Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 605522
DX 599700 LOCHGILPHEAD 
11 November 2025 
NOTICE OF MEETING 
A meeting of the PLANNING, PROTECTIVE SERVICES AND LICENSING COMMITTEE will be
held BY MICROSOFT TEAMS on TUESDAY, 18 NOVEMBER 2025 at 11:00 AM, which you are
requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST 
3. MINUTES 
(a) Planning, Protective Services and Licensing Committee held on 22
October 2025 at 11.00 am (Pages 3 - 8)  
(b) Planning, Protective Services and Licensing Committee held on 22
October 2025 at 2.30 pm (Pages 9 - 10)  
(c) Planning, Protective Services and Licensing Committee held on 22
October 2025 at 3.30 pm (Pages 11 - 16) 
4. THE SCOTTISH GOVERNMENT: SECTION 36 CONSULTATION FOR WIND FARM
CONSISTING OF 9 TURBINES EACH WITH A MAXIMUM BLADE TIP HEIGHT OF
UP TO 180 METRES.  GENERATING CAPACITY WILL BE MORE THAN 50MW:
KILLEAN ESTATE, NEAR TAYINLOAN (REF: 24/01541/S36) (Pages 17 - 66)  
Report by Head of Development and Economic Growth 
5. MR KYLE KENNEDY: ERECTION OF DWELLINGHOUSE, FORMATION OF
VEHICULAR ACCESS AND ASSOCIATED WORKS: LAND BETWEEN LAGARIE
LODGE AND LAGARIE HOUSE, TORWOODHILL ROAD, RHU (REF:
25/00576/PP) (Pages 67 - 96)  
Report by Head of Development and Economic Growth 
Public Document Pack

Page 2

6. MR GAETANO GRIEVE: ERECTION OF 4 DWELLINGS, INSTALLATION OF
SEWAGE TREATMENT PLANTS AND FORMATION OF 2 VEHICULAR
ACCESSES: LAND WEST OF KOMANI AROS MAINS, AROS, ISLE OF MULL
(REF: 25/01248/PP) (Pages 97 - 128)  
Report by Head of Development and Economic Growth 
7. TARBERT CONSERVATION AREA APPRAISAL AND MANAGEMENT PLAN
(Pages 129 - 196)  
Report by Executive Director with responsibility for Development and Economic
Growth 
8. DEVELOPMENT MANAGEMENT PERFORMANCE UPDATE - FQ2 2025/26 (Pages
197 - 210)  
Report by Executive Director with responsibility for Development and Economic
Growth
E1 9. EMERGENCY TREE PRESERVATION ORDER (Pages 211 - 218)  
Report by Executive Director with responsibility for Development and Economic
Growth 
The Committee will be asked to pass a resolution in terms of Section 50(A)(4) of the Local
Government (Scotland) Act 1973 to exclude the public for items of business with an “E” on the
grounds that it is likely to involve the disclosure of exempt information as defined in the
appropriate paragraph of Part I of Schedule 7a to the Local Government (Scotland) Act 1973. 
The appropriate paragraph is:- 
E1 Paragraph 13  Information which, if disclosed to the public, would reveal that the
authority proposes- 
(a) to give under any enactment a notice under or by virtue of which requirements
are imposed on a person; or
(b) to make an order or direction under any enactment. 
Planning, Protective Services and Licensing Committee 
Councillor John Armour Councillor Gordon Blair (Vice-Chair)
Councillor Jan Brown Councillor Audrey Forrest
Councillor Kieron Green (Chair) Councillor Amanda Hampsey
Councillor Daniel Hampsey Councillor Graham Hardie
Councillor Fiona Howard Councillor Mark Irvine
Councillor Andrew Kain Councillor Paul Donald Kennedy
Councillor Liz McCabe Councillor Dougie Philand
Councillor Peter Wallace   
Contact: Fiona McCallum                  Tel. No. 01546 604392

Page 3

MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING
COMMITTEE held BY MICROSOFT TEAMS on WEDNESDAY, 22 OCTOBER 2025 
Present: Councillor Kieron Green (Chair) 
Councillor Jan Brown
Councillor Amanda Hampsey
Councillor Graham Hardie
Councillor Fiona Howard
Councillor Andrew Kain 
Councillor Paul Donald Kennedy
Councillor Liz McCabe
Councillor Dougie Philand
Councillor Peter Wallace 
Attending: Stuart McLean, Committee Manager
Peter Bain, Development Manager
Sandra Davies, Major Applications Team Leader
Arlene Knox, Senior Planning Officer 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors John Armour, Gordon Blair, Audrey
Forrest, Daniel Hampsey and Mark Irvine. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. MINUTES 
a) The Minute of the Planning, Protective Services and Licensing Committee held on 16
September 2025 at 11.00 am was approved as a correct record. 
b) The Minute of the Planning, Protective Services and Licensing Committee held on 16
September 2025 at 2.30 pm was approved as a correct record. 
c) The Minute of the Planning, Protective Services and Licensing Committee held on 16
September 2025 at 3.30 pm was approved as a correct record. 
d) The Minute of the Planning, Protective Services and Licensing Committee held on 30
September 2025 at 10.00 am was approved as a correct record. 
e) The Minute of the Planning, Protective Services and Licensing Committee held on 30
September 2025 at 2.00 pm was approved as a correct record. 
4. THE SCOTTISH GOVERNMENT: SECTION 36 CONSULTATION FOR WIND
FARM CONSISTING OF 9 TURBINES EACH WITH A MAXIMUM BLADE
TIP HEIGHT OF UP TO 180 METRES.  GENERATING CAPACITY WILL BE
MORE THAN 50MW: KILLEAN ESTATE, NEAR TAYINLOAN (REF:
24/01541/S36) 
The Senior Planning Officer spoke to the terms of the report which provided a
recommended response to the Scottish Government’s Energy Consents Unit (ECU)
Page 3 Agenda Item 3a

Page 4

consultation on a Section 36 Application for a wind farm on the Killean Estate, near
Tayinloan. 
This report reviewed the relevant policy considerations, planning merits, and views of
consultees and representations. 
An extension was requested from the ECU in May to enable objections to be resolved
from NatureScot, The Royal Society for the Protection of Birds (RSPB) Scotland and
National Air Traffic Services (NATS) and a consultation response to be received from
West of Scotland Archaeology Service.  This request was refused, and a holding objection
was submitted which requested that the ECU postpone making a decision on the
application until the outstanding matters had been resolved and the Council provides
another response.  Apart from the outstanding NATS objection all matters have been
resolved, and it is intended that this report and its recommendation will provide the
Council’s final consultation response to the ECU. 
The Committee was asked to agree the recommended response to the ECU set out in the
report of handling. 
During consideration of this item the Chair ruled, and the Committee agreed, to
adjourn the meeting at 12 noon to allow Members time to consider a competent
Motion to object to this application.   
The Committee reconvened at 12.20 pm with all those present as per the sederunt. 
Decision 
The Committee agreed that the ECU be notified accordingly that: 
1. There is an unresolved objection from National Air Traffic Services Safeguarding
(NATS). Consequently, Argyll and Bute Council Object on the grounds that the
proposal will have an adverse Aviation Impact, contrary to the provisions of Policy 11 –
Energy of National Planning Framework 4 (NPF4) which requires that project design
and mitigation demonstrates how impacts on aviation and defence interests including
seismological recording have been addressed, Policy 30 – the Sustainable Growth of
Renewables of Local Development Plan 2 (LDP2) which requires impacts on aviation
and defence interests and seismological recording to be addressed, and Policy 43 –
Safeguarding of Aerodromes of LDP2 which stipulates that development will not be
permitted where it would compromise the safe operation of an Aerodrome or Technical
Site or constrain their present or future operations. 
2. Argyll and Bute Council also intends to object to the application on the basis of
NPF 4 policies 4a and 11 Section E, Paragraphs 2, 3, 4 and 13 and LDP2 Policy
30 on the basis that the application would have a cumulative, significant and
unacceptable adverse impact in respect of landscape, visual and cumulative
matters and that a detailed representation would be submitted following
consideration of the matter at the next scheduled meeting of PPSL Committee. 
Having moved an Amendment which failed to find a seconder, Councillor Paul Kennedy
asked for his dissent from the foregoing decision to be recorded. 
(Reference: Report by Head of Development and Economic Growth dated 6 October
2025, submitted)
Page 4

Page 5

Councillor Paul Kennedy left the meeting at this point. 
5. THE SCOTTISH GOVERNMENT: SECTION 36 CONSULTATION FOR
ERECTION OF 12 WIND TURBINES WITH A MAXIMUM BLADE TIP
HEIGHT OF UP TO 200 METRES AND BATTERY ENERGY STORAGE
SYSTEM (BESS) - CORR CHNOC WIND FARM:  LAND APPROXIMATELY
2KM NORTH EAST OF KILMORE AND 5KM EAST OF THE CENTRE OF
OBAN (25/00036/S36) 
The Major Applications Team Leader spoke to the terms of the report which provided a
recommended response to the Scottish Government’s Energy Consents Unit (ECU)
consultation on a Section 36 Application for Corr Chnoc Wind Farm on land approximately
2km North East of Kilmore and 5km East of the centre of Oban. 
This report reviewed the relevant policy considerations, planning merits, and views of
consultees and representations.  Reference was also made to a supplementary report
which provided an update regarding an issue in relation to NatureScot’s consultation
response to the ECU and an update on the numbers of representations submitted to the
ECU. 
The Committee was asked to agree the recommended response to the ECU set out in the
report of handling. 
Decision 
The Committee agreed that the ECU be notified accordingly that: 
1. Argyll and Bute Council Objects to the proposal on the grounds that there are
unresolved ornithology issues contrary to the provisions of National Planning
Framework 4 (NPF) Policies 3 and 11 and Local Development Plan 2 (LDP2) Policies
30 and 73, and it is not possible to reach a conclusion on the proposal's acceptability
in this regard at this time.   
NOTE - If these matters are resolved to the satisfaction of NatureScot, Argyll and Bute
Council will withdraw this objection.  Should the objection remain unresolved, and the
proposal progresses to Public Inquiry, Argyll and Bute Council would defer to
NatureScot. 
2. Argyll and Bute Council does not object on landscape and visual grounds subject to
the removal of Turbine 18 (as agreed by the applicant).   
The Council recommends the following advice is also considered by the Energy
Consents Unit: 
Mitigation - Consideration should be given to the mitigation recommended by the
Council’s Consultant Landscape Architect: 
1. Felling of 27.44 ha of woodland and forest would be required for construction of the
access including 5.63 ha of AWI woodland. Of the total felling, 10.76 ha of
woodland would be restocked on site. The remaining 16.68 ha of felled woodland
would not be restocked within the site, but compensation planting would be
required to comply with the Scottish Government's Control of Woodland Removal
Page 5

Page 6

Policy. The Applicant commits to providing appropriate compensatory planting to be
agreed with Scottish Forestry and controlled through planning conditions. Where
possible restocking should be local to the windfarm area and comprise native
species broadleaf woodland to help offset losses of AWI woodland, enhance the
surrounding landscape and potentially provide ‘positive effects for biodiversity’ (in
line with NPF4 Policy 2). 
2. Smart aviation lighting (ADLS) activated by approaching aircraft be implemented if
it is approved for use in UK airspace before construction of the windfarm.  A
condition is recommended to ensure that ADLS be installed should it become
available for use in the UK. 
3. Argyll and Bute does not object on noise impact grounds subject to the inclusion of a
condition recommended by the Council’s Noise Consultant including the apportioned
limits as set out in the July 2025 response from the applicant (Metrica 15/7/25). 
4. Argyll and Bute Council does not object on Public Access grounds subject to a
condition requiring the developer to prepare an Access Plan for approval by the
Council prior to the commencement of construction. 
5. Argyll and Bute Council does not object on Roads grounds subject to the conditions
specified by the Roads Service in their consultation response dated 14/01/25, namely: 
• New accesses at junction with public road, (UC32 Glenlonan)to be constructed in
accordance with Operational Services Drg No SD08/001a and aligned to 90° to the
public road. New accesses on UC32 to be staggered for a minimum 30m and not
be directly opposite each other. 
• No walls, fences, hedges etc will be permitted within 2m from the channel line of
the public road. Visibility splays measuring 84m x 2.4m to be cleared and
maintained at connections with UC32 Road. 
• A system of surface water drainage is required to prevent the flow of water from
passing onto the public road. Any roadside ditch/drains to be culverted in
agreement with Roads. 
• Road signs and road markings as per TSRGD to be installed as following. 
• Signs as per Dia 504.1 to be installed at an agreed location on the public road,
(UC32) east and west of new junctions. 
• Road markings as per Dia 1002.1 and 1022 to be installed at new junctions at
connections with UC32. 
• Junction signs as per Dia 601.1 to be installed at junctions with public road. 
6. Argyll and Bute Council requests that the recommendations of the Local Biodiversity
Officer are considered by the ECU: 
While the impact to bats is unlikely to be significant, it would be advisable to monitor
any fatalities that may occur from collision as they are found to forage within the wind
Page 6

Page 7

turbine areas. This information will feed into mitigation measures which can be altered
accordingly to ensure any negative impacts to foraging / commuting bats is minimal. 
7. Marsh Fritillary Butterflies: Whilst NatureScot has not objected to this issue, it is noted
that there are unresolved issues between the applicant and NatureScot. It is
recommended that the ECU gives further consideration to this issue before
determining the application. 
8. Argyll and Bute Council requests that all other conditions recommended by consultees
are included in any Consent. 
(Reference: Report by Head of Development and Economic Growth dated 6 October 2025
and Supplementary Report Number 1 dated 21 October 2025, submitted) 
Councillor Amanda Hampsey left the meeting during consideration of the foregoing item. 
Page 7

Page 8

This page is intentionally left blank

Page 9

MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING
COMMITTEE held BY MICROSOFT TEAMS on WEDNESDAY, 22 OCTOBER 2025 
Present: Councillor Kieron Green (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Audrey Forrest 
Councillor Fiona Howard
Councillor Dougie Philand 
Attending: Stuart McLean, Committee Manager
David Walker, Solicitor
James Gray, Applicant 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Gordon Blair, Amanda Hampsey,
Daniel Hampsey, Graham Hardie, Mark Irvine, Andrew Kain, Paul Kennedy and Liz
McCabe. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. CIVIC GOVERNMENT (SCOTLAND) ACT 1982: APPLICATION FOR
GRANT OF TAXI CAR LICENCE (J GRAY, OBAN) 
The Chair welcomed everyone to the meeting.  In line with recent legislation for Civic
Government Hearings, the parties (and any representatives) were given the options for
participating in the meeting today.  The options available were by video call, by audio call
or by written submission.  For this hearing the Applicant opted to proceed by way of audio
call and Mr Gray joined the meeting by telephone. 
The Chair outlined the procedure that would be followed and invited the Applicant to
speak in support of their application. 
APPLICANT 
Mr Gray advised that he has been working as a taxi driver with Lorn Taxis for a number of
years and that he also ran his own tour business.  He said that he had recently purchased
a new vehicle and advised that, due to demand for his tours dropping off, and no further
tour business expected during the winter months, rather than work for someone else, and
the additional costs associated with this, he would rather work for himself. 
He said that as a taxi driver he could see the need for more taxis in the town.  He advised
that since the survey was carried out in 2019, demand in the town had changed,
especially at the weekends.  He made reference to the new housing development in
Dunbeg with over 2,000 homes built and no provision for them. 
He advised that this has led to him receiving a lot of complaints from customers that have
had to wait longer for a taxi.  He said this issue particularly affected the elderly whom he
liked to support. 
Page 9 Agenda Item 3b

Page 10

MEMBERS’ QUESTIONS 
Councillor Brown sought and received confirmation from Mr Gray that it was demand for
his tour business that had dropped off and that his taxi work was more important than
ever. 
Councillor Philand sought and received confirmation from Mr Gray that all the necessary
insurances were in place for his new vehicle. 
SUMMING UP 
Applicant 
Mr Gray thanked the Committee for their time, and he confirmed that he had received a
fair hearing. 
DEBATE 
Councillor Brown advised that she had no issues with granting this taxi car licence and
that she would be happy to approve the application. 
Councillor Green agreed with Councillor Brown and commented that Mr Gray had set out
how the situation in the town had changed since 2019.  He said he could fully understand
the additional demand for taxis. 
DECISION 
The Committee unanimously agreed to grant a Taxi Car Licence to Mr Gray and noted
that he would receive written confirmation of this within 7 days. 
(Reference: Report by Head of Legal and Regulatory Support, submitted) 
Page 10

Page 11

MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING
COMMITTEE held BY MICROSOFT TEAMS on WEDNESDAY, 22 OCTOBER 2025 
Present: Councillor Kieron Green (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Audrey Forrest 
Councillor Fiona Howard
Councillor Dougie Philand
Councillor Peter Wallace 
Attending: Stuart McLean, Committee Manager
Alida Acherman, Licensing Standards Officer
David Walker, Solicitor
Alan Morrison, Applicant
Pi Davidson, Applicant’s Agent
Patricia Jackson, Objector 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Gordon Blair, Amanda Hampsey,
Daniel Hampsey, Graham Hardie, Mark Irvine, Andrew Kain, Paul Kennedy and Liz
McCabe. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. CIVIC GOVERNMENT (SCOTLAND) ACT 1982, THE CIVIC GOVERNMENT
(SCOTLAND) ACT 1982 (LICENSING OF SHORT-TERM LETS) ORDER
2022: APPLICATION FOR GRANT OF A SHORT-TERM LET LICENCE (A
MORRISON, CURLEW COTTAGE, BRUICHLADDICH, ISLE OF ISLAY) 
The Chair welcomed everyone to the meeting.  In line with recent legislation for Civic
Government Hearings, the parties (and any representatives) were given the options for
participating in the meeting today.  The options available were by video call, by audio call
or by written submission.   
For this hearing the Applicant and his Agent opted to proceed by way of video call and
Alan Morrison and Pi Davidson joined the meeting by MS Teams. 
Patricia Jackson, Objector, opted to proceed by audio call and joined the meeting by
telephone. 
Before proceeding further, the Chair invited the Licensing Standards Officer to address the
matter of a late letter of objection from Mrs Jackson which had been received out with the
time period allowed by the Civic Government (Scotland) Act 1982 for making objections or
representations.   
It was noted that it would be competent under Paragraph 3(2) of Schedule 1 of the 1982
Act for the Committee to entertain a late objection or representation if they were satisfied
that there was sufficient reason for it not having been made within the time allowed.  It
was also noted that the Applicant had been provided with a copy of the late objection. 
Page 11 Agenda Item 3c

Page 12

Mrs Jackson explained that this was not a new objection, but additional information to
clarify her previous objection.  Mr Morrison confirmed that he would have no objection to
this late submission being admitted into the hearing today. 
Having noted the reason for the late objection, the Committee agreed to accept this into
the process. 
The Chair ruled, and the Committee agreed, to adjourn the meeting at 3.40 pm for 10
minutes to allow time for the late objection to be circulated and considered.  The
Committee reconvened at 3.50 pm with all those present as per the sederunt. 
The Chair invited the Licensing Standards Officer to speak to the terms of the report. 
Thereafter the procedure set out in Appendix 6 of the report was followed, and the Chair
invited the Applicant and his Agent to speak in support of the application. 
APPLICANT 
The following statement was read out by the Applicant. 
My name is Alan Morrison.  I've owned Curlew Cottage since 2007 and operated it
successfully as a holiday let from 2008 until 2022, when the licensing scheme was
introduced. 
This cottage was purpose-built as a holiday let in 1985.  For nearly 15 years, I operated it
with no complaints from neighbours.  I would like to resume that use, with Mrs Davidson
managing on a day-to-day basis. and I want to do it properly. 
I understand Mrs Jackson has legitimate concerns about boundaries and the septic
system.  I take full responsibility for addressing both. 
I commit to installing a boundary fence with vehicle gate before accepting any guest
bookings.  This will clearly separate the two properties and address privacy and security
concerns.  I acknowledge there is an issue with where the boundary lies but I'm ready to
work with Mrs Jackson on this and the fence design and will ensure it's appropriate for the
rural setting. 
I commit to completing the septic tank replacement.  The work is scheduled for the week
commencing 24th November 2025, with written confirmation from our contractor, Callum
Simpson of Septic Tank Services.  A new system will be installed entirely within our
boundary, fully compliant with SEPA regulations. 
No guests will be accepted until both the fence and septic tank are complete.  I will
provide photographic evidence to the licensing officer before we begin operating. 
The Licensing Officer inspected the property and recommended approval. We meet all
safety requirements.  We simply want to resume what this cottage was built for - providing
quality holiday accommodation on the island - while being responsible, considerate
neighbours. 
Thank you. 
The Applicant’s Agent read out the following statement.
Page 12

Page 13

My name is Pi Davidson, and I'll be managing the day-to-day operations of Curlew
Cottage as Alan's agent.
I also want to acknowledge that communication between myself and Mrs Jackson has
been difficult at times.  I take responsibility for my part in that.  Moving forward, I'm
committed to maintaining professional, respectful communication, and we have local
contacts who can help mediate any issues that arise.
I understand that Mrs Jackson has concerns about how the property will be managed.  I
want to reassure the Committee and Mrs Jackson that we take neighbour relations
seriously.
Here's how we'll manage the property responsibly:
Bins: Stored at the property and wheeled to the roadside only on collection days.
The shared driveway: Our house manual includes clear instructions for navigating the
access track safely, including protocols for passing other vehicles.
Comprehensive house manual: All guests will receive detailed information about
boundaries, expected behaviour standards, and respecting neighbours.  This will be
provided in pre-arrival communications, welcome emails, and a physical manual inside the
property.
We have two local contacts who can respond immediately to any issues raised by
neighbours or guests.
I live on Jura and travel to Islay regularly.  I'm accessible and committed to addressing any
concerns quickly and professionally.
We want to be exemplary neighbours and responsible operators.  This property operated
successfully for 15 years - we're asking for the opportunity to demonstrate we can do so
again.
Thank you.
QUESTIONS FROM OBJECTOR 
Mrs Jackson asked Mr Morrison where the evidence was that the cottage was used as a
holiday let between 2020 and 2022.   She said that she bought her property at the
beginning of 2020 and had been assured at that time by Mr Jackson and Mrs Davidson
that Curlew Cottage had been used as a holiday let in the past and was no longer used. 
She said that during 2020 it had been occupied 3 or 4 times by family and friends.  She
said the claim made that it was operating as a holiday let until 2022 was not correct. 
Mr Morrison advised it was the case that it was last let in 2022.  He referred to dealing
with the Covid period when no one was visiting.  He said that he’d had a good relationship
with his previous neighbour and had previously had a number of regular visitors to the
cottage.  He said that he was disappointed that due to the incoming licensing legislation
and being a busy time personally for himself because of post Covid work, he was not able
to continue letting it.  He said it was the case that they were letting it until the new
licensing regime came into place. 
Page 13

Page 14

OBJECTOR 
Mrs Jackson said that she hoped the issue with the septic tank would be addressed.  She
commented that it would be really close to her boundary.  She advised that the boundary
fence remained an issue and referred to trying and failing to make contact with Mr
Morrison to discuss this.  She said she would like Mr Morrison’s assurance that he would
meet with her to have a proper discussion about where the boundary was.  She said it
was a complicated boundary which cut diagonally across the land.  She said it was going
to be difficult to put a fence up along the boundary. 
She advised that the other issue was privacy.  She referred to seating outside the front of
Curlew Cottage.  She explained that as the land was higher there than her land, those
seats looked directly into her dining room where her family sat quite often.  She said that
people sitting on the seats outside could be heard from inside her house and that she
could see them watching her.  She said she would like the seating to be removed from the
front of the house.  She advised that at the moment it was located 2 metres from where
she got out of her car and that people were able to watch her coming and going.  She said
she wanted Mr Morrison to address that. 
She advised that this would have a huge impact on her day-to-day life, being presented
with different people every week and the potential for hundreds of different dogs in the
area over the year.  She said it would be a massive impact on her life. 
QUESTIONS FROM APPLICANT 
Mr Morrison advised that he had no questions. 
MEMBERS’ QUESTIONS 
Councillor Forrest asked the Licensing Standards Officer for her view on whether the
seats overlooked the neighbour’s house.  Ms Acherman advised that when she visited the
property she looked out of all the windows from inside the property.  She said she did not
sit on the seats which were positioned in front of the middle of the property.  She said she
did not notice at any point that she was looking into someone’s dining area or kitchen
when she was at the front of the property. 
Councillor Green asked Mr Morrison if the proposed fence would resolve Mrs Jackson’s
concerns regarding overlooking.  Mr Morrison said he was not certain.  He explained the
boundary fence would come from the front southeast of the cottage.  He said the corner of
the cottage adjacent to Mrs Jackson’s property had an accessible pathway, with a gentle
sloping ramp to the front door that continued around the front of the property.  The location
of the seating was next to the front door in the middle of the front elevation.  Mr Morrison
advised that the fence would be on his boundary and that he did not think it would be a
solid barrier type fence. 
Mrs Jackson agreed that a post and wire fence with vegetation would be more in keeping
with the area.  She said the seating at the front elevation and the path were higher than
her parking area and window into her dining area.  She advised that unless the fence was
really high, anyone sitting there would be able to look over. 
SUMMING UP 
Objector
Page 14

Page 15

Mrs Jackson referred to her objection about the septic tank and said she hoped that would
be dealt with.  She advised that she still had misgivings about the significant effect this
proposed short-term let would have on her and her family’s privacy and security.  She said
that until a gate was installed securely children and dogs would not be able to be kept
under control within Curlew Cottage grounds.  She commented that if Mr Morrison was
saying he would address this, she would just have to wait and see. 
Applicant 
Mr Morrison said that he and his family have always visited the cottage 3 to 5 times per
year with their dog.  He advised that they never let their dog loose in the front garden off
lead.  He referred to sheep being in the adjacent field.  He confirmed that he would make
it a house rule that only dogs on a lead can be walked from the house.  He said that he
shared Mrs Jackson’s frustration about the septic tank.  He advised that the problem came
about just after Covid and had never been a problem before.  He said he found getting a
locally based contractor very difficult as they were very busy on the island.  He advised
that the contractor was local to Lochgilphead and a specialist in septic tanks and that he
was sure he would do a first-class job.  He confirmed that he would be happy to work with
Mrs Jackson in respect of the boundary.   He commented that Mrs Jackson and her family
had done an excellent job renovating their property and grounds.  He referred to running
the property as a holiday let in the past with people staying there year after year.  He said
he was confident that things would settle down and the issues Mrs Jackson had would be
resolved. 
When asked, both parties confirmed that they had received a fair hearing. 
DEBATE 
Councillor Brown said she shared the issues highlighted by the Objector.  She said these
issues were not new and were often highlighted by neighbours.  She commented that she
appreciated that this property was not a short-term let when Mrs Jackson took possession
of her home.  She advised that she hoped, with a good bit of give and take on both sides
that these issues could be resolved.  She said she would be happy to grant this short-term
let licence. 
Councillor Howard sought and received confirmation from the Council’s Solicitor that the
Committee would not be able to include a condition regarding the boundary fence as this
was a private matter for parties to resolve and fell out with the licensing regime.  He said
Members could, if they wished, make a recommendation in this regard. 
Councillor Green asked the Council’s Solicitor if a condition could be included preventing
pets from being in the property until the fence was erected.  Mr Walker advised that it may
be best to make a recommendation that this be included in the guest handbook but he
would double check and get back to the Committee. 
Councillor Armour referred to the property being a self-catering property from 2007 to
2020.  He said he assumed that due to Covid they did not have anyone staying there from
2020 to 2022 as it was very difficult to operate anything at all during that time.  He
commented that if this was a family home there could be potentially more than the
recommended maximum of 6 people for the short-term let residing there.  He said there
would not be people there all the time.  He advised that he could see where the Objector
was coming from in respect of concerns about privacy but commented that this was part of
Page 15

Page 16

living next door to someone else.  He advised that if someone wanted total privacy then
they would need to have a house well away from everyone else.  He added that as
someone that used to have a holiday let business, he met some very nice and interesting
people and that there were very few that caused problems.  He said that he had noted that
there were people on the island that would be able to deal with any problems that came
up.  He said he understood the Objector was looking for privacy but as this had been run
successfully as a holiday let until 2022, he could not see what will have changed and that
he would have no issue with approving this application. 
Councillor Philand said he was reassured that Mr Morrison intended to help his neighbour
with the issues raised and that he wished to address these.  He said he believed that
would happen.  He also noted that a number of the recommended conditions associated
with the licence would address some of these issues.  He hoped that these conditions and
working with Mr Morrison to address the other issues, would give Mrs Jackson some
reassurance.  He said he would be happy to grant this licence. 
Councillor Green said he was satisfied that the Applicant had responded to the various
concerns raised from the neighbouring property.  He said he was likewise minded to
support this application. 
Mr Walker referred to the earlier question about a condition to prevent dogs coming to the
property until the fence was erected.  He advised that the condition relating to anti-social
behaviour could be used to raise any issues in respect of dogs. 
DECISION 
The Committee unanimously agreed to grant a short-term let licence to Alan Morrison
subject to the inclusion of additional conditions set out in the report in respect of anti-social
behaviour, privacy and security, littering and waste disposal, damage to property, and
wood burning stoves/open fires, and noted that he would receive written confirmation of
this within 7 days. 
(Reference: Report by Regulatory Services and Building Standards Manager and late
objection, tabled) 
Page 16

Page 17

Argyll and Bute Council  
Development and Economic Growth     
This Supplementary report is a recommended response to the Scottish Government’s
Energy Consents Unit (ECU) consultation on the Section 36 application for a wind farm
located on the Killean Estate, near Tayinloan consisting of 9 turbines each with a
maximum blade tip height of up to 180m. Generating capacity will be more than 50MW
_________________________________________________________________________  
Reference No: 24/01541/S36/ECU00004927
Applicant:       The Scottish Government Consultation 
Proposal: Section 36 Consultation for wind farm located on the Killean Estate,
near Tayinloan, consisting of 9 turbines each with a maximum blade tip
height of up to 180m. Generating capacity will be more than 50MW
Site Address:   Killean Estate, near Tayinloan
________________________________________________________________________   
SUPPLEMENTARY REPORT NO. 1 
1. INTRODUCTION  
1.1 
1.2 
1.3 
1.4 
1.5 
This Supplementary Report is for the consideration of Members. 
A detailed Report of Handling was prepared for PPSL Committee on the 22nd
October 2025. 
At said committee the Senior Planning Officer spoke to the terms of the report which
provided a recommended response to the Scottish Government’s Energy Consents
Unit (ECU) consultation on the Section 36 Application for Killean wind farm. This
report reviewed the relevant policy considerations, planning merits, and views of
consultees and representations. 
An extension was requested from the ECU in May to enable objections to be
resolved from NatureScot, The Royal Society for the Protection of Birds (RSPB)
Scotland and National Air Traffic Services (NATS) and a consultation response to
be received from West of Scotland Archaeology Service. This request was refused,
and a holding objection was submitted which requested that the ECU postpone
making a decision on the application until the outstanding matters had been resolved
and the Council provides another response. Apart from the outstanding NATS
objection all matters have been resolved, and it is intended that this report and its
recommendation will provide the Council’s final consultation response to the ECU. 
The Committee was asked to agree the recommended response to the ECU set out
in the report of handling. During consideration of this item the Chair ruled, and the
Committee agreed, to adjourn the meeting to allow Members time to consider a
competent Motion to object to this application. The Committee reconvened and
agreed that the ECU be notified accordingly that: 
1. There is an unresolved objection from National Air Traffic Services Safeguarding
(NATS). Consequently, Argyll and Bute Council Object on the grounds that the
proposal will have an adverse Aviation Impact, contrary to the provisions of Policy
11 – Energy of National Planning Framework 4 (NPF4) which requires that project
Page 17 Agenda Item 4

Page 18

2.
design and mitigation demonstrates how impacts on aviation and defence interests
including seismological recording have been addressed, Policy 30 – the Sustainable
Growth of Renewables of Local Development Plan 2 (LDP2) which requires impacts
on aviation and defence interests and seismological recording to be addressed, and
Policy 43 – Safeguarding of Aerodromes of LDP2 which stipulates that development
will not be permitted where it would compromise the safe operation of an Aerodrome
or Technical Site or constrain their present or future operations. 
2. Argyll and Bute Council also intends to object to the application on the basis of
NPF 4 policies 4a and 11 Section E, Paragraphs 2, 3, 4 and 13 and LDP2 Policy 30
on the basis that the application would have a cumulative, significant and
unacceptable adverse impact in respect of landscape, visual and cumulative matters
and that a detailed representation would be submitted following consideration of the
matter at the next scheduled meeting of PPSL Committee. 
Conclusion  
2.1 Following PPSL Committee on the 22nd October, Officers informed the ECU of
Members decision and advised them that matters would be considered further at the
November Committee and thereafter the final response from Argyll & Bute Council
would be provided.  
3. Recommendation 
It is recommended that Members consider the contents of this report. 
Author of Report: Arlene Knox        Date: 3rd November 2025
Reviewing Officer: Sandra Davies       Date: 4th November 2025
 
  
Fergus Murray   
Head of Development and Economic Growth  
Page 18

Page 19

Argyll & Bute Council
Development & Economic Growth   
This report is a recommended response to the Scottish Government’s Energy
Consents Unit (ECU) consultation on the Section 36 application for a wind farm
located on the Killean Estate, near Tayinloan consisting of 9 turbines each with a
maximum blade tip height of up to 180m. Generating capacity will be more than 50MW 
Reference No: 24/01541/S36/ECU00004927
Applicant: The Scottish Government
Proposal: Section 36 Consultation for wind farm located on the Killean Estate,
near Tayinloan, consisting of 9 turbines each with a maximum blade
tip height of up to 180m. Generating capacity will be more than 50MW.
Site Address: Killean Estate, near Tayinloan 
(A)  THE APPLICATION 
The Section 36 Application comprises the following key elements: 
• Up to 9 wind turbines, each with a maximum tip height of 180m
• At each wind turbine, associated low to medium voltage transformers and related
switchgear
• Permanent wind turbine foundations
• Hardstanding areas for crane erection at each wind turbine
• Two new watercourse crossings and 14 existing crossings which may need to
be upgraded
• Approx. 10.5km of access tracks, comprising 5.58km of new tracks and 4.92km
of existing tracks to be upgraded
• Upgraded site access from the existing junction with the A83
• Temporary turning area to facilitate access on opposite side of road to site
access
• Onsite underground electrical cables and cable trenches
• Substation compound
• A temporary construction compound for office welfare and materials storage
• Up to 6 borrow pit search areas
• The potential for onsite concrete batching, the location of which would be
confirmed prior to commencement of development once need is confirmed
• Felling of 41.3ha hectares of forestry and associated compensatory planting.
• Habitat management and biodiversity improvements as set out in Outline
Biodiversity Enhancement Management Plan (OBEMP) 
The expected operational life is 50 years from the date of commissioning. 
Connection to Electricity Grid - The proposal is likely to be connected to the grid
network at Carradale substation, approx. 11.2km southeast of the site. Works
required to connect to the national grid would be the subject of a separate consenting
process. 
Page 19

Page 20

(B) RECOMMENDATION: 
That the ECU be notified accordingly that: 
(1) There is an unresolved objection from National Air Traffic Services Safeguarding
(NATS). Consequently, Argyll & Bute Council OBJECT on the grounds that the
proposal will have an adverse Aviation Impact, contrary to the provisions of
Policy 11 – Energy of NPF4 which requires that project design and mitigation
demonstrates how impacts on aviation and defence interests including seismological
recording have been addressed, Policy 30 – the Sustainable Growth of Renewables
of LDP2 which requires impacts on aviation and defence interests and seismological
recording to be addressed, and Policy 43 – Safeguarding of Aerodromes of LDP2
which stipulates that development will not be permitted where it would compromise
the safe operation of an Aerodrome or Technical Site or constrain their present or
future operations. 
Note: If NATS withdraw their objection and subject to any conditions they
recommend being attached to any grant of consent Argyll & Bute Council
would no longer object on these grounds. Should the objection remain
unresolved, and the proposal progresses to Public Inquiry, Argyll & Bute
Council would defer to NATS. 
(2) Argyll & Bute Council has no objection in respect to landscape and visual
impact subject to conditions to secure the mitigation recommended by the Council’s
Consultant Landscape Architect being attached to any grant of consent: 
• Aircraft Detection Lighting System 
• Substantial increases in broadleaved planting as part of the wind farm restocking
plan including riparian planting across the wider Killean estate. 
• Redesign of the outer margins of productive woodland to remedy hard angular edges
and improve the fit of plantations with landform. 
• Compensatory planting should be undertaken within the Killean Estate. Argyll & Bute
Council and Scottish Forestry should be consulted on the location, extent, and
composition. 
• Management of existing mature mixed woodlands in the vicinity of Killean House
including new planting to retain and enhance screening of the proposed wind farm
from the coast and protect the landscape setting provided to the Killean Estate
buildings and St John’s Church. 
(3) Argyll & Bute Council has no objection in respect to archaeological impact,
subject to conditions to secure appropriate archaeological mitigation being attached to
any grant of consent following further consultation with the West of Scotland
Archaeology Service. 
(4) Argyll & Bute Council has no objection in respect to Biodiversity Impact, subject
to conditions to secure the recommendations of the Local Biodiversity Officer being
attached to any grant of consent. 
• An appropriate plan for mitigation against potential deer impact on newly planted
trees until such time as they are established and no longer vulnerable to over-
browsing.
Page 20

Page 21

• While the impact to bats is unlikely to be significant, it would be advisable to monitor
any fatalities that may occur from collision as they are found to forage within the wind
turbine areas. 
(5) Argyll & Bute Council has no objection in respect to noise impact, subject to
suitably worded conditions to limit the noise levels, tonality, and amplitude modulation to
control noise levels from the proposal and provide appropriate noise mitigation as
recommended and agreed by the Councils Noise Consultant. 
(6) Argyll & Bute has no objection in respect to flood risk subject to conditions to
secure the recommendations of the Flood Risk Assessor being attached to any grant
of consent: 
• To ensure watercourse crossings are designed so there is no reduction in pre-
development channel cross sectional area ideally to pass the 1 in 200 year plus
climate change flood event; and,
• Surface water drainage is designed in accordance with CIRIA C753 and ensures
that post development runoff is attenuated to the 1 in 2 year greenfield runoff
rate. The surface water drainage should be in operation prior to the start of
construction. 
(7) Argyll & Bute Council has no objection in respect to Access subject to the
condition to secure the recommendation of the Access Officer being attached to any
grant of consent: 
• Access Plan to be submitted and agreed in writing by the Council prior to the
commencement of development. 
(8) Argyll & Bute Council has no objection in respect to provision of the turning area
across from the site access subject to the following conditions being attached to any
grant of consent. 
• Exact details and specifications of the design of the turning area to be submitted for
the written approval of the Planning Authority prior to commencement of
development.
• Exact details and specification of the restoration plan for the turning area to be
submitted for the written approval of the Planning Authority prior to commencement
of development. These shall include details of timescales and landscaping.
• A condition to limit the turning area to an appropriate temporary period to be agreed
in writing by the Planning Authority. 
(9) Argyll & Bute Council requests that all conditions recommended by other
consultees are included in any Consent. 
(C) CONSULTATIONS 
ENERGY CONSENTS UNIT RESPONSES 
NatureScot (18th November 2024) – advised the ECU they objected until further
collision risk information regarding the Kintyre Goose Roosts Special
Protection Area was provided. That while there are significant adverse landscape
and visual effects, they do not raise issues of national interest. They noted the
presence of Leisler’s bats within the footprint of the proposal, and that further advice
Page 21

Page 22

would be provided separately. They defer to Argyll & Bute Council and North
Ayrshire Council in terms of effects on locally designated landscapes. 
NatureScot (23rd January 2025) (Leisler bat advice) – advised the ECU that the bat
surveys indicate that there is at least a moderate level of bat activity within the survey
area. Of note is the occurrence of Leisler’s bat, which is a rare and high-risk species.
Kintyre is not currently acknowledged to be within the Leisler’s bat range; however,
the bat survey provides evidence of a wider distribution of this species in Scotland
than is currently known. Bat Mitigation - as the Applicant is proposing to keyhole
turbines into existing forestry, this can increase the risk of bat fatalities due to the
increase in forest edge habitat close to the turbines and associated infrastructure.
NatureScot advise that feathering is routinely applied to the turbine blades below
cut-in speed during operation. This measure can help reduce the risk of bat
casualties by 50%. If feathering is implemented, NatureScot would ask that
monitoring is carried out for 3 years post-construction to assess changes in bat
activity. NatureScot note that the Applicant was unable to have bat data analysed
through Ecobat as it was unavailable. NatureScot believe it is now available and
advise that the Applicant has the data analysed, if possible, to provide an
independent assessment on the level of bat activity at the site. 
NatureScot (30th May 2025) (response to additional information provided regarding
the Kintyre Goose Roosts Special Protection Area) – advised the ECU there are
natural heritage interests of international importance, but they will not be adversely
affected. This response should be read in conjunction with their other advice
provided on landscape & visual, ecological and bat impacts. 
Applicant Response to NatureScot’s further comments (18th June 2025) –
Applicant provided a note on NatureScot’s 30th May response to the ECU on issues
relating to ornithology, including Greenland White-fronted Geese, Survey Quality,
Golden Eagle, Black Grouse and Red-throated Diver. 
RSPB Scotland (29th November 2024) – advised the ECU they shared NatureScot's
concern regarding collision risk for Greenland White-fronted Geese and would
comment further on this once the information was provided. They advised that the
Outline Biodiversity Enhancement and Management Plan (oBEMP) is appropriate
and welcome the proposals that have been included. They note that felling will be
required should the proposal be consented. It is unclear where the Compensatory
Planting (CP) is to be provided. They recommend that it is delivered as low-density
native shrub and broadleaf woodland, and that planting on good quality open ground
habitats is avoided. 
RSPB (17th June 2025) (response to additional information provided regarding the
Kintyre Goose Roosts Special Protection Area) – advised the ECU they have no
further comments to make on the revised collision risk model for Greenland White-
fronted Goose. They do not object. 
Historic Environment Scotland (HES) (20th November 2024) – advised the ECU
the proposal does not raise historic environment issues of national significance, and
they do not object. They recommend that any trees forming the woodland backdrop
to the Killean Estate damaged or removed by works to upgrade the wind farm access
tracks, should be replaced. The access tracks should be designed to avoid direct
impacts on the Category A listed Doll’s Houses and avoid impacts on their setting,
and removal of the temporary bellmouth upon completion of turbine delivery. 
Page 22

Page 23

Scottish Forestry (25th September 2024) – advised the ECU compensatory planting
should be secured by a condition. Furthermore, the appropriate consenting route
required to accommodate construction, including infrastructure and management
felling, totalling 41.3ha would be the Section 36 consent. Restocking of management
felling areas and compensatory planting relating to permanent woodland loss would
also be via the Section 36 consent. 
Transport Scotland (TS) (4th October 2024) – advised the ECU they have no
objection subject to conditions being attached to any consent to secure approval of
details of the means of access to the trunk road, the route for abnormal loads,
abnormal load accommodation measures required, any necessary additional signing
or temporary traffic control measures, a Construction Traffic Management Plan
(CTMP), and wheel washing facilities. In addition, advisory notes are provided
relating to works within the trunk road boundary. 
SEPA (Scottish Environment Protection Agency) (2nd October 2024) – have
advised the ECU they have no objection subject to conditions being attached to any
consent to secure finalised plans for borrow pit management and restoration prior to
commencement of development (if not attached SEPA object), and a Finalised Peat
Management Plan. 
Argyll District Salmon Fishery Board (ADSFB) (25th September 2024) – advised
the ECU they are satisfied the proposal should not have any significant impact on
migratory salmonid fish habitat providing the construction phase is conducted
according to current environmental regulations. ADSFB are mindful that migratory
salmonid fish (sea trout) are present in the lower reaches of the Killean Burn,
Tayinloan Burn, Clachaig Water and Carradale Water which may be affected by any
deterioration in water quality caused during construction. ADSFB advise that in the
event of consent being granted monitoring of Water quality, macroinvertebrates, and
fish is undertaken to Scottish Government guidelines. 
Scottish Water (26th August 2024) – advised the ECU they have no objection. They
provide advice on Drinking Water Protected Areas and Surface Water. 
Ironside Farrar, Peat Landslide Hazard Risk Assessment (PLHRA), Stage 1
Checking Report (PLHRA) (6th February 2025) – advised the ECU the PLHRA is
satisfactory. 
Defence Infrastructure Organisation (DIO) (30th August 2024) – advised the ECU
that, subject to conditions to secure Aviation Lighting and Aviation Charting and
Safety Management they have no objection. 
NATS Safeguarding (23rd August 2024) – advised the ECU the proposal conflicts
with their safeguarding criteria and they object. 
NATS Safeguarding (14th July 2025) – advised the ECU that it is always their
preference to identify mitigation and, put in place the delivery framework before
withdrawal of their objection. However, they can confirm that they do have an
identified mitigation that with the commitment of both parties can be delivered prior
to the development commencing. 
Glasgow Airport (9th September 2024) – advised the ECU they have no objection. 
Glasgow Prestwick Airport (GPA) (4th October 2024) – advised the ECU they have
no objection.
Page 23

Page 24

Highlands & Islands Airport (22nd October 2024) – advised the ECU they required
an updated Instrument Flight Procedure Assessment report and submitted a holding
objection. 
Highlands and Islands Airports Limited (HIAL) (27th January 2025) advised the
ECU that an updated Instrument Flight Procedure impact assessment has been
provided which confirms the proposal will have no impact on the IFPs serving
Campbeltown Airport. Therefore, HIAL remove their holding objection. 
Campbeltown Community Council (3rd October 2024) – advised the ECU they
object on the following grounds: proximity to A83 and visibility, industrialisation of
Kintyre landscape, adverse impact on tourism, adverse visual impact, flooding on
the A83, adverse impact on peat deposits, use of outside contractors instead of local
firms, road delays caused by delivery of abnormal loads, and movement at night will
cause disruption due to noise and vibrations. 
West Kintyre Community Council (4th October 2024) – have advised the ECU they
object on the grounds of landscape & visual impact (including cumulative), adverse
impact on tourism, increase in local flooding, adverse noise and visual impact for
nearby properties, possible ill health effects, lack of information on battery storage
plans, and adverse ornithological impact. 
East Kintyre Community Council (22nd August 2024) – have advised the ECU they
object on the grounds of lack of full economic assessment on tourism attractions
(based on Kintyre), and adverse visual impact. 
Tarbert & Skipness Community Council (TSCC) (3rd October 2024) – have
advised the ECU they object on the grounds of the previous refusal on this site (WIN-
130-3), adverse visual impact, length of consent sought (50 years), approval would
set bad precedent, adverse impact on recreation & tourism, Adverse impact on
natural heritage and ornithology, cultural heritage impacts and adverse impact of
aviation Lighting. 
BT (29th August 2024) – advised the ECU they have no objection. 
Arqiva (28th August 2024) – advised the ECU they have no objection subject to a
condition to mitigate the impact of any degradation of television and radio reception
caused by the wind turbines. 
Joint Radio Company (29th August 2024) – advised the ECU the proposal is
cleared subject to a condition to secure 100m Micrositing with respect to radio link
infrastructure operated by the local energy networks. 
North Ayrshire Council (4th October 2024) – advised the ECU that consideration
should be given to the potential impacts on the North Arran NSA. 
Argyll & Bute Council Consultee Responses 
Consultant Landscape Architect (10th February 2025) - recommends no objection
in respect of landscape and visual interests subject to conditions to secure: an Aircraft
Detection Lighting System, Substantial increases in broadleaved planting as part of the
wind farm restocking plan including riparian planting across the wider Killean estate,
Redesign of the outer margins of productive woodland to remedy hard angular edges
and improve the fit of plantations with landform, Compensatory planting within the Killean
Page 24

