MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING
COMMITTEE held BY MICROSOFT TEAMS on TUESDAY, 16 SEPTEMBER 2025 
Present: Councillor Kieron Green (Chair) 
Councillor John Armour
Councillor Gordon Blair
Councillor Jan Brown
Councillor Graham Hardie
Councillor Fiona Howard 
Councillor Andrew Kain
Councillor Paul Donald Kennedy
Councillor Liz McCabe
Councillor Dougie Philand
Councillor Peter Wallace 
Attending:  Fergus Murray, Head of Development and Economic Growth
Shona Barton, Governance Manager
Peter Bain, Development Manager
Bryn Bowker, Area Team Leader – Mid Argyll, Kintyre and the Islands
Kirsty Sweeney, Area Team Leader - Bute, Cowal, Helensburgh and
Lomond
David Moore, Senior Planning Officer
Stuart Ramsay, Senior Planning Officer 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Audrey Forrest, Amanda Hampsey,
Daniel Hampsey and Mark Irvine. 
2. DECLARATIONS OF INTEREST 
Councillor Graham Hardie declared a non-financial interest in Planning Application
reference 25/00535/PP as members of his family submitted letters of support in respect of
this proposal. 
Councillor Hardie also declared a non-financial interest in Enforcement Case Reference
15/00051/ENAMEN as his wife was a friend of the landowner.   
He confirmed that he would leave the meeting and take no part in the consideration of
these cases which were dealt with at items 5 and 9 of this Minute. 
3. MINUTES 
a) The Minute of the Planning, Protective Services and Licensing Committee held on 20
August 2025 at 11.00 am was approved as a correct record. 
b) The Minute of the Planning, Protective Services and Licensing Committee held on 20
August 2025 at 2.30 pm was approved as a correct record. 
c) The Minute of the Planning, Protective Services and Licensing Committee held on 20
August 2025 at 3.30 pm was approved as a correct record.

Page 2

4. SCOTTISH GOVERNMENT SECTION 36 CONSULTATION:
CONSTRUCTION AND OPERATION OF BALLIEMEANOCH PUMPED
STORAGE HYDRO SCHEME: 4.4 KM TO THE SOUTH OF
PORTSONACHAN AND 9 KM NORTHWEST OF INVERARAY (REF:
24/01324/S36) 
The Senior Planning Officer spoke to the terms of the report which provided a
recommended response to the Scottish Government’s Energy Consents Unit and
Deployment Unit consultation on a revised Section 36 Application for the construction and
operation of Balliemeanoch Pumped Storage Hydro Scheme at land 4.4 km to the South
of Portsonachan and 9 km Northwest of Inveraray. 
Before proceeding with his presentation, the Senior Planning Officer advised that the
Applicant had submitted a late Community Wealth Economic Growth and Resilience
submission, which had been circulated by the Applicant to the Members and a copy of this
had also been placed on public record.   This submission stated that the Applicant wished
to commit to funded apprenticeships - a £500,000 fund for apprenticeships and training
working with the University of the Highlands and Islands to deliver training and legacy
benefits by seeking to utilise young people in both the construction and future operation of
the facility.  Secondly, a Community Resilience Fund of £50,000 per annum for 25 years
to tackle the effects of climate change, a total of £1.25 million, and thirdly, the construction
of 12 new homes in Inveraray within the approved Masterplan area, which would initially
be used by the Senior Project Managers and, thereafter, would be transferred for general
housing use, either to a Registered Social Landlord, or for general occupation in the area. 
He advised that community benefits were not normally considered to be material planning
considerations and were a voluntary contribution matter dealt with out with the planning
system and out with Officer reports.  He said, however, that it was his opinion that the
training provision commitment and the housing provision commitment could be regarded
as material planning considerations to the application in respect of NPF4 Planning Policies
11c and/or Policy 25 and having regard to the Council’s declared Housing Emergency.  In
respect of the promoted Community Resilience Fund, it was his view that as it was set out,
this was not capable of being considered and should not be considered, as a material
planning consideration in the determination of this application.  The late submission made
by the Applicant did not change the recommendation in the main report before the
Committee for consideration. 
This report reviewed the policy considerations which were applicable to this proposal and
the planning merits of the development, the views of bodies consulted by the Scottish
Government along with other consultations undertaken by the Council, and third party
opinion expressed to the Scottish Government. 
The application details were amended by the Applicant following objections received,
mainly expressing concerns relating to the alteration of the water levels of Loch Awe and
consequent potential adverse flooding impacts on roads, houses and businesses.  There
were also objections to the original larger proposal from SEPA and NatureScot related to
the impact of the development on peat and habitat.  The Applicant has revised and
reduced the scale of the development, and the current application has been amended
from the original scheme and now constitutes the application details before the Council
with the original Environmental Impact Assessment Report (EIAR) now supported by
additional environmental evaluation contained within the Further Environmental
Information (FEI) documentation.

