ARGYLL AND BUTE COUNCIL     ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE                                18 DECEMBER 2025 
BUS INFRASTRUCTURE FUND 
1.0 INTRODUCTION 
1.1  Argyll and Bute Council has received a capital allocation of £414,000 from 
Transport Scotland’s Bus Infrastructure Fund. Notification of this funding 
allocation was made in July 2025. Details of the terms for the funding are 
currently being discussed with Transport Scotland, however notwithstanding 
officers will endeavor to have this fully committed by financial year end.
1.2  The proposed programme includes new bus stops, shelter upgrades, lighting
improvements, and partnership working with local communities and transport
operators. The aim is to improve accessibility, safety, and service quality for
bus users, particularly in rural and underserved areas. These have been
selected following operational feedback on areas where safety, functionality
and convenience can be improved, along with sites that have had long-
standing community requests for new or improved bus stop infrastructure. 
1.3  This report outlines the proposed works under the following headings:
• Loch Fyne Oysters – new bus stops, shelters, and laybys.
• West Loch Tarbert – new shelter installation and boarding area in
existing Glasgow-bound layby.
• Rural Bus Stop Lighting Programme – a scalable Argyll-wide
programme of 75-200 solar powered timer or button activated light up
bus stop poles, flags and timetable cases.
• Guildford Square – roof and seating upgrades to the two existing
bespoke Victorian style shelters in Guildford Square, Rothesay.
• North Ledaig – new shelter installation adjacent to the Travelers Site.
• Islay – new shelter installations at various locations.
• Argyll-wide programme of selective bus shelter refurbishments, to bring
their appearance and functionality up to modern standards.

Page 2

• Bus stop pole replacement programme – primarily focused in the
Cowal area to replace corroded infrastructure on safety and
functionality grounds.           
At present the proposed programme is being costed and routes to
procurement worked out. Whilst some elements can be scaled to fit available
budget, it should be noted that there is an extremely tight turnaround from the
funding award to financial year end. Furthermore the Bus Infrastructure Fund
is putting significant load on the few bus stop infrastructure suppliers in
Scotland. Officers will endeavor to spend the full allocation by the end of
March 2026.   
2.0 RECOMMENDATIONS 
2.1 The Environment, Development and Infrastructure Committee is asked to
agree that Officers continue to liaise with Transport Scotland, landowners and
operators, to scope out costs, delivery timescales and delivery of the
programme.  
3.0 DETAIL 
3.1 The detail of the proposed programme is set out below - 
3.2  Loch Fyne Oysters
Proposal: Install new bus stops with hard standing, pole, flag, shelter, and 
potentially full laybys, in both directions (Glasgow-bound and Campbeltown-
bound).
Actions: Liaise with Transport Scotland to confirm acceptable standards and
delivery options; confirm landowner consent; engage with West Coast Motors,
Scottish Citylink, Loch Fyne Oysters business representatives and the
Community Council.
3.3  West Loch Tarbert
Proposal: Install a marked stop and bus shelter on the Glasgow-bound 
carriageway.
Actions: Liaise with Transport Scotland to confirm cost and delivery method; 
engage with West Coast Motors, Scottish Citylink to ascertain standards 
meet their requirements.
3.4  Rural Bus Stop Lighting Programme
Proposal: Install solar-powered light-up bus stops at rural locations to improve 
visibility and safety.

Page 3

Actions: Work up a list of suitable locations and develop a scalable
programme to match as much of the remaining budget as possible. 
3.5  Guildford Square, Rothesay
Proposal: Upgrade existing bespoke shelters with new roofs and seating.
Actions: Project managed by Roads and Infrastructure team.
3.6  North Ledaig
Proposal: Install a northbound shelter at the travelers’ site.
Actions: Awaiting quote from suppliers.
3.7  Islay – Various Shelters           
Proposal: Install a shelter opposite the medical centre in Port Charlotte, in
Port Ellen on Charlotte Street, and opposite Ceol Na Fairge in Bowmore.
Actions: Seek land use permission; obtain contractor quote for   
groundworks and shelter supply; install shelters.
3.8  Bus Shelter Refurbishments           
Proposal: Refurbishment of various bus shelters around Argyll to improve
safety and functionality.
Actions: Seek quotes from shelter manufacturers.
3.9  Bus Stop Pole Replacement Programme – Various Locations           
Proposal: Deliver a programme of new standard bus stop poles to replace
existing end of life infrastructure.
Actions: Work up a scalable programme of bus stop pole replacements. 
4.0 CONCLUSION
4.1 The Bus Infrastructure Fund presents a valuable opportunity to improve public   
transport infrastructure across Argyll and Bute. The proposed programme is
designed to maximise impact within the available budget and timeframe, with
a focus on rural accessibility, safety, and service quality. 
5.0 IMPLICATIONS
5.1 Policy – Supports Council objectives for sustainable transport and rural
connectivity. 
5.2 Financial - £414,000 must be spent within the current financial year.
5.3  Legal – Landowner agreements required for certain installations.

Page 4

5.4  HR – None known. 
5.5 Customer Service – Enhancements will improve experience and safety. 
5.6 Risk - Risk of underspend if delivery timelines are not met; mitigation through
scalable programmes.
5.7 Climate Change - Solar lighting and improved public transport infrastructure
support low-carbon travel.
5.8  Fairer Scotland Duty – None known. 
5.9 Equalities - protected characteristics – None known.
5.10 Consumer Duty – None. 
5.11 Island Communities – Programme includes island locations.
5.12 Children’s Rights and Wellbeing – None known. 
Kirsty Flanagan
Executive Director with responsibility for Roads and Infrastructure Services
Policy Lead Councillor John Armour
21 November 2025                                                  
For further information contact:
Scott Reid – scott.reid@argyll-bute.gov.uk 
Martin Arnold – martin.arnold@argyll-bute.gov.uk