Page 25

Estate. Argyll & Bute Council should be consulted, in addition to Scottish Forestry, on
the location, extent and composition of this planting, and management of existing mature
mixed woodlands in the vicinity of Killean House including new planting to retain and
enhance screening of the proposed wind farm from the coast and protect the landscape
setting provided to the Killean Estate buildings and St John’s Church. 
West of Scotland Archaeology Service (WOSAS) (28th August 2025) – does not
recommend an objection and provides general comments and advice on direct and
indirect physical impact issues and setting and cumulative impact issues. In terms
of cumulative impact WOSAS find they cannot support the proposed encroachment
onto lower ground that is more densely populated with known archaeological sites
and monuments. WOSAS does not believe that an objection solely based on
predicted adverse impacts on the historic environment would be likely to be
sustained. However, they believe that the broader impacts they have referred to
might be employed to add weight to the Landscape & Visual Impact Assessment of
the proposal. Should the Council determine to object on these or on other grounds
they would be pleased to advise further as required. Similarly, if a potential
archaeological condition or conditions are required for submission to the ECU or at
a later stage, they will be pleased to suggest a suitable form of words. 
Applicant Response to WOSAS (16th September 2025) – They are pleased there
is no objection recommended on cultural heritage grounds, and that there is no
specific issue with the predicted cultural heritage impacts. There is a comment that
there may be too much focus of the assessment on individual heritage assets. This
may be how the assessment is set out, however any relevant relationships to other
monuments / relevant historic landscapes, as far as it is possible to identify these,
would have been addressed as part of that. The comments are referring to a broader,
and more subjective appreciation of the historic environment. As this remains quite
vague, they are not sure there is much they can offer by way of a detailed response;
other than to emphasise that they have considered wider landscape relationships as
part of the setting impact assessment. If there is a specific monument or group of
monuments that they have not suitably assessed, they would be happy to respond
accordingly – noting there is a large range of heritage assets/archaeological sites
which span a large period. 
West of Scotland Archaeology Service – a copy of the Applicant’s response was
sent to WOSAS. At time of writing no further response has been received. 
Local Biodiversity Officer (23rd September 2024) – provides advice on the Kintyre
Goose Roosts SPA and its associated SSSI, Habitats Regulations assessment,
Biodiversity Enhancement Management Plan (BEMP), Habitat Losses and Impact,
peatland, European Protected Species, Species Protection Plan, Protected Species,
ecological clerk of works, ornithology. The Local Biodiveristy Officer recommends
that the applicant should include an appropriate plan for mitigation against potential
deer impact on newly planted trees until such a time that they are established and
no longer vulnerable to over-browsing and while the impact to bats is unlikely to be
significant, it would be advisable to monitor any fatalities that may occur from
collision as they are found to forage within the wind turbine areas. 
Noise Consultant (3rd March 2025) – advise that good practice has been adopted
by the applicant, with a few minor issues identified. The most significant of these
issues are: 
• The study area for Killean wind farm includes receptors that are exposed to noise
levels from the operational Deucheran wind farm and consented Clachaig Glen
Page 25

Page 26

wind farm. It has been shown that the application of apportioned noise limits will
be necessary to ensure cumulative noise impacts do not exceed the derived
noise limits at some receptors. It is recommended that the Applicant considers
this and suggests suitable values. 
• The omission of the details of any screening attenuation and concave ground
corrections that have been applied. The inclusion of the applied values in the
reporting is suggested within good practice but is not a formal requirement,
however, it has potentially led to an inability to accurate replicate the applicant’s
calculations. 
• The receptor labelled H27 ‘South Beachmore Farm’ is incorrectly named ‘High
Crubasdale’ in Tables 11.7, 11.8, 11.9 and 11.10. 
• Confirmation there are no derelict properties with residential planning status in
the study area. 
• The proposed noise condition does not contain the partial levels. Nor include a
suitable control for amplitude modulation. 
Following a satisfactory response there would be no reason to object on noise
grounds.  A suitably worded condition to limit the noise levels, tonality and amplitude
modulation should be applied to control noise levels from the proposal.  A revision
based on the proposed condition should be provided. 
Applicant response to Noise Consultant (1st October 2025) – have considered
the Council’s Noise Consultants review and note that some minor points have been
raised. They will be pleased to agree a wording for a revised noise condition which
will include updated limits that more thoroughly account for potential cumulative
operational impacts and that include controls for amplitude modulation (AM). This
will provide further comfort that the requirements of ETSU-R-97 will be met in
practice. They consider that this can be addressed during the agreement of
conditions process. Additionally, they acknowledge the error highlighted relating to
receptor location coordinates and will be happy to correct this. Finally, they confirm
that from their understanding, the previous consent for the reinstatement of a
residential dwelling at Braids has lapsed and there are no derelict properties with
residential planning status in the study area. 
Noise Consultant (1st October 2025) – have reviewed the clarifications provided
by the applicant and would respond as follows: 
• They agree that the apportioned limits can be agreed with the conditions (if
consent is granted)
• They note that no further information on screening or valley correction has been
provided – it will be the applicant’s responsibility to ensure the agreed noise limits
can be met. They are unable to verify this in the absence of this information.
• Confirmation of typos is fine.
• Confirmation that there are no derelict properties is fine.
• Confirmation that the applicant will accept an AM condition is also fine. 
On that basis, they conclude that satisfactory clarifications have been provided or
can be dealt with at the conditions stage of the application, and their previous
conclusions regarding the acceptability of the scheme still stand. 
Page 26

Page 27

ABC Roads and Amenity Services (5th September 2024) – no objection. The site
access connects directly to the A83 Tarbet - Campbeltown Trunk Road, Transport
Scotland should be notified. 
Flood Risk Assessor (7th November 2024) – no objection subject to conditions to
ensure watercourse crossings are designed so there is no reduction in pre-
development channel cross sectional area ideally to pass the 1 in 200 year plus
climate change flood event; and, surface water drainage is designed in accordance
with CIRIA C753 and ensures that post development runoff is attenuated to the 1 in
2 year greenfield runoff rate. The surface water drainage should be in operation prior
to the start of construction. 
Access Officer (8th July 2025) – no objection subject to a condition requiring the
developer to prepare an Access Plan for approval by the Council prior to the
commencement of construction. 
Please note: the above are summaries and the full consultee responses can
be viewed on the Energy Consent Unit and Argyll & Bute Council websites. 
(D) HISTORY:   
16/03400/S36 – S36 consultation for proposed Killean Wind Farm, Killean Wind
Farm, Tayinloan – Objection submitted to ECU 18th October 2017. 
16/01313/PP - Erection of 14 wind turbines (13 with a blade tip height of up to 126.5m
(and hub height of up to 80m) and one with a blade tip height of up to 115.5m (and
hub height of up to 69m)), upgrading of permanent access, formation of site access
tracks, erection of permanent anemometer mast, control building and substation,
watercourse crossings and temporary construction compound, Clachaig Glen wind
farm, Land North East of Muasdale – Refused 21st September 2017. 
Both the above wind farms were considered at a conjoined Public Inquiry which
commenced on the 9th of January 2019 the outcome of which is detailed below: 
WIN-130-3 Killean – Scottish Ministers refused the application on the 18th of
December 2019 
PPA-130-2064 (Planning Permission Appeal) Clachaig Glen – Scottish Ministers
allowed the appeal and granted planning permission on the 18th of December 2019. 
22/00613/S36 – S36 Consultation regarding the proposed Clachaig Glen wind farm
and battery storage located approximately 20km north of Campbeltown and 1.8km
north-east of Muasdale on the west coast of the Kintyre – Objection submitted to the
ECU on the 19th of January 2023. 
WIN-130-7 Clachaig Glen – Following objection from the Planning Authority, a Public
Inquiry was held on various dates between August and December 2023, the
outcome of which was that Scottish Ministers granted Section 36 consent on the 8th
of November 2024. 
(E)       PUBLICITY:   
As the Council is not the Determining Authority the ECU oversees the Publicity of
the application. 
Page 27

Page 28

Public Consultation – Whilst not a statutory requirement for Section 36
applications, the applicant has undertaken Public Consultation. Further information
on this is contained in the Killean wind farm Pre-Application Consultation (PAC)
Report, July 2024 available on the ECU website (reference: ECU00004927). 
(F) REPRESENTATIONS:   
As the Council is not the determining Authority any letters of representation are
considered by the ECU. At time of writing, the ECU are in receipt of 21 objections
and one general comment. The objections are from residents within the local area.
The main concerns raised relate to: 
• Public Inquiry – objectors would like to be kept informed and included.
• Historic Environment, Archaeology, and Listed Buildings (including the Dolls
Houses)
• Biodiversity - birds (including eagles), badgers, bats, otters, red squirrels, pine
martens, and Greenland White fronted geese. 
• Scale of development
• landscape and visual impact 
• Impact of aviation lighting on dark skies
• Misleading photomontages of VP’s
• Noise and Acoustic Environment, health, amplitude modulation, infrasound 
• Private water supplies
• Transportation – impact on roads, businesses, and homes 
• Amenity impacts on the property ‘Braids’ from turbines T14 and T17 
• Impact on the local economy and tourism 
• Walking routes and the Kintyre Way
• Previous refusal on this site for smaller wind farm
• Duration of consent – increase from 25 – 50 years
• Aviation/Navigation Safety
• Compensation/money/community benefit
• Maintenance and disposal of used turbines 
• Scotland does not need to produce any more energy
• Health & wellbeing 
• Impact on house at Kilmory 1968m
• Impact on peat
• Flooding
• Cumulative Impact - High level of applications in Kintyre
• Planning Policy LDP & NPF4 
Note: The comments raised above are addressed in the assessment of the
proposal at Appendix A of this report. 
Note: Please note that the representations above have been summarised, and
the full letters of representation are available on the ECU website. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
Page 28

Page 29

(i) Environmental Impact Assessment Report (EIAR): Yes 
EIAR presented in 4 volumes:   
• Volume 1: Written Statement
• Volume 2a: Figures (excluding LVIA)
• Volume 2b: LVIA Figures and Visualisations
• Volume 3: Technical Appendices
• Volume 4: Non-Technical Summary 
Key topics covered in the EIAR include: 
• Introduction 
• Chapter 2. Proposed Development Description 
• Chapter 3. Design Evolution and Alternatives 
• Chapter 4. Approach to EIA/Climate Change, Legislative and Policy
Context Chapter 5. Landscape and Visual Impact Assessment 
• Chapter 6. Cultural Heritage Assessment 
• Chapter 7. Ecology 
• Chapter 8. Ornithology 
• Chapter 9. Geology, Hydrology and Hydrogeological Assessment 
• Chapter 10. Traffic and Transport 
• Chapter 11. Noise 
• Chapter 12. Aviation, Radar, and Defence 
• Chapter 13. Other Issues (Socioeconomics, Telecommunications,
Infrastructure, Shadow Flicker, Carbon Balance). 
• Chapter 14. Schedule of Mitigation 
• Chapter 15. Summary of Residual and Cumulative Effects 
In addition, the following documents are also provided in support of the
application: 
• Planning Statement 
• Design Statement 
• Pre-Application Consultation Report 
(ii)  An Appropriate Assessment under the Conservation (Natural Habitats)
Regulations 1994:   NatureScot will advise the ECU  
(iii)  A Design or Design/Access statement:   Yes  
(iv)  Sustainability Checklists (with reference to the requirements of LDP2
Policy 04): Not required proposal accompanied by full EIAR.  
(v)  A report on the impact of the proposal e.g. Retail impact, transport
impact, noise impact, flood risk, drainage impact etc:  All relevant
reports are encompassed within the EIAR 
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:  No
Page 29

Page 30

(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  No  
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been considered in the
assessment of the application 
(i) List of all Development Plan Policy considerations considered in assessment
of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 5 – Soils
NPF4 Policy 6 – Forestry, Woodland, and Trees
NPF4 Policy 7 – Historic Assets and Places
NPF4 Policy 11 – Energy
NPF4 Policy 22 – Flood Risk and Water Management
NPF4 Policy 33 – Minerals 
Annex B – National Statements of Need 
3. Strategic Renewable Electricity Generation and Transmission Infrastructure 
Argyll & Bute Local Development Plan 2 (LDP2) (Adopted 2024) 
Policy 02 – Outwith Settlement Areas
Policy 04 – Sustainable Development
Policy 15 – Protection, Conservation and Enhancement of Our Historic Environment
Policy 16 – Listed Buildings 
Policy 19 – Scheduled Monuments
Policy 20 – Gardens and Designed Landscapes
Policy 21 – Sites of Archaeological Importance
Policy 30 – The Sustainable Growth of Renewables
Policy 31 – Minerals 
Policy 35 – Design of New and Existing, Public Roads and Private Access Regimes
Policy 43 – Safeguarding of Aerodromes
Policy 55 – Flooding
Policy 56 – Land Erosion
Policy 57 – Risk Appraisals
Policy 58 – Private Water Supplies and Water Conservation
Policy 59 – Water Quality and the Environment
Policy 60 – Private Sewage Treatment Plants and Wastewater Drainage Systems
Policy 61 – Sustainable Drainage Systems (SuDS)
Policy 62 – Drainage Impact Assessments
Policy 63 – Waste Related Development and Waste Management
Policy 70 – Development Impact on National Scenic Areas (NSA’s)
Policy 71 – Development Impact on Local Landscape Areas (LLA’s)
Policy 73 – Development Impact on Habitats, Species and Biodiversity
Policy 74 – Development Impact on Sites of International Importance
Page 30

Page 31

Policy 75 - Development Impact on Sites of Special Scientific Interest (SSSIs)
Policy 76 - Development Impact on Local Nature Conservation Sites (LNCS)
Policy 77 – Forestry, Woodland, and Trees
Policy 78 – Woodland Removal
Policy 79 – Protection of Soil and Peat Resources
Policy 80 - Geodiversity 
(ii) List of all other relevant planning considerations considered in the
assessment of the application, having due regard to Annex A of Circular
3/2013 
• Scottish Energy Strategy (2017)
• Onshore Wind Policy Statement (2022)
• Draft Energy Strategy and Just Transition Plan (2023)
• Good Practice Principles for Shared Ownership of Renewable Energy
Developments, Scottish Government, 2019
• Onshore Wind Turbines: Planning Advice, Scottish Government (May 2014)
• The Argyll & Bute Landscape Wind Energy Capacity Study, 2017 (LWECS)
• ABC Technical Note – Biodiversity (Feb 2017)
• Landscape Institute and Institute of Environmental Management and
Assessment – Guidelines for Landscape and Visual Impact Assessment, Third
Edition (2013)
• Scottish Natural Heritage – Visual Representation of Wind Farms Guidance
(Version 2.2, 2017)
• Scottish Natural Heritage - Siting and Designing Wind Farms in the Landscape
Guidance (Version 3a, 2017)
• Historic Environment Policy for Scotland (2019)
• Scottish Government, Draft Planning Guidance: Biodiversity, 2023
• The Climate Change (Emissions Reduction Targets) (Scotland) Act 2024 
• Managing Change in the Historic Environment 
• PAN 1/2011: ‘Planning and Noise’ (March 2011)
• Scottish Government’s Policy on ‘Control of Woodland Removal’ (Forestry
Commission Scotland 2009) 
• UK Forestry Standard (UKFS)
• PAN 60 – Planning for Natural Heritage (Jan 2008)
• Views of statutory and other consultees
• Planning history of the site
• Legitimate public concern or support expressed on relevant planning matters 
(G) Is the proposal a Schedule 2 Development not requiring an EIAR: No, an EIAR
was required. 
(H) Has the application been the subject of statutory pre-application consultation
(PAC):  No - PAC is not required for S36 applications. 
(I) Does the Council have an interest in the site: No 
(J) Requirement for a pre-determination hearing: No
(K) Is the proposal consistent with the Development Plan: No – due to unresolved
objection from National Air Traffic Services 
Page 31

Page 32

(L) Need for notification to Scottish Ministers or Historic Environment Scotland:
No 
Author of Report: Arlene Knox                       Date: 3rd October 2025 
Reviewing Officer: Sandra Davies                 Date: 6th October 2025 
Fergus Murray
Head of Development & Economic Growth 
Page 32

Page 33

APPENDIX A – RELATIVE TO APPLICATION NUMBER: 24/01541/S36   
COMMITTEE REPORT   
PLANNING LAND USE AND POLICY ASSESSMENT   
1. THE SECTION 36 CONSENTING REGIME  
1.1 Any application for an onshore power generating station with an installed capacity
of over 50 megawatts (MW) requires the consent of Scottish Ministers under
Section 36 of the Electricity Act 1989. Any authorisation given includes a deemed
planning permission. Consequently, there is no need for a planning application to
be made to the Council. The Council’s role in this process is one of a consultee.  
1.2 The Development Plan is not the starting point for considering S36 applications.
The reason for this is that sections of the Planning Act which establish the primacy
of Development Plan Policy in decision making are not engaged. NPF4 and LDP2
form the Development Plan. Whilst they do not have primacy in S36 decision
making, they remain an important consideration to inform the Council’s
consultation response.  
1.3 Schedule 9 of the Electricity Act requires the applicant and the decision maker to
have regard to the preservation of amenity. It requires that in the formulation of
proposals the developer shall have regard to: 
(a) the desirability of preserving natural beauty, of conserving flora, fauna and
geological or physiological features of special interest and of protecting sites,
buildings, and objects of architectural, historical, or archaeological interest; and 
(b) shall do what he reasonably can to mitigate any effect which the proposals
would have on the natural beauty of the countryside or on any such flora, fauna,
features, sites, buildings, or objects.  
1.4 It obliges the Scottish Ministers as decision maker to have regard to the
desirability of the matters at (a) and the extent to which the applicant has complied
with the duty at (b).  
1.5 Assessment of the proposal against the policies of NPF4 and LDP2 will ensure
that proper consideration is given by the Council to the extent that the proposal
satisfies these Schedule 9 duties.  
1.6 The Council can either support or object and recommend conditions to be
imposed if consent is granted by Scottish Ministers.  If an objection is raised by
the Council, Scottish Ministers are obliged to hold a Public Local Inquiry (PLI) if
they are minded to grant consent. They can also choose to hold a PLI in other
circumstances at their own discretion. Any Inquiry would be conducted by a
Reporter appointed by the Directorate for Planning and Environmental Appeals.
If consent is granted the Council as Planning Authority is responsible for the
agreement of matters pursuant to conditions, ongoing monitoring, and
enforcement.  
Page 33

Page 34

1.7 This report considers the relevant policy considerations, planning merits, views of
consultees and representations. It recommends views to be conveyed to the ECU
for consideration before a decision is made.  
2. BACKGROUND 
2.1 An extension was requested from the ECU in May to enable objections to be
resolved from NatureScot, RSPB Scotland, and National Air Traffic Services and
a consultation response to be received from the West of Scotland Archaeology
Service. This request was refused, and a holding objection was submitted which
requested that the ECU postpone making a decision on the application until the
outstanding matters had been resolved and the Council provides a further
response. Apart from the outstanding NATS objection all matters have been
resolved, and it is intended that this report and its recommendations will provide
the Council’s final consultation response to the ECU.  
3. SPATIAL AND SETTLEMENT STRATEGY  
2.1 Policy 02 – Outwith Settlement Areas establishes acceptable scales of
development in three different zones. The wind farm site is located within Remote
Countryside, which only supports specific categories of development. This
includes renewable energy related development. In principle, Policy 02 supports
renewable energy and ancillary development in these areas, providing they are
consistent with all other relevant LDP2 Policies. With respect to the requirement
for developments to accord with all other relevant policies, particular attention is
drawn to Policies 70 to 76 with respect to landscape and the natural environment.
Proposals must also demonstrate that there will be no unacceptable adverse
effects (individual or cumulative) on natural heritage, built and/or cultural heritage,
and landscape and visual amenity. 
2.2 Policy 71 – Development Impact on Local Landscape Areas (LLA)  - requires that
proposals in or affecting a LLA must demonstrate that: a) any significant adverse
effects on the landscape quality for which the area has been designated are
clearly outweighed by social, economic or environmental benefits of community
wide importance; b) The proposal is supported by a landscape and visual impact
assessment and has taken account of the content of any relevant Argyll & Bute
Landscape Capacity Assessment; and c) The location, scale, design, materials
and landscaping would be of a high standard and would safeguard or enhance
the special qualities and character of the Local Landscape Area.  Part of the
existing access and proposed temporary turning area to be located across from it
on the other side of the road would be in the West Kintyre (Coast) LLA. Given the
temporary nature of this it is acceptable subject to condition to secure submission
of the exact details and specification of the temporary turning area and
reinstatement proposals (including landscaping) for agreement with the planning
authority prior to commencement of works. A condition is also recommended to
ensure that the turning area is temporary, and use is restricted.  
2.3 Policy 04 – Sustainable Development requires that in preparing new proposals
developers should demonstrate the following sustainable development principles
(where relevant) such as: maximise the opportunity for local community benefit;
support existing communities and maximise the use of existing infrastructure and
services; conserve and enhance the natural and built environment and avoid
significant adverse impacts on biodiversity, natural and heritage assets; respect
Page 34

Page 35

the landscape character of an area and the setting and character of settlements;
avoid places with significant risk of flooding, or ground instability and avoid having
significant adverse impacts on land, air and water environment.  This application
is supported by an EIAR which sets out in detail the measures proposed to ensure
the proposal is ‘Sustainable Development.’  
2.4 Policy 11 – Energy of NPF4 and Policy 30 – Sustainable Growth of Renewables
LDP2 provide the primary policy framework for assessing renewable energy
proposals. In this case, due to the outstanding objection from National Air Traffic
Services the proposal is contrary to development plan policy relating to the spatial
and settlement strategy which requires proposals to be consistent with all relevant
policies.  
2.5 Having due regard to the above, this proposal is contrary to the provisions
of LDP 2 Policy 02 – Outwith Settlement Areas and LDP Policy 04 –
Sustainable Development.  
3. ENERGY & SUPPORTING THE SUSTAINABLE GROWTH OF RENEWABLES  
3.1 Argyll & Bute Council is keen to ensure that Argyll & Bute continues to make a
positive contribution to meeting the Scottish Government’s targets for renewable
energy generation. These targets are important given the compelling need to
reduce our carbon footprint and reduce our reliance on fossil fuels, reinforced by
the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019. The
Council will support renewable energy developments where these are consistent
with the principles of sustainable development, and it can be adequately
demonstrated that there would be no unacceptable significant adverse effects.  
3.2 This proposal has been assessed primarily against the two lead Statutory
Development Plan policies relating to renewable energy, Policy 11 – Energy of
NPF4 and Policy 30 – the Sustainable Growth of Renewables of LDP2. Other
policies are referred to where relevant.  
4. LOCATION, NATURE, AND DESIGN OF PROPOSAL  
4.1 The proposal is located off the A83, at approx. 2.5km east of Tayinloan, on the
Kintyre Peninsula. The site extends to approx. 1,052 ha and comprises upland
plateau moorland and conifer forest, locally known as the Killean Estate.  
4.2 Within the site are several small lochs, from north to south these include Loch
Dirigadale, Loch a' Ghlinn Bhig, Loch Luireach, Loch Fionn-Ghleann and Loch na
Naich. Several watercourses also run through the site - primarily the tributaries of
Allt Chaltuinn to the north and Killean Burn to the west. Killean Burn passes
through the west of the site and flows westwards into the Sound of Gigha. 
4.3 The A83 passes northwards, approx. 1km to the west of the western boundary of
the site.    
4.4 Proposed Development – the main components are: 
• Up to 9 wind turbines, each with a maximum tip height of 180m
Page 35

Page 36

• At each wind turbine, associated low to medium voltage transformers and
related switchgear
• Permanent wind turbine foundations
• Hardstanding areas for crane erection at each wind turbine
• Two new watercourse crossings and 14 existing crossings which may need
to be upgraded
• Approx. 10.5km of access tracks, comprising 5.58km of new tracks and
4.92km of existing tracks to be upgraded
• Upgraded site access from the existing junction with the A83
• Temporary turning area to facilitate access on opposite side of road to site
access
• Onsite underground electrical cables and cable trenches
• Substation compound
• A temporary construction compound for office welfare and materials storage
• Up to 6 borrow pit search areas
• The potential for onsite concrete batching, the location of which would be
confirmed prior to commencement of development once need is confirmed
• Felling of 41.3ha hectares of forestry and associated compensatory planting.
• Habitat management and biodiversity improvements as set out in Outline
Biodiversity Enhancement Management Plan (OBEMP)  
4.5 It is anticipated that construction would take approx. 15 months, depending upon
seasonal working and weather conditions. The proposal is expected to operate
for up to 50 years following which decommissioning of the wind turbines and other
infrastructure would be undertaken. 
Infrastructure  
4.6 Connection to Electricity Grid – The proposal would be connected at Carradale
Substation, located approx. 11.2km southeast of the site. The connection would
be comprised of buried 132kV cables and/or Overhead lines (OHL). The exact
arrangement of this grid connection is subject to detailed design by SSEN
Transmission, the Transmission Operator (TO). Any final grid connection route
and associated consents would be the responsibility of the TO and this route
would require further studies and would be subject to a separate consenting
process.  
4.7 Scottish Water – have advised the ECU that they have no objection. Advice is
provided on Drinking Water Protected Areas, and Surface Water.  
4.8 Drinking Water Protected Areas – they have confirmed there are no Scottish
Water drinking water catchments or water abstraction sources, which are
designated as Drinking Water Protected Areas under the Water Framework
Directive, in the area that may be affected by the proposal.  
4.9 Surface Water – for reasons of sustainability and to protect customers from
potential future sewer flooding, Scottish Water have advised that they will not
accept any surface water connections into their combined sewer system.  
4.10 Private Water supplies (PWS) – SEPA have not provided any advice on private
water supplies.  
Page 36

Page 37

5. NET ECONOMIC IMPACT, INCLUDING LOCAL AND COMMUNITY SOCIO-
ECONOMIC BENEFITS  
5.1 Policy 11 – Energy of NPF4 states that proposals will only be supported where
they maximise net economic impact, including local and community socio-
economic benefits such as employment, associated business, and supply chain
opportunities. Policy 30 – the Sustainable Growth of Renewables of LDP 2
requires all applications for wind turbine developments to be assessed in terms
of net economic impact, including local and community socio-economic benefits
such as employment, associated business, and supply chain opportunities.  
5.2 Socio-Economic Impact - The proposal would deliver some economic benefits
during its construction and operation. It is estimated that during construction, the
proposal could generate £5.9 million Gross Value Added (GVA) and 80 jobs in
Argyll & Bute and £18.1 million GVA and 260 jobs in Scotland. During the
operational phase, annually the proposal could generate £0.3 million GVA and 3
jobs in Argyll & Bute; and £1.1 million GVA and 12 jobs across Scotland.  
5.3 The Applicant has stated that through local partnerships they will support
communities to develop skills sought after within the onshore wind sector, to
secure jobs and optimise the opportunities associated with the proposal. They
have also committed to prioritise local companies in the provision of contracts
during construction and operation.  
5.4 The proposal will contribute to public finances through the payment of non-
domestic rates, which could amount to £0.7 million annually, or £35.6 million over
a 50-year operational lifetime. This will support the funding of local public services
in the context of challenging public sector finances.  
5.5 To support local ambitions and needs, it has become customary practice to offer
community benefit funding, with Scottish Government guidance suggesting
£5,000 per annum per installed MW. This level of funding would generate around
£0.3 million every year for the local economy, equivalent to £14.9 million over the
lifetime of the wind farm and could support up to 5 jobs locally.  
5.6 The local area also could take part in the Applicant’s Local Electricity Discount
Scheme, reducing the household energy bills in the community, as well as shared
ownership options.  
5.7 The latest position from the Applicant is they now have internal approval to
formally offer a revenue share to the community. It is anticipated that the
Information Memorandum will be ready for presentation to the community groups
around the date of committee. They expect to be able to offer the Community an
opportunity to purchase up to 5% of the project post construction.  
5.8 The economic benefits associated with this proposal relating to job creation and
benefits to the local economy from the influx of construction workers, by spending
on accommodation, eating out and visiting local attractions are a relevant
consideration, which has been considered. Community Benefit is not however, a
‘material planning consideration’ in the determination of planning applications, as
there is no planning mechanism available to secure it. If consent were to be
granted, the negotiation of any community benefit either directly with the local
Page 37

Page 38

community or under the auspices of the Council, would take place outside the
application process.  
5.9 Having due regard to the above it is considered a degree of net economic
impact including local and community socio-economic benefits typical of
such developments will be provided. It is therefore concluded that the
proposal is consistent with the provisions of Policy 11 – Energy of NPF4
and Policy 30 – The Sustainable Growth of Renewable of LDP2 in this
regard.  
6. IMPACTS ON COMMUNITIES AND INDIVIDUAL DWELLINGS, INCLUDING
RESIDENTIAL AMENITY, VISUAL IMPACT, NOISE AND SHADOW FLICKER  
6.1 Policy 11 – Energy of NPF4 requires that project design and mitigation will
demonstrate how impacts on communities and individual dwellings, including
residential amenity, visual impact, noise, and shadow flicker have been
addressed. Policy 30 – the Sustainable Growth of Renewables of LDP2 requires
all applications for renewable developments to be assessed in terms of impacts
on communities and individual dwellings, including visual impact, residential
amenity noise, and shadow flicker (including cumulative).   
Noise  
6.2 ABC Noise Consultant – has advised that good practice has been adopted by the
applicant, with a few minor issues identified. The most significant of these issues
are: 
• The study area for Killean wind farm includes receptors that are exposed to
noise levels from the operational Deucheran wind farm and consented
Clachaig Glen wind farm. It has been shown that the application of
apportioned noise limits will be necessary to ensure cumulative noise impacts
do not exceed the derived noise limits at some receptors. It is recommended
that the Applicant considers this and suggests suitable values. 
• The omission of the details of any screening attenuation and concave ground
corrections that have been applied. The inclusion of the applied values in the
reporting is suggested within good practice but is not a formal requirement,
however, it has potentially led to an inability to accurate replicate the
applicant’s calculations. 
• The receptor labelled H27 ‘South Beachmore Farm’ is incorrectly named ‘High
Crubasdale’ in Tables 11.7, 11.8, 11.9 and 11.10. 
• Confirmation that there are no derelict properties with residential planning
status in the study area. 
• The proposed noise condition does not contain the partial levels. Nor include
a suitable control for amplitude modulation. 
6.3 Following a satisfactory response, it is considered that there would be no reasons
to object on noise grounds.  A suitably worded condition to limit the noise levels,
tonality and amplitude modulation should be applied to control noise levels from
Page 38

Page 39

the proposed development.  A revision based on the proposed condition should
be provided.  
6.4 Applicant’s response to Noise Consultant – they have considered the Noise
Consultants review and note that some minor points have been raised. They will
be pleased to agree wording for a revised noise condition which will include
updated limits that more thoroughly account for potential cumulative operational
impacts and that include controls for amplitude modulation (AM). This will provide
further comfort that the overall requirements of ETSU-R-97 will be met in practice.
They consider that this can be addressed during the agreement of conditions
process. Additionally, they acknowledge the error highlighted in the Councils
Noise Consultants review relating to receptor location coordinates and will be
happy to correct this. Finally, they confirm that from their understanding, the
previous consent for the reinstatement of a residential dwelling at Braids has now
lapsed and there are no derelict properties with residential planning status in the
study area.  
6.5 ABC Noise Consultant - have reviewed the clarifications provided by the applicant
and would respond as follows. They agree that the apportioned limits can be
agreed with the conditions (if consent is granted). They note that no further
information on screening or valley correction has been provided – it will be the
applicant’s responsibility to ensure the agreed noise limits can be met. They are
unable to verify this in the absence of this information. Confirmation of typos is
fine. Confirmation that there are no derelict properties is fine. Confirmation that
the applicant will accept an AM condition is also fine. On that basis, they would
conclude that satisfactory clarifications have either been provided or can be dealt
with at the conditions stage of the application, and therefore their previous
conclusions regarding the acceptability of the scheme still stand. 
Shadow Flicker  
6.6 A shadow flicker assessment is required when any properties lie within 10 rotor
diameters of a wind farm. This is in line with Scottish Government online
renewables planning advice on ‘onshore wind turbines’ which states that: “where
separation is provided between wind turbines and nearby dwellings (as a rule 10
rotor diameters), ‘shadow flicker’ should not be a problem.”  
6.7 Analysis was performed on all properties within ten rotor diameters of any turbine.
This shadow flicker assessment is based on turbines with a 155m rotor diameter,
and a 100m micro-siting allowance for infrastructure. As such, this 100m distance
is added to the ten-rotor diameter (1,550 = 10 * 155) m distance to give a total
distance of (1,650 = 1550 + 100) m from any turbine. Analysis was undertaken
for shadow flicker at all properties within 1,650m from any wind turbine.  
6.8 With an allowance for 100m micro-siting, there are no inhabited houses within
1,650m of any wind turbine and thus no flicker is predicted. A property referred to
as Braids is scoped out of the assessment as it is uninhabited and would require
planning permission to make habitable. The building currently lacks a roof,
windows, and some walls, and is therefore not considered to be a building used
for long-term residential purposes. It is therefore concluded that Killean Wind
Farm will not cause a material reduction to residential amenity owing to shadow
flicker. 
Page 39

Page 40

6.9 Having due regard to the above, subject to the conditions recommended by
the Councils Noise Consultant being attached to any grant of consent it is
considered that the proposal is consistent with the provisions of Policy 11-
Energy, and Policy 30 – The Sustainable Growth of Renewables of the LDP2
in this respect.  
7. SIGNIFICANT LANDSCAPE AND VISUAL IMPACTS  
7.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how significant landscape and visual impacts have been addressed,
recognising that such impacts are to be expected for some forms of renewable
energy. Where impacts are localised and/or appropriate design mitigation has
been applied, they will generally be considered acceptable. Policy 4 a) - Natural
Places of NPF4 states that proposals which by virtue of type, location or scale will
have an unacceptable impact on the natural environment will not be supported.
Policy 30 – The Sustainable Growth of Renewables of LDP2 requires all
applications for wind turbine developments are assessed against landscape and
visual impacts.  
7.2 The Council’s Consultant Landscape Architect - has undertaken a review of the
landscape and visual effects of the proposal.  
7.3 The proposal - A previous application for a wind farm on a similar site was refused
following a Public Local Inquiry held in 2019. This original application comprised
a development of 15 turbines, 149.9m high to blade tip and extended more to the
east than the current proposal with around 6 turbines being located on open
moorland. The current application comprises 9 turbines up to 180m high to blade
tip. Most of the turbines are located within a conifer plantation with 3 turbines lying
in more open ground close to the woodland edge.  
7.4 A Design Statement has been produced which outlines opportunities, constraints
and decision-making influencing the design. This document notes the previous
application for a wind farm on this site and its refusal in 2019. It outlines the
changes that have occurred to Scottish planning policy since then with the
adoption of NPF4. It states that there is recognition that the reasons for refusal of
this previous scheme are important but that it is not possible to remove all
landscape and visual impacts given the increase in turbine height and it is
acknowledged that ‘in many instances the visual effects that would arise would
be of a similar nature’. One of the key aims has been to avoid a notable increase
in visual impact when compared with the previous scheme and the document
seems to express the view that the reduction in the number of turbines from 15 to
9 would be key to achieving this. 
7.5 The Landscape and Visual Impact Assessment (LVIA) - accords with the
Guidelines for Landscape and Visual Impact Assessment 3rd Edition (GLVIA3).
The visualisations are clear and consistent with best practice guidance although
the maps showing viewpoint locations are too small to read.  
7.6 The Council’s Consultant Landscape Architect considers that the LVIA generally
under-estimates landscape and visual effects. They have reviewed the findings
from the original Killean LVIA and note some key differences with the judgements
made in the LVIA for the current scheme. The LVIA for the original scheme
concluded that significant effects would occur on a larger number of Landscape
Page 40

Page 41

Character Types (LCTs) and on views from the Islay Ferry and Knapdale whereas
the current LVIA does not. The current proposal has a smaller number of turbines
although these are over 30m higher than the turbines proposed in the original
scheme. The extent of visibility of the proposal (despite the reduction in the
number of turbines) is similar to that of the original scheme.  
7.7 The Argyll & Bute Landscape Wind Energy Capacity Study 2017 - The proposal
lies within the Upland Forest Moor Mosaic (6) Landscape Character Type (LCT).
The Argyll & Bute Landscape Wind Energy Capacity Study (ABLWES) finds the
combined landscape and visual sensitivity of this landscape to be high-medium
to wind turbines >80m high.  
7.8 The study identifies major constraints as potential cumulative effects with other
wind farms. It notes that while no designated landscapes apply to this LCT, it
abuts a coastal APQ in places and turbines visible on prominent skylines above
the coastal fringe may indirectly affect special qualities. Key cumulative issues
are highlighted in the study and these include: ‘Larger turbines and/or more
extensive wind farm developments sited on the outer edges of the Kintyre uplands
where they would be likely to significantly increase landscape and visual impacts
on the settled coastal edge of Kintyre and on views from Arran and Gigha and
would also further erode the established pattern of wind farm developments
largely associated with the less sensitive core of these uplands’.  
7.9 The guidance set out for the Upland Forest Moor Mosaic LCT advises that there
is very limited scope for additional large typology turbines to be accommodated
within this landscape principally due to potential cumulative effects that could
occur on the coastal fringes of Kintyre and on views from Arran and Gigha. The
guidance advises that significant intrusion on adjacent settled and small-scale
landscape character types and on Arran and Gigha should be avoided by siting
larger turbines well back into the interior of these uplands.    
7.10 Effects on landscape character - The LVIA finds that significant effects would arise
on the character of the Upland Forest Moor Mosaic LCT within which the
proposed wind farm would be sited. The Council’s Consultant Landscape
Architect agrees with this finding and with the judgement that these effects would
extend up to around 6km or so from the wind farm. The LVIA concludes that there
would be no significant effects on any other LCT within the LVIA study area.  
7.11 Contrary to the findings of the LVIA, the Council’s Consultant Landscape Architect
considers that the wind farm would incur significant adverse effects on the Coastal
Plain LCT which forms a triangular and flat area of farmland, woodland and moor
extending west to Rhunahaorine Point. This is a small LCT, and effects would be
widespread. The Council’s Consultant Landscape Architect also disagrees with
the judgement made in the LVIA regarding effects on the character of the Coastal
Parallel Ridges LCT which covers the whole of the island of Gigha. Gigha lies less
than 3km from the west coast of the Kintyre peninsula at its closest point across
the narrow Sound of Gigha. The very large turbines would be prominent in views
from Gigha and from the Sound of Gigha and the Council’s Consultant Landscape
Architect considers that significant adverse effects would occur on the sense of
remoteness and naturalness associated with the island and the immediate waters
surrounding it. It should be noted that the recent consent of the Clachaig Glen II
wind farm will diminish the current perceptual qualities associated with Gigha and
its immediate seascape if constructed. 
Page 41

Page 42

7.12 There would also be some localised adverse effects on the Rocky Mosaic LCT
where the proposal would be seen principally in the vicinity of Glenacardoch Point
and where the creation of the access off the A83 would involve the removal of
vegetation and road widening near Killean. Sections of hedgerow are proposed
to be removed near the site access. Some removal of trees near the site access
also formed part of the previous proposal considered at PLI but this does not
appear to be mentioned in the EIAR. While the Council’s Consultant Landscape
Architect considers that there will be some significant adverse effects on parts of
the Rocky Mosaic LCT, they will be limited in extent and effects on this LCT would
not be widespread. 
7.13 Effects on designated landscapes - The proposal is not located in a designated
landscape but would lie within 1.7km of the West Kintyre Coast Local Landscape
Area (LLA). There is no citation for this, but it principally comprises settled and
more intricately patterned coastal fringes with key special qualities likely to
comprise a diverse landform and landcover pattern and views along the coast and
out to sea to the west to Gigha, Islay and Jura. The LVIA concludes that the
proposal would not have significant effects on this LLA. It is considered that there
would be significant adverse effects on some of the key qualities of this LLA but
that overall, the integrity of the designation would not be compromised given the
limited visibility of the proposal particularly from the more diverse parts of the
coast and lack of intrusion in westward views.        
7.14 Visual effects - The location of the proposal on west-facing outer slopes of the
Kintyre peninsula would increase visibility from the sea, coast, and Gigha. It is
considered that significant adverse effects on views would principally occur from
the following locations:   
• The Kintyre Way where the proposal would be seen at close quarters as the
route is aligned through the site. VP’s 1 and 2 illustrate the close views that
would occur from this nationally important route. While the proposal would be
seen from the Kintyre Way where it is aligned along the coast in the vicinity of
Rhunahaorine Point, effects would be particularly severe along approx. 7km
of the route east of Tayinloan. The proposal would be likely to introduce new
visibility of a large-scale wind energy development along approximately 5km
of the route but would be seen together with the consented Clachaig Glen II
wind farm principally between the eastern edge of the site and Loch na Naich
for around 2km distance (The cumulative ZTV Figure 5.36 indicates
theoretical visibility of the Clachaig Glen II within Killean Glen and across the
Killean wind farm site but from field observations it is considered that
woodland (including non-productive woodland aligning the Killean burn) and
local landform features would be likely to screen views so that the Killean wind
farm would only be seen from this part of the Kintyre Way). Both
developments would be likely to result in an overwhelming effect for walkers
who would be surrounded by very large wind turbines.   
• The Sound of Gigha and Gigha - The proposal would be visible across much
of Gigha and the Sound of Gigha. There will be fairly consistent visibility of the
proposal from the single-track road which runs the length of Gigha, from
settlement which is principally located on the more sheltered eastern side of
the island and from walking routes along the coast and on the hills on the
higher spine of the island. These views are illustrated by VP’s 6 and 8. The
recently consented Clachaig Glen II wind farm would have a similar visual
influence in views from the Sound of Gigha and Gigha. Both wind farms would
Page 42

Page 43

appear to lie near each other and would increase the extent of visibility of wind
turbines seen on the skyline of the Kintyre uplands   
• The west Kintyre coast - there would be extensive visibility of the proposal
from the open Coastal Plain (VP 3 from Tayinloan jetty, VP 4 Point Sands).
There would also be visibility in the vicinity of Glenacardoch Point. (The A83
is tucked into the base of rising and often wooded slopes and the raised beach
edge south of Clachan and views of the proposal would be limited from this
route as it traverses the western coast of Kintyre). The recently consented
Clachaig Glen II wind farm will be seen in close association with this proposal
and would increase the extent of large wind turbines seen on the skyline of
hills to the east from the coast.   
• Knapdale - There would be visibility of the proposal from the southern part of
the Knapdale peninsula with this likely to be restricted to more open coastal
locations due to the extensive woodland present. More distant operational
wind farms located in the central part of the Kintyre peninsula are already
clearly seen in the view but are not prominent due to the size of turbines, their
partial screening by landform and their distance. Viewpoint 11 from the B8204
illustrates how the turbines will appear overly large in relation to the height of
the northern uplands of the Kintyre peninsula increasing the impact on views.
It should be noted that the recently consented Clachaig Glen II wind farm
would appear to overlap with this proposal from this part of Knapdale. If built,
this consented scheme would lessen the effects of the proposal from this
location.   
• The Islay Ferry - Similar to the account of views from Knapdale above, the
Council’s Landscape Architect considers that while alone the proposal would
incur significant adverse effects due to its size and prominent position on east-
facing slopes as the ferry approaches West Loch Tarbet, should the
consented Clachaig Glen be built, these effects would be reduced where both
schemes appear to overlap.  
7.15 The LVIA concludes that significant night-time effects would arise from three
viewpoints (two of these along the Kintyre Way at Killean and Loch na Naich VPs
1 and 2). The Council’s Landscape Architect considers that night-time lighting
would additionally extend the duration of significant effects from the Sound of
Gigha and from Gigha (the night-time visualisation from VP6 at Ardminish is
useful but it cannot compare with the brightness of wind turbine lighting seen in
the field).  
7.16 Residential Visual Amenity Assessment - The Residential Visual Amenity
Assessment (RVAA) identifies 12 residential properties lying within 2km of the
proposal. One of these properties (Braids which lies very close to the wind farm)
is uninhabited and 8 properties (lying in the vicinity of Largie Farm on lower
wooded slopes) have no theoretical visibility of the proposal due to the screening
provided by landform and trees. The RVAA found that effects on the remaining 3
properties would not be significant. Although the Councils Landscape Architect
has not been able to visit each of the properties considered in the RVAA, based
on the visual material produced in the LVIA, they consider the findings to be
reasonable. 
Page 43

Page 44

7.17 Cumulative landscape and visual effects with other proposed wind farms - This
proposal has greatest potential to incur significant adverse cumulative effects with
the consented Clachaig Glen II wind farm which lies within 1km to the south.
Significant adverse combined cumulative effects would occur on landscape
character and on views from the Kintyre Way, the Sound of Gigha and Gigha. The
Killean proposal will increase the horizontal extent of turbines seen on the upland
skyline but, in a scenario where the Clachaig Glen II proposal is constructed, it
would not introduce new larger wind turbines to views. 
7.18 Conclusions - A key aim of the design has been to avoid a notable increase in
visual impact when compared with the previous Killean scheme which was
refused in 2019. The location of the previous scheme on open west-facing slopes
opposite Gigha and the size of the turbines were key factors influencing significant
landscape and visual effects and the reasons for refusal. While this proposal has
fewer turbines, they are larger. There have been some improvements to the siting
of turbines but only as far as turbines have been removed from sensitive open
moorland to minimise effects on Golden Eagles. The site still comprises west-
facing slopes lying on the outer edges of the Kintyre peninsula which are more
open to views from the Kintyre coast and Gigha and its immediate seascape. The
Councils Landscape Architect considers that some of the objectives identified in
the Design Statement, for example the aim to offset the distance between turbines
and the Kintyre Way, would achieve no meaningful mitigation in terms of reducing
the prominence of very large wind turbines seen near this route. 
7.19 The previous Clachaig Glen wind farm proposal was preferred at the conjoined
inquiry held with Killean in 2019 principally because of its reduced landscape and
visual effects. This was due in part to its more visually contained siting and smaller
turbines (115-126m high to blade tip). The Clachaig Glen II proposal (comprising
larger turbines than the original consented scheme) was recently consented on
appeal in November 2024. The reporter considered that while this wind farm
would have significant effects on landscape character extending 3km from the
development, it would not harm the West Kintyre LLA, would not dominate the
settled small scale Rocky Mosaic LCT or affect or detract from the character of
the coast. In terms of the effects on views, the Reporter concluded that significant
effects would occur on Gigha and the Sound of Gigha, the Kintyre Way, and Point
Sands but it would not intrude on views from the west. The Councils Landscape
Architect considers that the Clachaig Glen II significantly increases the intrusion
on Gigha and the Sound of Gigha when compared with the original Clachaig Glen
scheme which comprised smaller turbines and additionally benefitted from some
screening by landform. 
7.20 Changes have occurred to national planning policy since the 2019 Conjoined
Killean and Clachaig Glen Wind Farms PLI. NPF4 Policy 11e ii states that
significant landscape and visual impacts are to be expected for some forms of
renewable energy and where impacts are localised and/or appropriate design
mitigation has been applied, they will be acceptable. NPF4 provides no guidance
on the definition of what constitutes ‘localised’ effects. 
7.21 The proposal would have significant adverse effects on landscape and coastal
character and on the character of the island of Gigha. Significant adverse effects
on views will principally occur from Gigha Sound, from the settled eastern coast
and small spine of hills on Gigha, the Kintyre Way and the Rhunahaorine
Point/Point Sands area. Visible aviation lighting of 4 turbines will increase the
duration of adverse effects on views. 
Page 44

Page 45

7.22 Cumulative landscape and visual effects would principally arise between the
consented Clachaig Glen II wind farm and this proposal. As there is a strong
likelihood that the consented Clachaig Glen II scheme will be constructed, it is
important that the Killean proposal is not considered in isolation. In many key
views, for example from Point Sands (VP4) and from Gigha (VPs 6 and 8), the
Killean proposal will appear as an extension to Clachaig Glen II, exacerbating
significant adverse effects, for example, in terms of increasing the extent of
turbines seen on skylines looking east but not being the first to introduce new
much larger and more prominent wind turbines to the scene. Put simply, the
consent of Clachaig Glen II will already incur significant adverse effects on key
views from Gigha, Gigha Sound and part of the west Kintyre coast and this will
reduce landscape and visual sensitivity and the magnitude of change likely to
occur should the 9 turbines of the Killean proposal be added in a similar location.
This is confirmed by the cumulative wirelines produced in the EIAR for VPs 4, 6
and 8. In views from the A83 both wind farms will generally be seen together with
the presence of Clachaig Glen II, in VP 9 near Clachan for example, likely to result
in the effects of the Killean proposal being not significant if subsequently
constructed. A similar reduction in the sole effect of Killean would occur from VP
11 in Knapdale if Clachaig Glen II were present. 
7.23 Recommendation in terms of landscape and visual matters - The proposal would
have similar significant adverse landscape and visual effects to the previous
proposal which was refused in 2019. Changes to national planning policy and the
consent of the Clachaig Glen II wind farm have a bearing on the decision to be
made on the acceptability of this proposal in terms of its landscape and visual
effects. While the Councils Landscape Architect considers that the effects of this
proposal on its own could be termed more than local in extent because of the
significant effects on landscape/coastal character and on views from Gigha and
the Sound of Gigha that would arise (lying up to 9km distance), the likely
construction of the Clachaig Glen II wind farm would moderate these effects. The
Councils Landscape Architect therefore recommends that no objection should
be raised in respect of landscape and visual interests subject to the following
conditions being imposed:   
Visible aviation lighting - The Applicant’s proposal for a condition to allow for
implementation of an Aircraft Detection Lighting System (outlined in the Schedule
of Mitigation) Chapter 14 of the EIAS is welcomed. While the Clachaig Glen II
reporter’s findings on conditions requiring periodic review of aviation lighting are
acknowledged the Councils Consultant Landscape Architect considers that the
large number of wind farm proposals across Argyll & Bute requiring aviation
lighting is a major concern and such a condition is imperative to reduce the
cumulative landscape and visual effects of such lighting   
Woodland and wider landscape mitigation and enhancement – the Councils
Landscape Architect considers that the Applicant should adopt a more ambitious
approach to forest restructuring using the wind farm development as a catalyst
for more effective and speedier restructuring of productive forestry which would
enhance both landscape character and biodiversity and fit with the aims of NPF4
Policy 3. Wider landscape enhancement should also be undertaken as should
measures to ensure the longevity of screening woodland. A condition should be
set up to require the applicant to undertake: 
Page 45

