute.
Short, Medium and Long-term measures are presented at a high level in this
report. 
1.9 A summary of the Roundtable discussions is further reported.

Page 3

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE SERVICES   18 DECEMBER 2025 
REST AND BE THANKFUL ROUNDTABLE DISCUSSIONS REPORT 
2.0 INTRODUCTION 
2.1 This report advises of the current and planned measures to mitigate against the
closures and works to the A83 Rest and Be Thankful by the Scottish
Government as well as updating the committee on the Roundtable stakeholder
discussions chaired by Jenni Minto MSP. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that members of the EDI Committee 
a. consider the contents of this report and the concerns raised by local
stakeholders.
b. Note that
i. these concerns have been summarised in a letter to the Cabinet
Secretary for Transport (Appendix 1) 
ii. a response has been received from the Cabinet Secretary for Transport
(Appendix 2) acknowledging the economic and wellbeing concerns and
that 
iii. the Cabinet Secretary for Transport has instructed Transport Scotland to
review the work undertaken to date in relation to providing two-way
operation for the MTS including use of the forestry track and a full two
way road option.

Page 4

4.0 DETAIL 
4.1 Short-Term measures currently in use when the A83 at the Rest and Be
Thankful is closed for weather events such as landslips and associated flooding
include the below:
• the use of the Old Military Road as a diversion.
• Convoy system: When the Old Military Road is in use, traffic is managed under
a convoy system.
• Traffic management: Temporary traffic lights may be used on the A83.
• Landslide mitigation: Physical measures include debris fences, roadside catch-
pits, and improved drainage systems.
• Monitoring: Daily monitoring of the A83 includes checking weather forecasts and
geotechnical inspections to assess risk.
Medium Term Measures include:
• Improving the Old Military Road (OMR): The OMR is being upgraded to be more
resilient and better operated as a diversion route. The southern section of the
OMR has already been realigned.
• Managing landslide risk: The solution will address landslide issues at the Rest
and Be Thankful location on the A83.
• Connecting to the local road network: The plan includes connecting the
proposed works to the local road network, specifically the B828.
• Consultation and planning
• An Environmental Impact Assessment (EIA) was published in December 2024,
with a statutory consultation period ending February 7, 2025.
• Draft Road Orders were sent out for engagement at the end of 2024, which
forms part of a consultation process.
Long Term measures include:
• Debris flow shelter: The preferred long-term solution is a 1.4 km debris flow
shelter, which will be built along the line of the existing A83.
• Construction timeframe: The construction is estimated to take three to four years
after improvements are made to the Old Military Road.
• Additional features: The project also includes upgrades to the car park and
viewpoint and a new active travel link. 
4.2 The Cabinet Secretary for Transport currently chairs the A83 Task Force with
the below remit: 
Primary Objective: 
• To oversee delivery of actions required to deliver the short, medium and long
term solution. 
• To ensure communications are shared with wider stakeholders.

Page 5

Secondary Objective: 
• To input and provide oversight on the ongoing road operation and
maintenance work on the wider A83 Trunk Road. 
• To ensure communications are shared with wider stakeholders.
4.3 As a result of
• wider stakeholder concerns and in particular local businesses and
• representation from the Policy Lead for Roads and Infrastructure in Argyll and
Bute Council
regarding the Medium and Long term solutions, the Cabinet Secretary agreed to
a Roundtable event being chaired by Jenni Minto MSP to take place and report
back their findings to the Rest and be Thankful Stakeholder Group. 
The roundtable event held in Inveraray on 12 September 2025, brought together
Jenni Minto MSP, Brendan O’Hara MP, Jackie Baillie MSP, elected officials,
business leaders, transport providers, and community representatives to discuss
the impact of the proposed four-year closure of the A83 at the Rest and Be
Thankful (RABT), with reliance on the Old Military Road (OMR) as a diversion. 
The consensus across all sectors was clear: the current proposal poses a
significant economic, social, and human risk to Argyll and Bute.
4.4  Key Issues raised:
4.4.1 Transport & Logistics 
• Hauliers reported severe delays and increased costs due to the single-lane
OMR. 
• Two-way access is essential for operational viability. 
• Driver regulations and compliance issues are exacerbated by delays. 
• Western Ferries could offer partial relief but lacks capacity for dangerous
goods.
4.4.2 Business & Industry 
• Aquaculture, timber, agriculture, and whisky sectors face rising costs,
reduced competitiveness, and potential job losses. 
• Timber sector forecasts a 10–50% cost increase depending on route. 
• Construction and housing industries fear stagnation and reduced
workforce due to access issues.

