ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE    18TH DECEMBER 2025 
ELECTRIC VEHICLE CHARGING STRATEGY – PROGRESS AND PROPOSED
DELIVERY MODEL 
1.0 EXECUTIVE SUMMARY 
This report provides Members with an update on the delivery of the Council’s
Electric Vehicle Charging (EVC) Strategy and seeks approval for a revised
approach to delivery now that external funding has been confirmed.
The Strategy, approved by the Council in 2022, set out a vision and a strategic
basis to expand the availability of public electric vehicle charging (EVC)
infrastructure throughout Argyll and Bute. Its purpose was to provide fair and
convenient access for residents, visitors and businesses, supporting both the
transition to low-carbon transport and the Council’s wider climate objectives.
Following confirmation that the Council has now been awarded £1.033 million
through the national Electric Vehicle Infrastructure Fund (EVIF), officers have
reviewed the existing strategy and expansion plan to ensure that proposals for
the scale and pace of delivery reflect the resources available and that
investment achieves the greatest possible public benefit.
It is therefore proposed that the Council alter its strategy to include an additional
layer – a “hub-first” delivery model, concentrating initial investment on a network
of well-equipped, high-use charging hubs in key towns and island centres. This
would then be followed by a second phase of smaller “spoke” installations
across smaller settlements/in other key areas, maintaining connectivity and
enabling local flexibility, with the latter element being delegated to local Area
Committees. 
The report also provides updates on related workstreams, including the
transition to the new Scottish Power back-office system and the development of
a local cross-footway charging approach to support safe home charging.
Overall, the report seeks Member approval for the proposed revised delivery
methodology, funding allocation and next steps that will allow us to move from
planning to implementation in 2026.

Page 2

RECOMMENDATIONS
It is recommended that the Environment, Development and Infrastructure
Committee:
a) Note progress on the implementation of the Electric Vehicle Charging
Strategy; 
b) Approve the proposed “hub-first” delivery methodology, whereby key
town and island hubs will be delivered as Phase 1 of the programme,
followed by local “spoke” installations in Phase 2; 
c) Approve the proposed allocation of the £1.033 million EVIF funding,
comprising: 
• £100,000 for maintenance and repair of the existing network,
• £100,000 as a contingency to address connection and construction
cost      fluctuations, and
• £833,000 for the delivery of new infrastructure; 
d) Agree that the residual budget for Phase 2 be delegated to local Area
Committees on the following basis: 
• Bute & Cowal – 19.78%
• Helensburgh & Lomond – 10.67%
• Mid Argyll, Kintyre & Islay – 32.71%
• Oban, Lorn & the Isles – 36.84% 
e) Note the ongoing parallel workstreams relating to the development of a
cross-footway charging policy, the migration of the back-office system to
Scottish Power / Fuuse, and the continued review of tariffs and
maintenance arrangements; and 
f) Note that a further report will come back to committee in March once the
costing exercise which is currently underway is complete.

Page 3

ARGYLL AND BUTE COUNCIL  ENVIRONMENT, DEVELOPMENT AND 
INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE    18TH DECEMBER 2025 
ELECTRIC VEHICLE CHARGING STRATEGY – PROGRESS AND PROPOSED
DELIVERY MODEL 
2.0 INTRODUCTION 
2.1 This report provides Members with an update on the delivery of the Council’s
Electric Vehicle Charging (EVC) Strategy and seeks approval for a revised
approach to delivery now that external funding has been confirmed. 
3.0 RECOMMENDATIONS 
It is recommended that the Environment, Development and Infrastructure
Committee:
a) Note progress on the implementation of the Electric Vehicle Charging
Strategy; 
b) Approve the proposed “hub-first” delivery methodology, whereby key town
and island hubs will be delivered as Phase 1 of the programme, followed by
local “spoke” installations in Phase 2; 
c) Approve the proposed allocation of the £1.033 million EVIF funding,
comprising: 
• £100,000 for maintenance and repair of the existing network,
• £100,000 as a contingency to address connection and construction cost
fluctuations, and
• £833,000 for the delivery of new infrastructure; 
d) Agree that the residual budget for Phase 2 be delegated to local Area
Committees on the following basis: 
• Bute & Cowal – 19.78%