Page 46

• Substantial increases in broadleaved planting as part of the wind farm
restocking plan (the increases above the agreed forest plan which are
currently proposed are relatively small) including riparian planting across the
wider Killean estate (both new woodlands and management and expansion
of existing riparian woodlands, for example those within the valley of the
Killean Burn). 
• Redesign of the outer margins of productive woodland (this tying in where
appropriate with measures set out in the BEMP to enhance Black Grouse
habitat) to remedy hard angular edges and improve the fit of plantations with
landform. 
• Compensatory planting should be undertaken within the Killean Estate. Argyll
& Bute Council should be consulted, in addition to Scottish Forestry, on the
location, extent and composition of this planting. 
• Management of existing mature mixed woodlands in the vicinity of Killean
House including new planting to retain and enhance screening of the
proposed wind farm from the coast and protect the landscape setting provided
to the Killean Estate buildings and St John’s Church (as seen in Cultural
Heritage Figure 6.4)  
7.24 Key visualisations for the Committee to review include: VP1: Loch na Naich –
Kintyre Way, VP2: Killean – Kintyre Way, VP3: Tayinloan Jetty, VP4: Point Sands,
VP6: Ardminish Bay, Gigha, VP8: Creag Bhan, Gigha, VP9: A83 near Clachan
(Sheet A illustrates how the proposal would be seen together with Clachaig Glen
2), and Figure 6.4: Killean Estate Buildings  
7.25 NatureScot – in summary, have advised the ECU while there are significant
adverse landscape and visual effects, these do not raise issues of national
interest. Furthermore, they defer to Argyll & Bute Council and North Ayrshire
Council in terms of effects on locally designated landscapes. NatureScot advise
that the nature and scale of the proposal at this location is such, that it cannot be
accommodated without significant adverse landscape and visual effects,
including cumulative effects and night-time effects. They consider that given the
proposed siting, scale, and type of development, it would be very challenging to
overcome the significant adverse effects identified within the site parameters.
They would encourage the Applicant to reconsider the design, particularly where
the proposal would have significant adverse effects on parts of the west coast of
Kintyre, the Isle of Gigha, and the Sound of Gigha. This is likely to require a
reduction in the vertical height of the turbines which may reduce some of the
severity of effects. 
7.26 North Ayrshire Council - advised the ECU that consideration should be given to
the potential impacts of the North Arran NSA when determining the application. 
Officer’s Conclusion  
7.27 Based on the advice of the Council’s Landscape Architect, NatureScot, and North
Ayrshire Council it is concluded that the proposal does not warrant an objection
on landscape and visual grounds. This is however subject to the conditions
recommended by the Councils Landscape Architect being attached if the proposal
receives consent.  
Page 46

Page 47

7.28 Having due regard to the above subject to the conditions recommended by
the Councils Landscape Architect being attached to any grant of consent it
is concluded that the proposal complies with the provisions of Policies 11
– Energy and 4 – Natural Places of NPF4, and Policy 30 – The Sustainable
Growth of Renewables of LDP2 in this respect.  
8. IMPACTS ON TOURISM AND RECREATION    
8.1 Policy 11 – Energy of NPF4 does not require impacts on tourism to be considered.
Policy 30 – The Sustainable Growth of Renewables of LDP2 requires all
applications for wind turbine developments to be assessed against impacts on
tourism and recreation.  
8.2 Tourism – Policy 11 of NPF4 does not include a requirement for the impact of
proposals on tourism to be assessed. However, Policy 30 – The Sustainable
Growth of Renewables of the LDP does. In Argyll & Bute the landscape is
regarded as being a particularly valued asset both in terms of its intrinsic qualities
and in terms of its value to the tourism economy. For all types of development,
the maintenance of landscape character is an important facet of decision-making
in the countryside in Argyll & Bute, regardless of the scale of development
proposed.  
8.3 As Tourism and Landscape & Visual matters are intrinsically linked, and there is
little evidence to demonstrate whether wind farms adversely affect tourism, it is
considered that such impacts are covered in the landscape and visual impact
assessment of the proposal. 
8.4 Having due regard to the above it is considered that the proposal is
consistent with the provisions of Policy 11 – Energy of NPF4 and Policies
04 – Sustainable Development and 30 – The Sustainable Growth of
Renewables of ABLDP2 in this respect.  
9. PUBLIC ACCESS    
9.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how impacts on public access are addressed, including impact on
long distance walking, and cycling routes and scenic routes. Policy 30 – the
Sustainable Growth of Renewables of LDP2 requires all applications for wind
turbine developments to be assessed against impacts on public access, including
impact on long distance walking and cycling routes and those scenic routes
identified in NPF4. Policy 32 – Active Travel of LDP2 requires active travel and
recreation to be integrated in developments from the start of the wider design
process and existing active travel networks should be safeguarded and integrated
with the development. 
9.2 The Council’s Access Officer has advised that the 9 wind turbines will be visible
for over 5 miles of the Kintyre Way which is the most heavily used path in the area
affected by the proposal being popular with walkers, cyclists, and horse
riders.     The height of the turbines is understood to be 180m and this is
inevitable.  This is the latest of around 16 wind farms in operation or under
construction in the Kintyre area.   The Access Officer does not know whether this
concentration of wind farms has had a positive or negative effect on tourism in
the area.   The 9 turbines will be close to the Kintyre Way; however, this will not
Page 47

Page 48

be the only location where this is the case.  This is not unique to the Kintyre Way
with many long-distance paths in Scotland and the rest of the world passing close
to wind farms.    
9.3 The Access Officer is concerned that the developer has not produced an Access
Plan which details how they will manage public access during the construction
phase, especially the upgrading of the main access road which is a designated
Core Path C094(b) and follows the route of the Kintyre Way.  The developer and
their contractors are required to keep the Core Path open throughout the works
and will need to manage the construction to allow this.   Elsewhere contractors
have been able to upgrade forestry tracks without closing them to the public
although this has required additional planning and the employment of banksmen
etc.   Whilst it is permissible to divert sections of the route on to adjacent routes
this will require a Section 208 Path Diversion Order for which the developer should
allow at least 8 weeks for consultation.  This is only possible for one part of the
affected section of the Core Path and some improvements to the alternate route
via Braids may be required before it can be used, as will the permission of the
landowner.  
9.4 In summary the Access Officer does not have any objection to the proposed wind
farm.  The Applicant will need to consider how they manage the construction
phase of the project to ensure that the public can continue to exercise their legal
rights of access, and the Access Officer is happy to discuss this with them at that
stage.  A condition requiring the developer to prepare an Access Plan for approval
by the Council prior to the commencement of construction will ensure that this
happens.  The Access Officer is also happy to meet the developer and the
contractor to advise on the draft Access Plan prior to its submission. 
9.5 Having due regard to the above subject, to the condition to secure an
Access Plan being attached to any grant of consent it is considered that the
proposal is consistent with the provisions of Policy 11- Energy of NPF4,
Policy 30 – the Sustainable Growth of Renewables; and Policy 32 - Active
Travel of the LDP2.  
10. AVIATION AND DEFENCE INTERESTS INCLUDING SEISMOLOGICAL
RECORDING   
10.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how impacts on aviation and defence interests including
seismological recording have been addressed. Policy 30 – the Sustainable
Growth of Renewables of LDP2 requires impacts on aviation and defence
interests and seismological recording to be addressed. Policy 43 – Safeguarding
of Aerodromes of LDP2 stipulates that development will not be permitted where it
would compromise the safe operation of an Aerodrome or Technical Site or
constrain their present or future operations.  
10.2 Defence Infrastructure Organisation (DIO) – advised the ECU that, subject to the
conditions to secure Aviation Lighting and Aviation Charting and Safety
Management, they have no objection.  
10.3 Highlands & Islands Airport initially submitted a holding objection and advised the
ECU they required an updated Instrument Flight Procedure impact assessment
report. An updated Instrument Flight Procedure impact assessment was
Page 48

Page 49

submitted which confirmed the proposal will have no impact on the IFPs serving
Campbeltown Airport. Therefore, HIAL removed the holding objection and
confirmed they have no objections.  
10.4 National Air Traffic Services Safeguarding (NATS) has advised the ECU the
proposal conflicts with their safeguarding criteria. Accordingly, they object. They
further advised the ECU that it is always their preference to identify a specific
mitigation and, if possible, put in place a delivery framework before actively
offering a conditional withdrawal of their objection. However, they have confirmed
that they have an identified mitigation that with the commitment of both parties
can be delivered prior to the development commencing.  
10.5 Glasgow Prestwick Airport and Glasgow Airport have advised the ECU they have
no objection.  
10.6 Having due regard to the unresolved NATS objection it is concluded the
proposal is contrary to the provisions of Policy 11 – Energy of NPF4 and
Policies 30 – The Sustainable Growth of Renewables and 43 – Safeguarding
of Aerodromes, of the LDP2.   
Note: If NATS withdraw their objection, and the ECU is minded to grant
consent for this proposal.  Any conditions recommended by NATS to secure
any necessary mitigation and the conditions recommended by the Ministry
of Defence should be attached.  
11. TELECOMMUNICATIONS AND BROADCASTING INSTALLATIONS  
11.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how impacts on telecommunications and broadcasting installations,
have been addressed particularly, ensuring that transmission links are not
compromised. Policy 30 – The Sustainable Growth of Renewables of LDP2
requires all applications for wind turbine developments to be assessed against
impacts on telecommunications and broadcasting installations, particularly
ensuring that transmission links are not compromised. 
11.2  BT advised the ECU that the proposal should not cause interference to their
current and presently planned radio network. Arqiva advised the ECU they have
no objection and recommend a planning condition to mitigate the impact of any
degradation of television and radio reception caused by the wind turbines. Joint
Radio Company - advised the ECU the proposal is CLEARED - subject to 100m
Micrositing (as stated in the EIAR) - with respect to radio link infrastructure
operated by the local energy networks.  
11.3 Having due regard to the above subject to the condition recommended by
Arqiva and the Joint Radio Company it is concluded that the proposal will
not have any adverse impacts on telecommunications, broadcasting
installations and transmission links (including cumulative impacts) and is
consistent with the provisions of Policy 11- Energy of NPF4 and Policy 30 –
The Sustainable Growth of Renewables of LDP2 in this respect.    
12. ROAD TRAFFIC AND ADJACENT TRUNK ROADS    
Page 49

Page 50

12.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how impacts on road traffic and on adjacent trunk roads have been
addressed, including during construction. Policy 30 – the Sustainable Growth of
Renewables of LDP2 requires all applications for wind turbine developments to
be assessed against impacts on road traffic and impacts on adjacent trunk roads.
Policy 35 – Design of New and Existing, Public Roads and Private Access
Regimes of LDP2 acceptance of development utilising new and existing public
roads, private roads and private access regimes is subject to road safety and
street design issues being addressed to the satisfaction of the Roads Authority
and the Planning Authority. Policy 38 – Construction Standards for Public Roads
requires that accesses which connect to or impact significantly on a Trunk Road
require consultation with Transport Scotland.  
12.2 Transport Scotland (TS) have advised the ECU the nearest trunk road to the site
is the A83(T) which would provide access into the development via a private
access track. A turning area on the west side of the A83(T) opposite the site
access is required to assist with the right turn manoeuvre required to enter the
site. Based on the review undertaken, Transport Scotland can confirm that they
are satisfied with the submitted EIAR and have no objection to the development
in terms of environmental impacts on the trunk road network. They would,
however, request that the following conditions be attached to any consent that
may be granted: details of the proposed means of access to be submitted for
approval, the proposed route for any abnormal loads to be submitted for approval,
details of any accommodation measures to be approved and implemented, any
additional signing or temporary traffic measures must be undertaken by a
recognised QA traffic management consultant prior to the movement of any
components, Construction Traffic Management Plan (CTMP) to be submitted and
approved, and wheel washing facilities to prevent vehicles depositing debris on
the trunk road. Transport Scotland advise that in addition to the conditions the
Applicant should be informed of their advisory notes which set out the
requirements for works within the trunk road boundary.  
12.3 ABC Roads and Amenity Services - have advised they have no objection. The
site access connects directly to the A83 Tarbet - Campbeltown Trunk Road,
Transport Scotland should be notified.  
12.4 Having due regard to the above, subject to the conditions recommended by
Transport Scotland it is considered that the proposal is consistent with the
provisions of Policy 11 – Energy of NPF4, Policy 30 – The Sustainable
Growth of Renewables, Policy 35 – Design of New and Existing, Public
Roads and Private Access Regimes and Policy 38 – Construction Standards
for Public Roads in this regard.  It is recommended that the conditions
required by Area Roads and Amenity Services are attached to any consent
granted by the ECU. 
13. HISTORIC ENVIRONMENT    
13.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how impacts on the historic environment have been addressed.
Policy 7 – Historic Assets and Places of NPF4 intent is to protect and enhance
historic environment assets and places, and to enable positive change as a
catalyst for the regeneration of places. Policy 30 – The Sustainable Growth of
Renewables of LDP2 requires all applications for wind turbine developments to
be assessed against impacts on the historic environment, including scheduled
Page 50

Page 51

monuments, listed buildings and their settings. Policy 15 – Protection,
Conservation and Enhancement of Our Historic Environment, Policy 19 –
Scheduled Monuments, Policy 20 – Gardens and Designed Landscapes, and
Policy 21 – Sites of Archaeological Importance support the key policies and
provide guidance on assessing development proposals against heritage impacts. 
13.2 Historic Environment Scotland (HES) – have advised the Energy Consents Unit
that their view is that the proposals do not raise historic environment issues of
national significance, and they do not object. 
13.3 Historic Scotland advise that there are 4 Category A listed buildings immediately
adjacent to the application site boundary with the potential to be affected by the
construction of access tracks for the proposal. These are the ‘Doll’s Houses,’
Killean. The following additional Category A listed buildings may also be affected
by the proposal: Killean House (LB12005) and Killean Chapel (St John’s), Killean
Burial Ground (LB12004). There are also several nearby scheduled monuments
which may be affected. These include the following: Killean, fort NE of (SM3179),
Beacharr, standing stone & long cairn (SM182), Dun Beachaire, dun (SM3143),
and Low Clachaig, cup marked boulder 915m E of (4352).  
13.4 Whilst the proposal would be visible in key views associated with the settings of
several heritage assets, HES are content that the severity of impacts is such that
the turbines would not result in significant adverse impacts to the level where they
would object.  
13.5 They have also considered the impact of the proposed bellmouth and site access
on the setting of St John's Church, church, burial ground, and carved stones,
Killean (SM3030). This monument consists of the remains of the old parish church
of Killean and its burial ground. A simple, unicameral church was erected here
probably in the second half of the 12th century, it was altered several times of the
following centuries before being abandoned in 1770. The setting of the monument
is focused on the sense of place. Its location on the flat coastal plain meant it was
visible from much of the surrounding area. There is little modern development
west of the road which adds to a sense of separation and means that its place in
views up and down the coastline remains uncompromised.  
13.6 A bellmouth is proposed just to the north of the monument, to the west of the A83,
to facilitate the transport of turbine components approaching from Campbeltown
and turning right up the access track to the proposed wind farm. The ground will
be reinstated upon completion of turbine delivery. Whilst components are likely to
be visible from St John's and the tranquillity and isolation of the church’s setting
compromised when in use, the bellmouth will be temporary and then removed
upon completion of turbine delivery. Provided this can be ensured HES do not
object to these impacts.  
13.7 HES have also previously advised that if any trees forming the woodland
backdrop to the Killean Estate are damaged or removed by works to upgrade the
wind farm access tracks, they should be appropriately replaced.  It is
recommended that these concerns should be addressed by condition if the
proposal received consent.  
13.8 West of Scotland Archaeology Service – does not recommend an objection and
provides general comments and advice on direct and indirect physical impact
Page 51

Page 52

issues and setting and cumulative impact issues. In terms of cumulative impact
WOSAS find they cannot support the proposed encroachment onto lower ground
that is more densely populated with known archaeological sites and monuments.
WOSAS does not believe that an objection solely based on predicted adverse
impacts on the historic environment would be likely to be sustained. However,
they believe that the broader impacts they have referred to might be employed to
add weight to the Landscape & Visual Impact Assessment of the proposal. Should
the Council determine to object on these or on other grounds they would be
pleased to advise further as required. Similarly, if a potential archaeological
condition or conditions are required for submission to the ECU or at a later stage,
they will be pleased to suggest a suitable form of words.  
13.9 Applicant Response to WOSAS (16th September 2025) – note that there is no
objection recommended on cultural heritage grounds, and that there is no specific
issue with the predicted cultural heritage impacts. There is a comment that there
may be too much focus of the assessment on individual heritage assets. This may
be how the assessment is set out, however any relevant relationships to ther
monuments/relevant historic landscapes, as far as it is possible to identify these,
would have been addressed as part of that. The comments are referring to a
broader, and perhaps more subjective appreciation of the historic environment.
As this remains quite vague, they are not sure there is much that can be offered
by way of a detailed response; other than to emphasise that wider landscape
relationships have been considered as part of the setting impact assessment. If
there is a specific monument or group of monuments that in the view of WOSAS
has not been suitably assessed the Applicant would be happy to respond
accordingly – noting that there is a large range of heritage assets/archaeological
sites which span a large period.  
13.10 West of Scotland Archaeology Service – were sent a copy of the Applicants
response to ascertain whether they had any further comments.  At time of writing
no further response has been received. 
13.11 Having due regard to the above subject to the conditions to address the
concerns of Historic Scotland (tree protection/planting and timeous
reinstatement of the temporary bellmouth) and any  conditions
recommended by  the West of Scotland Archaeology Service following
further consultation it is considered that the proposal is consistent with the
provisions of Policy 11 – Energy and Policy 7 – Historic Assets and Places
of NPF4, and Policies 30 – The Sustainable Growth of Renewables; 15 –
Protection, Conservation and Enhancement of Our Historic Environment;
19 – Scheduled Monuments; 20 – Gardens and Designed Landscapes; and
21 – Sites of Archaeological Importance of the LDP2  
14. HYDROLOGY, THE WATER ENVIRONMENT AND FLOOD RISK  
14.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how effects on hydrology, the water environment and flood risk have
been addressed. Policy 30 – Supporting the Sustainable Growth of Renewables
of LDP2 requires all applications for wind turbine developments to be assessed
against impacts arising from effects on hydrology, the water environment and
flood risk (including cumulative). Policy 55 - Flooding of LDP2 provides guidance
on the type of development that will be permissible within specific flood risk areas.
Policy 57 – Risk Appraisals requires flood risk assessments, and drainage impact
assessments, to accompany applications where required.
Page 52

Page 53

14.2 The Council’s Flood Prevention Officer – has advised that they have no objection
subject to conditions to ensure that watercourse crossings are designed so there
is no reduction in pre-development channel cross sectional area ideally to pass
the 1 in 200 years plus climate change flood event; and, surface water drainage
is designed in accordance with CIRIA C753 and ensures that post development
runoff is attenuated to the 1 in 2 year greenfield runoff rate. The surface water
drainage should be in operation prior to the start of construction.    
14.3 Having due regard to the above, subject to the conditions recommended by
the Flood Prevention Officer it is concluded that the proposal is consistent
with the provisions of Policy 11 – Energy of NPF 4, Policy 30 – The
Sustainable Growth of Renewables, Policy 55 – Flooding; and Policy 57 Risk
Appraisals of LDP2.    
15. BIODIVERSITY    
15.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how impacts on biodiversity, including birds have been addressed.
Policy 1 – Tackling the climate and nature crises of NPF4 requires that when
considering all proposals significant weight will be given to the global climate and
nature crises. Policy 3 – Biodiversity of NPF4 requires proposals to protect
biodiversity, reverse biodiversity loss, deliver positive effects from development
and strengthen nature networks. Policy 5 – Soils of NPF4 supports the generation
of energy from renewable sources that optimises the contribution of the area to
GHG emissions reduction targets on peatland, carbon-rich soils, and priority
peatland. A detailed site-specific assessment will be required for development on
peatland which will include the net effects of the development on climate
emissions and loss of carbon. Policy 30 – The Sustainable Growth of Renewables
of LDP2 requires all applications for wind turbine developments to be assessed
against impacts arising from effects on the natural heritage, including birds and to
be assessed against impacts on carbon rich soils, using the carbon calculator
(including cumulative). Policy  73 – Development Impact on Habitats,
Species and Biodiversity requires proposals to incorporate, safeguard and
enhance existing site biodiversity wherever possible. 
15.2 NatureScot initially advised the ECU the proposal could affect internationally
important natural heritage interests, and they objected until further information
regarding the Kintyre Goose Roosts Special Protection Area was provided. This
would enable them to carry out an appraisal of these effects and help the ECU
determine the proposal. NatureScot also noted the presence of Leisler’s bats
within the footprint of the proposal and advised they would provide further advice
on this is due course.  
15.3 NatureScot provided advice to the ECU on bats at the site. 
Bats - The bat activity surveys indicate that there is at least a moderate level of
bat activity within the survey area with Nyctalus, Myotis and Pipistrellus species
being recorded. Of note is the occurrence of Leisler’s bat (Nyctalus leisleri), which
is considered a rare and high-risk species in Scotland. Kintyre is not currently
acknowledged to be within the Leisler’s bat established range; however, the bat
activity survey provides evidence of a wider distribution of this species in Scotland
than is currently known.
Page 53

Page 54

15.4 Bat Mitigation - As the Applicant is proposing to keyhole turbines into the existing
forestry, this can increase the risk of bat fatalities due to the increase in forest
edge habitat close to the turbines and associated infrastructure. We would advise
that feathering is routinely applied to the turbine blades below cut-in speed during
operation. This measure can help reduce the risk of bat casualties by 50%. If
feathering is implemented, we would ask that monitoring is carried out for three
years post-construction to assess changes in bat activity. We note that the
Applicant was unable to have bat data analysed through EcoBat as it was
unavailable at the time. We believe it is now operational and would advise that
the Applicant has the data analysed, if possible, to provide an independent
assessment on the level of bat activity at the site.  
15.5 NatureScot have provided the ECU with a response to the additional information
provided by the Applicant, which they requested in their initial response. In
summary, they advise that there are natural heritage interests of international
importance on the site, but their advice is that these will not be adversely affected
by the proposal. They refer to their previous advice in relation to landscape and
visual impacts and ecological impacts.  
15.6 Kintyre Goose Roosts Special Protection Area - The Proposal is located approx.
540 m to the south-west of Loch an Fhraoich, a component loch of the Kintyre
Goose Roosts Special Protection Area (SPA), Ramsar Site, and the Kintyre
Goose Lochs Site of Special Scientific Interest (SSSI). Rhunahaorine Point SSSI
(also part of the Kintyre Goose Roosts SPA) is located approx. 1.7 km to the
north-west of the proposal. These sites are all designated for overwintering
populations of Greenland white-fronted geese (GWFG). 
15.7 The site’s status means that the requirements of the Conservation (Natural
Habitats, &c.) Regulations 1994 as amended (the ‘Habitats Regulations’) apply
or, for reserved matters, The Conservation of Habitats and Species Regulations
2017. Consequently, ECU is required to consider the effect of the proposal on the
SPA before it can be consented (commonly known as Habitats Regulations
Appraisal). 
15.8 NatureScot’s advice is that this proposal is likely to have a significant effect on
the GWFG feature of the SPA. Consequently, ECU, as competent authority, is
required to carry out an appropriate assessment in view of the site’s conservation
objectives for its qualifying interest. They advise that based on the information
provided, their conclusion is that the proposal will not adversely affect the integrity
of the site. 
15.9 RSPB Scotland – initially advised the ECU that they shared NatureScot's concern
regarding the assessment of collision risk for Greenland White-fronted Geese.
They would be pleased to provide further comment on this element once the
information requested by NS has been provided. Having considered the revised
collision risk model for Greenland White-fronted Goose they have advise the ECU
they have no further comments and do not object.  
15.10 Outline Biodiversity Enhancement and Management Plan (oBEMP) - RSPB
Scotland considers the oBEMP to be appropriate and welcomes the outline
proposals therein.  
Page 54

Page 55

15.11 Compensatory Planting - It is noted that infrastructure felling of 33.4 ha and
management felling of 7.9 ha will be required should the proposal be consented,
but it is presently unclear where the required Compensatory Planting (CP) is
proposed to be delivered. RSPB Scotland recommends that wherever possible in
an Argyll context, CP is delivered as low-density native shrub and broadleaf
woodland, and that planting on good quality open ground habitats is avoided.  
15.12 SEPA (Scottish Environment Protection Agency) have advised the ECU that a
planning condition in relation to Borrow Pit restoration should be attached to any
consent if granted. If this will not be applied, then SEPA object. 
15.13 Peat Management Plan - SEPA note the proposal to use a depth of 2m peat as
restoration of the borrow pits. As most of the borrow pits appear to lie on shallower
peat it is unlikely restoration of peat, tying into existing water tables will be
successful. SEPA also note the applicant proposes to use this infill of acrotelm
and catotelm peat as 'substrate for afforestation' on top of restored borrow pits.
Any form of tree planting on top of peat is likely to result in its desiccation; loss of
its carbon storing potential and cause it to no longer be peat. SEPA are of the
opinion this would therefore be viewed as peat and would require a waste
management license.  
15.14 SEPA therefore request a condition is attached to any consent for the submission
of detailed finalised plans for borrow pit management and restoration prior to
commencement of construction on site. In the meantime, they recommend the
applicant explores further re-uses of the excavated peat. SEPA recommend the
submission of a Finalised Peat management Plan is also conditioned.  
15.15 Groundwater Dependent Terrestrial Ecosystems (GWDTE) - SEPA have
reviewed Technical Appendix 7.1 and the Outline Biodiversity Action Plan and
confirm they have no detailed comments to make on these aspects of the
proposal. However, they recommend the applicant explores the possibility of the
use of peat, even if in small volumes, in conjunction with the proposed drain
blocking to improve existing bog habitat.   
Peat Landslide Hazard Risk Assessment    
15.16 Ironside Farrar, Peat Landslide Hazard Risk Assessment (PLHRA), Stage 1
Checking Report advised the ECU that no further response is required. The
PLHRA is satisfactory. The checking report has determined that the PLHRA is
sufficiently robust in all respects, although some recommendations may be made
for clarity, no further revisions are required.  
15.17 The Council’s Local Biodiversity Officer (LBO) – has provided the following advice
and recommendations. 
15.18 The Kintyre Goose Roosts SPA/Ramsar/SSSI – lies 540m north of the site
boundary and 2.2km from the closest wind turbine. Its Qualifying Feature is -
wintering population of Greenland white-fronted goose (Anser albifrons). The
Local Biodiversity Officer notes NatureScot’s response of the 28th of October 2023
where they: ‘Advise that the proposal is likely to have a significant effect on the
qualifying interests of the Kintyre Goose Roosts SPA and its associated SSSI, so
a Habitats Regulations assessment will be required. Effects on the geese could
include collision mortality, barrier effects, disturbance during construction and
Page 55

Page 56

operation, and cumulative effects. The applicant has included a Habitats
Regulation Appraisal Report with an overall conclusion ‘the Proposed
Development would have no adverse effect on the integrity of the Kintyre Goose
Roosts SPA.’ The Local Biodiversity Officer agrees with the findings in this report
and the mitigation measures of no construction work for the access site taking
place to the west of the A83 during October to March to prevent disturbance
during feeding. The Local Biodiversity Officer welcomes the objectives within the
Biodiversity Enhancement Management Plan (BEMP) to include a long-term
enhanced monitoring programme and GPS-tagging to obtain more data. 
15.19 Predicted Habitat Losses and Impacts – has advised that none of the predicted
habitat losses (acid flush, blanket bog, wet modified bog, wet heath, marshy
grassland, and hedgerow) are likely to have a significant impact and there would
be no effects on other habitats of conservation value. The Local Biodiversity
Officer welcomes the habitat and peatland enhancement objectives within the
BEMP and the continued monitoring of habitat and peatland restoration
throughout the lifetime of the wind farm. They advise that the applicant should
include an appropriate plan for mitigation against potential deer impact on
newly planted trees until such a time that they are established and no longer
vulnerable to over-browsing.  
15.20 Peatland - One wind turbine will be located on blanket bog but on peat less than
1m depth. Design of the proposal has changed to avoid areas of deep peat as
much as possible and reduce habitat loss of blanket bog. Floating access tracks
will be adopted where the levels of peat exceed 1m in depth. The Local
Biodiversity Officer welcomes the objectives within the BEMP for peatland
enhancement and monitoring throughout the lifetime of the wind farm.   
Summary of European Protected Species  
15.21 Bats – Seven species of bats were identified in the surveys. The surveys did not
identify any area of high bat activity that would require buffering in the wind farm
design. No loss of potential bat roosts. No significant impact to bats with a low-
risk site for collision with wind turbines. The Local Biodiversity Officer welcomes
the avoidance of bat preferred habitat features with a minimum 50m buffer
maintained between wind turbine blade tips and the nearest woodland edge. The
Local Biodiversity Officer makes the following recommendation: While the
impact to bats is unlikely to be significant, it would be advisable to monitor
any fatalities that may occur from collision as they are found to forage
within the wind turbine areas.  
15.22 Otter – Evidence of otter was recorded along many of the watercourses and along
several of the waterbodies within the site. The Local Biodiversity Officer welcomes
the inclusion of a Species Protection Pan (SPP) to include pre-construction
surveys undertaken within one month of the commencement of works, to inform
the need for any mitigation measures to ensure significant effects on the species
are avoided. 
Summary of Protected Species    
15.23 Badger - No records found within the potential impact zone (30m). A sett was
located 50m from the proposed access track across the Killean Burn. Water Vole,
Page 56

Page 57

Red Squirrel, Pine Marten, and Reptiles - No evidence recorded. Suitable habitat
is present  
15.24 Fish - Species likely present are brown trout and European eel. Some suitable
habitat present. Watercourses will be buffered by 50m apart from locations where
access tracks unavoidably need to cross. The Local Biodiversity Officer welcomes
the inclusion of the Species Protection Plan (SPP) and appointment of an
Ecological Clerk of Works (ECoW) to implement the SPP to include provision of
a Toolbox Talk to all construction staff and contractors and to conduct pre-
construction surveys of protected species of within a month of works starting and
implement appropriate mitigation measures where necessary. 
15.25 Summary of Ornithology – 58 species recorded in the Breeding Bird Surveys with
an additional 15 non-breeding bird species. 45 species recorded in the Wintering
Bird Populations. Species recorded are a mix of raptors, wild fowl, passerines,
and grassland birds. Black grouse lekking sites were recorded on site. Red
throated divers recorded breeding within 2km of the site. No significant impact of
residual impacts on any bird species. Proposal would not affect the favourable
conservation status of any bird species of conservation importance. No adverse
effect on the integrity of any SPA qualifying interests  
15.26 The Local Biodiversity Officer welcomes the removal of the two northernmost
wind turbines to avoid the main goose flight corridor as well as location of the wind
turbines and associated infrastructure to avoid protected sites and species
including the Kintyre Goose Roost SPA, golden eagles, and hen harriers. It is also
noted that there will be a 500m buffer between wind turbines and used black
grouse leks and no construction work will take place before 09:00 within 750m of
any lek sites during April and May.  
15.27 The Local Biodiversity Officer welcomes the creation of 10ha low-density native
woodland edges to improve connectivity and black grouse habitat as outlined in
the BEMP. They also welcome the provision of three artificial nest rafts for red-
throated divers and long-term monitoring to include breeding bird surveys (BBS),
vantage point (VP) surveys, and winter geese surveys. 
15.28 Recommendation – as with the habitat and peatland enhancement, the
application needs to include a plan for mitigation against potential deer
impact on newly planted trees until such a time that they are established
and no longer vulnerable to over-browsing.  
15.29 Biodiversity Enhancement Management Plan (BEMP) - the Local Biodiversity
Officer welcomes the following objectives within the plan: habitat and peatland
enhancement including black grouse, red-throated diver, greenland white-fronted
goose, long term monitoring of planned objectives, reporting of monitoring results
to relevant parties and implementation of a Biodiversity Enhancement
Management Group.  
15.30 Construction Environmental Management Plan (CEMP) - the Local Biodiversity
Officer welcomes the inclusion of the plan to include implementation of an EcoW,
provision of Toolbox talks to all construction staff and contractors, conduction of
pre-construction works within one month prior to works starting, and
implementation of appropriate mitigation measures where necessary. The Local
Page 57

Page 58

Biodiversity Officer welcomes the appointment of an ECoW prior to construction
and throughout works where necessary.  
15.31 Argyll District Salmon Fishery Board (ADSFB) – advised the ECU they are
satisfied the proposal should not have any significant impact on migratory
salmonid fish habitat within the site providing the construction phase is conducted
in accordance with current environmental regulations. Migratory salmonid fish
(sea trout) are present in the lower reaches of the Killean Burn, Tayinloan Burn,
Clachaig Water and Carradale Water (which also has Atlantic salmon) which may
be affected by any deterioration in water quality caused during construction.
ADSFB urge that in the event the proposal receives consent that monitoring of
Water quality, macroinvertebrates, and fish should be undertaken to Scottish
Government guidelines. It is recommended that the matters raised by ADSFB in
relation to the construction phase and monitoring are secured by condition.  
15.32 Having due regard to the above, subject to the recommendations made by
NatureScot, SEPA, RSPB Scotland, the Argyll District Salmon Fishery
Board and the Local Biodiversity Officer being secured by condition in the
event that consent is granted it is considered that the proposal is consistent
with the provisions of Policies 11 – Energy, 3 Biodiversity, 5 – Soils and
Policies 30 – The Sustainable Growth of Renewables of and 79 – Protection
of Soil and Peat Resources of LDP2  
16. TREES, WOODS, AND FORESTS  
16.1 Policy 11 – Energy of NPF4 requires that project design and mitigation will
demonstrate how impacts on trees, woods and forests have been addressed.
Policy 6 – Forestry, woodland, and Trees of NPF4 intent is to protect and expand
forests, woodland, and trees. Policy 77 – Forestry, Woodland, and Trees of LDP2
states that there is a strong presumption in favour of protecting woodland
resources. Policy 78 – Woodland Removal of LDP2 states that proposals that
involve the removal of woodland resources will be assessed against the criteria
for determining the acceptability of woodland removal, in accordance with the
Scottish Government’s Control of Woodland Removal Policy. Where this
assessment concludes that compensatory planting would be appropriate,
developers will need to provide for this in accordance with the advice in the
Scottish Government’s Control of Woodland Removal Policy.  
16.2 Scottish Forestry have advised the ECU that compensatory planting should be
secured by a condition. Furthermore, that the appropriate consenting route for the
management felling required to accommodate construction of the development,
including infrastructure and management felling, totalling 41.3ha would be the
Section 36 consent. Restocking of management felling areas and compensatory
planting relating to permanent woodland loss would also be via the Section 36
consent. 
16.3 Having due regard to the above subject to the condition recommended by
Scottish Forestry being attached in the event that the proposal receives
consent it is consistent with the provisions of Policies 11 – Energy and 6 –
Forestry, woodland and Trees of NPF4, and Policies 30 – The Sustainable
Growth of Renewables; 77 – Forestry, Woodland and Trees and 78 –
Woodland Removal of the LDP2  
Page 58

Page 59

17. MINERALS  
17.1 Policy 33 – Minerals of NPF4 states that proposals for borrow pits will only be
supported where the proposal is tied to a specific project and is time-limited, the
proposal complies with the mineral extraction criteria in Policy 33 taking into
account the temporary nature of the development, and appropriate restoration
proposals are enforceable and Policy 31 – Minerals of LDP2 states that proposals
for mineral extraction will generally be supported for borrow pits where the
proposal is found to be acceptable after being assessed against NPF4 Policy 33
criterion e).  
17.2 Borrow pits may be used to provide the stone for the construction of access
tracks, compounds, and hardstands, subject to sufficient quality and quantity of
stone being available at the six borrow pit search areas. These search areas are
shown as the maximum potential area of borrow pit extraction, but it is not
anticipated these areas would be fully exploited. Final borrow pit locations within
the borrow pit search areas would be subject to detailed ground investigations to
confirm suitability of material. A condition is recommended to secure details of the
borrow pits and a borrow pit restoration plan.  
17.3 Having due regard to the above taking into account that the proposed
borrow pits are tied to the proposal and subject to a condition to secure
details of the borrow pits and a borrow pit restoration plan being attached
to any consent it is concluded that the proposal is consistent with the
provisions of Policy 33 – Minerals of NPF4 and Policy 31 – Minerals of LDP2
in this regard, subject to a condition to secure details of the borrow pit and
a borrow pit restoration plan.  
18. DECOMMISSIONING, SITE RESTORATION AND QUALITY OF SITE
RESTORATION PLANS    
18.1 Policy 11 – Energy of NPF4 requires that project design and mitigation
demonstrate how the decommissioning of developments, including ancillary
infrastructure, and site restoration have been addressed. It also requires that
project design and mitigation demonstrate how the quality of site restoration plans
have been addressed including the measures in place to safeguard or guarantee
availability of finances to effectively implement those plans. Policy 30 – The
Sustainable Growth of Renewables of the LDP2 requires consideration to be
given to the long-term environmental management of the site. 
18.2 The proposal is expected to operate for up to 50 years following which
decommissioning of the wind turbines and other infrastructure would be
undertaken as required. Any alternative to this action would be subject to a further
consenting process.  
18.3 In the event of decommissioning, or replacement of the wind turbines, it is
anticipated that the likelihood of environmental effects is like, or less than, that
expected during construction. Decommissioning would be undertaken in line with
best practice processes and methods and will be managed through an agreed
CEMP. Decommissioning will involve the following: dismantling and removal of
wind turbines and electrical equipment; restoration of the wind turbine areas,
hardstands, and access tracks; and dismantling and removal of the substation
compound. The CEMP will be updated as required to ensure best practice is
Page 59

Page 60

adopted during decommissioning. It is recommended that this matter is covered
by planning conditions consistent with other projects across Argyll & Bute if the
proposal obtains consent from the ECU. 
18.4 Having due regard to the above it is concluded that subject to an
appropriate condition being attached if the proposal receives consent the
proposal is consistent with the provisions of Policy 11 – Energy of NPF4
and Policy 30 - The Sustainable Growth of Renewables of the LDP2  
19. CUMULATIVE IMPACTS  
19.1 Policy 11 – Energy of NPF4 requires that project design and mitigation will
demonstrate how cumulative impacts have been addressed. Policy 30 – The
Sustainable Growth of Renewables of the LDP2 also requires cumulative impacts
to be addressed. Any cumulative impacts which have been identified are covered
in the preceding sections of this report.  
20. RENEWABLE ENERGY GENERATION TARGETS AND GREENHOUSE GAS
EMISSIONS REDUCTION TARGETS. 
20.1 Policy 11 – Energy of NPF4 requires that, in considering the impacts of the
proposal, significant weight will be placed on the contribution of the proposal to
renewable energy generation targets and on greenhouse gas emissions reduction
targets. Policy 1 – Tackling the climate and nature crises of NPF4 requires that
when considering proposals significant weight will be given to the global climate
and nature crises. Policy 30 – The Sustainable Growth of Renewables of LDP2
requires all renewable developments to be assessed against the scale of
contribution to renewable energy generation targets and greenhouse gas
emissions. 
20.2 Renewable Electricity Generation - Both UK and Scottish Government energy
policy recognises the need for substantial increases in renewable energy
generation if the transition towards net zero is to be achieved. The turbines would
have an anticipated capacity of approx. 6.6MW. The annual generation from the
turbines is therefore estimated at approx. 227.8 Gigawatt hours (GWh) based on
a site derived capacity factor of 43.77% 1. The turbines will therefore supply
renewable electricity equivalent to the approximate annual domestic needs of up
to 70,3162 average UK households. Each unit of renewable electricity transmitted
will displace a unit of conventionally generated electricity, therefore displacing
carbon dioxide (CO2) emissions. It is estimated that the proposed wind turbines
will displace approx. 96,5873 tonnes of CO2 emissions per year, or 4,829,360
tonnes over the anticipated 50-year lifespan of the proposal.  
20.4 Greenhouse Gas Emissions – The proposal would reduce greenhouse gas
emissions through replacing fossil fuel generation. The length of time a wind
turbine needs to be in operation before it has, by displacing fossil fuel energy
generation, avoided as much carbon dioxide as was released in its lifecycle is
known as the carbon payback period. A carbon balance assessment has been
undertaken using the Scottish Government’s carbon calculator. The results reveal
the net impact will be positive overall, as the calculations of total carbon dioxide
emission savings and payback time indicate the overall payback period would be
approx. 1.5 years, when compared to the fossil fuel mix of electricity generation.
Over the expected 48.5 years the proposal is likely to be generating carbon-free
Page 60

Page 61

electricity, this could result in around 4,829,360 tonnes of net carbon dioxide
emission savings when replacing fossil fuel-mix electricity generation. Overall, the
proposal would lead to substantial net carbon savings and reduction of
greenhouse gas emissions over its operational life. Peatland is an important
carbon store, and the proposal has potential to impact peat, despite mitigations
proposed to limit disturbance. A carbon balance assessment report has been
produced and Scottish Government’s online carbon calculator tool completed to
determine the carbon payback time for the proposal. The results from the carbon
calculator reveal that the net impact of the proposal will be positive overall, as the
calculations of total carbon dioxide emission savings and payback time for the
proposal indicates the overall payback period would be approximately 1.5 years,
when compared to the fossil fuel mix of electricity generation. This means that the
proposal is expected to take between 0.6 and 1.9 years to repay the carbon
exchange to the atmosphere (the CO2 debt) through construction of the wind
turbines; the proposal would in effect be in a net gain situation following this time
period and would contribute to national CO2 reduction targets. The proposal
therefore illustrates a significantly positive net impact in terms of its contribution
towards the reduction of greenhouse gas emissions from energy production.  
20.5 Having due regard to the above it is considered that the proposal is
consistent with the provisions of Policies 1 – Tackling the climate and
nature crisis and 11 – Energy of NPF 4, and Policies 30 – The Sustainable
Growth of Renewables and 04 – Sustainable Development of LDP2 in
respect to renewable energy generation targets and greenhouse gas
emissions reduction targets.    
21. GRID CAPACITY & ENERGY STORAGE    
21.1 Policy 11 – Energy of NPF4 requires that grid capacity should not constrain
renewable energy development. It is for developers to agree connections to the
grid with the relevant network operator. Furthermore, that proposals for all forms
of renewable, low-carbon and zero emissions technologies will be supported,
which include energy storage. Policy 30 – The Sustainable Growth of Renewables
of LDP2 requires the Council to have regard to the opportunities for energy
storage. 
21.2 Grid Capacity - Connection to Electricity Grid - The proposed point of connection
into the electricity grid system is at the substation compound. The proposal would
be connected at Carradale Substation, a substation located approx. 11.2km
southeast of the site. The connection would be comprised of buried 132kV cables
and/or Overhead lines (OHL). The exact arrangement of this grid connection is
subject to detailed design by SSEN Transmission. Any final grid connection route
and associated consents would be subject to a separate consenting process and
EIA if required.  
21.3 Energy storage – This project will not have a Battery Energy Storage System
(BESS). The reason there is no BESS proposed at Killean is simply down to the
terms of the Applicant’s option agreement with the landowner. It was signed
around the time of the original application, before BESS became more commonly
included in wind applications, so they currently have rights for a wind farm only.
Not to say that this could not be amended and incorporated in future.  
Page 61

Page 62

21.4 Having due regard to the above it is considered that the proposal is
consistent with the provisions of Policy 11 – Energy of NPF 4, and Policy 30
– The Sustainable Growth of Renewables of the ABLDP2 in respect to Grid
Capacity and Energy Storage.  
22. PERPETUITY    
22.1 Policy 11 – Energy of NPF4 requires that consents for proposals may be time
limited. Areas identified for wind farms are, however, expected to be suitable for
use in perpetuity. It is acknowledged that areas identified for wind farms are
expected to be suitable for use in perpetuity. However, as the expected
operational life of the proposal is 50 years from the date of commissioning, should
consent be granted, Officers would expect it to be time limited to 50 years to
reflect the life of the wind farm as detailed in the EIAR.  
23. CONCLUSION   
23.1 This proposal is classed as “Strategic Renewable Electricity Generation” - a
National Development, in terms of the Spatial Strategy given its capacity to
generate and store more than 50MW. In principle, there is support for this scale
of development given its importance in the delivery of Scotland’s Spatial Strategy.
However, such projects are still required to be assessed against the provisions of
the Development Plan, which consists of NPF4 and LDP 2.  
23.2 The lead Development Plan policies support renewable energy development in
principle but require proposals to be assessed against the criterion detailed in this
report. While the weight to be given to each of the considerations is a matter for
the decision maker, NPF4 is clear that significant weight will require to be placed
on the contribution of the proposal to renewable energy generation targets and
on greenhouse gas emission reduction targets. However, a balance still requires
to be reached in terms of the impact of the development. 
23.3 In relation to landscape and visual impacts NPF4 advises that where impacts are
localised and/or appropriate design mitigation has been applied such effects will
be considered acceptable. However, NPF4 must be read as a whole, and detailed
consideration given to linked policies. Policy 4 (Natural Places) – sets out that
proposals which by virtue of type, location or scale will have an unacceptable
impact on the natural environment will not be supported. Whilst it is considered
that this proposal will have a significant landscape and visual impact, it is not
considered that it warrants an objection subject to the conditions recommended
by the Councils Consultant Landscape Architect. 
23.4 The Scottish Government gives considerable commitment to renewable energy
and encourages Planning Authorities to support the development of wind farms
where they can operate successfully in appropriate locations. This is not however
blanket support without qualification. In considering the appropriateness of the
development, significant weight has been given to these matters. 
23.5 In conclusion, it is recommended by Officers that the Council objects to this
proposal until such time as National Air Traffic Services remove their objection.
Thereafter, the Council would have no objection to this proposal subject to the
recommended conditions being included in any consent granted by Scottish
Ministers.
Page 62

Page 63

24. RECOMMENDATION  
24.1 That the ECU be notified accordingly that: 
(1) There is an unresolved objection from National Air Traffic Services
Safeguarding (NATS). Consequently, Argyll & Bute Council OBJECT on the
grounds that the proposal will have an adverse Aviation Impact, contrary to
the provisions of Policy 11 – Energy of NPF4 which requires that project design
and mitigation demonstrates how impacts on aviation and defence interests
including seismological recording have been addressed, Policy 30 – the
Sustainable Growth of Renewables of LDP2 which requires impacts on aviation
and defence interests and seismological recording to be addressed, and Policy
43 – Safeguarding of Aerodromes of LDP2 which stipulates that development will
not be permitted where it would compromise the safe operation of an Aerodrome
or Technical Site or constrain their present or future operations. 
Note: If NATS withdraw their objection and subject to any conditions they
recommend being attached to any grant of consent Argyll & Bute Council
would no longer object on these grounds. Should the objection remain
unresolved, and the proposal progresses to Public Inquiry, Argyll & Bute
Council would defer to NATS. 
(2) Argyll & Bute Council has no objection in respect to landscape and visual
impact subject to conditions to secure the mitigation recommended by the Council’s
Consultant Landscape Architect being attached to any grant of consent: 
• Aircraft Detection Lighting System 
• Substantial increases in broadleaved planting as part of the wind farm restocking
plan including riparian planting across the wider Killean estate. 
• Redesign of the outer margins of productive woodland to remedy hard angular
edges and improve the fit of plantations with landform. 
• Compensatory planting should be undertaken within the Killean Estate. Argyll &
Bute Council and Scottish Forestry should be consulted on the location, extent,
and composition. 
• Management of existing mature mixed woodlands in the vicinity of Killean House
including new planting to retain and enhance screening of the proposed wind farm
from the coast and protect the landscape setting provided to the Killean Estate
buildings and St John’s Church. 
(3) Argyll & Bute Council has no objection in respect to archaeological impact,
subject to conditions to secure appropriate archaeological mitigation being attached
to any grant of consent following further consultation with the West of Scotland
Archaeology Service. 
(4) Argyll & Bute Council has no objection in respect to Biodiversity Impact,
subject to conditions to secure the recommendations of the Local Biodiversity Officer
being attached to any grant of consent. 
Page 63

Page 64

• An appropriate plan for mitigation against potential deer impact on newly planted
trees until such time as they are established and no longer vulnerable to over-
browsing.
• While the impact to bats is unlikely to be significant, it would be advisable to
monitor any fatalities that may occur from collision as they are found to forage
within the wind turbine areas. 
(5) Argyll & Bute Council has no objection in respect to noise impact, subject to a
suitably worded conditions to limit the noise levels, tonality, and amplitude modulation
to control noise levels from the proposal and provide appropriate noise mitigation as
recommended and agreed by the Councils Noise Consultant. 
(6) Argyll & Bute has no objection in respect to flood risk subject to conditions to
secure the recommendations of the Flood Risk Assessor being attached to any
grant of consent: 
• To ensure watercourse crossings are designed so there is no reduction in pre-
development channel cross sectional area ideally to pass the 1 in 200 year
plus climate change flood event; and,
• Surface water drainage is designed in accordance with CIRIA C753 and
ensures that post development runoff is attenuated to the 1 in 2 year
greenfield runoff rate. The surface water drainage should be in operation prior
to the start of construction. 
(7) Argyll & Bute Council has no objection in respect to Access subject to the
condition to secure the recommendations of the Access Officer being attached to
any grant of consent: 
• Access Plan to be submitted and agreed in writing by the Council prior to the
commencement of development. 
(8) Argyll & Bute Council has no objection in respect to provision of the turning
area across from the site access subject to the following conditions being
attached to any grant of consent. 
• Exact details and specifications of the design of the turning area to be submitted
for the written approval of the Planning Authority prior to commencement of
development.
• Exact details and specification of the restoration plan for the turning area to be
submitted for the written approval of the Planning Authority prior to
commencement of development. These shall include details of timescales and
landscaping.
• A condition to limit the turning area to an appropriate temporary period to be
agreed in writing by the Planning Authority. 
(9) Argyll & Bute Council requests that all conditions recommended by other
consultees are included in any Consent.   
Page 64

