ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE                              18th DECEMBER 2025 
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to provide Members of the Environment,
Development and Infrastructure Committee with an update on progress and
next steps in relation to the Roads and Infrastructure Service Review (RIS
Review). 
1.2 In providing this update reference is made to information contained in the
previous report to this Committee in relation to the RIS Review in September
2025 and to the actions taken in the intervening period. 
1.3 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) Consider the progress made in relation to the priority improvement actions,
including the financial impacts of these, and; 
b) Agree to receive a further report on progress of the RIS Review in March
2026.
c) Endorse the extension of the external consultancy to support the RIS
review project at a cost of up to £90,000 noting that where possible this
would be funded from within existing resources but recommend to Council
that should there be insufficient existing resources within RIS that this is
funded from the Strathclyde Pension Fund Gain earmarking set aside for
transformation/spend to save initiatives. 
d) Agree to recommend to Council that 
i. the increase in saving target of £500k due to be applied in 2026/27 to
the RIS Review be removed and 
ii. instead, the RIS Review work towards achievement of the cumulative
£500k saving from 2024/25 & 2025/26 recurring.

Page 2

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE                              18th DECEMBER 2025 
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update to Members of this Committee on progress of the
Roads and Infrastructure Service Review (RIS Review), since the last update in
September 2025. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members of the Environment, Development and
Infrastructure Committee:- 
a) Consider the progress made in relation to the priority improvement actions,
including the financial impacts of these, and; 
b) Agree to receive a further report on progress of the RIS Review in March
2026.
c) Endorse the extension of the external consultancy to support the RIS
review project at a cost of up to £90,000 noting that where possible this
would be funded from within existing resources but recommend to Council
that should there be insufficient existing resources within RIS that this is
funded from the Strathclyde Pension Fund Gain earmarking set aside for
transformation/spend to save initiatives. 
d) Agree to recommend to Council that 
i. the increase in saving target of £500k due to be applied in 2026/27 to
the RIS Review be removed and 
ii. instead, the RIS Review work towards achievement of the cumulative
£500k saving from 2024/25 & 2025/26 recurring.

Page 3

4.0 DETAIL 
4.1 The RIS Review has been structured around 4 stages of activity as illustrated
below:   
4.2 As set out in previous reports to this Committee the opportunity is being taken
to deliver the planned improvement activities from stages 3 and 4
concurrently. This results in a number of priority improvement actions being
progressed at the same time as the development and implementation of the
revised target operating model and organisation structure for the service.
4.3 Appendix 1 provides a comprehensive update on progress with each of the
current 12 priority improvement actions. As set out in the previous update to
this Committee, a staged approach is being taken to the implementation of the
approved priority improvement actions in order to ensure that the service
improvement activity does not place an unsustainable burden on an already
busy service.
4.4 In June 2023 the EDI committee recommended to Council that £150,000 be
set aside from the Strathclyde Pension Fund gain earmarking for
transformation/spend to save initiatives in order to progress the actions from
the RIS Review. This was agreed by Council in June 2024.  The funding has
been used to buy in consultancy support from SOLACE (Stephen Hall) and
also to provide administrative support to the project.  The funding will be fully
spent by February 2026 and it is recommended that further funding of up to
£90,000 is made available in order to continue the good work that has
commenced for a further 6 months beyond February 2026.  Officers
recommend that this is funded from within existing resources in RIS or if
insufficient, then fund from the Strathclyde Pension Fund gain earmarking for
transformation/spend to save initiatives. This approach has been endorsed by
the Executive Leadership Team.

Page 4

The work that will be taken forward during the additional 6 months is
summarised below:
• Finalise the reshaping of Roads and Infrastructure Services
• Further progress the Roads and Information Asset Management Systems
(RIAMS) improvement project to deliver improvements to customer service
and the data required to improve service efficiency.
• Household Residual Waste Collection Reduction
• Review of Commercial Waste income
4.5  Savings targets exist in relation to the RIS Review process as follows:
2024/25 £200k, rising to £300k in 2025/26, and then rising by a further £500k
in 2026/27 to give a £1m p.a. recurring saving in 2026/27 and beyond. An
additional income target in relation to increased income in commercial waste
contracts of £700k for 2025/26 also exists. 
4.6 To date additional income through commercial waste contracts of over £450k
has been achieved, with activity continuing to further increase this additional
income. In addition, the RIS Review has also enabled £3m of capital to be
released to other priorities within the service following a review of the
business case for the Helensburgh waste transfer station, thereby reducing
pressure on capital financing in relation to preparation for the ban on
municipal waste top landfill. 
4.7 It has not yet been possible to achieve either the 2024/25 or 2025/26 revenue
savings (cumulative value £500k) attached to the RIS review as it has been
more challenging than originally anticipated to drive out financial efficiencies.
A number of service areas have required intervention to respond to immediate
term operational challenges. In addition, the service has put forward over
£900k of savings as part of Council wide options to close the budget gap for
2026/27. With such significant savings already identified and proposed by
Roads and Infrastructure Services, there is low confidence that the savings
target of £1m for the RIS Review in 2026/27 will be achieved. It is therefore
proposed that the increase in saving target of £500k due to be applied in
2026/27 be removed and that instead the RIS Review work towards
achievement of the cumulative £500k saving from 2024/25 & 2025/26
(recurring) continues. 
5.0 CONCLUSION
5.1 This report provides an update on the implementation of the 12 Priority
Improvement Actions as developed under Stage 4 of the RIS Review process.

Page 5

6.0 IMPLICATIONS
6.1 Policy – No direct policy implications within this report. A number of the priority
improvement actions result in changes to existing policies. Where this is the
case further reports have been considered or will be considered in the future
by Committee in relation to these.
6.2 Financial – A number of the priority improvement actions aim to increase
efficiency and deliver financial benefits to the Council. Others may require
further financial input. Such cases will be brought forward for Members’
consideration at the appropriate time. This report asks Members to agree and
recommend to Council that should access to Strathclyde Pension Fund
earmarking be required that this is approved.  
6.3  Legal – Legal aspects are being reviewed as part of each of the priority
improvement actions.
6.4  HR – The proposals to reshape the organisation structure of the Roads and
Infrastructure Service have implications for staff. All relevant Council policies
and procedures are being followed in this regard.
6.5 Customer Service – A number of the priority improvement actions aim to
improve customer experience. Within the priority improvement actions
currently being progressed, improvements in customer experience in relation
to household waste collection, commercial waste services and road
maintenance are being developed.
6.6 Risk – Risks are being managed in relation to each of the priority
improvement actions.
6.7 Climate Change – Reduction in carbon emissions will be achieved as a result
of implementation of waste disposal arrangements that respond to the ban on
municipal waste to landfill.
6.8  Fairer Scotland Duty - None identified at this time.
6.9 Equalities - protected characteristics: Will be considered as part of each of the
priority improvement actions as these progress.
6.10 Consumer Duty – None identified at this time.
6.11 Island Communities - None identified at this time.
6.12 Children’s Rights and Wellbeing - None arising directly from this report.

Page 6

Kirsty Flanagan, Executive Director with responsibility for Roads and 
Infrastructure
Councillor John Armour, Policy Lead for Roads, Transport and Amenity 
Services 
December 2025                                                  
For further information contact:
Andy Summers, Head of Roads and Infrastructure
Andrew.summers@argyll-bute.gov.uk 
Stephen Hall, Consultant, Roads and Infrastructure Service Review 
Stephen.hall@argyll-bute.gov.uk 
APPENDICES
Appendix 1 – Summary of Priority Improvement Actions