Page 3

It was recommended that no objection be raised to the revised S36 proposals subject to
the imposition of appropriate conditions summarised within the report and other
consultation responses and that the current ‘holding objection’ lodged with the Scottish
Ministers be withdrawn. 
Decision 
The Committee agreed that no objection be raised to the revised S36 proposals subject to
the imposition of appropriate conditions summarised within the report and other
consultation responses and that the current ‘holding objection’ lodged with the Scottish
Ministers be withdrawn. 
(Reference: Report by Head of Development and Economic Growth dated 5 September
2025, submitted) 
Councillor Graham Hardie, having declared an interest in the following item, left the
meeting at this point. 
5. TARBERT HARBOUR AUTHORITY: EXTENSION OF EXISTING CAR PARK
TO FORM MIX OF CAR PARKING AND BOAT STORAGE AND
FORMATION OF SLIPWAY: LAND ADJACENT TO MARINA OFFICE,
GARVAL ROAD, TARBERT (REF: 25/00535/PP) 
The Area Team Leader spoke to the terms of the report.  This is an application for an
extension of an existing car park to form a mix of car parking and boat storage and
formation of a slipway at an existing established marina site.   
In terms of the adopted Argyll and Bute Local Development Plan (LDP) 2, the application
site is located within a Conservation Area, near listed buildings and Scheduled
Monuments and within the Settlement Area of Tarbert.  The site is also identified within a
Tourist Development Opportunities area. 
A total of 57 representations have been received for the application, for which 16 were in
support, 21 neutral and 40 in objection to the proposal.  There have been no objections
received from statutory consultees. 
The proposal is considered to be consistent with the relevant provisions of the
Development Plan, and there are no other material considerations of sufficient
significance to indicate that it would be appropriate to withhold planning permission having
regard to S25 of the Act. 
It was recommended that planning permission be granted subject to the conditions and
reasons detailed in the report of handling. 
Decision 
The Committee agreed to grant planning permission subject to the following conditions
and reasons: 
Standard Time Limit Condition (as defined by Regulation) 
Standard Condition on Soil Management During Construction

Page 4

Additional Conditions 
1. PP - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details specified on the
application form dated 01.04.2025, supporting information and, the approved drawings
listed in the table below unless the prior written approval of the planning authority is
obtained for an amendment to the approved details under Section 64 of the Town and
Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date
Received
Location Plan 107065-MMD-01-
XX-DR-C-0120
2 23.04.2025
Location Plan 1:750 107065-MMD-01-
XX-DR-C-0121
2 23.04.2025
Existing Site Plan 107065-MMD-01-
XX-DR-C-0122
2 23.04.2025
Proposed Site Plan (Winter
Use)
107065-MMD-01-
XX-DR-C-0130
2 23.04.2025
Proposed Site Plan
(Summer Use - Car Parking)
107065-MMD-01-
XX-DR-C-0131
2 23.04.2025
Proposed Site Plan (Mixed
Use)
107065-MMD-01-
XX-DR-C-0132
2 23.04.2025
Boat Recovery Positions 107065-MMD-01-
XX-DR-C-0136
2 23.04.2025
Proposed Site Sections and
Finished Floor Level
(Section A-A and Section B-
B)
107065-MMD-01-
XX-DR-C-0135
2 23.04.2025
Proposed Site Sections and
Finished Floor Level
(Section C-C and Section D-
D)
107065-MMD-01-
XX-DR-C-0137
2 23.04.2025 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
2. Notwithstanding the provisions of condition 1, for the purposes of clarity strictly no
excavation shall take place below the public road / toe of embankment. 
Reason: In the interests of Road Safety. 
3. PP – Road Condition Survey 
No development shall commence until a survey recording the condition of between the
A83 Tarbet - Campbeltown Trunk Road / U40 Shore Road (Garvel Road) junction and
the application site has been undertaken and deposited with the Roads Authority. 
The survey shall be undertaken to a specification which has first been agreed in writing
with the Roads Authority and shall address the condition of the carriageway and