Page 65

"""""
"
"
""
"
"
"
"
""
© Crown Copyright and database right 2024
All rights reserved. OS license (customer) account number AC0000849384
Location Plan Relative to: 24/01541/S36
O
1:35,000
0 325 650162.5 Meters
Application Site
Page 65

Page 66

This page is intentionally left blank

Page 67

Argyll and Bute Council
Development & Economic Growth   
Planning Application Report and Report of Handling as required by Schedule 2 of the
Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013 relative to applications for Planning Permission or Planning Permission
in Principle 
Reference No: 25/00576/PP
Planning Hierarchy: Local Application
Applicant: Mr Kyle Kennedy
Proposal: Erection of dwellinghouse, formation of vehicular access and
associated works
Site Address:  Land Between Lagarie Lodge And Lagarie House Torwoodhill
Road Rhu Argyll And Bute      
DECISION ROUTE 
Committee Decision under Local Government Scotland Act 1973   
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission
• Erection of dwellinghouse
• Formation of vehicular access and associated works
• Tree removal 
(ii) Other specified operations
• N/A 
(B) RECOMMENDATION: 
Having due regard to the Development Plan and all other material considerations, it is
recommended that planning permission be granted subject to the conditions and reasons
appended to this report. 
(C) CONSULTATIONS:   
Core Paths – No response, therefore, assumed no objection. 
Scottish Rights Of Way And  Access Society -  No response, therefore, assumed no
objection. 
Scottish Water - 24.04.2025 –  No objection however Scottish Water have noted; There is
currently sufficient capacity in the Blairlinnans Water Treatment Works to service your
development. However, please note that further investigations may be required to be carried
out once a formal application has been submitted to us. This proposed development is within
Page 67 Agenda Item 5

Page 68

the Rhu Sep Waste Water Treatment Works catchment. Single house developments; unless
utilising private drainage methods, are required to submit a Waste Water Application via our
Customer Portal to allow us to fully appraise the proposals. We recommend that this is done at
the earliest opportunity to allow for network appraisal to be carried out ahead of development
proceeding. The applicant should be aware that we are unable to reserve capacity at our water
and/or waste water treatment works. When planning permission has been granted and a formal
connection application has been submitted, we will review the availability of capacity at that
time and advise the applicant accordingly. For reasons of sustainability and to protect our
customers from potential future sewer flooding, Scottish Water will not accept any surface
water connections into our combined sewer system. There may be limited exceptional
circumstances where we would allow such a connection for brownfield sites only, however this
will require significant justification from the customer taking account of various factors including
legal, physical, and technical challenges. 
Roads Helensburgh And Lomond - 08.05.2025 –  No objection subject to conditions relating
to; detailing of the vehicular access, gradients, surfacing materials, visibility splays, parking
provision, turning, drainage and gates. 
Roads Helensburgh And Lomond – 05.11.25 - No objection subject to conditions. Roads
have updated their initial consultation response to ensure consistency with previous
recommendations for the site. The recommended conditions relation to the vehicular visibility
splay has been updated as well as the condition relating to the access detailing. 
Built Heritage Conservation Officer - 06.06.2025 – Notes that the principle of development
on the site has been accepted through the approval of 23/01502/PP, which remains extant.
However, the built heritage conservation officer also notes potential issues with the proposed
design and suggests some possible amendments (see detailed comments with assessment
below). 
Built Heritage Conservation Officer - 14.10.2025 – The built heritage conservation officer
was re-consulted on design amendments and relays concern in regards to the accuracy of the
submitted drawings, the proposed materials and also the apparent lack of a further assessment
as per NPF4 Policy 7 (see detailed comments with assessment below). 
Local Biodiversity Officer - 08.05.2025 – No objections, however, additional information has
been requested by way of the following: European protected species surveys for bats and otter
prior to determination, further protected species surveys prior to works starting on site, Tree
survey prior to determination and details of proposed bio-diversity enhancement measures
(see detailed comments with assessment below). 
Local Biodiversity Officer - 24.09.2025 – The Local Biodiversity Officer was re-consulted on
the submitted tree survey and bat scoping survey report in light of their initial consultation
response. The Local Biodiversity Officer confirms that the submitted bat scoping survey report
has been undertaken by an appropriately qualified person and that a desk-study search shows
there are no otters within 5km of the site and no waterways are present on the site. As a
precautionary approach, and due to the transient nature of wildlife, they ask that a pre-works
survey is carried out for Protected Species. 
(D) HISTORY:   
C6986 
Conversion of Lagarie house from children’s home to from 4 flats, including the erection of 4
detached dwellinghouses to the West of the Lagarie house. Note: During determination the
proposal for 4 dwellinghouses was reduced to 3 dwellinghouses. 
24.05.1983 (application approved) 
C6986 
Page 68

Page 69

Erection of 3 dwellings houses 07.07.1983 (application approved) 
C6994 
Erection of 2 detached dwellinghouses North-West of Lagarie house. 
28.06.1983 (outline) (application approved) 
C8400 
Erection of a 2 storey detached dwellinghouse with double integral garage to the East of Lagarie
House.
07.04.1989 (outline) (application refused / appeal dismissed) 
P/PPA/SH/137 
Appeal of planning refusal reference C8400.
05.02.1990 (appeal dismissed) 
11/00528/PP
Erection of 5 flats and car ports
07.11.2011 (application withdrawn) 
19/02162/PP
Erection of 2 dwellinghouses and garages
14.02.2020 (application withdrawn)   
20/01382/PP
Erection of dwellinghouse with integral garage and formation of new vehicular access
16.08.2023 (application withdrawn)   
20/01383/LIB
Formation of new vehicular access through the existing stone wall
16.08.2023 (application withdrawn)   
23/01502/PP
Erection of dwellinghouse and formation of new vehicular access
23.05.2024 (application approved)   
23/01503/LIB
Formation of new vehicular access through the existing stone wall
23.05.2024 (application approved)   
(E) PUBLICITY:   
Advert Type: Listed Building/Conservation Advert               Expiry Date: 15.05.2025 
(F) REPRESENTATIONS:   
(i) Representations received from: 
Objection 
M Edwards Lagarie Cottage Mor Torwoodhill Road Rhu Argyll And Bute 14.10.25
Irene Edwards Lagarie Cottage Torwoodhill Road Rhu Argyll And Bute 14.10.25
P Cassidy Auchenlea Lodge Torwoodhill Road Rhu G84 8LF 14.10.2025
G Grant Auchenlea Lodge Torwoodhill Road Rhu G84 8LF 14.10.2025
Page 69

Page 70

Jim Crawford Garden Cottage Lagarie Torwoodhill Road Rhu Argyll And Bute
09.05.2025, 12.05.25, 21.07.25, 04.08.25, 06.10.25, 07.10.25, 24.10.25, 07.11.25,
10.11.25
Irene Crawford Garden Cottage Lagarie Torwoodhill Road Rhu Argyll And Bute
09.05.2025, 24.10.25
Dr Krystina Crawford 736 Crow Road, Anniesland, Glasgow, G13 1NF 13.05.2025
Annamarie Kelly 3 Lagarie House Torwoodhill Road Rhu Argyll And Bute 03.10.2025,
24.10.25
Sloan Kelly Flat 3 Lagarie House Torwoodhill Road Rhu 09.10.2025, 24.10.25
Mr Doolen Doonpark Torwoodhill Road Rhu Argyll And Bute 09.10.2025
V Doolen Doonpark Torwoodhill Road Rhu Argyll And Bute 09.10.2025
Moira Burke Lagarie Lodge Torwoodhill Road Rhu Argyll And Bute 09.10.2025,
24.10.25
Russell Burke Lagarie Lodge Torwoodhill Road Rhu Argyll And Bute 09.10.2025,
24.10.25
Kate Austin Flat 2 Lagarie House Torwoodhill Road Rhu 09.10.2025, 24.10.25
Ron McKechnie Flat 1 Lagarie House Torwoodhill Road Rhu 09.10.2025, 24.10.25
Anne McKechnie Flat 1 Lagarie House Torwoodhill Road Rhu 09.10.2025, 24.10.25
Duncan McGuire Flat 4 Lagarie House Torwoodhill Road Rhu 09.10.2025, 24.10.25
Sandra McGuire Flat 4 Lagarie House Torwoodhill Road Rhu 09.10.2025, 24.10.25 
Representations are published in full on the planning application file and are available to view
via the Public Access section of the Council’s website. 
(ii) Summary of issues raised: 
• Note that no public notice has been erected at the application site. 
Comment; Officers can confirm that the required notice was erected on the 
22.05.2025. 
• Note that a Listed Building Consent application is also required. 
Comment; Officers confirm that a Listed Building Consent application is not
required in this instance as the only development requiring Listed Building
Consent is the alterations to the boundary wall to form the new vehicular
access, however, these works currently benefit from Listed Building Consent
approval under approval reference; 23/01503/LIB. No changes are proposed
under this application that deviate from this approval therefore a separate
listed building consent application is not required at this time. 
• Concern that the Design and Conservation Officer has not been consulted on
the application. 
Comment; Officers confirm that the Design and Conservation Officer has been
consulted on this application. 
• Concern that no tree survey has been submitted. 
Comment; officers can confirm that a tree survey has been submitted. 
• Note that no consultation has been requested from the community council. 
Comment; The authority is only required to consult with the community council
on applications where the proposed development is likely to affect the amenity
of the area. In this instance officers do not consider that the proposed
development affects the amenity of the area (see assessment below).
Page 70

Page 71

Furthermore, the community council  can choose to submit a consultee
response, however, they have not in this instance. 
• Note that the application site is the front garden of the neighbouring listed
property. 
Comment; the application site no longer forms part of the neighbouring listed
properties curtilage due to the passage of time the lawn area has been
separated by vegetation and is not used in association with the main house. 
• Concern in terms of existing drainage pipes (foul & surface water) running
through the site. 
Comment; This is noted, however, this is a private civil matter. It is also
confirmed that a standards SUDS condition will be added to this application
with regards to surface water on the application site. 
• Concern in regard to the proposed parking positioning in terms of the potential
negative effects on the access to the neighbouring listed property. 
Comment; this is noted and it is considered that with the appropriate screening
(as included by condition) this is acceptable. It is further noted that the
neighbouring property Lagarie Lodge has an access onto the shared access
to the neighbouring listed property and currently has a parking area to the
rear. 
• Concern in regard to proposed tree removal as the site forms part of a TPO
area. 
Comment; please see assessment below. 
• Concern that the proposals do not take into account SUDS. 
Comment:  A detailed SUDS scheme will be conditioned. 
• Note that a transport assessment / noise assessment should be provided in
regard to the new vehicular access. 
Comment; the area roads manager has been consulted on the proposals
and has confirmed that they have no objections subject to conditions. There
is no requirement for a transport/noise assessment in this instance given the
small scale nature of the proposals. 
• Note that daylight / sunlight calculations should be provided. 
Comment; this is noted, however, the above calculations are not a
requirement and in this instance officers consider that there are no negative
effects on the daylight / sunlight to neighbouring properties arising from the
proposed development. 
• Note that an ecology / habitat survey should be provided. 
Comment; it is confirmed that a preliminary ecological assessment has been
submitted with regards to the application site. 
• Note that the bat scoping survey has not been completed by a qualified
ecologist in line with the bio-diversity officer’s consultation response. 
Page 71

Page 72

Comment; The Local Biodiversity Officer has confirmed that the submitted
bat scoping survey report has been undertaken by an appropriately qualified
person. 
• Note that no details of the proposed bio-diversity enhancement measures as
requested by the bio-diversity officer have been submitted. 
Comment; It is confirmed that the proposed bio-diversity enhancement
measures have been included within the submitted preliminary ecological
assessment. 
• Note that no details on the bio-diversity value of the trees on site have been
submitted as per the request of the bio-diversity officer. 
Comment; this is noted, however, it is confirmed that the council’s
biodiversity officer has provided an updated response which is detailed in
assessment below. 
• Note that no detail drawings have been submitted in regards to the proposed
access alterations. 
Comment; the access alterations are shown on the proposed site plan,
which notes ‘New access, visibility splays and wall to be as per previous
approval ref: 23/01502/PP….’ 
• Concern with regards to the suitability of the landscaping proposals. 
Comment; it is recommended that a planning condition is added to any
approval requiring the submission and approval of a detailed landscaping
scheme. 
• Note that the revised design submitted should have required a fresh
planning application as the changes are significant given the increase in size
and height. It was previously a two low level pitched roofs at the same pitch
angle and now it is a single roof spanning the full width of the proposed
house with significant increase in roof height. The new house type in plan,
section, elevations and location on site bearing no resemblance to the initial
building proposal. 
Comment; it is confirmed that it is the view of officers that the design
amendments are considered to be non-material and therefore a fresh
planning application is not required in this instance. The amendments are
not significant as the footprint has only increased by 25sqm, the positioning
is slightly closer to the main house but not by much and the ridge has
increased but it is marginal and the house remains single storey. 
• Note that the public should be notified of the revised design proposals. 
Comment; it is confirmed that there is no requirement to re-notify interested
parties as the design amendments are considered to be non-material,
however, officers have exercised discretion in this instance and have re-
notified all interested parties. 
• Note that the scale of the proposed house is inappropriate in the context. 
Comment; please see assessment below. 
Page 72

Page 73

• Comment that the historical approvals; C6986 for the conversion of Lagarie
House from children's home to from 4 flats, including the erection of 4
detached dwellinghouses to the West of Lagarie House (during the
determination process this was reduced to the erection of 3 dwellinghouses
to the West in lieu of the initial 4 applied for) and C6994 for the erection of 2
detached dwellinghouses to the North-West of Lagarie House, there was a
planning condition on these approvals that stated ‘there shall be no direct
access, vehicular or pedestrian on to the A814. Therefore, the proposed
access under this application should not be allowed as the previous
condition is legally binding and the subsequently the recent approval on the
site has no legal means of access and is thus invalid. 
Comment; This condition was in relation to previous planning approvals
(references; C6986 & C6994) and was complied with. It is not a condition
binding on all future developments for the overall site.  The 5 detached
dwellinghouses approved under the aforementioned applications are located
to the West and North-West of Lagarie House, this application site is located
to the East of Lagarie House. This application is in relation to a different
development; therefore, officers will access the suitability of the proposed
access onto the A814 under the current development plan and all material
planning considerations. It is further noted the area roads manager was
consulted on the current application and the proposed vehicular access on
to the A814 and has noted that they have no objections to this subject to
recommended planning conditions. 
• Concern about potential impacts on wildlife. 
Comment:  please see assessment below. 
• Concern about forming a new access through a listed wall. 
Comment; please see assessment below. 
• Concern that the removal of trees or bushes would create greater traffic
noise for neighbouring properties. 
Comment; this is noted however this is considered to be minimal.   
• Concern that the proposals could affect bats. 
Comment; the applicants have submitted a potential bat roost assessment.
This assessment concludes ‘Having regard to the distribution of species,
habitat, potential roost features, suitability and importance of any of these
and signs of bat activity the risk of bat roosts or bats being disturbed is
negligible or low and roosting can reasonably be ruled out’. Furthermore, the
submitted preliminary ecological assessment also makes reference to bats
and concludes ‘No further survey is required unless plans for tree felling are
changed at which point a pre-felling check should be undertaken’. 
• Note that a previous application for a single dwelling on the proposal site
was refused in 1989 and also refused at the subsequent appeal in 1990 and
therefore this application should also be refused. 
Comment; this is noted however, it is confirmed that the previous decision
simply confirms that the principle of development was determined to be
Page 73

Page 74

unacceptable having regard to the detail of the proposal, development plan
policy and circumstances at the point in time that the appeal decision was
made. A substantial period of time has elapsed since the appeal decision
and within this time the relevant development plan and other relevant policy
considerations have been superseded by subsequent iterations of the Local
Development Plan and National Policy and Guidance and accordingly it is
necessary for any decision on the current application to be assessed against
these revised provisions and in relation to the current circumstances of the
site and its surrounds. It should also be noted that the most recent
application for this site was approved in May 2024 for a single house
(reference; 23/01502/PP). 
• Concern about the removal of the mature rhododendron hedge. 
Comment; rhododendron ponticum is an invasive species and the removal of
this would benefit the biodiversity on the site. 
• Concern that SEPA / the flood risk advisors have not been consulted on the
proposal with regards to potential flooding, surface water drainage and
existing below ground drains. 
Comment; As the site is not within the indicative flood risk zone (coastal /
surface / river) as per the SEPA maps, the trigger for consulting SEPA / the
flood risk consultants as a statutory consultee has not been met, therefore,
there is no need to consult as the development is not considered to be at
risk of flooding. With regards to surface water drainage, this will be added as
a planning condition and to confirm SEPA / the flood risk consultants do not
require to be consulted with regard to surface water. Lastly the possible
presence of existing below ground drains within the site are a private civil
matter and not a matter for SEPA or the flood risk consultants, it is also
noted that Scottish Water have noted no objections and have not flagged
that they have any Scottish Water assets in proximately to the site within
their consultation response.   
• Note that a flood risk assessment is required. 
Comment; There is no requirement for a flood risk assessment as the site is
not considered to be at risk of flooding (see comment above). 
• Note that no site levels have been shown and there is a possibility that the
finished floor levels could be lower than the SEPA required levels on other
applications. 
Comment; The site is not considered to be at risk of flooding and therefore
SEPA have not been consulted. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Impact Assessment Report:  No  
Page 74

Page 75

(ii) An Appropriate Assessment under the
Conservation (Natural Habitats) Regulations 1994: 
No  
(iii) A Design or Design/Access statement:
A planning supporting statement has been submitted
which covers the following topics; 
• Site Context and Surroundings
• Accessibility
• Design
• Policy overview 
The statement concludes the following: The
development will improve on the sense of identity and
character of the area of the village of Rhu. The potential
redevelopment of the site for residential purposes is of
a scale and nature that will positively compliment
surrounding properties within Rhu. In conclusion, taking
into consideration Argyle and Bute’s Local Development
Plan it is our view that the proposed development is
acceptable, and the proposed scale, design and
massing of the residential development complies with
policy criteria as set out in the LDP2 and NPF4. The
above information provides sufficient evidence and
justification to show a compliance to Policy related to
proposals of this nature. 
Yes  
(iv) Sustainability Checklists (with reference to the
requirements of LDP2 Policy 04) 
TN06 Sustainability Checklist
TN07 Sustainable Buildings Checklist
Yes
Yes  
(v) A report on the impact of the proposed development
eg. Retail impact, transport impact, noise impact,
flood risk, drainage impact etc: 
Planning Further Assessment (Allison Architecture,
May 2025). This report provides an assessment
demonstrating the acceptability of design in regards
to the adjacent listed building as per the
requirements of NPF 4 Policy 7. 
Preliminary Ecological Assessment (JDC Ecology
Limited, July 2025) The assessment was
undertaken on the 25th of June 2025.  The
assessment provides an overview of the area as
regards the main habitat types and the presence or 
likely presence of protected or notable species and
Invasive Non-Native Species (INNS).  The
assessment concludes that the land as surveyed
would be regarded overall as of moderate
biodiversity value, including both the woodland and
grasslands. However, the woodland requires
suitable management to resolve current issues,
which includes an established cover of
Rhododendron, and general lack of management to
optimise woodland structure and diversity. 
Yes
Page 75

Page 76

Tree Survey Report (Julian A Morris, June 2025)
The survey was undertaken in May 2025. Each tree
over 75mm diameter on site was recorded. Around
50 trees on and around the site were recorded,
measured and categorised individually. The survey
did not identify the presence of individual veteran or
ancient trees on or around the site. Root protection
areas were identified for all the trees. 
Bat Scoping Survey Report (Julian A Morris, June
2025) The nature of the survey was to undertake a
preliminary character assessment to ascertain
whether the site has potential to support roosting
and/or foraging bats and identify the species of bat
and any trees and their potential for roost feature
and signs of bat use. The survey was carried out in
May 2025. The stone wall was checked for cavities
or unbound rubble interiors and no signs of this was
found. All trees were checked for holes, cavities and
hollows and no sign of potential roost features were
identified on any of the trees.   
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   No   
(I) Has a Direction been issued by Scottish Ministers in terms
of Regulation 30, 31 or 32:  
No    
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been taken into account in the
assessment of the application 
(i)  List of all Development Plan Policy considerations taken into account in
assessment of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
Part 2 – National Planning Policy 
Sustainable Places
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 2 – Climate Mitigation and Adaption
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 5 – Soils
NPF4 Policy 6 – Forestry, Woodland and Trees
NPF4 Policy 7 – Historic Assets and Places
NPF4 Policy 13 – Sustainable Transport 
Liveable Places
NPF4 Policy 14 – Design, Quality and Place
Page 76

Page 77

NPF4 Policy 15 – Local Living and 20 Minute Neighbourhoods
NPF4 Policy 16 – Quality Homes 
Argyll and Bute Local Development Plan 2 (Adopted 2024) 
Spatial and Settlement Strategy
Policy 01 – Settlement Areas
Policy 04 – Sustainable Development 
High Quality Places
Policy 05 – Design and Placemaking
Policy 08 – Sustainable Siting
Policy 09 – Sustainable Design
Policy 10 – Design – All Development
Policy 15 – Protection, Conservation and Enhancement of Our Historic Environment
Policy 16 – Listed Buildings
Policy 17 – Conservation Areas 
Connected Places
Policy 34 – Electric Vehicle Charging Points
Policy 35 – Design of New and Existing, Public Roads and Private Access Regimes
Policy 36 – New Private Accesses
Policy 39 – Construction Standards for Private Accesses
Policy 40 – Vehicle Parking Provision 
Sustainable Communities
Policy 61 – Sustainable Urban Drainage Systems (SUDS)
Policy 63 – Waste Related Development and Waste Management 
Homes for People
Policy 66 – New Residential Development on Non-Allocated Housing Sites within
Settlement Areas 
High Quality Environment
Policy 73 – Development Impact on Habitats, Species and Biodiversity
Policy 77 – Forestry, Woodland and Trees
Policy 79 – Protection of Soil and Peat Resources 
(ii)  List of all other material planning considerations taken into account in the
assessment of the application, having due regard to Annex A of Circular
3/2013. 
• Third Party Representations
• Consultation Reponses
• Planning History
• ABC Technical Note – Biodiversity (Feb 2017)
• TN06 Sustainability Technical Note and Checklist (Oct. 2023)
• TN07 Sustainable Buildings Technical Note and Checklist (Oct. 2023)
• ABC Housing Needs and Demand Assessment
• ABC Housing Emergency Statement
• SEPA Standing Guidance for Development Management (Dec. 2022)
• Historic Environment Scotland – HEPS
• Historic Environment Scotland – Managing Change in The Historic Environment - various 
Page 77

Page 78

(K) Is the proposal a Schedule 2 Development not requiring an
Environmental Impact Assessment:  
No    
(L) Has the application been the subject of statutory pre-
application consultation (PAC):  
No 
(M) Does the Council have an interest in the site:   No 
(N) Requirement for a pre-determination hearing: 
Please note that officers are not recommending a pre-determination
hearing as it is considered that there would be no added value in this
as all material planning considerations have been taken into account
within this report including; consultee responses, third party
representations and planning history etc. 
No 
(O)(i) Key Constraints/Designations Affected by the Development: 
Conservation Area  
Setting of Listed Buildings -  Lagarie House (Category B) and Ardencaple Hotel (Category A) 
Tree Preservation Order - TPO 26 - Lagarie Children's Home, Rhu (confirmed 1984) 
(O)(ii) Soils
Agricultural Land Classification:  Built Up Area 
Peatland/Carbon Rich Soils Classification: N/A 
Peat Depth Classification: N/A 
Does the development relate to croft land? No
Would the development restrict access to croft or better
quality agricultural land?
N/A
Would the development result in fragmentation of croft
/ better quality agricultural land?
N/A 
(O)(iii) Woodland  
Will the proposal result in loss of trees/woodland?  Yes
Does the proposal include any replacement or
compensatory planting?
Yes 
(O)(iv) Land Status / LDP Settlement Strategy
Status of Land within the Application  Greenfield 
ABC LDP2 Settlement Strategy Settlement Area
Page 78

Page 79

ABC LDP2 Allocations/PDAs/AFAs etc: N/A 
(P) Summary assessment and summary of determining issues and material
considerations: 
The proposed development relates to the erection of a 2 bed detached dwellinghouse and
formation of new vehicular access. 
The site is located within the settlement area of Rhu as identified in the adopted Argyll and
Bute Local Development Plan (LDP2) wherein Policy 01 (Settlement Areas) notes that
development will normally be acceptable on a non-brownfield site where, the proposal is
considered acceptable in relation to the overall land supply, it is compatible with surrounding
uses, it is of an appropriate scale and fit for the size of settlement in which it is proposed;
and respects the character and appearance of the surrounding townscape in terms of
density, scale, massing, design, external finishes and access arrangements. 
The proposal lies within the Rhu Conservation Area and the residential property adjacent to
the West, “Lagarie House” which is a Category “B” listed building. Additionally, within the
vicinity is the Category “A” listed “Ardencaple Hotel”. As such, the impact of the proposed
development on the historic environment is a determining factor. In addition, the proposed
development has been assessed more generally with regard to siting, scale, massing form,
and detailed design in relation to the aim of respecting and reflecting the visual character of
the existing built development pattern; and protecting local residential amenity. 
The site is covered by an area Tree Preservation Order (TPO), however, the site is not
located within or in proximity to any nature conservation sites, nor does it lie within
NatureScot Ancient Woodland Inventory. However, any impact upon the natural
environment in relation to biodiversity and impact on trees/woodland requires to be assessed
in connection with the proposal. 
The proposal has also been assessed with regard to the satisfactory provision of services
infrastructure provision. 
A fully detailed assessment with reference to the above determining factors, and all other
material considerations, including planning history and material planning issues raised by
third party representations (not addressed above) are set out in the Appendix A to this report. 
Having regard to all material considerations it is considered that the proposal is acceptable. 
(Q) Is the proposal consistent with the Development Plan:  Yes 
(R) Reasons why Planning Permission or Planning Permission in Principle Should be
Granted: 
The proposal is considered to be consistent with the relevant provisions of the
Development Plan, and there are no other material considerations of sufficient
significance to indicate that it would be appropriate to withhold planning permission
having regard to s25 of the Act. 
Page 79

Page 80

(S) Reasoned justification for a departure to the provisions of the Development Plan: 
N/A 
(T) Need for notification to Scottish Ministers or Historic
Environment Scotland:  
No 
Author of Report:  Emma Jane Date:  05.11.2025 
Reviewing Officer: Kirsty Sweeney Date: 11.11.2025 
Fergus Murray
Head of Development & Economic Growth
Page 80

Page 81

CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO. 25/00576/PP 
Standard Time Limit Condition  (as defined by Regulation) 
Standard Condition on Soil Management During Construction 
Additional Conditions  
1. PP - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details specified on the
application form dated 07.04.25; supporting information and, the approved drawings listed
in the table below unless the prior written approval of the planning authority is obtained for
an amendment to the approved details under Section 64 of the Town and Country Planning
(Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Location Plan 1 of 13 A 9th April 2025
Site Plan as
Existing
2 of 13 - 8th April 2025
Site Sections A-A +
B-B as existing
3 of 13 A 5th  September
2025
Site Sections C-C +
D-D as existing
4 of 13 A 5th  September
2025
Site Plan as
proposed
5 of 13 A 5th  September
2025
Site Sections A-A +
B-B as proposed
6 of 13 A 5th  September
2025
Site Sections C-C +
D-D as proposed
7 of 13 A 5th  September
2025
Ground Floor Plan
as proposed
8 of 13  A 5th  September
2025
South West
Elevation
9 of 13 A 5th  September
2025
North East
Elevation as
proposed
10 of 13 - 5th  September
2025
South East
Elevation as
proposed
11 of 13 - 5th  September
2025
North West
Elevation as
proposed
12 of 13 A 5th  September
2025
Roof Plan as
proposed 
13 of 13 A 7th November 2025 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details.  
2. Scottish Water – Notwithstanding Condition 1, Prior to the commencement of
development, the developer shall submit written evidence to the Planning Authority that an
agreement with Scottish Water is in place for the connection of the proposed development
to the public water supply and wastewater sewage network. 
Reason: In the interests of public health and to ensure the availability of an adequate water
supply to serve the proposed development. 
Page 81

Page 82

3.  Sustainable Urban Drainage – Notwithstanding Condition 1, details of a sustainable
urban drainage system compliant with the guidance set out in CIRIA’s SuDS Manual C753
must be submitted to and approved in writing by the planning authority prior to the
commencement of development. The surface water drainage shall be operational prior to
the development being brought into use and shall be maintained as such thereafter. 
Reason: To ensure adequate surface water drainage is implemented to prevent flooding
elsewhere. 
4. Landscape - Notwithstanding Condition 1, Prior to the commencement of development,
full details of both hard and soft landscape works to be carried out at the site shall be
submitted to and approved in writing by the local planning authority in the form of a detailed
landscaping plan. The approved hard landscaping works shall be carried out prior to first
occupation of the development and the soft landscaping works / replacement tree planting
within the first planting season following first occupation of the development. The details
submitted shall include: 
- details of the proposed hard surfacing (including proposed materials);
- details of proposed boundary treatments; 
- details of proposed soft landscaping;
- details of the replacement tree planting (location, size and species); 
- programme for completion and subsequent on-going maintenance. 
Reason: In the interests of biodiversity and the natural environment. 
5. Biodiversity Enhancement - Notwithstanding Condition 1, Prior to the commencement of
development, a revised biodiversity statement based on the Preliminary Ecological
Assessment table 6  shall be submitted to and approved in writing by the Planning
Authority. The statement shall demonstrate how the proposal will contribute to
conservation/restoration/enhancement of biodiversity, and how these benefits will be
implemented and maintained for the lifetime of the development. 
All physical biodiversity enhancement measures (bird nesting boxes, ‘swift bricks’, wildlife
ponds, bat and insect boxes, hedgehog homes etc) as set out in the Preliminary Ecological
Assessment table 6 and also include the retention of any felled native species as deadwood
shall be implemented in full before the development hereby approved is first brought into
use. 
All biodiversity enhancement measures consisting of new or enhanced planting shall be
undertaken either in accordance with the approved scheme of implementation or within the
next available planting season following the development first being brought into use. 
Reason: To comply with the requirements of NPF4 Policy 3 and the recommendations of
the council biodiversity officer. 
6. Trees – Notwithstanding Condition 1, Prior to the commencement of development, a tree
protection plan shall be submitted to and approved in writing by the authority. Thereafter,
all retained trees on site shall be protected at all times during construction in accordance
with the British Standard; BS 5837:2012 (Trees in relation to design, demolition and
construction – Recommendations). 
Reason: The landscape features to be protected are important to the appearance and
character of the site and the surrounding area and are required to successfully integrate
the proposal with its surroundings. 
7. Pre-works checks - Notwithstanding Condition 1, Prior to the commencement of
development, pre-works checks for the presence of bats, breeding birds, hibernating
Page 82

Page 83

hedgehogs and amphibians on site; shall be carried out by an appropriately qualified
person. In circumstances where species of interest are identified as being present, or at
risk from construction works, a statement shall be submitted to and approved by the
authority in writing to provide suggested avoidance and or mitigation measures, including
timing constraints, to address such presence or risk. 
Reason: In order to establish that the circumstances of the site have not changed
significantly between approval and implementation of the development for the purpose of
protecting natural heritage assets in the interest of nature conservation. 
8. Invasive Non-Native Species Eradication Plan - Notwithstanding Condition 1, Prior to
the commencement of development, a non-native species eradication plan (in accordance
with the ‘Code of Practice with regard to non-native species;  
http://www.scotland.gov.uk/Publications/2012/08/7367/0’) for the non-native species
present on site shall be submitted to and approved in writing by the authority. 
Reason: In the interest of nature conservation. 
9. External Materials - Notwithstanding Condition 1, Prior to the commencement of
development, samples of the proposed materials to be used for the external finishes of the
development hereby approved shall be submitted to and approved in writing by the
Planning Authority. 
Reason: In the interests of visual amenity and in order to integrate the proposal with its
surroundings. 
10. Sustainable Design – Notwithstanding Condition 1, Prior to the commencement of
development, details of the on-site micro renewable energy to provide heat or
electricity to the property and details of the use of the final materials – including
details of any re-cycled materials or local sourced materials and their embodied
energy for each materials, shall first be submitted and approved in writing by the
Local Planning Authority. Thereafter the approved micro renewables and materials
must be used in the development hereby approved. 
Reason: In order to ensure compliance with LDP2 Policy 09 and to ensure the
building is being as energy efficient as possible in order to respond to climate change. 
11. Quality homes – Notwithstanding Condition 1, Prior to the commencement of
development, details of the proposed timescale for completion of the approved
development have been submitted to and approved by the Planning Authority. Thereafter,
the development shall be implemented in accordance with the duly approved timescale for
completion unless an alternative timescale for completion is otherwise agreed in writing
with the Planning Authority. 
Reason: In order to comply with the requirements of NPF4 Policy 16F. 
12. Potential sources of nuisance – Notwithstanding Condition 1, Prior to the
commencement of development, identification and assessment of all potential sources of
nuisance, including noise/ vibration, dust, and any temporary lighting provided, which may
cause disturbance to nearby residents during the demolition / construction process shall
be undertaken by the applicant. This should include consideration of intended hours of
operation, movement of vehicles, use of plant and storage of equipment and materials on
site. 
For all potential sources of nuisance, the applicant will be required to provide a 
management plan with details of suitable control measures to be put in place so as to 
ensure that construction does not cause loss of amenity to local residents and/or 
statutory nuisance. The management plan must be submitted to and approved by the 
Planning Authority and thereafter complied with.
Page 83

Page 84

Reason: In order to avoid sources of nuisance in the interest of amenity. 
13. Parking and Turning – Notwithstanding Condition 1, The parking and turning area shall
be laid out in accordance with the details shown on the approved  drawing reference; 00-
003 REV. A prior to the development first being occupied and shall thereafter be maintained
clear of obstruction for the parking and manoeuvring of vehicles. 
Reason: In the interest of road safety. 
14. Junction with public road - Notwithstanding Condition 1, the proposed access shall be
formed in accordance with the Council’s Roads Standard Detail Drawing SD 08/005 Rev.
B (as laid out on approved drawing reference; 00-003 REV. A) incorporating vehicular
visibility splays of 75 x 2.4 x 1.05 metres measured from the edge of the carriageway and
pedestrian visibility splays of 2.4 m x 2.4 x 0.9 metres measured from the rear of the
footway. Thereafter the driveway shall be formed in accordance with the Council’s Roads
Standard Detail Drawing SD 08/002 Rev. B, providing a minimum driveway access width
of 5.5m for the first 10m, reducing to no less than 3.7m thereafter (3.5m where not bound
by walls). The access shall be surfaced with a bound material for the first 5m. Gradients of
the access drive must be no greater than 5% over the first 5.0m and thereafter must not
exceed 12.5%. Drainage shall be achieved within the boundary such that no water shall
discharge onto the public carriageway. Prior to the commencement of development the
access hereby approved shall be formed to at least base course standard and the visibility
splays shall be cleared of all obstructions such that nothing shall disrupt the required
visibility spays. The final wearing surface on the access shall be completed prior to the
development first being occupied and the visibility splays shall thereafter be maintained
clear of all obstructions in perpetuity. 
Reason: In the interests of road safety. 
Page 84

Page 85

ADDITIONAL NOTES TO APPLICANT 
• LDP2 Policy 34 - Electric Vehicle Charging states that for all new build houses with private
off street parking dedicated cable ducting connecting each private residential parking space
to the nearest electricity supply connection point capable of supporting the installation of a
7-kilowatt EV charging point shall be installed. This has since been superseded by a new
Building Regulations standard (ref 7.2 of Technical Handbook Jan 2025 edition) which
requires a minimum of one electric vehicle charge point socket with an output rating of not
less than 7 kW to be provided adjacent to the parking space. As it is controlled via Building
Standard then this has not been subject to a condition. 
• A roads opening permit (Section 56) must be obtained prior to any works on, or alongside
the existing adopted carriageway. 
• It is noted that no gates have been included within the application, if new access gates are
proposed these will likely require a further planning application. Furthermore, any access
gates would need to be sited at least 6 metres from the edge of the carriageway to allow an
entering vehicle to stop clear of the carriageway when the gates are closed. Any access
gates must be hung so that they do not open towards the carriageway. 
Page 85

Page 86

COMMITTEE REPORT
APPENDIX A – RELATIVE TO APPLICATION NUMBER:  25/00576/PP 
PLANNING LAND USE AND POLICY ASSESSMENT 
1. Settlement Strategy 
1.1. The site is located within the settlement area of Rhu as identified in the adopted Argyll and Bute
Local Development Plan (LDP2) wherein Policy 01 (Settlement Areas) notes that development
will normally be acceptable on a non-brownfield site where the proposal is considered
acceptable in relation to the overall land supply for the proposed use, and it is compatible with
surrounding uses including but not exclusively; providing access, service areas, infrastructure
for existing, proposed or potential future development, and it is of an appropriate scale and fit
for the size of settlement in which it is proposed; and respects the character and appearance of
the surrounding townscape in terms of density, scale, massing, design, external finishes and
access arrangements; and lastly that it complies with all relevant LDP2 policies. 
1.2. LDP2 Policy 66 (New Residential development on non–allocated housing sites within Settlement
Areas) requires that new buildings will only be permitted where: 
a) the layout, density, plot ratio, scale, form and materials of any proposed development do not
detract from the character of the surrounding buildings and the local area; 
b) it does not affect the privacy and amenity of existing and proposed properties; 
c) the site provides a suitable residential environment; 
d) it provides appropriate private and public open space and; 
e) an appropriate standard of access to and parking for vehicles associated with the
development is provided, it does not result in the loss of any existing parking spaces, and that
traffic generated as a result of the development is capable of being accommodated within the
capacity of the existing road network surrounding the development; 
f) it is not detrimental to the overall housing land supply of the LDP2. 
The proposals must also demonstrate that they meet the tests laid down in National Planning
Framework 4 Policy 16 (Quality homes) criterion f). 
1.3. NPF4 Policy 16 (f) supports new homes on land not allocated for housing where the proposal is
supported by an agreed timescale for build-out, it is otherwise consistent with the plan spatial
strategy and other relevant policies including local living and the proposal is for smaller scale
opportunity within an existing settlement. 
1.4. NPF4 Policy 1 (Tackling the climate and nature crises) requires that significant weight be given
the global climate and nature crises when considering new development. Policy 2 (Climate
mitigation and adaptation) seeks to encourage, promote and facilitate development that
minimises emissions and adapts to impacts on climate change. NPF 4 Policy 5 (Soils) aims to
protect locally, regionally, national and internationally valued soils. 
1.5. The development is considered small-scale as it for the erection of one dwelling. It is located
within an identified settlement with access to community facilities and public transport networks,
consistent with NPF 4 Policy 15 (Local Living and 20 minute Neighbourhoods), and is compatible
with the provisions of NPF 4 Policy 1 in terms of addressing the Climate Crisis in principle. The
site is located within an established residential area and will not impact upon soil that has
material value. It is recommended that any planning permission will be subject to a model
planning condition. 
1.6. On the above basis, it is considered that there is a general presumption in favour of the principle
of this proposed development in terms of its location, nature and scale when assessed against
the policy provisions relating to the LDP2 and relevant NPF4 Policies. 
Page 86

Page 87

2. Location, Nature and Design of Proposed Development 
2.1. The application site measures approximately 3254sqm and is bounded to the North by the
existing access to neighbouring Lagarie House, to the East by the boundary of Lagarie Lodge,
to the West by the boundary of Lagarie House and to the South by an existing stone wall that
separates the site from the A814. It is proposed to create the access to the site through this
stone wall which is considered to be listed by way of curtilage listing relative to Lagarie House
(category B listed), there is a extant listed building consent for the alterations to this wall
(reference; 23/01503/LIB). There is an established belt of trees and large shrubs along the
South, East and West site boundaries separating it from the grounds of Lagarie House and the
A814. To the Southern boundary of the site and also extending up the Western boundary there
is a large rhododendron hedge. The site slopes gently upwards from South to North. 
2.2. The application site formerly formed part of Lagarie House’s curtilage and was part of the main
House’s lawn. Lagarie House was however, subdivided into flats historically and its curtilage
was divided into plots. 5no. Dwellinghouses have subsequently been built to the North-West
and West of the Lagarie House as well as Lagarie Lodge which was built to the East. This plot
is located in between Lagarie House, the original main house and Lagarie Lodge (an infill house
built in the mid-1900’s) and has been separated visually from the main house by vegetation. It
is therefore not considered that the site forms part of the curtilage of Lagarie House. 
2.3. The proposed house is to be sited centrally within the plot from West to East and from South to
North it is to be sited such that the front elevation is in line with the front elevation of both Lagarie
House and Lagarie Lodge. The proposed access from the A814 will be formed through the
existing stone wall on the Southern boundary and will be located centrally on this boundary, with
driveway extending to the West of the of the proposed house and to the rear where a turning
area and parking for 3no. vehicles is proposed. The proposed dwellinghouse will have 2
bedrooms with a footprint of approximately 160sqm, a maximum eaves height of 2.5 metres and
a maximum ridge height of approximately 5 metres. The proposed house is traditional in
massing but utilises contemporary design materials and detailing which complements the
architectural character of the surrounding area. The proposed house uses single storey massing
which is in keeping with the adjacent Lagarie Lodge. The massing of the proposed house is
made up of 2 intersecting gable forms with the projecting gable element to the principal ‘street
facing’ elevation being mainly glazed to emphasis this principal elevation a central chimney is
also proposed which will provide an attractive roofscape. A contemporary pallet of materials is
proposed to respect and enhance the characteristics of the surrounding properties and wider
conservation area. This will include; slate roof, dark grey polyester powder coated aluminium
facias and rain water goods, off-white wet dash render, beige-grey polyester powder coated
aluminium windows and doors and lastly a vertical western red cedar cladding to the inset porch.
There would also be integrated photo voltaic panels installed to the south facing roof slopes. 
2.4. It is noted that a revised house design was submitted during the determination process. Further
details and reasoning behind this will be proved in section 4 below. 
2.5. NPF4 Policy 14 (Design, quality and place) requires that development proposals be designed
to improve the quality of an area; and, offers support to development that achieve the six
qualities of Health; Pleasant; Connected; Distinctive; Sustainable; and, Adaptable. Development
that is poorly designed, detrimental to the amenities of surrounding areas or inconsistent with
the aforementioned six qualities will not be supported. 
2.6. NPF4 Policy 14 is closely aligned with the provisions of LDP2 Policy 04 (Sustainable
Development) which requires that developers to demonstrate certain sustainable development
principles and also Policy 05 (Design and Placemaking) which requires developers to comply
with certain placemaking criteria including; compatibility with surrounding land uses, make use
of existing infrastructure, respect site topography, improve connectivity, incorporate green and
blue infrastructure, adopting design that respects and complements its surroundings, siting and
design should respond to the natural environment and the design should be sustainable in terms
of materials and construction and should consider future adaptability, and climate change
mitigation measures.
Page 87

Page 88

2.7. LDP2 Policy 08 (Sustainable Siting) requires that development integrates into the landscape or
existing built form to minimise detrimental effects on the environment, and the siting of a
development should take into account the character of the area in terms of its settlement pattern,
layout and density; development should be carefully sited to avoid overshadowing or
overlooking of itself or other properties; development should be positioned within the landscape
to make the best use of solar gain, natural ventilation and shelter from the elements;,
development should be sited within easy access of existing infrastructure and services; and any
ancillary development such as parking and turning areas, should be sensitively designed and
sited. LDP2 Policy 09 (Sustainable Design) requires that development proposals demonstrate
consideration of renewable energy and sustainable design & construction methods. LDP2 Policy
10 (Design: All Development) requires demonstration of an appropriate response to the
development site and wider context, acknowledgement of the scale / massing of nearby
buildings and use materials that are harmonious with the context. 
2.8. Having regard to the built development pattern and densities of the local area, it is noted that
there is a range of scale and design of houses, and whilst the overall pattern of built development
is very spacious, there is a range of plot ratios. The ratio of built development to open curtilage
in the case of this proposal is spacious in nature and reflects the plot ratio of the adjacent Lagarie
Lodge. The scale of the house is comparably small, and it is considered that the siting, form,
massing and material finishes will respect and reflect the existing character of the built
environment and compliment the visual character of the area in accordance with the relevant
provisions of NPF4 and LDP2. 
2.9. The proposed house will be screened from Lagarie House and Lagarie Lodge by existing natural
boundary features and the planting of additional trees to the North will screen the proposals
including the rear car parking area from Lagarie cottage, in conjunction with the proposed
orientation of windows and separation distances will mean that there will be no material loss of
residential amenity to the occupiers of these properties by reason of overlooking. It is also
considered that the proposed siting and scale of the proposals there will be no negative effects
on the daylight / sunlight to neighbouring properties arising from the development. On this basis,
Officers area satisfied that the proposed development will not have a material impact upon the
residential amenities of nearby properties in accordance with the relevant provisions of NPF4
and LDP2. 
2.10. In relation to sustainability, the application has included the submission of the Sustainability
Checklist and the Sustainable Buildings Checklist in response to LDP2 Policy 09. The
application responds to the sustainability criteria as follows: 
• The site is located in accordance with the LDP2 settlement and spatial strategy;
• It is well connected in terms of active travel and public transport routes;
• It avoids high quality agricultural land and does not raise issues of flood risk or land erosion;
• It maintains the quality of the historic environment;
• Proposed siting has minimised groundworks including excavation and fill;
• The house is designed to be adaptable for future needs and is all on one level; 
• The house is designed to have integrated photo voltaic panels to the south facing roof slopes; 
• The house is designed internally to have main habitable rooms in the elevations which benefit
from maximum daylighting and solar gain. 
2.11. As such, with regard to sustainable principles, it is accepted that the application is sustainably
located. Whilst some principles of sustainable design and construction methods are not clearly
set out, it is considered that further information can be obtained via condition (in this instance)
to demonstrate clearly how sustainable principles are being incorporated into the design. 
3. Natural Environment 
3.1. NPF4 Policy 3 (Biodiversity) generally seeks to protect biodiversity, reverse biodiversity loss and
to deliver positive benefits from development that strengthens nature networks. Policy 3(c)
requires that proposals for local development will include appropriate biodiversity measures
Page 88

Page 89

proportionate to the scale and nature of the proposal. Policy 3(d) requires any potential adverse
impacts on biodiversity/nature networks/natural environment to be minimised by planning and
design. NPF 4 Policy 3 is generally aligned with LDP2 Policy 73 (Development Impact on
Habitats, Species and Biodiversity), although NPF4 Policy 3(c) goes beyond the LDP2
requirements in relation to current biodiversity interests of the site. 
3.2. NPF4 Policy 4 (Natural places) generally confirms that development that will have an
unacceptable impact on the natural environment will not be supported. Outside of European,
national and local designations, development is expected to meet the relevant statutory tests in
terms of protected species legislation; and potential impacts must be fully considered prior to
determination of planning applications. NPF4 Policy 4 (insofar as it relates to the location, nature
and scale of the current proposal) largely aligns with the provisions of LDP2 Policy 73. 
3.3. LDP2 Policy 04 seeks to conserve and enhance the natural and built environment and avoid
significant adverse impacts on biodiversity, natural and heritage assets. LDP2 Policy 73 ensures
that other legislation relating to biodiversity habitats are fully considered in relation to
development proposals; and generally, that development does not have an adverse impact on
habitat or species, particularly in relation to habitat or species designated as being of European,
national or local significance. 
3.4. The site is not located within or in proximity to any nature conservation designation. 
3.5. The Council’s Local Biodiversity Officer has been consulted on the proposals and requested
additional information (prior to determination) by way of; European protected species surveys
for bats & otter and a tree survey (including the bio-diversity value of individual trees). The
applicants have subsequently provided a Bat Scoping Survey Report, a full Tree Survey and a
Preliminary Ecological Assessment. With regards to the potential presents of bats and otter, the
submitted Bat Scoping Survey Report concludes that ‘having regard to the distribution of
species, habitat, potential roost features, suitability and importance of any of these and signs of
bat activity the risk of bat roosts or bats being disturbed is negligible or low and roosting can
reasonably be ruled out.’ Furthermore, the submitted Preliminary Ecological Assessment also
concludes with regards to bats ‘No further survey is required unless plans for tree felling are
changed at which point a pre-felling check should be undertaken’ based on the forgoing with
regards to bats it is recommended a pre-felling check for the presents of bats is undertaken prior
to the felling of any trees. With regards to the potential presence of otter the council bio-diversity
officers second consultation response notes that ‘A desk-study search shows there are no otters
within 5km of the site and no waterways are present on the site’. Furthermore, the submitted
Preliminary Ecological Assessment also concludes with regards to otter ‘No evidence of otters
was recorded, the Site is not suitable for otters either lying up or moving through territory, and
this species is not considered to be an issue.’ Based on the forgoing with regards to otter it is
considered that no further surveys are required.. With regards to trees this will be accessed
under section 5 below. 
3.6. The Council’s Local Biodiversity Officer also initially recommended that further protected
species surveys and proposed bio-diversity enhancement measures are conditioned as part of
any approval, however, they have updated their response in light of the submitted Preliminary
Ecological Assessment and provided a third consultation response. Within this they have
provided subsequent recommendations which are summarised as follows; that vegetation
clearance and tree felling are to be undertaken outwith the breeding bird season, pre-works
checks for bats, breeding birds (if it is not possible to clear outwith breeding bird season),
hedgehogs and amphibians are carried out prior to vegetation clearance and tree felling, a
programme for the eradication of INNS Rhododendron ponticum is submitted, that any felled
native species trees should be retained as deadwood, that the biodiversity enhancement
measures identified within the PEA report should be are followed and that a programme of tree
planting should be submitted to include species which must be native and appropriate to the
locality of the area including a schedule of monitoring and maintenance until such a time as the
trees become established. It is therefore recommended that appropriate planning conditions be
added to any approval covering the aforementioned. 
Page 89