Page 6

4.4.3. Tourism & Hospitality 
• Visitor confidence is declining due to poor communication and travel
disruptions. 
• Survey by Association of Scotland’s Self Caterers (ASSC) shows: 
a. 72% expect moderate to severe impacts.
b. Up to 50% turnover losses.
c. 13% of businesses may close permanently. 
• Reputational damage could be long-lasting.
4.4.4. SMEs & Local Economy 
• Small businesses predict 5–30% cost increases. 
• Recruitment and retention challenges are growing. 
• Depopulation concerns are linked to reduced accessibility and opportunity.
4.4.5. Public Sector & Community Services 
• Emergency services face operational risks due to delays. 
• Volunteer transport services for medical appointments are heavily
impacted. 
• Waste management costs projected to rise by £700k annually due to
landfill ban and increased haulage.
4.4.6 Economic Impact Assessments 
• Total projected cost of delays and business losses: ~£500 million over the
project’s lifetime. 
• Tourism sector impact: £404–£532 million over six years. 
• Potential permanent loss: £60 million annually if closures lead to business
shutdowns.
4.4.7 Recommendations & Proposed Actions from Stakeholders at the meeting: 
1. Upgrade medium-term solution to a two-way road without traffic lights or
convoy systems. 
2. Improve communication: 
• Real-time travel updates.
• Clear signage avoiding acronyms.
• National marketing campaign to reassure visitors. 
3. Expand Timberlink scheme to reduce road pressure. 
4. Support ferry alternatives with road equivalent tariffs. 
5. Provide direct business support:

Page 7

• Grants, tax relief, and rate adjustments. 
6. Reassess delay calculations using peak travel times (7am–7pm) rather
than 24-hour averages.
5.0 CONCLUSION
5.1 The Rest and Be Thankful issue is not just a transport challenge—it is a regional
crisis affecting every sector of Argyll and Bute. Without urgent action to ensure
reliable two-way access, the area risks long-term economic decline,
depopulation, and loss of investor and visitor confidence.
5.2 A letter was sent by Brendan O’Hara MP to the Cabinet Secretary for Transport
on behalf of all attendees at the roundtable meeting highlighting the issues
being experienced and very real costs to businesses as a result of the plans.
(Appendix 1).
5.3  The Cabinet Secretary for Transport has responded by letter to Brendan
O’Hara MP (Appendix 2). This letter confirmed that, from the feedback
received from officials at Transport Scotland who attended the A83
Roundtable meetings, coupled with the discussion at the recent A83
Taskforce on 1 October, the Cabinet Secretary has gained a strong sense of
feeling from contributing stakeholders of their economic and wellbeing
concerns in respect of the use of the OMR as a diversion route during
construction of the LTS. Subsequently as discussed at the most recent A83
Taskforce meeting, the Cabinet Secretary has instructed Transport Scotland
to review the work undertaken to date in relation to providing two-way
operation for the MTS, including use of the forestry track and a full two way
road option. The Cabinet Secretary further states that she is aware of the
concerns of A83 Roundtable attendees and also that time has passed since
these options were assessed and has also asked Transport Scotland to
continue to engage with John Gurr of the A83 Campaign Group with a view to
holding further meetings with the Group for open discussion on the MTS
options previously assessed.
5.4  In tandem The Cabinet Secretary for Transport has actioned Transport
Scotland to engage with Highland and Island Enterprise and Argyll and Bute
Council with a view to setting up an Economic Action Group to consider
potential economic impacts during construction of the LTS and possible
mitigation or policies to assist in alleviating such impacts. Further, the officials
at Transport Scotland will also progress further engagement with the Road
Haulage Association and Western Ferries to consider possible measures to
encourage hauliers to use ferry services as opposed to the A83.

Page 8

6.0 IMPLICATIONS
6.1 Policy – None Known
6.2 Financial – None Known at this time
6.3  Legal – None Known
6.4  HR – Delays may impact on staff traveling across the A83.
6.5 Customer Service - Delays may impact on Social Care services and other like
services if staff traveling across the A83 are delayed.
6.6 Risk – None Known
6.7 Climate Change – None Known
6.8  Fairer Scotland Duty – None Known
6.9 Equalities - protected characteristics – Delays may impact some residents
should services be delayed as a result of the planned works.
6.10 Consumer Duty – None Known
6.11 Island Communities – None Known
6.12 Children’s Rights and Wellbeing – None Known 
Kirsty Flanagan
Executive Director with responsibility for Development and Infrastructure
Policy Lead John Armour
6 November 2025                                                  
For further information contact: 
Andrew Summers, Head of Roads and Infrastructure
mailto:Andrew.summers@argyll-bute.gov.uk
Hugh O’Neill, Network and Standards Manager
Hugh.o’neill@argyll-bute.gov.uk