Page 5

verges and the condition of any bridges and culverts along the route. (Video recording
would be beneficial). 
Reason: To establish the condition of the public road prior to construction works being
commenced in order to provide a baseline against which the need for reinstatement
works may be assessed. 
Note to Applicant: 
Damage arising from abnormal traffic associated with the construction of this
development shall be reinstated in accordance with details to be submitted to and
approved by the Roads Authority in accordance with the provisions of the Roads
(Scotland) Act 1984 either upon significant damage being identified during the course
of construction works, or following a final inspection upon completion of construction
works, whichever is the sooner. 
4. PP – Construction Traffic Management Plan and Method Statement 
No development shall commence until a Traffic Management Plan and Method
Statement has been submitted for the written approval of the Planning Authority in
consultation with the Roads Authority. The Traffic Management plan should include
details of all materials, plant, equipment components and labour required during the
construction works. The Plan shall also detail approved access routes, agreed
operational practices (including avoidance of convoy movements, specifying conduct in
use of passing places, identification of turning areas, reporting of verge damage) and
shall provide for the provision of an appropriate Code of Practice to drivers of
construction and delivery vehicles. The development shall be implemented in
accordance with the duly approved Traffic Management Plan.  
Reason: To address abnormal traffic associated with the development in the interests
of road safety. 
5. PP - Parking and Turning As Shown 
The parking and turning area shall be laid out and surfaced in accordance with the
details shown on the approved plans prior to the development first being occupied and
shall thereafter be maintained clear of obstruction for the parking and manoeuvring of
vehicles. This shall include provision for 3 disabled parking spaces. 
Reason: In the interest of road safety. 
6. PP – Basic Landscape/Surface/Boundary Treatment 
No development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved in writing by the
Planning Authority. The scheme shall include details of: 
i) Location, design and materials any proposed walls, fences and gates;
ii) Surface treatment of proposed means of access and hardstanding areas;
iii) Any proposed re-contouring of the site by means of existing and proposed
ground levels;
iv) Proposed hard and soft landscape works;

Page 6

The development shall not be occupied until such time as the boundary treatment,
surface treatment and any re-contouring works have been completed in accordance
with the duly approved scheme. 
All of the hard and soft landscaping works shall be carried out in accordance with the
approved scheme during the first planting season following the commencement of the
development, unless otherwise agreed in writing by the Planning Authority. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity. 
7. PP – Biodiversity Enhancement 
Notwithstanding the provisions of Condition 1, no development shall commence until a
biodiversity statement has been submitted to and approved in writing by the Planning
Authority. The statement shall demonstrate how the proposal will contribute to
conservation/restoration/enhancement of biodiversity, and how these benefits will be
implemented and maintained for the lifetime of the development. 
All physical biodiversity enhancement measures (bird nesting boxes, ‘swift bricks’,
wildlife ponds, bat and insect boxes, hedgehog homes etc) shall be implemented in full
before the development hereby approved is first brought into use. 
All biodiversity enhancement measures consisting of new or enhanced planting shall
be undertaken either in accordance with the approved scheme of implementation or
within the next available planting season following the development first being brought
into use. 
The biodiversity statement should refer to Developing with Nature guidance |
NatureScot as appropriate. 
Reason: To comply with the requirements of NPF4 Policy 3. 
Note to applicant:  Your attention is drawn to the consultation comments of the
Council’s Local Biodiversity Officer regarding suggested biodiversity enhancement
measures. 
8. No development, including demolition and/or construction works associated with the
hereby approved development shall take place outside 08.00 hours to 18.00 hours
Mondays to Fridays; 08.00 hours to 13.00 hours on Saturdays or at any time on
Sundays or Bank Holidays. 
Any variation to the hours of operation shall be submitted to and agreed in writing by
the Local Planning Authority prior to any agreed change being implemented. 
Reason - To ensure that the residential amenities that occupiers can reasonably
expect to enjoy are adequately protected. 
9. No development shall commence until details of flood risk signage to be erected at the
application site have been submitted to and approved in writing by the Planning
Authority, in consultation with the Council’s Flood Risk Advisor. The duly approved
details shall be implemented thereafter prior to commencement of first use of the
hereby approved development.