Page 90

3.7. It is further recommended that any planning permission be subject to a condition requiring the
submission of a detailed scheme of landscaping including; hard and soft landscaping as well as
boundary treatments is submitted to and approved by the authority prior to works starting on
site. 
3.8. Based on the above and subject to appropriate planning conditions it is considered that the
proposals will have no adverse effect on a European Protected Species and meets the
requirements of LDP2 Policy 73. 
4. Built / Historic Environment 
4.1. The application site forms part of the original grounds of a Category B listed building, “Lagarie
House.” Additionally, within the vicinity is Category A listed “Ardencaple Hotel” which is adjacent
to Lagarie Lodge on the opposite side of Torwoodhill Road. 
4.2. The site is located within the Rhu Conservation Area. 
4.3. NPF4 Policy 7 (Historic assets and places) generally seeks to protect and enhance the historic
environment, assets and places, and to enable positive change as a catalyst for the regeneration
of places. 
4.4. NPF4 Policy 7(a) requires that development proposals with a potentially significant impact on
historic assets or places be accompanied by an assessment based on an understanding of the
cultural significance of the asset and/or place. Development will only be supported where the
character and appearance of the conservation area is preserved or enhanced. It is noted that
officers are satisfied that the proposals have met the policy requirements of NPF4 Policy 7(a)
and have submitted a further assessment in May 2025 which provides an assessment
demonstrating the acceptability of design as per the requirements of NPF 4 Policy 7. 
4.5. NPF4 Policy 7(c) requires that development proposals affecting the setting of a listed building
preserve its character, and its special architectural or historic interest. LDP2 Policy 16 (Listed
Buildings) add to this that that development must be of the highest quality, and respect the
original structure in terms of setting, scale, design, materials and proposed use. 
4.6. NPF4 Policy 7(d) requires that development proposals in a conservation area will only be
supported when the character or appearance of the conservation area is preserved or
enhanced. Relevant considerations include the architectural and historic character of the area;
existing density, built form and layout; context and siting, quality of design and suitable materials.
LDP2 Policy 17 (Conservation Areas) broadly reflects this. 
4.7. The Council’s Design and Conservation Officer was consulted on the initial proposals and
summarised; ‘…the principle of development on the site has been accepted through the
approval of 23/01502/PP, which remains extant. 25/00576/PP puts forward a revised design,
being small scale and single storey. The front façade remains in line with those of Lagarie House
and Lagarie Lodge. The elevations appear to be erroneously named as, from the plan, the
elevation marked “south-east” would face the road (to the south, south-west). The design of this
elevation with its square full height glazing, does not appear to fit particularly harmoniously with
either Lagarie House or Lagarie Lodge. It would perhaps be more appropriate to rotate the
design 90 degrees counter-clockwise to allow some of the more traditional elements of the
design to face the road.’ Subsequently discussions were had with the applicants to address the
concerns raised by the council Design and Conservation Officer and a revised house design
was submitted. The design amendments, alter the massing and proportions of the proposed
house to allow for a street facing elevation which appears to be more formal and gives the
appearance of a principal elevation as opposed to the previous design, the from is still of two
gable elements, however as opposed to have the two gable elements of differing ridge heights
in parallel to each other, they are now proposed to bi-sect and the two ridge heights are equal
which pulls up the ridge height to similar proportions as the neighbouring property Lagarie
Page 90

Page 91

Lodge. The footprint has also increased slightly by 25sqm and has moved slightly closer to the
West as to omit any possible privacy issues with Lagarie Lodge. The materials pallet has also
been updated to take queues from the surrounding built environment. The councils Design and
Conservation Officer has been re-consulted on the design amendments and has noted ‘The
design currently being assessed under 25/00576/PP has been revised, with changes made to
the scale, materials and design. The proposal now includes beige-grey windows (RAL 7006) as
well as off-white wet dash render and red cedar cladding, introducing potentially too many
confusing elements with insufficient cognisance of the architectural character of the immediate
context. Additionally, the proposed roof design is unclear as, while the elevations show the
whole roof to be one height, this is not what is shown on the roof plan – this shows the side roofs
meeting the main roof at a point approx. 1/6 of the distance from ridge to eaves, which would
alter the elevations…. A Planning Statement has been submitted however this does not include
analysis of the site within the conservation area and setting of listed Lagarie House, and how
the design has developed within this regard….’. with regards to the Design and Conservation
Officer’s updated comments officers would note that the applicants have submitted an updated
roof plan which ties in with the submitted elevations, with regards to the proposed materials; the
off-white wet dash render is intended to match the existing style of surrounding properties, the
slate roof will also match neighbouring properties, the dark grey rainwater goods and fascias
are to tie in with the slate roof, the beige-grey windows and doors draw inspiration from
neighbouring Lagarie House’s feature sandstone which is a similar colour and the inset western
red cedar porch is to add an element of interest to the principal elevation which draws inspiration
from the painted woodwork on Lagarie House. It is recommended that a planning condition will
be added to any approval requiring the submission and approval of all external materials
samples prior to works commencing on site to ensure these are appropriate when viewed as a
whole. Lastly the councils Design and Conservation Officer notes concern that a further
assessment with regards to NPF4 Policy 7 has not been included within the Planning Supporting
Statement. Officers can confirm that the applicants submitted a separate further assessment as
noted within section (G) of this report above. 
4.8. Officers are satisfied that the proposed development, by reason of siting, scale, form and
architectural style is of a sufficiently high standard and will preserve the character and
appearance of this part of the Rhu Conservation Area and will not have an adverse impact on
character of surrounding listed properties in accordance with NPF 4 Policy 7, LDP2 Policy 16,
LDP2 Policy 17 and relevant HES guidance on development impact on historic assets. 
5. Impact on Trees 
5.1. The site was formerly part of Lagarie House’s lawn, however the land surrounding Lagarie
House has been subdivided and is now in separate ownership. There is an established natural
belt of trees and large shrubs along the South, East and West site boundaries separating it from
the grounds of Lagarie House, Lagarie Lodge and the A814. To the Southern boundary of the
site and also extending up the Western boundary there is a large rhododendron hedge. 
5.2. A tree survey has been undertaken of the site and its surrounds as summarised earlier in the
report. It is proposed to remove the large rhododendron hedge and 8no. Trees to enable this
development (as shown on the Existing Block Plan), these are mainly located to the area where
the new access and driveway area are proposed. It is noted that the site is covered by an Area
TPO which was established on the 23.08.1983. Trees planted after this date would not be
covered by this TPO, however, as the site is also within a conservation area all existing trees
(with a trunk diameter over 75mm measured at 1.5m in height above ground) are automatically
protected. The Tree Survey Report submitted as part of this application has categorises the
trees to be removed as; one category B tree (an Oak), 6 category C trees (a Wild Cherry, an
Oak, two Elm trees and two Holly trees) and one category U tree (a Rowan tree). Please note
that category B trees are considered to be; trees of moderate quality, category C trees are
considered to be; trees of low quality and category U trees are considered to be trees unsuitable
for retention. Trees will remain along the east and west boundaries to maintain the privacy of
neighbouring properties, as side from 3no. Trees which will be removed on the west boundary.
Page 91

Page 92

Indicative replacement planting has been indicated on the proposed block plan to the Northern
boundary, however, a detailed planning condition is recommended which will require details of
the proposed compensatory tree planting to be submitted to and approved by the authority prior
to works commencing. Lastly it is proposed to fully remove the substantial rhododendron hedge
as this is a non-native invasive species this is considered acceptable and a planning condition
is recommended to ensure that this non-native invasive species is eradicated according to best
practice guidelines. 
5.3. NPF4 Policy 6 requires the retention of any individual trees of high biodiversity value or veteran
trees. In this instance, the survey found that no ancient or veteran trees are present on or around
the site. In other respects, with regards to the biodiversity value of trees within the site, it is noted
that the councils biodiversity officer initially requested that the biodiversity value of all trees within
the site was recorded, however, we have subsequently received a Preliminary Ecological
Assessment which concludes that the woodland within the site is considered to be of a moderate
bio-diversity value. It is also noted that all trees to be removed are located within or in close
proximity to the rhododendron hedge, the present of which is considered to negatively affect the
biodiversity value of these trees. Therefore it is not considered that the individual trees to be
removed are of high biodiversity value and that removal of the trees proposed will have an
adverse impact on the ecological condition of the area, based on the Preliminary Ecological
Assessment, Tree Survey Report and Officers inspection of the site, this is further supported by
the additional planting of additional native species trees, to be secured by condition. It is also
noted that the council’s biodiversity officer has recommended that any felled native species
should be retained as deadwood to further enhance the biodiversity of the site, it is confirmed
that a planning condition will be recommended requiring this. 
5.4. It is recommended that any planning permission be subject to a condition requiring the
submission of a tree protection plan and that all retained trees on site are protected during
construction in accordance with the British Standard; BS 5837:2012 (Trees in relation to design,
demolition and construction – Recommendations). 
5.5. On the above basis it is considered that the proposal is in accordance with the provisions of
NPF4 Policy 6 (Forestry, woodland and trees) and LDP2 Policy 77 (Forestry, Woodland and
Trees). 
6. Road Network, Parking and Associated Transport Matters. 
6.1. Access to the site is proposed directly from the A814. It is proposed to create the access to the
site through the existing stone wall which bounds the frontage of the site, the new access will
be located centrally on this frontage. The existing stone wall is considered to be listed by way
of curtilage listing relative to Lagarie House (category B listed) and there is an extant listed
building consent for the alterations to this wall (reference; 23/01503/LIB). 
6.2. From the access junction a private driveway will continue approximately 60m into the application
site to a parking and turning area laid out to the rear of the proposed house. Three car parking
spaces are identified on the application drawings as well as the location for the proposed waste
storage facilities. 
6.3. NPF4 Policy 13 (Sustainable transport) generally aims to encourage, promote and facilitate
developments that prioritise alternative means of transport to car journeys and reduce the need
to travel unsustainably. The requirement to submit a Transport Assessment is introduced for
some developments however this relates to larger scale developments than the current proposal
for a single house, this policy is largely aligned with LDP2 Policy 33 (Public Transport
Infrastructure). 
6.4. The elements of NPF 4 Policy 13 that are relative to the scale and nature of this development
are largely aligned with the provisions of LDP2 polices 36 (New Private Accesses) & 39
(Construction Standards for Private Access), which relate to new private accesses and
construction standards for private access. 
Page 92

Page 93

6.5. The consultation response from Council Area Roads notes that roads have no objection to the
proposed, subject to any approval being subject of planning conditions relating to; access
detailing (As per standard detail SD08/002 Rev.B), gradients, surfacing, visibility splays, parking
& turning, drainage and any gates. 
6.6. The submitted site layout drawing shows 3 no. car parking spaces and adequate turning space
and notes; New access, visibility splays and wall to be as per previous approval ref;
23/01502/PP. 
6.7. On the above basis and subject to the recommended roads conditions it is considered that the
proposal is in accordance with the provisions of NPF4 Policy 13 and LDP2 Policies 36 & 39. 
7. Infrastructure 
7.1. Water supply and foul drainage is proposed to be by means of a connection to the existing
Scottish Water network. The consultation response from Scottish Water does not indicate any
issues with this but advises that further investigations may be required to be carried out once a
formal application has been submitted to them. Scottish water has also noted that the applicants
are required to submit a wastewater application to allow Scottish Water to fully appraise the
proposals. On this basis, officers are satisfied in principle that there are no known constraints in
respect of public water and sewage infrastructure. 
7.2. The consultation response from Scottish Water specifically advises that a surface water
connection into its combined drainage system will not be accepted. Therefore, any approval will
be subject to a planning condition that the development incorporate a Sustainable Urban
Drainage System (SuDS). SuDS to be designed and installed in accordance with the principles
of the SuDS Manual (C753). 
7.3. In terms of potential flood risk, the application site, is not overlain by any recorded areas at risk
to coastal, fluvial or surface water flooding with reference to the SEPA Flood Map. 
7.4. It is further recommended that the provision of electric vehicle charge points, as per LDP2 Policy
34 (Electric Vehicle Charging), is subject of an informative given the new Building Standards
regulations introduced after the publication of the LDP. 
7.5. Subject to the above, it is considered that the proposal makes adequate provision for services
infrastructure in accordance with the provisions of NPF4 Policies 18 (Infrastructure first), 20
(Blue and green infrastructure) & 22 (Flood risk and water management) and LDP2 Polices 06
(Green and Blue Infrastructure), 33 (Public Transport Infrastructure), 34 (Electric Vehicle
Charging) & 61 (Sustainable Drainage Systems). 
8. Planning history 
8.1. The application site was formerly part of the garden ground of B listed Lagarie House. Lagarie
House is dated 1901 and was designed by the noteworthy architect A N Paterson and is a 2
storey plus attic asymmetrical Arts and Crafts house. The property was a private residence until
operating as a children’s home from 1949 until 1982. From researching historical maps it
appears that Lagarie Lodge was built in the 1950’s. Lagarie House was initially listed in 1980 as
a category C listed property however, since then the category of listing has been uplifted to
category B. In 1983 planning consent was given for the change of use and sub-division of the
property to form 4 flats. At this time planning permission was also given for the erection of 5
additional dwelling houses within the garden ground to the North-West & West of Lagarie House
(application references; C6986 & C6994). 
8.2. In 1989 there was an outline planning application for the erection of a detached 2 storey
dwellinghouse with integral double garage on this application site (application reference;
C8400). This application was refused and the decision was subsequently appealed. This appeal
was dismissed in 1990 (appeal reference; P/PPA/SH/137). 
Page 93

Page 94

8.3. There was a planning application for the site (reference; 11/00528/PP) submitted in 2011 by a
different applicant for the erection of 5 flats and car ports, this application was withdrawn prior
to determination. 
8.4. There was a planning application for 2 houses with detached garages and a proposed access
from Torwoodhill Road in 2019 (reference; 19/02162/PP). This application was withdrawn prior
to determination due to concerns raised by the roads department in terms of the proposed
access and also concerns raised by officers in regards to the proposal for 2 houses being
overdevelopment of the site / not appropriate in terms of the settlement pattern in the area. 
8.5. In 2020 there was a further planning application (reference; 20/01382/PP) for a single dwelling
with proposed access from the A814. At this time an accompanying listed building consent
application was also submitted in relation to the formation of the vehicular access through the
listed wall (reference; 20/01383/LIB). At this time officers had concerns in regards to the design
and scale of the proposal in terms of its relationship to the site and surrounding residential area.
This application along with the listed building consent application was withdrawn prior to
determination. 
8.6. In 2023 a planning application (reference; 23/01502/PP) for a single dwelling with proposed
access from the A814 was submitted along with an accompanying listed building consent
application in relation to the formation of the vehicular access through the listed wall (reference;
20/01383/LIB). These applications were both approved on the 23rd of May 2024 and remain
extant consents.   
8.7. It is noted that the planning history of the site is a material planning consideration, which has
been taken into consideration and afforded weight in determining this application. In the case of
the previous refusal, appeal and subsequent dismissal for outline planning permission for a
single dwelling on the site, which has been noted by objectors. Officers have considered this
and for the avoidance of doubt it is confirmed that the existence of a previous appeal decision,
refusing planning permission, does not preclude a future planning application being submitted,
nor does it prevent the Council as planning authority from determining the application. In the
instance of this application a substantial period of time has elapsed since the appeal decision;
within this time the relevant development plan and other relevant policy considerations have
been superseded by subsequent iterations of the Local Development Plan and National Policy
and Guidance and accordingly it is necessary for any decision on the current application to be
assessed against these revised provisions and in relation to the current circumstances of the
site and its surrounds. It is also confirmed that the approval for a single dwelling (reference;
23/01502/PP) in May 2024 on this application site accepts the principle of development for a
single dwelling on this site. 
8.8. On the basis of the above it is confirmed that having regard to all material considerations it is
considered that the proposal is acceptable. 
Page 94

Page 95

© Crown Copyright and database right 2025
All rights reserved. OS license (customer) account number AC0000849384
Location Plan Relative to: 25/00576/PP
O
0 25 5012.5 Meters
Application Site
Page 95

Page 96

This page is intentionally left blank

Page 97

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Argyll and Bute Council
Development & Economic Growth   
Planning Application Report and Report of Handling as required by Schedule 2 of the
Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013 relative to applications for Planning Permission or Planning
Permission in Principle 
Reference No: 25/01248/PP
Planning Hierarchy: Local Development
Applicant: Mr Gaetano Grieve
Proposal: Erection of 4 dwellinghouses, installation of sewage treatment
plants and formation of 2 vehicular accesses
Site Address:  Land West of Komani Aros Mains, Aros, Isle of Mull    
DECISION ROUTE 
☐Delegated - Sect 43 (A) of the Town and Country Planning (Scotland) Act 1997 
☒Committee - Local Government Scotland Act 1973 
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission
• Erection of four dwellinghouses 
• Installation of private drainage systems
• Formation of two vehicular accesses 
(ii) Other specified operations
• Connection to public water supply 
(B) RECOMMENDATION: 
It is recommended that planning permission be granted subject to the conditions and
reasons appended to this report. 
(C) CONSULTATIONS:   
Argyll and Bute Council – Area Roads Authority
Report dated 03.11.2025 advising of no objections to the application subject to
conditions relating to the formation of the accesses at the junction with the public
road; the clearance and maintenance of visibility splays; the provision of a system of
surface water drainage; the provision of parking and turning areas; the culverting of
the roadside ditches at the site accesses; the provision of bin storage areas; and the
provision of proportionate improvements to the public approach road to include the
provision of an additional passing place and the levelling of the road verges to create
a level step off for pedestrians. 
Page 97 Agenda Item 6

Page 98

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Scottish Water
Letter dated 06.08.2025 advising of no objection to the application and confirming
that the proposed development is within the Tobermory Water Treatment Works
catchment. Scottish Water further advised that there is no public waste water
infrastructure within the vicinity of the proposed development and therefore private
arrangements will be required. 
The above represents a summary of the issues raised. Full details of the consultation
responses are available to view via the Public Access section of the Council’s
website. 
(D) HISTORY:   
24/01849/PP
Erection of 6 dwellinghouses, installation of sewage treatment plants and formation
of 2 vehicular accesses
Withdrawn on 15.07.2025 
(E) PUBLICITY:   
The proposal has been advertised in terms of Regulation 20 and Neighbour
Notification procedures, overall closing date 28.08.2025. 
(F) REPRESENTATIONS:   
(i) Representations received from: 
27 objections, 1 representation and 2 expressions of support have been
received to the application. 
OBJECTIONS 
Mr Hugh Andrew, Keepers Cottage, Aros, Isle of Mull, PA72 6JP (07.08.2025)
David Hartley (07.08.2025)
Dr Lesley Graham, Keepers Cottage, Aros, Isle of Mull, PA72 6JP (12.08.2025)
Ms Celia Thomson, 19 Garden House Drive, Acomb, Hexham, NE46 4RZ
(13.08.2025)
Mrs Abigail Macleod, Riverside House, Aros, Isle of Mull, PA72 6JP (13.08.2025)
Mr Alistair Cameron, Glenaros Lodge, Aros, Isle of Mull, PA72 6JP (13.08.2025)
Mrs Fae Cameron, Glenaros Lodge, Aros, Isle of Mull, PA72 6JP (13.08.2025)
Prof. Mauvis Gore, Komani, Aros Mains, Aros, Isle of Mull, PA72 6JP – by email only
(14.08.2025)
Dr Rupert Ormond, Komani, Aros Mains, Aros, Isle of Mull, PA72 6JP – by email
only (14.08.2025)
Mr James MacLennan, Seileasdair, Aros, Isle of Mull, PA72 6JP (15.08.2025)
Mr Richard Kellett, Main Cottage, Castle Steadings, Aros, Isle of Mull, PA72 6JP
(15.08.2025)
Mrs Maggie Thomson, Aros Mains House, Aros, Isle of Mull, PA72 6JP (15.08.2025)
Miss Evie Kellett, Main Cottage, Castle Steadings, Aros, Isle of Mull, PA72 6JP
(15.08.2025)
Page 98

Page 99

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Christina Thomson Jones, Grianan, Aros, Isle of Mull, PA72 6JP – by email only
(13.08.2025)
Mr Roderick Thomson, 11 Queens Walk, London, W5 1TP (17.08.2025)
Mrs Alison Spence, Bridges Cottage, Aros, Isle of Mull, PA72 6JP (17.08.2025)
Mrs Kirsten Bennett, Main Cottage, Castle Steadings, Aros, Isle of Mull, PA72 6JP
(17.08.2025)
Ms Leonora Thomson, 98 Taff Embankment, Cardiff, CF11 7BH (18.08.2025)
Mr Richard Pells, 13 Valley View, Liskeard, PL14 4QH (18.08.2025)
Ms Natasha Smailes, West Highland Cottage, Aros, Isle of Mull, PA72 6JP
(18.08.2025)
Mrs Caitlin MacLennan, Seileasdair, Aros, Isle of Mull, PA72 6JP (18.08.2025)
Mr Stuart Davidson, Riverside Cottage, Aros Bridge, Aros, Isle of Mull, PA72 6JP
(18.08.2025)
Mr Duncan Spence, Bridges Cottage, Aros, Isle of Mull, PA72 6JP (18.08.2025)
Mrs Linda Devlin, 2 Aros Mains, Isle of Mull, PA72 6JP – by email only (19.08.2025)
Harriet Smailes, West Highland Cottage, Aros Mains, PA72 6JP – by email only
(17.08.2025)
Nick Holmes, 2 Aros Mains, Isle of Mull, PA72 6JP (19.08.2025)
Ms Alison Holt, Heriot Cottage, Aros, Isle of Mull, PA72 6JP (20.08.2025) 
REPRESENTATIONS 
Oban & District Access Panel – by email only (18.08.2025) 
SUPPORT 
Mr Grant Holland, Toomeran Lodge, Lochbuie, Isle of Mull, PA62 6AA (25.08.2025)
Ms Juliet Knight, 25/3 Mentone Terrace, Edinburgh, EH9 2DF (27.08.2025) 
Representations are published in full on the planning application file and are
available to view via the Public Access section of the Council’s website. 
(ii) Summary of issues raised: 
OBJECTION 
Water supply and drainage 
• The ground to which this application relates sits on a number of private water
supplies. Existing private water supplies would be compromised. The
existing pipes are buried shallow and require to be accessed to resolve
blockages. If the pipes are disturbed during construction, water supplies
would be cut off. 
• The development references soakaways with further potential for permanent
impact on water supply and quality. 
• Local residents were requested to cut mains usage due to water shortages.
Has the applicant got any assurance that they would be accepted on to mains
water supply. 
• The proposed development is not near a public sewer and will therefore
require sewage treatment, from which the outflow will discharge into
soakaways. Properties located below the proposed development are
Page 99

Page 100

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
supplied by a spring located in proximity to the proposed development. The
proposal would breach SEPA’s guidance with regards to proximity to existing
springs supplying domestic water and to an existing watercourse. There is
concern that the quality of existing water supplies would be biologically
compromised, contrary to LDP2 Policy 60. 
• There is no guarantee that these properties can be attached to mains water.
If Scottish Water decline to supply the development, water will have to be
provided by a private supply. This would interfere with existing supplies. 
• The increased water and sewage runoff could harm the health and affect
wildlife at the river and the estuary. The effect on the estuary and its
significant and unique estuarine flora and fauna is unknown and potentially
disastrous. 
Officer Comment: The Council’s Building Standards Service will apply sufficient
control over the treatment plant arrangements at Building Warrant stage. The
proposed drainage system would be regulated under the building standards to
ensure that it is capable of being provided to a safe, effective and appropriate
technical standard. Any discharge to the water environment would be regulated by
SEPA under the Water Environment (Controlled Activities) (Scotland) Regulations
2011 (as amended). It is the responsibility of the installer and owner to ensure that
the drainage system is installed and maintained correctly. Pollution enforcement is
the responsibility of SEPA and as the proposed development is not located within a
Waste Water Drainage Consultation Area there is no reason to assume that a safe
and effective private wastewater system cannot be utilised. 
The rights of third parties to access the application site for purposes relating to the
existing private water supplies is a Civil Matter to be resolved between the affected
parties. 
The application indicates a connection to the public water supply. Scottish Water
have been consulted on the application and raised no objection to the application,
confirming that the proposed development is within the Tobermory Water Treatment
Works catchment. In the event that a public water supply connection cannot be
obtained an alternative private water supply would constitute a material amendment
requiring the submission of a further planning application. 
Visual impact 
• The building of tall structures on a rising bank at the top of another steep
bank is going to be unavoidably extremely prominent. Much is made of the
screening effect of the trees; this is on separate private ground and for half
the year it is bare and provides minimal screening. The benefit of the
screening cannot be relied upon for considering visual impact in the future.
The visual impact will be severe in winter months when the trees are without
leaves. 
• The road passage on the far side of the Aros Water and on to Tobermory is
one of the most used roads on the west coast of Scotland. The view across
the water to Aros Castle is one of the most iconic on the west coast. It is a
historic landscape, and visitors will now see a ribbon development along the
skyline. The development represents a very substantial intrusion into one of
the more famous and photographed views of the Hebrides. Plot 4 would be
Page 100

Page 101

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
particularly visible in what is an iconic view. The deterioration of the area
would impact upon the local tourist sector. The proposed development would
stand out against the skyline and would detract from the historically important
setting. 
• Given the small size of Aros Mains, the development would represent a
significant expansion of the settlement outside of the settlement boundary. A
smaller development, at the same level, consistent with the existing houses,
would be less visually obtrusive and more in keeping with the area. 
• LDP2 notes that most development should be within the settlements and not
within the countryside. The proposal does not represent infill, rounding off or
redevelopment. The development would be a new estate rather than being
in keeping with the existing area. 
• There is concern that the granting of the application would bring similar plans
that would provide the area with a ‘strip mall’ appearance. The proposed
development would extend into the open countryside. 
• LDP2 encourages appropriate development along the Dalmally-Oban-
Craignure-Tobermory corridor. However the applicant is interpreting this
policy incorrectly for development at any location along this route. This would
result in a strip of development along the whole of the north coast of Mull
between Craignure and Tobermory, adversely impacting upon the coastal
landscape of the area. 
• The size and location of the proposed development would be contrary to
LDP2 Policy 71. 
• The previously withdrawn application proposed to utilise more discreet facing
materials. 
• The proposed development would lead to overdevelopment. The
development would double the number of properties served by the access
and would bring a suburban style ribbon development. The development
would be out of scale and would alter the character of the area. Four large,
elevated houses would dominate the view. The development of four
properties with two access points is unreasonable when considered in the
context of the location and density of the existing dwellings. 
• There are no plans for landscaping. Any planting would need to be
maintained until it was able to manage on its own. The impact on local
character and landscape could be further reduced if there were areas of
planting of native shrubs and trees. 
• The visualisations submitted with the application are being used to mislead
and misrepresent the impact of the proposed development. 
Officer Comment: The application site is not covered by any specific environmental
or landscape designations. Notwithstanding this, the application has been submitted
with a Landscape and Visual Impact Assessment to assist in the assessment of the
likely significance of the effects of change resulting from the proposed development
upon the landscape, views and visual amenity. 
Page 101

Page 102

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The proposed development would be set towards the south of the site and would sit
no higher in the landscape than the adjacent properties to the east. There are a
number of substantial properties in proximity to the site, and the proposed
development would form a well-contained, distinct grouping, respecting the wider
plot densities. The ground to the north of the site continues to rise, which would
provide an appropriate backdrop to the proposed development. Whilst the
established trees are outwith the application site, they would provide a degree of
screening; it is acknowledged that the trees may be felled, however the proposed
development would remain backdropped and viewed in the context of existing,
established clusters of development. The settlement pattern of the wider area is
characterised by clusters of development, and the proposed development would
contribute to this. 
The proposed development has been reduced in scale since the submission of the
initial planning application relating to the site, which was withdrawn (our reference
24/01849/PP). This current application seeks to address the concerns raised
following the submission of the previous application, including the reduction of the
number of dwellinghouses from six to four, and amendments to the siting to ensure
that the proposal would not lead to a two-tiered development pattern. 
The proposed facing and roofing materials are considered appropriate to the context
of the site and would be similar in appearance to the facing and roofing materials of
the existing dwellings to the east. 
A scheme for boundary treatment, surface treatment and landscaping is to be
secured via planning condition, to include the submission of details any proposed
walls, fences and gates; surface treatment; and hard and soft landscaping works. 
Housing need 
• There is no evidence that the intention of the applicant is to develop
affordable housing. The specifications and size of the dwellings make it clear
that this is a development to be sold for high prices to maximise profit. What
guarantees will be given to ensure that the development is affordable, built
to the standards stated, and that it is not to maximise land value. 
• The proposal is for luxury houses that will, without regulation, most likely be
either second homes or holiday lets. Approval should be subject to a Section
75 Agreement requiring local occupancy by persons with an agreed local
connection, affordability safeguards, prohibition of short-term letting or
second home use without further consent, and delivery in accordance with
the submitted high quality design; this should be monitored and enforced.
Without such safeguards, the proposal risks undermining the housing
strategy of the island by adding to the stock of premium or recreational
housing rather than meeting identified community need. 
• The existing housing shortage is not for large houses but for affordable
accommodation and cheaper starter homes. The proposed houses are
unlikely to be affordable to those on low or moderate incomes. 
Officer Comment: The proposal the subject of this planning application seeks
consent for the erection of four dwellinghouse. It is important to ensure that new
housing developments meet the varied needs of all sectors of communities; the
number of dwellinghouses proposed would be of a small scale and the proposal
Page 102

Page 103

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
does not reach the threshold for the number of units required to contribute a
proportion of affordable housing. Whilst it is acknowledged that the future occupancy
or tenure of the dwellinghouses is unknown, the Council currently has no planning
policies that could control this and, in that regard, this is not considered a planning
issue of any overriding material significance. 
Neighbour notification 
• For an area like Argyll and Bute, the adoption of a 20-metre planning impact
radius means that those affected by a planning application are unlikely to be
made aware of a neighbouring proposed development. 
• The application did not appear to have been published anywhere. This is
unacceptable. 
Officer Comment: The Council is required to notify those with an interest in
“neighbouring land” of a planning application - this constitutes land within 20 metres
of the boundary of the land for which the development is proposed. Where such
neighbouring land consists of open fields, countryside or woodland with no obvious
premises on it, then an advert would be necessary; in this instance, the application
is advertised in the Oban Times under Regulation 20 procedures. 
Access 
• The road is not suitable for construction traffic or the increase in usage which
the proposed development would lead to on top of the existing housing. One
of the occupants along the road works in essential services and the road is
a vital link for medical services on the island. The increased traffic from
construction and occupation would delay emergency response times, risking
lives. The proposal does not show how safe access will be maintained nor
how increased traffic volumes can be safely managed.   
• The road is a narrow, single track with few passing places and has no
pavement. Vehicles have to reverse around corners to get to the nearest
passing places, which are not long enough or wide enough. The road is
regularly used by walkers and visitors to the historic Aros Castle. The
development would considerably increase traffic and the tight turn offs to the
development could be hazardous. 
• The proposed exit plans for Plot 3 and Plot 4 suggest that the land is owned
outright by the applicant; this is incorrect and misleading. 
• The use of the access road would lead to an increase in noise and exhaust
pollution. 
• Four properties are likely to generate around eight vehicles for the residents,
in addition to visitor vehicles and leisure vehicles. The information submitted
with the application does not detail the containment of run-off from the access
and parking areas.   
Officer Comment: The Council’s Roads Authority have been consulted on the
application and advised of no objections subject to conditions. Such conditions
include off site highway improvements to address the increase in vehicular traffic on
the public approach road that would result from the proposed development. An
Page 103

Page 104

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
appropriate condition will secure the provision of an additional passing place and
levelling off the roadside verges between the proposed site accesses and junction
of the UC79 with the A848 to create a level step off for pedestrians. 
Suitability and use of the site 
• The applicant states that the site is an agricultural field which is used for
grazing cattle and sheep; it has been used for grazing in recent times. One
of the current tenant farmers will be evicted. 
• The proposed development would aggravate the flooding issue affecting the
properties along the shore below Aros Mains. House plots are not permeable
and the development would occupy a significant area of land. Local flooding
will become more severe given the increasing rainfall expected with climate
change. Runoff from new hard surfaces would worsen the problem of
flooding on the stretch of road near Aros Mains, increasing ice hazards in
winter weather. 
• If soakaways and drains are unmaintained in the long term, there would be
an increased risk of flooding to the existing properties below the proposed
development. 
Officer Comment: The ceasing of the agricultural use of the land does not form a
material planning consideration. In terms of the land capability for agriculture, the
application site falls within Class 5.1 where the land is capable for use as improved
grassland. The proposed development would be of a small scale and would not
impact upon prime agricultural land, or land of lesser quality that is culturally or
locally important for primary use. 
The site for the proposed development is located outwith all flood extents as per the
SEPA Future Flood Maps. A suitable condition will secure the provision of
sustainable urban drainage systems to ensure that the proposed development would
effectively manage rain and surface water. Systems of surface water drainage are
required to prevent water passing onto the public road, and the provision of such
systems will be secured via planning condition. 
REPRESENTATION 
• The Panel advise that the site is an eminently suitable location for disabled
people who need ready access to medical and other essential services and
facilities. The Panel suggest that an overlay internal layout floorplan based
on Inclusive Design principles for one of the houses is provided. This would
enable disabled people to ascertain the prospects of adapting the layout on
disabled-friendly principles. 
Officer Comment: The agent has since provided a plan to show how the internal
layout of one of the proposed house types could be varied to provide accessibility. 
SUPPORT 
• The potential of new houses in the Aros area is essential to provide adequate
properties for permanent residents for either current or future families on
Mull. As evidenced by other local land sales close by in Salen, uptake is quick
and those plots already host young families and frontline workers. This
Page 104

Page 105

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
planning type is essential for the regeneration and survivability of the island.
The site is currently used as a grazing field for minimal livestock; the potential
of four new homes far outweighs the impact on agricultural usage. 
• It is imperative that land is freed up to build new homes on the island for
communities to thrive and to allow workers to move their families and to move
up the housing ladder. There is a critical shortage of housing which makes it
difficult for businesses to attract and retain staff or to fill essential roles. Many
houses are holiday properties serving the tourist industry and land available
for building is extremely limited. There are people at all stages of the housing
ladder who either already live on Mull or need to move there for work. 
• Aros is well served by public transport, with access to schools, shops and
other amenities. The area is accessed via a good road with low traffic levels
and no existing residential property looks onto the proposed development.
The proposed development is sensitively designed and, as there are already
new houses along the road, they will not look out of keeping.   
Officer Comment: The expressions of support are noted by the Planning Authority. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Impact Assessment Report: ☐Yes ☒No  
(ii) An Appropriate Assessment under the
Conservation (Natural Habitats) Regulations
1994:   
☐Yes ☒No  
(iii) A Design or Design/Access statement:    ☒Yes ☐No 
A Design & Access
Statement has been
submitted with the
application. 
(iv) Sustainability Checklists (with reference to the requirements of LDP2
Policy 04) 
TN06 Sustainability Checklist
TN07 Sustainable Buildings Checklist
☒Yes ☐No
☒Yes ☐No 
The relevant
Sustainability Checklists
have been submitted
and examined. It is the
assessment of the Case
Officer that the applicant
has understood and
given adequate
consideration to the
sustainability aspects of
Page 105

Page 106

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
the proposed
development, sufficient
to accord with the core
sustainability
requirements of both
national and local
planning policy,
specifically the relevant
details of the
‘Sustainable Places’
group of policies within
NPF4 and LDP2 policies
04, 08 and 09.  
(v) A report on the impact of the proposed
development eg. Retail impact, transport
impact, noise impact, flood risk, drainage
impact etc:  
☐Yes ☒No   
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   ☐Yes ☒No   
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  ☐Yes ☒No    
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been taken into account in the
assessment of the application 
(i)  List of all Development Plan Policy considerations taken into account
in assessment of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
Part 2 – National Planning Policy 
Sustainable Places
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 2 – Climate Mitigation and Adaption
NPF4 Policy 3 – Biodiversity
NPF4 Policy 4 – Natural Places
NPF4 Policy 5 – Soils
NPF4 Policy 9 – Brownfield, Vacant and Derelict Land and Empty Buildings (includes
provisions relevant to Greenfield Sites)
NPF4 Policy 11 – Energy
NPF4 Policy 12 – Zero Waste
NPF4 Policy 13 – Sustainable Transport 
Liveable Places
NPF4 Policy 14 – Design, Quality and Place
Page 106

Page 107

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 15 – Local Living and 20 Minute Neighbourhoods
NPF4 Policy 16 – Quality Homes
NPF4 Policy 17 – Rural Homes
NPF4 Policy 18 – Infrastructure First
NPF4 Policy 22 – Flood Risk and Water Management 
Argyll and Bute Local Development Plan 2 (Adopted 2024) 
Spatial and Settlement Strategy 
Policy 02 – Outwith Settlement Areas
Policy 04 – Sustainable Development 
High Quality Places 
Policy 05 – Design and Placemaking
Policy 08 – Sustainable Siting
Policy 09 – Sustainable Design
Policy 10 – Design – All Development 
Connected Places 
Policy 34 – Electric Vehicle Charging Points
Policy 35 – Design of New and Existing, Public Roads and Private Access Regimes
Policy 36 – New Private Accesses
Policy 39 – Construction Standards for Private Accesses
Policy 40 – Vehicle Parking Provision
Policy 41 – Off Site Highway Improvements 
Sustainable Communities 
Policy 60 – Private Sewage Treatment Plants and Wastewater Drainage Systems
Policy 61 – Sustainable Urban Drainage Systems (SUDS)
Policy 63 – Waste Related Development and Waste Management 
Homes for People 
Policy 67 – Provision of Housing to Meet Local Needs Including Affordable Housing 
High Quality Environment 
Policy 73 – Development Impact on Habitats, Species and Biodiversity
Policy 79 – Protection of Soil and Peat Resources
Policy 83 – Safeguarding Agricultural and Croft Land 
(ii)  List of all other material planning considerations taken into account in
the assessment of the application, having due regard to Annex A of
Circular 3/2013. 
• Third Party Representations
• Consultation Reponses
• Planning History
• ABC Technical Note – Biodiversity (Feb 2017)
• ABC draft Technical Note – Argyll and Bute Windows (April 2018)
Page 107

Page 108

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
• TN06 Sustainability Technical Note and Checklist (Oct. 2023)
• TN21 VII and LVIA Light Technical Note (Oct. 2023)
• TN07 Sustainable Buildings Technical Note and Checklist (Oct. 2023) 
• ABC Housing Needs and Demand Assessment
• ABC Housing Emergency Statement 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental
Impact Assessment:  ☐Yes ☒No    
(L) Has the application been the subject of statutory pre-application consultation
(PAC):  ☐Yes ☒No 
(M) Does the Council have an interest in the site:  ☐Yes ☒No 
(N) Requirement for a pre-determination hearing: ☐Yes ☒No 
Whilst there has been considerable objection raised, primarily from residents in the
immediate locality of the development, it is noted that the representations relate largely to
existing water supplies, the suitability of the access to serve the proposed development,
and the visual impact resulting from the proposed development. The application site is not
covered by any specific environmental or landscape designations and the Officer’s
recommendation is aligned with the consultation responses received from both the
Council’s Roads Authority and Scottish Water and as such it is not considered that a pre-
determination hearing would add significant value to the decision making process. 
(O)(i) Key Constraints/Designations Affected by the Development:
• N/A 
(O)(ii) Soils
Agricultural Land Classification:  Class 5.1 - Land capable of use as
improved grassland. Few problems
with pasture establishment and
maintenance and potential high
yields. 
Peatland/Carbon Rich Soils Classification: ☐Class 1
☐Class 2
☐Class 3
☒N/A
Peat Depth Classification: N/A  
Does the development relate to croft land? ☐Yes ☒No
Would the development restrict access to croft
or better quality agricultural land?
☐Yes ☒No ☐N/A
Would the development result in
fragmentation of croft / better quality
agricultural land?
☐Yes ☒No ☐N/A
Page 108

Page 109

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(O)(iii) Woodland  
Will the proposal result in loss of
trees/woodland? 
☐Yes
☒No 
Does the proposal include any replacement or
compensatory planting?
☐Yes
☐No details to be secured by condition
☒N/A  
(O)(iv) Land Status / LDP Settlement Strategy
Status of Land within the Application  ☐Brownfield
☐Brownfield Reclaimed by Nature
☒Greenfield 
ABC LDP2 Settlement Strategy 
☐Settlement Area
☒Countryside Area
☐Remote Countryside Area
☐Helensburgh & Lomond Greenbelt
ABC LDP2 Allocations/PDAs/AFAs etc: 
N/A 
(P) Summary assessment and summary of determining issues and material
considerations 
The proposal the subject of this planning application is seeking to secure planning
permission for the erection of four dwellinghouses, the installation of private drainage
systems and the formation of two vehicular accesses. 
With regard to the planning history for the site, a previous application was submitted
for the development of the site with six dwellinghouses and associated works (our
reference 24/01849/PP); this application was subsequently withdrawn following
concerns raised by the Planning Authority with regard to the density and siting of the
proposed development. The current application proposes an amended scheme,
seeking to address the previous concerns. 
In terms of the adopted LDP2 the site is defined as ‘Outwith Settlement Areas’ within
an area identified as ‘Countryside Area' where Policy 02 of LDP2 gives a
presumption in favour of sustainable development where it is of an appropriate scale,
design, siting and use for its countryside location, as set out in the relevant
sustainable siting and design policies of LDP2. 
Policy 02 further states that certain development will be supported, generally without
the need for detailed environmental assessments, with these comprising, infill,
redevelopment opportunities of clusters; or previously developed sites. In
Countryside Areas, where there are nature conservation or landscape designations
in place, Policy 02 details that development proposals will have to demonstrate that
they are compatible with the designation interests. 
The application site comprises an area of sloping managed grassland to the north of
the UC79 public road, sited approximately 400 metres to the east of the A848 public
road. The site as existing features a single agricultural building within the southeast
corner, accessed via an existing track. A dense mature tree belt is situated to the
Page 109

Page 110

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
south of the UC79 public road, which follows the line of the road. Further to the south,
an additional access closely follows the edge of the bay to provide access to
dwellings at the mouth of the River Aros. There are a number of existing residential
properties in proximity to the application site, with three houses immediately to the
east and an additional cluster of dwellings at the end of the UC79 public road. 
The proposed dwellings would be accessed by two new private accesses which
would extend from the UC79 public road; Plot 1 and Plot 2 would share a new access
and parking area set a short distance immediately to the north of the public road,
and Plot 3 and 4 would be accessed via a shared hard landscaped area that would
be of sufficient size to allow turning for larger delivery, maintenance and emergency
vehicles. Water supply would be via connection to the public water supply and foul
drainage would be via private domestic sewage treatment plants and associated
soakaways due to the lack of public infrastructure within the vicinity of the site. All
access, parking and infrastructure matters are considered acceptable and are
discussed in detail in the main assessment of the proposal within Appendix A of this
report.   
The proposal has elicited 27 objections, 1 representation and 2 expressions of
support. 
The key factor in the assessment of this application is whether or not the erection of
four dwellinghouses and associated development are of an appropriate scale,
design, siting and use for their countryside location and whether the development is
consistent with the provisions of adopted National and Local Planning Policy. 
It is the opinion of Planning Officers that the siting, scale and design of the proposed
dwellinghouses and the associated development would pay appropriate regard to
the characteristics of the area within which it proposed to ensure no significant
adverse impact arises and the proposal is considered to accord with the provisions
of the current Development Plan and with national planning policy. 
Taking account of the above, it is recommended that planning permission be granted
subject to the conditions appended to this report.   
A full report is provided within Appendix A. 
(Q) Is the proposal consistent with the Development Plan: ☒Yes ☐No 
(R) Reasons why Planning Permission or Planning Permission in Principle Should
be Granted: 
The proposal is considered to be consistent with the relevant provisions of the
Development Plan, and there are no other material considerations of sufficient
significance, including issues raised by third parties, to indicate that it would be
appropriate to withhold planning permission having regard to Section 25 of the Act. 
(S) Reasoned justification for a departure to the provisions of the Development
Plan 
N/A
Page 110

Page 111

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
(T) Need for notification to Scottish Ministers or Historic Environment Scotland:
☐Yes ☒No 
Author of Report: Emma Shaw Date: 04.11.2025 
Reviewing Officer: Tim Williams Date: 04.11.2025 
Fergus Murray
Head of Development & Economic Growth 
Page 111

Page 112

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO. 25/01248/PP 
Standard Time Limit Condition  (as defined by Regulation) 
Standard Condition on Soil Management During Construction 
Additional Conditions  
1. PP - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details specified on the
application form dated 22.07.2025, supporting information and, the approved drawings
listed in the table below unless the prior written approval of the planning authority is
obtained for an amendment to the approved details under Section 64 of the Town and
Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Location Plan 677_PL_001 C 28.07.2025
Site Plan –
Existing
677_PL_002  28.07.2025
Site Sections –
Existing
677_PL_003 A 28.07.2025
Site Plan – Ground
Floor
677_PL_010 C 28.07.2025
Site Plan – First
Floor
677_PL_011 D 28.07.2025
Site Plan – Roof 677_PL_012 D 28.07.2025
Site Plan – Aerial
photomontage
677_PL_013 B 28.07.2025
Site Sections –
Proposed 
677_PL_020 A 28.07.2025
House Type A1 677_PL_101 C 28.07.2025
House Type A2 677_PL_102 D 28.07.2025
House Type B1 677_PL_103  B 28.07.2025
House Type B
variant plans –
accessibility study
677_PL_104  23.10.2025 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details.  
2. Timescale to be Agreed for Completion 
No development shall commence until details of the proposed timescale for completion
of the approved development have been submitted to and approved by the Planning
Authority. Thereafter, the development shall be implemented in accordance with the
duly approved timescale for completion unless an alternative timescale for completion
is otherwise agreed in writing with the Planning Authority. 
Reason: In order to comply with the requirements of NPF4 Policy 16F. 
3. Sustainable Drainage System 
Page 112

Page 113

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Notwithstanding the effect of Condition 1, the development shall incorporate a surface
water drainage system which is consistent with the principles of Sustainable urban
Drainage Systems (SuDS) compliant with the guidance set out in CIRIA’s SuDS
Manual C753 and Sewers for Scotland 4th Edition. The requisite surface water
drainage shall be operational prior to the development being brought into use and shall
be maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage system and
to prevent flooding. 
Note to Applicant: 
• Further advice on SuDS can be found in SEPA’s Standing Advice for Small
Scale Development – www.sepa.org.uk .  
4. Junctions with Public Road 
Notwithstanding the provisions of Condition 1, the proposed accesses shall be formed
in accordance with the Council’s Roads Standard Detail Drawing SD08/004b and
visibility splays of 25 metres to point X by 2.4 metres to point Y from the centre line of
the proposed access. The access shall be surfaced with a bound material in
accordance with the stated Standard Detail Drawing. Prior to work starting on site the
access hereby approved shall be formed to at least base course standard and the
visibility splays shall be cleared of all obstructions such that nothing shall disrupt
visibility from a point 1.05 metres above the access at point X to a point 0.6 metres
above the public road carriageway at point Y. The final wearing surface on the access
shall be completed prior to the development first being brought into use and the
visibility splays shall be maintained clear of all obstructions thereafter. 
Reason: In the interests of road safety. 
Note to Applicant: 
• A Road Opening Permit under the Roads (Scotland) Act 1984 must be
obtained from the Council’s Roads Engineers prior to the formation/alteration
of a junction with the public road. 
• The access shall be constructed and drained to ensure that no surface water
is discharged onto the public road. 
• Bin storage areas shall be located to the rear of the bay element of the
Council’s Roads Standard Detail Drawing SD08/004b. 
5. Parking and Turning – Further Details Required 
Notwithstanding the provisions of Condition 1, no development shall commence until
full  details of the layout and surfacing of parking and turning areas to accommodate
two vehicles per dwelling for House Types ‘A1’ and ‘A2’ and three vehicles for House
Type ‘B’ within the application site have been submitted to and approved in writing by
the Planning Authority in consultation with the Council’s Roads Engineers. The duly
approved scheme shall be implemented in full prior to the development first being
occupied and shall thereafter be maintained clear of obstruction for the parking and
manoeuvring of vehicles. 
Page 113