Page 4

• Helensburgh & Lomond – 10.67%
• Mid Argyll, Kintyre & Islay – 32.71%
• Oban, Lorn & the Isles – 36.84% 
e) Note the ongoing parallel workstreams relating to the development of a
cross-footway charging policy, the migration of the back-office system to
Scottish Power / Fuuse, and the continued review of tariffs and maintenance
arrangements; and 
f) Note that a further report will come back to committee in March once the
costing exercise which is currently underway is complete. 
4.0 DETAIL 
4.1 In 2022, the Council approved its Electric Vehicle Charging Strategy, setting out
the long-term ambition to fill geographic gaps in provision and to ensure
equitable coverage of public EV charging infrastructure across Argyll and Bute.
4.2 The Strategy was structured around two principal delivery themes:
1. Charging on the Move – focusing on route-based coverage to allow drivers
to travel confidently across and through the area; and
2. Destination Charging – providing charging points in locations where users
are likely to dwell for longer periods, such as town centres, car parks, and
visitor destinations.
4.3 Between 2023 and 2024, officers developed an expansion plan and
methodology that identified 55 potential sites across the Council area. This
approach was framed around achieving fairness and geographic balance and
was developed on the assumption that further external funding would become
available to support full implementation.
4.4 In 2024, the Environment, Development and Infrastructure (EDI) Committee
reaffirmed this direction while awaiting confirmation of national funding through
the Scottish Government’s Electric Vehicle Infrastructure Fund (EVIF). 
CURRENT POSITION
4.5 In August 2025, the Council secured £1.033 million from the national EVIF
programme, which is administered regionally through HITRANS. 
4.6 The consultancy Urban Foresight was engaged to undertake detailed
assessments of each of the 55 long-listed sites. This work produced
comprehensive “factfiles” describing site conditions, grid capacity, charger
configurations and indicative costs. However, it became clear that the outputs
needed refinement to reflect the proposed new strategic approach – this work is
ongoing.

Page 5

4.7 Based on average installation costs from previous programmes, the original 55-
site plan was estimated to require approximately £1.65 million. The confirmed
allocation of £1.033 million therefore requires a more targeted, phased
approach. Officers have reviewed the methodology to focus on high-impact
locations that provide the greatest utilisation and value for money. 
PROPOSED DELIVERY MODEL
4.8 It is proposed that the Council adopt a “hub-first” delivery model, establishing
a core network of well-equipped, multi-charger hubs in the principal towns and
island centres. Each hub would typically provide a mix of fast and rapid
chargers, be conveniently located near local amenities, and be designed for
scalability so that additional chargers can be added in future years as demand
increases.
4.9 This approach represents an evolution of the original “Destination
Charging” theme. Rather than installing several smaller 22 kW chargers in
multiple car parks within a single town, these would be consolidated into one
central hub offering improved reliability, faster charging speeds, and easier
maintenance.
4.10 The second phase of delivery would then extend provision outward to smaller
“spoke” sites, typically one- or two-charger installations serving rural
communities. This ensures the network retains the original “Charging on the
Move” ethos of connectivity across strategic routes while delivering a financially
sustainable core system.
4.11 When developing the new methodology Officers have considered:
• population and visitor demand;
• the impact of seasonal tourism “swell”;
• grid capacity and connection feasibility;
• deliverability, accessibility and cost efficiency; and
• the presence of existing or planned private-sector chargers to avoid
duplication.
This methodology ensures that investment is guided by practical, evidence-
based criteria rather than theoretical mapping. 
HUB METHODOLOGY
4.12 Strategic principle: Build reliable, visible hubs first, then expand to smaller
“spokes” once the network backbone is established, ensuring full route coverage
across Argyll and Bute. This also complements the existing network. 
• Identify sites that deliver strategic coverage – locations where people visit,
shop and work
• Potential for high utilisation

Page 6

• Represent value for money
• Access to local amenities
• Avoid duplicating private provision 
• Resilience and cluster logic
• We have a proposed criteria for this based on population. The hub (single-
site) methodology is:
Population Rapid Fast Total
10k plus 5 5 10
5k to 10k 3 3 6
2k to 5k* 2 2 4
*when not near an existing large town 
• We will add in an element of population swell through tourist locations where
they would therefore move up to the next bracket:
• Population centres proposed for hubs reflect places where visitors and
residents visit, rather than domestic users charging at home
This methodology would therefore provide the following hubs:
Town/area Pop Tourist swell  Hub/cluster
Helensburgh  13k N 5R; 5F
Oban  8.5k Y 5R; 5F
Dunoon  8.9k N 3R; 3F
Lochgilphead  2.3k N 2R; 2F 
Campbeltown 4.5k N 2R; 2F
Islay – Bowmore 3k island Y 3R; 3F 
Mull – Craignure  3k island Y 3R; 3F
Bute – Rothesay  6k island N 3R; 3F