Page 7

Reason: In order to ensure appropriate mitigation for flood risk. 
10. PP - Bird Breeding Season 
The removal of any vegetation or trees should be undertaken outside the nesting bird
season (March-September) or alternatively a nesting bird survey should be undertaken
to confirm no active nests are present. The survey shall be submitted to and approved
in writing by the planning authority prior to the removal of any vegetation and trees. 
Reason: To protect breeding birds in the interests of nature conservation. 
11. PP – Pre-commencement Survey 
No development or other work shall be carried out on the site until a pre-
commencement survey for the presence of Otters has been carried out by an
appropriately qualified person and has been submitted for the written approval of the
Planning Authority, in consultation with the Council’s Biodiversity Officer. In
circumstances where species of interest are identified as being present, or at risk from
construction works, the survey shall further provide suggested avoidance and or
mitigation measures, including timing constraints, to address such presence or risk.
The development shall be implemented in accordance with the measures identified in
the duly approved scheme. 
Reason: In order to establish that the circumstances of the site have not changed
significantly between approval and implementation of the development for the purpose
of protecting natural heritage assets in the interest of nature conservation. 
12. PP – Surface Water Drainage – No further detail required 
Notwithstanding the provisions of Condition 1, the development shall incorporate a
surface water drainage system which is consistent with the principles of Sustainable
urban Drainage Systems (SuDS) compliant with the guidance set out in CIRIA’s SuDS
Manual C753. The requisite surface water drainage shall be operational prior to the
development being brought into use and shall be maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage system and to
prevent flooding. 
13. Notwithstanding the provisions of Condition 1, no development shall commence until
the design and external construction materials to be used in the proposed boat wash
water treatment unit shown on the hereby approved plan ref 107065-MMD-01-XX-DR-
C-0130 Rev 2 have been submitted to and approved in writing by the Planning
Authority. The development shall be implemented in accordance with the duly
approved details. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity. 
14. PP – Construction Environmental Management Plan 
Prior to the commencement of the development hereby approved, a Construction
Environmental Management Plan (CEMP) shall have been submitted to and approved

Page 8

in writing by the Local Planning Authority. The duly approved plan shall be fully
adhered to throughout the construction period, and shall provide, amongst other
things, for: 
- measures for controlling dust and preventing any spills;
- specifications and a timetable of works for the construction phase of the
development;
- pollution prevention measures including management of plant, materials,
chemicals and fuels, and washing/storage arrangements;
- the parking of vehicles of site operatives and visitors;
- loading and unloading of plant and materials;
- the erection and maintenance of any security hoarding/fencing.  
The submitted details shall have regard to SEPA's Guidelines for Pollution Prevention
5: Works and maintenance in or near water. 
Reason: In the interests of biodiversity and the natural environment. 
(Reference: Report by Head of Development and Economic Growth dated 2 September
2025, submitted) 
Councillor Hardie returned to the meeting. 
6. SAULMORE BAY RESORT LTD: PROPOSAL OF APPLICATION NOTICE
FOR MARINA; BOATYARD INCLUDING ANCILLARY OFFICES (CLASS 4)
AND STORE (CLASS 6); LEISURE RESORT INCLUDING BUILDINGS FOR
OFFICES (CLASS 4), LEISURE USE, GYM AND SPA (CLASS 11), RETAIL
(CLASS 1A), RESTAURANTS AND CAFES (CLASS 3), AND RELATED
USES; HOLIDAY LODGES (SUI GENERIS); AND OTHER HOLIDAY
ACCOMMODATION TYPES (SUI GENERIS); NEW PARKING AREAS,
ROADS, WALKWAYS, AND CYCLEWAYS; DRAINAGE AND OTHER
INFRASTRUCTURE; AND LANDSCAPING AND BIODIVERSITY
ENHANCEMENT: LAND AT CAMUS BRUAICH RUAIDHE, CONNEL (REF:
25/01210/PAN) 
The Senior Planning Officer spoke to the terms of the report. 
The proposed site is located within open countryside, adjacent to the western settlement
boundary of Connel and to the North of the A85, around Camus Bruaich Ruaidhe bay
(Loch Etive).  The site is also identified as a Potential Development Area (PDA) in the
adopted Local Development Plan 2 for a Marina/Leisure/Tourism use. 
The report sets out the information submitted to date as part of the Proposal of Application
Notice (PAN) and summarises the policy considerations, against which any future
planning application will be considered as well as potential material considerations and
key issues based upon the information received to date.   
It was recommended that Members note the content of the report and submissions and
provide such feedback as they consider appropriate in respect of the PAN to allow these
matters to be considered by the Applicant in finalising any future planning application
submission. 
Decision