Page 114

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Reason: In the interest of road safety.  
6. Landscaping and Biodiversity Enhancement 
No development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved by the Planning
Authority. The scheme shall include details of: 
i) Location, design and materials of proposed walls, fences and gates; 
ii) Surface treatment of proposed means of access and hardstanding
areas; 
iii) Any proposed re-contouring of the site by means of existing and
proposed ground levels; 
iv) Proposed hard and soft landscape works; 
v) A biodiversity statement demonstrating how the proposal will contribute
to conservation/restoration/enhancement of biodiversity, and how
these benefits will be maintained for the lifetime of the development;
and 
vi) A management plan for the removal of invasive non-native species, to
include a programme of monitoring and maintenance. 
The development shall not be occupied until such time as the physical biodiversity
enhancement measures (bird nesting boxes, ‘swift bricks’, wildlife ponds, bat and
insect boxes, hedgehog homes etc), the boundary treatment, surface treatment and
any re-contouring works have been completed in accordance with the duly approved
scheme. 
All biodiversity enhancement measures consisting of new or enhanced planting shall
be undertaken either in accordance with the approved scheme of implementation or
within the next available planting season following the development first being brought
into use. 
All of the hard and soft landscaping works shall be carried out in accordance with the
approved scheme during the first planting season following the commencement of the
development, unless otherwise agreed in writing by the Planning Authority. 
The biodiversity statement should refer to Developing with Nature guidance |
NatureScot as appropriate. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity.  
7. Electric Vehicle Charging – Residential with off street parking 
Prior to the commencement of the development (or such other timescale as may be
agreed in writing with the Planning Authority), a scheme detailing the provision of four
minimum 7kw electric vehicle charging points shall be submitted to and approved in
writing by the Planning Authority. Where charging cannot be provided then the
appropriate ducting to future proof the property must be installed. 
Page 114

Page 115

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The approved charging point, or where relevant, the approved cable ducting shall be
installed in full prior to the first occupation of the development, and thereafter retained
in perpetuity unless otherwise agreed in writing by the Planning Authority 
Reason: To comply with the provisions of NPF4 Policy 13 Sustainable Transport and
LDP2 Policy 34 – Electric Vehicle Charging.  
8. Offsite Highway Improvements 
Notwithstanding the provisions of Condition 1 no development shall commence until
full details of offsite highway improvements have been submitted to and approved by
the Planning Authority in consultation with the Council’s Roads Engineers. Such
details shall incorporate: 
i) The provision of an additional passing place, to be installed approximately
50 to 70 metres from the junction of the UC79 with the A848; 
ii) The road verges to be levelled off between the site accesses and the
junction of the UC79 with the A848, to create a level step off for
pedestrians; and 
iii) The culverting of roadside ditches at the site accesses. 
Prior to the dwellinghouses hereby granted being first occupied, the approved scheme
of works shall be completed. 
Reason: In the interest of road safety to provide a standard of access commensurate
with the scale of the development.   
Page 115

Page 116

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
COMMITTEE REPORT
APPENDIX A – RELATIVE TO APPLICATION NUMBER:  25/01248/PP 
PLANNING LAND USE AND POLICY ASSESSMENT 
1. Introduction 
1.1. The proposal the subject of this application is seeking to secure planning permission for
the erection of four dwellinghouses, the installation of private drainage systems and the
formation of two vehicular accesses. 
2. Settlement Strategy 
2.1. In terms of the Settlement Strategy set out in the adopted LDP2, the site is defined as
‘Outwith Settlement Areas’ within an area identified as ‘Countryside Area' where Policy
02 of LDP2 gives a presumption in favour of sustainable development where it is of an
appropriate scale, design, siting and use for its countryside location, as set out in the
relevant sustainable siting and design policies of LDP2. 
In order to address the determining issues, the key considerations in this application are: 
2.1.1. Compliance with the Development Plan and other relevant planning policy
2.1.2. Any other material considerations. 
3. Proposal 
3.1. The site is a south facing slope with a level of 42mAOD at the highest point dropping to
approximately 17mAOD at the southern boundary. The site as existing features an
agricultural building and an associated track which crosses the site from east to west. 
With regard to the planning history for the site, a previous application was submitted for
the development of the site with six dwellinghouses and associated works (our reference
24/01849/PP); this application was subsequently withdrawn following concerns raised by
the Planning Authority with regard to the density and siting of the proposed development.
The current application proposes to address the previous concerns, with a reduction to
four dwellinghouses sited towards the southern boundary of the site with a variation in set
back and orientation so as to avoid the previously proposed two-tiered development
pattern. 
The layout of the proposed development would comprise four plots in a roughly linear
formation, with two new accesses proposed to each serve two dwellings. The dwellings
would be arranged to allow all the principal living spaces to gain views to the south, and
the dwellings would be located within their plots to maximise south and west facing
gardens. 
Plot 1, being the westernmost plot, would facilitate a dwelling of one and a three-quarter
storey in design. The dwelling would have a ‘T’ shaped form, facilitating four bedrooms.
The main section of the dwelling would comprise a narrow linear form with a dual-pitched
roof and gable ends. The adjoining single storey elements would be flat-roofed. 
Plot 2 would be located immediately to the east of Plot 1 and would share an access with
Plot 1. Plot 4 would be the easternmost plot. These plots would facilitate a dwelling of one
and three-quarter storey in design. The dwellings would have a simple, narrow linear form,
Page 116

Page 117

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
facilitating three bedrooms. The dwellings would have a dual-pitched roof and gable ends
and would feature a small flat-roofed projection which would facilitate a porch. 
Plot 2, located centrally between Plots 2 and 4 and sharing an access with Plot 4, would
facilitate a dwelling of one and three-quarter storey in design. The dwelling would have a
simple, narrow linear form, facilitating three bedrooms. The dwelling would have a dual-
pitched roof and gable ends and would feature a small flat-roofed projection which would
facilitate a porch. 
The proposed dwellings would comprise local vernacular forms with appropriately
proportioned massing and simply composed elevations. The proposed facing materials
would be traditional white render, with vertical timber cladding to the flat-roofed entrances
and to the single storey elements of the proposed dwelling at Plot 1. Vertical untreated
timber cladding would also be used around the main windows and doors, which would
weather to a silver colour over time. The roofs would be constructed using slate tiles. 
4. Compliance with National Planning Framework 4 and Local Development Plan 2
Policy 
Argyll and Bute ‘Local Development Plan 2’ (LDP2) was adopted on 28 February 2024
which, together with NPF4 which was adopted on 13 February 2023, represent the
Development Plan providing the policy background against which proposed developments
are assessed. 
The proposal is assessed against the relevant NPF4 Policies below which include details
of the associated LDP2 policies. 
4.1. NPF4 Policy 1 – Tackling the Climate and Nature Crises 
NPF4 Policy 1 seeks to prioritise the climate and nature crises in all decisions; it requires
to be applied together with other policies in NPF4. 
Guidance from the Scottish Government advises that it is for the decision maker to
determine whether the significant weight to be applied tips the balance in favour for, or
against a proposal on the basis of its positive or negative contribution to climate and
nature crises.   
4.2. NPF4 Policy 2 – Climate, Mitigation and Adaption 
NPF4 Policy 2 seeks to ensure that new development proposals will be sited to minimise
lifecycle greenhouse gas emissions as far as possible, and that proposals will be sited
and designed to adapt to current and future risks from climate change. 
Guidance from the Scottish Government confirms that at present there is no single
accepted methodology for calculating and / or minimising emissions. The emphasis is on
minimising emissions as far as possible, rather than eliminating emissions. The Spatial
Settlement Strategy set out within LDP2  seeks to deliver sustainable levels of growth by
steering the majority of development to our existing settlements as these are where the
most of our current infrastructure, services, employment opportunities, housing and
community facilities are to be found, however LDP2 recognises that there are instances
where a different approach to significant development has to be taken particularly where
existing infrastructure or services are at capacity and where a more sustainable option
would be to provide new facilities elsewhere. 
4.3. NPF4 Policy 3 – Biodiversity 
Page 117

Page 118

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 3 seeks to protect biodiversity, reverse biodiversity loss and deliver positive
effects from development and strengthen nature networks. 
In the case of the development proposed by this application, it is considered that there are
no issues of compliance with Policy 3. The application proposes to develop an area of
managed grassland and no material biodiversity impacts have been identified in the
assessment of this application by the Planning Authority and whilst no specific proposals
for biodiversity improvements have been submitted, it is considered that adequate and
proportionate measures for biodiversity enhancement and protection can be delivered by
planning condition. 
With a condition to secure adequate and proportionate biodiversity enhancement and
protection measures within the development, the proposal aligns with the broad aims of
NPF4 Policy 3 and is consistent with the requirements of LDP2 Policy 73, Development
Impact on Habitats, Species and Biodiversity. 
4.4. NPF4 Policy 4 – Natural Places 
NPF4 Policy 4 seeks to protect, restore and enhance natural assets making best use of
nature-based solutions. 
The development proposed by the current planning application is considered appropriate
in terms of its type, location and scale such that it has no unacceptable impact on the
natural environment. The proposed development is not within any designated European
site of natural environment conservation or protection, it is not located within a National
Park, a National Scenic Area a SSSI or RAMSAR site, or a National Nature Reserve.
Neither is it located within a site designated as a local nature conservation site or
landscape area or within an area identified as wild land. 
The proposed development is considered to be consistent with NPF4 Policy 4 and does
not conflict with any policies set out in LDP2. 
4.5. NPF4 Policy 5 – Soils 
NPF4 Policy 5 seeks to seeks to protect carbon-rich soils, to restore peatlands and to
minimise disturbance to soils from development. 
The development the subject of this planning application seeks to develop an area of
managed grassland. The wider site within the applicant’s ownership has an area of
approximately 2.2 hectares; it is proposed to develop the southern area of the site,
covering an area of 0.7 hectares. The site is not within an identified area of peatland,
carbon-rich soils or priority peatland habitat. Whilst the proposed development would
result in the use of a small area of managed grassland, it would not weaken the viability
of an agricultural unit, result in the fragmentation of field systems and the integrity of a
unit, nor would the proposal result in the loss of access to field systems. 
The development proposed is therefore considered to be in accordance with NPF4 Policy
5 and Policies 79 and 83 of LDP2. 
4.6. NPF4 Policy 9 – Brownfield, Vacant and Derelict Land and Empty Buildings 
NPF4 Policy 9 seeks to encourage, promote and facilitate the reuse of brownfield, vacant
and derelict land and empty buildings, and to help reduce the need for greenfield
development.
Page 118

Page 119

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The site is considered to be on a greenfield site by virtue of its designation as Countryside
Area in the adopted LDP2. In this regard Part (b) of Policy 9 states that proposals on
greenfield sites will not be supported unless the site has been allocated for development
or the proposal is explicitly supported by policies in the LDP. 
However, LDP2 Policy 02, Outwith Settlement Areas, seeks to promote a more flexible
approach to development in areas identified as Countryside Area, with Part A of Policy 02
giving a presumption in favour of sustainable development where it is of an appropriate
scale, design, siting and use for its countryside location, as detailed in the relevant
sustainable siting and design policies contained within LDP2.   
LDP2 Policy 02 requires development proposals to demonstrate that there will be no
unacceptable adverse effects (either individually or cumulatively) on natural heritage
resources, built and/or cultural heritage resources, and landscape and visual amenity. For
any development where there is preliminary evidence that there may be such adverse
effects (and where a formal environmental impact assessment is not required), a
landscape and visual impact assessment, natural heritage assessment, or built and/or
cultural heritage assessment may be required. 
Whilst the application site is not covered by any specific environmental or landscape
designations, the application has been submitted with a Landscape and Visual Impact
Assessment. The Assessment takes into account the site’s elevated position, the proximity
to the defined settlements, and the existing landscape character. The analysis of the
potential effects of the proposed development upon the landscape setting and the visual
amenity of the area are detailed below. 
The site is within a rural landscape, characterised by a south facing hillside with a band of
mature woodland screening beyond the southern boundary. To the east, the proposed
development is bounded by the settlement of Aros Mains and to the west, the settlement
of Aros Bridge. These two settlement areas are separated by intervening ground which
includes the site the subject of this application. 
The site is located in close proximity to the remains of Aros Castle, at a distance of
approximately 350 metres, a significant historical landmark in the region. The presence of
the castle remains contributes to the cultural and historical character of the surrounding
landscape, with the A848 providing views of the castle over the estuary of the River Aros
on the approach to Aros Bridge. The remains of Aros Castle are prominent within the
landscape. The sight lines between the castle and the application site are screened
through typography and woodland. 
The proposed dwellings would be clustered in a roughly linear formation, with variations in
orientation and set back, in the southernmost part of the site where existing mature
woodland beyond the site boundary would provide immediate visual screening. This siting
minimises the visual impact from key viewpoints such as the approach along the A848 or
the nearby settlements of Aros Bridge and Aros Mains. The site is not visible from Aros
Castle. The Assessment states that during the months when the trees are in full leaf, the
site would be largely if not completely concealed from the described viewpoints. 
Given the proximity of the distinct settlements of Aros Mains to the east and Aros Bridge
to the west, there is a requirement to respect the gap between the settlements so as to
avoid the risk of visual coalescence. Maintaining the separation would preserve the distinct
identities of both settlements and the character of the surrounding landscape. The
contextually appropriate material choices would further minimise the prominence of the
proposed development, and maintaining open spaces between the site and the adjacent
Page 119

Page 120

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
settlements would preserve the areas distinct character and avoid visual coalescence. The
siting of the proposed development adjacent to the public road within the south of the site
would assist in concealing the proposal from prominent views behind the existing mature
woodland; this natural screening would assist in integrating the dwellings into the
landscape and thereby reduce their visual significance. 
The detailed information submitted with the Assessment advises that the proposed
development would avoid prominent ridgelines and respect existing vegetation and key
view corridors, particularly from the A848 and across the Sound of Mull. The Assessment
further advises that the proposed development would adopt simple forms and massing to
reduce their visual impact within open views. A muted and natural material palette
referencing traditional island structures, including timber cladding and slate roofs would by
sympathetic to the surrounding built and natural context. 
The Assessment demonstrates that the application site has the capacity to facilitate the
proposed development without any adverse landscape and visual effects. The application
seeks planning permission for the erection of four dwellinghouses and associated
development. The site for the proposed development is located immediately adjacent to
an existing public road in proximity to the main A848 road which links the area to larger
defined settlements. The scale and design of the proposed dwellinghouses, and the plot
density, would respect the surrounding built environment. The site is not subject to any
nature conservation or landscape designations. In this instance, therefore, the site is
considered to represent an appropriate opportunity for development with a suitably sited
and designed development within the Countryside Area which has been specifically
designed with due regard to the context of the site in terms of its character and appearance
and in this regard would be consistent with NPF4 Policy 9 which does not conflict with the
spatial and settlement strategy set out in LDP2 Policy 02. 
4.7. NPF4 Policy 11 – Energy 
NPF4 Policy 11 seeks to encourage, promote and facilitate all forms of renewable energy
development onshore and offshore. This includes energy generation, storage, new and
replacement transmission and distribution infrastructure and emerging low-carbon and
zero emissions technologies. 
NPF4 Policy 11(a) states that development proposals for all forms of renewable, low-
carbon and zero emissions technologies will be supported. The proposed development,
through the provision of solar panels upon the roofslopes of the dwellinghouses and the
provision of aur source heat pumps, would contribute to the expansion of low-carbon and
zero emission technologies and is thereby supported by NPF4 Policy 11 and there is no
conflict with LDP2 Policy 09, Sustainable Design, which seeks proposed developments
to consider renewable sources of energy. 
4.8. NPF4 Policy 12 – Zero Waste 
NPF4 Policy 12 seeks to encourage, promote and facilitate development that is consistent
with the waste hierarchy as defined within the policy document. 
The development the subject of this planning application seeks to secure permission for
four dwellinghouses. Whilst this is a development likely to generate waste when
operational, it will benefit from regular waste uplifts by the Council and will be expected
to comply with our adopted and enforced recycling and reuse strategy. 
In this regard, the proposed development is considered to be in compliance with NPF4
Policy 12 and does not conflict with the requirements of LDP2 Policy 63, Waste Related
Page 120

Page 121

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Development and Waste Management which seek to ensure that effective provision for
waste/recycling is provided within developments. 
4.9. NPF4 Policy 13 – Sustainable Transport 
NPF4 13 seeks to encourage, promote and facilitate developments that prioritise walking,
wheeling, cycling and public transport for everyday travel and reduce the need to travel
unsustainably. 
The application is seeking to secure permission for four dwellinghouses, which is not
considered to be a a proposal where it is considered important to monitor travel patterns
resulting from the development.   
Part (b) of Policy 13 requires consideration of the sustainable travel hierarchies including
provision for vehicles and cycle charging points. The provision of electric vehicle charging
points will be secured via condition. 
The proposed dwellings would be accessed by two new private accesses which would
extend from the UC79 public road; Plot 1 and Plot 2 would share a new access and
parking area set a short distance immediately to the north of the public road, and Plot 3
and Plot 4 would be accessed via a shared hard landscaped area that would be of
sufficient size to allow turning for larger delivery, maintenance and emergency vehicles. 
LDP2 Policy 41, Off Site Highway Improvements, states that, in the judgement of the
Planning Authority where development proposals will significantly increase vehicular or
pedestrian traffic on substandard private or public approach roads, then developments
will be required to contribute proportionately to improvements to an agreed section of the
public or private road network. 
The Area Roads Authority have been consulted on the application and advised of no
objections subject to conditions relating to the formation of the accesses at the junction
with the public road; the clearance and maintenance of visibility splays; the provision of a
system of surface water drainage; the provision of parking and turning areas; the
culverting of the roadside ditches at the site accesses; the provision of bin storage areas;
and the provision of proportionate improvements to the public approach road to include
the provision of an additional passing place and the levelling of the road verges to create
a level step off for pedestrians. 
Subject to the relevant conditions, the proposed development is consistent with the broad
aims of NPF4 Policy 13 and is consistent with the requirements of LDP2 Policies 35, 36,
39, 40 and 41 which collectively seek to ensure that proposed developments are served
by a suitable and safe access regime and provide appropriate parking provision
commensurate with the scale of the development proposed. 
4.10. NPF4 Policy 14 – Design, Quality and Place 
NPF4 Policy 14 seeks to encourage, promote and facilitate well designed development
that makes successful places by taking a design-led approach and applying the ‘Place
Principle’. 
NPF4 Policy 14(a) details that development proposals should be designed to improve the
quality of an area whether in urban or rural locations, regardless of scale with Part (b)
affording support to developments where they are consistent with the six qualities of
successful places: Healthy, Pleasant, Connected, Distinctive, Sustainable and Adaptable. 
Page 121

Page 122

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Part (c) details that development proposal which are poorly designed, detrimental to the
amenity of the surrounding area, or inconsistent with the six qualities of successful places,
will not be supported. 
NPF4 Policy 14(a) requires development proposals to be designed to improve the quality
of an area, whether in urban or rural locations and regardless of scale. In this instance,
the proposed development would be sited adjacent to the public road, in proximity to
existing residential properties, screened by the adjacent established tree cover. Whilst
there would be views of the proposed development, these would be in the context of the
wider surroundings which include existing residential properties, and the views would be
against the backdrop of rising land to the rear of the application site. The wider
surrounding settlement patterns are formed of sporadic clusters of developments which
generally share an access track from the main road, are often screened from views by
established vegetation, and are often sited parallel to the access road. The development
proposed by this application would be accessed off the main road and would form a well
contained small cluster of development. The orientations of each of the proposed
dwellings would be varied so as to suit the site topography and climatic conditions of each
plot and to provide variation. 
The siting of the proposed development in relation to the existing properties to the east of
the site would be such that separation distances and the intervening topography would
mean that there would be no adverse impacts upon neighbour amenity with regard to
overlooking, visual intrusion or shading. Neighbour amenity would therefore be suitably
retained. 
The proposed development is considered to be designed to an appropriate standard to
ensure compliance with the six qualities of successful places set out in NPF4 Policy 14
as follows. Healthy: being situated within a quiet rural setting but within proximity to an
existing community; Pleasant: being attractively designed and finished dwellinghouses
that would contribute to the character of the area; Connected: situated adjacent to the
public road which would connect the development with the settlements of Tobermory,
Salen and Craignure, all of which provide a number of services and facilities; Distinctive:
the design of the dwellings would be of a distinct, high quality design which would respond
to the setting whilst respecting the surrounding natural landscape; Sustainable: the
dwellings would utilise appropriately proportioned and designed fenestration which would
maximise potential for natural light; Adaptable: the development would be of a high
quality design that would be capable of adaption for accessibility and for alternative future
uses. 
The development the subject of this planning application is considered to be in
accordance with the broad aims of NPF4 Policy 14 and does not conflict with the
sustainable siting and design policies of LDP2 namely Policy 5, Design and Placemaking,
Policy 08, Sustainable Siting, Policy 09, Sustainable Design and Policy 10, Design: all
policies which, in summary, collectively seek to ensure that developments are compatible
with surrounding land uses, are sited sensitively within the landscape making use of
existing infrastructure, are of an appropriate scale, sustainable design and finishes for
their site, and ensure that no adverse visual or amenity impacts arise. 
4.11. NPF4 Policy 15 – Local Living and 20 Minute Neighbourhoods 
NPF4 Policy 15 seeks to encourage, promote and facilitate the application of the Place
Principle and create connected and compact neighbourhoods where people can meet the
majority of their daily needs within a reasonable distance of their home. 
Page 122

Page 123

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 15(a) seeks development proposals to contribute to local living including,
where relevant, 20 minute neighbourhoods. To establish this, consideration will be given
to existing settlement pattern, and the level and quality of interconnectivity of the proposed
development with the surrounding area, including local access to a number of facilities. 
The LDP2 settlement strategy seeks to deliver sustainable levels of growth by steering
the majority of development to our existing settlements where the most of our current
infrastructure, services, employment opportunities, housing and community facilities are
to be found and thereby making best use of these resources is a sustainable approach to
development. 
In terms of our adopted settlement strategy, the site of the proposed dwellinghouses is in
an area identified as being Outwith Settlement Areas where LDP2 Policy 02 seeks to
promote a more flexible approach to development in areas identified as Countryside Area,
within which the site is situated, with Part A of Policy 02  giving a presumption in favour
of sustainable development where it is of an appropriate scale, design, siting and use for
its countryside location, as detailed in the relevant sustainable siting and design policies.   
In this instance, it is considered that the small scale of the proposed development, and its
rural location, would reasonably comply with Policy 15 of NPF4 given the existing
dispersed geographical scale of the environment within which the development is to be
located, and given its compliance with the existing settlement pattern and the level and
quality of interconnectivity of the proposed development with the surrounding area where
people can reasonably meet the majority of their daily needs within a reasonable distance
of their home. 
The proposed development aligns with NPF4 and there is no conflict with LDP2 Policy
02. 
4.12. NPF4 Policy 16 – Quality Homes 
NPF4 Policy 16 seeks to encourage, promote and facilitate the delivery of more high
quality, affordable and sustainable homes in the right locations and providing choice of
tenure to meet diverse housing needs. 
Policy 16(c) supports development proposals for new homes that improve affordability
and choice by being adaptable to changing and diverse needs, and which address
identified gaps in provision, including ‘self-provided homes’ of which the proposed
development represents. 
With regards to Part (f) of Policy 16(i) an agreed timescale for build-out will be covered
through the use of a planning condition; 16(ii), whilst the development proposed by this
planning application is not on land actively allocated for housing in the LDP2, it would
wholly accord with the adopted settlement strategy and would accord with the principles
of ‘local living’ and ‘20 minute neighbourhoods’; 16(iii) the proposal is consistent with
NPF4 Policy 17, Rural Homes, being a suitable site which is in keeping with the landscape
character of the area. 
The proposed development is deemed to be consistent with NPF4 Policy 16 and there is
no conflict with LDP 2 Policy 02, Outwith Settlement due to the proposed development
being of an appropriate scale, design and use for its countryside location.   
4.13. NPF4 Policy 17 – Rural Homes 
Page 123

Page 124

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
NPF4 Policy 17 seeks to encourage, promote and facilitate the delivery of more high
quality, affordable and sustainable rural homes in the right locations. 
Policy 17(a) supports development proposals for new homes in rural areas where the
development is suitably scaled, sited and designed to be in keeping with the character of
the area. It has been demonstrated at NPF4 Policy 14 above that the proposed
dwellinghouses would be of a suitable scale and design for their countryside location. 
Policy 17(b) requires proposals for new homes in rural areas to consider how the
development will contribute towards local living and take into account identified local
housing needs. It has already been seen at NPF4 Policy 15 above that the proposed
development is consistent with our adopted settlement strategy policies and that it would
have no material harmful access or environmental impact. The proposed development
seeks the introduction of four new dwellinghouses and associated works which would
accord with the Council’s key planning policies aims of supporting and sustaining fragile
rural communities by contributing to actions to reverse our falling rural populations and
supporting the local economy. 
Policy 17(c) offers support to new homes in remote rural areas where such proposals (i)
support and sustain existing fragile communities; (ii) support identified local housing
outcomes; and (iii) are suitable in terms of location, access and environmental impact. 
The development proposed accords with the broad aims of NPF4 Policy 17 and does not
conflict with LDP2 Policy 09, Sustainable Development, Policy 10, Design all
Development, and Policy 67, Provision of Housing to Meet Local Needs. 
4.14. NPF4 Policy 18 – Infrastructure First 
NPF4 Policy 18 seeks to encourage, promote and facilitate an infrastructure first approach
to land use planning, which puts infrastructure considerations at the heart of placemaking. 
The application indicates water supply via connection to the public network with each
proposed dwellinghouse having a separate domestic sewage treatment plant, in the form
of a Klargester BioDisc with associated soakaways, due to the lack of public drainage
infrastructure within the vicinity of the site. The Council’s Building Standards Service will
apply suitable control over the detailed arrangements of the proposed private drainage
systems at Building Warrant stage. 
The proposed development aligns with NPF4 Policy 18 and is in accordance with LDP2
Policy 04, Sustainable Development and Policy 60, Private Sewage Treatment Plants and
Wastewater Drainage Systems, which seek to ensure that suitable infrastructure is
available to serve proposed developments and give support to private drainage
arrangements where connection to the public system is not available. 
4.15. NPF4 Policy 22 – Flood Risk and Water Management 
NPF4 Policy 22 seeks to strengthen resilience to flood risk and to ensure that water
resources are used efficiently and sustainably. 
The development the subject of this planning application proposes a connection to the
public water supply. Scottish Water have been consulted on the application and raised no
objection to the application, confirming that the proposed development is within the
Tobermory Water Treatment Works catchment. 
Page 124

Page 125

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
The management of rain and surface water at the site would be managed through the
provision of a sustainable urban drainage system, which can be adequately secured
through the use of a planning condition. Subject to such a condition, the proposal aligns
with NPF4 Policy 22 and LDP2 Policy 61, Sustainable Drainage Systems. 
5. Public Representation 
5.1. At the time of writing, representations had been received from 30 respondents in relation
to this planning application. 27 respondents raise objection and two provide support, with
one representation. 
It is not considered that the objections raise any complex or technical issues that have
not been addressed in the current Report of Handling. 
6. Conclusion 
6.1. The key factor in the assessment of this application is whether or not the erection of four
dwellinghouses and the associated development is of an appropriate scale, design, siting
and use for its countryside location and whether the development is consistent with the
provisions of adopted National and Local Planning Policy. 
No objections have been received from consultees with regards to the infrastructure,
servicing or access required to serve the proposed development. 
The proposed development has been assessed against the provisions of both the
adopted National and Local Policy set out above and is deemed to be in compliance with
their requirements and in accordance with the recently declared ‘housing emergency’. 
The issues raised by third parties are not considered to amount to material planning
considerations that have not been addressed through the processing of the planning
application. 
Accordingly the application is recommended for approval subject to conditions. 
Page 125

Page 126

This page is intentionally left blank

Page 127

Track
Riverside Keepers
Cottage
Shingle
Komani
Grianan
Seileasdair
Mean High Water
Marsh
Track
Riverside
Shingle
Shingle
Shingle
Mean High Water Springs
TCB
LB
MHWS
Cottage
House
Springs
© Crown Copyright and database right 2025
All rights reserved. OS license (customer) account number AC0000849384
Location Plan Relative to: 25/01248/PP
O
0 40 8020 Meters
Application Site
Page 127

Page 128

This page is intentionally left blank

Page 129

ARGYLL AND BUTE COUNCIL           PPSL COMMITTEE                                                  
DEVELOPMENT AND ECONOMIC GROWTH           18th NOVEMBER 2025 
TARBERT CONSERVATION AREA APPRAISAL AND MANAGEMENT PLAN 
1.0 EXECUTIVE SUMMARY  
1.1 The purpose of this report is to seek Member approval to consult on the draft
Tarbert Conservation Area Appraisal and Management Plan. 
1.2 Conservation areas are designated under the Planning (Listed Buildings and
Conservation Areas) (Scotland) Act 1997. Local planning authorities should
designate and review existing and potential conservation areas, and these
should be supported by Conservation Area Appraisals and Management
Plans. Further to a recent review of Tarbert Conservation Area as part of work
to support funding applications for a proposed Tarbert Heritage Regeneration
Scheme, a draft Conservation Area Appraisal and Management Plan has
been produced (Appendix 1). 
1.3 Planning authorities have a duty to submit their proposals for the preservation
and enhancement of conservation areas for consideration to a local public
meeting, and should, when preparing schemes, seek the advice and views of
local residents and community groups. 
1.4 A 6-week consultation period is therefore proposed to run between 5th
January and 16th February 2026, with a drop in event proposed to be held on
14th January.   
RECOMMENDATION 
It is recommended that Members:
Agree to the consultation of the draft Tarbert Conservation Area Appraisal and
Management Plan, noting a consultation period of 6-weeks is proposed, which would
run between 5th January and 16th February 2026, with a drop in event planned to be
held on 14th January. 
Page 129 Agenda Item 7

Page 130

ARGYLL AND BUTE COUNCIL         PPSL COMMITTEE 
DEVELOPMENT AND ECONOMIC GROWTH      18th NOVEMBER 2025 
TARBERT CONSERVATION AREA APPRAISAL AND MANAGEMENT PLAN 
2.0 INTRODUCTION 
2.1 The purpose of this report is to seek Member approval to consult on the draft
Tarbert Conservation Area Appraisal and Management Plan.   
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members:
Agree to consultation of the draft Tarbert Conservation Area Appraisal and
Management Plan noting a consultation period of 6-weeks is proposed, which
would run between 5th January and 16th February 2026, with a drop in event
planned to be held on 14th January. 
4.0 DETAIL 
4.1 The draft Conservation Area Appraisal and Management Plan (Appendix 1)
was produced in support of funding bids to National Lottery Heritage Fund and
Historic Environment Scotland for a proposed Tarbert Heritage Regeneration
Scheme. Submissions were made to each funder in August 2025 and are now
subject to a period of review, with decisions expected in early 2026. If
successful, a heritage-led regeneration project would be delivered in Tarbert
between 2026 and 2031.
4.2 Conservation areas are designated under the Planning Listed Buildings and
Conservation Areas (Scotland) Act 1997. A conservation area can be described
by its character and seeks to protect the buildings and the spaces between that
are of architectural or historic interest. Its purpose is to ensure that any
development or alteration positively contributes to the area’s character. 
Page 130

Page 131

4.3 The definition of a conservation area is contained within Section 61 of the
Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997 as, “an
area of special architectural or historic interest, the character or appearance of
which it is desirable to preserve or enhance”. Local planning authorities should
designate and review existing and potential conservation areas, and these
should be supported by Conservation Area Appraisals and Management Plans.
A draft Tarbert Conservation Area Appraisal and Management Plan has
therefore been produced.
4.4 Tarbert Conservation Area was established in 1972 and extended in 1977. As a
dynamic and constantly evolving entity, the review of existing areas is required
and provides opportunity to assess the justification for the designation, consider
the validation of boundaries, identify opportunities for enhancement and set
management priorities. The purpose of the recent review was to define and
evaluate the character and appearance of the existing conservation area to
support funding bids for a Tarbert Heritage Regeneration Scheme and also
assess whether the conservation area would benefit from extension. Its
boundary was reviewed in 2019, and in 2024 with no amendments proposed.
4.5 The purpose of a Conservation Area Appraisal and Management Plan is to
define what is important about the area’s character and appearance in order to
identify its characteristics and special features, and to explain this in a clear and
meaningful format. Subsequent to a period of consultation, the draft document
will be amended to reflect comments received, before being brought back to
PPSL for approval.  Once finalised, the document would provide a framework for
the positive management of change and provide a material consideration to
support planning decisions. The draft Tarbert Conservation Area Appraisal and
Management Plan accompany this report as Appendix 1.
4.6 A consultation period of 6-weeks is proposed to run between 5th January and
16th February 2026, with a drop in event planned to be held on 14th January.
Consultation questions would be hosted on the council’s website, and
advertised via press release, social media and by email notification to local
organisations, such as Tarbert and Skipness Community Trust and the
Community Council. Hard copies of the draft document would be made
available at Manse Brae and Tarbert Library, and a draft would be provided to
Historic Environment Scotland. 
5.0 CONCLUSION 
5.1 Conservation areas are designated under the Planning (Listed Buildings and
Conservation Areas) (Scotland) Act 1997. Local planning authorities should
designate and review existing and potential conservation areas, and these
should be supported by Conservation Area Appraisals and Management Plans.
A draft Tarbert Conservation Area Appraisal and Management Plan has been
produced and should now be subject to a period of consultation. 
Page 131

Page 132

5.2 This report therefore recommends that members agree to a 6-week public
consultation to ensure that the document can incorporate feedback and best
serve to preserve and enhance the special architectural or historic interest of the
area. 
6.0 IMPLICATIONS
6.1 Policy – Sections 61-63 of the Planning (Listed Buildings and Conservation
Areas) (Scotland) Act 1997.
6.2 Financial – None.
6.3  Legal – None.
6.4  HR – None.
6.5 Customer Service – None.
6.6 Risk – None.
6.7 Climate Change – None.
6.8  Fairer Scotland Duty – None.
6.9 Equalities - protected characteristics – None.
6.10 Consumer Duty – None.
6.11 Island Communities – None.
6.12 Children’s Rights and Wellbeing – None. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth
Policy Lead – Councillor Kieron Green
17th September 2025                                                  
For further information contact: 
Lorna Pearce, Senior Development Officer, 01700 501 374 / Kim de Buiteleir, Senior
Planning and Strategies Officer, 01546 604 126 
APPENDICES
Appendix 1 – Draft Tarbert Conservation Area Appraisal and Management Plan
Page 132

Page 133

Tarbert
Area Character Appraisal
Argyll & Bute Council
Appendix 1
Page 133

Page 134

Argyll & Bute Council
Tarbert Area Character Appraisal 
Rev A October 2025 
Photography credits:
Photographs contained within this report are reproduced here
under licence and/or credited where applicable.
Page 134

Page 135

4.5 Open Spaces and Landscape Setting
4.5.1 Open Spaces
4.5.2 Tree Preservation Orders
4.5.3 Nature of dominant species
Overview
1.0 Introduction, Purpose and Justification
1.1 Purpose and Scope
1.2 Climate Change
1.3 Community
2.0 Methodology
Conservation Area Appraisal & Management Plan
1.0 Introduction
1.1 Conservation Guidance
2.0 Context & Overview of Area Today
2.1 General identity & Summary of Character and Significance
2.2 Climate
2.3 SEPA Flood Maps
2.4 Planning Context
2.5 Nature and level of statutory protection / designations
3.0 Location, History and Development
3.1 Location
3.2 Geology
3.3 Settlement Development
3.4 Archaeology
4.0 Character and Appearance
4.1 Setting
4.2 Activity & Movement
4.3 Street Pattern & Topography
4.4 Buildings and Townscape
4.4.1 Scheduled Monuments
4.4.2 Key listed and unlisted buildings
4.4.3 Sense of place and intangible qualities
4.5.4 Landmark Trees
4.6 Character Areas and aspects of distinctiveness
4.6.1 The Village Centre
4.6.2 Peir Road
4.6.3 Barmore Road and Garvel Road
4.6.4 Tarbert Castle
4.6.5 Key aspects of distinctiveness
4.6.6 Negative impacts on character
5.0 Public Realm
6.0 Photographic Record of Buildings (Gazetteer)
7.0 Potential Buildings at Risk & Analysis of Sensitivity
8.0 Values and Significance
9.0 Summary of Assessment of Significance
10.0 Community Engagement
11.0 Evaluation of Vulnerabilities and Opportunities
11.1 Summary of the general fabric condition of heritage assets
11.2 Vulnerabilities of heritage assets and Conservation Area
11.3 Opportunities of heritage assets and Conservation Area
11.4 Approach to Climate Change
12.0 Opportunities for Planning Action
13.0 Conservation Strategy
14.0 Policies and Action Plan
15.0 Monitoring and Review
16.0 Appendices
16.1 Gazetteer of Heritage Assets
16.2 Community Engagement
16.3 Management & Maintenance Plan Checklist
List of Contents
Page 135

Page 136

Overview  1.0 Introduction, Purpose &
Justification
This work took place between April 2024 and March 2025. 
1.1 Purpose and Scope 
The purpose of the appraisal and plan, in line with best conservation practice, is to
review the previous draft Conservation Area Appraisal and Conservation Strategy
that was carried out in 2019, and to update this accordingly. 
The scope included: 
• A review of the draft Conservation Area Appraisal and Conservation Strategy, as
well as gathering and reviewing source materials
• Carrying out existing and historic mapping exercises.
• Preparation of a gazetteer of heritage assets of value (listed and unlisted),
with recommendations for listing or conservation area(s), if applicable, and
highlighting any historic buildings at risk (listed or otherwise) eligible for addition
to the Buildings at risk Register.
• Assessment of the cultural significance and identification of place making
opportunities in line with best practice guidance.
• A description of the heritage and conservation value of the area, and potential
threats.
• Policies and strategies.
• A framework for design and maintenance standards.
• Evidence of community consultation and engagement.
• A short statement about how the plan will be put into practice.
• Consideration as to whether any training and learning activities are necessary
to sustain a conservation-led approach to managing the area over the longer-
term and build upon traditional skills training and community heritage activities
completed during the scheme.
• Setting out good practice standards that owners of historic assets will
be expected to achieve in work to their buildings and places, including
maintenance.
• Expressing how the long-term vision for the area will be achieved. 
1.2 Climate Change 
In addition to the exposed conditions of the west coast of Scotland, it is essential
to consider what impact increased rainfall and extreme weather, due to climate
change, has on our stock of traditional buildings and townscapes, and the resulting
implications on repairs and maintenance.
Page 136

Page 137

DRAFT Conservation Area
Appraisal & Management Plan 
1.3 Community 
The local community need to be genuinely engaged in their environment and
heritage in order that the integrity of the area’s historic character is celebrated,
maintained, and managed sustainably in a way that supports a community to thrive
for future generations.
2.0 Methodology 
The Conservation Area Appraisal was carried out first and the findings used to
inform the Conservation Management Plan. 
The methodology, and format used to document these studies is in line with
guidance given within the following: 
• Scottish Executive Planning Advice Note 71, Conservation Area
Management, Part 1 and 2, 2004
• Stephen Bond & Derek Worthing, Managing Built Heritage, The Role of
Cultural Values and Significance, 2015
• Heritage Lottery Fund, Conservation Plan Guidance, 2017
• Historic Environment Scotland, Conservation Plans: A Guide to the
Preparation of Conservation Plans
• Historic Environment Scotland, Interim Guidance on the Designation of
Conservation Areas and Conservation Area Consent, 2019 
Methodology of research included desktop research and reference, archival
research, site visits, as well as community meetings and consultations. 
Diagrams, maps, and photographs have been used as much as possible to create
the clearest and most accurate record of Tarbert Conservation Area.
Page 137

Page 138

1.0 Introduction 
Conservation areas are designated under the Planning (Listed Buildings and
Conservation Areas) (Scotland) Act 1997. Local planning authorities should
designate and review existing and potential conservation areas, and these should
be supported by Conservation Area Appraisals and Management Plans. 
The definition of a conservation area is contained within Section 61 of the Planning
(Listed Buildings and Conservation Areas) (Scotland) Act 1997 as, “an area of
special architectural or historic interest, the character or appearance of which it is
desirable to preserve or enhance”. Local planning authorities should designate and
review existing and potential conservation areas, and these should be supported by
Conservation Area Appraisals and Management Plans. 
This Conservation Area Appraisal and Management Plan was compiled by Studio
SJM Architects. 
“A conservation area appraisal is a management tool which helps to identify the
special interest and changing needs of an area. An appraisal provides the basis for
the development of a programme of action that is compatible with the sensitivities
of the historic area and enables local authorities to fulfil their statutory duties to
protect and enhance conservation areas. Appraisals also inform policy and assist
development control. They provide an opportunity to educate residents about the
special needs and characteristics of the area and help developers identify and
formulate development proposals.” 
PAN 71 Conservation Area Management, December 2004
1.1 Conservation Guidance 
Once adopted, this Conservation Area Appraisal will accompany the policies
within the Local Development Plan 2 and assist in the improved management and
enhancement of Tarbert to encourage and promote economic growth. It will be used
by Argyll and Bute’s Planning and Conservation team as a Material Consideration
when assessing appropriateness of development applications during the planning
process. 
Anyone looking to make a change to their property is encouraged to seek advice
from their local planner: Contact Planning | Argyll and Bute Council. 
Historic Environment Scotland (HES) have a wide range of short guides, available
to download online, which contain practical information relating to carrying out works
on all elements of traditional buildings, including maintenance, windows, retro-fit
guidance and traditional shopfronts. 
• Short Guide: Maintaining Your Home | Historic Environment Scotland
• Short Guide: Maintaining Your Home | Historic Environment Scotland
• Short Guide: Sash and Case Windows | Historic Environment Scotland
• Short Guide: Sash and Case Windows | Historic Environment Scotland
• Guide to Energy Retrofit of Traditional Buildings | Hist Env Scotland
• Guide to Energy Retrofit of Traditional Buildings | Hist Env Scotland
• Short Guide: Scottish Traditional Shopfronts | Hist Env Scotland
• Short Guide: Scottish Traditional Shopfronts | Hist Env Scotland
(Note that many more short guides are available to download from the HES
website.) 
Historic Environment Scotland’s, Engine Shed is a dedicated building conservation
centre in Stirling which also offers useful and sound advice to owners of traditional
buildings. 
Learning |The Engine Shed | Part of Historic Environment Scotland
Page 138

Page 139

1.2 Planning Guidance 
Guidelines within this document are consistent with; 
• National Planning Framework 4 (NPF4) principally relevant policies: 
Policy 7: Historic assets and places
Policy 9: Brownfield, vacant and derelict land and empty buildings
Policy 14: Design, quality and place
Policy 15: Local Living and 20 Minute neighbourhoods
https://www.gov.scot/publications/national-planning-framework-4/
• The Local Development Plan 2 published by Argyll and Bute Council in early
2024. Specific relevant polices are highlighted within section 2.5 Planning
Context of this document. 
https://www.argyll-bute.gov.uk/planning-and-building/planning-policy/local-
development-plan-2 
As stated in the overview, diagrams, maps and photographs have been used
as much as possible to create the most clear and accurate record of Tarbert
Conservation Area. 
On review, the draft Conservation Area Appraisal carried out in 2019, is still
generally an accurate representation of the topography and architectural
characteristics of Tarbert Conservation Area. This document supersedes the 2019
draft. 
In line with good conservation practice, this draft document seeks to ensure that
the appraisal is fully up to date in terms of condition of buildings and assessment of
cultural values and significance, opportunities, and risks.
Page 139

Page 140

2.0 
Map on opposite
page showing
Consevation Area
Boundary
Context & Overview of Area Today 
Tarbert Conservation Area was established in 1972. Its boundary was extended in
1977. 
The area has been reviewed as follows: 
• 1972 - The special architectural character and historic significance of the inner
harbour area of Tarbert was recognised with a Conservation Area designation. 
• 1977 – The Conservation Area boundary was extended to include Victorian villas
along Garvel Road, Peir Road and Lady Ileene Road, as well as the curtilage of
Tarbert Castle. 
• 2019 – The Conservation Area boundary was reviewed, and no amendments
were proposed. 
• 2024 – The Conservation Area boundary was reviewed, and no amendments
are proposed. 
• Tarbert Conservation Area is covered by an Article 4 Direction, meaning
permitted development rights may be affected or removed. Property owners are
therefore encouraged to speak with their local planner prior to embarking on
works to their building. 
Email: planning.maki@argyll-bute.gov.uk
Conservation Areas | Argyll and Bute Council
Page 140

Page 141

2.1 
Map on opposite
page showing
Consevation Area
Boundary and
Conservation Area
Character Areas.
Identity & Summary of Character
& Significance
The village of Tarbert (An Tairbeart in Scottish Gaelic) is built around East Loch
Tarbert, which is an inlet of Loch Fyne. The village stretches over the isthmus which
links Kintyre to Knapdale and West Loch Tarbert. This location made Tarbert an
important harbour, and historically a strategic trading and guard point to Kintyre and
the Inner Hebrides. Its origins date back to as early as the first century, indicating
a place of unique identity, with significance in terms of several categories of value
including: historical, scenic, associational, and archaeological. 
These values are particularly evident within the boundaries of Tarbert Conservation
Area. The variation of character within the Conservation Area reflects the timeline of
Tarbert’s development and rich history. The draft 2019 Conservation Area Appraisal
categorises the Conservation Area into four distinct character areas: 
• The Village Centre
A mix of architectural styles and uses which radiate from the activity of the
fishing harbour, stretching west to Tarbert Parish Church on Campbeltown
Road. 
• Pier Road
A series of mostly large, handsome, Victorian villas, whose plots follow
one side of the road alongside the south shoreline providing panoramic
views across East Loch Tarbert and Loch Fyne, continuing east from the
edge of the village centre, past the East Peir and Battery Point to the
Conservation Area boundary at Old Peir. 
• Barmore Road (North) & Garvel Road
A mix of architectural styles and uses to the North of East Loch Tarbert,
animated by the activity of the marina. 
• Tarbert Castle
The curtilage of the scheduled monument of the 15th century castle tower
house remains on the elevated plateau to the Southeast of the loch,
overlooking Peir Road, and associated Tarbert Castle Heritage Park and
Community Woodland and Nature Conservation Area in the sheltered valley
beyond.
Page 141

Page 142

2.2 Climate 
The climate in Tarbert is typical to the West of Scotland. Statistics from www.
meteoblue.com recorded that in 2023, the highest temperature was around 24
degrees in July and lowest was around -2 degrees in January and December with
average temperatures between 6 degrees and 17 degrees throughout the year.
The same research demonstrates that during 2023 precipitation did not fall below
around 110mm per month with the highest precipitation of around 175mm recorded
in January and October. 
www.meteoblue.com also recorded a steady increase in both mean yearly
precipitation and mean yearly temperatures in Tarbert from 1979 to 2023 which is
consistent with Climate Change weather patterns.
2.3 
1. Depth of
Coastal Flooding
Likelihood - Map
Updated 08 Nov
2023 
2. Environment
Sites at Risk - Map
Updated 08 Nov
2023 
3. Likelihood of
Area Flooding -
Map Updated 08
Nov 2023 
Source:
Maps extracted
from https://beta.
sepa.scot/flooding/
flood-maps/
SEPA Flood Maps 
Page 142

Page 143

2.4 Planning Context 
Opposite page:
Map extracted
from LDP 2
- Diagram 6
Tourisim 
Source:
https://storymaps.
arcgis.com/storie
s/0e4137e311864
857937eee8f140a
eb9e
Tarbert should be considered within the context of the current Local Development
Plan 2 . 
The objective of the LDP2, published in early 2024, recognises that, “Argyll and
Bute’s economic success is built on a growing population.” 
Argyll and Bute Local Development Plan 2
https://storymaps.arcgis.com/stories/0e4137e311864857937eee8f140aeb9e
In particular, within the LDP2, Tarbert is identified as;
• a ‘Key Settlement’
• ‘not economically fragile’
• a Tourist Development Opportunity with the Cowal Way, existing cycle track
network, the ferry route and Argyll Sea Kayak Trail all passing through the
town – see Diagram 6 Tourism
• as an area where there is an existing public electric car charging point, on a
ferry route, on a main trunk road and where infrastructure action should be
taken – see Diagram 7 Connectivity 
The Areas for Action Schedule within LDP2 highlights the following potential
development opportunities; 
• A3004 Tarbert Harbour and Conservation Area Strategic; harbour
improvements; regeneration and environmental improvements, and
flood protection scheme
• A3013 Tarbert - South Campbeltown Road/Back Street Local; land use
rationalisation and redevelopment Business & Industry
• B3007 0.7 Tarbert - Glasgow Road Industry, Business and Storage Housing
• H3024 Tarbert – Oakhill/Easfield 50 units Potential Development Areas
• P3019 Tarbert – Campbeltown Road Mixed use – housing and open space
Page 143