Page 7

4.13 To progress this we have asked our consultants to:
• Assess the current provision in each location including non ABC operated
publicly available chargers. That assessment should consider as a ‘’hub’’
any chargers within a cluster area less than one mile  from the hub site
identified in the above table
• Focus on new hubs/expansion of existing to be on a single site 
• Identify the number and type of chargers required to meet the above hub
targets, after accounting for existing provision both Council and non-Council.
• Assuming hubs/clusters will be developed on existing sites, base on
following as the core deliverability criteria on the basis we are trying to
assess if sites pass or fail:
o Proximity to existing electrical infrastructure; 
o Compliance with accessibility standards; 
o No flood risk
o Strong data connectivity 
• To assess in binary terms whether the sites pass or fail
• Include usage information on existing chargers at current sites. 
• Determine total costs for any additional EVCs required to meet the above
requirement. Assume mid range costs 
• Assess scalable expansion options at each site 
PHASE TWO LOCAL DELIVERY
4.14 Phase 2 delivery will focus on individual chargers and smaller sites (‘spokes’)
that maintain network continuity and local access.
4.15 These sites could be selected and prioritised by Area Committees within their
allocated share, to support local decision-making and flexibility under the
strategic framework.
4.16 This ensures alignment with the original thematic principles and equitable
access across rural routes and communities. 
FUNDING ALLOCATION
4.17 The Council’s confirmed £1.033 million EVIF allocation is proposed to be split
as follows:
• £100,000 – to address essential maintenance and repair of the existing
network, safeguarding reliability;

Page 8

• £100,000 – to be held as a contingency fund to manage potential cost
escalation and connection charges; and
• £833,000 – for the phased delivery of new charging infrastructure.
4.18 It is proposed that:
• Phase 1 deliver the network of strategic hubs within key towns and island
centres; and
• Phase 2 deploy the remaining balance as smaller “spoke” sites to maintain
route coverage and local accessibility, with this element being delegated to
local Area Committees.
4.19 To ensure equity, it is proposed that any residual Phase 2 funding be
apportioned in line with the Council’s established roads-capital programme
distribution percentages:
• Bute & Cowal – 19.78%
• Helensburgh & Lomond – 10.67%
• Mid Argyll, Kintyre & Islay – 32.71%
• Oban, Lorn & the Isles – 36.84%
4.20 This approach would allow for local input within a consistent strategic
framework.
ADDITIONAL WORKSTREAMS
4.21 Cross-Footway Charging
Officers are developing a local policy framework for cross-footway EV charging
to respond to increasing demand from residents who wish to charge at home
but lack private driveways.
It is proposed that a three-stage approach be adopted:
1. Short-term use of approved ramped cable protectors;
2. Medium-term pilot of below-ground ducting (2026); and
3. Long-term adoption process supported by a leasing and cost-recovery
model.
Engagement with disability and access groups will ensure accessibility
standards are maintained throughout.
4.22 Back-Office Migration
The Council’s network of 37 existing chargers is being migrated to the new
Scottish Power back-office system, which provides enhanced data visibility,
automated fault reporting and compliance with national contactless-payment
regulations. This transition will improve uptime and simplify network
management.
4.23 Tariffs and Maintenance
The current tariff of £0.70 per kWh will remain under review to maintain an
appropriate balance between user affordability and cost recovery.

Page 9

At present, the EVC network is managed operationally by one officer within the
Roads and Infrastructure team. As the network expands, it is proposed that
officer capacity and resourcing be reviewed to ensure long-term sustainability. 
RISKS
4.24 Key risks associated with delivery include:
• Grid connection costs and availability, particularly in rural or island
locations;
• Potential overlap with private-sector provision, such as forecourts and
supermarkets;
• Resourcing constraints, given that day-to-day management currently rests
with one officer;
• Transitional reliability risks during the migration to the new back-office;
and
• Construction-cost volatility in the current market.
4.25 Mitigation measures include early engagement with SP Energy Networks, use of
the contingency allocation to absorb fluctuations, phased delivery, and
continuous liaison with private operators to coordinate provision.  
5.0 CONCLUSION
5.1 The proposed hub-first delivery model offers a realistic and financially
sustainable pathway for expanding the Council’s EV charging network within the
confirmed funding envelope.
5.2 It maintains strategic coverage and fairness while focusing investment on sites
with the highest potential utilisation.
5.3 Subject to Committee approval, officers will:
• finalise site selection and connection estimates with Urban Foresight 
• report progress back to the Committee once the above is complete 
5.4 This phased, data-led approach will enable the Council to strengthen the
network’s reliability, improve user experience, and support both local economic
activity and carbon-reduction goals. 
6.0 IMPLICATIONS
6.1 Policy - Supports the objectives of the approved Electric Vehicle Charging
Strategy.
6.2 Financial - £1.033 million secured through EVIF; proposed allocations and
phasing detailed in the report.

Page 10

6.3  Legal - All works will comply with roads, procurement and accessibility 
legislation.
6.4  HR – none.
6.5 Customer Service – back office migration needs to be managed with supplier.
6.6 Risk – noted in the body of the report.
6.7 Climate Change – supports move to net zero.
6.8  Fairer Scotland Duty – none known.
6.9 Equalities – none known.
6.10 Consumer Duty – none known.
6.11 Island Communities – none known.
6.12 Children’s Rights and Wellbeing – none known. 
Kirsty Flanagan
Executive Director with responsibility for Roads and Infrastructure
Policy Lead Councillor John Armour
13 November 2025                                                  
For further information contact: Mark Calder 
APPENDICES
Appendix 1 – Updated Expansion List
Appendix 2 – Member Seminar Slides