Page 9

The Committee noted the content of the report and requested that the following matters be
given consideration in finalising any future planning application submission – 
• To ensure that any improvements to infrastructure are tied into neighbouring
developments or potential developments as outlined in LDP2, in particular, the Oban
Development Road, leisure development (potential Golf Course) and maybe housing
nearby. 
• Minimise impacts on transport links and potentially have a benefit that can be shared
across several developments. 
• Any development to be undertaken to have a high standard of sensitivity to this area. 
(Reference: Report by Head of Development and Economic Growth dated 29 August
2025, submitted) 
Councillor Peter Wallace left the meeting during consideration of the foregoing item. 
7. UPDATE ON PLANNING PERMISSION NON-DETERMINATION APPEAL:
LAND TO THE IMMEDIATE WEST OF TAYNUILT SUBSTATION,
TAYNUILT 
The Senior Planning Officer spoke to the terms of the report. 
The planning application for the Battery Energy Storage Unit at land to the immediate
West of Taynuilt Substation was presented to Members for determination on 18 June
2025 with a recommendation from Officers that it should be approved.  At this meeting
Members agreed to hold a pre-determination hearing to assist them in making a
determination on whether to approve or refuse this application. 
The Applicant has now lodged an appeal to Scottish Ministers on the basis of non-
determination which means the matter has been removed from Council process without
Members have an opportunity to express a formal view and the site visit and hearing have
now been superseded by the appeal and can now no longer proceed. 
Within the appeals process there is an opportunity for the Planning Authority to make
submission to the Reporter on the mechanism by which the appeal should be decided. 
A report seeking a view from Members on the response to the Appeal was considered. 
Decision 
The Committee agreed: 
1. to note the submission of the Non-Determination Appeal; and  
2. that the response to the Appeal should include the following: 
• Reflect the factual position the PPSL had reached advising on the level of objection
and comment the application has generated and, in particular, that Members had
determined to have a site visit and pre-determination hearing and therefore

Page 10

recommend by submissions that this is a course that the Reporter should follow in
this case. 
• Due to the weight of public opinion the PPSL were of the view that only a site visit
and pre-determination hearing would give them a better understanding of the
location of the proposed development, before they reached a conclusion on their
deliberations. 
• Members were cognisance of public opinion on this and with that public opinion, as
a planning authority, the Committee felt they had a duty not only to look at the
Development Plans and Policies and consider applications against those, but to be
seen to do that in the eyes of the public.  In this case the level of interest was such
that for the public to have confidence in the planning system, and the Committee as
planning authority, that the Committee were carrying out their role and scrutinising
this, and in comparing the application with the policies, that a pre-determination
hearing and site visit were the proportionate and appropriate course of action.  The
Committee were of the view that the only way at this point where they could
continue to reach that view reached by democratic decision, and avoid a
democratic deficit with that, was for the Reporter now to take on that role of being
seen to not only consider the Policies, but to be seen to consider publically these
Policies before coming to a decision. 
• The Committee felt there was more information they required than what was
contained in the submissions before them.  The Committee felt this information
would be more readily obtained from seeing the site first hand and from the
hearing.  Also in relation to the exact location of the site, the impact on
neighbouring properties, noise, and also the potential risks with such a
development, and being able to put these into context.  They believed having that
site visit and hearing, where they would have been able to gather that information
directly and follow it up with questions, was vital in this instance. 
(Reference: Report by Head of Development and Economic Growth dated 5 September
2025, submitted) 
8. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - FQ1 2025/26 
A report providing an update on the performance of the Development Management
Service for the reporting period FQ1 2025/26 was considered. 
Decision 
The Committee reviewed and agreed the content of the report. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 8 September 2025, submitted) 
The Committee resolved in terms of Section 50(A)(4) of the Local Government (Scotland)
Act 1973 to exclude the press and public for the following 2 items of business on the
grounds that they were likely to involve the disclosure of exempt information as defined in
Paragraph 13 respectively of Part 1 of Schedule 7A to the Local Government (Scotland)
Act 1973.

Page 11

Councillor Graham Hardie, having declared an interest in the following item, left the
meeting at this point. 
9. ENFORCEMENT REPORT - REFERENCE 15/00051/ENAMEN 
The Committee considered enforcement case reference 15/00051/ENAMEN. 
Decision 
The Committee agreed the recommendations detailed in the report. 
(Reference: Report by Head of Development and Economic Growth dated 18 September