Page 144

2.5 
Photograph:
View South East
over the Loch.
Nature and level of statutory
protection / designations
As well as having Conservation Area status, the village of Tarbert has ten listed
buildings, and two scheduled monuments within Tarbert Castle Heritage Park; all of
which are within the Conservation Area. 
The trees, and vegetation, within Tarbert Conservation Area contribute significantly
to its character and as such any tree within the Conservation Area is protected and
permission may be required to cut, lop, or uproot etc. In addition to this, there are a
number of Tree Preservation Orders. 
Reference should be made to paragraph 73 of the following:
Scottish Planning Series: Planning Circular 1 2011: Tree Preservation Orders 
East Loch Fyne is within the Clyde Marine Region, but is not a designated Marine
Protected Area, nor are there any other associated statutory protections.
3.0 Location, History & Development 
Page 144

Page 145

3.1 Location 
Tarbert nestles around the natural harbour of East Loch Tarbert. The landscape is
characterised by the local geology and varied topography which blends coastal and
rugged bedrock hill formations creating a picturesque back drop to the village. 
The coastline is dotted with small, rocky coves and sandy beaches, providing
views across East Loch Tarbert and beyond to Loch Fyne. The working harbour
to the south of the loch is sheltered and often filled with fishing boats, contrasting
with the leisure of the marina and yachts to the north, reflecting both historic and
contemporary maritime significance. 
Inland, the terrain quickly rises into a series of rolling hills and rugged high ground.
The hills are covered with a mix of heather, bracken, and areas of ancient woodland,
providing a rich tapestry of colours throughout the year. The highest points offer
panoramic views of the surrounding landscape, including the intricate coastline of
the Kintyre peninsula, the distant peaks of the Scottish Highlands, and on clear
days, the islands of Jura and Islay. 
As previously noted, this unique location historically made Tarbert an important
harbour and strategic trading and guard point to Kintyre and the Inner Hebrides.
Indeed, the ancient hill fort, which later became the site of the Royal Castle, and the
fishing port and walls were constructed to take advantage of the natural topography.
3.2 
Map:
Geological Map
Source: Argyll
and the Islands,
A Landscape
Fashioned by
Geology, David
Stephenson and
Jon Merritt
Geology 
Tarbert and the immediate surrounding areas of Knapdale and Kintyre are formed
of Metamorphosed sedimentary rocks - mainly Dalradian (late Precambrian) and
Dykes (Palaeogene). 
As is the case across Kintyre, large loose rocks can be found some distance away
from similar rocks, around Tarbert. 
The land itself is peaty and mossy, which accounts for the large areas of woodland
and forestry.
Page 145

Page 146

3.3 
The development
of settlement in
Tarbert reflects the
pattern of land use
that is still evident
today. A timeline
of key events
throughout the
history of Tarbert
have informed
settlement
development.
Settlement development 3.3.1 
Photograph:
Historic
Photograph from
Tarbert Life -
undated. Likely
early 19th century.
Source: Tarbert
Life.
Early Development 
It is known that East Loch Tarbert was used as a shelter for fisherman and traders
for over a thousand years. There are records of a settlement in the area as early as
the first century, with the oldest part of the now ruined castle, presumed to date back
to a seventh century hill fort. 
Tarbert became a royal burgh and a much more developed settlement with the
construction of the Royal Castle, on the site of the ancient hill fort, to the south of
East Loch on the high ground overlooking the isthmus between East and West
Lochs Tarbert, at the northern end of the Kintyre peninsula. This brought about
increased trade and a growing population who were employed in administration and
law enforcement. 
From the 1700s Tarbert was established as a thriving fishing community, and it
is recognised that a small village had developed to the west of the castle. Local
archives suggest this development consisted of a row of simple thatched cottages
with earth floors, along what is now known as Back Street, with similar cottages
dispersed across the hillside. 
Page 146

Page 147

3.3.2 
Photographs:
Historic
Photographs
from Tarbert Life
- undated. Likely
mid 19th century.
Source: Tarbert
Life.
1800s Development 
Developments in the early 1800s started to inform the street pattern and character
of the village as it is today. Improvements to the harbour wall by Thomas Telford
along with the introduction of steamers in the early 1800s meant increasing
population and number of visitors to Tarbert. In turn, further infrastructure such as
houses, lodging houses and shops, started to be built on the front street and Tarbert
Church was established in 1837. 
By the late 1800s key development such as Battery point, an extension to Tarbert
Church, a Cholera isolation Hospital, a wooden landing place, the Peir Road
and Garvel Road villas as well as the historic Old Templars Hall had all been
constructed. 
By this time Tarbert had become a thriving community and holiday resort supported
by the construction of the Tarbert and Victoria hotels as well as around 58 shops,
such as sweet shops, grocers, bakers, butchers, tailors and chandlers. There were
also banks, tea rooms, a fish and chip shop and cinema.
3.4 
Map:
Tarbert Heritage
Park
Source:
https://www.
tarbertcastle.info
Archaeology 
Tarbert Castle Trust in partnership with Historic Environment Scotland, Kilmartin
House Museum and the local school and community, has commissioned a series of
excavations in and around the site of the castle. Reports and findings can be found
on Tarbert Castle Trust’s website. 
https://www.tarbertcastle.info/archaeological-dig 
Page 147

Page 148

4.0 Character and Appearance 4.1 Setting 
Tarbert Conservation Area covers the heart of the village of Tarbert. The village
is set in picturesque natural landscape and surroundings, forming a panoramic
backdrop of seascape, rugged hills and coastline to its built heritage, in a way that
creates an intrinsic link between nature and architecture. 
This intrinsic link is likely why the configuration of the natural setting has
fundamentally informed the development and function of the built environment over
many centuries from the location of the castle as a strategic vantage point to the
location of the fishing harbour set within the sheltered natural inlet of the East Loch.
From these two strategic settlements, places of worship, commerce and trade,
homes and later tourism and leisure have filled the landscape between, radiating
from the shores of the loch. 
The extent and topography of the Conservation Area means there are numerous
significant panoramic vistas to, across and from, which contribute greatly to the
character of the setting. Notably, these views are framed by the natural topography
of the rock formations and shoreline or are anchored between the verticality of the
castle tower ruins and Tarbert Parish Church. 
Photograph
looking South
to the Village
Centre, Castle
and Harbour from
Garvel Road. 
Map on opposite
page showing key
views and focal
points.
Page 148

Page 149

4.2 Activity & Movement 
The diagram on the opposite page highlights the following activity and movement
within the Conservation Area: 
• Direction
• Mode
• Volume
• Circulation, and levels of activity
• Accessibility 
This activity and movement is impacted by day, night and seasonal variations.
Page 149

Page 150

4.3 
Extract of Map -
surveyed in 1865
-1866. Published in
1893.
Street Pattern & Topography 
As established, the street pattern of Tarbert Conservation Area and wider village is
intrinsically linked to the topography and historical development of the area. 
This topography has provided a natural restriction to the development of the village. 
The village follows a logical pattern of streets radiating from Harbour Road on the
loch side edge in the village centre, graduating up into the hillside with Pier Road
extending from the village centre along the south of the loch side, eastward to the
Old Pier. The main routes through the village centre form a slight ‘V’ shape where
Campbeltown Road and Barmore Road slope to meet at the tip of the harbour walls.
Barmore Road rises north up the hillside to leave Tarbert, while Garvel Road forks
off to follow the northern edge of the loch side. 
In a street pattern that has remained relatively unchanged for centuries, streets are
principally loch facing as they hug the loch side providing panoramic viewpoints.
Similarly, as the streets radiate up the hillside from the loch side, views to the loch
are maintained.
Page 150

Page 151

4.3.1 
Photographs of
the Old Library on
Barmore Road close
and back court with
cobbles.
Frontages & Beyond 
These strong street frontages are punctured by vennels secured by metal gates
which lead to back court areas that are often carved out of the bedrock or within
rock outcrops which often retain their native flora of gorse bracken and brambles.
In many of these back courts there are historic structures, such as outhouses and
stables, ancillary to the main buildings. 
Arguably, the pattern of vennels, court yards and ancillary buildings contributes just
as significantly to the street pattern and character of Tarbert Conservation Area as
the frontages. 
Photographs
Top left: Pend
at the Starfish
Restaurant on
Castle St. 
Top right: Pend at
1 Argyll Place. 
Bottom left and
right: back court
/ garden areas
that carved out
of bedrock to the
buildings along
Harbour Road.
Page 151

Page 152

4.4 
Photograph:
View looking
Eastwards towards
the Village Centre
from Pier Road.
Buildings & Townscape 4.4 .1 
Photograph:
Description Tarbert,
Tarbert Castle.
General view from
South.
Date 1967
Collection Records
of the Royal
Commission
on the Ancient
and Historical
Monuments of
Scotland (RCAHMS),
Edinbugh
Catalogue Number
SC 2527117
Category On-line
Digital Images 
Map:
Description Tarbert,
Tarbert Castle. Part
plan of site, sheet 1.
Date 1966
Collection Records
of the Royal
Commission
on the Ancient
and Historical
Monuments of
Scotland (RCAHMS),
Edinburgh
Catalogue Number
DP 339485
Category On-line
Digital Images
Scheduled Monuments 
A scheduled monument is a site of
national importance that is protected
by law and maintained by Historic
Environment Scotland. Scheduled
monuments can be buildings, structures,
caves, or excavations that are above or
below the surface. 
Tarbert Castle
SM276
designated in 1935 
Full HES listing can be viewed online:
Tarbert Castle (SM276)
Page 152

Page 153

02 
4.4 .2 
Photographs:
Top right:
Tarbert Hotel
Harbour Street 
Bottom left:
Old Harbour
Master’s Office,
Harbour Street 
Bottom right:
Larkfield
Garvel Road, Tarbert
Key listed and unlisted buildings 
Refer to Gazetteer within the appendix
for listing, description and photographs
of each building within the Conservation
Area. 
The table on the following pages lists
key listed and unlisted buildings. 
Building /
Structure
Category Listing
/ Scheduled
Monument
Within Tarbert
Conservation Area
Within Tarbert
Regeneration
Scheme Boundary 
‘Larkfield’, Garvel
Road 
C Yes  No
‘Lorne Villa’,
Garvel Road 
B Yes  No
‘Lorne Cottage’,
Garvel Road 
C Yes  No
Victoria Hotel,
Barmore Road 
C Yes  Yes
Tarbert Harbour
Walls Including
Former
Weighbridge,
Slipways and
Beilding 
B Yes  Yes
Tarbert Church
Of Scotland,
Campbeltown
Road 
B Yes  No
Tarbert Hotel,
Harbour Street,
Kintyre Place, And
Church Street 
C Yes  Yes
‘Queensgate’ Peir
Road 
C Yes  Yes
Columba Hotel,
Peir Road 
C Yes  Yes
Peir House, Peir
Road 
C Yes  Yes
Argyll Place &
ancillary structures 
Not listed  Yes  Yes 
Page 153

Page 154

4.4 .3 
Photographs
Top right: view to
the marina from
the harbour. 
Bottom right: view
back to the village
from Pier Road.
Sense of place and intangible
qualities
The way in which the built environment
engages with the dramatic natural
geology and coastline provides a unique
experiential quality within each character
area of the Conservation Area. 
There is a contrast between the Village
Centre and the other character areas
within the Conservation Area. 
The village centre is noisy with the bustle
of people, sea gulls, traffic, and general
activity in and around the harbour,
marina and shops. 
There is a quieter, calmer atmosphere
around the high ground at the castle,
along Pier Road and Garvel Road.
These three areas offer incredible
vantage points and a connection to
nature. Furthermore, the castle remains
and archaeology within Tarbert Castle
Heritage Park, offer a connection to an
ancient past and geology. 
Along Pier Road and Garvel Road there
is a close connection to the loch where
the lapping of water and bird song are
inescapable. 
Several public benches are available
throughout the Conservation Area, which
offer people the opportunity to sit and
experience the unique qualities of each
space. 
It is perhaps these intangible qualities
and sense of place that have made
Tarbert such an attractive place to
people since the first century.
The Old Bank Not listed Yes Yes
The Old
Chandlery,
Harbour St
Not listed Yes Yes 
The Old Harbour
Master Office 
Not listed  Yes  Yes
Leitch & Son
Sailmakers,
Garval Terrace 
Not listed  Yes  No 
Undercliffe,
Harbour St 
Not listed  Yes  Yes
Quay House,
Harbour St 
Not listed  Yes  Yes 
Page 154

Page 155

4.5 
Photographs
Top right: Southern
backdrop of the
Conservation Area. 
Bottom right: view
to Garvel Road
and the marina
from the harbour.
Open Spaces and Landscape
Setting
As described, Tarbert’s natural
topography has largely informed the plan
of the village and as such there are no
formal public designed landscapes or
gardens within the Conservation Area. 
Telford’s harbour wall is one of the
most significant man-made structures
impacting upon the natural landscape
setting however even this construction
has been designed to support the
topography of the natural harbour. 
The beauty of the natural topography
and landscape setting of the
Conservation Area and wider geological
context of the village of Tarbert,
described previously, is augmented by
the lush vegetation that exists all year
round in both private gardens and public
areas. 
Generally, the vegetation is a mix of
native and some non-native species
of flora and trees, mostly typical to the
costal location. Over time introduced
planting and native woodland have
created an important characteristic of the
Conservation Area.
4.5 .1 Open Spaces 
There are a number of public spaces within the Conservation Area, which are
distinct in their character and landscape setting.
Page 155

Page 156

4.5 .1.1 Tarbert Castle Heritage Park 4.5 .1.2 The Promenade 
Photograph:
Looking south to
Tarbert Castle
Heritage Park
which forms the
back drop to the
village centre
character area.
Tarbert Castle Heritage Park is a public area located on the high open grassland
plateau around the castle, which leads to an orchard, community woodland and
sculpture trail beyond. Places to sit, informal pathways and boardwalks lead through
interpretation of the historic castle structure and adjacent archaeological finds as
well as to key panoramic viewpoints over the village of Tarbert, the loch and the
Kintyre beyond. 
More information relating to Tarbert Castle Heritage Park can be found at:
https://www.tarbertcastle.info/ 
The woodland in this area was planted in the early 2000s and includes native tree
species such as Alder, Birch, Hawthorn, Rowan and Willow with a ground cover of
Calluna, also known as Ling heather. 
The importance of this area of land on the character of the village was established
in 1977 when the Conservation Area was enlarged to include the slope to the
woodland. This high ground is important as it provides the southern backdrop to the
Conservation Area.
Photographs:
Top: view to the
West along the
promenade. 
Bottom: The
marnia and leisure
area.
The modern pedestrian promenade runs
parallel to Garvel Road at lower level
hugging the shore of the loch. It provides
an area of car-free public realm,
connecting Harbour Street to the marina,
leisure and events developments to the
northwest of the loch. 
This area also provides key viewpoints
back to the village centre and the south
shore of the loch to Pier Road. 
The adjacent landscape of the Garvel
peninsula is relatively untouched with
rugged rock outcrops and native trees
such as Birch, Hazel, Willow and Scots
Pine, with a ground cover of bracken,
blaeberry, ferns and sedge grasses. 
Page 156

Page 157

4.5 .1.3 Pier Road 4.5 .1.4 Tarbert Parish Church 
Photographs:
Informal parking
eroding the grass
verges along Pier
Road,
Although there are no pavements or footpaths, Pier Road could be said to provide
an informal promenade to the south side of the loch. It is characterised by villas
with dry stone boundary walls to the south of the road with an informal grass verge
of varying widths to the shoreline, which extends right to the boundary of the
Conservation Area at the East Loch Tarbert viewpoint and memorial. 
The tops of some of the boundary walls to the private plots are planted with Privet or
Griselinia hedges while some boundaries are less formally planted with ornamental
shrubs such as Hydrangea and Fuschia. A common characteristic is vegetation
growth of sedums and ferns from the dry stone walls and bedrock planted up with
ornamental shrubs. 
Playfully coloured seating and some shelters are dotted along the grass verge on
this route facing outwards to the rocky shoreline and verge. However as noted in the
2020 Conservation Appraisal, the character of this setting is at risk due to informal
parking eroding the grass verges.
Photographs:
Left: view
East down
Campbeltown
Road to village
centre. 
Right: view of
Tarbert Parish
Church North
Elevation.
Tarbert Parish church sits to the western extent of the Conservation Area on a
grassy embankment raised from street level. The church sits back from the pattern
of the street scape creating an open space around the front of the building to signify
its importance to the community at the time of building. The gates to the grounds are
not locked allowing free public access to this space. 
The raised ground also assists in the verticality of the church tower which is a
significant element of the townscape skyline. 
Page 157

Page 158

4.5 .1.5 White Shores (Port Ban) 4.5 .2 Tree Preservation Orders 
White Shores skirts the northern
side of Tarbert Harbour at the mouth
of East Loch. Although out-with the
Conservation Area, it is an open public
space offering key viewpoints back to
the townscape and sea inlets.
Photograph:
Left: Trees and
vegetation growth
on the rock
outcrops along
Pier Road. 
Right: Common
Alder Tree at
Battery Point is the
only landmark tree
within the Tarbert
Conservation Area.
Any tree within the Conservation Area is protected and permission may be required
to cut, lop, or uproot etc. In addition to this there are a number of Tree Protection
Orders within the Conservation Area. 
See paragraph 73 of:
Scottish Planning Series: Planning Circular 1 2011: Tree Preservation Orders 
The trees within Tarbert Conservation Area play a significant role in the character
of the landscape setting and it is important that this is considered when considering
any future development. 
Page 158

Page 159

4.5 .3 Nature of dominant species 4.6 Character Areas and aspects of
distinctiveness 
4.5 .4
The following native tree species can be found within the Conservation Area;
Alder, Birch, Common Ash & Sessile Oak
The following non-native tree species can be found within the Conservation Area;
Beech, Sycamore, Whitebeam and Ornamental Cherry
Dominant evergreen species is Scots Pine. 
Non-native ‘exotic’ tree species as follows;
Crimean Pine, False Cypress, Monkey Puzzle and Silver Firs 
Landmark Trees
Photograph:
View from the
marina to the
harbour, village
centre and castle.
The character of an area is derived from what makes it unique in comparison to any
other place. The character of Tarbert Conservation Area can be categorised into
four distinct character areas; the Village Centre, Pier Road, Barmore Road & Garvel
Road and Tarbert Castle. 
Generally, within each area the prominence and importance of traditional windows
to the overall character of the Conservation Area is of considerable significance. 
A Landmark tree can be defined as a tree or grove of trees of historical or cultural
value, an outstanding specimen, an unusual species and/or of significant community
benefit. 
The Common Alder Tree at Battery Point is the only such tree within the Tarbert
Conservation Area.
Page 159

Page 160

4.6.1 The Village Centre
Harbour St, Barmore Rd & Campbeltown Rd 
Photograph:
Top: View looking
East along
Harbour Street. 
Bottom: View
showing harbour
from Tarbert
Castle. 
Opposite page:
View East towards
Harbour Street
from Barmore
Road.
The iconic character of the village
centre was predominately established
around the activity and development
of the fishing harbour in the 1800s.
The uninterrupted line of colourful
building frontages, many with traditional
shop fronts, creates a strong sense
of enclosure around the harbour from
which the townscape pattern is set. 
The Category B listed dry stone harbour
walls, beilding in the mid harbour,
weighbridge, and cottage, constructed
of locally quarried stone, which were
designed by Thomas Telford. These
remain integral elements of the village
centre and harbour character. The lines
of the harbour walls act to reinforce the
architectural enclosure. 
Although mostly 19th century
construction, there are varying
architectural styles with some modern
insertions, all varying in quality. The
scale of buildings is a mix of two and
three storeys with attic dormers and
distinct gable ends, creating a rhythm
of change in scale and articulation of
roofline which is unique to Tarbert and
a key townscape feature. Furthermore,
the characterful articulated rooflines
of the buildings to the inner harbour
are complimented by the Scots Gothic
steeple of Tarbert Parish Church further
up the hillside on Campbeltown Road.
Page 160

Page 161

4.6.1.2 The Village Centre
Harbour St - West 
Photograph:
Top: View looking
East along
Harbour Street. 
Bottom: Out
buildings at 1
Argyll Place.
Generally, the buildings along Harbour
Street follow a traditional tenement
arrangement with shop fronts or public
access at ground level and housing
above creating a strong commercial
heart to the village. Shop frontages
which have retained their historic
proportions and features contribute
significantly to the character of the area. 
This pattern is interrupted only by
buildings such as the Tarbert Hotel
and Templar Arts Centre and the poor
quality modern WC block. 
Beyond the street frontages of the
buildings along Harbour Road and the
village centre area are ‘back courts’
which are cut into the rock formations
of the hillside. Accessed through pends
many of these areas contain small
scale out-buildings or the remains of,
which historically were likely to have
been stables or for other uses. The
out buildings at Argyll Place are an
interesting example. ¬ 
The character and scale of the
outhouses within the ‘back courts’,
which are reminiscent of the older village
of Tarbert, continues behind Harbour
Street, along Castle Street, School Road
and Brunswick Street creating another
important defining element of the
townscape.
As Harbour Street progresses east, the
Page 161

Page 162

4.6.1.2 The Village Centre
Harbour St - East
4.6.1.3 The Village Centre
Barmore Road 
Photograph:
Top: View looking
West along
Harbour Street. 
Bottom: Undercliffe
building.
traditional retail units stop and buildings
associated with the fishing industry
begin indicating a change in character
and scale of architecture. One storey
buildings such as those at Fish Quay
and the Harbour Authority, the old
Chandlery and old Harbour Masters
office have an industrial quality. The
Undercliffe tenements have arched
openings with ledged and braced doors
at ground floor. 
The juxtaposition of these building
types with the contrasting village centre
tenement typology contribute greatly
to the unique character of the area,
reinforcing the significance of the fishing
industry in Tarbert. 
The southern end of Barmore Road
Photograph:
Top: View looking
North down
Barmore Road. 
Bottom: Old
Library window
details. 
Opposite page:
View West to
Barmore Road
from the harbour.
forms a ‘V’ shape with Harbour Street
as it follows the line of the harbour, with
the buildings following the same scale
and architectural tenement typologies
as those described on Harbour Street.
Particularly distinctive architecture such
as the Bannockburn Building and the
old Library contribute significantly to the
townscape character. 
The continuous street frontage to the
commercial heart of the village stops
at the prominent bright yellow, old
Victoria Hotel. The yellow gable of
the old Victoria Hotel acts as marker
when arriving on Barmore Road as it
introduces the gable-to-gable rhythm of
the village centre streetscape. From here
this frontage rhythm breaks down into
detached mostly Victorian villas on the
hillside surrounded by lush vegetation.
Campbeltown Road becomes a
continuation of Harbour Street westward,
at the ‘V’ with Barmore Road, making
this an important point in the Village
Centre streetscape. It is marked on the
southern edge by a red sandstone two
storey building with a unique turreted
corner bay. 
There is a mix of shopfronts within the
village centre, a noticeable number
of which are classically proportioned.
There are also a number of traditional
timber windows of note.
Page 162

Page 163

4.6.1.4 The Village Centre
Campbeltown Road 
Photograph:
Top: Beginning
of Campbeltown
Road from the
Village Centre. 
Bottom: View
East towards the
Village Centre
from Campbeltown
Road.
Campbeltown Road consists of
residential plots of various dates and
architectural styles on both sides of
the road. However, the most prominent
building is Tarbert Parish Church.
Sitting in an elevated position over the
village, with its Scots Gothic tower, the
architecture creates many key views and
is a critical element of the townscape
character. 
Page 163

Page 164

4.6.2 
Photograph:
Top: View East
along Pier Road. 
Bottom: Modern
extension to the
old Columba Hotel
(Category C listed)
Pier Road 
Pier Road is an eastward continuation
of Harbour Street. It is formed of a
composition of predominantly, handsome
Victorian villas of various scales, whose
plots follow one side of the road along
the south lochside providing panoramic
views across East Loch Tarbert and
Loch Fyne, continuing east from the
edge of the village centre, past the
East Pier and Battery Point to the
Conservation Area boundary at Old
Pier. Most plots are demarcated by
freestanding dry-stone walls that are in
retention to the front / roadside. 
The architecture of Pier Road is
reflective of the prosperity of the village
around the Victorian era. 
The pattern of the dry-stone walls and
decorative iron gates to gardens with
their mature and ornamental planting,
that appear to be carved out of the
hillside bedrock, contribute significantly
to the character of this area. 
In contrast Pier House is distinct in its
older, more simple architectural form
as it deviates from the Victorian street
pattern sitting hard to the roadside with
no front garden. Again this contributes to
the character of Pier Road in revealing
an earlier domestic architectural style.
4.6.2.1 
Photograph:
Top: Old Pier
House (Category C
lised) 
Bottom left:
Fishermen’s
memorial at Old
Pier. 
Bottom right:
East Pier
Pier Road
East
The relative tranquility of much of Pier
Road is interrupted by the daily flow of
passengers and vehicles at the roll-on
roll-off ferry slip at Battery Point as well
as the small scale fishing which takes
place off timber East Pier. Indeed this
activity is heightened when the Waverly
docks and several hundred passengers
descend onto Pier Road to walk into the
village centre. 
Tarbert’s deep routed connection with
the water is reinforced at the Old Pier
where a poignant memorial to two
fishermen has been placed.
Page 164

Page 165

4.6.3 Barmore Rd (North) & Garvel Road 4.6.3.1 Garvel Road Views 
Photograph:
Top: Northern end
of Barmore Road. 
Bottom right:
Lorne Villa on
Garvel Road -
Category C listed,
burnt out in a
house fire in 2020.
Generally, this character area is a mix of
architectural styles and uses to the North
of East Loch Tarbert, animated by the
activity of the marina. 
The Northern end of Barmore Road and
northern tip of Lady Ileene Road are in
an elevated position. Low plot density
means there are a small number of
cottages and semi-detached dwellings
with frontages on to Barmore Road,
characterised by their rubble boundary
walls and mature garden planting and
hedges. 
The townscape character is
compromised in this area by the varying
quality of contemporary development
which does not respond to the
established boundary patterns. 
Garvel Road sweeps down below
Barmore Road as it follows the line
of the lochside to the north. The
marina and associated single storey
contemporary buildings, dominate to the
west end while the road continues east,
the character is quiet and domestic. In
ways the character of Garvel Road is
similar to Pier Road however Garvel
Road is slightly denser and more
informal in plot layout and there are
more contemporary dwellings of varying
quality.
Photograph:
Top: Sail makers
on Garvel Road. 
Bottom:
View to Garvel
Road and the
marina from the
harbour.
Perhaps the key character value of this
area is assessed in relation to the views
to and from Garvel Road and how they
impact the wider conservation area. 
This area also provides significant
associations with not only Tarbert’s
maritime cultural heritage but its
importance to the village today.
Page 165

Page 166

4.6.4 
Photograph:
Top: View East to
the castle tower 
Bottom:
View to the castle
tower from Pier
Road.
Tarbert Castle 
This character area of Tarbert Castle
includes the curtilage of the 15th century
castle tower house remains, which is a
scheduled monument. The castle tower
is located on the elevated plateau to the
Southeast of the loch, overlooking Pier
Road, and associated with the Tarbert
Castle Heritage Park and Community
Woodland and Nature Conservation
Area in the sheltered valley beyond. 
There is a quintessentially Scottish
romanticism about the ruins within this
conserved hillside that is special. The
high position of the castle not only acts
as an indicator to the inner harbour but
provides an enduring focal point that
contributes significantly to the character
of Tarbert Conservation Area. 
Indeed the draft 2019 Conservation
Area Appraisal remarks, ‘The ruinous
composition has a townscape
counterpoint to the insistent verticality
of the steeple.’ These two vertical focal
points act as bookends to the village.
From the tower itself, there are
unparallelled panoramic views over
Loch Fyne and the Western shore of the
Cowal Peninsula as well as down on to
the roofscape of Pier Road and the inner
harbour itself and across to Garvel and
Barmore Road character areas. 
The interpretation, walkways, seating,
and covered shelters make the castle
grounds a place where people can
spend time.
4.6.5 
Photograph:
Opposite
page:view East to
Harbour Street and
the Harbour.
Key aspects of distinctiveness 
We have identified the following characteristics as contributing to Tarbert
Conservation Area’s unique character. These aspects should be protected and
enhanced when considering any future development. 
• Tarbert Castle and Heritage park 
• The townscapes intrinsic relationship to the natural landscape and
lochside bay setting 
• Connection with the water and panoramic vistas / key views 
• Strong frontage, gables and articulated roofline of the Village Centre
Character Area 
• Back Courts and Pends within the Village Centre Character Area 
• Distinct character of each area within the Conservation Area –
residential, working fishing port & harbour, the busy village centre, the
marina and the quiet of Tarbert Castle and Old Pier 
• Category B listed harbour walls 
• Distinctive skyline with contrasting vertical structures – Tarbert Castle
and church steeple 
• Historic fishing related structures and architectural elements,
particularly the store doors 
• The prominence and importance of traditional timber windows
Page 166

Page 167

4.6.6 Negative impacts on character 
Following our study of the historic development and unique character of Tarbert
Conservation Area it is necessary to list any negative factors that detract from or
threaten the special character and appearance of the townscape.
Generally, the building fabric and associated traditional features and materials,
within the Conservation Area, are vulnerable due to several factors which are often
linked: 
• The age of the building stock – mostly 19th century 
• Lack of planned maintenance and inspections which is often linked
with ownership and vacant properties and lack of knowledge. 
• Flooding / Severe weather conditions due to West of Scotland location
and Climate Change 
• Economic Climate and escalating cost of repairs 
• Lack of traditional skills 
• Difficulty and cost of safe access to carry out inspections and repairs 
• Lack of public knowledge regarding historic building conservation and
maintenance or grants available. 
• Absentee owners 
• Inappropriate development in the Conservation Area 
• Inappropriate alterations to heritage assets 
• Loss of historic architectural detail from heritage assets 
• Inappropriate shop frontages and signage. 
It is understood that issues around closing businesses and vacant shop units can
be attributed to lack of affordable housing to buy or rent for workers. Businesses are
therefore unable to recruit or retain staff. Inadequate public transport can also make
employment in Tarbert prohibitive.
Page 167

Page 168

5.0 Public Realm 
Photograph:
Top left: Tarbert
Hotel falling into
disrepair - hotel not
in use. 
Top right:
Loss of historic
architectural detail. 
Bottom left:
inappropriate shop
frontages and
signage. 
Bottom right:
UPVC windows
and downpipes
and cement
repairs.
Photograph:
Top right:
benches placed at
view points along
the lochside on
Pier Road. 
Bottom left:
Wayfinding
signage and
interpretation
panels at stairs to
Tarbert Castle from
Harbour Street. 
Bottom right:
Wayfinding
signage,
interpretation
and seating in
the vi;;age centre
at the corner of
Harbour Street and
Barmore Road.
Street furniture is adequately provided,
well maintained, and well positioned at
interesting vantage points around the
Conservation Area and beyond. 
Way finding signage for visitors and
pedestrians could be improved.
Page 168

Page 169

6.0 Photographic Record of Buildings
Gazetteer
7.0 Potential Buildings at Risk &
Analysis of Sensitivity 
Photograph:
Bottom left:
Harbour Street and
1 Argyll Place in
the village centre. 
Bottom right:
Queen’s Gate, Pier
Road (Category C
listed)
A photographic record of the buildings and structures within the Conservation Area
is provided as an appendix to this report within a Gazetteer. 
Photographs were taken between May and October 2024. The photographs are
intended to record the condition of the buildings at this time including and any
alterations carried out to serve as a monitoring indicator and enforcement tool if
required. 
The photographic survey shows that the condition of the buildings varies due to the
factors documented previously.
Photograph:
Bottom left:
Tarbert Hotel,
Harbour Street. 
Bottom right:
Glendale, Kintyre
Street.
The Scottish Civic Trust definition of a building at risk is the following; 
A Building at Risk is usually a listed building, or an unlisted building within a
conservation area, that meets one or several of the following criteria: 
• vacant with no identified new use
• suffering from neglect and/or poor maintenance
• suffering from structural problems
• fire damaged
• unsecured and open to the elements
• threatened with demolition 
As of September 2024, the Buildings at Risk Register has been paused while
alternative approaches are considered. At this moment in time, no more buildings
are currently being considered for inclusion. However, the following buildings, which
contribute to the character of the Conservation Area, are particularly vulnerable and
meet some of the criteria of a Building at Risk. 
Page 169

Page 170

01 
7.1 Schedule of Buildings at Risk 
The following schedule lists the buildings considered to be at risk and reasoning
why.
Building /
Structure
Category
Listing /
Scheduled
Monument
Within Tarbert
Conservation
Area
Within Tarbert
Regeneration
Scheme
Boundary 
Glendale,
Kintyre Street 
Not listed  Yes  Yes  • vacant with no
identified new
use
• suffering
from neglect
and/or poor
maintenance
• suffering from
structural
problems (TBC
by Engineer)
‘Lorne Villa’,
Garvel Road 
B Yes  No  • fire damaged 
Out buildings
within back
courts
generally 
Some may
be listed
within the
curtilage
of a listed
building 
Yes  Yes  • vacant with no
identified new
use
• suffering
from neglect
and/or poor
maintenance
• suffering from
structural
problems (TBC
by Engineer)
• unsecured and
open to the
elements 
East Pier  Not Listed  Yes  No  • suffering
from neglect
and/or poor
maintenance
• suffering from
structural
problems (TBC
by Engineer) 
Tarbert Hotel,
Harbour
Street, Kintyre
Place, And
Church Street 
C Yes  Yes  • vacant with no
identified new
use
• suffering
from neglect
and/or poor
maintenance 
Page 170

Page 171

7.2 Summary 8.0 Values & Significance 
Photograph:
Top right: the old
Bank, Harbour
Street. 
Bottom right:
Victoria Hotel,
Barmore Road.
Town and Country Planning legislation
provides laws and regulations that
provide protection to built heritage at
risk. 
In addition to the buildings identified as
potentially at risk, the village centre is
also vulnerable to the national trend of
decline in the local high street which
in turn has a significant impact on the
character of the place. 
The village centre has seen the recent
closure of key amenities including
the bank and butchers as well as the
relocation of Tarbert Life, which has left
a prominent corner unit vacant. 
The Tarbert Hotel is a listed building
located in another prominent position at
the heart of the village centre, within the
Conservation Area, that has fallen into
disrepair and is now closed to the public.
Indeed, the Victoria Hotel on Barmore
Road is also closed to the public and is
at risk of also falling into disrepair.
For the purposes of this Conservation Area Appraisal, the values used are those
set out in the book Managing the Built Heritage: the Role of Cultural Values and
Significance by Stephen Bond and Derek Worthing. 
It should be noted that significance is assessed in relation to social and cultural
value while character can be defined as a unique set of qualities that distinguish one
place from another. 
Levels of significance: 
• Exceptional - international importance 
• Considerable - national importance (e.g. category A-listed, scheduled
monument, Inventory landscape) 
• Some - regional importance or group value
• Limited - local importance 
• Unknown/No - insufficient information or no evident significance
Page 171

Page 172

01 
8.1 Schedule Summary 
The following schedule lists the values and level of significance of key areas within
the Conservation Area. 
• Aesthetic 
• Scenic/panoramic 
• Architectural / technological 
• Historical 
• Associational 
• Archaeological 
• Economic 
• Educational 
• Recreational 
• Artistic 
• Social 
• Commemorative 
• Symbolic / iconic 
• Value 
• Spiritual & Religious 
• Inspirational 
• Ecological 
• Environmental
Value Key Area Level of Significance 
Aesthetic All areas of the
Conservation Area
contribute to this value 
Considerable 
Scenic/panoramic All areas of the
Conservation Area
contribute to this value 
Considerable 
Architectural /
technological
All areas of the
Conservation Area
contribute to this value,
but the Harbour Walls
in the Village Centre
Character Area are
arguably the most
significant. 
Some 
Historical All areas of the
Conservation Area
contribute to this
value, but Tarbert
Castle Character Area
is arguably the most
significant. 
Considerable 
Associational Village Centre and Tarbert
Castle Character Areas 
Some 
Archaeological Tarbert Castle Character
Area 
Considerable 
Economic All areas of the
Conservation Area
contribute to this value,
but Tarbert Castle
Character Area and
Village Centre Character
Area arguably the most
significant. 
Considerable 
Educational All areas of the
Conservation Area
contribute to this value,
but Tarbert Castle
Character Area and
Village Centre Character
Area arguably the most
significant. 
Considerable 
Page 172

Page 173

02 
8.2 
Photograph:
Tarbert Harbour
Description of Values 
The following section describes the the values and reasoning for level of
significance. 
Recreational All areas of the
Conservation Area
contribute to this value,
but Tarbert Castle
Character Area and
Village Centre Character
Area and the marina
are arguably the most
significant.
Considerable 
Artistic All areas of the
Conservation Area
contribute to this value 
Limited 
Social All areas of the
Conservation Area
contribute to this value,
but the Village Centre
Character Area and the
marina are arguably the
most significant. 
Considerable 
Commemorative Old Pier, Pier Road
Character Area 
Some 
Symbolic / iconic All areas of the
Conservation Area
contribute to this value 
Considerable 
Value  Key Area  Level of Significance 
Spiritual & Religious Tarbert Castle Character
Area & Tarbert Church Of
Scotland, Campbeltown
Road, Tarbert Village
Centre Character Area 
Limited 
Inspirational All areas of the
Conservation Area
contribute to this
value 
Considerable 
Ecological All areas of the
Conservation Area
contribute to this value
(with the Village Centre
Character area being
least significant) 
Considerable 
Environmental All areas of the
Conservation Area
contribute to this
value 
Considerable 
Page 173

Page 174

8.2.1 Aesthetic Value 8.2.2 Scenic / Panoramic 
Photographs:
Bottom left: Detail
of a garden wall at
the eastern end of
Pier Road. 
Bottom right:
Lochside with view
to the castle tower
at Pier Road.
(capacity to elicit sensory pleasure: atmosphere, spaces, colours, textures, sounds
and even smells) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: The definition of Aesthetic as set out in the categories that inform this
document, states this is ‘what makes a sense of place’ and should take cognisance
of full sensory experience of the place – both tangible and intangible. In the case of
Tarbert Conservation Area, it is an important example of a West of Scotland fishing
community, within a picturesque landscape setting. Each character area defined by
its aesthetic and unique atmosphere, which is created through sensory experience
– materiality, colour, smell and sound, as well as the architecture and relationship to
the land and water.
Photograph:
Panoramic view
from Castle
Heritage Park.
(scenic: beauty in a confined setting / panoramic: long views and sweeping outward
vistas) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: These values are closely related to aesthetic values but are concerned
with scenic outward vistas and the more confined beauty of a smaller setting. Each
character area of Tarbert Conservation area offers their own unique long views and
sweeping outwards vistas to the village harbour, East Loch and Kintyre beyond,
representing important viewpoints of this area of the West of Scotland. 
Page 174

Page 175

8.2.3 Architectural / Technological 8.2.4 Historical 
Photograph:
View around the
harbour and walls.
(example of an architectural idea or movement; craft value; development of
technology and materials) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Some 
Reasoning: Architectural value is concerned with representing a fine example of
an architectural typology or development of technology. In this respect Tarbert
Conservation Area has some significance which is evidenced in the Category B
designation of some buildings and the harbour walls.
Photograph:
Historic
Photograph from
Tarbert Life -
undated. Likely
mid 19th century.
Source: Tarbert
Life.
(capacity of a site to convey links to the past) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: This value is of fundamental importance in the assessment of built
heritage and to some extent underpins and validates the other values. This value is
concerned with a site’s capacity to convey a link to the past. 
Tarbert Conservation Area, with all its components in relation to fishing and
maritime, has considerable historical value in conveying links to the changing daily
life in a West of Scotland coastal community, which date back to as early as the first
century. 
Page 175

Page 176

8.2.5 Associational 8.2.6 Archaeological 
Photograph:
Historic postcard of
Tarbert Castle from
Tarbert Life - dated
1904
Source:
Tarbert Life.
(substantial link to a person or event) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Some 
Reasoning: As this value is related to a particular event or person, we have
assessed that Tarbert Conservation Area is of some associational significance.
Although the area is of considerable historical and archaeological significance and
has links to Robert the Bruce, as far as we understand, there are no particularly
unique links to significant people or historic events.
(value linked to educational value and relates to be ability to be a source of
information about the past through scientific investigation)
Location / Description: Tarbert Conservation Area, Argyll & Bute
Level of Significance: Considerable
Reasoning: This value relates to the site being able to serve as an educational
tool. Linked with heritage value there is considerable educational value associated
with Tarbert Castle and the surrounding Heritage Park. Furthermore, there may
be further educational value in any undiscovered archaeology in relation to the
castle and early settlement that could potentially increase this value to exceptional
dependent on discoveries. 
Page 176

Page 177

8.2.7 Economic 8.2.8 Educational 
(value linked to how much money can be generated either directly through
admissions, sales etc or indirectly through attracting visitors, value of land etc) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: This value is concerned with the area’s ability to generate revenue
either directly or indirectly. All areas of the Conservation Area do generate income
for the community at present however each area, particularly the village centre
and Tarbert Castle, potentially have the ability to increase generation of direct and
indirect income in line with the Local Development Plan 2 policies to grow Argyll and
Bute communities.
(derived from historical value of the place and a person’s sense of curiosity to learn
more etc) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: This value is related to the historical value of the site and its ability to
stimulate a person to learn more. Our assessment is that Tarbert Conservation Area
and its setting is of considerable educational significance due to the historic, social,
archaeological, aesthetic, and environmental significance, however, this value could
be strengthened if any future development included a more coherent interpretation
strategy that considered all educational aspects of the village and setting.
Page 177

Page 178

8.2.9 Recreational 8.2.10 Artistic 
(value as an amenity - engagement with the past may be primary or secondary
reason for the visit) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: This value is concerned with the site as a source of recreation, where
engagement with heritage may be the secondary reason for the visit. This is true
for Tarbert Conservation Area. Our assessment is that Tarbert is a ‘stop’ on a longer
journey for cyclists, tourists, and sailors. The harbour, marina, panoramic views and
associated aesthetic values with walks, as well as being a stop on the Waverley
Steamer, are arguably the most common reasons to visit the village. We anticipate
that these reasons will remain so for years to come and that these important existing
assets could be enhanced to increase recreational and educational values which in
turn could increase economic value for the community.
(value closely related to historical and educational value - may be related to the
work of a particular person, artistic or architectural movement) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Limited
Reasoning: This value is concerned with the relationship a site may have with the
artistry of a particular person or movement. Although the site is of considerable
aesthetic value, there is no evidence of a clear association with a particular artist or
movement so we have assessed Tarbert Conservation Area as having limited artistic
significance in relation to these values. Page 178

Page 179

8.2.11 Social 8.2.12 Commemorative 
(meaning that an asset has for individuals or groups because of association they
have with it or events that occurred there) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: This value refers to social cohesion and group identity relating to
events that have occurred at a site. This value is closely related to the considerable
significance in the site’s historic and iconic significance in that the village brings
together the past and present West of Scotland coastal communities as well as
maritime and fishing communities. Events such as the annual Scottish Series Yacht
Regatta and various festivals held throughout the year cement Tarbert as a social
centre.
(asset may or may not be located where the event took place) 
Location / Description: Old Pier - Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Some 
Reasoning: This value is associated with a place designated for commemoration.
A memorial for two fisherman who lost their lives in a tragic accident on Loch
Fyne when their fishing vessel capsized, is located at the Old Pier, to the far east
of the Pier Road Character Area. As far as we understand there are no other
commemorative sites within the Conservation Area. Page 179

Page 180

8.2.13 Symbolic / Iconic 8.2.14 Spiritual & Religious 
(value can be interpreted differently by different groups, linked with a sense of
belonging and home) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: This value can be interpreted differently by different groups but is
often linked to a sense of home, and of belonging. Tarbert is of considerable iconic
significance to visitors and locals alike. Closely related to social value, the place is
of considerable iconic significance to fishing and maritime communities as well as
locals in terms of its long history and the unique relationship its built heritage has to
the natural form of the landscape. This relationship is particularly distinctive when
viewed from the water.
(contribution to the spiritual or belief system of a cultural group)
Location / Description: Tarbert Conservation Area, Argyll & Bute
Level of Significance: Limited
Reasoning: This value is associated with a place of religion or spirituality. Although
Tarbert has an ancient history and long-established Christian heritage, as far as we
understand there is no known spiritual and religious significance associated with
Tarbert.
Page 180

Page 181

8.2.15 Inspirational 8.2.16 Ecological 
(ambiguous to define but related to inspirational drive or emotions)
Location / Description: Tarbert Conservation Area, Argyll & Bute
Level of Significance: Considerable
Reasoning: This value can be difficult to define and can be personal in nature
however it can be defined as a place that is ‘awe-inspiring’. In terms of making
our assessment we have considered the unique aesthetic, scenic and panoramic,
historical and iconic qualities of Tarbert to conclude that this is a place of
considerable inspirational significance. There are pockets of the Conservation Area
which demonstrate more of this value than others. For example the high ground
around Tarbert Castle, the Old Pier on Pier Road and east on Garvel Road offer the
most inspirational value due to their aesthetic quality and panoramic views of the
natural landscape and beyond to the waters of the loch.
(holistic value of living things with archaeology and history)
Location / Description: Tarbert Conservation Area, Argyll & Bute
Level of Significance: Considerable
Reasoning: The Ecological value should be assessed holistically and include
archaeology and history as well the ecology of the place. When we consider the
considerable historic value, potentially considerable archaeological value along with
the areas of natural terrain, vegetation and waters of the East Loch, we assess that
Tarbert Conservation Area has considerable Ecological value. Page 181

Page 182

8.2.17 Environmental 9.0 Summary of Assessment of
Significance 
(holistic value of natural surroundings & landscape) 
Location / Description: Tarbert Conservation Area, Argyll & Bute 
Level of Significance: Considerable 
Reasoning: The environmental value should be assessed holistically taking natural
surroundings and landscape into account. In this respect the setting of Tarbert
Conservation Area is of considerable significance due to the diversity of the natural
landscape, vegetation, and East Loch.
There has been settlement around the area that is now the village of Tarbert since at
least the first century which gives an indication towards the rich history of the area
and ancient roots of the community which sustained itself from the loch and natural
landscape which has in turn shaped the built heritage and industry of the village.
The combination of natural beauty and heritage, along with its continued activity as
a working fishing and maritime community, means that Tarbert has considerable
significance over numerous values of significance, such as aesthetic, scenic,
historical, archaeological, economic, educational, recreational, social, iconic,
inspirational, ecological and environmental. 
Although each Character Area of the Conservation Area contributes to the overall
value of the cultural significance of place, the Old Pier, Tarbert Castle Character
Area and the Village Centre Character Area, as well as the modern Marina are key
and offer the most opportunity for enhancement of existing assets.
Our assessment is that despite there being only some significant architectural value,
Tarbert Conservation Area is of considerable cultural significance meaning that it is
of national importance to Scotland, in response to the combination of its distinctive
features.
Page 182

Page 183

10.0 
Photographs:
Top:
Consultation board
panels 
Bottom:
Community
Consultation event
Community Engagement 
The local community need to be
genuinely engaged in their environment
and heritage in order that the integrity
of the area’s historic character is
celebrated, maintained, and managed
in a way that supports a community to
thrive for future generations. 
As part of the collation of information
for this Character Appraisal and
Management Plan, open consultation
was held with the community. 
Key interests for the local community at
this time include: 
• Housing 
• Heritage and Conservation 
• Amenities and Services 
• Community Spaces and
Facilities 
• Regeneration and
Development 
• Tourism and Economic
Development 
• Environment and Safety 
• Equity and Community
fairness 
A full report documenting the open
consultation and key findings is attached
to this document as an appendix.
11.0 Evaluation of Vulnerabilities &
Opportunities
With an understanding of the cultural significance of the area, it is important to
identify and evaluate the vulnerabilities which may impact the integrity, in parallel
with identifying opportunities to enhance the area and its heritage assets and in turn
consider what benefits these improvements could bring to the community of Tarbert
and the wider area. 
In order to analyse and make a holistic assessment of the conservation needs, this
section of the document provides commentary on the following; 
• Summary of the general fabric condition of heritage assets 
• Vulnerabilities of heritage assets and Conservation Area 
• Opportunities of heritage assets and Conservation Area 
• Approach to Climate Change
Page 183

Page 184

11.1 Summary of fabric condition of
Heritage Assets
11.2 Evaluation of Vulnerabilities &
Opportunities 
Generally, the building fabric of heritage assets within the Conservation area varies.
Many buildings, particularly in the Village Centre Character Area, are beginning to
deteriorate. The historic fabric and associated traditional features and materials
are failing in some cases, and damp, rot and decay are beginning to take hold. It is
important that action is taken to tackle these issues as soon as possible. 
The villas of Pier Road Character Area and Barmore Road (North) & Garvel Road
Character Area are generally in better condition although there are examples of
inappropriate alterations and repairs 
11.2.1
Photograph:
Brackenhill on
Harbour Street is
vacant and fallen
into disrepair.
Specific vulnerabilities to Tarbert Conservation Area are identified on the following
pages. 
Need for Repair
There are a number of historic buildings,
especially within the Village Centre
Character Area which have not been
adequately maintained or have poor
quality and or inappropriate repairs for
a traditional building. This could be the
result of the economic context / lack
of investment, climate change and the
impact of increased rainfall and extreme
weather, lack of skills & knowledge. 
Included within this is the East Pier
which is in poor condition. This is
particularly significant as this is where
the Waverly docks, bringing with it an
important stream of income for the
village.
Page 184

Page 185

11.2.2 
Photograph:
Historic
photograph
of flooding on
Barmore Road.
DATE TBC
Source: Tarbert
Life 
11.2.3 
Photograph:
Inappropriate
cement repairs.
Extreme weather
/ flooding
Tarbert’s exposed location and proximity
to the loch side makes it more vulnerable
to the effects of extreme weather and
flooding. 
Generally underground drainage and
rainwater goods on buildings need to
have capacity to cope with increased
rainfall. 
More specifically to Tarbert the increased
water run- off from the rock face is
impacting the drainage of adjacent
structures as well as causing loose rocks
to fall. Increased water levels and rainfall
also increase the risk of flooding from
the loch. 
Inappropriate
Repairs
There are numerous historic buildings
throughout the Conservation Area which
have poor quality and or inappropriate
repairs for a traditional building, which
could cause more rapid decline of
the historic fabric. This could be the
result of the economic context / lack of
investment or lack of skills & knowledge.
This can lead to loss of visual character
if there is a loss of traditional details and
traditional materials.
11.2.4 
Photographs:
Top: large vacant
shop unit in
prominent position
in the Village
Centre. 
Bottom:
Vacant hotel
building in
prominent position
in the Village
Centre.
Vacant Properties 
Again, especially within the Village
Centre Character Area, there are several
vacant historic buildings, creating blank
street frontages which in turn establishes
a sense of economic downturn and low
morale within the community. It also
potentially creates future maintenance
issues. 
Arguably the most significant vacant
property is the Tarbert Hotel. The lack
of activity within this prominent building
at the heart of the village centre is
detrimental to the appearance and
character of the townscape as well
as the economy. This is typical of the
decline in local high streets nationally.
Page 185

Page 186

11.2.5 Loss of Traditional Windows 11.2.7 Car Parking 
Photograph:
Replacement
window and door. 
11.2.6 
Photograph:
historic poor quality
development on
Harbour Street.
Loss of original sash and case windows
and use of UPVC windows in many
buildings within the Conservation Area
threatens the integrity of the historic
character and fabric of the buildings.
This is likely the result of existing
windows being draughty and expensive
to repair, as well as lack of knowledge
about appropriate replacement or
window repairs. 
Poor quality
development
There are a number of examples of
inappropriate development throughout
the Conservation Area such as poor
quality extensions.
Photograph:
Cars parked along
Harbour Street. 
11.2.8 
Photograph: Bins
on the pavement
on Harbour Street.
Although this may be considered a
‘necessary evil’, car parking along the
edge of the harbour, within the Village
Centre and on the verges of Pier Road,
detracts from the historic character and
natural beauty of the area. Furthermore,
on Pier Road, these are not demarcated
parking spaces and consequentially the
verges are being eroded. 
Unsightly refuse
storage
Bins containing waste from many of
commercial units in the Village Centre
are located on the pavement. This not
only causes an obstruction but creates
clutter which is visually intrusive and
detracts from the character.
Page 186

Page 187

11.2.9 
Photograph: Pier
Road towards East
Pier 
11.2.10 
Photograph:
Shop frontage on
Barmore Road
Lack of
pavements
Lack of pavements from East Pier /
Battery Point into the village centre
No pavements along this route can
become a hazard for pedestrians,
especially when the Waverley Steamer
docks at the East Pier 
Inappropriate
shop frontages
Several shops have inappropriate
frontages and signage that detracts
from the historic character of the Village
Centre.
11.2.11 
Photograph:
Buildings to the
rear of 1 Argyll
Place. 
11.2.12 
Photograph: The
Old Sailmakers on
Garvel Road.
Back Courts 
Dilapidated buildings within back courts.
A number of the historic structures
within the back courts are in very
poor condition. These structures are
significant to the character of the back
courts and their historic use. 
Loss of Fishing
Heritage
Buildings such as the Old Harbour
Master’s Office and Old Chandlery
currently have no statutory protection
despite their significant contribution to
Tarbert’s fishing heritage and character
of the Conservation Area.
Page 187

Page 188

11.3 Opportunities for Heritage Assets
and Tarbert Conservation Area
11.4 Approach to Climate Change 
Specific opportunities for Tarbert
Conservation Area are identified as
follows: 
• Coherent Interpretation & way
finding through the village 
• Further archaeological
investigation 
• Increased tourism and increased
commerce in the Village Centre 
• Management of the Conservation
Area’s assets, including
education in traditional skills 
• Improvements to shop fronts and
signage 
• Temporary improvements to
blank frontages through artworks 
• Conservation and adaptive reuse
of back court buildings 
• Partnerships and Community
engagement to find new uses
for vacant buildings – housing,
storage, workshops etc /
amenities and services 
• Increased recreational activities –
cycle and walking routes 
• Celebration of fishing heritage
through the protection of
associated buildings
The effects of Climate Change are a
critical factor in the approach to the
conservation, maintenance, and any
adaptive re-use of heritage assets
and the urban realm within Tarbert
Conservation Area. 
The impact of any development on
the environment of the area, as well
as the impact of the physical effects of
climate change, we now experience,
on the heritage assets should both be
analysed. 
In 2019, Historic Environment Scotland
published a useful guide to the
impacts of Climate Change on the built
environment. Particularly relevant to
Tarbert are the references to the specific
impacts on Coastal Communities. 
A Guide To Climate Change Impacts |
Historic Environment Scotland 
A Guide To Climate Change Impacts |
Historic Environment Scotland
Page 188

Page 189

11.4.1 Impact on Heritage Assets 11.4.2 Improvements to Heritage Assets 
In terms of the impact any development of heritage assets will have on the
environment - as historic, traditionally constructed buildings, the following aspects
should be considered: 
• The structure is currently carbon neutral as it is unoccupied
however the energy efficient adaptive re-use and retrofit of our existing
building stock is a key aspect to achieving carbon neutral. 
• Traditionally constructed buildings need to be treated differently from modern
construction due to the breathability and permeability characteristics of
traditional buildings with a holistic view of all the contributing elements.
• Before any retro-fit proposals are installed, the condition of the building fabric
must be good. 
• The insulation of the envelope of a traditional building must be assessed
proportionally taking into account what thermal improvements can
be made from a technical standard, ensuring the use of hygrothermal
modelling is considered but also from an assessment of the impact that
any installation of insulation would have on any historical significance.
For example external wall render may not be appropriate due to the
significance of the appearance of the historic stonework however if
much of the historic interior is lost, internal wall insulation may be most
appropriate. 
In terms of the impact of the physical effects of climate change, we now experience,
Tarbert Conservation Area is at increased risk of extreme weather events due to
its exposed location on the West coast of Scotland, meaning flooding mitigation
may be relevant in some areas, replacement and repair details should be designed
accordingly. For example this could include increasing the size of rainwater goods,
appropriate lime pointing specification to protect the structures, flood mitigation
measures and any plant or services relocated from lower levels. 
It is vital that building owners are educated about the impact of Climate Change and
how to appropriately maintain and improve their historic properties.
The following factors should also be considered in developing the improvement
strategy for any heritage assets: 
• Fabric Repairs & Building Maintenance 
• Historic significance 
• Energy source – current consideration of renewable energy sources by
Community Groups 
• Fabric Improvements by Insulating Building Envelope: 
• Ventilation / Airtightness 
• Hygrothermal Modelling 
• Operational Energy - Heating and Cooling 
• Carbon Emissions 
• Occupants well-being - thermal, air quality, day lighting, noise 
• Cost 
• Total Performance 
The following HES documents previously referenced are excellent in providing and
introduction to the impacts of Climate Change and approach to retro-fit and energy
efficiency in traditional buildings; 
A Guide To Climate Change Impacts | Historic Environment Scotland
A Guide To Climate Change Impacts | Historic Environment Scotland 
Guide to Energy Retrofit of Traditional Buildings | Hist Env Scotland
Guide to Energy Retrofit of Traditional Buildings | Hist Env Scotland
Page 189

Page 190

12.0 Opportunities for Planning Action 13.0 Conservation Strategy 
We do not recommend any need for boundary refinement of the Tarbert
Conservation Area. This should however be kept under review.
The Conservation Strategy for a Conservation Area should be reflective of the
established cultural values of the place and structured to suit the identified
vulnerabilities and opportunities. It should provide a strategy beyond the immediate
future and inform the framework of policies and action plan. 
Informed by the opportunities and vulnerabilities noted previously, the Conservation
Strategy for Tarbert Conservation Area prioritises the following themes through the
Policies and Action plan: 
• Retain local community support and engagement 
• Enhance and retain the unique character of Tarbert Conservation Area 
• Tackle the issue of absent landlords 
• Bring business and retail back into the Village Centre 
• Increase tourism through heritage interpretation and education (and outdoor
activities) 
• Celebrate fishing heritage 
• Support the re-opening of Tarbert Hotel and Victoria Hotel 
• Affordable housing for locals and staff 
• Identification of most vulnerable buildings and prioritise necessary repair
works within the Conservation Area which will make most impact 
• Take measures to educate and mitigate for Climate Change in the built
environment – including thermal performance of heritage assets 
• Address inappropriate repairs and alterations 
• Education in traditional skills and maintenance of traditional buildings 
• Education in funding for fabric repairs 
• Further archaeological investigations
Page 190

Page 191

14.0 Policies and Action Plan 14.1 Conservation Management Plan 
The articulation of significance and the evaluation of vulnerability and opportunities
become the basis for a framework for policies, procedures, and future management
to mitigate vulnerability and enhance the significance of the Conservation Area and
heritage assets. Each vulnerability and opportunity is addressed within a policy. 
The policies and action plan are combined into a table to give clear guidance for
next steps and priorities to safeguard the historic area. As development plans for the
area progress, these sections can be expanded and split into separate sections with
review of policies, actions and timescales. 
The actions will require effort from the community and local organisations.
The following table schedules a framework of the policies, which vulnerability or
opportunity they seek to address and what action is required to assist with these
efforts.
Page 191

Page 192

01 02 Policies Vulnerability
/ Opportunity
Addressed
Action Suggested
Who /
Timescale 
Use & Management of
the Historic Area   
Retention of Tarbert  Management &  Review as per  Planning
Conservation Area Conservation statutory process Policy / to align
designation to safeguard   with changes
its status   in Local   
Development   
Plan policy 
Retention of all Listed  Management &  Review on a case-by-  Historic
Building designations to Conservation case basis Environment
safeguard their status   Scotland /   
as and when   
required 
Review of Listed Building
designation to identified
fishing heritage buildings 
Loss of Fishing
Heritage buildings 
Celebration of fishing
heritage through
the protection of
associated buildings 
Request HES review
designation of the
Old Harbour Master’s
Office and the Old
Chandlery. 
Historic
Environment
Scotland –
Listings Team
/ to align
with review
timescales. 
Monitor / review
buildings identified as ‘at
risk’ 
Need for Repair
Vacant Properties 
Request input from
HES in absence of
Buildings at Risk
register. 
Historic
Environment
Scotland – BAR
Team 
Adaptive re-use of
heritage assets 
Dilapidated buildings
within back courts 
Affordable housing 
Education
programme / access
of information &
funding for building
owners. 
Tarbert Regen
Scheme
– Training
Programme 
Glendale has been
identified as a
Priority Building for
repairs to create
affordable housing. 
Guidance on building
professionals
specialising in
Conservation. 
Encourage Conservation
safeguards in Contracts
and Tenders
Inappropriate
Repairs 
Skills shortage
Guidance on building
professionals
specialising in
Conservation.
Guidance for building
owners on how to
engage a Contractor.
Argyll and
Bute Council
- Housing
Team / Tarbert
Regen Scheme
– Grants
Programme 
Managing absent
landlords and vacant
properties 
Need for Repair
Vacant Properties 
Council Housing
Team to help set up
Owners Associations. 
Council Empty
Business Property
Officer to support
empty property
owners find tenants
and new businesses. 
Argyll and
Bute Council
- Housing and
Empty Business
Property Teams  
Temporary
improvements to
blank frontages
through artworks 
Prioritise necessary
repair works within the
Conservation Area which
will make most impact
for grant funding. 
Management &
Conservation 
Need for Repair 
Informed by this
document.
Consult with the
community 
Tarbert Regen
Scheme
– Grants
Programme 
Inappropriate repairs 
Grant application
Specialist
Conservation
Consultant 
Records   
Development of online
database of archival
information and
photographs. 
Interpretation
development 
Archaeological 
Support Tarbert Life
and Tarbert Castle
Trust to digitise
material. 
Tarbert Regen
Scheme –
Community
Programme   
Tarbert Life   
Tarbert Castle
Trust 
Create processes to
work towards net zero. 
Extreme weather /
flooding 
Utilise procurement
route to support
appropriate repair,
use of sustainable
materials and local
labour. 
Argyll and
Bute Council -
Climate Team 
Page 192

Page 193

03 04 
Improve shop frontages Inappropriate shop
frontages and
signage 
Increased tourism
and increased
commerce
Skills training for
local contractors
Tarbert Regen
Scheme –
Grants, Training
and Community
Programmes 
Education
programme / access
of information &
funding for building
owners  
Improve thermal
performance of heritage
assets
Energy retro-fit
improvements 
Draughtproofing
windows
Education
programme / access
of information &
funding for building
owners
Tarbert Regen
Scheme –
Grants and
Training
Programmes  
Skills training for
local contractors
Specialist
Consultant
Record building
materials within
Conservation Area.
Inappropriate
Repairs
Materials Audit is
being carried out.
Specialist
Consultant 
Skills shortage   
Interpretation
development   
Conservation
Principles and the
Management of change   
Review of Management
Plan and Conservation
Area Appraisal 
Management &
Conservation 
Align with review of
LDP. 
Argyll and
Bute Council -
Planning Policy 
Poor quality modern
/ contemporary
development  
Specialist
Conservation
Consultant 
Training of building
owners and local
contractors in
conservation approach 
Inappropriate
Repairs
Retaining traditional
windows and doors 
Education
programme / access
of information for
building owners 
Tarbert Regen
Scheme
– Training
Programme  
Skills shortage
Skills training for local
contractors
Specialist
Consultant /
Contractor 
Improve refuse storage
within the Conservation
Area
Unsightly refuse
storage
Review refuse
storage protocol
and bin sizes for the
Conservation Area
Argyll and
Bute Council -
Amenity 
Plan long term defence
for future sea level rise 
Extreme weather /
flooding 
Interrogate
information on water
levels and plan
long term mitigation
measures 
Tarbert Harbour
Authority
Specialist
Consultant 
Encourage safer
pedestrian route from
ferry to village centre 
Management &
Conservation 
Strategy to to create
enhanced route. 
Argyll and
Bute Council
- Sustainable
Transport
Maintenance
Management   
Encourage building
owners to implement a
planned maintenance
regime for individual
heritage assets and
develop a long term plan
which includes annual
inspections. 
Need for repairs
Inappropriate repairs
Dilapidated buildings
within back courts 
Education
programme / access
of information &
funding for building
owners. 
Guidance on building
professionals
specialising in
Conservation. 
Tarbert Regen
Scheme –
Grants and
Training
Programmes 
Specialist
Consultant /
Contractor  
Use of grant contract
conditions. 
Implement maintenance  Need for repairs  Review key  Argyll and Bute
checks for the  properties of interest Council - MAKI
Conservation Area.  through the MAKI APAG  
Area Property Action 
Group. 
Disaster Management   
Plan a protocol for
extreme weather events 
Extreme weather /
flooding 
Argyll and Bute
Council review and
update policies. 
Argyll and Bute
Council 
People Management   
Upgrading of orientation
and signage 
Increased tourism
and increased
commerce 
Introduce a new
orientation material 
Tarbert Regen
Scheme   
Tarbert Harbour
Authority 
Page 193

Page 194

05 06 Communication,
Education &
Interpretation   
Establish stakeholder
forums and development
of an engagement policy
Management &
Conservation 
Community
engagement &
support
Events and
education
programmes that
allow for wide
engagement
Local Area
Partnership 
Improved dissemination
of information
regarding repairs and
improvements to heritage
assets 
Increased tourism
and increased
commerce
Interpretation
development 
Education
programme / access
of information &
funding for building
owners 
Tarbert Regen
Scheme –
Community
Programme  
Community
engagement &
support
Skills training for
local contractors 
Improved heritage and
interpretation strategy for
the village 
Interpretation
development 
Design of coherent
Interpretation &
way finding through
the village and
information point. 
Tarbert Regen
Scheme 
Tarbert Harbour
Authority
Further archaeological
investigation
Management &
Conservation
Develop a plan for
further investigation.
Tarbert and
Skipness
Community Trust 
Interpretation
development
Consider impact
of climate change
on the uncovering
of any buried
archaeology. 
Specialist
Consultant 
Involvement of local
community in the future
of heritage assets 
Community
engagement &
support 
Develop a plan
for Partnerships
and Community
engagement to find
new uses for vacant
buildings – housing,
storage, workshops
etc / amenities and
services. 
Tarbert Regen
Scheme 
Tarbert and
Skipness
Community Trust 
Specialist
Consultant 
Exploration of any
further potential strategic
partnerships
Management &
Conservation 
Interpretation
development
Community
engagement &
support
Develop a plan to
explore potential
partners and make
contact.
Tarbert Regen
Scheme 
Page 194

Page 195

14.2 Management & Maintenance Plan 15.0 Monitoring and Review 
Please refer to appendix for a checklist which can be adapted for use in the
management and maintenance of individual heritage assets within the Conservation
Area. Please note that a risk assessment should always be undertaken before
carrying out any maintenance tasks. This checklist has been adapted from an
Historic England example. 
The checklist can be expanded to include planned repair works as identified within
the fabric repair surveys for each heritage asset.
An indication of proposed priorities of actions to safeguard the integrity of the
historic character of Tarbert Conservation Area are noted in the previous section
however as a Conservation Plan is a working document it should be reviewed,
expanded, and updated as any plans for the area are developed. 
As development plans for the area progress, we recommend that the Policies and
Action Plan are expanded with review of policies, actions and timescales. 
Tarbert Conservation Area is covered by an Article 4 Direction, meaning permitted
development rights may be affected or removed. Property owners are therefore
encouraged to speak with their local planner prior to embarking on works to their
building. 
Email: planning.maki@argyll-bute.gov.uk
Page 195

Page 196

16.0 Appendices 
16.1 Gazetteer of Heritage Assets 
16.2 Community Engagement 
16.3 Management & Maintenance Plan Checklist
Page 196

Page 197

ARGYLL AND BUTE COUNCIL  PPSL Committee                                                      
Development & Economic Growth  18 November 2025 
Development Management Performance Update – FQ2 2025/26 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the performance of the Development
Management Service for the reporting period FQ2 2025/26. 
1.2 The attached document Appendix 1 provides an overview of the current demands
upon the Development Management Service, its output during this period, the
handling of the current backlog of casework, and the average time taken to
determine planning applications.   
2.0 RECOMMENDATIONS 
2.1 It is recommended that PPSL: 
(a) Review and agree the content of the report. 
3.0 DETAIL & BACKGROUND 
3.1  The performance of the Council’s Development Management Service has been
significantly impacted by the legacy effect of the Covid Pandemic upon
interruption to workflow and a subsequent increase in demand for regulatory
activity relating to new development. This situation has been exacerbated by the
Service having previously been down-sized in response to the longer-term wider
financial pressures facing the Council combined with a number of long-term
vacancies that proved extremely difficult to fill as a result of a national shortage of
planning professionals. The determination of planning applications has also been
impacted by the uncertainty created by a changing planning policy backdrop with
the Scottish Government’s adoption of National Planning Framework 4 (NPF4) in
February 2023 with minimal transition arrangements having had a noticeable
adverse impact on FQ4 2022/23 output as a result of a significant volume of
casework requiring to be reassessed prior to its determination.  The cumulative
effect of these extraordinary pressures has given rise to a significant backlog of
planning casework that continues to impact upon the ability of the Council to
deliver the Development Management Service in an efficient and effective
manner at this time, and impacts upon customer service. At FQ4 2022/23 the
backlog of applications amounted to approximately 375 formal applications and
175 pre-application enquiries.
3.2 An Improvement Action Plan (IAP) was prepared in early 2023 in response to the
Page 197 Agenda Item 8

Page 198

significant decrease in performance and wider issues impacting upon the
resourcing of the service and its interactions with customers. The implementation
of the IAP has ensured the delivery of additional capacity within the Development
Management Service and along with this improvement initially in terms of output
and more latterly improving trends are also now able to be identified in relation to
the making of timely determinations. Building upon the foundation of the IAP, the
Development Management Service Plan and Development Management Charter
approved by PPSL on 18th September 2024 set out updated performance targets
for the Service. These include a wider range of measures that seek to
demonstrate the delivery of individual elements of the IAP and in addition to
timeliness include measures which can be utilised to measure customer
satisfaction, and staff welfare. 
3.3 DEMAND: The Development Management Service receive approximately 2000
planning and related application case work items on an annual basis. The
Development Management Service is resourced with the expectation that
demand will be relatively constant and steady throughout the year. Whilst the
volume of new submissions decreased by approximately 10% during 2020/21
they had returned to and exceeded pre-pandemic levels during 2021/22.
Submission rates have subsequently been maintained at a high level and during
2022/23 were 5% up on pre-pandemic levels. Appendix 1, Sheet 1 shows that
whilst submission rates continued to show an increase in demand during FQ2
2025/26 this has decreased slightly from the previous reporting period. 
3.4  During the majority of FQ2 2025/26 the DM Service has operated with 2 vacant
posts in addition to impacts arising from unplanned absence, including the impact
of work related stress. One vacant post has been taken up since mid Sept. and is
currently being trained on appropriate ways of working; the second vacant post
has been successfully recruited however the new member of staff is unable to
take up post until January 2026. To assist with capacity issues during this period
one agency staff member has been retained to augment the MAKI team. 
3.5 OUTPUT: Notwithstanding the reduced availability of professional officer
resource within the DM Service during FQ2 output has improved from FQ1 and is
broadly comparable to previous reporting periods. (Appendix 1, Sheet 2). It is
anticipated that productivity will continue to improve once recruitment to vacant
posts has been completed. It is however highlighted that additional vacancies
have arisen during FQ3 which will further disrupt performance across the DM
Service. These include the loss of ½ fte planning officer and 1fte enforcement
officer in the BCHL team, and the departure of the MAKI Team Leader. 
3.6 FQ2 has seen output from the DM Service keep pace with the number of
applications validated during this period (Appendix 1, Sheet 3). A review of ‘live’
casework has however identified that whilst there has been a slight increase in
the number of ‘legacy’ cases which are older than 1 year from validation remain
‘live’ and it is noted that these have increased from 90 to 91 items during FQ2
(Appendix 1, Sheet 4). 16 legacy items were determined during FQ2 however in
the same period 17 additional items became legacy cases. Whilst the dip in
productivity is as a result of reduced resource availability in the short-term it is a
Page 198

Page 199

matter which gives some cause for concern in terms of immediate performance
but also indicates that the Service has unresolved issues in relation to its
resilience which will be closely monitored moving forward. 
3.7 PRE-APPLICATION ENQUIRIES: Demand for pre-application advice remains
high however Pre-application turnover is currently on track. Performance during
FQ2 has met demand from new submissions. A commitment has been provided
to review and improve the pre-application process, this will include the provision
of enhanced information on the Council website to allow a greater proportion of
customers to ‘self-serve’; development and roll out of a new pre-application
service has been identified as a priority project. 
3.8 ‘HOUSEHOLDER’ DEVELOPMENT: The performance of the Development
Management Service is also measured in terms of the time taken to determine
applications as it is recognised that failure to provide timely decisions can create
uncertainty and be detrimental to the delivery of development across the Council
area. Overall ‘time-taken’ measures have been skewed for sometime by the
determination of a high volume of older ‘legacy’ applications that have accrued as
part of the planning backlog. The increasing proportion of older applications being
determined from FQ3 2022/23 onwards is identified in the bar graphs that provide
a breakdown of application age within the average time measures (Appendix 1,
Sheet 5 and Sheet 6) and demonstrate that ‘legacy’ applications are successfully
being targeted for determination. The previous resolution of legacy householder
items has underpinned the continuing improvement to underlying performance
during FQ2. 
3.9 This is particularly evident again within the ‘householder’ average time measure
(Appendix 1, Sheet 5) where the overall reduction in householder ‘legacy’ items
has allowed for improvement of the headline KPI from 10.4 weeks in FQ1 2025/26
to 7.9 weeks in FQ2 2025/26. It is also highlighted that this position relates to ‘raw’
data and does not factor in delays which have arisen as a result of matters outwith
the control of the Council, or applications that have been subject to processing
agreements. Whilst the data sets are not directly comparable it is still helpful to
reference the SG Returns as a benchmark. In this respect the national average
for householder applications at FQ2 2024/25 was 8.7 weeks. 
3.10 ‘LOCAL’ DEVELOPMENT: The determination of ‘legacy’ applications continued
to have an adverse impact upon the average time taken measure applied to all
other ‘local’ planning applications (Appendix 1, Sheet 6) where the determination
of 16 ‘legacy’ applications during FQ2 cumulatively added 10.2 weeks to an
average time measure that reports on the determination of 123 applications in
total. During FQ2 88% of all other ‘local’ applications determined were less than
1 year old at the time of their determination and were determined in an average
of 14.3 weeks (previously 88% in 17.9 weeks at FQ1 2025/26). 74% of the total
were less than 6 months old and determined in 10.9 weeks on average (previously
63% in 10.2 weeks in FQ4 2024/25). The average time taken to determine ‘all
other local applications’ has decreased slightly during FQ2 from 26.7 weeks to
24.5 weeks. It is again highlighted that this position relates to ‘raw’ data and does
not factor in delays which have arisen as a result of matters outwith the control of
Page 199

Page 200

the Council, or applications that have been subject to processing agreements.
During FQ1 the Council determined a number of legacy applications which have
impacted on the raw data relating to the average time period, including items that
were delayed largely due to matters outwith the control of the Council. Whilst the
data sets are not directly comparable it is still helpful to reference the SG Returns
as a benchmark. In this respect the national average for local applications
(excluding householder) at FQ2 2024/25 was 14.8 weeks. 
3.11 CONCLUSIONS: It is highlighted that the indicator for determination of
‘householder’ applications has returned to within target for the first time since prior
to the Covid pandemic and is a success that reflects the hardwork and
determination of the Council’s DM team to recover performance and improve the
quality of service delivery. 
3.12 The determination of extant ‘legacy’ items does however continue to impact on
‘local’ application performance and will do so until such time as the remaining 91
items have been determined, and subject to appropriate intervention to prevent
new ‘legacy’ items from accruing. 
3.13 Analysis of the granular data shows that average time periods for determining all
applications are in general continuing to reduce and that despite headline figures
that might raise alarm, the majority of applications continue to be processed within
much faster timescales that are showing improvement over time and which within
the target of being within 10% of the national average. It is further noted that the
improvement to performance during FQ2 has been achieved despite the reduced
availability of officer resource. It will be a significant challenge to maintain this
position in light of the further staff departures during FQ3 and in this context it is
remains critical that the Council continues to ensure that the Development
Management Service is adequately resourced to ensure that the recent
improvements to performance are able to be sustained in the longer term. 
4.0 IMPLICATIONS 
4.1 Policy None
4.2 Financial None
4.3 Legal None
4.4 HR None
4.5 Customer Service Requirement to manage customer expectations in
the determination planning and related applications
4.6 Risk Failure to determine planning and related
applications in efficient and effective manner would
have potential to adversely impact upon the local
economy, delivery of housing, and health and
wellbeing of individuals.
4.7 Climate Change None
4.8 Fairer Scotland Duty 
4.9 Equalities –
Protected
Characteristics
None
Page 200

Page 201

4.10 Consumer Duty None
4.11 Island Communities None
4.12 Children’s Rights
and Wellbeing
None 
Executive Director with responsibility for Development and Economic Growth
Policy Lead: Cllr Kieron Green
31st October 2025                                                  
For further information contact: Peter Bain – 01546 604204 
APPENDICES 
Appendix 1 – FQ2 2025/26 DM performance report 
Page 201

Page 202

This page is intentionally left blank

Page 203

#
Volumes
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
Statutory 508 509 511 451 508 512 457 468 404 422 469 423 412 386 415 411 2012 75.9% 1982 76.1% 1751 74.3% 1690 76.1% 826 75.3%
Non-Statutory 21 10 10 10 14 17 15 26 25 21 14 22 23 26 23 25 56 2.1% 51 2.0% 87 3.7% 85 3.8% 48 4.4%
PREAPP 122 166 153 146 121 150 122 137 120 141 119 104 107 117 116 107 582 22.0% 570 21.9% 520 22.1% 447 20.1% 223 20.3%
Totals 651 685 674 607 643 679 594 631 549 584 602 549 542 529 554 543 2650 2603 2358 2222 1097
This data is unfiltered - it shows all casework received. YTD as at 30th September 2025
data source = UNIform (Access queries)
This tab provides information on the volume of DM case work received by financial quarter and includes a breakdown between statutory items (planning and related applications), non-
statutory items (consultations from other regulatory bodies), and pre-application enquiries.
FY25/26 YTD
Split of Casework Received
The data set covers the last 16 financial quarters and confirms that demand for the determination of planning
applications and other statutory activity of the Council as the Planning Authority remains high and relatively
constant in its volume. End FQ2 25/26: Submission rates for FQ2 were within expected parameters.
Commentary:
FY24/25
New Casework Received
FY21/22 FY22/23 FY23/24
508 509 511
451
508 512
457 468
404 422
469
423 412 386 415 411
21 10 10
10
14 17
15 26
25 21
14
22 23
26
23 25
122 166 153
146
121
150
122
137
120
141
119
104 107 117
116 107
0
100
200
300
400
500
600
700
FY21/22
FQ3
FQ4 FY22/23
FQ1
FQ2 FQ3 FQ4 FY23/24
FQ1
FQ2 FQ3 FQ4 FY24/25
FQ1
FQ2 FQ3 FQ4 FY25/26
FQ1
FQ2
Volume of New Casework Received
PREAPP
Non-Statutory
Statutory
75.3%
4.4%
20.3%
Split of Casework Received: FY25/26 YTD
Statutory Non-Statutory PREAPP
Appendix 1
Page 203

Page 204

#
Volumes
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
Statutory 393 396 410 369 402 368 476 421 458 423 464 464 427 425 370 407 1610 72.4% 1549 74.5% 1778 75.1% 1780 76.5% 777 73.8%
Non-Statutory 9 13 9 8 5 11 19 18 21 17 17 31 15 25 21 22 46 2.1% 33 1.6% 75 3.2% 88 3.8% 43 4.1%
PREAPP 117 145 149 119 124 104 150 109 121 133 106 122 115 116 133 100 568 25.5% 496 23.9% 513 21.7% 459 19.7% 233 22.1%
2224 2078 2366 2327 1053
This data is unfiltered - it shows all casework closed.
data source = UNIform (Access queries) YTD as at 30th September 2025
This tab provides detail on the volume of DM casework that has been closed and includes a breakdown between statutory items (planning and related applications), non-statutory items
(consultations from other regulatory bodies), and pre-application enquiries.
FY21/22 FY22/23 FY23/24
Casework Closed
FY24/25 FY25/26 YTD
Split of Casework Closed
The data set covers the last 16 financial quarters and demsonstrates that regardless of performance issues in
respect of timeliness output remains high. There has been a notable improvement in productivity from FQ1
2023/24 which corresponds with the increasing availability of officer resource and a more settled position
following the significant disruption to workflow arising from NPF4 (FQ4 2022/23); this improving position has
continued through subsequent reporting periods.  End FQ2 25/26: Productivity during 2025/26 has reduced
although this is not wholly unexpected as the Service has operated with vacancies during this period. Output
during FQ 2 has improved from the previous period but still lags behind output from 24/25. Output continues to be
impacted by vacancies and training of incoming staff members; performance is also impacted by the Summer
holiday period which has seen reduced availability of officers.
Commentary:
393 396 410
369 402 368
476
421 458 423
464 464 427 425
370 407
9 13 9
8
5
11
19
18
21
17
17 31
15 25
21
22
117
145 149
119
124
104
150
109
121
133
106
122
115 116
133
100
0
100
200
300
400
500
600
700
FY21/22
FQ3
FQ4 FY22/23
FQ1
FQ2 FQ3 FQ4 FY23/24
FQ1
FQ2 FQ3 FQ4 FY24/25
FQ1
FQ2 FQ3 FQ4 FY25/26
FQ1
FQ2
Volume of Casework Closed
PREAPP
Non-Statutory
Statutory
73.8%
4.1%
22.1%
Split of Casework Closed: FY25/26 YTD
Statutory Non-Statutory PREAPP
Page 204

Page 205

#
Volumes
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
Closed 402 409 419 377 407 379 495 439 479 440 481 495 442 450 391 429
Validated 438 450 462 455 436 509 462 428 366 428 425 425 370 400 387 427
Difference (no) -36 -41 -43 -78 -29 -130 33 11 113 12 56 70 72 50 4 2
This data is unfiltered - it shows the number of cases closed vs number of cases validated.
data source = UNIform (Access queries)
Casework Turnover - Volume
This tab shows a comparison between the volume of new statutory and non-statutory casework and output per financial quarter. The Y axis has been formatted to track the cumulative backlog of
applications over the last rolling 16 financial quarters.
Commentary:
The graph shows that after 7 financial quarters (FQ2 2021/22 -
FQ4 2022/23) where output was lower than input, a backlog of
375 casework items were accumulated. During this period the
DM Service were impacted by Covid restrictions/recovery and
required to operate with a number of key vacancies due to a
national shortage of planning professionals. Improving
performance during 2023/24 has however reduced the backlog
at the end of that period to 206 items.   As significant
improvement in performance is evident from FQ1 2023/24 which
corresponds with the resolution of key staffing issues within the
Service, this improving position has been maintained moving
forward from that point. End FQ2 25/26: Turnover during FQ2 to
date has  seen output match demand.
-36
-41
-43
-78
-29
-130
33 11
113 12
56
70
72
50 4 2
FY21/22 FQ3
FQ4
FY22/23 FQ1
FQ2
FQ3
FQ4
FY23/24 FQ1
FQ2
FQ3
FQ4
FY24/25 FQ1
FQ2
FQ3
FQ4
FY25/26 FQ1
FQ2
-400
-350
-300
-250
-200
-150
-100
-50
0
50
100
Casework Turnover Rate
Page 205

Page 206

Jan '24 Apr Jul Oct Jan '25 Apr Jul Oct Jan '26 Apr Jul Oct
1 - 2 Years 204 166 130 89 66 48 48 54
2+ Years 85 73 62 40 36 38 42 37
289 239 192 129 102 86 90 91 0 0 0 0
Estimated on 1st August 2024. Data sourced from Uniform on - or as near as possible to first working day of each financial quarter (from August 2024)
Live Legacy Applications - quarterly progress:   Argyll & Bute Council
Commentary:
This graph provides detail of the volume of 'legacy' cases
remaining at the start of each Quarter since Jan 2024 (start FQ4
24/25). 'Legacy' cases are statutory items that remain
undetermined more than 1 year after validation. These cases are
generally items that have a high degree of complexity, can be
contentious, or are not readily aligned with the requirements of
the Development Plan. A significant number of 'legacy' items are
items that have required substantial reworking or the provision
of additional information from the applicant with the intention
of addressing identified short-comings in the original submission,
often requiring extensive input from planning officers. In some
cases 'legacy' items are no longer being actively pursued by
applicants but have not as yet been formally withdrawn. The
determination of 'legacy' items has a significant adverse effect
on average time performance measures and can also impact on
allocation of staff resource and morale. Excellent progress has
been made over the course of 2024/25 months in reducing the
volume of legacy items from 239 to 86 items. End FQ2 25/26: 
During FQ2, 16 legacy items were detewrmined. However,
during this period 17 new legacy items have accrued. 2025 to
date has seen a period where efforts at addressing outstanding
legacy cases has plateaued and gives rise to concern.
204
166
130
89
66 48 48 54
0 0 0 0
85
73
62
40
36
38 42 37
0 0 0 00
50
100
150
200
250
300
Jan '24 Apr Jul Oct Jan '25 Apr Jul Oct Jan '26 Apr Jul Oct
Live Legacy Applications: Argyll & Bute
1 - 2 Years 2+ Years
Page 206

Page 207

#
Volumes
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
Closed 117 145 149 119 124 104 150 109 121 133 106 122 115 116 133 100
Validated 118 153 159 137 117 140 117 132 120 130 115 92 103 116 117 100
Difference (no) -1 -8 -10 -18 7 -36 33 -23 1 3 -9 30 12 0 16 0
Number of PREAPP's closed vs number of PREAPP's validated.
data source = UNIform (Access queries)
PREAPP Turnover - Volume
This tab shows a comparison between the volume of new pre-application casework and output per financial quarter. The Y axis has been formatted to track the cumulative backlog of pre-
application enquiries over the last rolling 16 financial quarters.
Commentary:
The Graph shows the accumulation of a backlog of pre-
application enquiries over the period FQ3 2021/22 - FQ4
2022/23 during a period where the DM Service operated with a
number of key vacancies and has experienced significant
workflow disruption with the introduction of NPF4. It had
previously been identified that the backlog amounted to around
180 applications; however following a review of the data input
and accuracy of the data available (see detail of correction
below) it has become evident that earlier reports included cases
that were invalid and cases that had not been closed off
proprerly in the back office system. The updated report confirms
that the backlog of pre-application enquiries reached a
maximum of just over 50 items; this position has seen significant
improvement. End FQ2 25/26: FQ2 to date has seen output
continuing to keep pace with demand.
-1
-8
-10
-18
7
-36
33
-23
1 3
-9
30
12
0
16
0
FY21/22 FQ3
FQ4
FY22/23 FQ1
FQ2
FQ3
FQ4
FY23/24 FQ1
FQ2
FQ3
FQ4
FY24/25 FQ1
FQ2
FQ3
FQ4
FY25/26 FQ1
FQ2
-100
-80
-60
-40
-20
0
20
40
PREAPP Turnover Rate
Page 207

Page 208

#
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
< 6 months 10.6 10.8 10.9 10.2 11.0 13.3 11.8 11.6 11.8 12.0 9.6 9.6 10.1 8.5 8.1 7.9 < 6 months 92 79 71 69 82 51 43 67 63 54 50 56 52 60 59 66
< 1 year 10.8 13.3 12.4 12.4 12.0 17.3 17.8 15.4 14.6 18.3 12.4 12.6 12.6 9.8 8.7 7.9 6 months - 1 year 1 8 5 6 4 11 13 12 9 19 6 8 5 4 1 0
< 2 years 11.8 13.8 12.4 13.1 12.0 17.3 18.5 18.1 16.8 20.0 16.1 19.0 13.5 12.2 10.4 7.9 1 - 2 years 0 1 0 1 0 0 1 4 3 2 4 7 1 3 2 0
All Determined 11.8 13.8 12.4 13.1 12.0 17.3 21.6 18.1 16.8 20.0 16.1 26.1 15.9 14.2 10.4 7.9 Over 2 years 1 0 0 0 0 0 2 0 0 0 0 4 1 1 0 0
Total 94 88 76 76 86 62 59 83 75 75 60 75 59 68 62 66
This data is filtered - as per Scottish Government statistical returns - to allow benchmarking. "Householder" = Development Type N01.
data source = UNIform (Access queries)
Commentary:
The line graph shows performance over time; the bar graph shows the proportionate split between 'legacy' casework and newer items. A comparison of the two demonstrates that the 'All Determined' average can be readily impacted by the determination of a small number of 'legacy'
applications. The improving resource availability has allowed the focus of the DM Service from FQ1 2023/24 to move from addressing the most urgent applications to also addressing the wider backlog of application casework. Increasing output does however mean that a high volume of 'legacy'
applications continue to be determined with significant deteriment to average time measures as is seen with the deterioration of performance across FQ4 2022/23 to FQ4 2023/24. In order to provide some context additional information is provided that demonstrates the effect of removing
older applications from reporting to provide a truer picture of the time taken to deliver the larger proportion of casework. The bar graph provides this breakdown in a format which shows the increasing volume of older applications currently being determined but also confirms that a significant
proportion of output is still undertaken in a timely manner. Peformance from FQ1 2024/25 has shown a marked improvement which demonstrates that the majority of householder applications are now being determined in much shorter time periods. End FQ2 25/26:  During FQ2 to date 
Householder Applications have been determined in an average of 7.9 weeks (improvement from 10.4 weeks during FQ1 25/26); no legacy items have been determined during FQ2. Performance in the determination of householder applications is currently on track (DM Service Plan Target <10
weeks), National Average (latest data FQ2 24/25) was 8.7 weeks.
Average Time to Determine Applications: Householder ( <6 Month, <1 Year, <2 Year, All) Volume of Applications Determined: Householder - Time Taken
The Average Time Taken to Determine Householder Planning Applications
This tab provides detail on the average time taken to determine 'householder' planning applications, this is based on raw data which does not take into account any delays that might arise from matters outwith the control of the planning authority.
10.6 10.8 10.9 10.2 11.0
13.3
11.8 11.6 11.8 12.0
9.6 9.6 10.1
8.5 8.1 7.9
7.9
7.9
11.8
13.8
12.4 13.1 12.0
17.3
21.6
18.1
16.8
20.0
16.1
26.1
15.9
14.2
10.4
7.9
0
5
10
15
20
25
30
FY21/22
FQ3
FQ4 FY22/23
FQ1
FQ2 FQ3 FQ4 FY23/24
FQ1
FQ2 FQ3 FQ4 FY24/25
FQ1
FQ2 FQ3 FQ4 FY25/26
FQ1
FQ2
Average no. of weeks to determine: Householder   (<6 Month, <1 Year, <2 Year, All)
< 6 months < 1 year < 2 years All Determined
92
79
71
69
82
51
43
67
63
54
50
56
52
60
59
66
1
8
5
6
4
11
13
12
9
19
6
8
5
4
1
1
1
1
4
3
2
4
7
1
3
2
1
2
4
1
1
50% 60% 70% 80% 90% 100%
FY21/22 FQ3
FQ4
FY22/23 FQ1
FQ2
FQ3
FQ4
FY23/24 FQ1
FQ2
FQ3
FQ4
FY24/25 FQ1
FQ2
FQ3
FQ4
FY25/26 FQ1
FQ2
% Split: Householder  
(<6 Month, <1 Year, <2 Year, All)
< 6 months 6 months - 1 year 1 - 2 years Over 2 years
Page 208

Page 209

#
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
FY21/22
FQ3 FQ4
FY22/23
FQ1 FQ2 FQ3 FQ4
FY23/24
FQ1 FQ2 FQ3 FQ4
FY24/25
FQ1 FQ2 FQ3 FQ4
FY25/26
FQ1 FQ2
< 6 months 11.1 11.5 12.4 10.1 10.2 12.9 13.5 14.0 12.7 12.1 11.6 11.5 12.7 12.2 10.2 10.9 < 6 months 118 125 114 110 104 69 87 106 95 79 97 106 104 110 80 92
< 1 year 13.5 13.4 14.5 14.0 18.0 19.2 19.3 18.7 18.8 21.0 19.0 16.3 17.0 15.6 17.9 14.3 6 months - 1 year 13 11 14 19 43 25 31 27 32 40 39 26 22 17 33 15
< 2 years 13.9 14.2 15.7 16.1 19.9 23.6 21.9 25.0 25.8 29.3 26.1 24.5 25.6 20.7 21.4 19.7 1 - 2 years 1 2 3 6 6 10 7 20 22 19 23 25 22 13 9 11
All Determined 18.5 16.7 16.8 17.0 19.9 24.5 27.6 27.4 30.2 33.4 30.0 37.8 31.2 26.4 26.7 24.5 Over 2 years 4 3 1 1 0 1 4 3 6 6 4 19 7 7 6 5
Total 136 141 132 136 153 105 129 156 155 144 163 176 155 147 128 123
This data is filtered - as per Scottish Government statistical returns - to allow benchmarking. "Local (excluding Householder)" = Development Types N02B/C, N03B/C, N04B/C, N05B/C, N06B/C, N07B/C, N08B/C, N09B/C, N10B/C.
data source = UNIform (Access queries)
Commentary:
The line graph shows performance over time; the bar graph shows the proportionate split between 'legacy' and newer items. A comparison of the two demonstrates that the 'All Determined' average can be readily impacted by the determination of a small number of 'legacy' applications. The
improving resource availability has allowed the focus of the DM Service is to move during 2023/24 from addressing the most urgent applications to also addressing the wider backlog of application casework. Increasing output does however mean that a higher volume of 'legacy' applications will
be determined with significant deteriment to average time measures as is seen with the deterioration of overall average time performance measures from FQ2 2022/23 to FQ4 2023/24. In order to provide some context additional information is provided that demonstrates the effect of
removing older applications from considerations to provide a truer picture of the time taken to deliver the larger proportion of casework that has been determined. The bar graph provides this breakdown in a format which shows the increasing volume of older applications currently being
determined but also confirms that a significant proportion of output is still undertaken in a timely manner. Performance during FQ1 2024/25 has markedly improved and appears to indicate the start of an improving trend with decreasing time periods. End FQ2 25/26: FQ2 has seen 16 legacy
applications cleared to date, with the effect of adding 10.2 weeks to the overall average time measure which now sits at 24.5 weeks (improvement from 26.7 weeks in FQ1 2025/26).  It is also noted that some of the negative impact is attributed to delays to determination which were outwith
the control of the planning authority and which will be adjusted in statutory reporting by the Scottish Government. During FQ2 the determination of non-legacy local applications were undertaken in an average of 14.3 weeks (improvement from 17.9 weeks in FQ1 25/26). It is however
highlighted that a consistently high proportion of applications are continuing to being determined at an early stage with 74% of all local applications in FQ2 to date were newer items determined in an average time of 10.9 weeks (previously 62% in 10.4 weeks in FQ1 2025/26). Due to the impact
of legacy items, the headline measure remains off-track (DM Service Plan Target <16 weeks). For the purpose of comparison, the National Average (latest data FQ2 24/25) was 14.8 weeks.
Average Time to Determine Applications: Local (Excluding Householder) ( <6 Month, <1 Year, <2 Year, All) Volume of Applications Determined: Local (Excluding Householder) - Time Taken
The Average Time Taken to Determine Local (excluding Householder) Planning Applications
This tab provides detail on the average time taken to determine 'local' planning applications, this is based on raw data which does not take into account any delays that might arise from matters outwith the control of the planning authority.
11.1 11.5 12.4
10.1 10.2
12.9 13.5 14.0 12.7 12.1 11.6 11.5 12.7 12.2
10.2 10.9
13.5 14.313.9
19.7
18.5
16.7 16.8 17.0
19.9
24.5
27.6 27.4
30.2
33.4
30.0
37.8
31.2
26.4 26.7
24.5
0
5
10
15
20
25
30
35
40
FY21/22
FQ3
FQ4 FY22/23
FQ1
FQ2 FQ3 FQ4 FY23/24
FQ1
FQ2 FQ3 FQ4 FY24/25
FQ1
FQ2 FQ3 FQ4 FY25/26
FQ1
FQ2
Ave no. of weeks to determine: Local (Excluding Householder) (<6 Month, <1 Year, <2 Year, All)
118
125
114
110
104
69
87
106
95
79
97
106
104
110
80
92
13
11
14
19
43
25
31
27
32
40
39
26
22
17
33
15
1
2
3
6
6
10
7
20
22
19
23
25
22
13
9
11
4
3
1
1
1
4
3
6
6
4
19
7
7
6
5
50% 60% 70% 80% 90% 100%
FY21/22 FQ3
FQ4
FY22/23 FQ1
FQ2
FQ3
FQ4
FY23/24 FQ1
FQ2
FQ3
FQ4
FY24/25 FQ1
FQ2
FQ3
FQ4
FY25/26 FQ1
FQ2
% Split: Local (excluding Householder)
(<6 Month, <1 Year, <2 Year, All)
< 6 months 6 months - 1 year 1 - 2 years Over 2 years
Page 209

Page 210

This page is intentionally left blank

Page 211

Document is Restricted
Page 211 Agenda Item 9NOT FOR PUBLICATION by virtue of paragraph(s) 13
of Schedule 7A of the Local Government(Scotland) Act 1973

Page 212

This page is intentionally left blank

Page 213

Document is Restricted
Page 217
NOT FOR PUBLICATION by virtue of paragraph(s) 13
of Schedule 7A of the Local Government(Scotland) Act 1973

Page 214

This page is intentionally left blank